HomeMy WebLinkAboutC22005922 Conditions of ApprovalDEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
Conditions for Permit C22005922
Engineering
1 THE PROJECT SHALL DEMONSTRATE THAT IT MEETS THE MINIMUM REQUIREMENTS OF SECTION
1.2.9.2.2 BY PROVIDING A BMP PER SECTION 1.2.9.2.2 OR BY DEMONSTRATING LID PERFORMANCE
STANDARD PER SECTION 1.2.9.1.B.
THE TIR SHALL BE REVISED AND RESUBMITTED TO THE DEVELOPMENT ENGINEERING PROJECT
MANAGER FOR REVIEW AND APPROVAL PRIOR TO INSTALLATION OF ON-SITE BMPS.
Not Satisfied
2 ADD PUMP SYSTEM TO OPERATIONS AND MAINTENANCE MANUAL AND RESUBMIT TIR TO
DEVELOPMENT ENGINEERING PROJECT MANAGER FOR REVIEW AND APPROVAL PRIOR TO PROJECT
CLOSEOUT.
Not Satisfied
3 THE PROJECT SHALL DEMONSTRATE THE NEED FOR WALLS WITHIN THE RIGHT-OF-WAY AND PROVIDE
AN UPDATED GRADING PLAN AND CROSS SECTIONS TO THE CURRENT PLANNING PROJECT MANAGER
FOR REVIEW AND APPROVAL PRIOR TO INSTALLATION OF ANY WALLS.
Not Satisfied
4 THE PROJECT SHALL ELIMINATE THE SOUTHERNMOST WALL WITHIN THE RIGHT-OF-WAY AND PROVIDE
AN UPDATED GRADING PLAN TO THE DEVELOPMENT ENGINEERING PROJECT MANAGER FOR REVIEW
AND APPROVAL PRIOR TO INSTALLATION OF ANY WALLS.
Not Satisfied
Page 1 of 1