HomeMy WebLinkAbout10_Construction Mitigation Plan RYAN COMPANIES US, INC. 3900 E. Camelback Rd. Suite 100 Phoenix, AZ 85018 602-322-6100 phone 602-322-6300 fax Page 1 of 1 WWW.RYANCOMPANIES.COM August 20, 2015 Mr. Clark Close City of Renton Planning Division 1055 South Grady Way Renton, WA 98057 RE: Longacres Business Center – Phase II Construction Mitigation Description Dear Mr. Close: For Application Item 10, Construction Mitigation Description, Ryan Companies is providing the following items: 1. Anticipated construction start date is December, 2015 with completion in June, 2017. 2. Allowable working hours will be from 6:00 am to 10:00 pm Monday-Friday and from 6:00 am to 6:00 pm on Saturday. It is not anticipated that work will occur overnight and on Sundays, however as conditions present themselves we reserve the ability to work off-hours and Sundays as necessary to maintain the construction schedule. 3. The primary transportation route anticipated to site via 405 will be 167 to Grady Way, Lind Ave, to our primary entrance off of 27th. A secondary entrance will be provided off Oakesdale but will be primarily used for exiting. A Haul Route plan is attached. 4. A dedicated traffic control is not anticipated, however as required this will be developed in conjunction with the City of Renton. 5. The attached site logistic plan addresses the location of the contractor trailer complex, parking, site security and silt fencing, and wash out and track out stations. 6. Dust control will be controlled on site with water as required. A Storm Water Pollution Protection Plan will be provided as part of the final civil design package. Please do not hesitate to contact Ryan Companies if you have any questions or need further information. Sincerely, Ryan Companies U.S., Inc. Cory Handfelt Project Manager Cc: Molly Carson, Ryan Companies U.S., Inc. Dave Williams, Ryan Companies U.S., Inc. LONGACRES BUSINESS PARK: PHASE 2 SITE LOGISTICS PLAN ACCESS ROAD CRANE PATH ACCESS ROADCRANE PATH CRANE PATH ACCESS ROAD CRANE PATH CRANE PATH ACCESS ROAD TRAILER / LAY DOWN AREA FENCING FENCING FENCING FENCING FE N C I N G FENCING FENCING FENCINGFENCINGFENCING FENCINGFENCINGENTRANCE EXITACCESS ROADGROUP HEALTH - PHASE 2 SITE LOGISTICS 8/13/2015 WASHOUT/TRACKOUT STATION HAUL ROUTE SITE LOGISTICS