KING COUNTY EASTSIDE INTERCEPTOR SECTION 2
REHABILITATION – PHASE II
TIER 2 TEMPORARY USE SUBMITTAL
KING COUNTY WASTEWATER TREATMENT DIVISION
201 S. Jackson Street, Suite 507
Seattle, WA 98104
RECEIVED
11/28/2018
amorganroth
PLANNING DIVISION
DEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
1
H:\CED\Data\Forms-Templates\Self-Help Handouts\Planning\Temporary Use Tier 2.doc Rev: 2/2017
TP SUBMITTAL REQUIREMENTS
TIER 2 TEMPORARY USE PERMIT
Planning Division
1055 South Grady Way, Renton, WA 98057
Phone: 425-430-7294 | www.rentonwa.gov
PURPOSE: To allow the City to review proposed short-term uses or structures which do not comply with
current zoning and/or development standards.
FREE CONSULTATION MEETING: Prior to submitting an application, the applicant should informally
discuss the proposed development with the Planning Division. The Planning Division will provide
assistance and detailed information on the City’s requirements and standards. Applicants may also take
this opportunity to request the waiver of the City’s typical application submittal requirements, which
may not be applicable to the specific proposal. For further information on this meeting, see the
instruction sheet entitled “Submittal Requirements: Pre-Application.”
APPLICATION SCREENING: Applicants are required to bring in a CD or USB portable (flash/hard) drive
(or other device or pathway as approved by your assigned project manager) with one PDF file of the
application package for informal review by staff, prior to scheduling an intake meeting. Please allow
approximately 45 minutes for application screening.
COMPLETE APPLICATION REQUIRED: In order to accept your application, each of the numbered items
must be submitted at the same time. If you have received a prior written waiver of a submittal item(s)
during a pre-application meeting, please provide the waiver form in lieu of any submittal item not
provided.
APPLICATION SUBMITTAL HOURS: Applications should be submitted to Development Services staff at
the 6th floor counter of Renton City Hall, 1055 South Grady Way, between 8:00 a.m. and 4:00 p.m.
Monday through Friday. Please call your assigned project manager to schedule an appointment or call
425-430-7294 to reach the Planning Division. Due to the screening time required, applications delivered
by messenger cannot be accepted.
ADDITIONAL PERMITS: Additional permits from other agencies may be required. It is the applicant’s
responsibility to obtain these other approvals. Information regarding these other requirements may be
found at http://apps.oria.wa.gov/opas/.
All Plans and Attachments are subject to Electronic File Standards
2
H:\CED\Data\Forms-Templates\Self-Help Handouts\Planning\Temporary Use Tier 2.doc Rev: 2/2017
APPLICATION MATERIALS:
1.Pre-Application Meeting Summary: If the application was reviewed at a “pre-application
meeting.”
2.Waiver Form: If you received a waiver form during or after a “pre-application meeting.”
3.Land Use Permit Master Application Form: The application must have notarized signatures
of ALL current property owners listed on the Title Report. If the property owner is a
corporation, the authorized representative must attach proof of signing authority on behalf
of the corporation. The legal description of the property must be attached to the
application form.
4.Fees: The application must be accompanied by the required application fee (see Fee
Schedule). Please call 425-430-7294 to verify the exact amount required. Checks should be
made out to the City of Renton and cannot be accepted for over the total fee amount.
Credit cards may also be used to pay required application fees. Fees are paid at Cashier on
the 1st Floor City Hall.
5.Project Narrative: Please provide a clear and concise description of the proposed project,
including the following:
Project name, size and location of site;
Land use permits required for proposed project;
Zoning designation of the site and adjacent properties;
Current use of the site and any existing improvements;
Special site features (i.e. wetlands, water bodies, steep slopes);
Statement addressing soil type and drainage conditions;
Proposed use of the property and scope of the proposed development;
For plats indicate the proposed number, net density and range of sizes (net lot area)
of the new lots;
Access;
Proposed off-site improvements (i.e. installation of sidewalks, fire hydrants, sewer
main, etc.);
Total estimated construction cost and estimated fair market value of the proposed
project;
Estimated quantities and type of materials involved if any fill or excavation is
proposed;
Number, type and size of any trees to be removed;
Explanation of any land to be dedicated to the City;
Any proposed job shacks, sales trailers, and/or model homes; and
Any proposed modifications being requested (include written justification).
For projects located within 100 feet of a stream or wetland, please include:
Distance in feet from the wetland or stream to the nearest area of work.
X
X
X
X
X
3
H:\CED\Data\Forms-Templates\Self-Help Handouts\Planning\Temporary Use Tier 2.doc Rev: 2/2017
For projects located within 200-feet of Black River, Cedar River, Springbrook Creek, May
Creek and Lake Washington please include the following additional information:
Distance from closest area of work to the ordinary high water mark;
Description of the nature of the existing shoreline; and
The approximate location of and number of residential units, existing and potential,
that will have an obstructed view in the event the proposed project exceeds a height
of 35-feet above the average grade level.
6.Environmental Checklist: Please ensure you have signed the checklist and that all questions
on the checklist have been filled in before making copies. If a particular question on the
checklist does not apply, fill in the space with “Not Applicable .”
7.Abatement Agreement: This agreement assures the temporary use will ultimately be
removed as required by the terms of the permit.
8.Construction Mitigation Description: Please provide a written narrative addressing each of
the following:
Proposed construction dates (begin and end dates);
Hours and days of operation;
Proposed hauling/transportation routes;
Measures to be implemented to minimize dust, traffic and transportation impacts,
erosion, mud, noise, and other noxious characteristics;
Any special hours proposed for construction or hauling (i.e. weekends, late nights);
and
Preliminary traffic control plan.
If your project requires the use of cranes, please contact the City’s Airport Manager at 425 -
430-7471 to determine whether Federal Aviation Administration (FAA) notification will be
required.
9.Neighborhood Detail Map: Please provide a map drawn at a scale of 1" = 100' or 1" = 200'
(or other scale approved by the Planning Division) to be used to identify the site location on
public notices and to review compatibility with surrounding land uses. The map shall
identify the subject site with a much darker perimeter line than surrounding properties and
include at least two cross streets in all directions showing the location of the subject site
relative to property boundaries of surrounding parcels. The map shall also show: the
property's lot lines, lot lines of surrounding properties, boundaries of the City of Renton (if
applicable), north arrow (oriented to the top of the plan sheet), graphic scale used for the
map, and City of Renton (not King County) street names for all street s shown. Please ensure
all information fits on a single map sheet.
Kroll Map Company (206-448-6277) produces maps that may serve this purpose or you may
use the King County Assessor’s maps as a base for the Neighborhood Detail Map. Additional
information (i.e. current city street names) will need to be added by the applicant.
N/A
X
X
X
4
H:\CED\Data\Forms-Templates\Self-Help Handouts\Planning\Temporary Use Tier 2.doc Rev: 2/2017
10.Site Plan: Please provide a fully-dimensioned plan sheet drawn at a scale of 1"=20' (or
other scale approved by the Planning Division). We prefer the site pla n be drawn on one
sheet of paper unless the size of the site requires several plan sheets to be used. If you are
using more than a single plan sheet, please indicate connecting points on each sheet.
The Site Plan should show the following:
Name of proposed project;
Date, scale, and north arrow (oriented to the top of the paper/plan sheet);
Drawing of the subject property with all property lines dimensioned and names of
adjacent streets;
Widths of all adjacent streets and alleys;
Location of all existing public improvements including, but not limited to, curbs,
gutters, sidewalks, median islands, street trees, fire hydrants, utility poles, etc.,
along the full property frontage;
Location and dimensions of existing and proposed:
1.structures
2.parking, off-street loading space, curb cuts and aisle ways
3.fencing and retaining walls
4.free-standing signs and lighting fixtures
5.refuse and recycling areas
6.utility junction boxes and public utility transformers
7.storage areas and job shacks/sales trailers/model homes
Setbacks of all proposed buildings from property lines;
Location and dimensions of all easements referenced in the title report with the
recording number and type of easement (e.g. access, sewer, etc.) indicated;
Location and dimensions of natural features such as streams, lakes, required buffer
areas, open spaces, and wetlands; and
Ordinary high water mark and distance to closest area of work for any project
located within 200-feet from a lake or stream.
11.Architectural Elevations: Please provide for each building and each building face (N, S, E, &
W) a 24” x 36” fully-dimensioned architectural elevation plan drawn at a scale of 1/4” = 1’
or 1/8” = 1’ (or other size or scale approved by the Planning Division). The plans must clearly
indicate the information required by the “Permits” section of the currently adopted
International Building Code (IBC) and RCW 19.27 (State Building Code Act, Statewide
amendments), including, but not limited to the following:
Identify building elevations by street name (when applicable) and orientation i.e.
Burnett Ave. (west) elevation;
Existing and proposed ground elevations;
Existing average grade level underneath proposed structure;
Height of existing and proposed structures showing finished roof top elevat ions
based upon site elevations for proposed structures and any existing/abutting
structures;
Building materials and colors including roof, walls, any wireless communication
X
N/A
5
H:\CED\Data\Forms-Templates\Self-Help Handouts\Planning\Temporary Use Tier 2.doc Rev: 2/2017
facilities, and enclosures;
Fence or retaining wall materials, colors, and architectural design;
Architectural design of on-site lighting fixtures;
Screening detail showing heights, elevations, and building materials of proposed
screening and/or proposed landscaping for refuse/recycling areas; and
Cross section of roof showing location and height of roof-top equipment (include air
conditioners, compressors, etc.) and proposed screening.
12.Floor Plans: Please provide a plan showing general building layout, proposed uses of space,
walls, exits and proposed locations of kitchens, baths, and floor drains, with sufficient detail
for City staff to determine if an oil/water separator or grease interceptor is required and to
determine the sizing of a side sewer.
13.Tree Retention/Land Clearing (Tree Inventory) Plan: Please provide a fully dimensioned
plan drawn by a certified arborist or a licensed landscape architect if ANY trees or
vegetation are to be removed or altered. The plan shall be based on finished grade, drawn
at the same scale as the project site plan with the northern property line at the top of the
paper, and clearly show the following:
All property boundaries and adjacent streets, location and dimensions of rights - of-
way, utility lines, fire hydrants, street lighting, and easements;
Location of all areas proposed to be cleared;
Location, species, and sizes of trees on or immediately abutting the site. This
requirement applies only to trees with a caliper of at least six inches (6"), or an alder
or cottonwood tree with a caliper of at least eight inches (8"), when measured at
fifty-four inches (54") above grade;
Clearly identify trees to be retained and to be removed;
Future building sites and drip lines of any trees which will overhang/ overlap a
construction line. Where the drip line of a tree overlaps an area where construction
activities will occur, this shall be indicated on the plan; and
Show critical areas and buffers.
14.Tree Retention Worksheet: Please provide a completed City of Renton tree retention
worksheet.
15.Arborist Report: Please provide an arborist report by a certified Arborist or a licensed
Landscape Architect that correlates with the Tree Retention/ Land Clearing Plan and
addresses the following:
Identification scheme used for each tree (e.g. tree number);
Species and size of each tree (caliper measured at 54 inches above grade);
Reason(s) for any tree removal (e.g. poor health, high risk of failure due to structure,
defects, unavoidable isolation (high blow down potential), unsuitability of species,
etc.) and for which no reasonable alternative action is possible (pruning, cabling,
etc.);
For trees proposed to be retained, a complete description of each tree' s health,
N/A
N/A
N/A
N/A
6
H:\CED\Data\Forms-Templates\Self-Help Handouts\Planning\Temporary Use Tier 2.doc Rev: 2/2017
condition, and viability;
For trees proposed to be retained, a description of the method(s)used to determine
the limits of disturbance (e.g., critical root zone, root plate diameter, or a case- by-
case basis description for individual trees);
A description of the impact of necessary tree removal to the remaining trees,
including those in a grove or on abutting properties;
The suggested location and species of supplemental trees to be used when required.
The report shall include planting and maintenance specifications; and
An analysis of retained trees according to Priority of Tree Retention Requirements
specified in RMC 4-4-130H.1.b.
16.Wetland Assessment: Please provide a map and a report if ANY wetlands are located on
the subject property or within 100 feet of the subject property. The wetland
report/delineation must be prepared by a qualified professional and include the
information specified in RMC 4-8-120D.23. In addition, if any alteration to the wetland or
buffer is proposed, a wetland mitigation plan is also required. See RMC 4-8-120D.23 for
plan content requirements.
17.Standard Stream or Lake Study: Please provide a report containing the information
specified in RMC Section 4-8-120D.19. In addition, if the project involves an unclassified
stream, a supplemental stream or lake study is also required. If any alteration to a water-
body or buffer is proposed a supplemental stream or lake study and mitigation plan are
also required. See RMC 4-8-120D.19 for plan content requirements.
18.Flood Hazard Data: Please provide a scaled plan showing the nature, location, dimensions,
and elevations of the area in question; existing or proposed structures, fill, storage of
materials, and drainage facilities. Also indicate the following:
Elevation in relation to mean sea level of the lowest floor (including basement) of all
structures;
Elevation in relation to mean sea level to which any structure has been flood -
proofed;
Certification by a registered Professional Engineer or Architect the flood-proofing
methods criteria in RMC 4-3-050G.4.c have been met; and
Description of the extent to which a watercourse will be altered or relocated as a
result of proposed development.
19.Habitat Data Report: If the project site contains or abuts a critical habitat per RMC 4-3-
050F.2.b, please provide a report containing the information specified in RMC 4-8-120D.8.
20.Geotechnical Report: Please provide a study prepared and stamped by a State of
Washington licensed Professional Engineer including soils and slope stability analysis, boring
and test pit logs, and recommendations on slope setbacks, foundation design, retaining wall
design, material selection, and all other pertinent elements.
N/A
N/A
N/A
N/A
N/A
7
H:\CED\Data\Forms-Templates\Self-Help Handouts\Planning\Temporary Use Tier 2.doc Rev: 2/2017
21.Utilities Plan, Generalized (sewer, water, stormwater, transportation improvements):
Please provide a plan drawn on 22" x 34" plan sheets using a graphic scale of 1" = 40' (or
other size or scale approved by the Planning Division) clearly showing all existing (to remain)
and proposed public or private improvements to be dedicated or sold to the public
including, but not limited to, curbs, gutters, sidewalks, median islands, street trees, fire
hydrants, utility poles, free-standing lighting fixtures, utility junction boxes, public utility
transformers, etc., along the full property frontage. The finished floor elevations for each
floor of proposed and existing (to remain) structures shall also be shown.
22.Drainage Control Plan: Please provide a plan drawn to scale and stamped by a Washington
State licensed Professional Engineer and complying with the requirements of RMC 4-6-030
and the King County Surface Water Management Design Manual, 2009 edition, as adopted
and amended by the City of Renton.
23.Drainage Report: Please provide a report stamped and dated by a State of Washington
licensed Professional Engineer complying with the requirements of the City of Renton
Drafting Standards, (RMC 4-6-030), the King County Surface Water Design Manual
(KCSWDM), 2009 edition, and the City of Renton Amendments to the KCSWDM, Chapters 1
and 2 as adopted by the City of Renton. The report shall contain the following:
Table of Contents;
Technical Information Report (TIR) Worksheet;
Section 1: Project Overview;
Section 2: Conditions and Requirements Summary;
Section 3: Offsite Analysis;
Section 4: Flow Control and Water Quality Facility Analysis and Design;
Section 5: Conveyance System Analysis and Design;
Section 6: Special Reports and Studies;
Section 7: Other Permit;
Section 8: Construction Stormwater Pollution Prevention Plan (CSWPPP) Analysis
and Design;
Section 9: Bond Quantities, Facility Summaries, and Declaration of Covenant; and
Section 10: Operations and Maintenance Manual.
All Plans and Attachments are subject to Electronic File Standards
REVIEW PROCESS: Once a complete land use application package has been accepted for initial review,
the Planning Division will post one notice of the pending application at or near the subject site and mail
notices to property owners within 300 feet of the project site. The proposal will be routed to other City
departments and other jurisdictions or agencies that may have an interest in the application. The
reviewers have two (2) weeks to return their comments to the Planning Division. In review of the
proposal, the Planning Division will ensure the following criteria have been addressed:
1.The temporary use will not be materially detrimental to the public health, safety, or welfare, nor
injurious to property or improvements in the vicinity of the temporary use; and
N/A
N/A
X
8
H:\CED\Data\Forms-Templates\Self-Help Handouts\Planning\Temporary Use Tier 2.doc Rev: 2/2017
2.Adequate parking facilities and vehicle ingress and egress are provided to serve the temporary
use and any existing uses on the site; and
3.Hours of operation of the temporary use are specified, and would not adversely impact
surrounding uses; and
4.The temporary use will not cause nuisance factors such as noise, light, or glare which adversely
impact surrounding uses; and
5.If applicable, the applicant has obtained the required right-of-way use permit.
After review of the proposal and any staff or public comment, the Planning Division will issue a decision.
The decision to approve, conditionally approve, or deny the proposal will be mailed to all persons listed
on the Master Application and all parties of record.
APPEAL AND RECONSIDERATION PROCESS FOR DECISIONS: Any person, including the applicant,
aggrieved by the granting or denial of an application, may make a written application for reconsideration
to the Reviewing Official within 14 calendar days of the date of the decision. After review of the request,
the Reviewing Official may take whatever action is deemed proper. The Reviewing Official’s written
decision on the reconsideration request will be mailed to all parties of record within 10 days from the
date the request was filed. If any party is still not satisfied after a reconsideration decision has been
issued, an appeal may be submitted within 14 days to:
The Hearing Examiner for Administrative decisions
The City Council for Hearing Examiner decisions
An appeal may be filed without first requesting reconsideration by the Reviewing Official; however, it
must be filed within 14 days of the date when the original decision was issued. See Renton Municipal
Code, Section 4-8-110 for further information on the appeal process and time frames.
BUILDING AND CONSTRUCTION PERMIT ISSUANCE AND INSTALLATION OF IMPROVEMENTS: In the
City of Renton, a Building Permit must be obtained to build buildings and structures. A Construction
Permit must be obtained to install utility lines, transportation improvements and undertake work in City
right-of-ways. Building and Construction Permits are separate permits.
Applicants may apply for building and construction permits concurrently with their request for a land
use application. However, the applicant should be aware any conditions of land use permit approval may
create a need for revisions to other permit applications whereby additional fees may be charged.
Refunds of building permit charges are not available.
If no appeals or reconsideration requests are filed within fourteen (14) days of the effective date of the
decision to approve the application, the applicant may obtain building and construction permits. A
construction permit for the installation of on-site and off-site utilities will be issued upon the review and
approval of civil engineering drawings by the Division’s Public Works Section and receipt of all applicable
development and permit fees. A building permit will be issued upon the Building Section’s approval of
building plans and receipt of all applicable fees.
EXPIRATION AND EXTENSIONS: Shall be as listed on the approved permit.
DEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425-430-7200
www.rentonwa.gov
LAND USE PERMIT MASTER APPLICATION
PROPERTY OWNER(S) PROJECT INFORMATION
NAME:
City of Renton
PROJECT OR DEVELOPMENT NAME:
King County Eastside Interceptor Section 2
Rehabilitation – Phase II
ADDRESS: 1055 S. Grady Way PROJECT/ADDRESS(S)/LOCATION AND ZIP CODE:
The project generally follows Logan Avenue N. The
northern terminus starts near Houser Way N, then
follows Logan Avenue N. to its southern terminus near
the intersection of N. 6th Street and Burnett Avenue N. CITY: Renton ZIP: 98057
TELEPHONE NUMBER: 425-430-6400 KING COUNTY ASSESSOR’S ACCOUNT NUMBER(S):
N/A
APPLICANT (if other than owner)
NAME:
Darlene Gaziano for King County
EXISTING LAND USE(S): Road right-of-way, Boeing parking
lot and staging area.
COMPANY (if applicable): King County Wastewater
Treatment Division
PROPOSED LAND USE(S): There would be no change in
land use.
ADDRESS:
201 S. Jackson Street, Suite 507
EXISTING COMPREHENSIVE PLAN MAP DESIGNATION:
Commercial mixed use
CITY:
Seattle
ZIP:
98104
PROPOSED COMPREHENSIVE PLAN MAP DESIGNATION
(if applicable) N/A
TELEPHONE NUMBER: 206-263-0562 EXISTING ZONING: Urban Center
CONTACT PERSON PROPOSED ZONING (if applicable): N/A
NAME: Darlene Gaziano SITE AREA (in square feet): 9,790 sq ft
COMPANY (if applicable): King County Wastewater
Treatment Division
SQUARE FOOTAGE OF PUBLIC ROADWAYS TO BE
DEDICATED: N/A
ADDRESS:
201 S. Jackson Street, Suite 507
SQUARE FOOTAGE OF PRIVATE ACCESS EASEMENTS:
Temporary Construction Easements of 65,651 sq ft
CITY:
Seattle
ZIP:
98104
PROPOSED RESIDENTIAL DENSITY IN UNITS PER NET
ACRE (if applicable) N/A
TELEPHONE NUMBER AND EMAIL ADDRESS:
206-263-0562
dgaziano@kingcounty.gov
NUMBER OF PROPOSED LOTS (if applicable)
N/A
NUMBER OF NEW DWELLING UNITS (if applicable):
N/A
1
KING COUNTY EASTSIDE INTERCEPTOR SECTION 2 REHABILITATION – PHASE II
TIER 2 TEMPORARY USE PROJECT NARRATIVE AND JUSTIFICATION
PROJECT NARRATIVE
Project name, size and location of site:
The name of the Project is the King County Eastside Interceptor Section 2 Rehabilitation - Phase
II (ESI2). The Project would consist of the rehabilitation of approximately 3,900 linear feet of
the 96-inch reinforced concrete wastewater pipe and eight (8) 48-inch diameter maintenance
holes mostly located within the Logan Avenue N. right-of-way between Lake Washington Blvd.
N. and Burnett Avenue N. (see Figure 1).
The project is needed due to severe corrosion of the pipeline as a result of exposure to
hydrogen sulfide gas. To rehabilitate the pipeline, sewer flow would be diverted via a
temporary bypass system and the pipeline would be rehabilitated in place using an in-situ liner
method called Linabond. The Linabond system results in a polyurethane coating inside of the
pipe to prevent further corrosion and can be installed using the existing maintenance holes
with the pipe in the dry.
Existing wastewater flows from upstream of the in-pipe work area would be pumped into a
bypass system to allow the Linabond system to be installed. Minimal local flows from side
sewer connections within the work area would continue to flow under the installation platform.
The bypass consists of the installation of high-density polyethylene (HDPE) piping that would
include three (3) 24-inch lines. The anticipated bypass pipeline route totals 4,200 feet. Most of
the bypass line would be located above ground either side by side or in a rack (see Figure 2).
Approximately 1,200 feet of trenched temporary piping would be located underground where
access to adjacent properties needs to be maintained (see Figure 3). There is also one
maintenance hole (R02-04) that was paved over and would need to be located and restored
before the lining work can occur.
At the upstream end of the Project, there would be an excavation (aka North Pit) to access the
existing pipe. A suction trench would be located downstream of maintenance hole RO2-08 at
the northern end of the alignment within the 200-foot segment of the pipeline previously
rehabilitated with Linabond. The top of the ESI2 pipeline would be exposed, and a window
would be cut from the top of the pipe to install the bypass pump suction piping (see Figure 4).
To shore the excavation, sheet piles, walers, and beams would be used to produce watertight
shoring. The soils within the excavation and within its vicinity would be chemically grouted to
further seal the excavation and provide structural stability. The North Pit would be
approximately 62 feet long by 17 feet wide and 9 feet deep.
2
The North Pit staging area will also consist of the bypass pumps and ancillary facilities. This
includes: 8 primary and 2 backup electric driven pumps; a utility meter, transformer and
transfer switch; a mobile diesel generator for backup power; two job trailers; and odor control
measures (see Figure 5). There may also be a Baker Tank in the event it is necessary to dewater
the excavation pit. The staging area also includes a parking area and material and equipment
storage area. At the southern end of the Project, another small excavation (aka South Pit)
would be dug to reconnect the bypass line. This excavation will be approximately 12 feet long
by 12 feet wide and 6 feet deep. There will also be a second staging area located in the Boeing
parking lot.
Land use permits required for proposed project:
• Tier 2 Temporary Use permit
• Noise Variance
• Work Hour/Day Variance
Zoning designation of the site and adjacent properties:
The project site and surrounding area is zoned Urban Center.
Current use of the site and any existing improvements:
The current use is a sewer line that consists of a 96-inch pipe located underground mostly in
the Logan Avenue N. right-of-way. The project starts at its northern end on Logan Avenue N.
near the intersection of Lake Washington Blvd. N and Garden Avenue N. The pipeline
alignment then follows Logan Avenue N. towards the southern end of the project where the
pipe crosses under a Boeing parking lot, and terminates in the Burnett Avenue N. right-of-way
nears its intersection with N. 6th Street.
The project will rehabilitate the sewer pipeline that has experienced severe corrosion from
contact with hydrogen sulfide gas in the wastewater.
Special site features:
The project is located in a high seismic hazard area.
Soil type and drainage conditions:
The soils in the project area are a mixture of fill and alluvium. The fill typically consists of silty
sand with varying amounts of gravel. Alluvium is located beneath the fill and consists of
interbedded sand with varying amounts of silt. The fill varies in thickness from nine to 13 feet.
The project occurs in an area that is almost 100 percent covered by impervious surface, thus
drainage from stormwater runoff is captured in the city’s stormwater collection system. It is not
anticipated that there would be any drainage concerns given the limited soil disturbance and that
the design groundwater level is at 9 feet below the surface.
3
Proposed use of property and scope of the proposed development:
There is no change in the proposed use of the property, which is to transmit wastewater
underground to the wastewater treatment plant.
Access:
Access to the project site is on Logan Avenue N, N. 6th Street, and Burnett Avenue N. There
would also be two temporary construction easements acquired for the project.
Proposed off-site improvements:
There are no off-site improvements proposed.
Total estimated construction costs:
The estimated construction cost of the project is $411,157.16.
Estimated quantities and types of materials involved for fill and excavation:
Total excavation:
• North Pit: 9,450 cubic feet
• South Pit: 900 cubic feet
• Bypass pipe trenches: 33,600 cubic feet (1,200 lineal feet @ 7 feet wide and 4 feet
deep average)
• Maintenance Hole 04: 50 cubic feet (5 feet x 5 feet square and 2 feet deep)
• Total: 44,000 cubic feet
• All excavations would be backfilled with the native material originally removed.
Number, type and size of any trees to be removed:
It is not anticipated that any trees would be removed. The notes on the construction plans
state that no trees shall be damaged or removed without prior approval from the City of
Renton.
Any land to be dedicated to the city:
There would be no land dedications.
Proposed job shacks:
Two temporary job trailers would be placed in the north staging area.
Any proposed modifications being requested:
Yes, the Tier 2 Temporary Use permit is being requested to establish two staging areas for the
project (see Figure 3). One at the north end and one near the south end. The northern staging
area (North Pit) is currently being used as a storage area for Boeing and is fully fenced. It would
$311,010.00.
4
be used for the pumping operation and job headquarters with parking for construction staff.
The southern staging area is located north of the Boeing parking lot and will be used to stage
equipment and material. King County has coordinated the use of these sites with the Boeing
Company.
JUSTIFICATION
1) The temporary use will not be materially detrimental to the public health, safety or welfare,
nor injurious to property or improvements in the vicinity of the temporary use.
The two staging areas would be fenced with a secure access for safety. The north staging area
would contain the job trailers, and construction staff that would monitor the pumping
operation would also ensure that the public is kept away from the operation.
The project would not affect other property or improvements in the vicinity as the operations
would be contained on the temporary use sites. Once the project is completed, the two sites
would be restored to their original conditions.
2) Adequate parking facilities and vehicle ingress and egress are provided to serve the
temporary use and any existing uses on the site.
The north and south staging areas would accommodate parking for construction staff and
vehicles and there would be adequate ingress and egress from Logan Avenue N.
3) Hours of operation of the temporary use are specified, and would not adversely impact
surrounding land uses.
The project construction would occur 24 hours a day, 7 days a week, and a variance request has
been made to accommodate this schedule. The aggressive schedule would minimize the
disruptions to surrounding land uses by reducing the amount of time that traffic and residences
are affected. It would allow the work to be coordinated so that road closures could occur
during nighttime hours and project work timed to not adversely affect access during shift
changes at Boeing.
4) The temporary use will not cause nuisance factors such as noise, light, or glare, which
adversely impact surrounding land uses.
The south staging area would produce some nuisance impacts as it is located very close to
single-family residences (the closest residences are approximately 50 feet and 150 feet from
the south excavation). Nighttime lighting would be necessary, but directed downward to limit
lighting effects. Noise would be generated from the movement of equipment and materials
and use of a generator, some of which could be minimized by limiting nighttime work in this
area and use of noise barriers.
Similarly, the north staging area would also generate noise and nighttime lighting effects, but
residences (apartments) are located farther away (approximately 525 feet) and these
5
apartments are newer structures with better insulation to minimize outside noise. The project
would implement several measures to control noise from the pumping operation including the
use of electrical pumps and noise barriers, which would not generate sound levels that exceed
the noise standards.
5) If applicable, the applicant has obtained the required right-of-way use permit.
Yes, there will be approval for right-of-way work obtained as part of the civil construction
permit. The City indicated that a separate right-of-way permit would not be necessary.
CONSTRUCTION MITIGATION DESCRIPTION
Proposed Construction Dates
The project is estimated to occur between March 1, 2019 and November 30, 2020.
Hours and Days of Operation
Construction would take place 24 hours a day and 7 days a week. A variance has been
requested for nighttime and weekend construction.
Proposed Hauling/Transportation Routes
Logan Avenue N. and Southport Drive N. would be used to access I-405.
Measures to be Implemented to Minimize Dust, Traffic, Transportation Impacts, Erosion, Mud,
Noise and Other Obnoxious Characteristics
The earth work is very minimal and the staging areas are impervious surface. The only likely
source of dust or erosion/mud would be from the soil stockpiles from the excavation. There
would be a silt fence erected around the piles and they would be covered with weighted down
plastic so that no dust, mud or erosion occurs.
Traffic would be controlled through the use of flaggers, signage, barriers, detours, etc.
Construction would be coordinated with Boeing shift changes so as not to impede access. A
traffic control plan is attached to this application.
The project would employ the use of electric pumps to minimize noise and will erect noise
barriers around the pumping operation in the north staging area.
Security lighting would be directed downward to limit light effects.
The contractor will also be required to prepare an environmental mitigation plan addressing:
site maintenance, waste disposal, street cleaning, dust, odor, light and noise control, traffic
control, water quality protection, tree and vegetation protection, spill prevention and spill
response, and historic/cultural resources protection (including an inadvertent discovery plan).
Any Special Hours Proposed for Construction or Hauling
6
Yes, construction is proposed during weekends and evening hours.
Preliminary Traffic Control Plan
A formalized traffic control plan (TCP) would be prepared consistent with the provisions of the
Washington State Manual on Uniform Traffic Control Devices and submitted to the city for
review (the TCP is in process). The TCP is anticipated to employ a number of measures to
control traffic including signs, barriers and flaggers. Some examples of signage include: Start
Road Work, End Road Work, One Lane Road Ahead, Road Work Ahead, Detour, Shoulder
Closed, Lane Closed, Sidewalk Closed, Road Closed to Through Traffic (local traffic only), Road
Closed Ahead, Detour Ahead, and Be Prepared to Stop. Signs with images such as arrows, lane
configuration diagrams, and pictures of flaggers would also be used. A number of barrier
devices may be employed such as traffic cones, striped wood Type 3 barricades, jersey barriers,
and yellow tape. Flagger and sign placement would be coordinated with the city inspectors.
The TCP would include conditions of approval. For example, changes in traffic control devices,
detours, or major road, bike lane, or sidewalk closures would trigger notifications to adjacent
property owners, emergency providers (fire, police, and ambulance), and other affected parties
(school buses, shift changes at Boeing, etc.) in advance of the work. Accommodations would be
made for pedestrian and cyclists when sidewalks, bike lanes or walkways would be impeded.
Any other conditions applied to the project by the city would be incorporated into the TCP.
Figure 1 - Neighborhood Detail Map
Gene Coulon
Memorial Beach
Park
Gene Coulon
Memorial Beach
Park
The Bristol at
Southport
Apartments
The Bristol at
Southport
Apartments
The Reserve
Apartments
The Reserve
Apartments
The Landing
Shopping
Center
The Landing
Shopping
Center
The Landing
Parking
Garage
The Landing
Parking
Garage
Boeing
Renton
Boeing
Renton
Sanctuary
Apartments
Sanctuary
Apartments
Boeing
Renton
Boeing
Renton
Kenworth
Truck Plant
Kenworth
Truck Plant
ESI Sewer Pipe
KC-WTD Manhole
ESI2 Rehab Project
Bypass System
Staging Area
Boeing
Gate D-9
Figure 2 - Bypass Pipeline Configurations
Figure 3 - Trenched and Open Bypass Segments
Bypass Staging Area
Equipment/Material
Staging Area
Bus Stop
Boeing Facility
Employee Entrance
Boeing
Gate D-9
Overland Piping on Grade
Shallow Trenched Piping
Standard Trenched Piping
Overland Piping on Racks within
Shoulder/Bike Lane
ESI Sewer Pipe
KC-WTD Manhole
ESI2 Rehab Project
1700 LF
890 LF
175 LF
1425 LF
BYPASS PIPING KEY
A
E
G
H
I
J
B
C
D
Bus Stop
Alternative Bypass
Piping Route
F
The Landing
Shopping
Center
The Landing
Shopping
Center
The Landing
Parking
Garage
The Landing
Parking
Garage
Boeing
Renton
Boeing
Renton
Boeing
Renton
Boeing
Renton
Kenworth
Truck Plant
Kenworth
Truck Plant
Figure 4 - Suction Trench Schematic North Staging Area
Cross Beam(s)
Coupon(s) Cut From Pipe Crown
For Installation Of Suction Lines
and Replaced Following Construction
Existing ESI2 Pipe
BNSF Fenceline
Waler
Existing Pile Cap
and Piles
Sheet Piling
Chemical Grouting
Ground Improvement
Between Pipe and
Sheet Piles
Existing Grade
Figure 5 - North Pit Layout
Pump
Suction Lines
3-24" Bypass
Discharge Lines
Limits of Lined Pipe
(200' from Manhole
RO2-08)
Pump Suction
Trench
Existing 96"
ESI Pipe
PSE Power Substation
Access to be Maintained
During Construction
Trailer Mounted
Odor Control Unit
Pump Staging Area
PSE Power Substation
Bypass Piping
LEGEND
Transformer +
Recommended
Clearance
Existing
PSE Pole
Portable Generator
Switchgear w/ ATS
Site Trailer
Site Parking
Pump Discharge
Material and
Equipment
Storage Area
Potential Baker Tank
and Dewatering
Equipment Area
EXHIBIT A
EASEMENT DESCRIPTION
TAX PARCEL NO. 088661-0020
TEMPORARY CONSTRUCTION EASEMENT
That portion of Lot 5B-1, Lakeshore Landing 2 BSP Lots 5A-5E Lot Line Adjustment,
City of Renton Lot Line Adjustment No. LUA-08-072-LLA as recorded in Volume 253
of Plats, Pages 80 and 81, under King County Recording No. 20080916900008, records
of King County, Washington; described as follows:
Commencing at the northeast corner of said Lot 5B-1;
thence along the easterly line of said lot, South 00°57’03” West 468.28 feet;
thence WEST 250.57 feet to the True Point of Beginning;
thence continuing WEST 80.00 feet;
thence NORTH 75.00 feet;
thence EAST 80.00 feet;
thence SOUTH 75.00 feet to the True Point of Beginning.
Containing: 6000 Square Feet, more or less.
EXHIBIT B attached and by this reference made a part hereof.
DRAFT
DRAFT
EXHIBIT A
EASEMENT DESCRIPTIONS
TAX PARCEL NO. 088661-0060
TEMPORARY CONSTRUCTION EASEMENTS
Those portions of Lot 6 of Boeing Lakeshore Landing Binding Site Plan, as recorded in Volume
225 of Plats at Pages 82 – 86, inclusive, under King County Recording No. 20041223000856,
records of King County, Washington; described as follows:
EASEMENT 1
Commencing at an angle point in the northwesterly line of said Lot 6, being the southwesterly
terminus of a course shown as “N 53°24’44” E 842.00’” on said plat;
thence along said northwesterly line, North 53°24’44” East 318.69 feet to a point hereinafter
referred to as Point “A”;
thence South 34°24’51” East 30.60 feet to the True Point of Beginning;
thence continuing South 34°24’51” East 40.00 feet to the northwesterly margin of Logan Avenue
North as it now exists and a point on a non-tangent curve, concave southeasterly and having a
radius of 980.00 feet;
thence along said margin and curve southwesterly 2.57 feet through a central angle of 0°09’01”;
thence tangent from said curve, continuing along said margin, South 55°18’09” West 42.77 feet
to the beginning of a tangent curve to the left and having a radius of 815.00 feet;
thence along said curve and margin southwesterly 14.66 feet through a central angle of 1°01’50”;
thence leaving said margin, non-tangent from said curve, North 34°24’51” West 26.50 feet;
thence North 37°55’30” East 45.52 feet;
thence North 55°10’48” East 16.62 feet to the True Point of Beginning.
Containing: 2104 Square Feet, more or less.
EASEMENT 2
Commencing at the hereinabove described Point “A”;
thence along the northwesterly line of said Lot 6, North 53°24’44” East 366.06 feet;
thence South 36°35’16” East 74.00 feet to an angle point on the southeasterly boundary of said
Lot 6;
thence along said boundary line, South 15°44’45” East 50.33 feet to the True Point of
Beginning;
thence continuing South 15°44’45” East 18.41 feet to the northwesterly margin of Logan Avenue
North as it now exists;
thence along said northwesterly margin through the following courses:
thence South 68°06’39” West 29.80 feet to a point on a non-tangent curve to the right and having
a radius of 638.00 feet, a radial line of said curve from said point bears North 23°17’49” West;
thence along said curve southwesterly 35.37 feet through a central angle of 3°10’36”;
thence tangent from said curve, South 69°52’47” West 3.41 feet;
DRAFT
EXHIBIT A
thence leaving said margin, North 29°10’58” West 8.98 feet;
thence North 60°49’02” East 72.27 feet to the True Point of Beginning.
Containing: 963 Square Feet, more or less.
EASEMENT 3
Beginning at the most northerly corner of said Lot 6;
thence along the northwesterly line of said lot through the following courses:
thence South 46°36’56” West 13.25 feet;
thence South 47°42’47” West 37.87 feet;
thence South 48°37’57” West 37.00 feet;
thence South 49°22’46” West 37.33 feet;
thence South 49°57’47” West 37.25 feet;
thence South 50°22’49” West 37.18 feet;
thence South 50°37’51” West 37.10 feet;
thence South 50°42’51” West 363.11 feet;
thence South 53°24’44” West 68.98 feet;
thence leaving said northwesterly line, South 39°04’36” East 20.34 feet;
thence North 50°26’05” East 104.47 feet;
thence South 10°26’00” West 132.08 feet to the southeasterly line of said Lot 6 and a point on a
non-tangent curve concave northwesterly and having a radius of 933.50 feet, a radial line of said
curve from said point bears North 21°59’22” West;
thence along said southeasterly line and curve northeasterly 32.35 feet through a central angle of
1°59’08”;
thence leaving said southeasterly line, non-tangent from said curve, North 10°26’00” East 140.41
feet;
thence North 50°47’06” East 46.84 feet;
thence South 39°52’56” East 18.33 feet;
thence North 50°30’02” East 141.51 feet;
thence South 38°19’39” East 90.35 feet;
thence South 87°00’41” East 20.24 feet to said southeasterly line of Lot 6 and a point on a non-
tangent curve concave northwesterly and having a radius of 933.50 feet, a radial line of said
curve from said point bears North 43°07’56” West;
thence along said southeasterly line and curve northeasterly 50.10 feet through a central angle of
3°04’29”;
thence continuing along said southeasterly line, tangent from said curve, North 43°47’35” East
290.47 feet;
thence North 46°12’25” West 109.09 feet to the Point of Beginning;
Excepting Therefrom all of Tract X of said Boeing Lakeshore Landing Binding Site Plan,
described as follows:
Commencing at the most easterly corner of said Lot 6;
DRAFT
EXHIBIT A
thence along said southeasterly line of Lot 6, South 43°47’35” West 165.01 feet;
thence North 43°20’11” West 97.12 feet to a point on a non-tangent curve concave southeasterly
and having a radius of 347.64 feet, a radial line of said curve from said point bears
South 43°20’11” East, said point being the True Point of Beginning;
thence along said curve southwesterly 60.82 feet through a central angle of 10°01’26”;
thence non-tangent from said curve, North 39°22’09” West 10.00 feet;
thence North 51°07’37” East 60.00 feet to the True Point of Beginning.
Containing: 55,584 Square Feet, more or less.
EXHIBIT B attached and by this reference made a part hereof.