HomeMy WebLinkAbout42. S.SW 7th Street Corridor Improvements - Naches Ave S to Talbot Road STRANSPORTATION IMPROVEMENT PROGRAM
2019 - 2024
TIP No. 42
Project Title:7th Street Corridor Improvements - Naches Ave S to Talbot Road S
Community Planning Area:City Center Fund:
Functional Classification:Minor Arterial Project:
Project Length:1.16 mi Contact:
Project Description:
Justification:
Status:
Changes:
Funded:Unfunded:
Pre-2018 2018 Total 2019 2020 2021 2022 2023 2024
Expenditures:
Planning 32,270 32,270 - - - - - - - -
Preliminary Engineering 2,311,842 311,842 - 2,000,000 - - 200,000 800,000 1,000,000 -
R-O-W (includes Admin)1,725,124 25,124 - 1,700,000 - - - 800,000 900,000
Construction 11,362,668 975,141 14,599 10,372,928 - - - - 7,264,000 3,108,928
Construction Services 1,999,882 299,882 - 1,700,000 - - - - 1,200,000 500,000
Post Construction Services - - - - - - - - - -
Other - - - - - - - - - -
Total Expenses 17,431,786 1,644,259 14,599 15,772,928 - - 200,000 1,600,000 10,364,000 3,608,928
Resources:
Vehicle Fuel Tax - - - - - - - - - -
Business & Occupation Share 52,115 52,115 - - - - - - - -
Fund Balance + Reserve 72,164 60,401 11,763 - - - - - - -
Grants In-Hand (STP)497,241 494,405 2,836 - - - - - - -
Grants In-Hand (TIB)613,338 613,338 - - - - - - - -
Mitigation In-Hand 424,000 424,000 - - - - - - - -
Bonds / LID's Formed - - - - - - - - - -
Other In-Hand (1)- - - - - - - - - -
Other In-Hand (2)- - - - - - - - - -
- - - - - - - - - -
Undetermined 15,772,928 - - 15,772,928 - - 200,000 1,600,000 10,364,000 3,608,928
Total Sources 17,431,786 1,644,259 14,599 15,772,928 - - 200,000 1,600,000 10,364,000 3,608,928
1,658,858 15,772,928
Project Expenditures & Resources Programmed Programmed Pre-2019 Six-Year Program
7th Street Corridor Improvements - Naches Ave S to Talbot
Road S
Added costs for the SW 7th St Sidepath. It is assumed that no ROW would be required.
317
122151
Vangie Garcia 425-430-7319
Widening the existing S 7th St from Talbot Road S to Rainier Ave S roadway to 3 lanes (2 lanes EB and 1 lane WB) and a separated multi-use trail. Includes new curb, gutter, wider
sidewalks, street lighting, landscaping, channelization and upgrades to traffic signals. The S 7th St Project - Traffic Analysis Report provided alternatives for corridor improvement
options. This project also includes a sidepath on SW 7th St between Rainier Ave S and Naches Ave S.
The segment of the S 7th St corridor connects Talbot Rd S (SR 515) with Rainier Ave S (SR 167). The segment of S 7th St is part of a designated east-west ped/bike route through
the City's commercial core and an important link between regional trails. The South Renton Neighborhood Study has identified South 7th St as needing streetscape
improvements. The Trails and Bicycle Master Plan Update identified SW 7th St/S 7th St as a good alternate/parallel route as the L2S Trail (TIP #30) is developed. With the
expansion of the South Renton Transit Center and Bus Rapid Transit (BRT) implementation, S 7th St is important non-motorized link to downtown core.
Costs incurred are for Phase 1, which added a traffic signal and an eastbound right-turn lane at the intersection of S 7th St and Shattuck Ave S. Project is pending future grant
funding availability.