HomeMy WebLinkAboutCESCL Inspection_RTC_02-27-26Construction Stormwater Site Inspection Form
Page 1
Project Name Renton Transit Center Permit # WAR314062 Inspection Date 02/27/26 Time 1030
Name of Certified Erosion Sediment Control Lead (CESCL) or qualified inspector if less than one acre
Print Name: Ashley Kollmorgen
Approximate rainfall amount since the last inspection (in inches): 0.31”
Approximate rainfall amount in the last 24 hours (in inches): 0.0”
Current Weather Clear Cloudy x Mist Rain Wind x Fog
A. Type of inspection: Weekly Post Storm Event Daily
B. Phase of Active Construction (check all that apply):
Pre Construction/installation of
erosion/sediment controls
Clearing/Demo/Grading Infrastructure/storm/roads
Concrete pours Vertical
Construction/buildings
Utilities
Offsite improvements Site temporary stabilized Final stabilization
C. Questions:
1. Were all areas of construction and discharge points inspected? Yes No
2. Did you observe the presence of suspended sediment, turbidity, discoloration, or oil sheen Yes No X
3. Was a water quality sample taken during inspection? (refer to permit conditions S4 & S5) Yes No
4. Was there a turbid discharge 25 NTU or greater, or Transparency 6 cm or less?* Yes No
5. If yes to #4 was it reported to Ecology? Yes No
6. Is pH sampling required? pH range required is 6.5 to 8.5. Yes No
If answering yes to a discharge, describe the event. Include when, where, and why it happened; what action was taken,
and when.
Sampling Results: Date:
Parameter Method (circle one) Result Other/Note
NTU cm pH
Turbidity tube, meter, laboratory
Turbidity tube, meter, laboratory
Turbidity tube, meter, laboratory
Construction Stormwater Site Inspection Form
Page 2
D. Check the observed status of all items. Provide “Action Required “details and dates.
Element # Inspection Response Description Action
required
(describe in
section F)
yes no n/a
1
Clearing
Limits
Before beginning land disturbing
activities are all clearing limits,
natural resource areas (streams,
wetlands, buffers, trees) protected
with barriers or similar BMPs? (high
visibility recommended)
Pre-installation of high vis
fencing for tree and shrub
protection.
2
Construction
Access
Construction access is stabilized
with quarry spalls or equivalent
BMP to prevent sediment from
being tracked onto roads?
Sediment tracked onto the road
way was cleaned thoroughly at the
end of the day or more frequent as
necessary.
3
Control Flow
Rates
Are flow control measures installed
to control stormwater volumes and
velocity during construction and do
they protect downstream
properties and waterways from
erosion?
Treatment system installation
in progress.
If permanent infiltration ponds are
used for flow control during
construction, are they protected
from siltation?
4
Sediment
Controls
All perimeter sediment controls
(e.g. silt fence, wattles, compost
socks, berms, etc.) installed, and
maintained in accordance with the
Stormwater Pollution Prevention
Plan (SWPPP).
Asphalt berms installed across
driveways and halfway across
North end of site.
Sediment control BMPs (sediment
ponds, traps, filters etc.) have been
constructed and functional as the
first step of grading.
Stormwater runoff from disturbed
areas is directed to sediment
removal BMP.
5
Stabilize
Soils
Have exposed un-worked soils
been stabilized with effective BMPs
to prevent erosion and sediment
deposition?
Construction Stormwater Site Inspection Form
Page 3
5
Stabilize Soils
Cont.
Are stockpiles stabilized from erosion,
protected with sediment trapping
measures and located away from drain
inlet, waterways, and drainage channels?
Have soils been stabilized at the end of
the shift, before a holiday or weekend if
needed based on the weather forecast?
6
Protect
Slopes
Has stormwater and ground water been
diverted away from slopes and disturbed
areas with interceptor dikes, pipes and
or swales?
Is off-site storm water managed
separately from stormwater generated
on the site?
Asphalt berm installed
halfway across North side.
Is excavated material placed on uphill
side of trenches consistent with safety
and space considerations?
Have check dams been placed at regular
intervals within constructed channels
that are cut down a slope?
7
Drain Inlets
Storm drain inlets made operable during
construction are protected.
Are existing storm drains within the
influence of the project protected?
8
Stabilize
Channel and
Outlets
Have all on-site conveyance channels
been designed, constructed and
stabilized to prevent erosion from
expected peak flows?
Is stabilization, including armoring
material, adequate to prevent erosion of
outlets, adjacent stream banks, slopes
and downstream conveyance systems?
9
Control
Pollutants
Are waste materials and demolition
debris handled and disposed of to
prevent contamination of stormwater?
Need lid for dumpster to
prevent blow out.
Has cover been provided for all
chemicals, liquid products, petroleum
products, and other material?
Has secondary containment been
provided capable of containing 110% of
the volume?
Were contaminated surfaces cleaned
immediately after a spill incident?
Were BMPs used to prevent
contamination of stormwater by a pH
modifying sources?
Wheel wash wastewater is handled and
disposed of properly.
10
Control
Dewatering
Concrete washout in designated areas.
No washout or excess concrete on the
ground.
Construction Stormwater Site Inspection Form
Page 4
Dewatering has been done to an
approved source and in compliance with
the SWPPP.
3 sumps will be installed to
convey surface water.
Dewatering system
installation in the coming
weeks.
Were there any clean non turbid
dewatering discharges?
11
Maintain
BMP
Are all temporary and permanent
erosion and sediment control BMPs
maintained to perform as intended?
12
Manage the
Project
Has the project been phased to the
maximum degree practicable?
Has regular inspection, monitoring and
maintenance been performed as
required by the permit?
Need to coordinate bird
survey for vegetation
clearing. Implement daily
inspections on 3/3.
Has the SWPPP been updated,
implemented and records maintained?
13
Protect LID
Is all Bioretention and Rain Garden
Facilities protected from sedimentation
with appropriate BMPs?
Is the Bioretention and Rain Garden
protected against over compaction of
construction equipment and foot traffic
to retain its infiltration capabilities?
Permeable pavements are clean and free
of sediment and sediment laden-water
runoff. Muddy construction equipment
has not been on the base material or
pavement.
Have soiled permeable pavements been
cleaned of sediments and pass
infiltration test as required by
stormwater manual methodology?
Heavy equipment has been kept off
existing soils under LID facilities to retain
infiltration rate.
E. Check all areas that have been inspected.
All in place BMPs All disturbed soils All concrete wash out area All material storage areas
All discharge locations All equipment storage areas All construction entrances/exits
Construction Stormwater Site Inspection Form
Page 5
F. Elements checked “Action Required” (section D) describe corrective action to be taken. List the element number;
be specific on location and work needed. Document, initial, and date when the corrective action has been completed
and inspected.
Element
#
Description and Location
Completion
Date
Initials
9 Need lid for dumpster to prevent blow out.
10 Grout outfall and install pump at southern CB
10 Install sump in NW corner
10 Grout outfall and install pump at West entrance CB
12 Need to coordinate bird survey with ST for vegetation clearing
12 Implement daily inspections with George (Shimmick) on 3/3
Attach additional page if needed
Sign the following certification:
“I certify that this report is true, accurate, and complete, to the best of my knowledge and belief.”
Inspected by: (print) Ashley Kollmorgen (Signature) Date: 02/27/26
Title/Qualification of Inspector: Encore - CESCL
Dumpster needs a lid to prevent blow out and
water retention
South Central CB - Grout outfall and install pump
Asphalt berms installed at all entrances Asphalt berm installed halfway across site on
North end.
Install sump in NW corner CB near office trailers at entrance - Grout outfall
and install pump.
Shimmick working on pumping water from well
to treat for first batch of sampling in the water
treatment system.