PROJECT NARRATIVE
FOR
TALBOT HILLS SHORT PLAT
Prepared for Schneider Family Homes
Prepared by Core States Group
Job No. 23382
December 8, 2025
SITE DESCRIPTION: The site is a 2.25-acre vacant property that is mapped by city of Renton with R-1 (Talbot
Urban Separator Overlay) and R-4 zoning. Por8ons of the site are moderately forested with moderate to
steep slopes descending from east to west. South 55th Street establishes por8ons of the site's southern
boundary in two loca8ons. A small intervening property, parcel 793100-0140, creates a separa8on of
frontage on South 55th Street.
PROJECT DESCRIPTION: The proposal is to subdivide 2.25 acres with split zoning into four single family
residen8al lots with tracts for access, landscaping, and open space/tree reten8on/NGPA. Access to the lots
is from South 55th Street via a shared driveway.
Lots and tracts will cross both zoning districts on the site. Area tables are provided on the short plat map to
show the amount of area in each zoning district for lots and tracts.
ZONING EVALUATION
The proposal is a short plat that proposes four split-zoned lots with por8ons of each lot in the R-4 zone and
the R-1 zone. Calcula8ons are provided and setback lines for each lot/zone are depicted on Sheet 3 to
demonstrate compliance with both zoning standards for lot width, lot area, setbacks, and R-1 open space.
Each lot is depicted with R-4 setbacks and R-1 setbacks, as applicable for the por8on of each lot in the two
zones. As required for the Talbot Urban Separator Overlay, non-revocable open space is provided in Tract C,
with 30,895 sf (67.3%) in the R-1 zone specifically. See Urban Separator Open Space calcula8ons provided
on Sheet 3 that demonstrate compliance with the requirement to provide 50 percent of the R-1 area in
non-revocable open space.
Talbot Hills
Schneider Family Homes | Preliminary Short Plat
Page 2
23382.005-Project Narrative-Prelim Short Plat
UTILITIES
The drainage facility is designed to provide deten8on and water quality per the Renton Surface Water
Design Manual. The project's stormwater will be conveyed to a proposed stormwater drainage facility
located in Tract A. The stormwater drainage facility will consist of a deten8on chamber system to provide
conserva8on flow control followed by a water quality vault to provide basic water quality treatment. The
deten8on facility is located at the southwest corner of the project within the private access tract. The water
quality facility will outlet to the exis8ng roadside ditch in South 55th Street where the drainage will be
conveyed to the exis8ng drainage ouIall to Springbrook Creek, which is the natural downstream drainage
course.
Water will be provided by Soos Creek Water and Sewer District (SCWSD) subject to an interlocal agreement.
A water availability cer8ficate is included with the applica8on materials. The applicant/developer will work
with the city and SCWSD to establish the interlocal agreement. One new fire hydrant is provided at the
southwest corner of Lot 1 near the site’s street frontage.
City of Renton will provide sewer. Exis8ng side sewers may be used if possible. A new sewer main will be
extended into the site and to the north property line in a 15-foot-wide sewer easement.
ACCESS
The site will access the four proposed lots from a shared driveway origina8ng at South 55th Street near the
southwest corner of the site. Lot 1 has more than 50 feet of frontage on South 55th Street. Frontage
improvements will be provided for a por8on of South 55th Street consis8ng of new curb, guKer and
sidewalk along the south boundary of Lot 1 to the west site boundary.
SAFE SCHOOL WALKING ROUTE(S)
Renton School District has indicated that students would aKend Benson Hill Elementary, Nelsen Middle
School, Lindbergh High School and would all be bussed to school. The closest exis8ng bus stops are located
at Talbot Road South and South 53rd Street, approximately 1,050 feet from the site. Sidewalks and/or
shoulder are not currently present along the walking route. Por8ons of the south side of 55th Street have
shoulder suitable for safe walking condi8ons to Talbot Road.
Benson Hill Elementary | 18665 116th Ave SE | Renton, WA 98058 | (425) 204-3300
Nelsen Middle School | 2403 Jones Ave S | Renton, WA 98055 | (425) 204-3000
Lindbergh High School | 16426 128th Ave SE | Renton, WA 98058 | (425) 204-3200
REQUIRED NARRATIVE ITEMS
PROJECT NAME, SIZE, AND LOCATION OF SITE
• Project Name: Preliminary Short Plat of Talbot Hills
• Gross Site Area: 2.25 acres
Talbot Hills
Schneider Family Homes | Preliminary Short Plat
Page 3
23382.005-Project Narrative-Prelim Short Plat
• Loca8on: No address assigned
LAND USE PERMITS REQUIRED FOR PROPOSED PROJECT
• Preliminary Short Plat
ZONING DESIGNATION OF THE SITE AND ADJACENT PROPERTIES
• Site: R-4 & R-1
• Adjacent proper8es: R-4 (west and south); R-1 & R-14 (north), R-8 (east)
CURRENT USE OF THE SITE AND ANY EXISTING IMPROVEMENTS
The site is vacant.
SPECIAL SITE FEATURES (i.e., WETLANDS, WATER BODIES, STEEP SLOPES)
The site contains steep slopes and an unregulated drainage ditch.
STATEMENT ADDRESSING SOIL TYPE AND DRAINAGE CONDITIONS
Per the Geotechnical Engineering Report "The referenced geologic map iden fies kame deposits (Qit) across
the subject site, with ground moraine deposits (Qgt) present on the western property margin. The geological
map iden fies a historic pebble mine on the property, located approximately in the northeastern corner of
the subject site. As described on the geologic map, Kame deposits are areas of sand and pebble gravel in
sca%ered terraces. Ground moraine deposits are characterized as abla on ll over thick sec ons of
lodgment ll. Till is typically comprised of unsorted cobbles, pebbly sand, and sandy silt, with a locally
compact layer (referred to as “hardpan”) at depth.
The referenced WSS resource iden fies Alderwood gravelly sandy loam, 8 to 15 percent slopes, (Map Unit
Symbol: AgC) as the primary units underlying the subject site. The Alderwood series formed in glacial ll
plains.
Based on the field observa ons, the na ve deposi onal environment is characterized as rela vely medium
dense to dense glacial ll, which is consistent with local geologic mapping. A pebble and gravel surface mine
was historically located on the subject site based on the referenced geologic map. Based on our experience
with kame deposits in similar deposi onal environments, in our opinion, the clean sands and gravels
associated with the kame deposits have been removed from the subject site, with the remainder of the na ve
soils being characterized as glacial ll."
The project's stormwater will be conveyed to a proposed stormwater drainage facility located in Tract A.
The stormwater drainage facility will consist of a deten8on chamber system to provide conserva8on flow
control followed by a water quality vault to provide basic water quality treatment. The deten8on facility is
located at the southwest corner of the project within the private access tract. The water quality facility will
outlet to the exis8ng roadside ditch in South 55th Street where the drainage will be conveyed to the exis8ng
drainage ouIall to Springbrook Creek, which is the natural downstream drainage course.
Talbot Hills
Schneider Family Homes | Preliminary Short Plat
Page 4
23382.005-Project Narrative-Prelim Short Plat
PROPOSED USE OF THE PROPERTY AND SCOPE OF THE PROPOSED DEVELOPMENT
The proposed project is a single-family residen8al project consis8ng of infill development of a large single-
family lot located on South 55th Street. The proposed project is to construct four (4) single-family lots with
associated roads and u8li8es.
FOR PLATS, INDICATE THE PROPOSED NUMBER, NET DENSITY, AND RANGE OF SIZES (NET LOT AREA) OF THE
NEW LOTS
The project will contain four lots for detached single-family
residences. The gross site area is 98,010 sf (2.25 acres). The net
site area is ±0.86 ac in R-1 and ±1.03 ac (allowances for
rounding). Net density of the project is one dwelling units per
net acre (du/acre) in R-1 and four dwellings per acre in R-4. Each
lot contains a minimum of 250 square feet of private open space
in their rear yards.
ACCESS
The project will construct one new private shared driveway in Tract A, which will provide direct access for
the lots. Frontage improvements will be constructed on South 55th Street along a por8on of the property's
frontage.
PROPOSED OFF-SITE IMPROVEMENTS (i.e., INSTALLATION OF SIDEWALKS, FIRE HYDRANTS, SEWER MAIN,
ETC.)
Offsite construc8on could include limited road shoulder widening along South 55th Street or other
improvement for school walking condi8ons. Frontage improvements, including pavement widening, curb
and guKer, sidewalks, street trees, and street ligh8ng will occur along a por8on of the property's frontage.
TOTAL ESTIMATED CONSTRUCTION COST AND ESTIMATED FAIR MARKET VALUE OF THE PROPOSED PROJECT
The construc8on costs and fair market value are to be determined.
ESTIMATED QUANTITIES AND TYPE OF MATERIALS INVOLVED IF ANY FILL OR EXCAVATION IS PROPOSED
Approximately 9,000 cubic yards of total grading will be necessary for the project, with a net export of
approximately 8,500 cubic yards. Exported material will be hauled to an approved fill site. At this 8me,
imported fill is not an8cipated.
NUMBER, TYPE, AND SIZE OF ANY TREES TO BE REMOVED
Per the Tree Protec8on Plan by, A.B.C. Consul8ng Arborists LLC dated September 3, 2025:
• Cri8cal Area or Buffer Trees: There were 16 trees located in a steep slope area or an associated
buffer.
Talbot Hills
Schneider Family Homes | Preliminary Short Plat
Page 5
23382.005-Project Narrative-Prelim Short Plat
• Non-viable/Hazard Trees: 35 non-viable or hazard trees on the site.
• Conflict with Improvements: Of the 88 significant trees 41 conflict with the site improvements and
will be removed.
• Trees to be Retained: 47 significant viable trees in the net por8on of the site are proposed for
reten8on and will be retained.
• Offsite Trees: There were 0 offsite trees near the site that had driplines that may extend over
construc8on areas.
EXPLANATION OF ANY LAND TO BE DEDICATED TO THE CITY
No land dedica8on is an8cipated.
ANY PROPOSED JOB SHACKS, SALES TRAILERS, AND/OR MODEL HOMES
To be determined.
CONSTRUCTION STANDARDS
1. Haul Routes: A construction plan indicating haul routes and hours, construction hours, and a traffic
control plan must be submitted to the Development Services Division for approval prior to a
construction permit being issued.
2. Haul Hours: Haul hours shall be restricted to the hours between eight-thirty (8:30) a.m. and three-
thirty (3:30) p.m., Monday through Friday unless otherwise approved in advance by the
Development Services Division.
3. Permitted Work Hours in or Near Residential Areas: Construction activities that require
construction or building permits and that are conducted in residential areas or within three
hundred feet (300') of residential areas shall be restricted to the following hours:
Talbot Hills
Schneider Family Homes | Preliminary Short Plat
Page 6
23382.005-Project Narrative-Prelim Short Plat
a. Single Family Remodel or Single Family Addition Construction Activities: Single family
remodel or single family addition construction activities shall be restricted to the hours
between seven o’clock (7:00) a.m. and ten o’clock (10:00) p.m., Monday through Friday.
Work on Saturdays and Sundays shall be restricted to the hours between nine o’clock
(9:00) a.m. and ten o’clock (10:00) p.m.
b. Commercial, Multi-Family, New Single Family and Other Nonresidential Construction
Activities: Commercial, multi-family, new single family and other nonresidential
construction activities shall be restricted to the hours between seven o’clock (7:00) a.m.
and eight o’clock (8:00) p.m., Monday through Friday. Work on Saturdays shall be
restricted to the hours between nine o’clock (9:00) a.m. and eight o’clock (8:00) p.m. No
work shall be permitted on Sundays.
4. Emergency Extensions to Permitted Work Hours: The Development Services Division Director is
authorized to grant an extension of working time during an emergency. An emergency shall include
but is not limited to natural and manmade disasters.
5. Temporary Erosion Control: Temporary erosion control must be installed and maintained for the
duration of the project. This work must comply with the Surface Water Design Manual and must
be approved by the Renton Development Services Division.