Loading...
HomeMy WebLinkAboutCM_Construction_Mitigation_FFCC_v1 September 5, 2019 Family First Community Center PROPOSED CONSTRUCTION MITIGATION DESCRIPTION Proposed Construction Dates May 2020 – July 2021 Haul Routes A construction plan indicating haul routes and hours, construction hours, and a traffic control plan will be submitted to the Development Services Division for approval. Haul Hours Haul hours shall be restricted to the hours between eight-thirty (8:30) a.m. and three-thirty (3:30) p.m., Monday through Friday unless otherwise approved in advance by the Development Services Division. Permitted Work Hours in or Near Residential Areas Construction activities for the project shall be restricted to the following hours: b. Construction activities shall be restricted to the hours between seven o’clock (7:00) a.m. and eight o’clock (8:00) p.m., Monday through Friday. Work on Saturdays shall be restricted to the hours between nine o’clock (9:00) a.m. and eight o’clock (8:00) p.m. No work shall be permitted on Sundays. Emergency Extensions to Permitted Work Hours The Development Services Division Director is authorized to grant an extension of working time during an emergency. An emergency shall include but is not limited to natural and manmade disasters. Temporary Erosion Control Temporary erosion control must be installed and maintained for the duration of the project. This work will comply with the Surface Water Design Manual and must be approved by the Renton Development Services Division. (Ord. 5526, 2-1-2010) Hydroseeding Required: a. Within thirty (30) days of completion of grading work, the applicant shall hydroseed or plant an appropriate ground cover over any portion of the site that is graded or cleared of vegetation and where no further construction work will occur within ninety (90) days. b. Alternative measures to hydroseeding such as mulch, sodding, or plastic covering as specified in the Surface Water Design Manual may be proposed between the dates of October 1st and April 30th of each year. Plastic covering may be used for soil protection for soils that will be utilized as structural or fill materials only; provided, that soils that are to be reused for other purposes shall be covered for no more than fourteen (14) days. Family First Community Center September 5, 2019 Page 2 of 2 c. The Development Services Division’s approval of this work is required prior to final inspection and approval of the permit. (Ord. 5526, 2-1-2010; Ord. 5828, 12-12-2016) Construction Debris Construction debris, such as concrete, lumber, etc., will be removed and not buried on site. Preliminary Traffic Control Plan A traffic control plan will be submitted for review and approval by City of Renton after the General Contractor is selected.