HomeMy WebLinkAboutRenton-Walter followup response 12-3-19_final
1
PSE Follow-up Responses to Comments from Karen Walter – Muckleshoot Tribe
1. With a project of this magnitude involving Cedar River and other streams and wetlands with
substantial documents to review, the City should have required a 30 day minimum comment
period.
PSE Response: PSE does not have an opinion as to the suggested comment period.
However, the revised project does not result in impacts to the designated Shoreline of the
Cedar River. The proposed project uses an existing transmission line corridor that was
established in the late 1920s and early 1930s. PSE listened to public and agency input and
revised the project design so that no impacts would occur near the Cedar River. The
proposal was subject to an Environmental Impact Statement preparation process over
several years that included multiple public comment periods and public meetings. PSE
provided a revised Shoreline Exemption Project Narrative to the City dated January 25th
2018, which describes the revised proposal within the designated Shoreline of the Cedar
River (see attached).
2. Per the Critical Areas Report for this project, “Two existing poles will be removed from and
replaced outside of wetland and stream buffer resulting in a net increase of only 68 square
feet of permanent impact. Vegetation community conversion impacts in wetland and stream
buffers total 18,786 square feet and 20,064 square feet of temporary disturbance will occur.”
The impacted areas are the Cedar River and Honey Creek (a May Creek tributary). The
project proposes to mitigate for these impacts at Riverview Park near the Cedar River (see
Appendix F of the CAR) and near Honey Dew Creek.
More information is needed regarding the proposed mitigation, including how the project is
sufficiently providing mitigation for a full suite of riparian functions, including future wood
recruitment. The only proposed mitigation is planting new trees that are within the PSE
corridor which means they are likely to be managed and not allowed to grow to their full
heights. Further, there is no proposal to add removed trees back into the affected streams.
Both the Cedar River and Honey Dew Creek (and May Creek) lack wood. The removed
trees should be added back into these affected streams to partial mitigate for the tree
removal (both temporary and permanently removed).
PSE Response: The Revised January 2019 Renton Critical Areas Report provides
additional information on mitigation. Specifically, no tree removal is proposed in the area of
the Cedar River shoreline nor is mitigation. The proposed tree removal in the area of Honey
Dew Creek will occur within the existing managed transmission line corridor where trees are
trimmed or removed on a regular maintenance cycle to ensure compliance with electrical
safety clearances. The existing trees would never be allowed to grow to their mature height
as they would pose a safety risk to the existing transmission lines. However, mitigation
plans for the Honey Dew Creek area include snags and hinge cut trees, which leaves all
woody material in the area (see Appendix F). Replacement trees are provided for on PSE
property located near wetland NR01 as shown on the plans.
2
It is also not clear how the proposed mitigation covers the same amount of buffer areas, in
part because the mitigation area for the lower Cedar River area is not quantified on the
sheets.
PSE Response: Based on public and agency input, PSE revised the project design so that
no impacts would occur near the Cedar River; thus, no mitigation is proposed along the
Cedar River.
For the Honey Dew Creek mitigation site, if trees are removed from the buffer, then native
trees, not shrubs as proposed, should be restored. If trees cannot be planted in the any of
the mitigation areas, then the applicant should find other mitigation sites to plant trees or
contribute to King County’s ILF program. The amount of mitigation should equal as least 1:1
in square foot area to avoid a net loss of functions. Currently, the mitigation area for Honey
Dew Creek is less than 1:1 to impact area.
PSE Response: The proposed project is located within an existing transmission line corridor.
Vegetation management occurs on regular intervals. PSE used Washington State
Department of Ecology mitigation guidelines for vegetation conversion of buffers. Regarding
tree replacement, PSE is proposing to plant at least 280 trees in Renton along the corridor,
which exceeds the 212 regulated trees that are proposed for removal, a ratio of greater than
1:1 mitigation to impacts. This, along with a more detailed outline of how PSE is proposing
to replace vegetation, is documented in the Vegetation Replacement Approach letter dated
July 24, 2019 and submitted to the City of Renton as part of the Conditional Use Permit
materials for this project.