HomeMy WebLinkAboutCM_Construction Mitigation Description.pdfConstruction Mitigation Description
I-Kuan-Tao Cultural Center Addition
711 Monroe Ave NE Renton
08-25-2018
Proposed construction dates
01/01/2019 to 12/31/2019
Hours and days of operations
7am to 5pm (Mon to Fri) / 8am to 5pm (Sat)
Proposed hauling / transportation route
I-405 NE Sunset Blvd NE NE 10th St. Monroe Ave NE
Measures of construction
There is large space between the building and the street providing construction vehicle parking and
staging. Existing concrete driveway will be used for construction entrance. Portable toilet will be placed
away from sidewalk and adjacent properties. Silt fence will be installed to limit disturbance area. Volume
of radio play will be controlled to avoid bothering the neighborhood.
Traffic control plans
Not required.