Conditions for Permit C17001559
Engineering
1 Engineering General Conditions
Construction cannot begin on any on-site or off-site improvements until a pre-construction meeting is held.
2 Engineering General Conditions
A permit issued by Seattle Public Utilities (SPU) is required prior to approval of any work within the SPU right of
way. Work is not permitted in the SPU right of way until the permit from SPU is issued.
3 Engineering General Conditions
Renton Commons LLC shall provide a signed and executed Stormwater Facility Agreement to the City prior to
approval of any work within the SPU right of way.
4 Engineering General Conditions
Construction cannot begin on any on-site or off-site improvements until a construction permit surety in the amount
of $350,505.40 is received and accepted by the City.
5 Engineering General Conditions
A Certificate of Insurance for Renton Commons LLC shall be provided to the City prior to any on-site or off-site
work for the right of way use permit.
6 Engineering General Conditions
Renton Commons LLC shall provide a signed and executed Emergency Response Plan for the on-site private
stormwater pump to the City prior to construction closeout. The Emergency Response Plan should be in
accordance with the 2017 Renton Surface Water Design Manual and is subject to review and approval by CED
staff.