Loading...
HomeMy WebLinkAboutAdden C - Bidder Question Memo No3_2019_0921 COMMUNITY SERVICES DEPARTMENT M E M O R A N D U M #3 DATE: September 20, 2019 TO: Bidders CC: Dean W. Koonts, HBB Landscape Architecture FROM: Alan J. Wyatt, Capital Projects Manager SUBJECT: SNP2—Bidder Questions & Responses 1. Bidder's Question: (Chris McGarvey, Northwest Playground Equipment, Inc.) • We are working with a vendor for the mist tubing that has it at 275' but if you scale drawing C-18 it appears to be less. Can you confirm the distance between the fountain and the equipment room? Response: (Chris Wiest, PND Engineers) • The Decorative Mist Feature is approximately 63 feet from the equipment room as measured from the edge of the proposed trench drain and the south east building corner. Response: (Alan J.Wyatt,City of Renton, Parks Planning and Natural Resources) • The contractor is responsible for the quantities of all components of the Work and to provide the necessary materials, labor and equipment to complete the Work in accordance with the Contract Documents. Quantities provided are only for the convenience of the Bidder. \\rv12rfpso5\depts\cs\parks plan ning\capital project coordinator\projects a-z\a-sunset neighborhood park\park design\phase ii\bidding\bidder questions\bidder question memo no3_2019_0921.docx