HomeMy WebLinkAboutMFP18006390DEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
Franchise Permit: MFP18006390
IVR Number: 18006390
Permit Informaon
Permit Name:Comcast Cable Franchise Permit
Address/Locaon :11/19/2018Application Date:3223059054Parcel Number:17816 108TH AVE SE
Permit Type:01/29/2019Issue Date:Franchise
Permit Work Class:01/29/2020Expiration Date:Minor Utility
Job Number:JT#303696Franchise Type:Cable
Description:Place 24ct fiber in 440' of existing Comcast underground system. Overlash for a total of 441' for 4 spans on existing
system. Restoration per City of Renton standards.
CONDITIONS OF OVERHEAD APPROVAL: 1. Any existing height violations within the Project Reach must be resolved
at the time of construction. New aerial lines within the Project Reach must have a minimum vertical clearance of 15’
6”. 2. Any abandoned or unused lines within the Project Reach must be removed at the time that construction is taking
place. 3. A traffic control plan must be separately submitted to the City, and no construction may take place until the
City has approved a traffic control plan. 4. The new aerial fiber lines within the Project Reach must be converted to
underground facilities in the future, at Comcast’s cost, when any one of the following events occurs: (1) any other
utilities are undergrounded within the Project Reach, (2) a joint use trench is proposed by a franchisee within the
Project Reach, in which case Comcast shall participate in the joint use trench installation for the purpose of
undergrounding its aerial lines, or (3) a conduit is made available within the Project Reach that will accommodate the
aerial lines. The new aerial lines must be undergrounded within one year, or approved otherwise by the City of
Renton Community and Economic Development Administrator or designee, from the first event triggering the
requirement to underground the aerial lines.
Contacts
Name Address PhoneTypeBilling
Comcast Cable Communication
Management & Comcast Cable
B: (215) 665-1700Applicant
Tom Donnelly
Comcast Business Communications
1701 Jfk Blvd, 32nd Floor
Philadelphia, PA 19103
B: (215) 286-7347
C: (215) 286-7557
Contact
Michael Cannon
Cannon Constructors Inc
406 Porter Way
Milton, WA 98354
B: (253) 922-2787Contractor
Business License Number: 41539Construction Contractor: CANNOCI055CS
CITY OF RENTON ROW 1055 S Grady Way
Renton, WA 98057-3232
Owner
Laurie Dietz
Comcast - Billing
1701 John F. Kennedy Blvd.
Philadelphia, PA 19103
H: (425) 741-5733Specialized
Billing
X
General Condions & Signature
Permission is hereby given for the work described on this permit according to the conditions hereon and according to the
approved plans and specifications pertaining thereto, subject to compliance with the Ordinance of the City of Renton.
This permit and plans must be posted at the job site at all times.
I hereby certify that no work is to be done except as described above and in approved plans, and that work is to conform to
Renton Trench Restoration and Street Overlay Requirements.
Call 425.430.7203 or go to: www.MyBuildingPermit.com one working day in advance to schedule an inspections and for ANY
work in the Right of Way.
Call 8 1 1 to locate underground utilities at least two full business days prior to any excavation.
In accordance with RCW 19.122.033(4) the permit holder is required to contact (Williams Northwest Pipeline at 425.868.1010)
(Olympic Pipeline at 206.510.0575) (Puget Sound Energy at 425.375.3397) to request a consultation with the transmission
pipeline company prior to performing any construction or excavation activities. This requirement to consult with the
transmission pipeline company is in addition to the requirement to Call before You Dig as required in RCW 19.122.
Page 1 of 2THIS PERMIT AND PLANS MUST BE POSTED AT THE JOB SITE AT ALL TIMES
DEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
Franchise Permit: MFP18006390
(Date)(Signature)
Page 2 of 2THIS PERMIT AND PLANS MUST BE POSTED AT THE JOB SITE AT ALL TIMES
MFP18006390Scott Warlick11/20/2018Justin Johnson11-29-2018
MFP18006390Justin Johnson11-29-20188:00 am to 3:00 pmMonday through Friday
MFP18006390
MFP18006390
MFP18006390
MFP18006390
MFP18006390
MFP18006390
MFP18006390
MFP18006390
MFP18006390
MFP18006390
MFP18006390
CANNON CONSTRUCTION,
406 PORTER WAY
MILTON WA, 98354
11/8/2018
City of Renton
1055 South Grady Way
Renton, WA 98057
RE: Aerial Variance Request for JT# 303696
To whom it may concern,
Cannon Construction has been contracted to design and engineer this project on behalf of Comcast
Cablevision. Comcast is applying for a variance request in order to upgrade their existing facilities.
Comcast proposed to over lash approximately 441’ of aerial fiber along the right of way of NE 10th St
between NE Sunset Blvd and Kirkland Ave NE. Please see maps and drawings for more details.
Comcast is requesting that the City of Renton approve this variance request based on the fact that the
requirements for undergrounding this proposed over lash will not cause substantial adverse impacts to
other persons or entities in the immediate area and will cause undue hardship.
1. Installation of undergrounding facilities will increase the total cost of construction roughly
15-25 times the amount of an aerial over lash on the existing Comcast strand.
2. Potential damage to underground facilities will be increased.
3. Over lash will not cause substantial adverse impact to other persons or entities in the
immediate area. Over lashing the cable will be accomplished in a few days, and the
residents will not notice any impact. Comcast will clean up the over lashed spans as
necessary and identify and remove and existing dead cables along this route.
4. The variance is necessary to prevent any undue hardship due to the increased construction
costs if forced to install the proposed extension underground.
5. The granting of the variance will not be materially detrimental to the public welfare because
Comcast does agree to underground the cable system, but they are waiving the obligation
into the future when all other utilities are underground to prevent an undue hardship
against Comcast currently.
Upon the granting of the Variance, Comcast will coordinate construction and traffic control as per your
requirements. Comcast and their contractors want to cooperate at the highest level and agree to adhere
to all provisions and requirements set forth by the City of Renton to insure safe installation and
maintenance of the proposed facilities.
If you have any further questions regarding this project, please contact Cody Shackett at (253) 864-4246
Thank you for your consideration in this matter.
MFP18006390
Cody Shackett
Construction Coordinator
Attachments:
1. Application for ROW permit
2. 11” x 17” Site plan
3. 11” x 17” Design plan
4. Traffic Control Plan
January 29, 2019
Cody Shackett
Comcast Cable Communications, LLC
410 Valley Ave NW
Puyallup, WA 98371
Via Email: owen_shackett@comcast.com
SUBJECT: Request for Undergrounding Exemption (JT#303696, MFP18006390, 17816 108th Avenue SE)
Dear Mr. Shackett:
The City of Renton has reviewed your request to grant Comcast an exemption from Renton Municipal
Code (RMC) 4-6-090(C) which states that all new electrical or communication facilities shall be required
to be installed underground, pursuant to the standards of the section of RMC.
Comcast proposes to have Cannon Construction overlash approximately 441 lineal feet of new 24-count
aerial fiber to existing Puget Sound Energy (PSE) poles beginning at the following two locations:
1. South side of NE 10th Street approximately 140 feet east of NE Sunset Boulevard continuing east
approximately 430 feet to an existing pole on the south side of NE 10th Street; and
2. Southwest corner of NE 10th Street and Jefferson Avenue NE continuing approximately 330 feet
northeast to an existing pole located on the on the east side of Jefferson Avenue NE.
ANALYSIS: The City has considered the request for an exemption from RMC 4-6-090(D)(1)(h) i and ii.
Ordinance 5720 grants Comcast, the right to install fiber optic cable and related appurtenances under,
along, over, below, through and across the streets, avenues and alleys of City of Renton within the right-
of-way of Renton. Section 3.4 of the franchise ordinance states that if all of the distribution lines all the
wireline service providers, such as telecommunications service providers, as defined in RCW 35.99.010, a
utility service provider or a Cable Operator (collectively “Service Providers”) in any portion of the Franchise
Area are underground, Grantee shall place its Cable System’s distribution cables underground within that
area; provided that such underground locations are actually capable of accommodating Grantee’s cable
and other equipment without technical degradation of the Cable Systems’ signal quality.
The proposal would utilize existing poles and attach to the existing Comcast aerial path. As minimum
vertical height clearance of 15’-6” would need to be provided for, and existing obsolete cable would need
to be removed; staff recommends these as conditions of approval. Therefore, the City is granting an
exemption with conditions, per RMC 4-6-090(D)(1)(h) i and ii which allows for extensions of existing
overhead communication facilities when there are continuing requirements for poles and it is not likely
that there will be undergrounding in the foreseeable future; and, when there are existing overhead
Comcast Job JT#303696
Page 2 of 2
January 29, 2019
electrical or communication facilities that will not be removed and the facilities that would have been
required to be removed are parallel to the facilities that will not be removed.
DECISION: The requested exemption from underground utility installation requirements (RMC4-6-090 (C)
as requested by the applicant is approved with conditions subject to the conditions below as the request
complies with exemption criteria of RMC 4-6-090(D)(1)(h) i and ii.
Conditions of Approval:
1. Any existing height violations within the Project Reach must be resolved at the time of
construction. New aerial lines within the Project Reach must have a minimum vertical
clearance of 15’-6”.
2. Any abandoned or unused lines within the Project Reach must be removed at the time that
construction is taking place.
3. A traffic control plan must be separately submitted to the City, and no construction may take
place until the City has approved a traffic control plan.
4. The new aerial fiber lines within the Project Reach must be converted to underground
facilities in the future, at Comcast’s cost, when any one of the following events occurs: (1) any
other utilities are undergrounded within the Project Reach, (2) a joint use trench is proposed
by a franchisee within the Project Reach, in which case Comcast shall participate in the joint
use trench installation for the purpose of undergrounding its aerial lines, or (3) a conduit is
made available within the Project Reach that will accommodate the aerial lines. The new
aerial lines must be undergrounded within one year, or approved otherwise by the City of
Renton Community and Economic Development Administrator or designee, from the first
event triggering the requirement to underground the aerial lines.
This decision to approve the exemption with conditions is subject to a fourteen (14) day appeal period
from the date of this letter per RMC 4-8-110. Any appeals of the administrative decision must be filed
with the City Clerk, along with the required appeal fee, by 5:00 pm, February 12, 2019.
Sincerely,
Brianne Bannwarth, PE
Development Engineering Manager
cc: C.E. “Chip” Vincent, CED Administrator
Gregg Zimmerman, PW Administrator
Jennifer Henning, Planning Director
Justin Johnson, Civil Engineer II
Scott Warlick, Engineering Specialist II
Holly Powers, Permit Technician
Pat Miller, Construction Inspection Supervisor
Franchise Permits