HomeMy WebLinkAbout06-18-2026 - Citys Response to bid protest CAG-26-096
June 18, 2026
Sent via e-mail on 6/18/26
Mr. Steve Raudenbush, Owner
Raudenbush Earthworks, LLC
13108 155th Lane SE
Rainier, WA 98576
Sent via e-mail to Steve@raudenbushearthworks.com
RE: Bid Protest for PRV Station 1 Rehabilitation Project CAG-26-096
Notice of Contract Execution
Dear Steve:
The City received your Bid Protest e-mail dated Friday, May 22, 2026, at 3:02 p.m., following the
bid opening held on Wednesday, May 20, 2026, at 3:00 p.m.
Basis of Protest:
The City has reviewed the substance of your protest. Your protest asserts that the apparent low
bidder, CR Construction LLC, failed to provide the name of the rebar installation subcontractor
with whom it intends to directly subcontract if awarded the contract.
Review and Determination:
The City carefully reviewed the bid requirements and applicable statutory provisions, including
RCW 39.30-060 as amended. Under the statute, bidders are required to identify certain
subcontractors, including for structural steel and rebar installation, only for public works
contracts exceeding $1,000,000.
For this project, the engineer’s estimate range is between $475,000 and $500,000. Accordingly,
the statutory subcontractor listing requirement does not apply to this bid solicitation. Therefore,
CR Construction LLC, as well as all other bidders, was not required to provide to complete or
submit a subcontractor listing form including the rebar installation subcontractor as part of its
bid.
Although the subcontractor listing form was included in the bid documents, its inclusion does not
create a mandatory requirement beyond the applicable statutory threshold, nor does it create a
material bid requirement inconsistent with state law. Therefore, the omission identified in your
protest does not constitute a material defect, irregularity, or basis for bid rejection.
Based on the foregoing, the City denies the bid protest.
Fury Site Works, Inc.
Page 2 of 2
Notice of Contract Execution - RCW 39.04.105
The City intends to award contract no. CAG-26-096 PRV Station 1 Rehabilitation Project, to
CR Construction LLC at the City Council meeting on Monday, June 22, 2026. Execution of the
contract will occur following award and completion of the contract assembly and signature
process.
Please contact me at 425-430-7210 or via email at Agafour@rentonwa.gov, if you have any
questions regarding this determination.
Sincerely,
Abdoul Gafour
Water Utility Engineering Manager
Public Works Department
cc: Ron Straka
Jeremy Valdez
Attachment: Bid protest e-mail from Raudenbush Earthworks, LLC
1
Abdoul Gafour
From:Steve Raudenbush <Steve@raudenbushearthworks.com>
Sent:Tuesday, May 26, 2026 10:36 AM
To:Abdoul Gafour
Cc:Jeremy Valdez; Jason Seth; Cynthia Moya; Ronald Straka
Subject:Re: PRV Station 1 Rehabilitation Project - CAG-26-096 - Bid Protest
Thank you for the update.
Steve Raudenbush
Cell Phone: (360)-999-3890
Contractors License: #RAUDEEL789J8
From: Abdoul Gafour <Agafour@Rentonwa.gov>
Sent: Friday, May 22, 2026 3:11 PM
To: Steve Raudenbush <Steve@raudenbushearthworks.com>
Cc: Jeremy Valdez <JValdez@Rentonwa.gov>; Jason Seth <JSeth@Rentonwa.gov>; Cynthia Moya
<CMoya@Rentonwa.gov>; Ronald Straka <rstraka@Rentonwa.gov>
Subject: RE: PRV Station 1 Rehabilitation Project - CAG-26-096 - Bid Protest
Hello Steve,
The City of Renton Water Utility has received your email bid protest regarding the PRV 1 Station Rehabilitation
project CAG-26-0963 on Friday 5/22/26 at 3:02 p.m.
We will review your protest and provide a written response within the next 10 days.
Sincerely,
Abdoul Gafour
Water Utility Engineering Manager
City of Renton Public Works
1055 S Grady Way
Renton, WA 98057
425-430-7210
206-406-0027 cell
agafour@rentonwa.gov
CAUTION: This email originated from outside the City of Renton. Do not click links, reply or open attachments unless
you know the content is safe.
2
From: Steve Raudenbush <Steve@raudenbushearthworks.com>
Sent: Friday, May 22, 2026 3:00 PM
To: Jeremy Valdez <JValdez@Rentonwa.gov>
Cc: Abdoul Gafour <Agafour@Rentonwa.gov>
Subject: Re: PRV Station 1 Rehabilitation Project
Jeremy,
During the review of CR constructions bid submittal package I noticed their bid is missing the rebar
installer on page 2 of the sub-contractor document.
Raudenbush Earthworks is protesting CR Constructions bid due to the sub-contractor document being
incomplete. The bid submittal package provided by the city of Renton states that their bid is considered
non-responsive/void.
Thank you,
Steve Raudenbush
Cell : 360-999-3890
Contractors License # RAUDEEL789J8
From: Jeremy Valdez <JValdez@Rentonwa.gov>
Sent: Thursday, 21 May 2026 09:23:02
To: Steve Raudenbush <Steve@raudenbushearthworks.com>
Cc: Abdoul Gafour <Agafour@Rentonwa.gov>
Subject: RE: PRV Station 1 Rehabilitation Project
Good morning Steve,
Please see attached for the copy of the CR Construction Bid Package for PRV Station #1 Rehabilitation Project
CAG-26-096.
Thanks,
Jeremy Valdez | Civil Engineer
City of Renton | PW | Water Utility Engineering Division
1055 S Grady Way | 5th Floor | Renton, WA 98057
O: (425) 430-7295 C: (206) 200-5172 | jvaldez@rentonwa.gov
NOTICE OF PUBLIC DISCLOSURE: This message complies with Washington State’s Public Records Act – RCW 42.56
From: Steve Raudenbush <Steve@raudenbushearthworks.com>
Sent: Wednesday, May 20, 2026 3:39 PM
CAUTION: This email originated from outside the City of Renton. Do not click links, reply or open attachments unless
you know the content is safe.
3
To: Jeremy Valdez <JValdez@Rentonwa.gov>
Subject: PRV Station 1 Rehabilitation Project
Jeremy,
Please send me a copy of CR Constructions Bid Package for the Renton PRV Station 1 Project CAG-26-096, I would
like to review it for completeness.
Thank you,
Steve Raudenbush
Cell Phone: (360)-999-3890
Contractors License: #RAUDEEL789J8
CAUTION: This email originated from outside the City of Renton. Do not click links, reply or open attachments unless
you know the content is safe.