HomeMy WebLinkAboutChange Order - 2Public Works
Facilities Division CONTRACT NO:CAG-25-016 CO NO. 2
CONTRACT CHANGE ORDER (CO)PROJECT TITLE:Renton Market and Piazza Renovation
TO: Schuchart Corporation (CONTRACTOR)
Description Amount
CRP 002 Unexpected Electrical & FA Re-work 26,351.28$
CRP 014 Replace Lighting on N Façade at Pilaster 6,213.64$
WSST 10.5% for 2026 3,419.31$
-$
-$
-$
CONTRACT SUM:
35,984.23$
(WASHINGTON STATE SALES TAX INCLUDED)
CONTRACT TIME:
CALENDAR DAYS
CONTRACT SUMMARY (Internal Use Only)
ORIGINAL CONTRACT SUM 6,424,546.00$
PREVIOUS ADDITIONS/DELETIONS 34,347.75$
PREVIOUS TOTAL 6,458,893.75$
CHANGE AMOUNT THIS CHANGE ORDER 35,984.23$
REVISED CONTRACT TOTAL 6,494,877.98$
PERCENT TOTAL CHANGE FROM ORIGINAL 1.09%
NOTICE TO PROCEED DATE July 29, 2025
PREVIOUS CONTRACT CALENDAR DAYS 250
PREVIOUS SUBSTANTIAL COMPLETION DATE April 5, 2026
REVISED CONTRACT CALENDAR DAYS THIS CHANGE ORDER 250
CURRENT SUBSTANTIAL COMPLETION DATE April 5, 2026
Architect Acknolwedgement Date Contractor Acknowledgement Date
AUTHORIZING SIGNATURE DATE
The following mutually agreed to and Owner approved Change Order Proposal(s) are hereby incorporated by reference into
the contract.
The foregoing amount covers everything required in connection with the change. All other provisions of the contract remain in full force and
effect.
The City of Renton hereby accepts the foregoing Change Order Proposal(s). This formal acceptance constitutes a Change to the contract only
when authorizing signature is affixed. Invoices incorporating this Change Order constitute acceptance by the Contractor as total
reimbursement due in connection with this Change Order.
OF:
OF:
NO CHANGE
INCREASE
DECREASE
NO CHANGE
INCREASE
DECREASE
1/08/2026
Digitally signed by Brian M. Jonas
Date: 2026.01.08 13:55:50-08'00'Ross Liston
Digitally signed by Ross Liston
DN: C=US, E=ross.liston@schuchart.com,
O=Schuchart Corporation, OU=Sr. Project
Manager, CN=Ross Liston
Date: 2026.01.08 14:39:15-08'00'
CAG-25-016, CO #2-26