Loading...
HomeMy WebLinkAboutMemo_Energize Eastside_and_Exhibits_191121 ENVIRONMENTAL REVIEW COMMITTEE MEMO APPLICATION NUMBER: LUA18-000055, CUP-H, SME APPLICANT: Brad Strauch, PSE PROJECT NAME: Energize Eastside DESCRIPTION OF PROPOSAL: The applicant is requesting Hearing Examiner Conditional Use Permit approval and a Shoreline Exemption for the upgrade of 4 miles of two existing 115 kV transmission lines with two 230 kV transmission lines beginning at the City’s northern boundary with Newcastle and ending at the existing Talbot Hill substation. The upgrade is located entirely within PSE’s existing 100-ft electrical transmission utility corridor. The project site is located within multiple zoning designations, including: Commercial Arterial (CA), Commercial Office Residential (COR), Center Village (CV), Light Industrial (IL), Residential-1 (R-1), Residential-10 (R-10), Residential-14 (R- 14), Residential-4 (R-4), Residential-6 (R-6), Residential-8 (R-8), Resource Conservation (RC), and Residential Multi-Family (RM-F). The proposed upgrade would require the replacement of approximately 144 existing wood and steel poles (H-frame designs) with approximately 41 steel monopoles of either single-circuit or double-circuit design. The height of the proposed poles would vary by location, but are estimated at an average height of between 85 and 95 feet. Within the Talbot Hill substation, additional breakers and associated controls will be added to accommodate the new lines. The Project’s southern extent is PSE’s Talbot Hill substation located at 2400 S. Puget Drive. From the substation, the Project continues north along the existing PSE transmission line corridor to the northern city limits, between I-405 and the eastern city limits. Multiple critical areas are mapped along the project corridor including wetlands, streams, steep slopes, landslide hazards, coal mine hazards, and wellhead protection areas. The project would include the replacement of aerial wire across the Cedar River, which is classified as a Shoreline of the State. The project proposes the replacement of poles outside of the 200-foot shoreline jurisdiction and the aerial wire crossing would not require any disturbances within the shoreline jurisdiction. To date, three environmental review documents under the State Environmental Policy Act (SEPA) have been prepared for the Energize Eastside Project , all of which can be found online at www.energizeeastsideeis.org:  Energize Eastside Phase I Draft Environmental Impact Statement (January 2016);  Energize Eastside Phase II Draft Environmental Impact Statement (May 2017);  Energize Eastside Final Environmental Impact Statement (March 2018). In order to ensure that the submitted Conditional Use Permit application materials are consistent with the existing environmental documents prepared for the Energize Eastside project, the City contracted with EA Engineering, Science, and Technology, Inc., PBC to prepare an Environmental Consistency Analysis. The following elements of the environment have been addressed in the Environmental Consistency Analysis: Earth, Water Resources, Plants & Animals, Greenhouse Gases, Environmental Health: EMF, Environmental Health: Pipeline Safety, Land Use & Housing, Scenic Views & Aesthetics, Historic & Cultural Resources, Recreation, and Economics. The Environmental City of Renton Department of Community & Economic Development Environmental Review Committee Memo Energize Eastside LUA18-000055, CU-H, SME November 25, 2019 Page 2 of 2 Consistency Analysis determined that the impacts of development under the proposed Conditional Use Permit application materials are within the impacts analyzed under the EIS altern atives in the past SEPA review. No new mitigation measures are required beyond those identified in the 2018 FEIS, and there are no significant unavoidable impacts that cannot be mitigated. Exhibits Exhibit 1: ERC Memo Exhibit 2: Environmental Consistency Analysis, November 2019 ENVIRONMENTAL CONSISTENCY ANALYSIS Energize Eastside Project Renton, Washington November 21, 2019 Prepared by: EA Engineering, Science, and Technology, Inc., PBC Landau Associates Grette Associates Cultural Resource Consultants ECONorthwest Prepared for: City of Renton Department of Community and Economic Development Energize Eastside Project i Table of Contents Environmental Consistency Analysis ENERGIZE EASTSIDE ENVIRONMENTAL CONSISTENCY ANALYSIS TABLE OF CONTENTS TABLE OF CONTENTS ..................................................................................................................... i EXECUTIVE SUMMARY ............................................................................................................. E-1 CHAPTER 1 COMPARISON OF PROJECT FEATURES UNDER THE PHASE 2 DEIS, FEIS, & CURRENT PROPOSALS ................................................................................................. 1-1 CHAPTER 2 COMPARISON OF IMPACTS UNDER THE PHASE 2 DEIS, FEIS, & CURRENT PROPOSALS .................................................................................................................. 2-1 CHAPTER 3 MITIGATION MEASURES .............................................................................................. 3-1 APPENDICES Appendix A – Current Proposal Site Plan LIST OF FIGURES Figure Page 1-1 Regional Map ..................................................................................................................... 1-2 1-2 Entire Energize Eastside Project ........................................................................................ 1-3 1-3 Renton Segment of Energize Eastside Project ................................................................... 1-4 LIST OF TABLES Table Page 1-1 Comparison of Project Features – Phase 2 DEIS, FEIS, & Current Proposal ....................... 1-8 2-1 Comparison of Impacts – Phase 2 DEIS, FEIS, & Current Proposal ..................................... 2-2 Energize Eastside Project E-1 Environmental Consistency Analysis EXECUTIVE SUMMARY The Energize Eastside Project Environmental Consistency Analysis confirms that the Current Proposal is within the range of development and probable environmental impacts analyzed in the past SEPA environmental review for the Renton segment of the project, and that there are no significant unavoidable adverse impacts that cannot be mitigated. Minor additions/clarifications to the mitigation measures identified in the 2018 FEIS and in the CUP and Shoreline Exemption application materials are recommended based on the Environmental Consistency Analysis. Below is further discussion of the analysis. The Applicant, Puget Sound Energy, Inc. (PSE) is proposing to upgrade approximately four miles of two existing 115 kV transmission lines with two new 230 kV transmission lines in the city of Renton. The Renton PSE upgrade is part of the larger Energize Eastside Project that would also occur in the cities of Bellevue, Redmond, and Newcastle, and in unincorporated King County. The proposed project would require the replacement of approximately 144 existing wood and steel poles (H- frame design) with approximately 41 steel monopoles of either single-circuit or double-circuit design. Within the Talbot Hill substation, additional breakers and associated controls would be added to accommodate the new line. The upgrade would be entirely within the existing 100-foot wide transmission line corridor. To date, three environmental review documents under the State Environmental Policy Act (SEPA) have been published by the Partner Cities (the Cities of Bellevue, Kirkland, Newcastle, Redmond, and Renton) on the Energize Eastside Project: •Energize Eastside Project Phase 1 Draft EIS (January 28, 2016), •Energize Eastside Project Phase 2 Draft EIS (May 6, 2017), and •Energize Eastside Project Final EIS (March 1, 2018). The following permits will be required from the City of Renton for the proposed PSE electrical utility upgrade: •Zoning Conditional Use Permit (CUP), •Shoreline Exemption, •Utility Construction Permit, and •Building Permits. On March 14, 2018, PSE submitted complete CUP and Shoreline Exemption applications to the City of Renton (the “Current Proposal”). The following report contains an Environmental Consistency Analysis of the Current Proposal. Energize Eastside Project E-2 Environmental Consistency Analysis Goal of this Analysis The goal of the Energize Eastside Project Consistency Analysis is to confirm that proposed development and associated environmental impacts under the Current Proposal are within the range of development and environmental impacts analyzed in the past SEPA review for the project, particularly the Phase 2 DEIS and FEIS, which contained project-specific analysis of the proposed utility upgrade. A further goal of the Consistency Analysis is to recommend additional mitigation measures for the Current Proposal, as necessary. Development Types, Levels, and Features Chapter 1 of this Environmental Consistency Analysis compares the types, levels, and features of development under the Current Proposal to those under the proposals in the Phase 2 DEIS and FEIS. The proposed type of use (electrical utility) under the Current Proposal would be identical to the type of use assumed in the Phase 2 DEIS and FEIS for the Renton segment of the Energize Eastside Project. The level of development under the Current Proposal would be similar to or less than the levels of development assumed under the proposals in the past SEPA review. The Current Proposal would upgrade approximately four miles of two existing 115 kV transmission lines with two new 230 kV transmission lines, requiring the replacement of approximately 144 existing wood and steel poles (H-frame design) with approximately 41 steel monopoles of either single-circuit or double-circuit design. Within the Talbot Hill substation, additional breakers and associated controls would be added to accommodate the new lines. The upgrade would be entirely within the existing 100-foot wide transmission line corridor. Key similarities between the Current Proposal and the Phase 2 DEIS and FEIS proposals include: •The upgrade would follow the same general route and would be entirely located within PSE’s existing 100-foot wide corridor; •Proposed pole replacement would generally be in the same locations as the existing pole locations; •There would be fewer replacement poles than existing poles; •Replacement poles would be taller and larger in diameter than existing poles; and, •Proposed pole replacement would be outside the 200-foot Cedar River shoreline jurisdiction. Key differences between the Current Proposal and the Phase 2 DEIS and FEIS proposals include: •Fewer poles would be removed under the Current Proposal than in the Phase 2 DEIS, but the same number as in the FEIS; •Fewer poles would be replaced under the Current Proposal than in the Phase 2 DEIS, but the same number as in the FEIS; •The lowest wires in the shoreline jurisdiction would be 20 to 30 feet higher than the existing wires, and, •Additional information on construction and pole design is available in the applications. Energize Eastside Project E-3 Environmental Consistency Analysis Therefore, the Current Proposal would be within the range, or would represent less intensive development than, analyzed in the past EISs for the project. Environmental Impacts Chapter 2 of this Environmental Consistency Analysis compares the probable significant environmental impacts under the Current Proposal to the those under the proposals analyzed in the Phase 2 DEIS and FEIS. The following elements of the environment are addressed in this Consistency Analysis: Earth, Water Resources, Plants and Animals, Greenhouse Gases, Environmental Health: Electromagnetic Fields, Environmental Health: Pipeline Safety, Land Use and Housing, Scenic Views and Aesthetics, Historic and Cultural Resources, Recreation, and Economics. The Environmental Consistency Analysis confirms that the impacts of development under the Current Proposal are within the range of impacts analyzed under the proposals in the past SEPA review, and that there are no significant unavoidable adverse impacts that cannot be mitigated. This is because the Current Proposal is identical in most respects to the FEIS proposal. The differences between the proposals primarily relate to pole placement, tree removal, and details on mitigation provided under the Current Proposal. The impacts under the Current Proposal would generally be similar to or less than those described in the Ph. 2 DEIS and FEIS. Mitigation Measures Chapter 3 of this Environmental Consistency Analysis lists the mitigation measures from the FEIS; highlights additional measures from the CUP and Shoreline Exemption application materials; and, notes any further measures recommended through this Environmental Consistency analysis. The measures specified by code are listed as “Regulatory Requirements” and would be required. “Potential Mitigation Measures” are also listed based on comprehensive plan policies and existing PSE programs, and would be at the discretion of the applicant to adopt or the City of Renton to impose as a condition of project approval. Minor additions/clarifications to the mitigation measures identified in the FEIS and application materials are recommended based on the Environmental Consistency Analysis. Conclusion The Environmental Consistency Analysis confirms that the Current Proposal is within the range of development and probable environmental impacts analyzed in the past SEPA environmental review of the Renton segment of the project, and that there are no significant unavoidable adverse impacts that cannot be mitigated. Minor additions/clarifications to the mitigation measures identified in the 2018 FEIS and in the CUP and Shoreline Exemption application materials are recommended based on the Environmental Consistency Analysis. Chapter I PROJECT FEATURES UNDER THE PHASE 2 DEIS, FEIS, & CURRENT PROPOSALS Energize Eastside Project 1-1 Project Features Environmental Consistency Analysis CHAPTER 1 PROJECT FEATURES UNDER THE PHASE 2 DEIS, FEIS & CURRENT PROPOSALS 1.1 INTRODUCTION The Applicant, Puget Sound Energy, Inc. (PSE) is proposing to upgrade approximately four miles of two existing 115 kV transmission lines with two new 230 kV transmission lines in the city of Renton. The Renton PSE upgrade is part of the larger Energize Eastside Project that would also occur in the cities of Bellevue, Redmond, and Newcastle, and in unincorporated King County (see Figure 1-1, Regional Map, and Figure 1-2, Entire Energize Eastside Project). The Renton segment would extend from the city’s boundary with Newcastle to the north to PSE’s Talbot Hill Substation to the south (see Figure 1-3, Renton Segment of Energize Eastside Project). The proposed project would require the replacement of approximately 144 existing wood and steel poles (H-frame design) with approximately 41 steel monopoles of either single-circuit or double-circuit design. Within the Talbot Hill substation, additional breakers and associated controls would be added to accommodate the new line. The upgrade would be entirely within the existing 100-foot wide transmission line corridor. The existing PSE Eastside transmission lines were installed in the 1960s. Electricity demands in the region have increased over the last 60 years. Based on federally-mandated planning studies, PSE has determined that upgraded transmission lines and a new substation are needed to address deficiencies in electrical transmission capacity in peak periods. These deficiencies are expected because of existing population and employment, and anticipated population/employment growth on the Eastside. During the environmental review process for the project, several commenters questioned the need for the upgrades. Five separate studies performed by four separate parties confirmed the need to address Eastside transmission capacity. Combined with aggressive conservation, the Energize Eastside Project is intended to significantly improve reliability for Eastside communities, including the City of Renton, and would supply the additional electrical capacity needed for current and anticipated growth. The proposed upgrade is located within multiple City of Renton zoning designations, including: Commercial Arterial (CA), Commercial Office Residential (COR), Center Village (CV), Light Industrial (IL), Residential-1 (R-1), Residential-4 (R-4), Residential-6 (R-6), Residential-8 (R-8), Residential-10 (R-10), Residential-14 (R-14), Resource Conservation (RC), and Residential Multi-Family (RM-F). Multiple critical areas are mapped along the project corridor, including: wetlands, streams, steep slopes, landslide hazards, coal mine hazards, seismic, and wellhead protection areas. The Cedar River, a Shoreline of the State, flows across the corridor. The existing transmission lines are co - located with Olympic Pipeline petroleum pipelines for about 0.2 mile at the north end of the corridor, as well as 0.6 mile at the south end of the corridor near the Talbot Hill substation. Energize Eastside Project 1-2 Project Features Environmental Consistency Analysis Energize Eastside Project 1-3 Project Features Environmental Consistency Analysis Energize Eastside Project 1-4 Project Features Environmental Consistency Analysis Energize Eastside Project 1-5 Project Features Environmental Consistency Analysis 1.2 EIS PROCESS & PERMIT APPLICATIONS The City of Bellevue and four partner Eastside Cities (Kirkland, Newcastle, Redmond, and Renton) through which the upgraded transmission lines would pass, together with PSE, concluded that the Energize Eastside Project is likely to have significant adverse environmental impacts on the environment. The Partner Cities jointly conducted environmental review for the project under the State Environmental Policy Act (SEPA). Pursuant to SEPA, a Threshold Determination of Significance was issued on the project on April 30, 2015, in compliance with WAC 197-11-360. Environmental Impact Statements (EISs) were prepared to address the potential for significant environmental impacts from the project. The City of Bellevue assumed the role of lead agency on the EIS, consistent with WAC 197-11-944. Phased environmental review, consistent with WAC 197-11-060 (5) (c), was conducted. Three documents were published, and are described in greater detail below: • Energize Eastside Project Phase 1 Draft EIS (January 28, 2016); • Energize Eastside Project Phase 2 Draft EIS (May 6, 2017); and, • Energize Eastside Project Final EIS (March 1, 2018). These documents are available for review at Renton City Hall and via download on the City of Renton website – www.rentonwa.gov. Public/agency commenting was invited at each of the EIS scoping stages and for each of the Draft EISs. Phase 1 DEIS The Energize Eastside Project Phase 1 Draft EIS (DEIS) was a programmatic-level evaluation of the potential impacts on the environment of four alternatives, including: • No Action Alternative; • Alternative 1 - New Substation and 230 kV Transmission Line (four options for this alternative were analyzed); • Alternative 2 - Integrated Resource Approach; and, • Alternative 3 - New 115 kV Lines and Transformers. Impacts on the following environmental elements were analyzed in the Phase 1 DEIS: Earth, Greenhouse Gas (GHG) Emissions, Environmental Health, Plants and Animals, Noise, Land Use and Housing, Views and Visual Resources, Historic and Cultural Resources, Transportation, Recreation, Energy and Natural Resources, and Utilities. Phase 2 DEIS The analysis of alternatives in the Energize Eastside Project Phase 1 DEIS resulted in a narrowing of reasonable alternatives to an overhead transmission line solution. The Phase 2 DEIS contained a project-level review of an overhead transmission line route action alternative and the No Action Alternative: • No Action Alternative; and, • Alternative 1 - New Substation and 230 kV Transmission Lines. Energize Eastside Project 1-6 Project Features Environmental Consistency Analysis Alternative 1 in the Phase 2 DEIS included three route options in the Bellevue Central Segment and four route options in the Bellevue South Segment. Only one route opt ion was provided for the Redmond, Newcastle, and Renton segments. The Phase 2 DEIS evaluated the impacts of these alternatives on the following environmental elements: Water Resources, Plants and Animals, GHG Emissions, Environmental Health : Pipeline Safety, Environmental Health: Electromagnetic Fields (EMFs), Land Use and Housing, Scenic Views and Aesthetics, Historic and Cultural Resources, Recreation, and Economics. The following elements of the environment evaluated in the Phase 1 DEIS would not be significantly impacted by the project, and were, therefore, not analyzed in the Phase 2 DEIS: Earth Resources, Public Services, Utilities, Transportation, and Energy and Natural Resources. FEIS The Energize Eastside Project FEIS provided additional project-level evaluation of the impacts of two alternatives: • No Action Alternative; and, • PSE’s Proposed Alignment: New Substation and 230 kV Transmission Lines. The analysis in the FEIS was based on the most recent design details provided by PSE at the time the FEIS was being prepared. In several areas, the design had been refined since publication of the Phase 2 DEIS. For example, new information on pole types and locations was provided thro ughout the corridor, and more detailed information was provided in some areas where the design was more advanced. The FEIS evaluated the impacts of these alternatives on the same elements of the environment studied in the Phase 2 DEIS (Water Resources, Plants and Animals, GHG Emissions, Environmental Health: Pipeline Safety, Environmental Health: Electromagnetic Fields, Land Use and Housing, Scenic Views and Aesthetics, Historic and Cultural Resources, Recreation, and Economics). In response to comments on the Phase 2 DEIS, additional information was provided in the FEIS on Earth Resources related to seismic risks. The FEIS included responses to public and agency comments on both the Phase 1 and Phase 2 DEIS, and will be used by the Partner Cities to support any permit decisions that are required. Permit Applications On March 14, 2018, PSE submitted a complete application to the City of Renton (the “Current Proposal”) for a zoning Conditional Use Permit (CUP) and a Shoreline Exemption. The project will also require utility construction and building permits from the City. If approvals are granted, construction of the Renton segment of the Energize Eastside Project may begin as early as Summer 2019. It is expected that construction would take between six to nine months Energize Eastside Project 1-7 Project Features Environmental Consistency Analysis Environmental Consistency Analysis This Environmental Consistency Analysis has been prepared to confirm that the utility improvements and associated environmental impacts under the Current Proposal represented in the CUP and Shoreline Exemption applications submitted to City of Renton are within the range of alternatives and impacts analyzed in the Phase 2 DEIS and FEIS. The Consistency Analysis also lists the mitigation measures from the FEIS, and any additional measures under the Current Proposal, and recommends further measures to address impacts, as necessary. EA Engineering Science, and Technology, Inc., PBC (EA) and their sub-consultants prepared this analysis. Below is a list of the EA team and the elements of the environment for which they were responsible: • EA – Overall Consistency Analysis author, Water Resources, Environmental Health: EMF, Environmental Health: Pipeline Safety, Land Use, Aesthetics, Recreation • Landau Associates – Earth, Air Quality • Grette Associates – Plants and Animals • Cultural Resource Consultants – Historic and Cultural Resources • ECONorthwest – Economics 1.3 COMPARISON OF PROJECT FEATURES The Energize Eastside Project Environmental Consistency Analysis shows that the Current Proposal would be within the range, or would represent less intensive development, than analyzed in the past EISs for the project, as described below. The following section of the Environmental Consistency Analysis describes the type and extent of utility construction and other features under the Phase 2 DEIS, FEIS, and Current proposals. The site plan for the Current Proposal is contained in Appendix A. Table 1-1 summarizes the project features of the previous proposals and compares them to the Current Proposal. Text that is highlighted in red under the Current Proposal represents additions or changes from the 2018 FEIS Proposal. The last column in Table 1-1 summarizes if there are changes between the Current Proposal and the FEIS Proposal. Energize Eastside Project 1-8 Project Features Environmental Consistency Analysis Table 1-1 COMPARISON OF PROJECT FEATURES - PHASE 2 DEIS, FEIS, & CURRENT PROPOSAL Description of Features May 2017 Ph. 2 DEIS Proposal Mar. 2018 FEIS Proposal Current Proposal Change from FEIS Proposal 1. Start/End • Newcastle-Renton Boundary/Talbot Hill Substation • Newcastle-Renton Boundary/Talbot Hill Substation (same as Ph. 2 DEIS) • Newcastle-Renton Boundary/Talbot Hill Substation (same as Ph. 2 DEIS & FEIS) No 2. Jurisdiction • Renton and a small portion of unincorporated King County • Renton • Renton (same as FEIS) No 3. Length of Renton Segment • 4.5 miles • 4 miles • 4 miles (same as FEIS) No 4. Number of Transmission Line Circuits • 2 circuits • 2 circuits (same as Ph. 2 DEIS) • 2 circuits (same as Ph. 2 DEIS & FEIS) No 5. Voltage of Circuit Lines • 230 kV and high capacity 115kV • 230 kV • 230 kV (same as FEIS) No 6. Easement/Property Acquisition • Entirely within PSE’s existing 100-ft. kV corridor; no easements or property acquisitions necessary • Entirely within PSE’s existing 100-ft. kV corridor; no easements or property acquisitions necessary (same Ph. 2 DEIS) • Entirely within PSE’s existing 100-ft. kV corridor; no easements or property acquisitions necessary (same as Ph. 2 DEIS & FEIS) No 7. Shoreline Jurisdiction • Upgrades would be outside 200- ft. Cedar River shoreline jurisdiction • The height of the new wires in the shoreline jurisdiction would not change. • Upgrades would be outside 200- ft. Cedar River shoreline jurisdiction (same as Ph. 2 DEIS) • The height of the new wires in the shoreline jurisdiction would not change (same as Ph. 2 DEIS) • Upgrades would be outside 200- ft. Cedar River shoreline jurisdiction (same as Ph. 2 DEIS & FEIS) • The lowest wires in the shoreline jurisdiction would be 20-30 feet higher than the existing wires. Yes 8. Olympic Pipeline • Co-located in existing corridor for 0.2 mile. Pipelines leave corridor where it crosses SCL line near Honey Creek Open Space. Pipelines buried on one side (east or west) of corridor • Co-located in northern portion of existing corridor; pipelines buried in the center of corridor. • Co-located in northern portion of existing corridor; pipelines buried in the center of corridor (same as FEIS) No Energize Eastside Project 1-9 Project Features Environmental Consistency Analysis Description of Features May 2017 Ph. 2 DEIS Proposal Mar. 2018 FEIS Proposal Current Proposal Change from FEIS Proposal • Poles would be placed in the center of the corridor south of Honey Creek Open Space • Poles would be placed with one on either side of the pipelines. • Poles would be placed with one on either side of the pipelines (same as FEIS) 9. Single-Circuit Steel Pairs • Location • Pole Replacement • Typical Height • Maximum Height • Clearing for Vegetation over 15’ in Height • SCL Crossing May Require Wires and Structures to be Raised, and Lattice Towers Replaced with Monopoles • Existing corridor north of Honey Creek Open Space • Approx. 12 existing wooden H - frames replaced with approx. 6 pairs of single-circuit 230 kV/115kV steel monopoles • 85’ (existing 55’) • 125’ (existing 93’) • 16’ from outside transmission wire • Yes • Existing corridor north of Honey Creek Open Space (same as Ph. 2 DEIS) • Approx. 22 existing wooden H- frames replaced w/ approx. 11 pairs of single-circuit 230kV steel monopoles • 50-84’ • 50-94’ • 16’ from outside transmission wire (Same as in Ph. 2 DEIS) • Yes (Same as in Ph. 2 DEIS) • Existing corridor north of Honey Creek Open Space (same as Ph. 2 DEIS & FEIS) • Approx. 22 existing wooden H- frames replaced w/ approx. 11 pairs of single-circuit 230kV steel monopoles (same as FEIS) • 50-84’ (same as FEIS) • 50-94’ (same as FEIS) • 16’ from outside transmission wire (same as Ph. 2 DEIS & FEIS) • Yes (same as in Ph. 2 DEIS & FEIS) No 10. Double-Circuit Steel Monopoles • Location • Pole Replacement • Typical Height • Maximum Height • Clearing for Vegetation over 15’ in Height • Existing corridor south of Honey Creek Open Space. • Approx. 69 wooden H-frames replaced with approx. 46 double-circuit 230kV/115 kV steel monopoles. • 90’ (existing: 55’) • 125’ (existing: 93’) • 16’ from outside transmission wire • Existing corridor south of Honey Creek Open Space (Same as Ph. 2 DEIS) • Approx. 48 wooden H-frames replaced w/ approx. 27 double- circuit 230 kV steel monopoles. • 94’ • 118’ • 16’ from outside transmission wire (Same as Ph. 2 DEIS) • Existing corridor south of Honey Creek Open Space (same as Ph. 2 DEIS & FEIS) • Approx. 48 wooden H-frames replaced w/ approx. 27 double- circuit 230 kV steel monopoles (same as FEIS). • 94’ (same as FEIS) • 118’ (same as FEIS) • 16’ from outside transmission wire (same as Ph. 2 DEIS & FEIS) No Energize Eastside Project 1-10 Project Features Environmental Consistency Analysis Description of Features May 2017 Ph. 2 DEIS Proposal Mar. 2018 FEIS Proposal Current Proposal Change from FEIS Proposal • Number of Poles Required at Talbot Hill Substation for Dead-End Structures • SCL Crossing May Require Wires and Structures to be Raised, and Lattice Towers Replaced with Monopoles. • 2 poles • Yes • 2 (Same as Ph. 2 DEIS) • Yes (Same as Ph. 2 DEIS) • 2 (same as Ph. 2 DEIS & FEIS) • Yes (same as Ph. 2 DEIS & FEIS) Source: 2017 Ph. 2 DEIS, 2018 FEIS, and PSE, 2019. SCL = Seattle City Light Energize Eastside Project 1-11 Project Features Environmental Consistency Analysis 1.4 CONCLUSION In conclusion, the type of use (electrical utility upgrade) under the Current Proposal would be identical to the type of use assumed in the Phase 2 DEIS and FEIS for the Renton segment of the Energize Eastside Project. The level of development under the Current Proposal would be similar to or less than the levels of development assumed under the proposals in the past SEPA review, and would be almost identical to the FEIS Proposal. The Current Proposal would upgrade approximately 4 miles of two existing 115 kV transmission lines with two 230 kV transmission lines, requiring the replacement of approximately 144 existing wood and steel poles (H-frame design) with approximately 41 steel monopoles of either single-circuit or double-circuit design. Within the Talbot Hill substation, additional breakers and associated controls would be added to accommodate the new lines. Key similarities between the Current Proposal and the Phase 2 DEIS and FEIS proposals include: • The upgrade would follow the same general route and would be entirely located within PSE’s existing 100-foot corridor; • Proposed pole replacement locations would generally be in the same locations as the existing pole locations; • There would be fewer replacement poles than existing poles; • Replacement poles would be taller and larger in diameter than existing poles; and, • Proposed pole replacement would be outside the 200-foot Cedar River shoreline jurisdiction. Key differences between the Current Proposal and the Phase 2 DEIS and FEIS proposals include: • Fewer poles would be removed under the Current Proposal than in the Phase 2 DEIS, but the same number as in the FEIS; • Fewer poles would be replaced under the Current Proposal than in the Phase 2 DEIS, but the same number as in the FEIS; • The lowest wires in the shoreline jurisdiction would be 20-30 feet higher than the existing wires; and, • Additional information on construction and pole design is available in the CUP permit and Shoreline exemption applications. Therefore, the Current Proposal would be within the range, or would represent less intensive development, than analyzed in the past EISs for the project. Chapter 2 ENVIRONMENAL IMPACTS UNDER THE PHASE 2 DEIS, FEIS, & CURRENT PROPOSALS Energize Eastside Project 2-1 Environmental Impacts Environmental Consistency Analysis CHAPTER 2 ENVIROMENTAL IMPACTS UNDER THE PH. 2 DEIS, FEIS, & CURRENT PROPOSALS 2.1 COMPARISON OF IMPACTS The Energize Eastside Environmental Consistency Analysis confirms that the impacts of development under the Current Proposal are within the range of impacts analyzed under the proposals in the past SEPA review, and that there are no significant unavoidable adverse impacts that cannot be mitigated, as described below. This section of the Consistency Analysis compares the probable significant impacts under the Phase 2 DEIS, FEIS, and Current proposals. Table 2-1 summarizes the significant impacts of the proposals documented in the 2017 Phase 2 DEIS and 2018 FEIS and compares these impacts with those under the Current Proposal described in the CUP and Shoreline Exemption application materials. The terms “less-than-significant” and “significant” are used in Table 2-1 to describe impacts. These terms relate to less than a moderate potential and more than a moderate potential for impacts, respectively. The specific meaning of “less-than-significant” and “significant” varies for each element of the environment and is described in the Phase 2 DEIS and FEIS. Text that is highlighted in grey under the Current Proposal represents additional information on the Current Proposal. Text in red indicates changes in impacts from the FEIS. Energize Eastside Project 2-2 Environmental Impacts Environmental Consistency Analysis Table 2-1 COMPARISON OF IMPACTS – PH. 2 DEIS, FEIS & CURRENT PROPOSAL May 2017 Ph. 2 DEIS Proposal Mar. 2018 FEIS Proposal Current Proposal Less-Than-Significant/ Significant Impact 3.1 EARTH Construction Impacts • Construction would require vegetation clearing and excavation, which could temporarily increase erosion.1 Approx. 81 H-frames would be replaced with 6 single circuit pairs and 46 double circuit monopoles • Construction could involve grading and installation of infrastructure in geotechnical hazard areas (e.g., steep slopes, landslide, coal mine, and seismic hazards).1 • An earthquake could occur during construction, resulting in slope failures, liquefaction, ground settlement, or equipment destabilization.1 • Vibration from construction equipment could damage nearby structures.1 • Construction could result in impacts to Olympic Pipelines from contact, vibration, or erosion.1 • Less than Ph. 2 DEIS because less clearing/ excavation for fewer poles removed and replaced (approx. 70 H-frames would be replaced with 11 single circuit pairs and 27 double circuit monopoles). • Same as Ph. 2 DEIS • Same as Ph. 2 DEIS • Same as Ph. 2 DEIS • Same as Ph. 2 DEIS • Same as FEIS. Approx. 177,500 sq. ft of land disturbance and 450 to 650 CY of excavation would be required. • Same as Ph. 2 DEIS and FEIS • Same as Ph. 2 DEIS and FEIS • Same as Ph. 2 DEIS and FEIS • Same as Ph. 2 DEIS and FEIS • With implementation of BMPs, impacts would be less- than-significant. Additional information on construction mitigation measures is provided for the Current Proposal. • With geotechnical evaluation and appropriate construction specifications, impacts would be less-than-significant. • The likelihood of an earthquake coinciding with construction would be low; therefore, less-than- significant impacts are expected. • Less-than-significant impacts expected. • With existing regulations and PSE practices, impacts would be less-than-significant. Operational Impacts • Seismic activity and associated shaking and liquefaction are likely during life of project and could cause damage, power outages, and life safety concerns.1 • Same as Ph. 2 DEIS • Same as Ph. 2 DEIS and FEIS • With implementation of NESC standards, geotechnical recommendations, and regulatory requirements, impacts would be less-than- significant. Energize Eastside Project 2-3 Environmental Impacts Environmental Consistency Analysis • Reuse of unstable or unsuitable soils could cause damage or corrosion of new facilities.1 • Same as Ph. 2 DEIS • Same as Ph. 2 DEIS and FEIS • With geotechnical investigations and recommendations, impacts would be less-than- significant. Cumulative Impacts • The entire region is seismically active and could be at risk from shaking and liquefaction.1 • Same as Ph. 2 DEIS • Same as Ph. 2 DEIS and FEIS • With implementation of NESC standards, geotechnical recommendations, and regulatory requirements, impacts would be less-than- significant. 3.2 WATER RESOURCES Construction Impacts • Construction would require vegetation clearing and excavation, which could temporarily increase erosion and sedimentation of nearby water resources (e.g., four stream reaches including the Cedar River, and one wetland). • Pole installation could encounter shallow groundwater requiring dewatering. Groundwater contamination could occur. • Contamination of water resources could occur from accidental spills and leaks. • Portions of the segment are within Zone 2 of Renton’s Wellhead Protection Area. Installation of poles and increases in impervious surfaces could impact groundwater. • Less impacts on water resources than Ph. 2 DEIS because less clearing/ excavation for fewer poles removed and replaced. (see Section 3.1, Earth, for details on pole replacement • Less than Ph. 2 DEIS, as fewer poles would be installed. • Same as Ph. 2 DEIS • Less than Ph. 2 DEIS, as fewer poles would be installed. • Six wetlands were identified. However, impacts on water resources would be the same as FEIS. • Same as FEIS • Same as Ph. 2 DEIS and FEIS • Same as FEIS. Approx. 969 sq. ft. of new impervious surfaces would be installed. • With implementation of BMPs, impacts would be less- than-significant. Additional information on construction mitigation measures is provided for the Current Proposal. • Excavated areas would be small, so dewatering would be minimal, and impacts would be less-than-significant. • With implementation of a spill prevention plan, impacts would be less-than- significant. • Through compliance with the City’s construction standards, impacts would be less-than- significant. Operational Impacts • The transmission line would cross three creeks and the Cedar River in the existing • Same as Ph. 2 DEIS. • Same as Ph. 2 DEIS and FEIS • Through compliance with applicable critical area regulations, impacts would be Energize Eastside Project 2-4 Environmental Impacts Environmental Consistency Analysis corridor. No poles would be placed in the streams or their buffers. The crossings would not cause long-term impacts to streams and no impacts to buffers. • No poles would be placed in wetlands. One new pole would be placed in a Category III wetland buffer. Impacts would be minor. • New poles and access roads would result in minor increases in stormwater runoff and erosion. • Same as Ph. 2 DEIS • Same as Ph. 2 DEIS • Similar to the Ph. 2 DEIS and FEIS. One new pole would be located in the outer buffer of Wetland NR02 and there would be larger footprints from the Lake Tradition Line replacement poles in the Talbot wetland buffer. Two existing poles would be removed from the overlapping buffers of Wetlands NRO1 and NRO5. • Same as Ph. 2 DEIS and FEIS less-than-significant. A critical areas mitigation plan is provided for the Current Proposal. • Through compliance with applicable critical area, impacts would be less-than- significant. • Through compliance with applicable stormwater regulations, impacts would be less-than-significant. Cumulative Impacts • The project is not expected to contribute to indirect or direct impacts to water resources resulting from other projects; therefore, no cumulative impacts are expected. • Same as Ph. 2 DEIS • Same as Ph. 2 DEIS and FEIS • Less-than-significant impacts expected. 3.3 PLANTS & ANIMALS Construction Impacts • Loss or disturbance of plants and habitat would occur during construction activities. Impact levels would depend largely on pole placement. - Total trees removed: 350 - Significant trees removed: 250 - Trees removed from critical areas: 3 • Same as Ph. 2 DEIS • Fewer trees would be removed than Ph. 2 DEIS and FEIS. - Total trees removed: 339 - Significant trees removed: 238 confirmed (significance of 4 trees could not be determined) • Less-than-significant because the segment would be located in the existing corridor, construction BMPs would be implemented, and disturbed areas would be replanted with native vegetation. A critical areas mitigation plan is provided for the Current Proposal. Energize Eastside Project 2-5 Environmental Impacts Environmental Consistency Analysis - Trees removed from critical area buffers: 38 (see 3.2, Water Resources, regarding pole placement in critical areas). • No impacts to terrestrial protected species are expected because none are known to inhabit the study area. Protected fish species occur in Cedar River; however, stream habitat would not be affected by the project. • Wildlife could be temporarily disturbed by noise from ground-clearing activities. • Discriminating use of growth regulators and herbicides for vegetation management would be used in accordance with existing permits and associated BMPs. • Same as Ph. 2 DEIS • Same as Ph. 2 DEIS • Same as Ph. 2 DEIS - Trees removed from critical areas: 0 - Trees removed from critical area buffers: 47 (22 trees in stream buffers and 25 trees in wetland buffers (trimming of trees could also be required). • Same as Ph. 2 DEIS and FEIS • Same as Ph. 2 DEIS and FEIS • Same as Ph. 2 DEIS and FEIS • Less-than-significant impacts expected. • Less-than-significant impacts expected. • Less-than-significant impacts expected. . Operational Impacts • Minor disturbance or loss of habitat would result through routine vegetation maintenance activities and facility maintenance. • Loss of wildlife habitat would occur due to tree removal, trimming and management activities. • Fish habitat would be lost or degraded due to removal of trees in critical areas and their buffers. • Same as Ph. 2 DEIS • Same as Ph. 2 DEIS • Same as Ph. 2 DEIS • Same as Ph. 2 DEIS and FEIS • Same as Ph. 2 DEIS and FEIS • Same as Ph. 2 DEIS and FEIS • Less-than-significant impacts because the basic character and functions of the habitat in the corridor would be maintained. • Less-than-significant impacts because few protected wildlife species regularly occur in the study area. • Less-than-significant impacts expected. Energize Eastside Project 2-6 Environmental Impacts Environmental Consistency Analysis Cumulative Impacts • Development increases the likelihood of impacts to fish and wildlife habitat. The project would contribute to urbanization through the removal of trees and a reduction of fish and wildlife habitat. • Same as Ph. 2 DEIS • Same as Ph. 2 DEIS and FEIS • Less-than-significant impacts expected. 3.4 GREENHOUSE GASES Construction Impacts • Construction truck trips, off- road equipment, and worker trips would temporarily generate GHG emissions. There is also a potential for lifecycle emissions from manufacturing and transport of material resources for the project. • Similar to Ph. 2 DEIS • Similar to Ph. 2 DEIS and FEIS • Less-than-significant impacts because GHG emissions would be temporary, would not represent a continuing burden on the statewide inventory, and would likely be below state reporting thresholds. Operational Impacts • Removal of trees and vegetation would result in 7.1 metric tons of CO2e per year in sequestration losses. • Employee vehicle trips to maintain the new facilities would increase GHG emissions. • Tree removal would result in 7.5 metric tons of CO2e per year in sequestration losses. • Same as Ph. 2 DEIS • Less CO2e sequestration losses expected than Ph. 2 DEIS and FEIS, because fewer trees would be removed (see Section 3.3, Plants and Animals, for details on tree removal). • Same as Ph. 2 DEIS and FEIS • GHG emissions would be substantially below the State of Washington reporting threshold of 10,000 metric tons, and, therefore, less- than-significant. • Less-than-significant impacts expected. Cumulative Impacts • GHGs are a component of cumulative climate change impacts; both the construction and operational impacts reflect cumulative impacts. • Same as Ph. 2 DEIS • Same as Ph. 2 DEIS and FEIS • Less-than-significant impacts expected. 3.5 ENVIRONMENTAL HEALTH: EMF Construction Impacts • Magnetic fields from construction equipment would be indistinguishable from background levels for • Same as Ph. 2 DEIS • Same as Ph. 2 DEIS and FEIS • Less-than-significant impacts expected. Energize Eastside Project 2-7 Environmental Impacts Environmental Consistency Analysis the public outside of the construction sites. Operational Impacts • All parts of the project would have associated magnetic fields during operation and would vary depending on the pole type and electrical load. • Operation of the proposed transmission line would result in a decrease in magnetic field levels compared to existing conditions. • There are no known health effects from pole frequency EMF. • Same as Ph. 2 DEIS • Same as Ph. 2 DEIS • Same as Ph. 2 DEIS • Same as Ph. 2 DEIS and FEIS • Same as Ph. 2 DEIS and FEIS • Same as Ph. 2 DEIS and FEIS • Less-than-significant impacts expected. • Less-than-significant impacts expected. • The calculated magnetic fields levels would be well below industry guidelines, and, therefore, less-than- significant. Cumulative Impacts • The project would reduce magnetic fields along existing corridors; therefore, there would be no cumulative effects. • Same as Ph. 2 DEIS • Same as Ph. 2 DEIS and FEIS • Less-than-significant impacts expected. 3.6 ENVIRONMENTAL HEALTH: PIPELINE SAFETY Construction Impacts • During construction, the Olympic Pipelines would be exposed to an increased risk of damage from outside force/excavation. • The possibility of pipeline damage could occur from excavation activities and/or surcharge loading from construction equipment. In this unlikely event, a damaged pipeline could result in an immediate or subsequent release or fire that could place the public, workers, natural resources, and other elements of the environment at risk. • Same as Ph. 2 DEIS • Same as Ph. 2 DEIS • Same as Ph. 2 DEIS and FEIS • Same as Ph. 2 DEIS and FEIS • Less-than-significant because the change in risk would not be substantial. • Less-than-significant because the change in risk would not be substantial and mitigation would reduce the potential for impacts further. Energize Eastside Project 2-8 Environmental Impacts Environmental Consistency Analysis Potential impacts could be significant if such an unlikely event were to occur. Operational Impacts • The probability of a pipeline incident -- such as damage to a pipe wall -- due to electrical interference could be slightly higher in some locations. The likelihood of pipeline rupture and fire would remain low, and no substantial change in risk was identified. • Impacts to natural resources and other elements of the environment could be significant in the unlikely event that an accidental release or fire were to occur. • Same as Ph. 2 DEIS • Same as Ph. 2 DEIS • Same as Ph. 2 DEIS and FEIS • Same as Ph. 2 DEIS and FEIS • In locations where pipeline incidents could occur, testing, monitoring, engineering analysis, and implementation of mitigation measures would lower these risks, and impacts would be less-than- significant. • The likelihood of pipeline rupture and release would be low, and mitigation would reduce the risk further. Therefore, the potential risk to natural resources and other elements of the environment would be less-than- significant. Cumulative Impacts • Activities by other parties unrelated to the projects may occur in the corridor on occasion. While these activities remain a source of potential pipeline safety risk in the corridor, the project would not contribute to adverse impacts from these activities; therefore, no cumulative impact to environmental health from pipeline safety would occur. • Same as Ph. 2 DEIS • Same as Ph. 2 DEIS and FEIS • Less-than-significant impacts expected. 3.7 LAND USE & HOUSING Construction Impacts • Construction impacts, due to their temporary nature, would be less-than-significant. No significant excavation would be required, access to • Same as Ph. 2 DEIS • Same as Ph. 2 DEIS and FEIS • Less-than-significant impact expected. Energize Eastside Project 2-9 Environmental Impacts Environmental Consistency Analysis adjacent land uses would be maintained, and installation would not create significant noise. Operational Impacts •The project would be consistent with applicable City of Renton land use-related policies. •The project would not impact existing or future land use patterns in the Renton segment (primarily in single- family uses). It would use the existing corridor and not require new easements from adjoining properties. •The project would cross shorelines of the state associated with the Cedar River. Replacement of poles would be outside the 200-ft. shoreline jurisdiction, and the aerial wire crossing 200 ft. above the river would not require any disturbance within the shoreline jurisdiction. The project would be allowable through the approval of a Shoreline Conditional Use Permit. •Same as Ph. 2 DEIS •Same as Ph. 2 DEIS. •Similar to Ph. 2 DEIS. However, because the project qualifies as repair/ maintenance, a Shoreline Exemption is being sought. •Same as Ph. 2 DEIS and FEIS •Same as Ph. 2 DEIS and FEIS •Same as FEIS. •Less-than-significant impacts expected. •Less-than-significant impacts expected. •Less-than-significant impacts expected. Cumulative Impacts •The project is not expected to alter land use or the supply of housing. It would not affect the scale of additional development. However, if the project were not constructed, it could slow the rate of additional development on the Eastside. •Same as Ph. 2 DEIS •Same as Ph. 2 DEIS and FEIS •Less-than-significant impacts expected. Energize Eastside Project 2-10 Environmental Impacts Environmental Consistency Analysis 3.8 SCENIC VIEWS & AESTHETICS Construction Impacts • Construction impacts, due to their temporary nature, would be less-than-significant. Areas cleared for construction activities would be replanted post-construction; the presence of construction vehicles, equipment, materials, and personnel would end; and increased light and glare would be reduced. • Same as Ph. 2 DEIS • Same as Ph. 2 DEIS and FEIS • Less-than-significant impacts expected. Operational Impacts • Visual quality could change due to contrast of structures with the natural and built environment from vegetation removal, incompatibility with surrounding environment, and visual clutter. • Scenic views could be obstructed by increased pole height or placing poles in new locations. Groups with the highest viewer sensitivity are residential viewers and users of recreation areas. Proposed poles would be taller than (up to 125’ vs. 93’) and greater in diameter than existing poles. • Less than Ph. 2 DEIS, because fewer existing poles would be removed and replaced (see Section 3.1, Earth, for details on pole removal/ replacement). • Less than Ph. 2 DEIS, because poles would be shorter (up to 118’ proposed vs up to 93’ existing). • Same as FEIS • Same as FEIS • Less-than-significant impacts expected. Additional information on pole design/mitigation (e.g., surface treatments) is provided for the Current Proposal. • Less-than-significant impacts expected. Cumulative Impacts • Development would increase the likelihood of impacts to scenic views and the aesthetic environment. The project would not affect the overall scale of development but if the project were not constructed, it could slow the rate of development on the Eastside. • Same as Ph. 2 DEIS • Same as Ph. 2 DEIS and FEIS • Less-than-significant impacts expected. Energize Eastside Project 2-11 Environmental Impacts Environmental Consistency Analysis 3.9 HISTORIC & CULTURAL RESOURCES Construction Impacts • Construction impacts on historic and cultural resources, due to their temporary nature, would be less-than-significant. • Same as Ph. 2 DEIS • Same as Ph. 2 DEIS and FEIS • Less-than-significant impacts expected. Operational Impacts • Potential impacts to significant historic resources and protected archaeological resources could result from pole replacement, ground disturbance, demolition, relocation, or alterations to the visual setting of resources. • Potential impacts to unevaluated historic resources will be determined when the historic property inventory is conducted. Significant impacts to these resources could occur, although not all are likely to be eligible for listing. • Less than Ph. 2 DEIS, because fewer existing poles would be replaced and poles would be shorter. • Same as Ph. 2 DEIS • Same as FEIS. An historic property inventory has been prepared and an archaeological survey has been conducted. 118 historic properties were identified, 6 of which were recommended eligible for historic registers; one historic district is present; and, one archaeological resource was found that could be impacted by the proposed project. • Same as Ph. 2 DEIS and FEIS • Through consultation with DAHP, USACOE, King County Historic Preservation Program, City of Renton, affected Tribes, and other stakeholders, less-than- significant impacts are expected. • Through consultation with DAHP, USACOE, King County Historic Preservation Program, City of Renton, affected Tribes, and other stakeholders, less-than- significant impacts are expected. Cumulative Impacts • Development increases the potential for impacts to historic and cultural resources, if present where development could occur. Impacts to below-ground archaeological resources could occur during ground disturbance. Impacts to historic resources could occur from demolition or alterations to the setting. • Same as Ph. 2 DEIS • Same as Ph. 2 DEIS and FEIS • Less-than-significant impacts expected. Energize Eastside Project 2-12 Environmental Impacts Environmental Consistency Analysis 3.10 RECREATION Construction Impacts • Construction activities may result in the temporary loss of the use of a recreation site (e.g., Sierra Heights Park, Honey Creek Open Space, and Cedar River Natural Zone). • Construction activities may decrease the enjoyment of a recreation site. • Trees and vegetation may be temporarily removed within the managed right-of-way adjacent to recreation sites. • Construction workers may use parking space or adjacent streets for parking. Recreation site or facilities may be used for temporary construction staging. • Same as Ph. 2 DEIS • Same as Ph. 2 DEIS • Same as Ph. 2 DEIS • Same as Ph. 2 DEIS • Same as Ph. 2 DEIS and FEIS • Same as Ph. 2 DEIS and FEIS • Same as Ph. 2 DEIS and FEIS • Same as Ph. 2 DEIS and FEIS • Less-than-significant impacts expected. • Less-than-significant impacts expected. • With restoration of vegetation, less-than- significant impacts are expected. • Less-than-significant impacts expected. Operational Impacts • Park user experience may change with replacement poles that are taller and/or in different location than existing poles. However, there would be fewer replacement poles than existing poles. • Park user experience could be negatively impacted by tree removal in some recreation areas. • The magnitude of impacts would vary depending on location of poles and number of trees removed. Impacts on park uses would not be significant in any location. • Less than Ph. 2 DEIS, because poles would be shorter, but still taller than existing poles (e.g., in Sierra Heights Park, Honey Creek Open Space, and Cedar River Natural Zone). • Same as Ph. 2 DEIS. • Similar to Ph. 2 DEIS. • Same as FEIS, except that poles in the Honey Creek Opens Space would be 5 ft. shorter than in FEIS. • Same as Ph. 2 DEIS. • Less than Ph. 2 DEIS and FEIS, because fewer trees would be removed (see Section 3.3, Plants and Animals, for details on tree removal). • Less-than-significant impacts expected. • Less-than-significant impacts expected. • Less-than-significant impacts expected. Cumulative Impacts • In general, there is pressure on recreation areas from development and increased • Same as Ph. 2 DEIS • Same as Ph. 2 DEIS and FEIS • Less-than-significant impacts expected. Energize Eastside Project 2-13 Environmental Impacts Environmental Consistency Analysis Source: 2017 Ph. 2 DEIS, 2018 FEIS, and PSE, 2019. 1 The Ph. 2 DEIS did not include an Earth section because impacts were expected to be less-than-significant. The impacts listed here are from the Phase 1 DEIS. use. The significant impacts to recreation sites could contribute to the degradation of existing recreation resources and limit the ability for municipalities to provide additional recreation opportunities, unless mitigation is provided. 3.11 ECONOMICS Construction Impacts •No impacts are expected; the economic aspects of the project would not relate to construction impacts. •Same as Ph. 2 DEIS •Same as Ph. 2 DEIS and FEIS •Less-than-significant impacts expected. Operational Impacts •Undergrounding transmission lines would potentially cost the community. The burden on a very small number of payees would be considerable, while the cost when shared would be less. •With loss of tree cover, and associated ecosystem services, the natural environment would be less able to reduce air pollutants and stormwater runoff and sequester carbon dioxide •Same as Ph. 2 DEIS •Similar to Ph. 2 DEIS. •Same as Ph. 2 DEIS and FEIS •Less than Ph. 2 DEIS and FEIS, because fewer trees would be removed (see Section 3.3, Plants and Animals, for details on tree removal). •Less-than-significant impacts are expected if the cost of undergrounding transmission lines is shared. •Less-than-significant impacts expected. Cumulative Impacts •Property values would likely rise with growth and development; the project could also contribute to the combined loss of ecosystem services, in combination with other development projects in the area. •Same as Ph. 2 DEIS •Same as Ph. 2 DEIS and FEIS •Less-than-significant impacts expected. Energize Eastside Project 2-14 Environmental Impacts Environmental Consistency Analysis 2.2 SUMMARY OF IMPACTS Due to the nature of the impact, level of impact, and/or through compliance with federal, state and local regulations, policies or programs, impacts of the Current Proposal on the environment are expected to be similar to or less than the impacts described for the FEIS Proposal. As described in the previous EISs, the impacts of the project are expected to be less-than-significant for all the elements of the environment that were studied. Probable impacts are compared in Table 2-1 and are briefly discussed for each element of the environment below. Earth The Renton segment crosses multiple geological hazard areas (including landslide hazard, steep slope, and erosion hazard areas). Seismic hazard areas (including ground shaking and earthquake induced soil liquefaction) are also present along the segment. Similar to the Phase 2 DEIS and FEIS Proposals, construction and operation of the Current Proposal would not completely avoid impacts to geologic hazard areas due to the prevalence of these features in the project area. Furthermore, pole replacement activities associated with the transmission line upgrade must occur in specific locations for proper functioning of the electrical system, and pole placement in some geological hazard areas would be unavoidable. Like the FEIS Proposal, fewer poles would be removed and replaced under the Current Proposal than under the Phase 2 DEIS Proposal, which would reduce the potential for impacts on earth resources. Through proper engineering (including geotechnical engineering); compliance with applicable local critical area regulations and relevant state and local codes, including National Electric Safety Code (NESC) standards; and, implementation of BMPs during construction, impacts on earth resources would be less-than-significant. Water Resources The Renton segment crosses four stream reaches: Cedar River, Honey Creek, Ginger Creek, and an unnamed tributary of the Cedar River. Six wetlands and Zone 2 Wellhead Protection Areas are also present in the project area. Similar to the Phase 2 DEIS and FEIS Proposals, construction and operation of the Current Proposal could impact the quantity and quality of surface water and groundwater resources (e.g., from contaminants generated during construction and an increase in impervious surfaces and associated stormwater runoff with development). In terms of direct impacts on water resources, no poles would be placed in wetlands, streams, or stream buffers; one pole would be placed in a wetland buffer; there would be larger pole-base footprints in a wetland buffer; and, two existing poles would be removed from overlapping wetland buffers. Like the FEIS Proposal, fewer poles would be removed and replaced under the Current Proposal than under the Phase 2 DEIS Proposal which would reduce the potential for impacts on water resources. Through compliance with applicable Energize Eastside Project 2-15 Environmental Impacts Environmental Consistency Analysis critical area and stormwater regulations, and implementation of BMPs during construction, impacts on water resources would be less-than-significant. Plants and Animals The Renton segment follows PSE’s existing corridor which largely consists of landscaped or maintained areas. Much of the existing corridor includes substantially modified fish and wildlife habitat. No protected plant or terrestrial wildlife species are present in the Renton segment; four protected fish species (Chinook salmon, steelhead, bull trout, and lamprey) occur in the Cedar River which crosses the segment. A total of 574 trees were assessed for the tree inventory of the study area; 367 of these trees are considered “significant” and seven trees are considered “landmark” by the City of Renton. Under the Current Proposal, a maximum of 339 trees would be removed, 238 of which are considered significant trees. No landmark trees and no trees in critical areas would be removed. Fewer trees overall and fewer significant trees would be removed under the Current Proposal than under the Phase 2 DEIS and FEIS Proposals. More trees in critical area buffers would be removed than under the previous proposals. No poles would be placed in streams or stream buffers and only one pole in the Renton segment would be installed in a wetland buffer. Similar to the Phase 2 DEIS and FEIS Proposals, there are no significant unavoidable impacts to plants and animals that cannot be mitigated under the Current Proposal. Impacts would be minimized by using the existing transmission line corridor, limiting disturbance, implementing BMPs, and installing transmission lines between poles with minimal site disturbance. The project would meet or exceed City of Renton regulations on tree removal and replacement, as well as federal transmission line operational standards. Most of the trees in the existing corridor are ornamental and associated with existing property usage; therefore, their removal would not represent a significant impact on native plant and animal habitat. The Current Proposal’s impacts on plants and animals are expected to be less-than-significant and would generally be less than described in the Phase 2 DEIS and FEIS, as fewer trees/significant trees/trees in critical areas would be removed. GHG Emissions Existing GHG emissions in the Renton segment are associated with vegetation maintenance/removal, fuel use by construction-related trucks and equipment, fuel use by maintenance vehicles, and fugitive emissions from substation equipment using sulfur hexafluoride (SF6, a GHG) as an insulating gas. Like the Phase 2 DEIS and FEIS Proposals, GHG impacts were determined to be less-than-significant under the Current Proposal. Carbon dioxide equivalent (CO2e) emissions would be lower under the Current Proposal than under the previous proposals because fewer trees would be removed and more GHGs would remain sequestered. Based on the information provided for the Current Proposal, the GHG impacts associated with short-term/construction and long-term/operation would be roughly equivalent to or slightly less than evaluated in the Phase 2 DEIS or the FEIS. Energize Eastside Project 2-16 Environmental Impacts Environmental Consistency Analysis Environmental Health – EMF Existing magnetic fields in the study area for the Renton segment are associated with PSE transmission lines and substations. Maximum magnetic fields were calculated along the existing Renton segment. These levels were well below industry standards. Like the Phase 2 DEIS and FEIS Proposals, impacts from magnetic fields generated by the Current Proposal are expected to be less-than-significant. All parts of the project would have associated magnetic fields during operation. However, operation of the Current Proposal would result in a decrease in magnetic field levels compared to existing conditions. There are no known health effects from pole frequency EMF. Environmental Health – Pipeline Safety The Olympic Pipeline is located within the existing PSE corridor and surrounding area. Two petroleum pipelines are currently co-located with PSE facilities in the northern portion of the Renton segment. As described for the DEIS and FEIS Proposals, construction of the Current Proposal would expose the Olympic Pipeline to an increased risk of damage. A damaged pipeline could result in a petroleum release or fire that could place the public, workers, natural resources and other elements of the environment at significant risk. During operation of the Current Proposal, electrical interference could cause pipeline rupture and the associated significant risks of petroleum release or fire. Similar to the Phase 2 DEIS and FEIS Proposals, this interference and associated risks could be slightly higher during operation of the Current Proposal than under existing conditions. However, given that the likelihood of these incidents is considered low, and with implementation of regulatory requirements and mitigation measures, impacts on pipeline safety would be less- than-significant. Land Use & Housing Existing land uses in the Renton segment include single family residential, vacant land, and transportation facilities. Future uses in the segment are expected to be single and multi-family residential, mixed-use, and industrial. There are 11 zoning districts and several neighborhoods through which the segment passes. Shoreline High Intensity and Urban Conservancy Environments are present in the segment (e.g., associated with the Cedar River). New land uses and development along the Renton segment are regulated by the City of Renton’s development regulations and Shoreline Master Program. Like the Phase 2 DEIS and FEIS Proposals, the Current Proposal’s impacts on land use and housing along the segment are expected to be less- than-significant. Specifically, the zoning districts in the study area allow electrical utility facilities as a conditional use and the Current Proposal is consistent with City of Renton land use-related plans; the Current Proposal would not impact existing or future land use patterns; and, the proposal Energize Eastside Project 2-17 Environmental Impacts Environmental Consistency Analysis would not remove or impact existing housing. Like the Phase 2 DEIS and FEIS Proposals, the Current Proposal would occur within the existing PSE corridor and would not require new easements from adjoining properties. The project would pass through the Shoreline High Intensity and Urban Conservancy Shoreline Environments, but poles would not be placed within the shoreline zone. Because the Current Proposal is considered required maintenance and repair, a Shoreline Exemption would be required. No adverse effects to the shoreline or shorelines uses are anticipated; therefore, shoreline impacts would be less-than-significant. The Current Proposal is consistent with land use policies from the City of Renton Comprehensive Plan (2015) (e.g., Policy L- 55 related to preserving features that contribute to the City’s identity and define neighborhoods, and Policy L-56 related to providing landscaping). Scenic Views & Aesthetics The visual character of the Renton segment is defined by rolling topography, some steeper ravines and stands of trees along Honey Creek and Cedar River, and a mix of land uses (see above under Land Use). Areas with generally high visual quality include residential areas, Honey Creek and Cedar River, and less disturbed natural areas in King County along the corridor. Scenic views along the corridor include views of the Olympics and Cascades, and near Talbot Hill of Mt. Rainier, Lake Washington, and Cedar River. Impacts to scenic views and the aesthetic environment under the Current Proposal would be less- than-significant and would be similar to or less than the impacts under the Phase 2 DEIS and FEIS Proposals. Although the Current Proposal’s new poles would typically be taller and larger in diameter than existing poles, the segment would be located entirely within PSE’s existing corridor, resulting in low contrast with existing conditions. Overall viewer sensitivity is considered low because development in the areas has already occurred around the existing transmission lines. The degree of additional obstruction of scenic views would be minimal compared with existing conditions. Like the FEIS Proposal, fewer poles would be removed and replaced under the Current Proposal than the Phase 2 DEIS Proposal which would reduce the potential for scenic view and aesthetic impacts. The Current Proposal is consistent with aesthetic and view policies from the City of Renton Comprehensive Plan (2015) (e.g., Policy L-47 related to maintaining Renton’s natural beauty, and Policy L-54 related to protecting public scenic views and view corridors). Historic & Cultural Resources Based upon the results of the archaeological and historic resource surveys, the following historic and cultural resources are located in the Renton study area: one archaeological site, 117 individual historic inventory properties, and one historic district (the Eastside Transmission System). No impacts to the archaeological site are anticipated because all proposed pole replacements would be well removed from the site. Five of the individual historic inventory properties are recommended eligible for listing in the National Register of Historic Places (NRHP) under Criterion C for their architectural character. However, the transmission corridor predates each of these Energize Eastside Project 2-18 Environmental Impacts Environmental Consistency Analysis resources and their setting would continue to include the transmission corridor under the Current Proposal. As such, no significant impacts would occur to these resources. The Eastside Transmission System is recommended for listing in the NRHP under Criterion A for its association with broad patterns of history. The Current Proposal would allow the system to continue to fulfill its original function and would not detract from the characteristics that make it eligible for the NRHP. Impacts to historic and cultural resources in the Renton segment under the Current Proposal would be less- than-significant and would be similar to or less than the impacts under the Phase 2 DEIS and FEIS Proposals. The Current Proposal would follow the same route evaluated in the Phase 2 DEIS and FEIS. The Current Proposal includes refined design details for pole types and placement that would reduce impacts on historic and cultural resources. Poles would be located entirely within the existing transmission corridor, resulting in little change from existing conditions. This minimal change, coupled with implementation of regulatory requirements and mitigation measures, would result in less-than-significant impacts. Recreation The following opportunities for recreation are located in the Renton segment: Sierra Heights Park, Sierra Heights Elementary School, May Creek Greenway, Honey Creek Open Space/Greenway, Cedar River Natural Zone, and Riverview Park. Impacts to recreation sites in the Renton segment under the Current Proposal would be less-than- significant because vegetation clearing and changes to poles and wires would not affect the use of these sites. The Current Proposal would follow the same route evaluated in the Phase 2 DEIS and FEIS. The Current Proposal includes refined design details for pole types, heights, and placement that would reduce impacts on recreation relative to the previous proposals, reducing potential impacts. Economics The Phase 2 DEIS and FEIS described the existing tree cover and associated value of the trees in in the Renton segment. In the FEIS, a total of 499 trees were documented in the segment (not including trees with low ecological value), with a total fixed value of $701,189, and a total service value/year of $1,478. Similar to the Phase 2 DEIS and FEIS Proposals, the Current Proposal is expected to have less-than- significant economic impacts. The economics analysis evaluated two issues: 1- the cost of undergrounding utilities, and 2- ecosystem service loss resulting from tree removal. The operational impacts of undergrounding transmission lines would depend on where the lines are built relative to the cost sharing burden. If only a very small number of payees are involved, the cost would be a large burden. If the cost is shared broadly, the impacts would be less. The ecosystem service analyses in the Phase 2 DEIS and FEIS were based on the total number of trees removed, and covered the entire PSE corridor (the Renton segment was not separated out). The Current Proposal would remove fewer trees/significant trees than the previous proposals; Energize Eastside Project 2-19 Environmental Impacts Environmental Consistency Analysis therefore, there should be less ecosystem service impacts. Ecosystem service is not expected to be significantly impacted by the Current Proposal. 2.3 CONCLUSION The Environmental Consistency Analysis confirms that the impacts of development under the Current Proposal are within the range of impacts analyzed under the proposals in the past SEPA review, and that there are no significant unavoidable adverse impacts that cannot be mitigated. This is because the Current Proposal is identical in most respects to the FEIS Proposal. The differences between the proposals primarily relate to pole placement, tree removal, and details on mitigation provided under the Current Proposal. The impacts under the Current Proposal would generally be similar to or less than those described in the Phase 2 DEIS and FEIS. Chapter 3 MITIGATION MEASURES Energize Eastside Project 3-1 Mitigation Measures Environmental Consistency Analysis CHAPTER 3 MITIGATION MEASURES & SIGNIFICANT UNAVOIDABLE ADVERSE IMPACTS Mitigation measures are implemented to reduce or eliminate the adverse impacts associated with a proposed action. Mitigation can be achieved through avoidance, minimization, rectification, elimination, compensation, or monitoring of environmental impacts (WAC 197-11-768, Mitigation). Below are the mitigation measures identified for the Energize Eastside Project. Mitigation measures specified by code are listed as “Regulatory Requirements” and will be required. Those listed as “Potential Mitigation Measures” are based on comprehensive plan policies, existing PSE programs, and the recommendations of the Environmental Consistency Analysis, and will be at the discretion of the Applicant to adopt or the City of Renton to impose as a condition of project approval to reduce impacts to non-significant levels. The following mitigation measures are organized based on the stage at which they will be applied (i.e., before construction, during construction, at project start-up, and during operation). The mitigation measures from the March 1, 2018 Energize Eastside Project FEIS are noted without any edits or highlights. Those measures from the 2018 FEIS that do not apply to the Renton segment or make specific reference to other segments of the Energize Eastside Project are shown with black strike-edit. Corrections, clarifications, or new measures from the March 14, 2018 CUP and Shoreline Exemption application materials are shaded in grey. Further corrections, clarifications, or new measures recommended thorough this Environmental Consistency Analysis and discussions between the Applicant and City of Renton are noted in red. In the future, if the CUP and/or Shoreline Exemption applications submitted to City of Renton are changed, these mitigation measures will need to be re-examined and possibly modified. As appropriate and for consistency, auxiliary verbs in the mitigation measures (e.g., “would” and “should”) have been updated to “will” to indicate definitive commitments. Minor additions/clarifications to the mitigation measures identified in the 2018 FEIS and in the CUP and Shoreline Exemption application materials are recommended based on the Energize Eastside Environmental Consistency Analysis, as shown below. 3.1 EARTH Regulatory Requirements For PSE, national and state codes and regulations, and industry guidelines govern the design, installation, and operation of transmission lines and associated equipment. The National Electric Safety Code (NESC) 2017, as adopted by the Utilities and Transportation Commission (UTC), Energize Eastside Project 3-2 Mitigation Measures Environmental Consistency Analysis provides safety guidelines that PSE follows, including provisions for worker and public safety during seismic events. Potential Mitigation Measures Prior to Construction 1. Avoid construction on steep slopes, known and potential landslide zones, and areas with organic or liquefiable soils, where feasible. 2. Use appropriate shoring during construction. 3. Use erosion and runoff control measures, including retention of vegetation, replanting, groundcover, etc. 4. Comply with relevant state and local critical areas codes and other applicable requirements. 5. Dispose of soils at approved disposal sites. 6. Coordinate with other utility providers, as appropriate, to determine how best to avoid or minimize any impacts. PSE would will work with other utility service providers during design of the project to coordinate the placement of new facilities and ensure protection of other utilities. 7. Conduct settlement and vibration monitoring, as applicable, du ring construction to identify potential adverse conditions to critical structures and local facilities. PSE will identify schools, hospitals, and registered historic buildings located in the utility corridor and will assess and plan for potential impacts from vibrations, as applicable and feasible. 8. Confirm that a Washington State licensed geotechnical engineer has conducted geotechnical hazard evaluations for all proposed elements addressing ground-shaking, fault rupture, liquefaction, and landslides, and that all geotechnical recommendations have been incorporated into project design. The project geotechnical engineer will review the final construction plans, including all foundation, shoring, cut, and fill designs. The project geotechnical engineer will provide geotechnical inspection during project construction, when applicable. A letter from the project geotechnical stating that the plans conform to the recommendations in the geotechnical report and any addendums and supplements will be submitted to the clearing and grading section prior to issuance of the construction permit. 9. Design the Richards Creek Substation in accordance with the design recommendation presented in the project geotechnical report (Geoengineers, 2016). This will ensure that substation structures are designed to IBC seismic standards even though the IBC exempts this project from its requirements. 10. Use the 2012 International Building Code (IBC), or future adopted IBC, parameters for short- period spectral response acceleration (Ss), 1-second period spectral response acceleration (S1), and Seismic Coefficients FA and FV presented in Table 2 of the geotechnical report (GeoEngineers, 2016). 11. Use site-specific soil input parameters for lateral load design that consider the effects of liquefaction through the application of p-multipliers for LPILE soil parameters that are input to LPILE or similar computer programs that are designed to analyze the behavior of laterally-loaded foundations. Energize Eastside Project 3-3 Mitigation Measures Environmental Consistency Analysis 12. For the area north of the proposed Richards Creek substation, reevaluate the lateral spreading risk to the proposed poles in this area once their final locations have been determined, to determine appropriate foundation dimensions. 13.Where liquefiable deposits areas subject to liquefaction are present, extend foundations below the loose to medium density liquefiable deposits into underlying dense, non- liquefiable soils. 14. Reevaluate the axial capacity of the pole foundations and potential downdrag loads for poles in liquefiable deposits areas subject to liquefaction once final locations are selected and consider these in the structural design. 15. For the one location where soil test results indicated a moderate to high potential for Corrosion test results indicate that all the samples have a low to moderate potential for corrosion. As a result, a corrosion engineer could will be involved in the design of the project. PSE will assess the safety and AC corrosion risks under steady-state operating conditions of the transmission lines. 16. Where bedrock is near the surface, additional options such as rock anchors or micropiles might be appropriate as an alternative to drilled shafts. If micropiles are used, the contractor should submit a detailed micropile plan describing methods and demonstrating consistency with specifications. The project geotechnical engineer will review the final construction plans, including all foundation, shoring, cut, and fill designs. A letter from the geotechnical engineer stating that the plans conform to the recommendations in the geotechnical report and addendums and supplements will be submitted to the plan review section prior to issuance of the construction permit. 17./18. Prior to construction, PSE will The contractor should submit a detailed Drilled Shaft Installation Plan prepared by their construction contractor describing casing and drilled shaft construction methods for review and comment by the engineer before construction. The submittal should will include a narrative describing the contractor’s understanding of the anticipated subsurface conditions, underground utilities, the overall construction sequence, access to the pole locations, and the proposed pole foundation installation equipment. The contractor should will submit a detailed direct embedment pole installation plan describing both uncased and temporary casing methods as appropriate. If drilled shafts are used where groundwater is present, the concrete for drilled shafts will be placed using the “tremie” method and will be considered and evaluated by PSE’s onsite geotechnical engineer (described in the geotechnical report). The Plan will be reviewed by the project geotechnical engineer before construction commences; the Plan will include documentation of this review, which will be provided to the City of Renton Department of Community and Economic Development. During Construction 19. Monitor all improvements for changes in conditions such as cracking foundations, slumping slopes, or loss of vegetative cover. 20.Implement inspection and maintenance programs for all improvements to ensure consistent performance and stability. The project geotechnical engineer will provide geotechnical inspection during project construction when applicable. The project geotechnical engineer will monitor and test soil cuts and fills for pole foundations. The project geotechnical Energize Eastside Project 3-4 Mitigation Measures Environmental Consistency Analysis engineer also will observe, monitor, and test any unusual seepage, slope, or subgrade conditions as applicable. 21. Comply with relevant state and local critical areas codes. 22. If drilled shafts are used where groundwater is present, the concrete for drilled shafts should be placed using the “tremie” method (as described in the geotechnical report ). 23. Monitor the installation of the drilled shafts to confirm that soil conditions are as anticipated and that the shafts are installed in accordance with project plans and specifications, document variations in the field if necessary, and provide consultation as required should conditions vary from those anticipated. 22./23.The project geotechnical engineer will provide geotechnical inspection during project construction when applicable. The geotechnical engineer will monitor and test soil cuts and fills for pole foundations. The geotechnical engineer also will observe, monitor, and test any unusual seepage, slope, or subgrade conditions. 24. Where existing sensitive structures may be present within about 100 feet of the work area, vibration should be monitored. PSE will monitor for vibrations, as applicable and where feasible, during ground disturbing activities, where a school, a hospital, or a registered historic building is within the utility corridor. During Operation 25. Develop and implement a monitoring and maintenance program that includes inspection and reporting on structural stability (e.g. cracking foundations, slumping slopes, or loss of vegetative cover). As part of PSE’s regular inspection of the transmission line, monitor all improvements for changes in conditions such as cracking foundations or slumping slopes that could reduce the ability of structures to resist seismic disturbances. This could include regular reporting to permitting agencies to ensure compliance. PSE will develop a monitoring and maintenance program that includes inspection and reporting on the ability of the transmission line poles to resist seismic disturbances. As part of PSE’s regular inspection of the poles, it will monitor all poles for changes in conditions that could reduce the ability of the structures to resist seismic disturbances . If changes are identified during inspection and monitoring of conditions, PSE will implement additional measures to reduce or minimize those impacts. Significant Unavoidable Adverse Impacts • Damage and potential injury or death from a significant seismic event are never completely avoidable. The proposed project would will not increase these risks. The project would will meet the most recent scientifically-based seismic design standards. Therefore, significant unavoidable adverse earth resources impacts are not expected. Energize Eastside Project 3-5 Mitigation Measures Environmental Consistency Analysis 3.2 Water Resources Regulatory Requirements The project would will need to comply with applicable, federal, state, and local City of Renton requirements for stormwater, streams, wetlands, and critical areas, and Shorelines of the State. Prior to Construction Before If any direct wetland impacts occur to water resources are proposed, PSE would will obtain federal and state authorization, and must will provide: A. A jurisdictional determination from the U.S. Army Corps of Engineers stating whether the delineated wetlands are under federal jurisdiction. B. An application and report presenting impacts on jurisdictional wetlands. C. A mitigation plan for unavoidable wetland impacts following the standards in Wetland Mitigation in Washington State – Part 1: Agency Policies and Guidance (Ecology, 2006). The project would will need to comply with the following regulations of the Partner Cities City of Renton: D. Stormwater regulations of the Partner Cities City of Renton, which are based on the standards set by Ecology’s Stormwater Management Manual for Western Washington (Ecology, 2014). E. Requirements of Shoreline Master Programs for Renton in crossing the Cedar River (see 2018 FEIS Appendix B-3). F. Requirements of each applicable Partner City’s City of Renton’s critical areas ordinance. Typical mitigation measures suggested in the ordinances include: a. Replacement of wetland acreage based on replacement ratios in critical areas ordinances. b. Replacement of lost buffer area. c. Enhancement or restoration of buffers. G. Avoid locating poles in wetlands and wetland buffers to the extent possible. It should be possible to avoid most wetlands by raising the height of poles, allowing for a longer stretch of transmission line over the wetland. H. Apply for all necessary permits (BMPs specific to the site and project would be specified in the construction contract documents that the Construction contractor would be required to implement). During Construction I. Comply with code provisions for the protection of water resources from clearing and grading activities. J. Comply with all necessary permits: a. National Pollutant Discharge Elimination System general permit for construction (issued by Ecology). Energize Eastside Project 3-6 Mitigation Measures Environmental Consistency Analysis b. Possible Hydraulic Project Approval (issued by WDFW) due to crossing of the Cedar River with the upgraded line. c. Construction Stormwater General Permit. K. Implement the Stormwater Pollution Prevention Plan (SWPPP) and Temporary Erosion and Sediment Control Plan to mitigate potential increased sedimentation and turbidity from stormwater runoff. These plans would include BMPs to ensure that sediment originating from disturbed soils would be retained, within the limits of disturbance such as the following: a. Temporary covering of exposed soils and stockpiled materials. b. Silt fencing, catch basin filters, interceptor swales, or hay bales. c. Temporary sedimentation ponds or sediment traps. d. Installation of a rock construction entrance and street sweeping. e. Upon completion of work in each area, exposed soils would be permanently stabilized with seeding or gravel. f. Monitoring of the project by a Certified Erosion and Sediment Control Lead. L. Implement a Spill Prevention, Control, and Countermeasures Plan to minimize the potential for spills or leaks of hazardous materials. BMPs in the Spill Prevention, Control, and Countermeasures Plan would include the following: a. Operating procedures to prevent spills. o Control measures such as secondary containment to prevent spills from entering nearby surface waters. o Countermeasures to contain, clean up, and mitigate the effects of a spill. o Construction vehicle storage and maintenance and fueling of construction equipment would be located away from streams and wetlands. M. Comply with a dewatering plan to monitor groundwater withdrawal during excavations and to avoid groundwater contamination. This would likely include collecting dewatering water from excavations and treating it before discharge to surface water or stormwater systems at an approved off-site location. N. Comply with construction standards applicable to Wellhead Protection Area Zone 2 (RMC 4- 4-030.C8) in the City of Renton. These standards include requirements for the following: a. Secondary containment for hazardous materials. b. Securing hazardous materials. c. Removal of leaking vehicles and equipment. d. Cleanup equipment and supplies. O. Monitor soils from construction-related excavation/grading for contamination; if contaminated soils are encountered, mitigate in accordance with federal, state, and City of Renton regulations. During Operation P. Implement Spill Prevention Control and Countermeasures Plans during maintenance activities (for poles, the transmission corridor, and access roads) to prevent spills or leaks of hazardous materials, paving materials, or chemicals from contaminating surface or groundwater. Energize Eastside Project 3-7 Mitigation Measures Environmental Consistency Analysis Potential Mitigation Measures Prior to Construction 1. Avoid locating poles in wetlands and wetland buffers. to the extent possible. It should be possible to avoid most wetlands by raising the height of poles, allowing for a longer stretch of transmission line over the wetland. 2. Apply for all necessary permits (BMPs specific to the site and project would be specified in the construction contract documents that the Construction contractor would be required to implement). Project and site specific BMPS will be specified in the construction contract documents that the construction contractor will be required to implement. It is noted the BMPs used on construction sites change and often need to be modified during construction based on current conditions. During Construction 3. Comply with code provisions for the protection of water resources from clearing and grading activities. 4. Comply with all necessary permits: a. National Pollutant Discharge Elimination System general permit for construction (issued by Ecology). b. It is the City’s understanding that a Hydraulic Project Approval is not required; however, based on the project as currently proposed, it is pPossible that a Hydraulic Project Approval (issued by WDFW) could be necessary due to crossing of the Cedar River with the upgraded line. c. Construction Stormwater General Permit. The applicant, PSE, will be responsible for consulting with all other local, state, federal, or regional agencies, and/or tribal entities with jurisdiction (if any) for applicable permit or other regulatory requirements that pertain to any aspect of the project addressed in this permit. 5. Implement the Stormwater Pollution Prevention Plan (SWPPP) and Temporary Erosion and Sediment Control Plan to mitigate potential increased sedimentation and turbidity from stormwater runoff. These plans would will include BMPs to ensure that sediment originating from disturbed soils would will be retained, within the limits of disturbance such as the following: d. Temporary covering of exposed soils and stockpiled materials. e. Silt fencing, catch basin filters, interceptor swales, or hay bales. f. Temporary sedimentation ponds or sediment traps. g. Installation of a rock construction entrance and street sweeping. h. Upon completion of work in each area, exposed soils would will be permanently stabilized with seeding or gravel. i. Monitoring of the project by a Certified Erosion and Sediment Control Lead. 6. Implement a Spill Prevention, Control, and Countermeasures Plan to minimize the potential for spills or leaks of hazardous materials. BMPs in the Spill Prevention, Control, and Countermeasures Plan wcould include the following: Energize Eastside Project 3-8 Mitigation Measures Environmental Consistency Analysis o Operating procedures to prevent spills. o Control measures such as secondary containment to prevent spills from entering nearby surface waters. o Countermeasures to contain, clean up, and mitigate the effects of a spill. o Construction vehicle storage and maintenance and fueling of construction equipment would will be located away from streams and wetlands. 7.Comply with a dewatering plan to monitor groundwater withdrawal during excavations and to avoid groundwater contamination. This would likely include collecting dewatering water from excavations and treating it before discharge to surface water or stormwater systems at an approved off-site location. The clearing and grading permit application will include a SWPPP. The structure and content of the SWPPP will follow the requirements of the Renton Clearing and Grading Code and the Renton Clearing and Grading Development Standards. BMPs in the plan could include: o Operating procedures to prevent spills. o Control measures such as secondary containment to prevent spills from entering nearby surface waters. o Countermeasures to contain, clean up, and mitigate the effects of a spill. o Construction vehicle storage and maintenance and fueling of construction equipment would will be located away from streams and wetlands. 8.Comply with construction standards applicable to Wellhead Protection Area Zone 2 (RMC 4- 4-030.C8) in the City of Renton. These standards include requirements for the following: j.Secondary containment for hazardous materials. k.Securing hazardous materials. l.Removal of leaking vehicles and equipment. m.Cleanup equipment and supplies. 9.Monitor soils from construction-related excavation/grading for contamination; if contaminated soils are encountered, mitigate in accordance with federal, state, and City of Renton regulations. Visually monitor soils from construction-related excavation/grading for contamination in accordance with federal, state, and City of Renton regulations. Mitigate in accordance with federal, state, and City of Renton regulations as applicable. During Operation 10.Implement Spill Prevention Control and Countermeasures Plans during maintenance activities (for poles, the transmission corridor, and access roads) to prevent spills or leaks of hazardous materials, paving materials, or chemicals from contaminating surface or groundwater. Significant Unavoidable Adverse Impacts •The proposed project would will comply with applicable regulations and implement appropriate BMPs. Therefore, no significant unavoidable adverse water resources impacts are expected. Energize Eastside Project 3-9 Mitigation Measures Environmental Consistency Analysis 3.3 Plants & Animals Regulatory Requirements Federal, state, and City of Renton regulations and ordinances have been established to protect natural resources (e.g., tree protection and critical area regulations) and are required to be followed. During Construction A. Replace trees removed for the project based on the tree protection regulations and critical areas regulations in each jurisdiction; some of these trees would likely be planted off-site or, in the case of the City of Newcastle, mitigated by paying into an in-lieu fee program. Replacement may be based on cross-sectional diameter of trees removed, or on habitat functions lost due to tree removal, depending on applicable regulations. B. In the Bridal Trails Subarea of the City of Bellevue, plant replacement trees as required under the City’s Tree Retention and Replacement Code. C. Restore affected critical area buffers at a ratio of 1:1. D. Install high-visibility orange construction fencing around the extent of critical areas and their buffers (including native growth protection areas) to prevent disturbance. E. Trees to be retained would will be protected in accordance with City of Renton tree protection standards. Implementation of the mitigation measures described in Section 3.2, Water Resources, to minimize impacts on water resources would will also minimize impacts on plants and animals. In addition, PSE would comply with applicable construction windows for in-water work. If a Hydraulic Project Approval (HPA) is required by Washington Department of Fish and Wildlife (WDFW), a Joint Aquatic Resources Permit Application (JARPA) would be prepared and PSE would will also comply with all requirements of their JARPA the HPA imposed by natural resource agencies WDFW to protect fish and wildlife species and their habitat, such as these could include: F. Limit work to allowable “fish window” time periods. G. Limit work during sensitive nesting and breeding seasons for protected wildlife species occurring in the area. H. Implement PSE’s established bird protection programs and procedures. I. Provide fish exclusion if required to prevent harm to protected species. J. Replant and stabilize disturbed construction and staging areas with native trees, shrubs, and grasses. K. Implement temporary erosion control measures. L. Utilize a Spill Prevention and Control Plan. During Operation M. Trees removed from critical area in Bellevue and Renton may require mitigation monitoring. N. Trees replaced within wetlands or wetland buffers in Renton could require mitigation monitoring for a period of five years or more, consistent with RMC 4-3-050L(3). Energize Eastside Project 3-10 Mitigation Measures Environmental Consistency Analysis Potential Mitigation Measures Prior to Construction 1.Increase pole heights to allow greater separation between poles, allowing for some poles to be moved outside of critical areas or buffer. 2.Partner with local City of Renton, state, and federal agencies to identify potential off-site mitigation areas that are currently degraded. 3.Develop enhancement plans to convert off-site mitigation areas into thriving ecosystems, with an emphasis on enhancing critical habitat areas and buffers through planting of native trees and shrubs to provide shade to streams and habitat for birds, woody debris for fish and amphibians, foraging habitat for mammals, and nesting habitat for avian species. 4.Pay an in-lieu fee to the City of Bellevue for trees removed in the City’s right-of-way to offset loss of public amenity. 5.Pay an in-lieu fee to the City of Renton if tree replacement ratios cannot be met within the corridor. Vegetation mitigation will be completed consistent with PSE’s July 24, 2019, “Vegetation Replacement Approach” letter to the City. During Construction 6.Replant disturbed areas using native vegetation, where feasible and appropriate, that would will meet transmission line clearance requirements and would will not need to be removed or require maintenance (i.e., trimming) in the future. 7.Critical area and buffer trees would will be trimmed and not removed if possible, and trimmed branches and trunks at least 4 inches in diameter would will be left in place to provide a greater amount of woody debris for the area streams, compared to the long- term natural recruitment process, where the underlying property owner approves the placement of woody debris and there are no safety issues related to replacement. 8.PSE would continue to implement an ecologically based, integrated weed management program to control the spread of invasive and noxious weeds at disturbed areas by planting native plants. PSE will implement an ecologically based, integrated weed management plan to control the spread of invasive and noxious weeds at disturbed areas by planting native plants where feasible and appropriate. The Plan will be submitted to the City for approval prior to issuance of the construction permit. 9.Flag the limits of construction, trees to be retained, and critical habitat areas and associated buffers to be avoided. 10.Where pole access is through vegetated areas, maintain existing vegetation to the greatest extent possible. Many of the remaining poles could be replaced from the roadway, reducing the disturbed areas to approximately the footprint of the pole 11.As part of the construction permit process, PSE will coordinate with the City of Renton regarding access roads and possible use of cranes. At sites where access is difficult, a helicopter or large crane may be used to limit the extent of disturbance necessary for construction access. Energize Eastside Project 3-11 Mitigation Measures Environmental Consistency Analysis 12. Retain or replace trees at ratios contained in the PSE July 24, 2019 “Vegetation Replacement Approach” letter to the City. that meet or exceed regulatory standards, as proposed in the Renton Tree Retention Plan (Watershed 2017). o To mitigate for the loss of significant trees in the transmission corridor, PSE is proposing mitigation ratios that exceed the City’s regulatory standards. 13. If trees are planted offsite, larger trees could be clustered, which would contribute to increasing habitat quality and area aesthetics. PSE will submit a Final Tree Retention and Replacement Plan at the time of construction permit review. Where feasible and authorized, PSE will cluster large trees. During Operation 14. Continue to implement an PSE will submit for approval an ecologically based integrated weed management program plan to control the spread of invasive and noxious weeds along the corridor, and at PSE substation facilities, including the removal of existing infestations of invasive species, where feasible and appropriate. 15. Continue to implement PSE’s Avian Protection Program (PSE, 2016b), and mitigate for the direct loss of nesting and roosting habitat for protected species (i.e., eagles, osprey, and other raptors). This mitigation typically occurs by providing nesting platforms in isolated areas away from power lines when nests of species protected under the Migratory Bird Treaty Act and the Bald and Golden Eagle Protection Act need to be removed from the power structures. Any such removal/replacement would occur outside of the nesting season to minimize the disturbance of the birds. In addition, PSE would continue to proactively discourage and minimize the use of the power structures by all avian species by retrofitting existing structures with wire guards, flight diverter devices, and bird guards. PSE will implement its Avian Protection Plan, including methods and equipment to reduce collisions, electrocution, and problem nests. To reduce impacts to birds, the timing and location of construction work will consider critical time periods such as the nesting season for species of local importance present in the immediate Project area. A habitat biologist or other qualified professional will submit a plan to the City documenting recommended measures to limit impacts. 16. During tree maintenance activities, Critical area and buffer trees would will be trimmed and not removed if possible, and trimmed branches and trunks at least 4 inches in diameter would will be left in place to provide a greater amount of woody debris for the area streams, compared to the long-term natural recruitment process, where the underlying property owner approves the placement of woody debris and there are no safety issues related to placement. Significant Unavoidable Adverse Impacts • The major impact of the proposed project on plants and animals would will be the removal of trees, including significant trees. Protected species are not known to occupy the habitat within the Renton segment, and the urbanized setting is unlikely to provide suitable habitat for these species in the future. Therefore, no significant unavoidable adverse plant or animal impacts are expected. Energize Eastside Project 3-12 Mitigation Measures Environmental Consistency Analysis 3.4 Greenhouse Gases Regulatory Requirements Although there’re are no regulations specifically limiting GHG emissions, PSE would will need to comply with applicable federal, state, and local regulations that apply to other resources, some of which would will mitigate the potential for long-term adverse GHG impacts (e.g., regulations that protect tree coverage in critical areas). The following measure s identified in Section 3.3, Plants and Animals, would will potentially offset the long-term sequestration impacts. A. Replace trees removed for the project based on the City of Renton tree protection and critical areas regulations in each jurisdiction; some of these trees would likely could be planted offsite or in the case of the City of Newcastle, mitigated by paying into an in-lieu fee program. Replacement may be based on the cross-sectional diameter of trees removed, or on habitat functions lost due to tree removal, depending on applicable regulations. Potential Mitigation Measures Prior to Construction 1. For equipment installed as part of Energize Eastside at the Talbot Hill substation, if SF6-filled equipment is used, use equipment manufactured guaranteed leakage rate of 0.1 percent. Installation of such equipment could reduce fugitive SF6 emissions by up to 80 percent over older equipment types. As appropriate, use an alternative insulation system for closely spaced equipment. During Construction 2. If available, prudent and not likely to cause harm to equipment, u Use renewable diesel for diesel-powered construction equipment. The fuel can achieve a 40 –80 percent reduction in GHG emissions compared to fossil diesel and is a recommended component of GHG reduction efforts in other jurisdictions such as the Drive Clean Seattle program (Seattle OSE, 2012). 3. Use non-petroleum lubricants for construction equipment. 4. Where compatible with the transmission lines, the underlying property owner agrees, and where feasible based on areas use, rReplant disturbed construction and staging areas with native trees, shrubs, and grasses. 5. Retain or replace trees at ratios that meet or exceed regulatory standards, as proposed in the Renton Tree Retention Plan (Watershed 2017). Vegetation mitigation will be completed consistent with PSE’s July 24, 2019, “Vegetation Replacement Approach’ letter to the City. During Operation 6. BMPs could be implemented to reduce GHG contributions Energize Eastside Project 3-13 Mitigation Measures Environmental Consistency Analysis Significant Unavoidable Adverse Impacts •Construction-related GHG emissions would will be temporary, and construction and operational GHG emissions would will not create an increase that would will be above the state reporting thresholds. Therefore, significant unavoidable adverse GHG emission impacts are not expected. 3.5 Environmental Health – Pipeline Safety Regulatory Requirements PSE is responsible for the Energize Eastside Project’s design, construction, and operational parameters within the shared corridor with the Olympic Pipeline system. For PSE, national and state standards, codes, and regulations, and industry guidelines govern the design, installation, and operation of transmission lines and associated equipment. The National Electric Safety Code (NESC) 2017, as adopted by the UTC, provides the safety guidelines th at PSE follows. The NESC contains the basic provisions necessary for worker and public safety under specific conditions, including electrical grounding, protection from lightning strikes, extreme weather, and seismic hazards. PSE would will use these in developing the final design. To address concerns about potential interaction between the Energize Eastside Project transmission lines and Olympic Pipeline system, PSE and Olympic have coordinated regarding the project since 2012, and both have indicated that they would will continue their coordination through final design and construction. PSE For construction activities within all segments, the appropriate party would will need to comply with applicable federal, state, and local damage preventions laws, regulations, and requirements, and Olympic’s general construction requirement for work near its pipelines, including: A. Develop construction and access plans in coordination with Olympic’s Damage Prevention Team and mutually agreed upon by both parties. These plans would will outline the specific actions that PSE would will take to protect the pipelines from vehicle and equipment surcharge loads, excavation, and other activities in consideration of Olympic’s general construction requirements and in consultation with Olympic on the Energize Eastside project design specifically. Consistent with regulatory requirements, tThe following general measures, at a minimum wcould be included in the construction and access plans: o Notify “one-call” 811 utility locater service at least 48 hours prior to PSE or PSE designated contractors conducting excavation work. (Olympic’s line marking personnel would will then mark the location of the pipelines near the construction areas. These procedures are designed to ensure that excavation would will not damage any underground utilities and to decrease potential safety hazards.) o Field verify the distance between the pipelines and transmission line pole grounds. o Add the pipeline location and depth to project plans and drawings and submit to Olympic for evaluation. Energize Eastside Project 3-14 Mitigation Measures Environmental Consistency Analysis o Arrange for Olympic representatives to be on-site to monitor construction activities near the pipelines. o Install temporary fencing or other markers around the pipeline area. o Provide all necessary information for Olympic to perform pipe stress calculations for equipment crossings and surface loads (surcharge loads). Based on pipe stress calculations, and in coordination with Olympic, provide additional cover that may include installing timber mats, steel plating, or temporary air bridging; utilize a combination of these; or avoid crossing in certain identified areas in order to avoid impacts on Olympic pipelines. Ensure that mitigation to address potential surcharge load impacts is implemented in accordance with applicable requirements and recommended practices, including the following: ▪ 49 CFR 195, Transportation of Hazardous Liquid by Pipeline. ▪ American Petroleum Institute Recommended Practice 1102, Steel Pipelines Crossing Railroads and Highways. ▪ American Lifelines Alliance, Guidelines for the Design of Buried Steel Pipe. o Comply with additional measures related to minimizing surcharge loads included in Olympic’s general construction requirements (see 2018 FEIS Appendix I-2). B. As part of Olympic’s general construction requirements for all work proposed near the pipelines (see 2018 FEIS Appendix I-2), comply with other applicable requirements, including the following: o No excavation or construction activity would will be permitted in the vicinity of a pipeline until appropriate communications have been made with Olympic’s field operations and its Right-of-Way Department. A formal engineering assessment (conducted by Olympic) may be required. o No excavation or backfilling within the pipeline right-of-way would will be permitted for any reason without a representative of Olympic on-site giving permission. o In some instances, excavation and other construction activities around certain pipelines can be conducted safely only when the pipeline operating pressure has been reduced. PSE must will inform its designated contractors that excavation that exposes or significantly reduces the cover over a pipeline may have to be delayed until the reduced operating pressures are achieved. o For a project within 100 feet of the pipelines, Olympic’s Damage Prevention Team would will meet the construction crew on-site at the beginning of the project and weekly thereafter. If excavation has the potential to be within 10 feet of the pipelines, the Damage Prevention Team would will be onsite at all times to monitor excavation. Potential Mitigation Measures Prior to Construction 1. PSE will cContinue to coordinate with Olympic and include safeguards in the project design to protect nearby pipelines from interaction with the new transmission lines due to AC current density, faults caused by lightning strikes, mechanical/equipment failure, or other Energize Eastside Project 3-15 Mitigation Measures Environmental Consistency Analysis causes. PSE will optimize conductor geometry to the extent feasible and consistent with engineer recommendations, where the Olympic pipelines are collocated with the upgraded transmission line. 2. PSE will pPerform an AC Iinterference Sstudy incorporating the final powerline transmission route, configuration, and operating parameters to confirm that current densities would remain within acceptable levels and inform Olympic of any locations where additional measures may be needed to protect the pipelines. PSE will provide Olympic with the Study and if requested, provide the City with documentation establishing that the Study was performed and submitted to Olympic. 3. Obtain and incorporate all the pipeline parameters required for detailed modeling and study (i.e., locations and details of above-grade pipeline appurtenances/stations, bonds, anodes, mitigation, etc.). This should include a review of the annual test post cathodic protection survey data. 4. PSE will fFully assess the safety and coating stress risks for phase-to-ground faults at powerline structures transmission line poles along the entire area of co-location, including both inductive and resistive coupling. 5. PSE will Fully assess the safety and AC corrosion risks under steady-state operating conditions on the powerline. 6. PSE will rReassess the safe separation distance between the transmission line and Olympic’s pipeline at each pole location to minimize arcing risk based on NACE SP0177- 2014 and considering the findings in CEA 239T817 (Stantec, 2017). 7. Ensure that the separation distance between the pipelines and the powerline structures exceeds the safe distance required to avoid electrical arcing by installing pole grounds at appropriate distance from the pipeline based on engineering analysis. Specify appropriate distances for pole grounds from the pipeline to reduce, to the maximum extent feasible, electrical arcing as recommended by the engineer. Field verify the distance between the pipelines and transmission line pole grounds. 8. Consistent with the approved Construction Management and Access Plan, PSE will document all mitigation measures implemented, monitored, and conducted. If requested by the City of Renton, PSE will fFile a mitigation and monitoring report with the City of Renton demonstrating that sufficient safety factors have been incorporated into the design, and documenting all consultations with Olympic, including the sharing of modeling and engineering information with Olympic to assist Olympic in its monitoring and mitigation responsibilities. that documents consultations with Olympic and mitigation measures to address safety-related issues. The mitigation and monitoring report should include a plan that identifies the process for conducting will demonstrate that sufficient pipeline safety measures have been implemented, and document all consultations with Olympic, including the sharing of modeling, engineering, and as-built information with Olympic to assist Olympic in its ongoing monitoring and mitigation responsibilities. The report will identify any additional Energize Eastside Project 3-16 Mitigation Measures Environmental Consistency Analysis field surveys and data collection necessary for verifying mitigation measures following project start-up, and any proposed monitoring to ensure that mitigation measures related to operational issues are followed. additional field surveys and data collection for identifying mitigation measures following project start-up, and proposed monitoring to ensure that mitigation related to operational issues is followed. 9.Install Optical Ground Wire (OPGW) shield wire on the transmission line poles. 10.Prior to permit issuance of the Energize Eastside project, prepare a preliminary plan detailing measures PSE would require of its contractor to protect the pipeline during construction. Where the utilities are co-located, PSE will develop a Construction Management and Access Plan in coordination with Olympic’s Damage Prevention Team that is mutually agreed upon by both parties. This plan will outline the specific actions that PSE will take to protect the pipelines from vehicle and equipment surcharge loads, excavation, and other activities in consideration of Olympic’s general construction and right-of-way requirements and in consultation with Olympic on the Energize Eastside project design specifically. 11.Prior to construction of the Energize Eastside project, file a mitigation and monitoring report with the Partner Cities City of Renton documenting consultations with Olympic and mitigation measures to address safety-related issues. The report should include a monitoring plan that identifies how mitigation measures would be monitored to ensure that mitigation related to construction activities is followed. 12.Require that aThe project geotechnical engineer review final plans and indicate in their report measures necessary to ensure that construction activity would not increase the risk of landslides that could damage the Olympic Pipeline system. will certify that PSE has conducted geotechnical hazard evaluations for all proposed elements of the transmission poles, and that all geotechnical recommendations have been incorporated into project design/ PSE will provide required certification and supporting documentation to the City of Renton. The geotechnical report will address all code requirements and provide a discussion of how the design meets or exceeds the following: o The 2012 International Building Code (IBC), or as amended, parameters for short period spectral response acceleration (SS), 1-sectond period spectral response acceleration (S1), and Seismic Coefficients FA and FV presented in Table 2 of the geotechnical report. o Consistent with the project geotechnical engineer’s recommendation, use soil input parameters for lateral load design that considers the effects of liquefaction through the application of p-multipliers for LPile parameters (or equivalent computer program). o Where areas subject to liquefaction are present, extend foundations below the loose to medium density liquefiable deposits into underlying dense, non-liquefiable soils. o Reevaluate the axial capacity of the pole foundations and potential downdrag loads for poles in areas subject to liquefaction once final locations are selected and consider these in the structural design. 13.Coordinate with Olympic and include safeguards in the project construction and access plans to protect nearby pipelines from excavation activities and surcharge loads. Energize Eastside Project 3-17 Mitigation Measures Environmental Consistency Analysis 14.PSE will develop a Construction Management and Access Plan in coordination with Olympic’s Damage Prevention Team that is mutually agreed upon by both parties. The Plan will identify appropriately sized construction zones to protect the general public, construction timing limits, and other mitigation measures that would will effectively limit the exposure of the general public to potential pipeline incidents 15.Coordinate with school districts Renton School District to identify the most appropriate time for construction to occur near schools that would minimize exposure to students or others in the school facility. To reduce potential impacts to recreation sites as a result of project construction, PSE will coordinate construction activities with Renton Technical College. During Construction 16.To address the potential to encounter boulders, use vacuum truck/equipment (or hand digging in difficult to access areas) to dig past the depth of the pipelines before auguring type equipment is utilized. As directed by Olympic, use soft dig methods (e.g., hand excavation, vacuum excavation, etc.) whenever the pipeline(s) are within 25 feet of any proposed excavation or ground disturbance below original grade. 17.PSE will cCoordinate with Olympic to ensure that line marking personnel mark the entire length of any pipeline within 50 feet of any excavation or ground disturbance below original grade, and not only the location of angle points (points of intersection). 18.Use soft dig methods (e.g., hand excavation, vacuum excavation, etc.) whenever the pipeline(s) are within 25 feet of any proposed excavation or ground disturbance below original grade. 19.Coordinate with Olympic to ensure that an Olympic representative employee trained in the observation of excavations and pipeline locating is onsite at all times during excavation and other ground-disturbing activities that occur within 100 feet of the pipelines where the pipelines are co-located with the proposed transmission lines. If requested by the City of Renton, PSE will file mitigation and monitoring reports with the City quarterly during construction. The reports will identify any additional mitigation measures and monitoring that may be required as a result of PSE’s coordination with Olympic The mitigation and monitoring report will demonstrate that sufficient pipeline safety measures under PSE’s authority and control have been implemented, and document all consultations with Olympic, including the sharing of modelling, engineering, and as-built information with Olympic to assist Olympic in its ongoing monitoring and mitigation responsibilities. The report will identify any additional field surveys and data collection necessary for verifying PSE’s mitigation measures following project start-up, and any proposed monitoring to ensure that mitigation measures related to operational issues are followed. 20.Arrange for a special monitor (third-party monitor) onsite at all times during excavation and other ground-disturbing activities that occur within 100 feet of the pipelines where the pipelines are co-located with the proposed transmission lines. Energize Eastside Project 3-18 Mitigation Measures Environmental Consistency Analysis 21.Where excavations would will be within 10 to 20 feet of the Olympic Pipeline system, the project geotechnical engineer in coordination with Olympic Pipeline will consider temporary casing in the upper 10 to 15 feet should be considered to reduce the risk of sloughing under the pipeline. 22. As required by Olympic, sSteel plates or mats should will be placed over the pipelines to distribute vehicle loads where construction equipment needs to cross over the pipelines. 23. Utility settlement monitoring points, similar to those described below and recommended by PSE’s geotechnical engineer, should will be established on the Olympic Pipeline system corridor at the direction of Olympic where drilled shafts would will be within 15 feet, if requested by Olympic, (or another distance as stipulated by Olympic) to monitor settlement during installation of the drilled shafts. Settlement monitoring points should will be installed so that base-line readings of the settlement monitoring points may be completed prior to the contractor mobilizing to the site. Monitoring should will continue during construction on a daily basis and twice a week in the 3 weeks following construction. The monitoring readings should will be reviewed by the Engineer on a daily basis. If measured settlement exceeds 1 inch, or the amount specified by the utility owner Olympic, the integrity of the utility should will be tested and the contractor should be required to PSE will work with Olympic to repair any damage to the utilities as a result of construction. At Project Start-up 24.PSE will wWork with Olympic to evaluate and implement appropriate mitigation measures to reduce electrical interference on the Olympic Pipeline system to safe levels. (Olympic has informed PSE that, after the system is energized, it plans to collect field data to assess the necessity for the installation of AC grounding or similar systems to address steady-state conditions. Olympic has informed PSE that it plans to implement appropriate mitigation measures to the extent needed based on its analysis of field data collected following system energization. AC grounding systems are commonly installed in connection with power transmission poles to dissipate any energy to ground.) PSE will provide information to Olympic as appropriate or when requested by Olympic for Olympic to record AC pipe-to-soil potentials during its annual cathodic protection survey. PSE will provide Olympic with as much advance notice as practical of when outages are planned on the individual circuits (i.e., when only one circuit of the double circuit transmission lines is in operation) to allow monitoring of the AC induction effects on the pipelines. PSE will provide Olympic with data on anticipated maximum loads under peak winter operating conditions on an annual basis, and, if requested, provide copies to the City of Renton to verify that this data has been provid ed to Olympic. After the transmission line is installed and energized, Olympic is expected (due to its federal requirements to protect the pipeline from damage) to measure the actual AC Energize Eastside Project 3-19 Mitigation Measures Environmental Consistency Analysis interference with the pipeline in order to ensure that all AC interference risks have been fully mitigated under steady-state operation of the transmission line. PSE will cooperate with Olympic in completing post energization AC site survey to determine if any adjustments are needed to Olympic’s pipeline protection systems. PSE will provide load data for the survey, along with any design or as-built information requested by Olympic 25.Verify arc distances once poles are installed and, where necessary, install ground wires or other grounding systems to ensure that pole grounds are all adequately separated from the pipelines. A qualified licensed engineer will verify the separation distances between the transmission grounding system and the pipeline. The separation distance should will meet the recommendations in the Final Pipeline Interaction Assessment and Design Report after poles are installed. If grounding distances are not consistent with the recommendations, PSE will reinstall the grounding system to comply with the recommendations. 26. Mitigation that Olympic could provide based on the results of the analysis may include the installation of additional protective measures such as grounding mats, horizontal surface ribbon, and/or deep anode wells based on a detailed mitigation study, as appropriate. During Operation 27. If indicated by the AC interference study conducted for final design, inform Olympic when the electrical system is expected to operate at or near winter peak loading so as to provide Olympic a reasonable opportunity to take appropriate steps to measure actual AC current densities. PSE will provide Olympic with data on anticipated maximum loads under peak winter operating conditions on an annual basis. If requested, copies of the data will be provided to the City of Renton to verify that this data has been provided to Olympic. 28. To detect any unexpected changes between the pipeline and transmission line, provide information to Olympic as necessary for Olympic to record AC pipe-to-soil potentials and DC pipe-to-soil potentials during their annual cathodic protection survey. PSE will provide information to Olympic as appropriate or when requested by Olympic for Olympic to record AC pipe-to-soil potentials and DC pipe-to-soil potentials during its annual cathodic protection survey. 29. PSE will pProvide Olympic with as much advance notice as practical of when outages are planned on the individual circuits, as the AC induction effects on the pipelines may be magnified when only one circuit (of the double-circuit transmission lines) is energized (i.e., when only one circuit of the double circuit transmission lines is in operation) to allow monitoring of the AC induction effects on the pipelines. 30.PSE will pProvide the Partner Cities City of Renton with PSE monitoring Olympic with data on maximum currents loads under peak winter operating conditions on an annual basis. If requested, copies of the data will be provided to the City of Renton to verify that this data has be provided to Olympic. Energize Eastside Project 3-20 Mitigation Measures Environmental Consistency Analysis Significant Unavoidable Adverse Impacts • Even with worst-case assumptions related to the increased risk during construction and operation of the proposed project, the likelihood of a pipeline release and fire would will remain low and no substantial increase in risk compared to the existing conditions was identified. It is expected that any increase in risks within the corridor c ould be fully mitigated. Therefore, no significant unavoidable adverse pipeline safety impacts are expected. 3.6 Environmental Health – Electric & Magnetic Fields (EMF’S) Potential Mitigation Measures No adverse impacts from magnetic fields are expected. At Project Start-up / During Operation 1. If In the event that radio frequency interference is found by a radio operator, PSE would will de- tune pole structures by installing hardware (such as arresters). Mitigation for potential corrosion of the pipeline is discussed under Section 3.5, Environmental Health – Pipeline Safety. If that mitigation is incorporated into the project, it would will further reduce magnetic field levels at the ground level from the proposed transmission lines. Significant Unavoidable Adverse Impacts • No adverse impacts are likely from power frequency EMF at the levels of public exposure from the proposed project. Therefore, no significant unavoidable adverse EMF impacts are expected. 3.7 Land Use & Housing Regulatory Requirements All of the segments and options The Renton segment would will need to meet the regulations of the zoning districts through which it traverses. In areas where the use is not allowed outright within a zoning district, a Conditional Use Permit would will be required. The proposed use is not allowed outright within City of Renton zoning districts. Therefore, a Conditional Use Permit is required, and a complete application was filed with the City on March 14, 2018. Adherence to the zoning regulations of each jurisdiction City of Renton is generally not discretionary and would will provide some mitigation for project-related impacts to land use. Energize Eastside Project 3-21 Mitigation Measures Environmental Consistency Analysis Undergrounding of transmission lines is not required by any of the subarea plans in the study area City of Renton regulations. If the City of Renton does request that a portion of the transmission line be placed underground, PSE would will work with the City to determine the cost of undergrounding and how a tariff may apply. In Newcastle, PSE intends to apply for a variance from the setback requirements, which would enable the use of shorter poles in that segment. The City has the right to impose conditions on the facility in regards to location, development, design, use or operation to mitigate impacts, as summarized in the section below. Prior to Construction A. Design and operate utility facilities to minimize impacts on the surrounding uses, the environment, and the city (NMC 18.44.052.C.1). B. Work with the City of Newcastle to adopt any conditions imposed relating to the location, development, design, use, or operation of a utility facility to mitigate environmental, public safety or other identifiable impacts. Mitigation measures may include, but are not limited to, natural features may serve as buffers, or other site design elements such as fencing and site landscaping (NMC 18.44.052.D) Potential Mitigation Measures Prior to Construction 1. Consolidate utility facilities and co-locate multiple utilities (City of Newcastle Plan Policy UT- P3). 2. Implement new and expanded transmission and substation facilities in such a manner that they are compatible and consistent with the local context and the land use pattern established in the Comprehensive Plan (City of Bellevue Plan Policy UT-95). 3. Design, construct, and maintain facilities to minimize their impact on surrounding neighborhoods (City of Bellevue Plan Policy UT-8) 4. Conduct a siting analysis for new facilities and expanded facilities at sensitive sites (areas in close proximity to residentially-zoned districts) (City of Bellevue Plan Policy UT-96), 5. Underground sections of the transmission lines where inconsistencies with the comprehensive plan policies regarding aerial facilities would otherwise occur. (Undergrounding of transmission lines is not required by any of the subarea plans in the study area City of Renton regulations. If a City of Renton does request that a portion of the transmission line be placed underground, PSE would work with the City to determine the cost of undergrounding and how a tariff may apply.) 6. In locations where access is difficult, PSE will identify any areas where a helicopter or large crane could be used to lift foundation rebar and/or poles over adjacent properties and into place. Helicopters could also be used to facilitate , or to facilitate stringing the new transmission lines. into place, reducing the need to enter property to feed the initial lead line (called a “sock line”) that is used to pull the actual conductors into place. PSE or its contractor will provide copies of the “congested air” permit from the Federal Aviation Energize Eastside Project 3-22 Mitigation Measures Environmental Consistency Analysis Administration (FAA). PSE will also coordinate with the City of Renton to determine where this type of construction is allowed. The decision to use a large crane or helicopter is usually determined by the construction contractor to address access concerns and minimize site disturbance. Use of a helicopter for this purpose is regulated by the Federal Aviation Administration (FAA). A “congested air” permit and advance notification are required. Because of the potential impacts of this type of construction, local regulators may also want to limit where this type of construction would be allowed. Appendix A-3 includes a series of questions and answers about helicopter use. Following is a brief summary of considerations regarding this type of construction. o Helicopter use for stringing the sock line takes only a few minutes per pole, for each conductor. It involves flying directly over the poles and would not likely involve suspending anything over occupied buildings or homes. o If a crane or helicopter were used to install poles, it would require occupants of buildings or homes in the path of the poles being transported to vacate the premises for up to 2 hours at a time during daylight working hours. o Helicopters generate substantial noise that is not regulated by local codes. Appendix A-4 of the 2018 FEIS includes a table that shows expected noise levels. o Helicopter use would not eliminate the need for construction access by vehicles for excavation and pouring concrete. During Operation 7. To the extent allowable under state law governing pole attachments, PSE will lLimit the number of cellular telecommunication facilities that could be installed on the proposed 230 kV poles to the number locations currently installed in the corridor and proposed to be reinstalled as part of the 2018 FEIS. to reduce potential land use and visual impacts. Reinstalled facilities will be in approximately the same locations as they were previously. Facilities will be required to get City approval per current land use regulations before reinstalling telecommunication equipment; provided, however, PSE will not be liable for any third party’s obligation or failure to obtain such City approval. 8. Require the reinstalled telecommunications facilities to be in the same approximate locations as they were previously and to comply with the requirements of Chapter 80.54 RCW, Chapter 480-54 WAC, and City of Renton regulations. Significant Unavoidable Adverse Impacts • Any nuisances to land uses caused by construction activities would will be short-term and less-than-significant. Long-term land use and housing impacts would be less-than-significant as well because the transmission line upgrade in the Renton segment is a land use anticipated in the City and its subarea plans and would will not impact existing or future land use patterns. Therefore, no significant unavoidable adverse land use or housing impacts are expected. Energize Eastside Project 3-23 Mitigation Measures Environmental Consistency Analysis 3.8 Scenic Views & Aesthetics Regulatory Requirements Local regulations would will require some mitigation of project-related impacts to the aesthetic environment. Requirements are summarized in the 2018 FEIS by jurisdiction and would will be required to be incorporated into the design prior to construction. City of Renton would will require some mitigation measures for indirect project-related impacts to the aesthetic environment (e.g., through mitigation to address critical area and land use impacts), and these measures should will be implemented during the design stage (prior to construction) and as long-term mitigation strategies (e.g., maintenance of screening vegetation), as listed below. The City does not have regulations that directly address mitigation of impacts to scenic views or the aesthetic environment that would will be produced by the proposed project, although their general policies do address general aesthetic qualities and public views. As mentioned previously under Land Use, undergrounding of transmission lines is not required by City of Renton regulations. If City of Renton does request that a portion of the transmission line be placed underground to address unavoidable significant impacts to scenic views or the aesthetic environment, PSE will work with the City to determine the cost of undergrounding and how a tariff may apply. Potential Mitigation Measures Prior to Construction 1. Ensure siting and location of transmission facilities is accomplished in a manner that minimizes adverse impacts on the environment and adjacent land uses (City of Renton Plan Policy U-72). 2. Consolidate utility facilities and co-locate multiple utilities (City of Newcastle Plan Policy UT-P3). 3. Implement new and expanded transmission and substation facilities in such a manner that they are compatible and consistent with the local context and the land use pattern established in the Comprehensive Plan (City of Bellevue Plan Policy UT-8). 4. Conducts a siting analysis for new facilities and expanded facilities at sensitive sites (areas in close proximity to residentially-zoned districts (City of Bellevue Plan Policy UT-96) 5. New development should install a dense visual vegetative screen along Richards Road (City of Bellevue Plan Policy S-RV-31). 6. Consider neighborhood character in planting appropriate varieties and trimming tree limbs around overhead lines (City of Newcastle Plan Policy UT-P9). 7. Design overhead transmission lines in a manner that is aesthetically compatible with surrounding land uses (City of Newcastle Plan Policy UT-P10). This could include design measures such as changes to pole height, spacing, location, or color. Energize Eastside Project 3-24 Mitigation Measures Environmental Consistency Analysis 8. Minimize visual and other impacts of transmission towers and overhead transmission lines on adjacent land uses through careful siting and design (City of Newcastle Plan Policy UT- P14). 9. Design transmission structures to minimize aesthetic impacts appropriate to the immediate surrounding area whenever practical (City of Newcastle Plan Policy UT-P16). 10. Underground section of the transmission lines where unavoidable significant impacts to scenic views or the aesthetic environment would otherwise occur. 11. Position poles and adjust pole height to minimize impacts to the greatest extent possible. In Newcastle a variance from setback requirements would allow the poles to positioned farther away from the houses. This would also allow for shorter poles. 12. Specify poles with an aesthetic treatment (such as paint or a self-weathering finish) to reduce contrast with the surrounding environment. 13. If steel poles are used, a non-reflective coating would be applied. A non-reflective coating will be used on steel poles, unless specifically requested by the City. 14. Position poles and adjust pole height to minimize impacts to the greatest extent possible feasible in light of applicable regulations and technological and safety constraints. 15. PSE would will continue to coordinate with property owners along the existing corridor to develop property-specific landscaping and tree replacement plans, with a focus on controlling invasive species and enhancing native species. Where individual property owners decline to have new trees planted onsite, PSE would will work with the City to place additional trees offsite or would will participate in the City’s fee in lieu of program. Vegetation mitigation will be completed consistent with PSE’s July 24, 2019, “Vegetation Replacement Approach” letter to the City of Renton . During Construction 16. Retain or replace trees in a manner consistent with to the greatest extent possible at ratios that meet or exceed regulatory standards as proposed in the Renton Tree Retention Plan (Watershed 2017). PSE’s July 24, 2019, “Vegetation Replacement Approach” letter to the City of Renton. 16A.PSE will incorporate art (wraps or painted) on the lower portion of the support structures, in order to mitigate the aesthetic impacts of the new larger poles within the proposed corridor. During Operation 17. Limit disturbance to vegetation within major utility transmission corridors to what is necessary for the safety and maintenance of transmission facilities (City of Newcastle Plan Policy UT-P8). In areas where vegetation disturbance is unavoidable and to the extent authorized by the underlying property owners, replant with vegetation that would will be compatible with vegetation clearance requirements, preventing future vegetation removal or maintenance in the future. 18. Use landscape plantings to screen or improve the appearance of areas surrounding above- ground utility facilities and to diminish visual impacts due to vegetation clearing in the corridor (City of Newcastle Plan Policy UT-P20). Energize Eastside Project 3-25 Mitigation Measures Environmental Consistency Analysis 19. Require the reinstalled telecommunications facilities to be in the same approximate locations as they were previously and to comply with the requirements of Chapter 480.54 RCW, Chapter 480-54 WAC, and local jurisdiction City of Renton regulations. To the extent allowable under state law governing pole attachments, PSE shall limit the number of telecommunication facilities installed on the 230 kV poles to the locations currently installed in the corridor to reduce potential land use and visual impacts. Reinstalled facilities shall be in approximately the same locations as they were previously. Facilities shall be required to get City approval per current land use regulations before reinstalling telecommunication equipment; provided, however, PSE shall not be liable for any third party’s obligation or failure to obtain such City approval. Significant Unavoidable Adverse Impacts • No significant unavoidable adverse scenic views or aesthetic impacts are expected. 3.9 Historic & Cultural Resources Regulatory Requirements Prior to Construction A. Develop resource-specific mitigation measures during consultation with DAHP, affected Tribes, KCHPP, and other appropriate stakeholders if a protected archaeological resource is identified during pre-construction archaeological survey or historic property inventory. B. Apply for an archaeological excavation permit from DAHP (WAC 25-48-060) if impacts to a protected archaeological resource cannot be avoided. C. Request an eligibility determination from DAHP for resources listed recommended as eligible for listing in the NRHP (Eastside Transmission System, Somerset Neighborhood, Newcastle Cemetery, Mt. Olivet Cemetery, and the Columbia & Puget Sound Railroad). If any are determined eligible, mitigation measures specific to those resources would will be developed during consultation with DAHP, affected Tribes, and any other appropriate stakeholders. D. Obtain a Certificate of Appropriateness (COA) from KCHPP (KCC 20.62) if there are potential impacts to a designated KC Landmark. E. Avoid cemeteries in accordance with state law (Chapters 68.60 RCW and 68.50 RCW). F. Avoid graves outside of the dedicated boundaries of a cemetery in accordance with state law (Chapters 27.44 RCW and 68.60.050). During Construction G. Develop mitigation measures during consultation with DAHP, affected Tribes, and any other appropriate stakeholders if a protected archaeological resource is identified during construction. In accordance with RWC 27.53, an archaeological resource identified during Energize Eastside Project 3-26 Mitigation Measures Environmental Consistency Analysis construction is protected until DAHP determines whether it is eligible for listing in the NRHP.1 H. Follow procedures dictated by state law (RCW 27.44) if human skeletal remains are discovered. I. Obtain an excavation permit from DAHP if unmarked graves would will be disturbed. Potential Mitigation Measures Prior to Construction 1. Conduct a historic property inventory (field work is complete; resulting forms and associated report have been submitted to DAHP and U.S. Army Corps of Engineers (USACE) for review and approval). 2. Conduct archaeological resource surveys for the selected route that include subsurface testing (pedestrian and subsurface survey of the 16-mile alignment and specific proposed pole locations began in August 2017 and was on-going in January 2018; PSE will conduct a second pedestrian and subsurface survey to assess staging areas, laydown areas, stringing sites, and access roads once more information on these locations is available; as of this writing, this has not started (the archaeological survey has been conducted. The applicant is currently working with DAHP and the USACE to obtain necessary approvals). 3. Prepare an Inadvertent Discovery Plan (IDP) for the project and discuss the IDP during pre- construction meeting(s). 4. Conduct subsurface testing. 5. Consult with DAHP and any other appropriate stakeholders to develop resource-specific mitigation measures for impacts to significant cultural resources. 6. Preserve or add screening at proposed pole sites to minimize potential impacts to the viewsheds of historic cemeteries. 7. Adjust the proposed pole locations to reduce potential direct impacts to historic cemeteries. 8. Conduct ground penetrating radar analysis in areas adjacent to Newcastle Cemetery, if conditions are determined appropriate. Prior to construction, PSE will conduct archaeological resource surveys for the selected route that include subsurface testing and a second pedestrian and subsurface survey to assess staging areas, laydown area, stringing sites, and access roads after more information on these locations is available. Prior to construction, PSE will develop resource-specific mitigation measures during consultation with the Washington Department of Archaeology and Historic Preservation (DAHP), affected Tribes, King County Historic Preservation Program (KCHPP), and other appropriate stakeholders if a protected archaeological resource is identified during the pre-construction archaeological survey or historic property inventory. 1 Isolated (single) artifacts, either precontact or historic, are not protected because they do not meet the definition of a “site” under state law (WAC 25-48-020(9)). Energize Eastside Project 3-27 Mitigation Measures Environmental Consistency Analysis PSE will prepare an Inadvertent Discovery Plan (IDP) for the project and discuss the IDP with the contractor during pre-construction meeting(s). PSE will apply for an archaeological excavation permit from DAHP (WAC 25-48-060) to the extent required under applicable law. If any resources are determined eligible for listing in the National Register of Historic Places (NHRP) by DAHP, mitigation measures specific to those resources will be developed during consultation with DAHP, affected Tribes, and any other appropriate stakeholders. Any final determination and mitigation measures developed based on this determination will be reported to the City of Renton to the extent allowed by law. During Construction 9. PSE will follow the procedures identified in the IDP if any cultural resources are encountered during construction. PSE will also follow procedures identified for any historic resources through consultation with DAHP. Significant Unavoidable Adverse Impacts • It is probable that all historic and cultural resource impacts could be mitigated through consultation with DAHP, King County Historic Preservation Program, Renton, affected Tribes, and other stakeholders. Therefore, no significant unavoidable adverse historic or cultural resource impacts are expected. 3.10 Recreation Regulatory Requirements None of the Partner CitiesThe City of Renton does not have regulations that would will require mitigation of project-related impacts to recreational resources. Prior to Construction A. Avoid placement of infrastructure within or adjacent to recreation sites where there is none currently to the extent possible. B. Use BMPs to minimize noise, dust, and other disturbances to visitors to recreation sites during construction, as well as in areas used for infor mal recreation (e.g., along roads). Potential Mitigation Measures Prior To Construction 1. Use vegetation outside of any area required to be cleared to screen poles and wires where transmission infrastructure is placed within a recreation site. 2. Work with each Partner City of Renton to determine mitigation for tree removal within recreation sites in its jurisdiction. Vegetation mitigation will be completed consistent with PSE’s July 24, 2019, “Vegetation Replacement Approach” letter to the City of Renton. Energize Eastside Project 3-28 Mitigation Measures Environmental Consistency Analysis 3. Coordinate with potentially affected park districts/departments City of Renton Community Services Department. 4. Provide alternative access points to recreation sites and trail detours. 5. Avoid construction during months when recreation sites are busier, when possible. In areas where construction will impact use of recreation sites and where feasible, avoid construction during times those recreation sites have higher usage. As appropriate detour and temporary closure signs will be used. 6. Avoid vegetation clearing for construction activities where possible. 7. Avoid placing poles at Rose Hill Middle School and Tyee Middle School while school is in session. 8. Notify local jurisdictions City of Renton, Renton School District schools, or private owners 60 days in advance of work within recreation sites. 9. Notify the public of any temporary closure of trails or recreations sites 2 weeks in advance. 10. Provide signage along trails or park entrances at least 1 week prior to closures. 11. Avoid placement of infrastructure within or adjacent to recreation sites where there is none currently to the extent possible. Use BMPs to minimize noise, dust, and other disturbances to visitors to recreation sites during construction, as well as in areas used for informal recreation (e.g., along roads). Post Construction 12. Restore recreation sites or trails after construction to pre-construction conditions. Significant Unavoidable Adverse Impacts • Any nuisances to recreation activities caused by construction activities would will be short- term and less-than-significant. Long-term impacts to recreation would will be less-than significant as well because the project would will not adversely affect recreation use or opportunities. Therefore, no significant unavoidable adverse recreation impacts are expected. 3.11 Economics Regulatory Requirements Mitigation for economic impacts from a project is not required under SEPA; however, PSE would will need to comply with applicable federal, state, and local regulations that apply to other resources, some of which would will mitigate the potential for economic impacts (e.g., regulations that protect tree coverage in critical areas). During Construction A. Replace trees removed for the project based on the City of Renton tree protection ordinance and critical areas regulations in each jurisdiction; some of these trees would Energize Eastside Project 3-29 Mitigation Measures Environmental Consistency Analysis likely could be planted offsite. or, in the case of City of Newcastle, mitigated by paying into an in-lieu fee program. Replacement may be based on cross-sectional diameter of trees removed, or on habitat functions lost due to tree removal, depending on applicable regulations. Potential Mitigation Measures 1. Retain or replace trees at ratios that meet or exceed regulatory standards, as proposed in the Renton Tree Retention Plan (Watershed 2017). Vegetation mitigation will be completed consistent with PSE’s July 24, 2019, “Vegetation Replacement Approach” letter to the City of Renton. o To mitigate for the loss of significant trees in the transmission corridor, PSE is proposing mitigation ratios that exceed the City’s regulatory standards. 2. If trees are planted offsite, larger trees could be clustered, which would will contribute to increasing habitat quality and area aesthetics. Vegetation mitigation will be completed consistent with PSE’s July 24, 2019, “Vegetation Replacement Approach” letter to the City of Renton. 3. To mitigate the ecosystem service impacts due to tree loss, tree species that absorb carbon at higher rates (e.g., common horse-chestnut, black walnut, American sweetgum, Ponderosa pine, red pine, white pine, London plane, Hispaniolan pine, Douglas fir, scarlet oak, red oak, Virginia live oak, and bald cypress2) could be planted. Vegetation mitigation will be completed consistent with PSE’s July 24, 2019, “Vegetation Replacement Approach” letter to the City of Renton. Significant Unavoidable Adverse Impacts • No economic impacts are anticipated during construction. Long-term, there would will be no significant impacts on assessed property values. The proposed project would will require tree removal along the existing corridor; however, the value of total ecosystem services lost because of tree removal would will be minimal. Therefore, no significant unavoidable adverse economic impacts are expected. 2 Nowak, D. J., Stevens, J. C., Sisinni, S. M., & Luley, C. J. (2002). Effects of urban t ree management and species selection on atmospheric carbon dioxide. APPENDICES APPENDIX A CURRENT PROPOSAL SITE PLAN MAP CREATED BY: Date: 1/18/2018Path: G:\Projects\Washington\Puget_Sound_Energy_007022\EnergizeEastsideMapbook_10059878\7.2_WP\Map_Docs\Landuse_CUP\Renton\Version_N\PSE_Renton_Index.mxdTopo Basemap - ESRI Online,Transmission Line - PSE ST169 ST900 §¨¦405 Renton Renton Newcastle KingCounty 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 I0 0.25 0.5 Mile RENTON CONDITIONAL USE PERMIT INDEX /CRITICAL AREAS LAND USE PERMIT SOURCES: APPLICANT: Brad Strauch Puge t Sound Energy P.O. Box 97034, Bellevue WA 98009-9734 (425) 456 - 2556 ACREAGE IN RENTON: 54.5 acres §¨¦405 Renton Newcastle 8888!(D!(D&-&-4/2C-16AA1 4/2C-16BA1 K i n g C o u n t ySE 95TH WAY 0423059142 33451004453345100450 3345100470 3345100475 7788000140 K i n g C o u n t yC i t y o f N e w c a st l eC i t y o f R e n t o n Da te: 1/18/2018Path: G:\Projects\Washington\Puget_Sound_Energy_007022\EnergizeEastsideMapbook_10059878\7.2_WP\Map_Docs\Renton\Landuse_CUP\Version_N\PSE_Renton_CUP.mxdProjec t Corrid or &-Prop osed Pole L oc a tion !(D Existing Pole L oc a tion–To Be Rem oved Tra nsm ission L ine - Prop osed Tra nsm ission L ine - Existing #*Potentia l Stringing Site Rec om m end ed Ac c ess- Prop osed Pole U nd erground Power U tility L ine U nd erground Wa ter & Wa stewa ter U tility L ine Pa rc el City Jurisd ic tion Bound a ry Strea m Wetla nd Wetla nd or Strea m Buffer L a nd slid e Ha za rd L a nd slid e Ha za rd 50ft Buffer Steep Slop e Steep Slop e 50ft Buffer Erosion Ha za rd I220+00831 4/2SCT10EAST 100FT/WEST 100FTSTA=221+56.71HT=88FT EL E=325.36 400 420 440 460 480 340 360 380 320 300 280 SITE PLAN 500 520 540 560 400 420 440 460 480 340 360 380 320 300 280 500 520 540560 Profile V iew Struc ture Cond uc tor Ground L ine Ma jor Eleva tion Grid Ma jor Sta tion Grid Minor Sta tion Grid Page 1 of 30 BASED ON PSE ENGINEERINGDESIGN REVISION NI02550Feet1 inc h = 50 feet MAP EXTENT RENTON SOU RCES: Roa d s a nd Pa rc els - King County (2015), Aeria l- King County (2015); Strea m s, Wetla nd s a nd Buffers,L a nd slid e Ha za rd a nd Buffers, a nd Steep Slop es a ndBuffers from Wa tershed Com p a ny (2017). For cartographic purposes only. Note:Note: Underground utility lines are surveyed in thevicinity of poles only. Existing Lake Tradition poles aren'trepresented by new conductors because they are anexisting line, and are being represented due to the polesbeing replaced. 5/7C-16A1 Prop osed Pole Num b er Struc ture Typ e (See Ap p x. A) Construc tion Sc ena rio Key(See Ap p x. B)MATCHLINE SHEET: 2 §¨¦405 Renton Newcastle88!(D!(D&-&-4/1C-18AC1 4/1 C-18BC1 #*#*0423059069 0423059142 3345100450K i n g C o u n t yC i t y o f R e n t o n SITE PLAN Da te: 1/18/2018Path: G:\Projects\Washington\Puget_Sound_Energy_007022\EnergizeEastsideMapbook_10059878\7.2_WP\Map_Docs\Renton\Landuse_CUP\Version_N\PSE_Renton_CUP.mxdPro jec t Co rrido r &-Pro p o sed Po le Lo c a tio n !(D Existing Po le Lo c a tio n–To Be Rem o ved T ra nsm issio n Line - Pro p o sed T ra nsm issio n Line - Existing #*Po tentia l Stringing Site Rec o m m ended Ac c ess- Pro p o sed Po le U ndergro und Po wer U tility Line U ndergro und W a ter & W a stewa ter U tility Line Pa rc el City Jurisdic tio n Bo unda ry Strea m W etla nd W etla nd o r Strea m Buffer La ndslide Ha za rd La ndslide Ha za rd 50ft Buffer Steep Slo p e Steep Slo p e 50ft Buffer Ero sio n Ha za rd I215+00210+00501 831 4/1 SCDE60EAST 072FT /W EST 072FTST A=213+1.0HT =72FT ELE=449.25 400 420 440 460 480 340 360 380 320 500 520 540560 580 600 Pro file View Struc ture Co nduc to r Gro und Line Ma jo r Eleva tio n Grid Ma jo r Sta tio n Grid Mino r Sta tio n Grid Page 2 of 30 BASED ON PSE ENGINEERINGDESIGN REVISION NI02550Feet1 inc h = 50 feet MAP EX T ENT RENTON SOU RCES: Ro a ds a nd Pa rc els - K ing Co unty (2015), Aeria l- K ing Co unty (2015); Strea m s, W etla nds a nd Buffers,La ndslide Ha za rd a nd Buffers, a nd Steep Slo p es a ndBuffers fro m W a tershed Co m p a ny (2017). For cartographic purposes only. Note:Note: Underground utility lines are surveyed in thevicinity of poles only. Existing Lake Tradition poles aren'trepresented by new conductors because they are anexisting line, and are being represented due to the polesbeing replaced. 5/7C-16A1 Pro p o sed Po le Num b er Struc ture T yp e (See Ap p x. A) Co nstruc tio n Sc ena rio K ey(See Ap p x. B)MATCHLINE SHEET: 1MATCHLINE SHEET: 3 §¨¦405 Renton Newcastle 888888!(D!(D!(D!(D!(D&-&-&-&-&-3/9C-17AC1 3/9C-17BC1 3/10C-2AC1 3/10C-2BC1 4/1C-18AC1#*S E 1 0 0 T H S T N E 2 4 T H S T 0423059002 0423059069 0423059142 0423059282 0423059313 04280000100428000015 0428000020 0428000290 K i n g C o u n t yCity of RentonSITE PLAN Da te: 1/18/2018Path: G:\Projects\Washington\Puget_Sound_Energy_007022\EnergizeEastsideMapbook_10059878\7.2_WP\Map_Docs\Renton\Landuse_CUP\Version_N\PSE_Renton_CUP.mxdPro jec t Co rrido r &-Pro p o sed Po le Lo c a tio n !(D Existing Po le Lo c a tio n–To Be Rem o ved T ra nsm issio n Line - Pro p o sed T ra nsm issio n Line - Existing #*Po tentia l Stringing Site Rec o m m ended Ac c ess- Pro p o sed Po le U ndergro und Po wer U tility Line U ndergro und W a ter & W a stewa ter U tility Line Pa rc el City Jurisdic tio n Bo unda ry Strea m W etla nd W etla nd o r Strea m Buffer La ndslide Ha za rd La ndslide Ha za rd 50ft Buffer Steep Slo p e Steep Slo p e 50ft Buffer Ero sio n Ha za rd I210+00501 205+00418 3/10SCA15EAST 095FT /W EST 095FTST A=208+1.11HT =95FT ELE=450.50 400 420 440 460 480 380 500 520 540560 580 600 620 640 660 680 Pro file View Struc ture Co nduc to r Gro und Line Ma jo r Eleva tio n Grid Ma jo r Sta tio n Grid Mino r Sta tio n Grid Page 3 of 30 BASED ON PSE ENGINEERINGDESIGN REVISION NI02550Feet1 inc h = 50 feet MAP EX T ENT RENTON SOU RCES: Ro a ds a nd Pa rc els - K ing Co unty (2015), Aeria l- K ing Co unty (2015); Strea m s, W etla nds a nd Buffers,La ndslide Ha za rd a nd Buffers, a nd Steep Slo p es a ndBuffers fro m W a tershed Co m p a ny (2017). For cartographic purposes only. Note:Note: Underground utility lines are surveyed in thevicinity of poles only. Existing Lake Tradition poles aren'trepresented by new conductors because they are anexisting line, and are being represented due to the polesbeing replaced. 5/7C-16A1 Pro p o sed Po le Num b er Struc ture T yp e (See Ap p x. A) Co nstruc tio n Sc ena rio K ey(See Ap p x. B)MATCHLINE SHEET: 2MATCHLINE SHEET: 43/9SCHDE5EAST 050FT /W EST 050FTST A=203+76.41HT =50FT ELE=440.87 §¨¦405 Renton Newcastle 888!(D!(D!(D!(D&-&-&-&-&-3/7C-1A1 3/8C-17AC1 3/8C-17BC1 3/9C-17AC1 3/9C-17BC1 S E 1 0 0 T H S T 126TH AVE SE0423059002 04280000200428000025 0428000095 04280000950428000100 0428000105 0428000155 0428000160 0428000165 04280001900428000195 04280002000428000205 0428000210 0428000290 0428000290 0428100530 3449820290 3449820300 3449820310 3449820320 K i n g C o u n t yC i t y o f R e n t o n SITE PLAN Da te: 1/18/2018Path: G:\Projects\Washington\Puget_Sound_Energy_007022\EnergizeEastsideMapbook_10059878\7.2_WP\Map_Docs\Renton\Landuse_CUP\Version_N\PSE_Renton_CUP.mxdPro jec t Co rrido r &-Pro p o sed Po le Lo c a tio n !(D Existing Po le Lo c a tio n–To Be Rem o ved T ra nsm issio n Line - Pro p o sed T ra nsm issio n Line - Existing #*Po tentia l Stringing Site Rec o m m ended Ac c ess- Pro p o sed Po le U ndergro und Po wer U tility Line U ndergro und W a ter & W a stewa ter U tility Line Pa rc el City Jurisdic tio n Bo unda ry Strea m W etla nd W etla nd o r Strea m Buffer La ndslide Ha za rd La ndslide Ha za rd 50ft Buffer Steep Slo p e Steep Slo p e 50ft Buffer Ero sio n Ha za rd I200+00361239 3/9SCHDE5EAST 050FT /W EST 050FTST A=203+76.41HT =50FT ELE=440.87 3/8SCHDE5STA=200+3.60EAST 050FT /W EST 050FTELE = 438.00 3/7DCT 2D90FTST A=197+97.16HT =77FT ELE=444.87 400 420 440 460 480 380 500 520 540560 580 600 620 640 660 Pro file View Struc ture Co nduc to r Gro und Line Ma jo r Eleva tio n Grid Ma jo r Sta tio n Grid Mino r Sta tio n Grid Page 4 of 30 BASED ON PSE ENGINEERINGDESIGN REVISION NI02550Feet1 inc h = 50 feet MAP EX T ENT RENTON SOU RCES: Ro a ds a nd Pa rc els - K ing Co unty (2015), Aeria l- K ing Co unty (2015); Strea m s, W etla nds a nd Buffers,La ndslide Ha za rd a nd Buffers, a nd Steep Slo p es a ndBuffers fro m W a tershed Co m p a ny (2017). For cartographic purposes only. Note:Note: Underground utility lines are surveyed in thevicinity of poles only. Existing Lake Tradition poles aren'trepresented by new conductors because they are anexisting line, and are being represented due to the polesbeing replaced. 5/7C-16A1 Pro p o sed Po le Num b er Struc ture T yp e (See Ap p x. A) Co nstruc tio n Sc ena rio K ey(See Ap p x. B)MATCHLINE SHEET: 3MATCHLINE SHEET: 5 §¨¦405 Renton Newcastle8!(D!(D&-3/6C-1A1 NE21STS T NEW P O RT CTNE OLYMPIAAVENE0423059035 0428100530 0428100540 0428100545 3449820140 3449820150 3449820160 3449820170 3449820190 3449820200 3449820210 3449820220 34498202303449820240 3449820250 3449820260 3449820270 3449820280 3449820460 3449820470 SITE PLAN Da te: 1/18/2018Path: G:\Projects\Washington\Puget_Sound_Energy_007022\EnergizeEastsideMapbook_10059878\7.2_WP\Map_Docs\Renton\Landuse_CUP\Version_N\PSE_Renton_CUP.mxdPro jec t Co rrido r &-Pro p o sed Po le Lo c a tio n !(D Existing Po le Lo c a tio n–To Be Rem o ved T ra nsm issio n Line - Pro p o sed T ra nsm issio n Line - Existing #*Po tentia l Stringing Site Rec o m m ended Ac c ess- Pro p o sed Po le U ndergro und Po wer U tility Line U ndergro und W a ter & W a stewa ter U tility Line Pa rc el City Jurisdic tio n Bo unda ry Strea m W etla nd W etla nd o r Strea m Buffer La ndslide Ha za rd La ndslide Ha za rd 50ft Buffer Steep Slo p e Steep Slo p e 50ft Buffer Ero sio n Ha za rd I 195+00190+00615 3/6DCT 2D95FTST A=191+72.13HT =80FT ELE=401.63 852 400 420 440 460 480 380 500 520 540560 580600 400 420 440 460 480 340 360 380 320300 500 520 540560 580600 Pro file View Struc ture Co nduc to r Gro und Line Ma jo r Eleva tio n Grid Ma jo r Sta tio n Grid Mino r Sta tio n Grid Page 5 of 30 BASED ON PSE ENGINEERINGDESIGN REVISION NI02550Feet1 inc h = 50 feet MAP EX T ENT RENTON SOU RCES: Ro a ds a nd Pa rc els - K ing Co unty (2015), Aeria l- K ing Co unty (2015); Strea m s, W etla nds a nd Buffers,La ndslide Ha za rd a nd Buffers, a nd Steep Slo p es a ndBuffers fro m W a tershed Co m p a ny (2017). For cartographic purposes only. Note:Note: Underground utility lines are surveyed in thevicinity of poles only. Existing Lake Tradition poles aren'trepresented by new conductors because they are anexisting line, and are being represented due to the polesbeing replaced. 5/7C-16A1 Pro p o sed Po le Num b er Struc ture T yp e (See Ap p x. A) Co nstruc tio n Sc ena rio K ey(See Ap p x. B)MATCHLINE SHEET: 4MATCHLINE SHEET: 6340 360 320300 §¨¦405 Renton Newcastle 8 8 !(D!(D&-&-3/5C-18AC1 3/5C-18BC1#*#*MR01(Honey Creek)Type F 0423059035 0423059342 3888320090 SITE PLAN Da te: 1/18/2018Path: G:\Projects\Washington\Puget_Sound_Energy_007022\EnergizeEastsideMapbook_10059878\7.2_WP\Map_Docs\Renton\Landuse_CUP\Version_N\PSE_Renton_CUP.mxdPro jec t Co rrido r &-Pro p o sed Po le Lo c a tio n !(D Existing Po le Lo c a tio n–To Be Rem o ved T ra nsm issio n Line - Pro p o sed T ra nsm issio n Line - Existing #*Po tentia l Stringing Site Rec o m m ended Ac c ess- Pro p o sed Po le U ndergro und Po wer U tility Line U ndergro und W a ter & W a stewa ter U tility Line Pa rc el City Jurisdic tio n Bo unda ry Strea m W etla nd W etla nd o r Strea m Buffer La ndslide Ha za rd La ndslide Ha za rd 50ft Buffer Steep Slo p e Steep Slo p e 50ft Buffer Ero sio n Ha za rd I185+00852 3/5SCDE60EAST 090FT /W EST 090FTST A=183+20.03HT =90FT ELE=403.89 400 420 440 460 480 340 360 380 320300 280 260 500520 240 400 420 440 460 480 340 360380 320 300 280 260 500 520 240 Pro file View Struc ture Co nduc to r Gro und Line Ma jo r Eleva tio n Grid Ma jo r Sta tio n Grid Mino r Sta tio n Grid Page 6 of 30 BASED ON PSE ENGINEERINGDESIGN REVISION NI02550Feet1 inc h = 50 feet MAP EX T ENT RENTON SOU RCES: Ro a ds a nd Pa rc els - K ing Co unty (2015), Aeria l- K ing Co unty (2015); Strea m s, W etla nds a nd Buffers,La ndslide Ha za rd a nd Buffers, a nd Steep Slo p es a ndBuffers fro m W a tershed Co m p a ny (2017). For cartographic purposes only. Note:Note: Underground utility lines are surveyed in thevicinity of poles only. Existing Lake Tradition poles aren'trepresented by new conductors because they are anexisting line, and are being represented due to the polesbeing replaced. 5/7C-16A1 Pro p o sed Po le Num b er Struc ture T yp e (See Ap p x. A) Co nstruc tio n Sc ena rio K ey(See Ap p x. B)MATCHLINE SHEET: 5MATCHLINE SHEET: 7 §¨¦405 Renton Newcastle 8 8 !(D!(D&-3/4C-1A1 NE 15 T H ST0423059023 0423059097 0423059269 0423059342 SITE PLAN Da te: 1/18/2018Path: G:\Projects\Washington\Puget_Sound_Energy_007022\EnergizeEastsideMapbook_10059878\7.2_WP\Map_Docs\Renton\Landuse_CUP\Version_N\PSE_Renton_CUP.mxdPro jec t Co rrido r &-Pro p o sed Po le Lo c a tio n !(D Existing Po le Lo c a tio n–To Be Rem o ved T ra nsm issio n Line - Pro p o sed T ra nsm issio n Line - Existing #*Po tentia l Stringing Site Rec o m m ended Ac c ess- Pro p o sed Po le U ndergro und Po wer U tility Line U ndergro und W a ter & W a stewa ter U tility Line Pa rc el City Jurisdic tio n Bo unda ry Strea m W etla nd W etla nd o r Strea m Buffer La ndslide Ha za rd La ndslide Ha za rd 50ft Buffer Steep Slo p e Steep Slo p e 50ft Buffer Ero sio n Ha za rd I180+00175+00672 3/4SCDE60105FTST A=176+67.86HT =91FT ELE=397.38 400 420 440 460 480 340 360 380 320300 500 520 540560 580600 400 420 440 460 480 340 360 380 320300 500 520 540560 580 600 Pro file View Struc ture Co nduc to r Gro und Line Ma jo r Eleva tio n Grid Ma jo r Sta tio n Grid Mino r Sta tio n Grid Page 7 of 30 BASED ON PSE ENGINEERINGDESIGN REVISION NI02550Feet1 inc h = 50 feet MAP EX T ENT RENTON SOU RCES: Ro a ds a nd Pa rc els - K ing Co unty (2015), Aeria l- K ing Co unty (2015); Strea m s, W etla nds a nd Buffers,La ndslide Ha za rd a nd Buffers, a nd Steep Slo p es a ndBuffers fro m W a tershed Co m p a ny (2017). For cartographic purposes only. Note:Note: Underground utility lines are surveyed in thevicinity of poles only. Existing Lake Tradition poles aren'trepresented by new conductors because they are anexisting line, and are being represented due to the polesbeing replaced. 5/7C-16A1 Pro p o sed Po le Num b er Struc ture T yp e (See Ap p x. A) Co nstruc tio n Sc ena rio K ey(See Ap p x. B)MATCHLINE SHEET: 6MATCHLINE SHEET: 88 §¨¦405 Renton Newcastle8888!(D!(D!(D!(D&-&-3/2C-1C1 3/3C-1C1 SR 9 0 0 0423059080 04230590970423059127 0423059145 0423059153 0423059269 SITE PLAN Da te: 1/18/2018Path: G:\Projects\Washington\Puget_Sound_Energy_007022\EnergizeEastsideMapbook_10059878\7.2_WP\Map_Docs\Renton\Landuse_CUP\Version_N\PSE_Renton_CUP.mxdPro jec t Co rrido r &-Pro p o sed Po le Lo c a tio n !(D Existing Po le Lo c a tio n–To Be Rem o ved T ra nsm issio n Line - Pro p o sed T ra nsm issio n Line - Existing #*Po tentia l Stringing Site Rec o m m ended Ac c ess- Pro p o sed Po le U ndergro und Po wer U tility Line U ndergro und W a ter & W a stewa ter U tility Line Pa rc el City Jurisdic tio n Bo unda ry Strea m W etla nd W etla nd o r Strea m Buffer La ndslide Ha za rd La ndslide Ha za rd 50ft Buffer Steep Slo p e Steep Slo p e 50ft Buffer Ero sio n Ha za rd I170+00536401 3/3DCA15100FTST A=171+22.20HT =100FT ELE=389.41 3/2DCA15090FTST A=167+21.64HT =90FT ELE=391.71 400 420 440 460 480 340 360 380 320300 500 520 540560 580 600 400 420 440 460 480 340 360 380 320300 500 520 540 560 580 600 Pro file View Struc ture Co nduc to r Gro und Line Ma jo r Eleva tio n Grid Ma jo r Sta tio n Grid Mino r Sta tio n Grid Page 8 of 30 BASED ON PSE ENGINEERINGDESIGN REVISION NI02550Feet1 inc h = 50 feet MAP EX T ENT RENTON SOU RCES: Ro a ds a nd Pa rc els - K ing Co unty (2015), Aeria l- K ing Co unty (2015); Strea m s, W etla nds a nd Buffers,La ndslide Ha za rd a nd Buffers, a nd Steep Slo p es a ndBuffers fro m W a tershed Co m p a ny (2017). For cartographic purposes only. Note:Note: Underground utility lines are surveyed in thevicinity of poles only. Existing Lake Tradition poles aren'trepresented by new conductors because they are anexisting line, and are being represented due to the polesbeing replaced. 5/7C-16A1 Pro p o sed Po le Num b er Struc ture T yp e (See Ap p x. A) Co nstruc tio n Sc ena rio K ey(See Ap p x. B)MATCHLINE SHEET: 7MATCHLINE SHEET: 9 §¨¦405 Renton Newcastle8!(D!(D&-3/1C-1A1 NE 12TH STLYNNWOOD AVE NE MONROE AVE NE 0423059096 0423059127 0423059169 0423059182 0423059316 0423059317 77361000057736100009773610001077361000157736100016 7801300000 Da te: 1/18/2018Path: G:\Projects\Washington\Puget_Sound_Energy_007022\EnergizeEastsideMapbook_10059878\7.2_WP\Map_Docs\Renton\Landuse_CUP\Version_N\PSE_Renton_CUP.mxdPro jec t Co rrido r &-Pro p o sed Po le Lo c a tio n !(D Existing Po le Lo c a tio n–To Be Rem o ved T ra nsm issio n Line - Pro p o sed T ra nsm issio n Line - Existing #*Po tentia l Stringing Site Rec o m m ended Ac c ess- Pro p o sed Po le U ndergro und Po wer U tility Line U ndergro und W a ter & W a stewa ter U tility Line Pa rc el City Jurisdic tio n Bo unda ry Strea m W etla nd W etla nd o r Strea m Buffer La ndslide Ha za rd La ndslide Ha za rd 50ft Buffer Steep Slo p e Steep Slo p e 50ft Buffer Ero sio n Ha za rd I 165+00160+00564458 3/1DCT 2125FTST A=161+67.96HT =109FT ELE=383.42 400 420 440 460 480 340 360 380 320 SITE PLAN 500 520 540 560 580 600 400 420 440 460 480 340 360 380 320 500 520 540560 580 600 Pro file View Struc ture Co nduc to r Gro und Line Ma jo r Eleva tio n Grid Ma jo r Sta tio n Grid Mino r Sta tio n Grid Page 9 of 30 BASED ON PSE ENGINEERINGDESIGN REVISION NI02550Feet1 inc h = 50 feet MAP EX T ENT RENTON SOU RCES: Ro a ds a nd Pa rc els - K ing Co unty (2015), Aeria l- K ing Co unty (2015); Strea m s, W etla nds a nd Buffers,La ndslide Ha za rd a nd Buffers, a nd Steep Slo p es a ndBuffers fro m W a tershed Co m p a ny (2017). For cartographic purposes only. Note:Note: Underground utility lines are surveyed in thevicinity of poles only. Existing Lake Tradition poles aren'trepresented by new conductors because they are anexisting line, and are being represented due to the polesbeing replaced. 5/7C-16A1 Pro p o sed Po le Num b er Struc ture T yp e (See Ap p x. A) Co nstruc tio n Sc ena rio K ey(See Ap p x. B)MATCHLINE SHEET: 8MATCHLINE SHEET: 10 §¨¦405 Renton Newcastle 8 8 !(D!(D!(D!(D&-&-2/9C-1A1 2/10C-1A1#*MONROE AVE NE LYNNWOOD AVE NE 28548000302854800035285480004028548000452854800050 2854800055 28548000602854800065 285480007028548000752854800080 7227900028 7227900030 7801300000 SITE PLAN Da te: 1/18/2018Path: G:\Projects\Washington\Puget_Sound_Energy_007022\EnergizeEastsideMapbook_10059878\7.2_WP\Map_Docs\Renton\Landuse_CUP\Version_N\PSE_Renton_CUP.mxdProjec t Corrid or &-Prop osed Pole L oc a tion !(D Existing Pole L oc a tion–To Be Rem oved Tra nsm ission L ine - Prop osed Tra nsm ission L ine - Existing #*Potentia l Stringing Site Rec om m end ed Ac c ess- Prop osed Pole U nd erground Power U tility L ine U nd erground Wa ter & Wa stewa ter U tility L ine Pa rc el City Jurisd ic tion Bound a ry Strea m Wetla nd Wetla nd or Strea m Buffer L a nd slid e Ha za rd L a nd slid e Ha za rd 50ft Buffer Steep Slop e Steep Slop e 50ft Buffer Erosion Ha za rd I155+00525 2/10DCT2100FTSTA=156+96.08HT=86FT EL E=390.15 2/9DCT2100FTSTA=151+75.53HT=86FT EL E=397.22 400 420 440 460 480 340 360 380 320 500 520 540560 580 600620 400 420 440 460 480 340 360 380 320 500 520540 560 580 600620 Profile V iew Struc ture Cond uc tor Ground L ine Ma jor Eleva tion Grid Ma jor Sta tion Grid Minor Sta tion Grid Page 10 of 30 BASED ON PSE ENGINEERINGDESIGN REVISION NI02550Feet1 inc h = 50 feet MAP EXTENT RENTON SOU RCES: Roa d s a nd Pa rc els - King County (2015), Aeria l- King County (2015); Strea m s, Wetla nd s a nd Buffers,L a nd slid e Ha za rd a nd Buffers, a nd Steep Slop es a ndBuffers from Wa tershed Com p a ny (2017). For cartographic purposes only. Note:Note: Underground utility lines are surveyed in thevicinity of poles only. Existing Lake Tradition poles aren'trepresented by new conductors because they are anexisting line, and are being represented due to the polesbeing replaced. 5/7C-16A1 Prop osed Pole Num b er Struc ture Typ e (See Ap p x. A) Construc tion Sc ena rio Key(See Ap p x. B)MATCHLINE SHEET: 9MATCHLINE SHEET: 11 §¨¦405 Renton Newcastle 8 !(D!(D&-2/8C-1A1NE10THST MONROE AVE NE 2854800080 2854800085285480009028548000952854800100 2854800105 2854800110 2854800115 2854800120 2854800125 7227900028 7809000005780900001078090000157809000020 7809200005 780920001078092000157809200020 Da te: 1/18/2018Path: G:\Projects\Washington\Puget_Sound_Energy_007022\EnergizeEastsideMapbook_10059878\7.2_WP\Map_Docs\Renton\Landuse_CUP\Version_N\PSE_Renton_CUP.mxd&-Pro p o sed Po le Lo c a tio n !(D Existing Po le Lo c a tio n–To Be Rem o ved T ra nsm issio n Line - Pro p o sed T ra nsm issio n Line - Existing #*Po tentia l Stringing Site Rec o m m ended Ac c ess- Pro p o sed Po le U ndergro und Po wer U tility Line U ndergro und W a ter & W a stewa ter U tility Line Pa rc el City Jurisdic tio n Bo unda ry Strea m W etla nd W etla nd o r Strea m Buffer La ndslide Ha za rd La ndslide Ha za rd 50ft Buffer Steep Slo p e Steep Slo p e 50ft Buffer Ero sio n Ha za rd I 150+00145+00533542 2/8DCT 2110FTST A=146+42.17HT =95FT ELE=393.88 400 420 440 460 480 340 360380 SITE PLAN 500 520540 560 580 600620 400 420 440 460 480 340 360 380 500 520 540560 580 600 620 Pro file View Struc ture Co nduc to r Gro und Line Ma jo r Eleva tio n Grid Ma jo r Sta tio n Grid Mino r Sta tio n Grid Page 11 of 30 BASED ON PSE ENGINEERINGDESIGN REVISION NI02550Feet1 inc h = 50 feet MAP EX T ENT RENTON SOU RCES: Ro a ds a nd Pa rc els - K ing Co unty (2015), Aeria l- K ing Co unty (2015); Strea m s, W etla nds a nd Buffers,La ndslide Ha za rd a nd Buffers, a nd Steep Slo p es a ndBuffers fro m W a tershed Co m p a ny (2017). For cartographic purposes only. Note:Note: Underground utility lines are surveyed in thevicinity of poles only. Existing Lake Tradition poles aren'trepresented by new conductors because they are anexisting line, and are being represented due to the polesbeing replaced. 5/7C-16A1 Pro p o sed Po le Num b er Struc ture T yp e (See Ap p x. A) Co nstruc tio n Sc ena rio K ey(See Ap p x. B)MATCHLINE SHEET: 10MATCHLINE SHEET: 12Projec t Corr dior §¨¦405 Renton Newcastle!(D!(D&-2/7C-1A1 NE 8TH STNE 7TH CTMONROE AVE NE 7809000025780900003078090000357809000040780900004578090000507809000055 78092000207809200025780920003078092000357809200040780920004578092000507809200055780920006078092000657809200070 7809200075 SITE PLAN Da te: 1/18/2018Path: G:\Projects\Washington\Puget_Sound_Energy_007022\EnergizeEastsideMapbook_10059878\7.2_WP\Map_Docs\Renton\Landuse_CUP\Version_N\PSE_Renton_CUP.mxdPro jec t Co rrido r &-Pro p o sed Po le Lo c a tio n !(D Existing Po le Lo c a tio n–To Be Rem o ved T ra nsm issio n Line - Pro p o sed T ra nsm issio n Line - Existing #*Po tentia l Stringing Site Rec o m m ended Ac c ess- Pro p o sed Po le U ndergro und Po wer U tility Line U ndergro und W a ter & W a stewa ter U tility Line Pa rc el City Jurisdic tio n Bo unda ry Strea m W etla nd W etla nd o r Strea m Buffer La ndslide Ha za rd La ndslide Ha za rd 50ft Buffer Steep Slo p e Steep Slo p e 50ft Buffer Ero sio n Ha za rd I140+00615 542 2/7DCT 2110FTST A=140+98.42HT =95FT ELE=394.84 400 420 440 460 480 340 360 380 500 520 540560 580 600 620 400 420 440 460 480 340 360 380 500 520 540 560 580 600 620 Pro file View Struc ture Co nduc to r Gro und Line Ma jo r Eleva tio n Grid Ma jo r Sta tio n Grid Mino r Sta tio n Grid Page 12 of 30 BASED ON PSE ENGINEERINGDESIGN REVISION NI02550Feet1 inc h = 50 feet MAP EX T ENT RENTON SOU RCES: Ro a ds a nd Pa rc els - K ing Co unty (2015), Aeria l- K ing Co unty (2015); Strea m s, W etla nds a nd Buffers,La ndslide Ha za rd a nd Buffers, a nd Steep Slo p es a ndBuffers fro m W a tershed Co m p a ny (2017). For cartographic purposes only. Note:Note: Underground utility lines are surveyed in thevicinity of poles only. Existing Lake Tradition poles aren'trepresented by new conductors because they are anexisting line, and are being represented due to the polesbeing replaced. 5/7C-16A1 Pro p o sed Po le Num b er Struc ture T yp e (See Ap p x. A) Co nstruc tio n Sc ena rio K ey(See Ap p x. B)MATCHLINE SHEET: 11MATCHLINE SHEET: 13 §¨¦405 Renton Newcastle 8 8 888!(D!(D!(D!(D&-&-2/5C-1A1 2/6C-1A1NE 7TH STNE 7TH PLMONROE AVE NE 7227800425 7227800426 7809200080 SITE PLAN Da te: 1/18/2018Path: G:\Projects\Washington\Puget_Sound_Energy_007022\EnergizeEastsideMapbook_10059878\7.2_WP\Map_Docs\Renton\Landuse_CUP\Version_N\PSE_Renton_CUP.mxdProjec t Corrid or &-Prop osed Pole L oc a tion !(D Existing Pole L oc a tion–To Be Rem oved Tra nsm ission L ine - Prop osed Tra nsm ission L ine - Existing #*Potentia l Stringing Site Rec om m end ed Ac c ess- Prop osed Pole U nd erground Power U tility L ine U nd erground Wa ter & Wa stewa ter U tility L ine Pa rc el City Jurisd ic tion Bound a ry Strea m Wetla nd Wetla nd or Strea m Buffer L a nd slid e Ha za rd L a nd slid e Ha za rd 50ft Buffer Steep Slop e Steep Slop e 50ft Buffer Erosion Ha za rd I 135+00130+00601 2/6DCT2115FTSTA=134+85.06HT=100FT EL E=386.81 2/5DCT2100FTSTA=128+84.48HT=86FT EL E=378.68 400 420 440 460 480 340 360 380 320 500 520 540 560 580 400 420 440 460 480 340 360380 320 300 500 520 540 560 580 Profile V iew Struc ture Cond uc tor Ground L ine Ma jor Eleva tion Grid Ma jor Sta tion Grid Minor Sta tion Grid Page 13 of 30 BASED ON PSE ENGINEERINGDESIGN REVISION NI02550Feet1 inc h = 50 feet MAP EXTENT RENTON SOU RCES: Roa d s a nd Pa rc els - King County (2015), Aeria l- King County (2015); Strea m s, Wetla nd s a nd Buffers,L a nd slid e Ha za rd a nd Buffers, a nd Steep Slop es a ndBuffers from Wa tershed Com p a ny (2017). For cartographic purposes only. Note:Note: Underground utility lines are surveyed in thevicinity of poles only. Existing Lake Tradition poles aren'trepresented by new conductors because they are anexisting line, and are being represented due to the polesbeing replaced. 5/7C-16A1 Prop osed Pole Num b er Struc ture Typ e (See Ap p x. A) Construc tion Sc ena rio Key(See Ap p x. B)MATCHLINE SHEET: 12MATCHLINE SHEET: 14300 §¨¦405 Renton Newcastle8!(D!(D&-2/4C-1C1 NE 6TH PLNE 6TH STRENTON TECH ACRD MONROE AVE NE 7227800425 SITE PLAN Da te: 1/18/2018Path: G:\Projects\Washington\Puget_Sound_Energy_007022\EnergizeEastsideMapbook_10059878\7.2_WP\Map_Docs\Renton\Landuse_CUP\Version_N\PSE_Renton_CUP.mxdPro jec t Co rrido r &-Pro p o sed Po le Lo c a tio n !(D Existing Po le Lo c a tio n–To Be Rem o ved T ra nsm issio n Line - Pro p o sed T ra nsm issio n Line - Existing #*Po tentia l Stringing Site Rec o m m ended Ac c ess- Pro p o sed Po le U ndergro und Po wer U tility Line U ndergro und W a ter & W a stewa ter U tility Line Pa rc el City Jurisdic tio n Bo unda ry Strea m W etla nd W etla nd o r Strea m Buffer La ndslide Ha za rd La ndslide Ha za rd 50ft Buffer Steep Slo p e Steep Slo p e 50ft Buffer Ero sio n Ha za rd I125+00120+00598594 2/4DCA15085FTST A=122+86.01HT =85FT ELE=378.32 400 420 440 460 480 340 360380 320 300 280 500 520 540 560 Pro file View Struc ture Co nduc to r Gro und Line Ma jo r Eleva tio n Grid Ma jo r Sta tio n Grid Mino r Sta tio n Grid Page 14 of 30 BASED ON PSE ENGINEERINGDESIGN REVISION NI02550Feet1 inc h = 50 feet MAP EX T ENT RENTON SOU RCES: Ro a ds a nd Pa rc els - K ing Co unty (2015), Aeria l- K ing Co unty (2015); Strea m s, W etla nds a nd Buffers,La ndslide Ha za rd a nd Buffers, a nd Steep Slo p es a ndBuffers fro m W a tershed Co m p a ny (2017). For cartographic purposes only. Note:Note: Underground utility lines are surveyed in thevicinity of poles only. Existing Lake Tradition poles aren'trepresented by new conductors because they are anexisting line, and are being represented due to the polesbeing replaced. 5/7C-16A1 Pro p o sed Po le Num b er Struc ture T yp e (See Ap p x. A) Co nstruc tio n Sc ena rio K ey(See Ap p x. B)MATCHLINE SHEET: 13MATCHLINE SHEET: 15 §¨¦405 Renton Newcastle88!(D!(D&-2/3C-1A1 M O NR O E A V E N E R E N T O N T E C H A C RD72278004257227800500 SITE PLAN Da te: 1/18/2018Path: G:\Projects\Washington\Puget_Sound_Energy_007022\EnergizeEastsideMapbook_10059878\7.2_WP\Map_Docs\Renton\Landuse_CUP\Version_N\PSE_Renton_CUP.mxdPro jec t Co rrido r &-Pro p o sed Po le Lo c a tio n !(D Existing Po le Lo c a tio n–To Be Rem o ved T ra nsm issio n Line - Pro p o sed T ra nsm issio n Line - Existing #*Po tentia l Stringing Site Rec o m m ended Ac c ess- Pro p o sed Po le U ndergro und Po wer U tility Line U ndergro und W a ter & W a stewa ter U tility Line Pa rc el City Jurisdic tio n Bo unda ry Strea m W etla nd W etla nd o r Strea m Buffer La ndslide Ha za rd La ndslide Ha za rd 50ft Buffer Steep Slo p e Steep Slo p e 50ft Buffer Ero sio n Ha za rd I 120+00594 115+00652 2/3DCT 2110FTST A=116+81.81HT =95FT ELE=341.54 400 420 440 460 480 340 360380 320 300 280 500 520 540 560 Pro file View Struc ture Co nduc to r Gro und Line Ma jo r Eleva tio n Grid Ma jo r Sta tio n Grid Mino r Sta tio n Grid Page 15 of 30 BASED ON PSE ENGINEERINGDESIGN REVISION NI02550Feet1 inc h = 50 feet MAP EX T ENT RENTON SOU RCES: Ro a ds a nd Pa rc els - K ing Co unty (2015), Aeria l- K ing Co unty (2015); Strea m s, W etla nds a nd Buffers,La ndslide Ha za rd a nd Buffers, a nd Steep Slo p es a ndBuffers fro m W a tershed Co m p a ny (2017). For cartographic purposes only. Note:Note: Underground utility lines are surveyed in thevicinity of poles only. Existing Lake Tradition poles aren'trepresented by new conductors because they are anexisting line, and are being represented due to the polesbeing replaced. 5/7C-16A1 Pro p o sed Po le Num b er Struc ture T yp e (See Ap p x. A) Co nstruc tio n Sc ena rio K ey(See Ap p x. B)MATCHLINE SHEET: 14MATCHLINE SHEET: 16 §¨¦405 Renton Newcastle88!(D!(D!(D!(D&-&-&-2/1C-18AC1 2/1C-18BC1 2/2C-1C1#*NE 4TH STRENTON TECH ACRD1623059058 1623059059 1623059111 1623059112 7227800500 SITE PLAN Da te: 1/18/2018Path: G:\Projects\Washington\Puget_Sound_Energy_007022\EnergizeEastsideMapbook_10059878\7.2_WP\Map_Docs\Renton\Landuse_CUP\Version_N\PSE_Renton_CUP.mxdPro jec t Co rrido r &-Pro p o sed Po le Lo c a tio n !(D Existing Po le Lo c a tio n–To Be Rem o ved T ra nsm issio n Line - Pro p o sed T ra nsm issio n Line - Existing #*Po tentia l Stringing Site Rec o m m ended Ac c ess- Pro p o sed Po le U ndergro und Po wer U tility Line U ndergro und W a ter & W a stewa ter U tility Line Pa rc el City Jurisdic tio n Bo unda ry Strea m W etla nd W etla nd o r Strea m Buffer La ndslide Ha za rd La ndslide Ha za rd 50ft Buffer Steep Slo p e Steep Slo p e 50ft Buffer Ero sio n Ha za rd I110+00281 2/2DCA15D115FTST A=110+39.98HT =115FT ELE=340.44 2/1SCDE30EAST 100FT /W EST 100FTST A=107+58.76HT =100FT ELE=339.96 105+00400 420 440 460 480 340 360380 320 300 280 500 520 540 260 400 420 440 460 480 340 360 380 320 300 280 260 500 520 540 Pro file View Struc ture Co nduc to r Gro und Line Ma jo r Eleva tio n Grid Ma jo r Sta tio n Grid Mino r Sta tio n Grid Page 16 of 30 BASED ON PSE ENGINEERINGDESIGN REVISION NI02550Feet1 inc h = 50 feet MAP EX T ENT RENTON SOU RCES: Ro a ds a nd Pa rc els - K ing Co unty (2015), Aeria l- K ing Co unty (2015); Strea m s, W etla nds a nd Buffers,La ndslide Ha za rd a nd Buffers, a nd Steep Slo p es a ndBuffers fro m W a tershed Co m p a ny (2017). For cartographic purposes only. Note:Note: Underground utility lines are surveyed in thevicinity of poles only. Existing Lake Tradition poles aren'trepresented by new conductors because they are anexisting line, and are being represented due to the polesbeing replaced. 5/7C-16A1 Pro p o sed Po le Num b er Struc ture T yp e (See Ap p x. A) Co nstruc tio n Sc ena rio K ey(See Ap p x. B)MATCHLINE SHEET: 15MATCHLINE SHEET: 17 §¨¦405 Renton Newcastle!(D!(D&-1/7C-1A1 1434000010 1434000012 1434000020 1623059059 SITE PLAN Da te: 1/18/2018Path: G:\Projects\Washington\Puget_Sound_Energy_007022\EnergizeEastsideMapbook_10059878\7.2_WP\Map_Docs\Renton\Landuse_CUP\Version_N\PSE_Renton_CUP.mxdProjec t Corrid or &-Prop osed Pole L oc a tion !(D Existing Pole L oc a tion–To Be Rem oved Tra nsm ission L ine - Prop osed Tra nsm ission L ine - Existing #*Potentia l Stringing Site Rec om m end ed Ac c ess- Prop osed Pole U nd erground Power U tility L ine U nd erground Wa ter & Wa stewa ter U tility L ine Pa rc el City Jurisd ic tion Bound a ry Strea m Wetla nd Wetla nd or Strea m Buffer L a nd slid e Ha za rd L a nd slid e Ha za rd 50ft Buffer Steep Slop e Steep Slop e 50ft Buffer Erosion Ha za rd I 105+00100+00755 1/7DCT2D105FTSTA=100+3.83HT=91FT EL E=331.93 400 420 440 460 480 340 360380 320 300 280 260 500 520 540 Profile V iew Struc ture Cond uc tor Ground L ine Ma jor Eleva tion Grid Ma jor Sta tion Grid Minor Sta tion Grid Page 17 of 30 BASED ON PSE ENGINEERINGDESIGN REVISION NI02550Feet1 inc h = 50 feet MAP EXTENT RENTON SOU RCES: Roa d s a nd Pa rc els - King County (2015), Aeria l- King County (2015); Strea m s, Wetla nd s a nd Buffers,L a nd slid e Ha za rd a nd Buffers, a nd Steep Slop es a ndBuffers from Wa tershed Com p a ny (2017). For cartographic purposes only. Note:Note: Underground utility lines are surveyed in thevicinity of poles only. Existing Lake Tradition poles aren'trepresented by new conductors because they are anexisting line, and are being represented due to the polesbeing replaced. 5/7C-16A1 Prop osed Pole Num b er Struc ture Typ e (See Ap p x. A) Construc tion Sc ena rio Key(See Ap p x. B)MATCHLINE SHEET: 16MATCHLINE SHEET: 18 §¨¦405 Renton Newcastle!(D!(D&-1/6C-1A1 1434000010 1434000020 1623059133 SITE PLAN Da te: 1/18/2018Path: G:\Projects\Washington\Puget_Sound_Energy_007022\EnergizeEastsideMapbook_10059878\7.2_WP\Map_Docs\Renton\Landuse_CUP\Version_N\PSE_Renton_CUP.mxdProjec t Corrid or &-Prop osed Pole L oc a tion !(D Existing Pole L oc a tion–To Be Rem oved Tra nsm ission L ine - Prop osed Tra nsm ission L ine - Existing #*Potentia l Stringing Site Rec om m end ed Ac c ess- Prop osed Pole U nd erground Power U tility L ine U nd erground Wa ter & Wa stewa ter U tility L ine Pa rc el City Jurisd ic tion Bound a ry Strea m Wetla nd Wetla nd or Strea m Buffer L a nd slid e Ha za rd L a nd slid e Ha za rd 50ft Buffer Steep Slop e Steep Slop e 50ft Buffer Erosion Ha za rd I95+0090+00673585 1/6DCT2105FTSTA=93+31.08HT=91FT EL E=337.03 400 420 440 460 480 340 360380 320 300 280 260 500 520 540 400 420 440 460 480 340 360 380 320 300 280 260 500 520 540 300 280 260 Profile V iew Struc ture Cond uc tor Ground L ine Ma jor Eleva tion Grid Ma jor Sta tion Grid Minor Sta tion Grid Page 18 of 30 BASED ON PSE ENGINEERINGDESIGN REVISION NI02550Feet1 inc h = 50 feet MAP EXTENT RENTON SOU RCES: Roa d s a nd Pa rc els - King County (2015), Aeria l- King County (2015); Strea m s, Wetla nd s a nd Buffers,L a nd slid e Ha za rd a nd Buffers, a nd Steep Slop es a ndBuffers from Wa tershed Com p a ny (2017). For cartographic purposes only. Note:Note: Underground utility lines are surveyed in thevicinity of poles only. Existing Lake Tradition poles aren'trepresented by new conductors because they are anexisting line, and are being represented due to the polesbeing replaced. 5/7C-16A1 Prop osed Pole Num b er Struc ture Typ e (See Ap p x. A) Construc tion Sc ena rio Key(See Ap p x. B)MATCHLINE SHEET: 17MATCHLINE SHEET: 19 §¨¦405 Renton Newcastle!(D!(D!(D!(D&-&-1/4C-1A1 1/5C-1A1SE 1ST STINDEX AVE SE1434000010 1434000020 1623059133 4307300550 4307300560 4307300570 4307300580 4307300590 4307300600 4307300610 4307301240 4307310360 4307310370 4307310380 43073103904307310400 4307330340 4307350010 4307350020 4307351230 SITE PLAN Da te: 1/18/2018Path: G:\Projects\Washington\Puget_Sound_Energy_007022\EnergizeEastsideMapbook_10059878\7.2_WP\Map_Docs\Renton\Landuse_CUP\Version_N\PSE_Renton_CUP.mxdPro jec t Co rrido r &-Pro p o sed Po le Lo c a tio n !(D Existing Po le Lo c a tio n–To Be Rem o ved T ra nsm issio n Line - Pro p o sed T ra nsm issio n Line - Existing #*Po tentia l Stringing Site Rec o m m ended Ac c ess- Pro p o sed Po le U ndergro und Po wer U tility Line U ndergro und W a ter & W a stewa ter U tility Line Pa rc el City Jurisdic tio n Bo unda ry Strea m W etla nd W etla nd o r Strea m Buffer La ndslide Ha za rd La ndslide Ha za rd 50ft Buffer Steep Slo p e Steep Slo p e 50ft Buffer Ero sio n Ha za rd I85+00583 585 1/5DCT 2115FTST A=87+86.09HT =100FT ELE=299.67 1/4DCT 2; 130FTST A=81+73.15HT =113FT ELE=259.19 400 420 440 460 340 360 380 320 300 280 260 180 200 220240 300 280 260 Pro file View Struc ture Co nduc to r Gro und Line Ma jo r Eleva tio n Grid Ma jo r Sta tio n Grid Mino r Sta tio n Grid Page 19 of 30 BASED ON PSE ENGINEERINGDESIGN REVISION NI02550Feet1 inc h = 50 feet MAP EX T ENT RENTON SOU RCES: Ro a ds a nd Pa rc els - K ing Co unty (2015), Aeria l- K ing Co unty (2015); Strea m s, W etla nds a nd Buffers,La ndslide Ha za rd a nd Buffers, a nd Steep Slo p es a ndBuffers fro m W a tershed Co m p a ny (2017). For cartographic purposes only. Note:Note: Underground utility lines are surveyed in thevicinity of poles only. Existing Lake Tradition poles aren'trepresented by new conductors because they are anexisting line, and are being represented due to the polesbeing replaced. 5/7C-16A1 Pro p o sed Po le Num b er Struc ture T yp e (See Ap p x. A) Co nstruc tio n Sc ena rio K ey(See Ap p x. B)MATCHLINE SHEET: 18MATCHLINE SHEET: 20 §¨¦405 Renton Newcastle!(D!(D!(D!(D&-&-1/3C-1A1 1/4C-1A1 #*FERNDALEAVESE4307300390 4307300410 4307300420 4307300430 4307300460 4307300470 4307300480 4307300490 4307300500 4307300510 4307300520 4307300530 4307300540 4307301230 4307301240 430732022043073202304307320240430732025043073202604307320270 4307330270 4307330280 4307330290 4307330300 4307330310 4307330320 4307330330 4307330340 SITE PLAN Da te: 1/18/2018Path: G:\Projects\Washington\Puget_Sound_Energy_007022\EnergizeEastsideMapbook_10059878\7.2_WP\Map_Docs\Renton\Landuse_CUP\Version_N\PSE_Renton_CUP.mxdPro jec t Co rrido r &-Pro p o sed Po le Lo c a tio n !(D Existing Po le Lo c a tio n–To Be Rem o ved T ra nsm issio n Line - Pro p o sed T ra nsm issio n Line - Existing #*Po tentia l Stringing Site Rec o m m ended Ac c ess- Pro p o sed Po le U ndergro und Po wer U tility Line U ndergro und W a ter & W a stewa ter U tility Line Pa rc el City Jurisdic tio n Bo unda ry Strea m W etla nd W etla nd o r Strea m Buffer La ndslide Ha za rd La ndslide Ha za rd 50ft Buffer Steep Slo p e Steep Slo p e 50ft Buffer Ero sio n Ha za rd I 1/4DCT 2; 130FTST A=81+73.15HT =113FT ELE=259.19 80+00515548 1/3DCT 2D085FTST A=76+58.13HT =73FT ELE=306.00 75+00400 420 440 460 340 360 380 320 300 280 260 180 200 220 240 Pro file View Struc ture Co nduc to r Gro und Line Ma jo r Eleva tio n Grid Ma jo r Sta tio n Grid Mino r Sta tio n Grid Page 20 of 30 BASED ON PSE ENGINEERINGDESIGN REVISION NI02550Feet1 inc h = 50 feet MAP EX T ENT RENTON SOU RCES: Ro a ds a nd Pa rc els - K ing Co unty (2015), Aeria l- K ing Co unty (2015); Strea m s, W etla nds a nd Buffers,La ndslide Ha za rd a nd Buffers, a nd Steep Slo p es a ndBuffers fro m W a tershed Co m p a ny (2017). For cartographic purposes only. Note:Note: Underground utility lines are surveyed in thevicinity of poles only. Existing Lake Tradition poles aren'trepresented by new conductors because they are anexisting line, and are being represented due to the polesbeing replaced. 5/7C-16A1 Pro p o sed Po le Num b er Struc ture T yp e (See Ap p x. A) Co nstruc tio n Sc ena rio K ey(See Ap p x. B)MATCHLINE SHEET: 19MATCHLINE SHEET: 21 §¨¦405 Renton Newcastle !(D!(D!(D!(D!(D&-&-&-1/2C-18BC1 1/3 C-1 A1 1/2C-18AC1 #*#*FERNDALEAVESESE 3RD ST 3955901130 4307300380 4307300390 4307300400 4307300410 4307300420 4307301220 4307301230 4307301260 4307320250430732026043073202704307320280430732029043073203004307320310 SITE PLAN Da te: 1/18/2018Path: G:\Projects\Washington\Puget_Sound_Energy_007022\EnergizeEastsideMapbook_10059878\7.2_WP\Map_Docs\Renton\Landuse_CUP\Version_N\PSE_Renton_CUP.mxdPro jec t Co rrido r &-Pro p o sed Po le Lo c a tio n !(D Existing Po le Lo c a tio n–To Be Rem o ved T ra nsm issio n Line - Pro p o sed T ra nsm issio n Line - Existing #*Po tentia l Stringing Site Rec o m m ended Ac c ess- Pro p o sed Po le U ndergro und Po wer U tility Line U ndergro und W a ter & W a stewa ter U tility Line Pa rc el City Jurisdic tio n Bo unda ry Strea m W etla nd W etla nd o r Strea m Buffer La ndslide Ha za rd La ndslide Ha za rd 50ft Buffer Steep Slo p e Steep Slo p e 50ft Buffer Ero sio n Ha za rd I 548 75+0070+00410 1/2SCDE60EAST 070FT /W EST 070FTST A=71+9.79HT =70FT ELE=334.50 400 420 440 460 480 340 360 380 320 300 280 260 500 520 240 Pro file View Struc ture Co nduc to r Gro und Line Ma jo r Eleva tio n Grid Ma jo r Sta tio n Grid Mino r Sta tio n Grid Page 21 of 30 BASED ON PSE ENGINEERINGDESIGN REVISION NI02550Feet1 inc h = 50 feet MAP EX T ENT RENTON SOU RCES: Ro a ds a nd Pa rc els - K ing Co unty (2015), Aeria l- K ing Co unty (2015); Strea m s, W etla nds a nd Buffers,La ndslide Ha za rd a nd Buffers, a nd Steep Slo p es a ndBuffers fro m W a tershed Co m p a ny (2017). For cartographic purposes only. Note:Note: Underground utility lines are surveyed in thevicinity of poles only. Existing Lake Tradition poles aren'trepresented by new conductors because they are anexisting line, and are being represented due to the polesbeing replaced. 5/7C-16A1 Pro p o sed Po le Num b er Struc ture T yp e (See Ap p x. A) Co nstruc tio n Sc ena rio K ey(See Ap p x. B)MATCHLINE SHEET: 20MATCHLINE SHEET: 22 §¨¦405 Renton Newcastle!(D!(D&-1/1C-1A1 Not Rated SR 169 1623059035 1623059131 4307301220430730TRCT 430732032043073203304307320340430732TR-W SITE PLAN Da te: 1/18/2018Path: G:\Projects\Washington\Puget_Sound_Energy_007022\EnergizeEastsideMapbook_10059878\7.2_WP\Map_Docs\Renton\Landuse_CUP\Version_N\PSE_Renton_CUP.mxdPro jec t Co rrido r &-Pro p o sed Po le Lo c a tio n !(D Existing Po le Lo c a tio n–To Be Rem o ved T ra nsm issio n Line - Pro p o sed T ra nsm issio n Line - Existing #*Po tentia l Stringing Site Rec o m m ended Ac c ess- Pro p o sed Po le U ndergro und Po wer U tility Line U ndergro und W a ter & W a stewa ter U tility Line Pa rc el City Jurisdic tio n Bo unda ry Strea m W etla nd W etla nd o r Strea m Buffer La ndslide Ha za rd La ndslide Ha za rd 50ft Buffer Steep Slo p e Steep Slo p e 50ft Buffer Ero sio n Ha za rd I 410 65+001,524 1/1DCT 2D090FTST A=66+89.56HT =77FT ELE=333.62 400 340 360 380 320 300 280 260 120 140 160 180 200 220 240 Pro file View Struc ture Co nduc to r Gro und Line Ma jo r Eleva tio n Grid Ma jo r Sta tio n Grid Mino r Sta tio n Grid Page 22 of 30 BASED ON PSE ENGINEERINGDESIGN REVISION NI02550Feet1 inc h = 50 feet MAP EX T ENT RENTON SOU RCES: Ro a ds a nd Pa rc els - K ing Co unty (2015), Aeria l- K ing Co unty (2015); Strea m s, W etla nds a nd Buffers,La ndslide Ha za rd a nd Buffers, a nd Steep Slo p es a ndBuffers fro m W a tershed Co m p a ny (2017). For cartographic purposes only. Note:Note: Underground utility lines are surveyed in thevicinity of poles only. Existing Lake Tradition poles aren'trepresented by new conductors because they are anexisting line, and are being represented due to the polesbeing replaced. 5/7C-16A1 Pro p o sed Po le Num b er Struc ture T yp e (See Ap p x. A) Co nstruc tio n Sc ena rio K ey(See Ap p x. B)MATCHLINE SHEET: 21MATCHLINE SHEET: 23 §¨¦405 Renton Newcastle Cedar River [ND]Type S, Shoreline NR02Type Ns NR02Category II NR03Category III SR 169CEDAR RIVER TRLRIV E R VIE W P A R K WALK1623059012 1623059033 1623059078 162305HYDR SITE PLAN Date : 1/18/2018Path: G:\Projects\Washington\Puget_Sound_Energy_007022\EnergizeEastsideMapbook_10059878\7.2_WP\Map_Docs\Renton\Landuse_CUP\Version_N\PSE_Renton_CUP.mxdProje c t Corrid or &-Propos e d Pole Loc ation !(D Exis ting Pole Loc ation–To Be Re m ove d Trans m is s ion Line - Propos e d Trans m is s ion Line - Exis ting #*Pote ntial Stringing Site Re c om m e nd e d Ac c e s s - Propos e d Pole Und e rground Powe r Utility Line Und e rground W ate r & W as te wate r Utility Line Parc e l City Juris d ic tion Bound ary Stre am W e tland W e tland or Stre am Buffe r Land s lid e Hazard Land s lid e Hazard 50ft Buffe r Ste e p Slope Ste e p Slope 50ft Buffe r Eros ion Hazard I60+0055+001,524 320 300 280 260 100 120 140 160 180 200 220 240 40 60 80 Profile Vie w Struc ture Cond uc tor Ground Line Major Ele vation Grid Major Station Grid Minor Station Grid Page 23 of 30 BASED ON PSE ENGINEERINGDESIGN REVISION NI02550Fe e t1 inc h = 50 fe e t MAP EX TEN T RENTON SOURCES: Road s and Parc e ls - King County (2015), Ae rial- King County (2015); Stre am s , W e tland s and Buffe rs ,Land s lid e Hazard and Buffe rs , and Ste e p Slope s andBuffe rs from W ate rs he d Com pany (2017). For cartographic purposes only. Note:Note: Underground utility lines are surveyed in thevicinity of poles only. Existing Lake Tradition poles aren'trepresented by new conductors because they are anexisting line, and are being represented due to the polesbeing replaced. 5/7C-16A1 Propos e d Pole N um be r Struc ture Type (Se e Appx. A) Cons truc tion Sc e nario Ke y(Se e Appx. B)MATCHLINE SHEET: 22MATCHLINE SHEET: 24 §¨¦405 Renton Newcastle!(D!(D&-0/9C-1A1 SE8THSTHARRINGTON PL SE KIRKLAND AVE SE 1623059012 1623059078 1623059078 7701590000 SITE PLAN Da te: 1/18/2018Path: G:\Projects\Washington\Puget_Sound_Energy_007022\EnergizeEastsideMapbook_10059878\7.2_WP\Map_Docs\Renton\Landuse_CUP\Version_N\PSE_Renton_CUP.mxdProjec t Corrid or &-Prop osed Pole L oc a tion !(D Existing Pole L oc a tion–To Be Rem oved Tra nsm ission L ine - Prop osed Tra nsm ission L ine - Existing #*Potentia l Stringing Site Rec om m end ed Ac c ess- Prop osed Pole U nd erground Power U tility L ine U nd erground Wa ter & Wa stewa ter U tility L ine Pa rc el City Jurisd ic tion Bound a ry Strea m Wetla nd Wetla nd or Strea m Buffer L a nd slid e Ha za rd L a nd slid e Ha za rd 50ft Buffer Steep Slop e Steep Slop e 50ft Buffer Erosion Ha za rd I50+00595 0/9DCT2D100FTSTA=51+65.84HT=86FT EL E=249.01 400 420 340 360 380 320 300 280 260 120140 160 180 200 220 240 Profile V iew Struc ture Cond uc tor Ground L ine Ma jor Eleva tion Grid Ma jor Sta tion Grid Minor Sta tion Grid Page 24 of 30 BASED ON PSE ENGINEERINGDESIGN REVISION NI02550Feet1 inc h = 50 feet MAP EXTENT RENTON SOU RCES: Roa d s a nd Pa rc els - King County (2015), Aeria l- King County (2015); Strea m s, Wetla nd s a nd Buffers,L a nd slid e Ha za rd a nd Buffers, a nd Steep Slop es a ndBuffers from Wa tershed Com p a ny (2017). For cartographic purposes only. Note:Note: Underground utility lines are surveyed in thevicinity of poles only. Existing Lake Tradition poles aren'trepresented by new conductors because they are anexisting line, and are being represented due to the polesbeing replaced. 5/7C-16A1 Prop osed Pole Num b er Struc ture Typ e (See Ap p x. A) Construc tion Sc ena rio Key(See Ap p x. B)MATCHLINE SHEET: 23MATCHLINE SHEET: 25 §¨¦405 Renton Newcastle !(D !(D !(D !(D!(D &- &- &-&- &- 0/8C-18BC1 0/8C-18AC1 115-5 115-4115-3 #* #* NR02Type Ns NR04Category III H A R RIN G T O N P L S E SE 8 T H S T S E 8TH PL 2123059003 7701570000 7701590000 SITE PLAN Da te: 1/18/2018Path: G:\Projects\Washington\Puget_Sound_Energy_007022\EnergizeEastsideMapbook_10059878\7.2_WP\Map_Docs\Renton\Landuse_CUP\Version_N\PSE_Renton_CUP.mxdProjec t Corrid or &-Prop osed Pole L oc a tion !(D Existing Pole L oc a tion–To Be Rem oved Tra nsm ission L ine - Prop osed Tra nsm ission L ine - Existing #*Potentia l Stringing Site Rec om m end ed Ac c ess- Prop osed Pole U nd erground Power U tility L ine U nd erground Wa ter & Wa stewa ter U tility L ine Pa rc el City Jurisd ic tion Bound a ry Strea m Wetla nd Wetla nd or Strea m Buffer L a nd slid e Ha za rd L a nd slid e Ha za rd 50ft Buffer Steep Slop e Steep Slop e 50ft Buffer Erosion Ha za rd I45+00697 0/8SCDE90EAST 100FT/WEST 100FTSTA=45+62.15HT=100FT EL E=275.79 400 420 440 460 480 340 360 380 320 300 280 260 500 200220 240 Profile V iew Struc ture Cond uc tor Ground L ine Ma jor Eleva tion Grid Ma jor Sta tion Grid Minor Sta tion Grid Page 25 of 30 BASED ON PSE ENGINEERINGDESIGN REVISION N I 0 25 50 Feet1 inc h = 50 feet MAP EXTENT RENTON SOU RCES: Roa d s a nd Pa rc els - King County (2015), Aeria l- King County (2015); Strea m s, Wetla nd s a nd Buffers,L a nd slid e Ha za rd a nd Buffers, a nd Steep Slop es a ndBuffers from Wa tershed Com p a ny (2017). For cartographic purposes only. Note:Note: Underground utility lines are surveyed in thevicinity of poles only. Existing Lake Tradition poles aren'trepresented by new conductors because they are anexisting line, and are being represented due to the polesbeing replaced. 5/7C-16A1 Prop osed Pole Num b er Struc ture Typ e (See Ap p x. A) Construc tion Sc ena rio Key(See Ap p x. B)MATCHLINE SHEET: 24MATCHLINE SHEET: 26 §¨¦405 Renton Newcastle !(D !(D!(D !(D &- 0/7C-1A1 NR01(Ginger Creek)Type Np NR01Category III NR02Category IIINR02Category I I I D NR02 - E s t i m a t e d Category I I I NR02Category III 2023059001 2023059050 2123059003 SITE PLAN Da te: 1/18/2018Path: G:\Projects\Washington\Puget_Sound_Energy_007022\EnergizeEastsideMapbook_10059878\7.2_WP\Map_Docs\Renton\Landuse_CUP\Version_N\PSE_Renton_CUP.mxdPro jec t Co rrido r &-Pro p o sed Po le Lo c a tio n !(D Existing Po le Lo c a tio n–To Be Rem o ved T ra nsm issio n Line - Pro p o sed T ra nsm issio n Line - Existing #*Po tentia l Stringing Site Rec o m m ended Ac c ess- Pro p o sed Po le U ndergro und Po wer U tility Line U ndergro und W a ter & W a stewa ter U tility Line Pa rc el City Jurisdic tio n Bo unda ry Strea m W etla nd W etla nd o r Strea m Buffer La ndslide Ha za rd La ndslide Ha za rd 50ft Buffer Steep Slo p e Steep Slo p e 50ft Buffer Ero sio n Ha za rd I 40+0035+00702 0/7DCT 2D110FTST A=38+95.26HT =95FT ELE=360.45 400 420 440 460 480 340 360 380 320 300 280 500 520 540 560 Pro file View Struc ture Co nduc to r Gro und Line Ma jo r Eleva tio n Grid Ma jo r Sta tio n Grid Mino r Sta tio n Grid Page 26 of 30 BASED ON PSE ENGINEERINGDESIGN REVISION N I 0 25 50 Feet1 inc h = 50 feet MAP EX T ENT RENTON SOU RCES: Ro a ds a nd Pa rc els - K ing Co unty (2015), Aeria l- K ing Co unty (2015); Strea m s, W etla nds a nd Buffers,La ndslide Ha za rd a nd Buffers, a nd Steep Slo p es a ndBuffers fro m W a tershed Co m p a ny (2017). For cartographic purposes only. Note:Note: Underground utility lines are surveyed in thevicinity of poles only. Existing Lake Tradition poles aren'trepresented by new conductors because they are anexisting line, and are being represented due to the polesbeing replaced. 5/7C-16A1 Pro p o sed Po le Num b er Struc ture T yp e (See Ap p x. A) Co nstruc tio n Sc ena rio K ey(See Ap p x. B)MATCHLINE SHEET: 25MATCHLINE SHEET: 27 §¨¦405 Renton Newcastle !(D !(D !(D!(D!(D &-&- 0/5C-1A1 0/6C-1A1 NR02Category IIID C EDAR RIDGE DRSE 2023059001 2023059001 2023059050 2023059050 SITE PLAN Da te: 1/18/2018Path: G:\Projects\Washington\Puget_Sound_Energy_007022\EnergizeEastsideMapbook_10059878\7.2_WP\Map_Docs\Renton\Landuse_CUP\Version_N\PSE_Renton_CUP.mxdPro jec t Co rrido r &-Pro p o sed Po le Lo c a tio n !(D Existing Po le Lo c a tio n–To Be Rem o ved T ra nsm issio n Line - Pro p o sed T ra nsm issio n Line - Existing #*Po tentia l Stringing Site Rec o m m ended Ac c ess- Pro p o sed Po le U ndergro und Po wer U tility Line U ndergro und W a ter & W a stewa ter U tility Line Pa rc el City Jurisdic tio n Bo unda ry Strea m W etla nd W etla nd o r Strea m Buffer La ndslide Ha za rd La ndslide Ha za rd 50ft Buffer Steep Slo p e Steep Slo p e 50ft Buffer Ero sio n Ha za rd I30+00700 0/6DCT 2125FTST A=31+83.14HT =109FT ELE=400.66 400 420 440 460 480 340 360 380 500 520 540 560 580 600 620 Pro file View Struc ture Co nduc to r Gro und Line Ma jo r Eleva tio n Grid Ma jo r Sta tio n Grid Mino r Sta tio n Grid Page 27 of 30 BASED ON PSE ENGINEERINGDESIGN REVISION N I 0 25 50 Feet1 inc h = 50 feet MAP EX T ENT RENTON SOU RCES: Ro a ds a nd Pa rc els - K ing Co unty (2015), Aeria l- K ing Co unty (2015); Strea m s, W etla nds a nd Buffers,La ndslide Ha za rd a nd Buffers, a nd Steep Slo p es a ndBuffers fro m W a tershed Co m p a ny (2017). For cartographic purposes only. Note:Note: Underground utility lines are surveyed in thevicinity of poles only. Existing Lake Tradition poles aren'trepresented by new conductors because they are anexisting line, and are being represented due to the polesbeing replaced. 5/7C-16A1 Pro p o sed Po le Num b er Struc ture T yp e (See Ap p x. A) Co nstruc tio n Sc ena rio K ey(See Ap p x. B)MATCHLINE SHEET: 26MATCHLINE SHEET: 28 §¨¦405 Renton Newcastle !(D !(D !(D !(D!(D !(D!(D &- &- &- &- &-0/3C-19C10/5C-1A1 0/4C-18AC1 0/4C-18BC1 115-2 #*BEACON WAY S 2023059001 2023059002 2023059003 2023059066 SITE PLAN Da te: 1/18/2018Path: G:\Projects\Washington\Puget_Sound_Energy_007022\EnergizeEastsideMapbook_10059878\7.2_WP\Map_Docs\Renton\Landuse_CUP\Version_N\PSE_Renton_CUP.mxdPro jec t Co rrido r &-Pro p o sed Po le Lo c a tio n !(D Existing Po le Lo c a tio n–To Be Rem o ved T ra nsm issio n Line - Pro p o sed T ra nsm issio n Line - Existing #*Po tentia l Stringing Site Rec o m m ended Ac c ess- Pro p o sed Po le U ndergro und Po wer U tility Line U ndergro und W a ter & W a stewa ter U tility Line Pa rc el City Jurisdic tio n Bo unda ry Strea m W etla nd W etla nd o r Strea m Buffer La ndslide Ha za rd La ndslide Ha za rd 50ft Buffer Steep Slo p e Steep Slo p e 50ft Buffer Ero sio n Ha za rd I 25+0020+00546 0/5DCT 2D125FTST A=24+98.52HT =109FT ELE=414.55 0/4SCDE110EAST 070FT /W EST 070FTST A=19+47.02HT =70FT ELE=430.97 299 0/3DCDE2075FTST A=17+38.25HT =75FT ELE=43 Pro file View Struc ture Co nduc to r Gro und Line Ma jo r Eleva tio n Grid Ma jo r Sta tio n Grid Mino r Sta tio n Grid Page 28 of 30 BASED ON PSE ENGINEERINGDESIGN REVISION N I 0 25 50 Feet1 inc h = 50 feet MAP EX T ENT RENTON SOU RCES: Ro a ds a nd Pa rc els - K ing Co unty (2015), Aeria l- K ing Co unty (2015); Strea m s, W etla nds a nd Buffers,La ndslide Ha za rd a nd Buffers, a nd Steep Slo p es a ndBuffers fro m W a tershed Co m p a ny (2017). For cartographic purposes only. Note:Note: Underground utility lines are surveyed in thevicinity of poles only. Existing Lake Tradition poles aren'trepresented by new conductors because they are anexisting line, and are being represented due to the polesbeing replaced. 5/7C-16A1 Pro p o sed Po le Num b er Struc ture T yp e (See Ap p x. A) Co nstruc tio n Sc ena rio K ey(See Ap p x. B)MATCHLINE SHEET: 27MATCHLINE SHEET: 29400 420 440 460 480 340 360 380 500 520 540 560 580 600 620 §¨¦405 Renton Newcastle !(D!(D!(D!(D!(D!(D!(D!(D&-&-&-&-&-0CC0/1C-18BC10/2C-19C1 0/3C-19C1 0/4C-18AC10/4C-18BC1 0/1C-18AC1 0/4C-18A115-2#*BEACON WAY S 2023059002 2023059003 2023059051 2023059062 2023059066 2023059066 SITE PLAN Da te: 1/18/2018Path: G:\Projects\Washington\Puget_Sound_Energy_007022\EnergizeEastsideMapbook_10059878\7.2_WP\Map_Docs\Renton\Landuse_CUP\Version_N\PSE_Renton_CUP.mxdPro jec t Co rrido r &-Pro p o sed Po le Lo c a tio n !(D Existing Po le Lo c a tio n–To Be Rem o ved T ra nsm issio n Line - Pro p o sed T ra nsm issio n Line - Existing #*Po tentia l Stringing Site Rec o m m ended Ac c ess- Pro p o sed Po le U ndergro und Po wer U tility Line U ndergro und W a ter & W a stewa ter U tility Line Pa rc el City Jurisdic tio n Bo unda ry Strea m W etla nd W etla nd o r Strea m Buffer La ndslide Ha za rd La ndslide Ha za rd 50ft Buffer Steep Slo p e Steep Slo p e 50ft Buffer Ero sio n Ha za rd I 20+000/4SCDE110EAST 070FT /W EST 070FTST A=19+47.02HT =70FT ELE=430.97 15+00306 299 0/3DCDE2075FTST A=17+38.25HT =75FT ELE=430.35 0/2DCDE90090FTST A=12+38.27HT =90FT ELE=431.39 400 420 440 460 480 340 360380 500 520 540 560 580 600 620 Pro file View Struc ture Co nduc to r Gro und Line Ma jo r Eleva tio n Grid Ma jo r Sta tio n Grid Mino r Sta tio n Grid Page 29 of 30 BASED ON PSE ENGINEERINGDESIGN REVISION NI02550Feet1 inc h = 50 feet MAP EX T ENT RENTON SOU RCES: Ro a ds a nd Pa rc els - K ing Co unty (2015), Aeria l- K ing Co unty (2015); Strea m s, W etla nds a nd Buffers,La ndslide Ha za rd a nd Buffers, a nd Steep Slo p es a ndBuffers fro m W a tershed Co m p a ny (2017). For cartographic purposes only. Note:Note: Underground utility lines are surveyed in thevicinity of poles only. Existing Lake Tradition poles aren'trepresented by new conductors because they are anexisting line, and are being represented due to the polesbeing replaced. 5/7C-16A1 Pro p o sed Po le Num b er Struc ture T yp e (See Ap p x. A) Co nstruc tio n Sc ena rio K ey(See Ap p x. B)MATCHLINE SHEET: 28MATCHLINE SHEET: 30 §¨¦405 Renton Newcastle !(D!(D!(D &- &- &-0/1C-18AC1 0/1C-18BC1 0/2C-19C1 BEACONWAYS2023059003 2023059051 2023059062 2023059066 SITE PLAN Da te: 1/18/2018Path: G:\Projects\Washington\Puget_Sound_Energy_007022\EnergizeEastsideMapbook_10059878\7.2_WP\Map_Docs\Renton\Landuse_CUP\Version_N\PSE_Renton_CUP.mxdPro jec t Co rrido r &-Pro p o sed Po le Lo c a tio n !(D Existing Po le Lo c a tio n–To Be Rem o ved T ra nsm issio n Line - Pro p o sed T ra nsm issio n Line - Existing #*Po tentia l Stringing Site Rec o m m ended Ac c ess- Pro p o sed Po le U ndergro und Po wer U tility Line U ndergro und W a ter & W a stewa ter U tility Line Pa rc el City Jurisdic tio n Bo unda ry Strea m W etla nd W etla nd o r Strea m Buffer La ndslide Ha za rd La ndslide Ha za rd 50ft Buffer Steep Slo p e Steep Slo p e 50ft Buffer Ero sio n Ha za rd I 332 0/2DCDE90090FTST A=12+38.27HT =90FT ELE=431.39 10+00199 0/1SCDE110/SCDE90075FTST A10+35.18HT =75FT ELE=443.43 400 420 440 460 480 360380 500 520 540 560 580 600 620 640660 Pro file View Struc ture Co nduc to r Gro und Line Ma jo r Eleva tio n Grid Ma jo r Sta tio n Grid Mino r Sta tio n Grid Page 30 of 30 BASED ON PSE ENGINEERINGDESIGN REVISION N I 0 25 50 Feet1 inc h = 50 feet MAP EX T ENT RENTON SOU RCES: Ro a ds a nd Pa rc els - K ing Co unty (2015), Aeria l- K ing Co unty (2015); Strea m s, W etla nds a nd Buffers,La ndslide Ha za rd a nd Buffers, a nd Steep Slo p es a ndBuffers fro m W a tershed Co m p a ny (2017). For cartographic purposes only. Note:Note: Underground utility lines are surveyed in thevicinity of poles only. Existing Lake Tradition poles aren'trepresented by new conductors because they are anexisting line, and are being represented due to the polesbeing replaced. 5/7C-16A1 Pro p o sed Po le Num b er Struc ture T yp e (See Ap p x. A) Co nstruc tio n Sc ena rio K ey(See Ap p x. B)MATCHLINE SHEET: 29MATCHLINE SHEET: 31 STRUCTURE TYPES Appendix A Date: 1/18/2018 BASED ON PSE ENGINEERING DESIGN REVISION N RENTON Structure T ype Naming Convention Description SCDE C-18 A/B Single circuit deadend SCT C-16 A/B Single circuit tangent DCT C-1 / C-19 Double circuit tangent (D denotes OHGW overhead groundwire) DCA C-1B Double circuit angle - equiv to a C1 with a post brace to handle bigger angle SCHDE C-17 A/B Single circuit horizontal deadend (only under SCL line) SCA C-2 A/B Single circuit angle *number after type in table denotes angle Eastside 230 ROW and structure options.dgn 8/16/2017 2:06:44 PM Structure Height 65'-105' 85'-90' 70'-120' 85'-115' 50' 90'-95' CONSTRUCTION SCENARIOS Appendix B Date: 1/18/2018 BASED ON PSE ENGINEERING DESIGN REVISION N RENTONStructure Type Typical Construction Scenario (Not in critical area) Typical Construction Scenario (In a critical area) C-1 A1 A2 C-2 C1 C2 C-1B C1 C2 C-16 A1 A2 C-17 C1 C2 C-18 C1 C2