Beginning April 1, 2018, Medicare will start a year‐long project to replace all current
Medicare cards for beneficiaries to convert from using social security numbers to
using alphanumeric ID numbers. All new Medicare cards will come in the mail.
Nothing needs to be requested. There is a current scam whereby someone claiming
to be from Medicare will call to say a card is on the way but that a temporary card is
needed and a fee is required for the temporary card. They will ask for personal
information so they can process the temporary card. Remember: Medicare handles
all communications by mail unless you call them.
Tuesday, March 20th, 5:30 to 7:30 p.m. The City of Renton and the Federal
Emergency Management Agency (FEMA) will host a public meeting to discuss
updates to floodplain maps based on new data about flood hazards, what it means
to own property in or near a floodplain, and the current appeal and comment
period. The meeting will give residents an opportunity to learn more about both the
current and the preliminary floodplain maps and to get questions about the process
answered. The meeting will be held at the Renton Community Center Banquet
Room, 1715 Maple Valley Highway, Renton.
Information about preventative street maintenance, traffic impact projects, and
road closures happening this week can be found at
http://rentonwa.gov/trafficimpacts. Preventative street maintenance, traffic impact
projects, and road closures will be at the following locations:
Monday, March 19th through Friday, March 23rd, 9:00 a.m. to 3:30 p.m. Single
lane closure at the 300 block of Main Avenue South due to utility work. This
project is weather dependent. Questions may be directed to Pat Miller at 206‐
794‐6162.
Monday, March 19th through Friday, March 23rd, 7:00 a.m. to 3:30 p.m.
Additional truck traffic and hauling will occur in the vicinity of Valley Medical
Ed Prince, Council President
Members of Renton City Council
Page 2 of 2
March 19, 2018
Hospital related to the construction of the new Medical Office Building.
Questions may be directed to Tom Main at 206‐999‐1833.
Monday, March 19th through Friday, March 23rd, 9:00 a.m. to 3:00 p.m. Single
lane closure along northbound Talbot Road South between the northbound I‐
405 on‐ramp and the southbound I‐405 off‐ramp for the I‐405 Direct Connector
Project. Questions may be directed to Justin Johnson at 425‐430‐7291.
Monday, March 19th through Friday, March 23rd, 4:30 a.m. to 12:00 p.m.
Single lane closure along southbound Talbot Road South between the
northbound I‐405 on‐ramp and the southbound I‐405 off‐ramp for the I‐405
Direct Connector Project. Questions may be directed to Justin Johnson at 425‐
430‐7291.
Monday, March 19th through Friday, March 23rd, 8:30 a.m. to 3:00 p.m. Single
lane closure along northbound East Valley Road between SW 19th Street and
Maple Avenue SW for the I‐405 Direct Connector Project. Questions may be
directed to Justin Johnson at 425‐430‐7291.
Monday, March 19th through Friday, March 23rd, 9:00 a.m. to 2:30 p.m.
Expect intermittent lane closures and traffic delays along Talbot Road South (SR
515) related to the I‐405/SR 167 Interchange Direct Connector Project.
In addition, northbound and southbound nighttime lane restrictions and closures
along SR 167 and I‐405 are also scheduled this week related to the project.
Questions may be directed to Craig Smiley, WSDOT I‐405/SR 167 Corridor
Communications, at 425‐456‐8624, or visit the project website at
http://www.wsdot.wa.gov/Projects/I405/SR167ICDirectConnector.
Monday, March 19th through August 2018, 8:30 a.m. to 4:45 p.m. Additional
construction traffic due to the construction of Sartori Elementary School at the
300 block of Park Avenue North and Garden Avenue North. Questions may be
directed to Patrick DeCaro at 425‐207‐6013.
Monday, March 19th through December 2018. Road closure on South 14th
Street between Smithers Avenue South and Davis Avenue South for utility
construction. Questions may be directed to Patrick DeCaro at 425‐207‐6013.
Monday, March 19th through October 2019. The Renton Hill Utility
Replacement Project has commenced with anticipated completion in May 2019.
Following completion of the utility project, an overlay of the affected surface
streets will be conducted as part of the 2019 overlay project. The overlay is
scheduled to be completed prior to October 31, 2019.