HomeMy WebLinkAboutCM_Construction Mitigation_Madueno Short PlatConstruction Mitigation Description For: Madueno Short Plat (LUA Reapplication)
Address: 10639 SE 198th St, Renton, WA 98055 (Parcel #052205-9078)
a. Proposed construction dates; Based on this preliminary short plat reapplication date,
we anticipate construction permits for utilities and plat infrastructure to be finalized in
Spring of 2026, with utility and plat infrastructure construction beginning in Summer 2026.
Home construction on the lots should begin during the Fall of 2026 and run through at least
the Winter of 2027.
b. Hours and days of operation; Construction activities will be limited to the hours
between 7:00am and 8:00pm, Monday through Friday and 9:00am and 8:00pm Saturday. In
addition, haul hours are limited to the hours between 8:30am and 3:30pm on Saturdays,
unless approved in writing in advance by the development services division. No work
permitted on Sundays.
c. Proposed hauling/transportation routes; The site is accessible from the west via 106th
Ave SE / SE 199th St / 108th Avenue SE (to the south) and via 106th Ave SE / SE 196th St /
108th Avenue SE (to the north).
d. Measures to be implemented to minimize dust, traffic and transportation impacts,
erosion, mud, noise and other noxious characteristics; Water Truck, Temporary Erosion
Control Plan, BMPs, construction proposed during City of Renton permitted work hours.
e. Any special hours proposed for construction or hauling (i.e. weekends, late nights);
and No special hours for construction or hauling are anticipated or proposed at this time.
f. Preliminary traffic control plan; Site is located along 106th Ave SE (residential access).
Anticipate "construction ahead" warning signs north/south of the project along 106th Ave
SE and 108th Ave SE. Flaggers and additional signage will be provided when work is
required in either right-of-way. Construction staging will be limited to on-site with parking
on-site and along 106th Ave SE only as permitted.