M E M O R A N D U M #3
DATE: September 20, 2019
TO: Bidders
CC: Dean W. Koonts, HBB Landscape Architecture
FROM: Alan J. Wyatt, Capital Projects Manager
SUBJECT: SNP2—Bidder Questions & Responses
1. Bidder's Question: (Chris McGarvey, Northwest Playground Equipment, Inc.)
• We are working with a vendor for the mist tubing that has it at 275' but if you
scale drawing C-18 it appears to be less. Can you confirm the distance between
the fountain and the equipment room?
Response: (Chris Wiest, PND Engineers)
• The Decorative Mist Feature is approximately 63 feet from the equipment room
as measured from the edge of the proposed trench drain and the south east
building corner.
Response: (Alan J.Wyatt,City of Renton, Parks Planning and Natural Resources)
• The contractor is responsible for the quantities of all components of the Work
and to provide the necessary materials, labor and equipment to complete the
Work in accordance with the Contract Documents. Quantities provided are only
for the convenience of the Bidder.