HomeMy WebLinkAboutT-270311! r I CITY OF RENTON'S CONTRACTOR GENERAL NOTES PRE - CONSTRUCTION MEETING: 1. A pre - construction meeting will be held between Puget $pond Energy and the contractori installing the vault and conduit system. This Puget ,Sound Energy inspector and Project Manager along with the contractors supervisor and crew I foreman. This meeting shall precede any construction off ort described in this document. MATERIAL AND DELIVERY: 2. Puget Sound Energy is to provide vault and cover delivery and off load to job site or staging area per City Contractors desires. Minimum one week ad'a"o notice is required fa voCr /t de /l very. t t vaults into vault hole. r v l/ cranes or bo o se ou s a ma need to o ids a J. City's contractor P Y Larger vaults require access to VOL /t ha /e by delivery ,truck. Note: weight of void is indi toted in the VAULT INSTALLATION DETAILS. 4. Puget Sound Energy is to provide all materials ;nc /uding conduit, conduit spacers. po/yconduit. sonotubes, bends. brackets. PVC cement, put /ing fish line. ground plates. 2 Bare CU conductor and related hardware needed to comp /eeto the bare vault and conduit system. This delivery to be with o 48 hour notice. it 5. City's contractor supervisor is to sign the delivery invoice verifying the material delivered before Puger Sauna Energy wit/ off load material to des 'j gnoted site. 6. Any Puget Sound energy excess material will be turned.oYer to Puget Sound energy when it usable his exc ss malaria/ will be returned i is known that this material will not be used. T condition and City's contractor supervisor !s to sign aid return the invoice. 7. City's contractor is responsible for a// material and rgplacefrent of all material del rl vered to the job site. 8. Cltys contractor is to provide cover or protection for !voul is set in construction zone Any crushed covers or broken /ids wit/ not be accepted. Vaults will need to be bockf!//ed immediately or protection provided per City of Renton requirements• 9. All vaults. handho /es. conduits. pole risers and street) light po/ycondult and sonotubes ore to be installed according to the instructions given be /ow 'and in the VAULT INSTALLATION DETAILS. CONDUIT INSTALLAL TION DETAIL, and the DETAILS IOR THE INSTALLATION OF STREET LIGHT SYSTEM. VAULTS. VOI, V02 10. City of Renton contractor is to instal,/: 'I Two 76'X142':Y90" with 2 -42" manholes. The manhole cover ring is 4" thick. !n ooditi there wi I/ be four 12' risers stocked at each naMale. i) .a ire is to be instal st vaults �'with 142" dimension Ground plates and. 2 bore CU w y` parallel to the center line of construction . Vaults mu t be set on City of Renton rig t of -Roy or In easement area behind sidewalk. r 17I. Vou /t5 are to be set with the manhole Cover flush with ,de wo /k grvds . VAUL TS: V03. 12. City of Renton contractor Is to instal/: 1 One 76 x142 "x90" vault with 3 -3' square doors. I. Ground plate': and #2 Bore CU wire is to to installed. 5�t vaults with 142 "dimension P center /ineof construction . Vaults must be set, on Ci tX of Renton right- Of -way or in 'easement area behind the sidewalk. 'I 13. Vault to be set 2" above finished grade and to prof! /sin landscape areas. VAUL T5: '102' "031 J04. ✓05. 106. -i 14. City of Renton contractor to instal/: Five 56" x 84" x 60" vaults with 2 -3' square. doors Ground plate and a2 Bore CU wire. is to be installed. Sot vaults with 84" dimension ',petal /e/ to center line of construction except where noted. Vaults try st be set on City of Renton right - of -way or in easement area behind the sidewalk. 15. vaults H02. ✓01 & T03 are existing. Bring the new conduit to outside of vault and stop conduit runs. Puget Sound Energy shall tie in the new Conduit runs to existing energ ;�ed vaults. 16. A// voults are to be set and adjusted flush to the sidewalk or road prof! le. Vout is are to be set 2" above the finished grade and to profile !n landscaped areas. TRANSFORMERS :T01, T02, TO4, T05. 708. (PS£ to Into // TF6 and T07) 17. City's contractor is to install: 1 One 84" x 84" x 42" vault with 96" x 96" x 8" cover (601" x 24" access note). Four 56" x 56" x 42" vaults with 56" x 66" x 6" cover (:ff" x 20" access he /e). Provide vault excavation for one 36" x. 42" x 38" minipaQ handho /es (se /f grounding) Instal/ ground plates a minimum of 5 feet deep. Extendi.a'2 capper ground wires into j vaults. Locate these transformer vaults behind sldswal, on city's right-of-way or on private that set and level vault so the top /id is 2 " labove finished grade. Switch vaults: 501, 502 18. Cl ty of Renton contractor is to instal1:.. Two 76 x142 x90" vaults with 74" x 136" x B" cover (1: -31 door & 60" x 54" access) I; Ground plates and x2 Bore CU wire is to be installed (Py will instal/ perimeter groungI. Set vaults with 76" side parallel to center line of canstuctlan except where noted. Vocal fs must be set on City of Renton right- of -way or n�eosement area behind the sidewalk. HANDHOLES: H05. H06 & H08 19. City contractor is to install three 32" x 44" x 36" honghole with H2O steel door. HO1, H07 & H09 are existing and energized. They require additional conduit plumbed per detoi /s• Puget Sound Energy shall assist with the conduit installation into energized handholes, H02 will be removed and the customer will be required to wire out new service conductor to transformer TO2. CONDUIT AND POLE RISERS: { 20. Into /led conduit runs are to be cleaned and tested with a mandrel pulled freely from end to end. This testing is to be comp leted after Dackfill material is compacted to City of Renton's project requirements. A contra /led density slurry mdterlia /'may be used to obtain the needed protect Ion around the conduits to ensure that compacfiori of. bockfi// material will noticrush the conduits. 21. Conduit run must be tested before Puget Sound Energy wi4/ accept the installation. Conduit runs not passing mandrel testing Will be re- excavated and repaired at city's contractors expense. 'I I 22. City's contractor to camplete conduit runs section by section and not engage in multiple conduit section installation without completing the previous section. This enables Pu et Sound Energy, without delay, to install conductors and connectors to maintain project scheduling. 1 23. Conduit spacers will be used every 5 feet and pulling - fishline Installed in each conduit run. i 24. Pole riser conduit bends, transformer conduit bends, and trench conduit bends have different radius and the City's contractor, Will reference the sit notes, details and into /lotlpn instruction for the proper radius: bends. 25. Use ��90 degree bends only when specifically co /led for. :i Use 22.5 degree bends when needed . and approved by Puget Sound Energy inspector. 26. All transformer handhole conduits will ;sweep from the main trench to the transformer hondhhole. The only bends at the transformer will be th¢I bends directly in the nondholg. Via' W -sjo3 MAIN AVE SOUTH ROAD IMPRO VK ENTS & ELECTRICAL CO VERSION ' :V1L1 /V1 /r MA t-- N. T. S. PROJECT DESCRIPTION: The City ofRenton has entered into an agreement with Puget Sound Energy to convert the existing electrical overhead facilities to on underground electrical system 'along' Moira Ave S. The boundaries extend from South Grady Way to Houser Way S. 27. 'Total conduit footage is as to /lows:! : . 2"08 PVC -320 feet ' 3" DB PVC -- 7020 feet ' 4" OB PVC = 5260 feet 6 " OB PVC = 8020 feet 28. There ore twelve pole risers to be installed Five 4" risers Six 6" risers PUCET SOUND ENERGY CONSTRUCTION NOTES 1. . Puget Sound energy will be able to remove the existing overhead electrical poles and - conductors upon comp tali on of the following: -', The entire underground electrical system is !meta /led and energized. -'A /l individual house services ore determined to remain overhead or are served from the new underground main electrical trench. - All other utilities hove vacated the existing overhead poles. ' 2. Puget Sound Energy is to top poles and remove Puget Sound Energy facilities and abandon poles to other utilities per existing joint facility pole agreements. 3. All new pole locations ore Lobe installed by Puget Sound Energy. Poles are to be froned pet Puget Sound Energy Standards unless otherwise noted. 4. Pole locutions are to be stoked or marked in the field by Puget Sound Energy representative. 5. All construction is to be per Puget Sound Energy Stgndords according to documents ,con Coined in the following Puget Sound Energy publications or their replacements: Line Construction Manual. 1995 '. Line Practices Mgnuol, Vol. 1, 1995 'L ins Practices Manual, Vol. .2. 1995 underground circuit nap and '.ins fall cable numbers per underground circuit mop -' . 7. Puget Sound Energy to install service stubou is per cable notes ond;service circuit I GElb'_LIVRAL PROJECT NOTES CITY'S CONTRACTOR GENERAL RESPONS/BlLITIES: 1. The City of Renton's cantro - ctar will be . 9sponsib le for the installation o f the bore conduit and vault system in which Puget Sound Energy will %metal/ all electrical conductors and connections. This bare conduit and vault system inc /odes conduit, conduit spacers, vau /ts, vault covers, handho /es. ^� ^�^d p /ales with 02 Bore CU wire, and other related hardware.' 2. The bare conduit and vc ;/t system is described in individual site de tqi /s and specific installation instructions ore shown in the VAULT INSTALLATION DETAILS, and CONOU /T INSTALLATION DETAIL S.These details are contained in this document titled, Renton, City of - Main Avenue South Conversion, under Puget Sound Energy work order 9853449 J. Puget Sound Energy will be reponsib /e for vault and conduit installation on private property through the parking lot between 304 and 330 main ova south. 4. All trenching, vault and handhole excovdti on. bockfi l/, and res torotion to convert' the overhead a /ectricol system to an underground system is the responsibility of t ^e City of Renton's contractor. This inc /odes ol/ City right -of -way and private property work. except as noted in this document. 5. Back fi l/ material will be clean pi true sand. with 4 inches of cover. before repave spoils or select structure/ material is used fo back f! I the french. Conduits are to be encased with this clean pi trop sand before any bockfi // material and corrpacti on cormences. A controlled density slurry material may be used to obtain the needed protection around the conduits to ensure that compaction of bockfi ll material will not crush the conduit. INSPECTION REOU/REMENTS: 6. Puget Sound Energys inspector will be the construction site contact for al/ issues concerning this Main Avenue South conversion project. ' 7. The City's contractor will work with Puget Sound Energy inspector to ensure that oil vaults ' . and conduits ore installed to the specifications itemized in this document. Ci tys contractor is to notify. coordinate, and arrange with. Puget Sound Energy inspector 24 hours prior to ' any vault and conduit work or any construction work that involves. or affects :�Puget Sound, �i Energy foci / i ti es• ' : 8. Mu /tiple site construction to be scheduled the some '24 hours notice to ensure that Puget ' Sound Energy inspector will be :able to inspect multiple sites. 9. The city's contractor will not bockfi / /ony conduit. perform any vault construction or perform any work directly! affecting existing Puget Sound Energy facilities until the Puget Sound Energy inspector has approved the construction according to the specifications in this document. ' Construction work that is bockfi lied without inspection will be re- excavated by the Ci tys contractor for inspection by the Puget Sound Energy inspector before the construction is approved. 10. The coordination of any construction or any construction issues ifrp/ied by the above notes shall be inspected by the Puget Sound Energy inspector. Any changes of facilities covered in this document will be approved prior to construction. by the Puget Sound Energy ,inspector. 11. Puget SounO Energy inspector has the authority to stop construction of Puget Sound Energys foci /'ties if,ony OSHA. WlSHA or City of Renton. safety rules are violated. The Puget Sound Energy inspector also the authority to act upon any observed safety infractions or unsafe working conditions throughout: the entire project. The Puget Sound Energy inspector has the authority to report. safety Infractions or unsafe working conditions to the General Contractor. City of Renton.. and the Washington Department of labor and industries. PUCET SOUND ENERGY RESPONSIBILITIES. 12. Puget Sound Energy wi / /be responsible to provide all materials, including conduit, po /yconduit, sonotubes, bends. brackets. PVC ceflent, pulling fishline, vaults, access covers, ground plates, A7 Bore CU conductor, and related hardware needed for the complete bore conduit and vault system for the new underground electrical system. 13. Puget Sound Energy will installs all electrical conductors, connectors. fuses, street light poles. luminaries, and vault ground loops. 14. Puget Sound Energy will be able to remove the existing overhead electrical facilities only after o// the new underground electrical system is coop le to and energized, including all customer services converted to the new underground a /ectricol system. 15. Puget Sound Energy will either abandon the o/d poles to another utility or remove these poles according to the existing joint utilities pole agreement with US West and TC/. PUCE TSOUND ENERGY FOREMAN NOTES: ' 16. Charge Il conductorand equipment installation and makeup for work along Moira Ave. South associated with .circuit GRA -17 to work order 98- 53449. 17. Charge all conductor and :equipment installation and makeup for work along Main Ave. South associated with circuit GRA -16 to work order 98- 53451. 18. Charge 'all conductor and, equipment installation and makeup for work along Houser Way South and Renton Ave. South, associated with circuits GRA -16 and GRA -17 to work order 98- 53451. 19. a. Charge all trench, backfill, and restoration for vault and conduit installation on private property between 304 and 330 Main . Ave. South to work order 98- 53451. b. ' Charge all conduit, :.vault, conductor, and equipment installation and makeup between 304 and 330 Main Ave South to work order 98- 53457. PUCET SOUND ENERGY CONTACTS: ' Project Manager -Andy Lo Bey Telephone: 253 - 395 -6962 Cellular: 206 - 406 -5161 Pager:. 206- 994 -8723 Ti 270.311 i CALL i -800- 424 -5555 2 BUSINESS DAYS BEFORE YOU DIG WCbENT• WO• (POwEfl/ DRAWN, Y. FD PUCET ENGWEERED A. LOWREY roe -s]4an SOUND u A$1 Aw i "- ENERGY CMEGKEO� M. COPPS SCANNED FEB 15 2002 ArPAOVeO- J. GOODFELLOW SCALE: N.T.S. !/ 9 !74: It �; FIR 17:`16 U, + Q RfNTON 1 - - a $1 AIR OR7 WY � _ st q • _!3� �Yt NE z S=7LL1 t S TOBIH T,ufun 74. 8 to ^. 1 00n : ',N. sy@ air S 3 VICTORS 300 N S 2ND �'•, � 100 h v, �°° 8 � • 11 z ® S 3RD' •11 PL 1gLI0AY � � m' S J�Z PARK ■. ^ AO`� � � < �_ GATE (n ENTON VILLAGE CENTER Is .� ARNDID i I �ZN pP. � S.R TONVILLAGE ' :V1L1 /V1 /r MA t-- N. T. S. PROJECT DESCRIPTION: The City ofRenton has entered into an agreement with Puget Sound Energy to convert the existing electrical overhead facilities to on underground electrical system 'along' Moira Ave S. The boundaries extend from South Grady Way to Houser Way S. 27. 'Total conduit footage is as to /lows:! : . 2"08 PVC -320 feet ' 3" DB PVC -- 7020 feet ' 4" OB PVC = 5260 feet 6 " OB PVC = 8020 feet 28. There ore twelve pole risers to be installed Five 4" risers Six 6" risers PUCET SOUND ENERGY CONSTRUCTION NOTES 1. . Puget Sound energy will be able to remove the existing overhead electrical poles and - conductors upon comp tali on of the following: -', The entire underground electrical system is !meta /led and energized. -'A /l individual house services ore determined to remain overhead or are served from the new underground main electrical trench. - All other utilities hove vacated the existing overhead poles. ' 2. Puget Sound Energy is to top poles and remove Puget Sound Energy facilities and abandon poles to other utilities per existing joint facility pole agreements. 3. All new pole locations ore Lobe installed by Puget Sound Energy. Poles are to be froned pet Puget Sound Energy Standards unless otherwise noted. 4. Pole locutions are to be stoked or marked in the field by Puget Sound Energy representative. 5. All construction is to be per Puget Sound Energy Stgndords according to documents ,con Coined in the following Puget Sound Energy publications or their replacements: Line Construction Manual. 1995 '. Line Practices Mgnuol, Vol. 1, 1995 'L ins Practices Manual, Vol. .2. 1995 underground circuit nap and '.ins fall cable numbers per underground circuit mop -' . 7. Puget Sound Energy to install service stubou is per cable notes ond;service circuit I GElb'_LIVRAL PROJECT NOTES CITY'S CONTRACTOR GENERAL RESPONS/BlLITIES: 1. The City of Renton's cantro - ctar will be . 9sponsib le for the installation o f the bore conduit and vault system in which Puget Sound Energy will %metal/ all electrical conductors and connections. This bare conduit and vault system inc /odes conduit, conduit spacers, vau /ts, vault covers, handho /es. ^� ^�^d p /ales with 02 Bore CU wire, and other related hardware.' 2. The bare conduit and vc ;/t system is described in individual site de tqi /s and specific installation instructions ore shown in the VAULT INSTALLATION DETAILS, and CONOU /T INSTALLATION DETAIL S.These details are contained in this document titled, Renton, City of - Main Avenue South Conversion, under Puget Sound Energy work order 9853449 J. Puget Sound Energy will be reponsib /e for vault and conduit installation on private property through the parking lot between 304 and 330 main ova south. 4. All trenching, vault and handhole excovdti on. bockfi l/, and res torotion to convert' the overhead a /ectricol system to an underground system is the responsibility of t ^e City of Renton's contractor. This inc /odes ol/ City right -of -way and private property work. except as noted in this document. 5. Back fi l/ material will be clean pi true sand. with 4 inches of cover. before repave spoils or select structure/ material is used fo back f! I the french. Conduits are to be encased with this clean pi trop sand before any bockfi // material and corrpacti on cormences. A controlled density slurry material may be used to obtain the needed protection around the conduits to ensure that compaction of bockfi ll material will not crush the conduit. INSPECTION REOU/REMENTS: 6. Puget Sound Energys inspector will be the construction site contact for al/ issues concerning this Main Avenue South conversion project. ' 7. The City's contractor will work with Puget Sound Energy inspector to ensure that oil vaults ' . and conduits ore installed to the specifications itemized in this document. Ci tys contractor is to notify. coordinate, and arrange with. Puget Sound Energy inspector 24 hours prior to ' any vault and conduit work or any construction work that involves. or affects :�Puget Sound, �i Energy foci / i ti es• ' : 8. Mu /tiple site construction to be scheduled the some '24 hours notice to ensure that Puget ' Sound Energy inspector will be :able to inspect multiple sites. 9. The city's contractor will not bockfi / /ony conduit. perform any vault construction or perform any work directly! affecting existing Puget Sound Energy facilities until the Puget Sound Energy inspector has approved the construction according to the specifications in this document. ' Construction work that is bockfi lied without inspection will be re- excavated by the Ci tys contractor for inspection by the Puget Sound Energy inspector before the construction is approved. 10. The coordination of any construction or any construction issues ifrp/ied by the above notes shall be inspected by the Puget Sound Energy inspector. Any changes of facilities covered in this document will be approved prior to construction. by the Puget Sound Energy ,inspector. 11. Puget SounO Energy inspector has the authority to stop construction of Puget Sound Energys foci /'ties if,ony OSHA. WlSHA or City of Renton. safety rules are violated. The Puget Sound Energy inspector also the authority to act upon any observed safety infractions or unsafe working conditions throughout: the entire project. The Puget Sound Energy inspector has the authority to report. safety Infractions or unsafe working conditions to the General Contractor. City of Renton.. and the Washington Department of labor and industries. PUCET SOUND ENERGY RESPONSIBILITIES. 12. Puget Sound Energy wi / /be responsible to provide all materials, including conduit, po /yconduit, sonotubes, bends. brackets. PVC ceflent, pulling fishline, vaults, access covers, ground plates, A7 Bore CU conductor, and related hardware needed for the complete bore conduit and vault system for the new underground electrical system. 13. Puget Sound Energy will installs all electrical conductors, connectors. fuses, street light poles. luminaries, and vault ground loops. 14. Puget Sound Energy will be able to remove the existing overhead electrical facilities only after o// the new underground electrical system is coop le to and energized, including all customer services converted to the new underground a /ectricol system. 15. Puget Sound Energy will either abandon the o/d poles to another utility or remove these poles according to the existing joint utilities pole agreement with US West and TC/. PUCE TSOUND ENERGY FOREMAN NOTES: ' 16. Charge Il conductorand equipment installation and makeup for work along Moira Ave. South associated with .circuit GRA -17 to work order 98- 53449. 17. Charge all conductor and :equipment installation and makeup for work along Main Ave. South associated with circuit GRA -16 to work order 98- 53451. 18. Charge 'all conductor and, equipment installation and makeup for work along Houser Way South and Renton Ave. South, associated with circuits GRA -16 and GRA -17 to work order 98- 53451. 19. a. Charge all trench, backfill, and restoration for vault and conduit installation on private property between 304 and 330 Main . Ave. South to work order 98- 53451. b. ' Charge all conduit, :.vault, conductor, and equipment installation and makeup between 304 and 330 Main Ave South to work order 98- 53457. PUCET SOUND ENERGY CONTACTS: ' Project Manager -Andy Lo Bey Telephone: 253 - 395 -6962 Cellular: 206 - 406 -5161 Pager:. 206- 994 -8723 Ti 270.311 i CALL i -800- 424 -5555 2 BUSINESS DAYS BEFORE YOU DIG WCbENT• WO• (POwEfl/ DRAWN, Y. FD PUCET ENGWEERED A. LOWREY roe -s]4an SOUND u A$1 Aw i "- ENERGY CMEGKEO� M. COPPS SCANNED FEB 15 2002 ArPAOVeO- J. GOODFELLOW SCALE: N.T.S. !/ 9 !74: It �; FIR 17:`16 PL 1gLI0AY � � m' 27. 'Total conduit footage is as to /lows:! : . 2"08 PVC -320 feet ' 3" DB PVC -- 7020 feet ' 4" OB PVC = 5260 feet 6 " OB PVC = 8020 feet 28. There ore twelve pole risers to be installed Five 4" risers Six 6" risers PUCET SOUND ENERGY CONSTRUCTION NOTES 1. . Puget Sound energy will be able to remove the existing overhead electrical poles and - conductors upon comp tali on of the following: -', The entire underground electrical system is !meta /led and energized. -'A /l individual house services ore determined to remain overhead or are served from the new underground main electrical trench. - All other utilities hove vacated the existing overhead poles. ' 2. Puget Sound Energy is to top poles and remove Puget Sound Energy facilities and abandon poles to other utilities per existing joint facility pole agreements. 3. All new pole locations ore Lobe installed by Puget Sound Energy. Poles are to be froned pet Puget Sound Energy Standards unless otherwise noted. 4. Pole locutions are to be stoked or marked in the field by Puget Sound Energy representative. 5. All construction is to be per Puget Sound Energy Stgndords according to documents ,con Coined in the following Puget Sound Energy publications or their replacements: Line Construction Manual. 1995 '. Line Practices Mgnuol, Vol. 1, 1995 'L ins Practices Manual, Vol. .2. 1995 underground circuit nap and '.ins fall cable numbers per underground circuit mop -' . 7. Puget Sound Energy to install service stubou is per cable notes ond;service circuit I GElb'_LIVRAL PROJECT NOTES CITY'S CONTRACTOR GENERAL RESPONS/BlLITIES: 1. The City of Renton's cantro - ctar will be . 9sponsib le for the installation o f the bore conduit and vault system in which Puget Sound Energy will %metal/ all electrical conductors and connections. This bare conduit and vault system inc /odes conduit, conduit spacers, vau /ts, vault covers, handho /es. ^� ^�^d p /ales with 02 Bore CU wire, and other related hardware.' 2. The bare conduit and vc ;/t system is described in individual site de tqi /s and specific installation instructions ore shown in the VAULT INSTALLATION DETAILS, and CONOU /T INSTALLATION DETAIL S.These details are contained in this document titled, Renton, City of - Main Avenue South Conversion, under Puget Sound Energy work order 9853449 J. Puget Sound Energy will be reponsib /e for vault and conduit installation on private property through the parking lot between 304 and 330 main ova south. 4. All trenching, vault and handhole excovdti on. bockfi l/, and res torotion to convert' the overhead a /ectricol system to an underground system is the responsibility of t ^e City of Renton's contractor. This inc /odes ol/ City right -of -way and private property work. except as noted in this document. 5. Back fi l/ material will be clean pi true sand. with 4 inches of cover. before repave spoils or select structure/ material is used fo back f! I the french. Conduits are to be encased with this clean pi trop sand before any bockfi // material and corrpacti on cormences. A controlled density slurry material may be used to obtain the needed protection around the conduits to ensure that compaction of bockfi ll material will not crush the conduit. INSPECTION REOU/REMENTS: 6. Puget Sound Energys inspector will be the construction site contact for al/ issues concerning this Main Avenue South conversion project. ' 7. The City's contractor will work with Puget Sound Energy inspector to ensure that oil vaults ' . and conduits ore installed to the specifications itemized in this document. Ci tys contractor is to notify. coordinate, and arrange with. Puget Sound Energy inspector 24 hours prior to ' any vault and conduit work or any construction work that involves. or affects :�Puget Sound, �i Energy foci / i ti es• ' : 8. Mu /tiple site construction to be scheduled the some '24 hours notice to ensure that Puget ' Sound Energy inspector will be :able to inspect multiple sites. 9. The city's contractor will not bockfi / /ony conduit. perform any vault construction or perform any work directly! affecting existing Puget Sound Energy facilities until the Puget Sound Energy inspector has approved the construction according to the specifications in this document. ' Construction work that is bockfi lied without inspection will be re- excavated by the Ci tys contractor for inspection by the Puget Sound Energy inspector before the construction is approved. 10. The coordination of any construction or any construction issues ifrp/ied by the above notes shall be inspected by the Puget Sound Energy inspector. Any changes of facilities covered in this document will be approved prior to construction. by the Puget Sound Energy ,inspector. 11. Puget SounO Energy inspector has the authority to stop construction of Puget Sound Energys foci /'ties if,ony OSHA. WlSHA or City of Renton. safety rules are violated. The Puget Sound Energy inspector also the authority to act upon any observed safety infractions or unsafe working conditions throughout: the entire project. The Puget Sound Energy inspector has the authority to report. safety Infractions or unsafe working conditions to the General Contractor. City of Renton.. and the Washington Department of labor and industries. PUCET SOUND ENERGY RESPONSIBILITIES. 12. Puget Sound Energy wi / /be responsible to provide all materials, including conduit, po /yconduit, sonotubes, bends. brackets. PVC ceflent, pulling fishline, vaults, access covers, ground plates, A7 Bore CU conductor, and related hardware needed for the complete bore conduit and vault system for the new underground electrical system. 13. Puget Sound Energy will installs all electrical conductors, connectors. fuses, street light poles. luminaries, and vault ground loops. 14. Puget Sound Energy will be able to remove the existing overhead electrical facilities only after o// the new underground electrical system is coop le to and energized, including all customer services converted to the new underground a /ectricol system. 15. Puget Sound Energy will either abandon the o/d poles to another utility or remove these poles according to the existing joint utilities pole agreement with US West and TC/. PUCE TSOUND ENERGY FOREMAN NOTES: ' 16. Charge Il conductorand equipment installation and makeup for work along Moira Ave. South associated with .circuit GRA -17 to work order 98- 53449. 17. Charge all conductor and :equipment installation and makeup for work along Main Ave. South associated with circuit GRA -16 to work order 98- 53451. 18. Charge 'all conductor and, equipment installation and makeup for work along Houser Way South and Renton Ave. South, associated with circuits GRA -16 and GRA -17 to work order 98- 53451. 19. a. Charge all trench, backfill, and restoration for vault and conduit installation on private property between 304 and 330 Main . Ave. South to work order 98- 53451. b. ' Charge all conduit, :.vault, conductor, and equipment installation and makeup between 304 and 330 Main Ave South to work order 98- 53457. PUCET SOUND ENERGY CONTACTS: ' Project Manager -Andy Lo Bey Telephone: 253 - 395 -6962 Cellular: 206 - 406 -5161 Pager:. 206- 994 -8723 Ti 270.311 i CALL i -800- 424 -5555 2 BUSINESS DAYS BEFORE YOU DIG WCbENT• WO• (POwEfl/ DRAWN, Y. FD PUCET ENGWEERED A. LOWREY roe -s]4an SOUND u A$1 Aw i "- ENERGY CMEGKEO� M. COPPS SCANNED FEB 15 2002 ArPAOVeO- J. GOODFELLOW SCALE: N.T.S. !/ 9 !74: It �; FIR 17:`16