HomeMy WebLinkAboutPeer Review Comment and Status of Response Form_Transpo - TENW COMMENTSLongacres Master Plan Project EIS
PEER REVIEW COMMENT AND STATUS OF RESPONSE FORM
Deliverable: Peer Review of Transportation Reports
Reviewed: February 24, 2026
Peer Review Team Member: Kassi Leingang/Mike Swenson
Comment Response Provided:
Comments Due:
Comment Response Accepted:
Item #
Reviewer
Report Reviewed
Page
Line(s)
Review Comment
Level of Comment1
Status of Response
Explanation
1
Transpo
Longacres Campus Master Plan DEIS TTA (Nov 2025, TENW)
-
-
See minor redline comments in PDF.
2
ADDRESSED
See separate Excel SS for comments
2
City
General
The City issued its Comp Plan in 2024 with an unfinished version of the Transportation Element and Appendix D. The revised TE and Appendix D was issued in Sept. 2025 and revisions occurred
regarding the growth rates and background projects assumed. The project’s TIA should be consistent with the latest version and note it accordingly in the TIA and EIS.
2
ADDRESSED
The revised TE and Appendix D were reviewed and confirmed to be consistent with the draft TE and Appendix D. The growth rates used in the EIS analysis are appropriate.
3
Transpo
1
Alternative (No Action) – make clear that No Action is not a previously approved land use for the site. It represents a lesser density alternative allowed within existing zoning.
3
ADDRESSED
Text has been updated.
4
Transpo
1
Since noting Alternative 3 is allowed under existing zoning, clarify if the others would require a zoning modification
3
ADDRESSED
Text has been updated.
5
Transpo
7
The non-motorized discussion is very broad. Provide additional details to the non-motorized section of the report to support the mode split assumptions made later in the report for
the trip generation of the Alternatives. Suggest a table to highlight adjacent roadways that would be utilized to connect to transit facilities in the area. Consider including a map
of the Interurban Trail showing its relationship to the site.
1
ADDRESSED
Text and figures have been updated.
5
Transpo
7
The non-motorized discussion is very broad. Provide additional details to the non-motorized section of the report to support the mode split assumptions made later in the report for
the trip generation of the Alternatives. Suggest a table to highlight adjacent roadways that would be utilized to connect to transit facilities in the area. Consider including a map
of the Interurban Trail showing its relationship to the site.
1
ADDRESSED
Text and figures have been updated.
6
Transpo
7
The transit discussion is very broad. Provide additional details to the transit section of the report to support the mode split assumptions made later in the report for the trip generation
of the Alternatives. Details to consider include: service days/periods, headways during the weekday peak periods, distances to stops, etc.
1
ADDRESSED
Text figure has been updated (with table) and figure has been added to appendix.
7
Transpo
8
Expand review to include severity and collision types at study intersections including review of non-motorized collisions.
2
ADDRESSED
Tables have been added and text has been updated.
8
City
12
Planned improvement projects included in analysis should only include funded and planned projects for both Renton and Tukwila. Please include funding and timeframe and update included
projects accordingly.
2
ADDRESSED
Text has been updated.
9
Transpo
16
Confirm this list is representative of all pipeline projects to be included and provide a statement as appropriate.
1
ADDRESSED
Text has been updated.
10
City
16
Please identify funding status and timing of construction. Only those funded projects within the horizon year should be included in the analysis. For instance, the traffic signal identified
at Oakesdale/41st is not funded and therefore should not be assumed.
1
ADDRESSED
Text has been updated to identify funding status per the 2025-2030 TIP or other relevant documents.
11
City
16
All traffic signals should be adaptive signal control for 2040 baseline and build conditions. Please include this assumption.
2
ADDRESSED
Text and analysis have been updated to assume that all traffic signals are adaptive control for future 2040 conditions.
11
City
16
All traffic signals should be adaptive signal control for 2040 baseline and build conditions. Please include this assumption.
2
ADDRESSED
Text and analysis have been updated to assume that all traffic signals are adaptive control for future 2040 conditions.
12
Transpo
18
Suggest including the change from existing operations in text following table for the locations shown to operate below standard.
2
ADDRESSED
Text has been updated.
13
Transpo
19
Consider change in title of section – This section does not provide any “Impacts of the Alternatives”, rather it provides an overview of primarily common alternative assumptions.
3
ADDRESSED
Text has been updated.
14
City
21
Please use 2019 data for trip distribution instead of 2022 data to reflect non-covid condition.
2
ADDRESSED
Trip distribution assumptions were checked versus 2022 data and confirmed to be appropriate. No changes to proposed distribution.
15
Transpo
22
Mode Split discussion within trip generation - Please provide source per use rather than generally in a list for all uses. The list does not convey which source applies to which land
use.
1
ADDRESSED
Text has been updated.
16
Transpo
22
Mode Split discussion within trip generation - ITE data should only be assumed when demonstrated no local data is available. If using ITE infill data, demonstrate that ITE's infill
is appropriate for the site.
1
ADDRESSED
Text has been updated.
17
Transpo
23
For clarity of assignment and review purposes, please include all driveways in the figures to demonstrate all trips assigned to/from the site even if not a study intersection for evaluation.
Additionally, overall distribution pattern appears reasonable; however, local assignment of 10% via the BNSF tunnel seems underrepresented. Does this consider location of residential
on the west side of the project site, directly adjacent to this connection? This connection provides quick access to 405 shown to be 30% with an overall 40% to/from the direction.
City staff is seeking input from Tukwila on the current distribution assumption. City of Renton staff will provide further direction regarding this comment.
1
ADDRESSED
Detailed trip assignment figures for the internal intersections and driveways are now included in Appendix G. No changes were made to the distribution assumptions for Alternatives
1/2/3 and Alternatives 1A/2A/3A since it is assumed that vehicular access under these 2 scenarios to/from Longacres Way will be limited. A third access scenario (Alt 1B, 2B, 3B) is
also now included that assumes no access to/from Longacres Way (west of the BNSF railroad) and the Longacres Campus site.
17
Transpo
23
For clarity of assignment and review purposes, please include all driveways in the figures to demonstrate all trips assigned to/from the site even if not a study intersection for evaluation.
Additionally, overall distribution pattern appears reasonable; however, local assignment of 10% via the BNSF tunnel seems underrepresented. Does this consider location of residential
on the west side of the project site, directly adjacent to this connection? This connection provides quick access to 405 shown to be 30% with an overall 40% to/from the direction.
City staff is seeking input from Tukwila on the current distribution assumption. City of Renton staff will provide further direction regarding this comment.
1
ADDRESSED
Detailed trip assignment figures for the internal intersections and driveways are now included in Appendix G. No changes were made to the distribution assumptions for Alternatives
1/2/3 and Alternatives 1A/2A/3A since it is assumed that vehicular access under these 2 scenarios to/from Longacres Way will be limited. A third access scenario (Alt 1B, 2B, 3B) is
also now included that assumes no access to/from Longacres Way (west of the BNSF railroad) and the Longacres Campus site.
18
Transpo
23
Roundabout methodology - Identify the basis of the operational methodology assumed for the roundabout and explain rationale for differing from WSDOT's Sidra Policy. Applies to all roundabout
analysis.
2
ADDRESSED
Text has been updated.
19
Transpo
24
It is noted that “Channelization, intersection control, signal phasing, and site access assumptions for the 2040 With Alternative 1 analysis was assumed to be the same for all three
EIS Alternatives as discussed previously.” Are these parameters also consistent with the Baseline condition? Please clarify text.
2
ADDRESSED
Text has been updated.
20
Transpo
28
Expand discussion of transit impacts. While a capacity analysis is not presented, please provide a connectivity analysis to adjacent stops.
1
ADDRESSED
Text has been updated.
21
Transpo
41
General comments for signal warrants –
Why is alternative 3 not considered?
Warrant 3 appears to only potentially be applicable to Alternative 3. Per MUTCD, Warrant 3 specifies the following condition applies: This signal warrant should be applied only in unusual
cases, such as office complexes, manufacturing plants, industrial complexes, or high-occupancy vehicle facilities that attract or discharge large numbers of vehicles over
a short time. Given the mixed use nature of the project for Alternatives 1 and 2, this warrant does not appear to apply. Please re-evaluate using warrants 1 and 2 or clarify how warrant
3 is applicable to Alternatives 1 and 2.
2
ADDRESSED
Alternative 3 has been added to the signal warrant analysis. A discussion of Warrants 1 and 2 is also now included.
22
City
41
General comments for signal warrants – Include collision history in warrant review – particularly at the intersections of 34th/Oakesdale and 41st/Oakesdale.
2
ADDRESSED
A discussion regarding the crash history warrant has been added.
23
Transpo
41
Location 18 – This is a planned improvement that was assumed as signalized in the Baseline and Alternative analyses presented in the previous sections. This warrant should be reviewed
before assuming future signalization.
1
ADDRESSED
Analysis has been updated to assume stop-control (unsignalized) for future conditions and signal discussed as planned improvement.
23
Transpo
41
Location 18 – This is a planned improvement that was assumed as signalized in the Baseline and Alternative analyses presented in the previous sections. This warrant should be reviewed
before assuming future signalization.
1
ADDRESSED
Analysis has been updated to assume stop-control (unsignalized) for future conditions and signal discussed as planned improvement.
24
Transpo
41
Locations 7,17,30,31 – These are either site access intersections or locations being considered for mitigation. If assumed in primary alternative analysis as signalized, that warrant
should be included at that time or initially assumed as unsignalized and the warrant review included in the mitigation section when being considered.
1
ADDRESSED
Analysis/text have been updated to assume stop control (unsignalized) and signalization as potential mitigation.
25
Transpo
43
Trip assignment - Overall distribution pattern appears reasonable; however, local assignment of 10% via the BNSF tunnel seems underrepresented. Does this consider location of residential
on the west side of the project site, directly adjacent to this connection? Also, this connection provides quick access for outbound WB 405 trips shown to be 30% with an overall 40%
outbound from this connection.
Confirm this has also been reviewed and approved by Tukwila staff.
1
ADDRESSED
No changes were made to distribution since City was in agreement with general distribution assumptions and limited number of trips expected to use Longacres Way if access is provided
via Longacres Way. An additional alternative was added to the EIS analysis that assumes no access to Longacres Way (Alternatives 1B, 2B, 3B).
25
Transpo
43
Trip assignment - Overall distribution pattern appears reasonable; however, local assignment of 10% via the BNSF tunnel seems underrepresented. Does this consider location of residential
on the west side of the project site, directly adjacent to this connection? Also, this connection provides quick access for outbound WB 405 trips shown to be 30% with an overall 40%
outbound from this connection.
Confirm this has also been reviewed and approved by Tukwila staff.
1
ADDRESSED
No changes were made to distribution since City was in agreement with general distribution assumptions and limited number of trips expected to use Longacres Way if access is provided
via Longacres Way. An additional alternative was added to the EIS analysis that assumes no access to Longacres Way (Alternatives 1B, 2B, 3B).
26
Transpo
50
Include overall phasing plan of the development to support timing of mitigation measures being triggered. A triggers review or plan to identify timing should be included in the mitigation
section, including the two-way expansion of the roadway between the Longacres Campus site and the Tukwila Station.
1
ADDRESSED
General phasing plan is included in Appendix A. Timing of mitigation relative to phasing to be discussed further with City as part of the DA.
27
Transpo
50
Mitigation – general comment – Review the mitigation feasibility for all Alternatives (1-3), not only the preferred Alternative. Include a table of operations without mitigation and
with mitigation for all intersections in mitigation section for all alternatives relative to Baseline operations. If mitigation is not feasible, for any intersection under any alternative,
that needs to be identified in a Significant and Unavoidable Impacts section.
1
ADDRESSED
Table has been added that summarizes potential mitigation for all EIS alternatives and compares to baseline operations.
28
City
50
Mitigation – general comment – any proposed signals will need to include adaptive signal control concurrent with our current corridor programing.
3
ADDRESSED
Text has been updated to clarify that any proposed signals would be adaptive signal control.
28
City
50
Mitigation – general comment – any proposed signals will need to include adaptive signal control concurrent with our current corridor programing.
3
ADDRESSED
Text has been updated to clarify that any proposed signals would be adaptive signal control.
29
Transpo
50
# 1 – Identify mitigation for Alternatives 1 and 3, not only preferred. If not feasible, include in a Significant and Unavoidable Impacts section.
1
ADDRESSED
Mitigation Measures text has been updated.
30
Transpo
50
# 2 – Specify which Alternatives the identified mitigation applies to.
2
ADDRESSED
Mitigation Measures text has been updated.
31
Transpo/City
50
# 6 – Complete a signal warrant analysis. Include discussion of queues and impacts to adjacent intersections.
This intersection operating at LOS E or F in 2040. It will experience higher crash rates and no mitigation is considered by the City to be unacceptable. Please re-evaluate mitigation
options at this location.
1
ADDRESSED
Signal warrant analysis at Monster Rd/Oakesdale Ave SW has been added along with a discussion about mitigation options in the mitigation section.
32
Transpo
51
# 7 – Specify which Alternatives the identified mitigation applies to. Include reference to signal warrant analysis. What happens with Alternatives 1 and 3? If not mitigated with identified
improvement under other Alternatives, include in Significant and Unavoidable Impacts section.
2
ADDRESSED
Mitigation Measures text has been updated.
33
Transpo/City
51
# 12 – Demonstrate feasibility of proposed mitigation. Provide a concept as needed to support recommendation. Additionally, specify which Alternatives the identified mitigation applies
to. What happens with Alternatives 1 and 3? If not mitigated with identified improvement under other Alternatives, include in Significant and Unavoidable Impacts section.
2
ADDRESSED
Concept sketch has been prepared and is included in report. Significant and Unavoidable Impacts section has also been added.
33
Transpo/City
51
# 12 – Demonstrate feasibility of proposed mitigation. Provide a concept as needed to support recommendation. Additionally, specify which Alternatives the identified mitigation applies
to. What happens with Alternatives 1 and 3? If not mitigated with identified improvement under other Alternatives, include in Significant and Unavoidable Impacts section.
2
ADDRESSED
Concept sketch has been prepared and is included in report. Significant and Unavoidable Impacts section has also been added.
34
Transpo
51
#16, 17 - Is there not a reasonable mitigation for Alternatives 1 and/or 3?
2
ADDRESSED
Mitigation Measures text has been updated.
35
City
51
#17 – It is anticipated that a signal would be necessary for Alternative 1.
2
ADDRESSED
Mitigation Measures text has been updated.
36
City
51
Oakesdale/41st – This warranted signal should be identified as mitigation and not a background assumption. Credit for traffic impact fees can be collected for this mitigation project.
2
ADDRESSED
Analysis has been updated to assume stop-control (unsignalized) for future conditions and signal discussed as planned improvement in Mitigation Measures section.
37
Transpo/City
52
#24, 27, 28 - Provide rationale why no mitigation is feasible and/or reasonable at these traffic signals and added delay is not significant.
Capacity mitigation should be considered due to the project’s nature of trips originating/destined to-from the freeway. Specific considerations for East Valley Hwy/41st and 43rd below.
• SR 167/180th – Consider adding a WBT lane at intersection along 43rd per the Comp Plan TE. This concept may need to relocate the sidewalk and planter strip but does not assume widening
of the bridge.
• We suggest adding a North and Southbound through lane if the WBR turn is not feasible.
• Evaluate the overall north/south signal operations and feasibility of modifying signal timing to allow for concurrent phasing compared with the split phasing.
• Evaluate the potential of a SBR turn lane onto 43rd (next to the gas station).
1
ADDRESSED
Mitigation Measures text has been updated.
37
Transpo/City
52
#24, 27, 28 - Provide rationale why no mitigation is feasible and/or reasonable at these traffic signals and added delay is not significant.
Capacity mitigation should be considered due to the project’s nature of trips originating/destined to-from the freeway. Specific considerations for East Valley Hwy/41st and 43rd below.
• SR 167/180th – Consider adding a WBT lane at intersection along 43rd per the Comp Plan TE. This concept may need to relocate the sidewalk and planter strip but does not assume widening
of the bridge.
• We suggest adding a North and Southbound through lane if the WBR turn is not feasible.
• Evaluate the overall north/south signal operations and feasibility of modifying signal timing to allow for concurrent phasing compared with the split phasing.
• Evaluate the potential of a SBR turn lane onto 43rd (next to the gas station).
1
ADDRESSED
Mitigation Measures text has been updated.
38
Transpo
54
Add a Significant and Unavoidable Impacts section.
1
ADDRESSED
A Significant and Unavoidable Impacts section has been added to the report.
39
City
Appendix D/General
Synchro summary sheet for Oakesdale/43rd shows the incorrect channelization on the southbound leg. In 2040, the SBT should be a double left and shared right thru. Applicant should correct
and reanalyze to demonstrate the impact and any proposed mitigation.
1
ADDRESSED but City is not sure where this comment came from?
Analysis has been updated as requested.
40
Transpo
Appendix F
Detailed trip generation comments in redlines (PDF).
1
ADDRESSED
Trip generation has been updated per comments and agreed upon by Transpo.
1Comment Level Codes: 1 = Critical Issue - Address; 2 = Factual Issue – Check; 3 = Editorial – Consider.