FRANCHISE PERMIT APPLICATION
Published. 3/30/2017
TO THE APPLICANT: Submit an electronic copy of the plans with the Franchise Permit Application and the
Traffic Control Application to franchise permits@ rentonwa. ov. Permit cost is $360.50. Inspection fee for
trenching more than 60 lineal feet or installation of 6 or more poles will be billed at $60.00 per hour.
Franchise Agency: Comcast Cable Communications, LLC
Franchise Job Number: 184666
Contact Name: Rhonda Resnik
Phone: 253 686-7592
Email: rhonda_resnik@comcast,com
Job Site Address: 12858 144th Ave SE Project Name: KE16AB3x3 N RENTON
Description of work: Overlash 1300' of new 36ct fiber to existing poles. Proof and pull
520' of 36ct fiber through existing conduit underground.
Please check all that
❑ New Construction ❑ Repair/Relocate a Underground a Overhead Cl Sidewalk ❑ street
❑ Open Trench ❑ Bore # of feet:
Contractor Name- SEFNCO Communications, Inc.
Phone:
State Contractors License #- SEFNCC1850QD Clty of Renton Business License #: BL029666
"I certify that I am the owner or applicant's authorized agent and do hereby agree to abide to the terms and conditions set forth
under this permit and shall comply with the City of Renton's Trench Restoration and street Overlay Requirements. "
Signature
Date 11-13-2017
INSPECTIONS SHALL B9 REQUESTED 24 HOURS PRION TO COMMENCEMENT OF ALL WORK BY CALLING THE
INSPECTION LINE AT 425-430-7203 OR BY GOING TO MYBUILDINGPERMIT.COM
Jobs are required to be called in for job start, re -inspection and project final. Re -inspection fees are billed at X75/hour.
All Pre -Construction meetings shall be scheduled at a maximum of 14 days prior to the lob start date.
Plan Review/Development Engineering
Site Construction Inspector
Development Engineering Manager
Date
Date
Date
Approved as submitted
Pre -Construction Meeting required
F1 Approved with comments or redlines
F1 Camera Inspection of utilities required
Page I I Published: 3/30/2017