RE: Submittal of Deferral Application
ZK Short Plat
City of Renton File No. LUA13-001564
Dear Ms. Bannwarth:
On behalf of our client Hien Thao Real Estate Company, we are submitting the enclosed Application for
Deferral of the on-site final lift of asphalt (2 inches) and landscaping. I’m enclosing the following
documents for you to review and approval accordance with RMC 4-9-060(c):
1. One (1) copy of the completed City of Renton Deferral Application form signed by the
property owner
2. One (1) copy of project site map and grading plan which highlights the requested deferral
items.
The ZK Shortplat is 95% constructed and there are one (1) model home also under construction. On May
15th, 2017 we submitted 1st revision of the Final Plat Map to the City of Renton for review/approval.
The following information is being provided in support of our request:
Items and quantities involved: During the construction of the on-site homes (4 homes) TP
Home, LLC, on behalf of Hien Thao Real Estate Company, is requesting a delay of the final lift
of asphalt (on site) and landscaping to avoid damage. The items and quantities for the
referral are as follows:
o Final 2 inches of asphalt on the private road: 289 cubic feet, cost: $6,415.80 ($22.20
per cubic feet)
o Landscaping on public planter strip and private planter strip: $4,000 for labor and
materials
o Install road sign and no parking sign along the retaining wall: labor and material
$800
Justification: Since our short plat deadline is coming up on 7/7/2017, we will not have all of
documents in for short plat recording approval prior to the deadline. We can finish all of the
works by that time, but City of Renton and King County need at least 6 weeks to review and
approve for three (3) new tax parcels. Another justification is during construction the
various contractors/vendors will be utilizing large/heavy trucks for delivery of concrete,
rebar, lumber, trusses, etc. It’s very common that during the home building phase minor
damage occurs to the asphalt private road by the delivery trucks (especially during the
months). By leaving the final lift of asphalt, we assure the City of Renton and future home
owners a better roadway surface.
Please review this information and provide to us your approval to delay (defer) the requested public
improvement for a period of 7 months. This time frame will assure adequate time to complete all home
construction. If you have any questions or need further information. Please contact me at (206) 390-
5272. Thank you!
Respectfully,
Vinh Quang Vuong
TP Home, LLC
Representative
(206) 390-5272