HomeMy WebLinkAboutRES 2911 Km"'d E,:
�Fs a9�7
CITY OF RENTON, WASHINGTON
RESOLUTION NO. 2911
A RESOLUTION OF THE CITY OF RENTON, WASHINGTON, AMENDING
RESOLUTION NO. 2878 BY EXEMPTING CERTAIN APPLICATIONS
FROM THAT RESOLUTION.
WHEREAS, the City of Renton adopted Resolution No. 2878 which
established a single process for rezones and comprehensive plan
amendments until adoption of the new comprehensive plan; and
WHEREAS, certain projects were well advanced in the review
and permitting process such that the city had received materially
complete applications and the projects had undergone SEPA review;
and
WHEREAS, including those advanced projects within Resolution
No. 2878 would work a hardship on the projects; and
WHEREAS, it would be equitable to exempt those projects from
the projects to be handled under Resolution No. 2878 .
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF RENTON,
WASHINGTON, DO RESOLVE AS FOLLOWS :
SECTION I . The above recitals are found to be true and
correct in all respects .
SECTION II . Land use amendments or rezones for which
complete applications were received and substantial progress has
been made in processing the application, including SEPA review,
prior to the adoption of Resolution No. 2878 on January 27, 1992,
will not be part of the area-wide zoning process under that
Resolution but will proceed unaffected by that Resolution under
the normal city scheduling process . A list of the projects to be
1
RESOLUTION 297.1
exempted is attached hereto and incorporated by reference herein
as if fully set forth.
SECTION III . This resolution does not amount to a
commitment to zoning under the present Comprehensive Plan nor does
it create any vesting of rights to the applicants .
SECTION IV. Upon adoption of the new Comprehensive Plan,
any project that has been rezoned but does not have a materially
complete building permit application will be required to comply
with all existing development regulations as of the time of the
building permit application.
SECTION V. Upon adoption of the new Comprehensive Plan,
any proposed rezone that has had a public hearing but has not been
formally rezoned must become a contract rezone and may be required
to comply with the new regulations .
PASSED BY THE CITY COUNCIL this 6th day of JIlly , 1992 .
Marilyn. P tersen, City Clerk
APPROVED BY THE MAYOR thisay of July , 1992 •
7c,-�' �-A
L
Ea _ Cl'�ne , yor
Approves to form:
Lawrence J. War n, City Attorney
RES.206 :4/18/92 :as .
2
EXHIBIT B
Pipeline Projects To be Exempted
from Resolution 2878
May 4, 1992
1. Book Bales Rezone (110-91)
1726 Duvall
Rezone from G-1 to R-2 with Conditional Use
STATUS: Scheduled for Hearing Examiner on April 14, 1992.
2. Tall Firs Townhomes- (056-91)
4808 NE Sunset Blvd.
37 Townhomes
Rezone from G-1 to R-2
aring Examiner on April 14, 1992.
STATUS: Scheduled for. the He
3. The Orchards (138-90)
NE 8th and Duvall Ave. NE.
275 Multi-family units, 121 single family lots, 68 townhomes, 28,000 s.f. of
commercial/office
Contract rezone to R-3
STATUS: Scheduled for the Hearing Examiner on April 7, 1992 for Site Plan
approval.
4. dale Apartments (08
See #4 of 41�00 B� of Linco
modifications 198 units o - anvil
on committee Rezone -1 t
report. ST : Approved by caring Examiner; Council put on hold
( nditioned on Fire Benefit o ).
5. Malesis Rezone and Short Plat (050-90)
2202 Smithers Ave. So.
Single family residential
Rezone from G-1 to R-1
STATUS: Approved by Hearing Examiner; approval expires 9/18/92.
6. The Bluffs, east of L. Wash Blvd., west of 1-405
167 units multi-family
Rezone from R-1 to R-3
STATUS: EIS completed; project not expected to proceed.
7. Bakke, Inc. (107-88)
N.E. 4th and Union Ave. SE
111 multi-family units
Rezone from G-1 to R-3 and B-1
STATUS: Approval will expire in April; have requested two-year extension
from Hearing Examiner.
8. Forest Creste (093-88)
Duvall and SE 124th
200 multi-family units
Rezone from G-1 to R-3
STATUS: DEIS will be completed within month.
9. Dodi Thompson (045-88)
1222/1224 Kirkland Ave NE
Rezone from R-2 to R-3
STATUS: Hearing Examiner recommended approval with restrictive
covenants.
10. Sunset Gardens II/Crystal Heights (073-91)
Rezone
STATUS: (See attached letter from applicant).
Sound
�-
Planning
CDrpol"at'lon 10717 NE Fourth Street Bellevue,wa,sBooa Fax:206/646-9694 206/455-1822
April 13 , 1992
APR tj i
Manager
a
Mrs Kay Shoud y. na ge
Planning & Technical Services
Department of Planning, Building and Public Works
City of Renton
200 Mill Avenue South
Renton, Washington 98055
RE: CRYSTAL HEIGHTS/R-SA-073-91
EXEMPTION FROM RESOLUTION 2873
Dear Mrs . Shoudy:
Thank you for taking a moment on Wednesday, April 8th, to
discuss the impact of the implementation of Resolution 2878
on my client . I understand that you are requesting that the
City Council specifically exempt certain land use
applications that were in the planning process prior to
January 1 , 1992 .
My client , Cliff Mull , approached me back in June 1991 to
prepare the rezone application for a multiple family project
on the west side of Sunset Boulevard N. E. . His project
known as "Crystal Heights" was submitted in October and
assigned a file number of R-SA-073-91 . At our preliminary
review, Mr. Don Erickson, requested that because of the
geographic location, shape, size, topography, and history of
neighborhood development that we attempt to enlarge the
project to include the adjacent property owners . Over the
last 6 months we have been proceeding and have expended over
$35 , 000 . 00 in funds in following the request by staff .
My client ' s reflect specific site and building design
details that were required as part of the site plan
submission. Presently, he is expending another $4 , 000 . 00
for the conceptual storm water drainage plans .
Since our time schedule would call for construction and
occupancy by the summer of 1993 , we would request that we be
included your request for as an exemption to Resolution
2878 .
Sincerely,
ck
Roger J . B aylo
., - CITY OF RENTON
Planning/Building/Public Works Department
_ Lynn Guttmann, Administrator
Earl Clymer, Mayor
PLANNING DIVISION
CITY OF RENTON
.April 13, 1992 APR 1 3 1992
49ECEI ED
Roger Blaylock
10717 NE 4th Street, Suite 9
Bellevue, Washington 98004
Re: Your June 27, 1991 Application for Rezone and Site Plan Approval
Crystal Heights Apartment Project--File :R-SA-ECF-073-91
Dear Mr. Blaylock:
This letter is sent to formally advise you that
weneeds additional
inform
applia ionn in order to
further process the above-referenced Rezone/Site
In July of last year we requested additional information (i.e. storm drainage plan and report)
and recommended several revisions to the above-referenced application. When we returned
be retured
the package to you, you indicated se revisionos ns or thel additional inforvmtat hin on wee requested
To
date, we have not yet received the
Since it has been several months since your original application was submitted to us, we
will need to return your application fees (80%) and close out the file if we do not receive a
complete application package by May 13, 1992.
ly working on a Comprehensive Plan
your application
de
As you know, we are present
City Council has revised the rezone p'o ihro trough ths for re Plannings year's pacations. if nd Technical Services Division
is closed out, you will have to re-apply
(Long Range Planning) and await the final disposition of the Land Use Plan and associated
zone changes.
I have enclosed the current City of Renton "Rezone" and "Site Plan Approval Submittal
Requirements". Please review the instruction sheets and let me know if you have an of
Require order to expedite re
w require in questions about the additional information that e q
your r Rezone/Site Plan Approval application package. I can be reached at 235-2550.
Sincerely,
Laur /
_. een Nicola y
d
Associate Planner
enclosures
cc: Don Erickson
Kay Shoudy.
200 Mill Avenue South - Renton. Washingion 98055