OFDATE:PROJECT #:DRAWN:CHECKED:THIS DRAWING HAS BEEN PREPARED BASED ON INFORMATION PROVIDED TO ADS UNDER THE DIRECTION OF THE SITE DESIGN ENGINEER OR OTHER PROJECT REPRESENTATIVE. THE SITE DESIGN ENGINEER SHALL REVIEW THIS DRAWING PRIOR TO CONSTRUCTION. IT IS THE ULTIMATERESPONSIBILITY OF THE SITE DESIGN ENGINEER TO ENSURE THAT THE PRODUCT(S) DEPICTED AND ALL ASSOCIATED DETAILS MEET ALL APPLICABLE LAWS, REGULATIONS, AND PROJECT REQUIREMENTS.4640 TRUEMAN BLVDHILLIARD, OH 430261-800-733-7473ADVANCED DRAINAGE SYSTEMS, INC.REVDRWCHKDESCRIPTIONSC-310STANDARD CROSS SECTION11/18/14JLM1 1JLM70 INWOOD ROAD, SUITE 3 | ROCKY HILL | CT | 06067860-529-8188 |888-892-2694 | WWW.STORMTECH.COMDetention Retention Water QualityACCEPTABLE FILL MATERIALS: STORMTECH SC-310 CHAMBER SYSTEMS
PLEASE NOTE:
1.THE LISTED AASHTO DESIGNATIONS ARE FOR GRADATIONS ONLY. THE STONE MUST ALSO BE CLEAN, CRUSHED, ANGULAR. FOR EXAMPLE, A SPECIFICATION FOR #4 STONE WOULD STATE: "CLEAN, CRUSHED,
ANGULAR NO. 4 (AASHTO M43) STONE".
2.STORMTECH COMPACTION REQUIREMENTS ARE MET FOR 'A' LOCATION MATERIALS WHEN PLACED AND COMPACTED IN 6" (150 mm) (MAX) LIFTS USING TWO FULL COVERAGES WITH A VIBRATORY COMPACTOR.
3.WHERE INFILTRATION SURFACES MAY BE COMPROMISED BY COMPACTION, FOR STANDARD DESIGN LOAD CONDITIONS, A FLAT SURFACE MAY BE ACHIEVED BY RAKING OR DRAGGING WITHOUT COMPACTION
EQUIPMENT. FOR SPECIAL LOAD DESIGNS, CONTACT STORMTECH FOR COMPACTION REQUIREMENTS.
NOTES:
1.SC-310 CHAMBERS SHALL CONFORM TO THE REQUIREMENTS OF ASTM F2418 "STANDARD SPECIFICATION FOR POLYPROPYLENE (PP) CORRUGATED WALL STORMWATER COLLECTION CHAMBERS", OR ASTM
F2922
"STANDARD SPECIFICATION FOR POLYETHYLENE (PE) CORRUGATED WALL STORMWATER COLLECTION CHAMBERS".
2.SC-310 CHAMBERS SHALL BE DESIGNED IN ACCORDANCE WITH ASTM F2787 "STANDARD PRACTICE FOR STRUCTURAL DESIGN OF THERMOPLASTIC CORRUGATED WALL STORMWATER COLLECTION
CHAMBERS".
3."ACCEPTABLE FILL MATERIALS" TABLE ABOVE PROVIDES MATERIAL LOCATIONS, DESCRIPTIONS, GRADATIONS, AND COMPACTION REQUIREMENTS FOR FOUNDATION, EMBEDMENT, AND FILL MATERIALS.
4.THE "SITE DESIGN ENGINEER" REFERS TO THE ENGINEER RESPONSIBLE FOR THE DESIGN AND LAYOUT OF THE STORMTECH CHAMBERS FOR THIS PROJECT.
5.THE SITE DESIGN ENGINEER IS RESPONSIBLE FOR ASSESSING THE BEARING RESISTANCE (ALLOWABLE BEARING CAPACITY) OF THE SUBGRADE SOILS AND THE DEPTH OF FOUNDATION STONE WITH
CONSIDERATION FOR THE RANGE OF EXPECTED SOIL MOISTURE CONDITIONS.
6.PERIMETER STONE MUST BE EXTENDED HORIZONTALLY TO THE EXCAVATION WALL FOR BOTH VERTICAL AND SLOPED EXCAVATION WALLS.
7.ONCE LAYER 'C' IS PLACED, ANY SOIL/MATERIAL CAN BE PLACED IN LAYER 'D' UP TO THE FINISHED GRADE. MOST PAVEMENT SUBBASE SOILS CAN BE USED TO REPLACE THE MATERIAL REQUIREMENTS OF
LAYER 'C' OR 'D' AT THE SITE DESIGN ENGINEER'S DISCRETION.
MATERIAL LOCATION DESCRIPTION AASHTO MATERIAL
CLASSIFICATIONS
COMPACTION / DENSITY
REQUIREMENT
D
FINAL FILL: FILL MATERIAL FOR LAYER 'D' STARTS
FROM THE TOP OF THE 'C' LAYER TO THE BOTTOM
OF FLEXIBLE PAVEMENT OR UNPAVED FINISHED
GRADE ABOVE. NOTE THAT PAVEMENT SUBBASE
MAY BE PART OF THE 'D' LAYER
ANY SOIL/ROCK MATERIALS, NATIVE SOILS, OR PER
ENGINEER'S PLANS. CHECK PLANS FOR PAVEMENT
SUBGRADE REQUIREMENTS.
N/A
PREPARE PER SITE DESIGN ENGINEER'S PLANS.
PAVED INSTALLATIONS MAY HAVE STRINGENT
MATERIAL AND PREPARATION REQUIREMENTS.
C
INITIAL FILL: FILL MATERIAL FOR LAYER 'C'
STARTS FROM THE TOP OF THE EMBEDMENT
STONE ('B' LAYER) TO 18" (450 mm) ABOVE THE
TOP OF THE CHAMBER. NOTE THAT PAVEMENT
SUBBASE MAY BE A PART OF THE 'C' LAYER.
GRANULAR WELL-GRADED SOIL/AGGREGATE MIXTURES, <35%
FINES OR PROCESSED AGGREGATE.
MOST PAVEMENT SUBBASE MATERIALS CAN BE USED IN LIEU
OF THIS LAYER.
AASHTO M145¹
A-1, A-2-4, A-3
OR
AASHTO M43¹
3, 357, 4, 467, 5, 56, 57, 6, 67, 68, 7, 78, 8, 89,
9, 10
BEGIN COMPACTIONS AFTER 12" (300 mm) OF
MATERIAL OVER THE CHAMBERS IS REACHED.
COMPACT ADDITIONAL LAYERS IN 6" (150 mm) MAX
LIFTS TO A MIN. 95% PROCTOR DENSITY FOR
WELL GRADED MATERIAL AND 95% RELATIVE
DENSITY FOR PROCESSED AGGREGATE
MATERIALS. ROLLER GROSS VEHICLE WEIGHT
NOT TO EXCEED 12,000 lbs (53 kN). DYNAMIC
FORCE NOT TO EXCEED 20,000 lbs (89 kN).
B
EMBEDMENT STONE: FILL SURROUNDING THE
CHAMBERS FROM THE FOUNDATION STONE ('A'
LAYER) TO THE 'C' LAYER ABOVE.
CLEAN, CRUSHED, ANGULAR STONE, NOMINAL SIZE
DISTRIBUTION BETWEEN 3/4-2 INCH (20-50 mm)
AASHTO M43¹
3, 357, 4, 467, 5, 56, 57 NO COMPACTION REQUIRED.
A
FOUNDATION STONE: FILL BELOW CHAMBERS
FROM THE SUBGRADE UP TO THE FOOT (BOTTOM)
OF THE CHAMBER.
CLEAN, CRUSHED, ANGULAR STONE, NOMINAL SIZE
DISTRIBUTION BETWEEN 3/4-2 INCH (20-50 mm)
AASHTO M43¹
3, 357, 4, 467, 5, 56, 57
PLATE COMPACT OR ROLL TO ACHIEVE A FLAT
SURFACE. ² ³
18"
(450 mm)
20"6" (150 mm)
EXCAVATION WALL
(CAN BE SLOPED OR VERTICAL)
12" (300 mm) MIN 12" (300 mm) TYP34" (865 mm)6"
(150 mm) MIN
PERIMETER STONE
(SEE NOTE 6)
ADS GEOSYNTHETICS 601T NON-WOVEN GEOTEXTILE ALL AROUND
CLEAN CRUSHED, ANGULAR STONE IN A & B LAYERS
16"
(405 mm)
6" (150 mm)
SUBGRADE SOILS
(SEE NOTE 5)
PAVEMENT LAYER (DESIGNED
BY SITE DESIGN ENGINEER)
SC-310
END CAP
D
C
B
A
*TO BOTTOM OF FLEXIBLE PAVEMENT. FOR UNPAVED
INSTALLATIONS WHERE RUTTING FROM VEHICLES MAY
OCCUR, INCREASE COVER TO 24" (600 mm).
SC-310 CHAMBER
18" (450 mm) MIN WIDTH
CONCRETE SLAB
8" (200 mm) MIN THICKNESS
PAVEMENT
FLEXSTORM CATCH IT
PART# 6212NYFX
WITH USE OF OPEN GRATE
12" (300 mm) NYLOPLAST INLINE
DRAIN BODY W/SOLID HINGED
COVER OR GRATE
PART# 2712AG10N
SOLID COVER: 1299CGC
GRATE: 1299CGS
CONCRETE COLLAR
10" (250 mm) INSERTA TEE
PART#10N12ST31IP
INSERTA TEE TO BE CENTERED
ON CORRUGATION CREST
SC-310 INSPECTION PORT DETAIL
NTS
10" (250 mm) ADS N-12
HDPE PIPE
SHEET
OFDATE:PROJECT #:DRAWN:CHECKED:THIS DRAWING HAS BEEN PREPARED BASED ON INFORMATION PROVIDED TO ADS UNDER THE DIRECTION OF THE SITE DESIGN ENGINEER OR OTHER PROJECT REPRESENTATIVE. THE SITE DESIGN ENGINEER SHALL REVIEW THIS DRAWING PRIOR TO CONSTRUCTION. IT IS THE ULTIMATERESPONSIBILITY OF THE SITE DESIGN ENGINEER TO ENSURE THAT THE PRODUCT(S) DEPICTED AND ALL ASSOCIATED DETAILS MEET ALL APPLICABLE LAWS, REGULATIONS, AND PROJECT REQUIREMENTS.4640 TRUEMAN BLVDHILLIARD, OH 430261-800-733-7473ADVANCED DRAINAGE SYSTEMS, INC.REVDRWCHKDESCRIPTIONSC-310ISOLATOR ROW DETAILS11/18/14JLM1 1JLM70 INWOOD ROAD, SUITE 3 | ROCKY HILL | CT | 06067860-529-8188 |888-892-2694 | WWW.STORMTECH.COMDetention Retention Water QualityINSPECTION & MAINTENANCE
STEP 1)INSPECT ISOLATOR ROW FOR SEDIMENT
A.INSPECTION PORTS (IF PRESENT)
A.1.REMOVE/OPEN LID ON NYLOPLAST INLINE DRAIN
A.2.REMOVE AND CLEAN FLEXSTORM FILTER IF INSTALLED
A.3.USING A FLASHLIGHT AND STADIA ROD, MEASURE DEPTH OF SEDIMENT AND RECORD ON MAINTENANCE LOG
A.4.LOWER A CAMERA INTO ISOLATOR ROW FOR VISUAL INSPECTION OF SEDIMENT LEVELS (OPTIONAL)
A.5.IF SEDIMENT IS AT, OR ABOVE, 3" (80 mm) PROCEED TO STEP 2. IF NOT, PROCEED TO STEP 3.
B.ALL ISOLATOR ROWS
B.1.REMOVE COVER FROM STRUCTURE AT UPSTREAM END OF ISOLATOR ROW
B.2.USING A FLASHLIGHT, INSPECT DOWN THE ISOLATOR ROW THROUGH OUTLET PIPE
i)MIRRORS ON POLES OR CAMERAS MAY BE USED TO AVOID A CONFINED SPACE ENTRY
ii)FOLLOW OSHA REGULATIONS FOR CONFINED SPACE ENTRY IF ENTERING MANHOLE
B.3.IF SEDIMENT IS AT, OR ABOVE, 3" (80 mm) PROCEED TO STEP 2. IF NOT, PROCEED TO STEP 3.
STEP 2)CLEAN OUT ISOLATOR ROW USING THE JETVAC PROCESS
A.A FIXED CULVERT CLEANING NOZZLE WITH REAR FACING SPREAD OF 45" (1.1 m) OR MORE IS PREFERRED
B.APPLY MULTIPLE PASSES OF JETVAC UNTIL BACKFLUSH WATER IS CLEAN
C.VACUUM STRUCTURE SUMP AS REQUIRED
STEP 3)REPLACE ALL COVERS, GRATES, FILTERS, AND LIDS; RECORD OBSERVATIONS AND ACTIONS.
STEP 4)INSPECT AND CLEAN BASINS AND MANHOLES UPSTREAM OF THE STORMTECH SYSTEM.
NOTES
1.INSPECT EVERY 6 MONTHS DURING THE FIRST YEAR OF OPERATION. ADJUST THE INSPECTION INTERVAL BASED ON PREVIOUS
OBSERVATIONS OF SEDIMENT ACCUMULATION AND HIGH WATER ELEVATIONS.
2.CONDUCT JETTING AND VACTORING ANNUALLY OR WHEN INSPECTION SHOWS THAT MAINTENANCE IS NECESSARY.
SC-310 ISOLATOR ROW DETAIL
NTS
STORMTECH HIGHLY RECOMMENDS
FLEXSTORM PURE INSERTS IN ANY UPSTREAM
STRUCTURES WITH OPEN GRATES
COVER ENTIRE ISOLATOR ROW WITH ADS
GEOSYNTHETICS 601T NON-WOVEN GEOTEXTILE
5' (1.5 m) MIN WIDE
SC-310 CHAMBER
SC-310 END CAP
OPTIONAL INSPECTION PORT
24" SUMP DEPTH
12" (300 mm) HDPE ACCESS PIPE REQUIRED
USE FACTORY PRE-FABRICATED END CAP
PART #: SC310EPE12B
TWO LAYERS OF ADS GEOSYNTHETICS 315WTK WOVEN
GEOTEXTILE BETWEEN FOUNDATION STONE AND CHAMBERS
4' (1.2 m) MIN WIDE CONTINUOUS FABRIC WITHOUT SEAMS
CATCH BASIN
OR
MANHOLE