Construction Mitigation
PRE17000417
• Proposed construction dates (begin and end dates);
(permitting dependent) – Start fall 2019 / End fall 2020
• Hours and days of operation;
(deadline dependent) Standard construction hours ~7am – 5pm
• Proposed hauling/transportation routes;
TBD – Likely N to S 2nd St to Bronson Way N to 405
• Measures to be implemented to minimize dust, traffic and transportation impacts, erosion, mud, noise, and other noxious
characteristics;
-Project size and scope eliminates mud, erosion, bulk of noxious characteristics.
-Bulk of project is interior work, dust will be largely contained. Exterior masonry cutting will include wetting and
encapsulation to control dust.
-Noise should be controlled due to bulk of work being interior.
• Any special hours proposed for construction or hauling (i.e. weekends, late nights);
-Not at this time
• Preliminary traffic control plan
-Not at this time