HomeMy WebLinkAbout35. Monster Road SW.68th Ave S Roadway ImprovementsTRANSPORTATION IMPROVEMENT PROGRAM
2019 - 2024
TIP No. 35
Project Title:Monster Road SW/68th Ave S Roadway Improvements
Community Planning Area:Valley Fund:
Functional Classification:N/A Project:
Project Length:0.92 mi Contact:
Project Description:
Justification:
Status:
Changes:
Funded:Unfunded:
Pre-2018 2018 Total 2019 2020 2021 2022 2023 2024
Expenditures:
Planning 50,000 - - 50,000 - - - - 50,000 -
Preliminary Engineering 5,000,000 - - 5,000,000 - - - - - 5,000,000
R-O-W (includes Admin)3,000,000 - - 3,000,000 - - - - - 3,000,000
Construction - - - - - - - - - -
Construction Services - - - - - - - - - -
Post Construction Services - - - - - - - - - -
Other - - - - - - - - - -
Total Expenses 8,050,000 - - 8,050,000 - - - - 50,000 8,000,000
Resources:
Vehicle Fuel Tax - - - - - - - - - -
Business & Occupation Share - - - - - - - - - -
Fund Balance - - - - - - - - - -
Grants In-Hand (1)- - - - - - - - - -
Grants In-Hand (2)- - - - - - - - - -
Mitigation In-Hand - - - - - - - - - -
Bonds / LID's Formed - - - - - - - - - -
Other In-Hand (1)- - - - - - - - - -
Other In-Hand (2)- - - - - - - - - -
- - - - - - - - - -
Undetermined 8,050,000 - - 8,050,000 - - - - 50,000 8,000,000
Total Sources 8,050,000 - - 8,050,000 - - - - 50,000 8,000,000
- 8,050,000
Project Expenditures & Resources Programmed Programmed Pre-2019 Six-Year Program
Monster Road SW/68th Ave S Roadway Improvements
317
Vangie Garcia 425-430-7319
Widen existing roadway to four lanes plus two-way-left-turn-lane where needed and bike lanes. Realign Beacon Coal Mine Road approach to intersection with the Monster Road
SW roadway. Includes new roadway, curbs, sidewalk, drainage, street lighting, traffic signals, channelization, retaining walls and widening the existing bridge.
Will serve growing north-south traffic demand. A preliminary design study was completed in 1999. The project cost is estimated at $32M, with the City's share estimated at $13M
and King Co. at $19M.
Phase 1 of improvements will address drainage problems between the Monster Rd Bridge and the City limits. Scope, cost and implementation schedule to be determined. Project is
pending future grant funding availability. Cost beyond 2024 not shown.