Recreation and CAG-18-069,Adden#3-19
Conservation Office Amendment to Project Agreement
Project Sponsor: City of Renton Project Number: 16-1772 C
Project Title: Sunset Neighborhood Park, Ph. II-L Amendment Number: 3
Amendment Type:
Time Extension
Amendment Description:
Pursuant to a request from City of Renton the Project Agreement identified above is amended
to extend the end date of this agreement.
The project period of 01/25/2018 to 09/30/2019 is extended to allow the contracting party
until 12/31/2019 to complete the project.
Agreement Terms
In all other respects the Agreement, to which this is an Amendment, and attachments thereto,
shall remain in full force and effect. In witness whereof the parties hereto have executed this
Amendment.
State Of Washington
Recreation and Conservation Office
BY:e/
aleen Cottingham
S
TITL : Director
DATE: 9"jo
Pre-approved as to form:
By: /S/
Assistant Attorney General
LWCF Project Time Extension Amendment
General Fund-Federal RCW 79A.25,WAC 286
TIMEXTEN.RPT
Amendment Special Conditions
Project Sponsor: City of Renton Project Number: 16-1772 C
Project Title: Sunset Neighborhood Park, Ph. II-L Amendment Number: 3
Special Conditions
None
ASPECCOND.RPT September 10, 2019 Page 1
Amendment Milestone Report
Project Number: 16-1772 C Amendment Number: 3
Project Name: Sunset Neighborhood Park, Ph. II-L
Sponsor: Renton City of
IAC Project Manager: DeAnn Beck
X ! Milestone Target Date Comments/Description
X ! Cultural Resources Complete 11/30/2010
X SEPA/NEPA Completed 04/01/2011
X I Purchase Agreement Signed 01/11/2016
X ! Acquisition Closing 03/31/2016 Via waiver of retroactivity#14-36 dated
10/14/2014 and#15-54 dated
12/29/2015.
X Survey Complete 06/02/2016
X Recorded Acq Documents to RCO 07/05/2016
X Demolition Complete 09/30/2016 Via waiver of retroactivity#15-54 dated
12/29/2015.
X Order Appraisal(s) 09/15/2017 Appraisal also completed on
10/21/2015.
X Project Start 01/25/2018
X ! Order Appraisal Review(s) 01/31/2018
X Design Initiated 04/10/2018
X ! Progress Report Due 07/11/2018
X ! Annual Project Billing Due 10/31/2018
X 60% Plans to RCO 12/07/2018
X ! Progress Report Due 12/31/2018
X Applied for Permits 01/22/2019
X All Bid Docs/Plans to RCO 05/20/2019
X I Progress Report Due 06/30/2019
X ! Annual Project Billing Due 07/31/2019
Bid Awarded/Contractor Hired 10/31/2019
i Construction Started 11/06/2019
I Agreement End Date 12/31/2019
50% Construction Complete 03/31/2020
90% Construction Complete 04/03/2020
Construction Complete 06/12/2020
RCO Final Inspection 07/17/2020
Funding Acknowl Sign Posted 07/17/2020
AMILESTO.RPT September 10, 2019 Page: 1
Amendment Milestone Report
Final Billing Due 11/13/2020 Submit prior to final report.
Final Report Due 11/30/2020 Submit after final billing.
X=Milestone Complete
I =Critical Milestone
AMILESTO.RPT September 10, 2019 Page: 2