HomeMy WebLinkAboutIssued construction permit sewer Extension SE 132nd ( NE 2nd) Street U16006822.pdfDEPARTMENT OF COMMUNITYCITY OF
AND ECONOMIC DEVELOPMENT --•••••" ��Rent•n v
Constiruction PermitiU16006822
IVR Number: 16006822
Permiti Name SE 132nd (NE 2ND) STREET SEWER EXTENSION
Address/Location: 15522 SE 132ND ST Parcel Number: 1423059092 Application Datie 12/29/2016
Permiti Type Engineering Issue Datie 07/26/2017
Permiti Work Class Constiruction Expiration Datie 07/26/2018
Inspectioc Todd Freih 206-999-1832 Plan Reviewer: Rohini Nair 425-430-7298
Description: SANITARY SEWER MAIN EXTENSION ALONG WITH SEWER STUBS ON SE 132nd (NE 2ND) STREET KING COUNTY ROW.
Billing Type
X Applicanti
Contiacti
Contiractior
Owner
Name
KUSHAL S+KAJAL A RAM VARMA
Touma Engineers & Land Surveyors, PLLC
Brian Bowen
Bowen Constiruction Inc
Constiruction ContiractiolBOWENC1993QR
RAM KAJAL A
Address
10906 144tih Ave SE
RENTON, WA 98059
255 SW 41sti Sti
Rention WA 98057
PO Box 42
Buckley, WA 98321-0042
Business License Number: BL.032696
10906 144TH AVE SE
RENTON , WA 98059
Phone
B: (206) 353-3168
B: (206) 30-4356x7
B: (360) 829-6632
C: (253) 208-9412
• Permission is hereby given for the work described on this permit according to the conditions hereon and according to the
approved plans and specifications pertaining thereto, subject to compliance with the Ordinance of the City of Renton.
• This permit and plans must be posted at the job site at all times.
• I hereby certify that no work is to be done except as described above and in approved plans, and that work is to conform to
Renton codes and ordinances.
• Call (425) 430-7203 or go to: www.MyBuildingPermit.com one working day in advance to schedule an inspections and for
ANY work in the Right of Way.
• Call 8 1 1 to locate underground utilities at least two full business days prior to any excavation.
• In accordance with RCW 19.122.033(4) the permit holder is required to contact (Williams Northwest Pipeline at 425.868.1010
) (Olympic Pipeline at 206.510.0575)(Puget Sound Energy at 425.457.5816) to request a consultation with the transmission
pipeline company prior to performing any construction or excavation activities. This requirement to consult with the
transmission pipeline company is in addition to the requirement to Call before You Dig as required in RCW 19.122.
�!/-If
(Signatiure) (Datil
THIS PERMIT AND PLANS MUST BE POSTED AT THE JOB SITE AT ALL TIMES Page 1 of 1