HomeMy WebLinkAboutPre-Con Meeting Template updated Sewer 12.15.15.dotxATTACHMENT A CITY OF RENTON PRECONSTRUCTION MEETING HARDIE AVE SEWER MAIN EXTENSION 8.16.16 PROJECT PERSONNEL: Jan Illian, City Project Manager 425-430-7216</w:t></w:r></ Pat Miller, Public Works Inspector 206-794-6162</w:t></w:r></ Corey Thomas, Fire Inspector425-430-7024 FRANCHISE UTILITIES: 1.The franchise utilities require copies of the approved construction drawings before designing their facilities. Provide a copy of the approved composite drawing to each utility for inclusion with their permit application. 2.Each franchise utility shall apply for a separate permit prior to construction in existing or future right-of-way. A blueline drawing showing the location of all utilities, city and franchise, in redlines shall be submitted to the sixth floor counter for City review two weeks before installation.< 3.All franchise utilities shall be separated a minimum of five feet (5') horizontally and twelve inches (12") vertically from City utilities. 4.All franchise utilities within the City of Renton right-of-way must be inspected by the City of Renton franchise inspector. Call the inspection line at 425-430-7203, 24-hours prior to job start for coordination. 5.The composite drawing shall be as-built showing all franchise utility locations and crossings. The revised composite drawing shall be submitted with the as-built drawings after construction is complete. GENERAL: 1.CALL 425-430-7203 FOR INSPECTION (24 HR NOTICE) BEFORE YOU START WORK. NOTIFY FIRE, POLICE AND METRO OF CONSTRUCTION SCHEDULE. CALL 911 OR FIRE DISPATCH AT 253-852-2121 2.Contractors shall use only sets of drawings stamped and signed by the City of Renton for constructing utility and transportation improvements. The approved plans do not constitute a fill and grade permit or grant any rights to fill and/or grade outside of the right-of-way. Keep a set of approved drawings on-site at all times. 3.Work hours for hauling in right-of-way are weekdays, 8:30 AM to 3:30 PM, Saturday by approval only and no work on Sundays. 4.CONSTRUCTION HOURS: 7:00 AM to 8:00 PM Monday thru Friday and 9:00 AM to 8:00 PM on Saturdays by permission only. No work allowed on Sundays. 5.Contractor must call for City inspection before 3:00 p.m. on the previous day. Overtime takes special authorization and scheduling in advance. Pay schedule is $75 per hour for overtime. 6.Streets shall be kept clean at all times. Truck washing and other measures as approved are required for the duration of the project. Provide whatever measures necessary for cleanup and dust control during job and at night. 7.Traffic control plan to be in accordance with the Manual on Uniform Traffic Control Devices. Haul legal loads and observe all traffic laws. All truck maneuvering and materials storage to be on-site only. Right-of-way to remain unobstructed when possible. No stoc<kpiles are allowed in the right-of-way. 8.All utilities must be inspected prior to backfill. 9.The contractor, as well as the engineer, shall keep as-built drawings. All changes shall be shown on as-builts. As-builts shall be per City specifications. All bends on waterlines shall be surveyed prior to backfill with horizontal and vertical control for all bends established. Sewer lines may be surveyed after backfill at manhole access. As-built drawings must have a P.E. or P.L.S. stamp. Final plat recording or final occupancy will not be issued until receipt and approval of project utility and transportation improvement as-built drawings by the City. 10.Field changes: If minor, submit a shop drawing or schematic through the Public Works Inspector or by FAX 425-430-7300. If major, the project engineer should submit drawings and complete justification, information and calculations as applicable to the City Project Manager. City staff will respond by memo or schedule a meeting within two days. The Public Works Inspector cannot give approval in the field for major construction changes. 11.Street Restoration is required to conform to the City of Renton Trench Restoration and Street Overlay Standards. A copy has been provided. All street repairs shall be complete and in place within <14 days, or as directed by the Public Works Inspector. 12. Dewatering, if required, shall be less than 25 NTU if discharged into Waters of the State. Pipe conveyance systems that discharge eventually to the ‘Waters of the State’ is construed as ‘Waters of the State’. Downstream pipe conveyance systems shall be TV’d, as directed by the Inspector, prior to final acceptance of the project. Projects over 1 acre in size shall be required to provide the WAR (Ecology) number and send in the CESCL weekly reports to the inspector stating compliance to discharge requirements. If dewatering is proposed to a City Sewer system then a permit from the County and the City will need to be obtained. The contractor is strongly encouraged to obtain required sewer discharge permits in advance of any anticipated need to discharge to the sewer system. 13. Dust control shall be implemented as directed by the Inspector. (Dust suppression guidelines will be provided to the Contractor from the Inspector.) 14.If the materials shown on the approved plans differ from those shown on the City standard details, material submittals shall be reviewed and approved by the City prior to installation. 15.Spill Kit shall be located on site and identified with signage. 16.Storm Water Pollution Prevention Plan shall be located on site and shall be maintained throughout construction. 17.No shims or wedges shall be used on any utility structure. CITY UTILITIES SANITARY SEWER: 1.All pipes and materials shall be per approved plan and standard notes. However, any sewer pipe with less than four feet or greater than fifteen feet of cover shall be Ductile Iron, Class 50, or C900 pipe. 2.All manholes shall have all interior surfaces, including channeling, coated/sealed with a high solids urethane coating: Wasser MC-Conseal or approved equal. Coating shall be white. 3.Pipe bedding for PVC pipe shall be pea gravel or 5/8" minus crushed rock as approved by the inspector, 6" above and below the pipe. 4.Backfill shall be compacted to at least 95% of maximum density, within the right of way. 5.Contractor will be responsible for TVing of the sanitary line. TV after channeling is complete. Air tests on main and side sewers shall be per City specification. Number 6 wire shall be wrapped around the stub and extended to the top with a 2 x 4 marker stenciled in white. 6.Contractor shall as-built the invert elevation of side sewer stubs. If cleanouts are installed, the top and flowline shall be as-built and noted on the record drawings. STORM/EROSION CONTROL: 1.Approved temporary erosion control measures are to be installed as first order of business and maintained at all times per the approved drawings. 2.Weekly erosion control reports outlining the status and condition of the erosion control plan, with any recommendations of change or revision to maintenance schedules or installation, are required to be submitted by the project Engineer of record or project CECSL to the plan review project manager and construction inspector at the City. Certification of the installation, maintenance, and proper removal of the erosion control facilities is required prior to final approval. 3.All pipes and materials shall be per approved plan. All roadway excavation and backfill for construction of the road prism shall be accomplished prior to installation of the drainage facilities to avoid damage or disturbance of the new infrastructure. 4.Contractor must notify engineer of any vertical conflict prior to proceeding with construction. Please submit a shop drawing for review. 5.Bedding material shall be per WSDOT Standard Specifications 9-03.12(3) or as approved by the inspector. 6.Backfill shall be compacted to at least 95% of maximum density. < 7.Catch basins shall be grouted smoothly. 8.System shall be flushed and cleaned which includes the downstream system a minimum of two structures or 500 feet whichever is greater. Lines shall be tv’ed and maybe pressure tested. 9.Smooth interior wall corrugated polyethylene storm water pipe, where permitted, shall use watertight couplings. It shall also be bedded in pea gravel to the springline TRANSPORTATION: 1.The Manual of Uniform traffic control devices shall be followed for street closures and routing for traffic. An approved traffic control plan shall be in place prior to working in the City right-of-way. 2.Paving: The minimum compaction shall be 95% of maximum relative density on subgrade and rock surfaces. 3.Contractor shall not leave open trenches overnight. Backfill, plate or fence all trenches. The proposed method of cover or protection shall be submitted to the Public Works Inspector for approval. Shoring plates and cold mix to be on site at all times. The inspector may require cold mix for sidewalks and driveways for safety.< 4.Watch for pedestrian traffic. Provide "Sidewalk Closed" signing as needed. A Pedestrian Escort will be required if pedestrians are to be directed through construction. CONDITIONS TO ISSUANCE OF A CONSTRUCTION PERMIT: Submit a Traffic Control Plan for approval at least five days prior to construction. Waiting. Provide a Cost Estimate and Permit Bond in the amount of 150% of total street improvements to be constructed in the City right-of-way. Not received. Provide a copy of the utility contractor’s license number. Complete. Provide a copy of the utility contractor’s City of Renton business license number. Complete. Pay all system development, special assessment, and related permit fees at time of permit issuance. Complete. Provide a signed Authorization of Special Billing. Complete. DEPARTMENT OF COMMUNITY AND ECONOMIC DEVELOPMENT 4 Last Modified 6/20/2016