HomeMy WebLinkAboutC_Public_Comment_76.bComments to The City of Renton on Puget Sound Energy’s Energize Eastside & Renton EIS Consistency Analysis/Addendum :. Version number: 1.0 From: Todd Andersen 4419 138th Ave Bellevue WA 98006 This doc needs a serious rewrite but no time to do so. It is however factually correct in magnitude. To: City of Renton, Jill Ding Senior Planner, jding@rentonwa.gov , City Clerk jseth@rentonwa.gov CC: WA State Attorney General's Office Date: Jan 8, 2020 Subject: Renton’s EIS Consistency Analysis deficient & wrong in several key areas per new infor introduced by PSE at the City of Bellevue Administrative Hearing Mar/Apr 2019. The new information PSE provided shows massive decrease in 2 aspects of Renton’s review criteria “pipeline safety” and “economics” over existing power lines. Energize Eastside has a ~104 to 107 fold increase in likelihood of monopoles falling over due to earthquake liquefaction and rupturing the OPL pipeline over smaller existing wooden H-Frame structures. PSE introduced new information on monopole depths and distance from OPL at the Bellevue Administrative hearings under oath. Monopole foundations depths up to 46 ft deep and as shallow as 13ft. But here’s the kicker, only 13 feet away from the pipeline. And Energize Eastside has a ~104 to 107 increase in likelihood of OPL pipeline rupture from an earthquake of one or both of the 16” and 20” pipelines operating from 928psi to 1265psi than existing as built H- frames. The real killer is the new monopoles are far more top heavy and will have minimum +14X more leverage to the new foundations over the H-Frame foundations during an earthquake liquefaction or landslide. They also increase SCC on OPL. Why? 7 fold reduction in poles at more than twice the height. Bigger single point monopole foundations are far worse than smaller 2 point wooden H-frame foundations in their failure mechanisms on OPL. The other new information introduced by PSE in Renton’s EIS Consistency Analysis is “the replacement of approximately 144 existing wood and steel poles (H-frame design) with approximately 41 steel monopoles” per City of Renton EIS Consistency Analysis. Never stated in any EE EIS document. Here is what the Tokyo Gas Company, a utility 10x the size of PSE with far greater resources and knowledge said. To quote their 2011 presentation/paper of at the International Gas Union Conference “Pipeline operators were shocked at the first occurrence of AC corrosion in 1986 and subsequent AC corrosion failures of modern pipelines in Europe and North America despite satisfying the protection potential criterion.” “It has been definitely shown by the occurrence of AC corrosion on a catholically protected pipeline that AC corrosion cannot be prevented by CP [catholic protection, what “protects” OPL currently] in the presence of very high AC voltage of a pipeline.” PSE could use a DC line (Direct current) like Bonneville Power does to ship power from WA dams to Los Angles. This has zero AC inducted corrosion risk while PSE’s “solution” will remain unproven as detailed by the Toyko Gas Company published papers, as physics are physics and no amount of fraud from PSE will change that. Zero consideration of a DC line in the EIS. What does PSE’s AC inducted voltage expert David Kemp say? Notice PSE does not call him an AC inducted corrosion expert! His not even a AC inducted voltage expert PSE used a non qualified “expert” for any electromagnetic analysis with his only training being a BS in Mechanical Engineering. Even this so called PSE “expert” says “this typical approach that we use for our customers was not the route that PSE wished to pursue“1 Which is PSE’s phasing pipedream which will kill thousands. Here is CoB’s expert” Wolfgang Fieltsch used the exact same propaganda term of “holiday” and even had to explain it to Gary McLean, the City of Bellevue’s highly coaching Admin “judge”. (see XX above) Per Wolfgang Fieltsch’s own words “And some of the coatings are so good that there's very few holidays, if any. Holidays are basically holes in the coating” “these Olympic pipelines are older and therefore -- and have co-existed in the corridor with the power lines for probably more than 50 years. And because they [Olympic pipelines] are not well coated -- well, I shouldn't say not well coated, but it's an older coating, which isn't up to the same standards as the newer coating, the risk, the AC interference risk would be lower. 2 Admin Judge Gary McLean’s admonishment to Bellevue City Staff. He actually stopped the Hearing by saying “this is probably outside my authority, call this dicta” to the Bellevue Staff that he hopes the City has a way to inform any future removal of old OPL pipe with newer more corrosion resistant would be purely foolish. “I'll give you here is where he [Wolfgang Fieltsch from Stantec, City of Bellevue’s Pipeline “expert”] made the very clear point that newer pipelines pose greater risks. “ Unbelievable – Renton needs to save on court costs and embarrassment and do the right thing 1 Pg 226 of 439 (printed page 218 ) of City of Bellevue EE EIS, HEARING EXAMINER REPORT TRANSCRIPTS - VOL. 1 OF 3 [30 Vol 1 Transcript.pdf] From AUDIO RECORDING OF PUBLIC HEARING (3/28/2019, 3/29/2019, 4/3/2019 & 4/8/2019 2 Pg 360 & 361 of 439 (printed page 353,354 ) of City of Bellevue EE EIS, HEARING EXAMINER REPORT TRANSCRIPTS - VOL. 1 OF 3 [30 Vol 1 Transcript.pdf Sen. John McCain’s 2003 hearing on the Office of Pipeline Safety after a 8” pipeline sprayed 10k gallons all over brand new homes in Tuscon AZ. “The questions that have arisen from this incident suggest that delayed, lax, or worse, non-existent oversight and enforcement by OPS …... I hope that at today’s hearings we will get answers to these questions” They did get ansers and the fossil fuel crime syndicate removed McCain as chair of Senate Energy Comm. . Xxx finish short adds Furthermore PSE’s near zero ROI (less than 1%) on the company per year, since 2007, also means significant “Scenic Views and Aesthetics” decrease as PSE’s pole height increase +2x allows for new business model of 5G antenna farm on every pole. 5G has a +100X increase in number of antennas needed over 4G. If EE is approved, new Federal laws on 5G/etc mean the City of Renton will have zero local control what PSE does on aesthetics. Renton’s industrial look will significantly expands into residential area as PSE’s Renton antenna farm services 5G to the west side of Mercer Island far cheaper than PSE’s Mercer Island light poles. Professional Expertise: Former advisor to the US Secretary of Defense and the Chief of Naval Operations’ Strategic Studies Groups; Former Survivability & Lethality Manager US Naval Weapons Center; the US Navy’s lead fuel fire expert including suppression (think the +12 million gallons of gasoline & jet fuel that flow through Renton/Bellevue on OPL every day). Masters in Electrical Engineering: Electromagnetic propagation, Naval Postgraduate School. BS in Mechanical Engineering. Functional expert in accelerated aging and aging of mechanical and fuel systems (think corrosion & the ability to detail to frauds of the Federal Office of Pipeline & GAO oversight). Shared an office with the DOD’s top two PhD Geologists whose job included flying to any major earthquake in the world and detailing the damage. One of 100s of relevant interactions: how US Special Forces reacted to Singaporean Military detailing how they protect their critical pipeline infrastructure. Videos of City of Bellevue Admin hearing on Energize Eastside on Youtube: City of Bellevue’s SEPA responsible official and EE EIS head and attorney, slapping a camera out of a citizen’s hand at Energize Eastside public meetings. This one of many such incidents at EE EIS, this one at the Renton Technical College. www.youtube.com/watch?v=RfxzAsxF45o 22min https://youtu.be/LubO0oUT0QA 1hr3min= https://youtu.be/f7d7btufQ4w see the others by googling “youtube orca80sr” Executive Summary: 1) Renton’s EIS Consistency is incorrect as it is based on a fraudulent EE EIS and an EE EIS missing key information, which PSE partially disclosed for the first time during the EE Bellevue Admin hearing. PSE & City of Bellevue know they have created a highly fraudulent EE EIS which is why both PSE’s attorney and the City of Bellevue Assistant Attorney Matt McFarland warned the judge more than a dozen times that he can’t rule against them for a fraudulent EIS. Matt McFarland’s exact words “The Department [means the City of Bellevue’s legal office] has stated at multiple times during this hearing that the adequacy of the EIS is not an issue that is before the Hearing Examiner, because the City's Environmental Procedures Code does not provide for an administrative appeal of this specific issue.”3 It forces citizens to be organized & knowledgeable enough take their own city to court. Bellevue Admin Hearing rules do not even allow cross examination. The hearing examiners ears can be fill with fraud and misinformation for four days without cross examination. New information PSE presented at the City of Bellevue Administrative Hearing and in Renton’s Consistency Analysis work, both not in any of the EE EIS documents, give three independent reasons why Renton’s EIS Consistency Analysis is wrong. Why Energize Eastside cannot be built without a massive increase in pipeline rupture over existing lines and not meeting Renton’s Pipeline Safety, Economic and Aesthetics criteria. Earthquake/SCC PSE’s new information introduced Mar 2019 stated the actual steel monopoles foundations depths up to 3 times deeper over existing (13 to 46 feet deep per new information from PSE’s construction mgr Lowell Rogers under oath at Bellevue Admin Hearing see transcript4 ) Furthermore new info in Renton’s Consistency Analyses of a 7 fold reduction in number of poles and placement distance from OPL pipeline (also brand new information not in EE EIS) increases: 1. Earthquake risk in the 50ft to 100ft right-of-way by a massive amount ~104 to 107 increased risk in pipeline rupture over existing H-Frame structure. 2. From increased wind loads on taller and fewer monopoles and a +100x increase (+10,000?) in stress corrosion on pipelines from 13ft away. Zero mention of stress corrosion in ANY EE EIS document even though there have been three pipeline failures in 2003 from stress corrosion cracking (SCC) two in WA State alone (26” Williams Pipeline) These caused Senator John McCain to force the OPS to stop covering it up. PSE earthquake related info is another massive lie on top of PSE SCC lies. Here is PSE’s Dan Koch, Director of Electric Operations for Puget Sound Energy “We don't wait for earthquakes to occur before we decide that building codes should require buildings to be able to withstand an earthquake.5 True, so why don’t power lines have earthquake design codes and earthquake construction codes for power lines collocated the bulk pipelines 3 Pg 257 and of 332 35 Vol. 2 Transcript.pdf of City of Bellevue EE EIS, HEARING EXAMINER REPORT TRANSCRIPTS - VOL. 2 OF 3 4 Pg 108 and of 332 (print page 537) 35 Vol. 2 Transcript.pdf 5 Pg 87 of 439 (printed page 81) of City of Bellevue EE EIS, HEARING EXAMINER REPORT TRANSCRIPTS - VOL. 1 OF 3 [30 Vol 1 Transcript.pdf] From AUDIO RECORDING OF PUBLIC HEARING (3/28/2019, 3/29/2019, 4/3/2019 & 4/8/2019 carrying gasoline/jet fuel? Odd that PSE’s construction manager Lowell Rogers says that powerlines are not designed for earthquakes as they are “Acts of God”. Let us see what City of Bellevue’s well-known-safe-construction-engineer says, none other than City of Bellevue Assistant Attorney Matt McFarland has to say. Here are his comments telling the public that ‘if you are to stupid too not know that you need to address Bellevue’s world renown safe utility construction codes in your EE EIS comments then you get what you deserve’. Lets quote Matt McFarland directly from the EE Admin Hearing in March April 2019, “On the other hand, Section 20.20.255F contains substantive design standards. Subsection 255F has not really been at issue during this hearing, and the Department's analysis regarding the subsection is memorialized in the Staff Report and also the pre- hearing brief. Given the lack of public comment regarding these design standard regulations, I'm not going to belabor any of the points already memorialized in the record regarding Subsection F pg265/332 35 vol 2 Maybe citizen would of learned that they needed to review Bellevue’s extensive safe contraction code for power lines directly over bulk gasoline pipelines if the City of Bellevue’s SEPA responsible official and EE EIS head and attorney herself, was not busy slapping cameras out of citizens hands at Energize Eastside public meetings. This one of many such incidents at the Renton Technical College. www.youtube.com/watch?v=RfxzAsxF45o I for one was not aware of Bellevue’s impressive history of design code. After all the 2009 City Council overruled the City Commercial building code inspector for failing the building that Expedia was months away from moving into for what? Not having fire rated air circulation ducts. Expedia was soon so impressed with Bellevue moved to Seattle. Commercial building code inspector resigned. But I am aware that the 2000 City of Bellevue Mayor Chuck Mosher was so impressed with the City of Bellevue’s safe construction knowledge at that he formed the “Citizens Advisory Committee on Pipeline Safety” with the Mayor of Bellingham and got Governor Gary Locke to commission it. Well his heart was in the right place even if this was a defacto toothless event. Amazing the ability of $$$ to nullify & erase critical knowledge. Mayor Chuck Mosher was so impressed with the City of Bellevue that he and his wife moved from Somerset (Bellevue) to East Yakima. Meat of Earthquake What does PSE construction manger Lowell Rogers say about Energize Eastside’s earthquake design criteria at the Bellevue Admin Hearing? Zero design criteria REQUIRED by law. Let us quote Mr Rogers PSE EE construction manager as he is a bit more honest on the subject “Acts of God are things that we really don't plan for in engineering design. We plan for things that are reasonable and prudent and expected. Acts of God that have been brought up such as an enormous seismic event, huge landslides, those are going to affect a regional area, and I'll talk about comparing the existing condition with the new-built condition and how an act of God would apply to both of those.” 6 Mr Rogers is saying the Eastside is going to burn down during an Earthquake even if EE was not built. Not true. While still deadly EE is orders of magnitude more dangerous. Now back to Mr Rogers. “So the seismic risk falls into two categories. One is dictated by the International Building Code, and that prescribes ground response factors, and that is incorporated in our design parameters. The other, during an enormous seismic event is as more in the nature of the act of God that I'm talking about referenced earlier. Ref same but pg218/439. The professional engineering fraud by PSE continues. Note1: PSE was caught lying about earthquake design criteria in the drafts EE EIS and had to correct in the final EIS. Here is the screen shot. PSE first said that the WUTC had earthquake standards. I believe PSE lied there and is lying again with its fix of the first lie. PSE 6 Pg 215 of 439 (printed page 208 ) of City of Bellevue EE EIS, HEARING EXAMINER REPORT TRANSCRIPTS - VOL. 1 OF 3 [30 Vol 1 Transcript.pdf] From AUDIO RECORDING OF PUBLIC HEARING (3/28/2019, 3/29/2019, 4/3/2019 & 4/8/2019 is not to be trusted it is a convicted felon for falsifying pipeline safety records for 4 yrs in 2007. Fine a mere $1.2 million, the savings alone paid for the fine. Why does Renton believe it has changed it behavior has any penalty for doing so? One does not understand the level of propaganda/crime from coming from the for-profit Electric Utilities until one reads these. Here is the punch line from Federal Judge Richard Cudahy who saw first hand the criminal of electric utilites in his court room for ~40 yrs. “The authors reluctantly conclude that history will likely repeat itself” pg3 of 80 see item 4 below. 1 Electric Utilities: A crisis in Public Control by seven Syracuse University professors documents the first 40 yrs. Published in 1928 and Roosevelt used to win the Presidency. The for-profit monopoly US electric utilities had already a long record of racketeering by 1928. 2. 1937 book Pyramids of Power The Story of Roosevelt, Insull and The Utility Wars. 3. See a shocking level of corruption & propaganda below far below in Corporate Public Relations A NEW HISTORICAL PERSPECTIVE 1987 by Marvin N . Olasky The University of Texas at Austin. Any that book is still only a small part of the story. See quote from far below. 4. 2005, Senior Circuit Judge, U.S. Court of Appeals for the Seventh Circuit; Hon. Richard D. Cudahy and William D. Henderson Professor, Indiana University School of Law; FROM INSULL TO ENRON: CORPORATE (RE)REGULATION AFTER THE RISE AND FALL OF TWO ENERGY ICONS 80pgs Not notation of who this mystery organization ACI is in the EE EIS. Back to PSE’s crimes in progress Note2:the court transcript sometimes miss identifies Rogers as Johnson. Also is EIS is mis-transcribed as ASA??. ASA= (Alternative Siting Analysis) Per PSE’s construction manager Lowell Rogers “To simply state, the loads induced on a structure from anticipated earthquake ground motions are not greater than other conditions such as wind and ice loads, and therefore do not control the design.” Same ref pg 219 of439 It is good to know PSE and Mr Rogers know what the “anticipated earthquake ground motions” are going to be. This very major fact that was never documented in any of the EE EIS documents. Both 1) One is dictated by the International Building Code, and that prescribes ground response factors and 2) anticipated earthquake ground motions What is PSE’s lead attorney, Erin Anderson, legal assessment of what is required? Here are her exact words Per Erin Anderson, PSE’s lead outside Attorney, Put simply, the code requires the applicant to submit the ASA and show its work.pg307/332 35 vol 2 ASA= (Alternative Siting Analysis) Why is it that PSE only has to show it homework in the Alternative Siting Analysis? Who says meeting the IBC, ASCE and ACI are the correct or even valid standard for a power line collocated with flammable pipelines? Who the hell is ACI? PSE never states. Let take a look at transmission lines without pipelines directly underneath how have they preformed to IBC, ASCE , ACI=who?, NESC and IEEE earthquake standards? What kind of performance are do we get out high voltage power transmission systems in earthquakes? Same as for ice loads design standard, very poor. Let us ignore the 1000s of transmission towers that have failed from ice loads in the last 2 decades and just focus on earthquake. Even more unacceptable IF built on top of pipelines that kill 1000s if ruptured. See this 2017 Applied Science paper that notes just a few of the failures of electrical transmission systems in the USA, Japan and China during earthquake as the result of no earthquake design codes for them.7 The exact same thing was said of buildings before earthquake requirements were added. 1992 Landers earthquake, about 100 transmission lines, and several transmission towers, failed in the city of Los Angeles 1994 Northridge earthquake, a number of transmission towers were destroyed, and the power system was greatly damaged 1995 Kobe earthquake, more than 20 transmission towers were damaged 2008 Wenchuan earthquake, more than 20 towers collapsed and a 220 kV transmission line in Mao County was destroyed 2010 Haiti earthquake caused damage to transmission towers. 2013 Lushan earthquake, more than 39 transmission lines were destroyed. PSE never states what the anticipated earthquake ground motions are in any of the EE EIS documents. 7 Vibration Control of a Power Transmission Tower, 5 May 2017, Journal of Applied Sciences PSE states that safety measures would be incorporated into the project design to ….. prevent poles from falling and damaging the buried pipelines. PSE never “shows it homework” on how PSE will prevent poles from falling and damaging the buried pipelines. The Coso landslide has proven these maps are out of date. This is why WA State is doing new LIDAR mappings. PSE can stamp them Sources: King County, 2015; Ecology, 2014 but the data is still known to be inaccurate. How well will PSE’s EE preform in an earthquake? PSE’s new pole foundations 46 ft deep as close 13 feet away from pipelines which are only 3-4 ft underground and you are one earthquake away from a steel monopole falling over & a major disaster. See elsewhere in this document what PSE’s taller and heavier poles will do when it strikes the ground above the pipeline. PSE never shows its homework on why its foundations will not rip open the pipeline when they fallover. And compare why they are not orders of magnitude worse that the wooden H-Frames. PSE’s use of peak ground acceleration alone is complete engineering malpractice to determine the response difference between wooden H-frame structure and much taller steel monopoles. Any competent ‘flutter’ engineer can tell you that. It is just one factor and a tells you nothing about what matters most: the dynamic response of much taller monopoles and shorter stiffer H-Frames. What is that to PSE? They falsified pipeline safety records for 4 years and are a convicted felon because of it just 10 years ago. If a weak earthquake hits the resonance frequency of a structure it will do far more damage than a more powerful earthquake that is not in the frequency response range of a structure. Why did many more newer/stronger 10 to 20 story buildings in Mexico city fall down in 1985 earthquake yet much taller and weaker shorter ones did not? The frequency response of those buildings resonated with the periodicity of the earthquake, 1-2 seconds. This was my first introduction to the Navy’s two PhD geologist studying earthquakes I was interviewing for a position in Aircraft survivability. They were rushing out of their office to buy plane tickets when the quake was still happening ~1500 miles away, they could pinpoint it enough from our base in the California desert. I personally have been through more than 50 earthquakes in Ridgecrest CA. The most recent 7.1 magnitude in 2019 I was not there for is what OPL and the electrical system should be designed for. PSE never includes other far more structurally import factors particularly resonance spectrum for the H-frames and compare that to resonance spectrum of the steel monopoles. And for the wave types. Earthquakes have various wave types including P wave and S waves and a good flutter engineer could show the delta between the monopoles and H-Frame. The reason PSE didn’t do this work is the answer will be very bad for the very top heavy steel poles. This “flutter “ analysis is done on every new aircraft and it is criminal if not done on power lines collocated with gasoline pipelines. More lies/propaganda/misdirection by PSE in the final EE EIS? Below PSE says very low chance of ignition, which is it? Why was this never corrected? What other lies is PSE telling? None of the above cities in that 2017 earthquake paper were dumb enough to let the power lines be collocated over bulk gasoline pipelines. PSE will have you believe colocation is common which is a bold face lie. What is true is colocation with natural gas as nat gas pipeline rupture kill zone looks like San Bruno CA’s, under a 100 homes in a city. This because natural gas burns vertically, does not spread. But 100,000s of gallons of liquid, aka gasoline, spreads over miles killing 1000s even with no fire via suffocation as no obvious warning of danger. PSE’s EE EIS did say suffocation is the most likely cause with their estimate that a OPL break has a 97.5 % chance of not catching fire in the Eastside cities.8 Here is PSE’s propaganda that a EE caused OPL rupture will magically pool. 8 pg 228 of 274 Energize Eastside Project Phase 2 Draft Environmental Impact Statement Volume 2: Appendices May 8, 2017 Of course PSE committed fraud again and narrowed the review a snapshot of pipeline breaks from a 4.5 yr period 2010-2015 (OPS has that 5 yr period with only has 4.5yrs of data). Why just 2010-15? Because if one includes hundreds of decades newer pipelines the results are better. If PSE was honest & accurate they would just looked at pipelines break of the same age, coating types etc over time. But if PSE did that we would see the “bathtub curve” and EE would get canceled for sure. And, if the OPS didn’t note the fire in its records then it did not happen per PSE. Regardless almost all of them with gasoline caught fire after humans showed up. See the September 2016, the Colonial Pipeline break in the FDIC report on pipeline terrorist mentioned elsewhere in the doc and google “Colonial Pipeline fire” It caught fire ~3 days later after the repair crew showed up. Burned at least one repair man alive. During the 20 months prior to the Sept 2016 rupture, the Colonial Pipeline had 8 pipeline gasoline spills across its 5,500-mile fuel pipeline system. Energize Eastside has a ~104 to 107 increase in likelihood of OPL pipeline rupture from earthquake of one or both of the 16” and 20” pipelines operating from928psi to 1265psi and in multiple places than existing as built. Why? Energize Eastside has a ~104 to 107 increase in likelihood of monopoles falling over due to earthquake liquefaction and pipeline rupture over smaller existing wooden H- Frame structure. Surprisingly it does NOT matter which way the poles fall over west or east given the NW subduction zone fault. Even PSE slip fault gives a east west pole fall over direction. Also the resonate frequencies of PSE new monopoles are far more tuned to earthquake frequencies & susceptible to failure than wooden H-frame. The real killer just is the Monopoles are far more top heavy and will have +14X more leverage to the new foundations over the as built foundations during an earthquake. Why? The new information from Renton’s Consistency analyses and not in any EE EIS docs says 144 H-frames replaced with 41 monopoles. Given each H-frame has two poles we have a 7 fold reduction in poles and at twice the height even using PSE math gets 14X. It is far higher with increased wind loading but I am dumbing it down for the City attorneys at Bellevue & Renton. In liquidfaction or very wet soil it does not matter you 3x’ed the foundation. Large rocks do not float better in water. And to finish the kindergarten level explanation for Matt McFarland, when the monopoles fall over they either rip OPL out of the ground or pinch it down from above. The resulting pressure spike from trying to slow down miles of fuel will rupture the ¼ inch thick steel pipe 20” diameter pipe (0.312” for the 16”). The existing H-Frame wooden structures cannot crush the OPL like PSE new monopoles. The two PhD US Navy earthquake geologies I shared an office with for years were always impressed how much better wooden structures dampen energy from earthquake verse metal which more often than not resonates until failure. Here for poles near OPL the soil is the weakest link and H-frames win bigtime. The new monopole loads are pure bending at the foundation from both wind and earthquake swing and also have significantly different & greater risk profile of stress corrosion cracking on OPL. Add another way the EE monopole cause mechanical rupturing of OPL is during seismic liquefaction over existing H-frames and Energize Eastside nearly guarantees the Eastside burning down during a major earthquake unlike existing. Zero analysis in EE EIS nor in Renton’s Consistency Analysis nor Stress Corrosion Cracking, nor any professional engineering stamp on most of the EE EIS analysis nor any stating a level of safety. Wonder why there are no the stamps of any professional engineer qualified to practice in WA on ALL of PSE’s EE EIS? Only one select area. Terrosism 3) In my professional judgment, as a former DOD survivability & lethality manager/design engineer, an amateur non-state terrorist success risk goes from a low ~X% to almost 100% success for a single 400,000 gallon release success with EE on a single pipeline attack. Where X is a low number. Attacks of this nature are not just expected to have a 2x increase going to a 2x new-built higher voltage. A simple grounding of the pipeline to the new-built metal poles by non-state actor and wait for lighting strike or other slower effects, integrates success over time. I am purposely skipping explanations. All very easily to skip detection from OPL’s leak detection system pictured below. Even comparing pictures from one two-week- pass to the next, which this aircraft does to see if there is any dead vegetation from one period to the next. I know because the plane flys over my house every time always doing 2-3 circles around Tyee middle school as Somerset is a massive liquefaction/landslide zone. P1100417.jpg See Pipeline Patrol marked under plane. Tail number N7140K. Back to non PSE terrorism. Or worse, add shorting the 230kV line to the metal pole previous connect to the pipe 13 ft away. This cannot be done with existing wooden poles. Energize Eastside significantly increases risks by reduces risk of detection given it allows a piece meal attack vestor. I am leaving out a bunch of things but not the things anyone using google & maps can’t find. This is just one of several new attack vectors that Energize Eastside allows. The as-built 115 kV lines have a ~0.1X% for a four rupture site attack (~1.2 million gallon gasoline release: two 300k gallons on 16” line , two 400K gallon releases on the 20” line). With 230kV Energize Eastside there a 99% success chance on two of four attacks miles apart on the 16 and 20 inch lines. No analysis for increase terrorist risk provided by PSE EE EIS nor Renton’s review. Significant change in economic consequences. Any attack in Renton/Newcastle/Bellevue takes down I-90 at Bellevue shoreline several after hrs rupture should fuel ignite. The 1- 90 highway only needs to be heated on the bottom surface to 120F for complete collapse like I-85 in Atlanta 2016. 9 Same for Renton/I405/Cedar River. Also See FDIC 2017 report on pipeline terrorist attack. And what genius thought putting the OPL manual shut off values at the intersection of Seattle City lights 230kV power lines and the PSE 115 kV lines in 1964? Lots of new non state actor possibilities here with Energize Eastside. Where does the 9 See NTSB report on 2016 collapse of I-85 in Atlanta due plastics pipe fire, energy equivalent of 50 gallons of gasoline. the 300,000 to 700,000 gallons of gasoline go from a rupture here? See map below. This will shut down SecTac, Portland airport in 3 days and all auto gasoline deliveries south of break including to Portland. If anyone thinks that level of release is not going to put 10,000s of gallons on Boeing’s Renton factory shore you would be mistaken, save very strong winds from the south; even if the fuel caught on fire at the rupture site. The small portion that would make it way into the storm drains would guarantee that. Why? The first dozen or so storm drains would clog over with pebbles & debris after the first several 10,000 gallons or so. If I didn’t take pictures of that event myself I would not of believed it. And that was from a 6 inch water main break at 150psi in Somerset Sept 2017. I can say a lot more but I am going to stop my comments here expect to say Energize Eastside makes our WA state energy infrastructure orders of magnitude more vulnerable. How can that pass economic muster in Renton’s EIS Consistency analysis? The deadly recent history of 230 kV upgrades in San Francisco = the cause of San Bruno fire. And Stress Corrosion Concentrated loading of new-built larger steel monopoles & foundations 2 to 3 times larger than existing vastly increases earthquake & Stress Corrosion Cracking (details in section2) over smaller wooden H-frame. H-Frames also have less resonance over wider range of earthquake frequencies than new- built. With PSE’s design distance of 13 ft minimum from OPL, all proposed steel monopoles are capable of ripping open OPL in liquefaction. Per PSE’s Energize Eastside construction manager Lowell Rogers in Admin Hearings “The final structural design of Energize Eastside will comply with NESC'S standards adopted in Washington, which includes seismic standards”.10 NESC=National Electric Safety Code 10 Pg 219 of 439 (printed page 212 ) of City of Bellevue EE EIS, HEARING EXAMINER REPORT TRANSCRIPTS - VOL. 1 OF 3 [30 Vol 1 Transcript.pdf] From AUDIO RECORDING OF PUBLIC HEARING (3/28/2019, 3/29/2019, 4/3/2019 & 4/8/2019 While the above statement is true, it is pure fraud and professional malpractice for use as a seismic standard for Energize Eastside. Nowhere in the NESC code nor any other building codes are there any standards for constructing high voltage power (115kV/1000 amps) anywhere near highly volatile pipelines carrying +12 Million gallons/day. Let alone putting +100 ft steel poles with foundations up 46ft deep just 13 ft from the pipelines. [This is newly introduced information Renton’s reviewers would only know if they read the ~800pg transcript of PSE’s “experts” testifying to Bellevue Hearing Examiner] Put simply, the code requires the applicant to submit the ASA and show its work.pg307/332 35 vol 2 I would submit Puget left no stone unturned pg312/332 34 vol2 ASA submittal shows how the project satisfies the design criteria 304/332 35 vol2 Lack of public comment regarding these design standard regulations……Section 20.20.255F contains substantive design standards. Subsection 255F has not really been at issue during this hearing, pg265/332 35 vol 2 Why are there no design standards for this case? First, no one is dumb enough to do such a thing but PSE. PSE/(Eastside cities) are the only company/entities dumb enough in the entire world to collocate bulk gasoline/jet fuel pipeline directly under high power voltage lines. Second, powerline codes are where building codes were for earthquake decades ago. Nonexistent except for the assumption wind & ice loads cover small earthquakes. Careful readers of the Admin Court transcript will know PSE’s EE construction expert Lowell Rogers got the gullible and soon to make a complete fool of himself Hearing Examiner Greg McLean exited with Rogers “Jefferson Martin transmission line in San Francisco Peninsula” fraudulent example of safety. “This line is very similar to Energize Eastside in that it traverses a suburban setting, includes overhead transmission tubular steel poles constructed very close to a major gas pipeline. This project was constructed without incident. Like what has and will be done for Energize Eastside.” 11 Pray GOD that EE is not the case but before we discuss that here is the uneducated coaching comment from Bellevue Hearing Examiner Gary McLean. “THE EXAMINER: Just an interjection. That's a yardstick. That's the kind of testimony evidence that I'm looking for. I'd like to hear stuff like that. So go ahead.” Transcript mistaken IDs Mr Rogers as Mr Johnson. This is quite obvious has the Examiner only says Mr Rogers. I was in attendance & also confirmed via video. The PG&E Jefferson-Martin San Francisco 230 KV line AKA the San Bruno 30” natural gas pipeline explosion 11 Pg 213 of 439 (printed page 206) of City of Bellevue EE EIS, HEARING EXAMINER REPORT TRANSCRIPTS - VOL. 1 OF 3 Ok so what is this “Jefferson and Martin transmission line …. placed into service in 2006…..without incident”? per PSE construction mgr and expert Lowell Rogers who worked on the project!!!!!! Fact one. PG&E placed a 230 kV power line parallel to the brand new portion of a natural gas 30” pipeline (11 yrs old, 1995) and just a few feet away for 1170 feet. This 1995 portion with undisclosed coating (even after the criminal & accident investigations) but no doubt better that the coating on 1956 old portion of the same pipe where the San Bruno rupture occurred just 1300 feet way. See color code map below. It only took four years for Pg&E’s 2006 installed 230kV powerline to blowup Pg&E’s 30” natural gas pipeline in 2010. And in the spot likely seeing the highest above and below ground and electromagnetic energy, just 1170 ft away. Given PG&E was convicted of 10 felony counts of falsifying information on this and NTSB report is just as likely covering OPS efforts to look the other way we have no official determination yet besides my professional expertise. The official NTSB investigation is bad welds which is like say the Titanic sunk because of bad riveting. Here the iceberg is the +100 years of corrupted government by the Electric Utility industry. SEE background section below on this corruption. A book published in 1928 called Electric Utilities: A crisis in Public Control by seven Syracuse University professors documents the first 40 yrs. The for-profit monopoly US electric utilities had already a long record of racketeering by 1928. Or the book Pyramids of Power The Story of Roosevelt, Insull and The Utility Wars. How bad is the Electric Utility propanda? See a shocking level of corruption & propaganda below far below in Corporate Public Relations A NEW HISTORICAL PERSPECTIVE 1987 by Marvin N . Olasky The University of Texas at Austin. Any that book is only a small part of the story. Back to the PSE & PG&E frauds. San Bruno is still the biggest utility disaster in San Francisco peninsula’s history. The San Bruno natural gas pipeline explosion/fire only killed 8; only injured 64 and only destroyed 55 homes because this was natural gas and not gasoline.12 PSE Energize Eastside(EE) project will kill 1000s when the same electromagnetic coupling from EE on OPL causes OPL to break with a guaranteed spill ~300,000 gallons of gasoline from the smaller 16” line and ~400,000 gallons of gasoline for the 20 inch line. Why are the large spill sizes guaranteed if ruptured besides already having one massive spill in 1999? Read the 2017 FDIC report on Pipeline Terrorism and pipeline break response sizes and times to shut off up to 2017. Per FDIC report 78% of gasoline/jet fuel/natural gas breaks are not even detected by any leak detection system but passersby’s.13 Often days later in rural areas. 12 San Bruno CA rupture report www.ntsb.gov/investigations/AccidentReports/Reports/PAR1101.pdf 13 pg16 of 42 Terrorism and Oil & Gas Pipeline Infrastructure: Mar 2017 by FDIC & Univ of OK College of Law https://digitalcommons.law.ou.edu/cgi/viewcontent.cgi?article=1078&context=onej find=google "liability for petroleum pipelines" The red arrow is where PG&E’s San Bruno natural gas pipeline explosion occurred. Why am I talking about PG&E’s 2010 criminal disaster? Puget Sound Energy is making the same willful criminal act/neglect with Energize Eastside. PSE is even choosing NOT to go the route their own outside ”expert” David Kemp says “typical …approach that we use for our customers was not the route that PSE wished to pursue“ Instead of 8 dead EE will kill 1000 via suffocation and/or fire with hundreds of thousands of gasoline coming out at up to 1200psi. OPL has zero real time leak detection nor legal requirement for it let alone any manual shut off that is not measured in hours like the 1999 Bellingham incident. See 2017 FDIC pipeline Massive electrical coupling here between red underground 230 kV and blue, green & yellow 30” nat gas pipeline. Max power direction of unshielded monopole antenna weak as it is former from 230 kV cable directional bends . Weakest spot in 30’ nat gas pipe from AC inducted corrosion is 6 collocated pipeline pup sections in the 1956 yr old pipe. See fig. 16. terrorism report and you understand the biggest pipeline terrorist is Office of Pipeline Safety and the fossil fuel industry. Shockingly the 30 inch natural gas pipeline was a few feet away from the completely unshielded (faraday cage) from electromagnetic radiation from the 230 kV underground cable. While rupture was 1300 ft away it is likely where the greater field strengths were there given all the other underground metal pipelines water main, fire hydrants, smaller nat gas lines or sewer pipes acting as weak EMF wave-guides even if plastic or concrete. See figure 16 above. Far more disturbing the unintentional but at least three weakly functional monopole antennas formed by the 230 kV lines with the two above ground mainbeam ‘antenna’ planes parallel to the 30 inch natural gas pipeline. One vertical plane the other horizontal both parallel to the 30 inch pipeline that blew up and numerous other metal pipes. As a professional engineer who designed electrometric fields & directional control from 1 billionth of a watt (nanowatts) to +1 billion watts (gigawatt) it is shocking to see two quasi monopole antennas 2400ft away and a third just 1170feet way from the pipeline break. The amazing criminal engineering malpractice of PG&E is they place an unshielded underground 230 kV power line just a few feet away from their own 30 inch natural gas pipeline for ~1200feet!!!!! This will induce a massive amount of electrical coupling from the 230 kV line to the 30” steel pipeline, exactly the way farmer can and do steal power from power lines crossing their fields albeit with copper wire not pipe. This will cause AC induced corrosion on the pipeline. And given the portion the pipelthat picking up the current/voltage is very well coated for galvanic corrosion, stress corrosion cracking and etc14 the current travel down the 1956 year old pipe with the worse inaction at 6 “pup” weld joints likely the highest holes in the pipeline corrosion coating aka “holidays”. The fossil fuels industry and the Federal Office of Pipeline Safety have been committing massive fraud on pipeline safety for so long they have a special propaganda term for a holes in the corrosion protection coating of pipeline. The fossil fuels industry propaganda term is “holidays” so when uneducated pipeline worker hear holidays not failure in corrosion protections they don’t get worked up. Everybody wants a holiday!!! The more the better right? The reason the coating is on the pipeline in the first place to prevent all other types of corrosion like galvanic and stress corrosion to name just two. The industry learned that lesson the first few years they put unprotected pipelines in the ground back in the 1800s with methane gas from coal gasification plants. But City of Bellevue’s pipeline expert Wolfgang Fieltsch is either ignorant of that facts or committing fraud. A question I tried to put to him on video but the EE EIS SEPA responsible official Carol Helland held him back from being at a public EE presentation in Redmond. I guess someone will have to do that in court. Wolfgang Fieltsch used the exact same propaganda term of “holiday” and even had to explain it to Gary McLean, the City of Bellevue’s highly coaching Admin “judge”. (see XX above) Per Wolfgang Fieltsch’s own words “And some of the coatings are so good that there's very few holidays, if any. Holidays are basically holes in the coating” “these Olympic pipelines are older and therefore -- and have co-existed in the corridor with the power lines for probably more than 50 years. And because they [Olympic pipelines] are not well coated -- well, I shouldn't say not well coated, but it's an older coating, which isn't up to the same standards as the newer coating, the risk, the AC interference risk would be lower. 15 It would be comical if it was not so deadly to then hear the Energize Eastside Bellevue Hearing Examiner Gary McLean’s admonishment to Bellevue City Staff. He actually stopped the Hearing by saying “this is probably outside my authority, call this dicta” to the Bellevue Staff that he hopes the City has a way to inform any future removal of old OPL pipe with newer more corrosion resistant would be purely foolish. “I'll give you here is where he [Wolfgang Fieltsch from Stantec, City of Bellevue’s Pipeline “expert”] made the very clear point that newer pipelines pose greater risks. “16 Gary wanted to make sure the City had a way to prevent OPL from putting in new pipeline as they are more dangerous. Citizens are often beaten senseless with a stupidity stick by our legal system, but rarely so thoroughly. 14 including stress corrosion cracking (SCC), corrosion fatigue, hydrogen-stress cracking, hydrogen-induced cracking (HIC), hydrogen-induced loss of ductility, and sulfide-stress cracking (SSC). See pg 32of78 in OPSs SCC rpt 2008 15 Pg 360 & 361 of 439 (printed page 353,354 ) of City of Bellevue EE EIS, HEARING EXAMINER REPORT TRANSCRIPTS - VOL. 1 OF 3 [30 Vol 1 Transcript.pdf 16 Pg 367 & 368 of 439 (printed page #’s are 360 & 361) of City of Bellevue EE EIS, HEARING EXAMINER REPORT TRANSCRIPTS - VOL. 1 OF 3 [30 Vol 1 Transcript.pdf] From AUDIO RECORDING OF PUBLIC HEARING (3/28/2019, 3/29/2019, 4/3/2019 & 4/8/2019) Unbelievably criminal actions by Wolfgang and the City of Bellevue’s Assistant City Attorney Matt McFarland, not to mention a conflict of interest law violation from the 2016 Congressional law.17 Ok you caught me the above conflict of interest part is a lie, in practical terms. After Sen. John McCain was removed as Senate Energy Committee chair by the fossil fuel industry, the later made sure that 2016 law was neutered by adding “to the greatest extent practicable” in 4 key places. So never mind that. Sen. John McCain was chair of Senate Energy Committee until he investigated the industry after the 2003 stress corrosion break two in WA State one in AZ. He barely escaped from a massive fuel fire on the Forrestal Aircraft carrier and watched 131 follow sailor burned alive. Even a book written about it. That fire launched decades of R&D funding which I lead in the 1990s. Not bad John, breaking with the Keating 5 and doing the right thing. Sen Marie Cantwell on the other hand likely getting direct checks from Charles Koch like WA Representative Rick Larson. Rick is noted for his comments that ‘all is well’ after the 2004 Renton OPL break/fire in the press. Same break that caused Seattle Mayor Greg Nickols to sue ….how odd. During the Admin Hearing break I explained to my corrupt City Attorney Matt McFarland what his expert just said in order to protect the OPL from AC corrosion. Your expert says you have to make sure OPL stays unprotected from a bucket of other corrosion mechanisms like galvanic and Stress corrosion. Matt’s response, “ I am just an attorney I don’t understand these things” But the little scum of the earth attorney did his best to cover things up including reminding Gary McLean, the City of Bellevue’s highly coaching Admin “judge”, that the citizens of Bellevue, Renton, Newcastle, Redmond are just going to have to take City of Bellevue to court to not have a fraudulent PSE Energize Eastside EIS. Matt McFarland’s exact words from the official hearing transcript “The Department [The City of Bellevue’s legal Dept] has stated at multiple times during this hearing that the adequacy of the EIS is not an issue that is before the Hearing Examiner, because the City's Environmental Procedures Code does not provide for an administrative appeal of this specific issue.”18 Unbelievably the NTSB report on PG&E’s San Bruno murders never mentioned what coating was used, zero mention of AC inducted corrosion and zero mention of any catholic protection on the pipeline. The report did say the CPUC would propose future rules on “reporting cathodic protection deficiencies”. This is the current method OPL uses to ‘protect’ the OPL from PSE’s 115kV lines. Maybe WUTC can do the same for Renton after PSE/OPL burn it and, oh yes, the Renton Boeing facility to the ground. Further shocking is the J-M line even had an ElectroMagneticField Plan forced on them by CPUC before it was built but it was only for health of humans and only meant PG&E would dig the underground trench deeper around schools & the like. 17 www.congress.gov/bill/114th-congress/senate-bill/2276/all-info www.congress.gov/114/plaws/publ183/PLAW-114publ183.pdf 18 Pg 257 and of 332 35 Vol. 2 Transcript.pdf of City of Bellevue EE EIS, HEARING EXAMINER REPORT TRANSCRIPTS - VOL. 2 OF 3 Put in back? The elevation raise from where the crude monopoles created by the 230 kV Jefferson-Martin powerline transition from underground to above ground and across HW it is possible the maximum field strength is at location of the San Bruno pipeline explosion. The Glenview Drive Transition Tower and the above ground tower are shown below in thick red lines with the underground portion of the 230 kV Jefferson-Martin line in thinner red line. Those with antenna design experience or even RF signature reduction design experience will recognize this a one giant random but highly magnitude increasing antenna. PG&E will have you believe that the electromagnetic field strength drops off by 1/r2 for 3-phase power line with balances currents AND that may be true for MOST of the time.19 Given there are three massive and unintentional direction antennas from three transitional sections. 1) from underground to over head eastside of HW 35/Skyline Blvd. 2) from that east tower to the across HW 35 and lastly 3) the right angle turn to turn and go south. This and all the near-field interaction with the metal water tank and very high EMF (electromagnetic field). The 30 inch natural gas pipe and ages of the sections are color coded. The rupture occurred in the yellow section Back to PSE’s 230 kV plans The new-built EE will also be collocated all through Renton / Newcastle / Bellevue / Redmond with a 20” and 16” gasoline/jet fuel pipeline same as existing-built and just as unsafe right? Deadly wrong. EE is thousands to millions fold more dangerous. EE even guarantees the Eastside burns down during a major earthquake with just a few new steel monopoles falling over, unlike existing H-Frame unable to rupture OLP if they could even fall over. PSE is going to use steel monopoles with much deeper foundations over replacing wooden H-frames 1/3rd the size in diameter as PSE need the height to build the 5G antenna farm. Per code they only need to go up 3 feet when going from 115 kV to 230 kV. But without that 2x increase in height no antenna farm adding to a good industrial look. Most of the monopoles foundations are far deeper than their distance from the OPL. 13 to 46 feet deep per new information from PSE’s construction mgr Lowell Rogers under oath at Bellevue Admin Hearing see transcript20 And another staggering level of ignorance and new information from PSE at the Admin hearing is putting the pole as close as 13ft from the pipeline. With zero analysis of the long-term effect of on inducted stress corrosion from larger new-built foundations on the OPL pipeline; the cause of two pipeline breaks in WA State in 2003 alone. XXX See screen shots of key and more below. THE EXAMINER: So 13 feet away from the pipeline, the design plan? 13 feet away for construction that's activity that you might have to excavate? 19 www.cpuc.ca.gov/Environment/info/aspen/jefferson_martin/jeffmartin.htm see pg 4/21 of https://www.cpuc.ca.gov/Environment/info/aspen/jefferson_martin/mm/final_plan.pdf 20 Pg 108 and of 332 (print page 537) 35 Vol. 2 Transcript.pdf MR. ROGERS: That is what we've laid out as a criteria of a minimum separation.21 Zero analysis of this increase risk in the EE EIS and these foundation depths and placement distance from OPL are missing in the EE EIS documents. Back of the envelope calculations gives the risk of pipeline rupture during a major earthquake during liquefaction of ~100% fold for over existing H-Frame poles with low near zero. And a 500-10,000 fold increase in rupture from increased stress corrosion cracking (SCC)22 on the pipeline over existing H-frame wooden structure. Monopoles with the new stated foundation depths increase stress corrosion on the pipelines from long-term cyclic wind loading and/or slight soil movement from foundation drilling/vacuuming so close. While still a vast under reporting & falsification by Federal Office of Pipeline Safety, 32pg of the 2008 report says “Since its discovery in 1965 as a possible cause of failures in pipelines, SCC has caused, on average, one to two failures per year in the U. S.” 23 Yet in 2003 there were two SCC major pipeline failures in WAS alone. [Note: careful reading of Tokyo Gas Company’s pipeline reports like that on AC inducted corrosions shows how fraudulent OPS is even on pipeline coating statements]. Yet zero mention of stress corrosion in any of EE EIS not any in Renton’s Consistency analysis. Clear violation of Renton’s Pipeline safety and Economics criteria. See OPS final reports listing SCC on coal tar coated pipes, same a OPL, and SCC due to ground movement how ever small. 21 Pg 107 and of 332 35 Vol. 2 Transcript.pdf of City of Bellevue EE EIS, HEARING EXAMINER REPORT TRANSCRIPTS - VOL. 2 OF 3 From AUDIO RECORDING OF PUBLIC HEARING (3/28/2019, 3/29/2019, 4/3/2019 & 4/8/2019) 22 see the 201pg SCC report when Senator John McCain was still head of the Senate Energy Committee. https://primis.phmsa.dot.gov/gasimp/docs/SCC_Report-Final_Report_with_Database.pdf Not the watered down version put out after McCain has his committee chair taken from him 78 pg version EE EIS quotes which is found at www.phmsa.dot.gov/pipeline/gas-distribution-integrity-management/dimp-pipeline-corrosion-final-report-michael-baker- jr-november-2008 Baker78pgfinalreport_pipelinecorrosion.pdf 23 pg 32of78 pg report above link to get Baker78pgfinalreport_pipelinecorrosion.pdf https://primis- stage.phmsa.dot.gov/comm/reports/enforce/documents/520031003H/52003100 3H_Amendment%20to%20CAO_12182003.pdf All docs on WA State Williams Pipeline Company by OPS Enforcement actions back to 2002 listed at https://primis.phmsa.dot.gov/comm/reports/enforce/CaseDetail_cpf_520031003H .html?nocache=858#_TP_1_tab_2 Magically Tuscon Az Accident which Sen John McCain held hearing on are only in AZ state utility commission unavailable to the public 520031003H_post- hearing%20decision%20on%20CAO%20amendment_04092004.pdf See all at xxxx Below doc found at at www.gpo.gov/fdsys/pkg/CHRG- 108shrg20974/content-detail.html CHRG-108shrg20974.pdf Sen John McCain’s words below, then Chair of the Energy Committee “The questions that have arisen from this incident suggest that delayed, lax, or worse, non-existent oversight and enforcement by OPS and a company that reacts to safety problems after they occur instead of taking actions to prevent them. I hope that at today’s hearings we will get answers to these questions” AC inducted corrosion from Energize Eastside and the missing corrosion mechanisms PSE & Bellevue chose to cover-up. AC Summary 2). PSE used a non qualified “expert” for any electromagnetic analysis with his only training being a BS in Mechanical Engineering. Even this so called PSE “expert” says “this typical approach that we use for our customers was not the route that PSE wished to pursue“24 PSE could use a DC line (Direct current) like Bonneville Power does to ship power from WA dams to Los Angles. This has zero AC inducted corrosion risk while PSE’s “solution” will remain unproven as detailed by the Toyko Gas Company published papers, even in short term let alone long term +10 yrs. 2. There are at least three separate corrosion mechanisms for which PSE only addresses AC inducted corrosion and does that incompetently/fraudulently. At least two other corrosion types (galvanic and stress corrosion) cannot be safety mitigated even with PSE’s highly deceitful & unproven method stated at the 2019 Bellevue EE Administrative hearing. To quote “adjusting the phasing, the tower configurations, the loading, and even the route of the transmission line to perform sensitivity studies to this effect”25. This never been shown to be safe over decades NOR that it is even possible for OPL to do so and safely protect for other corrosion mechanisms. Likely the reason why British Petroleum sold 100% of its stake in OPL in 2017 after seeing PSE push the same in the EE EIS. BP only operates OPL with zero liability and zero equity stake. Even PSE own “expert” David Kemp states “So PSE engaged DNV GL back in 2015 to assess the likelihood of AC interference on the co-located pipeline segments as a result of the circuit upgrades. I should mention that my typical interference studies, my usual client is the pipeline operator” [And typical approach =] “so we assess the AC potentials on the pipeline, and then design mitigation to be installed on the pipeline afterwards” “this typical approach that we use for our customers was not the route that PSE wished to pursue.”26 Why was that not the route that PSE wanted to purse? David Kemp is after all PSE “expert” on the subject. Is it because PSE knows that Tokyo Gas Company, a utility 10 times larger than PSE, published a paper in 2011 that says ““It has been definitely shown by the occurrence of AC corrosion on a catholically protected pipeline that AC corrosion cannot be prevented by CP [catholic protection, what “protects” OPL currently] in the presence of very high AC voltage of a pipeline.” PSE and the Olympic Pipeline are risking 1000s of Renton/Bellevue/etc lives for decades and city governments are doing zero, save efforts by Settle City Mayor Greg Nickels(2004); Bellevue Chuck Mosher& Bellingham Mayor(2000-03). When OPL had a “pinhole” leak in Renton in May 2004 spilling 3300 -10,000 gallons. Why did Seattle mayor Nickel immediately sue Shell/BP/OPL in 2004?27 Why did Shell Oil sell 100% of its 37.5% stake in OPL to British Petroleum on Dec 2, 2005 just 1 yr 24 Pg 226 of 439 (printed page 218 ) of City of Bellevue EE EIS, HEARING EXAMINER REPORT TRANSCRIPTS - VOL. 1 OF 3 [30 Vol 1 Transcript.pdf] From AUDIO RECORDING OF PUBLIC HEARING (3/28/2019, 3/29/2019, 4/3/2019 & 4/8/2019 25 Pg 225 & 226 of 439 (printed page #’s are 218 & 219) of City of Bellevue EE EIS, HEARING EXAMINER REPORT TRANSCRIPTS - VOL. 1 OF 3 [30 Vol 1 Transcript.pdf] From AUDIO RECORDING OF PUBLIC HEARING (3/28/2019, 3/29/2019, 4/3/2019 & 4/8/2019 Casey & Donley, Inc. 509.539.6153 rdonley@caseydonley.com 26 IBID 27 Pipeline fire disrupts supply of gas to region - Olympic pipeline remains shut after rupture, blaze in Renton Newspaper May 24, 2004 | Seattle Times, & others. www.seattlepi.com/local/article/Wear-caused-gas-leak-in-Olympic- pipeline-1145599.php 3000 gal per OPL self reporting . And, given spills were on OPL pumping grounds not reportable to the OPS pipeline records, but a separate bucket, further hiding the true dangers. The two pipehole breaks sent 3 firefighters to the hospital and evacuated 1 square mile including that the closest responding firehouse. after the lawsuit was filed? Answer is Shell’s awesome operational research group did not want to risk a +$10 Billion dollar accident in Renton/Bellevue/Eastside bankrupting Shell. And while they knew the maximum federal fine was $3 million for even criminal convictions resulting in death was puny for Shell; the state fines could go to the billions, like PG&E’s 2010 San Bruno pipeline break. PG&E had a $1.4 billion CA State fine and a the maximun $3 million Federal fine for 10 felony convictions on 8 deaths and total destruction of 55 homes. Shell’s OR Group’s case studies are taught at the Naval Postgraduate School and the Strategic Studies groups of both the Sec Def & Chief of Naval Operations. What did Shell’s O.R. group see that caused it to unload its entire stake to BP at 3.7cents on the dollar? It took BP 12 yrs and Deepwater Horizon and PSE’s AC induced corrosion frauds to wise up. On Sept 2017 BP sold 100% of BP’s stake in OPL, contrary to the Final EE EIS which states BP has a partial stake. 28, 29 BP does still operate it for the new owner Enbridge 66% and ArcLight Capital out of Boston 34%. The list of why Shell (and 12 yrs later BP) sold ALL of their stake in OPL = Stress Corrosions Cracking on decades old pipe is overtaking other failure reasons and cannot be managed with replacing pipe. 1. In 2003 OPL filed for Chapter 11 bankruptcy protection due to the 1999 Bellingham 237,000 gallon rupture/fire/deaths. 2. Three large pipeline breaks all from SCC forced the Office of Pipeline Safety to stop covering up SCC related because the industry has no way to detect it at any level to insure no pipeline ruptures. 2A. Two massive pipeline ruptures in WA state a Williams Company 26 inch natural gas line.30 May 1, 2OO3 rupture of the line ~300 feet from Lake Tapps Elementary School, Pierce County ,WA. Shell learned that and saw what a disaster WA State few pipeline regulations are. Even Texas Law requires that pipelines be 3000ft from school. The second explosion on the Williams Company natural gas pipeline, Dec 13 2003, of was near Toledo WA and released for 3 hrs. 2B. A 8 inch gasoline blew up in Tuscon AZ on July 30, 2003 that sprayed dozens of new homes not yet occupied with +10,000 gallons gasoline.31 The industry in answer to Sen. John McCain’s question claimed for the 15,000 time that “The July 30 failure was caused by high pH Stress Corrosion Cracking (SCC), a phenomenon that is new to the refined products pipe- line industry.” This a bold face lie that even the 2008OPS SCC report refutes with their fraudulent 1965 statement. The US Naval Research Lab documented in a 1970 report on stress corrosion for DARPA that it 28 And contrary to PSE’s final EE EIS Vol 1 pg61/451 29 Shell Oil sold their 37.5% stake in the Olympic Pipeline Company Dec 2, 2005 to BP which 10 days later sold a controlling interest to Canada’s Enbridge for $101.9 million for 65% of OPL. Sept 2017 BP sold all of its stake in OPL to ArcLight Capital of Boston. www.bizjournals.com/seattle/stories/2005/12/12/daily4.html 30 https://primis.phmsa.dot.gov/comm/reports/enforce/documents/520031003H/520031003H_post- hearing%20decision%20on%20CAO%20amendment_04092004.pdf https://primis.phmsa.dot.gov/comm/reports/enforce/CaseDetail_cpf_520031003H.html?nocache=2164#_TP_1_tab_2 https://tdn.com/business/local/pipeline-bursts-near-auburn/article_9b509bd7-0c6e-53c7-9751-8eb8cc0222d6.html 31 pg 171/176 This doc found at www.gpo.gov/fdsys/pkg/CHRG-108shrg20974/content-detail.html CHRG- 108shrg20974.pdf was known since the 1930s pg8of27.32 Admitting so forces the pipeline industry to replace +$100 billion in older pipelines. 3 Shell saw final OPS report on the 2 WA pipeline breaks released the April 9 2004. The Federal Office of Pipeline Safety (OPS) knew since 1990 there was SCC on the line since 1990 and did nothing until these two breaks forcing Williams to replace all 300 miles. “There is a history of SCC with two failures in the past year, the existence of several known parameters for SCC, an expert opinion that TFI will not detect SCC in time to prevent failure, and no countervailing evidence. Factors that can play a role in SCC include the operating pressures, imposed loads placed on pipeline due to stress, the acidity of the soil, and coal tar coating. These are factors found on this 26-inch line.33 “….failures on the line that have occurred since 1990, including stress corrosion cracking and land movement , as risks” 34[causing SCC on the pipe & rupture] The NTSB report on the 2010 San Burno CA pipeline explosion notes that “about 61 percent of transmission pipelines are not piggable—meaning they cannot accommodate current gas-driven in-line inspection devices.”35 PSE nor EE EIS nor Renton’s review has any idea of what parts of OPL will see dangerous field strengths from PSE’s wing it & unproven “mitigation” and equally deadly OPL may have zero capability to inspect IF and inspection tools are developed in the future capable to monitor SCC, AC induced corrosion as well as normal external/internal corrosion. It did help that BP not have Shell’s operational research group, then only sold 67% stake to Enbridge in for 3.7% of OPLs replacement cost 10 day later. But Deepwater Horizon got BP to where Shells has ZERO ownership in OPL Sept 2017 BP sold all of its stake in OPL to ArcLight Capital Why, both just bought OPL several years earlier? If PSE was honest and not a convicted criminal company as of 2007 for falsifying pipeline safety for four years they would make Energize Eastside a DC power line and remove 100% of the AC inducted corrosion on the OPL pipeline. Bonneville Power uses a long distance DC powerline to ship power down to Los Angles. But even if PSE did, EE still at least double the success of a $2000 terrorist attack and makes what was not possible with using simple hardware purchases from Home Depot/Walmart now possible. If our local government and citizens were not corrupt the existing PSE power line over OPL would be shutoff and all existing power transferred to the Settle City Light. As of a few years ago the former CEO of SCL had leased those line to Bonneville for free for at least 15 yrs. Yet another fraud. It would be poetic justice to have the Eastside get EE and the resulting disaster if that disaster could happen 32 pg8/27 https://pdfs.semanticscholar.org/7ae3/8d35f7661a1950aa097138fbdc3be3421292.pdf 33 Pg3 of 7 https://primis-stage.phmsa.dot.gov/comm/reports/enforce/documents/520031003H/ 520031003H_Amendment%20to%20CAO_12182003.pdf 34 pg 3 of 9 https://primis.phmsa.dot.gov/comm/reports/enforce/documents/520031003H/520031003H_post- hearing%20decision%20on%20CAO%20amendment_04092004.pdf 35 pg 98of 153, www.ntsb.gov/investigations/AccidentReports/Reports/PAR1101.pdf also see https://www.ntsb.gov/investigations/AccidentReports/Pages/PAR1101.aspx quickly to those that deserve it. But I digress, back to the criminal behavior of our corporate-socialist companies. PSE, like PG&E, knows the maximum Federal fine from fraud by a utility resulting in deaths regardless of the number is $3 million. Before we get to the second reason that has no humor let us highlight the one that does related to engineering/corrosion even though it is as deadly as the second reason as Energize Eastside makes a $2000 unskilled terrorist attack possible. Interesting that when the FDIC details pipeline terrorism in a Mar 2017 42pg paper with the Univ of Oklahoma College of Law Oil and Gas36, they spend more time on the lack of competent engineering. Among other things the critical inadequacies of the USA’s pipeline basics of leak detection which, on average, takes days unless a passerby calls it in and zero automatic shut off even today Jan 1, 2020. OPL uses Piper cub aircraft looking for changes in live vs dead vegetation, every two weeks or so. The FDIC spent little time on corrosion with just a hand full of comments mainly around how smart pigs miss=Pg19/42. On 14/19=wsj. is Olympic Pipelines majority owner since 2005 Enbridge’s 40-year-old, 30-inch pipeline ruptured near Marshall, Michigan, discharging more than 20,000 barrels of crude37 First reason: For the very first time for Puget Sound Energy & City of Bellevue barely glossed over two of the three forms of corrosion present on the Olympic Pipelines and fraudulently claim all is well. & the 2016 Conflict of interest law To quote City of Bellevue’s pipeline expert Wolfgang Fieltsch from Stantec. CoB had to go all the way to Toronto Canada to find someone foolish enough to lie about xxx. Even the two mitigate together, preventing two of them make the 3rd worse. That 3rd mode is AC induct corrosion and comes solely from being underneath PSE’s powerlines. Mode 1: normal chemical corrosion of putting a pipe in the ground, Mode 2: Stress corrosion while known for thousand of years since man first started working with metal it has been the Federal Office of Pipeline Safety’s full time position to cover it up since the Office was created in 1970. They changed due to their criminal jeopardy 2005 after three major stress corrosion pipeline failures in 2003. Two here in WA State both on the 30” Williams Co. natural gas pipeline 6 months apart and the 3rd spraying homes in the Chairman of the Energy Committee Senator John McCain’s Tucson AZ. PSE & City Of Bellevue have demonstrated criminal neglect with zero mention of it any EE EIS document published. 36 Terrorism and Oil & Gas Pipeline Infrastructure: Mar 2017 by FDIC & Univ of OK College of Law https://digitalcommons.law.ou.edu/cgi/viewcontent.cgi?article=1078&context=onej find=google "liability for petroleum pipelines" ; Belle Hillenburg, Nation’s Pipeline Increasingly at Risk of Cyber, Physical Attacks, HOMELAND SECURITY TODAY, (May 9, 2016, 6:00 AM), http://www.hstoday.us/single- article/nation-s-pipelines-increasingly-at-risk-of- cyber-physical-attacks/e55550d405dcb 5ba3f1 e9ca1cabc7757.html. 37 Oil-Pipeline Cracks Evading Robotic Smart Pigs, Wall St. J. (Aug. 16, 2013), http://www.wsj.com/articles/SB10001 424127887323455104579015140328479048. see also Daniel Gilbert, Big Spills from Aging Oil Pipelines, Wall St. J. (Apr. 15, 2013), https://www.wsj.com/articles/SB10001424127887323741004578418693982405224. see also ); Mike Lee, Decades of Ruptures from Defect Shows Perils of Old Pipe, Bloomberg (Sept, 2, 2013) Mode 3: AC inducted corrosion which PSE & City Of Bellevue have demonstrated criminal neglect and outright engineering fraud on review & analysis the known record which if allowed to stand will result in the deaths of thousands. Here is what Toyko Gas Company, a utility 10x the size of PSE with far greater resources and knowledge said. To quote their 2011 presentation/paper of at the International Gas Union Conference “Pipeline operators were shocked at the first occurrence of AC corrosion in 1986 and subsequent AC corrosion failures of modern pipelines in Europe and North America despite satisfying the protection potential criterion.” “It has been definitely shown by the occurrence of AC corrosion on a catholically protected pipeline that AC corrosion cannot be prevented by CP [catholic protection, what “protects” OPL currently] in the presence of very high AC voltage of a pipeline.” Please compare the resume & publication record of Fumio Kajiyama main author to Tokyo Gas Company’s paper to that of Mr. David Kemp with his BS in Mechanical Engineering. PSE’s Attorney “He is here this evening to speak to the science of co-location.” I have the BSME and a Master in Electrical Engineering (Electromagnetic propagation & antenna design) and years multiple domain corrosion prevention. How Mr Kemp was allowed to speak in a court of law as an expert on the topic of “ the science of co-location” of high power lines and pipelines carrying highly volatile liquid is massive failures on multiple fronts. Kemp’s pulp fiction papers including those in NACE allow him to be the fall guy by PSE when OPL breaks and kills 1000 from suffocation the latter fire. PSE and City of Bellevue’s has created a highly inadequate EE EIS and I believe a criminally fraudulent EIS. Those with broad US Navy systems design experience will immediate recognize the hundreds of false hoods in the PSE and City of Bellevue’s EE EIS. The recognition of these hundreds of propaganda spins/lies come from engineering design for long-term reliability (read up to decades), accelerated aging engineering (aka “shake &bake”) and corrosion effects across multiple domains. The US Navy designs systems such that it is known when they will likely fail and need to be decommissioned even with decades of use. Even with that methodology there are surprises. The for-profit pipeline and electric utility industry while less the 20% of the number of entities do not use any such methodology as it cuts profit margins and threaten their replacement with other technologies even as early as 1910. Their criminal behavior in their first 40 yrs of existence is well documented in the 1928 book Electric Utilities: A crisis in Public Control resulting dozens of Congressional hearings.38 Instead the Electric Utilities got the maximum Federal fine for convicted criminal activity to be just $3 million regardless of number of count or number of deaths. As PSE mentioned The Jefferson-Martin as a sample of a success of 230 kV project “constructed very close to a major gas pipeline.” This Jeffereson-Martin transmission line was placed into service in 2006” “ This project was 38 and turning hardcore conservative Republican Nebraska Senator George W. Norris to end up left of FRD on for-profit electric utilities. constructed with out incident” per Lowell Roger PSE’s Construction Mgr under oath.39 Mr Rogers has an extremely warpped sense of without indicent as 900 ft away when the 230 KV line transitioned form above ground to below the largest pipeline explosion to occur in the history of the Bay Area occurred on Sept 9, 2010 vaporizing 38 homes, destroying 50 and killing 8 injuring 64.40 to Pacific Gas & Electric was convicted of 10 felons (the FBI & Justice Dept tried to get Instead of using failure of pipeline of the same age, construction techniques corrosion prevention and design, PSE’s EE EIS selects a whole irreverent category of all failures in a less than 5 year time period (due to corruption in OPS data) of any pipeline of any age failing between ~2010-2015. This vastly underestimates a failure rate attributed to OPL as 1) hundred of thousands of miles of much younger pipelines are wrongly added making failure rate of an older pipe appear orders of magnitude better that it is. 2) None of the pipes were under a ¼ mile let alone 24 miles of near field AC inducted corrosion or for that matter any known inducted AC corrosion. Likely PSE will tell you that data is not kept. Certainly true at the Federal Office of Pipeline safety but not true within the industry. The facts are it is just that PSE did not want to pull it together. 3) And critically damaging to PSE’s/Bellevue’s/etc safety case is from a Tokyo Gas Company paper at the 2011 International Gas Union Conference. “It has been definitely shown by the occurrence of AC corrosion on a catholically protected pipeline that AC corrosion cannot be prevented by CP [catholic protection, what “protects” OPL currently] in the presence of very high AC voltage of a pipeline.”41 This information was submitted to Renton & Bellevue EE EIS comment in 2016 and 2017. Why has it not been disputed? An AC corrosion weaken OPL pipeline during a major earthquake could kill 1000s and shut auto/truck and aircraft delivery to all points south of Rendomd/Bellevue as they have guaranteed liquidation breaks from Energize Eastside monopoles. These breaks include shutting off fuel to SeaTac and Portland Airport. 4) Contrary to false/misleading testimony in Bellevue’s Admin Hearing PSE’s colocation directly on top of OPL is in fact unique in the world let alone the USA. The best ~100 fold less voltage from electric rail systems operating at 400- 2000 volts sharing a right of way with a natural gas pipeline. 39 pg 213 & 214/439 [30 Vol 1 Transcript.pdf] of City of Bellevue EE EIS, HEARING EXAMINER REPORT TRANSCRIPTS - VOL. 1 OF 3 From AUDIO RECORDING OF PUBLIC HEARING (3/28/2019, 3/29/2019, 4/3/2019 & 4/8/2019) 40 https://en.wikipedia.org/wiki/San_Bruno_pipeline_explosion The Koch-tapus propaganda machine has stricken the 10 felony convictions of PG&E including falsify information related to the incident. The Federal Judges orginal fine was $500 million but the Appeal court intervened informing the Judge they would take action against him just months from his retirement if he went over the maximum allowed fine of $3 million regardless the number of deaths 41 TOKYO GAS CO., LTD Pg2/21 STRATEGY FOR ELIMINATING RISKS OF CORROSION AND OVERPROTECTION FOR BURIED MODERN PIPELINES, Main author Fumio Kajiyama, http://members.igu.org/old/IGU%20Events/igrc/igrc2011/igrc-2011-proceedings-and- presentations/poster-papers-session-2/P2-43_Fumio%20Kajiyama.pdf IGU= International Gas Union “Pipeline operators were shocked at the first occurrence of AC corrosion in 1986 and subsequent AC corrosion failures of modern pipelines in Europe and North America despite satisfying the protection potential criterion. It was proven that AC corrosion was attributed to induced AC voltage on a pipeline caused by (1) application of high resistivity coatings, and (2) the increased tendency to locate pipelines paralleling HVAC electric power lines and/or AC powered rail transit systems. To prevent a recurrence of AC corrosion, corrosion engineers have urged the necessity of a new cathodic protection (CP) criterion for AC corrosion protection. However, there are no agreed-on criteria for AC corrosion protection.” PSE & City of Bellevue’s EE EIS falsely (fraudulently?) analyses any pipeline failure in the period from 2010-2015 when the correct analyzes should be all pipeline of the same age bracket at failure. Most long-term failure mechanisms follow a bathtub curve. PSE/CoB processes and actions have purposefully left out key information and actively suppressed its discovery and spread misinformation at public out reach including holding back public access to key so called independent experts when they are questioned under video taping. Some of that suppression by EE EIS staff & leadership was videoed & is on YouTube including the slapping of a camera out of a citizen’s hand at a Renton EE EIS public meeting ref=xxx. Much more would be posted if time allowed. Some of the key new information left out of all of the EE EIS documents came out in the City of Bellevue Mar/Apr 2019 Administrative Hearing on EE’s partial permit application and just as import new information from City of Renton’s EIS Consistency Analysis. From Renton we learn the new information of the ratio of old wooden H-frame to new steel monopoles and from the Admin Hearing we learn from Lowell Rogers, PSE’s construction manager, the pole foundation deeps 13 to 46ft. Every single one of these pole foundations is XXX1000X more deadly in Bellevue/Newcastle/Redmond right of away of 50 ft. Even assuming Renton’s 100ft right of way is accurate the same +1000X increase in danger is true depending on how far apart the 16” and 20” gasoline/jet fuel pipelines are spaced. Likely they are spaced farther apart but if not the 46 ft foundations guarantee a pipeline rupture during a major earthquake with or w/o liquid faction. The new reveled (and NEVER analyzed) information means that during a major earthquake the fewer and stiffer steel pole are far more like to fall over and rip out of the ground rupturing the 50 yr old ¼ inch thick steel pipes. If just 4 pole failovers breaking the OPL the +24 mile Eastside during a major earthquake +1 million gallons of the 12.8 million gallons that pass through Renton everyday. Even PSE say the max release of 372,162 gallon release of a single break.42 The 1999 Bellingham WA break spilled 237,000 gallons of gasoline from the 16” which has a flow rate of 228,000 gallons per hour43. Nothing has changed on pipeline safety since the Including City of Bellevue SEPA responsible official Carol Helland who as an attorney and former Bellevue Developmental Service Director actively working to prevent videoing of public meetings to document the false information City of Bellevue and PSE were verbally telling the public. Carol even went as far as slapping a camera out of my hand at Renton EE EIS public meeting. All of the information in this executive summary was never disclosed in ANY of the EE EIS documents and only reveled The switch from 144 small wooden H-frame (~288 poles 1ft in diameter) with 41 monopole. The facts 42 Pg 238/274 8841 barrels =372,162 which is magically the 16” 1990 pipe break scaled to a 20 inch pipe. 43 Pg 170/274 energize_eastside_phase_2_draft_eis_volume_2_appendices.pdf and 46,800 gallons/mile for the 16” pipe, 77,767 gal/mile for the 20”. Pole Installation at page 7 & 28/274 of same 2_draft_app pdf (Final EE EIS just refers to these draft phase2s. Lowell Roger testifies under oath that no design just act of God=FIND Background The facts that make the colocation of the Olympic Pipelines/PSE high voltage powerlines the single most deadly pipeline accident or terrorist attack waiting to happen. Why? Let us review the facts that the folks involved with approval EE are unaware of or purposefully choosing to ignore. 1. Energize Eastside is a repeat of local history. PSE’s 2007 fraud conviction for falsifying pipeline safety records is nothing new, nor is the deadly Energize Eastside (EE) fraud (not yet noted so by the courts). A book published in 1928 called Electric Utilities: A crisis in Public Control by seven Syracuse University professors documents the first 40 yrs. The for-profit monopoly US electric utilities had already a long record of racketeering by 1928. FDR used the book to win his first presidential election. The Seattle Library has the only the two copies in entire Pac NW.44 The book details the criminal activity of the Electric Utilities and their Trade(crime?) syndicate National Electric Lighting Assc., which decided to change its name in 1932 after dozens of Congressional Hearings detailed their activities. The new name Edison Electric Institute(EEI), is still alive and involved in EE if not directly spiritually. On Mar 9, 1931 PSE’s puppet master, the NELA, got Seattle Mayor Frank E. Edwards to fire Seattle City Lights Superintendent James D. "J.D." Ross. Edwards was in his 2nd term and had been elected by the largest mayoralty majority ever recorded in Seattle. Even so Mayor Edwards was promptly recalled by voters 4 months later. JD was reinstated to SCL and employed by FDR on multiple dam projects & placed on the Securities Exchange Commission. A careful review of the 100s of hours of video of Energize Eastside EIS & “public out reach” will show the same falsification tactics used by NELA/EEI if not out right participation. 2. A taste of the massive propaganda machine of the for-profit corporate-socialist Electric Utility Companies like PSE, PG&E SoCalEd etc. Descriptions=Bernard J. Mullaney was former head to the US War Department Office of Propaganda for all of WW1; NELA = National Electric Lighting Association . Here is the taste from Corporate Public Relations A NEW HISTORICAL PERSPECTIVE 1987 by Marvin N . Olasky The University of Texas at Austin. In 1919 “Over $100,000 went to E. Hofer and Sons, a firm located in Salem, Oregon, away from major media centers. Annual payments of $84,000 from Insull's NELA allowed Hofer to send out almost 13,000 newspaper articles annually. The articles usually appeared as unattributed, "original" editorials. Use of such services was only a first step, though. Soon industry front groups began sending out enormous numbers of public relations "news re- leases." For example, in 1920 and 1921 "five million pieces of literature" were circulated in Illinois alone by the Illinois Committee on Public 44 Book is impossible to buy online. Call/txt me at to know how to get a pdf version or other key books detailing the massive +130 year criminal fraud of the corporate socialist monopolies electric utilities. Utility Information, headed by Insull's top public relations aide, Bernard J. Mullaney. Mullaney deliberately sent newspapers huge amounts of accurate copy to accustom editors to reliance on his work. Only after full trust was established would he begin slipping in a few fast ones. Mullaney noted proudly that his work became most valuable only when saturated editors began lowering their guard. Public relations managers working in other states reported similar successes.45 3. The 24 mile colocation of PSE/OPL one of a kind in the entire world – no other local/state or national government has allowed liquid gasoline lines to travel directly underneath 115kV line for miles let 24 miles. PSE approved the Olympic Pipeline Company to build directly under PSE existing 115 kilovolt power lines in 1964, 6 years before Congress was forced to create the Federal Office of Pipeline Safety (OPS). The Law was signed Aug 12, 1968 but OPS didn’t open its doors until 197046. The 16” OPL line was already in operation in 1965 with the 20 inch operating in 1972. The 16 inch OPL was built with corrosion protection obsolete even in 1960. That obsolete protection is coal tar slathered on to the outside of the pipe to protect against only 1 of the 3 corrosion mechanisms the Olympic pipeline are experiencing. Some might say well they have been in the ground since 1965 and all is well and good, how could this be true? These failures take several decades to occur and have happen quite regularly as even the FDIC in 2017 is starting to document given it ability to destabilize the banking industry. Even though the 42 pg paper is called Terrorism and Oil & Gas Pipeline Infrastructure47. they spend more time on the massive ineffectiveness of OPS preventing or even detecting pipeline breaks than. Here a just one quote relevant to OPL “According to a Reuters review of PHMSA data, since 2010, there have been at least 466 incidents in which a pipeline carrying crude oil or refined products has leaked. Of those, only 105, or 22%, were identified by an advanced detection system.” 4. The new 2019 Pipeline safety laws still have zero requirement for any automatic pipeline shut off system. OPL has zero real-time leak detection, same as during the 1999 Bellingham spill of 237,. OPL only 5. with ZERO effective measurement to gage when to preemptively replace. See OPS’s final report on the two 2003 Williams Pipeline explosions in WA, pg XXX. 6. Contrary to testimony in the Bellevue EE Administrative Hear by PSE’s construction manager Lowell Rogers so called Professional Engineer from his one man shop Oak Strategic, Inc. Deep pockets to sue there when the +$10 billion dollar disaster happens. Approving Energize Eastside increasing that danger by at least +100 fold for earthquake while increasing the odds of a $2000 terrorist attack on the 16” and 20” Olympic Pipelines simultaneously highly X1000 fold. The Cost is simply the cost of two 100 ft ½ inch steel cables tied to several 6ft steel tree stakes driven down to each OPL pipelines. I am leaving out several other key steps to get the success rate 45 24.BernardJ.Mullaney,"EstablishingPublicRelations,"GasAgeRecord,October 28, 1922, p. 577; Gruening, p. 19. Also see Insull, Public Utilities in Modem Life (Chicago: Privately printed, 1924). 46 www.phmsa.dot.gov/sites/phmsa.dot.gov/files/docs/Natural%20Gas%20Pipeline%20Safety%20Act%20of%201968.pdf 47 Terrorism and Oil & Gas Pipeline Infrastructure: Mar 2017 by FDIC & Univ of OK College of Law https://digitalcommons.law.ou.edu/cgi/viewcontent.cgi?article=1078&context=onej find=google "liability for petroleum pipelines" of up to ~100% rupture of both lines. The current 115 kV lines yield very low maybe 0.1% chance of single pipeline rupture, both pipelines ~0.01%. Doubling the voltage and the increase in amperage yields x1000 increase in terrorist attack. I put a single line in about this in my 17 page 2014 paper on PSE’s fraudulent Energize Eastside. But the willful criminal neglect and likely out right fraud of City of Bellevue attorneys & senior staff force me to detail. The two lawyers are 1) Carol Helland EE EIS SEPA responsible official, and Development Servvices Director who quit to work in City of Redmond when video of her surfaced attacking a Bellevue resident videing City of Bellevue & contractors lying to citzens at a Rent EE EIS public presentation. See on Youtube XXXXX. 2) Matt McFarland Assistant City of Bellevue Attorney. This double attack occurring miles apart, if timed during the correct windflow would take out both the Boeing Renton facility and surprising to even me the I-90 bridge even assuming PSE fake max spill number of 371xxx gallon for the 20inch line. While PSE simply scales the xxx gallon of the 1999 Bellingham WA release for the 16” pile to the 20” pipeline maximum gasoline of One key and new piece of information brought to light from the City of Bellevue Administrative Hearing Mar/April 2019 is the pole foundation depths, which was never disclosed nor analyzed in Puget Sound Energy’s Environment Impact Statement. Per pg Here is What Renton is going to get if it approves Energize Eastside: A giant 5G antenna farm. It will look like above except on EVERY Energize Easide pole. PSE’s near zero ROI (less than 1%) on the company in general, since 2007, also means significant “Scenic Views and Aesthetics” decrease as PSE’s pole =2x height increase allow for new business model of 5G antenna farm on every pole. 5G has a +100X increase in number of antennas needed over 4G. If EE is approved, new Federal laws on 5G/etc mean the City of Renton will have zero local control what PSE does on aesthetic. Renton’s industrial look will significantly expands into residential area as PSE’s Renton antenna farm services the west side of Mercer Island far cheaper than PSE’s Mercer Island light poles.