HomeMy WebLinkAboutERC Report RMC Title IV - Parks PlanDEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
ENVIRONMENTAL REVIEW COMMITTEE REPORT
ERC MEETING DATE: December 30, 2019
Project Name: Parks, Recreation, and Natural Areas Plan Update
Owner: City of Renton, 1055 S Grady Way, Renton, WA 98057
Applicant: Same as Owner
Contact: Angie Mathias, Long Range Planning Manager
File Number: LUA19-000299, ECF
Project Manager: Leslie Betlach, Parks Planning and Natural Resources Director and Erica
Schmitz, Parks Planning Manager.
Project Summary: The applicant is requesting Environmental (SEPA) Review for the Update of the
2011 Parks, Recreation, and Natural Areas Plan. The 2011 Plan established a
20-year vision for Renton’s park system and identified the community’s
priorities. In the past eight years, the City has worked with partners to build
new features like the Meadow Crest Playground and the bridge at Riverview
Park, make key land acquisitions, and explore new neighborhood-focused
programming. Since 2011, Renton has grown to be more diverse and dynamic
than ever. The updated Plan carries forward the community’s vision; re-
evaluates needs and priorities; gauged interest in existing events and
programs; and identifies partnership opportunities.
Project Location: Downtown Renton
Exist. Bldg. Area SF: N/A Proposed New Bldg. Area
(footprint):
Proposed New Bldg. Area (gross):
N/A
N/A
Site Area: N/A Total Building Area GSF: N/A
STAFF
RECOMMENDATION:
Staff Recommends that the Environmental Review Committee issue a
Determination of Non-Significance (DNS).
PART ONE: PROJECT DESCRIPTION / BACKGROUND
No actions are being taken at this time. This is a non -project action. The planning process for the
Parks, Recreation, and Natural Areas Plan update incorporated a variety of community engagement
opportunities in different formats and offered them at different times over the course of the year. A
multi-layered, multifaceted outreach approach broadens participation by allowing people to
participate on their own terms and to their own interest level. While some forums engaged more
participants than others, each activity was included to gain perspectives from the entire range of the
Renton community. This “layering” of activities ensured that a variety of interests and priorities
would be represented in this Plan. The Plan identifies the Level of Service (LOS) for the City in regards
to parks and natural areas. The LOS is 5.07 acres/1,000 population or 1 acre of park per 200 people
for developed parks and 6.14 acres/1,000 population for natural areas. The Plan also identifies gaps
City of Renton Department of Community & Economic Development Environmental Review Committee Report
PARKS, RECREATION, AND NATURAL AREAS PLAN UPDATE LUA19-000299, ECF
Report of December 30, 2019 Page 2 of 2
ERC Report 17-000725
in needed parks, natural areas, and programming. A chapter on the need to identify and plan for
ongoing maintenance is included. Finally, the plan includes an implementation strategy, ranks the
identified projects, and concept plans for some parks were created.
PART TWO: ENVIRONMENTAL REVIEW
In compliance with RCW 43.21C.240, the following environmental (SEPA) review addresses only those
project impacts that are not adequately addressed under existing development standards and
environmental regulations.
A. Environmental Threshold Recommendation
Based on analysis of probable impacts from the proposal, staff recommends that the Responsible
Officials:
Issue a DNS with a 14-day Appeal Period.
B. Mitigation Measures
None.
C. Exhibits
None.
D. Environmental Impacts
There are no environmental impacts that are anticipated to occur in conjunction with the proposal.
E. Comments of Reviewing Departments
The proposal will be circulated to City Department Division Reviewers and appropriate agencies.
All substantive comments will be provided to the Responsible Officials for their consideration and
possible recommendation that the comments be incorporated as “Advisory Notes to Applicant.”
Environmental Determination Appeal Process: Comments and Appeals of the environmental
determination must be filed in writing on or before 5:00 PM on January 17, 2020.
Renton Municipal Code Section 4-8-110.B governs appeals to the Hearing Examiner. Appeals must be filed
in writing at the City Clerk’s office along with the required fee. Additional information regarding the
appeal process may be obtained from the City Clerk’s Office, Renton City Hall - 7th Floor, 1055 S. Grady
Way, Renton WA 98057.