ADVISORY NOTES TO APPLICANT
The following notes are supplemental information provided in conjunction with the administrative land
use action. Because these notes are provided as information only, they are not subject to the appeal
process for the land use action.
Planning:
(Contact: Valerie Porter, 425-430-7288, vporter@rentonwa.gov)
1. RMC section 4-4-030.C.2 limits haul hours between 8:30 am to 3:30 pm, Monday through Friday
unless otherwise approved by the Development Services Division.
2. Commercial, multi-family, new single family and other nonresidential construction activities shall
be restricted to the hours between seven o’clock (7:00) a.m. and eight o’clock (8:00) p.m., Monday
through Friday. Work on Saturdays shall be restricted to the hours between nine o’clock (9:00) a.m.
and eight o’clock (8:00) p.m. No work shall be permitted on Sundays.
3. Within thirty (30) days of completion of grading work, the applicant shall hydroseed or plant an
appropriate ground cover over any portion of the site that is graded or cleared of vegetation and
where no further construction work will occur within ninety (90) days. Alternative measures such
as mulch, sodding, or plastic covering as specified in the current King County Surface Water
Management Design Manual as adopted by the City of Renton may be proposed between the dates
of November 1st and March 31st of each year. The Development Services Division’s approval of this
work is required prior to final inspection and approval of the permit.
4. A National Permit Discharge Elimination System (NPDES) permit is required when more than one
acre is being cleared.
5. The applicant will be required to submit a Final Stream Mitigation Report and Maintenance and
Monitoring proposal. In addition, the applicant will be required to comply with all the code
requirements of RMC 4-3-050 Critical Areas. This includes, but is not limited to, placing the critical
area within a Native Growth Protection Easement, providing fencing and signage, and providing the
City with a site restoration surety device and, later, a maintenance and monitoring surety device.
6. The applicant may not fill, excavate, stack or store any equipment, dispose of any materials,
supplies or fluids, operate any equipment, install impervious surfaces, or compact the earth in any
way within the area defined by the drip line of any tree to be retained.
7. The applicant shall erect and maintain six foot (6') high chain link temporary construction fencing
around the drip lines of all retained trees, or along the perimeter of a stand of retained trees.
Placards shall be placed on fencing every fifty feet (50') indicating the words, “NO TRESPASSING –
Protected Trees” or on each side of the fencing if less than fifty feet (50'). Site access to individually
protected trees or groups of trees shall be fenced and signed. Individual trees shall be fenced on
four (4) sides. In addition, the applicant shall provide supervision whenever equipment or trucks
are moving near trees.
8. This permit shall comply with the Bald and Golden Eagle Protection Act. The permitted is
responsible for adhering to the U.S. Fish and Wildlife Service National Bald Eagle Management
Guidelines (2007) and /or your U.S. Fish and Wildlife Service permit.
Development Engineering:
(Contact: Huy Huynh, 425-430-7384, hhuynh@rentonwa.gov)
1. See Attached Development Engineering Memo dated January 2, 2026.
EXHIBIT 13
Docusign Envelope ID: 55771A66-86E0-4A60-BC11-AE213CF62585
ADVISORY NOTES TO APPLICANT
Page 2 of 2 LUA22-000xxx
Fire Authority:
(Contact: Corey Thomas, 425-276-9582, cthomas@rentonrfa.org)
1. No comments at this time.
Technical Services:
(Contact: Amanda Askren, 425-430-7369, aaskren@rentonwa.gov)
1. No comments at this time.
Community Services:
(Contact: Erica Schmitz, 425-430-6614, eschmitz@rentonwa.gov)
1. Parks Impact fee per Ordinance 5670 applies.
Police:
(Contact: Cyndie Morris, 425-430-7521, cmorris@rentonwa.gov)
1. No comments at this time.
Building:
(Contact: Rob Shuey, 425-430-7290, rshuey@rentonwa.gov)
1. No comments at this time.
Docusign Envelope ID: 55771A66-86E0-4A60-BC11-AE213CF62585
DEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
M E M O R A N D U M
DATE: January 2, 2026
TO: Mariah Kerrihard, Planner
FROM: Huy Huynh, Civil Engineer II
SUBJECT: Billing Short Plat
14103 160th Ave SE
LUA24-000190
I have reviewed the application for the Billing Short Plat located at 14103 160th Ave SE and have the
following comments:
EXISTING CONDITIONS
The site is a single parcel (1423059011) of approximately 17,100 square feet. The site currently contains
a single family home. The site is fronted by private property in the north, private property to the west,
private property to the South and 160th Ave SE to the east.
WATER: The proposed development is within the King County Water District 90 service area
SEWER: The proposed development is within the City’s sewer service area. There is an existing 10-inch
PVC gravity wastewater main located in 160th Ave SE (record drawing S-323537), located east of
the proposed site, conveying wastewater south. There are two existing polyvinyl chloride sewer
stubs serving the existing home on the property.
STORM: The site is slightly sloped from the northwest to southeast. There is an existing 12-inch public
stormwater main on the east side of 160th Ave SE (see record drawing SWP2703472). There is an
existing surface water ditch and a 12-inch polyethylene stormwater main on the West side of
160th Ave Se (no record drawing)
STREETS: The proposed development fronts 160th Ave NE along the east property line. 160th Ave NE is
classified as a Residential Access Street with an existing ROW of approximately 60 feet.
WATER COMMENTS
1. Water service is provided by KC Water District 90.
2. Applicant shall obtain a water availability certificate from the District and provide it with the civil
construction permit submittal.
Docusign Envelope ID: 55771A66-86E0-4A60-BC11-AE213CF62585
Billing Short Plat– LUA24-000190
Page 2 of 7
Jan 2nd, 2026
a. A water availability certificate was provided with the land use application.
3. Review of the water plans will be conducted by King County Water District 90 and the Renton
Regional Fire Authority.
4. Plans approved by King County Water District 90 shall be routed to the City for final review prior
to civil construction permit issuance.
SEWER COMMENTS
1. Individual sewer stubs from the sewer main and individual side sewers are required for each lot.
All new sewer stubs shall conform to the standards in RMC 4-6-060 and City of Renton Standard
Details.
a. Proposal depicts keeping the existing sewer stub and install a new 4” PVC stub and side
sewer for the back lot. Sewer stub from the main to the property line must be a
minimum of 6” per COR std plan 406.1 and side sewer from the property line to the
house must be a minimum of 4” per COR std plan 406.2. Applicant shall revise the plans
submit with the civil construction permit application accordingly to show sewer stubs
and side sewers conforming to City standards.
2. The development is subject to a wastewater system development charge (SDC) fee. SDC fee for
sewer is based on the size of the new domestic water to serve the project. Current fees can be
found in the 2026 Development Fees Document on the City’s website. Fees will be charged based
on the rate at the time of construction permit issuance.
a. The current sewer fee for is $4,025.00 per 1-inch meter.
b. Final determination of applicable fees will be made after the water meter size has been
determined.
c. The full fee schedule can be found at:
https://edocs.rentonwa.gov/Documents/DocView.aspx?id=10067870&dbid=1&repo=Cit
yofRenton
3. The Central Plateau Interceptor Area Special Assessment District (SAD) is applicable on the
project. The SAD has reached its maximum assessment and is $538.48 per lot. Fees are due at
the time of construction permit issuance.
4. The Central Plateau Interceptor Frontage Special Assessment District is applicable on the
project. The SAD has reached its maximum assessment and is $8,889.82 per lot. Fees are due at
the time of construction permit issuance.
STORM DRAINAGE COMMENTS
1. A geotechnical report dated November 19, 2021, completed by Nelson Geotechnical Associates.
Inc, was provided with the Land Use Application. The report discusses the soil and groundwater
characteristics of the site and provides recommendations for project design and construction.
Geotechnical recommendations presented in this report state that full infiltration is not feasible;
however, shallow, low-impact design infiltration system may be feasible at specific areas within
the site.
2. A revised Preliminary Technical Information Report (TIR) dated on November 22nd, 2025 was
submitted with the Land Use Application. Based on the City of Renton’s flow control map, the site
falls within the Flow Control Duration Standard- Matching Forested and falls within a Flood
Problem Flow Control Standard and is within the Lower Cedar River Drainage Basin. Therefore,
the project must match the Existing site conditions for the 100-year peaks, in addition to matching
the Forested site conditions for the 2-year and 10-year peaks and the discharge durations from
Docusign Envelope ID: 55771A66-86E0-4A60-BC11-AE213CF62585
Billing Short Plat– LUA24-000190
Page 3 of 7
Jan 2nd, 2026
50% of the 2-year peak to the full 50-year peak. The report is based on a Full drainage review and
Core Requirements 1 thru 9 and the six Special Requirements have been discussed in the Technical
Information Report.
a. Offsite Analysis, RSWDM Core Requirement #2: All proposed projects must submit an
offsite analysis report that assesses potential offsite drainage and water quality impacts
associated with development of the project site.
i. The preliminary TIR submittal indicated that there are no downstream drainage
problems.
b. Flow Control, RSWDM Core Requirement #3: Any proposed detention and/or water
quality vault shall be designed in accordance with the RSWDM that is current at the time
of civil construction permit application. The preliminary TIR claims an exemption from
providing a flow control facility as the site split into two different TDAs and the run-offs
from each TDAs generate less than 0.15 CFS.
i. Staff concurs with the exemption based on the conceptual plan and revised TIR
included with the land use application. A more detailed review will be
conducted at the time of civil construction permit.
c. Conveyance, RSWDM Core Requirement #4: All new conveyance systems constructed as
part of the project must be sized to RSWDM standards for the total tributary area (onsite
and offsite) that the storm systems serve.
i. Conveyance analysis is not provided with the preliminary TIR submittal.
Applicant to provide conveyance analysis for the existing stormwater system
per RSWDM section 1.2.4.2.
ii. Applicant shall relocate existing stormwater system to the flow line of the new
frontage.
d. Construction Stormwater Pollution Prevention, Core Requirement #5: The proposal
indicates that a plan will be addressed during final design.
i. A CSWPP plan shall be provided as part of the TIR and construction plans
included with the Civil Construction Permit application.
e. Maintenance and Operations, Core Requirement #6: The proposal indicates that a
maintenance and operation manual will be addressed during final design.
i. A maintenance and operation manual shall be provided as part of the TIR and
included with the Civil Construction Permit application instead of the building
permit process as stated in the preliminary TIR submittal.
f. Water Quality, RSWDM Core Requirement #8: All projects that add more than 5,000
square feet of pollution generating impervious surface that is not fully dispersed and less
than 0.75 acre of pollution generating pervious surface that is not fully dispersed require
water quality. The TIR states that the project will utilize landscape area as stormwater
filter strip to provide water quality treatment for PGIS.
i. Staff concurs with this approach based on the conceptual plan and revised TIR
included with the land use application; however, a more detailed review will be
conducted at the time of civil construction permit.
g. Onsite BMPs, RSWDM Core Requirement #9: Appropriate on-site BMPs will be required
to help mitigate the new runoff created by this development. The project proposes
bioretention and infiltration per section 1.2.9.2.1 of the 2022 RSWDM - Small Lot BMP
requirements.
i. Staff concurs with this approach based on the conceptual plan and revised TIR
included with the land use application. A more detailed review will be
conducted at the time of civil construction permit.
Docusign Envelope ID: 55771A66-86E0-4A60-BC11-AE213CF62585
Billing Short Plat– LUA24-000190
Page 4 of 7
Jan 2nd, 2026
3. There is a 2026 System Development Charge of $0.94 per sqft. SDC fees are payable at
construction permit issuance.
TRANSPORTATION/STREET COMMENTS
1. Frontage improvements are required for all new construction with valuation in excess of
$175,000. The proposed development fronts 160th Ave NE along the East property line
a. 160th Ave NE is classified as a residential access street, with an existing right-of-way (ROW)
width of approximately 60-feet with an existing paved width of approximately 26-feet. To
meet the City’s complete street standards for Residential Access streets, a minimum ROW
width of 60-feet is required. Per RMC 4-6-060 half of street improvements as taken from
the ROW centerline shall be required and include a 26-foot paved road (16-feet each
side), a 0.5-foot curb, an 8-foot planting strip, a 5-foot sidewalk, 0.5-foot clear space
behind walk. No dedication is required.
1. Conceptual frontage improvement construction plan depicts the above
listed improvements which is acceptable.
2. Shared driveways are allowed for access up to 4 lots provided at least one of the four lots abuts a
public right-of-way with at least fifty linear feet of frontage and the subject lots are not created
by a subdivision of ten or more lots. Refer to the shared driveway requirements as outlined in
RMC 4-6-060.J. Shared driveways shall be within a tract; the width of the tract and paved surface
shall be a minimum of sixteen feet; the Fire Authority may require the tract and paved surface to
be up to twenty feet wide. If a shared driveway abuts properties that are not part of the
subdivision an eight-foot-wide landscaped strip shall be provided between the shared driveway
and neighboring properties.
a. Staff concurs with shared driveway depicted on civil construction plan.
3. Street lighting is not required along all public street frontages for projects with less than four (4)
homes.
4. All existing and proposed utility lines along the property frontage must be relocated underground
per RMC 4-6-090.
5. For dead end roads in excess of 150 feet an approved fire access turnaround is required. See city
code 4-6-060.H for types of turnarounds required.
a. Fire turnaround depicted in civil construction drawing is conceptually acceptable.
Applicant to show dimensions and radii on drawing submit with civil construction
permit.
6. Refer to City code 4-4-080 regarding driveway regulations.
a. A minimum separation of 5 feet is required between driveway and the property line.
b. Maximum driveway slopes shall not exceed 15%. Driveways exceeding 8% shall provide
slotted drains.
c. The maximum width of single loaded garage driveway shall not exceed nine feet (9') and
double-loaded garage driveway shall not exceed sixteen feet (16').
7. Paving and trench restoration within the City of Renton right of way shall comply with the City’s
Restoration and Overlay requirements.
8. The transportation impact fee that is current at the time of building permit application will be
levied, payable at building permit issuance.
a. The 2026 Transportation Impact Fee is $11,485.67 per single family home
Docusign Envelope ID: 55771A66-86E0-4A60-BC11-AE213CF62585
Billing Short Plat– LUA24-000190
Page 5 of 7
Jan 2nd, 2026
GENERAL COMMENTS
1. The fees listed are for 2026. The fees that are current at the time of the respective permit issuance
will be levied. Please see the City of Renton website for the current fee schedule.
2. All civil plans shall conform to the current City of Renton survey and drafting standards. Current
drafting standards can be found on the City of Renton website.
3. A separate plan submittal will be required for a construction permit for utility work and street
improvements. All plans shall be prepared by a licensed Civil Engineer in the State of Washington.
Please see the City of Renton website for the Construction Permit Application and Construction
Permit Process and Submittal Requirements. Please contact the City to schedule a construction
permit intake meeting.
4. A demo permit is required for the demolition of the existing building(s). The demo permit shall be
acquired through the building department.
5. All utility lines (i.e. electrical, phone, and cable services, etc.) serving the proposed development
must be underground in accordance with RMC 4-6-090. The construction of these franchise
utilities must be inspected and approved by a City of Renton inspector.
6. Retaining walls that are 4’ or taller from bottom of footing and stormwater detention vaults will
require a separate building permit. Structural calculations and plans prepared by a licensed
engineer will be required as part of the building permit review.
7. Paving and trench restoration within the City of Renton right of way shall comply with the City’s
Trench Restoration and Street Overlay Requirements.
8. Adequate separation between utilities as well as other features shall be provided in
accordance with code requirements.
a. 7-feet minimum horizontal and 1-foot vertical separation between storm and
other utilities is required with the exception of water lines which require 10-
feet horizontal and 1.5-feet vertical.
b. The stormwater line should be minimum 5 feet away from any other
structure or wall or building.
c. Trench of any utility should not be in the zone of influence of the retaining
wall or of the building.