HomeMy WebLinkAboutMFP18006381DEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
Franchise Permit: MFP18006381
IVR Number: 18006381
Permit Informaon
Permit Name:Puget Sound Energy - Electric
Address/Locaon :11/19/2018Application Date:0088000224Parcel Number:16301 116TH AVE SE
Permit Type:11/26/2018Issue Date:Franchise
Permit Work Class:11/26/2019Expiration Date:Minor Utility
Job Number:101115706Franchise Type:Electric
Description:Remove existing 25 kVA transformer and install 37.5 kVA transformer at P01. At P02 remove existing bad order pole
and install new pole (P03) and secondary UG riser. At P01 to P03 install 1 run of 1/0 OH tpx wire. Open work pit at P03
and trench from P03 to M01. Install 1 run of 1/0 UG tpx wire from P03 to M01. Restoration per City of Renton
standards.
Contacts
Name Address PhoneTypeBilling
ANISH KUMAR
PUGET SOUND ENERGY - ELECTRIC
6905 S 228th St
Kent, WA 98032
B: (253) 208-2183Applicant
Vicki Henson
Potelco Inc
8001 212th St S
Kent, WA 98032
B: (253) 863-0484Contractor
Business License Number: 5109Electrical Contractor: POTELI*344O4
Construction Contractor: POTELI*227PL
CITY OF RENTON ROW 1055 S Grady Way
Renton, WA 98057-3232
Owner
ANISH KUMAR
PUGET SOUND ENERGY - ELECTRIC
6905 S 228th St
Kent, WA 98032
B: (253) 208-2183Specialized
Billing
X
General Condions & Signature
Permission is hereby given for the work described on this permit according to the conditions hereon and according to the
approved plans and specifications pertaining thereto, subject to compliance with the Ordinance of the City of Renton.
This permit and plans must be posted at the job site at all times.
I hereby certify that no work is to be done except as described above and in approved plans, and that work is to conform to
Renton Trench Restoration and Street Overlay Requirements.
Call (425) 430-7203 or go to: www.MyBuildingPermit.com one working day in advance to schedule an inspections and for ANY
work in the Right of Way.
Call 8 1 1 to locate underground utilities at least two full business days prior to any excavation.
In accordance with RCW 19.122.033(4) the permit holder is required to contact (Williams Northwest Pipeline at 425.868.1010)
(Olympic Pipeline at 206.510.0575) (Puget Sound Energy at 425.375.3397) to request a consultation with the transmission
pipeline company prior to performing any construction or excavation activities. This requirement to consult with the
transmission pipeline company is in addition to the requirement to Call before You Dig as required in RCW 19.122.
(Date)(Signature)
Page 1 of 1THIS PERMIT AND PLANS MUST BE POSTED AT THE JOB SITE AT ALL TIMES
DEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
Page 1 | Published: 3/30/2017
Planning Division | 1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425-430-7200
Email: franchisepermits@rentonwa.gov Website: rentonwa.gov
FRANCHISE PERMIT APPLICATION
Published: 3/30/2017
TO THE APPLICANT: Submit an electronic copy of the plans with the Franchise Permit Application and the
Traffic Control Application to franchisepermits@rentonwa.gov. Permit cost is $360.50. Inspection fee for
trenching more than 60 lineal feet or installation of 6 or more poles will be billed at $60.00 per hour.
Franchise Agency:
Franchise Job Number: Phone:
Contact Name: Email:
Job Site Address: Project Name:
Description of Work:
Please check all that apply:
☐ New Construction ☐ Repair/Relocate ☐ Underground ☐ Overhead ☐ Sidewalk ☐ Street
☐ Open Trench ☐ Bore # of feet:
Contractor Name: Phone:
State Contractors License #: City of Renton Business License #:
“I certify that I am the owner or applicant’s authorized agent and do hereby agree to abide to the terms and conditions set forth under this permit and shall comply with the City of Renton’s Trench Restoration and Street Overlay Requirements. ”
Signature Date
INSPECTIONS SHALL BE REQUESTED 24 HOURS PRIOR TO COMMENCEMENT OF ALL WORK BY CALLING THE
INSPECTION LINE AT 425-430-7203 OR BY GOING TO MYBUILDINGPERMIT.COM
Jobs are required to be called in for job start, re-inspection and project final. Re-inspection fees are billed at $75/hour.
All Pre-Construction meetings shall be scheduled at a maximum of 14 days prior to the job start date.
Plan Review/Development Engineering Date Approved as submitted
Pre-Construction Meeting required
Site Construction Inspector Date Approved with comments or redlines
Camera inspection of utilities required
Development Engineering Manager Date
Puget Sound Energy - Electric
101115706
Anish Kumar
253-208-2183
anish.kumar@pse.com
16301 116th Ave SE 98058 101115706
At P01: Crew to remove existing 25 kVA transformer and install 37.5 kVA transformer. At P02:
Remove existing bad order pole and install new pole (P03) and secondary UG riser. P01 to P03: Install 1-run
of 1/0 OH tpx wire. Developer to open work pit at P03 and trench from P03 to M01. (Continued below)***
Potelco Inc.253-208-2183
BL005109 Poteli*227PL
11/12/2018
MFP18006381
Scott Warlick 11/19/2018
Holly Powers 11/26/2018
CITY OF RENTON
TRAFFIC CONTROL PLAN
PROJECT NAME: PERMIT#
CONSTRUCTION COMPANY: PHONE#:
CONTACT NAME: PHONE#:
ADDRESS: CELL#:
E-MAIL ADDRESS: FAX#:
PROJECT LOCATION: N/E/S/W OF:
WORK TIME: APPROVED BY:
WORK DATE: APPROVAL DATE:
OFFICE COPY T-
CONTRACTOR
DEV. SERVICE, INSPECTION P. MILLER
DEV. SERVICE, PLAN REVIEW B. BANNWARTH
POLICE CHARLES KARLEWICZ
FIRE FIRE MARSHALL FS #13
Permit Holder agrees to all the following:
• Comply with all traffic regulations of the City of Renton and the State of Washington.
• Prepare a traffic control plan and obtain City approval of that plan. That plan shall be implemented for
all street and lane closures, and the plan shall be performed in compliance with the Manual on
Uniform Traffic Control Devices.
• Notify emergency services (253-852-2121) twenty-four (24) hours before any street or lane closures.
• Any lane or street closures not in conformance with the approved traffic control plan and/or without
notification of emergency services may result in receiving a citation for violation of R.C.W. 47.36.200
through 47.36.220, 9A.36.050 Reckless Endangerment, and other applicable State and City codes.
• Indemnify and hold harmless the City of Renton from any and all claims, actions, and judgments,
including all costs of defense and attorney’s fees incurred in defending against same, arising from and
related to implementation of the approved traffic control plans including claims arising from towing of
private vehicles and the acts of the Permit Holder’s agents and employees.
• The City of Renton shall be entitled, in its reasonable discretion, to settle claims prior to suit or
judgment, and in such event shall indemnify and hold harmless the City for any such claims paid,
including the City’s reasonable attorney’s fees and litigation costs incurred resulting from such claim.
• In the event any claim or suit is brought against City within the scope of this Agreement, Permit Holder
will pay for legal counsel chosen by the City to defend against same.
• Flagger and sign placement are subject to revision by the City Inspector on site, if needed to address
traffic or pedestrian safety or travel.
• By my signature herein, I acknowledge all the above requirements.
PRINT NAME: DATE:
SIGNATURE:
Reset FormPrint Form
101115706
PSE/Potelco Inc.
Michael Been 425-757-0550
6905 S 228th St, Kent, WA 98032
michael.been@pse.com
16301 116th Ave SE
TBD
12/3/2018
Anish Kumar 11/12/2018
MFP18006381
Scott Warlick
11/26/2018
8:00AM - 3:30PM
Monday - Friday
SKETCH
I
-- NORTH --
I
NOTES:
• Work Zone Traffic Control shall be in accordance with the Manual on Uniform Traffic Control Devices (MUTCD)
and shown by sketch or reference to WSDOT.
• The plan must be submitted to the City’s PW/Transportation Division for review and/or approval at least three
working days prior to work.
• Approved Temporary Traffic Control Plan must be at the work site during work hours.
• Contractor or entity must call Renton School District (425-204-4455) or any public/private agency to be affected
by a temporary lane or road closure.
• Complete assistance and accommodation shall be provided to all kinds of pedestrian traffic when sidewalk or
walkway is impeded.
• Total road closure lasting more than 24 hours is subject to the approval by the City Council.
• Any vehicle, equipment, barricade, or portable tow-away sign used within the work area must display a
company logo or any legally acceptable sign showing the company name, address, and telephone number at a
conspicuous place on the vehicle or equipment.
In the case of Temporary No Parking Zones, all the following apply in addition to previous:
• Contractor must complete form to show limits of Temporary No Parking Zone identifying barricade locations for
vacate parking or curb lane usage.
• Contractor must post notice of dates and time of Temporary No Parking Zone with at least two signs per block
72 hours in advance of effective date and time.
• The cover sheet of this Traffic Control Plan form must be attached to each Temporary No Parking Sign on the
project site.
• Temporary traffic control devices must be removed immediately when work is done or no construction activities
are going on. If deemed abandoned, City crews will remove and store them at the City’s maintenance shop
(3555 NE 2nd Street).
Crew to install 1-run of 1/0 UG tpx wire from P03 to M01. No pavement cuts anticipated. Restoration per
City of Renton standards.
16301 116th Ave SE
Renton
WA 98058 13131010
1111111515SE 163RD ST
SE 164TH ST 116TH AVE SESTOP
FLAGGER
STOP
FLAGGER
STOP
FLAGGER
BUSSTOPBEPREPAREDTOSTOPW3-4ROADWORKAHEADW20-1W20-7A100'100'100'BUSSTOPONE LANEROADAHEADW20-4ROADWORKAHEADW20-1W20-7A100'100'100'ONE LANE
ROAD
AHEAD W20-4200'200'X'ROAD
WORK
AHEAD W20-1W20-7AUSE MAXIMUM AVAILABLE
SPACE FOR SIGN
BEPREPAREDTOSTOPW3-4ROADWORKAHEADW20-1
100'100'BEPREPAREDTOSTOPW3-4ROADWORKAHEADW20-1100'100'
RESIDENT(S) WILL BE INFORMED
OF TEMPORARY DRIVEWAY
CLOSURE
EMERGENCY VEHICLES WILL BE
ALLOWED TO PASS WORK ZONE.
60
60P03P02
P01
SE 162ND ST
N
28" TRAFFIC CONE
LEGEND
TRAFFIC FLOW
SIGN LOCATION
FLAGGER
STOP
POLE
WORK VEHICLE/
FLASHING LIGHTS
RIGHT OF WAY
Notes:
1. All signs and spacing to conform to the
MUTCD and City of Renton standards.
2. All sidewalks, driveways, exits and egresses
shall be completely clear unless otherwise indicated.
3. Channelizing devices are 28" traffic cones.
Use traffic drums (barrels) with steady burning
Type C lights on all State State Routes and Hwys.
4. Sign size can be a minimum of 36" x 36" and
shall not obstruct pedestrian access.
5. Crew is required to leave a minimum of 11' for
traveling lane width.
6. Alert affected residents and businesses.
7. Work to take place between 9 a.m. and 4 p.m
unless otherwise specified. All work for arterials
and major roadways will be from 9 a.m. to 3 p.m.
Puget Sound Energy
Traffic Control Supervisor:
Yuriy S. Bashtovoy
Card No. 011687
Card Exp. 06/30/2022
Yuriy.Bashtovoy@pse.com
(425)424-6603
Job#101115706
16301 116th Av SE , Renton, WA
October 31, 2018
Sheet 1 of 1
Yuriy.Bashtovoy@pse.com
(425) 424-6603
PSE PUGET
SOUND
ENERGY
CHANNELIZATION
DEVICE SPACING
MPH
55/70
35/45
25/30
TAPER
40
30
20
TANGENT
80
60
40
MINIMUM TAPER LENGTH = L (feet)
LANE
WIDTHS
POSTED SPEED LIMITS
20 25 30 35 40 45
10
11
12
55 +
60/65
45/55
35/40
30
25
SIGN SPACING
"X"
800
500'
350'
200'
100'
MFP18006381
16301
116TH AVE SED/WPARCEL #
0088000224
ROW
60'
SE 163RD ST
ROW60'316963-166570 1/1
25 kVA 120/240V (A)
37.5 kVA 120/240V (A)
316952-166570
316969-166566
SLAG4248
336.4 MCMACSRABC336.4 MCMACSRABC336.4 MCMACSRABC
#4ACSR
CN316952-166570
316969-166566
SLAG4248
ROL
16 116TH AVE SE1/0 TPX316969-166566
SLAG4248
CUSTOMER SUPPLIED
3/4" CUBIC YARD SAND
4' X 4' WORK PIT
CUSTOMER SUPPLIED
1 CUBIC YARD 5/8" CRUSHED ROCK
CUSTOMER SUPPLIED
4' X 4' WORK PIT
CUSTOMER SUPPLIED
PSE INST. 1-RUN 1/0 UG TPX ± 90'
CUSTOMER SUPPLIED
1-3" SCH'L 40 DISCONTINUOUS PVC CONDUIT ± 50' (SCH'L 80 IN ROW)
SITE PLAN
N
Vicinity Map
N/A
ARE TO BE INSTALLED, CROSS SECTION DETAILS OF THE TYPICAL EROSION
STRUCTURES, & SPECIAL REQUIREMENTS FOR WORK IN SENSITIVE AREAS.)
EROSION & SEDIMENT CONTROL REQUIREMENTS
NOTES DETAILING WHERE EROSION OR SEDIMENT CONTROL STRUCTURES
(LOCAL JURISDICTIONS MAY HAVE ADDITIONAL REQUIREMENTS INCLUDING
0150.3200 TECHNIQUES FOR TEMPORARY EROSION & SEDIMENT CONTROL
EROSION & SEDIMENT CONTROL SHALL BE PER PSE STANDARD PRACTICE
& ANY ADDITIONAL LOCAL JURISDICTION REQUIREMENTS.
FOREMAN (CHECK BOX WHEN COMPLETED)
PSE Equipment LOCKED/SECURED & Work Area left in CLEAN/SAFE Condition.
Grid, Cable, and Switch numbers INSTALLED & VERIFIED.
Field Changes RED-LINED on As-built.
Indicate correct FUSE SIZE on As-built & VERIFY proper PHASE.
Foreman's Signature _______________________________________________
Print Name ___________________________________ Date ______________
Material VERIFIED and CHANGES noted on Paperwork.
Total PRIMARY Cable noted on As-built.
Company ID#'s RECORDED in correct location on As-built.
Deviations noted on the As-built and their reason.
I certify that the work performed meets PSE's standards and procedures
and that all quality requirements are met.
PSE
No
No
No
Yes
Yes
Yes
No
YesDeveloper
"Flagging Required"
"Outages Required"
"Locates Required"
SCALE: 1" = 50'
THIS SKETCH NOT TO BE RELIED UPON FOR EXACT LOCATION OF EXISTING FACILITIES
CALL 811 TWO BUSINESS DAYS BEFORE YOU DIG
For contacts below dial 1-888-CALL PSE (225-5773)
NEW CABLE & CONDUIT DIAGRAM
NOT TO SCALE
JOB SITE
JOB SITE
ASPLUNDH CONSTRUCTION CORP. - QA/QC T. MYER
00 1"2"
00 50'100'
POWER GENERAL NOTES - RESIDENTIAL PROJECT
10.
7.
6.
5.
4.
3.
2.
1.All materials to be installed in accordance with Puget Sound Energy's (PSE) standards. Any deviation from
this work sketch must be AUTHORIZED by PSE's Project Manager and NOTED on the Foremans' Copy.
All switching arrangements and/or outage arrangements are to be made with the Project Manager at least
three (3) working days in advance.
Contact the Utilities Underground Location Center (1-800-424-5555) at least 48 hours prior to commencing
work to get the underground facilities located.
STAKING: The customer will provide all staking (transformer, handhole, trench, grade, lot, pole, sidewalk,
etc.). See sketch and details for locations. Equipment locations must be approved by the Project Manager.
SITE PREPARATION: The work area will be at or near finished grade, clear of trench spoils or construction
materials which would restrict construction and/or equipment access, before work can begin.
Roads shall be paved or have a compacted , crushed rock base in place.
CLEARANCES: Transformers require a minimum of 6 feet from fire fighting equipment, 10 feet from
combustible walls, overhangs, doors, and windows, and a minimum of 5 feet from the back of curb (or guard
posts will be required per PSE standards). All conduits and vaults are to be at least 5 feet away from water,
storm and sewer lines when paralleling them in the right of way, and at least 1 foot when crossing them, or
as required by your local municipality.
All work is to be done in accordance with local municipal and county permit requirements as applicable.
Inclement weather conditions may cause delays in construction times and dates.
EXCAVATION: The customer is to provide all trenching, backfill, vault excavations, compaction and
restoration per this sketch and per PSE standards. A minimum protective cover of 36" is required over
PSE's primary voltage equipment and 24" is required of PSE's secondary voltage equipment. The customer
will provide any and all shoring or they will side slope the trench to 1:1.
8.
9.
CUSTOMER DEVELOPMENT NOTES:
A PRE CONSTRUCTION MEETING IS REQUIRED WITH YOUR PROJECT MANAGER PRIOR TO STARTING ANY SITE
WORK.
CUSTOMER IS RESPONSIBLE FOR ALL TRENCHING, SELECT BACKFILL, COMPACTION & RESTORATION PER PUGET
SOUND ENERGY STANDARDS & LOCAL MUNICIPALITY.
**DEVELOPER NEEDS TO FOLLOW ALL TRENCH DETAILS ON SELECT BACKFILL**
CUSTOMER IS RESPONSIBLE FOR THE FOLLOWING:
CROSSING/BORING.
-OPEN TRENCH OR BORING FOR CROSSINGS ARE ALLOWED PER LOCAL MUNICIPALITY PERMIT
REQUIREMENTS.
-CROSSINGS IN RIGHT OF WAY MUST BE SCHEDULED WITH PROJECT MANAGER PRIOR TO
CONSTRUCTION.
-PROJECT MANAGER OR DESIGNATED REPRESENTATIVE MUST BE ON SITE DURING CONSTRUCTION
WORK IN RIGHT OF WAY.
-EXCAVATION CONTRACTOR MUST BE LICENSED AND BONDED TO PERFORM WORK IN RIGHT OF WAY.
VAULTS & WORK PITS.
-REQUIRED TO PROVIDE 4' X 4' WORK PIT & 1 CUBIC YARD 5/8" CRUSHED ROCK AT P03
-REQUIRED TO PROVIDE 4’ X 4’ WORK PIT & 3/4 CUBIC YARD OF SAND AT M01
TRENCHING & CONDUIT.
-INSTALL ± 5' OF 1-3" SCH'L 80 GREY PVC CONDUIT FROM P03 TO PROPERTY LINE AND INSTALL ± 45' OF 1-3"
SCH'L 40 GREY PVC CONDUIT TO CONTINUE FROM PROPERTY LINE TO M01 .
-REQUIRED TO PROVIDE AND INSTALL A 3/8" NON-POLY PULL ROPE IN ALL OF THE CONDUITS.
JOB SITE READINESS.
-JOB SITE NEEDS TO BE 100% READY FOR INSPECTION 5 BUSINESS DAYS PRIOR TO
CONSTRUCTION DATE.
-ALL WORK IN RIGHT OF WAY MUST BE COORDINATED WITH PROJECT MANAGER AND LOCAL
MUNICIPALITY.
-ALL TRENCH, AND LOCAL ELECTRICAL MUNICIPALITIES AKA "L&I, CITY", INSPECTIONS MUST BE
COMPLETED 5 BUSINESS DAYS PRIOR TO SCHEDULED CONSTRUCTION DATE.
-REQUIRED TO OPERATE AND PROVIDE EQUIPMENT TO PUMP OUT WATER FOR WORK PITS, VAULTS &
TRENCH AT ALL TIMES.
-REQUIRED TO HAVE EXCAVATION EQUIPMENT AND BE ON SITE THE DAY OF CONSTRUCTION TO COMPLETE
BACKFILLING.
- IF A SECOND INSPECTION IS REQUIRED, ADDITIONAL FEE'S WILL BE APPLIED.
-PLEASE REVIEW THE CITY OR KING COUNTY TRENCHING REQUIREMENTS UNDER THE PERMIT.
-IF A PRE-CON IS REQUIRED BY THE CITY, COUNTY OR W.S. DOT A PSE PROJECT MANAGER WILL SET-UP AND
SCHEDULE A MEETING WITH THE MUNICIPALITY BEFORE ANY EXCAVATION OR INSTALLATION BEGINS .
SITE SPECIFIC NOTES
AT P01: 316963-166570
-EXISTING POLE TO REMAIN
,167$//67,5583%2/7(' +27&/$03 7$3$0,'2254100 & 2153100)
-REMOVE (1) EX. 25kVA TRF
-INSTALL (1) 37.5kVA OH TRF 120/240v W/ LB C/O (FUSE @ 15T) PER STD 6025.1000 (TRFPXF)
AT P02: 316952-166570
-REMOVE EXISTING B/O 45' POLE
(POLE TO BE CHARGED TO 108109563)
AT P03: 316969-166566
-INSTALL NEW 45' CL-4 DISTRIBUTION POLE W/ GROUNDS PER STD 6031.1000 (PD454)
(POLE TO BE CHARGED TO 101115707)
-INSTALL (1) 3" SEC RISER ON NEW STANDOFF BRACKETS PER STD 6042.1000 (RIS3CSS)
BBB
$&78$/
M01 AT "16301": NEW METER BASE
-INSTALL 200A METER
SPAN SPECIFIC NOTES
P01 TO P03:
,167$//5812+73;
BBB
ACTUAL
P03 TO M01:
,167$//5818*73;
BBB
$&78$/
___
___
___
___
METER DETAIL @ M01
SCALE: NONE
32"
Typical
24"
Min
24"-36"
4'Top View
Electric & Joint Utility
Work Pit Dimensions
36"
Min
Drainage Pipe
12" Minimum Clearance
from Gas Service Lines
Conduit Depth
24" to 36" Max
Regulator
Gas Meter
Assembly
48"
4'8"
Service (Permanent Detail:)
Not to Scale
Conduit
Ends
Closed
4'8"
24" Min
36" Typical
3'
To Trench
Property Line
Conduit Stakes
Customer Provided
3" Schedule 40 Grey PVC
Power Cable Conduit
Customer Provided
Gas Service Line Conduit
3" Conduit Service Riser
Customer Provided
Elec. Mtr Base
Elec Mtr
utility provided
Gas Meter
Relief Vent
Building Wall
Elec. Mtr
Vent
Utility
Provided
Seal
24"-36"
UTILITY POLE EROSION CONTROL DETAIL
TOP VIEW
DRY DRAINAGE DITCH or DRY VEGETATED SITE
SLOPE
Place gravel bags for
Sediment Trap
Place straw mulch
on disturbed areaExcavated or
Augered Hole
Pole
SLOPE
Not to scale Drainage ditches or Dry vegetated sites
Phone & TV
Excavated Dirt Pile
Final Grade
24" Min
48"
Max
18"
Backfill for SCH'L 40 Conduit
12" Min
Separation
6" or 12" of sand, 5/8" minus
3" of sand, 5/8" minus, or clean backfill bedding
JOINT TRENCH DETAIL
36"
Min
Cover
ROADSIDE
Typical To Excavated Dirt Pile
(No Rocks over 10" Diameter)
or clean backfill shading
SCH'L 40 Grade Conduit
DB 120 (NTS)
- A 6" layer of sand, 5/8" minus, or clean shading is allowed when excavated native material
contains rocks no larger than 8" in diameter.
Trench and backfill requirements for electric line extension trenches (No PSE gas)
- A 12" layer of sand, 5/8" minus, or clean shading is required when excavated native material
contains rocks up to 10" in diameter.
FLOW DIRECTION
LAY 8" BOTTOM SKIRT ON TOP OF NATIVE SOIL,
SECURE WITH PEA GRAVEL BAGS.
6'
3'
8"
TECHNIQUES FOR EROSION AND SEDIMENT CONTROL
SILT FENCE DETAIL
Not to Scale 0150.3200
Removed at site:
Grid Number:
kVA Rating:
Foreman to redline the following information
TRANSFORMER REMOVAL
Company ID#:
Primary phase connected to:
Tested Secondary Voltage
P01
316963-166570
25kVA
Installed at site:
Grid Number:
kVA Rating:
Foreman to redline the following information
TRANSFORMER INSTALLATION
Company ID#:
Primary phase connected to:
Tested Secondary Voltage
Material ID#:
P01
316963-166570
37.5kVA
6211300
Field Face
Quadrant
Road Face
Quadrant
Climbing
Space
5" Min
CL Direction of Vehicular TrafficCL
TOP VIEW
Standoff Bracket
15" Min Length
Conduit Clamp
Conduit
CONDUIT RISER PLACEMENT DETAIL (P03)
SCALE: NONE
4'x4' Work Pit
CIRCUIT LOADING TABLE
AS OF
EXIST. PEAK LOAD
EST. NEW LOAD
TOTAL
CIRCUIT:
A PHASE B PHASE C PHASE
ROL-16
06/2018
168.00 176.00 170.00
1.75 0.00 0.00
169.75 176.00 170.00
UTILITIES
CONTACT
PHONE#
COUNTY
1/4 SEC
U-MAP NO (POWER)
OP MAP
Emer Sect Gas Wk Ctr POWER WK CTR
PLAT MAP
JOINT FACILITIES ARRANGEMENTS
DRAWN BY
CHECKED BY
APPROVED BY
FOREMAN #1
FOREMAN #2
MAPPING
INCIDENT MAOP
Gas Order Elect Order
SCALE PAGE
ENGR - POWER
ENGR - GAS
FUNCTION
PROJECT MGR
PERMITREAL ESTATE/EASEMENT
2
1
REV#
3
DATE DESCRIPTIONBY
CONTACT PHONE NO DATE
OH CKT MAP CIRCUIT NOUG CKT MAP
M. BEEN 425-757-0550 10/30/18
M. BEEN 425-757-0550 10/30/18
E. SCHOTT 714-893-2405 10/30/18
N/A N/A
SIGNATURE GENERAL CONSTRUCTION INC
TRF UPGRADE, OH LINE ADDITION
16301 116TH AVE SE, RENTON, WA 98058
N/A N/A
N/A 101115706
AS NOTED 1 OF 1
KING N/A N/A CSPSKEIN
NE 29-23N-05E N/A N/A
2305E113 2305E136 2305E113 ROL-16
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A N/A N/A
N/A N/A N/A
N/A N/A N/A
E-Mail:
Cell Phone:
Project Manager Contact Information:
Manager:MICHAEL BEEN
425-757-0550
MICHAEL.BEEN@PSE.COM
GAS
PHONE
CABLE TV
PROJECT PHASE
PWR
NOTIF#ORDER#101115706SCALE: 6" = 1 MILE
OVERHEAD CIRCUIT MAP 2305E136
Owner / Developer Contact Info
officeATTN:
SIGNATURE GENERAL CONSTRUCTION INC
14208 4TH AVE S
BURIEN, WA 98168
SARANJEET SHAGLANI 206-898-6775
CIRCUIT FEET ADDED:
SQ. FOOTAGE:
PANEL SIZE:
HEAT TYPE:
EST. DEMAND:
LRC:
% V. DROP:
% FLICKER:
0'
4,012 SQ FT
200A
NATURAL GAS
12kW
112A
2.8%
3.7%
RETIREMENT POLE TABLE
SITE
#
POLE DATA POLE TRANSFERS REMARKS
GRID #HEIGHT CLASS YEAR XFMR CO. ID#TOPPED RMVD TEL TV FIBER ST. LIGHT (ADDITIONAL INFORMATION)
P02 316952-166570 45 UNK 1958
POLE TABLE (NEW)
Site
#
Pole Data
Grid #Height Class Year Remarks / Location Ref.
P03 316969-166566 45 4
506305375 101115706Superior
108109562
583060637
101115707
108109563
593201010
101115708
108109564
BO Pole Replacement
506561445Service
MFP18006381
TO: City of Renton
RE: PSE Job Number 101115706
TYPE OF WORK:
Install a new overhead 37.5 kVA transformer at pole 316963-166570 and remove old 25
kVA transformer. Replace bad order pole (316952-166570). Install an additional run of
conductor between pole 316963-166570 and the replaced pole. The service for the house
will be overhead to underground.
LOCATION OF WORK:
In front of 16235 116th Ave SE (overhead distribution poles and conductor that will serve
a new house at 16301 116th Ave SE)
SCOPE OF WORK:
At location P01 (316963-166570) as shown on the attached copy of the worksketch, PSE
is requesting exemption to install new OH transformer and to remove the old OH
transformer in order to serve “16301 116th Ave SE”. We will also be replacing the pole at
P02 and adding an additional run of conductor between P01 and P02. A secondary
service riser will be installed on the new pole for the new underground service for the
house. We have also submitted the design for our approval process and traffic control
plans for this work.
Please feel free to contact me if you have any questions
Sincerely,
Michael Been
Puget Sound Energy
Project Coordinator
Customer & System Projects – NCC Electric, South King
Cell: (425) 757-0550
Michael.Been@pse.com