HomeMy WebLinkAboutD_LUA19-000309_Cedar River TrailDEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
PLANNING DIVISION
CERTIFICATE OF EXEMPTION
FROM CRITICAL AREAS REGULATIONS
EVALUATION FORM & DECISION
DATE:
PROJECT NUMBER:
PROJECT NAME:
PROJECT MANAGER:
December 09, 2019
LUA19-000309
Cedar River Trail Embankment Subsurface Exploration
Jill Ding, Senior Planner
OWNER:CITY OF RENTON
1055 S Grady Way
Renton, WA 98057
LOCATION:1500 HOUSER WAY S
DESCRIPTION:The applicant (King County) is requesting a Critical Areas Exemption and Shoreline
Exemption to to analyze existing flood and landslide hazards and risks, and their
interactions on the left bank of the Cedar River Trail Site A (CRT-A). In order to
characterize subsurface soil conditions, the project proposes to drill up to four borings to
collect soil data for analysis. Boring holes would be backfilled according to Washington
State regulations using bentonite pellets; the excavation and backfilling is less the 500 CY
of material. The project site encompasses approximately 75,000 SF and is adjacent to the
Cedar River Trail. The project site is located within the following critical areas: Moderate
Coal Mine Hazard Area, High Erosion Hazard Area, Moderate Land Slide Area, Protected
Slopes, Urban Conservancy Regulated Shoreline (Cedar River Reach C), stream buffer and
Wellhead Protection Zone 2. The proposed work is a geotechnical study and is to get a
better understanding of the geologic risk of the area. The project proposal would not
impact drainage or require re-grading, as surface would be returned to existing conditions.
The borings and site exploration would not require the removal of any trees or land
clearing. The distance from the closest area of work to the Ordinary High Water Mark of
the Cedar River is 20-feet.
CRITICAL AREA:Moderate Coal Mine Hazard Area, High Erosion Hazard Area, Moderate Land Slide Area,
Protected Slopes, Urban Conservancy Regulated Shoreline (Cedar River Reach C), stream
buffer and Wellhead Protection Zone 2.
EXEMPTION JUSTIFICATION: Site investigative work necessary for land use application submittals such as surveys,
soil logs, percolation tests and other related activities. Investigative work shall not disturb
any more than five percent (5%) of the critical area and required buffer. In every case,
impacts shall be minimized and disturbed areas shall be immediately restored at a
one-to-one (1:1) ratio.
Page 1 of 3
DocuSign Envelope ID: 2D14EABF-9218-464C-A476-53F085C2917D
City of Renton Department of Community & Economic Development Certificate of Exemption from Critical Areas Regulations
Cedar River Trail Embankment Subsurface Exploration LUA19-000309
FINDINGS:The proposed development is consistent with the following findings pursuant to RMC
section 4-3-050C.2.d:
i. The activity is not prohibited by this or any other provision of the Renton Municipal Code
or State or Federal law or regulation;
ii. The activity will be conducted using best management practices as specified by
industry standards or applicable Federal agencies or scientific principles;
iii. Impacts are minimized and, where applicable, disturbed areas are immediately
restored;
iv. Where water body or buffer disturbance has occurred in accordance with an exemption
during construction or other activities, revegetation with native vegetation shall be required;
v. If a hazardous material, activity, and/or facility that is exempt pursuant to this Section
has a significant or substantial potential to degrade groundwater quality, then the
Administrator may require compliance with the Wellhead Protection Area requirements of
this Section otherwise relevant to that hazardous material, activity, and/or facility. Such
determinations will be based upon site and/or chemical-specific data.
DECISION: An exemption from the Critical Areas Regulations is hereby Approved with Conditions*.
CONDITIONS:1. The applicant shall be required to obtain necessary approvals and/or permits from the
City of Renton Parks Department.
2. The applicant shall be required to obtain any necessary approvals and/or permits from
the City of Renton Plan Review Section.
SIGNATURE & DATE OF DECISION:
DateJennifer Henning, Planning Director
December 09, 2019
The above land use decision will become final if the decision is not appealed within the 14-day appeal period
(RCW 43.21.C.075(3); WAC 197-11-680).
Page 2 of 3
DocuSign Envelope ID: 2D14EABF-9218-464C-A476-53F085C2917D
City of Renton Department of Community & Economic Development Certificate of Exemption from Critical Areas Regulations
Cedar River Trail Embankment Subsurface Exploration LUA19-000309
APPEALS: An appeal of this administrative land use decision must be filed in writing together with the
required fee to the City of Renton Hearing Examiner, City of Renton, 1055 South Grady Way, Renton, WA 98057,
on or before 5:00 p.m., on December 23, 2019. RMC 4-8-110 governs appeals to the Hearing Examiner and additional
information regarding the appeal process may be obtained from the Renton City Clerk's Office, (425) 430-6510.
RECONSIDERATION: Within 14 days of the decision date, any party may request that the decision be reopened by the
approval body. The approval body may modify his decision if material evidence not readily discoverable prior to the original
decision is found or if he finds there was misrepresentation of fact. After review of the reconsideration request, if the approval
body finds sufficient evidence to amend the original decision, there will be no further extension of the appeal period. Any
person wishing to take further action must file a formal appeal within the 14-day appeal time frame.
EXPIRATION: Five (5) years from the date of decision (date signed).
Attachments:Vicinity/Neighborhood Detail Map, Site Plan
Page 3 of 3
DocuSign Envelope ID: 2D14EABF-9218-464C-A476-53F085C2917D
DEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
PLANNING DIVISION CERTIFICATE OF EXEMPTION
FROM SHORELINE SUBSTANTIAL DEVELOPMENT
EVALUATION FORM & DECISION
DATE: December 9, 2019
PROJECT NAME: Cedar River Trail Embankment Subsurface Exploration
PROJECT NUMBER: LUA19-000309, CA-E, SME
PROJECT MANAGER: Jill Ding, Senior Planner
OWNER:
City of Renton
1055 S Grady Way
Renton, WA 98057
APPLICANT:
Monica Walker
King County
201 S Jackson St
Seattle, WA 98104
PROJECT LOCATION: 1500 Houser Way S (parcel nos. 1723059015 and 1623059078)
PROJECT DESCRIPTION: The applicant (King County) is requesting a Critical Areas Exemption
and Shoreline Exemption to to analyze existing flood and landslide
hazards and risks, and their interactions on the left bank of the Cedar
River Trail Site A (CRT-A). In order to characterize subsurface soil
conditions, the project proposes to drill up to four borings to collect
soil data for analysis. Boring holes would be backfilled according to
Washington State regulations using bentonite pellets; the excavation
and backfilling is less the 500 CY of material. The project site
encompasses approximately 75,000 SF and is adjacent to the Cedar
River Trail. The project site is located within the following critical
areas: Moderate Coal Mine Hazard Area, High Erosion Hazard Area,
Moderate Land Slide Area, Protected Slopes, Urban Conservancy
Regulated Shoreline (Cedar River Reach C), stream buffer and
Wellhead Protection Zone 2. The proposed work is a geotechnical
study and is to get a better understanding of the geologic risk of the
DocuSign Envelope ID: 2D14EABF-9218-464C-A476-53F085C2917D
City of Renton Department of Community & Economic Development Certificate of Exemption from Shoreline Substantial Development Cedar River Trail Embankment Subsurface Exploration LUA19-000309, SME, CM-E
DATE OF PERMIT: December 9, 2019 Page 2 of 3
area. The project proposal would not impact drainage or require re-
grading, as surface would be returned to existing conditions. The
borings and site exploration would not require the removal of any
trees or land clearing. The distance from the closest area of work to
the Ordinary High Water Mark of the Cedar River is 20-feet.
LEGAL DESCRIPTION: PARCEL 1 CITY OF RENTON LOT LINE ADJUSTMENT NO LUA 13-000410
RECORDING NO 20140326900013 (BEING A PORTION OF NW QTR SW QTR STR 17-23-05 AND OF W HALF SE QTR STR 17-23-05)
PARCEL 3 CITY OF RENTON LOT LINE ADJUSTMENT NO LUA 13-000410 RECORDING NO 20140326900013 (BEING A PORTION OF S HALF SW
QTR STR 16-23-05)
SEC-TWN-R: SW16-23-05
WATER BODY: Cedar River Reach C
An exemption from a Shoreline Management Substantial Development Permit is hereby Approved
with Conditions* on the proposed project in accordance with RMC 4.9.190C 'Exemption from
Permit System' and for the following reasons:
Activities Necessary for Permit Application: Site exploration and investigation activities that are
prerequisites to preparation of an application for development authorization under the Shoreline
Master Program, if:
a. The activity does not interfere with the normal public use of the surface waters.
b. The activity will have no significant adverse impact on the environment including, but not limited
to, fish, wildlife, fish or wildlife habitat, water quality, and aesthetic values.
c. The activity does not involve the installation of a structure, and upon completion of the activity
the vegetation and land configuration of the site are restored to conditions existing before the
activity.
d. A private entity seeking development authorization under the Shoreline Master Program first
posts a performance bond or provides other evidence of financial responsibility to the Planning
Division to ensure that the site is restored to pre-existing conditions.
e. The activity is not subject to the permit requirements of RCW 90.58.550.
The proposed development is:
DocuSign Envelope ID: 2D14EABF-9218-464C-A476-53F085C2917D
City of Renton Department of Community & Economic Development Certificate of Exemption from Shoreline Substantial Development Cedar River Trail Embankment Subsurface Exploration LUA19-000309, SME, CM-E
DATE OF PERMIT: December 9, 2019 Page 3 of 3
Consistent with the policies of the Shoreline Management Act.
Not Applicable to the guidelines of the Department of Ecology where no Master Program has been
finally approved or adopted by the Department.
Consistent with the City of Renton Shoreline Master Program.
CONDITIONS: 1. The applicant shall be required to obtain necessary approvals
and/or permits from the City of Renton Parks Department.
2. The applicant shall be required to obtain any necessary approvals
and/or permits from the City of Renton Plan Review Section.
DATE OF DECISION ON LAND USE ACTION:
SIGNATURE:
Dec. 9, 2019
Jennifer Henning, AICP, Planning Director
Department of Community & Economic Development
Date
Attachments: Vicinity/Neighborhood Detail Map
Site Plan
cc: City of Renton - Owner
APPEALS: The administrative land use decision will become final if not appealed in writing to
the Hearinge Examiner on or before 5:00 p.m. on December 23, 2019. An appeal of the
decision(s) must be filed within the 14-day appeal period (RCW 43.21.C.075(3); WAC 197-11-
680), together with the required fee to the City of Renton Hearing Examiner, City of Renton,
1055 South Grady Way, Renton, WA 98057. City of RMC 4-8-110 governs appeals to the
Hearing Examiner and additional information regarding the appeal process may be obtained
from the Renton City Clerkâs Office, (425) 430-6510.
DocuSign Envelope ID: 2D14EABF-9218-464C-A476-53F085C2917D
King CountyN0400200Feet
Legend
Proposed Exploration Area
Parcel Boundaries
Cedar River Trail Site A - Feasibility Study: Proposed Borings
RECEIVED
12/06/2019 jding
PLANNING DIVISION
DocuSign Envelope ID: 2D14EABF-9218-464C-A476-53F085C2917D
&<&<&<&<
Cedar River
Cedar River Trail
KC Topobathymetric2019 Survey Data
PROJECTSITE
Bank Erosion/Lanslide
Tension CracksIn Trail Pavement
B-3 B-1 B-2
B-4
1623059011
1623059012
1623059033
1623059033
1623059037
1623059038
1623059078
1623059110
1723059015
1723059087 1723059101
1723059177
2123059003
0 10050
FeetµSITE AND EXPLORATION PLAN
FIG. 1
November 2019 104354
King CountyCedar River Trail Site AKing County, Washington
LEGEND
&<Proposed Boring Location& Designation
TB-KCS 0732
Elevation
315 - 330
300 - 315
285 - 300
270 - 285
255 - 270
240 - 255
225 - 240
210 - 225
195 - 210
180 - 195
165 - 180
150 - 165
135 - 150
120 - 135
105 - 120
90 - 105
75 - 90
60 - 75
45 - 60
31.27 - 45