HomeMy WebLinkAboutContract . CAG-13-026
CITY OF RENTON
CONTRACT AGREEMENT
THIS AGREEMENT is made as of the day of February, 2013, between the CITY OF RENTON, a
municipal corporation of the State of Washington, hereinafter referred to as "CITY" and EDI Enriched
Designs, Inc., hereinafter referred to as "CONTRACTOR,"to restore the Ron Regis Park Storage Facility
Due to Fire Damages, 1501 Orcas Ave.SE, Renton,Washington, 98058.
The City and Contractor agree as set forth below.
1. Scope of Services. The Contractor will provide all material and labor necessary to perform all work
described in the The Scope of Work and Proposal which is included with this Agreement as
"Attachment A."
2. Changes in Scope of Services. The City, without invalidating the Contract, may order changes in the
Services consisting of additions, deletions or modifications,the Contract Sum being adjusted
accordingly. Such changes in the work shall be authorized by written Change Order signed by the City
and the Contractor.
3. Time of Performance. The Contractor shall commence performance of the Contract no later than Ten
10 calendar days after Contract's final execution, and shall complete the full performance of the
Contract not later than Sixty 60 calendar days from the date of commencement.
4. Term Of Contract.The Term of this Agreement shall end at completion of the enclosed scope of work.
This Agreement may be extended to accomplish change orders, if required, upon mutual written
agreement of the City and the Contractor.
S. Contract Sum. The total amount of this Contract is the sum of$30,928.28 which includes Washington
State Sales Tax.
6. Retainage in Lieu of Bond. In lieu of a performance bond,the City will retain 50%of the contract
amount for a period of 45 days after Final Acceptance of the work.
7. Method of Payment. Payment by the City for the Services will only be made after the Services have
been performed and a voucher or invoice is submitted in a form acceptable to the City. Payment of
the initial 50%will be made in the next pay cycle of the Renton Finance Department after receipt of
such voucher or invoice (pay cycles are approximately bi-weekly). The remaining 50%will be paid 45
days after Final Acceptance. The City shall have the right to withhold payment to the Contractor for
any work not completed in a satisfactory manner until such time as the Contractor modifies such work
so that the same is satisfactory.
8. Employment.The Contractor's employees are not employees of the City of Renton.
9. Assignment and Subcontract. The Contractor shall not assign or subcontract any portion of this
Contract without express written consent of the City of Renton.
i
10. Record Keeping and Reporting. The Contractor shall maintain accounts and records which properly
reflect all direct and indirect costs expended and services provided`in the performance of this
Agreement. The Contractor agrees to provide access to any records required by the City.
11. Hold Harmless. The Contractor shall indemnify, defend and hold harmless the City, its officers,
agents, employees and volunteers,from and against any and all claims, including claims from third
parties, losses or liability, or any portion thereof, including attorneys fees and costs, arising from
injury or death to persons, including injuries, sickness, disease or death to Contractor's own
employees, or damage to property occasioned by a negligent act, omission or failure of the
Contractor.
12. Insurance. The Contractor shall maintain throughout the duration of this contract the following
insurance requirements: General Liability insurance in the amount of$1,000,000 per
occurrence/$2,000,000 aggregate; Professional Liability insurance in the amount of$1,000,000 per
claim; Automobile Liability in the amount of$1,000,000 per accident; and proof of Workers'
Compensation coverage. The City of Renton will be name as a Primary and Non-Contributory
Additional Insured on the insurance policy and an endorsement stating such shall be provided.
13. Compliance with Laws. The Contractor and all of the Contractor's employees shall perform the
services in accordance with all applicable federal, state, county and city laws, codes and ordinances.
14. Conflicts. In the event of any inconsistencies between contractor proposals and this contract, the City
of Renton contract shall prevail.
15. Prevailing Wage Rates. The Contractor must comply with the State prevailing wage requirements.
The Contractor must file an Intent To Pay Prevailing Wage at the beginning of the project and an
Affidavit of Wages Paid at the end of the project with the Washington State Department of Labor and
Industries, http://www.ini.wa.gov/TradesLicensing/PrevWage/default.asp
This Agreement is entered into as of the day and year written above.
CONTRACTOR CITY OF RENTON
Si ature Signature
Chuck Lindberg Terry Higashiyama, Community Services Administrator
Printed Name and Title Printed Name and Title
EDI, Enriched Designs, Inc.
Business Name
12920 SE 951h Way
Mailing Address
New Castle, WA 98056
City State Zip
206.459.1145, Fax 425.255.5467
Telephone
nY
CITY OF RENTON
ATTACHMENT A
Ron Regis Park
Storage Facility Restoration
1501 Orcas Avenue SE
Renton WA 98058
I
c �
CITY OF RENTON
SCOPE OF WORK
Ron Regis Park
Storage Facility Restoration
1501 Orcas Avenue SE
Renton WA 98058
The work involved under the terms of these Contract documents shall be full and complete
installation of the facilities, as shown on the plans and as described in the construction
specifications,to include but not be limited to:
Removal of all Fire Damages/Debris
Pressure Wash Interior and Exterior
Demo Existing Roof, Electrical for Interior Lighting and Exterior Soffit Lighting
Purchase and Install Framing and Truss Materials
Purchase and Install Roof and Gutters
Apply Felt Tex Underlayment
24 GA. 1700 Series Standing Seam: Old Town Gray
Eave Flashing, Hip and Ridge Flashing, Deck Tite Pipe Flashing
Soffits
Purchase and Install 6 inch Fascia Gutter, 2x3 Down Spouts
Purchase and Install Drywall: Interior Ceiling and Walls, Tape, and Finish
Prime and Paint: Drywall, Soffits, Fascia Board, all Doors, Exterior as needed
Purchase and Install Electrical: Permit, Demos as needed, 4 new Can Lights in Soffits, 2
new Exterior Wall Packs, 3 new Fluorescent Fixtures for Interior, Repair Damaged
Conduit, Replace Conduit and Mast for Photo Cell on Roof
Any contractor connected with this project shall comply with all Federal, State, County, and City
Codes and Regulations applicable to such work and perform the work in accordance with the
plans and specifications of this contract document. A total of sixty(60)working days will be
allowed for the completion of this project.
�* ELI PROPOSAL
***ENRICHED DESIGNS, INC.
Construction•Fixture Installation Date Estimate#
Tenant Improvements
1/16/2013 1870
Name/Address
Renton City Hall JOB#
1055 South Grady Way
Renton,WA 98055
Attn:Dennis Conte
Description Cost
Ron Regis Park - Fire Repairs
Architectural Plans for Permit 1,080.00
Demo existing roof structure complete
Clean up remaining fire debris left on site
Power wash interior and exterior complete 480.00
Demo electrical for interior lighting and exterior sofit lighting
Dump truck/dump fees 901.00
Framing and truss materials 2,520.00
Framing labor,sofits installed 3,216.00
Electrical 3,588.00
1. Supply electrical permit
2. Demo as needed for remodel
3. Install 4 new recessed can lights with glass lens in sofits
4.000Install two new surface mounted lights in recessed areas
5. Install three new strip fixtures inside building
6. Repair damaged conduit and wire caused by fire
7. Redo conduit and mast for photo cell on roof
Roof and Gutter 8,759.00
Apply felt tex underlay-mentexternal one inch over eave lines
Install 24 GA. 1700 Series standing seam roof
Install eave flashing along eave lines
Install hip and ridge flashing
Deck tite pipe flashing
Haul all debris away
Gutter-Install 6"fascia gutter with 2 x 3 down spouts
Attach gutter under roof eave flashing
Color Old Town Gray
Approval Signature III
Sales Tax (9.5%)
Total
12920 SE 95th Way • Newcastle, WA 98056 • (425) 25807 • Fax: (425) 271-1456 • edi-chuck @gwestoffice,net
�'O Ell PROPOSAL
OOOENRICHED DESIGNS, INC.
Construction•Fixture Installation Date Estimate#
Tenant Improvements
1/16/2013 1870
Name/Address
Renton City Hall JOB#
1055 South Grady Way
Renton,WA 98055
Attn:Dennis Conte
Description Cost
Drywall 2,942.00
Interior ceiling and walls,tape and finish exterior soffits complete
Painting 2,490.00
Prime and paint sofits and fascia boards
Repaint strip on exterior of back building
Prime and paint drywall on interior ceiling and walls
Paint exterior doors and interior door
Labor and Supervision 2,144.00
Material cart 125.00
Debris removal
Clean up
Plus WSST
Bid does not include permit fee
Approval Signature
Sales Tax (9.5%) $2,683.28
Total $30,928.28
12920 SE 95th Way • Newcastle, WA 98056 • (425) 256487 • Fax: (425) 271-1456 • edi-chuck @gwestoffice.net