HomeMy WebLinkAboutFINAL - Street Lighting Inspection Process.docxCITY OF RENTON
STREET LIGHTING INSPECTION PROCESS
Street Lighting Pre-Construction Meeting
Separate pre-Construction meeting will be held for the street lighting construction.
City Representatives:
CED Project Manager (plan reviewer)
Construction Inspector
Transportation Maintenance Inspector
Electrical Inspector
Applicant’s Representatives:
Applicant or General Contractor
Electrical Contractor
Inspection Items 1-3
Electrical Contractor will call the City of Renton Construction Inspection phone number provided on the permit to request and schedule first inspection of street lighting.
Construction Inspector will:
Inspect Items 1-3 on the Street Light-Luminaire Checklist. Any punch list items will be given directly to the electrical contractor.
Date and initial Street Light-Luminaire Checklist when the items are acceptable and sign off the Construction Inspection Street Lighting Inspection in Energov.
Leave permit/checklist with applicant.
Inspection Item 4
1. Electrical Contractor will call the City of Renton Electrical Inspection phone number provided on the permit to request and schedule Item 4 on the Street Light-Luminaire Checklist.
Electrical Inspector will:
Inspect Item 4 on the Street Light-Luminaire Checklist. Any code corrections items will be given directly to the electrical contractor.
Date and initial Street Light-Luminaire Checklist when the checklist item is acceptable and sign off the inspection in Energov.
Leave permit/checklist with applicant.
Inspection Item 5
Electrical Contractor will call the City of Renton Transportation Maintenance Inspection phone number provided on the permit to request and schedule Item 5 on the Street Light-Luminaire
Checklist.
Transportation Maintenance Inspector will:
Inspect Item 5 on the Street Light-Luminaire Checklist. Any punch list items will be given directly to the electrical contractor.
Date and initial Street Light-Luminaire Checklist when the checklist item is acceptable and sign off the inspection in Energov.
Leave permit/checklist in service cabinet and notify applicant that inspection has been completed.
Inspection Item 6
Electrical Contractor will call the City of Renton Electrical Inspection phone number provided on the permit to request and schedule Item 6 on the Street Light-Luminaire Checklist.
Electrical Inspector will:
Inspect Item 6 on the Street Light-Luminaire Checklist. Any code corrections items will be given directly to the electrical contractor.
Date and initial Street Light-Luminaire Checklist when the checklist item is acceptable and sign off the inspection in Energov.
Leave permit/checklist with applicant, notify contractor that they can now submit application (201E) to PSE to energize street lighting, and place service approval sticker in meter base.
Inspection Item 7
Electrical Contractor will:
Submit PSE Application (201E) to energize lights to PSE.
Call the City of Renton Electrical Inspection phone number provided on the permit to request and schedule Item 7 on the Street Light-Luminaire Checklist once lights have been energized.
Electrical Inspector will:
Inspect Item 7 on the Street Light-Luminaire Checklist. Any code corrections items will be given directly to the electrical contractor.
Date and initial Street Light-Luminaire Checklist when the checklist item is acceptable and finalize the electrical permit in Energov.
Give one copy of permit/checklist to applicant and one copy or email to Development Engineering Secretary for Energov construction permit close-out. Automated Energov email will be
sent to signal Shop of street lighting completion.