HomeMy WebLinkAboutAdden 1Renton Avenue South Resurfacing ADDENDUM NO. 1
TED4003844 January 29, 2019
Page 1 of 5
Addendum No. 1
Renton Avenue South Resurfacing
Federal Aid Number: STP(UL)‐1201(023)
Date of Issue: January 29, 2019
Bid Due Date: February 5, 2019 (REMAINS UNCHANGED)
Date of Bid Opening: February 5, 2019 (REMAINS UNCHANGED)
ATTENTION: ALL BIDDERS AND PLAN HOLDERS:
The Bid Documents for the above‐named project are modified as described below. Bidders
shall take this Addendum into consideration when preparing and submitting their bids.
Bidders shall attach this addendum to their copy of the Contract Documents, and shall
acknowledge receipt of this Addendum on the Proposal Signature Page. A Proposal may be
considered irregular and may be rejected if the receipt of Addenda is not acknowledged. A
Proposal will be considered irregular and will be rejected if the Schedule of Prices included in
this Addendum is not completed and submitted with the Proposal.
THE CONTRACT DOCUMENTS ARE MODIFIED AS FOLLOWS:
1. PROPOSAL – SCHEDULE OF PRICES
REPLACE the Schedule of Prices in the Proposal (5 pages) with the revised Schedule of Prices
(5 pages) attached to this Addendum. The Schedule of Prices was revised to reflect the
following:
Item No. 25 “ADJUST MANHOLE” quantity was revised.
Item No. 26 “ADJUST CATCH BASIN” quantity was revised.
Item No. 48 “PLASTIC CROSSWALK LINE” quantity was revised.
Item No. 53 “LANDSCAPE BLOCK WALL” quantity was revised.
2. SPECIAL PROVISIONS
The following special provision sections are revised for this contract as follows:
Section 2‐09.3(1) General Requirements, located on page SP 2‐11, line 1 is
supplemented as follows:
Renton Avenue South Resurfacing ADDENDUM NO. 1
TED4003844 January 29, 2019
Page 2 of 5
If the minimum vertical distance between the existing water line and the new utility
pipe is less than 6‐inches and such installation is approved by the Water Utility, a
foam pad shall be placed between the pipes.
The pad shall be O.D. x O.D. x 2.5 inches thick minimum or as required to protect the
pipes.
The above O.D. is equal to the outside diameter of the larger pipe.
The pad shall be a polyethylene foam plank per Section 9‐05.52.
Section 9‐05.52 Foam Plank , located on page SP 9‐57, line 25 is added as follows:
9‐05.52 Polyethylene Foam Plank
(******)
Section 9‐05.52 is a new section:
Foam plank for utility separation shall be a durable polyethylene closed cell foam
plank. It shall meet the following material specifications:
Renton Avenue South Resurfacing ADDENDUM NO. 1
TED4003844 January 29, 2019
Page 3 of 5
3.PLANS (VOLUME 2 OF 2)
REPLACE Site Preparation & TESC Construction Note 2 on Sheets 4/TE‐1 through 8/TE‐5 with
the following:
“FURNISH AND INSTALL HIGH VISIBILITY SILT FENCE PER DETAIL, SHEET 9/TE‐6”
REPLACE High Visibility Fence Standard Plan I‐10.10‐01 on Sheets 9/TE‐6 with the following:
High Visibility Silt Fence Standard Plan I‐30.17‐00
DELETE Paving Note 5 from the Plan view on sheet 15/RD‐1 near Sta 101+00 RT and near Sta
9+17 RT.
DELETE Paving Note 10 from the Plan view on sheet 15/RD‐1 near Sta 10+35 RT and at Sta
11+70 LT.
DELETE Paving Note 10 from the Plan view on sheet 16/RD‐2 near Sta 12+30 RT and Sta
16+65 RT and Sta 16+90 LT.
ADD Paving Note 10 in the Plan view on sheet 16/RT‐2 at the existing catch basin near Sta
200+60 LT.
REPLACE Paving Note 15 in the Plan view on sheet 16/RT near Sta 13+10 RT with Paving
Note 13.
DELETE Paving Note 10 from the Plan view on sheet 17/RD‐3 near Sta 21+10 RT and Sta
22+80 LT, Sta 24+25 LT, Sta 24+95 LT, 26+45 LT and Sta 27+65 LT.
DELETE Paving Note 10 from the Plan view on sheet 18/RD‐4 in its entirety.
DELETE Paving Note 5 from the Plan view on sheet 18/R‐4 in its entirety.
DELETE Paving Note 10 from the Plan view on sheet 19/RD‐5 in its entirety.
DELETE Paving Note 5 from the Plan view on sheet 19/RD‐5 near Sta 36+00 RT.
REPLACE Channelization Note 10 on sheets 33/CH‐1 to 37/CH‐5 with the following:
“CONTRACTOR SHALL PAINT ISLAND CURBS WHITE WHERE LOCATED ALONG THE RIGHT‐
HAND EDGE OF THE TRAVEL LANES, AND SHALL PAINT ISLAND CURBS YELLOW WHERE
LOCATED ALONG THE LEFT‐HAND EDGE OF THE TRAVEL LANES.”
Renton Avenue South Resurfacing ADDENDUM NO. 1
TED4003844 January 29, 2019
Page 4 of 5
REPLACE General Note 3 on sheets 33/CH‐1 to 37/CH‐5 with the following:
“ALL PAVEMENT MARKINGS SHALL BE THERMOPLASTIC UNLESS INDICATED
OTHERWISE."
DELETE the plastic crosswalk lines from the S 132nd Street leg of the Renton Ave S/132nd
Street intersection on sheet 34/CH‐2.
DELETE the R1‐6A signs from the median island at the Renton Ave S/132nd Street
intersection on sheet 34/CH‐2.
ADD the following sentences to the end of General Note #3 on sheet 34/CH‐
“NOTE PEDESTRIAN SIGNAL HEAD 29 IS MOUNTED ON POLE #4 (NOT POLE #3 AS
SHOWN ON 138.2). WIRING SHALL BE ADJUSTED ACCORDINGLY.”
REPLACE Legend Item “DECORATIVE SIGNAL POLE, TYPE PPB OR I” on sheet 44/TS1 with the
following:
“DECORATIVE SIGNAL POLE, TYPE PPB”.
SHIFT pedestrian signal head #29 on sheet 44/TS1 from signal pole #3 to signal pole #4.
REPLACE Construction Note #3 on sheet 44/TS1 with the following:
“NOT USED”.
ADD the following to the end of General Note #2 on sheet 44/TS1:
“, EXCEPT SIGNAL HEAD ASSIGNMENT NOTE #2 SHALL STATE MOUNTING TYPE “E”
INSTEAD OF MOUNTING TYPE “D”.”
DELETE Conduit Run 16 from the plan on sheet 44/TS1.
SHIFT pedestrian signal head #29 on sheet 45/TS2 from signal pole #3 to signal pole #4 in
the NE Corner Detail.
REPLACE Construction Note #3 in the NE Corner Detail on sheet 45/TS2 with Construction
Note #2
REPLACE Wire Note #3 in the NE Corner Detail on sheet 45/TS2 with Wire Note #4.
ADDENDUM NO. 1
Renton Avenue South Resurfacing
Page 1 of 5R
Schedule of Prices
2018
ITEM
NO.ITEM DESCRIPTION SPEC.
SECTION UNIT QUANTITY UNIT PRICE*EXTENSION
1 Unexpected Site Changes (1‑04.4(1))CALC 1 $10,000.00 $10,000.00
2 Record Drawings (Minimum Bid $500)(1‑05.18)LS 1
3 Roadway Surveying (1‑05.4)LS 1
4 Licensed Surveying (1‑05.4)FA 1 $2,000.00 $2,000.00
5 ADA Feature Surveying (1‑05.4)LS 1
6 SPCC Plan (1‑07.15(1))LS 1
7 Mobilization (1‑09.7)LS 1
8 Portable Changeable Message Sign (1‑10.5)HR 3,720
9 Project Temporary Traffic Control (1‑10.5)LS 1
10 Clearing and Grubbing (2‑01.5)AC 0.21
11 Removal of Structures and Obstructions (2‑02.5)LS 1
12 Roadway Excavation, Incl. Haul (2‑03.5)CY 310
13 Gravel Borrow, Incl. Haul (2‑03.5)TN 110
14 Unsuitable Foundation Excavation, Incl. Haul (2‑03.5)CY 10
15 Locate Existing Utilities (2‑09.5)LS 1
16 Controlled Density Fill (2‑09.5)CY 10
SCHEDULE OF PRICES
Renton Avenue South Resurfacing
ALL ENTRIES SHALL BE WRITTEN IN INK OR TYPED TO VALIDATE BID
SCHEDULE A - ROADWAY RESURFACING
NOTE: Unit prices for all items, all extensions, and total amount of bid shall be shown. Enter unit prices in numerical figures only, in dollars
and cents to two (2) decimal places (including whole dollar amounts). All figures must be clearly legible. Bids with illegible figures in the
Unit Price column will be regarded as nonresponsive and rejected. Where conflict occurs between the unit price and the total amount
specified for any item, the unit price shall prevail, and totals shall be corrected to conform thereto.
ADDENDUM NO. 1
Renton Avenue South Resurfacing
Page 2 of 5R
Schedule of Prices
2018
SCHEDULE OF PRICES
Renton Avenue South Resurfacing
ALL ENTRIES SHALL BE WRITTEN IN INK OR TYPED TO VALIDATE BID
NOTE: Unit prices for all items, all extensions, and total amount of bid shall be shown. Enter unit prices in numerical figures only, in dollars
and cents to two (2) decimal places (including whole dollar amounts). All figures must be clearly legible. Bids with illegible figures in the
Unit Price column will be regarded as nonresponsive and rejected. Where conflict occurs between the unit price and the total amount
specified for any item, the unit price shall prevail, and totals shall be corrected to conform thereto.
17 Crushed Surfacing Top Course (4‑04.5)TN 320
ITEM
NO.ITEM DESCRIPTION SPEC.
SECTION UNIT QUANTITY UNIT PRICE*EXTENSION
18 Planing Bituminous Pavement (5‑04.5)SY 21,000
19 Pavement Repair Excavation, Incl. Haul (5‑04.5)SY 420
20 HMA Cl. 1/2" PG 64-22 (5‑04.5)TN 4,050
21 Job Mix Compliance Price Adjustment (5‑04.5)CALC 1 $0.00 $0.00
22 Compaction Price Adjustment (5‑04.5)CALC 1 $0.00 $0.00
23 CPEP Storm Sewer Pipe, 12 In. Diam. (Incl.
Bedding) (5‑04.5)LF 90
24 Catch Basin, Type 1 (7‑05.5)EA 2
25 Adjust Manhole (7‑05.5)EA 2
26 Adjust Catch Basin (7‑05.5)EA 8
27 Trench Excavation Safety Systems (7‑08.5)LS 1
28 Bank Run Gravel for Trench Backfill (7‑08.5)TN 60
29 Trench Excavation, Incl. Haul (7‑08.5)CY 55
30 Removal of Unsuitable Material (Trench) (7‑09.5)CY 5
31 Television Inspection (7‑12.5)LS 1
32 Adjust Meter Box (7‑15.5)EA 3
33 Adjust Valve Box (7‑15.5)EA 3
ADDENDUM NO. 1
Renton Avenue South Resurfacing
Page 3 of 5R
Schedule of Prices
2018
SCHEDULE OF PRICES
Renton Avenue South Resurfacing
ALL ENTRIES SHALL BE WRITTEN IN INK OR TYPED TO VALIDATE BID
NOTE: Unit prices for all items, all extensions, and total amount of bid shall be shown. Enter unit prices in numerical figures only, in dollars
and cents to two (2) decimal places (including whole dollar amounts). All figures must be clearly legible. Bids with illegible figures in the
Unit Price column will be regarded as nonresponsive and rejected. Where conflict occurs between the unit price and the total amount
specified for any item, the unit price shall prevail, and totals shall be corrected to conform thereto.
34 Seeding, Fertilizing and Mulching (8‑01.5)SY 100
ITEM
NO.ITEM DESCRIPTION SPEC.
SECTION UNIT QUANTITY UNIT PRICE*EXTENSION
35 Erosion/Water Pollution Control (8‑01.5)LS 1
36 Topsoil, Type A (8‑02.5)CY 60
37 Cement Conc. Traffic Curb and Gutter (8‑04.5)LF 990
38 Cement Conc. Driveway Entrance (8‑06.5)SY 40
39 Cement Conc. Driveway Repair (8‑06.5)SY 10
40 Raised Pavement Marker, Type 1 (8‑09.5)HD 39
41 Raised Pavement Marker, Type 2 (8‑09.5)HD 5
42 Adjust Monument Case and Cover (8‑13.5)EA 2
43 Cement Conc. Sidewalk (8‑14.5)SY 215
44 Cement Conc. Curb Ramp (8‑14.5)EA 9
45 Video Detection (8‑20.5)LS 1
46 Permanent Signing (8‑21.5)LS 1
47 Plastic Line (8‑22.5)LF 660
48 Plastic Crosswalk Line (8‑22.5)SF 107
49 Plastic Stop Line (8‑22.5)LF 60
50 Plastic Traffic Arrow (8‑22.5)EA 10
ADDENDUM NO. 1
Renton Avenue South Resurfacing
Page 4 of 5R
Schedule of Prices
2018
SCHEDULE OF PRICES
Renton Avenue South Resurfacing
ALL ENTRIES SHALL BE WRITTEN IN INK OR TYPED TO VALIDATE BID
NOTE: Unit prices for all items, all extensions, and total amount of bid shall be shown. Enter unit prices in numerical figures only, in dollars
and cents to two (2) decimal places (including whole dollar amounts). All figures must be clearly legible. Bids with illegible figures in the
Unit Price column will be regarded as nonresponsive and rejected. Where conflict occurs between the unit price and the total amount
specified for any item, the unit price shall prevail, and totals shall be corrected to conform thereto.
51 Plastic Yield Lane Symbol (8‑22.5)EA 6
ITEM
NO.ITEM DESCRIPTION SPEC.
SECTION UNIT QUANTITY UNIT PRICE*EXTENSION
52 Temporary Pavement Marking – Short
Duration (8‑23.5)LF 16,500
53 Landscape Block Wall (8‑24.5)SF 60
TOTAL BID AMOUNT, SCHEDULE A =
ITEM
NO.ITEM DESCRIPTION SPEC.
SECTION UNIT QUANTITY UNIT PRICE*EXTENSION
100 Trench Excavation Safety Systems (7‑09.5)LS 1
101 Bank Run Gravel for Trench Backfill (7‑09.5)TN 300
102 Trench Excavation, Incl. Haul (7‑09.5)CY 400
103 DI Water Main Pipe, 8 In. Diam. (7‑09.5)LF 540
104 Connection to Existing Water Main (7‑09.5)EA 2
105 Additional Ductile Iron Fittings (7‑09.5)LB 500
106 Gate Valve, 8 In. (7‑12.5)EA 1
107 Tapping Sleeve and Valve Assembly (7‑12.5)EA 1
108 Fire Hydrant Assembly (7‑14.5)EA 2
109 Service Connection, 1 In. Diam. (7‑15.5)EA 5
SCHEDULE B - WATER SYSTEM IMPROVEMENTS
ADDENDUM NO. 1
Renton Avenue South Resurfacing
Page 5 of 5R
Schedule of Prices
2018
SCHEDULE OF PRICES
Renton Avenue South Resurfacing
ALL ENTRIES SHALL BE WRITTEN IN INK OR TYPED TO VALIDATE BID
NOTE: Unit prices for all items, all extensions, and total amount of bid shall be shown. Enter unit prices in numerical figures only, in dollars
and cents to two (2) decimal places (including whole dollar amounts). All figures must be clearly legible. Bids with illegible figures in the
Unit Price column will be regarded as nonresponsive and rejected. Where conflict occurs between the unit price and the total amount
specified for any item, the unit price shall prevail, and totals shall be corrected to conform thereto.
TOTAL BID AMOUNT, SCHEDULE B =
ITEM
NO.ITEM DESCRIPTION SPEC.
SECTION UNIT QUANTITY UNIT PRICE*EXTENSION
200 Pedestrian Hydbrid Beacons (Hawk) Signal
System, Complete (8‑20.5)LS 1
TOTAL BID AMOUNT, SCHEDULE C =
TOTAL BID AMOUNT, SCHEDULES A, B AND C =
*NOTE: All applicable sales tax shall be included in the unit and lump sum bid price per section 1-07.2(1) and WAC 458-20-171.
SCHEDULE C - HAWK SIGNAL
en z w
0:: w
ID
....1
....1
iii
~
~
0
BACKFILLED &
COMPACTED
NATIVE SOIL
NOTE
POST -SEE STD.
SPEC. 8-01.3(9)A
FASTEN GEOTEXTILE TO
POST EVERY 6" (IN.) O.C.
SELF-LOCKING TIE-NYLON 6/6 (MIN. GRADE),
120# MIN. TENSILE STRENGTH, UV STABILIZED
DURING EXCAVATION, MINIMIZE DISTURBING THE GROUND
AROUND TRENCH AS MUCH AS IS FEASIBLE, AND SMOOTH
SURFACE FOLLOWING EXCAVATION TO AVOID CONCENT-
RATING FLOWS. COMPACTION MUST BE ADEQUATE TO
PREVENT UNDERCUTTING FLOWS.
TYPICAL INSTALLATION DETAIL
(STEEL POSTS SHOWN)
TYPICAL HIGH VISIBILITY SILT FENCE
WITHOUT BACKUP SUPPORT
ISOMETRIC
(STEEL POSTS SHOWN)
NOTES
1. Install the ends of the high visibility silt fence to point slightly upslope
to prevent sediment from flowing around the ends of the fence .
2. Perform maintenance in accordance with Standard Specifications
8-01.3{9)A and 8-01.3{15).
3. Splices shall never be placed in low spots or sump locations. If
splices are located in low or sump areas, the fence may need to be
reinstalled unless the Project Engineer approves the installation.
4. Install silt fencing parallel to mapped contour lines.
GEOTEXTILE FOR HIGH VISIBILITY SILT FENCE
COLOR-ORANGE -SEE STANDARD
SPECIFICATION SECTION
9-33.2 (1), TABLE 6
POST-
WOOD OR STEEL
(TYPICAL) STATE OF
WASHINGTON
REGISTERED
LANDSCAPE ARCHITECT
FASTEN GEOTEXTILE TO
POST EVERY 6" (IN.) O.C.
ANORA L.SALISBURY
CERTIFICATE NO. 000860
,...-------NOTE: THIS PLAN IS NOT A LEGAL ENGINEERING DOCU-
MENT BUT AN ElECTRONIC DUPLICA 1E. THE ORIGINAL, SIGNED BY THE ENGINEER AND
APPROVED FOR PUBLfCATION, IS KEPT ON FILE AT THE WASHINGTON STATE DEPART-
MENT OF TRANSPORTATION. A COPY MAY BE OBTAINED UPON REQUEST.
SPLICED FENCE SECTIONS SHALL BE CLOSE ENOUGH TOGETHER
TO PREVENT SILT LADEN WATER FROM ESCAPING THROUGH THE
FENCE AT THE OVERLAP. JOINING SECTIONS SHALL NOT BE PLACED
IN LOW SPOTS OR IN SUMP LOCATIONS.
SPLICE DETAIL
(WOOD POSTS SHOWN)
HIGH VISIBILITY
SILT FENCE
STANDARD PLAN 1-30.17-00
SHEET 1 OF 1 SHEET
APPROVED FOR PUBLICATION
Pasco Bakotich Ill 3122113
STATE DESIGN ENGINEER DATE ......
... Washington State Department of Transportation