FW: Cyprus Lane - Slope on South Side of Vault
From Bob Wenzl <Bob@tuscanywa.com>
Date Thu 9/4/2025 2:46 PM
To cliff sitedme.com <cliff@sitedme.com>
Cliff
The city wants me to work on some type of modification for the landscape wall in front of the south vault.
Please follow up with Brianne and see what she wants, supposedly she is going to waive a bunch of the
applications.
bob
From: Brianne Bannwarth <BBannwarth@Rentonwa.gov>
Sent: Tuesday, August 12, 2025 4:01 PM
To: Bob Wenzl <Bob@tuscanywa.com>
Cc: Nathan Janders <NJanders@Rentonwa.gov>; Jill Ding <JDing@Rentonwa.gov>; Clark Close <CClose@Rentonwa.gov>
Subject: RE: Cyprus Lane - Slope on South Side of Vault
Hello Bob,
As we discussed, the following link is to an example of a modification that was recently submitted for a very similar
instance.
Maple Highlands (Example Modification): https://edocs.rentonwa.gov/Documents/Browse.aspx?
id=10246873&dbid=0&repo=CityofRenton
Submittal Documents: https://edocs.rentonwa.gov/Documents/Browse.aspx?
id=10246874&dbid=0&repo=CityofRenton
We would be Ok with the following submittal items:
Master application
Modification Justification
Revised/Redlined Civil Sheet reflecting the wall
Roadway section reflecting the wall
If you have any questions, let us know.
BRIANNE BANNWARTH, P.E., LEED AP, Director
City of Renton // Development Engineering
Virtual Permit Center // Online Applications and Inspections
office 425-430-7299
NOTICE OF PUBLIC DISCLOSURE: This message complies with Washington State’s Public Records Act – RCW 42.56
From: Brianne Bannwarth
Sent: Tuesday, August 12, 2025 12:08 PM
To: Bob Wenzl <Bob@tuscanywa.com>
Cc: Nathan Janders <NJanders@Rentonwa.gov>; Jill Ding <JDing@Rentonwa.gov>; Clark Close <CClose@Rentonwa.gov>
Subject: RE: Cyprus Lane - Slope on South Side of Vault
Hello Bob,
I’m responding on behalf of Nate and Jill, who are out of the office this week. We are okay with a retaining wall
adjacent to the sidewalk with an exposed height of no more than 2.5 feet, if possible.
CAUTION: This email originated from outside the City of Renton. Do not click links, reply or open attachments unless you
know the content is safe.
To formally approve this request, a modification will need to be submitted to remove the required 3-foot separation
between the right-of-way and the face of the retaining wall (RMC 4-4-040.2.d). Here is a link to the modification
requirements. I’ve also copied Clark on this email—he can answer any questions about the modification process
while Jill is away.
Modification Submittal Requirements: https://edocs.rentonwa.gov/Documents/DocView.aspx?
id=8463026&dbid=0&repo=CityofRenton
Master Application: https://edocs.rentonwa.gov/Documents/DocView.aspx?id=8463013&dbid=0&repo=CityofRenton
Take Care,
BRIANNE BANNWARTH, P.E., LEED AP, Director
City of Renton // Development Engineering
Virtual Permit Center // Online Applications and Inspections
office 425-430-7299
NOTICE OF PUBLIC DISCLOSURE: This message complies with Washington State’s Public Records Act – RCW 42.56
From: Bob Wenzl <Bob@tuscanywa.com>
Sent: Thursday, August 7, 2025 11:26 AM
To: Nathan Janders <NJanders@Rentonwa.gov>
Subject:
Nathan
See pictures, the slope next to the vault is quite steep and one structure is above ground. I would like to
put a landscape wall 1.5 3.5 feet tall along the sidewalk to the entrance of the tract road to service the
vault. This would allow more landscaping that will be maintained and help sluffing of topsoil during rain
events. The wall right next to the sidewalk will help with weed control also.
Please let me know if it is approved and let me know you received these emails.
Thanks
Bob wenzl