Loading...
HomeMy WebLinkAbout03181 - Technical Information Report - Drainage ,� � ` � ' �� � � ' � Taylor ( Engineering � � Consultants � � m TARGETED DRAINAGE REVIEW REPORT for Morehouse 2-Lot Plat Tax Parcel No. 420440-0 9 84 LUA-04-057-SHPL Site Address: 323 Lind Avenue NW Renton, Washington �yp� M. rA j, � yp4 4 was 1 II . ' �' II O z � � ' �.� � G'ISTE4 ssj�N�Lti� ��,u`� t PIRES 1/4/� Prepared by: Lorna M. Taylor, P.E. TEC Project No. 317-B{QM Date: December 28, 2004 205 Front St.S. . P.O.Box 1787 . Issaquah,WA 98027-0073 . tel.(425)391-1415 . fax(425�391-1551 . www.teccivil.com 3 /�., � � Targeted Drainage Review Report - Morehouse 2-Lot Plat � I TABLE OF CONTENTS Section Description Page Number 1. Project Overview.......................................... 1 2. Conditions and Requirements Summary........... 1 3. Off-Site Analysis.......................................... 2 4. Flow Control and Water Quality Facility 3 Analysis and Design..................................... 5. Conveyance System Analysis and Design........ 3 6. Special Reports and Studies................. ......... 3 7. Other Permits.............................................. 3 8. ESC Analysis and Design...... ........................ 3 9. Bond Quantities, Facility Summaries, and 3 , Declaration of Covenant................................ 10. Operations and Maintenance Manual............... 3 Appendices Appendix: Figures 1. Technical Information Report (TIR) Worksheet 2. Site Location Map 3. Drainage Basins, Subbasins, & Site Characteristics and Off- site Analysis Map 4. Off-site Analysis Drainage System Table ' S. Site Information TEC • � , Targeted Drainage Review Report - Morehouse 2-Lot Plat � SECTION 1 PROJECT OVERVIEW This Targeted Drainage Review (TDR) Report is submitted to the City of Renton in accordance with the City-adopted King County Surface Water Design Manual (KCSWDM). This report is required of the project because it has the characteristics of TDR Category #1: it contains a sensitive slope area. The appendix contains a Technical Information Report (TIR) worksheet for the project (Figure 1), as well as a Site Location Map (Figure 2), a Drainage Basins, Subbasins, and Site Characteristics figure (Figure 3), an Off-site Analysis Drainage System Table (Figure 4), and a detailed Site Information figure (Figure 5). Site soils information is available in a site-specific Geotechnical Engineering Study produced for the project by Geotech Consultants, Inc., and dated April 8, 2004 More detailed site information is included on the site plan drawings. The 0.27 acre site is located at 323 Lind Avenue NW, in Renton, Washington. SECTION 2 CONDITIONS AND REQUIREMENTS SUMMARY The following summary describes how this new project will meet the eight "Core Requirements" and the "Special Requirements" that apply: Core Requirements 1. Discharge at the Natura/ Location: The site currently drains in a dispersed manner to the east to the Lind Avenue pavement drainage system. The project proposes to discharge runoff to this system. 2. Off-Site Ana/ysis: A Level 1 offsite analysis was conducted for this preliminary plat as described in Section 3. 3. Flow Control: Not Applicable. The project proposes to add less than 5,000 square feet of impervious surtaces so detention will not be required. To minimize the increase in runoff from the site, the project proposes to use perforated tightline connection BMP's. 4. Conveyance System: Not Applicable. The project is so small and the site is sloped so that minimum pipe sizes should be more than adequate to convey the 100-year storm runoff without flooding. 5. Erosion and Sedimentation Control: Runoff from the construction areas will be contained by a temporary construction entrance, silt fencing, and temporary catch basin protection in accordance with the KCSWDM during construction. The ESC facilities will only be removed once all exposed site surfaces have been stabilized. Other temporary erosion and sedimentation control measures will be installed as needed. 6. Maintenance and Operations: Not Applicable. 7. Financial Guarantees and Liability: Not Applicable. 8. Water Quality: Not Applicable. Treatment of runoff will not be required because only 2,889 square feet of new and replaced Pollution Generating Impervious Surfaces (PGIS) is proposed (including frontage improvements), which is less than the 5,000 square foot threshold for requiring treatment. 1 TEC � _ , Targeted Drainage Review Report �I Morehouse 2-Lot Plat Specia( Requirements 1. Ofher Adopfed Area-Specific Requirements: Not Applicable. 2. Floodplain/Floodway Delineation: Not Applicable. 3. Flood Protection Facilities: Not Applicable. 4. Source Contro/s: Not Applicable. 5. Oil Confro/: Not Applicable. SECTION 3 OFF-SITE ANALYSIS The following subsections describe the inspection and evaluation of the site and its surrounding areas particularly the downstream drainage path. Task 1. Study Area Definition and Maps Figure 3 in the appendix shows the extent of the study area and the local topography. The Site Plan drawing shows more detailed topographic information on the project site. Task 2. Resource Review The City's utility mapping was consulted. Task 3. Field Inspection A Level 1 off-site analysis was conducted on November 19, 2004. At the time of the site inspection, the weather was cool and sunny. Task 4. Drainage System Descriptions and Problem Descriptions There is minimal runoff onto the site from a narrow strip of land to the west. Runoff from the site flows in a dispersed manner to the east into the Lind Avenue pavement drainage system. Recent construction east of Lind Avenue forces all runoff from the site into the roadwa�r drainage system, which flows briefly south to a pipe system draining to the west in the NW 3` Street right-of-way. This runoff flows into a buried detention system in Maple Avenue NW, which discharges to the west and presumably connects to the Taylor Avenue drainage system. However, topography indicates that historically, the north portion of the site drained north to the NW 4'h Street drainage system, which flows down the hill to the east to the Taylor Avenue NW system which flows south. Either way, the runoff flows south along Taylor Avenue to Renton Avenue S, which is well beyond '/4 mile from the site. Figures 3 and 4 in the appendix describe the downstream drainage path for '/4 mile and more from the site. Task 5. Mitigation of Existing or Potential Problems To mitigate any water quantity impacts from the project, runoff will be conveyed to the downstream drainage system in "perForated tightline connections", in accordance with Appendix C of the King County Surface Water Design Manual (KCSWDM). Treatment of runoff will not be required because the development will not have more than 5,000 square feet of new and reptaced Pollution Generating Impervious Surfaces (PGIS). 2 TEC Targeted Drainage Review Report � Morehouse 2-Lot Plat SECTION 4 FLOW CONTROL AND WATER QUALITY FACILITY ANALYSIS AND DESIGN The project only proposes 2,556 square feet of new impervious surface, and a total of 2,889 square feet is pavement, as shown on Figure 5 in the appendix. Since these are below the 5,000 square foot thresholds for requiring formal flow control and treatment, drainage from the developed site will be addressed using Best Management Practices (BMP's). Runoff collected from the hard surfaces will be conveyed in "perForated tightline connections" to the downstream drainage system. SECTION 5 CONVEYANCE SYSTEM ANALYSIS AND DESIGN The project is so small that minimum pipe sizes should be more than adequate to convey the 100-year storm without flooding. SECTION 6 SPECIAL REPORTS AND STUDIES A Geotechnical Report was produced for this project by Geotech Consultants, Inc., and is avaitable under separate cover. SECTION 7 OTHER PERMITS Not Applicable. No other permits beyond those required by the City of Renton are anticipated to be required for this project. SECTION 8 ESC ANALYSIS AND DESIGN Erosion control for this project will include a stabilized construction entrance, silt fencing, and temporary catch basin protection in accordance with the KCSWDM. SECTION 9 BOND QUANTITIES, FACILITY SUMMARIES, AND DECLARATION OF COVENANT Not Applicable. SECTION 10 OPERATIONS AND MAINTENANCE MANUAL Not Applicable. 3 TEC I X 0 Z W � a a � � . . �►lz�, � .f �� � TECHNICAL INFORMATION REPORT (TIR) WORKSHEET ' Part 1 PR4J�CT OWNER AIdD Part 2 F'ROJECT LQCATl4ht AN� PROJECT EN�IN�ER 17E�CR1P1'EON Pr ect Owner . Project Name L�renc�av, �;n��l�ll.�,c✓� AQu�eh��. M.�re�w,,�s� Z- L�-� Address /t L � Location IIlZS - 320{ti► �4�e l� Lu✓✓�Ul�n Township 23 Phone Range 5 ProjectEngineer �-��-�-��-�-.Section NvU l� LA rv�rk !�/�. �a v �csv � Company �1� Ir�c . Address/Phone �'� }�� �ot�.��, Parf 3 TYPE QF PERIt11�T Par# 4 CITHER REtF1EWS At�D PERMITS APPLiCATION ` �__] Subdivison i- DFW HPA �� Shoreline Management � Short Subdivision ❑ COE 404 ❑ Rockery ❑ Grading ❑ DOE Dam Safety ❑ Structural Vaults ❑ Commercial ❑ FEMA Floodplain ❑ Other ❑ Other ❑ COE Wetlands Part� SITE COMMUNITY ANfl DRAINA�E BASIN Community +Ze�.}�-�-, Drainage Basin � 1 _ ��llae ��� Lake. u�a�Sh��v�Ton - -rt� _ ____ _ _ _ _ _ __ _ _ _ _ _ Part 6 SITE CHARACTERISTICS '� River ❑ Floodplain ❑ Wetlands ❑ Stream ❑ Seeps/Springs ❑ Critical Stream Reach ❑ High Groundwater Table ❑ DepressionslSwales ❑ Groundwater Recharge ❑ La ke ❑ Other � I Steep Slopes Figure 1 TIR Worksheet (3 pages) - _ __ _ _ _ _ _ __ _ ___ ___ ___. __ . ._ _ ___ __ ____ __ _ _ __ _. . . � Par�7 5CJ1LS Soil Type Slopes Erosion Potential Erosive Velcoties ��— a�eU�-`�Y�.�'L�l'c`.� (`2DbY� • ❑ Additional Sheets Attached Parf 8 >DEVELOPMENT L€MITATIOtdS REFERENCE LIMITATION/SITE CONSTRAINT �' Ch. 4—Downstream Analysis ❑ ❑ ❑ ❑ D ❑ Additional Sheets Attached Par€9 E8� F�EQLiIREhAENTS MINIMUM ESC REQUIREMENTS MINIMUM ESC REQUIREMENTS DURING CONSTRUCTION AFTER CONSTRUCTION ❑ Sedimentation Facilities � Stabilize Exposed Surface � Stabilized Construction Entrance `� Remove and Restore Temporary ESC Facilities �. Perimeter Runoff Control � Clean and Remove All Silt and Debris ❑ Clearing and Graing Restrictions ❑ Ensure Operation of Permanent Facilities `� Cover Practices ❑ Flag Limits of SAO and open space � Construction Sequence preservation areas ❑ Other ❑ Other - _ _ _ __. _ _..___ . ..._. _ _ _ . .. _ _ � Par# 't0 SUR�ACE Vk/ATER SY57EM ❑ Grass Lined ❑ Tank ❑ Infiltration Method of Analysis Channel , KC2T� ❑ Vault C Depression � Pipe System Compensation/Mitigati ❑ Energy Dissapator ❑ Flow Dispersal on of Eliminated Site ❑ Open Channel � wetland ❑ Waiver Storage ❑ Dry Pond ❑ Stream �� Regional ❑ Wet Pond Detention I Brief Description of System Operation S�U�M �rrlah � ('c3►� pC� tr[Ct�t� �_ ' ��,1�..,��(,�un ��ccm �ra.�h��� ,�vs�t�►-� Facility Related Site Limitations Reference Facility Limitation _ . _ _ _ _ _ _ __ _ _ _ _ _ __ __ _..._ ___ _ _ _ _ _ _ _ ___ __.. _ _ _ _ _ __ _ _ __ _ __ _ _ __..... ___ _ __ __ _ ___ _ _ _ __ _ ____.._ -:: __. _ _ _ _ _ _ _ _ _ __ _ __ _ _ ___ .... __ __ _ _ _ _ _ _ _ _.: _ . ___ _ _ P�r#-1'1 STRUCTURAL ANALYSIS Paet �� �ASEMENTS/TRACTS ❑ Cast in Place Vault ❑ Drainage Easement ❑ Retaining Wall ❑ Access Easement ❑ Rockery >4' High ❑ Native Growth Protection Easement � Structural on Steep Slope ❑ Tract � Other ❑ Other Part:13 SIGNATI}RE O� PRI��ES510NAL ENGtNEER I or a civil engineer under my supervision my supervision have visited the site. Actual site conditions as observed were incorporated into this worksheet and the attachments. To the best of my knowledge the information provided here is accurate. �� iz zd'�u� i ne ate MapQuest: Maps Page 1 of 1 . �.:� :��• � .� , � III1 Send To Printer Back to Map * � � 323 Lind Ave Nw � � � � I � Renton WA �" � 98055-1135 US � t, { �fi Notes: , t� `` ........ .......... ..... ..... ................ ..... ..... ................ ..... .... ,.,. , ::, ';, ,. ;:: ...... .. .r�.:��r _ ,, _ _ >> ............................................................................................ . ... `:'1: ':Ct'. '?�'; � ,�'.'�fd�$='�`I;��'��.:; . �.�.. .... s1:< ��. -���:_ ._ �. . � .~J � �� n �; � �` s� ��TTm��.�^:���� ;n ca '3;it f?3`..� �����F4 �€ � �, ,,� � � `� � �f+t`.7�i µ' � r � � .: �� m z, � ': » ?3��ih �t u � �,, . ;.,.: ,. � G. +. `a ?3 3'�; �a F:':��#:�'Z t. f� H. , •. � ; ' >, , _ . .�s. �,� � : "�w t,�`�4 � w � Ay C kt; , M � � �... .;`.���. ��.��'���.1����� � ._..� :: � . :. . . � �;• � ^ � M 'M <.$ <t#�'# m < �„ d„` r, u a'�,�4�#7�Si � F$�tt�i s? :�.. ha �� ' ��. �i�.v " " Y �� s'"h''s�.,e#i r:`,�zf3�z'i3 '��a� ....... � � "' . "� " ^ ,�, p� f f :� i 'St� � ,� S�i��.y+ v,, � : bg '�t �� Nxlftdn � ,, � �� #em�g�: � ; � {i�#;t�"'a3�' y� � �PS'v 4�5 a} � �1rE�d�i'! : � .. � 4�.... , '_ . ��r; a„ � � � h � ��� „3' ��* 1 ht�� ��«,� ���J��. ����£��5� �� �: � u`� p. �ta��; A� � ,r, M.c � � �'� �� 4�s. P(YY�tY%#�E '� €�}i�i` «� #;,Iti�,af . �` ��Yi6 r"xl a,_ �'�#'�u ..; ��� � - e - �S.r� :;��c�%':-{,�3T'!�i�i . .. . . . . . _ ... � . . . �...... . f .. _ . . : , �F' .. ._ �.,, . _ .'.: � ��'S�. ' . ;._ � €f3�iff'i�'tie,�y Y <� : ' �'rr � ` �'S1V•' . ...... . . ..1 � JT ; �;� _ � � � �,_ s �i ` I: : � � � -. ...... � ��� � x � �r � ��6.� ���� '-�'�,��a �� :". �€t�r��� � � � � f:3�`l`¢ �:y � :a�. °�.�r '�3 .� . '� � `� o � o . i^ � . � ... «� tzd �t � , �u �,,ar � ..: � : � . ' �...,� �,,• .� ��. � : �', n �&�. ��� a vf„�j�f� � ia a''�'tir���sfex3�. � ��1`F���' � �h ', �� z..�"� v�, ,> f tri 3�-: `E' �.:. „n.:... .....: r� ...�: `: a,�,. ty: i a.: � Fw .:- ...... _;L� �� � ' _ � . �Y �a��� �'. •t�'. , � ('i . .� . A . �f� . ��::��c� L�r, �� � �� ;�4�t,`��}•£ •R: :£" f.�'"'N d�'�'i: �'�' � ' �� �`x k�e� �rx�X�:�. ?�:?A#3A{y�st�te�.�u�st,#��.��i 2#A���3.�rf"'�€'.s :�t:�°��.,! All riqhts reserved. Use Subiect to LicenselCopvriqht � Map Leqend ;:��,yT�p; This map is informational only. No representation is made or warranty given as to its content. User assumes all risk of use. MapQuest and its suppliers assume no responsibility for any loss or delay resufting from such use. Privacy Policy & Leqal Notices pc 2004 MapQuest.com, Inc. All rights reserved. Figure 2 � Site Location Map htt //www.ma uest.com/ma s/ rint.ad �ma data= Sk o06 ZKZ� No Scale P� P9 P P P- P P qY Y Map Output Page 1 of 1 • � Kin� C�rtty ��� - - • - - , iMAP - Pro Information Plannin � } 'ti�� � ��1��' '� \. ,� � t t � � - � � �I)�� ``f{ti•y��+,� ���4� t-������\}4�\ s �y 7� � ''� I, y I � 7_"_'�; ��, j {�. 1 �. ��{'4 '����� ���� �' � � i ' '' � } � '� ` � � � � # 1 ,'� { �' ` � � � �� � � � � , � �,�,: : � � _ , � _ � �dTH ST�; ' '\� E t�-- - NW4TN_ST � '��������`�"�� ��k�� 11� � ��� `�� �� � - � � 4 ti� k '` � t � �� �.. i � �t ; \ �1 Y ���.� l 4 ��i�1!�--�� ` � � � { ' � G�OSTRE.�4�1 � ���,�'� �t � � � ; � ' ' ��f ^ � � �. � � ` V � ' � . � TRiduTA.�y A�r�J �.�t . , .;.�� � � � 7 y y, f ;� � tti` t, t� 'a ; � i '� . �:�\' �� ���, ti� �1, � i , ,, ,i ,�� j � �� �� 4 '� `'� '`� � }} 4 �, } , ��t, �� t i N��RD.E l t �� `Y\ { "'�•,1��� 'e , `� t'y��5' S'k 5' ? +}1 l �� i��T Z ��� . �ti� � � � � �'�� �, ? � �� �''�44� �i �, — ' �. ��,i � '�--� .`, 1t��4 �, t.: �.�t 1� i'� �' �,5 � �` � � � i� � � 4�J`-•1--iiSl� i�;�, � � � �� � �.� .�ti �� I ��� (£]. ' � Y � �.�-� 1j 5`� � � ` � � � �.1 f I . . � . b ��i'� `I ���� 5 l��'`��� y5y'..cY•��� '' � � � �.. �� i� .��� i� �it� _ 4k � r� � t�� � 'r i ,�., � /'��t�JELT-S! f , � ' ._ � �`1,i_�.._L �1 ��''� ,'q T� r�t�r�sRr�_sT � ��t"�t �; ' 1�� i �, �'j--S i I �- Cs �� � ( y. ��� �,��kS � i 1 � 1 � i i - (— [j r� /�r ��� j � ' �'`��114'= ��� ( I; 'ti�, �' t 'k � � c �� � � i� ;, � � /) � � ��t � �� t � v �.�� 1� _.'`-i! i � i �� � ti,y.f,'� }��x `, \ `\ �5 I5 l� .i , �i/ f�' ?� •.�. � � � � �, �� 4��� �,� ��, �`�?i � ��' � �' ,� a� � ti�.� � `.� � � � � `� ,� /�� - f �� ��. ti 'y � ��� � � �:�� � -- �� � � ��.,���;� ,�� � �, y �i 4 �� f / � � �� i� ` -- '_�1 7� ���__{_' ` ' ,� f i j(-� r �{I I ,;t1+ff ,,.j� 1 � � �� �J 3�� ' ���� '� r� � �I 7 � ` �' rf 3 � � 1 sr'� � . ��� ��/` " �NVii`2M�.PC ���� � � � l 'r J`` �f� � {, � ����� i I!I 11� 1 �j�r � � -� � f � �. � �� ;� f ___� - � / �-�` - --�'����� +1� ���� � � �' '�1 � ; � � �� //, -� �_���:,� /j f� � ; . J� : ---_.����/f�� ��i�t�'���. �a '� J'(f/JJ f/{f , f!/�, � 4 �jf ---�._ J{ �� .,����� �' r� �-}�/!�/J��f!� -#f.r � -'i�� - `� � 1 / � � � �� -t � ,� , _ � -_ �� �� � , �,.. - - ���.. _ �_���1 _�� .� � .-. �: --��_ � � . --�� . �___ _..S 132I11/� _ . 1 r . � /N/1 N D sT � ' . ��,- � // . � � 1 � , ��F�� �// f - � � � �'���c��� �, � �{� !7/ y � S �- � '��t� ; : , . � i�lzonK-�yc.e�y � J J 1 p . .�,.� ,., ��.� ; _: 0-�0 3mi��''�i��� informafan included on this map has been compiled by Kirtp County staff from a variety of sour s and is subjed to change without notice. ' g County makes ra represeMations or warranties,express or implied,as to aocuracy,completeness,timeliness,or rigFrts to the use of such formation.King Cou�ty shali not be liable for any gerteral,special,indired,incidental,or consequential damages including,but not limited to, st revenues or bst profits resufting from the use or misuse of the information contained on this map.My sale of this map or information on is ma is ohibited exce written rmissan of ' Coun . King Countv�GIS Center� News�Services�Commertts�Search By visiting this and other King County web pages,you expressly agree to be bound by terms and cond'Rions of the si6e.The details. Figure 3 Drainage Basins, Subbasins, Site Char. 8� Offsite Analysis Map (Scale as shown) http://www5.metrokc.gov/servlet/com.esri.esrimap.Esrimap?ServiceName=overview&Clie... 12l3/2004 � , , � FicuRE 4 � OFF-SITE ANALYSiS DRAINAGE SYSTEM TABLC SURFACE WATER DESIGN MANUAL, CORE REQUIREMENT#2 Basin: West Lake Washington—Seattle South Subbasin Name: Subbasin Number: __.__ - Symbol Drainage Drainage 51ope Distance Existing Potentiat Observations of#ield Component Type, Component from site Problems Problems inspector, resource Name, and Size Descri tion discharge reviewer, or resident sss map Type:sheet flow,swale, drainage basin,vegetation, �'o Y.ml=1,320 ft: constrictions, under capacity, ponding, tributary area, likelihood of problem, stream,channel, pipe, cover,depth,type of sensitive overtopping,flooding,habitat or organism overflow pathways, potentiai impacts pond; Size: diameter, area,volume destructfon,scouring, bank sloughing, surface area sedimentation incision,other erosion North Draina e Path � A-B Wedge curb gutter Upslope properties to 10 0' — 320' This appears to be the old flow west flow path for the northerly portion of the project site runoff— prior to construction of the new curb on the east side of Lind B-C Node B is a CB The first pipe is 6" dia. 10 320' — 850' Encountered three MH's inlet to pipe system and appears to bypass with "DRA1N" on lid on 4�'. flowing east. the nearest "DRAIN" Last one at the intersection Some site flow may MH, but presumably of Taylor and 4`t'. cross Lind to end connects to the storm up in the wedge pipe in 4`n curb ob the south side of 4�'. C-D Buried storm Picks up flow from the 3 850' — Encountered 4 CB's prior to drainage pipe northerly extension of 1,500' a pipe discharge to the west Taylor. side of Taylor in a roadside ditch. D-E Roadside ditch Conveys all of the 5 1,500' — Roadside ditch to an open west side of Taylor approx pipe end of a buried storm flows to the south. 2,300' drainage pipe system headed south, located approx. 400' north of Renton Ave. 98-4\inB04 . � _.._ _ _.-- -_ —----- __ _- —__ --- South Draina e Path ' A-F Sheet flow Cross slope of Lind 2 0' — 40' Flow picked up in new Ave gutter and flows to new CB at north end of opposite , ro'ect F-G 12" diam. pipe Pipe runs south, to end 2% net 40' — 250' The consistent design side of opposite project slope of Lind conveys the property. Picks up the runoff from the west side to upslope adjacent this system. ro ert to the west. G-H 12" diam. pipe Pipe runs east, down 35 250' —450' stee slo e to Ma le H-I 12" diam. pipe. Pipe runs north on 3 450' — 550' From the detention system, Maple to the opposite found "DRAIN" MH's with project detention locked lids. s stem I-J 12" diam. pipe. Pipe runs southeast 1 S50' — 650' As-built reference drawings from the detention show this buried pipe system to an angle system routed east along the point in the north on NW 3rd Street right-of-way, Maple to the opposite presumably to a connection project detention with the storm drainage system—determined system on Taylor on the from as-built record adjacent block. drawin s 9tS-4�inf3c)4 / • O ° O ° D � :_, , - - k- - - ' � = ; , , ' !. 4 � I � � ' .. - ;, , � � i + I � w ,;� a - � � � I - - - - _ � -•r 1T _. r_= :' _= . . , , ._. _.. , ;�. ;; ; ` ' ` . _; : °-,_- ' .. .. --. r, _. : N EXISTING SITE: PROPOSED SITE: PAV�MENT: 1,751 SF (0.04 AC) PAVEMENT: 1,765 S� (0.04 AC) BUILDING: 1,124 SF (0.03 AC) BUIIDiNG: 2,674 SF (0.08 AC) SIDEWALK: 354 SF (0.01 AC) SIDEWALK: 222 SF (0.01 AC) LANOSCAPE: 8,646 SF {0.20 AC) �ANDSCAPE: 7,214 SF (0.16 AC) TOTAL: 11,875 SF (0.27 AC) TOTAL: 11,875 SF (0.27 AC) PftOPOSED FRONTAGE: PAVEMENT: 1,124 SF (0.03 AC) I 15 � Figure 5 Site Information SCALE: 1" = so fc. 1" = 30'