Loading...
HomeMy WebLinkAboutFinal-Street Lighting Inspection Process.pdf STREET LIGHTING INSPECTION PROCESS Street Lighting Pre-Construction Meeting Separate pre-Construction meeting will be held for the street lighting construction. 1. City Representatives: a. CED Project Manager (plan reviewer) b. Construction Inspector c. Transportation Maintenance Inspector d. Electrical Inspector 2. Applicant’s Representatives: a. Applicant or General Contractor b. Electrical Contractor Inspection Items 1-3 1. Electrical Contractor will call the construction inspection phone number provided on the permit to request and schedule first inspection of street lighting. 2. Construction Inspector will: a. Inspect Items 1-3 on the Street Light-Luminaire Checklist. Any punch list items will be given directly to the electrical contractor. b. Date and initial Street Light-Luminaire Checklist when the items are acceptable and sign off the Construction Inspection Street Lighting Inspection in Energov. c. Leave permit/checklist with applicant. Inspection Item 4 1. Electrical Contractor will call the electrical inspection phone number provided on the permit to request and schedule Item 4 on the Street Light-Luminaire Checklist. 3. Electrical Inspector will: a. Inspect Item 4 on the Street Light-Luminaire Checklist. Any punch list items will be given directly to the electrical contractor. b. Date and initial Street Light-Luminaire Checklist when the checklist item is acceptable and sign off the inspection in Energov. c. Leave permit/checklist with applicant. Inspection Item 5 1. Electrical Contractor will call the electrical inspection phone number provided on the permit to request and schedule Item 4 on the Street Light-Luminaire Checklist. 2. Transportation Maintenance Inspector will: a. Inspect Item 5 on the Street Light-Luminaire Checklist. Any punch list items will be given directly to the electrical contractor. b. Date and initial Street Light-Luminaire Checklist when the checklist item is acceptable and sign off the inspection in Energov. c. Leave permit/checklist with applicant. Inspection Item 6 1. Electrical Contractor will call the electrical inspection phone number provided on the permit to request and schedule Item 6 on the Street Light-Luminaire Checklist. 2. Electrical Inspector will: a. Inspect Item 6 on the Street Light-Luminaire Checklist. Any punch list items will be given directly to the electrical contractor. b. Date and initial Street Light-Luminaire Checklist when the checklist item is acceptable and sign off the inspection in Energov. c. Leave permit/checklist with applicant, provide applicant with PSE application to energize lights, and place energize authorization sticker in junction box. Inspection Item 7 1. Electrical Contractor will: a. Submit PSE Application to energize lights to PSE. b. Call the electrical inspection phone number provided on the permit to request and schedule Item 7 on the Street Light-Luminaire Checklist once lights have been energized. 2. Electrical Inspector will: a. Inspect Item 7 on the Street Light-Luminaire Checklist. Any punch list items will be given directly to the electrical contractor. b. Date and initial Street Light-Luminaire Checklist when the checklist item is acceptable and finalize the electrical permit in Energov. c. Give one copy of permit/checklist to applicant and one copy or email to Development Engineering Secretary for Energov construction permit close-out. Automated Energov email will be sent to signal Shop of permit closeout.