HomeMy WebLinkAboutP_Tabor Crowall Emergency Stabilization Work Plan Project: #6245993 Tabor Crowall Revetment Date: December 15, 2025 To: Mark Ruebel, Capital Strike Team Supervisor River and Floodplain Management Email: Mark.Ruebel@kingcounty.gov Page 1 Contract #6245993 Tabor Crowall Revetment Construction Work Plan Tabor Crowall Revetment – Construction Work Plan Scope of Work · Secure the Cedar Riverbank as shown in the Tabor Crowall Revetment plans. · Design and implement Tra ic Control Plans (TCP) to ensure safe access to the work zone. · Clear and prepare the site for heavy equipment. · Install silt fence and plastic covering for stockpiles. · Install steel sheets for protection and weight dispersion. · Haul and stockpile 3–5 man-sized rock. · Place 3–5-man rock, working from east to west. · Place Class 5 Riprap over large rocks. · Compact rock using excavator bucket. · Clean up stockpile area, spread topsoil, and hydroseed. Supervisory Personnel Name Company Role Phone Mike Dysert Johansen Construction Division Manager 206-396-9784 Justin Drotz Johansen Construction General Foreman 253-421-2882 Jacob Obrigewitsch Johansen Construction Senior Project Engineer 253-417-0877 Dan Madsen Johansen Construction Foreman 206-786-5190 Schedule Work Hours: Monday – Friday, 7:00 AM to 5:30 PM Description Start Date End Date Prepare and Submit TCP 12/15/25 12/16/25 Clear and Prep Site 12/16/25 12/16/25 Project: #6245993 Tabor Crowall Revetment Date: December 15, 2025 To: Mark Ruebel, Capital Strike Team Supervisor River and Floodplain Management Email: Mark.Ruebel@kingcounty.gov Page 2 Contract #6245993 Tabor Crowall Revetment Construction Work Plan Install BMPs 12/16/25 12/16/25 Install Steel Sheets 12/16/25 12/16/25 Haul and Place 3–5 Man Rock 12/17/25 12/19/25 Haul and Place Class 5 Riprap 12/22/25 12/23/25 Remove Steel Sheets & Spread Topsoil 12/23/25 12/24/25 Hydroseed 12/29/25 12/29/25 Construction Sequencing 1. Implement TCP for safe access; requires an additional lane on Eastbound SR 169 for steel sheet and rock hauling. 2. Clear and level site; excavate 6” to align with sidewalk for steel sheet placement. Stockpile excavated topsoil for later use. 3. Install silt fence and plastic sheeting over stockpiles. 4. Install steel sheets for protection and weight distribution; overlap sheets if necessary for stability. 5. Haul and stockpile 3–5 man-sized rock. 6. Place rock from east to west, maintaining safe distance from slide edge. Once stabilized, place remaining rock and encapsulate with Class 5 Riprap. 7. Compact rock using excavator bucket. 8. Spread stockpiled topsoil and hydroseed. 9. Inspect sidewalk for damage and repair as needed. Materials · Silt Fence · Plastic Sheeting · Steel Sheets · 3–5 Man Rock (Mixed) · Class 5 Riprap · Hydroseed · Concrete (if sidewalk replacement is required) Project: #6245993 Tabor Crowall Revetment Date: December 15, 2025 To: Mark Ruebel, Capital Strike Team Supervisor River and Floodplain Management Email: Mark.Ruebel@kingcounty.gov Page 3 Contract #6245993 Tabor Crowall Revetment Construction Work Plan Equipment · 200-Class Excavator (rock placement) · 320 Loader (sheet handling and stockpile management) · Mini Excavator (site cleanup) Inspection & Testing Spec Section Test Description Responsible Party Timing N/A Visual Inspection King County During rock placement Prerequisites & Safety · Prerequisite: City of Renton must approve TCP before work begins. · Hold pre-activity meeting. · Stay clear of leading edge. · Use spotters for pedestrian safety. · Make eye contact with operators before entering work zone. · Wear eye protection at all times. · Stay clear of trucks during rock dumping. Hazardous Material Control · Place only clean rock in river channel. · Ensure spill kit is onsite and fully stocked. Special Events & Notifications · Notify King County and City of Renton if riverbank erosion approaches roadway. · Suspend work if river levels become unmanageable. Important Notes · Site conditions can change rapidly; inspect frequently for shifting embankments. · Keep personnel away from slide edge until stabilized. Contract #6245993 Name: Tabor Crowall Revetment Site Preparation Plan Silt Fence Clearing Area Topsoil Stockpile Contract #6245993 Name: Tabor Crowall Revetment Site Protection Stabilization Plan Steel Plate 8x20 Coldmix Asphalt Ramp Plastic Sheeting Contract #6245993 Name: Tabor Crowall Revetment Scour/Slide Repair Plan Steel Plate 8x20 Coldmix Asphalt Ramp Plastic Sheeting Basalt Rocks Sidedump trucks will haul to stockpile. A loader will be utilized to manage stockpile 200 Class Excavator will take from stockpile and place rock within the Scour area Scour/Slide Repair Plan Contract #6245993 Name: Tabor Crowall Revetment Place Mixed 3-5 Man Rock Scour/Slide Repair Plan Contract #6245993 Name: Tabor Crowall Revetment Place Class 5 Riprap over Larger Rock Scour/Slide Repair Plan Contract #6245993 Name: Tabor Crowall Revetment 60'-11" Scour/Slide Repair Plan Contract #6245993 Name: Tabor Crowall Revetment 60'-11" Tabor/Crowall Grading Exhibit Date Prepared - 06/13/2025 TC D S TC M I D TC U S 30'-0" Tabor/Crowall Grading Exhibit Date Prepared - 06/13/2025 proposed grade, typ existing grade, typ current river level (estimated and fluctuating) pre-slide/scour bank per topo survey data Current conceptual design final grading (gray line type) estimated slide/scour (based on drone photo post-slide) (?) possible residual slide debris at base on head scarp (?) removal is highly recommended prior to placement of geotextile and riprap to provide suitable foundation base for armor. 16-oz non-woven separation/filter geotextile for riprap bedding (such as Mirafi/Solmax 1160N. Secure with pins class 5 riprap (basalt or similar) for armoring(permanent or temporary) red line type setup paint marks/survey nails on road shoulder to monitor movement