Loading...
HomeMy WebLinkAboutP_CSWPPP_260611_v1 Construction Stormwater Pollution Prevention Plan SWARR Security Maintenance Project Renton, King County, Washington for Puget Sound Energy April 22, 2026 17425 NE Union Hill Road, Suite 250 Redmond, Washington 98052 425.861.6000 Construction Stormwater Pollution Prevention and Spill Control Plan (CSWPPS) For SWARR Security Maintenance Project Renton, King County, Washington Prepared for: Puget Sound Energy Permittee/Owner Developer Operator/Contractor Kathryn Hodges and Elaine Babby Puget Sound Energy Puget Sound Energy TBD Certified Erosion and Sediment Control Lead (CESCL) Name Organization Contact Phone Number Carla Woodworth GeoEngineers, Inc. 425.466.6772 Other CESCLs to be identified as needed CSWPPS Original Preparation Date April 22, 2026 Approximate Project Construction Dates (Target Dates for Planning Purposes, Subject to Revision) Construction Phase/Activity Target Dates Install TESC/BMPs June 2026 Tree and Shrub Cutting June 2026 Begin Maintenance and Repairs June 2026 Complete Maintenance and Repairs September 2026 Site Restoration and Remove TESC/BMPs September 2026 Construction Stormwater Pollution Prevention and Spill Control Plan SWARR Security Maintenance Project Renton, King County, Washington File No. 9186-184-00 Task 2032 April 22, 2026 Prepared for: Puget Sound Energy PO Box 97034 M/S EST-04W Bellevue, Washington 98009-9734 Attention: Kathryn Hodges and Elaine Babby Prepared by: GeoEngineers, Inc. 17425 NE Union Hill Road, Suite 250 Redmond, Washington 98052 425.861.6000 Carla Woodworth, LG, CESCL No. 81954 Brian C. Ranney, LEG, CESCL No. 82900 Project Geologist Principal Engineering Geologist CRW:BCR:kjb:tlm Disclaimer: Any electronic form, facsimile, or hard copy of the original document (email, text, table, and/or figure), if provided, and any attachments are only a copy of the original document. The original document is stored by GeoEngineers, Inc. and will serve as the official document of record. Puget Sound Energy | April 22, 2026 i File No. 9186-184-00 Task 2032 Table of Contents 1.0 Project Information ................................................................................................................... 1 2.0 Existing Conditions .................................................................................................................... 2 2.1 Site Topography and Drainage ................................................................................................................... 2 2.2 Drainage conditions .................................................................................................................................... 2 2.3 Existing Vegetation ..................................................................................................................................... 3 2.4 Soil Conditions and Erodibility .................................................................................................................... 3 2.5 Critical Areas ............................................................................................................................................... 3 2.6 Known Impairments for 303(d) listed or Total Maximum Daily Load (TMDL) for the Receiving Waterbodies ......................................................................................................................................................... 4 3.0 Planned Construction Activities ................................................................................................. 4 4.0 Construction Stormwater BMPs ................................................................................................. 5 4.1 BMP Elements ............................................................................................................................................. 5 4.1.1 Element No. 1: Clearing Limits ....................................................................................................... 5 4.1.2 Element 2: Cover Measures ........................................................................................................... 6 4.1.3 Element No. 3: Perimeter Protection ............................................................................................. 6 4.1.4 Element No. 4: Traffic Area Stabilization ....................................................................................... 7 4.1.5 Element No. 5: Sediment Retention ............................................................................................... 7 4.1.6 Element No. 6: Surface Water Collection ....................................................................................... 8 4.1.7 Element No. 7: Dewatering Control ................................................................................................ 8 4.1.8 Element No. 8: Dust Control ........................................................................................................... 9 4.1.9 Element No. 9. Flow Control ........................................................................................................... 9 4.1.10 Element 10: Control Pollutants ................................................................................................... 10 4.1.11 Element No. 11: Protect Existing and Proposed Flow Control BMPs ........................................ 11 4.1.12 Element No. 12: Maintain BMPs ................................................................................................. 12 4.1.13 Element No. 13: Manage the Project .......................................................................................... 12 5.0 Construction Schedule and BMP Implementation .................................................................... 13 6.0 Pollution Prevention Team ....................................................................................................... 13 6.1 Roles and Responsibilities ...................................................................................................................... 13 6.2 Team Members ........................................................................................................................................ 14 6.3 Spill and Release Response .................................................................................................................... 14 7.0 Site Observation ...................................................................................................................... 14 7.1 Stormwater Turbidity Observation .......................................................................................................... 15 7.2 pH .............................................................................................................................................................. 15 8.0 Recordkeeping ........................................................................................................................ 15 8.1 Access to Plans and Records .................................................................................................................. 15 8.2 Updating the Construction Stormwater Pollution Prevention Plan ....................................................... 16 9.0 References .............................................................................................................................. 16 Puget Sound Energy | April 22, 2026 ii File No. 9186-184-00 Task 2032 Appendices Appendix A. Temporary Erosion and Sediment Control Plan (Completed by others) Appendix B. Construction Stormwater BMPs Puget Sound Energy | April 22, 2026 Page 1 File No. 9186-184-00 Task 2032 1.0 Project Information Puget Sound Energy (PSE) plans to improve reliability and safety at the SWARR Station by maintaining and replacing existing fencing. The maintenance and repairs will be completed on PSE-owned Parcel No. 2023059071 located at 2100 Benson Drive South in Renton, King County, Washington. The property is situated within Section 20 of Township 23 North and Range 05 East of the Willamette Meridian (WM). The project will be completed within the southern developed 5 acres on an approximately 16.71-acre parcel. The station and project vicinity are shown in the Cover Sheet Drawing G001 of the Temporary Erosion and Sediment Control (TESC) plans in Appendix A, Temporary Erosion and Sediment Control Plan. PSE is proposing to replace the existing 6-foot-tall chain link fence around the SWARR Station with a new 8- to 12-foot-tall metal mesh fence including intrusion detection and security cameras to meet new Homeland Security requirements and PSE standards. PSE also plans to replace the vehicle and pedestrian gates at the main entrance to Benson Drive South in the southwest corner of the site and at the back entrance to South Puget Drive in the northeast corner of the site. The replacement fence alignment will generally follow existing fence alignment, with some segments shifting further into developed areas. The fence will not move outward away from the developed station footprint. New security cameras to be installed will require the installation of an electrical system and conduit. Conduits will be attached to the fence, to minimize trenching, except at gate crossings and between power source at control building and fence where conduits will be routed below ground. Minor grading or excavation, including augering or hydrovactoring, for fence and camera post installation, is proposed as part of the project. Vegetation management will be required to accomplish the project, including cutting and removing 42 dead or dying trees and 17 healthy trees and trimming approximately 430 square feet of evergreen and deciduous shrubs along the north, east and west sides of the station fence alignment to allow for installation of the new fence. Land disturbing activities will be required to complete site security maintenance activities. Land disturbance will include 3,200 square feet of temporary impact including brush and tree cutting for the fence alignment, excavation for the fence posts and excavations for the installation of the new underground conduit for some of the electrical system adjustments. Site restoration will be completed as soon as practical after construction activities are completed. Site restoration will include backfilling excavations, regrading workspaces to preconstruction conditions, if needed, and placing crushed rock, gravel, or asphalt or grass seed and mulch in disturbed areas to match preconstruction site conditions. Areas where trees and shrubs have been cut will be restored with mulch. The root systems of the cut trees and shrubs will be left intact. Planned construction activities are discussed in more detail in Section 3.0 Planned Construction Activities. The proposed area of excavation for the fence posts and new conduit is approximately 1,520 square feet (less than 0.035 acres). The proposed quantity of temporary excavation cut, and fill is approximately 127 cubic yards (excavations will be approximately 18 to 45 inches deep); however, there will be no net change in surface elevation as the materials removed from the excavations will be hauled off site for disposal. No buildings and no new impervious surface are proposed for the project. Puget Sound Energy | April 22, 2026 Page 2 File No. 9186-184-00 Task 2032 This Construction Stormwater Pollution Prevention Plan (CSWPPP) was prepared to meet the City of Renton (COR) Targeted Drainage Review (Category 2) Core Requirement No. 5, Construction Stormwater Prevention so that the project complies with the City of Renton Surface Water Design Manual (RSWDM). 2.0 Existing Conditions 2.1 SITE TOPOGRAPHY AND DRAINAGE The project site is situated in the southern portion of the parcel which is located in a northwest-southeast trending drainage of Rolling Hills Creek. The site is situated on a relatively flat to very gently sloping (slope gradients of 0 to 15 percent) ground surface. The developed portion of the site is bounded by a gently sloping (slope gradients between 5 and 15 percent) forested area to the north, by steep slopes (slope gradients ranging between 40 to 65 percent) up to South Puget Drive and businesses to the east, by gentle slopes (slope gradients between 5 and 20 percent) down to single-family residential developments to the south, and to the west by steep slopes (slope gradients ranging between 40 to 70 percent) up to Benson Drive South. When the station was built in the 1960s, the site was graded to provide a relatively flat to gently sloping ground surface between approximately Elevation 160 above mean sea level (MSL) to approximately 150 feet MSL from south to north. The project area is approximately 10 to 30 feet lower in elevation than Benson Drive South on the west side of the site and between approximately 50 and 90 feet lower in elevation than South Puget Drive on the east. 2.2 DRAINAGE CONDITIONS Based on our review of information available from COR Maps (COR 2024), the site is within the COR Flow Control Duration Standard (matching forested conditions) and within the Black River drainage basin. The project does not contain or is not adjacent to an aquifer protection area. Land use in the area includes residential development zone R-8. According to the COR Utility Geographic Information System (GIS) data (COR 2024a), there are multiple stormwater discharge points that direct water towards the SWARR Station parcel. Surface water along Benson Drive South collects within curbside gutters and enters three catch basins located on the east side of Benson Drive South adjacent to the west side of the project parcel. Stormwater along this portion of Benson Drive South as well as stormwater from the north side of Benson Drive South, South 21st Street and South 19th Street enters the stormwater drain system and discharges onto PSE’s property at a point outside of the northwest corner of the proposed work area. Evidence of water sheet flow (fine sediments, organic matter accumulation) has been observed from the discharge point that flows northeast through the northwest corner of the existing fence line towards Rolling Hills Creek. This sheet flow either infiltrates or eventually flows into Rolling Hills Creek. On the east side of the project site, surface water along South Puget Drive adjacent to the site is collected within curbside gutters and enters two catch basins located on the east and west sides of South Puget Drive. Water in the east catch basins flows directly to the catch basins on the west side of South Puget Drive which discharges stormwater onto the slopes on the east side of the project area. Plastic piping has been installed on the site slopes to capture the discharged water and transport it to the base of the slopes. Puget Sound Energy | April 22, 2026 Page 3 File No. 9186-184-00 Task 2032 Based on our surface reconnaissance, the water then flows into the half-rounds that have been installed on the east side of the site access road to convey the water along the toe of the slopes to the northeast corner of the site where the water flows into an existing catch basin and then discharges to Rolling Hills Creek on the north side of the developed site. Surface water near the intersection of South Puget Drive and Benson Road South enters a series of catch basins located near the intersection. This water then flows through the stormwater drain system and discharges to the slopes southeast of the project area into a tributary that directs flow westward towards Rolling Hills Creek. However, due to natural topography, water does not directly enter the stream and evidence of standing water was observed just east of the south portion of the site where Rolling Hills Creek enters the culvert. According to COR, Rolling Hills Creek is mapped as an open channel on the north and south sides of the project area. The creek flows into the culvert inlet at the south end of the project site and discharges to an open stream channel at the north end of the project site. The creek is located outside of the proposed work areas and will not be disturbed by construction. All land disturbance will occur within or immediately adjacent to the facilities, which are located in upland areas. 2.3 EXISTING VEGETATION The site vicinity is a mixed-use area including a combination of residential areas with single-family homes and apartment complexes, tennis courts and the PSE South Seattle Gate Station with associated landscaping; as well as pockets of forested areas vegetated with conifer trees, evergreen shrub, and deciduous trees and shrubs. The existing facilities located near the center of the project site include a one-story metal sided building, natural gas piping and aboveground storage tanks situated on a gravel surface. Existing underground storage tank facilities are located on the north side of the project site where the ground surface is vegetated with grass. The south side of the project site contains the main driveway into the site facilities and parking area, east to west trending underground gas pipelines, forested habitat with little understory vegetation and maintained grass areas. The northern portion of the parcel (outside of the fenced facility) is undeveloped and forested with shrub understory. Slopes around the site are vegetated with evergreen and deciduous trees and shrubs, blackberries, ivy, grass and other understory vegetation. 2.4 SOIL CONDITIONS AND ERODIBILITY Based on soil information available from the National Resources Conservation Service (NRCS), the project site is underlain by two general surficial soil units. The majority of the site is underlain by a soil unit referred to as the Alderwood gravelly sandy loam, 15 to 30 percent slopes and is classified as having a severe erosion hazard. The minor soil unit located along the western boundary of the project is referred to as the Beausite gravelly sandy loam characterized by 6 to 15 percent slopes and is classified as having a moderate erosion hazard. Potential erosion problems at the site during construction include turbid runoff from bare soils at the work sites during precipitation events. 2.5 CRITICAL AREAS The project is located adjacent to mapped potential erosion, regulated slope, landslide and coal mine hazards, Rolling Hills Creek and within the critical area buffers of these features. TESC and best Puget Sound Energy | April 22, 2026 Page 4 File No. 9186-184-00 Task 2032 management practices (BMPs) will be implemented during the project to minimize impacts to critical areas. Impacts to critical areas and buffers will be temporary. Excavations at the site will be shallow to minimize the likelihood of impacts to areas with mapped coal mine hazards. Site conditions will be restored to preconstruction contours, and pre-existing surface treatment, including gravel or paved surface conditions, mulched where trees and ground cover are disturbed or mulched and reseeded where grass is removed. 2.6 KNOWN IMPAIRMENTS FOR 303(D) LISTED OR TOTAL MAXIMUM DAILY LOAD (TMDL) FOR THE RECEIVING WATERBODIES The receiving waterbodies for the project are Rolling Hills Creek, which eventually flows into Springbrook Creek. Rolling Hills Creek (Listing ID 70148) was listed on Washington State Department of Ecology’s (Ecology) 303(d) Water Quality Assessment for Washington as a Category 5 for the parameter of Benthic Macroinvertebrates Bioassessments. The Green River Temperature TMDL is the approved TMDL within the project area (Ecology 2025, Water Quality Atlas - Map ). The creek is culverted through the proposed work areas and will not be disturbed by construction. All land disturbance will occur within or immediately adjacent to the facilities in upland areas. 3.0 Planned Construction Activities Construction will include tree and shrub cutting and trimming along portions of the proposed fence alignment. Construction also will include installation of a new perimeter fence and security cameras and associated electrical conduit and wiring. Restoration of all disturbed areas will occur once all construction activities are completed. Minor concrete work is planned to back fill the fence and camera post hole excavations and replacement of gate controller concrete pads which are about 2 feet by 2 feet in size. The station will be accessed using existing public roads and the main station driveway. The construction activities generally include the following: ■ Install TESC BMP measures prior to tree and brush cutting and land disturbing activities. ■ Mark trees and brush to be cut. ■ Cut and remove trees and brush from the proposed fence alignment. ■ Install mats or mulch to protect work areas within Critical Root Zone. ■ Complete camera conduit installation. Conduits will be attached to the fence, to minimize trenching, except at gate crossings and between power source at control building and fence where a small excavator will be used for trenching to install conduits below ground in locations where not attached to the fence. ■ Complete fence post excavations using augering, vactoring or air spade methodologies. ■ Install fence and camera posts. ■ Backfill post holes using concrete to be flush with the existing ground surface. ■ Install camera wiring and fence. ■ Install culvert pipe where fence crosses ditch. Puget Sound Energy | April 22, 2026 Page 5 File No. 9186-184-00 Task 2032 ■ Stabilize all excavation work areas and other disturbed ground surfaces with crushed rock, gravel or asphalt, or with mulch and appropriate seed mixtures as appropriate. ■ Remove TESC BMPs when disturbed areas are stabilized. We do not anticipate that perched groundwater will be encountered within shallow conduit and post excavations for the project. 4.0 Construction Stormwater BMPs The primary sources of turbid surface water runoff and potential sedimentation problems are likely to be caused by equipment and vehicles tracking sediment from the work areas onto driveways and roadways. In addition, erosion may occur from exposure of soils during conduit and post hole excavation and from backfilling and grading along the work areas. Straw wattles or compost socks, or equivalent, gravel surfacing and temporary ground protection mats will be installed around the work areas to help keep turbid water within the work areas. Although dewatering is not anticipated, if stormwater fills excavations, pumping may be required to periodically dewater the excavations. This water will be pumped using temporary pumps. Turbid water will be discharged through sediment bags onto vegetated ground surfaces more than 100 feet away from any surface water body or regulated slope, landslide or erosion hazard area. Small check dams or straw or compost wattles also may be placed on the vegetated surface downslope of the sediment bags, as needed, to slow discharge water. Below is a list of elements of the CSWPPS that will be employed during construction that are intended to reduce the likelihood of turbid stormwater discharging from the work areas. The proposed location of BMP elements are shown in the TESC plans in Appendix A. 4.1 BMP ELEMENTS According to the 2022 City of Renton Surface Water Design Manual – Appendix D (RSWDM), the project will comply with the Erosion and Sediment Control (ESC) Elements No. 1 through No. 13 below. BMPs will be implemented at the beginning of, inspected during and maintained throughout the duration of the projects. Unless specified otherwise, the BMPs specified with numbers below are from the 2022 RSWDM. BMPs are shown in the drawings in Appendix A. All temporary construction stormwater BMPs will be removed after construction is complete and construction areas have been stabilized. Any accumulated sediment will be removed after construction is complete or periodically during the construction activities if sediment accumulation exceeds established depths or thicknesses. BMPs relevant to the project are included in Appendix B, Construction Stormwater BMPs. 4.1.1 Element No. 1: Clearing Limits To protect the adjacent properties and to reduce the area of soil exposed to construction, work will occur within the limits of the existing security fence, which will provide security during construction of new fence with exception of when entrance gate is replaced, then 24-7 security will be needed. Portions of the existing fence will be removed after construction of new fence. Land disturbing activity will generally occur within about 10 feet on each side of the new fence. Critical tree root zones will be protected with a 3-inch layer of coarse arborist wood chips and/or construction mats. Additional details regarding tree and root protection Puget Sound Energy | April 22, 2026 Page 6 File No. 9186-184-00 Task 2032 is provided in the Swarr Station (Security Perimeter Maintenance) Arborist Report by Davey Resource Group, Inc. dated 07/2024 (Updated 10/2025). Existing vegetation and native topsoil in the work areas will be retained in an undisturbed state to the maximum extent possible. All construction limits and trees to be protected are shown in the TESC sheets in Appendix A. The BMPs relevant to marking the clearing limits and protecting trees that will be applied for this project include: ■ Clearing Limits (D.2.1.1) ■ Plastic or Metal Fence (BMP D.2.1.1.1) ■ Coarse Arborist Wood Chips ■ Construction mats 4.1.2 Element 2: Cover Measures Exposed and unworked soils will be stabilized with the application of effective BMPs to prevent erosion throughout the life of the project. This includes gravel, crushed rock and asphalt placement if the paved portion of the driveway is disturbed; plastic covering; mulching; and temporary and permanent seeding. The BMPs for cover measures that will be used on this project include: ■ Cover Measures (BMP D.2.1.2) ■ Mulching (BMP D.2.1.2.2) ■ Plastic Covering (BMP D.2.1.2.4) ■ Temporary and Permanent Seeding (BMP D.2.1.2.6) ■ Gravel, crushed rock and asphalt pavement restoration The project site is located west of the Cascade Mountain Crest. As such, no soils will remain exposed and unworked for more than 7 days during the dry season (May 1 to September 30) and 2 days during the wet season (October 1 to April 30). Regardless of the time of year, all soils will be stabilized at the end of the shift, before a holiday or weekend, if needed, based on weather forecasts. Excavated soil will be temporarily stockpiled onsite or loaded directly into trucks and transported to a permitted off-site disposal facility. Temporary and permanent gravel, rock and pavement restoration (if necessary), and mulch and seed placement will be used once work has been completed. Dust control measures will be implemented in accordance with the erosion and sediment control BMP presented in Section D.2.1.8 and Appendix B under dry conditions during construction. Cover measures will be implemented at the beginning of, inspected during and maintained throughout the duration of the project. 4.1.3 Element No. 3: Perimeter Protection Straw wattles or compost socks will be the primary BMPs to filter sediment from sheet flow and reduce erosion downstream of all disturbed areas during construction, if needed. A straw wattle will be placed along the perimeter of Rolling Hills Creek to reduce the risk of runoff entering the creek during construction. Check dams may also be used to reduce risk of runoff from the driveways if straw wattles cannot be staked or weighted effectively. Straw/compost wattles may also be installed around excavations or on the downhill Puget Sound Energy | April 22, 2026 Page 7 File No. 9186-184-00 Task 2032 side of excavations to reduce stormwater flow rates if required because of precipitation and runoff. The vegetation around the work areas will be maintained to the extent possible to provide additional filtering beyond work areas. The specific BMPs to control flow rates that will be used on this project include: ■ Perimeter Protection (BMP D.2.1.3) ■ Straw Wattles, staked or weighted (BMP D.2.1.2.5) ■ Silt Fence (BMP D.2.1.3.1) (if needed) ■ Vegetative Strip (BMP D.2.1.3.3) ■ Compost Socks (BMP D.2.1.3.6) 4.1.4 Element No. 4: Traffic Area Stabilization Construction access will be from the paved surfaces of adjacent roadways and the existing main driveway to the station from Benson Drive South. The driveway into the site is paved, while the parking areas adjacent to the driveway are gravel surfaced. Temporary ground protection mats and wood chips mulch will be used to protect existing ground and vegetation from construction equipment in non-paved areas. Construction equipment will enter and leave the site from existing asphalt driveway to minimize track out of soil onto Benson Drive South. The construction crews will keep paved surfaces swept to prevent soil materials from migrating off-site. If necessary, a street sweeper will be used to keep the driveways and roadways clean. The BMPs relevant to establishing construction access that will be applied for this project include: ■ Traffic Area Stabilization (BMP D.2.1.4) ■ Stabilized Construction Entrance (D.2.1.4.1) ■ Construction Road/Parking Area Stabilization (D.2.1.4.2) ■ Protective matts, wood chips or mulch on areas of grass, removed trees or underground piping. 4.1.5 Element No. 5: Sediment Retention All stormwater runoff from disturbed areas will pass through an appropriate sediment removal BMP before leaving the construction site. Silt fence or straw wattles, compost socks, vegetated strips and catch basin inserts will be used to control sediment-laden runoff and stormwater run-on from excavations as needed. If needed, gravel or sandbag berms can be used to filter turbid water before leaving the site. There is one catch basin in the station near the northeast corner of the site. Puget Sound Energy | April 22, 2026 Page 8 File No. 9186-184-00 Task 2032 As a protective measure, the BMPs relevant to controlling sediment that will be applied for this project include: ■ Sediment Retention (BMP D.2.1.5) ■ Storm Drain Inlet Protection, including Gravel and Sandbag Berms (BMP D.2.1.5.3) ■ Straw Wattles, staked (BMP D.2.1.2.5) ■ Silt Fence (BMP D.2.1.3.1) ■ Vegetated Strip (BMP D.2.1.3.3) ■ Compost Socks (BMP D.2.1.3.6) 4.1.6 Element No. 6: Surface Water Collection The project is not anticipated to cause measurable changes in stormwater runoff flow rates during construction. Construction activity may cause the temporary channelization of stormwater runoff which will be mitigated by filtering and dispersing runoff through straw wattles and compost socks. Straw wattles, compost socks, or gravel or sand bag berms will be used to divert stormwater away from work areas and excavations to the extent possible. If stormwater does flow into excavations, this water will be pumped from the excavations using temporary submersible pumps. The water will be discharged through sediment bags to a dry, vegetated area for infiltration. Water also may be removed using vacuum trucks and discharged off-site at an approved disposal facility. All discharge areas will be observed for erosion and to check for infiltration. Turbid water will not discharge to surface water bodies, including Rolling Hills Creek. No trenches or channels will be constructed as part of the project to intercept surface water from upstream or downstream of the work areas. The following BMPs will be used to intercept all surface water from disturbed areas or to control erosion at any discharge hose outlet and within the vegetated areas, if necessary: ■ Surface Water Collection (BMP D.2.1.6) ■ Straw Wattles (staked, BMP D.2.1.2.5) ■ Compost Socks (BMP D.2.1.3.6) ■ Pumps and Flexible Hoses, with discharge through sediment bag to dry, stable, vegetated areas for infiltration. ■ Sediment Bag ■ Gravel or Sandbag Berms 4.1.7 Element No. 7: Dewatering Control Dewatering is not anticipated as part of the project at this time. However, dewatering may be required if unseasonably heavy precipitation occurs during construction, or if groundwater is encountered within the excavations. If needed, water will be removed from excavations using submersible pumps. Dewatering water will be discharged through sediment bags to a dry, stable, vegetated area for infiltration. Straw wattles, compost socks, or gravel or sand bag berms will be used to slow discharged water flow for infiltration. Water may also be removed using vacuum trucks and discharged off-site at an approved disposal facility. Appropriate pumping methods are to be determined by the contractor depending on site Puget Sound Energy | April 22, 2026 Page 9 File No. 9186-184-00 Task 2032 conditions and needs. Extra pumps will be on-site to control stormwater runoff in the event of primary pump failure. If needed, the following BMPs will be used to control erosion at any channels or outlets during dewatering: ■ Dewatering Control (BMP D.2.1.7) ■ Straw Wattles (staked, BMP D.2.1.2.5) ■ Compost Socks (BMP D.2.1.3.6) ■ Pumps and Flexible Hoses, with discharge through sediment bag to dry, stable, vegetated areas for infiltration. ■ Sediment Bag ■ Gravel or Sandbag Berms 4.1.8 Element No. 8: Dust Control Prevention measures to minimize the wind transport of soil from work areas shall be taken to prevent sediment and dust from being blown from the site onto roadways, drainage ways and surface waters. Control measures shall be implemented when exposed soils are dry enough to be blown by the wind. The following BMP will be used to control dust during construction: ■ Dust Control (BMP D.2.1.8) 4.1.9 Element No. 9. Flow Control Surface water from disturbed areas are not expected to increase surface water flow of the existing site conditions above the existing 2-year and 10-year runoff peaks discharging from the site during construction. The proposed work is scheduled to be completed during the drier months of the year. However, if unseasonably heavy precipitation occurs during construction, water will be directed away from drainage areas and Rolling Hills Creek using straw wattles, compost socks, or gravel or sandbag berms. If needed, water will be contained and removed using vacuum trucks and discharged off-site at an approved disposal facility. Appropriate pumping methods are to be determined by the contractor depending on site conditions and needs. Extra pumps will be on-site to control stormwater runoff in the event of primary pump failure. If needed, the following BMPs will be used to control flow during construction: ■ Flow Control (BMP D.2.1.9) ■ Straw Wattles (staked, BMP D.2.1.2.5) ■ Compost Socks (BMP D.2.1.3.6) ■ Pumps and Flexible Hoses, with discharge through sediment bag to dry, stable, vegetated areas for infiltration. ■ Sediment Bag ■ Gravel or Sandbag Berms Puget Sound Energy | April 22, 2026 Page 10 File No. 9186-184-00 Task 2032 4.1.10 Element 10: Control Pollutants All pollutants, including waste materials that occur during construction, will be handled and disposed of in a manner that is consistent with practices that do not cause contamination of stormwater, surface water or groundwater. Good housekeeping and preventive measures will be taken to ensure that the site will be kept clean, well-organized and free of debris. Spill response kits will be located on the site for rapid and easy access. Any equipment leaks from a fuel tank, equipment seal or hydraulic line will be contained within a spill pad placed beneath potential leak sources. Each spill response kit will include plastic sheeting, tarps, overpack drums, absorbent pads and kitty litter. Shovels and excavating equipment will be onsite and the contractor will be prepared to excavate and remove impacted soil if a spill occurs. Cover, containment and protection from vandalism will be provided for all chemicals, liquid products, petroleum products and non-inert wastes present on the site (see Washington Administrative Code [WAC] 173-304 for a definition of inert waste). Maintenance and repair of heavy equipment and vehicles should be performed to the extent practical at off-site locations, or if warranted, at service facilities away from the site. Maintenance and repair at on-site locations must be conducted using spill prevention measures such as drip pans, temporary impermeable liners, absorbent pads and other appropriate methods. Contaminated surfaces will be cleaned immediately following any discharge or spill incident. Emergency repairs may be performed on-site using temporary plastic placed beneath, and if raining, over the equipment. The following specific BMPs that will be used to control pollutants include: ■ Material Delivery, Storage and Containment (BMP D.2.2.4) ■ Maintain Protective BMPS (BMP D.2.2.10) Other BMP practices to be implemented to control specific sources of pollutants are discussed below. 4.1.10.1 VEHICLES, CONSTRUCTION EQUIPMENT AND/OR PETROLEUM PRODUCT STORAGE/DISPENSING ■ All vehicles, equipment and petroleum product storage/dispensing areas will be inspected at least daily to detect any leaks or spills, and to identify maintenance needs to prevent leaks or spills. ■ Contaminated surfaces will be cleaned immediately following any discharge or spill incident. 4.1.10.2 CHEMICAL STORAGE Chemicals will not be stored on-site as part of the project. However, if any chemicals are used or temporarily stored in the construction areas, storage and handling procedures will conform to the details of the following BMPs: ■ Material Delivery, Storage and Containment (BMP D.2.2.4) ■ Maintain Protective BMPS (BMP D.2.2.10) 4.1.10.3 EXCAVATION AND DEWATERING WASTE Dewatering BMPs and BMPs specific to the excavation are discussed under Element No. 7. Puget Sound Energy | April 22, 2026 Page 11 File No. 9186-184-00 Task 2032 4.1.10.4 DEMOLITION Demolition activities include removing portions of existing chain link fence (posts will be cut at ground surface with foundations abandoned in place), hazardous trees will be cut at ground surface with stump and roots abandoned in-place, existing concrete gate controller pads (about 2 feet by 2 feet) will be replaced and a narrow portion of asphalt driveway will be saw cut and restored in-kind to support conduit installation for security power and communications services. 4.1.10.5 CONCRETE AND GROUT Minor concrete work is anticipated as part of the project. Concrete work will be associated with fence post installation. Wash water from areas should not be allowed to drain directly (without detention or treatment) to natural or constructed stormwater conveyances or Rolling Hills Creek. Wash water and leftover product should be contained in a lined container when no designated concrete washout areas (or formed areas) are available. Contained concrete and concrete wash water (process water) should be disposed of properly off-site. Under no circumstances shall concrete wash water be allowed to discharge to any site ground surfaces or the site storm drain system. The following specific BMPs that will be used to control pollutants associated with concrete handling include: ■ SWPPS Measures (BMP D.2.2) ■ Concrete Handling (BMP D.2.2.1) ■ Concrete Washout Area (BMP D.2.2.2) ■ Sawcutting and Surfacing Pollution Prevention (BMP D.2.2.3) 4.1.10.6 SANITARY WASTEWATER Portable sanitation facilities will be firmly secured, regularly maintained and emptied when necessary. 4.1.10.7 SOLID WASTE Solid waste will be stored in secure, clearly marked containers. 4.1.10.8 OTHER Other BMPs will be administered as necessary to address any additional pollutant sources onsite. 4.1.11 Element No. 11: Protect Existing and Proposed Flow Control BMPs Sedimentation and soil compaction reduce the infiltration capacity of native and engineered soils. Protection measures shall be used to prevent adverse impacts to existing flow control BMPs at the site. Engineered soils have not been used at the site for infiltration purposes. No new flow control structures are planned as part of this project and existing flow control structures will not be impacted as part of this project. Temporary protective matts or mulch will be used to protect native and existing fill soils from compaction during fence and conduit construction activities. The following BMPs will be used during construction: ■ Protect Existing and Proposed Stormwater Facilities and On-Site BMPs (BMP D.2.1.10) Puget Sound Energy | April 22, 2026 Page 12 File No. 9186-184-00 Task 2032 4.1.12 Element No. 12: Maintain BMPs All temporary and permanent erosion and sediment control BMPs will be maintained and repaired as needed to ensure continued performance of their intended function. Maintenance and repair will be conducted in accordance with each particular BMP’s specification. The following specific BMPs that will be used to maintain BMPs include: ■ Maintain Protective BMPs (BMP D.2.1.11) Whenever site observation reveals that the BMPs identified in this CSWPPS are inadequate because the actual discharge of or potential to discharge a significant amount of any pollutant, appropriate BMPs or design changes will be implemented as soon as possible. All temporary erosion and sediment control BMPs will be removed within 30 days after the final site stabilization is achieved or after the temporary BMPs are no longer needed. Trapped sediment will be removed or stabilized on site. Disturbed soil resulting from removal of BMPs or vegetation will be permanently stabilized. 4.1.13 Element No. 13: Manage the Project Temporary erosion and sediment control BMPs for this project have been designed based on the following principles: ■ Emphasize erosion control rather than sediment control. ■ Minimize the extent and duration of the area exposed. ■ Retain sediment onsite. ■ Thoroughly observe site and maintain all erosion and sediment control measures. ■ Schedule major earthwork during the dry season All BMPs will be inspected, maintained and repaired, as needed, to ensure continued performance of their intended functions during the project. Site observations will be conducted by a qualified person who will be on-site daily and/or on-call in case a stormwater issue arises. This person has the necessary skills to: ■ Assess the site conditions and construction activities that could impact the quality of stormwater. ■ Assess the effectiveness of erosion and sediment control measures used to control the quality of stormwater discharges. The following specific BMPs that will be used for project management include: ■ Manage the Project (BMP D.2.1.12) Puget Sound Energy | April 22, 2026 Page 13 File No. 9186-184-00 Task 2032 5.0 Construction Schedule and BMP Implementation The BMP implementation schedule is driven by the construction schedule. The following provides a sequential list of the proposed construction schedule milestones and the corresponding BMP implementation schedule. However, target dates are for planning purposes only and are subject to revision. The project site is located west of the Cascade Mountain Crest. As such, the dry season is considered to be from May 1st to September 30th, and the wet season is considered to be from October 1st to April 30th. CONSTRUCTION SCHEDULE CONSTRUCTION SCHEDULE MILESTONES IMPLEMENTATION SCHEDULE Mobilize equipment to site June 2026 Install ESC measures June 2026 Estimated tree and shrub cutting activities June 2026 Estimated ground disturbing activities June 2026 Estimated restoration/stabilization September 2026 Demobilize equipment from site September 2026 6.0 Pollution Prevention Team 6.1 ROLES AND RESPONSIBILITIES The pollution prevention team consists of personnel responsible for implementation of the CSWPPS, including the following: ■ Project Manager – Owner representative that is the project’s supervising engineer responsible for observations and issuing instructions and drawings to the contractor’s site supervisor or representative. ■ Contractor – the person, firm or corporation with whom the owner has the contract to perform all project area work, including installing and maintaining requirements of the CSWPPS for the duration of the project. ■ TESC/BMP responsible person – primary contractor contact, responsible for site observations (BMPs, visual observation, sampling, recording, etc.); to be called upon in case of failure of any erosion and sediment control measures. ■ TESC/BMP Supervisor – primary contact for site inspector responsible for issuing additional instructions in case of failure of any erosion and sediment control measures and for contacting Project Manager and then Ecology. ■ Emergency Owner Contact – individual that is the site owner or representative of the site owner to be contacted in the case of an emergency. Puget Sound Energy | April 22, 2026 Page 14 File No. 9186-184-00 Task 2032 ■ Washington Emergency Management Division (ERTS) and National Response Center – Reporting centers to be contacted by the Project Manager if contaminated liquids or product enters the roadside ditches or nearby stream networks areas. 6.2 TEAM MEMBERS Names and contact information for those identified as members of the pollution prevention team are provided in the following table. Chain of command should be followed at all times and is established as follows: TESC/BMP personnel should report directly to TESC/BMP supervisor and coordinate daily activities with the Project Manager. CSWPPS TEAM MEMBERS TITLE NAME(S) PHONE NUMBER PSE Project Manager James Mauldin 206.940.9557 PSE Construction Manager Sam Hicks 206-817-3704 PSE Land Planning Contacts Kathryn Hodges Elaine Babby 206.549.7606 425.462.3805 PSE Emergency Contact James Mauldin 206.940.9557 Contractor Contact TBD TBD TESC/BMP Responsible Person Carla Woodworth 425.466.6772 TESC/BMP Supervisor Carla Woodworth 425.466.6772 REPORTING TO ECOLOGY WILL BE DIRECTED CONDUCTED BY PSE PERSONNEL; CONTACT INFORMATION IS LISTED FOR REFERENCE. Emergency Ecology Contact Report a Spill 425.649.6300 Emergency Ecology Contact (non-office hours) Northwest Regional Office 206.594.0000 Ecology Contact (office hours) Northwest Regional Office 206.594.0000 Washington Emergency Management Division (ERTS) 1.800.258.5990, 1.800.OILS.911 National Response Center 1.800.424.8802 6.3 SPILL AND RELEASE RESPONSE In the event of a discharge or release of oil, fuel or chemicals into state waters or onto land with a potential for entry into state waters, containment and clean-up efforts will begin immediately and be completed as soon as possible, taking precedence over normal work. Clean-up will include proper disposal of any spilled material and used clean-up materials. The event also needs to be reported to Ecology, ERTS and the National Response Center at the number listed in the above table. 7.0 Site Observation Site observation includes visual observation of all BMPs and visual observation for turbidity. Puget Sound Energy | April 22, 2026 Page 15 File No. 9186-184-00 Task 2032 All BMPs will be inspected daily. All BMPs will be maintained and repaired as needed to ensure continued performance of their intended function. Site observations will be conducted by a person who is knowledgeable in the principles and practices of erosion and sediment control. The on-site inspector will have the skills to assess the potential for water quality impacts as a result of the type of construction activities occurring on-site, and the knowledge of the appropriate and effective erosion and sedimentation control measures needed to control the quality of stormwater discharges. Site observations will occur in all areas disturbed by construction activities and at all stormwater discharge points. Stormwater will be examined for the presence of suspended sediment, turbidity, discoloration and oily sheen. The site inspector will evaluate the effectiveness of the installed BMPs and determine if it is necessary to repair or replace any of the BMPs to improve the quality of stormwater discharges. All new BMPs or design changes will be documented on the TESC plans as soon as possible. 7.1 STORMWATER TURBIDITY OBSERVATION Visual water quality observation locations for turbid runoff discharged from the site, except for infiltration, will be field determined based on runoff observed during work activities. Contingency locations may be added in the vicinity of the area of work, as needed and as work progresses. If suspended sediment, turbidity, discoloration and oily sheen is observed on surface water in the project areas, the following steps will be conducted: ■ Monitoring of Discharges (BMP D.2.3.2) ■ Ensure all BMPs specified in this CSWPPS are installed and functioning as intended. ■ Assess whether additional BMPs should be implemented, and document additional BMPs that were installed in the CSWPPS and on the TESC plans if revised. 7.2 PH Minor concrete work is planned for the project. Visual water quality observation locations for discharge or release of concrete or concrete slurry will be field determined based on runoff observed during concrete work activities. If concrete impacted surface water is observed, containment and clean-up efforts will begin immediately and be completed as soon as possible, taking precedence over normal work. Clean-up will include proper disposal of any spilled material and used clean-up materials. The following steps also will be conducted: ■ Ensure all BMPs specified in this CSWPPS are installed and functioning as intended. ■ Assess whether additional BMPs should be implemented, and document additional BMPs that were installed in the CSWPPS and on the TESC plans if revised. 8.0 Recordkeeping 8.1 ACCESS TO PLANS AND RECORDS This CSWPPS will be retained onsite or within reasonable access to the site. Puget Sound Energy | April 22, 2026 Page 16 File No. 9186-184-00 Task 2032 8.2 UPDATING THE CONSTRUCTION STORMWATER POLLUTION PREVENTION PLAN This CSWPPS will be modified if the CSWPPS is ineffective in eliminating or significantly minimizing pollutants in stormwater discharges from the work areas or there has been a change in design, construction, operation or maintenance at the site that has a significant effect on the discharge, or potential for discharge, of pollutants to the waters of the State. The CSWPPS will be modified within 7 days of determination based on observation(s) that additional or modified BMPs are necessary to correct problems identified, and an updated timeline for BMP implementation will be prepared. 9.0 References City of Renton Maps (COR). 2024a. Available at COR Maps | City of Renton Swarr Station (Security Perimeter Maintenance) Arborist Report by Davey Resource Group, Inc. dated 07/2024 (Updated 10/2025). Washington State Administrative Code [WAC] 173-304, Minimal Functional Standards for Solid Waste Handling. Available at Chapter 173-304 WAC: Washington State Department of Ecology (Ecology). 2025. Water Quality Atlas - Map. Available at: https://apps.ecology.wa.gov/waterqualityatlas/wqa/map?CustomMap=y&BBox=-13612568, 6008369,-13591048,6030789&RT=0&Layers=27&Filters=y,n,n,n,n,n&F1.4=n,n,n,n,n,y Appendices Appendix A Temporary Erosion and Sediment Control Plan (Completed by others) ECB ECB M S S M M M M M M M M M T U D M P P P PP P UR G G G G G G G G G G G G G S 1 7 0 1 7 0 1 8 0 1 9 0 2 1 0 200 2 3 0 2 4 0 22 0 21 0 20 0 1 9 0 18 0 2 0 0 19 0 1 8 0 17 0 1 6 0 17 0 1 8 0 1 9 0 2 0 0 19 0 1 8 0 1 7 0 160 15 0 150 2 1 0 20 0 19 0 18 0 17 0 16 0 2 5 0 1 5 0 16 0 17 0 1 5 0 15 0 1 4 0 1 3 0 1 3 0 140 150 xx x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x Δ = 3 5 ° 1 8 ' 2 5 " R = 3 8 4 . 2 6 ' L = 2 3 6.7 9 ' S 2 1 ° 2 2 ' 1 0 " E 4 2 9 . 8 7 ' S0 5 ° 1 0 ' 1 6 " E 1 6 5 . 5 1 ' S0 0 ° 4 5 ' 4 9 " W 6 3 1 . 1 5 ' S 1 6 ° 2 2 ' 1 0 " E 1 , 1 1 5 . 9 2 ' BE N S O N D R S ( S R - 5 1 5 ) SWARR STATION 1 8 6 184 SWARR STATION S P U G E T D R VICINITY MAP SITE167 181 515 169 OA K E S D A L E A V E S W 900 S 2 1 S T S T I-405 SEE SURVEY SHT 6 OF 6 FOR PARCEL SITE PLAN SITE PLAN SWARR STATION SECURITY MAINTENANCE QUARTER-SECTION-TOWNSHIP-RANGE: SW 1/4 SEC. 20, TWP 23 N., RNG. 05E., W.M. CITY OF RENTON, KING COUNTY, WASHINGTON IN COMPLIANCE WITH CITY OF RENTON STANDARDS Call before you dig. PUGET SOUND ENERGY SWARR STATION SECURITY MAINTENANCE PROJECT 2100 BENSON DRIVE S, RENTON, WA 98055 SW A R R S T A T I O N S E C U R I T Y M A I N T E N A N C E P R O J E C T SW A R R S T A T I O N S E C U R I T Y M A I N T E N A N C E P R O J E C T WO NUMBER: 142003204 (LEADING), 10860860 (RETIREMENT) G0 0 1 COVER SHEET 04/19/202604/14/2026 x x x W W W W W W W P P P ^^^^ ^ ^^^^^^^^^^^^^^^^^^^^^ ^ ^ ^^^^^^^^^^^^^^^^ P P ^ ^ ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ x ^ ^ ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ ^ ^ ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ ^ ^ ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ ^ ^ ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ TOP NAIL IN CONC FILLED 2" IRON PIPE IN CONC MONUMENT IN CASE -0.6' BELOW GRADE (VISITED JUNE 2023) 389+83.40 P.T. BK 389+92.43 AHD. 31'RT. (DOT) ECB ECB CONC CONC G A T E G A T E PCONC CONC ASPH DW M TO P TO P DIT W W W TO P NAIL IN CONC FILLED 2" IRON PIPE IN CONC MONUMENT IN CASE -0.3' BELOW GRADE. (VISITED JUNE 2023) 391+62.25 31' RT (DOT) 391+62.28 32'RT (C) 8898700680 N/A TOP TO P VARIES R/ W R/ W EP EP EP EP EP TO P BE N S O N D R S ( S R - 5 1 5 ) SS SS SS SS SS SS SS SS SS SS SS SS SS SS SS SS SS SS SS SWARR STATION M M M M M ^^^^ ^ ^^^^^^^^^^^^^^^^^^^^^ ^ ^ ^^^^^^^^^^^^^^^^ ^ ^ ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ ^ ^ ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ TOP TOP TOE TO E TO P ER(2) TOE TOE/ROCKERY SD CBW 36 " C M P GVL 24 " C O N C P I P E W/ N O T O P S D SD CONC, TYP CONC EX P O S E D P I P E S GA T E GVL ER(2)CW CONC W/ VENT, TYP GENERATOR EA V E WR(2) WMICV CONC SD D DI T / H A L F P I P E EX LIGHT POLE W/ CAMERAS TOP GVL WV TOP TO P TOP M W W W W W W W P P P P P P P P P PPW P P P P P P P P P P P P P P P P P P P P P P P P P P P P P P P P P P P DIT P ER P P GV GV ECC GV URGV ECCECC DIT DI T DIT GVL EG EG E G S TO P S ℄ R/ W G G G G G G G G G G G G G G G G G G G G G G G G G G G G G G G G G G G G G G G G G G G G G G G G G G G G G G G G G G G G G G G G 10' EP 10 ' W I D E W A T E R EA S E M E N T P E R RE C O R D I N G N O . 95 1 1 1 6 0 3 9 2 TOP 15' WIDE P E R M A N E N T EASEME N T P E R RECORDI N G N O . 7 8 1 2 2 1 0 9 4 2 10' WIDE T E M P C O N S T R U C T I O N EASEME N T P E R R E C O R D I N G NO. 781 2 2 1 0 9 4 2 15 ' W I D E P U B L I C UT I L I T I E S E A S E M E N T PE R R E C O R D I N G N O . 77 0 7 0 1 1 0 0 9 15' WIDE PUBLIC UTILITIES EASEMENT PER RECORDING NO. 7707011009 1 5 ' W I D E P U B L I C U T I L I T I E S E A S E M E N T P E R R E C O R D I N G N O . 7 7 0 7 0 1 1 0 0 9 10' 5' 1 5 ' 15 ' ASPH DW ASPH TOE TOE BUILDING DI T / H A L F P I P E GRASS 15' SD 10 ' 10' 10' WIDE WATER EASEMENT PER RECORDING NO. 9511160392 18 4 164 16 6 16 8 1 7 0 18 0 1 7 2 17 4 17 6 1 7 8 160 1 7 0 1 6 2 1 6 4 1 6 6 1 6 8 17 2 1 7 0 18 0 1 9 0 20 0 21 0 1 6 8 17 2 1 7 4 17 6 1 7 8 18 2 18 4 18 6 18 8 1 9 2 19 4 19 4 1 9 4 1 9 6 19 8 20 2 20 4 20 6 20 8 17 0 18 0 1 9 0 164 16 6 168 17 2 1 7 4 17 6 178 18 2 1 8 4 1 8 6 1 8 8 1 9 2 1 9 4 1 9 6 19 8 17 0 18 0 16 6 16 8 17 2 17 4 1 7 6 1 7 8 1 8 2 1 8 4 24617 0 19 0 2 0 0 21 0 2 2 0 23 0 2 4 0 18 0 17 4 17 6 17 8 18 2 18 4 18 6 18 8 16 0 1 7 0 18 0 16 2 16 4 16 6 16 8 1 7 2 1 7 4 1 7 6 1 7 8 160 17 0 18 0 1 9 0 20 0 154 156 158 162 164 16 6 1 6 8 1 7 2 17 4 17 6 17 8 18 2 1 8 4 18 6 1 8 8 1 9 2 1 9 4 19 6 1 9 8 20 2 20 4 20 6 20 8 ^ ^ ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ ^ ^ ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ ^ ^ ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ ^ ^ ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ ^^^^ ^ ^^^^^^^^^^^^^^^^^^^^^ ^ ^ ^^^^^^^^^^^^^^^^ ^ ^ ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ 8898700660 2107 WELLS CT S 2103 WELLS CT S 8898700670 889870TR-D 1016 S 22ND CT 8898700710 8898700720 1022 S 22ND CT 1102 S 22ND CT 8898700730 2100 BENSON DR S 2023059071 2104 WELLS CT S x xxx x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx x x x x x x x x x x x x x x x x x x S87°07'55"W 764.47' N0 0 ° 1 2 ' 1 0 " W 3 2 . 0 9 ' S0 5 ° 1 0 ' 1 6 " E 1 6 5 . 5 1 ' S0 0 ° 4 5 ' 4 9 " W 6 3 1 . 1 5 ' TESC PLAN (SOUTH) KEY MAP ^ ^ ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ ^^^^ ^ ^^^^^^^^^^^^^^^^^^^^^ ^ ^ ^^^^^^^^^^^^^^^^ IN COMPLIANCE WITH CITY OF RENTON STANDARDS Call before you dig. PUGET SOUND ENERGY SWARR STATION SECURITY MAINTENANCE PROJECT 2100 BENSON DRIVE S, RENTON, WA 98055 SW A R R S T A T I O N S E C U R I T Y M A I N T E N A N C E P R O J E C T SW A R R S T A T I O N S E C U R I T Y M A I N T E N A N C E P R O J E C T WO NUMBER: 142003204 (LEADING), 10860860 (RETIREMENT) C0 0 2 TESC PLAN (SOUTH) 04/19/202604/14/2026 P P P P P P P P P P P P P P P P P ^ ^ ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ ^ ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ ^^^^ ^ ^^^^^^^^^^^^^^^^^^^^^ ^ ^ ^^^^^^^^^^^^^^^^^^^^ ^ ^^^^^^^^^^^^^^^^^^^^^ ^ ^ ^^^^^^^^^^^^^^^^ ^ ^ ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ ^ ^ ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ ^ ^ ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ ^ ^ ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ ^ ^ ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ ^ ^ ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ ^ ^ ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ ^ ^ ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ ^ ^ ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ ^ ^ ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ 7' CLF W/ BW 7' CLF W/ BW TO P SD SD SD SD TO E W W W W W W W W W W W W W W W W ASPH DW GATE TOP ER(2) T O E T O E TO P EM SD SD GATE CBW SD SD SD SD SD SD SD SD N/ A EP EP E P 7' C L F W / B W BE N S O N D R S ( S R - 5 1 5 ) SS SS SS SS SS SS SS SS SS SS SS SS SS SS SS SS SS SS SS S S SWARR STATION ^^^^ ^ ^^^^^^^^^^^^^^^^^^^^^ ^ ^ ^^^^^^^^^^^^^^^^ M ^^^^ ^ ^^^^^^^^^^^^^^^^^^^^^ ^ ^ ^^ ^^^^^^^^^^^^^^ ^^^^ ^ ^^^^^^^^^^^^^^^^^^^^^ ^ ^ ^^^^^^^^^^^^^^^^ M ^^^^ ^ ^^^^^^^^^^^^^^^^^^^^^ ^ ^ ^^^^ ^^^^^^^^^^^^ P P P P P P P P P P P P P P P P P TO E SP-1 GEISP-2 GEI TO E TOP TO P TO P T O P BUILDING GA T E CONC STEEL STEPS EXPOSED PIPES ER GVL ER P P ^ ^ ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ M M ^^^^ ^ ^^^^^^^^^^^^^^^^^^^^^ ^ ^ ^^^^^^^^^^^^^^^^ T GVL GRASS TOE T O E TOE TOP TO P GVL GVL GVL GVL DW TO E T O P TO E / R O C K E R Y ER GA T E W/ CAMERAS TOE EG EG TO E EXPOSED PIPES ON CONC GVL GV U EX P O S E D P I P E S ER SD 36 " C O N C T O P SHED GVL CONC, TYP GVL GVL STEEL STEPS CONC ECB EX P O S E D P I P E S GA T E CONC CONC W/ GENERATOR CONC W/ VENT, TYP CONC W/ AC UNIT ER W/ SENSOR TO P TOP TOE TO P T O P GV TOE TO E TO E TOPCONC CONC T O E W W W W W W W P P P P P P P P P P P P P P P P P P UTUT PPW P P P P P P P P P P P P P P P P PER P P ER ER P P ER ER P ER PER ECC GV P P P P P P P P ER ER(2) W/ SENSORGV UR GV GV E C C ECC P P GRASS GV GV ER GV EX P O S E D P I P E S GVL EX P O S E D P I P E S 7' CLF W/ BW EG EG EG EG EG ASPH TO E UNDERGROUND CENTER GAS TANK 38 UNDERGROUND CENTER OF TANK 9 UNDERGROUND CENTER OF TANK 8 UNDERGROUND CENTER OF TANK 7 UNDERGROUND CENTER OF TANK 6 UNDERGROUND CENTER OF TANK 5 UNDERGROUND CENTER OF TANK 4 UNDERGROUND CENTER OF TANK 3 UNDERGROUND CENTER OF TANK 2 UNDERGROUND CENTER OF TANK 1 UNDERGROUND CENTER GAS TANK 39 TOP/E G EX P O S E D P I P E S UNDERGROUND CENTER GAS TANK 37 UNDERGROUND CENTER GAS TANK 36 ERUNDERGROUND CENTER GAS TANK 19 UNDERGROUND CENTER GAS TANK 17 UNDERGROUND CENTER GAS TANK 16 UNDERGROUND CENTER GAS TANK 15 UNDERGROUND CENTER GAS TANK 14 UNDERGROUND CENTER GAS TANK 13 UNDERGROUND CENTER GAS TANK 12 UNDERGROUND CENTER GAS TANK 11 G G G G G G G G G G G G G CIRCULAR BASE W/ EXPOSED VERTICAL PIPES T O P ℄ TOP G G G G G G EDGE OF TANK 1 10' WIDE W A T E R EASEMEN T P E R RECORDIN G N O . 951116039 2 10' WIDE T E M P CONSTRU C T I O N EASEMEN T P E R RECORDI N G N O . 78122109 4 2 15' WIDE P E R M A N E N T EASEMEN T P E R RECORDI N G N O . 78122109 4 2 ECOLOGY BLOCK (TYP) 10 ' W I D E W A T E R EA S E M E N T P E R RE C O R D I N G N O . 95 1 1 1 6 0 3 9 2 UNDERGROUND CENTER GAS TANK 18 UNDERGROUND CENTER OF TANK 10 20 ' W I D E S E W E R A N D P U B L I C UT I L I T I E S E A S E M E N T P E R RE C O R D I N G N O . 6 0 1 4 7 9 8 1 5 ' W I D E P U B L I C U T I L I T I E S E A S E M E N T P E R R E C O R D I N G N O . 7 7 0 7 0 1 1 0 0 8 15' WIDE PUBLIC UTILITIES EASEMENT PER RECORDING NO. 7707011009 10' 10' 10' 1 5 ' 20 ' R/ W R/ W DI T / H A L F P I P E GVL 1 4 0 15 0 14 2 14 4 14 6 14 8 15 2 15 4 15 6 1 3 2 1 3 4 1 3 6 1 3 8 12 0 13 0 122 124 126 12 8 120 128 15 0 14 6 14 6 14 8 14 8 140 150 142 144 146 148 14 8 15 0 1 5 0 16 0 17 0 18 0 15 2 15 4 15 6 15 8 16 2 1 6 4 1 6 6 16 8 17 2 17 4 17 6 17 8 18 2 18 4 1 5 0 15 2 1 5 4 1 5 6 15 0 15 2 220 230 240 218 222 224 226 228 232 234 236 238 242 17 0 18 0 1 9 0 2 0 0 2 1 0 2 2 0 2 3 0 16 0 17 0 18 0 19 0 20 0 21 0 22 0 20 0 210 20 2 204 206 208 212 214 216 16 0 15 8 16 2 16 4 16 6 16 8 15 0 16 0 17 0 18 0 19 0 150 148 152 ^ ^ ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ ^ ^ ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ ^ ^ ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ ^ ^ ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ ^ ^ ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ ^ ^ ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ ^ ^ ^^^^^^^^^^^^^^^^^^^^^^^^ ^ ^ ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ 20 2 3 0 5 9 0 9 3 2100 BENSON DR S 2023059071 S P U G E T D R x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x x Δ = 3 5 ° 1 8 ' 2 5 " R = 3 8 4 . 2 6 ' L = 2 3 6 . 7 9 ' S0 0 ° 4 5 ' 4 9 " W 6 3 1 . 1 5 ' S 1 6 ° 2 2 ' 1 0 " E 1 , 1 1 5 . 9 2 ' x x x TESC PLAN (NORTH) KEY MAP IN COMPLIANCE WITH CITY OF RENTON STANDARDS Call before you dig. PUGET SOUND ENERGY SWARR STATION SECURITY MAINTENANCE PROJECT 2100 BENSON DRIVE S, RENTON, WA 98055 SW A R R S T A T I O N S E C U R I T Y M A I N T E N A N C E P R O J E C T SW A R R S T A T I O N S E C U R I T Y M A I N T E N A N C E P R O J E C T WO NUMBER: 142003204 (LEADING), 10860860 (RETIREMENT) ^ ^ ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ ^^^^ ^ ^^^^^^^^^^^^^^^^^^^^^ ^ ^ ^^^^^^^^^^^^^^^^ C0 0 3 TESC PLAN (NORTH) 04/19/202604/14/2026 12 1CATCH BASIN INSERT - 2STRAW WATTLES IN COMPLIANCE WITH CITY OF RENTON STANDARDS Call before you dig. PUGET SOUND ENERGY SWARR STATION SECURITY MAINTENANCE PROJECT 2100 BENSON DRIVE S, RENTON, WA 98055 SW A R R S T A T I O N S E C U R I T Y M A I N T E N A N C E P R O J E C T SW A R R S T A T I O N S E C U R I T Y M A I N T E N A N C E P R O J E C T WO NUMBER: 142003204 (LEADING), 10860860 (RETIREMENT) C0 0 4 TESC DETAILS 04/19/202604/14/2026 Appendix B Construction Stormwater BMPs Puget Sound Energy | April 22, 2025 Page B-1 File No. 9186-184-00 Task 2032 Appendix B City of Renton Construction Stormwater BMPs The following is a list of construction stormwater BMPs that are to be implemented during the project. Where applicable, BMPs are labeled according to the City of Renton Surface Water Design Manual (RSWDM 20221) BMP detail number and BMP details subsequently follow this page. ■ Clearing Limits (BMP D.2.1.1) ■ High Visibility Fencing (BMP D.2.1.1.1) ■ Cover Measure (BMP D.2.1.2) ■ Mulching (BMP D.2.1.2.2) ■ Plastic Covering (BMP D.2.1.2.4) ■ Straw Wattles, staked or weighted (BMP D.2.1.2.5) ■ Temporary and Permanent Seeding (BMP D.2.1.2.6) ■ Perimeter Protection (BMP D.2.1.3) ■ Silt Fence (BMP D.2.1.3.1) ■ Vegetative Strip (BMP D.2.1.3.3) ■ Compost Socks, staked or weighted (BMP D.2.1.3.6) ■ Traffic Area Stabilization (BMP D.2.1.4) ■ Stabilized Construction Entrance (BMP D.2.1.4.1) ■ Construction Road/Parking Area Stabilization (BMP D.2.1.4.2) ■ Sediment Retention (BMP D.2.1.5) ■ Storm Drain Inlet Protection (BMP D.2.1.5.3) ■ Surface Water Collection (BMP D.2.1.6) ■ Dewatering Control (BMP D.2.1.7) ■ Dust Control (BMP D.2.1.8) ■ Flow Control (BMP D.2.1.9) ■ Protect Existing and Proposed Stormwater Facilities and On-Site BMPs (BMP D.2.1.10) ■ Maintain Protective BMPS (BMP D.2.1.11) ■ Manage the Project (BMP D.2.1.12) 1 City of Renton Surface Water Design Design Manual (RSWDM). 2022. Available at: https://edocs.rentonwa.gov/Documents/ DocView.aspx?id=11464516&dbid=0&repo=CityofRenton Puget Sound Energy | April 22, 2025 Page B-2 File No. 9186-184-00 Task 2032 ■ SWPPS Measures (BMP D.2.2) ■ Concrete Handling (BMP D.2.2.1) ■ Concrete Washout Area (BMP D.2.2.2) ■ Sawcutting and Surfacing Pollution Prevention (BMP D.2.2.3) ■ Material Delivery, Storage and Containment (BMP D.2.2.4) ■ Maintain Protective BMPS (BMP D.2.2.10) ■ Manage the Project (BMP D.2.2.11) ■ Monitoring of Discharges (BMP D.2.3.2) ■ Coarse Arborist Wood Chips ■ Construction Mats ■ Pumps, Flexible Hose or Piping with Diffuser System at End (to be designed, as needed, by contractor) ■ Sediment Bag(s), Gravel or Sandbag or Equivalent Berms/Cofferdams ■ Gravel, Crushed Rock and Asphalt Pavement Restoration D.2.1 ESC MEASURES 2022 City of Renton Surface Water Design Manual 6/22/2022 D-11 facility, runoff treatment facility, and on-site BMP areas [existing or proposed] shall not be used for this purpose). 10. Control Pollutants: Stormwater pollution prevention (SWPPS) measures are required to prevent, reduce, or eliminate the discharge of pollutants to onsite or adjacent stormwater systems or watercourses from construction-related activities such as materials delivery and storage, onsite equipment fueling and maintenance, demolition of existing buildings and disposition of demolition materials and other waste, and concrete handling, washout and disposal. Section D.2.2 describes BMPs specific to this purpose; additionally, several of the ESC BMPs described herein are applicable. 11. Protect Existing and Proposed Stormwater Facilities and On-site BMPs: Sedimentation and soil compaction reduce the infiltration capacity of native and engineered soils. Protection measures shall be applied/installed and maintained so as to prevent adverse impacts to existing stormwater facilities and on-site BMPs and areas of proposed stormwater facilities and on-site BMPs for the project. Adverse impacts can prompt the requirement to restore or replace affected stormwater facilities and on-site BMPs. 12. Maintain Protective BMPs: Protection measures shall be maintained to ensure continued performance of their intended function, to prevent adverse impacts to existing BMPs/facilities and areas of proposed BMPs/facilities, and protect other disturbed areas of the project. 13. Manage the Project: Coordination and timing of site development activities relative to ESC concerns, and timely inspection, maintenance and update of protective measures are necessary to effectively manage the project and ensure the success of protective ESC and SWPPS design and implementation. D.2.1.1 CLEARING LIMITS Prior to any site clearing or grading, those areas that are to remain undisturbed during project construction shall be delineated. At a minimum, clearing limits shall be installed at the edges of all critical area buffers and any other areas required to be left uncleared such as portions of the site subject to clearing limits under RMC 4-4-060, areas around significant trees identified to be retained, on-site BMP areas to be protected, and other areas identified to be left undisturbed to protect sensitive features. Purpose: The purpose of clearing limits is to prevent disturbance of those areas of the project site that are not designated for clearing or grading. This is important because limiting site disturbance is the single most effective method for reducing erosion. Clearing limits may also be used to control construction traffic, thus reducing the disturbance of soil and limiting the amount of sediment tracked off site. When to Install: Clearing limits shall be installed prior to the clearing and/or grading of the site. Measures to Use: Marking clearing limits by delineating the site with a continuous length of brightly colored survey tape is sometimes sufficient. The tape may be supported by vegetation or stakes, and it shall be 3 to 6 feet high and highly visible. Critical areas and their buffers require more substantial protection and shall be delineated with plastic or metal safety fences or stake and wire fences. Fencing may be required at the City’s discretion to control construction traffic or at any location where greater protection is warranted. Permanent fencing may also be used if desired by the applicant. Silt fence, in combination with survey flagging, is also an acceptable method of marking critical areas and their buffers. D.2.1.1.1 PLASTIC OR METAL FENCE Code: FE Symbol: Purpose Fencing is intended to (1) restrict clearing to approved limits; (2) prevent disturbance of critical areas, their buffers, and other areas required to be left undisturbed; (3) limit construction traffic to designated construction entrances or roads; and (4) protect areas where marking with survey tape may not provide adequate protection. SECTION D.2 GENERAL CSWPP REQUIREMENTS 6/22/2022 2022 City of Renton Surface Water Design Manual D-12 Conditions of Use To establish clearing limits, plastic or metal fence may be used: 1. At the boundary of critical areas, their buffers, and other areas required to be left uncleared. 2. As necessary to control vehicle access to and on the site (see Sections D.2.1.4.1 and D.2.1.4.2). Design and Installation Specifications 1. The fence shall be designed and installed according to the manufacturer’s specifications. 2. The fence shall be at least 3 feet high and must be highly visible. 3. The fence shall not be wired or stapled to trees. Maintenance Requirements 1. If the fence has been damaged or visibility reduced, it shall be repaired or replaced immediately and visibility restored. 2. Disturbance of a critical area, critical area buffer, native growth retention area, or any other area required to be left undisturbed shall be reported to the City for resolution. D.2.1.2 COVER MEASURES Temporary and permanent cover measures shall be provided to protect all disturbed areas, including the faces of cut and fill slopes. Temporary cover shall be installed if an area is to remain unworked for more than seven days during the dry season (May 1 to September 30) or for more than two consecutive working days during the wet season (October 1 to April 30). These time limits may be relaxed if an area poses a low risk of erosion due to soil type, slope gradient, anticipated weather conditions, or other factors. Conversely, the City may reduce these time limits if site conditions warrant greater protection (e.g., adjacent to significant aquatic resources or highly erosive soils) or if significant precipitation (see Section D.2.4.2) is expected. Any area to remain unworked for more than 30 days shall be seeded or sodded, unless the City determines that winter weather makes vegetation establishment infeasible. During the wet season, slopes and stockpiles at 3H:1V or steeper and with more than ten feet of vertical relief shall be covered if they are to remain unworked for more than 12 hours. Also during the wet season, the material necessary to cover all disturbed areas must be stockpiled on site. The intent of these cover requirements is to have as much area as possible covered during any period of precipitation. Purpose: The purpose of covering exposed soils is to prevent erosion, thus reducing reliance on less effective methods that remove sediment after it is entrained in runoff. Cover is the only practical method of reducing turbidity in runoff. Structural measures, such as silt fences and sediment ponds, are only capable of removing coarse particles and in most circumstances have little to no effect on turbidity. When to Install: Any exposed soils that will remain unworked for more than the time limit set above shall be covered by the end of the working day. If the exposed area is to remain unworked for more than 30 days, the area shall be seeded with the temporary seed mix or an equivalent mix that will provide rapid protection (see Section D.2.1.2.6). If the disturbed area is to remain unworked for a year or more or if the area has reached final grade, permanent seed mix or an equivalent mix shall be applied. Measures to Use: Cover methods include the use of surface roughening, mulch, erosion control nets and blankets, plastic covering, seeding, and sodding. Mulch and plastic sheeting are primarily intended to protect disturbed areas for a short period of time, typically days to a few months. Seeding and sodding are measures for areas that are to remain unworked for months. Erosion nets and blankets are to be used in conjunction with seeding steep slopes. The choice of measures is left to the designer; however, there are restrictions on the use of these methods, which are listed in the “Conditions of Use” and the “Design and Installation Specifications” sections for each measure. The methods listed are by no means exhaustive. Variations on the standards presented here are encouraged if other cost-effective products or methods provide substantially equivalent or superior performance. Also, D.2.1 ESC MEASURES 2022 City of Renton Surface Water Design Manual 6/22/2022 D-13 the details of installation can, and should, vary with the site conditions. A useful reference on the application of cover measures in the Puget Sound area is Improving the Cost Effectiveness of Highway Construction Site Erosion and Pollution Control, Horner, Guedry, and Kortenhof (1990). D.2.1.2.1 SURFACE ROUGHENING Purpose The purpose of surface roughening is to aid in the establishment of vegetative cover and to reduce runoff velocity, increase infiltration, and provide for sediment trapping through the provision of a rough soil surface. The rough soil surface may be created by operating a tiller or other equipment on the contour to form horizontal depressions or by leaving slopes in a roughened condition by not fine grading. Conditions of Use 1. All slopes steeper than 3H:1V and greater than 5 vertical feet require surface roughening to a depth of 2 to 4 inches prior to seeding. 2. Areas that will not be stabilized immediately may be roughened to reduce runoff velocity until seeding takes place. 3. Slopes with a stable rock face do not require roughening. 4. Slopes where mowing is planned should not be excessively roughened. Design and Installation Specifications There are different methods for achieving a roughened soil surface on a slope, and the selection of an appropriate method depends upon the type of slope. Roughening methods include stair-step grading, grooving, contour furrows, and tracking. See Figure D.2.1.2.A for information on tracking and contour furrows. Factors to be considered in choosing a method are slope steepness, mowing requirements, and whether the slope is formed by cutting or filling. Sole reliance on roughening for temporary erosion control is of limited effectiveness in intense rainfall events. Stair-step grading may not be practical for sandy, steep, or shallow soils. 1. Disturbed areas that will not require mowing may be stair-step graded, grooved, or left rough after filling 2. Stair Step grading is particularly appropriate in soils containing large amounts of soft rock. Each step” catches material that sloughs from above, and provides a level site where vegetation can become established. Stairs should be wide enough to work with standard earth moving equipment. Stair steps must be on contour or gullies will form on the slope. 3. Areas that will be mowed (slopes less steep than 3H:1V) may have small furrows left by disking, harrowing, raking, or seed-planting machinery operated on the contour. 4. Graded areas with slopes greater than 3H:1V but less than 2H:1V should be roughened before seeding. This can be accomplished in a variety of ways, including “track walking” or driving a crawler tractor up and down the slope, leaving a pattern of cleat imprints parallel to slope contours. 5. Tracking is done by operating equipment up and down the slope to leave horizontal depressions in the soil. Maintenance Standards Periodically check roughened, seeded, planted, and mulched slopes for rills and gullies, particularly after a significant storm event. Fill these areas slightly above the original grade, then re-seed and mulch as soon as possible. D.2.1 ESC MEASURES 2022 City of Renton Surface Water Design Manual 6/22/2022 D-15 D.2.1.2.2 MULCHING Code: MU Symbol: Purpose The purpose of mulching soils is to provide immediate temporary protection from erosion. Mulch also enhances plant establishment by conserving moisture, holding fertilizer, seed, and topsoil in place, and moderating soil temperatures. There is an enormous variety of mulches that may be used. Only the most common types are discussed in this section. Conditions of Use As a temporary cover measure, mulch should be used: 1. On disturbed areas that require cover measures for less than 30 days 2. As a cover for seed during the wet season and during the hot summer months 3. During the wet season on slopes steeper than 3H:1V with more than 10 feet of vertical relief. Design and Installation Specifications For mulch materials, application rates, and specifications, see Table D.2.1.2.A. Note: Thicknesses may be increased for disturbed areas in or near critical areas or other areas highly susceptible to erosion. Maintenance Standards 1. The thickness of the cover must be maintained. 2. Any areas that experience erosion shall be remulched and/or protected with a net or blanket. If the erosion problem is drainage related, then the drainage problem shall be assessed and alternate drainage such as interceptor swales may be needed to fix the problem and the eroded area remulched. SECTION D.2 GENERAL CSWPP REQUIREMENTS 6/22/2022 2022 City of Renton Surface Water Design Manual D-16 TABLE D.2.1.2.A MULCH STANDARDS AND GUIDELINES Mulch Material Quality Standards Application Rates Remarks Straw Air-dried; free from undesirable seed and coarse material 2–3 thick; 5 bales per 1,000 sf or 2– 3 tons per acre Cost-effective protection when applied with adequate thickness. Hand-application generally requires greater thickness than blown straw. Straw should be crimped to avoid wind blow. The thickness of straw may be reduced by half when used in conjunction with seeding. Wood Fiber Cellulose No growth inhibiting factors Approx. 25–30 lbs per 1,000 sf or 1,500–2,000 lbs per acre Shall be applied with hydromulcher. Shall not be used without seed and tackifier unless the application rate is at least doubled. Some wood fiber with very long fibers can be effective at lower application rates and without seed or tackifier. Compost No visible water or dust during handling. Must be purchased from supplier with Solid Waste Handling Permit. 2 thick min.; approx. 100 tons per acre (approx. 1.5 cubic feet per square yard) More effective control can be obtained by increasing thickness to 3 (2.25 cubic feet per square yard). Excellent mulch for protecting final grades until landscaping because it can be directly seeded or tilled into soil as an amendment. Compost may not be used in Sensitive Lake7 basins unless analysis of the compost shows no phosphorous release. Hydraulic Matrices Bonded Fiber Matrix BFM]) This mulch category includes hydraulic slurries composed of wood fiber, paper fiber or a combination of the two held together by a binding system. The BFM shall be a mixture of long wood fibers and various bonding agents. Apply at rates from 3,000 lbs per acre to 4,000 lbs per acre and based on manufacturers recommendations The BFM shall not be applied immediately before, during or immediately after rainfall so that the matrix will have an opportunity to dry for 24 hours after installation. Application rates beyond 2,500 pounds may interfere with germination and are not usually recommended for turf establishment. BFM is generally a matrix where all fiber and binders are in one bag, rather than having to mix components from various manufacturers to create a matrix. BFMs can be installed via helicopter in remote areas. They are approximately $1,000 per acre cheaper to install. Chipped Site Vegetation Average size shall be several inches. 2 minimum thickness This is a cost-effective way to dispose of debris from clearing and grubbing, and it eliminates the problems associated with burning. Generally, it should not be used on slopes above approx. 10% because of its tendency to be transported by runoff. It is not recommended within 200 feet of surface waters. If seeding is expected shortly after mulch, the decomposition of the chipped vegetation may tie up nutrients important to grass establishment. 7 Sensitive lake means a lake that has proved to be particularly prone to eutrophication; the City did not have any lakes that had this designation at the time of SWDM adoption. D.2.1 ESC MEASURES 2022 City of Renton Surface Water Design Manual 6/22/2022 D-19 D.2.1.2.4 PLASTIC COVERING Code: PC Symbol: Purpose Plastic covering provides immediate, short-term erosion protection to slopes and disturbed areas. Conditions of Use 1. Plastic covering may be used on disturbed areas that require cover measures for less than 30 days. 2. Plastic is particularly useful for protecting cut and fill slopes and stockpiles. Note: The relatively rapid breakdown of most polyethylene sheeting makes it unsuitable for long-term applications. 3. Clear plastic sheeting may be used over newly-seeded areas to create a greenhouse effect and encourage grass growth. Clear plastic should not be used for this purpose during the summer months because the resulting high temperatures can kill the grass. 4. Due to rapid runoff caused by plastic sheeting, this method shall not be used upslope of areas that might be adversely impacted by concentrated runoff. Such areas include steep and/or unstable slopes. Note: There have been many problems with plastic, usually attributable to poor installation and maintenance. However, the material itself can cause problems, even when correctly installed and maintained, because it generates high-velocity runoff and breaks down quickly due to ultraviolet radiation. In addition, if the plastic is not completely removed, it can clog drainage system inlets and outlets. It is highly recommended that alternatives to plastic sheeting be used whenever possible and that its use be limited. Design and Installation Specifications 1. See Figure D.2.1.2.D for details. 2. Plastic sheeting shall have a minimum thickness of 0.06 millimeters. 3. If erosion at the toe of a slope is likely, a gravel berm, riprap, or other suitable protection shall be installed at the toe of the slope in order to reduce the velocity of runoff. FIGURE D.2.1.2.D PLASTIC COVERING TIRES, SANDBAGS, OR EQUIVALENT MAY BE USED TO WEIGHT PLASTIC SEAMS BETWEEN SHEETS MUST OVERLAP A MINIMUM OF 12" AND BE WEIGHTED OR TAPED TOE IN SHEETING IN MINIMUM 4"X4" TRENCH PROVIDE ENERGY DISSIPATION AT TOE WHEN NEEDED 10' MAX. 10' MAX. SECTION D.2 GENERAL CSWPP REQUIREMENTS 6/22/2022 2022 City of Renton Surface Water Design Manual D-20 Maintenance Standards for Plastic Covering 1. Torn sheets must be replaced and open seams repaired. 2. If the plastic begins to deteriorate due to ultraviolet radiation, it must be completely removed and replaced. 3. When the plastic is no longer needed, it shall be completely removed. D.2.1.2.5 STRAW WATTLES Code: SW Symbol: Purpose Wattles are erosion and sediment control barriers consisting of straw wrapped in biodegradable tubular plastic or similar encasing material. Wattles may reduce the velocity and can spread the flow of rill and sheet runoff, and can capture and retain sediment. Straw wattles are typically 8 to 10 inches in diameter and 25 to 30 feet in length. The wattles are placed in shallow trenches and staked along the contour of disturbed or newly constructed slopes. Conditions of Use 1. Install on disturbed areas that require immediate erosion protection. 2. Use on slopes requiring stabilization until permanent vegetation can be established. 3. Can be used along the perimeter of a project, as a check dam in unlined ditches and around temporary stockpiles 4. Wattles can be staked to the ground using willow cuttings for added revegetation. 5. Rilling can occur beneath and between wattles if not properly entrenched, allowing water to pass below and between wattles Design and Installation Specifications 1. It is critical that wattles are installed perpendicular to the flow direction and parallel to the slope contour. 2. Narrow trenches should be dug across the slope, on contour, to a depth of 3 to 5 inches on clay soils and soils with gradual slopes. On loose soils, steep slopes, and during high rainfall events, the trenches should be dug to a depth of 5 to 7 inches, or ½ to 2/3 of the thickness of the wattle. 3. Start construction of trenches and installing wattles from the base of the slope and work uphill. Excavated material should be spread evenly along the uphill slope and compacted using hand tamping or other method. Construct trenches at contour intervals of 3 to 30 feet apart depending on the steepness of the slope, soil type, and rainfall. The steeper the slope the closer together the trenches should be constructed. Vertical distance between wattles is not to exceed 10 feet. 4. Install the wattles snugly into the trenches and abut tightly end to end. Do not overlap the ends. 5. Install stakes at each end of the wattle, and at 4 foot centers along the entire length of the wattle. 6. If required, install pilot holes for the stakes using a straight bar to drive holes through the wattle and into the soil. 7. At a minimum, wooden stakes should be approximately ¾ x ¾ x 24 inches. Willow cuttings or 3/8 inch rebar can also be used for stakes. 8. Stakes should be driven through the middle of the wattle, leaving 2 to 3 inches of the stake protruding above the wattle. D.2.1 ESC MEASURES 2022 City of Renton Surface Water Design Manual 6/22/2022 D-21 Maintenance Standards 1. Inspect wattles prior to forecasted rain, daily during extended rain events, after rain events, weekly during the wet season, and at two week intervals at all other times of the year. 2. Repair or replace split, torn, raveling, or slumping wattles 3. Remove sediment accumulations when exceeding ½ the height between the top of the wattle and the ground surface. SECTION D.2 GENERAL CSWPP REQUIREMENTS 6/22/2022 2022 City of Renton Surface Water Design Manual D-22 FIGURE D.2.1.2.E STRAW WATTLES 1. STRAW ROLL INSTALLATION REQUIRES THE PLACEMENT AND SECURE STAKING OF THE ROLL IN A TRENCH, 3" x 5" (75-125mm) DEEP, DUG ON CONTOUR. 2. RUNOFF MUST NOT BE ALLOWED TO RUN UNDER OR AROUND ROLL. ROLL SPACING DEPENDS ON SOIL TYPE AND SLOPE STEEPNESS STRAW ROLLS MUST BE PLACED ALONG SLOPE CONTOURS 3'-4' 1.2m) 10'-25' 3-8m) 3"-5" 75-125mm) ADJACENT ROLLS SHALL TIGHTLY ABUT SEDIMENT, ORGANIC MATTER, AND NATIVE SEEDS ARE CAPTURED BEHIND THE ROLLS LIVE STAKE 1" x 1" STAKE 8"-10" DIA. 200-250mm) NOTES: STRAW WATTLES NTS D.2.1 ESC MEASURES 2022 City of Renton Surface Water Design Manual 6/22/2022 D-23 D.2.1.2.6 TEMPORARY AND PERMANENT SEEDING Code: SE Symbol: Purpose Seeding is intended to reduce erosion by stabilizing exposed soils. A well-established vegetative cover is one of the most effective methods of reducing erosion. Conditions of Use 1. Seeding shall be used throughout the project on disturbed areas that have reached final grade or that will remain unworked for more than 30 days. 2. Vegetation-lined channels shall be seeded. Channels that will be vegetated should be installed before major earthwork and hydroseeded or covered with a Bonded Fiber Matrix (BFM). 3. Retention/detention ponds shall be seeded as required. 4. At the City’s discretion, seeding without mulch during the dry season is allowed even though it will take more than seven days to develop an effective cover. Mulch is, however, recommended at all times because it protects seeds from heat, moisture loss, and transport due to runoff. 5. Prior to the beginning of the wet season, all disturbed areas shall be reviewed to identify which ones can be seeded in preparation for the winter rains (see Section D.2.4.2). Disturbed areas shall be seeded within one week of the beginning of the wet season. A sketch map of those areas to be seeded and those areas to remain uncovered shall be submitted to the CED inspector. The CED inspector may require seeding of additional areas in order to protect surface waters, adjacent properties, or drainage facilities. 6. At final site stabilization, all disturbed areas not otherwise vegetated or stabilized shall be seeded and mulched (see Section D.2.4.5). Design and Installation Specifications 1. The best time to seed is fall (late September to October) or in spring (mid-March to June). Irrigation is required during the first summer following installation if seeding occurs in spring or summer or during prolonged dry times of year. Areas may also be seeded during the winter months, but it may take additional spring seeding applications to develop a dense groundcover due to cold temperatures. The application and maintenance of mulch is critical for winter seeding. 2. To prevent seed from being washed away, confirm that all required surface water control measures have been installed. 3. The seedbed should not be compacted because soils that are well compacted will not vegetate as quickly or thoroughly. Slopes steeper than 3H:1V shall be surface roughened. Roughening can be accomplished in a variety of ways, but the typical method is track walking, or driving a crawling tractor up and down the slope, leaving cleat imprints parallel to the slope contours. 4. In general, 10-20-20 N-P-K (nitrogen-phosphorus-potassium) fertilizer may be used at a rate of 90 pounds per acre. Slow-release fertilizers are preferred because they are more efficient and have fewer environmental impacts. It is recommended that areas being seeded for final landscaping conduct soil tests to determine the exact type and quantity of fertilizer needed. This will prevent the over- application of fertilizer. Disturbed areas within 200 feet of water bodies and wetlands must use slow- release low-phosphorus fertilizer (typical proportions 3-1-2 N-P-K). 5. The following requirements apply to mulching: a) Mulch is always required for seeding slopes greater than 3H:1V (see Section D.2.1.2.2). b) If seeding during the wet season, mulch is required. SECTION D.2 GENERAL CSWPP REQUIREMENTS 6/22/2022 2022 City of Renton Surface Water Design Manual D-24 c) The use of mulch may be required during the dry season at the City’s discretion if grass growth is expected to be slow, the soils are highly erodible due to soil type or gradient, there is a water body close to the disturbed area, or significant precipitation (see Section D.2.4.2) is anticipated before the grass will provide effective cover. d) Mulch may be applied on top of the seed or simultaneously by hydroseeding. 6. Hydroseeding is allowed as long as tackifier is included. Hydroseeding with wood fiber mulch is adequate during the dry season. Application of hydroseeded wood fiber mulch should be appropriate for slope angle. Follow manufacturer specifications for application rates. 7. Areas to be permanently landscaped shall use soil amendments. Good quality topsoil shall be tilled into the top six inches to reduce the need for fertilizer and improve the overall soil quality. Most native soils will require the addition of four inches of well-rotted compost to be tilled into the soil to provide a good quality topsoil. Compost used should meet specifications provided in Reference Section 11-C of the SWDM. 8. The seed mixes listed below include recommended mixes for both temporary and permanent seeding. These mixes, with the exception of the wetland mix, shall be applied at a rate of 80 to 100 seeds per square foot. Wet sites should apply 120 to 150 seeds per square foot. Local suppliers should be consulted for information on current Pure Live Seed (PLS) rates and species specific seeds per pound in order to determine seed mix PLS pounds of seed per acre. The appropriate mix depends on a variety of factors, including exposure, soil type, slope, and expected foot traffic. Alternative seed mixes approved by the City may be used. Table D.2.1.2.B presents the standard mix for those areas where temporary or permanent vegetative cover is required. The following mix assumes a desired 150 seeds per square foot and should be applied at approximately 37 pounds of pure live seed per acre. TABLE D.2.1.2.B EROSION CONTROL SEED MIX Common Name/Latin Name Species Composition Desired Seeds per Square Foot PLS Pounds/Acre Spike bentgrass/Agrostis exarata 6 9 0.1 California brome/Bromus carinatus 15 23 9.8 Tufted hairgrass/Deschampsia cespitosa 15 23 0.4 Blue wildrye/Elymus glaucus 18 27 10.7 California oatgrass/Danthonia californica 18 27 5.6 Native red fescue/Festuca rubra var. rubra 18 27 2.4 Meadow barley/Hordeum brachyantherum 10 15 7.7 Table D.2.1.2.C provides just one recommended possibility for landscaping seed. It assumes a desired 100 seeds per square foot and should be applied at 18 pounds of pure live seed per acre. TABLE D.2.1.2.C LANDSCAPING SEED MIX Common Name/Latin Name Species Composition Desired Seeds per Square Foot PLS Pounds/Acre Sideoats grama/Bouteloua curtipendula 20 30 6.8 California oatgrass/Danthonia californica 20 30 6.2 Native red fescue/Festuca rubra var. rubra 30 45 3.9 Prairie junegrass/Koeleria macrantha 30 45 0.8 D.2.1 ESC MEASURES 2022 City of Renton Surface Water Design Manual 6/22/2022 D-25 This turf seed mix in Table D.2.1.2.D is for dry situations where there is no need for much water. The advantage is that this mix requires very little maintenance. TABLE D.2.1.2.D LOW-GROWING TURF SEED MIX Common Name/Latin Name Species Composition Desired Seeds per Square Foot PLS Pounds/Acre Hard fescue/Festuca brevipila 25 20 1.5 Sheep fescue/Festuca ovina 30 24 1.5 Native red fescue/Festuca rubra var. rubra 25 20 1.7 Prairie junegrass/Koeleria macrantha 20 16 0.3 Table D.2.1.2.E presents a mix recommended for bioswales and other intermittently wet areas. The mix assumes a desired 150 seeds per square foot and approximately 29 pounds of pure live seed per acre. Sod shall generally not be used for bioswales because the seed mix is inappropriate for this application. Sod may be used for lining ditches to prevent erosion, but it will provide little water quality benefit during the wet season. TABLE D.2.1.2.E BIOSWALE SEED MIX Common Name/Latin Name Species Composition Desired Seeds per Square Foot PLS Pounds/Acre American sloughgrass/Beckmannia syzigachne 15 23 0.9 Tufted hairgrass/Deschampsia cespitosa 20 30 0.5 Blue wildrye/Elymus glaucus 18 27 10.7 Native red fescue/Festuca rubra var. rubra 20 30 2.6 Meadow barley/Hordeum brachyantherum 12 18 9.2 Northwestern mannagrass/Glyceria occidentalis 15 23 4.9 The seed mix shown in Table D.2.1.2.F is a recommended low-growing, non-invasive seed mix appropriate for very wet areas that are not regulated wetlands (if planting in wetland areas, see Section 6.3.1 of the SWDM). Other mixes may be appropriate, depending on the soil type and hydrology of the area. This mixture assumes a target goal of 150 seeds per square foot and should be applied at a rate of 36 pounds per acre. TABLE D.2.1.2.F WET AREA SEED MIX* Common Name/Latin Name Species Composition Desired Seeds per Square Foot PLS Pounds/Acre California brome/Bromus carinatus 15 23 9.8 Columbia brome/Bromus vulgaris 18 27 8.1 Tufted hairgrass/Deschampsia cespitosa 15 23 0.4 California oatgrass/Danthonia californica 15 23 4.7 Native red fescue/Festuca rubra var. rubra 17 26 2.2 Western manna grass/Glyceria occidentalis 10 15 3.3 Meadow barley/Hordeum brachyantherum 10 15 7.7 Modified Briargreen, Inc. Hydroseeding Guide Wetlands Seed Mix SECTION D.2 GENERAL CSWPP REQUIREMENTS 6/22/2022 2022 City of Renton Surface Water Design Manual D-26 The meadow seed mix in Table D.2.1.2.G is recommended for areas that will be maintained infrequently or not at all and where colonization by native plants is desirable. Likely applications include rural road and utility right-of-way. Seeding should take place in September or very early October in order to obtain adequate establishment prior to the winter months. This seed mix assumes a target goal of 120 seeds per square foot and an application rate of 23 pounds of pure live seed per acre. TABLE D.2.1.2.G MEADOW SEED MIX Common Name/Latin Name Species Composition Desired Seeds per Square Foot PLS Pounds/Acre Common yarrow/Achillea millefolium 4 5 0.1 Pearly everlasting/Anaphalis margartacae 1 1 0.0 California brome/Bromus carinatus 15 18 7.8 California oatgrass/Danthonia californica 15 18 3.7 Blue wildrye/Elymus glaucus 16 19 7.6 Festuca idahoensis 15 18 1.7 Native red fescue/Festuca rubra var. rubra 18 22 1.9 Sickle keeled lupine/Lupinus albicaulis 1 1 2.2 Fowl bluegrass/Poa palustris 15 18 0.4 Maintenance Standards for Temporary and Permanent Seeding 1. Any seeded areas that fail to establish at least 80 percent cover within one month shall be reseeded. If reseeding is ineffective, an alternate method, such as sodding or nets/blankets, shall be used. If winter weather prevents adequate seed establishment and growth, this time limit may be relaxed at the discretion of the City when critical areas would otherwise be protected. 2. After adequate cover is achieved, any areas that experience erosion shall be re-seeded and protected by mulch. If the erosion problem is drainage related, the problem shall be fixed and the eroded area re- seeded and protected by mulch. 3. Seeded areas shall be supplied with adequate moisture, but not watered to the extent that it causes runoff. D.2.1.2.7 SODDING Code: SO Symbol: Purpose The purpose of sodding is to establish permanent turf for immediate erosion protection and to stabilize drainage ways where concentrated overland flow will occur. Conditions of Use Sodding may be used in the following areas: 1. Disturbed areas that require short-term or long-term cover 2. Disturbed areas that require immediate vegetative cover 3. All waterways that require vegetative lining (except biofiltration swales—the seed mix used in most sod is not appropriate for biofiltration swales). Waterways may also be seeded rather than sodded, and protected with a net or blanket (see Section D.2.1.2.3). SECTION D.2 GENERAL CSWPP REQUIREMENTS 6/22/2022 2022 City of Renton Surface Water Design Manual D-30 Provide immediate temporary protection from erosion by protecting soil from rainfall and slowing flow velocity over the soil surface. Enhance temporary or permanent plant establishment by conserving moisture, holding seed and topsoil in place, providing nutrients and soil microorganisms, and moderating soil temperatures. Compost blankets, applied at the proper thickness and tilled into the soil, are also an option for amending soils for permanent landscaping. Compost generally releases and adds phosphorous to stormwater. Therefore, compost blankets are not recommended for use in watersheds where phosphorous sensitive water resources are located. Unless prior approval is given by the City, they should not be used in Sensitive Lake Watersheds. Conditions of Use 1. Compost blankets may be used unseeded on disturbed areas that require temporary cover measures up to 1 year. Compost applied as temporary cover may be reclaimed and re-used for permanent cover. 2. Compost provides cover for protecting final grades until landscaping can be completed as it can be directly seeded or tilled into soil as an amendment. 3. Compost blankets meet mulch requirements for seed. 4. Seed may be applied to a compost blanket at any time for permanent or temporary stabilization of disturbed areas. Seed may be applied prior to blanket application, on top of blankets, or injected and mixed into the compost as it is applied. 5. Compost blankets may be applied on slopes up to 2H:1V. Design and Installation Specifications 1. Compost shall be applied at a minimum of 2 inches thick, unless otherwise directed by an ESC supervisor or the City. At an application of 2 inches, this will equal approximately 100 tons per acre compost generally weighs approximately 800 lbs per cubic yard). Thickness shall be increased at the direction of the design engineer for disturbed areas in or near critical areas or other areas highly susceptible to erosion. 2. Compost shall meet criteria in Reference Section 11-C of the SWDM. 3. Compost shall be obtained from a supplier meeting the requirements in Reference Section 11-C. 4. Compost blankets shall be applied over the top of the slope to which it is applied, to prevent water from running under the blanket 5. Compost blankets shall not be used in areas exposed to concentrated flow (e.g., channels, ditches, dikes) Maintenance Standards 1. The specified thickness of the blanket/cover must be maintained. 2. Any areas that show signs of erosion must be re-mulched. If the erosion problem is drainage related, then the drainage problem must first be remedied and then the eroded area re-mulched. D.2.1.3 PERIMETER PROTECTION Perimeter protection to filter sediment from sheetwash shall be located downslope of all disturbed areas and shall be installed prior to upslope grading. Perimeter protection includes the use of vegetated strips as well as, constructed measures, such as silt fences, fiber rolls, sand/gravel barriers, brush or rock filters, triangular silt dikes and other methods. During the wet season, 50 linear feet of silt fence (and the necessary stakes) per acre of disturbed area must be stockpiled on site. Purpose: The purpose of perimeter protection is to reduce the amount of sediment transported beyond the disturbed areas of the construction site. Perimeter protection is primarily a backup means of sediment control. Most, if not all, sediment-laden water is to be treated in a sediment trap or pond. The only D.2.1 ESC MEASURES 2022 City of Renton Surface Water Design Manual 6/22/2022 D-31 circumstances in which perimeter control is to be used as a primary means of sediment removal is when the catchment is very small (see below). When to Install: Perimeter protection is to be installed prior to any upslope clearing and grading. Measures to Use: The above measures may be used interchangeably and are not the only perimeter protection measures available. If surface water is collected by an interceptor dike or swale and routed to a sediment pond or trap, there may be no need for the perimeter protection measures specified in this section. Criteria for Use as Primary Treatment: At the boundary of a site, perimeter protection may be used as the sole form of treatment when the flowpath meets the criteria listed below. If these criteria are not met, perimeter protection shall only be used as a backup to a sediment trap or pond. Average Slope Slope Percent Flowpath Length 1.5H:1V or less 67% or less 100 feet 2H:1V or less 50% or less 115 feet 4H:1V or less 25% or less 150 feet 6H:1V or less 16.7% or less 200 feet 10H:1V or less 10% or less 250 feet D.2.1.3.1 SILT FENCE Code: SF Symbol: Purpose Use of a silt fence reduces the transport of coarse sediment from a construction site by providing a temporary physical barrier to sediment and reducing the runoff velocities of overland flow. Conditions of Use 1. Silt fence may be used downslope of all disturbed areas. 2. Silt fence is not intended to treat concentrated flows, nor is it intended to treat substantial amounts of overland flow. Any concentrated flows must be conveyed through the drainage system to a sediment trap or pond. The only circumstance in which overland flow may be treated solely by a silt fence, rather than by a sediment trap or pond, is when the area draining to the fence is small (see “Criteria for Use as Primary Treatment” in Section D.2.1.3 above). Design and Installation Specifications 1. See Figure D.2.1.3.A and Figure D.2.1.3.B for details. 2. The geotextile used must meet the standards listed below. A copy of the manufacturer’s fabric specifications must be available on site. AOS (ASTM D4751) 30–100 sieve size (0.60–0.15 mm) for slit film 50–100 sieve size (0.30–0.15 mm) for other fabrics Water Permittivity (ASTM D4491) 0.02 sec-1 minimum Grab Tensile Strength (ASTM D4632) see Specification Note 3) 180 lbs. min. for extra strength fabric 100 lbs. min. for standard strength fabric Grab Tensile Elongation (ASTM D4632) 30% max. (woven) Ultraviolet Resistance (ASTM D4355) 70% min. 3. Standard strength fabric requires wire backing to increase the strength of the fence. Wire backing or closer post spacing may be required for extra strength fabric if field performance warrants a stronger fence. SECTION D.2 GENERAL CSWPP REQUIREMENTS 6/22/2022 2022 City of Renton Surface Water Design Manual D-32 4. Where the fence is installed, the slope shall be no steeper than 2H:1V. 5. If a typical silt fence (per Figure D.2.1.3.A) is used, the standard 4 x 4 trench may be reduced as long as the bottom 8 inches of the silt fence fabric is well buried and secured in a trench that stabilizes the fence and does not allow water to bypass or undermine the silt fence. Maintenance Standards 1. Any damage shall be repaired immediately. 2. If concentrated flows are evident uphill of the fence, they must be intercepted and conveyed to a sediment trap or pond. 3. It is important to check the uphill side of the fence for signs of the fence clogging and acting as a barrier to flow and then causing channelization of flows parallel to the fence. If this occurs, replace the fence or remove the trapped sediment. 4. Sediment must be removed when the sediment is 6 inches high. 5. If the filter fabric (geotextile) has deteriorated due to ultraviolet breakdown, it shall be replaced. D.2.1 ESC MEASURES 2022 City of Renton Surface Water Design Manual 6/22/2022 D-33 FIGURE D.2.1.3.A SILT FENCE 2"X2" BY 14 Ga. WIRE OR EQUIVALENT, IF STANDARD STRENGTH FABRIC USED NOTE: FILTER FABRIC FENCES SHALL BE INSTALLED ALONG CONTOURS WHENEVER POSSIBLE JOINTS IN FILTER FABRIC SHALL BE SPLICED AT POSTS. USE STAPLES, WIRE RINGS OR EQUIVALENT TO ATTACH FABRIC TO POSTS. FILTER FABRIC BACKFILL TRENCH WITH NATIVE SOIL OR 3/4" TO 1-1/2" WASHED GRAVEL MINIMUM 4"x4" TRENCH 2"x4" WOOD POSTS, STEEL FENCE POSTS, REBAR, OR EQUIVALENT POST SPACING MAY BE INCREASED TO 8' IF WIRE BACKING IS USED 6' MAX. 2' MIN 12 M IN SECTION D.2 GENERAL CSWPP REQUIREMENTS 6/22/2022 2022 City of Renton Surface Water Design Manual D-34 FIGURE D.2.1.3.B SILT FENCE INSTALLATION BY SLICING 1. GATHER FABRIC AT POSTS, IF NEEDED. 2. UTILIZE THREE TIES PER POST, ALL WITHIN TOP 8" OF FABRIC. 3. POSITION EACH TIE DIAGONALLY, PUNCTURING HOLES VERTICALLY A MINIMUM OF 1" APART. 4. HANG EACH TIE ON A POST NIPPLE AND TIGHTEN SECURELY. USE CABLE TIES 50 LBS) OF SOFT WIRE. TOP OF FABRIC BELT DIAGONAL ATTACHMENT DOUBLES STRENGTH FLOW ST E E L S U PPO R T P O S T 1. POST SPACING: 7' MAX. ON OPEN RUNS 4' MAX. ON POOLING AREAS. 2. POST DEPTH: AS MUCH BELOW GROUND AS FABRIC ABOVE GROUND. 3. PONDING HEIGHT MAX. 24" ATTACH FABRIC TO UPSTREAM SIDE OF POST. 4. DRIVE OVER EACH SIDE OF SILT FENCE 2 TO 4 TIMES WITH DEVICE EXERTING 60 P.S.I. OR GREATER. 5. NO MORE THAN 24" OF A 36" FABRIC IS ALLOWED ABOVE GROUND. 6. VIBRATORY PLOW IS NOT ACCEPTABLE BECAUSE OF HORIZONTAL COMPACTION. 100% COMPACTION EACH SIDE OPERATION ROLL OF SILT FENCE PLOW FABRIC ABOVE GROUND HORIZONTAL CHISEL POINT 76 mm WIDTH)200-300mm SILT FENCE TOP 8" NOTES: ATTACHMENT DETAILS: SILT FENCE INSTALLATION BY SLICING METHOD NTS SECTION D.2 GENERAL CSWPP REQUIREMENTS 6/22/2022 2022 City of Renton Surface Water Design Manual D-36 D.2.1.3.3 VEGETATED STRIP Code: VS Symbol: Purpose Vegetated strips reduce the transport of coarse sediment from a construction site by providing a temporary physical barrier to sediment and reducing the runoff velocities of overland flow. Conditions of Use 1. Vegetated strips may be used downslope of all disturbed areas. 2. Vegetated strips are not intended to treat concentrated flows, nor are they intended to treat substantial amounts of overland flow. Any concentrated flows must be conveyed through the drainage system to a sediment trap or pond. The only circumstance in which overland flow may be treated solely by a strip, rather than by a sediment trap or pond, is when the area draining to the strip is small (see “Criteria for Use as Primary Treatment” in Section D.2.1.3). Design and Installation Specifications 1. The vegetated strip shall consist of a 25-foot minimum width continuous strip of dense vegetation with a permeable topsoil. Grass-covered, landscaped areas are generally not adequate because the volume of sediment overwhelms the grass. Ideally, vegetated strips shall consist of undisturbed native growth with a well-developed soil that allows for infiltration of runoff. 2. The slope within the strip shall not exceed 4H:1V. 3. The uphill boundary of the vegetated strip shall be delineated with clearing limits as specified in Section D.2.1.1. Maintenance Standards 1. Any areas damaged by erosion or construction activity shall be seeded immediately and protected by mulch. 2. If more than 5 feet of the original vegetated strip width has had vegetation removed or is being eroded, sod must be installed using the standards for installation found in Section D.2.1.2.7. If there are indications that concentrated flows are traveling across the buffer, surface water controls must be installed to reduce the flows entering the buffer, or additional perimeter protection must be installed. D.2.1.3.4 TRIANGULAR SILT DIKE (GEOTEXTILE ENCASED CHECK DAM) Code: TSD Symbol: Purpose Triangular silt dikes (TSDs) may be used as check dams, for perimeter protection, for temporary soil stockpile protection, for drop inlet protection, or as a temporary interceptor dike. Silt dikes, if attached to impervious surfaces with tack or other adhesive agent may also be used as temporary wheel wash areas, or concrete washout collection areas. Conditions of Use 1. May be used for temporary check dams in ditches. 2. May be used on soil or pavement with adhesive or staples. 3. TSDs have been used to build temporary sediment ponds, diversion ditches, concrete washout facilities, curbing, water bars, level spreaders, and berms. D.2.1 ESC MEASURES 2022 City of Renton Surface Water Design Manual 6/22/2022 D-39 3. Any damage to berms must be repaired immediately. Damage includes flattening, compacting, rills, eroded areas due to overtopping. 4. If concentrated flows are evident uphill of the berm, the flows must be intercepted and conveyed to a sediment trap or pond. 5. The uphill side of the berm shall be inspected for signs of the berm clogging and acting as a barrier to flows and causing channelization of flows parallel to the berm. If this occurs, replace the berm or remove the trapped sediment. 6. Sediment that collects behind the berm must be removed when the sediment is more than 6 inches deep. D.2.1.3.6 COMPOST SOCKS Code: COSO Symbol: Purpose Compost socks reduce the transport of sediment from a construction site by providing a temporary physical barrier to sediment-laden water and reducing the runoff velocities of overland flow. Compost socks trap sediment by filtering water that passes through the sock and allows water to pond behind the sock, creating a settling area for solids. Organic materials in the compost also may reduce metal and petroleum hydrocarbon concentrations in construction runoff. Compost socks function similarly to compost berms; however, because the compost is contained in a mesh tube, they are appropriate for both concentrated flow and sheet flow. Compost socks may be used to channel concentrated flow on hard surfaces. Conditions of Use 1. Compost socks may be used in areas requiring sediment or erosion control where runoff is in the form of sheet flow or in areas that silt fence is normally considered acceptable. Compost socks may also be used in sensitive environmental areas where migration of aquatic life, including turtles, salamanders and other aquatic life may be impeded by the used of silt fence. 2. Compost socks are not intended to treat substantial amounts of overland flow. However, compost socks may be subjected to some ponding and concentrated flows. If intended primarily as a filtration device, the socks should be sized and placed so that flows do not overtop the socks. 3. For purposes of long term sediment control objectives, compost socks may be seeded at the time of installation to create an additional vegetated filtering component. Design and Installation Specifications 1. Compost socks shall be produced using a pneumatic blower hose or equivalent to fill a mesh tube with compost to create a uniform cross-section and berm density. 2. Socks shall be filled so they are firmly – packed yet flexible. Upon initial filling, the socks shall be filled to have a round cross-section. Once placed on the ground, it is recommended to apply weight to the sock to improve contact with the underlying surface. This may cause the sock to assume an oval shape. 3. Compost socks shall be a minimum of 8 inches in diameter. Larger diameter socks are recommended for areas where ponding is expected behind the sock. 4. Compost socks shall not be used on slopes greater than 2H:1V. 5. Compost shall meet criteria in Reference Section 11-C of the SWDM, except for the particle size distribution (see Bullet 7). 6. Compost shall be obtained from a supplier meeting the requirements in Reference Section 11-C. SECTION D.2 GENERAL CSWPP REQUIREMENTS 6/22/2022 2022 City of Renton Surface Water Design Manual D-40 7. Compost particle size distribution shall be as follows: 99% passing a 1-inch sieve, 90% passing a 3/4-inch sieve and a minimum of 70% greater than the 3/8-inch sieve. A total of 98% shall not exceed 3 inches in length. 8. In order to prevent water from flowing around the ends of compost socks, the ends must be pointed upslope so the ends of the socks are at a higher elevation than the remainder of the sock. Maintenance Standards 1. Compost socks shall be regularly inspected to make sure the mesh tube remains undamaged, the socks retain their shape, and allow adequate flow through of surface water. If the mesh tube is torn, it shall be repaired using twine, zip-ties, or wire. Large sections of damaged socks must be replaced. Any damage must be repaired immediately upon discovery of damage. 2. When the sock is no longer needed, the socks shall be cut open and the compost dispersed to be incorporated into the soil or left on top of the soil for final seeding to occur. The mesh material must be disposed of properly as solid waste. If spills of oil, antifreeze, hydraulic fluid, or other equipment fluids have occurred that have saturated the sock, the compost must be disposed of properly as a waste. 3. Sediment must be removed when sediment accumulations are within 3 inches of the top of the sock. D.2.1.4 TRAFFIC AREA STABILIZATION Unsurfaced entrances, roads, and parking areas used by construction traffic shall be stabilized to minimize erosion and tracking of sediment off site. Stabilized construction entrances shall be installed as the first step in clearing and grading. At the City’s discretion, road and parking area stabilization is not required during the dry season (unless dust is a concern) or if the site is underlain by coarse-grained soils. Roads and parking areas shall be stabilized immediately after initial grading. Purpose: The purpose of traffic area stabilization is to reduce the amount of sediment transported off site by construction vehicles and to reduce the erosion of areas disturbed by vehicle traffic. Sediment transported off site onto paved streets is a significant problem because it is difficult to effectively remove, and any sediment not removed ends up in the drainage system. Additionally, sediment on public right-of- way can pose a serious traffic hazard. Construction road and parking area stabilization is important because the combination of wet soil and heavy equipment traffic typically forms a slurry of easily erodible mud. Finally, stabilization also is an excellent form of dust control in the summer months. When to Install: The construction entrance is to be installed as the first step in clearing and grading. Construction road stabilization shall occur immediately after initial grading of the construction roads and parking areas. Measures to Use: There are two types of traffic area stabilization: (1) a stabilized construction entrance and (2) construction road/parking area stabilization. Both measures must be used as specified under Conditions of Use” for each measure. D.2.1.4.1 STABILIZED CONSTRUCTION ENTRANCE Code: CE Symbol: Purpose Construction entrances are stabilized to reduce the amount of sediment transported onto paved roads by motor vehicles or runoff by constructing a stabilized pad of quarry spalls at entrances to construction sites. D.2.1 ESC MEASURES 2022 City of Renton Surface Water Design Manual 6/22/2022 D-41 Conditions of Use Construction entrances shall be stabilized wherever traffic will be leaving a construction site and traveling on paved roads or other paved areas within 1,000 feet of the site. Access and exits shall be limited to one route if possible, or two for linear projects such as roadway where more than one access/exit is necessary for maneuvering large equipment. For residential construction provide stabilized construction entrances for each residence in addition to the main subdivision entrance. Stabilized surfaces shall be of sufficient length/width to provide vehicle access/parking, based on lot size/configuration. Design and Installation Specifications 1. See Figure D.2.1.4.A for details. 2. A separation geotextile shall be placed under the spalls to prevent fine sediment from pumping up into the rock pad. The geotextile shall meet the following standards: Grab Tensile Strength (ASTM D4632) 200 lbs min. Grab Tensile Elongation (ASTM D4632) 30% max.(woven) Puncture Strength (ASTM D6241) 495 lbs min. AOS (ASTM D4751) 20–45 (U.S. standard sieve size) 3. Do not use crushed concrete, cement, or calcium chloride for construction entrance stabilization because these products raise pH levels in stormwater and concrete discharge to surface waters of the State is prohibited. 4. Hog fuel (wood based mulch) may be substituted for or combined with quarry spalls in areas that will not be used for permanent roads. The effectiveness of hog fuel is highly variable, but it has been used successfully on many sites. It generally requires more maintenance than quarry spalls. Hog fuel is not recommended for entrance stabilization in urban areas. The inspector may at any time require the use of quarry spalls if the hog fuel is not preventing sediment from being tracked onto pavement or if the hog fuel is being carried onto pavement. Hog fuel is prohibited in permanent roadbeds because organics in the subgrade soils cause difficulties with compaction. 5. Fencing (see Section D.2.1.1) shall be installed as necessary to restrict traffic to the construction entrance. 6. Whenever possible, the entrance shall be constructed on a firm, compacted subgrade. This can substantially increase the effectiveness of the pad and reduce the need for maintenance. Maintenance Standards 1. Quarry spalls (or hog fuel) shall be added if the pad is no longer in accordance with the specifications. 2. If the entrance is not preventing sediment from being tracked onto pavement, then alternative measures to keep the streets free of sediment shall be used. This may include street sweeping, an increase in the dimensions of the entrance, or the installation of a wheel wash. If washing is used, it shall be done on an area covered with crushed rock, and wash water shall drain to a sediment trap or pond. 3. Any sediment that is tracked onto pavement shall be removed immediately by sweeping. The sediment collected by sweeping shall be removed or stabilized on site. The pavement shall not be cleaned by washing down the street, except when sweeping is ineffective and there is a threat to public safety. If it is necessary to wash the streets, a small sump must be constructed. The sediment would then be washed into the sump where it can be controlled. Wash water must be pumped back onto the site and cannot discharge to systems tributary to surface waters. SECTION D.2 GENERAL CSWPP REQUIREMENTS 6/22/2022 2022 City of Renton Surface Water Design Manual D-42 4. Any quarry spalls that are loosened from the pad and end up on the roadway shall be removed immediately. 5. If vehicles are entering or exiting the site at points other than the construction entrance(s), fencing (see Section D.2.1.1) shall be installed to control traffic. FIGURE D.2.1.4.A SCHEMATIC REPRESENTATION OF A STABILIZED CONSTRUCTION ENTRANCE D.2.1.4.2 CONSTRUCTION ROAD/PARKING AREA STABILIZATION Code: CRS Symbol: Purpose Stabilizing subdivision roads, parking areas and other onsite vehicle transportation routes immediately after grading reduces erosion caused by construction traffic or runoff. Conditions of Use 1. Roads or parking areas shall be stabilized wherever they are constructed, whether permanent or temporary, for use by construction traffic. 2. Fencing (see Section D.2.1.1) shall be installed, if necessary, to limit the access of vehicles to only those roads and parking areas that are stabilized. Design and Installation Specifications 1. A 6-inch depth of 2- to 4-inch crushed rock, gravel base, or crushed surfacing base course shall be applied immediately after grading or utility installation. A 4-inch course of asphalt treated base (ATB) may also be used, or the road/parking area may be paved. It may also be possible to use cement or PER KING COUNTY ROAD DESIGN AND CONSTRUCTION STANDARDS (KCRDCS), DRIVEWAYS SHALL BE PAVED TO EDGE OF R-O-W PRIOR TO INSTALLATION OF THE CONSTRUCTION ENTRANCE TO AVOID DAMAGING OF THE ROADWAY. IT IS RECOMMENDED THAT THE ENTRANCE BE CROWNED SO THAT RUNOFF DRAINS OFF THE PAD. 12" MIN. THICKNESS PROVIDE FULL WIDTH OF INGRESS/EGRESS AREA IF A ROADSIDE DITCH IS PRESENT, INSTALL DRIVEWAY CULVERT PER KCRDCS GEOTEXTILE 4"- 8" QUARRY SPALLS R=25' MIN.100' MIN. E X I S T IN G R O A D 1 5 ' M I N . NOTES: D.2.1 ESC MEASURES 2022 City of Renton Surface Water Design Manual 6/22/2022 D-43 calcium chloride for soil stabilization. If the area will not be used for permanent roads, parking areas, or structures, a 6-inch depth of hog fuel may also be used, but this is likely to require more maintenance. Whenever possible, construction roads and parking areas shall be placed on a firm, compacted subgrade. Note: If the area will be used for permanent road or parking installation later in the project, the subgrade will be subject to inspection. 2. Temporary road gradients shall not exceed 15 percent. Roadways shall be carefully graded to drain transversely. Drainage ditches shall be provided on each side of the roadway in the case of a crowned section, or on one side in the case of a super-elevated section. Drainage ditches shall be designed in accordance with the standards given in Section D.2.1.6.4 and directed to a sediment pond or trap. 3. Rather than relying on ditches, it may also be possible to grade the road so that runoff sheet-flows into a heavily vegetated area with a well-developed topsoil. Landscaped areas are not adequate. If this area has at least 50 feet of vegetation, then it is generally preferable to use the vegetation to treat runoff, rather than a sediment pond or trap. The 50 feet shall not include vegetated wetlands. If runoff is allowed to sheet flow through adjacent vegetated areas, it is vital to design the roadways and parking areas so that no concentrated runoff is created. 4. In order to control construction traffic, the City may require that signs be erected on site informing construction personnel that vehicles, other than those performing clearing and grading, are restricted to stabilized areas. 5. If construction roads do not adequately reduce trackout to adjacent property or roadways, a wheel wash system will be required. Maintenance Standards Crushed rock, gravel base, hog fuel, etc., shall be added as required to maintain a stable driving surface and to stabilize any areas that have eroded. D.2.1.4.3 WHEEL WASH Code: WW Symbol: Purpose Wheel wash systems reduce the amount of sediment transported onto paved roadways and into surface water systems by construction vehicles. Conditions of Use When a stabilized construction entrance is not preventing sediment from being tracked onto pavement: Wheel washing is generally an effective erosion and sediment control method and BMP when installed with careful attention to topography. For example, a wheel wash can be detrimental if installed at the top of a slope abutting a right-of-way where the water from the dripping truck wheels and undercarriage can run unimpeded into the street. Pressure washing combined with an adequately sized and properly surfaced wash pad with direct drainage discharge to a large 10-foot x 10-foot sump can be very effective. Design and Installation Specifications A suggested detail is shown in Figure D.2.1.4.B. 1. A minimum of 6 inches of asphalt treated base (ATB) over crushed base material or 8 inches over a good subgrade is recommended to pave the wheel wash area. 2. Use a low clearance truck to test the wheel wash before paving. Either a belly dump or lowboy will work well to test clearance. SECTION D.2 GENERAL CSWPP REQUIREMENTS 6/22/2022 2022 City of Renton Surface Water Design Manual D-46 D.2.1.5 SEDIMENT RETENTION Surface water collected from disturbed areas of the site shall be routed through a sediment pond or trap prior to release from the site. An exception is for areas at the perimeter of the site with drainage areas small enough to be treated solely with perimeter protection (see Section D.2.1.3). Also, if the soils and topography are such that no offsite discharge of surface water is anticipated up to and including the developed 2-year runoff event, sediment ponds and traps are not required. A 10-year peak flow using the approved model with 15-minute time steps shall be used for sediment pond/trap sizing if the project size, expected timing and duration of construction, or downstream conditions warrant a higher level of protection (see below). At the City’s discretion, sites may be worked during the dry season without sediment ponds and traps if there is some other form of protection of surface waters, such as a 100-foot forested buffer between the disturbed areas and adjacent surface waters. For small sites, use the criteria defined in Section D.2.1.3, Perimeter Protection to determine minimum flow path length. If the site work has to be extended into the wet season, a back-up plan must be identified in the CSWPP plan and implemented. Protection of catch basins is required for inlets that are likely to be impacted by sediment generated by the project and that do not drain to an onsite sediment pond or trap. Sediment retention facilities shall be installed prior to grading of any contributing area and shall be located so as to avoid interference with the movement of juvenile salmonids attempting to enter off-channel areas or drainages. Purpose: The purpose of sediment retention facilities is to remove sediment from runoff generated from disturbed areas. When to Install: The facilities shall be constructed as the first step in the clearing and grading of the site. The surface water conveyances may then be connected to the facilities as site development proceeds. Measures to Use: There are three sediment retention measures in this section. The first two, sediment traps and ponds, serve the same function but for different size catchments. All runoff from disturbed areas must be routed through a trap or pond except for very small areas at the perimeter of the site small enough to be treated solely with perimeter protection (see Section D.2.1.3). The third measure is for catch basin protection. It is only to be used in limited circumstances and is not a primary sediment treatment facility. It is only intended as a backup in the event of failure of other onsite systems. Use of Permanent Drainage Facilities: All projects that are constructing permanent facilities for runoff quantity control are strongly encouraged to use the rough-graded or final-graded permanent facilities for ponds and traps. This includes combined facilities and infiltration facilities. When permanent facilities are used as temporary sedimentation facilities, the surface area requirements of sediment traps (for drainages less than 3 acres) or sediment ponds (more than 3 acres) must be met. If the surface area requirements are larger than the surface area of the permanent facility, then the pond shall be enlarged to comply with the surface area requirement. The permanent pond shall also be divided into two cells as required for sediment ponds. Either a permanent control structure or the temporary control structure described in Section D.2.1.5.2 may be used. If a permanent control structure is used, it may be advisable to partially restrict the lower orifice with gravel to increase residence time while still allowing dewatering of the pond. If infiltration facilities are to be used, the sides and bottom of the facility must only be rough excavated to a minimum of three feet above final grade. Excavation should be done with a backhoe working at “arm’s length” to minimize disturbance and compaction of the infiltration surface. Additionally, any required pretreatment facilities shall be fully constructed prior to any release of sediment-laden water to the facility. Pretreatment and shallow excavation are intended to prevent the clogging of soil with fines. Final grading of the infiltration facility shall occur only when all contributing drainage areas are fully stabilized (see Section D.2.4.5). Selection of the Design Storm: In most circumstances, the developed condition 2-year peak flow using the approved model with 15-minute time steps is sufficient for calculating surface area for ponds and traps and for determining exemptions from the sediment retention and surface water collection requirements Sections D.2.1.5 and D.2.1.6, respectively). In some circumstances, however, the approved model 10-year 15-minute peak flow should be used. Examples of such circumstances include the following: D.2.1 ESC MEASURES 2022 City of Renton Surface Water Design Manual 6/22/2022 D-47 Sites that are within ¼ mile of salmonid streams, wetlands, and designated sensitive lakes such as Lake Sammamish Sites where significant clearing and grading is likely to occur during the wet season Sites with downstream erosion or sedimentation problems. Natural Vegetation: Whenever possible, sediment-laden water shall be discharged into onsite, relatively level, vegetated areas. This is the only way to effectively remove fine particles from runoff. This can be particularly useful after initial treatment in a sediment retention facility. The areas of release must be evaluated on a site-by-site basis in order to determine appropriate locations for and methods of releasing runoff. Vegetated wetlands shall not be used for this purpose. Frequently, it may be possible to pump water from the collection point at the downhill end of the site to an upslope vegetated area. Pumping shall only augment the treatment system, not replace it because of the possibility of pump failure or runoff volume in excess of pump capacity. D.2.1.5.1 SEDIMENT TRAP Code: ST Symbol: Purpose Sediment traps remove sediment from runoff originating from disturbed areas of the site. Sediment traps are typically designed to only remove sediment as small as medium silt (0.02 mm). As a consequence, they usually only result in a small reduction in turbidity. Conditions of Use A sediment trap shall be used where the contributing drainage area is 3 acres or less. Design and Installation Specifications 1. See Figure D.2.1.5.A for details. 2. If permanent runoff control facilities are part of the project, they should be used for sediment retention see “Use of Permanent Drainage Facilities” in Section D.2.1.5). 3. To determine the trap geometry, first calculate the design surface area (SA) of the trap, measured at the invert of the weir. Use the following equation: SA = FS(Q2/Vs) where Q2 = Design inflow (cfs) from the contributing drainage area based on the developed condition 2-year or 10-year peak discharge using the approved model with 15-minute time steps as computed in the hydrologic analysis. The approved model 10-year 15-minute peak flow shall be used if the project size, expected timing and duration of construction, or downstream conditions warrant a higher level of protection, or if the pond discharge path leaves the site (note provisions must made to prevent increases in the existing site conditions 2-year and 10-year runoff peaks discharging from the project site during construction, see Section D.3.9, Flow Control). If no hydrologic analysis is required, the Rational Method may be used (Section 3.2.1 of the SWDM). Vs = The settling velocity (ft/sec) of the soil particle of interest. The 0.02 mm (medium silt) particle with an assumed density of 2.65 g/cm3 has been selected as the particle of interest and has a settling velocity (Vs) of 0.00096 ft/sec. FS = A safety factor of 2 to account for non-ideal settling. Therefore, the equation for computing surface area becomes: SA = 2 x Q2/0.00096 or 2080 square feet per cfs of inflow SECTION D.2 GENERAL CSWPP REQUIREMENTS 6/22/2022 2022 City of Renton Surface Water Design Manual D-52 FIGURE D.2.1.5.D SEDIMENT POND RISER DETAIL D.2.1.5.3 STORM DRAIN INLET PROTECTION Code: FFP or CBI or CBP Symbol: or or Purpose Storm drain inlets are protected to prevent coarse sediment from entering storm drainage systems. Temporary devices around storm drains assist in improving the quality of water discharged to inlets or catch basins by ponding sediment-laden water. These devices are effective only for relatively small drainage areas. Conditions of Use 1. Protection shall be provided for all storm drain inlets downslope and within 500 feet of a disturbed or construction area, unless the runoff that enters the catch basin will be conveyed to a sediment pond or trap. 2. Inlet protection may be used anywhere at the applicant’s discretion to protect the drainage system. This will, however, require more maintenance, and it is highly likely that the drainage system will still require some cleaning. 3. The contributing drainage area must not be larger than one acre. Design and Installation Specifications 1. There are many options for protecting storm drain inlets. Two commonly used options are filter fabric protection and catch basin inserts. Filter fabric protection (see Figure D.2.1.5.E) is filter fabric geotextile) placed over the grate. This method is generally very ineffective and requires intense maintenance efforts. Therefore, filter fabric protection is not allowed in the City of Renton. Catch basin inserts (see Figure D.2.1.5.F) are manufactured devices that nest inside a catch basin. This method also requires a high frequency of maintenance to be effective. 3.5' MIN. 18" MIN. 2X RISER DIA. MIN. CORRUGATED METAL RISER CONCRETE BASE ALTERNATIVELY, METAL STAKES AND WIRE MAY BE USED TO PREVENT FLOTATION DEWATERING ORIFICE, SCHEDULE 40 STEEL STUB MIN. DIAMETER AS PER CALCULATIONS 6" MIN. PROVIDE ADEQUATE STRAPPING POLYETHYLENE CAP PERFORATED DEWATERING DEVICE, SEE NOTE WATERTIGHT COUPLING TACK WELD NOTE: PERFORATED CORRUGATED POLYETHYLENE (CPE) DRAINAGE TUBING, DIAMETER MIN. 2" LARGER THAN DEWATERING ORIFICE. TUBING SHALL COMPLY WITH ASTM F667 AND AASHTO M294. D.2.1 ESC MEASURES 2022 City of Renton Surface Water Design Manual 6/22/2022 D-53 Trapping sediment in the catch basins is unlikely to improve the water quality of runoff if it is treated in a pond or trap because the coarse particles that are trapped at the catch basin settle out very quickly in the pond or trap. Catch basin protection normally only improves water quality where there is no treatment facility downstream. In these circumstances, catch basin protection is an important last line of defense. It is not, however, a substitute for preventing erosion. 2. It is sometimes possible to construct a small sump around the catch basin before final surfacing of the road. This is allowed because it can be a very effective method of sediment control. 3. Block and gravel filters, gravel and wire mesh filter barriers, and bag barriers filled with various filtering media placed around catch basins can be effective when the drainage area is 1 acre or less and flows do not exceed 0.5 cfs. It is necessary to allow for overtopping to prevent flooding. Many manufacturers have various inlet protection filters that are very effective in keeping sediment-laden water from entering the storm drainage system. The following are examples of a few common methods. a) Block and gravel filters (Figure D.2.1.5.G) are a barrier formed around an inlet with standard concrete block and gravel, installed as follows: Height is 1 to 2 feet above the inlet. Recess the first row of blocks 2 inches into the ground for stability. Support subsequent rows by placing a 2x4 through the concrete block opening. Do not use mortar. Lay some blocks in the bottom row on their side for dewatering the pooled water. Place cloth or mesh with ½ inch openings over all block openings. Place gravel below the top of blocks on slopes of 2:1 or flatter. An alternate design is a gravel donut. b) Gravel and wire mesh filters consist of a gravel barrier placed over the top of an inlet. This structure generally does not provide overflow. Install as follows: Cloth or comparable wire mesh with ½ inch openings is placed over inlet. Coarse aggregate covers the cloth or mesh. Height/depth of gravel should be 1 foot or more, 18 inches wider than inlet on all sides. c) Curb inlet protection with a wooden weir is a barrier formed around an inlet with a wooden frame and gravel, installed as follows: Construct a frame and attach wire mesh (½ inch openings) and filter fabric to the frame. Pile coarse washed aggregate against the wire/fabric. Place weight on frame anchors. d) Curb and gutter sediment barriers (Figure D.2.1.5.H) consist of sandbags or rock berms (riprap and aggregate) 3 feet high and 3 feet wide in a horseshoe shape, installed as follows: Bags of either burlap or woven geotextile fabric, filled with a variety of media such as gravel, wood chips, compost or sand stacked tightly allows water to pond and allows sediment to separate from runoff. Leave a “one bag gap” in the top row of the barrier to provide a spillway for overflow. Construct a horseshoe shaped berm, faced with coarse aggregate if using riprap, 3 x 3 and at least 2 feet from the inlet. Construct a horseshoe shaped sedimentation trap on the outside of the berm to sediment trap standards for protecting a culvert inlet. SECTION D.2 GENERAL CSWPP REQUIREMENTS 6/22/2022 2022 City of Renton Surface Water Design Manual D-54 4. Excavated drop inlet sediment traps are appropriate where relatively heavy flows are expected and overflow capability is needed. If emergency overflow is provided, additional end-of-pipe treatment may be required. Excavated drop inlets consist of an excavated impoundment area around a storm drain. Sediment settles out of the stormwater prior to enter the drain. Install according to the following specifications: a) The impoundment area should have a depth of 1 to 2 feet measured from the crest of the inlet structure. b) Side slopes of the excavated area must be no steeper than 2:1. c) Minimum volume of the excavated area should be 35 cubic yards. d) Install provisions for draining the area to prevent standing water problems. e) Keep the area clear of debris. f) Weep holes may be drilled into the side of the inlet. g) Protect weep holes with wire mesh and washed aggregate. h) Weep holes must be sealed when removing and stabilizing excavated area. i) A temporary dike may be necessary on the down slope side of the structure to prevent bypass flow. Maintenance Standards 1. Any accumulated sediment on or around inlet protection shall be removed immediately. Sediment shall not be removed with water, and all sediment must be disposed of as fill on site or hauled off site. 2. Any sediment in the catch basin insert shall be removed when the sediment has filled one-third of the available storage. The filter media for the insert shall be cleaned or replaced at least monthly. 3. Regular maintenance is critical for all forms of catch basin/inlet protection. Unlike many forms of protection that fail gradually, catch basin protection will fail suddenly and completely if not maintained properly. D.2.1 ESC MEASURES 2022 City of Renton Surface Water Design Manual 6/22/2022 D-55 FIGURE D.2.1.5.E FILTER FABRIC PROTECTION (NOT ALLOWED) FIGURE D.2.1.5.F CATCH BASIN INSERT CATCH BASIN NOTE: ONLY TO BE USED WHERE PONDING OF WATER ABOVE THE CATCH BASIN WILL NOT CAUSE TRAFFIC PROBLEMS AND WHERE OVERFLOW WILL NOT RESULT IN EROSION OF SLOPES. GRATE STANDARD STRENGTH FILTER FABRIC NOTE: THIS DETAIL IS ONLY SCHEMATIC. ANY INSERT IS ALLOWED THAT HAS: A MIN. 0.5 C.F. OF STORAGE, THE MEANS TO DEWATER THE STORED SEDIMENT, AN OVERFLOW, AND CAN BE EASILY MAINTAINED. OVERFLOW GRATECATCHBASIN POROUS BOTTOM SOLID WALLS FILTER MEDIA FOR DEWATERING SECTION D.2 GENERAL CSWPP REQUIREMENTS 6/22/2022 2022 City of Renton Surface Water Design Manual D-56 FIGURE D.2.1.5.G BLOCK AND GRAVEL CURB INLET PROTECTION 1. USE BLOCK AND GRAVEL TYPE SEDIMENT BARRIER WHEN CURB INLET IS LOCATED IN GENTLY SLOPING SEGMENT, WHERE WATER CAN POND AND ALLOW SEDIMENT TO SEPARATE FROM RUNOFF. 2. BARRIER SHALL ALLOW FOR OVERFLOW FROM SEVERE STORM EVENT. 3. INSPECT BARRIERS AND REMOVE SEDIMENT AFTER EACH STORM EVENT. SEDIMENT AND GRAVEL MUST BE REMOVED FROM THE TRAVELED WAY IMMEDIATELY. 2x4 WOOD STUD OVERFLOW WATER A A PLAN VIEW NTS SECTION A-A NTS BLOCK AND GRAVEL CURB INLET PROTECTION NTS CATCH BASIN COVER CURB INLET CONCRETE BLOCKS CATCH BASIN COVER CURB INLET CATCH BASIN BACK OF SIDEWALK CURB FACE 3/4" DRAIN GRAVEL (20 mm) WIRE SCREEN OR FILTER FABRIC POND HEIGHT WIRE SCREEN OR FILTER FABRIC 2x4 WOOD STUD 100x50 TIMBER STUD) 3/4" DRAIN GRAVEL (20 mm) NOTES: D.2.1 ESC MEASURES 2022 City of Renton Surface Water Design Manual 6/22/2022 D-57 FIGURE D.2.1.5.H CURB AND GUTTER BARRIER PROTECTION RUNOFF RUNOFF SPILLWAY 1. PLACE CURB-TYPE SEDIMENT BARRIERS ON GENTLY SLOPING STREET SEGMENTS, WHERE WATER CAN POND AND ALLOW SEDIMENT TO SEPARATE FROM RUNOFF. 2. SANDBAGS OF EITHER BURLAP OR WOVEN GEOTEXTILE FABRIC ARE FILLED WITH GRAVEL, LAYERED AND PACKED TIGHTLY. 3. LEAVE A ONE-SANDBAG GAP IN THE TOP ROW TO PROVIDE A SPILLWAY FOR OVERFLOW. 4. INSPECT BARRIERS AND REMOVE SEDIMENT AFTER EACH STORM EVENT. SEDIMENT AND GRAVEL MUST BE REMOVED FROM THE TRAVELED WAY IMMEDIATELY. GRAVEL FILLED SANDBAGS STACKED TIGHTLY DRAIN GRATE GUTTER CURB FACE CURB INLET SANDBAGS TO OVERLAP ONTO CURB BACK OF SIDEWALK PLAN VIEW NTS CURB AND GUTTER BARRIER NTS NOTES: SECTION D.2 GENERAL CSWPP REQUIREMENTS 6/22/2022 2022 City of Renton Surface Water Design Manual D-58 D.2.1.6 SURFACE WATER COLLECTION All surface water from disturbed areas shall be intercepted, conveyed to a sediment pond or trap, and discharged downslope of any disturbed areas. An exception is for areas at the perimeter of the site with drainage areas small enough to be treated solely with perimeter protection (see Section D.2.1.3). Also, if the soils and topography are such that no offsite discharge of surface water is anticipated up to and including the developed 2-year runoff event, surface water controls are not required. A 10-year approved model 15-minute peak flow shall be used for sizing surface water controls if the project size, expected timing and duration of construction, or downstream conditions warrant a higher level of protection (see the introduction to Section D.2.1.5). At the City’s discretion, sites may be worked during the dry season without surface water controls, if there is some other form of protection of surface waters, such as a 100-foot forested buffer between the disturbed areas and adjacent surface waters. Significant sources of upslope surface water that drain onto disturbed areas shall be intercepted and conveyed to a stabilized discharge point downslope of the disturbed areas. Surface water controls shall be installed concurrently with rough grading. Purpose: The purpose of surface water control is to collect and convey surface water so that erosion is minimized, and runoff from disturbed areas is treated by a sediment pond or trap. Surface water control essentially consists of three elements: 1. Interception of runoff on and above slopes 2. Conveyance of the runoff to a sediment pond or trap (if the runoff was collected from a disturbed area) 3. Release of the runoff downslope of any disturbed areas. When to Install: Surface water controls shall be constructed during the initial grading of an area and must be in place before there is any opportunity for storm runoff to cause erosion. Measures to Install: Interceptor dikes/swales intercept runoff, ditches and pipe slope drains convey the runoff, and riprap or level spreaders help release the runoff in a non-erosive manner. Each measure is to be used under different circumstances so there is very little overlap. However, the two options for releasing water in a non-erosive manner, outlet protection and level spreaders, can be somewhat interchangeable. See Figure D.2.1.6.A for a schematic drawing demonstrating the use of these measures. SECTION D.2 GENERAL CSWPP REQUIREMENTS 6/22/2022 2022 City of Renton Surface Water Design Manual D-66 FIGURE D.2.1.6.F LEVEL SPREADER D.2.1.7 DEWATERING CONTROL Any runoff generated by dewatering shall be treated through construction of a sediment trap Section D.2.1.5.1) when there is sufficient space or by releasing the water to a well vegetated, gently sloping area. Since pumps are used for dewatering, it may be possible to pump the sediment-laden water well away from the surface water so that vegetation can be more effectively utilized for treatment. Discharge of sediment-laden water from dewatering activities to surface and storm waters is prohibited. If dewatering occurs from areas where the water has come in contact with new concrete, such as tanks, vaults, or foundations, the pH of the water must be monitored and must be neutralized prior to discharge. Clean non-turbid dewatering water, such as well point ground water can be discharged to systems tributary to, or directly to surface waters provided the flows are controlled so no erosion or flooding occurs. Clean water must not be routed through a stormwater sediment pond. Highly turbid or contaminated dewatering water must be handled separately from stormwater. Purpose: To prevent the untreated discharge of sediment-laden water from dewatering of utilities, excavated areas, foundations, etc. When to Install: Dewatering control measures shall be used whenever there is a potential for runoff from dewatering of utilities, excavations, foundations, etc. Measures to install: 1. Foundation, vault, excavation, and trench dewatering water that has similar characteristics to stormwater runoff at the site shall be discharged into a controlled conveyance system prior to discharge to a sediment trap or sediment pond. Foundation and trench dewatering water that has similar characteristics to stormwater runoff at the site must be disposed of through one of the following options depending on site constraints: a) Infiltration, b) Transport offsite in a vehicle, such as a vacuum flush truck, for legal disposal in a manner that does not pollute surface waters, SPREADER MUST BE LEVEL 18" MIN. REBAR SUPPORTS 8' MIN. SPACING CROSS SECTION DETAIL OF SPREADER DENSELY VEGETATED FOR A MIN. OF 100' AND SLOPE LESS THAN 5:1 PRESSURE-TREATED 2"X10" 3' MIN. TREATED 2"x10" MAY BE ABUTTED END TO END FOR MAX. SPREADER LENGTH OF 50' 6" MIN. 6" MIN. 1" MIN. 2H:1VMAX. 1' MIN. D.2.1 ESC MEASURES 2022 City of Renton Surface Water Design Manual 6/22/2022 D-67 c) Discharge to the sanitary sewer discharge with approval from King County and the City of Renton if there is no other option, or d) Use of a sedimentation bag with outfall to a ditch or swale for small volumes of localized dewatering. 2. Clean, non-turbid dewatering water, such as well-point ground water, may be discharged via stable conveyance to systems tributary to surface waters, provided the dewatering flow does not cause erosion or flooding of receiving waters. 3. Highly turbid or contaminated dewatering water (high pH or other) shall be handled separately from stormwater. See Section D.2.2 , SWPPS Measures. D.2.1.8 DUST CONTROL Preventative measures to minimize the wind transport of soil shall be taken when a traffic hazard may be created or when sediment transported by wind is likely to be deposited in water resources or adjacent properties. Purpose: To prevent wind transport of dust from exposed soil surfaces onto roadways, drainage ways, and surface waters. When to Install: Dust control shall be implemented when exposed soils are dry to the point that wind transport is possible and roadways, drainage ways, or surface waters are likely to be impacted. Dust control measures may consist of chemical, structural, or mechanical methods. Measures to Install: Water is the most common dust control (or palliative) used in the area. When using water for dust control, the exposed soils shall be sprayed until wet, but runoff shall not be generated by spraying. Calcium chloride, Magnesium chloride, Lignin derivatives, Tree Resin Emulsions, and Synthetic Polymer Emulsions may also be used for dust control. Exposed areas shall be re-sprayed as needed. Oil shall not be used for dust control. The following table lists many common dust control measures. Some of the measures are not recommended for use in the City and must have prior approval prior to use from the CED inspector assigned to specific projects. TABLE D.2.1.8.A DUST CONTROL MEASURES Method Considerations Site Preparation Recommended Application Rate Water -Most commonly used practice Evaporates quickly Lasts less than 1 day For all liquid agents: Blade a small surface Crown or slope surface to avoid ponding Compact soils if needed Uniformly pre-wet at 0.03 – 0.3 gal/sq yd Apply solution under pressure. Overlap solution 6 – 12 inches Allow treated area to cure 0 – 4 hours Compact area after curing Apply second treatment before first treatment becomes ineffective 0.125 gal/sq yd every 20 to 30 minutes Salts Calcium Chloride CaCl) Restricts evaporation Lasts 6–12 months Can be corrosive Less effective in low humidity Can build up in soils and leach by rain Apply 38% solution at 1.21L/m2 (0.27 gal/yd2) or as loose dry granules per manufacturer SECTION D.2 GENERAL CSWPP REQUIREMENTS 6/22/2022 2022 City of Renton Surface Water Design Manual D-68 TABLE D.2.1.8.A DUST CONTROL MEASURES Method Considerations Site Preparation Recommended Application Rate Magnesium Chloride MgCl) Restricts evaporation Works at higher temperatures and lower humidity than CaCl May be more costly than CaCl Apply 26 – 32% solution at 2.3 L/m2 0.5 gal/yd2) Sodium Chloride NaCl) Effective over smaller range of conditions Less expensive Can be corrosive Less effective in low humidity Per Manufacturer Silicates -Generally expensive Available in small quantities Require Second application Surfactants -High evaporation rates Effective for short time periods Must apply frequently Copolymers -Forms semi-permeable transparent crust Resists ultraviolet radiation and moisture induced breakdown Last 1 to 2 years 750 – 940 L/ha (80 – 100 gal/ac) Petroleum Products Used oil is prohibited as a dust control method Bind soil particles May hinder foliage growth Environmental and aesthetic concerns Higher cost Use 57 – 63% resins as base. Apply at 750 – 940 L/ha 80–100 gal/ac) Lignin Sulfonate Paper industry waste product Acts as dispersing agent Best in dry climates Can be slippery Will decrease Dissolved Oxygen in waterways therefore cannot be used adjacent to surface water systems Loosen surface 25–50 mm (1–2 inches) Need 4–8% fines Vegetable Oils Coat grains of soils, so limited binding ability May become brittle Limited availability Per Manufacturer Spray on Adhesives Available as organic or synthetic Effective on dry, hard soils Forms a crust Can last 3 to 4 years Per Manufacturer D.2.1.9 FLOW CONTROL Surface water from disturbed areas must be routed through the project’s onsite flow control facility or other provisions must made to prevent increases in the existing site conditions 2-year and 10-year runoff peaks discharging from the project site during construction. Purpose: The purpose of surface water flow control is to mitigate increases in runoff peaks that occur during construction as a result of clearing vegetation, compacting the soil, and adding impervious surface. Such increases can cause or aggravate downstream flooding and erosion. D.2.1 ESC MEASURES 2022 City of Renton Surface Water Design Manual 6/22/2022 D-69 When to Install: Surface water flow control shall be installed or otherwise provided prior to any clearing and/or grading of the site, except that required to construct the surface water flow control facilities. Measures to Use: The project’s onsite flow control facility or other equivalent storage facility that meets the peak-matching performance criteria stated above. D.2.1.10 PROTECT EXISTING AND PROPOSED STORMWATER FACILITIES AND ON-SITE BMPS Protection measures shall be applied/installed and maintained so as to prevent adverse impacts to existing stormwater facilities and on-site BMPs and areas of proposed stormwater facilities and on-site BMPs for the project. Adverse impacts can prompt the requirement to restore or replace affected stormwater facilities and on-site BMPs. Purpose: The purpose of protecting existing and proposed stormwater facility and on-site BMP areas is to avoid sedimentation and soil compaction that would adversely affect infiltration, and also avoid contamination by other pollutants. When to Install: Stormwater facility and on-site BMP area protection shall be installed or otherwise provided prior to any clearing and/or grading of the site, except that required to construct stormwater facilities and on-site BMPs. Measures to Use: 1. Protect all stormwater facilities and on-site BMPs and proposed stormwater facility and on-site BMP footprints from sedimentation through installation and maintenance of erosion and sediment control BMPs on portions of the site that drain into the BMPs/facilities. 2. Stormwater facilities and on-site BMPs shall be restored to their fully functioning condition if they accumulate sediment during construction. Restoring the stormwater facilities and on-site BMPs shall include, at a minimum, removal of sediment and any sediment-laden bioretention soils, and replacing the removed soils with soils meeting the design specification. Replacement with a new fully- functioning stormwater facility and/or on-site BMP may be required if restoration to the fully- functioning condition can’t be accomplished. 3. Prevent compacting Bioretention BMPs/facilities by excluding construction equipment and foot traffic. Protect completed lawn and landscaped areas from compaction due to construction equipment. 4. Control erosion and avoid introducing sediment from surrounding land uses onto permeable pavement BMPs. Do not allow muddy construction equipment on the base material or pavement. Do not allow sediment-laden runoff onto permeable pavements. 5. Permeable pavement BMPs fouled with sediments or no longer passing an initial infiltration text must be cleaned using procedures from Appendix A or the manufacturer’s procedures. 6. Keep all heavy equipment off existing soils under stormwater facilities and on-site BMPs that have been excavated to final grade to retain the infiltration rate of the soils. D.2.1.11 MAINTAIN PROTECTIVE BMPS Protection measures shall be maintained to ensure continued performance of their intended function, to prevent adverse impacts to existing stormwater facilities and on-site BMPs and areas of proposed BMPs/facilities, and protect other disturbed areas of the project. Purpose: The purpose of maintaining protective BMPs is to provide continuous erosion and sediment control protection throughout the life of the project, and avoid sedimentation, soil compaction and contamination by other pollutants that would adversely affect infiltration and surface runoff. SECTION D.2 GENERAL CSWPP REQUIREMENTS 6/22/2022 2022 City of Renton Surface Water Design Manual D-70 When to Maintain: Protection measures shall be monitored per Section D.2.4.4 at a minimum, and promptly maintained to fully functioning condition as necessary to ensure continued performance of their intended function. Measures to Use: 1. Maintain and repair all temporary and permanent erosion and sediment control BMPs as needed to ensure continued performance of their intended function in accordance with BMP specifications. 2. Remove all temporary erosion and sediment control BMPs prior to final construction approval, or within 30 days after achieving final site stabilization or after the temporary BMPs are no longer needed. 3. Provide protection to all stormwater facilities and on-site BMPs installed for the permanent control of stormwater from sediment and compaction. All stormwater facilities and on-site BMPs that are to remain in place following completion of construction shall be examined and placed in full operating conditions. If sediment enters the stormwater facilities and/or on-site BMPs during construction, it shall be removed and the stormwater facility and on-site BMP shall be returned to the conditions specified in the construction documents or as required for full stormwater facility and on-site BMP replacement. 4. Remove or stabilize trapped sediment on site. Permanently stabilize disturbed soil resulting from removal of erosion and sediment control BMPs or vegetation. D.2.1.12 MANAGE THE PROJECT Coordination and timing of site development activities relative to ESC concerns (Section D.2.4), and timely inspection, maintenance and update of protective measures (Section D.2.3) are necessary to effectively manage the project and ensure the success of protective ESC and SWPPS design and implementation. Projects shall assign a qualified CSWPP Supervisor (Section D.2.3.1) to be the primary contact for ESC and SWPPP issues and reporting, coordination with subcontractors and implementation of the CSWPP plan as a whole. Measures to Use: 1. Phase development projects to the maximum degree practicable and take into account seasonal work limits. 2. Inspection and monitoring – Inspect, maintain, and repair all BMPs as needed to ensure continued performance of their intended function. Conduct site inspections and monitoring in accordance with the Construction Stormwater General Permit and City requirements. 3. Maintaining an updated construction SWPPP – Maintain, update, and implement the SWPPP in accordance with the Construction Stormwater General Permit and City requirements. 4. Projects that disturb one or more acres must have, site inspections conducted by a Certified Erosion and Sediment Control Lead (CESCL) (see Section D.2.3.1). Project sites less than one acre (not part of a larger common plan of development or sale) may have a person without CESCL certification conduct inspections. By the initiation of construction, the SWPPP must identify the CESCL or inspector, who shall be present onsite or on-call at all times. The CESCL or inspector (project sites less than one acre) must have the skills to assess the: Site conditions and construction activities that could impact the quality of stormwater. Effectiveness of erosion and sediment control measures used to control the quality of stormwater discharges. The CESCL or inspector must examine stormwater visually for the presence of suspended sediment, turbidity, discoloration, and oil sheen. They must evaluate the effectiveness of BMPs and determine if it is necessary to install, maintain, or repair BMPs to improve the quality of stormwater discharges. D.2.2 SWPPS MEASURES 2022 City of Renton Surface Water Design Manual 6/22/2022 D-71 Based on the results of the inspection, construction site operators must correct the problems identified by: Reviewing the SWPPP for compliance with all construction SWPPP elements and making appropriate revisions within 7 days of the inspection. Immediately beginning the process of fully implementing and maintaining appropriate source control and/or treatment BMPs as soon as possible, addressing the problems not later than within 10 days of the inspection. If installation of necessary treatment BMPs is not feasible within 10 days, the construction site operator may request an extension within the initial 10-day response period. Documenting BMP implementation and maintenance in the site log book (applies only to sites that have coverage under the Construction Stormwater General Permit). The CESCL or inspector must inspect all areas disturbed by construction activities, all BMPs, and all stormwater discharge points at least once every calendar week and within 24 hours of any discharge from the site. (For purposes of this condition, individual discharge events that last more than one day do not require daily inspections. For example, if a stormwater pond discharges continuously over the course of a week, only one inspection is required that week.) The CESCL or inspector may reduce the inspection frequency for temporary stabilized, inactive sites to once every calendar month. D.2.2 SWPPS MEASURES This section details the SWPPS measures that are required to prevent, reduce, or eliminate the discharge of pollutants to onsite or adjacent stormwater systems or watercourses from construction-related activities such as materials delivery and storage, onsite equipment fueling and maintenance, demolition of existing buildings and disposition of demolition materials and other waste, and concrete handling, washout and disposal. These SWPPS measures represent Best Management Practices (BMPs)8 for the control of pollutant drips and spills as well as other impacts related to construction such as increased pH in concrete construction and handling activities. Compliance with each of the SWPPS measures, and with any project- specific control measures, to the extent applicable and necessary to meet the performance criteria in Section D.2.2, and compliance with the CSWPP implementation requirements in Section D.2.4, constitutes overall compliance with the City’s CSWPP Standards. Note: Additional measures shall be required by the City if the existing standards are insufficient to protect adjacent properties, drainage facilities, or water resources. The standards for each individual SWPPS measure are divided into four sections: 1. Purpose 2. Conditions of Use 3. Design and Installation Specifications 4. Maintenance Requirements. Note that the “Conditions of Use” always refers to site conditions. As site conditions change, SWPPS measures must be changed to remain in compliance with the requirements of this appendix. Whenever compliance with City SWPPS Standards is required, all of the following SWPPS measures must be considered for application to the project site as detailed in the following sections. The construction pollutant generating concerns addressed by the BMPs that follow include: Concrete handling, washout and disposal(specifically portland cement concrete) Sawcutting and surfacing activities Materials delivery, storage and containment 8 Best Management Practices (BMPs) means the best available and reasonable physical, structural, managerial, or behavioral activities, that when singly or in combination, eliminate or reduce the contamination of surface and/or ground waters. SECTION D.2 GENERAL CSWPP REQUIREMENTS 6/22/2022 2022 City of Renton Surface Water Design Manual D-72 Filtration and chemical treatment of construction water to facilitate disposal or discharge to approved locations Reporting requirements and documentation availability for specific BMP processes Additionally, several of the ESC BMPs described in Section D.2.1 can be applicable to the SWPPS plan, e.g., use of cover, fencing and access protection to protect temporary materials storage locations. The applicant’s material supplier may be a resource (subject to City approval) for BMPs to address specific project applications or proposals. Conditions of approval on adjustments may also specify additional requirements for the SWPPS plan. D.2.2.1 CONCRETE HANDLING Purpose Concrete work can generate process water and slurry that contain fine particles and high pH, both of which can violate water quality standards in the receiving water. Concrete spillage or concrete discharge to surface waters of the State is prohibited. Use this BMP to minimize and eliminate concrete, concrete process water, and concrete slurry from entering waters of the state. Conditions of Use Any time concrete is used, utilize these management practices. Concrete construction projects include, but are not limited to, curbs, sidewalks, roads, bridges, foundations, floors, stormwater vaults, retaining walls, driveways and runways. Design and Installation Specifications 1. Ensure that washout of concrete trucks, chutes, pumps, and internals is performed at an approved off- site location or in designated concrete washout areas. Do not wash out concrete trucks, chutes, pumps, or internals onto the ground, or into storm drains, open ditches, streets, or streams. Refer to BMP D.2.2.2 for information on concrete washout areas. 2. Return unused concrete remaining in the truck and pump to the originating batch plant for recycling. Do not dump excess concrete on site, except in designated concrete washout areas. 3. Wash off hand tools including, but not limited to, screeds, shovels, rakes, floats, and trowels into formed areas awaiting future concrete pours only. 4. Do not wash out to formed areas awaiting infiltration BMPs. 5. Wash equipment difficult to move, such as concrete pavers in areas that do not directly drain to natural or constructed stormwater conveyances. 6. Do not allow washdown from areas, such as concrete aggregate driveways, to drain directly to natural or constructed stormwater conveyances. 7. Contain washwater and leftover product in a lined container when no formed areas are available. Dispose of contained concrete in a manner that does not violate ground water or surface water quality standards. 8. Always use forms or solid barriers for concrete pours, such as pilings, within 15-feet of surface waters. 9. Refer to BMPs D.2.2.7 and D.2.2.8 for pH adjustment requirements. 10. Refer to the Construction Stormwater General Permit for pH monitoring requirements if the project involves one of the following activities: Significant concrete work (greater than 1,000 cubic yards poured concrete or recycled concrete used over the life of a project). The use of engineered soils amended with (but not limited to) Portland cement-treated base, cement kiln dust or fly ash. Discharging stormwater to segments of water bodies on the 303(d) list (Category 5) for high pH. D.2.2 SWPPS MEASURES 2022 City of Renton Surface Water Design Manual 6/22/2022 D-73 Maintenance Standards Check containers for holes in the liner daily during concrete pours and repair the same day. D.2.2.2 CONCRETE WASHOUT AREA Purpose Prevent or reduce the discharge of pollutants to stormwater from concrete waste by conducting washout off-site, or performing onsite washout in a designated area to prevent pollutants from entering surface waters or ground water. Conditions of Use Concrete washout area best management practices are implemented on construction projects where: Concrete is used as a construction material It is not possible to dispose of all concrete wastewater and washout off-site (ready mix plant, etc.). Concrete trucks, pumpers, or other concrete coated equipment are washed onsite. Note: If less than 10 concrete trucks or pumpers need to be washed out onsite, the washwater may be disposed of in a formed area awaiting concrete or an upland disposal site where it will not contaminate surface or ground water. The upland disposal site shall be at least 50 feet from sensitive areas such as storm drains, open ditches, or water bodies, including wetlands. Design and Installation Specifications Implementation The following steps will help reduce stormwater pollution from concrete wastes: 1. Perform washout of concrete trucks at an approved off-site location or in designated concrete washout areas only. 2. Do not wash out concrete trucks onto the ground, or into storm drains, open ditches, streets, or streams. 3. Do not allow excess concrete to be dumped onsite, except in designated concrete washout areas. 4. Concrete washout areas may be prefabricated concrete washout containers, or self-installed structures above-grade or below-grade). 5. Prefabricated containers are most resistant to damage and protect against spills and leaks. Companies may offer delivery service and provide regular maintenance and disposal of solid and liquid waste. 6. If self-installed concrete washout areas are used, below-grade structures are preferred over above- grade structures because they are less prone to spills and leaks. 7. Self-installed above-grade structures should only be used if excavation is not practical. Education 1. Discuss the concrete management techniques described in this BMP with the ready-mix concrete supplier before any deliveries are made. 2. Educate employees and subcontractors on the concrete waste management techniques described in this BMP. 3. Arrange for contractor’s superintendent or Certified Erosion and Sediment Control Lead (CESCL) to oversee and enforce concrete waste management procedures. 4. A sign should be installed adjacent to each temporary concrete washout facility to inform concrete equipment operators to utilize the proper facilities. SECTION D.2 GENERAL CSWPP REQUIREMENTS 6/22/2022 2022 City of Renton Surface Water Design Manual D-74 Contracts Incorporate requirements for concrete waste management into concrete supplier and subcontractor agreements. Location and Placement 1. Locate washout area at least 50 feet from sensitive areas such as storm drains, open ditches, or water bodies, including wetlands. 2. Allow convenient access for concrete trucks, preferably near the area where the concrete is being poured. 3. If trucks need to leave a paved area to access washout, prevent track-out with a pad of rock or quarry spalls (see BMP D.2.1.4.2). These areas should be far enough away from other construction traffic to reduce the likelihood of accidental damage and spills. 4. The number of facilities you install should depend on the expected demand for storage capacity. 5. On large sites with extensive concrete work, washouts should be placed in multiple locations for ease of use by concrete truck drivers. On-Site Temporary Concrete Washout Facility, Transit Truck Washout Procedures: 1. Temporary concrete washout facilities shall be located a minimum of 50 feet from sensitive areas including storm drain inlets, open drainage facilities, and watercourses. (See Figures D.2.2.2.A, D.2.2.2.B, and D.2.2.2.C). 2. Concrete washout facilities shall be constructed and maintained in sufficient quantity and size to contain all liquid and concrete waste generated by washout operations. 3. Washout of concrete trucks shall be performed in designated areas only. 4. Concrete washout from concrete pumper bins can be washed into concrete pumper trucks and discharged into designated washout area or properly disposed of off-site. 5. Once concrete wastes are washed into the designated area and allowed to harden, the concrete should be broken up, removed, and disposed of per applicable solid waste regulations. Dispose of hardened concrete on a regular basis. 6. Temporary Above-Grade Concrete Washout Facility a) Temporary concrete washout facility (type above grade) should be constructed as shown on the details below, with a recommended minimum length and minimum width of 10 ft, but with sufficient quantity and volume to contain all liquid and concrete waste generated by washout operations. b) Plastic lining material should be a minimum of 10 mil polyethylene sheeting and should be free of holes, tears, or other defects that compromise the impermeability of the material. 7. Temporary Below-Grade Concrete Washout Facility a) Temporary concrete washout facilities (type below grade) should be constructed as shown on the details below, with a recommended minimum length and minimum width of 10 ft. The quantity and volume should be sufficient to contain all liquid and concrete waste generated by washout operations. b) Lath and flagging should be commercial type. c) Plastic lining material shall be a minimum of 10 mil polyethylene sheeting and should be free of holes, tears, or other defects that compromise the impermeability of the material. d) Liner seams shall be installed in accordance with manufacturers’ recommendations. D.2.2 SWPPS MEASURES 2022 City of Renton Surface Water Design Manual 6/22/2022 D-75 e) Soil base shall be prepared free of rocks or other debris that may cause tears or holes in the plastic lining material. Maintenance Standards Inspection and Maintenance 1. Inspect and verify that concrete washout BMPs are in place prior to the commencement of concrete work. 2. During periods of concrete work, inspect daily to verify continued performance. a) Check overall condition and performance. b) Check remaining capacity (% full). c) If using self-installed washout facilities, verify plastic liners are intact and sidewalls are not damaged. d) If using prefabricated containers, check for leaks. 3. Washout facilities shall be maintained to provide adequate holding capacity with a minimum freeboard of 12 inches. 4. Washout facilities must be cleaned, or new facilities must be constructed and ready for use once the washout is 75% full. 5. If the washout is nearing capacity, vacuum and dispose of the waste material in an approved manner. a) Do not discharge liquid or slurry to waterways, storm drains or directly onto ground. b) Do not use sanitary sewer without local approval. c) Place a secure, non-collapsing, non-water collecting cover over the concrete washout facility prior to predicted wet weather to prevent accumulation and overflow of precipitation. d) Remove and dispose of hardened concrete and return the structure to a functional condition. Concrete may be reused onsite or hauled away for disposal or recycling. 6. When you remove materials from the self-installed concrete washout, build a new structure; or, if the previous structure is still intact, inspect for signs of weakening or damage, and make any necessary repairs. Re-line the structure with new plastic after each cleaning. Removal of Temporary Concrete Washout Facilities 1. When temporary concrete washout facilities are no longer required for the work, the hardened concrete, slurries and liquids shall be removed and properly disposed of. 2. Materials used to construct temporary concrete washout facilities shall be removed from the site of the work and disposed of or recycled. 3. Holes, depressions or other ground disturbance caused by the removal of the temporary concrete washout facilities shall be backfilled, repaired, and stabilized to prevent erosion. SECTION D.2 GENERAL CSWPP REQUIREMENTS 6/22/2022 2022 City of Renton Surface Water Design Manual D-76 FIGURE D.2.2.2.A CONCRETE WASHOUT AREA (ABOVE GRADE) SECTION B-B NTS SECTION A-A NTS STAPLE DETAIL NTS PLAN NTS ABOVE GRADE TEMPORARY CONCRETE WASHOUT FACILITY NTS CONCRETE WASHOUT SIGN DETAIL NTS 10 mil PLASTIC LINING PLAN NTS TYPE "ABOVE GRADE" WITH WOOD PLANKS TYPE "ABOVE GRADE" WITH STRAW BALES 10 mil PLASTIC LINING 16 GAUGE STEEL WIRE 2" 8" LAG SCREWS ( 12" ) BLACK LETTERS 6" HEIGHT PLYWOOD 4' X 2' PAINTED WHITE WOOD POST 312" x 312" x 8' 3' 3' STRAW BALES TYP.) STAKE TYP.) WEDGE LOOSE STRAW BETWEEN BALES SAND OR GRAVEL-FILLED BAGS IN CORNERS 10' MIN. RECOMMENDED VARIES WOOD OR METAL STAKES 2 PER BALE) STRAW BALES (2 BALES HIGH, MAX.) ORIGINAL GROUND 10 mil PLASTIC LINING STAPLES (2 PER BALE) SAND OR GRAVEL-FILLED BAGS IN CORNERS NATIVE MATERIAL OPTIONAL) 10 mil PLASTIC LINING WOOD FRAME SECURELY FASTENED AROUND ENTIRE PERIMETER WITH TWO STAKES TWO-STACKED 2x12 ROUGH WOOD FRAME STAKE TYP.) 10' MIN. RECOMMENDED VARIES NOTES: 1. ACTUAL LAYOUT DETERMINED IN THE FIELD 2. THE CONCRETE WASHOUT SIGN SHALL BE INSTALLED WITHIN 30' OF THE FACILITY 1' MIN. Adapted from CalTrans Fig4-14 SAC 8-14-02 D.2.2 SWPPS MEASURES 2022 City of Renton Surface Water Design Manual 6/22/2022 D-77 FIGURE D.2.2.2.B CONCRETE WASHOUT AREA (BELOW GRADE) FIGURE D.2.2.2.C PREFABRICATED CONCRETE WASHOUT CONTAINER W/RAMP EARTHEN BERM TYPICAL SECTION NTS BELOW GRADE TEMPORARY CONCRETE WASHOUT FACILITY NTS CONCRETE WASHOUT SIGN DETAIL NTS SANDBAG PLAN NTS Adapted from CalTrans Fig4-14 SAC 8-14-02 10 mil PLASTIC LINING LAG SCREWS ( 12" ) BLACK LETTERS 6" HEIGHT PLYWOOD 4' X 2' PAINTED WHITE WOOD POST 312" x 312" x 8' 3' 3' EARTHEN BERM 10 mil PLASTIC LINING SANDBAG 10' MIN. RECOMMENDED VARIES BERM 3' LATH AND FLAGGING ON 3 SIDES NOTES: 1. ACTUAL LAYOUT DETERMINED IN THE FIELD 2. THE CONCRETE WASHOUT SIGN SHALL BE INSTALLED WITHIN 30' OF THE FACILITY SECTION D.2 GENERAL CSWPP REQUIREMENTS 6/22/2022 2022 City of Renton Surface Water Design Manual D-78 D.2.2.3 SAWCUTTING AND SURFACING POLLUTION PREVENTION Purpose Sawcutting and surfacing operations generate slurry and process water that contains fine particles and high pH (concrete cutting), both of which can violate the water quality standards in the receiving water. Concrete spillage or concrete discharge to surface waters of the State is prohibited. Use this BMP to minimize and eliminate process water and slurry created through sawcutting or surfacing from entering waters of the State. Conditions of Use Utilize these management practices anytime sawcutting or surfacing operations take place. Sawcutting and surfacing operations include, but are not limited to, sawing, coring, grinding, roughening, hydro- demolition, bridge and road surfacing Design and Installation Specifications 1. Vacuum slurry and cuttings during cutting and surfacing operations. 2. Slurry and cuttings shall not remain on permanent concrete or asphalt pavement overnight. 3. Slurry and cuttings shall not drain to any natural or constructed drainage conveyance including stormwater systems. This may require temporarily blocking catch basins. 4. Dispose of collected slurry and cuttings in a manner that does not violate ground water or surface water quality standards. 5. Do not allow process water generated during hydro-demolition, surface roughening or similar operations to drain to any natural or constructed drainage conveyance including stormwater systems. Dispose process water in a manner that does not violate ground water or surface water quality standards. 6. Handle and dispose cleaning waste material and demolition debris in a manner that does not cause contamination of water. Dispose of sweeping material from a pick-up sweeper at an appropriate disposal site. Maintenance Standards Continually monitor operations to determine whether slurry, cuttings, or process water could enter waters of the state. If inspections show that a violation of water quality standards could occur, stop operations and immediately implement preventive measures such as berms, barriers, secondary containment, and vacuum trucks. D.2.2.4 MATERIAL DELIVERY, STORAGE, AND CONTAINMENT Purpose Prevent, reduce, or eliminate the discharge of pollutants to the stormwater system or watercourses from material delivery and storage. Minimize the storage of hazardous materials onsite, store materials in a designated area, and install secondary containment. Conditions of Use These procedures are suitable for use at all construction sites with delivery and storage of the following materials: Petroleum products such as fuel, oil and grease Soil stabilizers and binders (e.g., Polyacrylamide) Fertilizers, pesticides and herbicides Detergents Asphalt and concrete compounds D.2.2 SWPPS MEASURES 2022 City of Renton Surface Water Design Manual 6/22/2022 D-79 Hazardous chemicals such as acids, lime, adhesives, paints, solvents and curing compounds Any other material that may be detrimental if released to the environment Design and Installation Specifications The following steps should be taken to minimize risk: 1. Temporary storage area should be located away from vehicular traffic, near the construction entrance(s), and away from waterways or storm drains. 2. Material Safety Data Sheets (MSDS) should be supplied for all materials stored. Chemicals should be kept in their original labeled containers. 3. Hazardous material storage onsite should be minimized. 4. Hazardous materials should be handled as infrequently as possible. 5. During the wet weather season (October 1 – April 30), consider storing materials in a covered area. 6. Materials should be stored in secondary containments, such as earthen dike, horse trough, or even a children’s wading pool for non-reactive materials such as detergents, oil, grease, and paints. Small amounts of material may be secondarily contained in “bus boy” trays or concrete mixing trays. 7. Do not store chemicals, drums, or bagged materials directly on the ground. Place these items on a pallet and, when possible, and within secondary containment. 8. If drums must be kept uncovered, store them at a slight angle to reduce ponding of rainwater on the lids to reduce corrosion. Domed plastic covers are inexpensive and snap to the top of drums, preventing water from collecting. Material Storage Areas and Secondary Containment Practices: 1. Liquids, petroleum products, and substances listed in 40 CFR Parts 110, 117, or 302 shall be stored in approved containers and drums and shall not be overfilled. Containers and drums shall be stored in temporary secondary containment facilities. 2. Temporary secondary containment facilities shall provide for a spill containment volume able to contain 10% of the total enclosed container volume of all containers, or 110% of the capacity of the largest container within its boundary, whichever is greater. 3. Secondary containment facilities shall be impervious to the materials stored therein for a minimum contact time of 72 hours. 4. Secondary containment facilities shall be maintained free of accumulated rainwater and spills. In the event of spills or leaks, accumulated rainwater and spills shall be collected and placed into drums. These liquids shall be handled as hazardous waste unless testing determines them to be non- hazardous. 5. Sufficient separation should be provided between stored containers to allow for spill cleanup and emergency response access. 6. During the wet weather season (October 1 – April 30), each secondary containment facility shall be covered during non-working days, prior to and during rain events. 7. Keep material storage areas clean, organized and equipped with an ample supply of appropriate spill clean-up material (spill kit). 8. The spill kit should include, at a minimum: 1-Water Resistant Nylon Bag 3-Oil Absorbent Socks 3 x 4 2-Oil Absorbent Socks 3 x 10 12-Oil Absorbent Pads 17 x 19 SECTION D.2 GENERAL CSWPP REQUIREMENTS 6/22/2022 2022 City of Renton Surface Water Design Manual D-80 1-Pair Splash Resistant Goggles 3-Pair Nitrile Gloves 10-Disposable Bags with Ties Instructions D.2.2.5 CONSTRUCTION STORMWATER CHEMICAL TREATMENT Purpose This BMP applies when using stormwater chemicals in batch treatment or flow-through treatment. Turbidity is difficult to control once fine particles are suspended in stormwater runoff from a construction site. Sedimentation ponds are effective at removing larger particulate matter by gravity settling, but are ineffective at removing smaller particulates such as clay and fine silt. Traditional erosion and sediment control BMPs may not be adequate to ensure compliance with the water quality standards for turbidity in receiving water. Chemical treatment can reliably provide exceptional reductions of turbidity and associated pollutants. Chemical treatment may be required to meet turbidity stormwater discharge requirements, especially when construction is to proceed through the wet season. Conditions of Use Formal written approval from Ecology is required for the use of chemical treatment regardless of site size. The City also requires review and approval. When approved, the chemical treatment systems must be included in the SWPPS portion of the project’s CSWPP. Design and Installation Specifications Coagulation and flocculation have been used for over a century to treat water. It is used less frequently for the treatment of wastewater. The use of coagulation and flocculation for treating stormwater is a very recent application. Experience with the treatment of water and wastewater has resulted in a basic understanding of the process, in particular factors that affect performance. This experience can provide insights as to how to most effectively design and operate similar systems in the treatment of stormwater. Fine particles suspended in water give it a milky appearance, measured as turbidity. Their small size, often much less than 1 m in diameter, give them a very large surface area relative to their volume. These fine particles typically carry a negative surface charge. Largely because of these two factors, small size and negative charge, these particles tend to stay in suspension for extended periods of time. Thus, removal is not practical by gravity settling. These are called stable suspensions. Polymers, as well as inorganic chemicals such as alum, speed the process of clarification. The added chemical destabilizes the suspension and causes the smaller particles to agglomerate. The process consists of three steps: coagulation, flocculation, and settling or clarification. Each step is explained below as well as the factors that affect the efficiency of the process. Coagulation: Coagulation is the first step. It is the process by which negative charges on the fine particles that prevent their agglomeration are disrupted. Chemical addition is one method of destabilizing the suspension, and polymers are one class of chemicals that are generally effective. Chemicals that are used for this purpose are called coagulants. Coagulation is complete when the suspension is destabilized by the neutralization of the negative charges. Coagulants perform best when they are thoroughly and evenly dispersed under relatively intense mixing. This rapid mixing involves adding the coagulant in a manner that promotes rapid dispersion, followed by a short time period for destabilization of the particle suspension. The particles are still very small and are not readily separated by clarification until flocculation occurs. SECTION D.2 GENERAL CSWPP REQUIREMENTS 6/22/2022 2022 City of Renton Surface Water Design Manual D-100 proper disposal must be submitted to the City. All authorizations for disposal shall be obtained prior to CKD/CTB application. Infiltration: Depending on the site conditions, pH-adjusted stormwater may be infiltrated. Prior to infiltration, pH must be between 6.5 and 8.5. Surface Water: Contact water from the application area shall not be discharged to surface waters, even if treatment has adjusted the pH. 8. Emergency backup plan: An emergency backup plan must be prepared and ready to implement to handle large quantities of stormwater. 9. Monitoring shall be conducted to determine that contact stormwater is not leaving the site. Offsite monitoring shall also be conducted to identify impacts to adjacent water bodies. Bonding may be required to cover mitigation of impacts and restoration. 10. A soils specialist will establish the mixing percentage for onsite soils. Soil amendments will never occur in excess of the ability of the onsite equipment and resources to meet all BMP requirements. 11. For sites one acre or larger, a Construction Stormwater General permit must be obtained from Ecology. Construction Stormwater General permits and ‘Stormwater Pollution Prevention Plans SWPPPs) must be amended and the use of CKD/CTB must be approved by Ecology prior to application. The contractor/developer shall comply will all federal, state, and local regulations. A health and safety plan may be required for the protection of CED inspectors. Additional BMPs may be applicable depending on mix design, proximity of wetlands or streams (e.g., within 300 feet of class/type I and 100 feet or less for other types) and site conditions. D.2.2.10 MAINTAIN PROTECTIVE BMPS Pollutant protection measures shall be maintained to ensure continued performance of their intended function. Reporting and documentation shall be kept current and made available to CED as indicated. Purpose: The purpose of maintaining protective BMPs is to provide effective pollutant protection when and where required by the plan and the project, and to provide timely and relevant project information. When to Maintain: Protection measures shall be monitored per Section D.2.4.4 at a minimum, continuously during operation, and promptly maintained to fully functioning condition as necessary to ensure continued performance of their intended function. Documentation shall be kept current per specific BMP requirements. Measures to Use: 1. Maintain and repair all pollutant control BMPs as needed to ensure continued performance of their intended function in accordance with BMP specifications. 2. Maintain and repair storage locations for equipment and materials associated with BMP processes. Conduct materials disposal in compliance with City requirements. 3. As required, provide current reporting and performance documentation at an accessible location for the site inspector and other CED staff. 4. Remove all temporary pollutant control BMPs prior to final construction approval, or within 30 days after achieving final site stabilization or after the temporary BMPs are no longer needed. D.2.2.11 MANAGE THE PROJECT SWPPP requirements shall be implemented and managed as part of the overall CSWPP plan. Concrete construction and its impacts are primary among pollutant concerns on site development projects. Fueling operations and materials containment of treatment chemicals and other project materials are also typical D.2.2 SWPPS MEASURES 2022 City of Renton Surface Water Design Manual 6/22/2022 D-101 pollutant concerns. Operations that produce these and other pollutants are often conducted by subcontractors and their laborers, yet may require specific protective measures, documentation and reporting. Protective measures and BMPs need to be made available prior to construction and suitable oversight provided to ensure inspection, monitoring and documentation requirements are met. Projects shall assign a qualified CSWPP Supervisor (Section D.2.3.1) to be the primary contact for SWPPP and ESC issues and reporting, coordination with subcontractors and implementation of the CSWPP plan as a whole. Measures to Use: 1. Phase development projects to the maximum degree practicable and take into account seasonal work limits. 2. Inspection and monitoring – Inspect, maintain, and repair all BMPs as needed to ensure continued performance of their intended function. Conduct site inspections and monitoring in accordance with the Construction Stormwater General Permit and City requirements. Coordinate with subcontractors and laborers to ensure the SWPPP measures are followed. 3. Documentation and reporting – Inspect, maintain, and repair all BMPs as needed to ensure continued performance of their intended function. Document site inspections and monitoring in accordance with the Construction Stormwater General Permit, specific BMP conditions and City requirements. Log sheets provided in Reference Section 8 may be used if appropriate. Follow reporting requirements and provide documentation as requested to CED staff. 4. Maintaining an updated construction SWPPP – Maintain, update, and implement the SWPPP in accordance with the Construction Stormwater General Permit and City requirements. Obtain approval for specific SWPPP measures (e.g., chemical treatments of stormwater) well in advance of need. Coordinate SWPPP plan updates with the site inspector (see Section D.2.4.1). D.2.3 CSWPP PERFORMANCE AND COMPLIANCE PROVISIONS The changing conditions typical of construction sites call for frequent field adjustments of existing ESC and SWPPS measures or additional ESC and SWPPS measures in order to meet required performance. In some cases, strict adherence to specified measures may not be necessary or practicable based on site conditions or project type. In other cases, immediate action may be needed to avoid severe impacts. Therefore, careful attention must be paid to ESC and SWPPS performance and compliance in accordance with the provisions contained in this section. D.2.3.1 CSWPP SUPERVISOR For projects in Targeted, Full, or Large Project Drainage Review, or projects in Directed Drainage Review as determined by CED review staff, the applicant must designate a CSWPP supervisor who shall be responsible for the performance, maintenance, and review of ESC and SWPPS measures and for compliance with all permit conditions relating to CSWPP as described in the CSWPP Standards. The applicant’s selection of a CSWPP supervisor must be approved by the City. (City approval may be rescinded for non-compliance, requiring the applicant to select another CSWPP supervisor and obtain City approval prior to continuing work on the project site.) For projects that disturb one acre or more of land, the CSWPP supervisor must be a Certified Professional in Erosion and Sediment Control (see <www.cpesc.net> for more information) or a Certified Erosion and Sediment Control Lead whose certification is recognized by the City.11 The City may also require a certified ESC professional for sites smaller than one acre of disturbance if CED determines that onsite ESC measures are inadequately installed, located, or maintained. 11 The City’s recognition of certification means that the individual has taken an approved third party training program and has passed the approved test for that training program. SECTION D.2 GENERAL CSWPP REQUIREMENTS 6/22/2022 2022 City of Renton Surface Water Design Manual D-102 For larger, more sensitive sites, the City may require a certified ESC professional with several years of experience in construction supervision/inspection and a background in geology, soil science, or agronomy. Typically, if a geotechnical consultant is already working on the project, the consultant may also be a certified ESC professional designated as the CSWPP supervisor. The design engineer may also be qualified for this position. This requirement shall only be used for sensitive sites that pose an unusually high risk of impact to surface waters as determined by CED. At a minimum, the project site must meet all of the following conditions in order to require the applicant to designate as the CSWPP supervisor a certified ESC professional with such expertise: Alderwood soils or other soils of Hydrologic Group C or D Five acres of disturbance Large areas (i.e., two or more acres) with slopes in excess of 10 percent. Proximity to streams or wetlands or phosphorus-sensitive lakes, such as Lake Sammamish, shall also be a factor in determining if such expertise in the CSWPP supervisor is warranted. However, proximity alone shall not be a determining factor because even projects that are a considerable distance from surface waters can result in significant impacts if there is a natural or constructed drainage system with direct connections to surface waters. The name, address, and phone number of the CSWPP supervisor shall be supplied to the City prior to the start of construction. A sign shall be posted at all primary entrances to the site identifying the CSWPP supervisor and his/her phone number. The requirement for a CSWPP supervisor does not relieve the applicant of ultimate responsibility for the project and compliance with Renton Municipal Code. D.2.3.2 MONITORING OF DISCHARGES The CSWPP supervisor shall have a turbidity meter onsite and shall use it to monitor surface and storm water discharges from the project site and into onsite wetlands, streams, or lakes whenever runoff occurs from onsite activities and during storm events. The CSWPP supervisor shall keep a log of all turbidity measurements taken onsite and make it available to CED upon request. If the project site is subject to a NPDES general permit for construction issued by the Washington State Department of Ecology (Ecology), then the project must comply with the monitoring requirements of that permit. The CSWPP supervisor shall also use the specific SWPPS BMP procedures for monitoring surface and stormwater discharge for pollutants and acceptable discharge levels. The CSWPP supervisor shall keep logs as required by the procedures of all measurements taken onsite and make them available to CED on request. D.2.3.3 ESC PERFORMANCE ESC measures shall be applied/installed and maintained so as to prevent, to the maximum extent practicable, the transport of sediment from the project site to downstream drainage systems or surface waters or into onsite wetlands, streams, or lakes or onto adjacent properties. This performance is intended to be achieved through proper selection, installation, and operation of the above ESC measures as detailed in the CSWPP Standards (Appendix D) and approved by the City. However, the CSWPP supervisor designated per Section D.2.3.1 or the City may determine at any time during construction that such approved measures are not sufficient and additional action is required based on one of the following criteria: 1. IF a turbidity test of surface and storm water discharges leaving the project site is greater than the benchmark value of 25 nephelometric turbidity units (NTU) set by the Washington State Department of Ecology, but less than 250 NTU, the CSWPP Supervisor shall do all of the following: a) Review the ESC plan for compliance and make appropriate revisions within 7 days of the discharge that exceeded the benchmark of 25 NTU, AND