HomeMy WebLinkAboutAgenda
AGENDA
Utilities Committee Regular Meeting
3:30 PM - Thursday, July 13, 2017
Council Conference Room, 7th Floor, City Hall – 1055 S. Grady Way
1. Harrington Ave. Stormwater Retrofit Bid Award
a) AB - 1950 Utility Systems Division Department reports the results from the June 13, 2017
bid opening for CAG-17-108, Harrington Ave. NE Green Connections Stormwater Retrofit
Project; submits the staff recommendation to accept the lowest responsive bid from DPK,
Inc., in the amount of $904,036; and requests approval of a budget transfer of $170,000
from the approved 2017 Downtown Storm System Improvement Project budget to be
included in the next budget adjustment.
2. Emerging Issues in Utilities
AB - 1950
City Council Regular Meeting - 10 Jul 2017
SUBJECT/TITLE: Bid Award for the Harrington Avenue NE Green Connections
Stormwater Retrofit Project - Phase II (CAG-17-108) and Budget
Transfer Request
RECOMMENDED ACTION: Refer to Utilities Committee
DEPARTMENT: Utility Systems Division
STAFF CONTACT: Beth Tan, Surface Water Civil Engineer III
EXT.: 7247
FISCAL IMPACT SUMMARY:
The low bid for the project is $904,036 (including sales tax) from DPK, Inc. (Please see summary below for
more details)
SUMMARY OF ACTION:
The bid opening for the Harrington Avenue NE Green Connections Stormwater Retrofit Project – Phase II was
held on June 13, 2017. Three bids were received. The low bid for the project was $904, 036 (including sales
tax) from DPK, Inc. The engineer’s estimate for the project construction cost was $799,855. The Surface
Water Utility reviewed the low bid for completeness, inclusion of all required forms, bid bond,
acknowledgements of addenda and mathematical correctness of the bid. All paperwork for the low bid is in
order.
The engineer’s estimate for the project construction cost was $799,855. The approved 2017 Capital
Improvement Program budget for the Harrington Avenue NE Green Connections Stormwater Retrofit Project -
Phase II is $943,647, which incorporates a $50,000 transfer that is included in the City’s 2017 2nd Quarter
Budget Amendment. The Surface Water Utility is requesting the approval of a budget transfer of $170,000
from the approved 2017 Downtown Storm System Improvement Project budget to the Harrington Avenue NE
Green Connections Stormwater Retrofit Project – Phase II budget. Staff estimates that there will be sufficient
remaining funds in the Downtown Project budget to complete the 2017 work plan, and projected 2018
expenses. The additional funding is needed due to the higher than estimated construction costs and to
provide a contingency for any change orders that may occur during the project construction. The project will
be partially funded (75%) by a Washington State Department of Ecology grant in the amount of $675,000.
EXHIBITS:
A. Issue Paper
B. Vicinity Map
C. Department of Ecology Agreement Funding Notice
D. Bid Tabulation Sheet
STAFF RECOMMENDATION:
Award the construction contract to the lowest responsive, responsible bidder, DPK, Inc., for the Harrington
Avenue NE Green Connections Stormwater Retrofit Project – Phase II in the amount of $904,036 and approve
the transfer of $170,000 from the approved 2017 Downtown Storm System Improvement Project budget to
AGENDA ITEM #1. a)
the Harrington Avenue NE Green Connections Stormwater Retrofit Project – Phase II budget. The funding
transfer will be included in the next quarterly budget adjustment.
AGENDA ITEM #1. a)
PUBLIC WORKS DEPARTMENT
M E M O R A N D U M
DATE:June 27, 2017
TO:Armondo Pavone, Council President
Members of Renton City Council
VIA:Denis Law, Mayor
FROM:Gregg Zimmerman, Administrator
STAFF CONTACT:Beth Tan, Surface Water Civil Engineer III, ext. 7247
SUBJECT:Bid Award for the Harrington Avenue NE Green Connections
Stormwater Retrofit Project – Phase II (CAG-17-108) and
Budget Transfer Request
ISSUE:
Should Council award the construction contract to the lowest responsive, responsible
bidder, DPK, Inc., for the Harrington Avenue NE Green Connections Stormwater Retrofit
Project – Phase II in the amount of $904,036 and approve the transfer of $170,000 from
the approved 2017 Downtown Storm System Improvement Project budget (427.475507)
to the Harrington Avenue NE Green Connections Stormwater Retrofit Project – Phase II
budget (427.475500)?
RECOMMENDATION:
Award the construction contract to the lowest responsive, responsible bidder, DPK, Inc.,
for the Harrington Avenue NE Green Connections Stormwater Retrofit Project – Phase II
in the amount of $904,036 and approve the transfer of $170,000 from the approved
2017 Downtown Storm System Improvement Project budget (427.475507) to the
Harrington Avenue NE Green Connections Stormwater Retrofit Project – Phase II budget
(427.475500). The funding transfer will be included in the next quarterly budget
adjustment.
BACKGROUND:
The bid opening for the Harrington Avenue NE Green Connections Stormwater Retrofit
Project - Phase II was held on June 13, 2017. Three bids were received. The low bid for
the project is $904,036 (including sales tax) from DPK, Inc. The engineer’s estimate for
the project construction cost was $799,855. The Surface Water Utility reviewed the low
bid for completeness, inclusion of all required forms, bid bond, acknowledgments of
addenda, and mathematical correctness of the bid. All paperwork for the low bid is in
order.
AGENDA ITEM #1. a)
Mr. Pavone, Council President
Page 2 of 3
June 27, 2017
\BTmc
The low bid meets the following conditions for award:
1. The low bid must be within the total project budget.
2. There must be more than one bidder.
3. The lowest, responsible, responsive bid contains no significant
irregularities.
The approved 2017 Capital Improvement Program budget for the Harrington Avenue NE
Green Connections Stormwater Retrofit Project - Phase II budget (427.475500) is
$943,647, which incorporates a $50,000 transfer that is included in the City’s 2017 2nd
Quarter Budget Amendment. The Surface Water Utility is requesting the approval of a
transfer of $170,000 from the approved 2017 Downtown Storm System Improvement
Project budget (427.475507) to the Harrington Avenue NE Green Connections
Stormwater Retrofit Project – Phase II budget (427.475500). The additional funding is
needed due to the higher than estimated construction costs and to provide a
contingency for any change orders that may occur during project construction.
The approved 2017 Downtown Storm System Improvement Project budget
(427.475507) is $1,999,854. There is sufficient funding remaining in the budget to
complete the planned 2017 project work, which includes conceptual analysis and design
to identify the extent of infrastructure improvement needed, and project design to start
in 2018. An additional $5,000,000 is programmed for the project in the approved 2018
Capital Improvement Project budget for construction. The design work will offer an
updated cost estimate to determine if additional funding is needed for project
construction, which if necessary, would be requested as part of the 2019 budget
process.
The Harrington Avenue NE Green Connections Stormwater Retrofit Project – Phase II is
located along Harrington Avenue NE between NE 7th Street and NE 8th Place (vicinity
map attached). The project constructs storm system improvements and adds low
impact development (LID) improvements, which includes 995 linear feet of new storm
pipe system, three bioretention facilities to provide water quality treatment to the
stormwater runoff from the roadway and 650 linear feet of porous concrete sidewalks
that reduce the quantity of stormwater runoff by infiltrating runoff, which will also
improve pedestrian access. This LID project will provide water quality treatment and
infiltrate the runoff, thereby reducing runoff to Johns Creek, which drains into Lake
Washington through Gene Coulon Memorial Park. The project was identified in the
Sunset Area Surface Water Master Plan developed as part of the approved Sunset
Community Planned Action EIS.
The Harrington Avenue NE Green Connections Stormwater Retrofit Project - Phase II
received a Washington State Department of Ecology (Ecology) grant in 2016 (WQC-
2016-Renton-00129) in the amount of $675,000 for design, construction and project
management. This grant provides 75% of the funding for the project. The cost for
AGENDA ITEM #1. a)
Mr. Pavone, Council President
Page 3 of 3
June 27, 2017
\BTmc
construction is now higher than originally estimated. The Surface Water Utility will
request additional grant funding from Ecology for the project. Washington State
Department of Ecology may be able to provide additional funding if there are unused
grant funds within their grant program from completed projects, or from grants that
were declined by other jurisdictions. However, Ecology will not know if there will be
funding available until later this year, which has prompted this request for approval of
the funding transfer so that the contract can be awarded.
Additionally, the City received a letter dated June 2, 2017, from Washington State
Department of Ecology (attached) regarding the grant agreement for the project. It
states that if the Washington State Legislature does not pass a budget by midnight on
June 30, 2017, the grant agreement will be suspended and we are to cease incurring any
further expenditures related to the grant agreement until the state budget is approved.
If the Legislature has not passed a state budget, and the grant agreement is suspended
at the time of the Council meeting for approval of the bid award and budget transfer for
the project, City staff will be required to change our recommendation to reject all bids
and not approve the budget transfer due to suspension of the grant agreement and
uncertainty surrounding state grant funding for the project. City staff anticipates the
state budget will pass before the June 30 deadline, or at least before the July 10 Council
meeting. The City has 45-days following a bid opening to award the construction
contract; the project bid opening date was June 13, 2017, which puts the 45-days at July
28, 2017.
Attached for reference is the bid tabulation sheet showing the engineer's estimate, the
low bid, and the other submitted bids. We are returning all bid envelopes and bid
documents from the other bidders to the City Clerk for their files.
CONCLUSION:
The Surface Water Utility requests that Council award the construction contract to DPK,
Inc., to construct the Harrington Avenue NE Green Connections Stormwater Retrofit
Project – Phase II in the amount of $904,036 and further requests that Council authorize
a transfer of $170,000 from the 2017 Downtown Storm System Improvement Project
budget (427.475507) to the Harrington Avenue NE Green Connections Stormwater
Retrofit Project – Phase II budget (427.475500) to fully fund the project.
Attachments
cc: Lys Hornsby, Utility Systems Director
Ron Straka, Surface Water Utility Engineering Manager
Hai Nguyen, ASD Sr. Finance Analyst
Kristin Trivelas, ASD Sr. Finance Analyst
Teresa Phelan, Utility Systems Sr. Program Specialist
Melissa Crawford, Utility Systems Administrative Secretary I
AGENDA ITEM #1. a)
Harrington Ave NE
Green Connections
Stormwater Retrofit
Phase II Project
Harrington Ave NE Green Connections
Project NE 7th St to NE 8th Pl –Phase II
Proposed Project
Vicinity Map AGENDA ITEM #1. a)
STATEOFWASHINGTONDEPARTMENTOFECOLOGYP0Box47600.Olympia,WA98504-7600•360-407-6000771forWashingtonRelayService•Personswithaspeechdisabilitycancall277-833-6347June2,2017RENTONCITYOFRENTONCITYHALL,5THFLOOR,1055SGRADYWAYRENTONWA92057-3232AgreementfundingNotice:PleaseForwardThistoYourOrganization’sContactforEcologyAgreementWQC-2016-Renton-00129.Thisletterprovidesnoticeofapossibleimpacttoyourcontract,grant,loan,orinterlocalagreement(“agreement”)withtheDepartmentofEcology.Asofthisletter’sdate,theWashingtonStateLegislaturehasnotyetenactedastatebudgettoappropriatefundstostateagenciesfortheupcomingbiennium.Theappropriationssetforthinthestate’scurrentbudgetexpireattheendofthedayonJune30,2017.Asageneralrule,theWashingtonStateConstitution(Article2,Section4)andstatelaw(RCW43.28.130andRCW43.22.290)prohibitexpendituresorcommitmentsofstatefundsintheabsenceofappropriationsofsuchfundsbytheLegislature.Withoutabudgetappropriation,agenciescanneitherexpendfundsnorincurliabilitiesafterJune30,2017.IfastatebudgetisenactedbymidnightonJune30,2017,orappropriationsareotherwiseauthorizedatthattime,thenyouragreementshallcontinuewithoutanyeffect.However,intheeventthebudgetisnotenactedintolawbythedeadlineofmidnightonJune30,2017,thisnoticewillsuspendyouragreementeffectiveattheendofthedayonJune30,2017.OncetheLegislaturesubsequentlypassesthebudgetanditissignedintolaw,youragreementwouldautomaticallybeactiveandallofthetermswithinwouldremaininfullforceandeffect.Pursuanttothiscontingentsuspensionortermination,ifastatebudgetisnotenactedbyJuly1,2017,thenEcologydirectsyoutoceaseorrefrainfromanyactivitiesthatincurexpensetothestateunderyouragreement.Thisfinancialrestrictionappliestoallsubcontractorstowhichyouhaveawardedworkunderyouragreement.WeexpectyoutonotifyyoursubcontractorsofthissituationandinstructthemtopreparetoceaseorrefrainfromanyactivitieseffectiveJuly1,2017.CostsincurredpriortoJuly1,2017arecoveredunderthecurrentbudgetandwillnotbeimpactedbythissuspension.AGENDA ITEM #1. a)
RentoncityofPage2June2,2017Oncethelegislatureenactsabudgetandprovidesappropriationtotheagencyfortheupcomingbiennium,wewillsendawrittennoticecancelingthesuspension.Weunderstandthatthisuncertaintyisconcerningtoourpartners,andweappreciateyourpatienceasweallawaitenactmentofastatebudgetorotherappropriations.PleasedirectallquestionstoJeffNejedly,(360)407-6572,whowillactasyourpointofcontactforthisissue.Thankyou,\\ErikFairchildChiefFinancialOfficerAGENDA ITEM #1. a)
CITYOFRENTONBIDTABULATIONSHEETProject:HarringtonAvNEGreenConnectionStormwaterRetrofitProject-PhaseII-CAG-17-108Date:June13,20171of1FORMSBidTotalfromBidderProposalBidDept.AddendaSubcontractorsScheduleofPrices&Aff.BondL&IAck.List*lncludesSalesTaxDPK,Inc/7829S.206thStreet1Kentjo4O?WA98032Jansen,IncVV/1215W.HollyStreet2Bellingham,2.7WA98225/RoadConstructionNorthwest,IncV‘‘PCBox2228V3RentonWA9805642Engineer’sEstimate$799,855.00AGENDA ITEM #1. a)