A. ADMINISTRATIVE DECISION
Decision: APPROVED APPROVED SUBJECT TO CONDITIONS DENIED
Report Date: July 9, 2026
Project File Number: PR18-000333
Project Name: Solera Phase II
Land Use File Number: LUA26-000205, FP
Project Manager: Heather Bray, Civil Engineer III
Owner/Applicant: TPG AG EHC III (NWHM) Multi State 3, LLC & Solera Manager, LLC
Contact: Jaden Storedahl, Land Development Construction Manager, 1700 NW Gilman
Blvd, Suite 220, Issaquah, WA 98027
Project Location: 2905 NE 11th St (Parcel No. 722780-1235, 722780-1405, and 722780-1785)
B. EXHIBITS:
Exhibit 1: Solera Phase II Final Plat Administrative Decision
Exhibit 2: Final Plat Map
Exhibit 3: Compliance with Preliminary Plat Conditions Summary (LUA18-000490)
Exhibit 4: Compliance with Preliminary Plat Conditions Summary (LUA20-000305)
Exhibit 5: Compliance with Preliminary Plat Conditions Summary (LUA24-000221)
Exhibit 6: Compliance with Preliminary Plat Conditions Summary (LUA24-000375)
C. FINDINGS OF FACT (FOF):
1. Conformance with Preliminary Plat:
Compliance Conformance with Preliminary Plat
Compliant
if
Conditions
of Approval
are met
The final plat shall:
1. Conform with only minor modifications to the preliminary plat.
2. The lot configuration remains unchanged.
3. The lots meet development standards of the Zoning Code.
4. Conditions of approval have been met as identified in Exhibits 3-6.
D. DECISION:
The Solera Phase II Final Plat, File No. LUA26-000205, FP, as depicted in the Final Plat Map (Exhibit 2), is
approved and is subject to the following condition:
1. Closeout of the construction phase for Civil Construction Permit C25003173, including all plat
infrastructure, lighting, franchise permits, streets, sidewalks, and punch list items, shall occur prior
to recording of the final plat.
Docusign Envelope ID: 9C998AA6-4BC1-8E93-80C8-EA7BBA32AF22
City of Renton Department of Community & Economic Development Solera Phase II Administrative Report & Decision LUA26-000205, FP
Report of July 9, 2026 Page 2 of 3
D_Solera Phase II_Final_Plat_20260709
DATE OF DECISION ON LAND USE ACTION:
SIGNATURE AND DATE:
Gina Estep
Community and Economic Development Administrator
Date
TRANSMITTED on July 9, 2026 to the Owner/Applicant/Contact:
Owner: Owner: Applicant:
TPG AG EHC III (NWHM) Multi State 3, LLC
ATTN: Steven Benson
8585 E Hartford DR, Ste 118
Scottsdale, AZ 85255
Steve.benson@essentialhousingops.com
Solera Manager, LLC
ATTN: Evan Hunden
10900 NE 8th St, Ste 1200
Bellevue, WA 98004
Jack.Hunden@devcous.com
Risewell Homes
ATTN: Jaden Storedahl
1700 NW Golman Blvd, Ste 220
Issaquah, WA 98027
jstoredahl@risewellhomes.com
TRANSMITTED on July 9, 2026 to the Parties of Record:
No parties of record
TRANSMITTED on July 9, 2026 to the following:
Matthew Herrera, Planning Director
Stephanie Rary, Property Services Specialist
Justin Johnson, Development Engineering Director
Nathan Janders, Development Engineering Manager
Scott Mitchell, Acting Building Official
Anjela Barton, Fire Marshal
E. LAND USE ACTION APPEALS, REQUEST FOR RECONSIDERATION, & EXPIRATION:
The administrative land use decision will become final if the decision is not appealed within 14 days of the
decision date.
This administrative land use decision will become final if not appealed in writing to the Hearing
Examiner on or before 5:00 PM on July 23, 2026. An appeal of the decision must be filed within the 14-
day appeal period (RCW 43.21.C.075(3); WAC 197-11-680). Appeals must be submitted electronically to
the City Clerk at cityclerk@rentonwa.gov or delivered to City Hall 1st floor Lobby Hub Monday through
Friday. The appeal fee, normally due at the time an appeal is submitted, will be collected at a future date if
your appeal is submitted electronically. The appeal submitted in person may be paid on the first floor in our
Finance Department. Appeals to the Hearing Examiner are governed by RMC 4-8-110 and additional
information regarding the appeal process may be obtained from the City Clerkâs Office,
cityclerk@rentonwa.gov.
EXPIRATION: The administrative final plat decision will expire six (6) months from the date of decision. To
revitalize the expired plat, the plat shall be resubmitted as a preliminary plat. One extension to the six (6)
month period may be granted by the Administrator pursuant to RMC 4-7-110.F.
RECONSIDERATION: Within 14 days of the decision date, any party may request that the decision be
reopened by the approval body. The approval body may modify his decision if material evidence not readily
discoverable prior to the original decision is found or if he finds there was misrepresentation of fact. After
review of the reconsideration request, if the approval body finds sufficient evidence to amend the original
Docusign Envelope ID: 9C998AA6-4BC1-8E93-80C8-EA7BBA32AF22
7/9/2026 | 9:19 AM PDT
City of Renton Department of Community & Economic Development Solera Phase II Administrative Report & Decision LUA26-000205, FP
Report of July 9, 2026 Page 3 of 3
D_Solera Phase II_Final_Plat_20260709
decision, there will be no further extension of the appeal period. Any person wishing to take further action
must file a formal appeal within the 14-day appeal time frame.
THE APPEARANCE OF FAIRNESS DOCTRINE: provides that no ex parte (private one-on-one)
communications may occur concerning the land use decision. The Doctrine applies not only to the initial
decision, but to Appeals to the Hearing Examiner as well. All communications after the decision/approval
date must be made in writing through the Hearing Examiner. All communications are public record and this
permits all interested parties to know the contents of the communication and would allow them to openly
rebut the evidence in writing. Any violation of this doctrine could result in the invalidation of the appeal by
the Court.
Docusign Envelope ID: 9C998AA6-4BC1-8E93-80C8-EA7BBA32AF22