HomeMy WebLinkAboutM_precon notes_20260618_v1 (2)DEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
Last Modified 1/30/2023 1 [Subject] 6/18/2026
CITY OF RENTON
PRECONSTRUCTION MEETING
C22006395 Kennydale Gateway
6/18/2026
PROJECT PERSONNEL:
Yong Qi, City Project Manager, 425-430-7349, YQi@Rentonwa.gov
Joel McCann, Public Works Inspector, 425-430-7435, JMccann@Rentonwa.gov
Clark Close, Planning Reviewer, 425-430-7289, CClose@Rentonwa.gov
Corey Thomas, Fire Inspector, 425-430-7024, CThomas@RentonRFA.org
Eric Cutshall, Transportation Maintenance Supervisor, 425-430-7223,
ECutshall@Rentonwa.gov
GENERAL:
1. Call the construction inspection line at 425-430-7203 24 hours before you start
work. Notify Fire Dispatch, Renton Police Department, and King County Metro
of project construction schedule.
Fire Dispatch can be reached at 253-852-2121. The Renton Police Department can be
reached at 425-430-7500. King County Metro can be reached at 206-477-1140.
2. CONSTRUCTION HOURS OUTSIDE OF RIGHT OF WAY: 7:00 AM to 8:00 PM
Monday thru Friday and 9:00 AM to 8:00 PM on Saturday. Saturday work is by
permission only. No work is allowed on Sunday.
3. CONSTRUCTION HOURS INSIDE OF RIGHT OF WAY: Follow approved traffic
control plan. Saturday work is by permission only. No work is allowed on
Sunday.
4. RIGHT OF WAY HAUL HOURS: 8:30 AM to 3:30 PM Monday thru Friday. Hauling
on Saturday is by permission only. No hauling is allowed on Sunday.
5. INSPECTION HOURS: 7:00 AM to 3:30 PM Monday thru Friday. Contractor must
call for City inspection before 3:00 PM on the previous day. Inspections outside
of inspection hours must be requested.
6. To request work, hauling, and inspections outside of the hours listed above, contact
the City no later than three working days prior to the requested activity.
Last Modified 9/8/2025 2 C22006395 Kennydale Gateway, 6/18/2026
7. After hours inspection fees (applies to inspections performed on Saturdays,
Sundays, observed City of Renton holidays, and non‐holiday Monday‐Fridays
outside the hours of 7:00am to 3:30pm). Current fees can be found on the City of
Renton Fee Schedule. Any outstanding fees are to be paid by the specialized billing
contact provided by the applicant.
8. Public Works Reimbursement (any work performed by City forces or under City
contract on behalf of a permit applicant to repair damage to the City infrastructure
caused by the permit applicant or contractor under its control, or any and all
roadway or right‐of‐way cleanup efforts performed by City forces or under City
contract that resulted from the work performed by the permit applicant or
contractors under its control. Current fees can be found on the City of Renton Fee
Schedule. Any outstanding fees are to be paid by the specialized billing contact
provided by the applicant.
9. Contractors shall use only sets of drawings approved by the City for constructing
utility and transportation improvements. Approved drawings are signed by the
Project Manager and / or other city staff on each plan sheet. A set of approved
drawings shall be kept on-site at all times.
10. RECORD DRAWINGS: It is the responsibility of the contractor and engineer to keep
record drawings. All changes to the approved construction plans shall be shown on
the record drawings. Record drawings are required to be submitted to the City.
Record drawings submitted to the City shall be prepared, stamped, and signed by a
Professional Land Surveyor or Professional Engineer licensed in the State of
Washington.
All plan sheets with utility and transportation improvements including those constructed
per design, must be verified, stamped, and signed “As-Built”. Record drawings shall first be
submitted to the City for review by the Public Works Inspector. Once the record drawings
are approved by the Public Works Inspector, final electronic plans (PDF) shall be submitted
for City permanent records. Recording of the final plat or short plat or issuance of final
occupancy will not be completed until final record drawings are received.
11. If the materials shown on the approved plans differ from those shown in the City
standard details, material submittals shall be made to the Project Manager for
approval prior to installation.
12. MINOR FIELD CHANGES: Identify the proposed change(s) to the Public Works
Inspector. If the Public Works Inspector determines that the change(s) is minor, the
Public Works Inspector can approve the change(s) in the field. A summary of any
minor changes approved by the Public Works Inspector shall be emailed to the
Project Manager. If the Public Works Inspector determines that the change(s) needs
Last Modified 9/8/2025 3 C22006395 Kennydale Gateway, 6/18/2026
further review and approval from other City staff, the contractor shall follow the
directions in the Major Field Changes section below.
13. MAJOR FIELD CHANGES: Submit a digital plan clearly showing the proposed
change(s) and justification via email to the Project Manager and Public Works
Inspector. City staff will respond to the requested change within two business days.
The Public Works Inspector cannot give approval for major construction changes in
the field.
14. Trenches with City utilities shall be left open for inspection prior to backfill.
15. A spill kit shall be located on site and easily identifiable with signage.
16. PROJECT CLOSEOUT: The Civil Construction Permit Final Inspection and
Construction Closeout Process Requirements document gives information of the
requirements for construction closeout. The current version of the Final Inspection
and Construction Closeout Process and Requirements document is included in this
preconstruction meeting packet. All requirements of the codes and regulations for
the construction permit closeout should be followed by the contractor and
developer.
17. FINAL INSPECTION WALKTHROUGH: Contractor shall accompany the Site
Inspector during the final walkthrough and provide any required traffic control.
TRANSPORTATION:
1. TRAFFIC CONTROL PLAN: An approved traffic control plan in accordance with
the Manual on Uniform Traffic Control Devices (MUTCD) is required prior to any
construction activity in the right of way.
A traffic control plan should be submitted to the Project Manager for review at least five
working days prior to proposed work in the right of way. The traffic control plan shall be
submitted with the traffic control plan cover sheet found here:
https://rentonwa.gov/city_hall/public_works/transportation_systems/operations/tra
ffic/traffic_control_plans
The traffic control plan shall address both roadway / vehicular and sidewalk / pedestrian
traffic impacts.
All traffic control plans will be required to submit no later than five (5) working days
before the date of work.
2. STREET RESTORATION: Street restoration is required to conform to the City of Renton
Trench Restoration and Street Overlay Requirements. A copy has been
Last Modified 9/8/2025 4 C22006395 Kennydale Gateway, 6/18/2026
provided. All street repairs shall be complete and in place within 14 days, or as
directed by the Public Works Inspector.
3. PAVING: Paving shall be done in accordance with WSDOT Standard Specifications
Division 5. Weather limitations from this specification shall be followed. Reference
Section 5-04.3(16) for HMA weather limitations. Pavement subgrade and rock
surfaces shall be compacted to at least 95% of the maximum density.
4. TRENCHES: Trenches shall not be left overnight without approval of the Public
Works Inspector. Trenches shall be backfilled, plated, or fenced. The proposed
method of cover or protection shall be submitted to the Public Works Inspector for
approval. Shoring plates and cold mix shall be available on site at all times. The
Public Works Inspector will require cold mix for trench restoration in sidewalks or
driveways.
5. City streets shall be kept clean at all times. Streets shall be swept in a timely
manner. Truck washing and / or other measures as approved by the Public Works
Inspector may be required for the duration of the project.
6. Construction traffic shall observe all traffic laws. All hauling shall consist of legal
loads.
7. The right of way shall remain unobstructed when possible. No stockpiles are
allowed in the right of way. All truck maneuvering and materials storage shall occur
on-site.
8. NOISE VARIANCE: Projects that include construction between 10 pm and 7 am will
require a noise variance if the project meets the criteria as specified in RMC 8-7-2.
• For work not exceeding 2 days, an Administrative noise variance is required. The
process will take approximately five to six weeks for the review, public notification,
decision, and end of appeal period prior to start of work.
• For work exceeding 2 days, a Public Hearing will be required. The process will take
approximately twelve weeks for the review, public notification, Public Hearing, Hearing
Examiner decision, and end of appeal period prior to start of work.
Please consider the noise variance time requirements when you plan and schedule the
construction work.
Last Modified 9/8/2025 5 C22006395 Kennydale Gateway, 6/18/2026
CITY UTILITIES
WATER:
1. For water main shut downs or to open or close a valve, call the City Public Works
Maintenance Services Division at 425-430-7400. For emergency water shutdowns,
call 911.
2. The Engineer of Record will be required to provide a signed Washington State
Department of Health Construction Completion Report Form along with the Record
Drawings for all water mains to be construction as part of the project. The form can
be obtained at the following address:
https://edocs.rentonwa.gov/Documents/DocView.aspx?id=8461966&dbid=0&repo
=CityofRenton
3. Pipe materials, valves, and fittings shall be as indicated on the approved plans and
standard notes.
4. When installing water main in new roadways, the proposed road prism shall be
constructed to subgrade prior to any utility installation.
5. The City of Renton shall install all connections to existing mains. The contractor
shall construct the new water main to a point approximately ten feet short of the
existing main. All necessary excavation, shoring, and materials are supplied by the
contractor and shall be on-site prior to scheduling. Allow at least seven working
days advance notice, and schedule the connection through the Public Works
Inspector.
6. Temporary and permanent thrust blocks shall be formed. Concrete for thrust blocks
shall be delivered to the job. No on-site mixes are allowed. Standard mix design
shall be 3,000 psi. All blocking shall be inspected before backfilling.
7. Procedure for cleaning and construction testing of new water lines:
1. Pipe cleaning shall be by poly pigging through vertical crosses installed at the
ends of the water lines to serve as pig launches and sediment traps.
2. Water main shall be polywrapped.
3. All water lines shall be pressure tested to minimum of 200 psi or 150 psi over
operating pressure (static) for 2 hours. Services may be tested separately by
visual inspection of the corp stop under static pressure.
Last Modified 9/8/2025 6 C22006395 Kennydale Gateway, 6/18/2026
4. Chlorinate for 24 hours, using liquid chlorine and chlorine pump assembly.
The Public Works shall schedule chlorination. Seven working days advance
notice is required.
5. Water used for flushing water lines shall be drained into the sanitary sewer
only.
6. The construction inspector will collect purity tests at blow-offs. Water purity
tests are taken to the testing laboratory by the Public Works Inspector. Test
results are available in 5-7 days.
8. 5/8” minus crushed rock backfill to grade is required in City right-of-way. Pit run
type material may be considered for use in backfill if approved by the Public Works
Inspector. Backfill shall be compacted to at least 95% of maximum density.
Compaction testing is required.
9. Where conflict exists, the water main shall go under other utilities; however, it is
preferred that no water mains shall have more than six feet of cover. Water mains
with a diameter of 10-inches and under shall have a minimum of three feet of cover.
Water mains 12-inches and larger shall have a minimum of four feet of cover.
10. All bends on water mains shall be surveyed prior to backfill with horizontal and
vertical control for all bends established.
11. Final acceptance shall be after final walk through inspection, adjustment of all
structures, and approval of as-builts, cost data inventory, easements and bill of sale
if applicable.
SANITARY SEWER:
1. Pipe and materials shall be as indicated on the approved plans and standard notes.
Any sewer pipe with less than four feet or greater than fifteen feet of cover shall be
Ductile Iron, Class 50, or C900 pipe.
2. When installing sewer main in new roadways, the proposed road prism shall be
constructed to subgrade prior to any utility installation.
3. All manholes shall have all interior surfaces, including channeling, coated/sealed
with a high solids urethane coating: Wasser MC-Conseal or approved equal.
Coating shall be white.
4. Pipe bedding shall be pea gravel or 5/8" minus crushed rock as approved by the
Public Works Inspector. Bedding shall extend 1-foot above the pipe and 6-inches
below the pipe. Backfill shall be compacted to at least 95% of maximum density.
Compaction testing is required.
Last Modified 9/8/2025 7 C22006395 Kennydale Gateway, 6/18/2026
5. A Number 6 wire shall be wrapped around the stub and extended to the top with a 2”
x 4” marker stenciled in white.
6. Contractor shall as-built the invert elevation of all side sewer stubs. If cleanouts are
installed, the top and flowline shall be as-built and noted on the record drawings.
7. No shims or wedges shall be used on any utility structure.
8. Contractor will be responsible for TVing of the sewer main. TVing shall occur after
channeling and coating is complete. Pressure tests on the main and side sewers
shall be per City specifications.
9. Sewer mains may be surveyed after backfill using the manholes as access points.
STORM/EROSION CONTROL:
1. Approved temporary erosion and sediment control (TESC) and stormwater pollution
prevention and spill control (SWPPS) measures are to be installed as first order of
business and maintained at all times per the approved drawings or at the direction
of the Construction Stormwater Supervisor, or the project Certified Erosion and
Sediment Control Lead (CESCL), and the Public Works Inspector.
2. The approved Construction Storm Pollution Prevention Plan (CSWPPP) shall be
located on site at all times.
3. The Construction Stormwater Supervisor or CESCL shall review the site’s TESC and
SWPPS measures at least weekly and within 24 hours of significant storms.
Weekly reports outlining the status and condition of the erosion control plan, with any
recommendations of change or revision to maintenance schedules or installation, are
required to be submitted by the project Engineer of record or CECSL to the Project Manager
and Public Works Inspector. Weekly reports shall include the project’s NPDES permit
number (if applicable).
4. If dewatering for the site is required, all site construction stormwater discharge shall
be less than 25 NTUs if discharged into Waters of the State. Any pipe conveyance
system that eventually discharges to a body of water is construed as discharging
into Water of the State.
5. If dewatering is proposed to the City sewer then a permit from the City and King
County will be required. If dewatering is proposed to a sewer system belonging to
another sewer district, contact that district for approval. Contractor is strongly
encouraged to obtain all required sewer discharge permits in advance of any
anticipated need to discharge to a sewer.
Last Modified 9/8/2025 8 C22006395 Kennydale Gateway, 6/18/2026
6. Wet Season requirements found in Appendix D of the 2022 City of Renton Surface
Water Design Manual (RSWDM) shall be adhered to for construction occurring
between October 1st and April 30th. For construction occurring during the wet
season, a Wet Weather fee, as defined in the City Fee Schedule, is applicable.
7. Dust control shall be implemented as directed by the Public Works Inspector.
8. Proper removal of all TESC measures is required prior to permit closeout unless
otherwise approved by the Public Works Inspector or Project Manager.
9. Pipe and materials shall be as indicated on the approved plans and standard notes.
10. When installing storm drain in new roadways, the proposed road prism shall be
constructed to subgrade prior to any utility installation.
11. Contractor must notify the Project Manager and Public Works Inspector of any vertical
conflict prior to proceeding with construction. Any proposed changes shall be
submitted to the City as described in the Major Field Changes note.
12. Pipe bedding material shall be per WSDOT Standard Specifications 9-03.12(3) or as
approved by the Public Works Inspector. Backfill shall be compacted to at least
95% of maximum density. Compaction testing is required.
13. Smooth interior wall corrugated polyethylene stormwater pipe, where permitted, shall
use watertight couplings. It shall also be bedded in pea gravel as described in the
City specifications.
14. Catch basin penetrations shall be grouted smoothly.
15. No shims or wedges shall be used on any utility structure.
16. Contractor will be responsible for TVing of the storm drain. Pressure tests on the storm
drain shall be per City specifications.
17. The storm system shall be flushed and cleaned prior to final approval. This includes the
downstream system for a minimum of two structures or 500 feet, whichever is
greater.
FRANCHISE UTILITIES:
1. Permits for franchise utility work shall be obtained prior to franchise utility
installation in existing or future right of way. Each franchise utility requires a
separate permit. Franchise permits can be applied for at the permit counter on the
6th floor of City Hall. Plans should be submitted at least two weeks prior to
anticipated installation. Provide a copy of the approved composite utility drawing
with each franchise permit application.
Last Modified 9/8/2025 9 C22006395 Kennydale Gateway, 6/18/2026
2. All franchise utilities within the City of Renton right of way must be inspected by the
City of Renton Franchise Inspector. Call the inspection line at 425-430-7203 24
hours prior to installation.
3. Permits for each franchise utility in a joint trench shall be obtained prior to the
excavation of the joint trench.
4. All franchise utilities shall be separated a minimum of 5’ horizontally and 12”
vertically from all City utilities.
5. The composite utility drawing shall be as-built to show all franchise utility locations
and crossings. The as-built composite drawing shall be included with the record
drawing submittal after construction is complete.
FIRE PREVENTION:
1. Access to the site shall be maintained at all times. Access must be able to support
emergency equipment in all types of weather.
2. Hydrants are required to be in place prior to any combustible installation above the
foundations.
3. All new hydrants shall be Cory type hydrants and painted Safety Yellow. Iowa and
Renselear are manufacturers of Cory type hydrants. Alternative hydrants, such as
Clow Medallion or Mueller Super Centurion have been approved for use. Any
hydrant installed shall be equipped with 5-inch diameter Storz "quick connect" style
fitting. All concrete blocking for the hydrant assembly shall be inspected by the
Public Works Inspector prior to backfill.
4. New hydrants shall be covered with burlap or heavy plastic and wrapped until
operational.
5. Hydrant water main leads that exceed 50 feet in length shall consist of a minimum
of 8-inch diameter pipe.
6. A separate permit from the Renton Fire Authority is required for the following items.
These permits can be applied for at the 6th Floor of City Hall.
1. Underground water mains serving fire sprinkler systems. All fire sprinkler
systems shall be installed by a Fire Sprinkler Contractor licensed in the State
of Washington.
2. Temporary storage, handling, or use of hazardous materials, as required by
International Fire Code and City of Renton Ordinance.
3. Temporary storage of fuel on site.
Last Modified 9/8/2025 10 C22006395 Kennydale Gateway, 6/18/2026
4. Abandonment, removal, or installation of fuel storage tanks.
5. Hot works on site (welding, soldering, cutting, brazing, etc.).
PLANNING:
1. TREE PROTECTION:
1. Prior to development activities, the applicant shall erect and maintain six
foot (6’) high chain link temporary construction fencing around the drip lines
of all retained trees or at a distance surrounding the tree equal to one and
one-quarter feet (1.25’) for every one inch (1”) of trunk caliper, whichever is
greater, or along the perimeter of a tree protection tract. Placards shall be
placed on fencing every fifty feet (50') indicating the words, “NO
TRESPASSING – Protected Trees,” or on each side of the fencing if less than
fifty feet (50'). Site access to individually protected trees or groups of trees
shall be fenced and signed. Individual trees shall be fenced on four (4) sides.
In addition, the applicant shall provide supervision whenever equipment or
trucks are moving near trees.
2. The applicant may not fill, excavate, stack or store any equipment, dispose of
any materials, supplies, or fluids, operate any equipment, install impervious
surfaces, or compact the earth in any way within the area defined by the drip
line of any tree to be retained.
3. All areas within the required fencing shall be covered completely and evenly
with a minimum of three inches (3”) of bark mulch prior to installation of the
protective fencing. Exceptions may be approved if the mulch will adversely
affect protected ground cover plants.
4. The applicant shall retain a certified arborist or licensed landscape architect
to ensure trees are protected from development activities and / or to prune
branches and roots, fertilize, and water as appropriate for any trees and
ground cover that are to be retained.
5. Tree protection (fencing, etc.) must be retained throughout the project (site
and building development).
2. If applicable, no work shall occur within critical areas and /or buffers unless
modified according to RMC 4-3-050 (buffer reduction, averaging, critical area
variance and / or exemption). Mitigation plantings shall occur in accordance with
the approved Final Mitigation plan.
3. Contact the Planning Reviewer directly for landscape inspection.
Last Modified 9/8/2025 11 C22006395 Kennydale Gateway, 6/18/2026
4. The contractor / applicant shall comply with all conditions of land use approval and
SEPA Environmental Review. Conditions are listed on the first or second sheet of
the approved plan.
ELECTRICAL:
1. After calling in the inspection request through the Inspection Request Line, contact
Greg Ryan (425-430-7423) at 7:30 a.m. the morning of the inspection to provide a
contact name and phone number for arranging the electrical inspection with your
representative.
2. Have in your possession the electrical permit and streetlight luminaire checklist. Insert
both in a clear plastic document protector and attach it to a conduit stubbed up. If
the signal control box is installed, for underground conduit inspection approval,
place the documents in the signal control box.
3. Service inspection for signal or lighting control pedestals requires access for electrical
inspection. If approved, a service approval sticker will be attached by the meter
opening for the serving utility. The serving utility will not and shall not connect
power unless the approval sticker is in place.
4. All grounding is to meet Standard Plan -119, dated January 26, 2015.
5. Provide Megger Test Report of all wiring to identify any undergrounded conductor that is
grounded or open not completing circuit.
6. When calling in a request for final electrical inspection, provide access to all handholes
and access openings to light poles. Some bolts require special sockets or
wrenches, which are not available to or provided by the Electrical Inspector.
7. Electrical cabinets (Millbank service cabinets) do not meet the minimum City code
standards, therefore shall not be considered allowable.
8. Lighting Contractor should coordinate with Construction inspector (425-430-7203), and
Transportation Maintenance / street light inspection (425-430-7423) for the required
inspections. Please see the Street Lighting Inspection checklist that is provided
with this preconstruction meeting packet for information of the necessary
inspections and the stages of construction when the respective inspection is
required to be called in by the contractor.
CONDITIONS TO ISSUANCE OF A CONSTRUCTION PERMIT:
1. Pay all system development, special assessment, and other outstanding permit
fees.