PROJECT PERSONNEL:
Ian Fitz-James, City Project Manager, 425-430-7288, IFitz-James@Rentonwa.gov
Patrick Decaro, Public Works Inspector, 425-207-6013, PDecaro@Rentonwa.gov
Clark Close, Planning Reviewer, 425-430-7289, CClose@Rentonwa.gov
Ryan Puddy, Electrical Inspector , 206-999-1821, rpuddy@Rentonwa.gov
Jack Oxford, Electrical Inspector, 206-999-1822, JOxford@Rentonwa.gov
Eric Cutshall, Transportation Maintenance Supervisor, 425-430-7223, ECutshall@Rentonwa.gov
ELECTRICAL:
After calling in the inspection request through the Inspection Request Line, contact Ryan Puddy (206-999-1821) or Jack Oxford (206-999-1822) at 7:30 a.m. the morning of the inspection
to provide a contact name and phone number for arranging the electrical inspection with your representative.
Have in your possession the electrical permit and streetlight luminaire checklist. Insert both in a clear plastic document protector and attach it to a conduit stubbed up. If the signal
control box is installed, for underground conduit inspection approval, place the documents in the signal control box.
Service inspection for signal or lighting control pedestals requires access for electrical inspection. If approved, a service approval sticker will be attached by the meter opening
for the serving utility. The serving utility will not and shall not connect power unless the approval sticker is in place.
All grounding is to meet Standard Plan -119, dated March 20, 2012.
Provide Megger Test Report of all wiring to identify any undergrounded conductor that is grounded or open not completing circuit.
When calling in a request for final electrical inspection, provide access to all handholes and access openings to light poles. Some bolts require special sockets or wrenches, which
are not available to or provided by the Electrical Inspector.
Electrical cabinets (Millbank service cabinets) do not meet the minimum City code standards, therefore shall not be considered allowable.
SIGNAL WORK:
School Beacon / Radar Detection Signs
All signs to be field located by City of Renton Transportation Maintenance prior to installation.
Controller Hub Installation on Existing Signal Pole
Contractor to provide City crews with controller hub.
Contractor to schedule installation of controller hub by City crews through Public Works Inspector
Fiber Connection to Existing RSD Fiber
Access to existing City of Renton Signal Cabinets
Other Topics / Questions