HomeMy WebLinkAboutReport 3 3 of 4King County
Department of Development
and Environmental Services
900 Oakesdale Avenue SW
Renton, WA 98055-1219
May 16, 2005
Cliff Williams
Belmont Homes
PO Box 2401
Kirkland, WA 98080-2401
RE: Permit Fee Estimate - Proposed Preliminary Plat of Talbot Ridge Estates
File Number: L05P0007
Dear Mr. Williams:
Beginning January 2, 2004, our office implemented a new program for managing certain
types of permit applications to provide customers with an enhanced level of customer service.
The Project Manager Program seeks to provide customers with increased predictability for the
permit process and better accountability from County review staff.
For permit applications using the Project Manager Program, a project manager is assigned to
the permit to facilitate communication with the applicant and provide a fee estimate to cover
the anticipated scope of review. The project manager will also monitor and manage the
permit application throughout the review process to ensure that review schedules remain in
line with performance standards and the overall work hours are within the range of estimated
fees for the project.
Your application was received by our office on March 24, 2005. The enclosed information
provides a summary of the fee estimate for the anticipated work disciplines and also discusses
the submittal process and disclaimers which may affect the final permit fees. Once the
attached estimated fee form is signed and submitted to our Department, including payment of
the estimated fee, review of your project will continue.
If you have any questions regarding the permit fees or other aspects of the review process,
please contact me via email Kimberly. claussenCcumetrokc.�gov or by phone at (206) 296-7167.
Sincerely,
im Claussen, Project Manager III
Current Planning Section
Enclosures
Cc: Lisa Dinsmore, Supervisor Current Planning Section, LUSD w/enc
Trishah Bull, Planner, Current Planning Section, LUSD w/enc
Bruce Whittaker, Senior Engineer, Engineering Review Section, LUSD w/enc
Administrative Section w/enc
Application File w/enc
(i)
King County
Department of Development
and Environmental Services
900 Oakesdale Avenue 5W
Renton, WA 98055-1219
Land Use Services Division Permit Fee Estimate
Application Estimate Number: L05P0007
Permit Title: Talbot Ridge Estates
Permit Type: Preliminary Plat
Date: 5/16/05
Based on permit information submitted by the applicant, the Department of Development and
Environmental Services (DDES) has determined the amount of review fees for the subject application.
The fees shown below do not include ancillary permit fees, recording fees, project -related mitigation
fees, or other fees that are passed through to the applicant from other agencies or as part of the
project's environmental review.
Fixed Fees:
Counter Service Fee for Application Intake 5483.00
Fire Review $211.83
Total Fixed Fees $694.83
Estimate for Hourly Fees: (277 Hours x $14490) $40,137.30
Total Permit Fee .Estimate: $40,832.13
Note: The estimate for hourly fees stated above is based on the total estimated number of hours not to
exceed 277. hours for the disciplines listed below, and is calculated using the department's hourly rate
in effect at the time the work is performed. Based upon the financial disclosures found on page 2, the
number of hours required may be modified. The total estimated hours reflect work performed by the
following disciplines: Engineering, Grayling, Sensitive Area, Traffic, Parks, Planning, and Project
Management. This estimate does not include hours and fees associated with variances and/or
adjustments to the King County Roads Standards and Surface Water Design Manual, engineering
plans, or additional time associated with the public hearing.
After receiving the fee estimate from DDES, the applicant has ninety (90) days to complete payment
and or establish a payment plan. Please call 206-296-6797 to set up an appointment with the Permit
Center to complete your payment. If the payment is not received within ninety (90) days, the
applicant may be required to obtain a new fee estimate or this application may be cancelled.
For further questions regarding this fee estimate or for other requirements about this permit
application, please contact Kim Claussen via email Kimberly. claussen[a)metrokc.gov or by phone at
206-296-7167.
m Claussen.
Project Manager III
Land Use Services Division
(i)
King County
Department of Development
and Environmental Services
900 Oakesdale Avenue 5W
Renton, WA 98055-1219
Land Use Services Division Permit Fee Estimate
Pre-app Estimate Number: L05P0007
Date: 5/16/05
Permit Title: Talbot Ridge Estates
Permit Type: Preliminary Plat
Estimated Maximum Hours: 277
Applicant: Cliff Will Homes
Total Fees: $40,832.13
The following disclaimers are attached and are part of the fee estimate for this permit. The applicant is
required to submit a signed copy of this form with the application and Fee payment acknowledging that
the applicant has read the disclaimers stated below.
Disclaimer
Applicants are responsible for all fixed fees, reported hours performed in reviewing submittal
materials and processing, up to the fee estimate. Changes in the scope of the project review will result
in a revised review fee estimate. Fee estimates are based on information submitted to DDES by the
applicant prior to finalization of the permit application_ In addition, estimates are determined by
utilizing historical data gathered from projects of similar type, size, and scope. The fee estimate will
be the maximum fee charged unless the scope of the project changes. Should fewer hours be required
to complete the review, then the applicant may receive a refund for those hours. If items are identified
that are not originally disclosed or identified later in the process, a new estimate may be required.
Applicants will be responsible for any additional hours identified in a new estimate because of.'
1) Changes in the project and unknown or undisclosed site issues
2) Incomplete information or errors in applicant submittal
3) County code fee changes
4) incomplete information from applicant
5) Errors in applicant information or submittal
6) County code fee changes
7) Appeals & public hearing(s)
S) Excessive Citizen inquiries, questions, etc.
9) Environmental Impact Statement
10) Additional Review for documents not provided with the initial submittal:
a) King County Road Variance application b) Surface Water Design Adjustment, etc.
Keeping review fees at or below the fee estimate will depend on the applicant's commitment to
complete the process review.
Acknowledged:
Applicant/Owner Name (signature) Date
Applicant/Owner Name (print)