HomeMy WebLinkAboutC_Public_Comment_47.e_180614.email_attch8of9Supporting Attachment No. 11
To Comments made by Richard Lauckhart dated December 11, 2017
Comments demonstrating that the Seattle City Light line is a legitimate and better
alternative to EE if there is a need and PSE chooses to use the FERC Open Access
Transmission Tariff (OATT) rules available to them in order to enable this option
to happen
May 11, 2017
Heidi Bedwell
City of Bellevue Development Services Department
450 110th Avenue NE
Bellevue, WA 98004
Re: Comment for Energize Eastside Phase 2 Draft EIS
Dear Ms. Bedwell:
I am writing to submit comment on the Energize Eastside Phase 2 Draft EIS.
This comment relates to pages 2-52 of the Phase 2 Draft EIS. In particular section 2.2.1 "Seattle
City Light Transmission Line" option.
In order to understand how this option works, one needs to be familiar with FERC's ProForma Open
Access Transmission Tariff (OATT). The FERC ProForma Open Access Transmission Tariff can be
found at:
htt s: www.ferc. ov industries electric indus-act oatt-reform order-890-B ro-forma-o en-
access,odf
Section 6 of the OATT discusses "Reciprocity". If SCL uses the lines of one or more FERC directly
regulated utilities, then SCL will have agreed to these terms when they use those lines. Meaning
under reciprocity, SCL agrees to also deal with requests for use of their transmission grid under the
FERC OATT approach.
Other sections of interest to this SCL Transmission Line option are:
Section 15. Service Availability
Section 16, Transmission Customer Responsibility
Section 17. Procedures for arranging for Firm Point to Point transmission service
[This section is particularly relevant to how PSE needs to ask SCL for use of its line to serve a new
23011.15 KV tronsformer at Lakeside. There is a requirement to make a formal application in the
format that is described in the GATT. PSE has never made such an application. An informal
request does not meet the required format for making a request to use the SCL line. PSE needs to
make this formal request to SCL].
Section 19. Additional studies procedures for Firm Transmission
With an understanding of how FERC's GATT works, it is clear that just about every sentence in the
discussion of the SCL option is incorrect, meaning these sentences are not consistent with the
OATT.
First sentence:
"SCL has indicated to the City of Bellevue that they expect to need the corridor for their own
purposes and are not interested in sharing the corridor with PSE (SCL, 2014)."
The EIS staff should already be aware that FERC does not allow a utility like SCL to "hoard" its
transmission capability. Further, the FERC OATT requires a utility like SCL to increase the rating of
its infrastructure (with needed construction) if that is what it takes to honor a request for
transmission and the requesting utility agrees to pay what FERC requires them to pay. No one
has performed a System Impact Study (as required by the OATT) to see what it would take to
honor a PSE request to use the SCL line to serve a new 230/115 KV transformer at Lakeside.
Second sentence:
"The existing SCL line would have to be rebuilt to provide a feasible solution for the Energize Eastside
project, because the current rating of the SCL fine is insufficient to meet PSE's needs (Strauch,
personal communication, 2015)."
If it can be shown that the existing SCL line would need to be rebuilt to provide a feasible solution
for the Energize Eastside project, then that is what the FERC OATT would require be done as long
as PSE agrees to pay what FERC would require them to pay for that construction. Until a study is
done, one cannot tell for sure what the rebuild cost would be. But it certainly would be less than
the cost of Energize Eastside. Further, it should be clear that the request to use the SCL line is
only for purposes of serving a new 230/115 KV transformer at Lakeside. The study to determine
what this cost must not include a requirement to deliver 1,500 MW to Canada unless BPA makes
that request and BPA would pay the bulk of the needed cost if the SCL line is also being used to
increase the ability of BPA to deliver power to Canada.
Third Sentence:
"PSE has estimated that rebuilding the SCL line would provide sufficient capacity for a period of less
than 10 years, which does not comply with PSE's electrical criteria (as described in Section 2.2.1 of
the Phase 1 Draft EIS) to meet performance criteria for 10 years or more after construction."
Under the FERC OATT rules that SCL needs to comply with, SCL does not get to stop serving
Lakeside after ten years even if SCL has a legitimate need for more use of its SCL line at that time.
The FERC OATT has clear rules on how a utility like PSE can assure its transmission service from
SCL can be retained even after SCL decides it needs the line for its own use. The FERC OATT
protects a utility like PSE from SCL stopping to provide them transmission service.
Fourth Sentence;
"Neither the City nor PSE can compel SCL to allow the use of this corridor; therefore, this option is
not feasible coed was not carried forward."
This statement is wrong. PSE can compel SCL to use its line to serve a new 230/115 KV
transformer by making a FERC Order 888 request (under the FERC OATT) for such transmission
service. If SCL refuses, FERC will compel them to do so. FERC uses its "reciprocity" ruling to
compel SCL. If SCL refuses, FERC will refuse to let SCL use any transmission lines that are under
direct FERC jurisdiction. SCL could not meaningfully its service obligations to its own customers
without using the transmission lines of FERC directly jurisdictional utilities.
Fifth Sentence:
"Even if compelled use of the corridor were allowed, the negotiations would likely prove lengthy,
and would li kely preclude completion of the project within the required timeline to meet project
objectives,"
The FERC GATT has tight timelines for dealing with requests for transmission service, FERC
intentionally put in these tight timelines to prohibit a utility like SCL from denying service by
delaying service. Further, PSE currently is not saying when it thinks it needs a new 230/115 KV
transformer to be in service at Lakeside. Any needed construction on the existing SCL line will
take considerably less time than permitting and building EE. Further, according to the only
reasonable load flow study done regarding serving the east side (the Lauckhart-Schiffman Load
Flow study), there is plenty of time before any new 230/115 KV transformer is needed at
Lakeside.
Thank you for the opportunity to clarify how this SCL Transmission Line option would work.
Sincerely,
f4tz,-�
Richard Lau ckhart
Energy Consultant
Davis, California
530-759-9350
lauckjr@hotmail.com