Press Alt + R to read the document text or Alt + P to download or print.
This document contains no pages.
HomeMy WebLinkAboutExhibit_22_PSE_Memo_Expert_Testimony_Attachments
99640
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
PUGET SOUND ENERGY’S HEARING
MEMORANDUM - 1
719 Second Avenue Suite 1150
Seattle, WA 98104
(206) 623 -9372
The Honorable Phil Olbrechts
BEFORE THE HEARING EXAMINER
FOR THE CITY OF RENTON, WASHINGTON
In re: Renton Land Use Matter
LUA18-000055
Puget Sound Energy, Inc.
Energize Eastside Conditional Use Permit
File
PUGET SOUND ENERGY, INC.’S
HEARING MEMORANDUM
Applicant Puget Sound Energy, Inc. (“PSE”) presents this Hearing Memorandum
in support of its application for a Conditional Use Permit (“CUP”) to upgrade and operate
approximately 4 miles of two 115 kV transmission lines in the cit y of Renton (“City” or
“Renton ”) with two 230 kV transmission lines (“Project”) in an existing utility corridor.
The Project is a critical component of an approximately 16-mile electric system upgrade
required to bring PSE’s system into compliance with federally-required planning criteria
by increasing transmission reliability on the Eastside, including Renton.
The Renton PSE upgrade is part of the larger Energize Eastside Project that would
also occur in the cities of Bellevue, Redmond, and Newcastle, and in unincorporated King
County.1 The Project in Renton would replace approximately 144 existing wood and steel
1 The City of Bellevue Hearing Examiner recently approved a conditional use
permit required to build the Richards Creek substation and the south segment of the
Energize Eastside Project. See City of Bellevue Hearing Examiner, Findings of Fact,
Conclusions and Decision on the Conditional Use Permit Application for the South
99640
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
PUGET SOUND ENERGY’S HEARING
MEMORANDUM - 2
719 Second Avenue Suite 1150
Seattle, WA 98104
(206) 623 -9372
poles of H-frame design with approximately 41 steel monopoles of double-circuit design.
The transmission line upgrade would be entirely within the existing 100-foot wide
transmission line corridor rather than being sited in an entirely new, presently non-
existent, corridor. The Project also includes some limited upgrades to the the Talbot Hill
substation located in Renton but these substation upgrades do not, themselves, trigger a
CUP and so are not part of this review.2
Renton was a partner city to the evaluation of the entire Project under the State
Environmental Policy Act (“SEPA”), a nearly 4-year process that included multiple
scoping meetings, public comment periods and public informational meetings. In
conjunction with Renton and the other partner cities of Redmond, Kirkland and
Newcastle, Bellevue as the nominal SEPA lead agency published a Phase 1 and a Phase 2
Draft Environmental Impact Statement (“DEIS”). The Phase 1 DEIS conducted a
programmatic review of multiple Project alternatives. The Phase 2 DEIS conducted a
focused review of overhead transmission line route alternatives and impacts. The Final
EIS (“FEIS”) assessed the impacts of certain routing alternatives proposed for the Project,
including the existing corridor presently occupied by PSE’s 115 kV lines . The existing
corridor was determined to be the least impactful alternative and was selected as the final
route for the upgrade. The FEIS contained a variety of impact mitigation
recommendations to the various cities that could further reduce Project impacts and meet
land use code criteria.
Bellevue Segment of the Energize Eastside Project (June 25, 2019) (attached as Exhibit
A). This decision was upheld unanimously on appeal by the Bellevue City Council. See
City of Bellevue, Ordinance 6494 (Dec. 2, 2019) (attached as Exhibit B).
2 Specifically, additional breakers and associated controls would be added within
the existing substation to accommodate the upgraded high voltage transmission lines
(“HVTLs”)).
99640
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
PUGET SOUND ENERGY’S HEARING
MEMORANDUM - 3
719 Second Avenue Suite 1150
Seattle, WA 98104
(206) 623 -9372
Following publication of the FEIS, Renton also conducted its own EIS consistency
review during evaluation of the CUP application. The City retained EA Engineering,
Science, and Technology, Inc. (“EA”), which engaged subconsultants PBC, Landau
Associates, Grette Associates, Cultural Resource Consultants and ECONorthwest to
confirm that PSE’s CUP application fell within the range of environmental impacts
analyzed in the DEISs and FEIS.3 As indicated in its November 26, 2019 Environmental
Consistency Analysis (“ECA”) report, EA confirmed that the proposal before the City is
within the range of development and probable environmental impacts analyzed in the
SEPA environmental review for the Renton segment of the project, and that there are no
significant unavoidable adverse impacts that cannot be mitigated. Minor additions to and
clarifications of mitigation measures identified in the EIS, CUP and Shoreline Exemption
application materials were recommended by EA based on the ECA.4
The ECA was then reviewed and approved as satisfactory and the imposition of
the ECA’s conditions on the CUP were recommended by the Renton Environmental
Review Committee on December 13, 2019 in accordance with Renton Municipal Code
(“RMC”) 4-9-070(M)(5). In turn, the conditions were all incorporated into the Department
of Community and Economic Development’s Staff Report, which recommends Hearing
Examiner approval of the CUP subject to imposition of the ECA conditions.5 PSE has
agreed to the imposition of all the ECA conditions via the CUP, save a request for a slight
modification of Staff Recommendation J.3, which is described in detail in Section II.B,
infra.
3 Department of Community and Economic Development Staff Report (“Staff
Report”), Exhibit 2 (Environmental Consistency Analysis—Energize Eastside Project
(Nov. 21, 2019)) at p. E-2.
4 Staff Report, Exhibit 2 at Ch. 3.
5 Staff Report at p. 17 (Recommendation J.1).
99640
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
PUGET SOUND ENERGY’S HEARING
MEMORANDUM - 4
719 Second Avenue Suite 1150
Seattle, WA 98104
(206) 623 -9372
The Project is located within multiple zoning designations.6 The Project is defined
as a “Utility, Large” land use under Renton Municipal Code (“RMC”) 4-11-210. This use
is allowed in each zoning district subject to issuance by the Hearing Examiner of a CUP.
See RMC 4-2-060; RMC 4-8-070(H)(1)(d)). The criteria that the Hearing Examiner’s
decision must be based on are set forth in RMC 4-9-030(D)(1) through (8), including
consistency with the goals and policies of the Renton Comprehensive Plan. See RMC 4-9-
030(D)(1). The table contained in Exhibit C hereto sets forth the applicable City
regulations and makes citations to where the materials can be found in the Administrative
Record that demonstrate how this Project complies with these criteria. Because this matter
is not a SEPA EIS adequacy appeal, the EIS should be treated as sufficient and final.
See generally, WAC 197-1 l-680(3)(a) (Challenge to the adequacy of an FEIS must be
raised at the same time as the administrative appeal of the underlying governmental
action).
The City’s Staff Report and PSE’s CUP Application detail how the Project
complies with the specific criteria set forth in the City’s Comprehensive Plan (“CP”) and
RMC. The evidence to be received at the public hearing, both orally and in writing, will
provide further evidence of how the Energize Eastside project meets the criteria for
approval. This Memorandum sets forth limited additional analysis to aid the Hearing
Examiner in his review of the City’s robust environmental review and permitting record.
I. REGULATORY BACKGROUND
A CUP may only be granted when the proposed project is consistent with the
RMC. Pursuant to RMC 4-9-030(F)(8), the Hearing Examiner must issue a CUP upon on
a determination, in writing, that the proposed use satisfies the applicable decision criteria
6 Staff Report at p. 2 (C.2).
99640
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
PUGET SOUND ENERGY’S HEARING
MEMORANDUM - 5
719 Second Avenue Suite 1150
Seattle, WA 98104
(206) 623 -9372
in RMC 4-9-030(D)(1) through (8). Here, no land use change will result from the Project:
transmission poles and wires have been a part of the existing character of the affected
areas for nearly 100 years. The event requiring a CUP is the ‘intensification’ of the
existing use from double-circuited 115 kV HVTLs to imperceptibly thicker 230 kV
HVTLs at a higher elevation and supported with fewer poles than exist today. The City’s
Staff Report and PSE’s CUP Application, as well as the testimony that will be provided at
hearing, demonstrate that the Project satisfies all applicable criteria.
II. ARGUMENT
Approval of the Project requires the Hearing Examiner to conclude that the
requirements of RMC 4-9-030(D)(1)-(8) are satisfied. In consideration of the size of the
permit file, the table attached hereto as Exhibit C provides citations to where, in the
Administrative Record, evidence supporting each criterion for CUP approval can be
found.
A. The Project satisfies all Renton CUP criteria.
i. RMC 4-9-030(D)(1): Consistency with Plans and Regulations
The City’s Comprehensive Plan vision is for a thriving, opportunity-rich
community. A lack of reliable power service would adversely affect Renton’s ability to
attract and retain businesses and residents. See Comprehensive Plan Land Use (“L”)
Elements L-B; L-2; L-J; Economic Development (“ED”) Element ED-14; Community
Planning (“CP”) Element CP-B; and Utility (“U”) Element U-A, U-5. Provision of
reliable electrical infrastructure, including the Energize Eastside project bringing a 230-
kV power source to the Eastside including Renton, fosters PSE’s compliance with
regulatory obligations of the utility and facilitates the City’s vision by providing electrical
resources that will support new residential and commercial facilities contributing to the
health of the community. Id. This investment in infrastructure supports Renton’s planned
99640
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
PUGET SOUND ENERGY’S HEARING
MEMORANDUM - 6
719 Second Avenue Suite 1150
Seattle, WA 98104
(206) 623 -9372
and projected growth while maximizing existing land use compatibility and minimizing
adverse impacts by stakeholder-informed design and use of the existing corridor partially
shared with Olympic Pipeline Company, rather than developing an entire new corridor.
See Renton Comprehensive Plan, U-2, U-72, U-73; U-3, U-4, U-5, U-7, U-O; L-55, L-56,
L-62.
No tree removal is proposed in the area of the Cedar River shoreline nor is
mitigation. See Renton Comprehensive Plan, Shoreline (“SH”) SH-7; U-46. Other tree
removal will occur within the existing managed transmission line corridor where trees are
trimmed or removed on a regular maintenance cycle to ensure compliance with electrical
safety clearances. See Renton Comprehensive Plan, L-B, L-P, L-35, L-55, L-56; U-A, U-
2, U-3, U-5, U-6; U-73. Tree replacement will generally occur at a ratio of greater than
1:1 mitigation to impacts. See Renton Comprehensive Plan, L-B, L-P, L-24, L-62; U-A,
U-72; Staff Report, Exhibit 8. Proposed new poles are sited to avoid direct impacts to
wetlands or streams, and all impacts are avoided within the shoreline jurisdiction,
including all flood hazard areas.7 See Renton Comprehensive Plan, L-B, L-P, L-24, L-35,
L-55, L-56; U-A, U-46, U-72; SH-7.
Design revisions have been made where feasible to minimize impacts where
avoidance is not possible, and Best Management Practices and construction techniques
will be used to minimize impacts to the built (including transportation, public
accessibility, other utility infrastructure) and natural (erosion hazard areas, landslide
hazard areas, steep slopes) environment. See Renton Comprehensive Plan, L-P, L-35, L-
56; U-3, U-5, U-7, U-43. Beyond these measures, PSE has led all northwest utilities in
energy conservation since 1979. See Renton Comprehensive Plan, L-62. Taken as a whole
7See Exhibit D (PSE Shoreline Exemption memo); Exhibit E (email from
Department of Ecology concurring with Shoreline Exemption analysis).
99640
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
PUGET SOUND ENERGY’S HEARING
MEMORANDUM - 7
719 Second Avenue Suite 1150
Seattle, WA 98104
(206) 623 -9372
and in balance with each other, the Renton Comprehensive Plan is robustly addressed by
and reflected in the Energize Eastside project. Further compliance with zoning regulations
and other applicable requirements is addressed below.
ii. RMC 4-9-030(D)(2): Appropriate Location
The Project is proposed to be located in the identical corridor where PSE’s
transmission infrastructure exists today. Selection of this route was significantly informed
by the DEISs and FEIS prepared for the proposal, which demonstrated that it was less
impactful on the built and natural environment than the other route alternatives studied.
Logically, the development of an entirely new corridor would result in greater impacts to
the environment including the clearing of vegetation, acquisition and development of new
access points, new effects on view sheds presently without transmission infrastructure,
and introduction of a new land use where it had not previously existed.
Conversely, the industrial, commercial and residential land uses along the existing
route developed over time after the corridor already existed. Those uses emerged with the
full awareness of the adjacent use of transmission facilities, confirming that the uses are
compatible with each other. In fact, they have co-existed peaceably these many decades.
The FEIS concludes the same, finding that the upgrade to the transmission system where it
presently exists will not cause any new, significant adverse impacts to the environment in
Renton, including land use compatibility.8 The proposed location is suited for the Project
and will not result in the detrimental overconcentration of a particular use within the City
or within the immediate area of the proposed use.
8 See Staff Report at Exhibit 18 (EIS at 4.1-20-21).
99640
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
PUGET SOUND ENERGY’S HEARING
MEMORANDUM - 8
719 Second Avenue Suite 1150
Seattle, WA 98104
(206) 623 -9372
iii. RMC 4-9-030(D)(3): Effect on Adjacent Properties
See discussion above. The proposed use at the proposed location is identical to the
use that exists today. Upgrading the existing system to fewer taller poles will not result in
new substantial or undue adverse effects on the adjacent properties with which it has co-
existed for nearly 100 years. See Exhibit C (Compliance Chart) at p. 2.
iv. RMC 4-9-030(D)(4): Compatibility
See discussion above. The proposed use at the proposed location is identical to the
use that exists today. Upgrading the existing system to fewer taller poles will not result in
new substantial or undue adverse effects on the adjacent properties with which it has co-
existed for nearly 100 years. See Exhibit C (Compliance Chart) at pp. 2-3.
v. RMC 4-9-030(D)(5): Parking
Operation of the transmission system in the existing corridor will not make use of
existing neighborhood parking or demand new parking. Temporary parking during
construction will be established consistent with the parking plan submitted to the City’s
planning project manager, which will be reviewed prior to the issuance of construction
permits. See Staff Report, p. 17 (Recommendation J.4); Exhibit C (Compliance Chart) at
pp. 3.
vi. RMC 4-9-030(D)(6): Traffic
A transportation management plan will be developed and submitted for City
approval prior to the start of construction to ensure safe and continuous pedestrian and
vehicular traffic circulation in areas of construction. See Staff Report at p. 17
(Recommendation J.5). The plan will be presented to the City Plan Review Section for
review, modification as necessary, and approval in advance. This way, disruptions to
pedestrian and vehicular circulation will be minimized to the maximum amount feasible.
See Exhibit C (Compliance Chart) at p. 4.
99640
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
PUGET SOUND ENERGY’S HEARING
MEMORANDUM - 9
719 Second Avenue Suite 1150
Seattle, WA 98104
(206) 623 -9372
vii. RMC 4-9-030 (D)(7): Noise, Light and Glare
Consistent with the Staff Report determinations at pp. 14-15 and the Project EIS,
the Project will not any significant noise, light or glare impacts. The proposed
transmission line replacement will cause temporary construction-related noise impacts,
including the potential use of helicopters for line stringing, but operational noise impacts
are negligible. See Staff Report, Exhibit 18 (FEIS at 1-13); Phase I DEIS at 9-14
(assessing potential operational noise impacts) (attached hereto as Exhibit G).9
Construction noise impacts would terminate once construction is complete and during
construction PSE will comply with all City, County and FAA codes relating to hours of
construction and noise. Given the temporary nature of potential noise impacts and PSE’s
obligation to comply with all related requirements to mitigate noise impacts, there would
be no unavoidable significant adverse noise impacts. See also Staff Report, Exhibit 18
(EIS at 1-13); see also Exhibit G, Phase I DEIS at Table 9-4; Staff Report, Exhibit 17
(Phase II DEIS at 4.1.1 and 4.4.9). Light and glare impacts would be de minimis as the
transmission poles themselves are not lit and the steel poles will be made of a non -
reflective material. See Exhibit C (Compliance Chart) at p. 4.
viii: RMC 4-9-030 (D)(8): Landscaping
The Project limits vegetation impacts by siting the upgraded facilities in an already
disturbed corridor managed for utility use. PSE has developed a vegetation management
plan that requires replanting to fully mitigate for impacts to vegetation and habitat ,
9 PSE attaches Phase I of the Draft EIS as an Exhibit to ensure that the Hearing
Examiner has a full copy of the complete the SEPA record for the Energize Eastside
project. Sections that PSE finds particularly demonstrative of CUP criteria compliance are
cited in Exhibit C (Compliance Chart).
99640
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
PUGET SOUND ENERGY’S HEARING
MEMORANDUM - 10
719 Second Avenue Suite 1150
Seattle, WA 98104
(206) 623 -9372
including a focus on improving habitat for pollinators.10 Under PSE’s Vegetation
Management Plan and CUP conditions, PSE’s vegetation removal mitigation provides a
greater than 1:1 ratio of removed to replanted vegetation (although trees replaced along
the corridor will remain subject to the height limits imposed now to ensure compliance
with federal standards (NERC FAC-003-04)).11 Notably, the Project design was further
refined based on stakeholder input, so there would be no work/disturbance in or to the
jurisdictional shoreline of the Cedar River.
The remaining analysis in Section II, infra, first requests a minor modification of
Staff Recommendation J.3 and then speaks to issues that have arisen during City and
stakeholder review of the Project and which are likely to be raised during the public
hearing.
B. Request for Slight Modification of Staff Recommendation J.3.
PSE has reviewed and agrees to all conditions set forth in the City’s Staff Report
and associated EIS Consistency Analysis, but requests a slight modification to Condition
J.3, concerning limited artwork on transmission line poles, to ensure that the Energize
Eastside project can proceed in a timely manner. The following language shows the Staff
Recommendation J.3 with modifications proposed by PSE in tracked changes:
Individual art wraps for the transmission line poles shall be submitted to
the Current Planning Project Manager for review and approval prior to the
issuance of a Construction Permit. PSE will install art wraps at up to 12
transmission line pole locations (including those previously discussed and
identified by the City at the Renton Technical College and on publicly
visible PSE-owned property). Artwork shall be installed prior to the
10 See Staff Report at 17 (Recommendation J.2); Staff Report, Exhibit 8 at 21
(providing pollinator habitat plan).
11 See Staff Report at 17 (Recommendation J.2); Staff Report, Exhibit 8 at 21
(providing pollinator habitat plan).
99640
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
PUGET SOUND ENERGY’S HEARING
MEMORANDUM - 11
719 Second Avenue Suite 1150
Seattle, WA 98104
(206) 623 -9372
energizing of the transmission line, or as otherwise approved by the
Current Planning Project Manager, but at no point will art installation
delay the transmission lines from being energized.
PSE previewed this language with the City’s planning staff and understands that they have
no objections to the slight modifications, which insure timely implementation of the
condition without giving rise to a possible delays in energizing the lines.
C. Propriety of Pipeline Co-location
For 0.4 miles in Renton (approximately half of which is in unincorporated King
County), the existing 115 kV HVTL system is co-located in the same utility corridor as
Olympic Pipeline Company’s (“OPL”) fuel pipeline. These two utilities have co-existed in
this shared corridor for nearly half a century. Nevertheless, the proposed location of new
230kV HVTL in the same corridor as the OPL pipeline raised questions about public
safety among stakeholders.
While it is not uncommon to co-locate HVTL and pipelines, as Lowell Rogers,
Prinicipal at Oak Strategic will testify, and is encouraged by Renton Comprehensive Plan
(see CP U-3), transmission lines located in proximity with petroleum pipelines can
potentially increase the risk of AC interaction, such as fault events and pipeline corrosion.
With this in mind, PSE used a thorough and iterative engineering process to determine the
co-location proposed for the Project. This process was informed by the two-phased EIS
and additional study regarding the potential effects of alternating current (“AC”)
electricity on nearby underground pipes. Based on the results of the study PSE further
adjusted routing, wire configuration and operational parameters to further limit potential
pipeline interactions.
Transmission lines existed in the corridor first, well before the pipeline.
Moreover, generally the pipeline company is responsible for monitoring the potential for
99640
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
PUGET SOUND ENERGY’S HEARING
MEMORANDUM - 12
719 Second Avenue Suite 1150
Seattle, WA 98104
(206) 623 -9372
interaction between the pipeline and transmission lines post construction, as David
Kemp—an DNV-GL engineer and expert on electrical facility and pipeline
interactions−will testify. Nevertheless, PSE engaged with this work proactively and
incorporated electric system recommendations made by Mr. Kemp and his team to
minimize interactions by proposing operating both transmission lines at 230 kV, using a
delta wire configuration, and installing additional safety features (e.g., a low impedance
shield wire). Additionally, the line will be built to comply with the National Electric
Safety Code—which in many cases exceed 21st century building standards—that account
for extreme weather and seismic events. These design and operational parameters, which
keep interaction between the transmission lines and pipelines below industry thresholds
for risk, effectively minimize and mitigate for Project impacts related to pipeline safety.
This is not PSE’s opinion alone; as part of the EIS development, the Partner Cities
engaged an independent consultant (Stantec), Dr. Wolfgang Filtch, to review the proposed
alignment and review DNV-GL/PSE’s work. See Staff Report, Exhibit 18 at Ch. 4.9;
Exhibit F (Stantec, Technical Review− Energize Eastside AC Interference Analysis (May
2, 2017)). Stantec concurred that DNV-GL’s study complied with industry standards and
recommended conditions, which are reflected in the conditions recommended in the ECA,
that effectively reduced potential risks associated with co-locating a transmission line with
pipeline facilities.12
D. Existing character of neighborhoods includes HVTL infrastructure.
PSE anticipates that the public may comment that the transmission line upgrade is
incompatible with the existing character of neighborhoods. Substantial evidence in the
12 See Staff Report, Exhibit 2 at pp. 3-9−3-15 (setting forth required pipeline safety
conditions).
99640
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
PUGET SOUND ENERGY’S HEARING
MEMORANDUM - 13
719 Second Avenue Suite 1150
Seattle, WA 98104
(206) 623 -9372
record and evidence that will be presented at hearing rebut this position.13 PSE proposes
that the transmission line upgrade occur in the existing utility corridor, which was
established in the late 1920s and early 1930s. Properties adjacent to the existing
transmission lines are generally subject to utility easements, and the adjacent and nearby
land uses were developed largely after the original utilities were installed. As development
occurred and the City grew, the utility corridor containing transmission lines became
integrated into adjacent residential uses. Siting the transmission line in a new utility
corridor would cause new and greater impacts to residents that are not currently adjacent
to transmission lines.14
Notably, the FEIS did not identify any significant adverse visual or aesthetic
impact associated with the upgrade of the existing lines.15 Nonetheless, PSE undertook
additional design work to refine pole placement, reduce the number of poles, propose the
least impactful pole color, decrease pole height and use more streamlined pole designs.
Based on these design features, the potential for aesthetic and land use incompatibility
was further minimized. The proposed transmission lines follow the existing route of
HVTL lines that are today already adjacent to or near all existing land uses in Renton. To
the extent stakeholders contend that the increased conductor heights and fewer poles will
13 See, e.g., Staff Report at pp. 11-12; Staff Report, Exhibit 18 at Ch. 4.1-20−21
(finding no significant land use impacts); 4.2-44—4.2-49 (concluding that “[i]mpacts to
the scenic views and the aesthetic environment in the Renton Segment would be less-than-
significant.).
14 See, e.g., Staff Report, Exhibit 17 at p. 3.4-25 (Table 3.4-1 comparing tree
removal impacts of using the existing transmission line corridor as opposed to siting a
new transmission line corridor).
15 See Staff Report, Exhibit 18 at Ch. 4.2-44—4.2-49.
99640
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
PUGET SOUND ENERGY’S HEARING
MEMORANDUM - 14
719 Second Avenue Suite 1150
Seattle, WA 98104
(206) 623 -9372
lead to adverse changes in property values, the EIS expressly found otherwise.16
Moreover, any non-significant impacts must also be considered in balance with Renton
Comprehensive Plan criteria that prioritize ensuring reliable power and planning for
economic and population growth, and siting new utilities in the existing transmission line
corridor.17
E. Project Not Impermissibly Bifurcated.
PSE anticipates testimony and/or argument at the hearing to the effect that the
CUP before the Renton Hearing Examiner is the result of impermissible permit
bifurcation of a single project. It may be suggested that failure to submit a single
application for the entire project prevents the Hearing Examiner from understanding the
project’s compliance with the RMC, thereby preventing him from ruling on the CUP. This
argument fails as a matter of law and fact.
Linear projects such as rail lines, transmission lines, or pipelines frequently cross
through multiple cities and counties. Every jurisdiction through which the facility travels
has its own– and very different− comprehensive plans, land use codes and development
regulations to be applied. Procurement of the development and construction permits for
such linear facilities is often broken into various stages, even within a single jurisdiction.
This is a practicality of infrastructure development, and is a lawful industry practice.
Here, the part of the Energize Eastside facility proposed for a CUP in Renton is
subject only to the RMC. PSE legally cannot submit the entire project to a single
municipal permit process, because other cities with jurisdiction over the project must
apply their own codes and have no authority to apply Renton’s. Furthermore, it is not
16 See Staff Report, Exhibit 17 at Ch. 3.10; Exhibit G (Phase I DEIS) at 10-21—
10-22 (summarizing review of studies analyzing the potential for economic impacts to
property value).
17 See CP U-O, U-1, U-68; CP at Appendix C.
99640
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
PUGET SOUND ENERGY’S HEARING
MEMORANDUM - 15
719 Second Avenue Suite 1150
Seattle, WA 98104
(206) 623 -9372
lawful to conduct a consolidated single hearing in a single jurisdiction where all cities’
hearing examiners attend and receive testimony simultaneously for later consideration.
See RCW 36.10B.110(7).
Segmentation of environmental review, however, is a concept that exists under
Washington law, but it is specific to SEPA. Evaluating the entirety of a single project for
environmental impacts is required under WAC 197-11-060(3)(b) unless phasing is
contemplated under WAC 197-11-106(5). A CUP, however, is not subject to the same
limitations because it serves a different purpose (providing for a more focused review of a
proposal’s compliance with local decisional criteria in order to allow a permitted use to
proceed with conditions that ensure compatibility). To the extent the Hearing Examiner is
presented with a SEPA-like argument for the proposition of impermissible permit
bifurcation for Energize Eastside, this principle has not been extended to land use
permitting in Washington.
It is note-worthy that the EIS studied the entire project, from Renton to Redmond,
in a single process– there was neither impermissible segmentation nor phasing of the
SEPA review. Regardless, to the extent it is contended the EIS was improperly scoped or
bifurcated, that issue is not before the Hearing Examiner. This proceeding is strictly a
permit review hearing, not a SEPA appeal hearing. The adequacy of the EIS is a verity for
purposes of evaluating PSE’s application to Renton for a CUP.
F. Only the Energize Eastside HVTL proposal is before the Hearing
Examiner.
PSE anticipates that some members of the public may offer new “alternatives” at
hearing as a basis for denial. PSE is seeking approval of a CUP for the upgrade of existing
high voltage transmission wires in the same utility corridor. That stakeholders wish that a
different project had been proposed using different routes or technologies is of no avail.
99640
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
PUGET SOUND ENERGY’S HEARING
MEMORANDUM - 16
719 Second Avenue Suite 1150
Seattle, WA 98104
(206) 623 -9372
The RMC does not give the Hearing Examiner authority to reject the proposal simply
because he or others may prefer a different hypothetical solution. The City and Hearing
Examiner only have the authority to approve, disapprove or approve with conditions the
proposal presented to it. RMC 4-9-030.F.8.
G. Project underwent robust public review.
It is anticipated that stakeholders will argue that insufficient engagement about this
proposal has occurred to inform the public and decision-maker about whether it merits a
CUP. There is no substance to this position. Renton spent almost two years reviewing the
proposal, and provided for public comment in accordance with the RMC. Although the
comment period lasted between March 14th and March 28th, 2018, the City continued to
receive and accept public comment up to the time of hearing. Indeed, the public was given
extra time to prepare for this hearing by reaching out to the Mayor, ex parte and without
notice to City legal or planning staff or the Applicant, t o obtain an extension of the
hearing date from the City’s initially proposed December 17, 2019 hearing.
In addition to the public engagement solicited directly by Renton, PSE has worked
for years across the Eastside to identify and expand its understanding of community
concerns as well as municipal land planning requirements that relate to this project. To do
so, the company began a number of initiatives early in the planning stage that ran on dual
tracks. PSE conducted an in-depth, multi-year community outreach effort to share
information and review and gather feedback on potential route options. It also
collaborated with local cities, residents, businesses and a 24 -member Community
Advisory Group to examine various routes. In all, PSE held 22 public meetings and nearly
550 project briefings with stakeholders, neighborhoods and cities. It mailed multiple
postcards and newsletters, and received nearly 3,000 comments and questions about the
99640
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
PUGET SOUND ENERGY’S HEARING
MEMORANDUM - 17
719 Second Avenue Suite 1150
Seattle, WA 98104
(206) 623 -9372
project. PSE has a public, project-specific website that contains the library of documents,
studies, briefings and other materials related to the proposal.
In September 2016, PSE began offering to meet with property owners along the
existing corridor to talk about site-specific designs for Energize Eastside. PSE shared its
current design for each owner’s specific property, including pole locations and how access
to those locations was proposed during construction.
Beyond this, a nearly four-year environmental review process was conducted
jointly by Renton, Newcastle, Bellevue, Redmond and Kirkland. At various stages, public
input was obtained via public meetings and open houses, in addition to the two expanded
public comment periods provided to review and comment on the Phase I and II DEISs.
In sum, the amount of review this Project has received far exceeds that of any
other transmission project ever undertaken by PSE. See, e.g., Exhibit A at ¶ 48. There has
been no deficiency in the number of opportunities that the public has had to engage in this
Project.
H. Project Need and Solution
Demonstration that the Project is needed to address a transmission reliability
deficiency on the Eastside, including Renton, is not a decisional criteria in Renton.
Nevertheless, and without waiving any objection to arguments that such criteria can be
inferred from or impliedly exists in the RMC, the record before the Hearing Examiner is
rife with studies, analyses and agency assessments confirming the methodology used and
conclusions drawn by PSE that this Project is needed at this time and in this location.18
18 See, e.g., Staff Report, Exhibit 18 at 1-4—1-6 (summarizing available studies);
Exhibit A at ¶¶ 52-57e, 77; Exhibit G at pp. 1-4—1-13 (incorporating by reference
Stantec, Energize Eastside Project Memorandum from Keith DeClerck to Mark Johnson
(July 31, 2015), available at http://www.energizeeastsideeis.org/library.html).
99640
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
PUGET SOUND ENERGY’S HEARING
MEMORANDUM - 18
719 Second Avenue Suite 1150
Seattle, WA 98104
(206) 623 -9372
Similarly, PSE anticipates that the public will offer up examples of what it
believes to be better solutions to the transmission deficiency on the Eastside, including in
Renton. PSE appreciates the public’s interest in electric utility operations. However,
nothing in the RMC gives its Hearing Examiner the authority to reject this application on
the grounds that the public may prefer some other technology to resolve the issue. See
RMC 4-9-030.F.8. As the utility provider mandated to make electricity available to all
customers in its service area, PSE is solely responsible for crafting a transmission
deficiency solution that takes into account the myriad potential interactions and impacts
that its choice could have on local and Eastside electric utility operations. In any event,
multiple solutions were evaluated in the Phase I DEIS, a process that included robust
public participation and examination. See Exhibit G.
III. CONCLUSION
Energize Eastside has been recommended to the Hearing Examiner for approval
subject to the conditions contained in the EIS Consistency Analysis. The project is
compatible with adjacent land uses, causes no significant adverse impacts to the built and
natural environment, and is consistent with all applicable plans, codes and policies of the
City of Renton. Having agreed to all conditions in the Staff Report, save the slight
modification to condition J.3 described above, PSE respectfully submits that the Hearing
Examiner can and will enter findings and conclusions supporting the decision that a CUP
for Energize Eastside should be issued.
DATED this 8th day of January, 2020.
99640
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
PUGET SOUND ENERGY’S HEARING
MEMORANDUM - 19
719 Second Avenue Suite 1150
Seattle, WA 98104
(206) 623 -9372
VAN NESS FELDMAN LLP
/s/ Erin Anderson
Erin Anderson, WSBA #23282
Sara A. Leverette, WSBA #44183
719 Second Avenue, Suite 1150
Seattle, WA 98104
Tel: (206) 623-9372
Fax: (206) 623-4986
E-mail: ela@vnf.com; sal@vnf.com
Attorneys for Puget Sound Energy, Inc.
99640
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
719 Second Avenue Suite 1150
Seattle, WA 98104
(206 ) 623 -9372
CERTIFICATE OF SERVICE
I, I’sha Willis, declare as follows:
That I am over the age of 18 years, not a party to this action, and competent to be a
witness herein;
That I, as a Legal Assistant in the office of Van Ness Feldman, caused true and
correct copies of the following documents to be emailed to the Hearing Exami ner and
counsel of record as set forth below:
1. Puget Sound Energy, Inc.’s Hearing Memorandum;
2. Certificate of Service;
and that on January 8, 2020, I addressed said documents and deposited them for delivery
as follows:
City of Renton Hearing Examiner
City of Renton
Leslie Clark
Jill Ding
I certify under penalty of perjury under the laws of the State of Washington that
the foregoing is true and correct.
EXECUTED at Seattle, Washington on this 8th day of January, 2020.
/s/ I’sha Willis
I’sha Willis, Declarant
1
TESTIMONY OF DAN KOCH
IN SUPPORT OF ENERGIZE EASTSIDE
RENTON CONDITIONAL USE PERMIT FILE LUA18-000055
January 8, 2020
Good evening, Mr. Hearings Examiner. I am Dan Koch, Director of Electric
Operations at Puget Sound Energy. I have worked at PSE for the last nine years and am
responsible for the 24/7 operation of PSE’s electric grid to ensure safe and reliable
delivery of electricity to PSE’s customers. I have a Bachelor’s of Science degree in
Mechanical Engineering, and am a licensed professional engineer in the states of
Washington and California. I have worked in large facility development for my entire
career, now nearly 30 years.
I also oversee the Energize Eastside project. A full list of my credentials is
attached to my written copy of this testimony, which I will provide to you this evening.
I want to kick-off PSE’s portion of this hearing with an overview of why we are
here, what processes we followed to understand and meet various municipal
requirements, and why we believe our record clearly shows that PSE went beyond due
diligence for this project and proposed the best possible solution for all.
On the Eastside of Lake Washington, electricity currently is delivered through
two 230 kV bulk electric substations – the Sammamish substation in Redmond and the
Talbot Hill substation in Renton. From these two delivery points electricity is distributed
to neighborhood distribution substations using 115 kV transmission lines.
While Energize Eastside between Sammamish and Talbot Hill substations is only
16 miles long within our existing corridor – which was established in the late 1920s and
2
1930s – the planning for this project was complicated by the extensive urbanization of the
area that has occurred in the last 50 years. However, a positive aspect of planning this
project is that we have benefitted from the modern pole and wire configurations that are
now available.
So, why are we here?
The simple explanation is that multiple studies projected that the demand for
electricity would exceed the capacity of the backbone of the Eastside’s transmission
system as early as winter 2017-18 and the summer 2018.
In fact, our actual summer system peak demand for electricity in 2017 did exceed
our forecasted summer peak demand for 2018 – one year earlier than expected. And
again, in August 2018 the actual summer peak demand exceeded the demand that had
been forecasted for 2020. PSE must have sufficient infrastructure to meet foreseeable
demand. Well, that foreseeable demand has already occurred.
The Energize Eastside project will provide the necessary infrastructure to meet
the North American Electric Reliability Corporation, or NERC, requirements in the form
of (1) a new substation at Richards Creek in Bellevue, (2) upgrading transmission lines
within the existing corridor from Redmond to Renton to supply this new substation, and
(3) aggressive conservation. The increased demand for electricity on the Eastside,
including Renton, drove the need for this new substation and once complete will improve
the reliability of electrical service to Renton residents, businesses and municipal
facilities. The addition of this new substation and associated lines utilizing the existing
corridor is the least impactful way to meet the increased demand.
3
It is important to note that if the status quo continues and no action is taken to
upgrade this backbone of the Eastside's transmission system, PSE is required under
federal law to continue using Corrective Action Plans under certain conditions outlined
by FERC and NERC. PSE’s Corrective Action Plans now must include the use of
intentional load shedding, or rolling blackouts, under these conditions for the grid
supplying the Eastside, including Renton.
Although PSE has made many system improvements on the Eastside over the
years, the primary 115 kV lines that connect the Sammamish and Talbot Hill substations–
which form the spine of the Eastside electrical system– have not been upgraded since the
1960s. Since that time, the Eastside’s population has grown from approximately 50,000
to nearly 400,000 people. A record breaking number of high-tech businesses are booming
today, industries are thriving, and the area is home to some of the best medical facilities
in the country. The Puget Sound Regional Council and Renton Comprehensive Plan both
expect this growth to continue.
Keeping the transmission lines in the existing corridor reflects our commitment to
limit impacts to the environment.
Our plan is to upgrade the existing sets of four wooden poles to one or two steel
poles. New poles will typically be located in the same or similar locations as the existing
poles. When completed, this upgrade will result in a significant reduction in the number
of poles, from the 144 in Renton today to only 41.
Safety has been a constant focus for both PSE and the public, including focusing
on how the upgraded line will relate to the Olympic fuel pipeline that shares one quarter
mile of the proposed four mile corridor in Renton. PSE has a long and successful history
of working closely with Olympic Pipe Line Company. PSE’s existing high voltage
4
transmission lines have safely coexisted with the Olympic pipelines throughout a 16-mile
corridor for decades, even with periodic construction to replace poles and add fiber optic
cables. And both companies have a strong mutual interest in the protection and safe
operation of facilities in the corridor.
In response to public concern expressed by some stakeholders over pipeline safety
issues, PSE took a more in depth look at the potential impact of collocating with the
pipelines. A leading national pipeline safety consulting firm studied and confirmed that
Energize Eastside can be safely co-located with Olympic Pipe Line Company’s pipelines
throughout the existing corridor. In fact, the selection of the proposed route over the route
initially preferred in the Phase II Draft EIS was chosen as a result of this work, and PSE
incorporated design mitigation recommendations into the design.
The existing route where the lines will be upgraded reflects our commitment to
safety. The project will be built and operated to the highest safety and engineering
standards. The project meets all federal regulations for transmission line design,
operation and constructability.
In closing, our studies clearly show, and the City of Renton Staff Report confirms,
that combined with continued aggressive conservation, Energize Eastside will improve
reliability for Renton and other Eastside communities and supply the needed electrical
capacity for anticipated growth and development for years to come.
EXHIBIT A
Renton segment
#*#144th Ave SENE 10th St
N E P a r k D r
148th Ave SENE 4th St
SR 515154th Pl SENE 12th St
S Puget DrS 7 th S t
NE 16th St
Duvall Ave NEDuvall Ave NESR 900Monroe Ave NEN 6th St
NE 27th St
Edmonds Ave NEUnion Ave NEN E 7 th S tS
R
1
6
9
SE 60th St
Factory Ave NNewcastle WayN 40th St
Aberdeen Ave NENewcastle Way
SR 900Lake Washi
ngt
on Bl
vd N116th Ave SETalbot Rd SS 2 1 s t
S t Jericho Ave NEEdmonds Ave NEPark Ave NLake Washington Blvd SEUnion Ave NESE 70th Pl 123rd Ave SENE 12th St119th Ave SES R 9 0 0
Forest Dr SEUnion Ave SES 7 th
St Nile Ave NES G r a d y W a y
SE 142nd St
Benson Rd SE Mercer Way116th Ave SENE 4th St112th Ave SES Puget Dr
Newcastle Way
SE 141st St
Edmonds Ave SE148th Ave SE116th Ave SEUnion Ave NEN Airport Way
Puget Dr SEGarden Ave NN 8t h St
140th
W
ay SE
SR 900
Garden Ave NS E 1 4 2 n
N 1 0 t h S t
NE 44th St
132nd Ave SEJericho Ave SESE May Valley Rd
N E 3 rd S tS R 9 0 0
Houser Way NLincoln Ave NEN 30th St
Newcastle Golf Club RdCoal Creek Pkwy SE§¨¦405 SE 100th St.126th Ave SESR
169
Ta lb ot Hil l
Su bs ta tio n
(e xis tin g)
Bel levue Newcastle
Ren ton
Lak eBoren
Cedar
River
Lak eWashing ton
Soo s Cre ek
Park a n d
Trai l
Ma y
Va ll ey
Park
Hon ey
Cree k
Op e n S pa ce
Ge n e
Cou lo n Me m or ia l
Bea c h P ark
Ma pl ew oo d
Park
Ced ar Rive r
Natu ra l
Zon e
Ced ar
River Pa rk
- Re nto n
Ced ar Rive r
Trai l S ite
- Re nto n Ma pl ew oo d
Go lf Co urse
Ron Re gi s
Park
Coa l C ree kNatural Are aLakeHeightsParkForestPark Op e nSpace
Ma y Cre ek
Park -
Cou nt y
Ma y
Cree k
Park
La keBorenPark
Ma y Cre ek
Op e n S pa c e
Chi na Cre ek
Op e n S pa c e
Cou ga r M o un ta in
Reg io na l
Wil dl an d Pa rk
Easts id e Ra ilCorridor ¯
Jul y 2017
Legend
C-1 st ruct ure s, one double c ir cuit
C-1B s truc tures, one double circuit
C-2 st ruct ure s, two single circut is
C-16 st ruct ures, two si ngle circuit s
C-18 st ruct ures, two si ngle circuit s
!(C-2 st ruct ure
!(C-17 st ruct ure
!(C-18 st ruct ure
#Exist ing subst ation
#*Ric hards Cr eek s ubs tat ion (new)
SEGMEN T 3 : WILLOW 1 ROU TEThe Ene rg ize Ea st side p roject will u pg ra de e xis t ing tr a ns m is sion lin es f rom th e Sa mm a mishsubstation in R e dm on d t o t he Ta lb ot Hill s u bst a tio n in R e nt on a nd con ne ct in t he m idd le withthe Ric h ards C ree k s u bst a tio n.
NOTE : Th e s e ma ps ar e f or i llust ra tiv e p ur po s es on ly. P re limi na ry ro ute, po le typ es, an d
po le h eig ht s ar e su bje c t to ch an ge pe nd in g de sig n, en gi ne eri ng , a nd en v iro nme n ta l re v iew.
F or h igh wa y cr os s in gs, po le t y p e an d h ei gh ts v a ry.
#
#
#
"3
"1
"2
#*Rich ard s
Creek
§¨¦405
VU520§¨¦405
§¨¦90
S R 9 0 0
SR 169
Beaux
A rts
Bel levu eClydeHillHuntsPointMedina
Mercer
Island
N ew ca st le
Redm o n dRedmond
Renton
Rent o n
YarrowPoint
Lake sid e
Sa m m am i sh
Ta lb ot
Hil l
Lak e
Sam mam is h
Lake
Washington
Soo s Cre ek
Park a n d
Trai l
Cou ga r M o un ta in
Reg io na l
Wil dl an d Pa rk
Ma rymoo rParkBridleTrailsState Pa rk Fo cu s ar e a: Seg men t 3
F o cus a r ea
LEGEND
energizeEASTSIDEproject newsletter
Summer 2017pse.com/energizeeastside
Summer 2017 project update
About Energize Eastside
The Eastside is outgrowing the backbone of the area’s electric grid.
Energize Eastside will build a new substation, upgrade existing
transmission lines, and continue aggressive conservation efforts to keep
Eastside lights on and foster economic development for years to come.
We’ve selected the existing corridor
as our final route
After nearly four years of study and extensive dialogue with Eastside
communities, PSE has selected the existing corridor “Willow 1” route as
the final route to permit for Energize Eastside.
Multiple independent studies have made it clear that we need to
upgrade the Eastside’s electric infrastructure now to accommodate
local population and economic growth and avoid planning for power
outages in the very near future.
The existing corridor is the least impactful route to
Eastside communities
PSE evaluated multiple route options and selected the existing corridor
because it is the least impactful route to Eastside communities. Our
decision was guided by two key factors:
1. Our commitment to safety. The project will be built and operated
to the highest safety and engineering standards. Using the existing
corridor, along with optimized designs and operations, the project
can safely co-exist with the Olympic Pipeline.
2. Our commitment to limit impacts to the environment. This
route affects the fewest trees and avoids the construction of new
corridors. We know our customers value trees. Our goal is for
there to be more trees when the project is complete, not fewer.
PSE will replace the poles in the existing corridor
Our plan is to upgrade the existing four wooden poles to one or two
steel poles, which allows us to have fewer poles within the existing
corridor. PSE is committed to keeping pole heights as low as possible.
New poles will typically be in the same or similar locations as the
existing poles.
##
#
!(!(
!(
!(
!(
#*
VU520
Sammamish
Substation
(existing)
Lakeside
Richards Creek
§¨¦405 124thAveNE102ndAveNE132nd Ave NEN E 8th St
106thAveNEBellevue Way SE166thAveNES E 24th
St
2nd
Ave S
N E 51st St
Northup Way
N E 83rd StSlaterAveNENE109thSt
Lake Hills BlvdEMercerWayN E 60th St
156th Ave SENE 12th
S t
Richards RdN E 80th St
AvondalWaS E 8th St
104thAveSE132nd Ave NE166th Ave NES E 37th St 173rdAveNE116th Ave NE1 5 t h
A v e
NE 68th StStateSt
SE 35thPl 160t
hAveNES E 22nd St148th Ave NE108th Ave NE140th Ave NES E Eastgate Way128th Ave NEBel
l
evueWaySE108thAveSES E 16th St
S E 34th St148th Ave NEN ERedmond Way
N E 1s t
S t
140thAveSES E 24th St 172ndAveNEN E 53rd St
NE 104th St
3rdSt171stAveNE108thAveNESR
2
0
2
139th Ave SEN
E
3
8
th
Pl
1
0
6
t
hAv
e
SE132nd Ave NE134th Ave NE116th Ave NE124th Ave NE145t
h Pl
SE156th AvS eESE38thSt108thAveNEN E 87th S t
148th Ave SENE 4th
St
C e n tra lW a y
140th Ave NE156th AvEN eN EOld Redmond RdN E 80th St
S E 17th St
N E 8th St
1
5
8
t
h
Av
e
NE161st Ave NEN E 40th St
124th Ave NEN E51st St130th Ave NE120th Ave NE152nd Ave NE128th Ave SEN E 5 2 n d St
Main St
126th Ave SENE 40 ht St126th Ave NE168th Ave SENEBel
l
evueRedmondRd EN 24th StN E 24th St
164th Ave NE112th Ave SE156th Ave NEN E70 htPl
116th Ave NEN E 9 0th S t
N E 100th
St
LakeviewDrNE148th Ave NES E 14th
St
NE 1 0 ht
St
N E 60th St
18th Ave N E 100th St
Leary Way NEN E 70th St
vA ht651e NE124th Ave NEWill
o
ws
Rd
NE
Nor
t
hup Way
N E 8th St
NE 95th
112th Ave NERailroad Ave120th Ave NEN E 95th St
156th Ave NES E 34th St8th St SN E 30th St122nd Ave NEKambe rRdN E 2nd
St
BeellvueWayNEKill
ar
neyWaySE 25th St 164th Ave NENE 104th St
140th Ave SELakeWashingtonBlvdNESE38thSt
N E 60th St
142ndPlSEN E70th Pl 166th Ave NE148th Ave SEF o rbe s Creek Dr
BellevueWayNEN E 9 7 t h S t
108th Ave NEN E 85t h
St
104thAveSE140th Ave NES E12th St
L a k e H i l l s
B l v d120th Ave NEN E 100th St
Main St 170thAveNEN E 90th St
N E4th St
FactoriaBlvdSE7 th Ave
148th Ave NEN E 7 9 t h S t
118th Ave SE164th Ave SE9 ht
Av e S
B
ea rCree k Pkwy
N E 24th St
148th Ave NE108thAveNEWestLakeSammamishPkwySEN E 80t h St
N E 1st St5th PlBellevue Redmond Rd ES1st StN E 20th St
S E 8 th S t1 2 t h
A ve
154th Ave NEN E 85th St
SE 36th St
Main St
N E12th St
Lake
Hills
Connector
150thAveSEB e lle v u e
R e d m o n d R d112th Ave NEBeau x
Arts
Bell evu e
Kirklan d
Redmond
Swan
Lak e
Larse n
Lak e
Merce r
Slo ugh
Phan tom
Lak e
Fo rb es
Lak e
Lake
Bellevue
Sam mami s h
River
La ke Hi ll s
Gr ee nb el t
Park
Ban ne rwo od
Bal lfi el d
Park
Kel sey
Cree k
Park
Me rc er Slough
Natu re Pa rk
Rob insw ood Par k
Nort h R os e
Hill Pa rk
Eve re st
Park
Gr ass La wn
Commun it y
Park
Brid le Crest
Trai l S ite -
Red mon d
Red mon d
Cen tra l
Con ne ctor
Ma rymoo r
Park
Bel levu e
Mu ni cip al
Go lf Co urse
Brid le
Trai ls
Sta te Pa rk
Wat ersh ed
Park
Ardmo re
Park
Crossroads
Park
Vi ewpoi nt
Park -
Bel le vu e
Eas tsid e
Rai l
Corri do r
Hid de n
Va ll ey
Park
Wil bu rto n
Hill Pa rk
We s t
Samma mi sh
Trai l S ite
Redm on d PSE
Trai l S ite ¯
Jul y 2017
Le ge nd
C-1 struct ure s, o ne d ou ble c ircu it
C-1B structu res , one doubl e ci rc ui t
C-2 struct ure s, tw o sin gle circu tis
C-16 s tru c tu res, two si ng le ci rc ui ts
C-18 s tru c tu res, two si ng le ci rc ui ts
!(C-2 struct ure
!(C-17 s tru c tu re
!(C-18 s tru c tu re
#Exi sting s u bs ta ti on
#*Ri c ha rds C ree k su bsta tion (n ew )
SEGMEN T 1: WILLOW 1 ROUTEThe E nerg ize East side p roject will u pg ra de exis t ing tr ansm ission lin es f rom th e Sa mm amis h
subst at ion in R edm on d t o t he Talb ot Hill s u bs t atio n in R e nt on a nd con nect in t he m idd le with
th e Rich ards C reek su bst atio n.
N OT E : T hese ma ps ar e f or i llustra t ive p ur po ses on ly. P re lim i na ry ro ute, po le typ es, an d
po le h eig hts ar e su bje ct t o ch an ge pe nd in g de s ig n, en gi ne eri ng , a nd en viro nmenta l re v iew.
For h igh wa y c r ossin gs, po le typ e and h ei gh ts va ry.
#Rich ard s
Creek
§¨¦405
VU520
§¨¦405
§¨¦90
S R 9 0 0
SR 169
Beau x
A rts
Bellevue
Clyde
H ill
H unts
Po in t
Medin a
M er cer
Is lan d
N ew ca stle
Red m ond
Red m ond
Ren t
Ren to n
Yar row
Po in t
Lake sid e
Sa mmami sh
Ta lb ot
H il l
Lak e
Sam mam is h
Lak e
Wash ing ton
Soo s Cre ek
Park and
Trai l
Cou ga r
Mo un ta in Regi onal
Wil dl and Pa rk
Ma rymoo r
Park
Brid le
Trai ls
Sta te Pa rk
Focu s are a: Seg men t 1
LE GE ND
Tra ns mi ssi on lin e
ch anges f ro m t wo
si ngle -c i rcu it
trans m issio n l ines
to one do uble-ci rcu it
transm issio n l ine.
C-16 struc ture s,
tw o si ng le -c ir cui t
tr ans m is sio n li n es.
C-1 a nd C-1B str uctu res,
dou bl e-ci rcu i t
tr ans m is sio n li n e
C-1 s tructu res ,
dou bl e-circu i t
tr ans mis sio n lin e.Tra ns mi ssi on lin e
ch anges f ro m one
doubl e-c ircuit
trans m issio n l ine t o
two sing le-circuit
trans m issio n l ines .
Energize Eastside project route
PSE selected the existing corridor, known
as the “Willow 1” route, as the final route to
permit for Energize Eastside.
Existing
substation
New
substation
Final route
Legend
Renton segment Energize Eastside project route
EXHIBIT B
Education
B.S. Mechanical
Engineering, 1991
University of Washington
Seattle, WA
Registrations
Professional
Engineering License,
Mechanical Engineer -
Washington, California,
and Oregon
Professional Societies
and Affiliations
Society of Naval
Architects and Marine
Engineers
American Society of
Mechanical Engineers
Society of Professional
Engineers
Summary
Mr. Koch has more than 25 years of experience in
engineering and project management primarily in the
Utility, Offshore and Marine sectors. He has been
involved in several complex projects from offshore
platform installations to on-site construction and
launching of sea-going vessels, hydro-powerhouse and
fish migration facilities construction and traditional T&D
Utility projects. Since joining PSE, Mr. Koch has
served as a Sr. and Consulting Project Manager in
Power Generation, Transmission and Distribution
Engineering Manager, Director of Engineering, and
Director of Electric Operations
Experience
Puget Sound Energy, Bellevue Washington – 2010 to
Present
Currently; Director of Electric Operations -
Responsible for Electric First Response, Substation
Operations, System Operations, Meter Operations and
Construction Performance Management
Guido Perla and Associates, Inc., Seattle Washington
– 1996 to 2010
A multi-national consulting naval architectural, marine,
mechanical/electrical engineering firm with a worldwide
reputation for its progressive and innovative approach to
engineering and ship design for a number of highly complex
marine industry sectors. Mr. Koch held a variety of positions
during his tenure:
Vice President of Engineering
Project Manager
Project/Principal Mechanical Engineer
Paroscientific, Bellevue Washington – 1994 to 1996
Applications Engineer supporting marketing and sales
for a digital pressure instrumentation manufacturer.
Exxon Company/Exxon Chemical Company, California
and Washington – 1991 to 1994
Project Engineer/Project
Manager for offshore oil
platforms, including;
construction, operational
reliability, and process
control and monitoring.
1
TESTIMONY OF LOWELL ROGERS
IN SUPPORT OF ENERGIZE EASTSIDE
RENTON CONDITIONAL USE PERMIT FILE # LUA18-000055
January 8, 2020
Good afternoon, your honor. My name is Lowell Rogers, and I am a licensed
Professional Engineer in Washington and California. I have nearly 25 years of experience in
transmission line siting, design, and construction. As a result, I have worked on the design or
siting of over 1,700 miles of transmission lines in suburban, industrial, and dense urban settings.
Since shared utilities corridors are often preferred by municipalities, as is reflected in the City’s
Comprehensive Plan, a considerable amount of this work has involved transmission lines being
designed, built, and operated in the same corridor with fuel pipelines.
The design and construction methodologies used for this project, specifically regarding
the effects of heavy wind and earthquakes as well as the proximity of the pipelines to the
proposed lines, have generated considerable public interest and concerns around the safety of the
project. On Energize Eastside, I am responsible for contributing to and reviewing studies and
reports required for the design of the project as well as evaluating future material supplier and
construction contractor proposals to ensure they meet applicable safety and building standards
that do address these public concerns. Therefore, I’ll speak to the specific approach to the area
within Renton where the Project and pipelines share the same corridor. Within the city of Renton
boundaries there are 1,208-feet of the Energize Eastside project that share a corridor with
Olympic Pipeline’s petroleum pipeline, which I will refer to as OPL. This means that the OPL
pipelines are not present in the majority of the Energize Eastside project’s four-mile path through
Renton. Even though these pipelines have coexisted with PSE’s existing transmission lines in
this corridor for decades without incident, PSE has a thorough plan to incorporate safety
requirements for the design and construction of the new transmission line.
PSE’s existing transmission corridor was established in the 1920’s and 30’s and the
transmission lines that Energize Eastside will replace were built in the 1960’s using the
technology and safety requirements of that time. OPL completed construction of it’s pipelines
about a decade later. Like most things, over the last 50 to 60 years safety codes and technology
2
have advanced. Current building codes, including the National Electric Safety Code, will apply
to Energize Eastside. These codes provide for the safe design, construction and operation of all
high voltage transmission lines, including those collocated with fuel pipelines. These codes and
standards are far better-informed than those used in the 1960’s for how transmission lines
perform under extreme weather and seismic events and they interact with other utilities that share
the same corridor.
The design of the Energize Eastside project considered 54 different physical loading
cases that modeled the range of forces that act on the structures. By this, I mean wind effects and
weight from extreme ice among other things that act on the transmission line. We have designed
the lines for a safe operating envelope that prevents them from getting too close to the ground,
vegetation and adjacent structures. In Renton, the Energize Eastside project is completely
located within PSE’s existing easement.
Now, I’ll describe PSE’s approach to the design and construction planning for the line in
the area. To begin, PSE conducted a land survey along the project route and identified pipeline
markers and incorporated these features into the preliminary project design. This design then was
used in order to confirm OPL’s original land survey data. After that, PSE performed an
underground survey through the 811 location service and then used ground penetrating radar
technology to further confirm the location of all underground utilities within a 50-ft radius of
each proposed pole.
Using this information, PSE is currently working with OPL to jointly develop the
construction access plan for the Project. This plan will address the ingress and egress of
construction equipment and, where appropriate, the use of steel plates or bridges to allow
equipment to safely cross over the pipeline and avoid any damage. Please refer to my Exhibit A
for pictures of these pipeline crossing measures. These methods are applied safely every day
across the country when equipment needs to drive over pipelines. Notwithstanding all of this, in
advance of construction, PSE will confirm the locations of the pipelines using either hand-
digging or vacuum excavation methods to visually confirm the exact location of OPL’s pipelines,
as well as other utilities in the corridor. Please refer to my Exhibit A for examples of these
3
potholing activities. This approach provides PSE with the maximum confidence in the location
of the facilities and confirms the construction plans in a measured, methodical, and safe way.
In Renton, the pole foundations range from 4 to 9 feet in diameter and 13 to 46 feet in
depth, depending on pole height and loading. In the 1,200-ft length of the project in Renton that
shares the corridor with the pipelines, there is sufficient separation between the edge of the
foundations and the pipelines to allow for safe construction. The foundations will be initially
excavated using the soft-dig vacuum system to a depth deeper than OPL’s pipelines which is a
non-damaging method that is a conservative measure not often employed in typical transmission
foundation construction. When the top portion of the excavation is clear, a temporary steel casing
will be use to prevent sloughing of the surrounding soil to prevent the risk impacting the
pipeline. Final excavation is then completed and the foundations are installed; followed by the
installation of the poles onto the foundations. Cranes will typically be used to set the poles onto
the foundations.
Due to the complex terrain, helicopters may be used to set poles and string in wire in
some of the areas along the Renton segment. The use of helicopters is common in transmission
line construction and is a method that PSE has used on other projects. The use of helicopters
facilitates faster installation of wires and often minimizes land disturbance that would result in
accessing pole locations using other methods. The use of helicopters will likely be used to install
the conductors at the crossing over the Cedar River and highway 169. PSE and their contractor
will comply with local and FAA congested air permit conditions and notification requirements,
including those related to the Renton Municipal Airport.
In early 2018, PSE received a Determination of No Hazard to Air Navigation for this
crossing from the FAA. As a condition of this determination, the FAA requires spherical markers
spaced approximately 200 feet apart along the wire for the line span over the Cedar River. In
total, six marker balls, 20-inchs in diameter with reflective tape will be used to mark this
crossing.
4
As I indicated, I personally have been involved in the routing and/or design of over 1,700
miles of transmission lines, a substantial portion of which are collocated with petroleum or
natural gas pipelines. In my experience, the planning and design of the Energize Eastside project
employs informed planning and rigorous safety protocols and I’m confident that will be brought
online safely and without incident. Furthermore, this new line that utilizes steel poles designed
to current codes and engineering standards will provide significant safety and reliability
improvements over the existing wood pole line that is in place today, benefiting the communities
it serves.
I am happy to answer any questions you may about my testimony or my work on
Energize Eastside.
EXHIBIT A
Energize Eastside Project
Construction Safety
Lowell Rogers, PE
Oak Strategic, Inc.
In support of Renton Conditional Use Permit
LUA18 -000055
Vacuum Excavation
Vacuum Truck Used
In Existing Corridor
Steel Plating
EXHIBIT B
LOWELL ROGERS, P.E
(916) 616-0292 ● Lowell.Rogers@oakstrategic.com
3840 San Ysidro Way, Sacramento, CA 95864
1
PROFESSIONAL LICENCING & EDUCATION
Professional Civil Engineer, CA No. C62437, WA No. 49711, New York No. 083583 (inactive)
Bachelor of Science, Civil Engineering, California State University, Chico, May 1998
PROFESSIONAL EXPERIENCE
Oak Strategic, Inc., Sacramento, CA, November 2016 - Present
PRINCIPAL / OWNER
Providing project management, engineering, and advising services to owners developing infrastructure
projects.
Sacramento Municipal Utility District, Sacramento, CA, June 2015 – December 2016
PROJECT MANAGER, SPECIAL PROJECTS
Project manager for the Colusa-Sutter Transmission, which is a $245M 500kV transmission line located
north of Sacramento, California. Managed the development of alternatives, environmental documents
(ESI/EIR), design, budgets, public outreach. Primary interface with SMUD’s partner WAPA.
POWER Engineers, Sacramento, CA, May 2012 – June 2015
SENIOR PROJECT MANAGER
Project manager for transmission projects (siting/feasibility, engineering, public outreach).
Responsibilities include managing internal project teams and subcontractors for the delivery of EHV
transmission projects. Includes scoping, budgeting, and scheduling work, negotiating contracts and
change management.
CH2M HILL, Sacramento, CA, February 2011 – May 2012
SENIOR PROJECT ENGINEERING MANAGER
Project manager and project engineer for EHV transmission projects (siting/feasibility, engineering,
design-build). Responsibilities included managing projects and client relationships, and marketing all
power delivery services to existing and new clients. Role included CPM scheduling, budget and cost
analysis, management of project teams, strategy, obtaining and successfully executing projects and
proposal writing and presentations.
HDR Engineering, Inc., Sacramento, CA, March 2005 – February 2011
POWER & ENERGY PROJECT DELIVERY MANAGER – WEST REGION &
SENIOR PROJECT MANAGER
As a member of the national Power and Energy management team, I supported and implemented
strategic planning efforts for projects across the energy sector and identified clients and emerging
opportunities. Responsible for project delivery in the division, I provided review and management for
approach, quality, budget, and schedule performance of proposals and projects.
Work closely with practice leaders and project teams to maintain high quality deliverables, develop
solutions that meet client needs and requirements, and minimize losses on projects by negotiating
advantageous terms, conditions, scope, and budgets for contracts. Monitor quality and client satisfaction,
and implement corrective action if required.
Facilitated HDR’s entry into design-build project delivery models in the energy sector where I lead the
proposal, negotiation, and execution of several design-build (EPC) projects.
LOWELL ROGERS, P.E
(916) 616-0292 ● Lowell.Rogers@oakstrategic.com
3840 San Ysidro Way, Sacramento, CA 95864
Lowell Rogers, P.E. Page 2 December 11, 2019
Conducted quality assurance reviews as Acquisition Integration Liaison for acquired companies and
implemented corrective action plans to improve quality and adhere to corporate guidelines.
Black & Veatch Corporation, Sacramento, CA / Portland, OR, June 1998 – March 2005
PROJECT ENGINEER
Designed all facets of transmission projects, including overhead and underground, lattice, wood, and
tubular steel structures, plan and profiles, foundations, and material specifications. Projects included
new line design, conductor re-ratings, fiber installations, failure analysis, and antenna installations.
Produced construction and material specifications for both engineering-only and engineer, procure, and
construct type projects.
LABORER / CREW FOREMAN / INSPECTOR
Multiple Contractors Summers 1991 – 1996
Various transmission line, substation, and highway bridge construction projects.
Laborer and crew foreman for foundation installation for transmission lines and substations. Advanced
to crew foreman responsible for interfacing with owner’s representatives, meeting production goals,
quality, and safety.
California Department of Transportation, Summer 1997
Inspector of highway bridge project for Caltrans. Conducted daily inspections of contractor work,
maintained records and logs, reviewed contractor submittals, and worked closely with the chief engineer.
OVERVIEW
Over his career (21+ years) Lowell Rogers has managed the routing and/or design of thousands of miles
of HVAC and HVDC overhead and underground transmission through 500 kV. As a professional
engineer experienced in transmission line design, Mr. Rogers uses his knowledge and experience of all
areas (engineering, environmental, real estate, public relations, etc.) to approach in a unique way to
provide solutions to challenges that often face transmission projects.
Mr. Rogers is experienced in transmission line design and analysis using PLS-CADD and the design of
wood and steel poles, self-supporting lattice tower, guyed-V lattice tower analysis and design from 12kV-
500kV using PLS-POLE and PLS-TOWER software. He has designed HVAC and HVDC underground
transmission lines.
He has developed feasibility studies for major transmission projects that looks at routing alternatives,
design requirements, construction feasibility, cost, and schedule matters. Mr. Rogers has successfully
obtained both NEPA and CEQA authorizations from federal and state agencies as well as other permits
from USFWS, FAA, USACE, CDFW, DOTs, counties, and cities. Mr. Rogers is experienced in cultural
resource management and is familiar with the Section 106 and AB52 processes, has experience interfacing
and negotiating with various California tribes, managed ethnographic studies and class III surveys,
negotiated multi-party programmatic agreements, and has managed the development of historic
properties treatment plans. Mr. Rogers has also led complex public relations strategies that engage
stakeholders in every venue from dining room table conversations to adversarial public meetings with
hundreds of participants.
LOWELL ROGERS, P.E
(916) 616-0292 ● Lowell.Rogers@oakstrategic.com
3840 San Ysidro Way, Sacramento, CA 95864
Lowell Rogers, P.E. Page 3 December 11, 2019
OVERHEAD TRANSMISSION EXPERIENCE
TEN WEST LINK TRANSMISSION LINE PROJECT PROJECT MANAGER
DCR TRANSMISSION, LLC (A JOINT VENTURE LED BY AFFILIATES OF STARWOOD ENERGY
GROUP)
Project manager representing the project owner for a 125-mile 500kV transmission line located in Arizona
and California. Responsible for the permitting (Federal, two states, three counties, tribal, military,
transportation, etc.), land acquisition, design, and construction. In this capacity I negotiate contracts,
manage budgets and schedules, oversee the design and procurement efforts, and lead governmental and
public outreach program. Manage an overall team of approximately 30 contracted firms (legal, land
agents, engineering, construction, economic modeling, environmental, public outreach, and government
relations).
COLUSA-SUTTER TRANSMISSION LINE PROJECT PROJECT MANAGER
SACRAMENTO MUNICIPAL UTILITY DISTRICT
Responsible for managing the siting and development of a 40-mile 500kV transmission line utilizing
lattice towers. Lead the governmental and community engagement and CEQA compliance, alternatives
development, and preliminary design criteria for the project and worked closely with the project partner
WAPA. Worked with SMUD management to set the vision and priorities for the project and
implemented the strategy for the entire team to maintain schedule and ensure the defensibility of the
environmental document. Worked closely with system planning, engineering, and in-house and outside
legal counsel.
ENERGIZE EASTSIDE 230 KV TRANSMISSION PROJECT PROJECT MANAGER
PUGET SOUND ENERGY
18 mile-long 230 kV transmission lines from Redmond, WA to Renton, WA. Responsible for managing
the delivery of line design including alternatives development and detail design of steel pole structures
utilizing PLS-CADD and material. The corridor is located in a suburban setting with a restricted corridor
containing overhead and underground 3rd party utilities (including petroleum pipeline interaction) that
needed to be accounted for in the design. Provided feasibility and cost estimates for overhead and
underground alternatives. Managed teams conducting visual simulations, EMF and induced current
modeling, and material specification. Represented PSE in 28 formal community outreach meetings to
describe the project to the public as well as dozens of smaller meetings.
Provided expert witness testimony on engineering and construction methods. Am a member of the public
relations tactics team which manages the strategy for public relations and obtaining the five local land
use permits that the project will require.
GATES-GREGG TRANSMISSION PROJECT PROJECT MANAGER
MIDAMERICAN TRANSMISSION AND PACIFIC GAS AND ELECTRIC (PARTNERSHIP)
Competitive FERC 1000 Pursuit. Managed the routing and engineering effort for an application to the
CAISO to Design, Build, Finance and Maintain the proposed 230 kV transmission line project spanning 59
miles between Coalinga, CA, and Fresno, California. Developed routing alternatives, risk assessments,
preliminary designs using PLS-CADD, cost estimates and schedules.
LOWELL ROGERS, P.E
(916) 616-0292 ● Lowell.Rogers@oakstrategic.com
3840 San Ysidro Way, Sacramento, CA 95864
Lowell Rogers, P.E. Page 4 December 11, 2019
JEFFERSON-MARTIN 230 KV TRANSMISSION LINE ENGINEERING MANAGER
PACIFIC GAS AND ELECTRIC CO.
Engineering Manager responsible for developing routing/feasibility studies, preliminary design, and cost
estimates, for the permitting of a 26-mile long, 230kV underground/overhead transmission line located in
a challenging urban and environmentally sensitive setting. Assisted in writing the Proponents
Environmental Assessment (PEA) for filing with the California Public Utilities Commission (CPUC), as
well as provided technical review and comments of the CPUC identified alternative routes identified in
the Draft Environmental Impact Report. Mr. Rogers also prepared and presented expert testimony before
the CPUC on behalf of PG&E and facilitated a number of public comment meetings.
Responsibilities also included managing the incorporation of the EIR required mitigation measures into
the final design of the Project. As part of this effort, it was necessary to interface with the CPUC
environmental consultant and to document compliance with the pre-construction mitigation measures in
order to receive the necessary notice to proceed (NTP) required for construction.
Some of the challenging issues that were successfully overcome included traffic flow, hazardous
materials, lake and dam crossings, interfacing with local and state officials, intervener groups EMF,
sensitive habitats, and existing utility conflicts. Mr. Rogers also worked closely with PG&E’s engineering,
operations, public/media relations, and legal representatives, as well as other consultants specializing in
the fields of biology, visual, and cultural resources.
After approval of the project Mr. Rogers served as engineering manager for the underground and
overhead components for the Engineer, Procure, Construct contractor. This included detailed design,
material procurement, and construction planning. Utilized the PLS-CADD and PLS-POLE software.
FT MCMURRAY TRANSMISSION PROJECT PROJECT MANAGER
MIDAMERICAN TRANSMISSION AND TRANSALTA JOINT VENTURE (TAMA)
500 km (310 mile) 500kV AC transmission line from Fort McMurray, Alberta to Edmonton, Alberta.
Managed the routing and engineering effort for an application to the AESO to Design, Build, Finance and
Maintain the project and associated substations work. Developed preliminary designs using PLS-CADD,
cost estimates, and schedules.
The scope of this fast-paced effort included the development of project design criteria and preliminary
structure design, contracting and managing local geotechnical and access road engineers and
procurement of material.
ZEPHYR TRANSMISSION PROJECT PROJECT MANAGER
DUKE / AMERICAN TRANSMISSION COMPANY JOINT VENTURE (DATC)
Managed the engineering effort for the preliminary development for the 3,000 MW HVDC transmission
line project traversing approximately 850 miles from Chugwater, WY to Las Vegas, NV
The scope of this effort generally includes the development of project design criteria for lattice tower
construction, preliminary structure design for fabrication, cost estimating, and elected- and public-
stakeholder communications and meetings. Utilized PLS-CADD and PLS-TOWER
LOWELL ROGERS, P.E
(916) 616-0292 ● Lowell.Rogers@oakstrategic.com
3840 San Ysidro Way, Sacramento, CA 95864
Lowell Rogers, P.E. Page 5 December 11, 2019
MARIPOSA ENERGY PROJECT PROJECT ENGINEER
DIAMOND GENERATING CORPORATION
Lead the transmission line design effort for a new 230 kV transmission line on steel monopoles to connect
a new natural gas generation plant near Tracy, California. This turn-key project included environmental
permitting, design, procurement, and construction. Design utilized PLS-CADD and PLS-POLE.
CALIFORNIA CLEAN ENERGY TRANSMISSION PROJECT (CETP) PROJECT MANAGER
STARWOOD ENERGY
Managed the routing and engineering effort for the for an application to the CAISO to Design, Build,
Finance and Maintain the proposed preliminary development for the 2,000 MW HVDC/HVAC
transmission line project traversing approximately 200 miles from throughout Southern California
The scope of this effort included system impact studies, the development of project routing, design
criteria, preliminary design of steel pole and lattice structures, and cost estimating for submarine,
underground, and overhead transmission facilities as well as HVDC converter stations and
interconnecting substations. Utilized the PLS-CADD and PLS-POLE software.
SLAC 60 KV TRANSMISSION LINE PROJECT MANAGER
STANFORD UNIVERSITY AND CITY OF PALO ALTO
Project Manager responsible for performing a siting study to identify alternative routes for a double-
circuit 60 kV lattice tower transmission line within the City of Palo Alto and adjacent to Stanford
University. The 60kV line is part of the City's proposed new 230 kV interconnect with Western Area
Power Administration's delivery system. Facilitated various stakeholder meetings to solicit input on
opportunities and constraints of different route alternatives. Performed high-level engineering
evaluation, cost estimating, and environmental impact assessment. Utilized the PLS-CADD and PLS-
POLE software.
BC RENEWABLES (CNC) TRANSMISSION LINE PROJECT MANAGER & PROJECT ENGINEER
PACIFIC GAS AND ELECTRIC CO.
Managed the engineering, right-of-way, and cost aspects of a feasibility study for the 900-mile long
BC Renewables (British Columbia to Northern California) 500 kV (AC & DC) transmission line.
Managed a multidiscipline team of engineers, right of way agents, system studies, and material
procurement to identify feasible route alternatives, the expected schedules, and alignment costs. Detailed
feasibility and cost studies were completed for both overland and submarine paths. Various line
configurations were considered, including single and double circuit 500 kV AC and 500 kV DC. This
feasibility study identified and evaluated the opportunities and constraints of the study area in order to
evaluate the feasibility of a specific corridor.
Developed specifications for line and lattice tower design and produced preliminary designs using PLS-
CADD and PLS-TOWER.
Required an in-depth understanding of transmission line construction practices, logistics, and
marketplace. Managed four subcontractors and internal staff from seven offices, requiring
application of work scheduling, quality control policies, and budget tracking.
KALISPELL-KERR TRANSMISSION PROJECT PROJECT MANAGER
BONNEVILLE POWER ADMINISTRATION
LOWELL ROGERS, P.E
(916) 616-0292 ● Lowell.Rogers@oakstrategic.com
3840 San Ysidro Way, Sacramento, CA 95864
Lowell Rogers, P.E. Page 6 December 11, 2019
Managed the design the 42-mile 115kV transmission line upgrade of wood pole structures including:
cross arms, cross braces, guys, anchors, insulator assemblies, conductor, ground wire, and disconnect
switches to the new BPA standards. Utilized the PLS-CADD and PLS-POLE software.
HIDDEN HILLS RANCH GENERATION PROJECT PROJECT ENGINEER
BRIGHTSOURCE ENERGY
Provided preliminary design and routing guidance during the permitting phase for new 230 and 500 kV
transmission lines near Pahrump, Nevada. This project is approximately 63 miles in length, and includes
10 miles of double circuit 230 kV tubular steel poles, a 230/500kV substation, and 53 miles of 500kV
tubular steel and lattice transmission structures. Technical challenges of the project include rugged
terrain, congested available corridors, and crossing a number of transmission lines ranging from 230 to
500kV. Design utilized PLS-CADD, PLS-POLE, and PLS-TOWER.
THURSTON COUNTY 230 KV TRANSMISSION PROJECT PROJECT MANAGER
PUGET SOUND ENERGY
Project Manager and engineer responsible for managing the project delivery of a design review of PSE’s
design for the Thurston County 230 kV Transmission Line Project, an approximately four-mile-long
transmission line that uses steel mono-pole transmission structures. Separately completed the foundation
design of drilled pier caisson foundations for 28 new 230 kV double circuit line structures in Thurston
County, Washington. These foundation types include up to two different special foundation designs be
utilized in the vicinity of McAllister Creek. Utilized PLS-CADD, PLS-POLE, and MFAD
XYZ PROJECT EVALUATION PROJECT ENGINEER
CONFIDENTIAL RAIL OWNER
Responsible for evaluating engineering and right-of-way aspects of a 3rd-party developer proposal to
construct an HVDC line within railroad property. Advised rail owner on the feasibility of the proposed
design and assessed the associated impacts to rail operations. Developed a list of alternative line
configurations available to the developer that could mitigate impacts to rail operations and/or limit
future rail expansion plans. Negotiated with developer on behalf of Owner to recommend alternative
designs to the developer and estimated costs to develop these alternatives with the goal being to establish
the maximum price that the developer would be prepared to pay for the rail easement before an
alternative alignment to the rail corridor would be seen as desirable. Presented findings to executive
management of the rail road, explaining complex technical issues and substantiating my
recommendations.
TRILOBITE SOLAR POWER PROJECT PROJECT MANAGER
PACIFIC GAS AND ELECTRIC CO.
Provided engineering for the design and routing of a low visual impact electric transmission 230 kV
interconnection of the PG&E Trilobite Solar Power Project in the southern California desert region, which
consisted of five steam turbine power blocks with a total capacity of up to approximately 750 MW.
Utilized PLS-CADD and PLS-POLE.
ROCKY FORD 230 KV DESIGN-BUILD TRANSMISSION LINE ENGINEER
GRANT COUNTY PUD
Design Engineer responsible for aspects of civil-structural engineering and procurement for transmission
line design. Also provided day-by-day support to field crews during the construction phase of the
project. Utilized PLS-CADD and PLS-POLE.
LOWELL ROGERS, P.E
(916) 616-0292 ● Lowell.Rogers@oakstrategic.com
3840 San Ysidro Way, Sacramento, CA 95864
Lowell Rogers, P.E. Page 7 December 11, 2019
HEARD COUNTY 500 KV LOOP ENGINEER
GEORGIA TRANSMISSION CORP.
Performed the civil-structural engineering and procurement for 500 kV transmission line generation tie
utilizing lattice towers and the analyses of 6 miles of lattice structures for the installation of a new OPGW.
Provided construction engineering day-by-day support to field crews during the construction phase of
the engineering, procurement, and construction services contract. Utilized PLS-CADD and PLS-TOWER.
FORT IRWIN, WIND ENERGY PLANNING AND DESIGN PROJECT MANAGER
JOHNSON CONTROLS, INC.
Managed the planning of a self-use wind energy project, providing pre-feasibility services including an
initial fatal flaw assessment related to permitting, utility interconnection and financial feasibility, a wind
data analysis and the recommendation of 3 sites for development of the project.
WARM SPRINGS WIND ENERGY DEVELOPMENT PROJECT MANAGER
WARM SPRINGS POWER ENTERPRISES
Managed engineering services to preliminary designs of collection system and generation interconnect
and cost estimates for a proposed 100 MW wind power plant located in north central Oregon.
VARIOUS CONCENTRATED SOLAR POWER PLANTS PROJECT MANAGER
CONFIDENTIAL CLIENT
Assisted client in the identification of feasible sites in California for utility-scale concentrated solar power
plants. Coordinated with land agents and environmental representatives in the assessment of projects.
Provided transmission interconnection design using steel poles, scheduling and cost estimating services
for project evaluation.
WOHLER 12KV UNDERGROUNDING AND OVERHEAD MODS PROJECT ENGINEER
SONOMA COUNTY WATER AGENCY
Provided design and construction engineering services for a new underground 12KV feeder from the
existing Wohler Substation. The project also included moving several spans of poleline out of a recharge
pond between Well Field Structures 4 and 5, relocating 2,500 KVA dry type unit substations at Well Field
Structures 3 and 4 to more stable soil, and providing necessary isolation and transfer switching at each
facility for the new feeder. Utilized PLS-CADD and PLS-POLE
CANAL TO DEWEYVILLE 345 KV TRANSMISSION LINE PROJECT MANAGER
KELSON TRANSMISSION
Project Manager; construction of a double-circuit, 95-mile long, 345-kV electric transmission line
extending from a new switching station in Chambers County, Texas to a new switching station near
Deweyville, Texas. Provided review, comment, and modification of the projects’ draft engineering,
procurement, and construction request for proposal packages. Utilized PLS-CADD and PLS-POLE.
EAST SOCIAL CIRCLE WINDER 230 KV TRANSMISSION LINE ENGINEER
CAROLINA POWER & LIGHT
Design Engineer; utilized surface and structure survey data obtained by a FLI-MAP (Faint Laser Imaging
Mapping and Profiling) process to prepare a PLS-CADD model of the transmission line using lattice
towers. Using this model, ground clearance violations were found for a range of operating temperatures,
which allowed for a cost/benefit analysis to be performed. Recommendations for conductor and
structure modification were made based on economic and engineering criteria that would provide the
desired maximum operating temperature at the lowest cost. Utilized PLS-CADD and PLS-TOWER.
LOWELL ROGERS, P.E
(916) 616-0292 ● Lowell.Rogers@oakstrategic.com
3840 San Ysidro Way, Sacramento, CA 95864
Lowell Rogers, P.E. Page 8 December 11, 2019
GEORGIA FEED 46 KV OH/UG TAP ENGINEER
GEORGIA TRANSMISSION
Project Design Engineer; designed a new 46 kV Tap line. This line provides service for the expansion of
the Georgia Feed Processing Plant and consists of a two span overhead section and a 320 ft. underground
section. Utilized PLS-CADD and PLS-POLE
BINATIONAL DESALINATION CENTRAL ARIZONA PROJECT ENGINEER
Lead the aspects related to electrical energy sourcing and delivery for the investigation of the
opportunities for desalination of ocean and brackish groundwater, conveyance to Imperial Dam,
environmental and institutional issues, and the power capacity necessary for water treatment and
conveyance to meet short and long term water demands of Arizona and Sonora, Mexico. Salt River
Project (SRP) and Central Arizona Project (CAP), in consultation with the Arizona Department of Water
Resources (ADWR) and Bureau of Reclamation, contracted to conduct the investigation of this possible
water supply.
APPLETON TO CANBY 115 KV TRANSMISSION LINE PROJECT ENGINEER
OTTER TAIL POWER
Rebuild of 45 miles of 115 kV transmission lines between Appleton and Canby, Minnesota. Assisted OTP
in preparing design documents for environmental and permit filings with MPUC. Prepared route and
need applications, supported public meetings, and worked closely with agencies. Conducted corridor
inventories of wetlands, cultural resources, threatened and endangered species, and water resources, and
prepared local, state, and federal permits.
CHISAGO COUNTY TO APPLE RIVER TRANSMISSION LINE ENGINEER
XCEL ENERGY
Upgrade an existing 69 kV transmission line to 115 kV and 161 kV. Provided environmental services and
agency coordination support associated with the Certificate of Need Environmental Report and
Minnesota Public Utility Commission Route Permit for the 18.3-mile section of the route in Minnesota.
Provided land use information, preliminary engineering, photo simulations, and GIS maps, and has
helped coordinate agency and public meetings. Utilized PLS-CADD and PLS-POLE
BLUE LAKE TROUTDALE TOWER ANALYSIS ENGINEER
PORTLAND GENERAL ELECTRIC
Design Engineer; analyzed the strength capacity of a dead-end lattice transmission tower for the addition
of an ADSS cable using PLS-CADD and PLS-TOWER. Made recommendations to strengthen specific
members that were overstressed due to the additional loading.
LADY ISLAND-RUNYAN 115 KV TRANSMISSION LINE PROJECT ENGINEER
CLARK COUNTY PUD Camas, Washington
Design Engineer responsible for detailed line design of a 115kV steel pole overhead and underground
transmission line. Utilized PLS-CADD and PLS-POLE
LIHUE ENERGY SERVICE CENTER ENGINEER
CITIZENS ENERGY SERVICES KAUAI ELECTRIC DIVISION Lihue, Hawaii
Design Engineer; engineering, procurement, and construction services for a new, double circuit 57 kV
with distribution underbuild, steel pole transmission line. This line will connect a new generation facility
to the existing system. Utilized PLS-CADD and PLS-POLE
LOWELL ROGERS, P.E
(916) 616-0292 ● Lowell.Rogers@oakstrategic.com
3840 San Ysidro Way, Sacramento, CA 95864
Lowell Rogers, P.E. Page 9 December 11, 2019
RIVERTON LAKE CROSSING ENGINEER
EMPIRE DISTRICT ELECTRIC COMPANY- Riverton, Kansas
Design Engineer responsible for analyzing the strength capacity of two, double circuit, dead-end lattice
transmission towers which were part of a line that was to be reconductored. This analysis was done using
PLS-TOWER. Made recommendations to strengthen specific members that were overstressed due to the
additional loading
SUBSTATION RELOCATION STUDY PROJECT MANAGER
CITY OF MYRTLE BEACH
Prepared feasibility analyses of three alternatives to reconfigure the existing electrical transmission
system and the connected substations within the Public Market District Beatification Area. Provided
preliminary engineering, cost estimating, and feasibility evaluation.
NORTH PARACHUTE POWER DISTRIBUTION PROJECT PROJECT MANAGER
ENCANA OIL AND GAS
Responsible for managing the development of conceptual design and cost estimate for the construction of
a 230kV to 25kV substation and four miles of 25kV distribution to serve 30 natural gas drilling platforms.
NATOMAS LEVEE IMPROVEMENT PROGRAM ENGINEER
SACRAMENTO AREA FLOOD CONTROL AGENCY
Provided electrical distribution line relocation design, a drainage study, predesign, design,
environmental documentation, permitting assistance, bid period, and construction support services for
reaches 1, 2, 4B, and 5A of the Sacramento River levee (east bank) in the Natomas area, which protects a
portion of Reclamation District No. 1000 (RD 1000). Levee repairs were needed to retain Federal
Emergency Management Agency (FEMA) certification and achieve a 200-year level of flood protection,
and included levee crown raising for all reaches (1, 2, 4B, and 5A), seepage berms (reaches 2 and 5A), and
cutoff walls (reach 4B). Redesign of the Garden Highway was required along the project reaches, as well
as relocation of utilities and other infrastructure.
AT&T - WEST UNION CELL SITE ENGINEER
PORTLAND GENERAL ELECTRIC
Analyze the strength capacity of a double circuit, light-angle lattice transmission tower for the addition of
a PCS antenna. This analysis was done using PLS-TOWER.
MARQUAM TOWERS ENGINEER
PACIFICORP
Analyzed the strength capacity of three, double circuit, lattice transmission towers which have
experienced heavy corrosion. This analysis included tower climbing and inspection, taking into account
decreased member sections caused by the corrosion. At the conclusion of the analysis, a report was issued
highlighting specific points of concern, recommending a repair procedure, and providing the estimated
life span of the structures based on different repair options. Utilized PLS-TOWER
RUSSELL 46 KV LINE RELOCATION ENGINEER
GEORGIA TRANSMISSION CORP
Designed a new wood pole distribution line because of the need to expand the existing substation.
Utilized PLS-CADD and PLS-POLE
LOWELL ROGERS, P.E
(916) 616-0292 ● Lowell.Rogers@oakstrategic.com
3840 San Ysidro Way, Sacramento, CA 95864
Lowell Rogers, P.E. Page 10 December 11, 2019
PLS-CADD TRINING FOR TELECOM REVIEW ENGINEER
EUGENE WATER AND ELECTRIC BOARD
Provided PLS-CADD and PLS-POLE training to engineers in EWEBs transmission line department
specifically to assist in analyzing the effects of placing communication cables by a third party onto their
existing would pole distribution lines.
UNDERGROUND / SUBMARINE TRANSMISSION EXPERIENCE
JEFFERSON-MARTIN 230 KV TRANSMISSION LINE ENGINEERING MANAGER
PACIFIC GAS AND ELECTRIC CO.
Engineering Manager responsible for developing routing/feasibility studies, preliminary design, and cost
estimates, for the permitting of a 26-mile long, 230kV underground/overhead transmission line located in
a challenging urban and environmentally sensitive setting. Assisted in writing the Proponents
Environmental Assessment (PEA) for filing with the California Public Utilities Commission (CPUC), as
well as provided technical review and comments of the CPUC identified alternative routes identified in
the Draft Environmental Impact Report. Mr. Rogers also prepared and presented expert testimony before
the CPUC on behalf of PG&E and facilitated a number of public comment meetings.
Responsibilities also included managing the incorporation of the EIR required mitigation measures into
the final design of the Project. As part of this effort, it was necessary to interface with the CPUC
environmental consultant and to document compliance with the pre-construction mitigation measures in
order to receive the necessary notice to proceed (NTP) required for construction.
Some of the challenging issues that were successfully overcome included traffic flow, hazardous
materials, lake and dam crossings, interfacing with local and state officials, intervener groups EMF,
sensitive habitats, and existing utility conflicts. Mr. Rogers also worked closely with PG&E’s engineering,
operations, public/media relations, and legal representatives, as well as other consultants specializing in
the fields of biology, visual, and cultural resources.
After approval of the project Mr. Rogers served as engineering manager for the underground and
overhead components for the Engineer, Procure, Construct contractor. This included detailed design,
material procurement, and construction planning.
POTRERO-HUNTERS POINT 115KV TRANSMISSION LINE ENGINEERING MANAGER
PACIFIC GAS AND ELECTRIC CO.
Engineering Manager; developed cost estimates, preliminary design, and routing/feasibility studies for
the permitting of a 3-mile long, 115kV underground transmission line through a dense urban area of San
Francisco. Worked closely with the client to review several different routes in order to select the
preferred route. This work included existing utility research, evaluation of contaminated soils, analyzing
HDD crossings, and interfacing with local government officials to discuss the project. Provided technical
input and review for the Proponents Environmental Assessment (PEA) for filing with the California
Public Utilities Commission.
Performed engineering, feasibility, and EPC cost estimating from feasibility and routing stage
through the certification of the project by the CPUC. Worked very closely with PG&E’s project
management, land department, legal, governmental affairs, and engineering staff.
LOWELL ROGERS, P.E
(916) 616-0292 ● Lowell.Rogers@oakstrategic.com
3840 San Ysidro Way, Sacramento, CA 95864
Lowell Rogers, P.E. Page 11 December 11, 2019
MURDEN COVE UNDERGROUND PROJECT PROJECT MANAGER
PUGET SOUND ENERGY
Responsible for developing and designing the cable system for the underground 115 kV, single-circuit
transmission line connecting Murden Cove substation to a future Bainbridge substation and continuing
to Winslow substation. Completed a feasibility study that identified a project study area for the new 115
kV transmission and developed the design criteria for an underground transmission line route
evaluation. Effort was undertaken to develop routes that minimize impacts to natural resources and
avoid disruption of developed areas during construction.
NEPTUNE REGIONAL TRANSMISSION SYSTEM PROJECT ENGINEER
NEPTUNE RTS.
Underground and undersea 500 kV DC transmission line connecting New Jersey to Long Island.
Engineer of record responsible for detailed design of the upland segment of the project.
CALIFORNIA CLEAN ENERGY TRANSMISSION PROJECT (CETP) PROJECT MANAGER
STARWOOD ENERGY
Managed the routing and engineering effort for the for an application to the CAISO to Design, Build,
Finance and Maintain the proposed preliminary development for the 2,000 MW HVDC/HVAC
transmission line project traversing approximately 200 miles from throughout Southern California
The scope of this effort included system impact studies, the development of project routing, design
criteria, preliminary design of steel pole and lattice structures, and cost estimating for submarine,
underground, and overhead transmission facilities as well as HVDC converter stations and
interconnecting substations.
BC RENEWABLES (CNC) TRANSMISSION LINE PROJECT MANAGER & PROJECT ENGINEER
PACIFIC GAS AND ELECTRIC CO.
Managed the engineering, right-of-way, and cost aspects of a feasibility study for the 900-mile long
BC Renewables (British Columbia to Northern California) 500 kV (AC & DC) transmission line.
Managed a multidiscipline team of engineers, right of way agents, system studies, and material
procurement to identify feasible route alternatives, the expected schedules, and alignment costs. Detailed
feasibility and cost studies were completed for both overland and submarine paths. Various line
configurations were considered, including single and double circuit 500 kV AC and 500 kV DC. This
feasibility study identified and evaluated the opportunities and constraints of the study area in order to
evaluate the feasibility of a specific corridor.
Required an in-depth understanding of transmission line construction practices, logistics, and
marketplace. Managed four subcontractors and internal staff from seven offices, requiring
application of work scheduling, quality control policies, and budget tracking.
ALCATRAZ ISLAND SOLAR PROJECT PROJECT MANAGER
NATIONAL PARK SERVICE
Managed programmatic and schematic designs, and RFP preparation, for the Alcatraz Island-to-
Mainland Electrical Connection project. This project involved offsetting the island’s current electricity
consumption by the generation of solar power on Alcatraz with the installation of photovoltaic panels
with the capacity to generate approximately 962,000 kWh/year. Designs for connecting island to
mainland via a submarine cable were also developed. Implemented creative plan to meet very aggressive
schedule requirements for the project as dictated by ARRA funding timetables. Motivated and
challenged staff to successfully meet this schedule while maintaining quality.
LOWELL ROGERS, P.E
(916) 616-0292 ● Lowell.Rogers@oakstrategic.com
3840 San Ysidro Way, Sacramento, CA 95864
Lowell Rogers, P.E. Page 12 December 11, 2019
BOWLINE SITE BENEFIT ANALYSIS PROJECT ENGINEER
NEW YORK POWER AUTHORITY
Project Engineer for a preliminary study (scope, schedule, & estimated cost) of new 7-mile long 345kV,
underground transmission line to provide the interconnection for a 2x1 CC or 3x1 CC power plant on the
existing Bowline Site.
CENTRAL LINCOLN RELIABILITY PROJECT PROJECT ENGINEER
LINCOLN ELECTRIC SYSTEM
Project engineer for the routing and conceptual design of a 115kV underground cable and overhead line
through the central core of the city of Lincoln, Nebraska. Interfaced with client’s engineering,
environmental, and public affairs groups to implement established strategy to address community
concerns while balancing project costs.
ALASKAN WAY VIADUCT AND SEAWALL REPLACEMENT PROJ. MANAGEMENT ASSISTANT
HATCH MOTT MCDONALD
Project Management Assistant Consultant (PMAC) for the existing two-level viaduct constructed in the
1950s was significantly damaged in the 2001 Nisqually earthquake and needs to be replaced. Functioned
as an extension of WSDOT staff and will provide project management support services inclusive of
design and construction phases, technical and management staff support, independent oversight and
review of preliminary design, constructability and contract methods, and packaging guidance and
support. Responsible for electrical underground facilities.
RAVENSWOOD-PALO ALTO PROJECT MANAGER
PACIFIC GAS AND ELECTRIC
Identify conceptual route alternatives that will allow two, underground 230 kV electrical transmission
circuits to connect PG&E’s Ravenswood substation and the City of Palo Alto’s Colorado substation.
Conducted engineering feasibility, construction methods analysis, and cost estimating.
WOHLER 12 KV UNDERGROUNDING AND OVERHEAD MODS PROJECT ENGINEER
SONOMA COUNTY WATER AGENCY
Provided design and construction engineering services for a new underground 12KV feeder from the
existing Wohler Substation. The project also included moving several spans of poleline out of a recharge
pond between Well Field Structures 4 and 5, relocating 2,500 KVA dry type unit substations at Well Field
Structures 3 and 4 to more stable soil, and providing necessary isolation and transfer switching at each
facility for the new feeder.
GEORGIA FEED 46 KV OH/UG TAP ENGINEER
GEORGIA TRANSMISSION
Project Design Engineer; designed a new 46 kV Tap line. This line provides service for the expansion of
the Georgia Feed Processing Plant and consists of a two-span overhead section and a 320 ft. underground
section.
NON-ELECTRICAL UTILITY EXPERIENCE
TURLOCK IRRIGATION DISTRICT UPPER MAIN CANAL REBUILD ENGINEER
The Upper Main Canal is an approximately 1-1/2 mile irrigation canal that was essentially nearing the
end of its reliable service life. Provided a study of alternatives and design of enhancements to the Upper
Main Canal to improve the long-term reliability and integrity of the water conveyance system as well as
maximize power generation at existing hydroelectric facilities.
LOWELL ROGERS, P.E
(916) 616-0292 ● Lowell.Rogers@oakstrategic.com
3840 San Ysidro Way, Sacramento, CA 95864
Lowell Rogers, P.E. Page 13 December 11, 2019
ELECTRICAL SUBSTATION EXPERIENCE
DIAMOND WILLOW WIND FARM SUBSTATION PROJECT MANAGER
MONTANA DAKOTA UTILITIES
Project Manager for the transmission system interconnection between a new wind farm and the electrical
system grid in Southeastern Montana. The substation design and construction were completed using full
EPC services and resulted in project completion in six months, which was six weeks ahead of schedule
allowing MDU to bring renewable energy to the grid to meet its 2007 renewable energy portfolio plans.
KIMBALL SUBSTATION ENGINEER
CALIFORNIA PUBLIC UTILITIES COMMISSION Provided engineering support for the preparation of
environmental documents pursuant to CEQA for the Kimball Substation, a Southern California Edison
project. The proposed project includes construction of a new 66/12 kV substation, modification of
approximately 6.7 miles of 66 kV sub-transmission line, and construction of underground electrical
circuits. In addition, 5.6 miles of existing wood poles are to be replaced.
FIELD CONSTRUCTION EXPERIENCE
PORTLAND GENERAL ELECTRIC VARIOUS SUBSTATION EXPANSIONS
Portland, Oregon. Groundman; construction of substation foundations.
GIANT PETROLEUM REFINERY SUBSTATION CONSTRUCTION
Gallup, New Mexico. Groundman; construction of substation foundations.
WESTERN AREA POWER ADMINISTRATION 500 KV SUBSTATION AND TRANSMISSION LINE
CONSTRUCTION
Tracy, California. Groundman; construction of substation and transmission line foundations.
Constructed access roads and foundations for the transmission line.
CALTRANS FEATHER RIVER BRIDGE AND HIGHWAY 162 EXPANSION
Oroville, California. Field Engineer responsible for inspection and contract conformance of roadway and
bridge structures.
CALTRANS CLEAR CREEK BRIDGE CONSTRUCTION
Redding, California. Laborer. Construction of 84-inch x 100-foot deep CIDH piles.
PRESENTATIONS
Integration of Engineering and Environmental Services in Project Development, Transmission Line
Design Subcommittee (IEEE), Albuquerque, NM, 2006
LOWELL ROGERS, P.E
(916) 616-0292 ● Lowell.Rogers@oakstrategic.com
3840 San Ysidro Way, Sacramento, CA 95864
Lowell Rogers, P.E. Page 14 December 11, 2019
TRAININGS
Design of Overhead Transmission and Distribution Lines using PLS-CADD, Instructed by Otto Lynch,
Power Line Systems
Dale Carnegie Course: Effective Communications & Human Relations/Skills for Success
HDR Career Skills: A thirteen-month, multi-phased training program to develop leadership,
communication, organizational, and other skills needed by future leaders.
1
TESTIMONY OF DAVID KEMP
IN SUPPORT OF ENERGIZE EASTSIDE
RENTON CONDITIONAL USE PERMIT FILE LUA18-000055
January 8, 2020
Good evening, your honor. My name is David Kemp and I am a senior engineer at DNV
GL. I am a licensed Professional Engineer in the state of Ohio and I have extensive background
using advanced computational methods to solve a variety of complex engineering problems and
phenomena.
One of the physical phenomenon I work with is AC interference on pipelines. This topic
is technical and dry, so please don’t hesitate to interrupt me if you have any questions for me or
want a clearer explanation.
The phrase “AC interference” refers to the induced AC voltages and resistive AC
interference effects on pipelines from nearby high voltage transmission lines, which can result in
corrosion and pipeline personnel safety hazards. I have worked on over 100 projects where I
have examined the likelihood of AC interference on pipelines that are co-located with
transmission lines in a shared utility corridor. The majority of these projects have involved
multiple pipelines and transmission lines within a shared corridor, often spanning several miles
or more.
Having both high voltage transmission lines and other utilities and pipelines in a shared
corridor is common and exist across the country. An example of that is PSE’s existing 115 kV
transmission facility that Energize Eastside will upgrade. These high voltage lines have been in
place for almost 60 years. The OPL pipelines have been located in the same shared corridor for
over 50 years.
Engineers like myself are most often hired to assess a pipeline’s susceptibility to AC
interference to determine whether mitigative measures can be taken, because as I mentioned, if
such effects are not properly addressed, AC interference effects on a pipeline can lead to
personnel safety risks and accelerated corrosion. These effects are not new phenomena. AC
interference is well-documented and there is an entire industry that studies and develops
mitigation plans to reduce these risks.
In the cases I have worked on, all but a small handful have involved pipelines and
transmission lines that were already operational in the same corridor, a retroactive approach if
2
you will. Because the facilities in these cases were already in place, the range of optimization or
mitigation measures that can actually be implemented to reduce AC interference was primarily
limited to mitigative measures installed in the ground, adjacent to and connected to the pipeline
as companies don’t typically remove and relocate their already constructed infrastructure
elsewhere simply to avoid AC interference.
Consistent with the approach by PSE on Energize Eastside, working to minimize AC
interference before the utilities are built is ideal to most efficiently mitigate AC interference
effects between utilities in shared corridors.
PSE engaged DNV GL in 2015, well before the design of Energize Eastside was
finalized. The company’s objective in hiring us was to determine whether design changes could
be made pre-construction to minimize the likelihood of AC interference effects. We worked not
only with PSE but also with OPL to get actual data about their pipelines, so that our AC
interference assessment reflected actual conditions in the ground for the existing facilities. We
studied two different scenarios for the circuits, as voltage ratings and operating loads play a role
in AC interference effects on the adjacent pipelines.
The first scenario was PSE’s preliminary proposed arrangement of one circuit operating
at 230 kV immediately and the other operating at 115 kV, which would be upgraded to 230 kV
in the future. The other scenario would have both circuits energized to 230 kV from inception.
Additionally, we modeled six different transmission line structure configurations within the
shared corridor. Using all of these variables, we ran calculations for two of the preferred routes
in order to compare the likelihood for AC interference for each of them. Based on the results of
these studies, we recommended that PSE operate both circuits at 230 kV from inception and that
the company use a specific pole design and a delta configuration in order to maximize the
reduction in potential for AC corrosion. PSE has implemented these measures in the final design
for the Energize Eastside transmission lines in the shared corridor. This work also identified
which route would enjoy the greatest minimization of potential for interference, which became
the company’s final route.
Following significant analysis incorporating data specific to this shared utility corridor,
we were able to determine that the final configuration proposed by PSE resulted in AC potentials
well within industry accepted levels for both pipeline safety and pipeline integrity in shared
corridors.
3
The project mitigation measures that are recommended in the City’s Staff Report include,
among others, the performance of just such an AC interference study. As I noted earlier, PSE had
the study performed without the City requiring it because the company wanted to proactively
optimize the design for safety. Based on this proactive approach, the company used the
recommendations from the study to revise the design of the project within the shared utility
corridor to maximize reduction in the potential for AC interference pre-construction.
The City recommended significant additional pipeline safety conditions to the Hearing
Examiner, which are detailed in the Staff Report, Exhibit 2 from pages 3-9—3-15, many of
which obligate PSE to work closely with OPL during construction and throughout the lifetime of
the project. My work focuses only on assessing and minimizing the potential for AC
interference. As you can see from what happened here, cooperation between electric utility and
pipeline operators can be very beneficial to both parties during the design phase, but this requires
early communication and information exchange.
I am happy to answer any questions you may have.
EXHIBIT A
DNV GL Headquarters, Veritasveien 1, P.O.Box 300, 1322 Høvik, Norway. Tel: +47 67 57 99 00. www.dnvgl.com
CURRICULUM VITAE
(CV generation date: 2020-01-03)
David Kemp
Senior Engineer
Current position
Senior Engineer, Computational Modeling Group, Materials Advisory Services - DNV GL
Education
Field of expertise University/School Year
Bachelor of Science, MECHANICAL
ENGINEERING
Miami University May 2008
Summary of professional experience
Mr. Kemp is a Senior Engineer for the Computational Modeling Group, under the Materials Advisory Services Section in
Dublin, Ohio. His primary work experience has involved using advanced computational and numerical methods to
analyze complex problems ranging from HVAC interference on pipelines and mitigation design, pipeline buckling,
fracture and shear damage, failure analysis, corrosion analysis, mechanical and thermal modeling, and Fitness-for-
Service analyses.
Papers and publications
·IPC2018-78636 Using Finite Element Analysis to Prioritize ILI Calls for Combined Features: Dents in Bends,
David Kemp, Shane Finneran, Justin Gossard, Joseph Bratton, ASME, Sep 2018
·Potential Impact of Powerlines on Corrosion of Abandoned Pipelines, David Kemp, Shane Finneran, PTAC,
Aug 2018
·C2018-11285 Minimizing HVAC Interference on Pipelines Through Transmission Line Design Optimization,
David Kemp, Shane Finneran, Barry Krebs, NACE International, May 2018
·CEATI PQAT 5170 Guide for Coordination of Electrical Distribution Feeders and Gas Pipelines, David Kemp,
Ray Harold, Shane Finneran, Barry Krebs, CEATI International Inc., Feb 2017
·IPC2016-64685 Evaluating Pipeline Ovality Acceptability Criteria for Straight Pipe Sections, David Kemp,
Shane Finneran, Justin Gossard, Joseph Bratton, ASME, Sep 2016
·Criteria for Pipelines Co-Existing with Electric Powerlines, Shane Finneran, David Kemp, Barry Krebs, INGAA
Foundation, Oct 2015
·C2015-5981 Examination of Grounding Methodologies for HVAC Induction on Buried Pipelines, David Kemp,
Dixon Arellano, Shane Finneran, NACE International, May 2015
Page 2 of 5 David Kemp
·IPC2014-33646 Fitness For Service of Dents Associated with Metal Loss Due to Corrosion, Hans Olav
Heggen, Joseph Bratton, David Kemp, Jun Liu, Jason Austion, ASME, Sep 2014
Employment
DNV GL Jun 2012 - Present
Position: Senior Engineer
Description: Works in the Computational Modeling group under the Materials Advisory Services
section. Uses his extensive background in Finite Element Analysis (FEA) to solve
complex problems primarily related to AC interference on pipelines, fitness-for-service
assessments, and pipeline defect assessment.
QuEST-ASE Jun 2008 - Jun 2012
Position: Senior Aero-Thermal Engineer
Description: Worked primarily in heat transfer and structural computer modeling for gas turbine
applications. Modeling work ranged from design of new cooling schemes for gas turbine
components to steady state and transient analysis and validation of current designs to
test data.
Projects
DNV Columbus, AC Mitigation Post installation comparisons Jan 2014 - Mar 2019
Description:Compared pipeline data collected in the field for AC potentials and AC current density
for pipelines after the recommended AC mitigation was installed to the modeled
predictions.
DNV Columbus, FEA Stress/Strain Assessment- Sagged Pipe
Segment
Oct 2015 - Nov 2015
Description:Performed a stress/strain assessment of a sagged pipeline segment, discovered during
excavation of an adjacent pipeline. Surveyed elevation measurements were used to first
calculate radius of curvature to determine axial strain along the pipeline. An FEA model
using pipe elements was then used to calculate more detailed strains along the pipe
segment to compare to the 1D hand calculations. These results were then compared to
acceptability standards for pipelines.
HVAC Interference Assessments on Co-Located Pipelines Jul 2012 - Jan 2020
Description:Completed over 100 projects related to AC interference and mitigation for pipelines
co-located with HVAC transmission lines. Project complexities ranging from single
pipeline/transmission line co-locations to over 50 pipelines and transmission lines
covering hundreds of miles. Created AutoCAD drawing details for mitigation design
installations to deliver to client for mitigation construction and installation.
Page 3 of 5 David Kemp
Description:Performed detailed stress-strain finite element assessment for excavated pipe segments.
Detailed laser scan of pipe dents with metal loss were used to develop finite element
models to then apply representative material properties and system loads. Detailed
sensitivity studies were performed to layout the appropriate analysis methodology to
ensure conservative conclusions for failure pressure accounting for constrained versus
unconstrained dents and residual stresses from the denting process.
DNV Columbus, Isolation Tool Certication Jan 2014 - Jul 2014
Description:Performed FEA for pipeline internal isolation tool to validate claims by manufacture for
pressure holding capacity and confirm stresses on pipeline did not exceed the yield
strength of the material. Model included elastic/plastic material properties for metallic
components as well as polymer properties to capture the deformation of the sealing
element throughout the tool's operation. Large deformations, non-linear contact, friction,
and 3D geometry were all modeled using Abaqus FEA solver.
DNV Columbus, Pipe Buckling FEA Oct 2013 - Feb 2014
Description:Used Abaqus to perform pipe buckling FEA for varying diameters and wall thicknesses of
pipe. Results of study were used to compare and validate claims and hypotheses from
published reports comparing the susceptibility to buckling for different diameter to wall
thickness ratios of pipe.
API 579 FFS Assessments for Crack-Like Flaws Mar 2019 - Jan 2014
Description:Performed Fitness for Service assessments for various crack-like flaws in the vicinity of
welds. Flaw orientations were both circumferential and axial defects assessed for mid-
wall, surface breaking ID & OD, and through-wall defects.
DNV Columbus, FGD Spray Header FEA Sep 2012 - Apr 2013
Description:Performed FEA on multiple Flue Gas Desulfurization spray headers experiencing severe
corrosion at weld heat affected zones. Several sensitivity studies performed with varying
levels and locations of corrosion to guide inspection intervals as well as to determine
welds critical to the structural integrity of the suspended piping on the headers.
DNV Columbus, Level 3 FFS Pipe Lift Jun 2012 - Aug 2012
Description:Level 3 Fitness-for-Service Assessment performed on a pipe segment undergoing
excavation. Excavation dig was flooded, causing the pipe to float. Level 3 FFS
performed to calculate induced stresses on the pipeline at the anchored ends of the
span.
DNV Columbus, Level 3 FFS Assessment of Flare Stack May 2012 - Aug 2012
Description:Performed level 3 Fitness-for-Service assessment of a refurbished flare stack installed at
a facility with a wrinkle at ~50% vertical span. Abaqus was used to model the geometry
of the flare stack and appropriate, worst case design conditions/loads were applied to
the model to calculate the induced stresses on the structure and determine the Fitness-
for-Service.
DNV Columbus, Pipe Dent Stress-Strain Assessment Jun 2015 - Oct 2015
Page 4 of 5 David Kemp
QuEST-ASE, Thermal-Stress Analysis of Heat Exchanger Jul 2011 - Feb 2012
Description:Performed thermal-stress analysis of heat exchanger using ANSYS. Using boundary
conditions provided by client, a thermal analysis was performed to obtain operating
temperatures at several different cycle conditions. These thermal results were then used
as boundary conditions on a separate stress model to obtain the stresses in the
assembly to determine lifing based upon low cycle and high cycle fatigue.
QuEST-ASE, 3D Whole Engine Thermal & Deflection Analysis Jun 2010 - Sep 2011
Description:Performed full 3D transient thermal and deflection analysis for gas turbine casing. The
goal of the study was to first convert an existing 2D model to function in ANSYS and
then build a full 3D engine casing model with a 2D axisymmetric rotor and match model
results to engine data using a physics based approach (predictive). The area of interest
was transient tip clearances, particularly during shutdown as tip clearances are directly
tied to engine efficiency.
QuEST-ASE, Thermal Stress Analysis of Manifold Mar 2011 - Jun 2011
Description:Performed transient thermal stress analysis of a turbocharger manifold. Computational
Fluid Dynamics (CFD) was used to generate internal boundary conditions of manifold at
three different cycle conditions. These boundary conditions were appied to a full 3D
ANSYS model of the assembly for a transient thermal-mechanical analysis. The final
outcome of the project was plastic strain values at several connections in the manifold
for design and operation purposes.
QuEST-ASE, Design of Internal Cooling Scheme for R2 Vane Sep 2010 - Mar 2011
Description:Tasked with developping a design tool to quickly iterate on internal cooling designs for
the Stage 2 Vane airfoil for a gas turbine used for power generation. The excel based
tool calculated boundary conditions and model input files for ANSYS which was then
used to analyze the designs. The tool and boundary conditions was first benchmarked
against a current design to verify functionality. The model was then used to develop two
designs for a new geometry, one using conventional cooling methods and a second
using advanced methods. Once the final designs were decided upon, the analysis was
performed on the full 3D geometry for each model. The final advanced concept design
saved a significant amount of flow, when compared to the conventional design. The final
advanced design was submitted for a patent in 2011
QuEST-ASE, Internal Cooling Design for Jet Engine Airfoils Jun 2009 - Dec 2009
Description:Design advanced internal cooling schemes for jet engine airfoils. Many designs were
developped using an excel and ANSYS based design tool which could quickly analyze
heat transfer effectiveness of designs. Several designs were chosen for futher stress
analysis by the customer.
QuEST-ASE, Transient Thermal Validation of Jet Engine Jun 2008 - Jan 2009
Description:Validated existing FEA thermal model of helicopter engine to existing engine test data.
Large amount of test data was used in validation and required detailed examination as
the test data was ~40 years old.
Page 5 of 5 David Kemp
Other information
Professional Engineer - Ohio Board of Professional Engineers and Surveyors
1
TESTIMONY OF BRAD STRAUCH
IN SUPPORT OF ENERGIZE EASTSIDE
RENTON CONDITIONAL USE PERMIT FILE LAU18-000055
January 8, 2020
Mr. Hearing Examiner, my name is Brad Strauch and I am the Program Manager for the
Energize Eastside project. I have a Bachelor of Science degree in Environmental and Systematic
Biology and have been working at PSE for more than 10 years. Additionally, I have more than
25 years of experience performing environmental analysis, siting, and permitting for utility
projects. This includes not only electrical transmission lines and substations, but also natural gas
pipelines, and power plants.
Since Energize Eastside was rolled out in late 2013, the public has expressed concern
about the number of trees that PSE is required to remove to construct and operate the proposed
230 kV transmission lines. Listening to this feedback, PSE created a new project goal – to make
sure that there are more trees on the Eastside at the completion of the project, not fewer.
But in fulfilling this goal, it is important to note why this project requires tree removal [in
the first place]. PSE is required by the National Electric Reliability Corporation, or NERC, to
have a plan to manage and maintain trees located in transmission line corridors that are operated
above 200 kV. This requirement, known as FAC-003-4, seeks to prevent trees from growing
into or falling on power lines, which can cause power outages. To meet this standard and
upgrade the transmission lines, we must remove certain trees along the existing 115 kV corridor.
A key factor for PSE selecting the existing corridor for the Energize Eastside project, is
that it has the fewest impacts to trees. The existing corridor was created specifically for
electrical transmission lines in the late 1920s and early 1930s. As a result, the remaining trees in
the corridor have been topped and trimmed on a regular basis to ensure safe operation of the
existing transmission lines. In other words, the majority of the trees that PSE is proposing to
2
remove have been managed by either trimming or topping over the years and as recently as a
year and a half ago. Based on our certified arborists’ assessments, around 65 percent of the
regulated trees that are expected to be removed have been classified as being in either fair or
poor condition. This is because they have been topped or trimmed over the years causing them
to decline in health.
We have identified 212 regulated trees and 122 non-regulated trees that are expected to
be removed in order to meet electrical safety clearances. It is important to emphasize that this
number is a conservative estimate based on our last survey of the trees in the corridor. For
example attached to my testimony as Exhibit A, which is a visual simulation of the proposed
project at KOP, South 12, Segment 3. This visual simulation was recently updated and is
different from what was originally submitted to the City to reflect that a large tree was removed
by the property owner and no longer requires mitigation.
As I have said, PSE is committed to providing more trees than are removed as part of the
project and will meet the City’s required tree replacement ratios as set forth in the Staff Report
recommendation J.2 and Exhibit 8, which require that PSE implement mitigation consistent with
PSE’s July 24, 2019, Vegetation Replacement Approach letter. This plan requires a 3:1
replacement ratio for trees that are removed from critical areas and replacement ratios ranging
from 1:1 to 3:1 for trees outside of critical areas, depending on their diameter (1:1 for 6” to ≤12”;
2:1 for >12 to <30”; and 3:1 for ≥30” dbh. As explained in the staff report, although this project
is exempt from tree replacement ratios under Renton’s code, these ratios are proposed to serve as
mitigation for impacts identified in the project EIS, and serve to ensure that PSE meets its goal of
more trees on the Eastside following project completion, not fewer.
To implement our vegetation plan, we have worked with the property owners to
understand their tree replacement preferences, identify which trees can remain, and develop
replacement landscaping and tree plans. An example is included with the Vegetation
3
Replacement Approach letter (which is attached to the Staff Report as Exhibit 8 and to my
testimony as Exhibit B). To date, we have met with about half of the Renton Segment property
owners who are expected to have vegetation changes. Based on the preliminary landscape plans
prepared to date, approximately 360 replacement trees are being proposed in Renton. This is
substantially more than the approximately 280 trees we anticipate will need to be replanted to
mitigate for tree removal using the replacement ratios provided in the Vegetation Replacement
letter. We expect that future meetings with the remaining half of property owners will provide
opportunities for additional new transmission line compatible trees along the corridor. PSE is
fully committed to fulfilling all of the tree planting and critical area conditions proposed by the
City.
Related to Recommendation J.3 of the staff report, I am also happy to respond to any
questions that you may have on the use of art poles in select, highly visible locations, particularly
near the Renton Technical College and along the PSE fee-owned utility corridor located at the
southern end of the project near the substations. PSE had a successful meeting with the City’s
Art Commission on November 5, 2019, to discuss the potential use of art wraps (essentially
decals which cover a portion of the pole) at select locations where the underlying property owner
is amenable. PSE has placed art wraps on poles and utility boxes in the past and concurs with
this condition if limited to the select poles (approximately 12 locations) previously discussed
with the City. Because the art wraps are placed on the lower portion of the pole, the art can be
installed and maintained without having to de-energize the line, which makes it a practicable
component of this project.
In conclusion, PSE has demonstrated that with appropriate mitigation and voluntary
planting efforts, we can effectively improve tree health and coverage within the City and add
aesthetic interest to address visual impacts in highly visible locations. I will provide a written
copy of my testimony.
EXHIBIT A
Puget Sound Energy
P.O. Box 97034
Bellevue, WA 98009-9734
PSE.com
July 24, 2019
Jill Ding
Renton City Hall, 6th Floor
11055 South Grady Way
Renton, WA 98057
RE: Renton Segment Energize Eastside – Vegetation Replacement Approach
Conditional Use (File# 17-120556-LB)
Dear Ms. Ding:
Puget Sound Energy, Inc. (PSE) provides the following information to the City of Renton (City) to support
the above referenced CUP permit application for the Energize Eastside project (Project), which also
traverses Redmond, Bellevue, Newcastle, and unincorporated King County. Within the City, the project
entails the replacement of two existing 115 kV transmission lines with two new 230 kV lines, all within
an existing utility corridor that was established in the late 1920s and early 1930s. Changing the 115 kV
system over to a 230 kV system will require vegetation management (i.e., tree trimming and removal) in
order to ensure compliance with federal requirements.
PSE is committed to fully restoring impacted areas and replacing trees for the Energize Eastside project.
Consistent with the vegetation management mitigation measures contemplated in the Energize Eastside
Final Environmental Impact Statement, the attached vegetation management approach and corridor
restoration plan is proposed.
Thank you for your effort in processing our application. Please let us know if additional clarification is
needed.
Sincerely,
Brad Strauch
Senior Land Planner
Attachments
A – Tree Retention Worksheets
B – Energize Eastside Plant Palettes
C – Draft Landscape and Tree Replacement Plan
D – Restoration Plan – Pollinator Habitat
Vegetation Approach
1
Background - Federal Requirements
The Federal Energy Regulatory Commission (FERC) has certified the North American Electrical Reliability
Corporation (NERC) as the electric reliability organization who establishes legally enforceable mandatory
standards for the U.S. bulk power system. PSE is required by NERC standards to maintain safe
clearances between vegetation and utility lines. Specifically, NERC FAC‐003‐41 (Transmission Vegetation
Management) sets forth the vegetation management requirements for transmission lines that operate
above 200 kV.
Under NERC FAC‐003‐4, PSE must prevent encroachments of vegetation into the Minimum Vegetation
Clearance Distance (MVCD) of its applicable line(s). Since the Project entails replacing the existing 115
kV lines with 230 kV lines, the upgraded transmission lines must comply with the NERC standards and
PSE’s 230 kV vegetation management standards, which generally require the removal of trees with an
expected mature height of more than 15 feet within the Wire Zone 2. Management of trees within the
transmission legal right of way3 may also be required depending on tree species, tree health, distance
from the wires, and topography.
Baseline Tree Inventory
Using GIS modeling that incorporates NERC standards, it has been estimated that there are 212
significant trees that do not meet the NERC and PSE vegetation management standards in the
transmission line corridor in Renton, the majority of which are located on private property. These trees
may need to be removed to meet the vegetation clearance requirements; however, it is important to
note that these trees are already located within an existing and managed transmission line corridor and
likely have been pruned or topped to accommodate the existing transmission lines, which can degrade
the overall health and quality of the trees. The final number of trees to be removed as a result of the
transmission line upgrade may change as the original tree inventory field work was completed on
October 13, 2016, and may also include trees that have since been removed by private property owners.
Additionally, the GIS modeling estimate does not account for changes in the overall significant tree
inventory attributed to tree growth or for trees that a certified arborist may ultimately decide do not
need to be removed. These factors are not expected to significantly affect the total number of trees
removed in the City.
1 https://www.nerc.com/_layouts/15/PrintStandard.aspx?standardnumber=FAC‐003‐
4&title=Transmission%20Vegetation%20Management&jurisdiction=United%20States
2 Wire Zone is described as 10’ outside the blowout wire alignment.
3 Legal right of way is described as the full width of the transmission corridor easement. The width varies depending on
location.
Vegetation Approach
2
Tree Replacement Approach
Under Renton Municipal Code (4‐4‐130.C.12 4), tree removal within PSE’s existing easement is an
allowed activity. Therefore, a Routine Vegetation Management Permit is not required under the City’s
code. The Tree Retention Worksheets provided as part of the Energize Eastside application materials
(see Attachment A) also confirmed that replacement trees are not required under Renton’s code. PSE
remains committed to working with property owners to replace significant trees removed and to restore
other vegetation impacts to the extent possible to fully meet the vegetation mitigation measures
discussed in the Energize Eastside Final Environmental Impact Statement.
The following methods will be used to replace trees that require removal as part of the project. PSE
understands that the City prefers that trees be replanted in proximity to where removal occurs and so
will first work to replant trees on private property located along the project corridor. PSE is also
proposing corridor restoration on the fee‐owned property located near PSE’s Talbot Hill and BPA’s
Maple Valley substations. In addition, a fee‐in‐lieu approach will be used to replace trees removed from
within City road right of way (ROW). If PSE’s tree replacement goals cannot be obtained within the
corridor on private property, then, the Arbor Day Foundation Energy Saving Tree Program will be used.
These specific approaches are described in detail in the subsequent sections. Following the description
of the various tree replacement approaches, the implementation methods are provided.
Working with Private Property Owners to Replace Trees
Removal of trees associated with transmission lines, especially when upgrading the lines within an
existing transmission line corridor, is a dynamic process. One factor that can influence evaluating and
determining which trees need to be removed is limitations on access to private property during the
design phase of a project. Not all property owners along the corridor elect to meet with PSE prior to
construction; therefore, property‐specific tree removal assessment cannot always be completed.
Using the data collected during the initial tree inventory work, the Vegetation Impact Analysis (VIA)
identified an estimated number of trees that are anticipated for removal in the corridor for each
property. Since collection of the data and subsequent analysis, PSE has been inviting property owners
to meet and discuss vegetation replacement options. At the property owner meetings project team
staff shares the current project design and gathers the property owners’ input on how their respective
properties can be replanted. Project staff shares an Energize Eastside‐specific plant palette (see
Attachment B), a reference guide of compatible replacement vegetation, and asks property owners to
share their plant preferences. Also during meetings with property owners PSE evaluates and re‐
confirms, and if necessary, updates the original tree inventory data. Using these tools, combined with
4 Utilities, Traffic Control, Walkways, Bikeways within Existing, Improved Rights‐of‐Way or Easements: Within
existing improved public road rights‐of‐way or easements, installation, construction, replacement, operation,
overbuilding, or alteration of all natural gas, cable, communication, telephone and electric facilities, lines, pipes,
mains, equipment or appurtenances, traffic control devices, illumination, walkways and bikeways. If activities
exceed the existing improved area or the public right‐of‐way, this exemption does not apply. Restoration of
disturbed areas shall be completed.
Vegetation Approach
3
discussions with the property owners, the information gathered informs the development of a Draft
Landscape and Tree Replacement Plan (see Attachment C).
Following the initial property owner meeting, project staff develops the property‐specific Draft
Landscape and Tree Replacement Plan. A second meeting is then scheduled with the property owner to
share and discuss the draft plan for their property. During the second meeting, the plan is reviewed
carefully with the property owner and necessary changes are discussed and documented.
PSE’s approach is to encourage property owners to incorporate additional trees into their landscape and
tree replacement plans; however, PSE cannot require property owners to do so nor can it dictate the
types of trees and/or vegetation that are planted. While some property owners take this as an
opportunity to add additional trees to their properties, others decline the offer of any replacement
trees. As of the end of June 2019, PSE has met with slightly more than half of the Renton property
owners who are expected to have vegetation changes along the route.
Corridor Restoration
PSE has identified areas along the Project corridor that will benefit from targeted post‐construction
restoration efforts. By using the existing transmission line corridor and focusing restoration efforts on
the properties that are owned by PSE, corridor restoration and improvements have the highest potential
for success. While most of the transmission line corridor within the City is established by easements,
the properties located directly north of PSE’s Talbot Hill and BPA Maple Valley substations are owned by
PSE. These parcels are well‐suited for restoration and improvements following construction as PSE has
control of the properties and can facilitate maintenance of the vegetation. As part of the restoration
effort PSE will use native species with an emphasis on vegetation that promotes use by pollinator
species. In addition, removal of invasive plant species will be included in the restoration work. The
restoration efforts that focus on pollinator habitat will be implemented on parcel 2023059002, which is
owned by PSE. Using PSE’s property helps ensure the successful implementation and maintenance of
the corridor restoration. Additional details are provided in the attached Restoration Plan – Pollinator
Habitat (see Attachment D). PSE believes that this approach is well‐suited for the areas as it will help
respond to declining pollinator populations at the local level, provide a passive recreational amenity,
and has long‐term vegetation compatibility with transmission lines.
City Rights of Way Tree Valuation
As stated earlier, PSE proposes to use the same City ROW tree valuation approach in Renton that has
been proposed in Bellevue to maintain an equitable approach among all affected cities. PSE
recommends using the method outlined in the Council of Tree and Landscape Appraisers’ Guide for
Plant Appraisal, 10th ed. (2018) to assess the value of trees that require removal from the City ROW. PSE
proposes that a mutually agreed upon certified arborist be selected to determine the total value of the
City ROW trees that require removal using the method described above. PSE will pay for the arborist
appraisal. Based on PSE’s review, there are 5 trees located in City ROW that would be in this category.
PSE will provide in‐lieu fee mitigation to the City for removal of City ROW trees prior to construction.
Vegetation Approach
4
This method of in‐lieu fee compensation is limited to City ROW trees and cannot be applied to trees on
other city‐owned properties or private properties over which PSE has existing easements that were
established in the late 1920s and early 1930s. These easements grant PSE the right to maintain
transmission line compatible vegetation. Consequently, trees on City (non‐ROW) and privately owned
property are only eligible for replacement with transmission line compatible species, not compensation.
Energy Saving Trees Program
If a sufficient number of trees cannot be replaced on private, PSE, or City property, then PSE will use the
Arbor Day Foundation’s Energy Saving Trees program to fully mitigate for required tree removal. More
information can be found at: https://energysavingtrees.arborday.org/#Home. PSE initiated a proactive
effort to help increase tree numbers in Renton in 2018. This effort was also utilized as a test to verify
the viability of such a program. PSE partners with the Arbor Day Foundation’s Energy‐Saving Trees
Program to provide trees to those residents that want to add trees to their property in a manner that
can help offset energy usage. While in most cases these trees are not planted along the project
corridor, they are within the City limits and help buffer potential tree loss due to factors such as
mortality and property owner changes (i.e., a new property owner removes existing trees due to
landscaping preferences). PSE also initiated use of the Energy‐Saving Trees Program in 2018 to help
offset anticipated tree removal. During the 2018 spring and fall events, PSE and the Arbor Day
Foundation provided 269 trees to Renton residents. PSE believes that continued use of this program
allows for trees to be provided to property owners who want additional trees and therefore, will make
the effort to maintain them.
Implementation
To implement these measures, PSE will follow the tree replacement approach that is described below.
PSE has successfully used the following proposed tree replacement approach on similar 115 kV to 230
kV upgrade projects. Vegetation management and replacement in long‐term utility corridors that are
primarily established by easement can be challenging. Although PSE has rights to operate transmission
lines in the corridor, the ability to require property owners to accept mitigation (i.e., additional trees) is
not specifically identified in the easements. In PSE’s experience, vegetation replacement on properties
where the owners actually want additional plantings is the most successful. This approach allows for
finalization of tree replacement numbers once construction begins. The proposed steps for tree
replacement include:
• At the time of construction, documentation of trees that are removed on a property‐by‐
property basis will be collected. This will include the tree species, inventory tag numbers, and
diameters at breast height (dbh) at the time of removal.
• This information will be cross‐referenced to the proposed landscape and tree replacement plan
that was provided to the property owner. Changes to the proposed plan could occur based on a
number of factors such as, but not limited to, property ownership changes and prior removal of
trees by the owner.
• Upon completion of replanting, PSE will document the number and species of trees that have
been removed and planted. Efforts will be made to meet the following replacement ratios:
Vegetation Approach
5
Tree Size (dbh) Replacement Ratio
Anticipated Number of
Trees to be Removed
Replacement
Trees
< 6” Per property owner request 122 (not regulated) TBD
6” to ≤ 12” 1:1 144 144
> 12” to < 30” 2:1 64 128
≥ 30” 3:1 4 12
Total 212 (regulated) 284
• PSE will monitor plant survival for one year after the planting, with replacement of the plant if a
plant does not survive.
If the required number of trees cannot be installed on private property along the corridor, PSE will
initiate the use of the Energy Saving Trees program within the city limits of Renton. This program will
target Renton ZIP codes and will be initiated during either the Fall or Spring planting season following
completion of construction.
T ECHNICAL M EMORANDUM
Date: December 21, 2017
To: Kelly Purnell
From: Amber Mikluscak, PLA, GISP
TWC Project Number: 111103
Project Name: Energize Eastside Tree Replacement Plan - Renton
Subject: Proposed Tree Retention and Replacement Methodology
for Energize Eastside – Renton Segment
As a linear corridor crossing multiple parcels, tree impacts associated with the Energize
Eastside project corridor cannot be analyzed using the standard City of Renton process. In
order to satisfy the intent of the process outlined in the Renton Municipal Code [RMC] 4-4-130
and in the City of Renton’s Tree Retention Worksheet, an alternate methodology must be
applied.
First, the bounds of the project corridor will serve as an effective “parcel” boundary, allowing
for analysis on a project-wide scale. Within the corridor, tree impacts will be analyzed using a
zonal approach; trees will be classified by zoning district, then aggregated according to the
tree retention factors that are stated in the Tree Retention Worksheet. After categorization into
zones, a Tree Retention Worksheet will be completed for each zone. Specifically, the zone s
will be as follows:
• Zone 1 – Commercial and industrial zones (0.1 retention factor)
• Zone 2 – Residential zones outside of those specified for Zone 3 (0.2 retention factor)
• Zone 3 – Zones RC, R-1, R-4, R-6 or R-8 (0.3 retention factor)
Using information gathered in the arborist field inventory and the results of the Vegetation
Impact Analysis (VIA), completed December 2017, tree retention and impacts within each
zone will be calculated using the step-by-step process outlined in the Tree Re tention
Worksheet.
To accompany each Worksheet, a map will be produced showing the extent of tree impacts
within the zone. In addition, a corresponding typical plan will be provided for each zone that
outlines the proposed replanting strategy that will be applied.
Once the required tree replacement for each zone is calculated, candidate areas for replanting
will be identified in an attempt to approach the necessary amount of required replacement
trees. In the event that there is insufficient area to achieve the required replacement quantity,
alternate strategies will be identified, such as in-lieu fee or private property owner outreach
strategies, such as tree giveaways or coupons for tree purchase, that will offset the aesthetic,
habitat, and/or other functions of the trees being impacted.
DEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
TREE RETENTION WORKSHEET
Planning Division
1055 South Grady Way-Renton, WA 98057
Phone: 425-430-7200 | www.rentonwa.gov
1.Total number of trees over 6” diameter 1, or alder or cottonwood
trees at least 8” in diameter on project site trees
2.Deductions: Certain trees are excluded from the retention calculation:
Trees that are dangerous 2 trees
Trees in proposed public streets trees
Trees in proposed private access easements/tracts trees
Trees in critical areas3 and buffers trees
Total number of excluded trees: trees
3.Subtract line 2 from line 1:trees
4.Next, to determine the number of trees that must be retained 4, multiply line 3 by:
0.3 in zones RC, R-1, R-4, R-6 or R-8
0.2 in all other residential zones
0.1 in all commercial and industrial zones trees
5.List the number of 6” in diameter, or alder or cottonwood trees
over 8” in diameter that you are proposing5 to retain4:trees
6.Subtract line 5 from line 4 for trees to be replaced:
(if line 6 is zero or less, stop here. No replacement trees are required) trees
7.Multiply line 6 by 12” for number of required replacement inches:inches
8.Proposed size of trees to meet additional planting requirement:
(Minimum 2” caliper trees required for replacement, otherwise enter 0)inches per tree
9.Divide line 7 by line 8 for number of replacement trees 6:
(If remainder is .5 or greater, round up to the next whole number) trees
1 Measured at 4.5’ above grade.
2 A tree certified, in a written report, as dead, terminally diseased, damaged, or otherwise dangerous to persons or property by a licensed
landscape architect, or certified arborist, and approved by the City.
3 Critical areas, such as wetlands, streams, floodplains and protected slopes, are defined in RMC 4-3-050.
4 Count only those trees to be retained outside of critical areas and buffers.
5 The City may require modification of the tree retention plan to ensure retention of the maximum number of trees per RMC 4-4-130H7a.
6 When the required number of protected trees cannot be retained, replacement trees, with at least a two-inch (2") caliper or an evergreen at least
six feet (6') tall, shall be planted. See RMC 4-4-130.H.1.e.(ii) for prohibited types of replacement trees.
1
H:\CED\Data\Forms-Templates\Self-Help Handouts\Planning\Tree Retention Worksheet.docx 08/2015
ZONE 1: Commercial and Industrial
Minimum Tree Density
A minimum tree density shall be maintained on each residentially zoned lot (exempting single-family
dwellings in R-10 and R-14). The tree density may consist of existing trees, replacement trees, or a
combination.
Detached single-family development 7: Two (2) significant trees 8 for every five thousand (5,000) sq. ft. of lot
area. For example, a lot with 9,600 square feet and a detached single-family house is required to have four (4)
significant trees or their equivalent in caliper inches (one or more trees with a combined diameter of 24”). This
is determined with the following formula:
Multi-family development (attached dwellings): Four (4) significant trees8 for every five thousand (5,000) sq.
ft. of lot area.
Example Tree Density Table:
Lot Lot size Min significant
trees required
New Trees Retained Trees Compliant
1 5,000 2 2 @ 2” caliper 0 Yes
2 10,000 4 0 1 tree (24 caliper
inches)
Yes
3 15,000 6 2 @ 2” caliper 1 Maple – 15
caliper inches
1 Fir – 9 caliper
inches.
Yes
7 Lots developed with detached dwellings in the R-10 and R-14 zoned are exempt from maintaining a minimum number of significant trees onsite,
however they are not exempt from the annual tree removal limits.
8 Or the gross equivalent of caliper inches provided by one (1) or more trees.
2
H:\CED\Data\Forms-Templates\Self-Help Handouts\Planning\Tree Retention Worksheet.docx 08/2015
DEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
TREE RETENTION WORKSHEET
Planning Division
1055 South Grady Way-Renton, WA 98057
Phone: 425-430-7200 | www.rentonwa.gov
1.Total number of trees over 6” diameter 1, or alder or cottonwood
trees at least 8” in diameter on project site trees
2.Deductions: Certain trees are excluded from the retention calculation:
Trees that are dangerous 2 trees
Trees in proposed public streets trees
Trees in proposed private access easements/tracts trees
Trees in critical areas3 and buffers trees
Total number of excluded trees: trees
3.Subtract line 2 from line 1:trees
4.Next, to determine the number of trees that must be retained 4, multiply line 3 by:
0.3 in zones RC, R-1, R-4, R-6 or R-8
0.2 in all other residential zones
0.1 in all commercial and industrial zones trees
5.List the number of 6” in diameter, or alder or cottonwood trees
over 8” in diameter that you are proposing5 to retain4:trees
6.Subtract line 5 from line 4 for trees to be replaced:
(if line 6 is zero or less, stop here. No replacement trees are required) trees
7.Multiply line 6 by 12” for number of required replacement inches:inches
8.Proposed size of trees to meet additional planting requirement:
(Minimum 2” caliper trees required for replacement, otherwise enter 0)inches per tree
9.Divide line 7 by line 8 for number of replacement trees 6:
(If remainder is .5 or greater, round up to the next whole number) trees
1 Measured at 4.5’ above grade.
2 A tree certified, in a written report, as dead, terminally diseased, damaged, or otherwise dangerous to persons or property by a licensed
landscape architect, or certified arborist, and approved by the City.
3 Critical areas, such as wetlands, streams, floodplains and protected slopes, are defined in RMC 4-3-050.
4 Count only those trees to be retained outside of critical areas and buffers.
5 The City may require modification of the tree retention plan to ensure retention of the maximum number of trees per RMC 4-4-130H7a.
6 When the required number of protected trees cannot be retained, replacement trees, with at least a two-inch (2") caliper or an evergreen at least
six feet (6') tall, shall be planted. See RMC 4-4-130.H.1.e.(ii) for prohibited types of replacement trees.
1
H:\CED\Data\Forms-Templates\Self-Help Handouts\Planning\Tree Retention Worksheet.docx 08/2015
ZONE 2: All other residential zones
Minimum Tree Density
A minimum tree density shall be maintained on each residentially zoned lot (exempting single-family
dwellings in R-10 and R-14). The tree density may consist of existing trees, replacement trees, or a
combination.
Detached single-family development 7: Two (2) significant trees 8 for every five thousand (5,000) sq. ft. of lot
area. For example, a lot with 9,600 square feet and a detached single-family house is required to have four (4)
significant trees or their equivalent in caliper inches (one or more trees with a combined diameter of 24”). This
is determined with the following formula:
Multi-family development (attached dwellings): Four (4) significant trees8 for every five thousand (5,000) sq.
ft. of lot area.
Example Tree Density Table:
Lot Lot size Min significant
trees required
New Trees Retained Trees Compliant
1 5,000 2 2 @ 2” caliper 0 Yes
2 10,000 4 0 1 tree (24 caliper
inches)
Yes
3 15,000 6 2 @ 2” caliper 1 Maple – 15
caliper inches
1 Fir – 9 caliper
inches.
Yes
7 Lots developed with detached dwellings in the R-10 and R-14 zoned are exempt from maintaining a minimum number of significant trees onsite,
however they are not exempt from the annual tree removal limits.
8 Or the gross equivalent of caliper inches provided by one (1) or more trees.
2
H:\CED\Data\Forms-Templates\Self-Help Handouts\Planning\Tree Retention Worksheet.docx 08/2015
DEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
TREE RETENTION WORKSHEET
Planning Division
1055 South Grady Way-Renton, WA 98057
Phone: 425-430-7200 | www.rentonwa.gov
1.Total number of trees over 6” diameter 1, or alder or cottonwood
trees at least 8” in diameter on project site trees
2.Deductions: Certain trees are excluded from the retention calculation:
Trees that are dangerous 2 trees
Trees in proposed public streets trees
Trees in proposed private access easements/tracts trees
Trees in critical areas3 and buffers trees
Total number of excluded trees: trees
3.Subtract line 2 from line 1:trees
4.Next, to determine the number of trees that must be retained 4, multiply line 3 by:
0.3 in zones RC, R-1, R-4, R-6 or R-8
0.2 in all other residential zones
0.1 in all commercial and industrial zones trees
5.List the number of 6” in diameter, or alder or cottonwood trees
over 8” in diameter that you are proposing5 to retain4:trees
6.Subtract line 5 from line 4 for trees to be replaced:
(if line 6 is zero or less, stop here. No replacement trees are required) trees
7.Multiply line 6 by 12” for number of required replacement inches:inches
8.Proposed size of trees to meet additional planting requirement:
(Minimum 2” caliper trees required for replacement, otherwise enter 0)inches per tree
9.Divide line 7 by line 8 for number of replacement trees 6:
(If remainder is .5 or greater, round up to the next whole number) trees
1 Measured at 4.5’ above grade.
2 A tree certified, in a written report, as dead, terminally diseased, damaged, or otherwise dangerous to persons or property by a licensed
landscape architect, or certified arborist, and approved by the City.
3 Critical areas, such as wetlands, streams, floodplains and protected slopes, are defined in RMC 4-3-050.
4 Count only those trees to be retained outside of critical areas and buffers.
5 The City may require modification of the tree retention plan to ensure retention of the maximum number of trees per RMC 4-4-130H7a.
6 When the required number of protected trees cannot be retained, replacement trees, with at least a two-inch (2") caliper or an evergreen at least
six feet (6') tall, shall be planted. See RMC 4-4-130.H.1.e.(ii) for prohibited types of replacement trees.
1
H:\CED\Data\Forms-Templates\Self-Help Handouts\Planning\Tree Retention Worksheet.docx 08/2015
ZONE 3: Zones RC, R-1, R-4, R-6, R-8
Minimum Tree Density
A minimum tree density shall be maintained on each residentially zoned lot (exempting single-family
dwellings in R-10 and R-14). The tree density may consist of existing trees, replacement trees, or a
combination.
Detached single-family development 7: Two (2) significant trees 8 for every five thousand (5,000) sq. ft. of lot
area. For example, a lot with 9,600 square feet and a detached single-family house is required to have four (4)
significant trees or their equivalent in caliper inches (one or more trees with a combined diameter of 24”). This
is determined with the following formula:
Multi-family development (attached dwellings): Four (4) significant trees8 for every five thousand (5,000) sq.
ft. of lot area.
Example Tree Density Table:
Lot Lot size Min significant
trees required
New Trees Retained Trees Compliant
1 5,000 2 2 @ 2” caliper 0 Yes
2 10,000 4 0 1 tree (24 caliper
inches)
Yes
3 15,000 6 2 @ 2” caliper 1 Maple – 15
caliper inches
1 Fir – 9 caliper
inches.
Yes
7 Lots developed with detached dwellings in the R-10 and R-14 zoned are exempt from maintaining a minimum number of significant trees onsite,
however they are not exempt from the annual tree removal limits.
8 Or the gross equivalent of caliper inches provided by one (1) or more trees.
2
H:\CED\Data\Forms-Templates\Self-Help Handouts\Planning\Tree Retention Worksheet.docx 08/2015
pse.com/energize eastside
Sample plant palette for vegetated screen
Replacement options are subject to location-specifi c approval and will be planted at less mature heights than shown below
Great early-spring fl owers with fragrance;
glossy, dark evergreen foliage
Four-season interest; edible summer fruit;
evergreen foliage
Flowers mid-June; evergreen foliage
Arbutus unedo ‘Compacta’
Dwarf Strawberry Tree
Camellia sasanqua
Sasanqua Camellia
Kalmia latifolia
Mountain Laurel
Edible
Parts
Maintenance
Requirement
Sun
Requirement
Water
Requirement
Friendly to
Pollinators
Native
Planting
Approximate
Size
Legend
Great winter interest; coarse leaves with
sharp margins; evergreen foliage
Small, evergreen leaves; can be sheared
or left to grow in loose mounds
Upright form; can be sheared; evergreen
needle-like leaves
Mahonia x media ‘Charity’
Hybrid Mahonia
Myrica californica
California Wax Myrtle
Taxus baccata
Yew
Tight, pyramidal, evergreen form Slender, small tree; evergreen foliage;
slow growing
Dark, evergreen foliage; fragrant blue /
purple blooms
Thuja occidentalis
Arborvitae
Tsuga mertensiana
Dwarf Mountain Hemlock
Ceanothus ‘Victoria’
California Lilac
Plant Characteristics: Plant Characteristics:
FULL MED.10’H/6’W MED.FULL MED.10’H/6’W LOW MED. MED.15’H/15’W MED.
Plant Characteristics:
FULL LOW10’H/6’W LOW FULL LOW15’H/15’W MED.MED. MED.15’H/15’W MED.
Plant Characteristics: Plant Characteristics: Plant Characteristics:
Plant Characteristics:
FULL MED.15’H/4’W LOW
Plant Characteristics:
FULL MED.20’H/8’W LOW
Plant Characteristics:
FULL MED.12’H/9’W LOW
6886 0818Updated summer 2018
pse.com/energize eastside
6886 0818
Sample plant palette for low-growing trees
Replacement options are subject to location-specifi c approval and will be planted at less mature heights than shown below
Edible
Parts
Maintenance
Requirement
Sun
Requirement
Water
Requirement
Friendly to
Pollinators
Native
Planting
Approximate
Size
Legend
Plant Characteristics: Plant Characteristics:
FULL MED.15’H/15’W LOW
Plant Characteristics:
Lace-like leaves, mounding form,
attractive branching pattern
Showy, 4-10” long pinnacles of red to
orange-red fl owers in spring
Star-shaped white fl owers, attractive fall
color; edible fruit
Aesculus pavia
Red Buckeye
Acer palmatum var. dissectum
Japanese Maple
Amelanchier alnifolia
Western Serviceberry
FULL MED.10’H/12’W LOW MED. MED.15’H/10’W LOW
FULL MED.15’H/20’W LOW FULL HIGH15’H/18’W LOW FULL MED.15’H/10’W MED.
Plant Characteristics: Plant Characteristics: Plant Characteristics:
Plant Characteristics:
FULL MED.20’H/20’W LOW
Plant Characteristics:
MED. MED.20’H/12’W LOW
Plant Characteristics:
FULL HIGH20’H/20’W MED.
Updated summer 2018
Small tree or deciduous shrub; blooms
yellow October - December
Slow-growing evergreen tree; dense and
irregular form
Disease resistant; pink fl owers in June
Compact deciduous tree with white
fl owers; golden fall color
Deciduous tree with nice fall color;
exfoliating bark on mature trees
Compact, deciduous tree with white
fl owers which bloom May - June
Hamamelis virginiana
Common Witch Hazel
Cryptomeria japonica
‘Black Dragon’
Black Dragon Japanese Cedar
Cornus kousa ‘Satomi’
Red Flowering Kousa Dogwood
Pyrus calleryana ‘Jaczam’
Jack Ornamental Pear
Parrotia persica
Persian Ironwood
Styrax japonicus
Japanese Snowbell
pse.com/energize eastside
6886 0818
Sample plant palette for low-growing trees
Replacement options are subject to location-specifi c approval and will be planted at less mature heights than shown below
Edible
Parts
Maintenance
Requirement
Sun
Requirement
Water
Requirement
Friendly to
Pollinators
Native
Planting
Approximate
Size
Legend
Plant Characteristics: Plant Characteristics:
MED. MED.20’H/20’W MED.
Plant Characteristics:
Upright, moderately spreading canopy;
four-season interest; vibrant white
fl owers and vivid red fall color
Easy growing; deciduous tree
with tri-lobed, glossy green
leaves; and vibrant fall color
Small, deep green showy foliage;
upright vase shaped tree with
exfoliating bark year-round
Acer buergerianum
Trident Maple
Amelanchier × grandifl ora
‘Autumn Brilliance’
Autumn Brilliance® Serviceberry
Chionanthus retusus
‘Tokyo Tower’
Tokyo Tower Fringe Tree
20’H/15’W MED. MED.20’H/10’W
Plant Characteristics: Plant Characteristics: Plant Characteristics:
Plant Characteristics:
MED. MED.18’H/7’W LOW
Plant Characteristics: Plant Characteristics:
Acer platanoides ‘Globosum’
Globe Norway Maple
Amelanchier grandifl ora
‘Princess Diana’
Princess Diana Serviceberry
Crataegus × mordenensis
‘Toba’
Toba Hawthorn
Halesia carolina
‘UConn Wedding Bells’
Wedding Bells Silverbell
Malus ‘Adirondack’
Adirondack Crabapple
Malus ‘JFS KW214MX’
Ivory Spear™ Crabapple
MED. MED.LOW MED.
MED. MED.20’H/20’W LOW
MED. MED.18’H/10’W LOWFULLMED.20’H/15’W MED.
MED. MED.20’H/15’W LOWMED. MED.15’H/18’W LOW
Updated summer 2018
Dense and round canopy;
near-perfect symmetry; and
vibrant fall color
Compact, oval shaped canopy;
large and signifi cant fl owers;
yellow fall foliage
A gracefully spreading small tree
with excellent long-lasting fall color;
pollinator friendly
Compact, dense, medium-
green foliage; very heavy white
fl ower clusters
A showy tree with fragrant pink
clustered fl owers in spring;
showy red berries in fall
Narrow, tightly-columnar, dark green
canopy; bright cherry-red fruit; vibrant
yellow fall color
pse.com/energize eastside
6886 0818
Sample plant palette for low-growing trees
Replacement options are subject to location-specifi c approval and will be planted at less mature heights than shown below
Edible
Parts
Maintenance
Requirement
Sun
Requirement
Water
Requirement
Friendly to
Pollinators
Native
Planting
Approximate
Size
Legend
Plant Characteristics: Plant Characteristics: Plant Characteristics:
Delicate looking and fi ne textured
leaves; elegant form with slender,
vase-shaped limbs
Hardy; small upright vase-shaped
canopy; medium green foliage with
white fl ower clusters
Narrow and columnar canopy; ascending
branch structure; purple, year-round
seasonal foliage interest
Plant Characteristics: Plant Characteristics: Plant Characteristics:
Plant Characteristics:
FULL MED.20’H/15’W LOW
Plant Characteristics: Plant Characteristics:
Maackia amurensis
Amur Maackia
Malus ‘Schmidtcutleaf’
Golden Raindrops® Crabapple
Malus ‘Red Barron’
Red Barron Crabapple
Malus ‘Jewelcole’
Red Jewel™ Crabapple
Prunus ‘Frankthrees’
Mt. St. Helens® Plum
Syringa reticulata ‘Ivory Silk’
Ivory Silk® Japanese Tree Lilac
Prunus × cistena ‘Schmidtcis’
Big Cis® Plum
Pyrus calleryana ‘Jaczam’
Jack® Pear
Tilia cordata ‘Halka’ PP 10589
Summer Sprite® Linden
FULL MED.16’H/10’W LOW14’H/12’W
20’H/15’WMED. MED.20’H/20’WFULLMED.15’H/12’W LOW
MED. MED.18’H/8’W MED.FULL MED.20’H/15’W MED.MED.LOW25’H/20’W LOW
MED.MED. MED.MED.
MED. MED.MED.
Updated summer 2018
Bright red, non-edible fruit;
upright and pyramidal canopy;
white fl owers in spring
Rounded dense, purple foliage;
light pink and fragrant fl owers
Small, rounded, upright spreading
canopy; purple foliage; hardy with
strong truck and branch form
Tight, upright, compact and oval
form; dark green foliage; bright
yellow fall color
Large, white plumes of fl owers smother
the branches in early spring; round
upright canopy
Semi-dwarf; dense, rounded, rounded
pyramid canopy; sheared appearance;
green foliage
pse.com/energize eastside
Sample plant palette for edible landscape
Replacement options are subject to location-specifi c approval and will be planted at less mature heights than shown below
Edible
Parts
Maintenance
Requirement
Sun
Requirement
Water
Requirement
Friendly to
Pollinators
Native
Planting
Approximate
Size
Legend
Plant Characteristics: Plant Characteristics: Plant Characteristics:
Deciduous shrub; spreading form; cross
pollination not needed
Multi-stemmed deciduous shrub; cross
pollination required
Deciduous small tree; requires pollination;
many proven varieties in PNW
Corylus avellana ‘Theta’
Theta Hazelnut
Ficus carica
Edible Fig
Malus domestica
Dwarf Apple
Plant Characteristics: Plant Characteristics: Plant Characteristics:
Plant Characteristics: Plant Characteristics: Plant Characteristics:
FULL MED.15’H/10’W HIGHFULLMED.20’H/20’W MED.FULL MED.20’H/15’W MED.
FULL MED.15’H/15’W HIGHFULLMED.15’H/15’W MED.FULL MED.10’H/15’W HIGH
FULL MED.20’H/15’W MED.FULL HIGH9’H/6’W MED.FULL MED.20’H/20’W HIGH
6886 0818Updated summer 2018
Trained table apple to grow horizontally;
great for small spaces
Deciduous tree; requires cross-pollination
Small, nut-bearing tree with
ornamental value
Best in acidic, well-drained soils; cross-
pollination recommended
Deciduous dwarf tree; numerous varieties
from sweet to bitter (pie cherry)
Best in rich, well-drained soils; the more
sun, the sweeter the fruit
Malus domestica
Espalier Apple Tree
Pyrus communis
Pear
Prunus dulcis
Hall’s Hardy Almond
Vaccinium corymbosum
Northern Highbush Blueberry
Prunus spp.
Cherry
Vitis labrusca
Table Grapes
pse.com/energize eastside
Sample plant palette for pollinator landscapes
Edible
Parts
Maintenance
Requirement
Sun
Requirement
Water
Requirement
Friendly to
Pollinators
Native
Planting
Approximate
Size
Legend
Plant Characteristics: Plant Characteristics: Plant Characteristics:
Herbaceous perennial; attracts birds and
butterfl ies; blooms June - August
Herbaceous perennial; attracts butterfl ies;
blooms June - September
Evergreen shrub; attracts bees; blooms in
May; blue berries in fall
Achillea millefolium
Yarrow
Echinacea purpurea
Purple Conefl ower
Mahonia nervosa
Dull Oregon Grape
FULL LOW2’H/4’W LOW
Plant Characteristics: Plant Characteristics: Plant Characteristics:
Plant Characteristics: Plant Characteristics: Plant Characteristics:
FULL LOW4’H/2’W LOWFULLLOW3’H/2’W LOW
FULL LOW2’H/2’W MED.MED. MED.6’H/6’W MED.FULL LOW10’H/8’W LOW
FULL MED.6’H/7’W LOWFULLLOW2’H/2’W LOWFULLMED.12’H/8’W HIGH
6886 0818Updated summer 2018
Deciduous shrub; attracts bees; blooms
June - August
Broadleaf deciduous; attracts bees;
blooms May - June
Deciduous shrub; attracts bees;
blooms July - August
Herbaceous perennial; attracts
butterfl ies; blooms September - October
Herbaceous perennial; attracts bufferfl ies,
bees; blooms June - August
Deciduous shrub; attracts butterfl ies;
blooms June - July
Ribes sanguineum
Flowering Currant
Holodiscus discolor
Oceanspray
Hydrangea quercifolia
Oakleaf Hydrangea
Hylotelephium ‘Herbstfreude’
Autumn Joy Sedum
Lavandula spp.
Lavendar
Spiraea japonica
Japanese Spirea
Description: A partially removed tree that is cut off 5 - 15 feet above the ground and coronet cut (see below) at the top. Provides habitat
for birds, amphibians, bees, bats, and small mammals as it decomposes in-place.
Habitat Snag Habitat Snag Habitat Snag
sample habitat snag features
pse.com/energize eastside
Sample habitat snag features
How the habitats are created
A habitat snag is an alternative where the lower portion of the tree remains. The upper portion of the tree is
removed and the tree is then 5 feet to 15 feet above the ground. The coronet cut (see below) at the top of the
tree can then provide habitat for birds, amphibians, bees, bats and small mammals as it decomposes in place.
Habitat Snag
Description: A partially removed tree that is cut off 5 - 15 feet above the ground and coronet cut (see below) at the top. Provides habitat
for birds, amphibians, bees, bats, and small mammals as it decomposes in-place.
Habitat Snag Habitat Snag Habitat Snag
sample habitat snag features
Habitat Snag
Description: A partially removed tree that is cut off 5 - 15 feet above the ground and coronet cut (see below) at the top. Provides habitat
for birds, amphibians, bees, bats, and small mammals as it decomposes in-place.
Habitat Snag Habitat Snag Habitat Snag
sample habitat snag features
Habitat Snag
Description: A partially removed tree that is cut off 5 - 15 feet above the ground and coronet cut (see below) at the top. Provides habitat
for birds, amphibians, bees, bats, and small mammals as it decomposes in-place.
Habitat Snag Habitat Snag Habitat Snag
sample habitat snag features
Step one Step two Step three Photo example
Coronet cut notes:
A coronet cut is a technique for producing a natural fracture effect in cut stub ends:
1. Cut at an angle to height as individually confi rmed in the fi eld by restoration consultant;
2. After slicing, cut down into the tree to create crevices at the top; and
3. Cut further by “bouncing” the chain saw on the top to create multiple incisions to encourage decay and colonization
by insects and fungi.
Chain saw / tool notes:
1. Use biodegradable bar and chain oil such as “motion lotion” or “Stihl.”
(Brown, Timothy K. 2002. Creating and Maintaining Wildlife, Insect, and Fish Habitat Structures in Dead Wood. U.S. Forest Service Gen. Tech. Rep.
PSW-GTR-181; Missouri Department of Conservation. 1994. Forest and Wildlife Benefi ts on Private Land, Snags and Den Trees.)
6886 0818Updated summer 2018
PLANT SHCEDULE SAMPLESAMPLESAMPLESAMPLESAMPLE RESIDENCE
© 2019 Microsoft Corporation © 2019 DigitalGlobe ©CNES (2019) Distribution Airbus DS 70717273APPROXIMATE PARCEL BOUNDARYPROPOSED TRANSMISSION POLELOCATIONPOLLINATOR PROJECT BOUNDARYEXISTING CONDITIONS160'40'20'080'LEGENDPERMIT SETNOT FORCONSTRUCTIONW1VICINITY MAPPROJECTLOCATIONPROJECT MANAGER: DESIGNED: DRAFTED: CHECKED:SHEET SIZE:ORIGINAL PLAN IS 22" x 34".SCALE ACCORDINGLY.BY© Copyright- The Watershed CompanyDATE PRINTED BY FILENAME THEWATERSHEDCOMPANYS c i e n c e & D e s i g n750 Sixth Street SouthKirkland WA 98033p 425.822.5242www.watershedco.comJOB NUMBER:SHEET NUMBER:SUBMITTALS & REVISIONS
DESCRIPTIONDATENO.TALBOT
RESTORATION PLAN - POLLINATOR
HABITAT
PSE ENERGIZE EASTSIDE
PARCEL # 2023059002, -9066, -9001, -9050 RENTON,
WA 98055JCLM/KC/LVLM/AJJC/KC/LV111103.13OF 51 11-05-2018 CONCEPT POLLINATOR HABITAT PLAN LM
2 02-12-2019 POLLINATOR HABITAT PLAN LM PARCEL #2023059002EE230 CORRIDORPARCEL #2023059003PARCEL #2023059066PARCEL #2023059001PARCEL #2023059062PROJECT SITECEDAR RIDGE DR SEAPPROX. EDGE OFEXISTING VEGETATIONOPL GAS LINE, TYP.RESTORATION PLAN - POLLINATOR HABITATPARCEL #2023059050INDEXW1 EXISTING CONDITIONSW2 POLLINATOR HABITAT, TRAIL, & TESC PLANW3 HABITAT ISLAND DETAILS & PLANT LISTW4 PLANT INSTALLATION NOTES & DETAILSW5 MAINTENANCE, MONITORING, &INSTALLATION SEQUENCE NOTESMOWED MAINTENANCEACCESS PATHPOLLINATOR PROJECT BOUNDARYTRANSMISSION TOWER, TYP.NOTENO SIGNIFICANT TREES PRESENT INPOLLINATOR HABITAT PLAN AREA. UTILITYCORRIDOR VEGETATION REGULARLY MANAGED.
70717273APPROXIMATE PARCEL BOUNDARYWOODY PLANTING ISLAND (17,800 SF)SEE DETAIL 1, W3 FOR DIMENSIONSMOWABLE POLLINATOR SEED MIX (99,215 SF)SPLIT RAIL FENCE (1,280-LF)SPOT TREAT INVASIVES WITH HERBICIDE ANDRETAIN EXISTING NATIVE VEGETATIONHIGH VISIBILITY CLEARING LIMITSFENCE (2090 LF)WALKING & MAINTENANCE ACCESSPATH (972 LF)FOLLOWING REMOVAL OF ORGANIC MATERIAL AND ROUGH GRADINGTRAIL BED, PROVIDE 95% COMPACTION. 2" 4"10'-0"CL2% CROSS SLOPE OR CROWN 6"GENERAL NOTES:1.FOLLOWING CLEARING WITHIN THE DESIGNED TRAILCORRIDOR, REMOVE ALL ORGANIC AND OTHERDEBRIS TO A DEPTH OF 6" PRIOR TO IMPORTINGCRUSHED ROCK. ESTABLISH DESIGN CROSS-SLOPEIN SUBGRADE MATERIALS, SLOPE OR CROWN ASDIRECTED.2.PROVIDE 4" BASE COURSE AND 2" TOP COURSE PERSPECIFICATION. ROLL/COMPACT EDGES OF FINISHPATH TO BLEND BACK TO ADJACENT GRADE.FINISHING GRADE OF PATH WILL BE FLUSH ORSLIGHTLY ELEVATED/CROWNED ABOVE ADJACENTSURFACES.3.IMPORT CRUSHED ROCK FOLLOWING APPROVAL OFPREPARED TRAIL BED. TAPER EDGES AT A 45°ANGLE INTO THE SUBGRADE. TOP COURSE FLUSHWITH FINISH GRADE. WHERE DESIRED, PROVIDECOMPLETE MECHANICAL COMPACTION. WHERE THISIS IMPRACTICAL OR IMPOSSIBLE, COMPACT BY HANDWITH AN APPROPRIATELY WEIGHTED IMPLEMENT.4.PERFORM SITE RESTORATION AND REVEGETATIONUPON COMPLETION OF TRAIL WORK OR AS DIRECTEDBY THE RESTORATION SPECIALIST.4" BASE COURSE - 5/8"-MINUS CRUSHED ROCK (COMPACTED)2" TOP COURSE - 1/4"-MINUS CRUSHED ROCK (COMPACTED)SILT FENCE FABRIC SHALL BE WIRED TOTOP, MIDDLE AND BOTTOM OF POSTSTEEL "T" POST OR 2"x4"WOOD POSTS, OREQUIVALENTHIGH VISIBILITY PLASTICFENCING MATERIAL (ORANGE)FINISHGRADE36" MIN.NOTES:1. DO NOT NAIL OR STAPLE FENCE TO EXISTING TREES OR UTILITY POLES.2.ANY DAMAGE TO THE FENCE SHALL BE REPAIRED IMMEDIATELY.3.FENCE TO BE REMOVED AFTER SUBSTANTIAL COMPLETION AND PRIOR TOOWNER ACCEPTANCE OF PROJECT.12" MIN.10' MAX18"
MIN.
4"12"3'-0"
6"8'-0" MAX.6"FINISHED GRADECOMPACTEDGRAVEL BASE. NOCONCRETE IS TOBE PLACED INSENSITIVE AREAS.COMPACTEDSUBGRADE6" x 6" ROUGH CUT CEDAR POSTNOTCHED TO CONTAIN ANDCONCEAL RAIL CONNECTION2" X 6" ROUGH CUTCEDAR RAILSPOLLINATOR HABITAT, TRAIL, & TESC PLAN160'40'20'080'LEGENDPERMIT SETNOT FORCONSTRUCTIONPROJECT MANAGER: DESIGNED: DRAFTED: CHECKED:SHEET SIZE:ORIGINAL PLAN IS 22" x 34".SCALE ACCORDINGLY.BY© Copyright- The Watershed CompanyDATE PRINTED BY FILENAME THEWATERSHEDCOMPANYS c i e n c e & D e s i g n750 Sixth Street SouthKirkland WA 98033p 425.822.5242www.watershedco.comJOB NUMBER:SHEET NUMBER:SUBMITTALS & REVISIONS
DESCRIPTIONDATENO.TALBOT
RESTORATION PLAN - POLLINATOR
HABITAT
PSE ENERGIZE EASTSIDE
PARCEL # 2023059002, -9066, -9001, -9050 RENTON,
WA 98055JCLM/KC/LVLM/AJJC/KC/LV111103.13OF 51 11-05-2018 CONCEPT POLLINATOR HABITAT PLAN LM
2 02-12-2019 POLLINATOR HABITAT PLAN LM PARCEL #2023059002PARCEL #2023059003PARCEL #2023059066PARCEL #2023059001PARCEL #2023059062CEDAR RIDGE DR SEAPPROX. EDGE OF EXISTINGVEGETATION (TO BE MAINTAINED)EXISTINGTRANSMISSION TOWEROPL GAS LINE, TYP.WOODY PLANTINGISLANDPROPOSED TRAILTRANSMISSION POLE TEMPORARYCONSTRUCTION ACCESS ROADScale: NTSWALKING & MAINTENANCE ACCESS TRAIL1SPOT TREAT INVASIVES WITHHERBICIDE AND RETAINEXISTING NATIVE VEGETATIONAS FLAGGED BY RESTORATIONSPECIALISTPARCEL #2023059050Scale: NTSHIGH VISIBILITY CLEARING LIMITS FENCE2Scale: NTSSPLIT RAIL FENCE32W23W21W21W3W2
FALLEN TREES TOBE APPROVED BYRESTORATIONSPECIALISTFINISHED GRADENOTES:1.LAYOUT OF DETAIL IS CONCEPTUAL. SEE PLAN FOR LOCATION. LAYOUTIN FIELD WITH ASSISTANCE FROM THE RESTORATION SPECIALIST.2.UTILIZE TREES REMOVED FROM THE TRANSMISSION LINE CORRIDOR.CORONET CUT ENDS.IF LOG HAS ROOTS,LEAVE ATTACHED1/3 ABOVE
GROUND HT.
OF SNAG
18-20' HT.NOTES1.UPRIGHT SNAGS ARE TO BE PLACED AT THELOCATIONS SHOWN ON THE PLAN2.ALL SNAGS SHALL BE WESTERN RED CEDAROR DOUGLAS-FIR TREES WITH ASUBSTANTIAL PORTION OF THEIR LIMBSLEFT INTACT. DO NOT TRIM TOPS, DAMAGEDOR BROKEN TOPS ARE PREFERRED.PROVIDE LOGS WITH NUMEROUSUNTRIMMED LIMBS. LOGS USED FOR SNAGSMAY BE PARTIALLY HOLLOW AND CONTAINCAVITIES AS LONG AS THEY AREGENERALLY SOUND.3.SNAGS SHALL BE A MINIMUM OF 18 INCHESIN DIAMETER AT GROUND SURFACE WHENINSTALLED AND SHALL BE PLACED TO ADEPTH INTO THE GROUND EQUAL TO 1/3RDOF THEIR ABOVE-GROUND HEIGHT.4.SNAGS WITH SUBSTANTIAL ROOT MASSESATTACHED MAY BE PLACED TO THE DEPTHINDICATED AND BACKFILLED WITHCOMPACTED SOIL ONLY UPON APPROVALOF EACH SNAG INDIVIDUALLY BY THERESTORATION CONSULTANT.5.UTILIZE TREES REMOVED FROM THETRANSMISSION LINE CORRIDORSNAG W/ ATLEAST 4LIMBSATTACHED4" MULCH ORPLANTED ASPER PLANTINGPLANSUBSOILBACKFILLUNDISTURBED SUBGRADECORONETCUTHABITAT ISLAND DETAILS & PLANT LISTPERMIT SETNOT FORCONSTRUCTIONScale: NTSWOODY PLANTING ISLAND1PROJECT MANAGER: DESIGNED: DRAFTED: CHECKED:SHEET SIZE:ORIGINAL PLAN IS 22" x 34".SCALE ACCORDINGLY.BY© Copyright- The Watershed CompanyDATE PRINTED BY FILENAME THEWATERSHEDCOMPANYS c i e n c e & D e s i g n750 Sixth Street SouthKirkland WA 98033p 425.822.5242www.watershedco.comJOB NUMBER:SHEET NUMBER:SUBMITTALS & REVISIONS
DESCRIPTIONDATENO.TALBOT
RESTORATION PLAN - POLLINATOR
HABITAT
PSE ENERGIZE EASTSIDE
PARCEL # 2023059002, -9066, -9001, -9050 RENTON,
WA 98055JCLM/KC/LVLM/AJJC/KC/LV111103.13OF 51 11-05-2018 CONCEPT POLLINATOR HABITAT PLAN LM
2 02-12-2019 POLLINATOR HABITAT PLAN LM PLANT LISTTREES:PACIFIC SERVICEBERRY / AMELANCHIER ALNIFOLIACORNELIAN CHERRY / CORNUS MASVINE MAPLE / ACER CIRCINATUMBLACK HAWTHORN / CRATAEGUS DOUGLASIICOMMON WITCH HAZEL / HAMAMELIS VIRGINIANASHRUBS:SNOWBRUSH / CEANOTHUS VELUTINUSTALL OREGON GRAPE / MAHONIA AQUIFOLUIMOCEAN SPRAY / HOLODISCUS DISCOLORMOCK ORANGE / PHILADELPHUS LEWISIIRED FLOWERING CURRANT / RIBES SANGUINEUMLAVENDAR / LAVANDULA SP.*GROUNDCOVER:SALAL / GAULTHERIA SHALLONSWORD FERN / POLYSTICHUM MUNITUMTUFTED HAIRGRASS / DESCHAMPSIA CESPITOSACONEFLOWER / ECHINACEA PURPUREA*PLANT AT EDGES OF WOODY PLANTING ISLANDSPOLLINATOR SEED MIX (APPLY AT SUPPLIER'S RECOMMENDED RATE):SHRUB, TYP.TREE, TYP.NATIVEPOLLINATORSEED MIX40' OR 60' (SEE W2)BRUSH PILE(SEE EXAMPLEPHOTO, W3)INSTALLED POLLINATORHABITAT STRUCTURE (SEEEXAMPLE PHOTO, W3)INSTALLEDSTANDINGSNAGBASKING &BATHING BOULDER(SEE EXAMPLEPHOTO, W3)INSTALLEDFALLEN TREEGROUNDCOVER, TYP.INSTALLED POLLINATOR HABITAT STRUCTURE EXAMPLE.PHOTO CREDIT: BEE-HAPPYHOME.DESIZE2 GAL2 GAL2 GAL2 GAL2 GAL1 GAL1 GAL1 GAL1 GAL1 GAL1 GAL1 GAL1 GAL1 GALSPACING8' O.C.8' O.C.8' O.C.8' O.C.8' O.C.4' O.C.4' O.C.4' O.C.4' O.C.4' O.C.2' O.C.2' O.C.2' O.C.2' O.C.QUANTITY16161616162502502502502509009009009002W33W32W42W41W4Scale: NTSSTANDING SNAG3Scale: NTSFALLEN TREE2BASKING & BATHING BOULDER EXAMPLE.PHOTO CREDIT: ONTARIO ROCK & LANDSCAPE SUPPLIESNATIVEPOLLINATORSEED MIXPOLLINATOR SEED MIX 1:PRODUCT NAME: NATIVE POLLINATOR SEED MIXSELLER: NORTHWEST MEADOWSCAPESAPPLICATION RATE: 5 OZ PER 1,000 SFPOLLINATOR SEED MIX 2:PRODUCT NAME: NATIVE POLLINATOR MIXSELLER: SILVER FALLS SEED COMPANYAPPLICATION RATE: 4 - 8 LBS PER ACREW3INSTALLED BRUSH PILE EXAMPLE.PHOTO CREDIT: OTTAWA FIELD NATURALIST'S CLUB
NOTES:1. PLANTING PIT SHALL NOT BE LESS THAN (2)TIMES THE WIDTH OF THE ROOT BALL DIA.2. LOOSEN SIDES AND BOTTOMS OF PLANTING PIT3. SOAK PLANTING PIT AFTER PLANTING2X MIN DIA. ROOTBALLREMOVE FROM POT OR BURLAP & ROUGH-UPROOT BALL BEFORE INSTALLING. UNTANGLEAND STRAIGHTEN CIRCLING ROOTS - PRUNE IFNECESSARY. IF PLANT IS EXCEPTIONALLYROOT-BOUND, DO NOT PLANT AND RETURN TONURSERY FOR AN ACCEPTABLE ALTERNATIVESPECIFIED MULCH LAYER. HOLD BACK MULCHFROM TRUNK/STEMSFINISH GRADEREMOVE DEBRIS AND LARGE ROCKS FROM PLANTINGPIT AND SCARIFY SIDES AND BASE. BACKFILL WITHSPECIFIED SOIL. FIRM UP SOIL AROUND PLANT.3"3"NOTES:1. PLANT GROUNDCOVER AT SPECIFIED DISTANCEON-CENTER (O.C.) USING TRIANGULAR SPACING, TYP.2. LOOSEN SIDES AND BOTTOM OF PLANTING PIT ANDREMOVE DEBRIS3. LOOSEN ROOTBOUND PLANTS BEFORE INSTALLING4. SOAK PIT BEFORE AND AFTER INSTALLING PLANTSPECIFIED MULCH LAYER.HOLD BACK MULCH FROMSTEMSSOIL AMENDMENTS AS SPECIFIEDIF VEGETATION EXISTS WITHINPLANTING AREA, SPACE AT 23 XFROM STEM OF EXISTINGVEGETATION2/3 X2/3 XAREA FOR SPACING ADJUSTMENTXXXX= PLANT SPACING= PLANTNOTE:FIRST PLACE PLANTS ALONG THEPERIMETER OF THE PLANTINGAREA, AND AROUND EXISTINGVEGETATION. THEN SPACE THEREMAINDER OF THE PLANTINGS.PLANT INSTALLATION NOTES & DETAILSPERMIT SETNOT FORCONSTRUCTIONPROJECT MANAGER: DESIGNED: DRAFTED: CHECKED:SHEET SIZE:ORIGINAL PLAN IS 22" x 34".SCALE ACCORDINGLY.BY© Copyright- The Watershed CompanyDATE PRINTED BY FILENAME THEWATERSHEDCOMPANYS c i e n c e & D e s i g n750 Sixth Street SouthKirkland WA 98033p 425.822.5242www.watershedco.comJOB NUMBER:SHEET NUMBER:SUBMITTALS & REVISIONS
DESCRIPTIONDATENO.TALBOT
RESTORATION PLAN - POLLINATOR
HABITAT
PSE ENERGIZE EASTSIDE
PARCEL # 2023059002, -9066, -9001, -9050 RENTON,
WA 98055JCLM/KC/LVLM/AJJC/KC/LV111103.13OF 51 11-05-2018 CONCEPT POLLINATOR HABITAT PLAN LM
2 02-12-2019 POLLINATOR HABITAT PLAN LM GENERAL NOTESQUALITY ASSURANCE1. PLANTS SHALL MEET OR EXCEED THE SPECIFICATIONS OFFEDERAL, STATE, AND LOCAL LAWS REQUIRING INSPECTION FORPLANT DISEASE AND INSECT CONTROL.2. PLANTS SHALL BE HEALTHY, VIGOROUS, AND WELL-FORMED,WITH WELL DEVELOPED, FIBROUS ROOT SYSTEMS, FREE FROMDEAD BRANCHES OR ROOTS. PLANTS SHALL BE FREE FROMDAMAGE CAUSED BY TEMPERATURE EXTREMES, LACK OREXCESS OF MOISTURE, INSECTS, DISEASE, AND MECHANICALINJURY. PLANTS IN LEAF SHALL BE WELL FOLIATED AND OFGOOD COLOR. PLANTS SHALL BE HABITUATED TO THE OUTDOORENVIRONMENTAL CONDITIONS INTO WHICH THEY WILL BEPLANTED (HARDENED-OFF).3. TREES WITH DAMAGED, CROOKED, MULTIPLE OR BROKENLEADERS WILL BE REJECTED. WOODY PLANTS WITH ABRASIONSOF THE BARK OR SUN SCALD WILL BE REJECTED.4. NOMENCLATURE: PLANT NAMES SHALL CONFORM TO FLORA OFTHE PACIFIC NORTHWEST BY HITCHCOCK AND CRONQUIST,UNIVERSITY OF WASHINGTON PRESS, 1973 AND/OR TO A FIELDGUIDE TO THE COMMON WETLAND PLANTS OF WESTERNWASHINGTON & NORTHWESTERN OREGON, ED. SARAH SPEARCOOKE, SEATTLE AUDUBON SOCIETY, 1997.DEFINITIONS1. PLANTS/PLANT MATERIALS. PLANTS AND PLANT MATERIALSSHALL INCLUDE ANY LIVE PLANT MATERIAL USED ON THEPROJECT. THIS INCLUDES BUT IS NOT LIMITED TO CONTAINERGROWN, B&B OR BAREROOT PLANTS; LIVE STAKES ANDFASCINES (WATTLES); TUBERS, CORMS, BULBS, ETC..; SPRIGS,PLUGS, AND LINERS.2. CONTAINER GROWN. CONTAINER GROWN PLANTS ARE THOSEWHOSE ROOTBALLS ARE ENCLOSED IN A POT OR BAG IN WHICHTHAT PLANT GREW.SUBSTITUTIONS1. IT IS THE CONTRACTOR'S RESPONSIBILITY TO OBTAIN SPECIFIEDMATERIALS IN ADVANCE IF SPECIAL GROWING, MARKETING OROTHER ARRANGEMENTS MUST BE MADE IN ORDER TO SUPPLYSPECIFIED MATERIALS.2. SUBSTITUTION OF PLANT MATERIALS NOT ON THE PROJECT LISTWILL NOT BE PERMITTED UNLESS AUTHORIZED IN WRITING BYTHE RESTORATION CONSULTANT.3. IF PROOF IS SUBMITTED THAT ANY PLANT MATERIAL SPECIFIED ISNOT OBTAINABLE, A PROPOSAL WILL BE CONSIDERED FOR USEOF THE NEAREST EQUIVALENT SIZE OR ALTERNATIVE SPECIES,WITH CORRESPONDING ADJUSTMENT OF CONTRACT PRICE.4. SUCH PROOF WILL BE SUBSTANTIATED AND SUBMITTED INWRITING TO THE CONSULTANT AT LEAST 30 DAYS PRIOR TOSTART OF WORK UNDER THIS SECTION.INSPECTION1. PLANTS SHALL BE SUBJECT TO INSPECTION AND APPROVAL BYTHE RESTORATION CONSULTANT FOR CONFORMANCE TOSPECIFICATIONS, EITHER AT TIME OF DELIVERY ON-SITE OR ATTHE GROWER'S NURSERY. APPROVAL OF PLANT MATERIALS ATANY TIME SHALL NOT IMPAIR THE SUBSEQUENT RIGHT OFINSPECTION AND REJECTION DURING PROGRESS OF THE WORK.2. PLANTS INSPECTED ON SITE AND REJECTED FOR NOT MEETINGSPECIFICATIONS MUST BE REMOVED IMMEDIATELY FROM SITEOR RED-TAGGED AND REMOVED AS SOON AS POSSIBLE.3. THE RESTORATION CONSULTANT MAY ELECT TO INSPECT PLANTMATERIALS AT THE PLACE OF GROWTH. AFTER INSPECTION ANDACCEPTANCE, THE RESTORATION CONSULTANT MAY REQUIRETHE INSPECTED PLANTS BE LABELED AND RESERVED FORPROJECT. SUBSTITUTION OF THESE PLANTS WITH OTHERINDIVIDUALS, EVEN OF THE SAME SPECIES AND SIZE, ISUNACCEPTABLE.MEASUREMENT OF PLANTS1. PLANTS SHALL CONFORM TO SIZES SPECIFIED UNLESSSUBSTITUTIONS ARE MADE AS OUTLINED IN THIS CONTRACT.2. HEIGHT AND SPREAD DIMENSIONS SPECIFIED REFER TO MAINBODY OF PLANT AND NOT BRANCH OR ROOT TIP TO TIP. PLANTDIMENSIONS SHALL BE MEASURED WHEN THEIR BRANCHES ORROOTS ARE IN THEIR NORMAL POSITION.3. WHERE A RANGE OF SIZE IS GIVEN, NO PLANT SHALL BE LESSTHAN THE MINIMUM SIZE AND AT LEAST 50% OF THE PLANTSSHALL BE AS LARGE AS THE MEDIAN OF THE SIZE RANGE.(EXAMPLE: IF THE SIZE RANGE IS 12" TO 18", AT LEAST 50% OFPLANTS MUST BE 15" TALL.).SUBMITTALSPROPOSED PLANT SOURCES1. WITHIN 45 DAYS AFTER AWARD OF THE CONTRACT, SUBMIT ACOMPLETE LIST OF PLANT MATERIALS PROPOSED TO BEPROVIDED DEMONSTRATING CONFORMANCE WITH THEREQUIREMENTS SPECIFIED. INCLUDE THE NAMES ANDADDRESSES OF ALL GROWERS AND NURSERIES.PRODUCT CERTIFICATES1. PLANT MATERIALS LIST - SUBMIT DOCUMENTATION TOCONSULTANT AT LEAST 30 DAYS PRIOR TO START OF WORKUNDER THIS SECTION THAT PLANT MATERIALS HAVE BEENORDERED. ARRANGE PROCEDURE FOR INSPECTION OF PLANTMATERIAL WITH CONSULTANT AT TIME OF SUBMISSION.2. HAVE COPIES OF VENDOR'S OR GROWERS' INVOICES ORPACKING SLIPS FOR ALL PLANTS ON SITE DURING INSTALLATION.INVOICE OR PACKING SLIP SHOULD LIST SPECIES BY SCIENTIFICNAME, QUANTITY, AND DATE DELIVERED (AND GENETIC ORIGIN IFTHAT INFORMATION WAS PREVIOUSLY REQUESTED).DELIVERY, HANDLING, & STORAGEPLANT MATERIALS1. TRANSPORTATION - DURING SHIPPING, PLANTS SHALL BEPACKED TO PROVIDE PROTECTION AGAINST CLIMATE EXTREMES,BREAKAGE AND DRYING. PROPER VENTILATION ANDPREVENTION OF DAMAGE TO BARK, BRANCHES, AND ROOTSYSTEMS MUST BE ENSURED.2. SCHEDULING AND STORAGE - PLANTS SHALL BE DELIVERED ASCLOSE TO PLANTING AS POSSIBLE. PLANTS IN STORAGE MUSTBE PROTECTED AGAINST ANY CONDITION THAT IS DETRIMENTALTO THEIR CONTINUED HEALTH AND VIGOR.3. HANDLING - PLANT MATERIALS SHALL NOT BE HANDLED BY THETRUNK, LIMBS, OR FOLIAGE BUT ONLY BY THE CONTAINER, BALL,BOX, OR OTHER PROTECTIVE STRUCTURE, EXCEPT BAREROOTPLANTS SHALL BE KEPT IN BUNDLES UNTIL PLANTING AND THENHANDLED CAREFULLY BY THE TRUNK OR STEM.4. LABELS - PLANTS SHALL HAVE DURABLE, LEGIBLE LABELSSTATING CORRECT SCIENTIFIC NAME AND SIZE. TEN PERCENTOF CONTAINER GROWN PLANTS IN INDIVIDUAL POTS SHALL BELABELED. PLANTS SUPPLIED IN FLATS, RACKS, BOXES, BAGS, ORBUNDLES SHALL HAVE ONE LABEL PER GROUP.WARRANTYPLANT WARRANTYPLANTS MUST BE GUARANTEED TO BE TRUE TO SCIENTIFIC NAMEAND SPECIFIED SIZE, AND TO BE HEALTHY AND CAPABLE OFVIGOROUS GROWTH.REPLACEMENT1. PLANTS NOT FOUND MEETING ALL OF THE REQUIREDCONDITIONS AT THE CONSULTANT'S DISCRETION MUST BEREMOVED FROM SITE AND REPLACED IMMEDIATELY AT THECONTRACTOR'S EXPENSE.2. PLANTS NOT SURVIVING AFTER ONE YEAR TO BE REPLACED ATTHE CONTRACTOR'S EXPENSE.PLANT MATERIALGENERAL1. PLANTS SHALL BE NURSERY GROWN IN ACCORDANCE WITHGOOD HORTICULTURAL PRACTICES UNDER CLIMATICCONDITIONS SIMILAR TO OR MORE SEVERE THAN THOSE OF THEPROJECT SITE.2. PLANTS SHALL BE TRUE TO SPECIES AND VARIETY ORSUBSPECIES. NO CULTIVARS OR NAMED VARIETIES SHALL BEUSED UNLESS SPECIFIED AS SUCH.QUANTITIESSEE PLANT LIST ON ACCOMPANYING PLANS AND PLANT SCHEDULES.ROOT TREATMENT1. CONTAINER GROWN PLANTS (INCLUDES PLUGS): PLANT ROOTBALLS MUST HOLD TOGETHER WHEN THE PLANT IS REMOVEDFROM THE POT, EXCEPT THAT A SMALL AMOUNT OF LOOSE SOILMAY BE ON THE TOP OF THE ROOTBALL.2. PLANTS MUST NOT BE ROOT-BOUND; THERE MUST BE NOCIRCLING ROOTS PRESENT IN ANY PLANT INSPECTED.3. ROOTBALLS THAT HAVE CRACKED OR BROKEN WHEN REMOVEDFROM THE CONTAINER SHALL BE REJECTED.PLANT INSTALLATION SPECIFICATIONSScale: NTSTREE AND SHRUB PLANTING2Scale: NTSGROUNDCOVER PLANTING1Scale: NTSPLANT SPACING3W4
MAINTENANCE, MONITORING, & INSTALLATION SEQUENCE NOTESPERMIT SETNOT FORCONSTRUCTIONPROJECT MANAGER: DESIGNED: DRAFTED: CHECKED:SHEET SIZE:ORIGINAL PLAN IS 22" x 34".SCALE ACCORDINGLY.BY© Copyright- The Watershed CompanyDATE PRINTED BY FILENAME THEWATERSHEDCOMPANYS c i e n c e & D e s i g n750 Sixth Street SouthKirkland WA 98033p 425.822.5242www.watershedco.comJOB NUMBER:SHEET NUMBER:SUBMITTALS & REVISIONS
DESCRIPTIONDATENO.TALBOT
RESTORATION PLAN - POLLINATOR
HABITAT
PSE ENERGIZE EASTSIDE
PARCEL # 2023059002, -9066, -9001, -9050 RENTON,
WA 98055JCLM/KC/LVLM/AJJC/KC/LV111103.13OF 51 11-05-2018 CONCEPT POLLINATOR HABITAT PLAN LM
2 02-12-2019 POLLINATOR HABITAT PLAN LM MAINTENANCE, MONITORING & INSTALLATION SEQUENCEW5PUGET SOUND ENERGY (PSE) PROPOSES A POLLINATOR HABITAT PLAN (PHP) TOIMPROVE DEGRADED VEGETATED LANDS UNDER EXISTING TRANSMISSION LINESIN THE CITY OF RENTON. THE PHP HAS BEEN DEVELOPED IN COORDINATIONWITH THE ENERGIZE EASTSIDE PROJECT (PROJECT) AND IS INTENDED AS ANOUT-OF-KIND MITIGATION STRATEGY TO COMPENSATE FOR THE REMOVAL OFTREES ASSOCIATED WITH THE PROJECT IN RENTON. THE PHP SEEKS TOIMPROVE HABITAT FUNCTIONS FOR LOCAL POLLINATORS AND SERVE AS ANAMENITY TO THE COMMUNITY IN WHICH IT'S LOCATED.THE PHP INCLUDES A WALKING PATHWAY FOR COMMUNITY AND MAINTENANCEUSE, EXPANSIVE AREAS OF HERBACEOUS POLLINATOR-FRIENDLY PLANTS(HERBACEOUS MEADOWS), AND VEGETATION ISLANDS WHICH INCLUDE DENSEWOODY VEGETATION, SNAGS, LOGS, BRUSH PILES, BOULDERS, ANDCONSTRUCTED POLLINATOR HABITAT STRUCTURES (WOODY ISLANDS). AVARIETY OF PLANTS INCLUDING NATIVE AND NON-NATIVE SPECIES WITHWIDE-RANGING BLOOM TIMES, COLORS AND FORMS HAVE BEEN SELECTED TOPROVIDE NECTAR AND POLLEN TO POLLINATORS THROUGHOUT THE YEAR.CONSTRUCTION NOTES AND SPECIFICATIONSTHE RESTORATION PROFESSIONAL WILL BE PRESENT FOR THE FOLLOWINGCONSTRUCTION BENCHMARKS:1. PRE-CONSTRUCTION MEETING (WORK SEQUENCE STEP #2)2. IDENTIFICATION OF WOODY ISLANDS AND TRAIL ALIGNMENT (WORKSEQUENCE STEPS #13 & 14)3. HABITAT FEATURE INSTALLATION (WORK SEQUENCE STEP #15)4. PLANT MATERIAL (WORK SEQUENCE STEPS #17 & 18):A. PLANT MATERIAL DELIVERY INSPECTION.B. 50% WOODY ISLAND INSTALLATION/LAYOUT INSPECTIONC. 100% WOODY ISLAND INSTALLATION INSPECTION AND HERBACEOUSMEADOW INSTALLATION OVERSIGHT.THE RESTORATION PROFESSIONAL SHALL BE IN REGULAR COMMUNICATIONWITH PSE AND/OR THE CONTRACTOR(S) CARRYING OUT SITE PREPARATION ANDINSTALLATION ACTIVITIES OVER THE COURSE OF THE INITIAL-WORK GROWINGSEASON. SITE PREPARATION AND INSTALLATION METHODS WILL DIRECTLYAFFECT FUTURE SUCCESS OF THE SITE, AND SHOULD BE CONDUCTEDTHOROUGHLY AND THOUGHTFULLY. THE RESTORATION PROFESSIONAL SHALLBE AVAILABLE FOR UNPLANNED COORDINATION AND CONSTRUCTIONADMINISTRATION AS NECESSARY TO IMPROVE EFFECTIVE AND ACCURATEINSTALLATION AND TO DOCUMENT ANY DEVIATIONS FROM THESE PLANS.WORK SEQUENCEFIRST DORMANT SEASON (LATER OCTOBER - JANUARY) - SITE PREP1. INSTALL HIGH VISIBILITY CLEARING LIMITS FENCE ACCORDING TO DETAIL 2,W2.2. DURING PRE-CONSTRUCTION WALK-THROUGH OR MEETING, RESTORATIONPROFESSIONAL SHALL FLAG AREAS OF EXISTING VEGETATION TO REMAINAND THE CENTER POINT OF WOODY ISLANDS.3. CUT DOWN AND GRIND STUMPS OF ANY TREES AND SHRUBS THAT ARE TOOLARGE TO MOW AND NOT PLANNED FOR RETENTION. BRANCHES AND LIMBSMAY BE STOCKPILED ONSITE FOR SUBSEQUENT CREATION OF BRUSH PILES(SEE STEP #15 BELOW).4. REMOVE ANY TRASH, DEBRIS, OR CONCRETE, AND PROPERLY DISPOSE OFOFFSITE. RECYCLE AS MUCH MATERIAL AS POSSIBLE.5. SALVAGE EXISTING BOULDERS FOUND THROUGHOUT HERBACEOUSMEADOWS AND STOCKPILE THEM ONSITE FOR INSTALLATION LATER (SEESTEP #15 BELOW).6. MOW IDENTIFIED PLANTING AREAS TO THE GROUND (MAJORITY OF SITE);RETAIN DESIRABLE NATIVE VEGETATION WHERE INDICATED INPRE-CONSTRUCTION MEETING.7. WHERE NOXIOUS WEEDS ARE GROWING IN PATCHES OF RETAINEDVEGETATION, DETERMINE APPROPRIATE METHOD OF TREATMENT WITHRESTORATION PROFESSIONAL (E.G., MANUAL REMOVAL, SPOT-SPRAY WITHHERBICIDE, WIPE/WICK WITH HERBICIDE, CUT-STUMP HERBICIDETREATMENT).GROWING SEASON (MARCH - SEPTEMBER - WEED TREATMENT, TRAIL & HABITATFEATURE INSTALLATION8. IN EARLY SPRING, WHEN MOWED VEGETATION BEGINS TO REGENERATE,BROADLY APPLY HERBICIDE TO PREVIOUSLY MOWED AREAS TO KILL THEEXISTING WEED-MAJORITY BASE. HERBICIDE SHOULD BE APPLIED BY ASTATE-LICENSED APPLICATOR AND IN ACCORDANCE WITH THE DIRECTIONSON THE PRODUCT LABEL. AVOID CONDITIONS THAT WOULD CAUSE SPRAYTO DRIFT, THEREBY AFFECTING NON-TARGET VEGETATION. EXERCISECARE WHEN APPLYING HERBICIDE NEAR DESIRABLE, NATIVE VEGETATIONTO BE RETAINED.9. CONTINUE CONTROL OF NOXIOUS WEEDS IN RETAINED VEGETATIONPATCHES (SEE STEP 7 ABOVE).10. MONITOR THE SITE AND APPLY ADDITIONAL, TARGETED ROUNDS OFHERBICIDE WHEN NEW GROWTH CAN BE OBSERVED ON PREVIOUSLYTREATED PLANTS OR AS NEW, WARM-WEATHER WEEDS GERMINATE LATERIN THE GROWING SEASON.11. MONITOR, AND HERBICIDE-TREAT THE SITE AS NEEDED, ON MONTHLY BASISFOR ONE FULL GROWING SEASON.12. AT THE END OF THE GROWING SEASON, ONCE AGAIN MOW THE TREATEDAREA TO THE GROUND TO REMOVE ANY REMAINING ABOVE-GROUND PLANTPARTS.13. FLAG THE BOUNDARIES OF THE WOODY ISLANDS.14. INSTALL WALKING AND MAINTENANCE ACCESS PATH ACCORDING TO DETAIL1, W2.15. INSTALL THE WOODY ISLAND HABITAT FEATURES INCLUDING STANDINGSNAGS, FALLEN TREES, BRUSH PILES, BOULDERS AND CONSTRUCTEDPOLLINATOR HABITAT STRUCTURES ACCORDING TO DETAILS 1, 2 AND 3, W3AND UNDER THE SUPERVISION OF A RESTORATION PROFESSIONAL.16. BLANKET MULCH THE WOODY ISLANDS WITH 4-INCHES OF WOOD CHIPMULCH.SECOND DORMANT SEASON - PLANT INSTALLATION & FENCING17. DURING THE FOLLOWING DORMANT SEASON (LATE OCTOBER - JANUARY),PLANT WOODY ISLANDS ACCORDING TO DETAIL 1, W3 AND DETAILS 1 AND 2,W4. SHRUBS SHOULD BE PLANTED IN GROUPS OF 3, 5 OR 7.18. DRILL-SEED HERBACEOUS MEADOWS DURING NOVEMBER - DECEMBERWITH THE SPECIFIED SEED MIXES AT RECOMMENDED RATES (SEE SHEETW3). DO NOT SEED THE INSTALLED WOODY ISLANDS.19. REMOVE HIGH-VISIBILITY CLEARING LIMITS FENCING.20. INSTALL SPLIT RAIL FENCING ACCORDING TO DETAIL 3, W2.21. SCHEDULE REGULAR MAINTENANCE ACTIVITIES TO BEGIN IN THEUPCOMING GROWING SEASON. REGULAR MAINTENANCE ACTIVITIES TO BESCHEDULED SHALL INCLUDE A WATERING TRUCK FOR AT LEAST THE FIRSTGROWING SEASON.SITE MAINTENANCE & LONG-TERM BMPSYEAR 1 MAINTENANCE1. IRRIGATE WOODY ISLANDS DURING PERIODS OF LOW RAINFALL FROM JUNE1 TO OCTOBER 1 ON A WEEKLY OR BI-WEEKLY BASIS. ENSURE PLANTSRECEIVE A DEEP SOAKING DURING WATERING VISITS, ESPECIALLY WHENINFREQUENT.2. IRRIGATE HERBACEOUS MEADOWS IN THE WEEKS FOLLOWINGINSTALLATION IF PRECIPITATION IS NOT ADEQUATE FOR SEEDGERMINATION. FOLLOWING SEED GERMINATION, WATER HERBACEOUSMEADOWS DURING WOODY ISLAND WATERING TO AID IN SEEDLINGSURVIVAL.3. CONTROL ANNUAL WEEDS (WHICH ARE OFTEN TIMES FAST-GROWING) BYREMOVING FLOWER HEADS BEFORE THEY BLOOM. THIS CAN BEACCOMPLISHED BY MOWING WEEDY AREAS AT WHATEVER HEIGHTNECESSARY TO REMOVE WEED FLOWER HEADS OR BY CUTTING ANDREMOVING FLOWER HEADS BY HAND. REGULAR ANNUAL-WEED-SEEDREMOVAL SHOULD OCCUR EVERY 4-6 WEEKS DURING THE FIRST GROWINGSEASON.A. HAND-PULLING IS NOT A PREFERRED WEED CONTROL METHOD IN YEAR 1BECAUSE IT ALSO IMPACTS NEARBY DESIRABLE SEEDLINGS.B. SPOT-SPRAYING OR WIPING WITH HERBICIDE MAY BE AN ACCEPTABLEAPPROACH FOR ISOLATED WEED PATCHES, IF APPROVED BY THERESTORATION PROFESSIONAL.4. AREAS PLANTED WITH POLLINATOR SEED MIXES SHALL BE MOWEDANNUALLY IN THE EARLY WINTER AFTER PLANTS HAVE BLOOMED FOR TWOYEARS FOLLOWING INSTALLATION.YEAR 2 MAINTENANCE1. RE-SEED SPARSE PATCHES IN HERBACEOUS MEADOW AREAS AS DIRECTEDBY RESTORATION PROFESSIONAL FOLLOWING THE YEAR 1 REPORT.2. DURING EXCEPTIONALLY DRY PERIODS, IRRIGATE WOODY ISLAND ANDHERBACEOUS MEADOWS WITH A THOROUGH SOAKING.3. WEED MAINTENANCE FOCUS SHOULD SHIFT FROM ANNUAL WEED SPECIESREMOVAL TO BIENNIAL WEED REMOVAL (SPECIES LIKE QUEEN ANNE'S LACE,DAUCUS CAROTA).A. MANAGE WEEDS BY MOWING OR MANUALLY REMOVING WEEDY FLOWERHEADS BEFORE THEY BLOOM, APPROXIMATELY EVERY 6 WEEKS.YEAR 3 MAINTENANCE & LONG-TERM BEST MANAGEMENT PRACTICES (BMPS)1. CEASE REGULAR MOWING OF THE HERBACEOUS MEADOW AREA ANDIRRIGATION OF ALL INSTALLED PLANTS.2. MANAGE WEEDS ACROSS THE SITE TWICE YEARLY (EARLY- ANDMID-GROWING SEASON IS BEST), OR MORE FREQUENTLY IF NECESSARY.A. SPOT-TREAT OR MECHANICALLY CONTROL HERBACEOUS WEEDS ANDWOODY VEGETATION IN HERBACEOUS MEADOWS (AS OPPOSED TOSITE-WIDE MOWING).B. HAND-PULL OR GRUB WEEDS AND WEED ROOTS FROM WOODY ISLANDPLANTING AREAS.3. MAINTAIN HABITAT FEATURES (SNAGS, LOGS, BRUSH PILES, BOULDERS,AND CONSTRUCTED POLLINATOR HABITAT STRUCTURES) IN GOODCONDITION TO THE EXTENT FEASIBLE WHILE ENSURING PUBLIC SAFETY.4. GENERAL UTILITY CORRIDOR BMPS FOR POLLINATOR HABITAT:A. LIMIT MOWING WHICH REMOVES FLOWERS, IMPACTS NEST SITES, ANDTENDS TO FAVOR DEVELOPMENT OF GRASSES OVER HERBACEOUSVEGETATION.B. IF MOWING IS NECESSARY, MOW AFTER LATE-FLOWERING PLANTS HAVEBLOOMED AND LEAVE SOME AREAS UNCUT, PER RECOMMENDATIONSFROM RESTORATION PROFESSIONAL. MOW SITE ON A THREE-FOUR-YEAR ROTATION.C. INSECTICIDE SHALL NOT BE USED.D. USE HERBICIDES STRATEGICALLY AND SPARINGLY TO SPOT-TREATWEEDS AND WOODY VEGETATION IN HERBACEOUS MEADOWS.
EXHIBIT B
EXHIBIT C
BRAD STRAUCH
Puget Sound Energy, 355 110th Ave. NE, Bellevue, WA 98004
bradley.strauch@pse.com
PROFILE OF QUALIFICATIONS
More than twenty-five years of professional experience in environmental related disciplines
and the biological sciences, including twenty years of project and program management
experience. Specializing in site development, linear utility projects, and environmental
permitting. In addition, extensive experience in the following areas:
Environmental Program Management Wetland Delineations
Environmental Permitting (SEPA & NEPA) Wildlife Studies
Siting Studies for Energy Facilities Regulatory Compliance Auditing
Environmental Construction Oversight Property Transfer Assessments
Asbestos Surveys Subsurface Investigations
PROFESSIONAL EXPERIENCE
Puget Sound Energy 2006 to Present
EFI Global, Inc. 2003 to 2006
SECOR International, Inc. 1999 to 2003
ENSR Consulting and Engineering 1989 to 1999
RELEVANT WORK EXPERIENCE
Project Permitting
Currently the Infrastructure Program Manager for PSE’s Energize Eastside project. This
entails overseeing and directing the permitting effort of the project, as well as coordinating
the technical analysis, engineering design, and community outreach components to ensure
compliance with applicable local, state, and federal regulations. Prior to the Energize
Eastside project, was responsible for developing and implementing critical areas
assessments and mitigation plans, project siting, and permit acquisition for PSE natural gas
and electrical projects.
While working at consulting firms, I was the Project Manager and Technical Lead for
numerous projects for Puget Sound Energy and Cascade Natural Gas involving new and
relocations of natural gas pipelines and electrical facilities. Work has continued as a
Municipal Land Planner for PSE. Project work has included the preparation of permit
applications, including SEPA checklists, storm water pollution prevention plan, the Joint
Aquatic Resource Permits Application (JARPA) for Hydraulic Project Approvals (HPA),
Shoreline Substantial Development and Conditional Use permits, Zoning Conditional Use
permits, Section 106 Historic Preservation Act Compliance, Ecology 401 Water Quality
Certifications, and U.S. Army Corps of Engineers 404 & Section 10 permits. Additional
responsibilities included agency negotiations, project development support, and preparing
erosion control and mitigation plans.
In addition, have developed erosion and sediment control plans, which include selection of
specific best management practices to be used in sensitive areas during project construction.
2
During project construction, have performed field inspections to ensure compliance with
plans and recommended restoration and compliance actions.
Natural Resources
Served as Project Manager and Technical Lead on various wildlife studies at sites primarily
in Washington State. Species studied included raptors, amphibians, reptiles, and small
mammals. Completed numerous Biological Assessments/Evaluations for development
projects and other federal activities. Assessed species presence, population status,
reproductive success, and habitat conditions. Also, evaluated impacts of surrounding
activities on species and their habitats, and provided recommendations for continuing
existing operations with minimal impacts on species and habitat. Studies consisted of
surveying hundreds of thousands of acres and establishing survey grids and trap arrays in
various habitats. Additionally, have performed numerous wetland/stream delineations
using the 1987 Corps of Engineers and Ecology delineation and rating manuals. Negotiated
clearing limits and permit conditions with local and state agencies and development
agencies. Developed wetland/stream crossing and mitigation plans, as well as planting
plans for right-of-way restoration.
Feasibility Analysis
Managed and directed feasibility studies and developed environmental permitting
schedules for proposed linear and development projects, including multi-jurisdictional
projects. Have organized and managed multi-disciplinary teams necessary to accomplish
the studies necessary to determine if the proposed projects were feasible and help identify
potential alternatives. Feasibility studies reviewed alternative routes for schedule, cost,
constructability, system reliability, permitting issues, environmental limitations, and
potential public opposition. Work a primary liaison between the legal department and the
project team to help balance the positions of both sides. In addition, participated in
meetings with the local, state, tribal, and federal agencies, as well as public open houses
associated with various projects.
Management and Supervisory
Have managed both large and small project teams and departments. Supervised a small
department of scientist brought on to develop a new business unit for a consulting firm. On
a larger scale, managed almost fifty individuals during a large project for the U.S. Army
that lasting over three years. Had to provide performance appraisals and at times assist
with disciplinary actions. Either with large or small groups, focus is and has always been on
empowering individual to take on more complex and difficult work activities by being
approachable and helping instill confidence. Mentorship and approachability have been
important skills/traits that I believe are critical to the success of a department. This has
been best developed by establishing a high level of trust.
EDUCATION, LICENSES, AND CERTIFICATIONS
B.Sc. Environmental and Systematic Biology, California Polytechnic State University at San
Luis Obispo, 1987
Certified Erosion and Sediment Control Lead, AGC Education Foundation, Seattle, WA
99640
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
PUGET SOUND ENERGY’S HEARING
MEMORANDUM - 1
719 Second Avenue Suite 1150
Seattle, WA 98104
(206) 623 -9372
The Honorable Phil Olbrechts
BEFORE THE HEARING EXAMINER
FOR THE CITY OF RENTON, WASHINGTON
In re: Renton Land Use Matter
LUA18-000055
Puget Sound Energy, Inc.
Energize Eastside Conditional Use Permit
File
PUGET SOUND ENERGY, INC.’S
HEARING MEMORANDUM
Applicant Puget Sound Energy, Inc. (“PSE”) presents this Hearing Memorandum
in support of its application for a Conditional Use Permit (“CUP”) to upgrade and operate
approximately 4 miles of two 115 kV transmission lines in the cit y of Renton (“City” or
“Renton ”) with two 230 kV transmission lines (“Project”) in an existing utility corridor.
The Project is a critical component of an approximately 16-mile electric system upgrade
required to bring PSE’s system into compliance with federally-required planning criteria
by increasing transmission reliability on the Eastside, including Renton.
The Renton PSE upgrade is part of the larger Energize Eastside Project that would
also occur in the cities of Bellevue, Redmond, and Newcastle, and in unincorporated King
County.1 The Project in Renton would replace approximately 144 existing wood and steel
1 The City of Bellevue Hearing Examiner recently approved a conditional use
permit required to build the Richards Creek substation and the south segment of the
Energize Eastside Project. See City of Bellevue Hearing Examiner, Findings of Fact,
Conclusions and Decision on the Conditional Use Permit Application for the South
99640
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
PUGET SOUND ENERGY’S HEARING
MEMORANDUM - 2
719 Second Avenue Suite 1150
Seattle, WA 98104
(206) 623 -9372
poles of H-frame design with approximately 41 steel monopoles of double-circuit design.
The transmission line upgrade would be entirely within the existing 100-foot wide
transmission line corridor rather than being sited in an entirely new, presently non-
existent, corridor. The Project also includes some limited upgrades to the the Talbot Hill
substation located in Renton but these substation upgrades do not, themselves, trigger a
CUP and so are not part of this review.2
Renton was a partner city to the evaluation of the entire Project under the State
Environmental Policy Act (“SEPA”), a nearly 4-year process that included multiple
scoping meetings, public comment periods and public informational meetings. In
conjunction with Renton and the other partner cities of Redmond, Kirkland and
Newcastle, Bellevue as the nominal SEPA lead agency published a Phase 1 and a Phase 2
Draft Environmental Impact Statement (“DEIS”). The Phase 1 DEIS conducted a
programmatic review of multiple Project alternatives. The Phase 2 DEIS conducted a
focused review of overhead transmission line route alternatives and impacts. The Final
EIS (“FEIS”) assessed the impacts of certain routing alternatives proposed for the Project,
including the existing corridor presently occupied by PSE’s 115 kV lines . The existing
corridor was determined to be the least impactful alternative and was selected as the final
route for the upgrade. The FEIS contained a variety of impact mitigation
recommendations to the various cities that could further reduce Project impacts and meet
land use code criteria.
Bellevue Segment of the Energize Eastside Project (June 25, 2019) (attached as Exhibit
A). This decision was upheld unanimously on appeal by the Bellevue City Council. See
City of Bellevue, Ordinance 6494 (Dec. 2, 2019) (attached as Exhibit B).
2 Specifically, additional breakers and associated controls would be added within
the existing substation to accommodate the upgraded high voltage transmission lines
(“HVTLs”)).
99640
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
PUGET SOUND ENERGY’S HEARING
MEMORANDUM - 3
719 Second Avenue Suite 1150
Seattle, WA 98104
(206) 623 -9372
Following publication of the FEIS, Renton also conducted its own EIS consistency
review during evaluation of the CUP application. The City retained EA Engineering,
Science, and Technology, Inc. (“EA”), which engaged subconsultants PBC, Landau
Associates, Grette Associates, Cultural Resource Consultants and ECONorthwest to
confirm that PSE’s CUP application fell within the range of environmental impacts
analyzed in the DEISs and FEIS.3 As indicated in its November 26, 2019 Environmental
Consistency Analysis (“ECA”) report, EA confirmed that the proposal before the City is
within the range of development and probable environmental impacts analyzed in the
SEPA environmental review for the Renton segment of the project, and that there are no
significant unavoidable adverse impacts that cannot be mitigated. Minor additions to and
clarifications of mitigation measures identified in the EIS, CUP and Shoreline Exemption
application materials were recommended by EA based on the ECA.4
The ECA was then reviewed and approved as satisfactory and the imposition of
the ECA’s conditions on the CUP were recommended by the Renton Environmental
Review Committee on December 13, 2019 in accordance with Renton Municipal Code
(“RMC”) 4-9-070(M)(5). In turn, the conditions were all incorporated into the Department
of Community and Economic Development’s Staff Report, which recommends Hearing
Examiner approval of the CUP subject to imposition of the ECA conditions.5 PSE has
agreed to the imposition of all the ECA conditions via the CUP, save a request for a slight
modification of Staff Recommendation J.3, which is described in detail in Section II.B,
infra.
3 Department of Community and Economic Development Staff Report (“Staff
Report”), Exhibit 2 (Environmental Consistency Analysis—Energize Eastside Project
(Nov. 21, 2019)) at p. E-2.
4 Staff Report, Exhibit 2 at Ch. 3.
5 Staff Report at p. 17 (Recommendation J.1).
99640
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
PUGET SOUND ENERGY’S HEARING
MEMORANDUM - 4
719 Second Avenue Suite 1150
Seattle, WA 98104
(206) 623 -9372
The Project is located within multiple zoning designations.6 The Project is defined
as a “Utility, Large” land use under Renton Municipal Code (“RMC”) 4-11-210. This use
is allowed in each zoning district subject to issuance by the Hearing Examiner of a CUP.
See RMC 4-2-060; RMC 4-8-070(H)(1)(d)). The criteria that the Hearing Examiner’s
decision must be based on are set forth in RMC 4-9-030(D)(1) through (8), including
consistency with the goals and policies of the Renton Comprehensive Plan. See RMC 4-9-
030(D)(1). The table contained in Exhibit C hereto sets forth the applicable City
regulations and makes citations to where the materials can be found in the Administrative
Record that demonstrate how this Project complies with these criteria. Because this matter
is not a SEPA EIS adequacy appeal, the EIS should be treated as sufficient and final.
See generally, WAC 197-1 l-680(3)(a) (Challenge to the adequacy of an FEIS must be
raised at the same time as the administrative appeal of the underlying governmental
action).
The City’s Staff Report and PSE’s CUP Application detail how the Project
complies with the specific criteria set forth in the City’s Comprehensive Plan (“CP”) and
RMC. The evidence to be received at the public hearing, both orally and in writing, will
provide further evidence of how the Energize Eastside project meets the criteria for
approval. This Memorandum sets forth limited additional analysis to aid the Hearing
Examiner in his review of the City’s robust environmental review and permitting record.
I. REGULATORY BACKGROUND
A CUP may only be granted when the proposed project is consistent with the
RMC. Pursuant to RMC 4-9-030(F)(8), the Hearing Examiner must issue a CUP upon on
a determination, in writing, that the proposed use satisfies the applicable decision criteria
6 Staff Report at p. 2 (C.2).
99640
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
PUGET SOUND ENERGY’S HEARING
MEMORANDUM - 5
719 Second Avenue Suite 1150
Seattle, WA 98104
(206) 623 -9372
in RMC 4-9-030(D)(1) through (8). Here, no land use change will result from the Project:
transmission poles and wires have been a part of the existing character of the affected
areas for nearly 100 years. The event requiring a CUP is the ‘intensification’ of the
existing use from double-circuited 115 kV HVTLs to imperceptibly thicker 230 kV
HVTLs at a higher elevation and supported with fewer poles than exist today. The City’s
Staff Report and PSE’s CUP Application, as well as the testimony that will be provided at
hearing, demonstrate that the Project satisfies all applicable criteria.
II. ARGUMENT
Approval of the Project requires the Hearing Examiner to conclude that the
requirements of RMC 4-9-030(D)(1)-(8) are satisfied. In consideration of the size of the
permit file, the table attached hereto as Exhibit C provides citations to where, in the
Administrative Record, evidence supporting each criterion for CUP approval can be
found.
A. The Project satisfies all Renton CUP criteria.
i. RMC 4-9-030(D)(1): Consistency with Plans and Regulations
The City’s Comprehensive Plan vision is for a thriving, opportunity-rich
community. A lack of reliable power service would adversely affect Renton’s ability to
attract and retain businesses and residents. See Comprehensive Plan Land Use (“L”)
Elements L-B; L-2; L-J; Economic Development (“ED”) Element ED-14; Community
Planning (“CP”) Element CP-B; and Utility (“U”) Element U-A, U-5. Provision of
reliable electrical infrastructure, including the Energize Eastside project bringing a 230-
kV power source to the Eastside including Renton, fosters PSE’s compliance with
regulatory obligations of the utility and facilitates the City’s vision by providing electrical
resources that will support new residential and commercial facilities contributing to the
health of the community. Id. This investment in infrastructure supports Renton’s planned
99640
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
PUGET SOUND ENERGY’S HEARING
MEMORANDUM - 6
719 Second Avenue Suite 1150
Seattle, WA 98104
(206) 623 -9372
and projected growth while maximizing existing land use compatibility and minimizing
adverse impacts by stakeholder-informed design and use of the existing corridor partially
shared with Olympic Pipeline Company, rather than developing an entire new corridor.
See Renton Comprehensive Plan, U-2, U-72, U-73; U-3, U-4, U-5, U-7, U-O; L-55, L-56,
L-62.
No tree removal is proposed in the area of the Cedar River shoreline nor is
mitigation. See Renton Comprehensive Plan, Shoreline (“SH”) SH-7; U-46. Other tree
removal will occur within the existing managed transmission line corridor where trees are
trimmed or removed on a regular maintenance cycle to ensure compliance with electrical
safety clearances. See Renton Comprehensive Plan, L-B, L-P, L-35, L-55, L-56; U-A, U-
2, U-3, U-5, U-6; U-73. Tree replacement will generally occur at a ratio of greater than
1:1 mitigation to impacts. See Renton Comprehensive Plan, L-B, L-P, L-24, L-62; U-A,
U-72; Staff Report, Exhibit 8. Proposed new poles are sited to avoid direct impacts to
wetlands or streams, and all impacts are avoided within the shoreline jurisdiction,
including all flood hazard areas.7 See Renton Comprehensive Plan, L-B, L-P, L-24, L-35,
L-55, L-56; U-A, U-46, U-72; SH-7.
Design revisions have been made where feasible to minimize impacts where
avoidance is not possible, and Best Management Practices and construction techniques
will be used to minimize impacts to the built (including transportation, public
accessibility, other utility infrastructure) and natural (erosion hazard areas, landslide
hazard areas, steep slopes) environment. See Renton Comprehensive Plan, L-P, L-35, L-
56; U-3, U-5, U-7, U-43. Beyond these measures, PSE has led all northwest utilities in
energy conservation since 1979. See Renton Comprehensive Plan, L-62. Taken as a whole
7See Exhibit D (PSE Shoreline Exemption memo); Exhibit E (email from
Department of Ecology concurring with Shoreline Exemption analysis).
99640
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
PUGET SOUND ENERGY’S HEARING
MEMORANDUM - 7
719 Second Avenue Suite 1150
Seattle, WA 98104
(206) 623 -9372
and in balance with each other, the Renton Comprehensive Plan is robustly addressed by
and reflected in the Energize Eastside project. Further compliance with zoning regulations
and other applicable requirements is addressed below.
ii. RMC 4-9-030(D)(2): Appropriate Location
The Project is proposed to be located in the identical corridor where PSE’s
transmission infrastructure exists today. Selection of this route was significantly informed
by the DEISs and FEIS prepared for the proposal, which demonstrated that it was less
impactful on the built and natural environment than the other route alternatives studied.
Logically, the development of an entirely new corridor would result in greater impacts to
the environment including the clearing of vegetation, acquisition and development of new
access points, new effects on view sheds presently without transmission infrastructure,
and introduction of a new land use where it had not previously existed.
Conversely, the industrial, commercial and residential land uses along the existing
route developed over time after the corridor already existed. Those uses emerged with the
full awareness of the adjacent use of transmission facilities, confirming that the uses are
compatible with each other. In fact, they have co-existed peaceably these many decades.
The FEIS concludes the same, finding that the upgrade to the transmission system where it
presently exists will not cause any new, significant adverse impacts to the environment in
Renton, including land use compatibility.8 The proposed location is suited for the Project
and will not result in the detrimental overconcentration of a particular use within the City
or within the immediate area of the proposed use.
8 See Staff Report at Exhibit 18 (EIS at 4.1-20-21).
99640
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
PUGET SOUND ENERGY’S HEARING
MEMORANDUM - 8
719 Second Avenue Suite 1150
Seattle, WA 98104
(206) 623 -9372
iii. RMC 4-9-030(D)(3): Effect on Adjacent Properties
See discussion above. The proposed use at the proposed location is identical to the
use that exists today. Upgrading the existing system to fewer taller poles will not result in
new substantial or undue adverse effects on the adjacent properties with which it has co-
existed for nearly 100 years. See Exhibit C (Compliance Chart) at p. 2.
iv. RMC 4-9-030(D)(4): Compatibility
See discussion above. The proposed use at the proposed location is identical to the
use that exists today. Upgrading the existing system to fewer taller poles will not result in
new substantial or undue adverse effects on the adjacent properties with which it has co-
existed for nearly 100 years. See Exhibit C (Compliance Chart) at pp. 2-3.
v. RMC 4-9-030(D)(5): Parking
Operation of the transmission system in the existing corridor will not make use of
existing neighborhood parking or demand new parking. Temporary parking during
construction will be established consistent with the parking plan submitted to the City’s
planning project manager, which will be reviewed prior to the issuance of construction
permits. See Staff Report, p. 17 (Recommendation J.4); Exhibit C (Compliance Chart) at
pp. 3.
vi. RMC 4-9-030(D)(6): Traffic
A transportation management plan will be developed and submitted for City
approval prior to the start of construction to ensure safe and continuous pedestrian and
vehicular traffic circulation in areas of construction. See Staff Report at p. 17
(Recommendation J.5). The plan will be presented to the City Plan Review Section for
review, modification as necessary, and approval in advance. This way, disruptions to
pedestrian and vehicular circulation will be minimized to the maximum amount feasible.
See Exhibit C (Compliance Chart) at p. 4.
99640
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
PUGET SOUND ENERGY’S HEARING
MEMORANDUM - 9
719 Second Avenue Suite 1150
Seattle, WA 98104
(206) 623 -9372
vii. RMC 4-9-030 (D)(7): Noise, Light and Glare
Consistent with the Staff Report determinations at pp. 14-15 and the Project EIS,
the Project will not any significant noise, light or glare impacts. The proposed
transmission line replacement will cause temporary construction-related noise impacts,
including the potential use of helicopters for line stringing, but operational noise impacts
are negligible. See Staff Report, Exhibit 18 (FEIS at 1-13); Phase I DEIS at 9-14
(assessing potential operational noise impacts) (attached hereto as Exhibit G).9
Construction noise impacts would terminate once construction is complete and during
construction PSE will comply with all City, County and FAA codes relating to hours of
construction and noise. Given the temporary nature of potential noise impacts and PSE’s
obligation to comply with all related requirements to mitigate noise impacts, there would
be no unavoidable significant adverse noise impacts. See also Staff Report, Exhibit 18
(EIS at 1-13); see also Exhibit G, Phase I DEIS at Table 9-4; Staff Report, Exhibit 17
(Phase II DEIS at 4.1.1 and 4.4.9). Light and glare impacts would be de minimis as the
transmission poles themselves are not lit and the steel poles will be made of a non -
reflective material. See Exhibit C (Compliance Chart) at p. 4.
viii: RMC 4-9-030 (D)(8): Landscaping
The Project limits vegetation impacts by siting the upgraded facilities in an already
disturbed corridor managed for utility use. PSE has developed a vegetation management
plan that requires replanting to fully mitigate for impacts to vegetation and habitat ,
9 PSE attaches Phase I of the Draft EIS as an Exhibit to ensure that the Hearing
Examiner has a full copy of the complete the SEPA record for the Energize Eastside
project. Sections that PSE finds particularly demonstrative of CUP criteria compliance are
cited in Exhibit C (Compliance Chart).
99640
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
PUGET SOUND ENERGY’S HEARING
MEMORANDUM - 10
719 Second Avenue Suite 1150
Seattle, WA 98104
(206) 623 -9372
including a focus on improving habitat for pollinators.10 Under PSE’s Vegetation
Management Plan and CUP conditions, PSE’s vegetation removal mitigation provides a
greater than 1:1 ratio of removed to replanted vegetation (although trees replaced along
the corridor will remain subject to the height limits imposed now to ensure compliance
with federal standards (NERC FAC-003-04)).11 Notably, the Project design was further
refined based on stakeholder input, so there would be no work/disturbance in or to the
jurisdictional shoreline of the Cedar River.
The remaining analysis in Section II, infra, first requests a minor modification of
Staff Recommendation J.3 and then speaks to issues that have arisen during City and
stakeholder review of the Project and which are likely to be raised during the public
hearing.
B. Request for Slight Modification of Staff Recommendation J.3.
PSE has reviewed and agrees to all conditions set forth in the City’s Staff Report
and associated EIS Consistency Analysis, but requests a slight modification to Condition
J.3, concerning limited artwork on transmission line poles, to ensure that the Energize
Eastside project can proceed in a timely manner. The following language shows the Staff
Recommendation J.3 with modifications proposed by PSE in tracked changes:
Individual art wraps for the transmission line poles shall be submitted to
the Current Planning Project Manager for review and approval prior to the
issuance of a Construction Permit. PSE will install art wraps at up to 12
transmission line pole locations (including those previously discussed and
identified by the City at the Renton Technical College and on publicly
visible PSE-owned property). Artwork shall be installed prior to the
10 See Staff Report at 17 (Recommendation J.2); Staff Report, Exhibit 8 at 21
(providing pollinator habitat plan).
11 See Staff Report at 17 (Recommendation J.2); Staff Report, Exhibit 8 at 21
(providing pollinator habitat plan).
99640
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
PUGET SOUND ENERGY’S HEARING
MEMORANDUM - 11
719 Second Avenue Suite 1150
Seattle, WA 98104
(206) 623 -9372
energizing of the transmission line, or as otherwise approved by the
Current Planning Project Manager, but at no point will art installation
delay the transmission lines from being energized.
PSE previewed this language with the City’s planning staff and understands that they have
no objections to the slight modifications, which insure timely implementation of the
condition without giving rise to a possible delays in energizing the lines.
C. Propriety of Pipeline Co-location
For 0.4 miles in Renton (approximately half of which is in unincorporated King
County), the existing 115 kV HVTL system is co-located in the same utility corridor as
Olympic Pipeline Company’s (“OPL”) fuel pipeline. These two utilities have co-existed in
this shared corridor for nearly half a century. Nevertheless, the proposed location of new
230kV HVTL in the same corridor as the OPL pipeline raised questions about public
safety among stakeholders.
While it is not uncommon to co-locate HVTL and pipelines, as Lowell Rogers,
Prinicipal at Oak Strategic will testify, and is encouraged by Renton Comprehensive Plan
(see CP U-3), transmission lines located in proximity with petroleum pipelines can
potentially increase the risk of AC interaction, such as fault events and pipeline corrosion.
With this in mind, PSE used a thorough and iterative engineering process to determine the
co-location proposed for the Project. This process was informed by the two-phased EIS
and additional study regarding the potential effects of alternating current (“AC”)
electricity on nearby underground pipes. Based on the results of the study PSE further
adjusted routing, wire configuration and operational parameters to further limit potential
pipeline interactions.
Transmission lines existed in the corridor first, well before the pipeline.
Moreover, generally the pipeline company is responsible for monitoring the potential for
99640
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
PUGET SOUND ENERGY’S HEARING
MEMORANDUM - 12
719 Second Avenue Suite 1150
Seattle, WA 98104
(206) 623 -9372
interaction between the pipeline and transmission lines post construction, as David
Kemp—an DNV-GL engineer and expert on electrical facility and pipeline
interactions−will testify. Nevertheless, PSE engaged with this work proactively and
incorporated electric system recommendations made by Mr. Kemp and his team to
minimize interactions by proposing operating both transmission lines at 230 kV, using a
delta wire configuration, and installing additional safety features (e.g., a low impedance
shield wire). Additionally, the line will be built to comply with the National Electric
Safety Code—which in many cases exceed 21st century building standards—that account
for extreme weather and seismic events. These design and operational parameters, which
keep interaction between the transmission lines and pipelines below industry thresholds
for risk, effectively minimize and mitigate for Project impacts related to pipeline safety.
This is not PSE’s opinion alone; as part of the EIS development, the Partner Cities
engaged an independent consultant (Stantec), Dr. Wolfgang Filtch, to review the proposed
alignment and review DNV-GL/PSE’s work. See Staff Report, Exhibit 18 at Ch. 4.9;
Exhibit F (Stantec, Technical Review− Energize Eastside AC Interference Analysis (May
2, 2017)). Stantec concurred that DNV-GL’s study complied with industry standards and
recommended conditions, which are reflected in the conditions recommended in the ECA,
that effectively reduced potential risks associated with co-locating a transmission line with
pipeline facilities.12
D. Existing character of neighborhoods includes HVTL infrastructure.
PSE anticipates that the public may comment that the transmission line upgrade is
incompatible with the existing character of neighborhoods. Substantial evidence in the
12 See Staff Report, Exhibit 2 at pp. 3-9−3-15 (setting forth required pipeline safety
conditions).
99640
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
PUGET SOUND ENERGY’S HEARING
MEMORANDUM - 13
719 Second Avenue Suite 1150
Seattle, WA 98104
(206) 623 -9372
record and evidence that will be presented at hearing rebut this position.13 PSE proposes
that the transmission line upgrade occur in the existing utility corridor, which was
established in the late 1920s and early 1930s. Properties adjacent to the existing
transmission lines are generally subject to utility easements, and the adjacent and nearby
land uses were developed largely after the original utilities were installed. As development
occurred and the City grew, the utility corridor containing transmission lines became
integrated into adjacent residential uses. Siting the transmission line in a new utility
corridor would cause new and greater impacts to residents that are not currently adjacent
to transmission lines.14
Notably, the FEIS did not identify any significant adverse visual or aesthetic
impact associated with the upgrade of the existing lines.15 Nonetheless, PSE undertook
additional design work to refine pole placement, reduce the number of poles, propose the
least impactful pole color, decrease pole height and use more streamlined pole designs.
Based on these design features, the potential for aesthetic and land use incompatibility
was further minimized. The proposed transmission lines follow the existing route of
HVTL lines that are today already adjacent to or near all existing land uses in Renton. To
the extent stakeholders contend that the increased conductor heights and fewer poles will
13 See, e.g., Staff Report at pp. 11-12; Staff Report, Exhibit 18 at Ch. 4.1-20−21
(finding no significant land use impacts); 4.2-44—4.2-49 (concluding that “[i]mpacts to
the scenic views and the aesthetic environment in the Renton Segment would be less-than-
significant.).
14 See, e.g., Staff Report, Exhibit 17 at p. 3.4-25 (Table 3.4-1 comparing tree
removal impacts of using the existing transmission line corridor as opposed to siting a
new transmission line corridor).
15 See Staff Report, Exhibit 18 at Ch. 4.2-44—4.2-49.
99640
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
PUGET SOUND ENERGY’S HEARING
MEMORANDUM - 14
719 Second Avenue Suite 1150
Seattle, WA 98104
(206) 623 -9372
lead to adverse changes in property values, the EIS expressly found otherwise.16
Moreover, any non-significant impacts must also be considered in balance with Renton
Comprehensive Plan criteria that prioritize ensuring reliable power and planning for
economic and population growth, and siting new utilities in the existing transmission line
corridor.17
E. Project Not Impermissibly Bifurcated.
PSE anticipates testimony and/or argument at the hearing to the effect that the
CUP before the Renton Hearing Examiner is the result of impermissible permit
bifurcation of a single project. It may be suggested that failure to submit a single
application for the entire project prevents the Hearing Examiner from understanding the
project’s compliance with the RMC, thereby preventing him from ruling on the CUP. This
argument fails as a matter of law and fact.
Linear projects such as rail lines, transmission lines, or pipelines frequently cross
through multiple cities and counties. Every jurisdiction through which the facility travels
has its own– and very different− comprehensive plans, land use codes and development
regulations to be applied. Procurement of the development and construction permits for
such linear facilities is often broken into various stages, even within a single jurisdiction.
This is a practicality of infrastructure development, and is a lawful industry practice.
Here, the part of the Energize Eastside facility proposed for a CUP in Renton is
subject only to the RMC. PSE legally cannot submit the entire project to a single
municipal permit process, because other cities with jurisdiction over the project must
apply their own codes and have no authority to apply Renton’s. Furthermore, it is not
16 See Staff Report, Exhibit 17 at Ch. 3.10; Exhibit G (Phase I DEIS) at 10-21—
10-22 (summarizing review of studies analyzing the potential for economic impacts to
property value).
17 See CP U-O, U-1, U-68; CP at Appendix C.
99640
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
PUGET SOUND ENERGY’S HEARING
MEMORANDUM - 15
719 Second Avenue Suite 1150
Seattle, WA 98104
(206) 623 -9372
lawful to conduct a consolidated single hearing in a single jurisdiction where all cities’
hearing examiners attend and receive testimony simultaneously for later consideration.
See RCW 36.10B.110(7).
Segmentation of environmental review, however, is a concept that exists under
Washington law, but it is specific to SEPA. Evaluating the entirety of a single project for
environmental impacts is required under WAC 197-11-060(3)(b) unless phasing is
contemplated under WAC 197-11-106(5). A CUP, however, is not subject to the same
limitations because it serves a different purpose (providing for a more focused review of a
proposal’s compliance with local decisional criteria in order to allow a permitted use to
proceed with conditions that ensure compatibility). To the extent the Hearing Examiner is
presented with a SEPA-like argument for the proposition of impermissible permit
bifurcation for Energize Eastside, this principle has not been extended to land use
permitting in Washington.
It is note-worthy that the EIS studied the entire project, from Renton to Redmond,
in a single process– there was neither impermissible segmentation nor phasing of the
SEPA review. Regardless, to the extent it is contended the EIS was improperly scoped or
bifurcated, that issue is not before the Hearing Examiner. This proceeding is strictly a
permit review hearing, not a SEPA appeal hearing. The adequacy of the EIS is a verity for
purposes of evaluating PSE’s application to Renton for a CUP.
F. Only the Energize Eastside HVTL proposal is before the Hearing
Examiner.
PSE anticipates that some members of the public may offer new “alternatives” at
hearing as a basis for denial. PSE is seeking approval of a CUP for the upgrade of existing
high voltage transmission wires in the same utility corridor. That stakeholders wish that a
different project had been proposed using different routes or technologies is of no avail.
99640
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
PUGET SOUND ENERGY’S HEARING
MEMORANDUM - 16
719 Second Avenue Suite 1150
Seattle, WA 98104
(206) 623 -9372
The RMC does not give the Hearing Examiner authority to reject the proposal simply
because he or others may prefer a different hypothetical solution. The City and Hearing
Examiner only have the authority to approve, disapprove or approve with conditions the
proposal presented to it. RMC 4-9-030.F.8.
G. Project underwent robust public review.
It is anticipated that stakeholders will argue that insufficient engagement about this
proposal has occurred to inform the public and decision-maker about whether it merits a
CUP. There is no substance to this position. Renton spent almost two years reviewing the
proposal, and provided for public comment in accordance with the RMC. Although the
comment period lasted between March 14th and March 28th, 2018, the City continued to
receive and accept public comment up to the time of hearing. Indeed, the public was given
extra time to prepare for this hearing by reaching out to the Mayor, ex parte and without
notice to City legal or planning staff or the Applicant, t o obtain an extension of the
hearing date from the City’s initially proposed December 17, 2019 hearing.
In addition to the public engagement solicited directly by Renton, PSE has worked
for years across the Eastside to identify and expand its understanding of community
concerns as well as municipal land planning requirements that relate to this project. To do
so, the company began a number of initiatives early in the planning stage that ran on dual
tracks. PSE conducted an in-depth, multi-year community outreach effort to share
information and review and gather feedback on potential route options. It also
collaborated with local cities, residents, businesses and a 24 -member Community
Advisory Group to examine various routes. In all, PSE held 22 public meetings and nearly
550 project briefings with stakeholders, neighborhoods and cities. It mailed multiple
postcards and newsletters, and received nearly 3,000 comments and questions about the
99640
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
PUGET SOUND ENERGY’S HEARING
MEMORANDUM - 17
719 Second Avenue Suite 1150
Seattle, WA 98104
(206) 623 -9372
project. PSE has a public, project-specific website that contains the library of documents,
studies, briefings and other materials related to the proposal.
In September 2016, PSE began offering to meet with property owners along the
existing corridor to talk about site-specific designs for Energize Eastside. PSE shared its
current design for each owner’s specific property, including pole locations and how access
to those locations was proposed during construction.
Beyond this, a nearly four-year environmental review process was conducted
jointly by Renton, Newcastle, Bellevue, Redmond and Kirkland. At various stages, public
input was obtained via public meetings and open houses, in addition to the two expanded
public comment periods provided to review and comment on the Phase I and II DEISs.
In sum, the amount of review this Project has received far exceeds that of any
other transmission project ever undertaken by PSE. See, e.g., Exhibit A at ¶ 48. There has
been no deficiency in the number of opportunities that the public has had to engage in this
Project.
H. Project Need and Solution
Demonstration that the Project is needed to address a transmission reliability
deficiency on the Eastside, including Renton, is not a decisional criteria in Renton.
Nevertheless, and without waiving any objection to arguments that such criteria can be
inferred from or impliedly exists in the RMC, the record before the Hearing Examiner is
rife with studies, analyses and agency assessments confirming the methodology used and
conclusions drawn by PSE that this Project is needed at this time and in this location.18
18 See, e.g., Staff Report, Exhibit 18 at 1-4—1-6 (summarizing available studies);
Exhibit A at ¶¶ 52-57e, 77; Exhibit G at pp. 1-4—1-13 (incorporating by reference
Stantec, Energize Eastside Project Memorandum from Keith DeClerck to Mark Johnson
(July 31, 2015), available at http://www.energizeeastsideeis.org/library.html).
99640
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
PUGET SOUND ENERGY’S HEARING
MEMORANDUM - 18
719 Second Avenue Suite 1150
Seattle, WA 98104
(206) 623 -9372
Similarly, PSE anticipates that the public will offer up examples of what it
believes to be better solutions to the transmission deficiency on the Eastside, including in
Renton. PSE appreciates the public’s interest in electric utility operations. However,
nothing in the RMC gives its Hearing Examiner the authority to reject this application on
the grounds that the public may prefer some other technology to resolve the issue. See
RMC 4-9-030.F.8. As the utility provider mandated to make electricity available to all
customers in its service area, PSE is solely responsible for crafting a transmission
deficiency solution that takes into account the myriad potential interactions and impacts
that its choice could have on local and Eastside electric utility operations. In any event,
multiple solutions were evaluated in the Phase I DEIS, a process that included robust
public participation and examination. See Exhibit G.
III. CONCLUSION
Energize Eastside has been recommended to the Hearing Examiner for approval
subject to the conditions contained in the EIS Consistency Analysis. The project is
compatible with adjacent land uses, causes no significant adverse impacts to the built and
natural environment, and is consistent with all applicable plans, codes and policies of the
City of Renton. Having agreed to all conditions in the Staff Report, save the slight
modification to condition J.3 described above, PSE respectfully submits that the Hearing
Examiner can and will enter findings and conclusions supporting the decision that a CUP
for Energize Eastside should be issued.
DATED this 8th day of January, 2020.
99640
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
PUGET SOUND ENERGY’S HEARING
MEMORANDUM - 19
719 Second Avenue Suite 1150
Seattle, WA 98104
(206) 623 -9372
VAN NESS FELDMAN LLP
/s/ Erin Anderson
Erin Anderson, WSBA #23282
Sara A. Leverette, WSBA #44183
719 Second Avenue, Suite 1150
Seattle, WA 98104
Tel: (206) 623-9372
Fax: (206) 623-4986
E-mail: ela@vnf.com; sal@vnf.com
Attorneys for Puget Sound Energy, Inc.
99640
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
719 Second Avenue Suite 1150
Seattle, WA 98104
(206 ) 623 -9372
CERTIFICATE OF SERVICE
I, I’sha Willis, declare as follows:
That I am over the age of 18 years, not a party to this action, and competent to be a
witness herein;
That I, as a Legal Assistant in the office of Van Ness Feldman, caused true and
correct copies of the following documents to be emailed to the Hearing Exami ner and
counsel of record as set forth below:
1. Puget Sound Energy, Inc.’s Hearing Memorandum;
2. Certificate of Service;
and that on January 8, 2020, I addressed said documents and deposited them for delivery
as follows:
City of Renton Hearing Examiner
City of Renton
Leslie Clark
Jill Ding
I certify under penalty of perjury under the laws of the State of Washington that
the foregoing is true and correct.
EXECUTED at Seattle, Washington on this 8th day of January, 2020.
/s/ I’sha Willis
I’sha Willis, Declarant
EXHIBIT A
DECISION APPROVING CONDITIONAL USE
PERMIT FOR THE SOUTH BELLEVUE SEGMENT
OF THE ENERGIZE EASTSIDE PROJECT, PUGET
SOUND ENERGY, APPLICANT –
FILE NO. 17-120556-LB
Page 1 of 38
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
BELLEVUE HEARING EXAMINER’S OFFICE
450 – 110TH AVENUE NE
P.O. BOX 90012
BELLEVUE, WASHINGTON 98009-9012
Before Hearing Examiner
Gary N. McLean
BEFORE THE HEARING EXAMINER
FOR THE CITY OF BELLEVUE
In the Matter of the:
Conditional Use Permit Application
for the South Bellevue Segment of the
Energize Eastside Project
PUGET SOUND ENERGY, Applicant
________________________________
)
)
)
)
)
)
)
)
)
)
DSD File No. 17-120556-LB
FINDINGS OF FACT,
CONCLUSIONS, AND
DECISION
I. SUMMARY of DECISION.
The applicant has met its burden of proof to demonstrate that a preponderance of the
evidence supports the conclusion that its application for a Conditional Use Permit (CUP)
merits approval. Accordingly, the pending Conditional Use Permit application is approved,
subject to conditions.
II. BACKGROUND and RELEVANT CODE PROVISIONS.
There is no dispute that a conditional use permit is mandated for this project because
the application is for new or expanding electrical utility facilities proposed on sensitive sites
described and depicted on Figure UT.5a (revised to Map UT-7) of the Utilities Element of
the City of Bellevue Comprehensive Plan. (LUC 20.20.255.C; Staff Report, pages 7-8, and
Attachment F, a copy of Comp. Plan Map UT-7).
In this matter, the Hearing Examiner has jurisdiction to conduct an open record public
hearing regarding the Conditional Use Permit application at issue. Under applicable City
codes, a CUP is a Process I land use decision processed in accord with LUC 20.35.100-140.
DECISION APPROVING CONDITIONAL USE
PERMIT FOR THE SOUTH BELLEVUE SEGMENT
OF THE ENERGIZE EASTSIDE PROJECT, PUGET
SOUND ENERGY, APPLICANT –
FILE NO. 17-120556-LB
Page 2 of 38
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
BELLEVUE HEARING EXAMINER’S OFFICE
450 – 110TH AVENUE NE
P.O. BOX 90012
BELLEVUE, WASHINGTON 98009-9012
As explained in LUC 20.35.140.A, the Hearing Examiner shall approve a project or
approve with modifications if the applicant has demonstrated that the proposal complies with
the applicable decision criteria of the Bellevue City Code, and the applicant carries the
burden of proof and must demonstrate that a preponderance of the evidence supports the
conclusion that the application merits approval or approval with modifications. In all other
cases, the Hearing Examiner shall deny the application. The preponderance of the evidence
standard is equivalent to “more likely than not.”1
Conditional Use Permit Decision Criteria: The decision criteria for a Conditional Use
Permit is found in LUC 20.30B.140, which explains that the City may approve or approve
with modifications an application for a conditional use permit if:
A. The conditional use is consistent with the Comprehensive Plan; and
B. The design is compatible with and responds to the existing or intended character,
appearance, quality of development and physical characteristics of the subject
property and immediate vicinity; and
C. The conditional use will be served by adequate public facilities including streets,
fire protection, and utilities; and
D. The conditional use will not be materially detrimental to uses or property in the
immediate vicinity of the subject property; and
E. The conditional use complies with the applicable requirements of this Code.
Additional Criteria for Electrical Utility Facilities: Because the proposal is to construct or
expand electrical facilities, the provisions of the City’s Land Use Code specifically
addressing Electrical Utility Facilities, found in LUC 20.20.255.E, must be satisfied. Prior
to submittal of any Conditional Use Permit application, a detailed Alternative Siting Analysis
was required. See LUC 20.20.255.D. In addition to the requirements set forth above for a
Conditional Use Permit, as detailed in Part 20.30B LUC, all proposals to locate or expand
electrical utility facilities shall comply with the following:
1. The proposal is consistent with Puget Sound Energy’s System Plan;
2. The design, use, and operation of the electrical utility facility complies with
1 In re Pers. Restraint of Woods, 154 Wn.2d 400, 414 (2005).
DECISION APPROVING CONDITIONAL USE
PERMIT FOR THE SOUTH BELLEVUE SEGMENT
OF THE ENERGIZE EASTSIDE PROJECT, PUGET
SOUND ENERGY, APPLICANT –
FILE NO. 17-120556-LB
Page 3 of 38
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
BELLEVUE HEARING EXAMINER’S OFFICE
450 – 110TH AVENUE NE
P.O. BOX 90012
BELLEVUE, WASHINGTON 98009-9012
applicable guidelines, rules, regulations or statutes adopted by state law, or any
agency or jurisdiction with authority;
3. The applicant shall demonstrate that an operational need exists that requires the
location or expansion at the proposed site;
4. The applicant shall demonstrate that the proposed electrical utility facility
improves reliability to the customers served and reliability of the system as a whole,
as certified by the applicant’s licensed engineer;
5. For proposals located on sensitive sites as referenced in Figure UT.5a of the
Utility Element of the Comprehensive Plan, the applicant shall demonstrate:
a. Compliance with the alternative siting analysis requirements of
subsection D of this section;
b. Where feasible, the preferred site alternative identified in subsection
D.2.d of this section is located within the land use district requiring
additional service and residential land use districts are avoided when the
proposed new or expanded electrical utility facility serves a nonresidential
land use district;
6. The proposal shall provide mitigation sufficient to eliminate or minimize long-
term impacts to properties located near an electrical utility facility. See LUC
20.20.255.E.
III. ASSOCIATED PERMIT.
Given the scale of the project, a Critical Areas Land Use Permit (CALUP), which is
a Process II Administrative Land Use Decision, was also required. The Director approved
the CALUP as explained in the same Staff Report issued for the pending Conditional Use
Permit. The CALUP was not appealed, so it was not on review as part of the Hearing
Examiner’s public hearing process. Specifically, the City thoroughly reviewed application
materials for, duly noticed, sought and considered public feedback for, and issued a Critical
Areas Land Use Permit for aspects of the South Bellevue Segment of the applicant’s Energize
Eastside Project, under File No. 17-120557-LO. Under the City’s code, the CALUP approval
is subject to appeal before the Hearing Examiner. Again, no appeal was filed, so the Critical
Areas permit stands without modification, as issued, and serves as support for the Conditional
DECISION APPROVING CONDITIONAL USE
PERMIT FOR THE SOUTH BELLEVUE SEGMENT
OF THE ENERGIZE EASTSIDE PROJECT, PUGET
SOUND ENERGY, APPLICANT –
FILE NO. 17-120556-LB
Page 4 of 38
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
BELLEVUE HEARING EXAMINER’S OFFICE
450 – 110TH AVENUE NE
P.O. BOX 90012
BELLEVUE, WASHINGTON 98009-9012
Use permit addressed in this Decision.2 All findings, conclusions and conditions of approval
in the CALUP are now beyond review. Any appeal of this Decision cannot be used to
collaterally attack any aspect of the CALUP or determinations made therein. See Wenatchee
Sportsmen Ass’n v. Chelan County, 141 Wn.2d 169, 182, 4 P.3d 123 (2000), and Habitat
Watch v. Skagit County, 155 Wn.2d 397, 410–11, 120 P.3d 56 (2005).
IV. RECORD AND EXHIBITS.
Exhibits entered into evidence as part of the record, and an audio recording of the
public hearing, are maintained by the City of Bellevue, and may be examined or reviewed by
contacting the Clerk in the Hearing Examiner’s Office.
Throughout the hearing process, some participants were represented by counsel. Matt
McFarland and Cheryl Zakrzewski from the Bellevue City Attorney’s Office represented city
staff who generated the Staff Report and oversaw preparation of environmental review
documents included in the record; Erin Anderson and Sara Leverette, from the Van Ness
Feldman law firm, represented the applicant, Puget Sound Energy; Richard Aramburu
represented CENSE (Coalition of Eastside Neighborhoods for Sensible Energy); and Larry
Johnson represented CSEE (Citizens for Sane Eastside Energy).
Exhibits: The Record includes all pre-hearing orders, motions, and briefs filed or
issued prior to the public hearing, copies of which are maintained by the Clerk for the Hearing
Examiner’s Office, and all exhibits described and numbered on the attached Exhibit List. In
sum, the record for this matter is somewhere near 15,000 pages.
Hearing Testimony: The following individuals presented testimony under oath at the
duly noticed public hearing for the underlying application, which spanned several days,
beginning on the evening of March 28th, continuing through March 29th, April 3rd, and April
8, 2019.
The following individuals provided testimony at some point on March 28th:
For the City of Bellevue:
Heidi Bedwell, Environmental Planning Manager, and Liz Stead, Land Use Director
2 As a Process II Decision, the CALUP had a 14-day appeal deadline, which expired on February 7, 2019. See
LUC 20.35.250.A.3. Any appeals would have been included in the Hearing Examiner’s public hearing process
for the project. There were none. See Staff Report for details on relevant dates, including date of issuance and
appeal deadline listed on page 2.
DECISION APPROVING CONDITIONAL USE
PERMIT FOR THE SOUTH BELLEVUE SEGMENT
OF THE ENERGIZE EASTSIDE PROJECT, PUGET
SOUND ENERGY, APPLICANT –
FILE NO. 17-120556-LB
Page 5 of 38
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
BELLEVUE HEARING EXAMINER’S OFFICE
450 – 110TH AVENUE NE
P.O. BOX 90012
BELLEVUE, WASHINGTON 98009-9012
For the Applicant, PSE:
Dan Koch, PE, Director of Electric Operations; Elizabeth Koch, PE, Director of Planning for
PSE; and Jens Nedrud, PE, Manager of Electrical System Planning for PSE.
General Public: Ms. Cofield; Mr. Anderson; Ms. Hirshci; Mr. Bannon; Mr. Alavi; Mr. Dachnahl; Mr.
Wallace; Mr. Oleson; Mr. Anderson; Ms. Hansen; Ms. Akiyama; Ms. Smith; Mr. Borgmann; Mr. Funk;
Mr. Sutton, Mr. Wagner, Mr. Shay, Mr. Townsend, Mr. Gilchrist, Mr. Yu, Mr. Finkbeiner, Ms.
Trescases, Mr. Davis, Mr. Kasner, Dr. Kaner, Ms. Kapela, Ms. Swenson, Ms. Ma, Mr. Fleck, Ms.
Talneja.
For CENSE:
Robert McCullough and Dean Apostol.
The following individuals provided testimony at some point on March 29th:
For the applicant, PSE:
Lowell Rogers, re: pipeline safety issues; and David Kemp, re: effects of transmission lines
on adjacent pipelines.
General Public:
Mr. Halverson, Ms. Jacobson, Mr. Woosley, Ms. Sander, Mr. Joe, Mr. O’Donnell, Ms. Kim,
Ms. Dean, Mr. Jaeger, Ms. Keller, Ms. Fischer, Mr. Allred, Mr. Davis, Mr. Zimmerman, Mr.
Johnson, Mr. Derdowski, Mr. Rumega, Ms. DeMund, Mr. Elworth, Ms. Elworth, Ms. Stronk,
Ms. Ossenkop, Mr. Albert, Mr. Cliff, and Ms. Lopez.
For the applicant, PSE:
Tom Priestley, re: visual impacts.
For CENSE:
Mr. Marsh and Karen Esayian, with legal arguments presented by Mr. Aramburu.
For CSEE:
Mr. Lauckhart, with legal arguments presented by Mr. Johnson.
For the City of Bellevue:
Wolfgang Fieltsch, re: pipeline safety issues.
DECISION APPROVING CONDITIONAL USE
PERMIT FOR THE SOUTH BELLEVUE SEGMENT
OF THE ENERGIZE EASTSIDE PROJECT, PUGET
SOUND ENERGY, APPLICANT –
FILE NO. 17-120556-LB
Page 6 of 38
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
BELLEVUE HEARING EXAMINER’S OFFICE
450 – 110TH AVENUE NE
P.O. BOX 90012
BELLEVUE, WASHINGTON 98009-9012
Testimony on April 3rd provided the applicant and staff the opportunity to offer rebuttal testimony to any
comments or evidence submitted during the course of the hearing.
Rebuttal testimony from the applicant, PSE:
Mr. Nedrud, Ms. Koch, Mr. Rogers, Mr. Thatcher, Mr. Strauch, and Mr. Koch.
Rebuttal testimony from City staff:
Mr. Johnson, who managed the EIS process from start to finish, Ms. Stead, and Ms. Bedwell,
all of whom confirmed that they heard nothing through the course of the hearing that would
change their opinions reflected in the EIS and/or Staff Report; and legal arguments from Mr.
McFarland.
April 8th was the date used for closing Arguments presented by counsel for the applicant, city staff, CENSE
and CSEE.
Given the size of the record and the volume of opposition comments received
throughout the process, the Examiner sought to read every exhibit with attention and a fair
mind. This involved site visits, to better appreciate comments from local residents, research,
and reviewing a lengthy record of public outreach and feedback, administrative reviews, and
a multi-phase set of environmental documentation that culminated in a Final EIS, which
included detailed review on specifics presented in this pending CUP application. This was
not a “small and simple” matter. Instead, it required considerable time and focus. All
participants were advised at the close of the hearing that generating a Decision for this
application would take significant time and attention. Having completed such review and
mindful of the legal standards involved, this Decision is now in order.
V. FINDINGS of FACT.
Based on the entire Record, estimated to be around 15,000 pages, the undersigned
Examiner issues the following Findings of Fact. Any statements contained in previous or
following sections of this Decision that are deemed to be Findings of Fact are hereby adopted
as such and incorporated by reference.
1. In September of 2017, Puget Sound Energy, Inc. (PSE) applied to the City of Bellevue
for a Conditional Use Permit and a Critical Areas Land Use Permit for the construction of a
new substation and 230 kilovolt (kV) transmission lines that will be located within the
Bellevue City Limits. (DSD 000002, 000006, and 000007).
2. The project elements that are at issue in this application are known as the “South
Bellevue Segment” of PSE’s Energize Eastside Project.
DECISION APPROVING CONDITIONAL USE
PERMIT FOR THE SOUTH BELLEVUE SEGMENT
OF THE ENERGIZE EASTSIDE PROJECT, PUGET
SOUND ENERGY, APPLICANT –
FILE NO. 17-120556-LB
Page 7 of 38
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
BELLEVUE HEARING EXAMINER’S OFFICE
450 – 110TH AVENUE NE
P.O. BOX 90012
BELLEVUE, WASHINGTON 98009-9012
3. The larger “Energize Eastside Project” is the PSE proposal to construct a new
substation in Bellevue (the “Richards Creek substation”) and to upgrade 16 miles of two
existing 115 kV transmission lines with 230 kV lines running from Redmond to Renton.
4. The Staff Report explains that PSE is applying for permits to construct the Energize
Eastside Project in two phases. PSE has applied for permits for the first construction phase
of the total Project in Bellevue, unincorporated King County, the City of Newcastle, and the
City of Renton. (DSD 000006).
5. The first phase of the Energize Eastside Project in Bellevue (the “South Bellevue
Segment”) is fully addressed and analyzed in the 151-page Staff Report, which includes a
detailed summary of public comments received (DSD 000086-000102), and ten attachments
described as follows:
A. Project Plans
B. Alternative Siting Analysis
C. PSE South Bellevue Segment CUP Analysis
D. Independent Technical Analysis of Energize Eastside (USE2015)
E. Vegetation Management Plan
F. Comprehensive Plan, Map UT-7
G. Comprehensive Plan Policy Analysis
H. Photo Simulations
I. Critical Areas Report
J. Pole Finishes Report-City of Bellevue (South)
With all attachment materials included, the “Final Combined Staff Report”, as it labeled in
the electronic project files, exceeds 1,500 pages. (DSD 000001-001510).
6. The South Bellevue Segment includes construction of a new “Richards Creek”
substation and upgrading 3.3 miles (the Bellevue portion) of existing 115 kV transmission
lines with 230 kV lines between the existing Lakeside substation and the southern city limits
of Bellevue. The remainder of the south portion of the Project continues through Newcastle,
unincorporated King County, and Renton. Bellevue only has permitting authority for work
proposed in its jurisdiction. The Project and PSE’s specific proposal for the South Bellevue
Segment involves the replacement of existing wooden H-frame poles with steel monopoles.
Within the existing utility corridor, the proposed pole locations for the rebuilt lines will
generally be in the same locations as the existing poles. (DSD 000006).
7. There is no credible dispute that the 3.3 miles of transmission line upgrades that will
be part of this South Bellevue Segment are to be constructed within an existing corridor that
was established in the late 1920s and early 1930s, and that current uses, including homes and
DECISION APPROVING CONDITIONAL USE
PERMIT FOR THE SOUTH BELLEVUE SEGMENT
OF THE ENERGIZE EASTSIDE PROJECT, PUGET
SOUND ENERGY, APPLICANT –
FILE NO. 17-120556-LB
Page 8 of 38
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
BELLEVUE HEARING EXAMINER’S OFFICE
450 – 110TH AVENUE NE
P.O. BOX 90012
BELLEVUE, WASHINGTON 98009-9012
various commercial uses, were developed over time after the original utilities (including PSE
powerlines) were installed. In the 1960s, the PSE lines were upgraded from 55 kV to 115
kV, which included replacement of original poles with H-frame poles. (DSD 000232, part
of Attachment B to Staff Report, Alternative Siting Analysis). Maintenance has occurred over
time, and in 2007, PSE replaced or reframed approximately 200 H-frame structures on the
existing corridor. (Final EIS, at Sec. 2.2.1.2.2 re: Overview of the New 230 kV Transmission
Lines, included in the Record at DSD 005445-5446). As part of the proposed Energize
Eastside Project, the existing, H-frame structures would be replaced primarily with a
combination of single-circuit and double-circuit steel monopoles, with some wood poles
remaining, particularly near substations. Id. The applicant notes that it identified the need
to upgrade the lines within the same corridor to the next higher transmission voltage (230
kV) in the early 1990s, and that the 230 kV upgrade concept has been included in the Bellevue
Comprehensive Plan since such time period. (DSD 000233; Testimony of PSE witnesses).
8. The Richards Creek substation, which is needed to step down voltage from 230 kV to
115 kV, will be constructed directly south of PSE’s existing Lakeside switching station. The
new substation will be located on parcel 102405-9130 (13625 SE 30th Street), currently used
as a PSE pole storage yard. The parcel is 8.46 acres in size and contains critical areas (steep
slopes, wetlands, and streams). Access to the substation site is from SE 30th Street. (DSD
000006).
9. Despite some comments, arguments, and requests to the contrary, the City of Bellevue
only has jurisdiction over segments of the Energize Eastside Project that lie within the
Bellevue City Limits. And, the Hearing Examiner only has jurisdiction to review this pending
application, not possible, future applications for other segments in the City that have not been
filed. Accordingly, the Examiner’s review has been limited to the 3.3 miles of transmission
line upgrades and the new Richards Creek Substation that are proposed within the City of
Bellevue, collectively known as the South Bellevue Segment.
Purpose and Need for project.
10. The Staff Report credibly explains that the purpose of the Energize Eastside Project
is to meet local demand growth and to protect reliability in the Eastside of King County,
roughly defined as extending from Redmond in the north to Renton in the south, and between
Lake Washington and Lake Sammamish. There is no dispute that it is PSE’s responsibility
to plan and operate the electrical system while complying with federal standards and
guidelines. (DSD 000008-11; Testimony of Ms. Koch, PSE’s Director of Planning, and Ex.
A-7, copy of Ms. Koch’s written remarks provided at the public hearing). Ms. Koch
thoroughly explained current federal, regional, and state mandates and regular system audit
requirements that electric utilities must meet.
DECISION APPROVING CONDITIONAL USE
PERMIT FOR THE SOUTH BELLEVUE SEGMENT
OF THE ENERGIZE EASTSIDE PROJECT, PUGET
SOUND ENERGY, APPLICANT –
FILE NO. 17-120556-LB
Page 9 of 38
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
BELLEVUE HEARING EXAMINER’S OFFICE
450 – 110TH AVENUE NE
P.O. BOX 90012
BELLEVUE, WASHINGTON 98009-9012
11. PSE defines its broad objectives for the Energize Eastside Project as follows:
• Address PSE’s identified deficiency in transmission capacity.
• Find a solution that can be feasibly implemented before system reliability is impaired.
• Be of reasonable Project cost.
• Meet federal, state, and local regulatory requirements.
• Address PSE’s electrical and non-electrical criteria for the Project. (DSD 000008).
12. Electricity is currently delivered to the Eastside area through two 230 kV/115 kV bulk
electric substations – the Sammamish substation in Redmond and the Talbot Hill substation
in Renton – and distributed to neighborhood distribution substations using 115 kV
transmission lines (see Staff Report, Figure II-1). Although numerous upgrades have been
made to PSE’s 115 kV systems (including new transmission lines), the primary 115 kV
transmission lines connecting the Sammamish and Talbot Hill substations have not been
upgraded since the 1960s, and no 230 kV-to-115 kV transformer upgrades have been made
at these substations. (DSD 000008-11).
13. Since then, the Eastside population has grown from approximately 50,000 to nearly
400,000. Both population and employment growth are expected to continue, but at a slower
pace of around 2% per year, according to Puget Sound Regional Council (PSRC) estimates.
A report prepared for PSE projects that electrical customer demand on the Eastside will grow
at a rate of approximately 2.4% per year through 2024. (Id.).
14. As required by federal regulations, PSE performs annual electric transmission
planning studies to determine if there are potential system performance violations
(transformer and line overloads) under various operational and forecasted electrical use
scenarios. These studies are generally referred to as “reliability assessments.” (Id., and
Testimony of PSE witnesses).
15. The need for additional 230 kV-to-115 kV transmission transformer capacity and 230
kV support in the Eastside was identified in the 1993 annual reliability assessment, and has
been included in PSE’s Electrical Facilities Plan for King County (System Plan) since that
time. In 2009, PSE’s annual reliability assessment found that if one of the Talbot Hill
substation transformers failed, it would significantly impair reliability on the Eastside. (DSD
000010).
16. Replacement of a failed 230 kV transformer can take weeks, or even months, to
complete depending on the level of failure and other site-specific parameters. Since 2009,
other reliability deficits have been identified. These include concerns over the projected
future loading on the Talbot Hill substation and increased use of Corrective Action Plans
DECISION APPROVING CONDITIONAL USE
PERMIT FOR THE SOUTH BELLEVUE SEGMENT
OF THE ENERGIZE EASTSIDE PROJECT, PUGET
SOUND ENERGY, APPLICANT –
FILE NO. 17-120556-LB
Page 10 of 38
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
BELLEVUE HEARING EXAMINER’S OFFICE
450 – 110TH AVENUE NE
P.O. BOX 90012
BELLEVUE, WASHINGTON 98009-9012
(CAPs) to manage outage risks to customers in this portion of the PSE system. (DSD
000010).
17. Between 2012 and 2015, PSE and the City of Bellevue commissioned three separate
studies by two different parties that confirmed the need to address Eastside transmission
capacity (DSD 000010):
• City of Bellevue Electrical Reliability Study prepared by Exponent, 2012.
• The Quanta Eastside Needs Assessment Report, 2013.
• The Quanta Supplemental Eastside Needs Assessment Report, 2015.
18. The Quanta Eastside Needs Assessment Report and Supplemental Eastside Needs
Assessment Report, performed by Gentile (with Quanta Technology) for PSE in 2013 and
2015, respectively, confirmed that if growth in demand continued as projected, then the
Eastside’s existing grid would not meet federal reliability requirements by the winter of
2017/2018 and the summer of 2018 without the addition of 230 kV-to-115 kV transformer
capacity in the Eastside area. (DSD 000010-11).
19. More significantly, and enhancing the credibility of reports submitted by the
applicant, the City of Bellevue commissioned a separate study to evaluate PSE’s system,
which also confirmed the need for the Energize Eastside Project. And, as part of the EIS
prepared for the Energize Eastside Project, Stantec Consulting Services Inc. also reviewed
PSE’s analysis and determined that PSE’s approach to the needs assessment determination
followed standard industry practice. (DSD 000011; Staff Report, Attachment D, “USE”
[Utility System Efficiencies, Inc.] Report, ‘Independent Technical Analysis of Energize
Eastside for the City of Bellevue, WA’, dated April 2015; and Stantec Review Memo on the
Eastside Needs Assessment Report, July 2015, included in the Record at DSD 000550-559,
and referenced throughout the hearing).
20. In June 2018, PSE notified the City of Bellevue that the actual peak demand in the
summer of 2017 was equal to the peak demand projected for summer 2018, and warned that
during peak summer demand periods CAPs would be in place that include intentional load
shedding (rolling blackouts) for Eastside customers. (DSD 000011; Testimony of Mr. Koch,
PSE Director of Electric Operations).
21. The application materials and materials referenced in the Staff Report provide a more-
detailed explanation regarding the use of load shedding. (Quanta, Supplemental Needs
Assessment Report, at DSD 000453). PSE recognizes that applicable federal and regional
agencies allow dropping “non-consequential” load for certain contingencies, but does not
endorse the practice of intentionally dropping load for serious contingencies in order to meet
federal planning requirements. (Id.). All electrical loads modeled in the Needs Assessment
work performed for PSE was considered “firm load” and PSE does not consider any of its
DECISION APPROVING CONDITIONAL USE
PERMIT FOR THE SOUTH BELLEVUE SEGMENT
OF THE ENERGIZE EASTSIDE PROJECT, PUGET
SOUND ENERGY, APPLICANT –
FILE NO. 17-120556-LB
Page 11 of 38
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
BELLEVUE HEARING EXAMINER’S OFFICE
450 – 110TH AVENUE NE
P.O. BOX 90012
BELLEVUE, WASHINGTON 98009-9012
firm requirements to be non-consequential. This is the practice of most utilities. It is also
consistent with the views of virtually all community officials who do not consider
intentionally blacking out segments of customers as a responsible way to operate a modern
electricity delivery system. (Id.).
22a. At the public hearing, several opponents questioned Mr. Koch’s warning, because
they haven’t seen any of the rolling blackouts occur. It appeared as though they viewed his
concerns about potential blackouts to be idle threats of doom to generate support for the
project that they oppose. The Examiner finds that Mr. Koch, Mr. Nedrud, Ms. Koch, and
other PSE witnesses appeared credible and forthright during their testimony presented at the
public hearing. Even after hearing challenges and dismissive remarks about their opinions
and work related to this project, Mr. Koch, Mr. Nedrud and other PSE witnesses appeared
thoughtful and genuinely concerned that the current PSE system could soon be forced to use
load-shedding (rolling blackouts) to address problems arising from peak demand on existing
substations and powerlines, negatively impacting Bellevue residents and businesses.
22b. At the hearing, Mr. Koch provided a personal account of a meeting that he attended
in Woodinville on July 24, 2018, with Emergency Management personnel, during which time
the PSE transmission system in that location experienced a rapid cascade of events, one
planned de-energization for a work-detail, one involving a squirrel that tripped off a line, all
followed by a pole-top fire, resulting in what is known in the industry as an “N minus 1 minus
1 minus 1” (N-1-1(-1)) situation that forced PSE to “drop load” in order to prevent damage
to equipment, i.e. the sequence of events caused PSE to intentionally black-out some
customers for a period of time because the transmission system exceeded its limits in the
area. While this project will not address the problems up in that part of King County, he
offered the example to demonstrate that PSE must plan for many unexpected things, not just
an occasional tree falling, but many events that, when happening at the same time, cause
undue stress on transmission capacity, resulting in unreliable power supply, and possible
blackouts. (Testimony of Mr. Koch, and Ex. A-3, a copy of his written remarks provided at
the public hearing).
23. Following a request for additional information from the City, PSE explained that it
did not perform any analysis on the electrical loads for the August 2017 dates, but that
increased air conditioning was a likely contributor. PSE’s planning-level modeling found that
both summer and winter peak customer load were driving the need for additional transmission
capacity. (Additional information regarding PSE’s determination of operational need is
discussed in Section VIII.C of the Staff Report in connection with Electrical Utility Facilities
Decision Criteria LUC 20.20.255.E.3). (DSD 000011).
DECISION APPROVING CONDITIONAL USE
PERMIT FOR THE SOUTH BELLEVUE SEGMENT
OF THE ENERGIZE EASTSIDE PROJECT, PUGET
SOUND ENERGY, APPLICANT –
FILE NO. 17-120556-LB
Page 12 of 38
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
BELLEVUE HEARING EXAMINER’S OFFICE
450 – 110TH AVENUE NE
P.O. BOX 90012
BELLEVUE, WASHINGTON 98009-9012
24. At the public hearing, PSE witnesses explained how powerlines lose efficiency when
they are overheated, and that when severe overloads/overheating occurs, some loads may
need to be lowered or turned off to prevent “sparks”, fire, other substantial failures in the
electrical system. This is obviously the case during summer months – when high air
temperatures combined with heavy electrical loads needed to power infrequently-used but
increasingly-common air conditioners, fans, as well as regular system users – all stress the
existing electrical transmission system. PSE witnesses explained how hotter lines cannot
carry the same loads as they can during cooler weather, making the system less efficient
during such hot weather events. Opposition comments that generally challenged the “project
need” because there has not been enough discussion and analysis of system loads during
summer months were not as credible or reliable as testimony provided by the applicant
witnesses, who have the professional training, education, and background to reasonably
ascertain that overheated powerlines can cause serious problems. Common sense supports
their concerns that extreme heat in summer months, or even like that experienced recently
during the past month with area temperatures in the high 80s and low 90s, poses a very real
risk of failure for a system that has not been upgraded for decades to address increased
demand caused by significant growth in the Eastside of King County.
25. The record includes ample information and evidence to support the need for the
pending project. More recent explanations and justifications pointing to risks/overloads that
can occur during hot weather only add to the evidence supporting the need for upgraded
powerlines in Bellevue and the Eastside. PSE’s planning-level modeling found that both
summer and winter peak customer load were driving the need for additional transmission
capacity. None of the project opponents provided testimony or evidence of comparable
weight or substance as that provided by the applicant or the analysis provided in the Staff
Report.
26. Arguments and comments challenging the need for the project because most study
information is focused on high demand during cold weather events, and recent winter demand
has not been as high as originally forecasted, were not convincing and do not serve as a basis
to deny the pending application. This is largely because such arguments fail to recognize that
just because the system hasn’t failed yet, does not mean that it cannot at some point in the
near future, and the consequences could be severe for Bellevue residents and businesses. PSE
witnesses credibly described steps they have taken to address peak demand during winter, as
well as summer, to avoid the need to use rolling blackouts. As the applicant has directed
attention throughout the record, prudent planning is required by applicable state and federal
utility system regulations to assure electrical system reliability. Hoping for warmer winters
and cooler summers, or speculating about future battery options, or the generosity of a
neighboring utility to help in a pinch, is not enough. No action is not a reasonable approach.
Not long ago, it was commonly thought that the tolerance for being without power was about
DECISION APPROVING CONDITIONAL USE
PERMIT FOR THE SOUTH BELLEVUE SEGMENT
OF THE ENERGIZE EASTSIDE PROJECT, PUGET
SOUND ENERGY, APPLICANT –
FILE NO. 17-120556-LB
Page 13 of 38
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
BELLEVUE HEARING EXAMINER’S OFFICE
450 – 110TH AVENUE NE
P.O. BOX 90012
BELLEVUE, WASHINGTON 98009-9012
2-3 days. Nowadays, for the vast majority of people, it is little more than the life of a cell
phone battery. (Testimony of Mr. Koch; Ex. A-3).
27. Some comments challenged the “need” for the project, arguing that carrying power
for loads headed to Canada or other distant locations could be or are already carried by other
powerlines; or that simple, local emergency generators could be fired up to produce additional
power supply, all somehow clearing up capacity in or generating additional power supply
needed for the existing lines, and obviating or delaying the urgency for new lines as proposed
in this application. These comments and related arguments run contrary to the City’s
unrebutted, independent consultant report on the topic, which provided the following relevant
and highly persuasive conclusions regarding the existing 115 kV powerlines and facilities
currently located along the Energize Eastside corridor, which specifically includes the South
Bellevue Segment at issue in this matter:
[A]n overloaded electrical system overheats. During peak load periods,
operators use CAPs to turn off (referred to as opening) lines from either
Sammamish or Talbot Hill substation to reduce heating on certain system
transformers and lines so that they will not be destroyed. They may be able to
keep the Eastside area supplied with electricity, but in doing so large areas of
the Eastside may only be fed from one source. If something happens to that
source, such as a tree falling into a line, or a car accidentally taking out a pole,
or a piece of equipment fails due to fatigue, at that moment the last viable
connection to a power source is gone and the lights go out. Even worse, as load
continues to grow, or the area hits the coldest winter or hottest summer on
record, the operator will be left with a decision: who will have power and who
will not. Until the peak period is over, in order to reduce overloads to an
acceptable level, large portions of the Eastside area could be left without power.
A further possible consequence would be that hospitals, nursing homes, fire
departments, police stations and other critical support services must run on
emergency power or are without power. In this situation the event has become
not just an inconvenience but a hazard.
There are a lot of questions surrounding the probability of these events occurring
on the Eastside. Most people are likely unaware of how many times an outage is
imminent or narrowly avoided. Attempting to specifically predict these events is
nearly impossible because of the number of potential scenarios and
permutations. Is it an extreme peak? Are 100% conservation levels being met?
Is there a system component out for repair? Has an accident removed a piece of
equipment from service? Has a natural or man-made disaster occurred that no
DECISION APPROVING CONDITIONAL USE
PERMIT FOR THE SOUTH BELLEVUE SEGMENT
OF THE ENERGIZE EASTSIDE PROJECT, PUGET
SOUND ENERGY, APPLICANT –
FILE NO. 17-120556-LB
Page 14 of 38
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
BELLEVUE HEARING EXAMINER’S OFFICE
450 – 110TH AVENUE NE
P.O. BOX 90012
BELLEVUE, WASHINGTON 98009-9012
one thought would ever happen? Was the forecast wrong and loads grew faster
than expected? The permutations are endless.
Regional electrical reliability is important to local communities. Without a
reliable regional backbone, energy generated by a wide variety of sources could
not be efficiently delivered to the population areas that need it. All the utilities in
the Northwest bear some responsibility to keep the transmission system in
working order. However, a local utility’s main role is its customers and each has
a legal duty to provide electricity to customers in its service area.
The local utility has two roles to play. On the community level, it needs to provide
an adequate infrastructure of facilities and equipment that can reliably deliver
energy to its local customers. As a regional player, the utility provides its
customers access to the larger interconnected system while making sure its
system is as reliable as its regional neighbors’ systems and not a detriment to the
whole.
The Energize Eastside Project is designed to bring the needed infrastructure to
supply the local need. Any regional benefits that it provides would be added
benefits of a stronger regional source, but these are not the primary reasons why
the project has been proposed. The transmission capacity deficiency is driven
primarily by local rather than regional growth. If the entire region surrounding
the Eastside was eliminated or disconnected from Sammamish and Talbot Hill
substations, and replaced with an independent 230 kV source of power at both
ends, the result would be the same. The Eastside 230 -115 kV system as it exists
cannot supply the projected load under all circumstances, with the required
levels of reliability that the community and neighboring utilities expect. (Stantec
Report, at DSD 000557-558).
28. Mr. Nedrud credibly testified that opposition comments relied too heavily on
consumption data instead of peak-demand data, which PSE must plan for. He emphasized
that the issue is not just about one or a few “what-if” scenarios, but many, and that the
through-put in existing lines is just too small. He described how “peak-generators” intended
to provide additional power supply would be of no value if the existing lines are too small to
carry the load during peak-demand situations. (Testimony of Mr. Nedrud on April 3rd).
29. Responding to challenges and complaints that the data used by PSE to demonstrate
“need” for the project is now too old, from 2015 or so, Mr. Nedrud credibly testified that PSE
has gone back to review whether deficiencies exist using more current data. He confirmed
DECISION APPROVING CONDITIONAL USE
PERMIT FOR THE SOUTH BELLEVUE SEGMENT
OF THE ENERGIZE EASTSIDE PROJECT, PUGET
SOUND ENERGY, APPLICANT –
FILE NO. 17-120556-LB
Page 15 of 38
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
BELLEVUE HEARING EXAMINER’S OFFICE
450 – 110TH AVENUE NE
P.O. BOX 90012
BELLEVUE, WASHINGTON 98009-9012
that PSE analyzed data again, in December of 2016, 2017, and 2018, and that updated data
from each time period showed peak-demand exceeding system capacity. Id.
Environmental Review and Public Engagement.
30. The Staff Report explains, and Department witnesses testified, that the City of
Bellevue, in cooperation with the “Partner Cities” of Kirkland, Newcastle, Redmond, and
Renton, conducted an environmental review of the entire Energize Eastside Project over the
course of several years. The Partner Cities stipulated that the City of Bellevue would act as
the SEPA lead agency. The culmination of the environmental review process was the Final
Environmental Impact Statement (EIS) issued on March 1, 2018. The Final EIS built upon
the previous Phase 1 Draft EIS and Phase 2 Draft EIS, released in January 2016 and May
2017, respectively. (DSD 000074, and DSD 005404).
31. PSE and the Partner Cities agreed to the rigorous two-phase environmental review.
(DSD 000012). During Phase I of the environmental review, the Partner Cities evaluated a
broad range of potential technological alternatives to address the identified transmission
facility deficit. Phase I review assessed the feasibility and environmental impacts of wire
solutions (i.e., overhead, underground and underwater transmission lines, including using
Seattle City Light’s existing corridor in the City of Bellevue) and non-wire solutions (ranging
from battery storage, distributed solar and the construction of natural gas peak shaving
facilities, among others). Id. As PSE witnesses summarized at the public hearing, running
high power transmission lines under Lake Washington presents expensive and time-
consuming challenges, and using City Light transmission lines is not a viable option for
several reasons discussed in the Phase I EIS, including without limitation because it would
mean that PSE would have to perform an entire “rebuild” of the existing City Light structures
and all conductors along the entire line, and create a new connector-route leading to PSE
substations. (Testimony of Mr. Nedrud; and Ph. I EIS, Sec. 2.3.2.3 discussion of Option B,
to use Seattle City Light 230kV Overhead Transmission Lines, at DSD 011181).
32. Following the elimination of Project alternatives that were infeasible or failed to meet
the Project’s purpose and need, Phase II focused on analyzing the potential environmental
impacts of route options for the overhead line alternative. Id. The Phase II Draft EIS and
Final EIS analyzed 14 routing alternatives including a north, central and south Bellevue
segment. (DSD 005435, listing routing alternatives). The EIS analyzed two central Bellevue
routing alternatives (including two by-pass routes that do not cross the East Bellevue
Community Council’s (“EBCC’s”) jurisdiction) and four routing alternatives for the south
segment. Id.
DECISION APPROVING CONDITIONAL USE
PERMIT FOR THE SOUTH BELLEVUE SEGMENT
OF THE ENERGIZE EASTSIDE PROJECT, PUGET
SOUND ENERGY, APPLICANT –
FILE NO. 17-120556-LB
Page 16 of 38
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
BELLEVUE HEARING EXAMINER’S OFFICE
450 – 110TH AVENUE NE
P.O. BOX 90012
BELLEVUE, WASHINGTON 98009-9012
33. The Partner Cities’ analysis confirmed that, of all alternatives and route options
analyzed, construction of an upgraded transmission line in the existing corridor best
addressed project need while limiting costs and environmental impacts. (DSD 005472, FEIS
at 2-45, which reads in relevant part: “At this time, [other than a transmission line upgrade]
there are no currently known, widely accepted technologies that PSE would employ that
could feasibly and reliably address the transmission capacity deficiency on the Eastside”;
and DSD 000014-15 (describing how siting limits environmental impacts).
34. Following the publication of the Phase II DEIS, PSE changed its preferred route
alternative from the “Willow 2” route to the “Willow 1” route, the analysis of which provides
the basis for this CUP application. PSE explained that it undertook this change in response
to data showing that the Willow 1 route, which follows the existing transmission line corridor,
was the safest, least impactful route. (See PSE discussion of its preferred site alternative at
DSD 000240-41; and PSE Response Brief to Motion to Continue, dated Feb. 11, 2019).
35. All of the option routes considered through the EIS and alternate site review process,
including Willow 1, traverse residential land use districts, but PSE determined that utilizing
the existing corridor would minimize impacts associated with the Project on surrounding
areas. As noted in the Staff Report and confirmed by Department and PSE witnesses at the
public hearing, PSE’s decision to use the existing corridor minimizes tree removal as
compared to establishing a new corridor and allows for better assessment of potential
interactions with the co-located Olympic pipeline. The existing corridor also minimizes the
creation of new impacts to adjacent uses, including residential uses. As properties adjacent
to the transmission line corridor currently have utility facilities in their viewsheds and
neighborhoods, the Willow 1 route has lower impacts compared to establishing a new
corridor. (DSD 000044).
36. The Alternative Siting Analysis (included in the Record as Attachment B to the Staff
Report) contains sufficient information regarding the methodology employed, the alternative
sites analyzed, the technologies considered, and the community outreach undertaken to
satisfy the requirements of LUC 20.20.255.D. The Analysis includes numerous appendices
addressing Project need, public outreach and input, and tracks the extensive environmental
review undertaken in connection with the Project. The Analysis also explains how, by
constructing the proposed transmission line facilities in the existing 115 kV transmission line
corridor and selecting the Richards Creek substation, site compatibility impacts are limited
by this preferred alternative. See LUC 20.20.255.D.2.d. Therefore, PSE’s Alternative Siting
Analysis complies with the provisions of LUC 20.20.255.D. (See discussion at DSD
000044).
DECISION APPROVING CONDITIONAL USE
PERMIT FOR THE SOUTH BELLEVUE SEGMENT
OF THE ENERGIZE EASTSIDE PROJECT, PUGET
SOUND ENERGY, APPLICANT –
FILE NO. 17-120556-LB
Page 17 of 38
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
BELLEVUE HEARING EXAMINER’S OFFICE
450 – 110TH AVENUE NE
P.O. BOX 90012
BELLEVUE, WASHINGTON 98009-9012
37. As noted in the Staff Report, an EIS is the most detailed form of environmental review
required under SEPA and is prepared when an agency determines that it is probable that a
project would have significant environmental impacts. The Phase 1 Draft EIS assessed a
range of impacts and implications associated with broad alternatives for addressing PSE’s
objectives in a non-project, or programmatic, EIS. (DSD 000074).
38. The environmental review undertaken by the Partner Cities and memorialized in the
Phase 2 Draft EIS and Final EIS considered the impacts on the environment of the entire
Energize Eastside Project throughout each jurisdiction – extending from Redmond in the
north to Renton in the south. The Phase 2 Draft EIS incorporated the Phase 1 Draft EIS by
reference and presented a project-level environmental review. (DSD 000074).
39. Based on the results of the Phase 2 Draft EIS analysis, PSE refined the proposed route
of the transmission lines and associated Project components. The Final EIS assessed PSE’s
project level proposed alignment (referenced as “Willow 1”) and considered environmental
impacts of the entire Energize Eastside Project in light of this proposed alignment (see
Chapters 1, 2, 4, 7, and 8 of the Final EIS). (DSD 000074).
40. While environmental analysis in the Staff Report focused on the impacts reviewed for
the portions of the Project currently under consideration in connection with the two Bellevue
Permits (specifically this CUP, and the associated, unchallenged Critical Areas permit,
identified as Permit Nos. 17-120556-LB and 17-120557-LO), the environmental review in
the Final EIS was not limited to any segment or portion of the Energize Eastside Project.
Instead, the Final EIS presented a comprehensive environmental assessment of the entire
Energize Eastside Project, including a full analysis of potential impacts and cumulative
impacts associated with the construction and operation of PSE's proposed alignment. (DSD
000074).
41. Staff properly found and concluded that the Energize Eastside Project Final EIS and
supporting documentation fulfill SEPA requirements for the pending proposal and the larger
Energize Eastside Project and, consistent with BCC 22.02.020 and WAC 197-11-635,
incorporated such documentation into the Staff Report by reference. (DSD 000074).
42. The Examiner concurs. The Final EIS, and the multi-year public outreach process
undertaken by the Partner Cities, fulfills applicable SEPA review requirements for the project
addressed in this permit.
43. The Final EIS reflects analysis of the South Bellevue Segment based on the
application details at issue in this matter. Again, it also includes a full analysis of potential
impacts and cumulative impacts associated with the construction and operation of the entire
DECISION APPROVING CONDITIONAL USE
PERMIT FOR THE SOUTH BELLEVUE SEGMENT
OF THE ENERGIZE EASTSIDE PROJECT, PUGET
SOUND ENERGY, APPLICANT –
FILE NO. 17-120556-LB
Page 18 of 38
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
BELLEVUE HEARING EXAMINER’S OFFICE
450 – 110TH AVENUE NE
P.O. BOX 90012
BELLEVUE, WASHINGTON 98009-9012
Energize Eastside Project and PSE's proposed alignment. The Final EIS facilitated broad
public participation and informed decision-making for both requested permits, the
unchallenged CALUP and the Conditional Use Permit addressed herein. The review process
for the South Bellevue Segment is the antithesis of any alleged failure to study, failure to
disclose, or improper “segmentation” or “piecemealing” as some opponents argued.
44. For instance, the Final EIS explains: “For the Richards Creek substation site and the
Bellevue South and Newcastle Segments, the analysis included a review of the project design
as presented in the permit applications submitted to Bellevue and Newcastle (PSE, 2017b
and PSE, 2017c, respectively). The results below have been revised relative to the Phase 2
Draft EIS, incorporating the more detailed information in the permit applications on pole
locations and critical areas (including wetlands, streams, and their buffers). The conclusions
regarding significant impacts on land use, however, are the same as presented in the Phase
2 Draft EIS.” (DSD 005495).
45. Instead of using a “general” study, or guesstimate as to what average impacts on views
and other aspects of the environment might be, as one might come to expect from a very
broad environmental review document, the impacts on views for the Energize Eastside
Project were analyzed by “segment” – which is the level of detail that specific neighborhoods
frequently demand. See Impact Analysis by Segment in the Final EIS, at DSD 005524, which
reads in part: “The following pages summarize the potential impacts on scenic views and the
aesthetic environment for PSE’s Proposed Alignment, presented for the Richards Creek
substation and by segment. For the Redmond, Bellevue North, Bellevue Central, and Renton
Segments, the analysis included a review of refined project design details for PSE’s Proposed
Alignment and updated simulations, with results revised relative to the Phase 2 Draft EIS to
reflect the new information. For these segments, the new information and analysis have not
altered the conclusions presented in the Phase 2 Draft EIS regarding significant impacts to
scenic views and the aesthetic environment.”
46. The Final EIS fully disclosed and discussed how the new transmission line project
would be developed in segments or phases. See for example the explanation provided in the
Sec. 2-37 of the Final EIS, at DSD 005464, which expressly informs the reader, the public,
and decision-makers, as follows:
“Construction Phasing and Schedule. Construction of the transmission lines would typically
take approximately 12 to 18 months (over two construction phases) and would be constructed
concurrently with construction of the Richards Creek substation. Under certain conditions,
construction can be accelerated or slowed down depending on the number of crews working at
the same time. The project is expected to be built in phases, with the south end (from the Talbot
Hill substation to the proposed Richards Creek substation) being the first phase, followed by the
north phase as soon as design, permitting, and energization of the south phase would allow. The
project needs to be built in two construction phases to keep the Lakeside substation energized,
DECISION APPROVING CONDITIONAL USE
PERMIT FOR THE SOUTH BELLEVUE SEGMENT
OF THE ENERGIZE EASTSIDE PROJECT, PUGET
SOUND ENERGY, APPLICANT –
FILE NO. 17-120556-LB
Page 19 of 38
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
BELLEVUE HEARING EXAMINER’S OFFICE
450 – 110TH AVENUE NE
P.O. BOX 90012
BELLEVUE, WASHINGTON 98009-9012
thereby keeping the transmission system on-line to serve customers. During the construction of
the south phase, the Lakeside substation will be served from the north and likewise, once the
south phase is complete, it will be used to serve the Eastside while the north half is constructed.”
47. Opposition arguments that challenged the pending application as improper
“segmentation”, “piecemealing”, an undisclosed last-minute change, a strategic surprise, and
the like, are factually incorrect. The Final EIS used to inform the public and decisionmakers
in reviewing the pending application fully discloses that the South Bellevue Segment can
function independently, and that the new transmission line will be developed in phases. It
also explains a public benefit rationale for PSE’s proposed phased construction schedule for
the Energize Eastside Project – keeping the transmission system on-line to serve customers
during construction.
48. PSE notes that the public review for its Energize Eastside Project has included the
following community outreach efforts (See DSD 000043-44; DSD 000249-252; and PSE
Response Brief to Motion to Continue, dated Feb. 11, 2019):
• 22 Community Advisory Group-related meetings, including six public open houses,
two question and answer sessions, and two online open houses at key project
milestones (four CAG meetings, three Sub-Area meetings, and an open house took
place in Bellevue);
• Nearly 650 briefings (~320 in Bellevue) with individuals, neighborhoods, cities and
other stakeholder groups;
• More than 300 comments and questions received, with more than 1,000 from
Bellevue residents;
• 40+ email updates to more than 1,600 subscribers, with 775 residing in Bellevue;
• 10 project newsletters to 55,000+ households (20,000+ of which are in Bellevue);
• Ongoing outreach to 500+ property owners, including door-to-door and individual
meetings, including approximately 130 parcels in Bellevue; and
• Participation in 16 EIS-related public meetings, five of which took place in Bellevue.
49. The Staff Report includes a detailed listing of public notices and public meetings
conducted over the last few years regarding the construction of a new transmission line to
connect the Talbot Hill and Lakeside substations, including the proposed Richards Creek
substation addressed in this permit. See DSD 000086-87. Staff confirmed that public
noticing requirements for the pending application were fully satisfied.
50. About 50 local residents, business owners, community leaders and interested citizens
testified at the public hearing portion regarding the CUP application, and many live in
neighborhoods that already have powerlines in their viewshed if they look at their windows
or drive along streets in their community. Given the size of the crowd in the room when the
DECISION APPROVING CONDITIONAL USE
PERMIT FOR THE SOUTH BELLEVUE SEGMENT
OF THE ENERGIZE EASTSIDE PROJECT, PUGET
SOUND ENERGY, APPLICANT –
FILE NO. 17-120556-LB
Page 20 of 38
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
BELLEVUE HEARING EXAMINER’S OFFICE
450 – 110TH AVENUE NE
P.O. BOX 90012
BELLEVUE, WASHINGTON 98009-9012
hearing opened, the Examiner granted a request to allow Bellevue residents the opportunity
to speak first, followed by people from other places. Most people observed the hearing rules.
People offered a wide-range of comments, with project supporters focusing on the need for
reliable power in the City, and opponents repeating themes and issues raised in written
comments analyzed throughout the EIS process and in the Staff Report. Several of the public
witnesses spoke twice.
51. A large share of the public comments opposing the project focused on pipeline safety
concerns. The applicant and staff properly note that pipeline safety issues are some of the
most detailed topics addressed in mitigation measures and conditions of approval proposed
in the FEIS and the Staff Report. Many of the opposition comments and presentations made
during the public hearing focused on the “need” issue, with little pushback given to portions
of the Staff Report that address how the project can be designed and conditioned to comply
with applicable city standards for such facilities. Many opponents questioned whether any
alternatives or routes ever really needed to be studied in the first place, reasoning that if
there’s no real need, then there is no reason for the project.
52. As noted in previous findings, “need” was analyzed over the past few years, and one
thing has not and shows few signs of changing – Bellevue and the Eastside are booming.
Even if growth were to grind to a halt, the rapid pace of growth and demand since the 115kv
lines along the corridor were last substantially improved, decades ago, makes challenges to
“need” and assertions that “demand just does not support the project” problematic.
53. Doing nothing, and simply maintaining the status quo, is not a responsible choice.
The Phase 2 Draft EIS concluded that “Under the No Action Alternative, PSE would continue
to manage its system in largely the same manner as at present. This includes maintenance
programs to reduce the likelihood of equipment failure, and stockpiling additional equipment
so that in the event of a failure, repairs could be made as quickly as possible. Implementation
of the No Action Alternative would not meet PSE’s objectives for the proposed project, which
are to maintain a reliable electrical system and to address a deficiency in transmission
capacity on the Eastside. Implementation of the No Action Alternative would increase the
risk to the Eastside of power outages or system damage during peak power events.” (Phase
2 DEIS, discussion of No Action Alternative at Sec. 2.1.1, included in the Record at DSD
010246-247, emphasis added).
54. While thoughtful and caring about their homes, neighborhoods, families, neighbors
and environmental stewardship, the vast majority of comments opposing the project came
from people with personal motivations like potential view impacts they believe will occur if
the project goes forward. While some people complained about the existing powerlines and
stray static events that can make your hair stand up on a misty day, most opposition witnesses
DECISION APPROVING CONDITIONAL USE
PERMIT FOR THE SOUTH BELLEVUE SEGMENT
OF THE ENERGIZE EASTSIDE PROJECT, PUGET
SOUND ENERGY, APPLICANT –
FILE NO. 17-120556-LB
Page 21 of 38
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
BELLEVUE HEARING EXAMINER’S OFFICE
450 – 110TH AVENUE NE
P.O. BOX 90012
BELLEVUE, WASHINGTON 98009-9012
would have to acknowledge that the existing powerlines and utility corridor were already in
place when they moved into their homes. Their questions and challenges to details in
environmental reviews, load studies, demand studies, and the like, appeared jaded and
heavily influenced by their desire to stop the project at any cost, to preserve existing
conditions. Some expressed their desire to see all lines removed and the corridor used as a
greenway.
55. Like other project opponents, CENSE and CSEE representatives voiced concerns but
did not offer sufficient, relevant, authoritative, or credible evidence that would rebut the
findings and recommendations made in the Staff Report.
56. The “need” studies, analysis of alternatives, pipeline safety reports and other
substantive materials provided by the applicant were thoroughly reviewed, challenged, and
revised by Staff and independent consultants engaged by the City to review applicant
submittals for this project. Independent consultants confirmed that PSE studies and reports
were conducted in a manner generally accepted by professionals specializing a particular
subject matter, like system reliability, pipeline safety, pole design and the like.
57a. Again, third-party reviews confirmed the substance of the applicant’s key submittals
at issue in this CUP application. At the close of the hearing, attorneys for the two opposition
groups, CENSE and CSEE, asked the Examiner to carefully read the Lauckhart and
McCullough materials, included in the record, to see how the applicant has failed to satisfy
approval criteria, mostly the requirement to show operational need. Having read and re-read
the opposition reports and evidence, and the independent studies prepared by Stantec and
USE, one finding and conclusion became crystal clear – the applicant reports, forecasts, and
data analyses were in compliance with applicable industry standards. The opponents failed
to rebut the independent consultant reviews of PSE’s work involved in this application
process, all of which concluded that PSE was planning and reviewing data in accord with
industry practice and standards.
57b. On the other hand, PSE firmly established that several key aspects of opposition
reports were defective and simply not credible, because they failed to follow industry
practice. Rebuttal testimony from Mr. Nedrud was powerful and credible. He showed how
Mr. McCullough’s presentation, which showed far less demand than PSE forecasts, failed to
properly account for several considerations required by industry practice and applicable
federal electrical system planning mandates (NERC requirements) described by Ms. Koch
during her testimony. Mr. Nedrud showed how Mr. McCullough’s research analysis
presented at the hearing only considered current loads to make load forecasts. This leads to
erroneous results, because such analysis fails to include consideration of weather events (at
peaks/extremes), projections of economic activity, population projections, building permits,
DECISION APPROVING CONDITIONAL USE
PERMIT FOR THE SOUTH BELLEVUE SEGMENT
OF THE ENERGIZE EASTSIDE PROJECT, PUGET
SOUND ENERGY, APPLICANT –
FILE NO. 17-120556-LB
Page 22 of 38
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
BELLEVUE HEARING EXAMINER’S OFFICE
450 – 110TH AVENUE NE
P.O. BOX 90012
BELLEVUE, WASHINGTON 98009-9012
and conservation goals. Testimony of Mr. Nedrud, and his rebuttal slides presented at the
hearing, included in the record as Ex. A-17. Further, Mr. Nedrud demonstrated how Mr.
Marsh’s illustrations challenging demand data used by PSE were problematic, because the
focus was on consumption (use) and not peak demand.
57c. Consumption is the amount of electricity that customers use over the course of a year.
“Consumption” is also called “use” or “energy”. “Demand” is customer usage at any given
moment in time. “Peak Demand” is the maximum amount of electricity that PSE customers
will demand at any given time.
57d. The City’s consultant addressed the difference of “use versus demand” in its
Independent Technical Analysis:
“Bellevue’s Resource Conservation Manager (RCM) program stats on declining energy use are
reflecting a decline in the average use per customer. The DSM programs, solar, etc. are showing
success with this decline. But, that is one piece of the story - the energy piece on a per customer
basis. The number of customers continues to increase, and the aggregate peak usage (peak
demand), is continuing to increase. Growth in peak demand drives the size and amount of
infrastructure required and drives the issue of grid reliability.” (USE report, included as
Attachment D to the Staff Report, found at DSD 000663-000739, on page 9 of 76; emphasis
added).
57e. In October of 2015, the Federal Energy Regulatory Commission (FERC) dismissed a
complex challenge to the Energize Eastside Project raised by CENSE, CSEE, Larry Johnson,
and others (identified by FERC as “Complainants”), which was supported by sworn
testimony from Mr. Lauckhart, CSEE’s principal witness in this matter. The FERC decision
includes the following passage, which applies just as well to this Decision: “Complainants
discuss alleged flaws in the load flow studies that Puget Sound conducted for the Energize
Eastside Project. However, Complainants do not demonstrate that the studies violated any
applicable transmission planning requirements or were otherwise unjust, unreasonable, or
unduly discriminatory or preferential. Complainants do not cite anything that would require
Puget Sound to use the study inputs and assumptions that Complainants prefer instead of the
inputs and assumptions that Puget Sound used.” (FERC Order Dismissing Complaint by
CENSE, CSEE, et al., issued Oct. 21, 2015, included in the record at DSD 000656, complete
Order at DSD 000630-000659). As in the FERC challenge, in this hearing process Mr.
Lauckhart alleged flaws in the load flow reports that PSE relied upon to demonstrate need
for its Energize Eastside Project, among other things. He did not rebut the favorable reviews
provided by independent consultants engaged by the city regarding PSE’s supporting studies.
Mr. Lauckhart and other project opponents did not demonstrate that the studies used by PSE
violated any applicable transmission planning requirements or were otherwise unjust,
unreasonable, or unduly discriminatory or preferential. Opponents do not cite anything that
DECISION APPROVING CONDITIONAL USE
PERMIT FOR THE SOUTH BELLEVUE SEGMENT
OF THE ENERGIZE EASTSIDE PROJECT, PUGET
SOUND ENERGY, APPLICANT –
FILE NO. 17-120556-LB
Page 23 of 38
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
BELLEVUE HEARING EXAMINER’S OFFICE
450 – 110TH AVENUE NE
P.O. BOX 90012
BELLEVUE, WASHINGTON 98009-9012
would require PSE to use the study inputs and assumptions that they prefer instead of the
inputs and assumptions that PSE used.
58a. Several opposition speakers directed attention to parts of the city’s code that they read
to say to that electrical facilities should be located where the need exists. In response, City
staff argued that city codes do not mandate an entirely new utility corridor if fewer site
compatibility impacts occur in a residential area than some other zoning district, and that the
South Bellevue Segment proposal is the most feasible, lowest-impact option, emphasizing
that the existing powerline route has been in the same place for decades, that poles have been
in place in the same neighborhoods for many years, and that no new right-of-way is required
as part of this project. The Staff Report, at pages 41-47, explains how the route selected by
PSE has fewer site-compatibility impacts than other options.
58b. Even if the City’s code could be read to require electrical facilities to only locate in
areas that benefit or need the new or expanded electrical facility in question, in this situation,
that is precisely what is proposed, because “load-shedding” – i.e. rolling blackouts – is
currently part of PSE’s corrective action plan (CAP) options in neighborhoods throughout
the Eastside, including residential neighborhoods that are located along the route of the South
Bellevue Segment. Given these circumstances, there truly is a critical “need” for the project
to prevent such problems going forward in the residential areas located along the route.
58c. Pole designs, placement, heights, and wire-connections on poles, were all analyzed to
generate conditions that minimize view impacts to the fullest extent reasonable, while still
achieving the project objectives, including enhancing the reliability and redundancy in the
power-transmission system that serves the City of Bellevue, including neighborhoods and
businesses in the area affected by this South Bellevue Segment proposal.
59. The Examiner adopts and incorporates the City of Bellevue’s administrative decision
approving the associated Critical Area Land Use Permit (CALUP) issued for this project,
under File No. 17-120557-LO, which was not appealed, as unchallenged findings,
conclusions, and conditions of approval, that all provide support for the requested
Conditional Use Permit, including without limitation:
• Findings and Conclusions re: Critical Areas Report Decision Criteria – General
Criteria, LUC 20.25H.255.A.4, on page 104 of the Staff Report, which reads as
follows:
The resulting development is compatible with other uses and development in the same land use
district.
DECISION APPROVING CONDITIONAL USE
PERMIT FOR THE SOUTH BELLEVUE SEGMENT
OF THE ENERGIZE EASTSIDE PROJECT, PUGET
SOUND ENERGY, APPLICANT –
FILE NO. 17-120556-LB
Page 24 of 38
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
BELLEVUE HEARING EXAMINER’S OFFICE
450 – 110TH AVENUE NE
P.O. BOX 90012
BELLEVUE, WASHINGTON 98009-9012
Finding: The project involves the replacement of an existing transmission line; therefore, no change
in land use proposed. The proposed substation is located adjacent to an existing substation and
other light industrial uses and non-residential development. PSE’s proposal is anticipated by and
included in Bellevue’s Comprehensive Plan (see Attachment F [Map UT-7] to this Staff Report).
The proposal is limited to the existing corridor, and the Project, as modified, is compatible with
and responds to the uses and development that has been built up around the transmission line
corridor for decades.
• Findings and Conclusions re: Critical Areas Land Use Permit Decision Criteria – item
4 re: LUC 20.30P.140.D, on page 106 of the Staff Report, which reads as follows:
4. The proposal will be served by adequate public facilities including street, fire protection, and
utilities.
Finding: The proposed transmission lines will not impact any existing public facility service level.
The Phase 1 Draft EIS and Final EIS concluded that the Energize Eastside Project would not
significantly increase the demand for public services, or significantly hinder the delivery of
services. Refer to Technical Reviews conducted by the Fire, Utilities, and Transportation in
Section V of this Staff Report.
• Findings and Conclusions re: Critical Areas Land Use Permit Decision Criteria – item
6, re: LUC 20.30P.140.F, on page 107 of the Staff Report, which reads as follows:
6. The proposal complies with other applicable requirements of this code.
Finding: As discussed in Section IV of this Staff Report, PSE’s proposal complies with
all other applicable requirements of the Land Use Code.
60. Section IV.A of the Staff Report analyzes and explains how the pending proposal is
consistent with applicable Land Use Code and Zoning Requirements, specifically PSE’s
obligation to comply with the Alternative Siting Analysis and design requirements found in
LUC 20.20.255.D and 20.20.255.F, which apply to Electrical Utility Facilities. (See Staff
Report at page 41). Given that the Critical Areas Land Use Permit was not appealed, any
arguments or opposition to the requested Conditional Use Permit that are based on challenges
to the Alternative Siting Analysis or design requirements found in the Land Use Code must
fail. All findings, conclusions and conditions of approval in the CALUP are now beyond
review. Any appeal of this Decision cannot be used to collaterally attack any aspect of the
CALUP or determinations made therein. (See Wenatchee Sportsmen Ass’n v. Chelan
County, 141 Wn.2d 169, 182, 4 P.3d 123 (2000), and Habitat Watch v. Skagit County, 155
Wn.2d 397, 410–11, 120 P.3d 56 (2005)).
61. City staff appropriately relied upon the Final EIS in its review of the requested CUP,
and in crafting proposed conditions of approval for the South Bellevue Segment project. The
DECISION APPROVING CONDITIONAL USE
PERMIT FOR THE SOUTH BELLEVUE SEGMENT
OF THE ENERGIZE EASTSIDE PROJECT, PUGET
SOUND ENERGY, APPLICANT –
FILE NO. 17-120556-LB
Page 25 of 38
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
BELLEVUE HEARING EXAMINER’S OFFICE
450 – 110TH AVENUE NE
P.O. BOX 90012
BELLEVUE, WASHINGTON 98009-9012
potential impacts studied in the EIS included a comprehensive set of worst-case scenarios
and detailed mitigation measures for the larger project as well as this specific portion of the
larger Energize Eastside Project, all of which should serve to adequately avoid, minimize,
rectify, reduce, or eliminate adverse impacts associated with the South Bellevue Segment
proposal. Several items in the conditions of approval require monitoring and data collection
as part of the project, to assure that powerline/pipeline conflicts do not result in adverse
impacts. (See Conditions of Approval, including without limitation No. 17, mandating that
PSE must file a mitigation and monitoring report with the City documenting consultations
held with Olympic Pipeline to address pipeline safety related issues at least quarterly during
construction, and post start-up monitoring to ensure that mitigation measures related to
operational issues are followed, at DSD 000144).
Olympic Pipeline System.
62. At the public hearing, multiple local residents expressed their genuine and legitimate
concerns with hazards posed by existing electrical lines spanning over the Olympic petroleum
pipeline though the City of Bellevue. Similar concerns were already provided in written
comments summarized in the Staff Report, including without limitation at DSD 000093.
63. The Olympic Pipeline system is an underground petroleum pipeline system that is co-
located with the existing PSE 115 kV transmission line corridor throughout the entire
Energize Eastside Project area, except in the central portion of the Renton Segment. The
Olympic Pipeline system is a 400-mile interstate pipeline system that runs from Blaine,
Washington to Portland, Oregon. The system transports gasoline, diesel, and jet fuel through
two pipelines – one 16 inches and one 20 inches in diameter. In the Energize Eastside Project
area, the pipelines are generally co-located with PSE’s transmission line within all of the
segments, although in the Renton Segment it only co-located in the north portion of the
segment (although it crosses the corridor in the southern portion of the segment). (DSD
005451).
64. The PSE transmission line corridor predates the pipeline by approximately three
decades. (Id.; Testimony of PSE witnesses).
65. In most of the segments, the pipeline system is along either the east or west side of
the PSE right-of-way, crisscrossing the right-of-way from east or west in numerous locations.
In parts of the corridor (especially the Newcastle Segment), however, the pipeline system is
buried in the center of the right-of-way. BP is the operator of the Olympic Pipeline system,
and partial owner of the Olympic Pipe Line Company, with Enbridge, Inc. (Olympic Pipe
Line Company, 2017). Typically, the proposed poles would be located at least 13 feet from
DECISION APPROVING CONDITIONAL USE
PERMIT FOR THE SOUTH BELLEVUE SEGMENT
OF THE ENERGIZE EASTSIDE PROJECT, PUGET
SOUND ENERGY, APPLICANT –
FILE NO. 17-120556-LB
Page 26 of 38
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
BELLEVUE HEARING EXAMINER’S OFFICE
450 – 110TH AVENUE NE
P.O. BOX 90012
BELLEVUE, WASHINGTON 98009-9012
the Olympic Pipeline system where it is co-located with the transmission lines to reduce the
need for additional arc shielding protection. (DSD 005451).
66. Due to the level of public concern expressed during scoping for both Phase 1 and
Phase 2 regarding the potential risk of a leak, fire, or explosion that could occur as a result of
constructing or operating the transmission lines in the same corridor as the Olympic Pipeline
system, the pipeline safety issue is addressed specifically as one of two environmental health
issues. Information on pipeline safety, both during construction and operation, is presented
in the Final EIS, at Sections 4.9 and 5.9, re: Environmental Health – Pipeline Safety. (DSD
005451).
67. As the City’s Land Use Director, Ms. Stead, noted during her testimony, the Final
EIS concludes that the potential for conflicts/risks involving PSE powerlines and the Olympic
Pipeline running beneath most all of the corridor in question will be lower or about the same
with the project than with no action.
68. The Final EIS provides the following “Impact Conclusion for PSE’s Proposed
Alignment”, which expressly includes the South Bellevue Segment addressed in this permit:
Based on the results of the risk assessment, the probability of a pipeline release and fire occurring
and resulting in fatalities remains low under PSE’s Proposed Alignment. However, the potential
public safety impacts would be significant if this unlikely event were to occur.
Under PSE’s Proposed Alignment, including mitigation for corrosion and arc risk incorporated
into the design, the probability of a significant pipeline safety incident would likely be the same
or lower than the No Action Alternative. Because of the variability of soils, it is possible that the
arcing risk could be slightly higher in some locations when compared with the No Action
Alternative. In these areas, testing, monitoring, engineering analysis, and implementation of
mitigation measures would lower these risks. See Section 4.9.8, Mitigation Measures for
measures that would lower the risks.
The individual and societal risks described in Section 3.9.5.2 of the Phase 2 Draft EIS would be
similar across all segments of PSE’s Proposed Alignment. The risk would be proportional to the
distance that the transmission lines are co-located with the Olympic Pipeline system. For PSE's
Proposed Alignment, the Renton Segment has the lowest number of co-located miles. Table 4.9-
1 lists the length of the Olympic Pipeline system (both the 20-inch and 16-inch diameter
pipelines) collocated with the transmission lines in each segment.
As described above, the lack of available data for existing fault and arc distance conditions
required the risk assessment to use certain assumptions for the No Action Alternative condition
that would allow for a worst-case analysis of the proposed 230 kV lines. Using these assumptions
likely understates the existing risk (No Action), thereby possibly overstating the actual difference
in risk between the No Action Alternative and PSE’s Proposed Alignment. The likelihood of a
pipeline rupture and fire would remain low, with no substantial change in risk. As a result, the
potential impact on environmental health with regard to pipeline safety is not considered
DECISION APPROVING CONDITIONAL USE
PERMIT FOR THE SOUTH BELLEVUE SEGMENT
OF THE ENERGIZE EASTSIDE PROJECT, PUGET
SOUND ENERGY, APPLICANT –
FILE NO. 17-120556-LB
Page 27 of 38
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
BELLEVUE HEARING EXAMINER’S OFFICE
450 – 110TH AVENUE NE
P.O. BOX 90012
BELLEVUE, WASHINGTON 98009-9012
significant. With implementation of the mitigation described in Section 4.9.8 of this Final EIS,
conditions related to potential for fault damage due to coating stress and arc distances would
likely improve under PSE’s Proposed Alignment over the existing operational baseline condition
(No Action Alternative) (DNV GL, 2016 – A Detailed Approach to Assess AC Interference Levels
Between the Energize Eastside Transmission Line Project and the Existing Olympic Pipelines,
OLP16 & OPL20. Memo to Puget Sound Energy, dated September 9, 2016. Note 15 on page 15
of the Staff Report [DSD 000015] explains that the entire DNV GL 2016 report is included in the
Phase 2 Energize Eastside Project EIS materials, and is included in the DSD official files for
Permit Nos. 17-120556-LB and 17-120557-LO). For additional details about the analysis of risks
under Alternative 1, see the Pipeline Safety Technical Report (EDM Services, 2017).
(FEIS, Chapter 4.9 Re: “Environmental Health – Pipeline Safety”, at DSD 005699. Full
discussion and thorough analysis of Pipeline Safety topics provided on pages DSD 005676-
005715. Proposed mitigation measures re: pipeline safety issues are addressed on pages DSD
005714-15).
69. Wolfgang Fieltsch is a qualified expert on issues regarding pipeline safety,
particularly when pipelines are located in corridors near powerlines such as the case presented
in this matter. During the public hearing, Mr. Fieltsch testified within his area of expertise.
His testimony was credible.
70. At the public hearing, the City called Mr. Fieltsch, a recognized expert in the field of
pipeline corrosion and safety issues where pipelines are co-located near powerlines, which
he testified is very common. Mr. Fieltsch was retained by the City to serve as its independent
expert on pipeline safety issues. He verified that he reviewed the DEN GL report (submitted
by the applicant) and summarized some of his work performed to address pipeline safety
issues discussed in the Environmental Impact Statement. He explained how mitigation
measures proposed in the EIS should result in a powerline/pole design that will include
“optimal phase arrangement” among other things, to cancel much of the potential AC
interference problems that could occur.
71. Mr. Fieltsch’s written report illustrates how the environmental review process for this
project has resulted in design changes and strict mitigation requirements that make the
proposal less likely to cause adverse impacts, particularly with respect to pipeline safety. His
professional opinion on the subject served as the basis for additional mitigation measures
addressed in the Final EIS, and the specific pipeline safety related conditions of approval
proposed in the Staff Report. The Fieltsch Report, identified as the TECHNICAL REVIEW
re: ENERGIZE EASTSIDE AC INTERFERENCE ANALYSIS, dated May 2, 2017, prepared
by Wolfgang Fieltsch, P. Eng. Team Lead – CP and AC Mitigation, for Stantec Consulting
Services, which was prepared for the Energize Eastside EIS review team, is included in the
Record at DSD 004532-4539, and provides the following detailed “Opinion” and
recommendations:
DECISION APPROVING CONDITIONAL USE
PERMIT FOR THE SOUTH BELLEVUE SEGMENT
OF THE ENERGIZE EASTSIDE PROJECT, PUGET
SOUND ENERGY, APPLICANT –
FILE NO. 17-120556-LB
Page 28 of 38
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
BELLEVUE HEARING EXAMINER’S OFFICE
450 – 110TH AVENUE NE
P.O. BOX 90012
BELLEVUE, WASHINGTON 98009-9012
The primary objective of the AC interference study performed by DNV GL was to perform a
sensitivity analysis to determine the optimal route and powerline configuration to minimize the
AC interference risks on the two collocated pipelines.
An optimal route, phasing, and conductor orientation was selected to minimize the steady-state
induced AC voltages on the paralleling pipelines. Shield wires were recommended to minimize
the conductive coupling and arcing risks due to a phase -to -ground fault on the powerline
structures.
Based on Stantec’s experience and industry standards, it is our opinion that the technical
approach used to achieve this objective in the subject AC interference study is consistent with
industry practice.
The report concluded that the modeling indicated that selection of the recommended optimal
route and configuration would result in no AC mitigation requirements on the pipelines. The
report further recommends that final mitigation design should be based on field data collected
after system energization.
In Stantec’s opinion, although the study and modeling performed is sufficient as a sensitivity
analysis, it cannot be used to determine the mitigation requirements for the pipelines related to
the final design of the powerlines. Furthermore, mitigation based on field testing after
energization is also not an acceptable approach, as measurements can only be taken at test
stations, which are not necessarily located at locations with highest induced AC voltages and at
greatest AC corrosion risk. Additionally, it is not possible to assess safety and integrity risks
under powerline fault conditions in the field. DSD 004537
As such, we recommend the following be performed in the detailed design stage of the project
prior to energization of the new powerline:
• Perform an AC interference study incorporating the final powerline route, configuration,
and operating parameters.
• Obtain and incorporate all of the pipeline parameters required for detailed modeling and
study (i.e., locations and details of above-grade pipeline appurtenances/stations, bonds,
anodes, mitigation, etc.). This should include a review of the annual test post Cathodic
Protection (CP) survey data.
• Fully assess the safety and coating stress risks for phase-to-ground faults at powerline
structures along the entire area of collocation. This assessment should include both
inductive and resistive coupling.
• Fully assess the safety and AC corrosion risks under steady-state operating conditions on
the powerline.
• Reassess the safe separation distance to minimize arcing risk based on NACE SP0177 and
considering the findings in CEA 239T817.
• Ensure that the separation distance between the pipelines and the powerline structures
exceeds the safe distance required to avoid electrical arcing.
• Design AC mitigation (as required) to ensure that all safety and integrity risks have been
fully mitigated along the collocated pipelines.
• Design monitoring systems to monitor the AC corrosion risks along the pipelines.
• Install and commission the AC mitigation and monitoring systems prior to energization of
DECISION APPROVING CONDITIONAL USE
PERMIT FOR THE SOUTH BELLEVUE SEGMENT
OF THE ENERGIZE EASTSIDE PROJECT, PUGET
SOUND ENERGY, APPLICANT –
FILE NO. 17-120556-LB
Page 29 of 38
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
BELLEVUE HEARING EXAMINER’S OFFICE
450 – 110TH AVENUE NE
P.O. BOX 90012
BELLEVUE, WASHINGTON 98009-9012
the 230 kV powerline.
• After energization, perform a site survey to ensure that all AC interference risks have been
fully mitigated under steady-state operation of the powerline.
Based on the sensitivity analysis performed by DNV GL, it is Stantec’s opinion that any
remaining AC interference risks to the pipeline identified in the detailed design stage of the
project can readily be mitigated via use of standard mitigation strategies. (DSD 004538).
72. The Fieltsch Opinion is largely mirrored in the mitigation measures recommended in
the EIS, at DSD 5712-5715, and the proposed pipeline safety related conditions of approval
(which include about 23 subparts) addressed in the Staff Report at pages 78-80, 134-137 and
143-146.
73. Pipeline safety arguments against the requested permit were not persuasive, as most
all opposition comments based on pipeline coordination and the like are fully addressed in
specific conditions of approval that should serve to improve the overall safety and oversight
of the Olympic pipeline that runs beneath most portions of the existing powerlines.
Opponents did not present any expert testimony to rebut evidence included in the Staff
Report, the FEIS, or witness testimony, which established that specific conditions of approval
can be included as part of this permit to prevent/avoid/mitigate/minimize potential adverse
impacts that could arise due to construction and operation of the powerlines over the Olympic
Pipeline.
74. The pipeline risk analyses provided in the record consistently explain that some of the
highest risks of pipeline ruptures/emergency incidents occur when people are digging or
performing construction work in close proximity to a petroleum pipeline. The Conditions of
Approval recommended for the requested permit should serve to enhance and hopefully
improve public safety by reducing current risks, as the pipeline corridor will be the subject
of strict oversight by city officials and greater public awareness, compared with the
complacency or inattention by residents and regulators that often accompanies conditions that
have gone unchanged for many years, i.e. where an aging petroleum pipeline runs through
neighborhoods beneath high transmission power lines.
Discussion.
75. The Staff Report explains that, with the exception of comments from various agencies
and tribes, virtually all written comments submitted before its issuance opposed or challenged
the pending permit. (DSD 000087). At the public hearing, and in written comments
submitted as part of the public hearing process, the balance of comments was more balanced.
About twenty speakers expressed support for the CUP application, while about thirty people
expressed their opposition. In any event, land use decisions may not be based solely upon
DECISION APPROVING CONDITIONAL USE
PERMIT FOR THE SOUTH BELLEVUE SEGMENT
OF THE ENERGIZE EASTSIDE PROJECT, PUGET
SOUND ENERGY, APPLICANT –
FILE NO. 17-120556-LB
Page 30 of 38
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
BELLEVUE HEARING EXAMINER’S OFFICE
450 – 110TH AVENUE NE
P.O. BOX 90012
BELLEVUE, WASHINGTON 98009-9012
community displeasure. Maranatha Mining v. Pierce County, 59 Wn. App. 795, at 804 (Div.
II, 1990). In Maranatha, the court overturned denial of a permit, because the local agency
disregarded the record before it, basing its decision instead "on community displeasure and
not on reasons backed by policies and standards as the law requires." Maranatha, 59 Wn.
App. at 805.
76. The record in this hearing process includes a reflection of broad support for reliable
and consistent electric service throughout the City of Bellevue.
77. The themes and topics raised in opposition comments from concerned citizens were
fully vetted and analyzed by Staff and consultants who aided in preparation of the multi-year
effort to generate the Final Environmental Impact Statement. Speculation about alternatives
and skepticism about PSE’s study data used to demonstrate “need” for the project is healthy,
and it led to a thorough analysis of almost every substantive comment or suggestion made by
topic throughout the review process. In the end, the City’s independent consultant verified
“need”, and the thorough EIS lays out specific mitigation measures that should apply to the
project, leading Staff to recommend approval, subject to lengthy and detailed conditions of
approval. Written comments about potential view impacts, especially those in the Somerset
neighborhood, were thoroughly analyzed in the Staff Report. Many speakers reiterated their
aesthetic/viewshed concerns at the public hearing, even though the project includes design
changes and conditions of approval intended to address such issues. (See Staff Report, at
page 119, and Finding 83(B) below).
78. Several public comments expressed opposition to the project without reservation, and
discounted all studies, reports, or proposed conditions to the contrary. Again, community
displeasure alone cannot be the basis of a permit denial. Kenart & Assocs. v. Skagit Cy., 37
Wn. App. 295, 303, 680 P.2d 439, review denied, 101 Wn.2d 1021 (1984). Multiple studies
regarding “need” and alternative site analysis are included in the Record. Substantial
evidence in the Record – far more than the preponderance needed – establishes that the
requested permit satisfies all applicable approval criteria. Accordingly, the city code
mandates that the permit shall be approved, subject to conditions.
79. While opposition testimony, presentations, and materials were thoughtful and well-
organized for the most part, none of the individuals testifying at the hearing or submitting
written comments opposing the project offered any persuasive expert reports, studies or other
compelling environmental analysis that would rebut the expert reports, certifications and/or
environmental analyses provided by the applicant, staff, or independent consultants engaged
by the City.
DECISION APPROVING CONDITIONAL USE
PERMIT FOR THE SOUTH BELLEVUE SEGMENT
OF THE ENERGIZE EASTSIDE PROJECT, PUGET
SOUND ENERGY, APPLICANT –
FILE NO. 17-120556-LB
Page 31 of 38
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
BELLEVUE HEARING EXAMINER’S OFFICE
450 – 110TH AVENUE NE
P.O. BOX 90012
BELLEVUE, WASHINGTON 98009-9012
80. The findings, recommendations and conclusions provided in the environmental
documentation submitted on behalf of the applicant, as well as the City’s reviewing
consultant reports, are credible and well-reasoned summaries of complicated regulations,
conditions, possible impacts and appropriate mitigation measures associated with the South
Bellevue Segment proposal. No person or organization presented comparable expert
witnesses or evidence with power transmission system planning, engineering, pipeline safety,
urban planning, design, or other relevant credentials to support opposing views.
81. The Staff Report includes a number of specific findings and conditions that establish
how the pending CUP application satisfies provisions of applicable law and/or can be
conditioned to comply with applicable codes and policies. Except as modified in this
Decision, all Findings contained in the Staff Report for the pending Conditional Use Permit
are incorporated herein by reference as Findings of the undersigned hearing examiner.3
82. In sum, city staff review was robust, thorough, and challenging to the applicant – as
it should be in a project of this scale and impact on local residents. As shown above, real,
substantive changes that will benefit affected parties, the city, and even the applicant, have
been made to the project from its initial conceptual notion to the present as a result of public
feedback, staff review, and exhaustive studies on various aspects of the project.
The application satisfies the City’s decision criteria for a Conditional Use Permit.
83. As noted above, the City’s decision criteria for the pending conditional use permit is
found in LUC 20.30B.140. Unlike the decision criteria specifically applied to electrical
facilities in LUC 20.20.255, the general conditional use permit requirements are the same as
would be applied to any conditional use permit decision. Applying facts and evidence in the
record to the decision criteria for a Conditional Use Permit (found in LUC 20.30B.140.A-E),
the Examiner finds and concludes as follows:
A. The conditional use is consistent with the Comprehensive Plan. Staff Report,
Attachment G, detailed review of Comprehensive Plan – Policy Analysis, addressing more
than 59 Comp. Plan Policies, at DSD 000892-000918; Staff Report, analysis provided on
pages 113-119; Application materials at DSD 000600-617; EIS at DSD 005495, 005502-3;
Testimony of
B. The design is compatible with and responds to the existing or intended character,
appearance, quality of development and physical characteristics of the subject property
3 For purposes of brevity, only certain Findings from the Staff Report are highlighted for discussion in this Decision, and
others are summarized, but any mention or omission of particular findings or analysis provided in the Staff Report should
not be viewed to diminish their full meaning and effect, except as modified herein.
DECISION APPROVING CONDITIONAL USE
PERMIT FOR THE SOUTH BELLEVUE SEGMENT
OF THE ENERGIZE EASTSIDE PROJECT, PUGET
SOUND ENERGY, APPLICANT –
FILE NO. 17-120556-LB
Page 32 of 38
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
BELLEVUE HEARING EXAMINER’S OFFICE
450 – 110TH AVENUE NE
P.O. BOX 90012
BELLEVUE, WASHINGTON 98009-9012
and immediate vicinity. Staff Report, pages 119-120, and pages 133-134, mandating “pole
finishes” to reduce aesthetic impacts, implementing recommendations set forth in Pole
Finishes Report, Attachment J to Staff Report, at DSD 001465-001510; EIS at DSD 005502-
03, 005520, 005525, 005540-5546, 005495, 010303, 010325-26; and application materials
at DSD 000617-618. Because so much testimony came from speakers with concerns about
potential impacts on views in the Somerset neighborhood, the following excerpt from page
119 of the Staff Report is incorporated as findings supporting this decision as it provides a
detailed summary of site-specific changes that have been made in the design to address such
concerns, in addition to a thorough consideration of trees, pole-heights, and pipeline safety
in the Somerset neighborhood:
PSE’s proposal is designed to respond to the existing and intended character appearance, quality
of development, and physical characteristics of the subject property and the immediate vicinity.
Because the Project is sited in an existing corridor shared with another utility (the Olympic
Pipeline system), the Project will not introduce a change in land use. It will consolidate the lines
onto fewer poles, which, although larger, will not increase visual clutter and could reduce it in
some areas. Various pole treatments will be employed to complement the natural environment,
and vegetation management will maintain the general appearance of landscaping in a similar
manner as the present. Although a number of trees will be removed, the remaining and proposed
trees will partially screen views of the taller poles. Likewise, the proposed substation will be
screened by a slope and native vegetation. Reinstallation of telecommunications facilities on the
same transmission facilities following construction will ensure that there will not be an increase
in the number of telecommunications facilities to the maximum extent feasible.
The City’s Comprehensive Plan states that electrical utility facilities should be designed,
constructed, and maintained to minimize the impact on surrounding neighborhoods (UT-8). The
Somerset neighborhood developed around the transmission line corridor, so the increase in height
of the current transmission line is not a new use. In the portion of the existing corridor within the
Somerset neighborhood where the Project will significantly impact neighborhood character (see
Figure 4.2-12 in the Final EIS), the pole design was modified to reduce the necessary height,
using dual monopoles instead of single monopoles preferred in other locations within the corridor.
These modifications to pole design respond to the existing physical characteristics of the
Somerset neighborhood, which has lower building and vegetation heights than other areas of the
corridor. The visual impacts in this area, while considered significant, will not cause blight, as
defined in the Revised Code of Washington (RCW) 35.81.015, or cause substantial dilapidation
or deterioration in this portion of the Somerset neighborhood.
Further modifications to necessary pole heights within the Somerset neighborhood would
increase the number of poles in the neighborhood and result in additional impacts to the character
and appearance of the immediate vicinity. For example, the City requested that PSE provide
additional information regarding pole heights in the Somerset neighborhood as part of the land
use process. The analysis provided in response by PSE indicates that pole heights in the Somerset
neighborhood could, on average, be reduced by around 16 feet. In order to facilitate this further
reduction in pole height, however, the number of poles would more than double (approximately
24 additional poles) and poles would be sited on properties that do not have poles currently
(approximately 17 poles sited on new properties). (PSE 9-21-18).
DECISION APPROVING CONDITIONAL USE
PERMIT FOR THE SOUTH BELLEVUE SEGMENT
OF THE ENERGIZE EASTSIDE PROJECT, PUGET
SOUND ENERGY, APPLICANT –
FILE NO. 17-120556-LB
Page 33 of 38
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
BELLEVUE HEARING EXAMINER’S OFFICE
450 – 110TH AVENUE NE
P.O. BOX 90012
BELLEVUE, WASHINGTON 98009-9012
An increase in the number of poles in the Somerset neighborhood would also impact the physical
characteristics of the corridor and the immediate vicinity because the quantity of excavation
would more than double due to the increased number of poles. Similarly, additional vegetation
impacts, including additional tree removal and fewer replanting options, would occur in the
immediate vicinity of the shorter poles. With taller poles, the conductors are installed with more
sag (i.e., they curve more), so the conductor attachment poles are farther from the ground, which
allows for taller vegetation options. Thus, the increase in pole number required for shorter poles
would result in increased excavation, more tree removal to accommodate the additional poles,
and fewer screening options for both the existing and new pole locations within the corridor.
Shorter poles (or a significant increase in the number of poles) may also increase the potential for
interaction with the co-located Olympic pipeline. While increased EMF levels and potential
interaction with the pipeline are unrelated to the visual impacts to the Somerset neighborhood
identified in the Final EIS, this information does suggest that the current proposal strikes a better
balance.
The Comprehensive Plan lacks policies to protect private residential views. Nevertheless, because
building and vegetation heights are lower in the Somerset neighborhood than other areas of the
corridor due to private covenants, viewer sensitivity in portions of Somerset is higher than in
other areas of the corridor. It is recognized that the contrast between the taller poles proposed by
the Project and the current pole heights in Somerset, combined with high viewer sensitivity, could
cause some Somerset residents to choose to move. However, the entire residential community
surrounding the transmission line has been built next to the existing corridor, and the Project, as
modified, is consistent with and responds to the existing or intended character, appearance,
quality of development, and physical characteristics the Somerset community. Despite the visual
impacts identified in the Final EIS, the Somerset neighborhood will continue to be a healthy,
vibrant, and unique community. With the Conditions of Approval specified below for aesthetic
impacts and vegetation management, the Project is consistent with LUC 20.30B.140.B.
C. The conditional use will be served by adequate public facilities including streets,
fire protection, and utilities. On this topic, there was minimal, if any, material dispute that
this criterion has been fully satisfied. Staff Report, pages 121-122, and discussion of relevant
technical reviews on the subject that appears on pages 70-73; Application materials at DSD
000618-621; EIS at 005420.
D. The conditional use will not be materially detrimental to uses or property in the
immediate vicinity of the subject property. Staff Report at 121-122; Application materials
at DSD 000618-621; EIS at DSD 005502-3, 005525, 005540-5546, 005495.
E. The conditional use complies with the applicable requirements of this Code. As
conditioned, the pending Conditional Use Permit application meets the applicable
DECISION APPROVING CONDITIONAL USE
PERMIT FOR THE SOUTH BELLEVUE SEGMENT
OF THE ENERGIZE EASTSIDE PROJECT, PUGET
SOUND ENERGY, APPLICANT –
FILE NO. 17-120556-LB
Page 34 of 38
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
BELLEVUE HEARING EXAMINER’S OFFICE
450 – 110TH AVENUE NE
P.O. BOX 90012
BELLEVUE, WASHINGTON 98009-9012
performance standards and requirements included in the City’s Land Use Code; Staff Report,
page 122, and pages 107-113; Application materials at DSD 000621.
The application satisfies the City’s additional criteria for Electrical Utility Facilities.
84. Because the proposal is to construct or expand electrical facilities, the provisions of
the City’s Land Use Code specifically addressing Electrical Utility Facilities, found in LUC
20.20.255, must be satisfied. Prior to submittal of any Conditional Use Permit application, a
detailed Alternative Siting Analysis was required. See LUC 20.20.255.D. Applying the facts
and evidence in the record to the additional requirements for new or expanding electrical
utility facilities, as detailed in LUC 20.20.255.E.1-6 and .F, the Examiner finds and concludes
as follows:
A. Re: 255.E.1. The proposal is consistent with Puget Sound Energy’s System Plan.
Testimony of PSE Manager of System Planning, Jens Nedrud; Staff Report at pages 107-108;
Application materials at DSD 000621, which reads in relevant part as follows: “The need
for additional 230 kV capacity in the Eastside region was identified, and has been included
in PSE’s Electrical Facilities Plan for King County (“Plan”), since 1993. As explained in
the Plan, “[t]he 230 kV sources for the 115 kV system in northeast King County are primarily
the Sammamish and Talbot Hill substation. The loads on the 230-115 kV transformers in
these stations will be high enough to require new sources of transformation.” Additionally,
the “Lakeside 230 kV Substation project [now referred to as Energize Eastside] will rebuild
two existing 115 kV lines to 230 kV between Sammamish and Lakeside [where PSE proposes
the construction of the Richards Creek substation], and between Lakeside and Talbot Hill.”
B. Re: 255.E.2. The design, use, and operation of the electrical utility facility complies
with applicable guidelines, rules, regulations or statutes adopted by state law, or any
agency or jurisdiction with authority. Staff Report at pages 108-109; Application
materials at DSD 000621-622; Testimony of Ms. Koch.
C. Re: 255.E.3. The applicant demonstrated that an operational need exists that
requires the location or expansion at the proposed site. Staff Report at pages 109-111,
noting that between 2012 and 2015, PSE and the City commissioned three separate studies
confirming the need to address Eastside transmission capacity. The Staff Report relies on
the analysis in the USE Report verifying operational need, and the entire USE Report, and
the other studies commissioned by PSE on the subject of need, are attached to the Staff Report
and included in the Record for this matter. See DSD 000663-739, the “USE” Report,
commissioned by the City. The review on “need” went further, as an independent electrical
system planning and engineering consultant (Stantec) reviewed PSE’s needs assessment as
DECISION APPROVING CONDITIONAL USE
PERMIT FOR THE SOUTH BELLEVUE SEGMENT
OF THE ENERGIZE EASTSIDE PROJECT, PUGET
SOUND ENERGY, APPLICANT –
FILE NO. 17-120556-LB
Page 35 of 38
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
BELLEVUE HEARING EXAMINER’S OFFICE
450 – 110TH AVENUE NE
P.O. BOX 90012
BELLEVUE, WASHINGTON 98009-9012
part of the EIS process and found PSE’s assessment “very thorough” and concluded that
PSE had followed standard industry practice. See DSD 004521-4531, the Stantec Report.
The Staff Report explains that the City’s Comprehensive Plan shows a potential need to
expand both the transmission line and the Lakeside substation [the “Richards Creek
substation”), which are the two parts of the pending CUP application. See Comp. Plan Map
UT-7, at DSD 000891, showing general locations and conceptual alignments for PSE’s
planned facilities in the City of Bellevue. See Finding 84(F), below.
D. Re: 255.E.4. The applicant demonstrated that the proposed electrical utility facility
improves reliability to the customers served and reliability of the system as a whole, as
certified by the applicant’s licensed engineer. Same as item C, above; Testimony of Mr.
Nedrud, a Washington State licensed engineer and PSE’s Manager of System Planning; Mr.
Nedrud’s July 20, 2017 reliability certification letter to Ms. Bedwell, the City’s
Environmental Planning Manager, referenced at page 111 of the Staff Report, included in
the record at DSD 000661-662; Staff Report discussion on page 111; Application materials
at pages 000623-626; EIS at DSD 005438, 005413-15, 011102-5, and 011168-70.
E. Re: 255.E.5.a. Because the proposal is located on sensitive sites as referenced in
Figure UT.5a (now Map UT-7) of the Utility Element of the Comprehensive Plan, the
applicant fully complied with the Alternative Siting Analysis requirements of LUC
20.20.255.D. Staff Report, pages 41-44 and 111-113; Application materials at DSD 000623
and 626; DSD 011049-747, Ph. 1 Draft EIS, evaluating technological alternatives; DSD
010205-11048, Ph. II Draft EIS, evaluating siting alternatives. See entire Alternative
Sighting Analysis included as Attachment “B” to the Staff Report, at DSD 000222-597. See
Findings 59 and 60 above, and Finding and Conclusion No. 6 in the CALUP issued for this
proposal.
F. Re: 255.E.5.b. Where feasible, the preferred site alternative is located within the land
use district requiring additional service and residential land use districts are avoided
when the proposed new or expanded electrical utility facility serves a nonresidential
land use district. As explained in the five separate studies performed by four separate
parties confirming the need to address Eastside transmission capacity – 1) Electrical
Reliability Study by Exponent, 2012 (City of Bellevue); 2) Eastside Needs Assessment Report
by Quanta Services, 2013 (PSE); 3) Supplemental Eastside Needs Assessment Report by
Quanta Services, 2015 (PSE); 4) Independent Technical Analysis by Utility Systems
Efficiencies, Inc. (“USE”), 2015 (City of Bellevue); and 5) Review Memo by Stantec
Consulting Services Inc., 2015 (EIS consultant), all of which are provided in the Alternative
Siting Analysis – PSE’s proposed transmission line upgrade is responsive to projected
growth in the Eastside generally and the City of Bellevue specifically. Even if the City’s code
could be read to require electrical facilities to only locate in areas that benefit or need the
DECISION APPROVING CONDITIONAL USE
PERMIT FOR THE SOUTH BELLEVUE SEGMENT
OF THE ENERGIZE EASTSIDE PROJECT, PUGET
SOUND ENERGY, APPLICANT –
FILE NO. 17-120556-LB
Page 36 of 38
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
BELLEVUE HEARING EXAMINER’S OFFICE
450 – 110TH AVENUE NE
P.O. BOX 90012
BELLEVUE, WASHINGTON 98009-9012
new or expanded electrical facility in question, in this situation, that is precisely what is
proposed, because “load-shedding” – i.e. rolling blackouts – is currently part of PSE’s
corrective action plan (CAP) options in neighborhoods throughout the Eastside, including
residential neighborhoods that are located along the route of the South Bellevue Segment.
Given these circumstances, there truly is a critical “need” for the project to prevent such
problems going forward in the residential land use districts located along the route.
G. Re: 255.E.6. The proposal, as conditioned, will provide mitigation sufficient to
eliminate or minimize long-term impacts to properties located near an electrical utility
facility. Staff Report, at page 113, and Conditions of Approval on pages 124-146. Mitigation
measures and conditions include requirements to address impacts related to visual impact,
tree and vegetation removal, pipeline safety, historic and cultural resource protection,
among other things. See full discussion of mitigation measures, conditions and requirements
provided in Sections III, IV, V, VI, VIII, and X of the Staff Report. DSD 000626, 001745-
3477,003528-3541 (re: vegetation and trees); DSD 003582-3626 (re: pole color); DSD
003629-63 (re: cultural resources); DSD 003664-72 (re: substation mitigation plan); EIS at
DSD 005424-33 (re: impact summary and mitigation options), and DSD 005696 (re:
proposed AC interference mitigation).
H. Re: 255.F. The proposal, as conditioned, complies with the additional design
standards that apply to projects to locate or expand electrical utility facilities. Staff
Report, pages 44-47, describing how project has been designed or can be conditioned to
comply with specific design standards, including without limitation those addressing site
landscaping, fencing, setbacks, and height; application materials at DSD 000626-628.
85. The Conditions of Approval included as part of this Decision are reasonable,
appropriate, fully supported by testimony and evidence in the record, and capable of
accomplishment.
//
//
//
DECISION APPROVING CONDITIONAL USE
PERMIT FOR THE SOUTH BELLEVUE SEGMENT
OF THE ENERGIZE EASTSIDE PROJECT, PUGET
SOUND ENERGY, APPLICANT –
FILE NO. 17-120556-LB
Page 37 of 38
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
BELLEVUE HEARING EXAMINER’S OFFICE
450 – 110TH AVENUE NE
P.O. BOX 90012
BELLEVUE, WASHINGTON 98009-9012
VI. CONCLUSIONS of LAW.
1. As explained above, the record includes credible, unrebutted, and substantial proof
that the Conditional Use Permit application satisfies all applicable decision criteria specified
in applicable city LUC 20.30B.140, as conditioned herein.
2. Similarly, the record includes credible, unrebutted, and substantial proof that the
proposal satisfies the additional criteria for Electrical Utility Facilities, set forth in LUC
20.20.255, as conditioned herein.
3. Based on the record, and all findings set forth above, the applicant established that
more than a preponderance of the evidence supports the conclusion that its permit application
merits approval, meeting its burden of proof imposed by LUC 20.35.340(A).
4. Any finding or other statement contained in this Decision that is deemed to be a
Conclusion of Law is hereby adopted as such and incorporated by reference.
VII. DECISION.
Based on the record, and for the reasons set forth herein, the requested Conditional
Use Permit for the South Bellevue Segment of the Energize Eastside Project should be and
is hereby approved, subject to the following conditions of approval, which are incorporated
herein by reference.
ISSUED this 25TH Day of June, 2019
_____________________________
Gary N. McLean
Hearing Examiner
Attachments: Conditions of Approval, 20 pages; and
Exhibit List.
DECISION APPROVING CONDITIONAL USE
PERMIT FOR THE SOUTH BELLEVUE SEGMENT
OF THE ENERGIZE EASTSIDE PROJECT, PUGET
SOUND ENERGY, APPLICANT –
FILE NO. 17-120556-LB
Page 38 of 38
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
BELLEVUE HEARING EXAMINER’S OFFICE
450 – 110TH AVENUE NE
P.O. BOX 90012
BELLEVUE, WASHINGTON 98009-9012
NOTICE OF RIGHTS
TO REQUEST CLARIFICATION OR RECONSIDERATION,
AND TO APPEAL
This Decision has been issued by the Hearing Examiner who has specific authority to address
Type I quasi-judicial matters following a public hearing. See LUC 20.35.100.
REQUEST FOR CLARIFICATION OR RECONSIDERATION – As provided in Rule 1.25 and 1.26 of
the Bellevue Hearing Examiner Rules of Procedure, a party may file a written request for
clarification or reconsideration of this Decision within five (5) working days after the date of
issuance. Additional requirements and procedures concerning Requests for Clarification or
Reconsideration are found in Rule 1.25 and 1.26 of the Hearing Examiner Rules of Procedure.
RIGHT TO APPEAL – TIME LIMIT – Persons and entities identified in Land Use Code (LUC)
20.35.150, may appeal a Process I decision of the Hearing Examiner to the Bellevue City
Council by filing a written statement of the Findings of Fact or Conclusions of Law which
are being appealed, and paying a fee, if any, as established by ordinance or resolution, no
later than 14 calendar days following the date that the decision was mailed. The written
statement must be filed together with an appeal notification form, available from the City
Clerk. The written statement of appeal, the appeal notification form, and the appeal fee, if
any, must be received by the City Clerk no later than 5:00 p.m. 14 calendar days following
the date that the decision was mailed. (Because this Decision has been mailed on June
25, 2019, the appeal deadline is July 9, 2019).
TRANSCRIPT OF HEARING – PAYMENT OF COST – An appeal of the Hearing Examiner’s
decision requires the preparation of a transcript of the hearing before the Hearing Examiner.
Within thirty (30) days of the decision which is appealed from, the appellant shall order from
the City Clerk, on a form provided by the Clerk, a full transcript of the hearing before the
Hearing Examiner. At the time the order for transcription is placed, the appellant shall post
security in the amount of One Hundred Dollars ($100.00) for each hearing hour to be
transcribed. If appellant fails to post security, the appeal shall be considered abandoned.
Additional requirements and procedures concerning appeals filed with the Council are found
at Resolution 9473 and in the City of Bellevue Land Use Code.
Seattle King County Realtors
David Crowell
12410 SE 32nd St, Suite 100
Bellevue, WA 98005
Joseph Eschbach
4915 145th Ave SE
Bellevue, WA 98006
Grace Drone
13715 SE 58th PL
Bellevue, WA 98006
David Schwartz
12218 NE 64th St
Kirkland, WA 98033
Julie Beffa
9110 NE 21st Pl
Clyde Hill, WA 98004
Stanislav Rumega
13225 SE 51st PL
Bellevue, WA 98006
Sue Meyers
4727 136th PL SE
Bellevue, WA 98006
William & Margaret Moore
4707 135th PL SE
Bellevue, WA 98006
Anna Ceberio-Verghese
18524 SE 60th St
Issaquah, WA 98027
Tom and Kristi Weir
4639 133rd Ave SE
Bellevue, WA 98006
Esther and Robert Moloney
4551 135th PL SE
Bellevue, WA 98006
Mick Tish
13432 NE 25th St
Bellevue, WA 98005
Jeffrey Hughes
15803 SE 3rd St
Bellevue, WA 98008
Susan Corscadden
16297 SE 63rd St
Bellevue, WA 98006
Marilyn Mayers
1907 161 Ave NE
Bellevue, WA 98008
Sarah Powers
15938 SE 43rd St
Bellevue, WA 98006
Carolyn Janisch
12131 SE 16th PL
Bellevue, WA 98005
Randy Tada
4716 Somerset PL SE
Bellevue, WA 98006
Dave and Denise Mickelson
4518 Somerset Dr SE
Bellevue, WA 98006
Craig A. Foreman
10400 NE 4th St., Suite 2500
Bellevue, WA 98004
Simon Sun
SE 51st PL
Bellevue, WA 98006
Paula Doe
5011 Somerset Dr SE
Bellevue, WA 98006
Karen and Sam Esayian
4601 - 135th Ave SE
Bellevue, WA 98006
Bruce Williams
8564 129th Avenue SE
Newcastle, WA 98056
Rob Lanzafame
1843 173rd Ave NE
Bellevue, WA 98008
Elizabeth Olson
13809 SE 20th St
Bellevue, WA 98005
Bill Picatti
5245 Highland Dr
Bellevue, WA 98006
Jo Sentell
203 168th Ave NE
Bellevue, WA 98008
Claudia Mansfield
5837 Pleasure Point Lane
Bellevue, WA 98006
Mike Roser
4615 133rd AVE SE
Bellevue, WA 98006
Linda Young
12813 SE 80th Way
Newcastle, WA 98056
Kirkland Chamber of Commerce /
Samantha St. John
440 Central Way
Kirkland, WA 98033
Loan Tong & Doug Kendall
13308 SE 44th PL
Bellevue, WA 98006
Natalie Duryea
12825 NE 32nd St
Bellevue, WA 98005
Amy Faith
15210 NE 8th St., Unit D
Bellevue, WA 98007
Sung Eun Park
1506 Pierce Ave NE
Renton, WA 98056
Grant Keeney
14411 SE 47th PL
Bellevue, WA 98006
Margaret Hager
905 243rd St SW
Bothell, WA 98021
Michael Todd Davis
4942 131st PL SE
Bellevue, WA 98006
Michael and Tracia Wong
8308 128th Ave SE
Newcastle, WA 98056
Lisle Steelsmith
904-146th Ave SE
Bellevue, WA 98007
Jeff Callison
1805 136th PL SE
Bellevue, WA 98005
Bert He
4405 138th Ave SE
Bellevue, WA 98006
Kristi Tripple/Rowley Properties
1595 NW Gilman Blvd, Ste 1
Issaquah, WA 98027
Jessica Erskine
1861 140th Ave SE
Bellevue, WA 98005
Joy Zhao
7050 166th Way SE
Bellevue, WA 98006
Kelly Snyder/UW Bothell
Box 358500 18115 Campus Way NE
Bothell, WA 98011-8246
Joan Nolan
4700 133rd Ave SE
Bellevue, WA 98006
Linda Gray
22629-78th Ave SE
Woodinville, WA 98072
Brian & Claire Dahlquist
4944 127th PL SE
Bellevue, WA 98006
Tammy Alford
8 Newport Key
Bellevue, WA 98006
Li Yu
13800 SE Newport Way
Bellevue, WA 98006
Brian Brand
10801 Main St., #110
Bellevue, WA 98004
Curt Allred & Barbara Braun
13609 SE 43rd PL
Bellevue, WA 98006
Benjamin & Megan Larson
4447 137th Ave SE
Bellevue, WA 98006
Rob Karlinsey/City of Kenmore
18120 68th Ave NE
Kenmore, WA 98028
Greg Johnson/ Wright Runstad & Co.
1201 Third Ave Ste 2700
Seattle, WA 98101
Amy Carlson
Jacobs Engineering Group
1100 112th Ave NE, Ste 500
Bellevue, WA 98004
Jonathan Kurz
13208 SE 49th St
Bellevue, WA 98006
Keith Mok
5918 128th Ave SE
Bellevue, WA 98006
John Davis
13224 SE 49th St
Bellevue, WA 98006
Mike Hubbard
601 Union #3015
Seattle, WA 98101
Heather Pierce/RHAWA
2414 SW Andover St, #D207
Seattle, WA 98106
Alison Dildine
8455 128th Ave SE
Newcastle, WA 98056
Karin Morgan
12427 NE 29th St
Bellevue, WA 98005
Brittany Caldwell
Bothell/Kenmore Chamber of Commerce
PO Box 1203
Bothell, WA 98041
Eldon Graham
13629 SE 20th St
Bellevue, WA 98005
Sirisha Dontireddy & Krishna Nareddy
4617 135th PL SE
Bellevue, WA 98006
Joshua Chau
13218 SE 51st PL
Bellevue, WA 98006
Judy Boyce
4932 131st PL SE
Bellevue, WA 98006
Craig Glazier
Urban Renaissance Group
3245 146th PL SE
Bellevue, WA 98007
David Huang
4525 132nd Ave SE
Bellevue, WA 98006
Fiona Cofield
516 157th Ave SE
Bellevue, WA 98008
Jane Kim
4425 137th Ave SE
Bellevue, WA 98006
Steve Wagner
13440 NE 45th St.
Bellevue, WA 98005
Nancy Shimeall
6634 159th Ave NE
Redmond, WA 98052
Anne Kim
4460 141 St Ave SE
Bellevue, WA 98006
Beth Asher
436 Mill Ave S
Renton, WA 98057
Pat McGiffert
13621 NE 42nd St
Bellevue, WA 98005
Oleg Ryabukha
324 102nd Ave SE, #401
Bellevue, WA 98004
Caroline Callender
3962 153rd Ave SE
Bellevue, WA 98006
Jennifer Wilson
14312 SE 45th St
Bellevue, WA 98006
Gary Luhm
9433 NE 129th PL
Kirkland, WA 98034
Don Marsh
4411 137th Ave SE
Bellevue, WA 98006
Qing Ye
4728 Somerset Ave SE
Bellevue, WA 98006
Michelle Molan
13805 SE 58th PL
Bellevue, WA 98006
Russell Borgmann
2100 120th PL SE
Bellevue, WA 98005
Marc & Jeanette DeBenedictis
13719 SE 17th St
Bellevue, WA 98005
Fang Cui
4543 135th Ave SE
Bellevue, WA 98006
Van Duong
4654 144th PL SE
Bellevue, WA 98006
Kathy Judkins
4324 136th PL SE
Bellevue, WA 98006
Paul Shah
13413 NE 27th St
Bellevue, WA 98005
Shane & Dana Burke
2103 138th Ave SE
Bellevue, WA 98005
Maya Keselman
4586 144th Ave SE
Bellevue, WA 98006
Sue Stronk
12917 SE 86th PL
Newcastle, WA 98056
Liping Ke
4670 144th PL SE
Bellevue, WA 98006
Melanie Sprague
13430 SE 43rd PL
Bellevue, WA 98006
Meredith Shank
9089 NE 39th PL
Yarrow Pt, WA 98004
Bo Li
4911 136th PL SE
Bellevue, WA 98006
Steve Hoffmann/GLY
200 - 112th Ave NE #300
Bellevue, WA 98004
Ann Brashear
5254 116th Ave SE
Bellevue, WA 98006
Mike Evered
4502 Somerset Blvd SE
Bellevue, WA 98006
William Kastner
Ross Jacobson & Josephine Vestal
601 Union St., Suite #4100
Seattle, WA 98101
Lindy Bruce
13624 SE 18th St
Bellevue, WA 98005
Ying Huang
5745 145th Ave SE
Bellevue, WA 98006
Helen Jiang
4673 174th Ave SE
Bellevue, WA 98006
William & Sally Herling
13825 Somerset Ln SE
Bellevue, WA 98006
Jin Tang
14001 SE 45th CT
Bellevue, WA 98006
Daniel, Brian & Lori Elworth
8605 129th Ct SE
Newcastle, WA 98056
Sandra Clea
25113 NE 108th St
Redmond, WA 98053
Hansen
3851 136th Ave NE
Bellevue, WA 98005
Rod Fleck
4817 134th PL SE
Bellevue, WA 98006
Lynn Ang
4408 Somerset Blvd SE
Bellevue, WA 98006
Naomi Chubay
12624 SE 61st St
Bellevue, WA 98006
Mary Dahlquist
4944 127th PL SE
Bellevue, WA 98006
Jessica Yeung
2627 153rd Ave SE
Bellevue, WA 98007
Honglian Gao
14205 SE 49th PL
Bellevue, WA 98006
Lisa Wyler
13421 NE 47th St
Bellevue, WA 98005
Rob Reifsnyder/PACCAR
777 106th Ave NE
Bellevue, WA 98004
Yanfen Fu
4441 145 Ave SE
Bellevue, WA 98006
Qinghui Liu & Min Chen
3814 139th Ave SE
Bellevue, WA 98006
Eric and Diana Ivarson
4503 141st Ave SE
Bellevue, WA 98006
Anne Watkins
6423 SE Cougar Mtn Way
Bellevue, WA 98006
Suet Young Pun & Kwok Man Lee
4551 135th Ave SE
Bellevue, WA 98006
Kristin Nasman
40 Orcas Key
Bellevue, WA 98006
Judith Reavell
13601 NE 34th PL
Bellevue, WA 98005
Meghan Wright/Su Development
10608 NE 2nd St, Ste. 202
Bellevue, WA 98004
Matt & Michele Brown-Ruegg
4570 Somerset Blvd SE
Bellevue, WA 98006
Deron Ferguson
4649 137th Ave NE
Bellevue, WA 98005
Gabriele Neighbors
1106 108th Ave N, Apt 502
Bellevue, WA 98004
Theresia McLynne
4643 147th PL SE
Bellevue, WA 98006
Huatong Sun
14225 SE 60th St
Bellevue, WA 98006
Leslie Geller
15102 SE 43rd St.
Bellevue, WA 98006
John Merrill
4800 134th PL SE
Bellevue, WA 98006
Jody Noerenberg
3917 Meadow Ave N
Renton, WA 98056
Dave Osmer
2307 129th Ave SE
Bellevue, WA 98005
Kathleen Sherman
4741 132nd Ave SE
Bellevue, WA 98006
Ingrid Turner
12512 SE 52nd St
Bellevue, WA 98006
Zoe Qiu
604 109th Ave SE
Bellevue, WA 98004
Leslee Jaquette
71 158th PL SE
Bellevue, WA 98008
Frank van der Harst
16652 SE 14th St
Bellevue, WA 98008
Bill and Margie Stewart
2240 135th PL SE
Bellevue, WA 98005
Joan Sinclair
4510 144th Ave SE
Bellevue, WA 98006
Qi Zhao
13401 NE 12th PL
Bellevue, WA 98005
Vincent Gao & Fay Wang
4727 132nd Ave SE
Bellevue, WA 98006
Andrea Wohlan
13240 SE 43rd St
Bellevue, WA 98006
Tess Martinovic
16505 SE 28th St
Bellevue, WA 98008
Zhixin Liu
13806 SE Newport Way
Bellevue, WA 98006
Jennifer MacDonald
5716 141st PL SE
Bellevue, WA 98006
Monica L
12819 SE 38th St
Bellevue, WA 98006
Margie Hussey
4700 132nd Ave SE
Bellevue, WA 98006
James & Chris Mantell
4215 187th Ave SE
Issaquah, WA 98027
Laura Fuller
475 155th PL SE
Bellevue, WA 98007
Aaron Hoard
University of Washington
218 Gerberding Hall
Seattle, WA 98195
Chris Johnson
Bellevue Chamber of Commerce
330 112th Ave NE #100
Bellevue, WA 98004
Geraldine Scanlan
13720 SE 58th PL
Bellevue, WA 98006
Sean & AnnLee Cox
4538 Somerset Dr SE
Bellevue, WA 98006
Kevin Milliken
6385 138th PL SE
Bellevue, WA 98006
Elaine Saito
16143 SE Newport Way
Bellevue, WA 98006
Heather Van Schoiack
4425 153rd Ave SE
Bellevue, WA 98006
Allison Shearer
16388 SE 48th Drive
Bellevue, WA 98006
Keith Hu and Lynn Ang
4408 Somerset Blvd SE
Bellevue, WA 98006
Jingdong Yu
4501 138th Ave SE
Bellevue, WA 9800allr
Jerron & Jolene Marshall
4531 Somerset PL SE
Bellevue, WA 98006
Roger Anderson
16561 SE 18th St
Bellevue, WA 98008
Colin Radford Radford & Co
10423 Main St.
Bellevue, WA 98004
Barry Zimmerman
5007 Somerset Dr SE
Bellevue, WA 98006
Courtney Hirschi
12040 NE 128th
Kirkland, WA 98034
John and Marilyn Hancock
14209 Se 45th St
Bellevue, WA 98006
Chit Saw
13809 SE 51st PL
Bellevue, WA 98006
Bernie Dochnahl
13200 Lake Kathleen Road SE
Renton, WA 98059
Kevin Steil
6505 128th Ave SE
Bellevue, WA 98006
Michael Lampi
2667 170th SE
Bellevue, WA 98008
Robert Wallace
5323 154th AVE SE
Bellevue, WA 98006
Janis Medley
4609 Somerset Dr SE
Bellevue, WA 98006
Sidonie De Cassis
13025 SE 21st PL
Bellevue, WA 98005
Todd Andersen
4419 138th Ave SE
Bellevue, WA 98006
Yvonne Pipkin
1120 N 38th St.
Renton, WA 98056
Christina Aron-Sycz
13725 NE 34th PL
Bellevue, WA 98005
Steve Oleson
4548 138th Ave SE
Bellevue, WA 98006
Warren Halverson
13701 NE 32nd PL
Bellevue, WA 98005
Haley Jacobson
10610 NE 9th PL
Bellevue, WA 98004
Sue Sander
4701 139th Ave SE
Bellevue, WA 98006
Norman Hansen
3851 136th Ave NE
Bellevue, WA 98005
Rich Wagner
10801 Main Street
Bellevue, WA 98004
Russell Joe
1600 124th Ave
Bellevue, WA 98005
Steve Funk
13560 Main Street
Bellevue, WA 98005
Robert Shay
610 123rd Ave NE
Bellevue, WA 98005
Katherine Ma
13912 SE 44th St
Bellevue, WA 98006
Michael Kahn
223 140th Ave NE
Bellevue, WA 98005
David Townsend
16579 SE 49th St
Bellevue, WA 98006
Bill Finkbeiner
401 Lake Ave W
Kirkland, WA 98033
Josh Sutton
14230 Bel-Red Road
Bellevue, WA 98007
Harvey Ries
13501 NE 38th PL
Bellevue, WA 98005
Vicki Baxter
625 S 4th St
Renton, WA 98057
Jim Hill/Kemper Development
575 Bellevue Way NE
Bellevue, WA 98004
TJ Woosley
PO Box 3325
Bellevue, WA 98009
Steve Kasner
1015 148th PL SE
Bellevue, WA 98007
Russell Borgman
2100 120th PL SE
Bellevue, WA 98005
Brian Derdowski
15642 SE Newport Way
Bellevue, WA 98006
Gloria Northcroft
5015 145th PL SE
Bellevue, WA 98006
Francis Bruehler
4562 150th Ave SE
Bellevue, WA 98006
Heather Trescases
15303 SE 49th St
Bellevue, WA 98006
Heidi Dean
11661 SE 56th St
Bellevue, WA 98006
Kathleen Ossenkop
3316 NE 12th St
Renton, WA 98056
Jennifer Keller
115 – 146th Ave SE
Bellevue, WA 98007
Ron Jaeger
13297 SE 54th PL
Bellevue, WA 98006
Sharmila Swanson
777 108th Ave N, #1200
Renton, WA 98056
Rick Kaner
6025 Hazelwood Ln SE
Bellevue, WA 98006
Jennifer Fischer
18021 SE 40th PL
Bellevue, WA 98008
Todd Langrom
22219 NE 12th PL
Sammamish, WA 98074
Richard Lauckhart
44475 Clubhouse Drive
El Macero, CA 95618
Matt McFarland/Cheryl Zakrzewski
City of Bellevue/City Attorney’s Office
PO Box 90012
Bellevue, WA 98009-9012
Kate Sayers
832 170th PL
Bellevue, WA 98008
Bob Gillespie
731 97th Ave SE
Bellevue, WA 98004
Rick Aramburu
720 3rd Ave, Suite 2000
Seattle, WA 98104
Gloria Thompson
13917 SE 42nd St
Bellevue, WA 98006
Irene Plenefiesch
Microsoft Corp.
One Microsoft Way
Redmond, WA 98052
Larry Johnson
8505 129th Ave SE
Newcastle, WA 98056
Leslie Smith
505 5th Ave S, Suite 400
Seattle, WA 98104
Stacey Graven
9321 NE 26th St
Clyde Hill, WA 98004
Steve O’Donnell
13526 SE 52nd St
Bellevue, WA 98006
Tom Gilchrist
600 106th AVE NE, Suite 200
Bellevue, WA 98004
Barry Alavi
10242 NE 65th St
Kirkland, WA 98033
Jeanne DeMund
2811 Mountain View Ave N
Renton, WA 98056
Betty Lou Kapela
5652 132nd Ave NE
Bellevue, WA 98005
Patricia Akiyama
Master Builders Association
335 116th Ave SE
Bellevue, WA 98004
Priya Talreja
4421 138th Ave SE
Bellevue, WA 98006
Patrick Bannon
Bellevue Downtown Association
400 108th Avenue, Suite 110
Bellevue, WA 98004
Joy Miller Paltiel
13615 SE 58th PL
Bellevue, WA 98006
Deborah Fox Sogge
Sammamish Chamber of Commerce
704 228th Avenue NE, #123
Sammamish, WA 98074
Laurie Tolkin
706 99th Ave NE, Unit 706
Bellevue, WA 98004
David Namura
CenturyLink
1600 7th Ave
Seattle, WA 98191
Erin Anderson/ Sara Leverette
Van Ness Feldman
719 Second Ave, Suite 1150
Seattle, WA 98104
Conditions of Approval,
PSE South Bellevue Segment
– CUP File No. 17-120556-LB
Page 1 of 20
CONDITIONS OF APPROVAL
For the
South Bellevue Segment
of PSE’s Energize Eastside Project
File No. 17-120556-LB
*(NOTE: Conditions imposed as part of the unchallenged Critical Areas Land Use Permit
issued for the project in File No. 17-120557-LO are also included)
AA. General Conditions added by the Hearing Examiner.
1. The Project addressed in this permit is known as the South Bellevue Segment of PSE’s
Energize Eastside Project, specifically including construction of a new “Richards Creek” substation
and upgrading 3.3 miles of existing 115 kV transmission lines with 230 kV lines between the
existing Lakeside substation and the southern city limits of Bellevue, as described in the Staff
Report and depicted in Project Plans, included as Attachment A to the Staff Report.
2. The applicant, PSE, shall be responsible for consulting with all other state, federal, local,
or regional agencies, and/or tribal entities with jurisdiction (if any) for applicable permit or other
regulatory requirements that pertain to any aspect of the project addressed in this permit. Any
conditions of other regulatory agency permits/licenses/approvals issued for any aspect of the
project shall be considered conditions of approval for this Project.
3. Compliance with these Conditions of Approval shall be reflected on all plans and
supporting documentation submitted for construction permits and design review approvals required
by the City in connection with this project.
4. PSE shall comply with all applicable Bellevue City Codes, Standards, and Ordinances in
effect at the time of filing a complete application for any permit or approval required by the City,
including without limitation the following development regulations:
Clearing & Grading Code – BCC 23.76
Fire Code – BCC 23.11
Land Use Code – BCC Title 20
Noise Control Code – BCC 9.18
Transportation – BCC 14.60
Transportation ROW – BCC 11.70 & 14.30
Utilities Codes – BCC Title 24
Conditions of Approval,
PSE South Bellevue Segment
– CUP File No. 17-120556-LB
Page 2 of 20
A. GENERAL CONDITIONS based on recommendations in Staff Report.
1. CHANGES TO POLE LOCATION AND/OR ALIGNMENT: Changes to the pole location and/or
alignment submitted as part of this Conditional Use application shall be reviewed as a Land Use
Exemption to this Conditional Use approval prior to construction.
AUTHORITY: LUC 20.30B.175
REVIEWER: Heidi Bedwell, Land Use
2. CONCEPTUAL DESIGN UTILITIES: Utility Department approval of the subject permits is
based on the conceptual design only. Changes to the site layout may be required to accommodate
the required utilities after utility engineering is approved.
AUTHORITY: BCC Title 24.02, 24.04, 24.06
REVIEWER: Arturo Chi, Utilities
3. CLEARING AND GRADING PERMIT REQUIRED: An application for a clearing and grading
permit must be submitted and approved before construction can begin. Plans submitted as part of
any permit application shall be consistent with the activity permitted under this approval.
AUTHORITY: LUC 20.30P.140; BCC 23.76.035 (Clearing & Grading Code)
REVIEWER: Thomas McFarlane, P.E.; Bellevue Development Services;
Clearing & Grading Section
4. UTILITY PERMIT AND/OR UTILITY DEVELOPER EXTENSION AGREEMENTS: The water,
sewer, and storm drainage systems shall be designed per current City of Bellevue Utility Codes and
Utility Engineering Standards. All design review, plan approval, and field inspection shall be
performed under the individual permits and/or Utility Developer Extension Agreements depending
on the extent of the work.
AUTHORITY: BCC Title 24.02, 24.04, 24.06
REVIEWER: Arturo Chi, Utilities
5. SIGHT DISTANCE: All structures installed under terms of this proposal must meet the
City’s sight distance requirements.
AUTHORITY: BCC 14.60.240, 14.60.241; Transportation Design Manual
(RL-100-1, RL-110-1, RL-120-1).
REVIEWER: Fay Schafi, (425) 452-4574
Conditions of Approval,
PSE South Bellevue Segment
– CUP File No. 17-120556-LB
Page 3 of 20
B. Conditions that apply prior to issuance of any Building, Engineering, or Clearing and Grading
Permits.
1. RIGHT-OF-WAY USE PERMIT: Prior to issuance of any construction or clearing and grading
permit, the applicant shall apply for required right-of-way use permits from the City’s Transportation
Department, which may include:
• Designated truck hauling routes.
• Truck loading/unloading activities.
• Location of construction fences.
• Hours of construction and hauling.
• Requirements for leasing of right of way or pedestrian easements.
• Provisions for street sweeping, excavation and construction.
• Location of construction signing and pedestrian detour routes.
• All other construction activities as they affect the public street system.
In addition, the applicant shall submit for review and approval a plan for providing pedestrian access during
construction of this project. Access shall be provided at all times during the construction process, except
when specific construction activities such as shoring, foundation work, and construction of frontage
improvements prevent access. General materials storage and contractor convenience are not reasons for
preventing access.
The applicant shall secure sufficient off-street parking for construction workers before the issuance of a
clearing and grading, building, a foundation or demolition permit.
AUTHORITY: BCC 11.70 & 14.30
REVIEWER: Tim Stever, (425) 452-4294
2. CIVIL ENGINEERING PLANS – TRANSPORTATION: Where required, civil engineering plans
produced by a qualified licensed engineer must be approved by the Transportation Department prior to
issuance of the clearing and grading permit. The design of all street frontage improvements and driveway
accesses must be in conformance with the requirements of the Americans with Disabilities Act, the
Transportation Development Code, the provisions of the Transportation Department Design Manual, and
specific requirements stated elsewhere in this document. All relevant standard drawings from the
Transportation Department Design Manual shall be copied exactly into the final engineering plans.
Requirements for the engineering plans include, but are not limited to:
• Traffic signs and pavement markings.
• Curb, gutter, sidewalk, and driveway approach design. The engineering plans shall be the
controlling document on the design of these features; architectural and landscape plans must
conform to the engineering plans as needed.
• Curb ramps and crosswalks constructed per ADA standards.
• Installation or relocation of streetlights and related equipment.
• Show the required sight distance triangles and include any sight obstructions, including
those off-site. Sight distance triangles must be shown at all driveway locations and must
Conditions of Approval,
PSE South Bellevue Segment
– CUP File No. 17-120556-LB
Page 4 of 20
consider all fixed objects and mature landscape vegetation. Vertical as well as horizontal
line of sight must be considered when checking for sight distance.
• Landings on sloping approaches are not to exceed a 7% slope for a distance of 30 feet
approaching the back edge of sidewalk. Driveway grade must be designed to prevent
vehicles from bottoming out due to abrupt changes in grade.
• Driveway aprons must be constructed in accordance with Design Manual Standard
Drawings SW-140-1 through SW-190-1.
• Location of fixed objects in the sidewalk or near the driveway approach.
• Trench restoration within any right of way or access easement.
The following street and access improvements are required to be designed and shown in the civil
engineering plan set:
• Provide a concrete driveway approach at SE 30th Street Per City of Bellevue’s Transportation
Design Manual. Driveway approach shall be a minimum of 26-feet wide. Minimum of 30-feet
distance is required from the right-of-way line to the new gate location.
• No fixed objects, including fire hydrants, trees, and streetlight poles, are allowed within ten
feet of a driveway edge, defined as Point A in standard drawings SW-140-1 through SW-190-
1. Fixed objects are defined as anything with breakaway characteristics greater than a four-inch
by four-inch wooden post.
• A street light analysis is required for SE 30th Street. Street lighting shall meet Bellevue’s
minimum standards contained in the Transportation Design Manual Appendix A or as amended.
• The applicant shall be required to provide appropriate clearances as provided for in the most
recent National Electric Safety Code (NESC) from existing overhead signal equipment for the
installation of the overhead transmission lines.
• Construction of all street and access improvements must be completed prior to closing the
clearing and grading permit and right of way use permit for this project. A Design Justification
Form must be provided to the Transportation Department for any aspect of any pedestrian route
adjacent to or across any street that cannot feasibly be made to comply with current ADA
standards. Design Justification Forms must be provided prior to approval of the clearing and
grading plans for any deviations from standards that are known in advance. Forms provided in
advance may need to be updated prior to project completion. For any deviations from standards
that are not known in advance, Forms must be provided prior to project completion.
AUTHORITY: BCC 14.60, Transportation Department Design Manual, and
the Americans with Disabilities Act
REVIEWER: Fay Schafi, (425) 452-4574
3. TURBIDITY AND PH MONITORING REQUIRED: A turbidity and pH monitoring plan must be
submitted and approved prior to issuance of the clearing and grading permit. The plan must be developed
Conditions of Approval,
PSE South Bellevue Segment
– CUP File No. 17-120556-LB
Page 5 of 20
in accordance with the Turbidity & pH Monitoring Requirements contained in the Bellevue Clearing &
Grading Development Standards, indicating appropriate locations and timing of turbidity and pH sampling
and testing. The plan must be implemented during site work and shall be modified as appropriate during
construction to reflect pace and extent of construction activity.
AUTHORITY: BCC 23.76.160 (Clearing & Grading Code)
REVIEWER: Thomas McFarlane, P.E.; Bellevue Development Services,
Clearing & Grading Section
4. DRAINAGE REPORT REQUIRED: Provide a final drainage report that documents the storm drainage
minimum requirements triggered for the project. In the report include either figure 2.2 or 2.3 from the
Utilities Surface Water Engineering Standards. PSE shall document if the project qualifies as either new
development or redevelopment and include a project summary. Document the amount of new, replaced and
pollution generating impervious surface changes. PSE shall also document any work within any critical
area, wetlands and/or buffers in the report.
AUTHORITY: Title 24.02, 24.04, 24.06 BCC
REVIEWER: Arturo Chi, Utilities
5. FINAL WETLAND ENHANCEMENT PLAN: PSE shall submit a Final Wetland Enhancement Plan
consistent with the plans submitted as part of this application in Attachment I (Critical Areas Report). The
Plan shall be submitted as part of the required clearing and grading permit. All plant species, size, and
spacing shall be consistent with the standard found in the City’s Critical Areas Handbook.
AUTHORITY: LUC 20.25H.220; 20.25H.230
REVIEWER: Heidi Bedwell, Land Use
6. FINAL STREAM HABITAT IMPROVEMENT PLAN: PSE shall submit a Final Stream Habitat
Improvement Plan consistent with the plans submitted as part of this application in Attachment I (Critical
Areas Report). The Plan shall be submitted as part of the required clearing and grading permit. All plant
species, size, and spacing shall be consistent with the standards found in the City’s Critical Areas
Handbook. The Plan shall include methods for fish exclusion, construction sequencing, monitoring and
maintenance.
AUTHORITY: LUC 20.20H.210, 20.25H.220, 20.25H.230
REVIEWER: Heidi Bedwell, Land Use
7. FINAL MITIGATION PLAN FOR PERMANENT IMPACTS AND VEGETATION CONVERSION IN
CRITICAL AREAS AND CRITICAL AREA BUFFERS: PSE shall submit a final mitigation plan for all
permanent impacts and vegetation conversion activities consistent with Attachment I (Critical Areas
Report) for review and approval by the City of Bellevue prior to issuance of the Clearing and Grading
Permit. The Plan shall depict tree and other vegetation to be removed within all critical area or critical area
buffers. Trees within a critical area or critical area buffer shall be replaced at a minimum of a 3:1 ratio. All
other areas of vegetation removal shall be mitigated in an equivalent area consistent with the replacement
ratios contained in Attachment I (Critical Areas Report). Final design shall also include wildlife snags
designed as recommended from the State of WA Department of Fish and Wildlife where feasible and in
consideration of PSE’s Avian Protection Plan. The mitigation plan shall include BMPs for construction
Conditions of Approval,
PSE South Bellevue Segment
– CUP File No. 17-120556-LB
Page 6 of 20
sequencing, monitoring, and maintenance and shall be developed consistent with the City’s Critical Areas
Handbook for species choice, plant size, and spacing.
AUTHORITY: Part 20.30P LUC
REVIEWER: Heidi Bedwell, Land Use
8. FINAL RESTORATION PLAN FOR TEMPORARY IMPACTS IN CRITICAL AREAS AND CRITICAL
AREA BUFFERS: PSE shall submit a final restoration plan showing temporary construction impacts.
Restoration of impacts shall be with native plants where native plants are being removed. All other areas
of temporary impact shall be re-vegetated except for those areas which contained impervious surfaces prior
to construction activities.
AUTHORITY: LUC 20.25H.220
REVIEWER: Heidi Bedwell, Land Use
9. AVIAN PROTECTION PROGRAM: PSE shall implement their Avian Protection Plan consistent with
Attachment I (Critical Areas Report), including methods and equipment to reduce avian collisions,
electrocution, and problem nests. To reduce impacts to birds, the timing and location of construction work
shall consider critical time periods such as the nesting season for species of local importance present in the
Project area. A habitat biologist or other qualified professional shall submit a plan documenting
recommended measures to limit impacts.
AUTHORITY: Part 20.30P LUC, LUC 20.20.255.G
REVIEWER: Heidi Bedwell, Land Use
10. CRITICAL AREAS AND CRITICAL AREA BUFFERS MAINTENANCE AND MONITORING REPORTS:
Mitigation plans shall include methods for vegetation maintenance and monitoring and shall be submitted
as part of the required clearing and grading permit. Mitigation sites are required to be maintained and
monitored for five years to ensure the plants successfully establish. Annual monitoring reports are required
to be submitted to document the plants are meeting approved performance standards. Photos from selected
photo points shall be included in the monitoring reports to document the planting. Land Use inspection is
required by Land Use staff to end the plant monitoring period.
Reporting shall be submitted no later than the end of each growing season or by December 31st, and shall
include a site plan and photos from photo points established at the time of Land Use Inspection. Reports
shall be submitted to Heidi Bedwell, or the City of Bellevue’s successor Environmental Planning Manager,
by the above-listed date and can be emailed to hbedwell@bellevuewa.gov or mailed directly to:
Environmental Planning Manager
Development Services Department
City of Bellevue
PO Box 90012
Bellevue, WA 98009-9012
AUTHORITY: Land Use Code 20.30P.140; 20.25H.220
REVIEWER: Heidi Bedwell, Land Use
Conditions of Approval,
PSE South Bellevue Segment
– CUP File No. 17-120556-LB
Page 7 of 20
11. ASSURANCE DEVICE- CRITICAL AREAS MITIGATION: As part of the Clearing and Grading
Permit, PSE shall submit a cost estimate prepared by a qualified professional for the proposed planting
materials and installation costs. An installation security shall be provided to the City of Bellevue in the
amount of 150% of the total cost. After the final mitigation plans have been implemented and inspected by
the City, the installation assurance device will be released and the City shall request and retain a
maintenance assurance device in the amount of 20% of the total cost estimate. The maintenance assurance
device shall be kept by the City until the performance objectives have been met.
AUTHORITY: LUC 20.40.490
REVIEWER: Heidi Bedwell, Land Use
12. GEOTECHNICAL REVIEW: The project geotechnical engineer (see BCC 23.76.030.G) must review
the final construction plans, including all foundation, retaining wall, shoring, cut, and fill designs. A letter
from the geotechnical engineer stating that the plans conform to the recommendations in the geotechnical
report and any addendums and supplements must be submitted to the clearing and grading section prior to
issuance of the construction permit.
AUTHORITY: BCC 23.76.050 (Clearing & Grading Code)
REVIEWER: Thomas McFarlane, P.E.; Bellevue Development Services; Clearing &
Grading Section
13. SEISMIC DESIGN: The project geotechnical engineer shall certify that PSE has conducted
geotechnical hazard evaluations for all proposed elements of the substation foundations, walls, and
transmission poles, and that all geotechnical recommendations have been incorporated into project design.
PSE shall provide required certification and supporting documentation to the City of Bellevue. The
geotechnical report shall address all code requirements and provide a discussion of how the design meets
or exceeds following:
• The 2012 International Building Code (IBC), or as amended, parameters for short period spectral
response acceleration (SS), 1-second period spectral response acceleration (S1), and Seismic
Coefficients FA and FV presented in Table 2 of the geotechnical report.
• Consistent with the project geotechnical engineer’s recommendation, use soil input parameters for
lateral load design that consider the effects of liquefaction through the application of p-multipliers
for LPile parameters (LPile is a computer program used to analyze deep foundations under lateral
loading).
• North of the proposed Richards Creek substation, reevaluate the lateral spreading risk to the
proposed poles in this area once their final locations have been selected, to determine appropriate
foundation dimensions.
• Where areas subject to liquefaction are present, extend foundations below the loose to medium
density liquefiable deposits into underlying dense, non- liquefiable soils.
• Reevaluate the axial capacity of the pole foundations and potential downdrag loads for poles in
areas subject to liquefaction once final locations are selected, and consider these in the structural
design.
AUTHORITY: Part 20.30P LUC, LUC 20.20.255.G
REVIEWER: Heidi Bedwell, Land Use
Conditions of Approval,
PSE South Bellevue Segment
– CUP File No. 17-120556-LB
Page 8 of 20
14. FINAL LANDSCAPE PLAN RICHARD CREEK SUBSTATION: PSE shall submit a final landscape plan
as part of the required construction permits consistent with the landscape plan submitted as part of this
application (Attachment A [Project Plans]). In addition to the vegetation proposed, all disturbed areas not
mitigated for critical area impacts shall be planted with low growing native vegetation. Landscape plan
shall include plant species, quantity, spacing and cost estimate for plant material and installation. To ensure
plant establishment, the applicant shall provide a landscape assurance device that shall cover 20% of the
fair market value of labor and materials for the initial landscape installation of all areas of restoration
required for the substation landscaping. This assurance device will cover the landscape maintenance of the
project for a period of one year from the date of final inspection.
AUTHORITY: LUC 20.20.520.K.1 & 2, 20.40.490
REVIEWER: Heidi Bedwell, Land Use
15. LIGHTING PLAN RICHARDS CREEK SUBSTATION: PSE shall submit a lighting plan as part of the
required clearing and grading permit showing proposed lighting at the substation. Lighting shall be designed
to direct light away from the stream and wetland areas including the use of shields or other methods to
reduce spillover into critical areas.
AUTHORITY: LUC 20.25H.080A and 100
REVIEWER: Heidi Bedwell, Land Use
16. TREE REMOVAL NON-CRITICAL AREAS: PSE shall submit a final Tree Replacement plan as part
of the required clearing and grading permits consistent with Attachment E (Vegetation Management Plan)
submitted as part of this application.
AUTHORITY: LUC 20.20.255.G
REVIEWER: Heidi Bedwell, Land Use
17. MITIGATION FOR TREE REMOVAL IN CITY OF RIGHT-OF-WAY (FEE IN LIEU PLAN): PSE has
agreed to mitigate for the loss of trees located in the City right- of-way with a fee in lieu method. Mitigation
will be based on a total value of the trees to be removed using the methods outlined in the Council of Tree
and Landscape Appraisers, Guide for Plant Appraisal. The fee will be used for replanting in the City right-
of-way or on other city owned parcels.
PSE shall prepare a final tree removal plan depicting trees to be removed in the right-of-way including their
size and species. This plan shall be submitted to the City of Bellevue for approval. PSE and the City will
identify and agree upon an independent third-party certified arborist to determine the total value of trees
removed from the City right-of-way. The arborist shall use the methods outlined in the Council of Tree and
Landscape Appraisers, Guide for Plant Appraisal. PSE shall pay for the arborist appraisal. No tree removal
is allowed until acceptance of the plan, appraisal, and payment to the City of Bellevue has occurred.
AUTHORITY: LUC 20.20.255.G
REVIEWER: Heidi Bedwell, Land Use
Conditions of Approval,
PSE South Bellevue Segment
– CUP File No. 17-120556-LB
Page 9 of 20
18. INSTALLATION SURETY-TREE REPLACEMENT (NON-CRITICAL AREAS): PSE shall submit as
part of the required Clearing and Grading permit a cost estimate in the amount of the total trees proposed
for replacement in non-critical areas. The estimate shall be based on the following replacement ratios
contained in Table VI-1 of the Staff Report:
The estimate and surety provided by PSE as required by this condition shall be in the amount of 100% of
the estimated cost of tree replacement (including materials and labor). The surety will be released one year
after tree replacement, consistent with the applicable Tree Replacement plan, is complete.
AUTHORITY: LUC 20.20.255.G
REVIEWER: Heidi Bedwell, Land Use
19. FINAL RESTORATION PLAN FOR TEMPORARY IMPACTS (NON-CRITICAL AREAS): PSE shall
submit a final restoration plan showing temporary construction impacts. The impacts shall be restored with
vegetation consistent with the pre-project condition when vegetation has been removed. Other
improvements impacted by construction activities shall be restored in coordination with the underlying
property owner.
AUTHORITY: LUC 20.20.255.G
REVIEWER: Heidi Bedwell, Land Use
20. PESTICIDES, HERBICIDES AND FERTILIZERS: Applicant shall submit written information
identifying the pesticide, herbicide and/or insecticide to be used AND written confirmation that the product
used has been reviewed and approved by a consulting arborist. Work shall be done in accordance with the
City of Bellevue’s “Environmental Best Management Practices.”
Prior to any use of pesticides, herbicides, and/or fertilizers associated with the proposal, the applicant must
receive approval from Land Use under the required Clearing and Grading Permit.
AUTHORITY: LUC 20.25H.080, LUC 20.20.255G
REVIEWER: Heidi Bedwell, Land Use
21. POLE FINISH: To reduce aesthetic impacts to the surrounding environment and reduce contrast
with the surrounding environment, PSE shall implement proposed pole finishes consistent with the
recommendations found in Attachment J (Pole Finishes Report City of Bellevue (South)).
AUTHORITY: LUC 20.20.255.G
REVIEWER: Heidi Bedwell, Land Use
PSE – Energize Eastside South Bellevue Segment
Project #’s 17-120556-LB and 17-120557-LO
Page 133 of 151
estimate in the amount of the total trees proposed for replacement in non-
critical areas. The estimate shall be based on the following replacement ratios
contained in Table VI-1 of the Staff Report:
The estimate and surety provided by PSE as required by this condition shall be
in the amount of 100% of the estimated cost of tree replacement (including
materials and labor). The surety will be released one year after tree
replacement, consistent with the applicable Tree Replacement plan, is
complete.
AUTHORITY:LUC 20.20.255.G
REVIEWER:Heidi Bedwell, Land Use
Final Restoration Plan for Temporary Impacts (Non-Critical
Areas):PSE shall submit a final restoration plan showing temporary
construction impacts. The impacts shall be restored with vegetation consistent
with the pre-project condition when vegetation has been removed. Other
improvements impacted by construction activities shall be restored in
coordination with the underlying property owner.
AUTHORITY:LUC 20.20.255.G
REVIEWER:Heidi Bedwell, Land Use
Pesticides, Herbicides and Fertilizers:Applicant shall submit written
information identifying the pesticide, herbicide and/or insecticide to be used
AND written confirmation that the product used has been reviewed and
approved by a consulting arborist. Work shall be done in accordance with the
City of Bellevue’s “Environmental Best Management Practices.”
Prior to any use of pesticides, herbicides, and/or fertilizers associated with the
proposal, the applicant must receive approval from Land Use under the
required Clearing and Grading Permit.
AUTHORITY:LUC 20.25H.080, LUC 20.20.255G
REVIEWER:Heidi Bedwell, Land Use
Pole Finish:To reduce aesthetic impacts to the surrounding
environment and reduce contrast with the surrounding environment, PSE shall
DSD 000133
Conditions of Approval,
PSE South Bellevue Segment
– CUP File No. 17-120556-LB
Page 10 of 20
22. FINAL PIPELINE INTERACTION ASSESSMENT AND DESIGN REPORT: To protect nearby pipelines
from interaction with the new transmission lines due to AC current density, faults caused by lightning
strikes, mechanical/equipment failure, or other causes, PSE shall continue to coordinate with Olympic and
include safeguards in the project design. PSE shall optimize conductor geometry, where a true delta
configuration provides the greatest level of field cancellation. PSE shall operate both transmission lines at
equivalent voltage ratings. These safeguards shall be certified by an engineer licensed in the state of
Washington. PSE shall also install an Optical Ground Wire (OPGW) shield wire or equivalent shield wire
recommended by DNV GL 2016 on the transmission line poles.
PSE shall perform an AC Interference Study incorporating the final transmission line route, configuration,
and operating parameters to confirm that current densities remain within acceptable levels. PSE shall
provide Olympic with the Study and provide the City with documentation establishing that the Study was
performed and submitted to Olympic.
The Study shall include a report detailing how the following have been addressed:
• PSE shall obtain and incorporate all of the pipeline parameters required for detailed modeling and
study (i.e., locations and details of above-grade pipeline appurtenances/stations, bonds, anodes,
mitigation, etc.).
• PSE shall assess the safety and AC corrosion risks under steady-state operating conditions on the
transmission lines.
• PSE shall fully assess the safety and coating stress risks for phase-to- ground faults at transmission
line structures along the entire area of co- location, including both inductive and resistive coupling.
• PSE shall reassess the safe separation distance at each pole location to minimize arcing risk based
on NACE SP0177-2014 and considering the findings in CEA 239T817.
• Specify appropriate distances for pole grounds from the pipeline to avoid electrical arcing as
recommended by the licensed engineer.
• PSE shall incorporate mitigation measures into the project design to prevent or minimize ground
fault arcing to the pipelines in areas where the pipelines are within the modeled arcing distance of
transmission line pole grounding rods.
AUTHORITY: BCC 22.02.140.B.1, 22.02.140.C
REVIEWER: Heidi Bedwell, Land Use
23. FINAL SUBSTATION PLAN: Consistent with the project plans for the proposed substation, PSE shall
comply with State and Federal standards to address the risk of substation fire. Designs should include the
following:
• Control systems to shut down equipment experiencing a fault or malfunction;
• Systems to conduct lightning to the ground rather than through lines or equipment; and
• Alternative insulation systems for closely spaced equipment.
AUTHORITY: LUC 20.20.255.G, 20.20.255.E.6
REVIEWER: Heidi Bedwell, Land Use
Conditions of Approval,
PSE South Bellevue Segment
– CUP File No. 17-120556-LB
Page 11 of 20
24. CONSTRUCTION MANAGEMENT AND ACCESS PLAN (PIPELINE SAFETY): PSE shall develop
Construction Management and Access Plan in coordination with Olympic’s Damage Prevention Team that
are mutually agreed upon by both parties. These plans shall outline the specific actions that PSE will take
to protect the pipelines from vehicle and equipment surcharge loads, excavation, and other activities in
consideration of Olympic’s general construction and right- of-way requirements and in consultation with
Olympic on the Energize Eastside project design specifically. The following general measures, at a
minimum, shall be included in the Construction Management and Access Plan:
• Notify ‘one-call’ 811 utility locater service at least 48 hours prior to PSE or PSE-designated contractors
conducting excavation work. (Olympic’s line marking personnel will then mark the location of the pipelines
near the construction areas. These procedures are designed to ensure that excavation will not damage any
underground utilities and to decrease potential safety hazards.)
• Field verify the distance between the pipelines and transmission line pole grounds.
• Add the pipeline location and depth to project plans and drawings, and submit to Olympic for evaluation.
To the extent that Olympic determines pipeline location and depth is secure or confidential information,
this information is not required to be submitted to the City of Bellevue under this condition.
• Arrange for Olympic representatives to be on-site to monitor construction activities near the pipelines.
• Identify demarcation and protection measures as recommended and required by Olympic.
• Provide all necessary information for Olympic to perform pipe stress calculations for equipment crossings
and surface loads (surcharge loads). Based on pipe stress calculations and in coordination with Olympic,
provide additional cover that may include installing timber mats, steel plating, or temporary air bridging;
utilize a combination of these; or avoid crossing in certain identified areas to avoid impacts on the Olympic
pipelines.
• Incorporate additional measures related to minimizing surcharge loads included in Olympic’s general
construction and right-of-way requirements.
• The Construction Management and Access Plan will identify contractor responsibilities including
appropriately sized construction zones to protect the general public, construction timing limits, and other
mitigation measures that will limit the exposure of the general public to potential pipeline incidents.
• No excavation or construction activity will be permitted in the vicinity of a pipeline until appropriate
communications have been made with Olympic’s field operations and its Right-of-Way Department. A
formal engineering assessment (conducted by Olympic) may be required.
• No excavation or backfilling within the pipeline right-of-way will be permitted for any reason without a
representative of Olympic on-site giving permission.
• Coordinate with Olympic regarding excavation and other construction activities to ensure that pipeline
operating pressures are reduced prior to these activities when necessary.
Conditions of Approval,
PSE South Bellevue Segment
– CUP File No. 17-120556-LB
Page 12 of 20
• As directed by Olympic, use soft dig methods (e.g., hand excavation, vacuum excavation, etc.) whenever
the pipeline(s) are within 25 feet of any proposed excavation or ground disturbance below original grade.
• Coordinate with Olympic to ensure that an Olympic representative, trained in the observation of
excavation and pipeline locating, is on-site at all times during excavation and other ground-disturbing
activities that occur within 100 feet of the pipelines where the pipelines are co-located with the proposed
transmission lines.
• Where excavations are within 20 feet of the Olympic Pipeline system, the project geotechnical engineer
shall consider temporary casing to reduce the risk of sloughing under the pipeline.
• As required by Olympic, steel plates or mats will be placed over the pipelines to distribute vehicle loads
where construction equipment needs to cross over the pipelines.
• Utility settlement monitoring points will be established on the Olympic Pipeline corridor at the direction
of Olympic where drilled shafts will be within 15 feet of a pipeline (or another distance as stipulated by
Olympic) to monitor settlement during installation of the drilled shafts. Settlement monitoring points will
be installed so that baseline readings of the settlement monitoring points may be completed prior to the
contractor mobilizing to the site. Monitoring will continue during construction on a daily basis and twice a
week in the 3 weeks following construction. The monitoring readings will be reviewed by the Engineer on
a daily basis. If measured settlement exceeds 1 inch, or an amount specified by Olympic, the integrity of
the utility will be tested and PSE will work with Olympic to repair any damage to the utilities as a result of
construction.
• The Construction Management and Access Plan shall include monitoring procedures to ensure that all
mitigation measures related to construction activities are followed.
The Construction Management and Access Plan shall be submitted to the City of Bellevue for its review
and approval before construction permit issuance. After permit issuance, any revisions or updates to the
Plan shall be provided to the City in a Final Construction Management and Access Plan before construction
begins.
AUTHORITY: BCC 22.02.140.B.1, 22.02.140.C
REVIEWER: Heidi Bedwell, Land Use
25. CONSTRUCTION MANAGEMENT AND ACCESS PLAN (RECREATION USES AND SCHOOLS): To
reduce impacts to recreation sites as a result of project construction, PSE shall include in their Construction
Access and Management Plan the following:
• Steps to coordinate with the City of Bellevue Parks Department.
• Phasing plan schedules to avoid construction activity near recreation sites, including but not limited
to public parks and Tyee Middle school, during time periods when the sites are most frequently
used.
• Plans for alternative access points to recreation sites and trail detours where necessary.
Conditions of Approval,
PSE South Bellevue Segment
– CUP File No. 17-120556-LB
Page 13 of 20
• Notification of local schools, or private owners (including the Somerset Recreation Club) 60 days
in advance of project construction within the recreation sites and again at least 2 weeks in advance
of work commencing.
• The location of signs notifying users of any temporary closure of trails or recreations sites and
installation of these signs 2 weeks in advance of closure.
The Construction Management and Access Plan shall be submitted to the City of Bellevue prior to the
issuance of construction permits.
AUTHORITY: LUC 20.20.255.G
REVIEWER: Heidi Bedwell, Land Use
26. PUBLIC OUTREACH PLAN: PSE shall submit to the City of Bellevue a public outreach plan that
details how PSE will provide information to the public about the types and locations of expected
construction impacts and mitigation measures. As part of the plan, a construction outreach team shall work
with affected residents and business owners to minimize construction-related impacts throughout the
duration of project construction. PSE will provide a contact with whom community members can address
specific concerns both prior to and during project construction. Also as part of the plan, PSE shall submit
to the City quarterly reports summarizing status of public outreach efforts including issues raised by the
community and how PSE is addressing concerns. Reports shall be submitted to the Development Services
Department Director through project completion.
AUTHORITY: LUC 20.20.255.G
REVIEWER: Heidi Bedwell, Land Use
Conditions of Approval,
PSE South Bellevue Segment
– CUP File No. 17-120556-LB
Page 14 of 20
C. Conditions that apply After Construction Permit Issuance and During Construction.
1. STATE AND FEDERAL PERMIT COMPLIANCE: To reduce indirect and direct water quality impacts
associated with construction of the new substation and transmission lines, PSE shall comply with applicable
state and federal regulatory requirements. Before any direct wetland impacts occur, PSE shall obtain the
necessary state and federal authorizations. PSE shall provide the City of Bellevue copies of all required
permits from the WDFW and the U.S. Army Corps of Engineers, including any requirements from the U.S.
Fish and Wildlife Service and National Marine Fisheries Service prior to the City of Bellevue’s pre-
construction meeting.
AUTHORITY: BCC 24.06.015, 24.06.020; LUC 20.20.255.E.2
REVIEWER: Heidi Bedwell, Land Use
2. CULTURAL RESOURCES PROTECTION: Prior to construction, PSE shall conduct archaeological
resource surveys for the selected route that include subsurface testing and a second pedestrian and
subsurface survey to assess staging areas, laydown areas, stringing sites, and access roads after more
information on these locations is available.
Prior to construction, PSE shall develop resource-specific mitigation measures during consultation with the
Washington Department of Archaeology and Historic Preservation (DAHP), affected Tribes, King County
Historic Preservation Program (KCHPP), and other appropriate stakeholders if a protected archaeological
resource is identified during the pre-construction archaeological survey or historic property inventory.
PSE shall prepare an Inadvertent Discovery Plan (IDP) for the project and discuss the IDP with contractor
during pre-construction meeting(s). PSE shall apply for an archaeological excavation permit from DAHP
(WAC 25-48-060) if impacts to a protected archaeological resource cannot be avoided.
If any resources are determined eligible for listing in the National Register of Historic Places (NHRP) by
DAHP, mitigation measures specific to those resources shall be developed during consultation with DAHP,
affected Tribes, and any other appropriate stakeholders. Any final determination and mitigation measures
developed based on this determination shall be reported to the City of Bellevue to the extent allowed by
law.
During construction, PSE shall follow outlined procedures in the IDP in the event that archaeological
resources are identified during construction activities.
During construction, PSE shall follow the procedures identified for any historic resources through
consultation with DAHP.
AUTHORITY: LUC 20.20.255.G
REVIEWER: Heidi Bedwell, Land Use
3. DRILLED SHAFT INSTALLATION PLAN: Prior to construction PSE shall submit a detailed Drilled
Shaft Installation Plan prepared by their construction contractor describing casing and drilled shaft
construction methods. The submittal will include a narrative describing the contractor’s understanding of
the anticipated subsurface conditions, underground pipelines, the overall construction sequence, access to
the pole locations, and the proposed pole foundation installation equipment. The contractor shall submit a
Conditions of Approval,
PSE South Bellevue Segment
– CUP File No. 17-120556-LB
Page 15 of 20
detailed direct embedment pole installation plan describing both uncased and temporary casing methods. If
drilled shafts are used where groundwater is present, the concrete for drilled shafts will be placed using the
“tremie” method will be considered and evaluated by an onsite geotechnical engineer (described in the
geotechnical report). The Plan shall be reviewed by the project geotechnical engineer before construction
commences; the Plan shall include documentation of this review, which shall be provided to the City of
Bellevue Development Services Department.
AUTHORITY: Part 20.30P LUC, LUC 20.20.255.G
REVIEWER: Heidi Bedwell, Land Use
4. GEOTECHNICAL INSPECTION: The project geotechnical engineer must provide geotechnical
inspection during project construction when applicable. The geotechnical engineer must monitor and test
soil cuts and fills for substation and pole foundations. The geotechnical engineer also must observe,
monitor, and test any unusual seepage, slope, or subgrade conditions.
AUTHORITY: BCC 23.76.050, 23.76.160 (Clearing & Grading Code)
REVIEWER: Thomas McFarlane, P.E.; Bellevue Development Services; Clearing &
Grading Section
5. RAINY SEASON RESTRICTIONS: Clearing and grading activity may be initiated during, or continue
into the rainy season, which is defined as October 1 through April 30, only with written authorization of
the Development Services Department. Should approval be granted for work during the rainy season,
increased erosion and sedimentation measures, as appropriate for the anticipated rainy season conditions,
must be implemented prior to beginning or resuming site work.
AUTHORITY: BCC 23.76.093.A (Clearing & Grading Code)
REVIEWER: Thomas McFarlane, P.E.; Bellevue Development Services; Clearing &
Grading Section
6. STREET AND ACCESS IMPROVEMENTS: All street and access improvements and other required
transportation elements including street lights revisions, must be constructed by the applicant and accepted
by the Transportation Department inspector. This includes improvements on SE 30th Street.
All areas disturbed (i.e., pavement, curb and gutter, landscaping, driveways, temporary access roads, etc.)
by the project shall be restored after construction to its previous or an improved state per City of Bellevue
ROW standards including current ADA standards.
AUTHORITY: BCC 14.60, Comprehensive Plan Policy UT-39, and the Transportation
Department Design Manual
REVIEWER: Fay Schafi, (425) 452-4574
7. PAVEMENT RESTORATION: A no-street-cut moratorium is in effect on SE 30th Street. Should street
cuts prove unavoidable or if the street surface is damaged in the construction process, a half-street or full-
street (depending on the extent of street cuts or damage) grind and overlay will be required.
Conditions of Approval,
PSE South Bellevue Segment
– CUP File No. 17-120556-LB
Page 16 of 20
The applicant will be required to restore all damaged pavement within City right-of-way caused by
construction activities related to this project. Limits and extent of pavement restoration shall be as required
by the Right-of-Way use permit.
AUTHORITY: BCC 14.60.250; Design Manual Design Standard #23
REVIEWER: Tim Stever (425) 452-4294
8. HELICOPTER OR LARGE CRANE USE: PSE shall identify any areas where a helicopter or large
crane will be used to lift foundation rebar and/or poles over adjacent properties and into place, or to facilitate
stringing the new transmission lines. PSE or its contractor shall provide copies of the “congested air” permit
from the Federal Aviation Administration (FAA). PSE shall also coordinate with the City of Bellevue to
determine where this type of construction is allowed.
AUTHORITY: Part 20.30M LUC
REVIEWER: Heidi Bedwell, Land Use
9. CONSTRUCTION STORMWATER POLLUTION PREVENTION PLAN (CSWPPP):
The clearing and grading permit application must include a CSWPPP. The structure and content of the
CSWPPP must follow the requirements of the Bellevue Clearing and Grading Code and the Bellevue
Clearing and Grading Development Standards. BMPs in the plan include the following:
• Operating procedures to prevent spills.
• Control measures such as secondary containment to prevent spills from entering nearby surface
waters.
• Countermeasures to contain, clean up, and mitigate the effects of a spill.
• Construction vehicle storage and maintenance and fueling of construction equipment will be
located away from streams and wetlands.
To avoid groundwater contamination, if any pole installation sites are determined to need dewatering, PSE
shall prepare and submit a dewatering plan for City approval. The dewatering plan must include provisions
for turbidity and pH monitoring of dewatering water. No refueling or staging shall be allowed within critical
area or critical area buffers.
AUTHORITY: Part 20.25H LUC; Chapter 23.76 BCC
REVIEWER: Heidi Bedwell, Land Use; Thomas McFarlane, P.E., Bellevue
Development Services, Clearing & Grading Section
10. TRAFFIC MANAGEMENT: As part of the right-of-way use permit, PSE shall ensure that access to
residential and commercial properties is maintained at all times, except when restricted access is required
for safety while work is occurring. At major driveways, flagger control may be needed to facilitate
alternating enter and exit traffic. Special treatment will be needed for developments with split driveways
(with one driveway serving entering traffic and one serving exiting traffic) if traffic cannot easily be shifted
to the other driveway for two-way operation. The contractor will be required to coordinate with property
owners when driveways or alleys are affected by construction.
AUTHORITY: BCC 14.30
REVIEWER: Tim Stever, Transportation/Right-of-Way
Conditions of Approval,
PSE South Bellevue Segment
– CUP File No. 17-120556-LB
Page 17 of 20
11. PAVEMENT DEGRADATION: As part of the right-of-way permit inspection process, pavement
degradation identified by the City that results from increased Project-related construction truck traffic or
excavation shall be fully restored upon completion of construction activities. This includes restoration of
streets, curbs, gutters, sidewalks, parking lots, driveways, and traffic signal induction loops where
appropriate.
AUTHORITY: BCC 14.30
REVIEWER: Tim Stever, Transportation/Right-of-Way
12. COORDINATION WITH OTHER UTILITY PROVIDERS AFFECTED BY PROPOSAL: PSE will
coordinate with any affected utility providers, as appropriate, to determine how best to avoid or minimize
any impacts while Project construction is occurring. The City of Bellevue will review project designs prior
to permit approval to ensure protection of other utilities. PSE and its contractors will be required to develop
construction sequence plans and coordinate schedules for utility work to minimize service disruptions and
provide ample advance notice when service disruptions are unavoidable, consistent with utility owner
policies. Relocation plans and service disruptions shall be reviewed and approved by the affected utility
providers before construction begins. PSE will coordinate with the other utility providers to assist in their
planning efforts for public outreach to inform their customers of potential service outages and construction
schedules.
AUTHORITY: LUC 20.20.255.G
REVIEWER: Heidi Bedwell, Land Use
13. FIELD VERIFICATION OF UTILITY LOCATIONS: PSE shall follow regulatory requirements to
field-verify utility locations such as gas lines or the Olympic Pipeline system. Field verification of the
Olympic Pipeline system may include methods as directed by Olympic, such as potholing using vacuum
truck excavation to avoid damage to the pipelines.
AUTHORITY: BCC 22.02.140.B.1, 22.02.140.C
REVIEWER: Heidi Bedwell, Land Use
14. PIPELINE MARKING PRIOR TO CONSTRUCTION: PSE shall coordinate with Olympic to ensure
that line marking personnel mark the entire length of Olympic’s pipeline within 50 feet of any excavation
or ground disturbance below original grade, and not only the location of angle points (points of intersection).
AUTHORITY: BCC 22.02.140.B.1, 22.02.140.C
REVIEWER: Heidi Bedwell, Land Use
15. GROUNDING SYSTEM: Qualified licensed engineer shall verify separation distances between the
transmission grounding system and the pipeline meets the recommendations in the Final Pipeline
Interaction Assessment and Design Report after poles are installed. If grounding distances are not consistent
with the recommendations, PSE shall reinstall grounding system to comply with the recommendations.
AUTHORITY: BCC 22.02.140.B.1, 22.02.140.C
REVIEWER: Heidi Bedwell, Land Use
Conditions of Approval,
PSE South Bellevue Segment
– CUP File No. 17-120556-LB
Page 18 of 20
16. OLYMPIC’S GENERAL CONSTRUCTION REQUIREMENTS: PSE shall comply with the approved
Construction Management and Access Plan including the identified measures from Olympic’s General
Construction and Right of Way Requirements for all work proposed near the pipelines.
AUTHORITY: BCC 22.02.140.B.1, 22.02.140.C
REVIEWER: Heidi Bedwell, Land Use
17. MITIGATION AND MONITORING REPORT- CONSTRUCTION MANAGEMENT AND ACCESS PLAN
(PIPELINE SAFETY): Consistent with the approved Construction Management and Access Plan, PSE shall
document all mitigation measures implemented, monitored, and conducted.
PSE will file a mitigation and monitoring report with the City of Bellevue that documents consultations
with Olympic and mitigation measures to address safety-related issues. PSE shall file the mitigation and
monitoring reports with the City of Bellevue quarterly during construction. The reports shall identify any
additional mitigation measures and monitoring that may be required as a result of PSE’s coordination with
Olympic.
The mitigation and monitoring report shall demonstrate that sufficient pipeline safety measures have been
implemented, and document all consultations with Olympic, including the sharing of modeling,
engineering, and as-built information with Olympic to assist Olympic in its ongoing monitoring and
mitigation responsibilities. The report shall identify any additional field surveys and data collection
necessary for verifying mitigation measures following project start-up, and any proposed monitoring to
ensure that mitigation measures related to operational issues are followed.
AUTHORITY: BCC 22.02.140.B.1, 22.02.140.C
REVIEWER: Heidi Bedwell, Land Use
Conditions of Approval,
PSE South Bellevue Segment
– CUP File No. 17-120556-LB
Page 19 of 20
D. Conditions that apply for the Life of the Project.
1. WATER QUALITY PROTECTION: During maintenance activities (for substation, poles, the
transmission line corridor, and access roads) PSE shall prevent spills or leaks of hazardous materials, paving
materials, or chemicals from contaminating surface or groundwater.
AUTHORITY: Part 20.25H LUC
REVIEWER: Heidi Bedwell, Land Use
2. MAINTENANCE AND MONITORING PROGRAM-STRUCTURAL STABILITY: PSE shall develop a
monitoring and maintenance program that includes inspection and reporting on the ability of the
transmission line poles to resist seismic disturbances. As part of PSE’s regular inspection of the poles, it
shall monitor all poles for changes in conditions that could reduce the ability of the structures to resist
seismic disturbances. PSE shall submit reporting to the City of Bellevue. If changes are identified during
inspection and monitoring of conditions, PSE shall implement additional measures to reduce or minimize
those impacts.
AUTHORITY: Part 20.30P LUC, 20.20.255.G
REVIEWER: Heidi Bedwell, Land Use
3. TELECOMMUNICATION FACILITIES: PSE shall limit the number of telecommunications facilities
installed on the 230 kV poles to the seven locations currently installed in the corridor. Reinstalled facilities
shall be in approximately the same locations as they were previously. Facilities shall be required to get City
approval per current land use regulations before reinstalling telecommunication equipment.
AUTHORITY: LUC 20.20.255.G, 20.20.255.E.6
REVIEWER: Heidi Bedwell, Land Use
4. ELECTROMAGNETIC FIELDS: In the event that radio frequency interference is found by a radio
operator, PSE shall de-tune pole structures by installing hardware (such as arresters).
AUTHORITY: LUC 20.20.255.G, 20.20.255.E.6
REVIEWER: Heidi Bedwell, Land Use
5. PIPELINE SAFETY DURING OPERATION: PSE shall work with Olympic to evaluate and implement
appropriate mitigation measures to reduce electrical interference on the Olympic Pipeline system to safe
levels.
PSE shall provide information to Olympic as appropriate or when requested by Olympic for Olympic to
record AC pipe-to-soil potentials and DC pipe-to-soil potentials during its annual cathodic protection
survey.
PSE shall provide Olympic with as much advance notice as practical of when outages are planned on the
individual circuits (i.e., when only one circuit of the double circuit transmission lines is in operation) to
allow monitoring of the AC induction effects on the pipelines.
Conditions of Approval,
PSE South Bellevue Segment
– CUP File No. 17-120556-LB
Page 20 of 20
PSE shall provide Olympic with data on anticipated maximum loads under peak winter operating conditions
on an annual basis, and provide copies to the City of Bellevue to verify that this data has been provided to
Olympic.
After the transmission line is installed and energized, Olympic is expected (due to its federal requirements
to protect the pipeline from damage) to measure the actual AC interference with the pipeline in order to
ensure that all AC interference risks have been fully mitigated under steady-state operation of the
transmission line. PSE shall cooperate with Olympic in completing a post- energization AC site survey to
determine if any adjustments are needed to Olympic’s pipeline protection systems. This survey should cover
the entire length of the new transmission line in the South Bellevue Segment. PSE shall provide load data
for the survey, along with any design or as-built information requested by Olympic.
PSE shall monitor oil insulation for evidence of arcing and gassing, and monitor substations for evidence
of overloading, overheating, or malfunctions.
PSE shall submit to the City of Bellevue, upon request by the City, documentation sufficient to show
compliance with the provisions imposed by this Condition of Approval.
AUTHORITY: BCC 22.02.140.B.1, 22.02.140.C
REVIEWER: Heidi Bedwell, Land Use
EXHIBIT B
EXHIBIT C
EXHIBIT C
1
Code Criteria City Staff Report
CUP Application
and PSE
Testimony
Environmental Impact Statement (EIS)
RMC 4-9-030(D)(1)
p. 5 and 9 (applying
Renton
Comprehensive
Plan, Utilities
Element)
Staff Report,
Exhibit 14 at pp.
4-18 (analyzing
compliance with
Utilities,
Shoreline
Management,
Economic
Development and
Land Use
Elements).
Staff Report, Exhibit 17 (Phase 2 DEIS) at p 3.1-44
(“The project would be consistent with the Renton
Comprehensive Plan. Zoning districts in the study area
allow electrical utility facilities as a conditional use.”).
Staff Report, Exhibit 18 (FEIS) at pp. 4.1-20 (“The
project would be consistent with the Renton
Comprehensive Plan (City of Renton, 2015).”).
PSE Hearing Memo, Exhibit G (Phase I DEIS) at F-54—
61 (identifying potentially applicable comprehensive
plan policies).
RMC 4-9-030(D)(2)
p. 10 (confirming
that project is sited
in an appropriate
location); Exhibit 2
at pp. 3-9—3-15
(pipeline safety
mitigation
measures).
Staff Report,
Exhibit 14 at p.
19; Testimony of
David Kemp
(describing
pipeline safety
analysis and
mitigation
measures);
Staff Report, Exhibit 17 (Phase 2 DEIS) at pp. 3.1-18,
3.1-44—45 (“The project would not impact the
existing land use pattern of single-family residential.
The project would use the existing corridor and not
require new easements from adjoining properties.”)
Staff Report, Exhibit 18 (FEIS) at pp. 4.1-20−21 (“The
potential impacts to land use and housing for the
Renton Segment would be less-than-significant
because it is consistent with City plans, and would not
adversely affect existing or future land use patterns.”);
6-12—6-13 (response to comments on pipeline
safety).
PSE Hearing Memo, Exhibit G (Phase I DEIS) at Ch. 10
(throughout).
EXHIBIT C
2
RMC 4-9-030(D)(3)
pp. 10-11;
Recommendations
J.3 and J.6; Exhibit
2 at pp. 3-9—3-15
(pipeline safety
mitigation
measures).
Staff Report,
Exhibit 14 at pp.
19-20; Testimony
of Lowell Rogers
(describing
construction
techniques);
Testimony of
David Kemp
(describing
pipeline safety
analysis and
mitigation
measures);
Testimony of
Brad Strauch
(describing
vegetation
restoration and
mitigation; art
poles).
Staff Report, Exhibit 17 (Phase 2 DEIS) at pp. 3.1-18,
3.1-44—45 (“The project would not impact future land
uses, which are anticipated to be mostly single-family
residential, mixed-use, and commercial. The project
would use the existing corridor and would not
interfere with planned development.”); 3.2-16
(assessing aesthetic impacts); 3.2-81−86 (concluding
that the project’s aesthetic impacts are less-than-
significant).
Staff Report, Exhibit 18 (FEIS) at pp. 4.1-20−21 (“The
potential impacts to land use and housing for the
Renton Segment would be less-than-significant
because it is consistent with City plans, and would not
adversely affect existing or future land use patterns.”);
4.2-44−49 (“Impacts to the scenic views and the
aesthetic environment in the Renton Segment would
be less-than-significant…”); 6-12—6-13 (response to
comments on pipeline safety).
PSE Hearing Memo, Exhibit G (Phase I DEIS) at Ch. 10
(containing Renton-specific analysis throughout); 10-
21—10-22 (summarizing review of studies analyzing the
potential for economic impacts to property value); 10-25
(assessing impacts if 230 kV lines are sited in existing
corridor);
RMC 4-9-030(D)(4)
pp. 11-12.
Staff Report,
Exhibit 14 at pp.
20-21; Testimony
Staff Report, Exhibit 17 (Phase 2 DEIS) at pp. 3.1-18,
3.1-44—45 (“The project would not impact future land
uses, which are anticipated to be mostly single-family
EXHIBIT C
3
of Lowell Rogers
(describing
construction
techniques);
Testimony of
David Kemp
(describing
pipeline safety
measures);
Testimony of
Brad Strauch
(describing
vegetation
restoration and
mitigation).
residential, mixed-use, and commercial. The project
would use the existing corridor and would not
interfere with planned development.”); 3.2-16
(assessing aesthetic impacts); 3.2-81−86 (concluding
that the project’s aesthetic impacts are less-than-
significant).
Staff Report, Exhibit 18 (FEIS) at pp. 4.1-20−21 (“The
potential impacts to land use and housing for the
Renton Segment would be less-than-significant
because it is consistent with City plans, and would not
adversely affect existing or future land use patterns.”);
4.2-44−49 (“Impacts to the scenic views and the
aesthetic environment in the Renton Segment would
be less-than-significant…”).
PSE Hearing Memo, Exhibit G (Phase I DEIS) at Ch. 10
(containing Renton-specific analysis throughout); 10-25
(assessing impacts if 230 kV lines are sited in existing
corridor); Ch. 11-7 (assessing potential visual impacts).
RMC 4-9-030(D)(5)
pp. 12-13;
Recommendation
J.4.
Staff Report,
Exhibit 14 at p.
21.
Staff Report, Exhibit 17 (Phase 2 DEIS) at 1-10
(explaining that transportation impacts were eliminated
from further analysis following the Phase I EIS due to a
lack of foreseeable impacts).
Staff Report, Exhibit 18 (FEIS) at 1-13 (explaining that
transportation impacts were eliminated from further
analysis following the Phase I EIS due to a lack of
foreseeable impacts).
PSE Hearing Memo, Exhibit G (Phase I DEIS) at 14-10-
12.
EXHIBIT C
4
RMC 4-9-030(D)(6)
pp. 13-14;
Recommendations
J.5 and J. 8.
Staff Report,
Exhibit 14 at pp.
21-22.
Staff Report, Exhibit 17 (Phase 2 DEIS) at 1-10
(explaining that transportation impacts were eliminated
from further analysis following the Phase I EIS due to a
lack of foreseeable impacts).
Staff Report, Exhibit 18 (FEIS) at 1-13 (explaining that
transportation impacts were eliminated from further
analysis following the Phase I EIS due to a lack of
foreseeable impacts).
PSE Hearing Memo, Exhibit G (Phase I DEIS) at 14-10-
12.
RMC 4-9-030(D)(7)
pp. 14-15.
Staff Report,
Exhibit 14 at pp.
22-24.
Staff Report, Exhibit 17 (Phase 2 DEIS) at Section
4.4.2.1 (Short-term Impacts Common to All
Components); 3.2-16 (assessing aesthetic impacts
including potential for light and glare); 3.2-81−86
(concluding that the project’s aesthetic impacts are
less-than-significant).
Staff Report, Exhibit 18 (FEIS) at 1-13 (concluding that
“there would be no significant and unavoidable
adverse noise impacts associated with any of the
project alternatives, either during construction or
operation”); 4.2-44−49 (“Impacts to the scenic views
and the aesthetic environment in the Renton Segment
would be less-than-significant…”); 6-14 (response to
comments); Appendix J-1 (Topic Noise).
PSE Hearing Memo, Exhibit G (Phase I DEIS) at 9-6
EXHIBIT C
5
(describing Renton noise standards); 9-13—9-15
(evaluating impacts).
RMC 4-9-030(D)(8)
pp. 15-16;
Recommendations
J.2 and J.7; Exhibit
2 at pp. 3-6—3-8;
Exhibits 8, 9 and
13;
Staff Report,
Exhibit 14 at pp.
24-25; Testimony
of Brad Strauch
(describing
vegetation
restoration and
mitigation).
Staff Report, Exhibit 17 (Phase 2 DEIS) at 3.4-13—3.4-
18; 3.4-32.
Staff Report, Exhibit 18 (FEIS) at 1-21; 4.4-22—4.4-24.
EXHIBIT D
January 25, 2018 1
Renton Shoreline Exemption Project
Narrative – PSE Energize Eastside
Project name, size, and location of the site
Puget Sound Energy’s (PSE) Energize Eastside project (Project) will upgrade approximately 4
miles of two existing 115 kV lines with two 230 kV lines beginning at the City’s northern
boundary with Newcastle and ending at the existing Talbot Hill substation. The Project is located
entirely within PSE’s existing 100-ft electrical transmission utility corridor and involves
replacement of approximately 144 existing wood and steel poles (H-frame designs) with
approximately 41 steel monopoles in either a single-circuit or double-circuit configuration. Within
the Talbot Hill substation (located at 2400 S. Puget Drive), additional breakers and associated
controls will be added to accommodate the new lines. From the substation, the Project runs
north within the existing PSE transmission line corridor where it continues into Newcastle at
Renton’s northern city limit.
The existing transmission lines and the proposed upgraded lines cross the Cedar River in areas
zoned as Shoreline High Intensity and Urban Conservancy (City of Renton, Renton Shoreline
Environment Overlays map, November 2011). The Cedar River is considered a “shoreline of the
state” under the state’s Shoreline Management Act (City of Renton, Ordinance No. 5633,
October 2011).
Brief description of proposed work
Pole replacement activities, construction laydown, access, or vegetation management activities
are not proposed within jurisdictional shorelines or the associated 200-foot buffer. Rather, the
Project involves the aerial replacement of a wire more than 200-feet over the Cedar River. The
lines will be replaced with the same quantity of lines and there is a negligible change in wire size
(an approximately 0.518-inch difference between the old and new lines). Replacement of the
lines will occur aerially (i.e., no work will occur on the ground surface or in waters in the
shoreline). No fill or excavation will occur within the shoreline. Additionally, no tree or vegetation
removal is proposed within the shoreline.
Basis for the exemption request
As relevant here, the City defines “development” as “[a] use consisting of the construction of
exterior alteration of structures.” To the extent the City considers replacement wires to be a
“structure,” the Project does not involve “development” in the shoreline because PSE does not
propose an “exterior alteration.” See RMC 4-11-040 (Definitions “D”).
The Project’s 0.518-inch increase in wire size does not constitute a material change in size,
shape, configuration or external appearance of the existing wire. The lowest replacement line is
approximately 20-30 feet higher than the lowest line on the existing structure, but the wires
traversing the Cedar River are otherwise substantially the same. The increased height generally
means that the wires are less visible in the shoreline and that any alteration of external
appearance will be imperceptible.
January 25, 2018 2
The proposed wire replacement also qualifies for an exemption as “normal maintenance or
repair of existing structure or developments” under the City’s code. The “replacement of a
structure” qualifies for an exemption as a “repair” where 1) “such replacement is the common
method of repair for the type of structure” and 2) “the replacement structure…is comparable to
the original structure” considering “size, shape, configuration, location and external appearance”
and 3) “the replacement does not cause substantial adverse effects to shoreline resources or
environment.” See RMC 4-9-190.C.3.c.iii. The Project meets all three prongs.
When replacing 60-year-old transmission line wires PSE regularly upgrades the capacity of
those wires. The Project replacement wires are approximately ½-inch bigger in diameter, but
are otherwise the same shape and configuration. This ½-inch difference is negligible in a
general sense, but even more so here as the wires will be strung more than 200-feet in the air.
The net impact of the wire replacement will cause no change to the external appearance of the
wires running over the vegetated ravine. As the wires replace existing wires and all construction
work required to hang the lines will occur outside the shoreline, the wire replacement will not
cause substantial adverse effects to shoreline resources or the environment.
The change in transmission line voltage (from 115 kV to 230 kV) has no impact on ecological
function nor will it cause a substantial adverse effect to shoreline resources (access, aesthetics,
etc.). By utilizing the existing utility corridor, new impacts to the shorelines are avoided. Further,
the Project avoids adverse impacts to navigation because the height of lines over the water will
be increased. As there are no shoreline impacts, there will also be no impact to shoreline
ecological function.
See the following letter from PSE to City of Renton (dated October 27, 2017) regarding the
shoreline exemption justification and email confirming an exemption is appropriate for this
project.
Anticipated dates of work
This work is anticipated to occur in Summer 2018, but this is contingent on the timelines for
processing other Project-related permits.
Other permits required for proposed project
The following permits and approvals are required from the City for the Project: Conditional Use
Permit; Shoreline Exemption; and Grading Permit.
Current and proposed use of the site
The Project site is currently occupied by PSE’s existing 115kV transmission lines. After Project
completion, proposed use will be 230kV transmission lines owned and operated by PSE.
Special site features (i.e., wetlands, water bodies, steep slopes)
Multiple critical areas are mapped within the existing transmission line corridor within the
shoreline, including wetlands (Cedar North Wetland and Wetland NR02); priority habitat (as
mapped by the Washington Department of Fish and Wildlife); priority steep slopes (as mapped
by The Watershed Company); erosion hazard (as mapped by the City); priority landslide hazard
areas (as mapped by the City); and floodway (as mapped by the City).
January 25, 2018 3
Details related to these areas are provided in the Project’s Critical Areas Report (Watershed
2018).
Statement addressing soil type and drainage conditions
Surface soils in the Project area include mainly silty gravel, silty sand, and silt. Soils along the
proposed route provide adequate support for the new poles (GeoEngineers 2017; see Appendix
C of Critical Areas Report). To minimize impacts to soil, a Sediment and Erosion Control Plan
will be addressed in the Project-specific Temporary Erosion and Sediment Control (or “TESC”)
Plan and Construction Stormwater Pollution Prevention Plan (CSWPPP). Areas of disturbance
will be limited to the minimum necessary within geological hazard areas, including limiting
equipment access. See Renton Critical Areas Report at Sections 4.3.5; 5.2.2; 7.1.2; and 8.3. All
disturbed areas will be restored. Drainage patterns will not be changed as a result of the
Project.
Total estimated construction cost and estimated fair market value of the proposed
project
The estimated construction cost/fair market value of the Project within Renton is approximately
$18 million.
Estimated quantities and type of materials involved if any fill or excavati on is proposed
Not Applicable; fill or excavation is not proposed within the shoreline.
Number, type and size of any trees to be removed
Not Applicable; tree removal is not proposed within the shoreline.
Distance from closest area of work to the Ordinary High Water Mark of the shoreline
Project activities will occur more than 200 feet from the ordinary high water mark of the
shoreline (Cedar River).
Nature of the existing shoreline (e.g., high bank, naturalize, rip rap, bulkhead, etc.)
The Maple Valley Highway is adjacent to the northern bank of the Cedar River within the project
area. A large concrete retaining wall at the river bank limits vegetation in this area. On the
southern side of the Cedar River, vegetation within 100 feet of the waterline is characterized by
a predominantly deciduous canopy of red alder, big leaf maple and black cottonwood. Upland
understory is dominated by non-native, invasive Himalayan blackberry. A portion of Wetland
NRO2, a depressional wetland dominated by palustrine scrub-shrub and forested vegetation is
present within 100 feet of the ordinary high water mark. Common plants observed within
Wetland NRO2 include red alder, black cottonwood, salmonberry, redtwig dogwood, blackberry,
skunk cabbage and lady fern.
Invasive blackberry is estimated at 60-90% of the project area in this vicinity. Due to the high
level of invasive coverage, native vegetation within 100 feet of the waterline, within the project
area, is estimated at 1,000-4,000 square feet.
January 25, 2018 4
If the proposed project exceeds a height of 35-feet above the average grade level,
discuss the approximate location of and number of residential units, existing and
potential, that will have an obstructed view
There are no residences adjacent to the proposed shoreline crossing location; the nearest are
single-family residences approximately 350-400 feet north of the shoreline jurisdiction, and
multi-family residences approximately 700 feet south of the shoreline jurisdiction. When
replacing 60-year-old transmission line wires PSE regularly upgrades the capacity of those
wires. The Project replacement wires are approximately ½-inch bigger in diameter, but are
otherwise the same shape and configuration. This ½-inch difference is negligible in a general
sense, but even more so here as the wires will be strung more than 200-feet in the air and there
are no adjacent residences. The net impact of the wire replacement will cause no change to the
external appearance of the wires running over the vegetated ravine.
94531482.1 0063442-00015
October 27, 2017
TO: Jill Ding and Leslie Clark, City of Renton
FROM: Brad Strauch, Infrastructure Program Manager, Puget Sound Energy
RE: Energize Eastside – Renton Segment
Shoreline Exemption Justification
I. Introduction
Puget Sound Energy, Inc. (“PSE”) respectfully requests a shoreline exemption for
the hanging of transmission lines over, but not within, the shoreline where the new lines
replace existing overhead lines and no shoreline will be touched during installation. For
the reasons stated in detail below, the transmission line replacement is both not a
“development” and qualifies as “normal repair and maintenance” under the City of
Renton’s (“City”) code. See RMC 4-11-040; RMC 4-9-190.C.3.c. As such, a shoreline
exemption is appropriate in this case.
II. Project Background
PSE proposes the replacement of approximately 18 miles of 115 kV transmission
lines with 230 kV lines in an existing transmission line corridor (“Project”). The
replacement transmission lines (which have not been updated since the 1960s) are
necessary as part of PSE ongoing utility line infrastructure maintenance. Combined with
aggressive conservation measures, the Project will improve reliability for Eastside
communities, including the City of Renton, and supply capacity needed for anticipated
growth and development locally and regionally.
The Project runs approximately 4.5 miles through the City. The Project is sited in
the existing transmission line corridor (established in the late 1920s and early 1930s) and
proposes pole replacement in roughly the same locations as the existing poles. The
existing transmission line crosses the Cedar River in areas zoned as either Shoreline High
Intensity or Urban Conservancy. The Cedar River is a “shoreline” under the state’s
Shoreline Management Act.
PSE’s Project does not propose any pole replacement activities, construction
laydown, access, or vegetation management activities in the shoreline. Rather, the
project involves the aerial replacement of a wire more than 200-feet over the Cedar
94531482.1 0063442-00015 2
River. The lines will be replaced with the same quantity of lines and there is a negligible
change in wire size (an approximate 0.518-inch difference between the old and new
lines). Replacement of the lines will occur aerially (i.e. no work will occur on the ground
surface or waters in the shoreline).
PSE’s ongoing utility infrastructure maintenance regularly requires upgrading old
lines with new, higher capacity lines. In this case, the existing lines were installed in the
1960’s. Almost 60 years later, PSE still provides transmission line service, but electricity
demands have increased. The technology for transmitting electricity, however, remains
substantially the same. PSE still runs wires on poles. The only part of PSE’s Project
traversing a shoreline is an aerial wire, which is comparable in size, shape and
configuration to the existing line.
III. City of Renton Shoreline Code Requirement
Subject to limited exceptions, a shoreline permit is required for all “use and
development” in the shoreline. RMC 4-9-190.B.3. “Use” refers to land uses permitted
(or not) in a given area. RMC 4-11-210 (Definitions “U”). Here, the transmission line
upgrade is a permitted use. “Development” is defined as a
[a] use consisting of the construction of exterior alteration of structures;
dredging; drilling; dumping; filling; removal of any sand, gravel or
minerals; bulkheading; driving of piling; placing of obstructions; or any
other projects of a permanent or temporary nature which interferes with
the normal public use of the surface of the waters overlying lands subject
to the Act at any state of water level.
RMC 4-11-040 (Definitions “D”) (explaining that this definition only applies to RMC 4-
3-090, Shoreline Master Program Regulations). A “structure” is “[a] permanent or
temporary edifice or building, or any piece of work artificially built or composed of parts
joined together in some definite manner, whether installed on, above, or below the
surface of the ground or water, except for vessels.” RMC 4-11-190 (Definitions “S”).
The City exempts “normal maintenance and repair” from shoreline permitting.
Under this category, the City explains that the
[r]eplacement of a structure or development may be authorized as repair
where such replacement is the common method of repair for the type of
structure or development and the replacement structure or development is
comparable to the original structure or development including, but not
limited to, its size, shape, configuration, location and external appearance
and the replacement does not cause substantial adverse effects
to shoreline resources or environment.
RMC 4-9-190.C.3.c.iii.
94531482.1 0063442-00015 3
IV. PSE’s Transmission Line Replacement Qualifies for a Shoreline Exemption
As relevant here, the City defines “development” as “[a] use consisting of the
construction of exterior alteration of structures.” To the extent the City considers
replacement wires to be a “structure,” the Project does not involve “development” in the
shoreline because PSE does not propose an “exterior alteration.” See RMC 4-11-040
(Definitions “D”).
The Project’s ½ inch increase in wire size does not constitute a material change in
size, shape, configuration or external appearance of the existing wire. The lowest
replacement line is approximately 20-30 feet higher than the lowest line on the existing
structure, but the wires traversing the Cedar River are otherwise substantially the same.
The increased height generally means that the wires are less visible in the shoureline and
that any alteration of external appearance will be imperceptible.
The Draft Environmental Impact Statement (“DEIS”) analyzing Project impacts
does not specifically apply the “exterior alteration” requirement, but its conclusions on
aesthetic impacts caused by the wire replacement over the Cedar River are instructive.
As found in the DEIS,
• “Poles and wires are marginally visible from within ravines (such as the Cedar
River ravine). This would continue to be the case under the project.”;
• “The height and location of the proposed poles and transmission line would not
obscure views of the Cedar River from the trail.”; and
• “The crossing within the Cedar River ravine would also not have significant
impacts because it is surrounded by tall, dense vegetation. Impacts to scenic views
would be less-than-significant.”
Energize Eastside—Phase II Draft Environmental Impact Statement at 3-82 , available at
http://www.energizeeastsideeis.org/uploads/4/7/3/1/47314045/section_3.2_scenic_views
_and_the_aesthetic_environment.pdf. These findings support a conclusion that the
Project does not involve an “exterior alteration.”
The proposed wire replacement also qualifies for an exemption as it constitutes
“normal repair and maintenance” under the City’s code. As set forth above, the
“replacement of a structure” qualifies for an exemption as a “repair” where 1) “such
replacement is the common method of repair for the type of structure” and 2) “the
replacement structure…is comparable to the original structure” considering “size, shape,
configuration, location and external appearance” and 3) “the replacement does not cause
substantial adverse effects to shoreline resources or environment.” See RMC 4-9-
190.C.3.c.iii. The Project meets all three prongs.
When replacing 60-year-old transmission line wires PSE regularly upgrades the
capacity of those wires. The Project replacement wires are approximately ½ inch bigger
in diameter, but are otherwise the same shape and configuration. This ½ inch difference
is negligible in a general sense, but even more so here as the wires will be strung more
94531482.1 0063442-00015 4
than 200-feet in the air. The net impact of the wire replacement will cause no change to
the external appearance of the wires running over the vegetated ravine. As the wires
replace existing wires and all construction work required to hang the lines will occur
outside the shoreline, the wire replacement will not cause substantial adverse effects to
shoreline resources or the environment.
Additionally, the change in voltage has no impact on ecological function nor will
it cause a substantial adverse effect to shoreline resources (access, aesthetics, etc.). By
utilizes the existing utility corridor new impacts to the shorelines is avoided. Further, the
Project avoids adverse impacts to navigation (the height of lines over the water will be
increased). As there are no shoreline impacts, there will also be no impact to shoreline
ecological function.
Indeed potential impacts to avian species will be reduced. As explained in the
DEIS,
[t]he project would reduce the electrocution and collision rates for avian
species. The most common cause of avian electrocution is when birds
simultaneously contact two power phases (wires carrying different
charge). Avian electrocutions occur most frequently with lower voltage
distribution lines (30 kV or less) because conductors on most these lines
are narrowly spaced and can be bridged by birds, particularly those with
large wing spans (Dwyer et al., 2013; SCL, 2014). Electrocution
incidences are lower with higher voltage transmission lines because of the
greater separation between wires. For the Energize Eastside project,
spacing of the 230 kV wires would typically be greater than the existing
115 kV lines, which would reduce the electrocution potential.”).
DEIS at 3.4-17. In sum, the Project will to some degree improve ecological functions
from the existing conditions by reducing electrocution risk.
If additional information is needed regarding the details of the proposed project,
please contact Brad Strauch by e-mail (brad.strauch@pse.com) or phone (425-456-2556).
94531482.1 0063442-00015 5
From:Hartje, Toni
To:Strauch, Bradley; Purnell, Kelly; Gifford, Marissa; Ronda Strauch
Subject:FW: Energize Eastside, Renton segment
Date:Wednesday, December 6, 2017 12:02:36 PM
Attachments:image001.png
Here is the e-mail from Jill regarding DOE’s response to our request to pursue a Shoreline Exemption
request.
Toni Hartje
Senior Municipal Land Planner
(425) 505-3252 (cell)
From: Jill Ding [mailto:JDing@Rentonwa.gov]
Sent: Monday, November 06, 2017 11:06 AM
To: 'Leverette, Sara A.'; Leslie Clark
Cc: Durbin, Kara; Strauch, Bradley; Hartje, Toni; Jennifer T. Henning
Subject: RE: Energize Eastside, Renton segment
Hi Sara,
I had a phone conversation with Misty Blair at DOE this morning regarding your request. She
indicated that she had no concerns with the work you are proposing within the Shoreline being
reviewed as a Shoreline Exemption as Maintenance and Repair. Since the work you are proposing is
bringing an existing use up to standard she also agreed that a Shoreline Conditional Use Permit
would not be necessary.
Please let me know if you have any further questions.
Thanks,
Jill
From: Leverette, Sara A. [mailto:sara.leverette@stoel.com]
Sent: Friday, October 27, 2017 9:52 AM
To: Jill Ding <JDing@Rentonwa.gov>; Leslie Clark <LClark@Rentonwa.gov>
Cc: Durbin, Kara <Kara.Durbin@pse.com>; Brad Strauch (bradley.strauch@pse.com)
<bradley.strauch@pse.com>; Hartje, Toni <Toni.Hartje@pse.com>; Jennifer T. Henning
<Jhenning@Rentonwa.gov>
Subject: RE: Energize Eastside, Renton segment
Jill,
My apologies for the long delay in getting you the additional information that you requested on
PSE’s request for a shoreline exemption for the aerial crossing of wires over the Cedar River.
Attached please find a full description of the transmission wire upgrade as it relates to the Cedar
River shoreline.
Please let me know if you have any questions about the attached and what you think are
appropriate next steps from here.
I hope your fall is going well!
Best regards,
Sara
Sara A. Leverette | Attorney
STOEL RIVES LLP | 600 University Street, Suite 3600 | Seattle, WA 98101-4109
Direct: (206) 386-7614 | Mobile: (503) 381-0281 | Fax: (206) 386-7500
sara.leverette@stoel.com | Bio | vCard | www.stoel.com
This email may contain material that is confidential, privileged and/or attorney work product for the sole use of the intended
recipient. Any unauthorized review, use, or distribution is prohibited and may be unlawful.
P Please consider the environment before printing this email.
From: Jill Ding [mailto:JDing@Rentonwa.gov]
Sent: Monday, August 07, 2017 1:41 PM
To: Leverette, Sara A.; Leslie Clark
Cc: Hartje, Toni; Kriner, Kerry; Jennifer T. Henning
Subject: RE: Energize Eastside, Renton segment
Sara,
I’ve spoken with Leslie Clark and she has indicated that it is okay for me to contact you directly.
Regarding your first question for the shoreline determination, our suggestion would be to have DOE
weigh in with regards to whether what you are proposing would be considered substantial
development. To frame my discussion with DOE, I would like to have a description of all work
proposed within the shoreline jurisdiction here in Renton. I would suggest that we wait to meet until
after I’ve had a chance to consult with DOE on this shoreline issue.
Thanks,
Jill
From: Leverette, Sara A. [mailto:sara.leverette@stoel.com]
Sent: Thursday, August 03, 2017 4:20 PM
To: Leslie Clark <LClark@Rentonwa.gov>
Cc: Jill Ding <JDing@Rentonwa.gov>; Hartje, Toni <Toni.Hartje@pse.com>; Kriner, Kerry
<Kerry.Kriner@pse.com>
Subject: RE: Energize Eastside, Renton segment
Leslie,
Thank you again for working with me to schedule this meeting. By way of background, PSE’s
proposed pole replacement does not involve any construction activities (temporary or otherwise) in
the shoreline, but rather would involve the stringing of a transmission line approximately 80’ (I’m
waiting for confirmation of the line height) over the shoreline. In similar situations, other
jurisdictions have used a shoreline exemption process because the line is replacing an existing line
and there are no impacts to the shoreline. PSE understands that the City has provided some
information responding to the application of the shoreline exemption process, but we have some
additional questions in light of the de minimis shoreline impacts, the likelihood of litigation in this
case, and the burdens associated with a shoreline permit hearing. Our issues are as follows:
1) PSE is struggling to find a basis in Renton’s code for the conclusion that the proposed wire
replacement is an intensification of a development. We would like to discuss how the code
supports (or does not support) this conclusion.
2) What is an EIS consistency review and what purpose does it serve where Renton is an author
of the EIS that is already underway? I understand that Toni and Jill have discussed this issue,
but, even with Toni’s help, I still have some questions.
We look forward to meeting and please let us know if there is anything you would like to discuss and
when you are available to meet.
Toni and Kerry, please pipe up if I forgot something!
Best regards,
Sara
Sara A. Leverette | Attorney
STOEL RIVES LLP | 600 University Street, Suite 3600 | Seattle, WA 98101-4109
Direct: (206) 386-7614 | Mobile: (503) 381-0281 | Fax: (206) 386-7500
sara.leverette@stoel.com | Bio | vCard | www.stoel.com
This email may contain material that is confidential, privileged and/or attorney work product for the sole use of the intended
recipient. Any unauthorized review, use, or distribution is prohibited and may be unlawful.
P Please consider the environment before printing this email.
From: Leslie Clark [mailto:LClark@Rentonwa.gov]
Sent: Wednesday, August 02, 2017 8:34 AM
To: Leverette, Sara A.
Cc: Jill Ding
Subject: Energize Eastside, Renton segment
Sara,
Thanks for the call yesterday regarding PSE’s Energize Eastside intended land use submittal to the
City of Renton. This responds to PSE’s request for a follow-up meeting to the pre-application
meeting held in June.
I’ve consulted with CED, and we believe that the most efficient way to move forward is for you to list
PSE’s questions. That gives City staff the opportunity to identify who should attend the meeting and
to do some pre-meeting legwork if necessary.
Let me know if you would like to discuss. Otherwise, I’ll look for a list of PSE’s questions from you,
then I will consult again with CED.
Thanks,
Leslie
LESLIE CLARK | Senior Assistant City Attorney
1055 S. Grady Way | Renton WA 98057
LClark@Rentonwa.gov | (425) 430-6482
EXHIBIT E
EXHIBIT F
TECHNICAL REVIEW
ENERGIZE EASTSIDE AC
INTERFERENCE ANALYSIS
Prepared for:
ESA Northwest Community
Development
5309 Shilshole Ave. NW, Suite 200
Seattle, WA 98107
Prepared by:
Stantec Consulting Services Inc.
9400 SW Barnes Road, Suite 200
Portland, OR 97225
Tel: 503-297-1631
Fax: 503-297-5429
&
Stantec Consulting Ltd.
300W-675 Cochrane Drive
Markham, ON L3R 088
Project 2000 079400
May 2, 2017, Rev 0
TECHNICAL REVIEW
ENERGIZE EASTSIDE AC INTERFERENCE ANALYSIS
Revision Chart
Rev. Reason for Change Author Reviewer
Approved
by Issue Date
0 Issued for Use WF NF NF 05/02/17
i
energize eastside ac study review 05-02-17 ifu.docx
TECHNICAL REVIEW
ENERGIZE EASTSIDE AC INTERFERENCE ANALYSIS
Sign-off Sheet
This document entitled TECHNICAL REVIEW ENERGIZE EASTSIDE AC INTERFERENCE ANALYSIS was
prepared by Stantec Consulting Services Inc./Stantec Consulting Ltd. (“Stantec”) for the
account of ESA Northwest Community Development (the “Client”). Any reliance on this
document by any third party is strictly prohibited. The material in it reflects Stantec’s professional
judgment in light of the scope, schedule, and other limitations stated in the document and in
the contract between Stantec and the Client. The opinions in the document are based on
conditions and information existing at the time the document was published and do not take
into account any subsequent changes. In preparing the document, Stantec did not verify
information supplied to it by others. Any use which a third party makes of this document is the
responsibility of such third party. Such third party agrees that Stantec shall not be responsible for
costs or damages of any kind, if any, suffered by it or any other third party as a result of decisions
made or actions taken based on this document.
Prepared by:
(signature)
Name / Title Wolfgang Fieltsch, P. Eng.
Team Lead–CP and AC Mitigation
Phone: (905) 944-6195
wolfgang.fieltsch@stantec.com
Reviewed by &
Approved by:
(signature)
Name / Title Nabil Farah, Senior Principal Power
Phone: (503) 297-1631
nabil.farah@stantec.com
ii
TECHNICAL REVIEW
ENERGIZE EASTSIDE AC INTERFERENCE ANALYSIS
Table of Contents
OVERVIEW ................................................................................................................................. 1
1.0 SCOPE OF WORK ........................................................................................................... 2
2.0 APPLICABLE STANDARDS .............................................................................................. 2
3.0 OPINION ........................................................................................................................ 2
TOC-i
TECHNICAL REVIEW
ENERGIZE EASTSIDE AC INTERFERENCE ANALYSIS
Overview
At the request of Environmental Services Associates (ESA) a review was conducted by Stantec
relating to the Energize Eastside project, which would involve upgrading of an existing 115 kV
transmission line to 230 kV. The new transmission line would consist of two 230 kV circuits,
although initially one of these circuits will be operated at 115 kV.
The proposed upgraded 230 kV transmission line would be collocated with two existing high
pressure petroleum pipelines owned by Olympic Pipe Line Company and operated by British
Petroleum (BP). These pipelines are presently collocated with the existing Eastside 115 kV circuit.
Det Norske Veritas (U.S.A.), Inc. (DNV GL) was retained by Puget Sound Energy (PSE) to perform
an AC interference study related to AC interference from the proposed 230 kV upgraded
powerline on the two existing, collocated Olympic pipelines. The study considered two route
options and several different powerline configurations, with the objective of determining the
option that would minimize the AC interference on the pipelines.
1
TECHNICAL REVIEW
ENERGIZE EASTSIDE AC INTERFERENCE ANALYSIS
1.0 Scope of Work
Stantec’s scope involved a high-level desktop review of the study report only. Confirmation of
model input parameters and modeling files was not included in the scope of this review.
2.0 Applicable Standards
The review was based on the following industry standards relevant to AC interference studies
between pipelines and powerlines:
1. NACE Standard Practice (SP) 0177, “Mitigation of Alternating Current and Lightning Effects
on Metallic Structures and Corrosion Control Systems”, 2014.
2. Institute of Electrical and Electronics Engineers (IEEE) Standard 80, “IEEE Guide for Safety in
AC Substation Grounding”, 2000.
3.0 Opinion
The primary objective of the AC interference study performed by DNV GL was to perform a
sensitivity analysis to determine the optimal route and powerline configuration to minimize the
AC interference risks on the two collocated pipelines.
An optimal route, phasing, and conductor orientation was selected to minimize the steady-state
induced AC voltages on the paralleling pipelines. Shield wires were recommended to minimize
the conductive coupling and arcing risks due to a phase-to-ground fault on the powerline
structures.
Based on Stantec’s experience and industry standards, it is our opinion that the technical
approach used to achieve this objective in the subject AC interference study is consistent with
industry practice.
The report concluded that the modeling indicated that selection of the recommended optimal
route and configuration would result in no AC mitigation requirements on the pipelines. The
report further recommends that final mitigation design should be based on field data collected
after system energization.
In Stantec’s opinion, although the study and modeling performed is sufficient as a sensitivity
analysis, it cannot be used to determine the mitigation requirements for the pipelines related to
the final design of the powerlines. Furthermore, mitigation based on field testing after
energization is also not an acceptable approach, as measurements can only be taken at test
stations, which are not necessarily located at locations with highest induced AC voltages and at
greatest AC corrosion risk. Additionally, it is not possible to assess safety and integrity risks under
powerline fault conditions in the field.
2
TECHNICAL REVIEW
ENERGIZE EASTSIDE AC INTERFERENCE ANALYSIS
As such, we recommend the following be performed in the detailed design stage of the project
prior to energization of the new powerline:
• Perform an AC interference study incorporating the final powerline route, configuration, and
operating parameters.
• Obtain and incorporate all of the pipeline parameters required for detailed modeling and
study (i.e., locations and details of above-grade pipeline appurtenances/stations, bonds,
anodes, mitigation, etc.). This should include a review of the annual test post Cathodic
Protection (CP) survey data.
• Fully assess the safety and coating stress risks for phase-to-ground faults at powerline
structures along the entire area of collocation. This assessment should include both inductive
and resistive coupling.
• Fully assess the safety and AC corrosion risks under steady-state operating conditions on the
powerline.
• Reassess the safe separation distance to minimize arcing risk based on NACE SP0177 and
considering the findings in CEA 239T817.
• Ensure that the separation distance between the pipelines and the powerline structures
exceeds the safe distance required to avoid electrical arcing.
• Design AC mitigation (as required) to ensure that all safety and integrity risks have been fully
mitigated along the collocated pipelines.
• Design monitoring systems to monitor the AC corrosion risks along the pipelines.
• Install and commission the AC mitigation and monitoring systems prior to energization of the
230 kV powerline.
• After energization, perform a site survey to ensure that all AC interference risks have been
fully mitigated under steady-state operation of the powerline.
Based on the sensitivity analysis performed by DNV GL, it is Stantec’s opinion that any remaining
AC interference risks to the pipeline identified in the detailed design stage of the project can
readily be mitigated via use of standard mitigation strategies.
3
TECHNICAL REVIEW
ENERGIZE EASTSIDE AC INTERFERENCE ANALYSIS
End of Document
END
EXHIBIT G
Energize Eastside Project
Phase I Draft Environmental Impact Statement
January 28, 2016
Prepared for the Cities of Bellevue, Kirkland, Newcastle,
Redmond, and Renton
FACT SHEET
NAME OF PROPOSAL
Energize Eastside Project
PROPONENT
Puget Sound Energy (PSE)
PROJECT LOCATION
The project involves improvements to PSE’s electrical grid in the Eastside area of King
County, Washington, to address a deficiency in electrical transmission capacity. The area
identified by PSE as having a transmission capacity deficiency is situated between the
Sammamish substation on the north end (Redmond/Kirkland area) and the Talbot Hill
substation on the south end (Renton area). Transmission improvements would need to be tied
to these two substations in order to address the need for the project; however, each alternative
has a slightly different study area (see Chapter 2 figures). The combined study area for the
project extends roughly from Lake Washington to the Novelty Hill substation (located east of
Redmond in unincorporated King County) and the Lake Tradition substation in Issaquah.
Communities in the combined study area include the following: Unincorporated King
County, Beaux Arts Village, Bellevue, Clyde Hill, Hunts Point, Issaquah, Kirkland, Medina,
Newcastle, Redmond, Renton, Sammamish, and Yarrow Point.
PROJECT DESCRIPTION
The purpose of the project is to address a projected deficiency in transmission capacity
resulting from growth in electrical demand, which could affect the future reliability of
electrical service for the Eastside. PSE proposes to construct and operate a major new
transformer served by approximately 18 miles of new high-capacity electric transmission
lines (230 thousand volts [kilovolts, or kV]) extending from Renton to Redmond. The
proposed transformer would be placed at a substation near the center of the Eastside.
Electrical power would be transmitted to this substation and the voltage lowered, or “stepped
down” (transformed), from 230 kV to 115 kV for distribution to local customers.
This Phase 1 Draft EIS evaluates the proposed 230 kV improvements as well as alternatives
to PSE’s proposal. Alternative 1 adds a new substation and has four options: constructing
new 230 kV overhead transmission lines (Option A), using existing 230 kV overhead
transmission lines (Option B), placing portions of the 230 kV line underground (Option C),
and submerging portions of the 230 kV line under water (Option D).
January 2016 FACT SHEET PHASE 1 DRAFT EIS FS-i
The EIS also considers an integrated resource approach (Alternative 2), including a
combination of energy efficiency, demand response, distributed generation, energy storage,
and peak generator components. Construction of new 115 kV lines and transformers at
existing substations (Alternative 3) is also considered. In accordance with the State
Environmental Policy Act (SEPA), a No Action Alternative is also evaluated. A detailed
summary of the alternatives evaluated in this Phase 1 Draft EIS is provided below.
SUMMARY OF ALTERNATIVES AND OPTIONS
No Action Alternative
PSE would continue to manage its maintenance programs to reduce the likelihood of
equipment failure, and would continue to stockpile additional equipment so that repairs could
be made quickly. PSE would also continue its energy conservation program systemwide and
for the Eastside.1 As appropriate, conductor replacement on existing lines would occur.
Alternative 1: New Substation and 230 kV Transmission Lines
Option A: New
Overhead
Transmission Lines
Construct a minimum of 18 miles of new overhead transmission lines
between the Talbot Hill and Sammamish substations. The new
transmission lines may be entirely within existing utility easements, or
partially in new locations currently not designated for utility operations.
A new transformer would be installed at or near one of three PSE-
owned properties that are either adjacent to existing substations or
have been purchased for future substations.
Option B: Existing
Seattle City Light
230 kV
Transmission
Corridor
Use Seattle City Light’s existing SnoKing-Maple Valley 230 kV overhead
transmission lines, and rebuild and reconductor both 230 kV
transmission lines. Loop one 230 kV line to a new transmission
substation, and loop the other 230 kV line to the Sammamish
substation.
Option C:
Underground
Transmission Lines
Place any portion of the new transmission line alignments considered
for Option A or B underground.
Option D:
Underwater
Transmission Lines
Place underwater transmission lines in Lake Washington. This option
would need to be connected to the Talbot Hill and Sammamish
substations and another centrally located substation with the new
transformer, using either overhead or underground lines.
Alternative 2: Integrated Resource Approach
Energy Efficiency
Component
Accelerate and expand the energy efficiency measures proposed under
the No Action Alternative to meet the project objectives for Energize
Eastside. Measures would include replacement of older, inefficient
appliances and lighting, adding insulation, weatherproofing, and other
similar actions.
Demand Response
Component
Reduce end-use electric customers’ electricity usage in a given time
period, or shift that usage to another time period. This requires special
metering and control equipment that can be used to adjust electricity
usage remotely, usually adjusting automatically according to pre-agreed
parameters.
FACT SHEET January 2016 FS-ii PHASE 1 DRAFT EIS
Distributed
Generation
Component
Construct distributed generation devices to generate power on PSE
customers’ property. Facilities would consist of gas turbines, anaerobic
digesters, reciprocating engines, microturbines, and fuel cells.
Energy Storage
Component
Build energy storage facilities to supplement power during peak
periods. This would involve large batteries to store energy near one or
more existing substation.
Peak Generation
Component
Build 20-megawatt peak generation plants at PSE-owned substations
within the Eastside. These systems typically burn natural gas to power a
generator used to help meet peak demand.
Alternative 3: New 115 kV Lines and Transformers
Approximately 60 miles of new overhead 115 kV lines would be constructed, and an existing
Bonneville Power Administration 230 kV line would be extended to the Lake Tradition
substation. These lines would likely follow existing utility or road rights-of-way, and would
either replace or be co-located with existing transmission and distribution lines wherever
possible.
Three new 230 kV to 115 kV transformers would be installed at the following existing
substations: Lake Tradition, Talbot Hill, and Sammamish substations. At a minimum, the
Talbot Hill substation would need to be expanded to accommodate an additional transformer
and additional security measures would be required at all three substations. Several other
substations would also need to be modified, and in some cases expanded.
1Energy efficiency improvements described under the No Action Alternative apply to all of the alternatives.
CONSTRUCTION TIMING FOR THE PROJECT
PSE studies show that Eastside customer demand will reach a point when the capacity of the
electric transmission system on the Eastside could experience a deficiency as early as winter
2017 - 2018. To be an effective solution, a project must be completed and in service by the
identified target need date.
STATE ENVIRONMENTAL POLICY ACT LEAD AGENCY
City of Bellevue is the Lead Agency.
The following municipalities are SEPA Co-Lead Agencies for the project: Kirkland,
Newcastle, Redmond, and Renton.
SEPA RESPONSIBLE OFFICIAL
Carol Helland
Development Services Land Use Director
City of Bellevue
450 110th Avenue NE
Bellevue, WA 98004
January 2016 FACT SHEET PHASE 1 DRAFT EIS FS-iii
EIS CONTACT PERSON
Heidi Bedwell
Energize Eastside EIS Program Manager
City of Bellevue
450 110th Avenue NE
Bellevue, WA 98004
Phone: (425) 452-4862
Email: HBedwell@bellevuewa.gov
CONTACT PERSON FOR EACH CO-LEAD AGENCY
City of Kirkland
Jeremy McMahan
Development Services - Planning Manager
(425) 587-3229
jmcmahan@kirklandwa.gov
City of Newcastle
Tim McHarg
Director of Community Development
(425) 649-4444
TimM@ci.newcastle.wa.us
City of Redmond
Catherine Beam
Principal Planner
(425) 556-2429
CBEAM@redmond.gov
City of Renton
Jennifer Henning
Planning Director
(425) 430-7286
Jhenning@Rentonwa.gov
GOVERNMENTAL ACTIONS
Because a preferred alternative has not been selected, it is not possible to present a complete
list of approvals and permits that would be required. Following are the most common
approvals and permits required for the types of projects presented in this document. These
approvals and permits are listed below by jurisdictional agency.
FACT SHEET January 2016 FS-iv PHASE 1 DRAFT EIS
Federal
• Section 10/404 permit—U.S. Army Corps of Engineers
• Endangered Species Act consultation—National Marine Fisheries Service and/or U.S.
Fish and Wildlife Service
State
• National Pollutant Discharge Elimination System Construction Stormwater General
Permit—Washington State Department of Ecology
• Section 401 Water Quality Certification—Washington State Department of Ecology
• Hydraulic Project Approval—Washington Department of Fish and Wildlife
• Section 106 National Historic Preservation Act or Executive Order 05-05
Consultation—Department of Archaeology and Historic Preservation
• Utility Rate Approval —Washington Utilities and Transportation Commission
Local City or County
• Shoreline substantial development or conditional use permit, or variance
• Building and related permits, as needed
• Clearing and grading permits
• Street use permits
AUTHORS AND PRINCIPAL CONTRIBUTORS
This Phase 1 Draft EIS has been prepared under the direction of the City of Bellevue, in
consultation with the co-lead agencies.
Research and analysis were provided by the following:
• Environmental Science Associates (ESA) – Alternatives development; analysis of
earth, greenhouse gas, water resources, plants and animals, energy and natural
resources, environmental health, noise, land use and housing, views and visual
resources, recreation, historic and cultural resources, public services, and utilities;
EIS document coordination and production.
• Enertech Consultants – EMF modeling and technical information.
• Asher Sheppard Consulting – EMF health effects background information.
• Heffron Transportation, Inc. – Transportation analysis.
• FCS Group – Economic analysis.
• Stantec Engineering – Alternatives development and electrical engineering technical
support.
January 2016 FACT SHEET PHASE 1 DRAFT EIS FS-v
DATE OF ISSUE
January 28, 2016
END OF COMMENT PERIOD
All comments must be postmarked or emailed before midnight, March 14, 2016.
COMMENTING ON THE DRAFT EIS
Individuals may comment on the Draft EIS by emailing or mailing written comments to:
Heidi Bedwell
Energize Eastside EIS Program Manager
Senior Planner, Land Use Division, Development Services
City of Bellevue
450 110th Avenue NE
Bellevue, WA 98004
Email: info@EnergizeEastsideEIS.org
Online at: www.EnergizeEastsideEIS.org
Commenters should include “Energize Eastside” in the subject line of the email or letter.
Individuals may also provide comments at any of the five public hearings to be held in
February and March, 2016. Each hearing will begin with an open house, followed by a short
presentation and an oral comment period. Hearings will be held as follows:
City of Kirkland Justice Center – 6:00 PM - 8:00 PM
11750 NE 118th St.
Kirkland, WA 98034
Tuesday, February 23
Renton City Hall – 6:00 PM - 8:00 PM
1055 S Grady Way
Renton, WA 98057
Thursday, February 25
Newcastle Elementary School Multipurpose Room – 2:00 PM - 4:00 PM
8400 136th Avenue SE
Newcastle, WA 98059
Saturday, February 27
Redmond City Hall – 6:00 PM - 8:00 PM
15670 NE 85th St
Redmond, WA 98052
Monday, February 29
FACT SHEET January 2016 FS-vi PHASE 1 DRAFT EIS
Bellevue City Hall – 6:00 PM - 9:00 PM
450 110th Ave NE
Bellevue, WA 98004
Tuesday, March 1
AVAILABILITY OF THE DRAFT EIS
Copies of the Phase 1 Draft EIS and/or Notices of Availability have been distributed to
agencies, tribal governments, and organizations on the Distribution List in Chapter 18.
The Draft EIS may be viewed online or downloaded from the project website
www.energizeeastsideeis.org or may be viewed at the following locations:
Libraries
Bellevue Library
1111 110th Ave. NE
Bellevue, WA 98004
Lake Hills Library
15590 Lake Hills Blvd.
Bellevue, WA 98007
Newcastle Library
12901 Newcastle Way
Newcastle, WA 98056
Newport Way Library
14250 SE Newport Way
Bellevue, WA 98006
Redmond Library
15990 NE 85th Street
Redmond, WA 98052
Renton Highlands Library
Before February 20th
2902 NE 12th Street
Renton, WA 98055
After February 20th
2801 NE 10th Street
Renton, WA 98056
Renton Library
100 Mill Avenue South
Renton, WA 98057
City Offices
City of Bellevue Development Services
Department
City Hall
450 110th Ave NE
Bellevue, WA 98004
City of Newcastle Planning Division
City Hall
12835 Newcastle Way, Suite 200
Newcastle, WA 98056
Redmond City Hall
Development Services Center (2nd floor)
15670 NE 85th St
Redmond, WA 98052
City of Renton Planning Division
City Hall, 6th floor
1055 South Grady Way
Renton, WA 98057
January 2016 FACT SHEET PHASE 1 DRAFT EIS FS-vii
Printed copies are available to purchase for cost of reproduction ($300) by contacting the
project email at info@energizeeastsideeis.org or by calling Environmental Science
Associates at (206) 789-9658. Copies of the EIS on CD may also be obtained (available at no
charge) at all four of the city offices listed directly above.
AVAILABILITY OF BACKGROUND MATERIALS
The Draft EIS includes appendices with information that is important to help understand the
EIS analysis. Other background materials developed specifically for this project and used by
the consultants are available on the website listed above.
FACT SHEET January 2016 FS-viii PHASE 1 DRAFT EIS
TABLE OF CONTENTS
FACT SHEET ........................................................................................................... FS-1
ACRONYMS AND GLOSSARY ............................................................................... AG-1
CHAPTER 1. INTRODUCTION AND SUMMARY ..................................................... 1-1
1.1 What is the project that is being evaluated in this Draft EIS? .................................1-1
1.2 Why is this EIS being prepared? .............................................................................1-4
1.3 What is the purpose and need for the Energize Eastside Project? ..........................1-4
1.4 How does Puget Sound Energy’s electrical system work? .....................................1-7
1.5 How is the SEPA review being conducted for this project? .................................1-13
1.5.1 Phase 1 and Phase 2 EIS ................................................................................1-13
1.6 How was this EIS developed? ...............................................................................1-15
1.7 How has public input been incorporated into the EIS process? ............................1-16
1.8 What are the applicant’s objectives for the Energize Eastside project and how
were they used for this draft Eis? ..........................................................................1-16
1.9 What alternatives are evaluated in the Phase 1 Draft EIS? ...................................1-17
1.9.1 No Action Alternative ...................................................................................1-17
1.9.2 Alternative 1: New Substation and 230 kV Transmission Lines ...................1-17
1.9.3 Alternative 2: Integrated Resource Approach ...............................................1-18
1.9.4 Alternative 3: New 115 kV Lines and Transformers ....................................1-18
1.10 What are the key findings of this Draft EIS? ........................................................1-18
1.11 How do the impacts of the alternatives compare? .................................................1-49
1.12 What are the areas of significant controversy? .....................................................1-56
1.12.1 Need for the Project .......................................................................................1-56
1.12.2 What Alternatives Should Be Examined .......................................................1-56
1.12.3 Impacts from the Project................................................................................1-57
1.13 What happens next in the Energize Eastside EIS process? ...................................1-57
CHAPTER 2. PROJECT ALTERNATIVES ................................................................. 2-1
2.1 What does this chapter cover? .................................................................................2-1
2.2 What are Puget Sound Energy’s project objectives for Energize Eastside? ...........2-1
2.2.1 Electrical Criteria .............................................................................................2-3
2.2.2 Non-electrical Criteria ...................................................................................2-10
2.2.3 Understanding System Contingencies and their Frequencies ........................2-11
2.2.4 Understanding Normal Winter and Summer Load Forecasting ....................2-12
2.3 Project Alternatives ...............................................................................................2-12
2.3.1 No Action Alternative ...................................................................................2-13
January 2016 TABLE OF CONTENTS PHASE 1 DRAFT EIS i
2.3.2 Alternative 1: New Substation and 230 kV Transmission Lines
(Puget Sound Energy Proposal) .................................................................... 2-15
2.3.3 Alternative 2: Integrated Resource Approach ............................................... 2-32
2.3.4 Alternative 3: New 115 kV Lines and Transformers .................................... 2-42
2.3.5 Construction Summary Table ....................................................................... 2-47
2.4 Alternatives Considered but Not Included ........................................................... 2-50
2.4.1 Use Existing BPA High-Power Transmission Line ...................................... 2-50
2.4.2 Upgrade/Adjust Existing Electrical System .................................................. 2-50
2.4.3 Larger Generation Facilities .......................................................................... 2-52
2.4.4 Submerged 230 kV Transmission Line in Lake Sammamish ....................... 2-53
2.4.5 Other Approaches ......................................................................................... 2-53
2.5 Benefits and Disadvantages of Delaying the Proposal ......................................... 2-54
CHAPTER 3. EARTH ................................................................................................. 3-1
3.1 How were earth resources in the study areas evaluated? ........................................ 3-1
3.2 What are the relevant plans, policies, and regulations? .......................................... 3-1
3.3 What earth resources and geologic hazards are present in the combined study
area? ....................................................................................................................... 3-3
3.3.1 Regional Geology and Topography ................................................................ 3-3
3.3.2 Soils ................................................................................................................. 3-3
3.3.3 Geologic Hazards ............................................................................................ 3-5
3.4 What geologic risks are present for existing electrical infrastructure? ................. 3-11
3.5 How were potential earth impacts assessed? ........................................................ 3-12
3.6 What are the likely construction impacts related to earth? ................................... 3-12
3.6.1 Construction Impacts Considered ................................................................. 3-13
3.6.2 No Action Alternative ................................................................................... 3-14
3.6.3 Alternative 1: New Substation and 230 kV Transmission Lines .................. 3-14
3.6.4 Alternative 2: Integrated Resource Approach ............................................... 3-16
3.6.5 Alternative 3: New 115 kV Lines and Transformers .................................... 3-16
3.7 How could operation of the project affect earth resources? ................................. 3-16
3.7.1 Operation Impacts Considered ...................................................................... 3-16
3.7.2 No Action Alternative ................................................................................... 3-18
3.7.3 Alternative 1: New Substation and 230 kV Transmission Lines .................. 3-19
3.7.4 Alternative 2: Integrated Resource Approach ............................................... 3-20
3.7.5 Alternative 3: New 115 kV Lines and Transformers .................................... 3-21
3.8 What mitigation measures are available for potential impacts to earth
resources? ............................................................................................................. 3-22
3.8.1 Construction Measures .................................................................................. 3-22
3.8.2 Operation Measures ...................................................................................... 3-22
TABLE OF CONTENTS January 2016 ii PHASE 1 DRAFT EIS
3.9 Are there any cumulative impacts to earth resources and can they be
mitigated?..............................................................................................................3-23
3.10 Are there any significant unavoidable adverse impacts to earth resources? .........3-23
CHAPTER 4. GREENHOUSE GAS EMISSIONS ....................................................... 4-1
4.1 How were greenhouse gas emissions in the combined study area evaluated? ........4-1
4.1.1 Greenhouse Gases Defined ..............................................................................4-2
4.1.2 Carbon Sequestration .......................................................................................4-2
4.1.3 Lifecycle Emissions .........................................................................................4-3
4.2 What are the relevant plans, policies, and regulations? ..........................................4-4
4.2.1 U.S. Environmental Protection Agency ..........................................................4-4
4.2.2 Washington State Department of Ecology ......................................................4-4
4.2.3 King County ....................................................................................................4-5
4.2.4 City Governments ............................................................................................4-5
4.2.5 Puget Sound Energy ........................................................................................4-8
4.3 What is the status of greenhouse gas emissions in the combined study area? ........4-9
4.4 How were potential impacts to greenhouse gas emissions Assessed? ..................4-10
4.5 What are the likely construction impacts related to greenhouse gas emissions? ..4-10
4.5.1 Construction Impacts Considered ..................................................................4-10
4.5.2 No Action Alternative ...................................................................................4-11
4.5.3 Alternative 1: New Substation and 230 kV Transmission Lines ...................4-11
4.5.4 Alternative 2: Integrated Resource Approach ...............................................4-15
4.5.5 Alternative 3: New 115 kV Lines and Transformers ....................................4-17
4.6 How could operation of the project affect greenhouse gas emissions? .................4-18
4.6.1 Operation Impacts Considered ......................................................................4-18
4.6.2 No Action Alternative ...................................................................................4-18
4.6.3 Alternative 1: New Substation and 230 kV Transmission Lines ...................4-18
4.6.4 Alternative 2: Integrated Resource Approach ...............................................4-18
4.6.5 Alternative 3: New 115 kV Lines and Transformers ....................................4-19
4.7 What mitigation measures are available for potential impacts to greenhouse
gas emissions? .......................................................................................................4-20
4.8 Are there any cumulative impacts to greenhouse gas emissions and can they
be mitigated? .........................................................................................................4-20
4.9 Are there any significant unavoidable adverse impacts to greenhouse gas
emissions? .............................................................................................................4-20
CHAPTER 5. WATER RESOURCES ......................................................................... 5-1
5.1 How were water resources in the combined study area evaluated? ........................5-1
5.2 What are the relevant plans, policies, and regulations? ..........................................5-2
5.3 What water resources are found in the combined study area? ................................5-6
January 2016 TABLE OF CONTENTS PHASE 1 DRAFT EIS iii
5.3.1 Streams and Rivers .......................................................................................... 5-6
5.3.2 Lakes and Ponds .............................................................................................. 5-7
5.3.3 Wetlands.......................................................................................................... 5-7
5.3.4 Floodplains ...................................................................................................... 5-8
5.3.5 Stormwater ...................................................................................................... 5-8
5.3.6 Groundwater.................................................................................................. 5-10
5.4 How were potential water resource impacts assessed? ......................................... 5-10
5.5 what are the likely construction impacts related to water resources? ................... 5-11
5.5.1 Construction Impacts Considered ................................................................. 5-11
5.5.2 No Action Alternative ................................................................................... 5-13
5.5.3 Alternative 1: New Substation and 230 kV Transmission Lines .................. 5-13
5.5.4 Alternative 2: Integrated Resource Approach ............................................... 5-18
5.5.5 Alternative 3: New 115 kV Lines and Transformers .................................... 5-18
5.6 How could operation of the project affect water resources? ................................ 5-19
5.6.1 Operation Impacts Considered ...................................................................... 5-19
5.6.2 No Action Alternative ................................................................................... 5-19
5.6.3 Alternative 1: New Substation and 230 kV Transmission Lines .................. 5-19
5.6.4 Alternative 2: Integrated Resource Approach ............................................... 5-20
5.6.5 Alternative 3: New 115 kV Lines and Transformers .................................... 5-20
5.7 What mitigation measures are available for potential impacts to water
resources? ............................................................................................................. 5-21
5.8 Are there any cumulative impacts to water resources and can they be
mitigated? ............................................................................................................. 5-21
5.9 Are there any significant unavoidable adverse impacts to water resources? ........ 5-21
CHAPTER 6. PLANTS AND ANIMALS ...................................................................... 6-1
6.1 How were plants and animals in the combined study area evaluated? ................... 6-1
6.2 What are the relevant plans, policies, and regulations? .......................................... 6-2
6.2.1 Federal and Washington State ......................................................................... 6-2
6.2.2 Local Regulations ........................................................................................... 6-4
6.3 What types of vegetation are found in the combined study area? .......................... 6-5
6.3.1 Vegetation Cover Types .................................................................................. 6-5
6.3.2 Rare Plants and High-Quality Vegetation Communities ................................ 6-5
6.3.3 Trees ................................................................................................................ 6-7
6.4 What animal species and habitats can be found in the combined study area? ........ 6-7
6.4.1 Habitat Types and Associated Species ............................................................ 6-7
6.4.2 Federal, State, and Local Listed Species ....................................................... 6-11
6.5 How were potential impacts to plants and animals assessed? .............................. 6-12
6.6 What are the likely construction impacts related to plants and animals? ............. 6-12
TABLE OF CONTENTS January 2016 iv PHASE 1 DRAFT EIS
6.6.1 Construction Impacts Considered ..................................................................6-12
6.6.2 No Action Alternative ...................................................................................6-14
6.6.3 Alternative 1: New Substation and 230 kV Transmission Lines ...................6-15
6.6.4 Alternative 2: Integrated Resource Approach ...............................................6-20
6.6.5 Alternative 3: New 115 kV Lines and Transformers ....................................6-21
6.7 How could operation of the project affect plants and animals? ............................6-22
6.7.1 Operation Impacts Considered ......................................................................6-22
6.7.2 No Action Alternative ...................................................................................6-23
6.7.3 Alternative 1: New Substation and 230 kV Transmission Lines ...................6-23
6.7.4 Alternative 2: Integrated Resource Approach ...............................................6-24
6.7.5 Alternative 3: New 115 kV Lines and Transformers ....................................6-25
6.8 What mitigation measures are available for potential impacts to plants and
animals? ................................................................................................................6-25
6.9 Are there any cumulative impacts to plants and animals and can they be
mitigated?..............................................................................................................6-26
6.10 Are there any significant unavoidable adverse impacts to plants and animals? ...6-26
CHAPTER 7. ENERGY AND NATURAL RESOURCES ............................................ 7-1
7.1. How were energy and natural resources in the combined study area evaluated? ...7-1
7.2. What are the energy delivery policies and requirements that apply to PSE? ..........7-1
7.3. What natural resources are used to generate the electrical energy provided by
PSE? ........................................................................................................................7-2
7.4. How were potential impacts to energy and natural resources assessed? .................7-3
7.5. How would construction of the project affect energy and natural resources? ........7-4
7.5.1 Construction Impacts Considered ....................................................................7-4
7.5.2 No Action Alternative .....................................................................................7-4
7.5.3 Alternative 1: New Substation and 230 kV Transmission Lines .....................7-4
7.5.4 Alternative 2: Integrated Resource Approach .................................................7-5
7.5.5 Alternative 3: New 115 kV Transmission Lines and Transformers ................7-6
7.6. What are the likely impacts to energy and natural resources from operation of
the project? ..............................................................................................................7-6
7.6.1 Operation Impacts Considered ........................................................................7-6
7.6.2 No Action Alternative .....................................................................................7-7
7.6.3 Alternative 1: New Substation and 230 kV Transmission Lines .....................7-8
7.6.4 Alternative 2: Integrated Resource Approach .................................................7-8
7.6.5 Alternative 3: New 115 kV Transmission Lines and Transformers ..............7-10
7.7. What mitigation measures are available for potential impacts to energy and
natural resources? .................................................................................................7-10
January 2016 TABLE OF CONTENTS PHASE 1 DRAFT EIS v
7.8. Are there any cumulative impacts to energy and natural resources and can
they be mitigated? ................................................................................................ 7-11
7.9. Are there any significant unavoidable adverse impacts to energy and natural
resources? ............................................................................................................. 7-11
CHAPTER 8. ENVIRONMENTAL HEALTH ............................................................... 8-1
8.1 How was environmental health evaluated for the combined study area? ............... 8-1
8.2 What are the relevant plans, policies, and regulations? .......................................... 8-1
8.2.1 Hazardous Materials ....................................................................................... 8-1
8.2.2 Public Safety Risks ......................................................................................... 8-2
8.2.3 Electric and Magnetic Fields ........................................................................... 8-7
8.2.4 Corona Ions ..................................................................................................... 8-8
8.3 What hazards are present in the combined study area or could be assocated
with the project? ..................................................................................................... 8-8
8.3.1 Hazardous Materials ....................................................................................... 8-8
8.3.2 Public Safety Risks – Activities Near Pipelines ........................................... 8-11
8.3.3 Public Safety Risks – Natural Phenomena .................................................... 8-11
8.3.4 Electric and Magnetic Fields and Corona Ionization .................................... 8-11
8.3.5 Electric and Magnetic Fields ......................................................................... 8-12
8.3.6 Corona Ions ................................................................................................... 8-22
8.4 How were potential environmental health impacts assessed? .............................. 8-22
8.5 What are the likely construction impacts related to environmental health? ......... 8-23
8.5.1 Construction Impacts Considered ................................................................. 8-23
8.5.2 No Action Alternative ................................................................................... 8-25
8.5.3 Alternative 1: New Substation and 230 kV Transmission Lines .................. 8-25
8.5.4 Alternative 2: Integrated Resource Approach ............................................... 8-31
8.5.5 Alternative 3: New 115 kV Transmission Lines and Transformers ............. 8-33
8.6 How could operation of the project affect environmental health? ........................ 8-34
8.6.1 Operation Impacts Considered ...................................................................... 8-34
8.6.2 No Action Alternative ................................................................................... 8-37
8.6.3 Alternative 1: New Substation and 230 kV Lines ......................................... 8-39
8.6.4 Alternative 2: Integrated Resource Approach ............................................... 8-42
8.6.5 Alternative 3: New 115 kV Transmission Lines and Transformers ............. 8-44
8.7 What mitigation measures are available for potential impacts to
environmental health? .......................................................................................... 8-44
8.7.1 Hazardous Materials ..................................................................................... 8-44
8.7.2 Public Safety Risks ....................................................................................... 8-46
8.7.3 EMF and Corona Ionization .......................................................................... 8-46
TABLE OF CONTENTS January 2016 vi PHASE 1 DRAFT EIS
8.8 Are there any cumulative impacts to environmental health and can they be
mitigated?..............................................................................................................8-46
8.9 Are there any significant unavoidable adverse impacts to environmental
health? ...................................................................................................................8-47
CHAPTER 9. NOISE .................................................................................................. 9-1
9.1 What is noise and how is it evaluated?...................................................................9-1
9.2 What are the relevant plans, policies, and regulations? ..........................................9-2
9.2.1 Washington State .............................................................................................9-2
9.2.2 King County ....................................................................................................9-3
9.2.3 City Codes and Policies ...................................................................................9-3
9.3 What is the existing noise environment in the combined study area?.....................9-7
9.3.1 Corona Discharge ............................................................................................9-7
9.3.2 Other Equipment Noise ...................................................................................9-8
9.4 How were potential noise impacts assessed? ..........................................................9-8
9.5 What are the likely construction impacts related to noise? .....................................9-8
9.5.1 Construction Impacts Considered ....................................................................9-8
9.5.2 No Action Alternative .....................................................................................9-9
9.5.3 Alternative 1: New Substation and 230 kV Transmission Lines ...................9-10
9.5.4 Alternative 2: Integrated Resource Approach ...............................................9-12
9.5.5 Alternative 3: New 115 kV Lines and Transformers ....................................9-13
9.6 How could operation of the project affect the noise environment? ......................9-14
9.6.1 Operation Impacts Considered ......................................................................9-14
9.6.2 No Action Alternative ...................................................................................9-14
9.6.3 Alternative 1: New Substation and 230 kV Transmission Lines ...................9-14
9.6.4 Alternative 2: Integrated Resource Approach ...............................................9-16
9.6.5 Alternative 3: New 115 kV Lines and Transformers ....................................9-17
9.7 What mitigation measures are available for potential noise impacts? ..................9-17
9.7.1 Nighttime Construction Noise .......................................................................9-17
9.7.2 Substation/Transformer Operational Noise ...................................................9-17
9.7.3 Distributed Energy Operational Noise ..........................................................9-17
9.8 Are there any cumulative impacts from noise and can they be mitigated? ...........9-18
9.9 Are there any significant unavoidable adverse noise impacts? .............................9-18
CHAPTER 10. LAND USE AND HOUSING ............................................................... 10-1
10.1 How were existing land uses and housing in the combined study areas
evaluated? .............................................................................................................10-1
10.2 What are the relevant plans, policies, and regulations? ........................................10-2
10.2.1 Comprehensive Planning Framework ...........................................................10-2
10.2.2 Shoreline Planning Framework .....................................................................10-6
January 2016 TABLE OF CONTENTS
PHASE 1 DRAFT EIS vii
10.2.3 Development and Zoning Framework ........................................................ 10-10
10.3 What are the existing land uses, population, and housing in the combined
study area? .......................................................................................................... 10-11
10.3.1 Existing Land Uses ..................................................................................... 10-11
10.3.2 Population ................................................................................................... 10-14
10.3.3 Housing Characteristics .............................................................................. 10-14
10.4 How will land use, population, and housing change in the future? .................... 10-17
10.5 How were potential impacts to land use and housing assessed? ........................ 10-18
10.6 What are the likely construction impacts to land use and housing? ................... 10-18
10.6.1 Construction Impacts Considered ............................................................... 10-18
10.6.2 No Action Alternative ................................................................................. 10-19
10.6.3 Action Alternatives ..................................................................................... 10-19
10.7 How could operation of the project affect land uses and housing? .................... 10-19
10.7.1 Operation Impacts Considered .................................................................... 10-19
10.7.2 No Action Alternative ................................................................................. 10-23
10.7.3 Alternative 1: New Substation and 230 kV Transmission Lines ................ 10-23
10.7.4 Alternative 2: Integrated Resource Approach ............................................. 10-28
10.7.5 Alternative 3: New 115 kV Lines and Transformers .................................. 10-30
10.8 What mitigation measures are available for potential impacts to land use or
housing? ............................................................................................................. 10-31
10.9 Are there any cumulative impacts to land and shoreline use or housing and
can they be mitigated? ........................................................................................ 10-31
10.10 Are there any significant unavoidable adverse impacts to land and shoreline
use or housing? ................................................................................................... 10-31
CHAPTER 11. VIEWS AND VISUAL RESOURCES ................................................... 11-1
11.1 How were viewpoints and visual resources in the combined study area
evaluated? ........................................................................................................................ 11-1
11.1.1 Visual Resources, Views, and Viewpoints Defined...................................... 11-2
11.1.2 Property Values, Views and Visual Resources ............................................. 11-2
11.2 What are the relevant plans, policies, and regulations? ........................................ 11-2
11.2.1 King County .................................................................................................. 11-3
11.2.2 Beaux Arts Village ........................................................................................ 11-3
11.2.3 Bellevue ........................................................................................................ 11-4
11.2.4 Clyde Hill ...................................................................................................... 11-4
11.2.5 Hunts Point .................................................................................................... 11-4
11.2.6 Issaquah ......................................................................................................... 11-5
11.2.7 Kirkland ........................................................................................................ 11-5
11.2.8 Medina .......................................................................................................... 11-5
TABLE OF CONTENTS January 2016 viii PHASE 1 DRAFT EIS
11.2.9 Newcastle ......................................................................................................11-6
11.2.10 Redmond ........................................................................................................11-6
11.2.11 Renton ............................................................................................................11-7
11.2.12 Sammamish ...................................................................................................11-7
11.2.13 Yarrow Point .................................................................................................11-8
11.3 What are the visual resources, viewpoints, and views in the combined study
area? ......................................................................................................................11-8
11.3.1 Visual Character on the Eastside ...................................................................11-8
11.3.2 Visual Resources ...........................................................................................11-9
11.3.3 Public Viewpoints .......................................................................................11-14
11.3.4 Private Viewpoints ......................................................................................11-17
11.3.5 Existing Light and Glare..............................................................................11-20
11.3.6 Existing Electrical Facilities ........................................................................11-20
11.4 How were Potential visual impacts assessed? .....................................................11-23
11.5 What are the likely construction impacts to views and visual resources?...........11-24
11.5.1 Construction Impacts Considered ................................................................11-24
11.5.2 No Action Alternative .................................................................................11-25
11.5.3 Alternative 1: New Substation and 230 kV Transmission Lines .................11-25
11.5.4 Alternative 2: Integrated Resource Approach .............................................11-27
11.5.5 Alternative 3: New 115 kV Lines and Transformers ..................................11-27
11.6 What are the likely operational impacts to views and visual resources? ............11-28
11.6.1 Operation Impacts Considered ....................................................................11-28
11.6.2 No Action Alternative .................................................................................11-30
11.6.3 Alternative 1: New Substation and 230 kV Transmission Lines .................11-31
11.6.4 Alternative 2: Integrated Resource Approach .............................................11-40
11.6.5 Alternative 3: New 115 kV Lines and Transformers ..................................11-41
11.7 What mitigation measures are available for potential impacts to views and
visual resources? .................................................................................................11-43
11.8 Are there any cumulative impacts to views and visual resources and can they
be mitigated? .......................................................................................................11-44
11.9 Are there any significant unavoidable adverse impacts to views and visual
resources? ............................................................................................................11-44
CHAPTER 12. RECREATION .................................................................................... 12-1
12.1 How were recreational resources in the combined study area evaluated? ............12-1
12.2 What are the relevant plans, policies, and regulations? ........................................12-1
12.3 What recreational resources are in the combined study area? ..............................12-3
12.4 How were potential impacts to recreation assessed? ............................................12-6
12.5 What are the likely construction impacts related to recreation? ...........................12-7
January 2016 TABLE OF CONTENTS PHASE 1 DRAFT EIS ix
12.5.1 Construction Impacts Considered ................................................................. 12-7
12.5.2 No Action Alternative ................................................................................... 12-8
12.5.3 Alternative 1: New Substation and 230 kV Transmission Lines .................. 12-8
12.5.4 Alternative 2: Integrated Resource Approach ............................................. 12-10
12.5.5 Alternative 3: New 115 kV Lines and Transformers .................................. 12-11
12.6 How could operation of the project affect recreation? ....................................... 12-12
12.6.1 Operation Impacts Considered .................................................................... 12-12
12.6.2 No Action Alternative ................................................................................. 12-12
12.6.3 Alternative 1: New Substation and 230 kV Transmission Lines ................ 12-13
12.6.4 Alternative 2: Integrated Resource Approach ............................................. 12-15
12.6.5 Alternative 3: New 115 kV Lines and Transformers .................................. 12-15
12.7 What mitigation measures are available for potential impacts to recreation? .... 12-16
12.7.1 Construction Measures ................................................................................ 12-16
12.7.2 Operation Measures .................................................................................... 12-16
12.8 Are there any cumulative impacts to recreation and can they be mitigated? ..... 12-16
12.9 Are there any significant unavoidable adverse impacts to recreation? ............... 12-17
CHAPTER 13. HISTORIC AND CULTURAL RESOURCES ...................................... 13-1
13.1 How were historic and cultural resources in the combined study area
evaluated? ............................................................................................................. 13-1
13.1.1 Historic Properties ......................................................................................... 13-1
13.1.2 Archaeological Resources ............................................................................. 13-2
13.2 What are the relevant plans, policies, and regulations? ........................................ 13-2
13.3 What historic and cultural resources are present in the combined study area? .... 13-3
13.3.1 Precontact Period .......................................................................................... 13-3
13.3.2 Postcontact or Historic Period ....................................................................... 13-4
13.3.3 Previous Archaeological Work ..................................................................... 13-6
13.3.4 Aboveground Historic Register Listed Properties ........................................ 13-7
13.4 How were potential impacts to historic and cultural resources assessed? .......... 13-10
13.5 What are the likely construction impacts related to historic and cultural
resources? ........................................................................................................... 13-10
13.5.1 Construction Impacts Considered ............................................................... 13-10
13.5.2 No Action Alternative ................................................................................. 13-11
13.5.3 Alternative 1: New Substation and 230 kV Transmission Lines ................ 13-11
13.5.4 Alternative 2: Integrated Resource Approach ............................................. 13-15
13.5.5 Alternative 3: New 115 kV Lines and Transformers .................................. 13-16
13.6 How could operation of the project affect historic and cultural resources? ....... 13-17
13.6.1 Operation Impacts Considered .................................................................... 13-17
13.6.2 No Action Alternative ................................................................................. 13-17
TABLE OF CONTENTS January 2016 x PHASE 1 DRAFT EIS
13.6.3 Alternative 1: New Substation and 230 kV Transmission Lines .................13-17
13.6.4 Alternative 2: Integrated Resource Approach .............................................13-18
13.6.5 Alternative 3: New 115 kV Lines and Transformers ..................................13-18
13.7 What mitigation measures are available for potential impacts to historic and
cultural resources? ..............................................................................................13-19
13.7.1 Construction Measures ................................................................................13-19
13.7.2 Operation Measures .....................................................................................13-20
13.8 Are there any cumulative impacts to historic and cultural resources and can
they be mitigated? ...............................................................................................13-20
13.9 Are there any significant unavoidable adverse impacts to historic and cultural
resources? ............................................................................................................13-20
CHAPTER 14. TRANSPORTATION .......................................................................... 14-1
14.1 How were transportation facilities in the combined study area evaluated? ..........14-1
14.2 What are the relevant plans, policies, and regulations? ........................................14-1
14.3 What are the existing transportation facilities in the combined study area? .........14-2
14.3.1 Roadways ......................................................................................................14-2
14.3.2 Parking Facilities ...........................................................................................14-6
14.3.3 Transit ............................................................................................................14-6
14.3.4 Non-motorized Facilities ...............................................................................14-8
14.4 How were potential impacts to transportation assessed? ....................................14-10
14.5 What are the likely construction impacts related to transportation? ...................14-10
14.5.1 Construction Impacts Considered ................................................................14-10
14.5.2 No Action Alternative .................................................................................14-10
14.5.3 Alternative 1: New Substation and 230 kV Transmission Lines .................14-10
14.5.4 Alternative 2: Integrated Resource Approach .............................................14-15
14.5.5 Alternative 3: New 115 kV Lines and Transformers ..................................14-16
14.6 How could operation of the project affect transportation? ..................................14-16
14.6.1 Operation Impacts Considered ....................................................................14-16
14.6.2 No Action Alternative .................................................................................14-17
14.6.3 Alternative 1: New Substation and 230 kV Transmission Lines .................14-17
14.6.4 Alternative 2: Integrated Resource Approach .............................................14-18
14.6.5 Alternative 3: New 115 kV Lines and Transformers ..................................14-18
14.7 What mitigation measures are available for potential impacts to
transportation? ....................................................................................................14-19
14.8 Are there any cumulative impacts to transportation and can they be
mitigated?............................................................................................................14-20
14.9 Are there any significant unavoidable adverse impacts to transportation? .........14-20
January 2016 TABLE OF CONTENTS PHASE 1 DRAFT EIS xi
CHAPTER 15. PUBLIC SERVICES ............................................................................ 15-1
15.1 How were public services in the combined study area evaluated? ....................... 15-1
15.2 What are the relevant plans, policies, and regulations? ........................................ 15-1
15.3 What public services are available in the combined study area? .......................... 15-2
15.3.1 Fire and Emergency Response Services ....................................................... 15-2
15.3.2 Police Services .............................................................................................. 15-6
15.4 How were potential impacts to public services assessed? .................................... 15-8
15.5 What are the likely construction impacts related to public services? ................... 15-9
15.5.1 Construction Impacts Considered ................................................................. 15-9
15.5.2 No Action Alternative ................................................................................... 15-9
15.5.3 Alternative 1: New Substation and 230 kV Transmission Lines .................. 15-9
15.5.4 Alternative 2: Integrated Resource Approach ............................................. 15-12
15.5.5 Alternative 3: New 115 kV Lines and Transformers .................................. 15-13
15.6 How could operation of the project affect public services?................................ 15-14
15.6.1 Operation Impacts Considered .................................................................... 15-14
15.6.2 What is corona-ion interference and is it a concern? .................................. 15-14
15.6.3 No Action Alternative ................................................................................. 15-16
15.6.4 Alternative 1: New Substation and 230 kV Transmission Lines ................ 15-17
15.6.5 Alternative 2: Integrated Resource Approach ............................................. 15-21
15.6.6 Alternative 3: New 115 kV Lines and Transformers .................................. 15-21
15.7 What mitigation measures are available for potential impacts to public
services? ............................................................................................................. 15-22
15.7.1 Emergency Response Services .................................................................... 15-22
15.7.2 Response Times .......................................................................................... 15-22
15.7.3 Substation Fire Risk .................................................................................... 15-23
15.8 Are there any cumulative impacts to public services and can they be
mitigated? ........................................................................................................... 15-23
15.9 Are there any significant unavoidable adverse impacts to public services? ....... 15-23
CHAPTER 16. UTILITIES ........................................................................................... 16-1
How were utilities in the combined study area evaluated? ................................... 16-1 16.1
What are the relevant plans, policies, and regulations? ........................................ 16-1 16.2
What Utilities are present in the combined study area?........................................ 16-3 16.3
16.3.1 Electrical ....................................................................................................... 16-8
16.3.2 Natural Gas ................................................................................................. 16-10
16.3.3 Petroleum Pipelines ..................................................................................... 16-11
16.3.4 Water, Wastewater, and Stormwater ........................................................... 16-12
16.3.5 Telecommunications ................................................................................... 16-13
16.3.6 Submerged Utilities and “Lake Lines” ....................................................... 16-13
TABLE OF CONTENTS January 2016 xii PHASE 1 DRAFT EIS
16.3.7 What is pipeline corrosion and why is it a concern? ...................................16-14
What are the utilities’ plans for future expansion in the combined study area? .16-16 16.4
16.4.1 Electrical ......................................................................................................16-16
16.4.2 Natural Gas ..................................................................................................16-17
16.4.3 Water and Wastewater .................................................................................16-17
How were potential impacts to utilities assessed? ..............................................16-18 16.5
What are the likely construction impacts related to utilities? .............................16-18 16.6
16.6.1 Construction Impacts Considered ................................................................16-18
16.6.2 No Action Alternative .................................................................................16-20
16.6.3 Alternative 1: New Substation and 230 kV Transmission Lines .................16-20
16.6.4 Alternative 2: Integrated Resource Approach .............................................16-25
16.6.5 Alternative 3: New 115 kV Lines and Transformers ..................................16-26
How could operation of the project affect utilities? ............................................16-27 16.7
16.7.1 Operation Impacts Considered ....................................................................16-27
16.7.2 No Action Alternative .................................................................................16-29
16.7.3 Alternative 1: New Substation and 230 kV Transmission Lines .................16-30
16.7.4 Alternative 2: Integrated Resource Approach .............................................16-34
16.7.5 Alternative 3: New 115 kV Lines and Transformers ..................................16-36
What mitigation measures are available for potential impacts to utilities? .........16-37 16.8
Are there any cumulative impacts to utilities and can they be mitigated? ..........16-38 16.9
Are there any significant unavoidable adverse impacts to utilities? ...................16-38 16.10
REFERENCES ................................................................................... 17-1 CHAPTER 17.
DISTRIBUTION LIST ......................................................................... 18-1 CHAPTER 18.
LIST OF APPENDICES
Appendix A: PSE Conservation Program
Appendix B: Potential Construction Equipment
Appendix C: Endangered and Threatened Species
Appendix D: Soil Types and Groundwater in Study Areas
Appendix E: Planning Documents Referenced for this Analysis
Appendix F: Potentially Applicable Comprehensive Plan and Shoreline Master Program
Goals and Policies
Appendix G: Applicable Polices and Code Requirements for Views and Visual Resources
Appendix H: Historic and Cultural Sites
Appendix I: Registered Historic Properties
Appendix J: Description of Applicable Historic Registers
Appendix K: Interview Questions for Fire Departments
January 2016 TABLE OF CONTENTS PHASE 1 DRAFT EIS xiii
Appendix L: Interview Questions for Police Departments
Appendix M: Pipeline Safety Requirements and Plans Relating to the Olympic Pipeline
LIST OF TABLES
Table 1-1. Regulatory and Coordinating Agencies Governing PSE ................................... 1-12
Table 1-2. Construction Impacts Comparison .................................................................... 1-50
Table 1-3. Operation Impacts Comparison ......................................................................... 1-53
Table 2-1. Peak Load Addressed Through Conservation Measures by PSE Service Area
and Year ............................................................................................................ 2-14
Table 2-2. Substation Modifications Required for Alternative 3 ........................................ 2-45
Table 2-3. Construction Summary Table ............................................................................ 2-48
Table 3-1. Soils in Combined Study Area ............................................................................ 3-4
Table 4-1. CO2 Sequestration by Vegetation Type ............................................................. 4-12
Table 5-1. Surface Water Resource Protection Framework ................................................. 5-2
Table 5-2. Groundwater Resource Protection Framework ................................................... 5-5
Table 6-1. Federal and State Regulations and Programs ...................................................... 6-2
Table 6-2. Local Regulations and Programs ......................................................................... 6-4
Table 6-3. Tree Canopy Cover in Study Area Communities with Tree Inventory
Reports ................................................................................................................ 6-7
Table 6-4. Aquatic and Terrestrial Habitats within the Combined Study Area .................... 6-8
Table 8-1. State Transmission Line Magnetic Field Standards and Guidelines ................... 8-7
Table 8-2. Summary of ICNIRP Exposure Guidelines ......................................................... 8-8
Table 8-3. Summary of ACGIH Exposure Guidelines ......................................................... 8-8
Table 8-4. IEEE Exposure Levels for 60 Hz Magnetic Fields .............................................. 8-8
Table 8-5. Properties of Materials Carried by Fuel Pipelines ............................................. 8-10
Table 8-6. Median Magnetic Fields Generated by Household Appliances in
Milligauss (mG) ................................................................................................ 8-17
Table 9-1. Exterior Sound Level Limits (Washington Administrative Code 173-60-040) .. 9-3
Table 9-2. Exterior Sound Level Limits (King County Code 12.88.020) ............................ 9-3
Table 9-3. Noise Codes and Policies of Cities in the Combined Study Area ....................... 9-4
Table 9-4. Typical Noise Levels from Construction Equipment .......................................... 9-9
Table 9-5. Construction Activity Noise Contour Distances ............................................... 9-11
Table 10-1. Alternative 1 - Existing Land Uses around Substations Needing
Expansion ...................................................................................................... 10-24
Table 10-2. Potential Land Use Restrictions for Alternative 1 ......................................... 10-26
Table 10-3. Land Use Restrictions for Alternative 2 ........................................................ 10-29
Table 10-4. Alternative 3 - Existing Land Uses around Substations Needing
Expansion ...................................................................................................... 10-30
Table 11-1. Public Viewpoints.......................................................................................... 11-14
Table 11-2. Impact Assessment Criteria ........................................................................... 11-23
TABLE OF CONTENTS January 2016 xiv PHASE 1 DRAFT EIS
Table 11-3. Applying Assessment Criteria to Assign Impact Classification ....................11-24
Table 12-1. Parks and Recreation Plans for Study Area Communities ...............................12-2
Table 12-2. Major Recreation Sites in the Combined Study Area ......................................12-6
Table 13-1. Historic Registers Applicable to this Project ...................................................13-3
Table 13-2. Precontact Time Periods ..................................................................................13-4
Table 13-3. Comparison of Recorded Archaeological Resources by Alternative ...............13-6
Table 13-4. Comparison of Historic Register Listed Properties by Alternative..................13-7
Table 14-1. Regulations, Guidelines, and Permits for Construction of Projects that
Affect the Transportation System ....................................................................14-1
Table 15-1. Fire and Emergency Medical Services (EMS) Provider for Each
Community .......................................................................................................15-2
Table 15-2. Law Enforcement Provider for Each Community ...........................................15-7
Table 16-1. Utility Providers Serving or Located in the Combined Study Area ..................16-6
LIST OF FIGURES
Figure 1-1. PSE Bulk Transmission System in the Eastside Area ........................................1-3
Figure 1-2. Eastside Customer Demand Forecast .................................................................1-6
Figure 1-3. PSE Service Area ................................................................................................1-8
Figure 1-4. Combined Study Area .........................................................................................1-9
Figure 1-5. How Electricity is Delivered from Generation to Customers ...........................1-10
Figure 1-6. Regulatory and Planning Framework for PSE ..................................................1-11
Figure 1-7. Environmental Impact Statement Process ........................................................1-14
Figure 2-1. Alternative 1 Study Area ..................................................................................2-17
Figure 2-2. Typical Pole Dimensions for 230 kV Overhead Transmission Lines ..............2-18
Figure 2-3. Transformer ......................................................................................................2-18
Figure 2-4. Lakeside Substation ..........................................................................................2-19
Figure 2-5. Alternative 1 – New Substation and 230 kV Transmission Line .....................2-20
Figure 2-6. Workers prepare to energize a transmission line ..............................................2-24
Figure 2-7. Workers Rebuilding a Transmission Line ........................................................2-24
Figure 2-8. Installation of Transmission Line .....................................................................2-24
Figure 2-1. Workers Rebuilding a Transmission Line ........................................................2-24
Figure 2-2. Submarine Cable Landing via Open Trench .................................................... 2-30
Figure 2-3. Typical Barge for 230 kV Cable Installation ................................................... 2-31
Figure 2-4. Alternative 2 Study Area ..................................................................................2-33
Figure 2-5. Additional Non-Transmission Resources Needed to Meet Project
Objectives in 2018 and 2024 ..........................................................................2-34
Figure 2-6. Example Mix of Energy Conservation, Storage, and Generation for Components
of Alternative 2 .............................................................................................2-35
Figure 2-7. Adding Insulation in an Existing Home ...........................................................2-36
Figure 2-8. Example Energy Monitoring System ................................................................2-36
Figure 2-9. Gas Turbine .....................................................................................................2-38
January 2016 TABLE OF CONTENTS PHASE 1 DRAFT EIS xv
Figure 2-18. Anaerobic Digester ......................................................................................... 2-38
Figure 2-19. Reciprocating Engine ..................................................................................... 2-38
Figure 2-20. Microturbine .................................................................................................. 2-38
Figure 2-21. Fuel Cell ........................................................................................................ 2-28
Figure 2-22. Battery Storage .............................................................................................. 2-40
Figure 2-23. Simple-Cycle Peak Generation Plant with 3 Gas-Fired Generators ............... 2-41
Figure 2-24. Alternative 3 Study Area ................................................................................ 2-43
Figure 2-25. Alternative 3 - New 115 kV Lines and Transformers .................................... 2-44
Figure 3-1. Landslide and Erosion Hazard Areas ................................................................. 3-7
Figure 3-2. Seismic Hazard Areas ...................................................................................... 3-10
Figure 4-1. Sources of GHG Emissions in Washington State .............................................. 4-9
Figure 5-1. Major Water Resources ...................................................................................... 5-9
Figure 6-1. Vegetation Cover by Type ................................................................................. 6-5
Figure 6-2. Vegetation Cover................................................................................................ 6-6
Figure 6-3. Great Blue Heron in Lake and Pond Habitat ...................................................... 6-9
Figure 6-4. Path through Marymoor Park ............................................................................. 6-9
Figure 6-5. Freshwater Wetland Habitat ............................................................................. 6-10
Figure 6-6. PSE Vegetation Management Program Zones ................................................. 6-15
Figure 7-1. Energy Sources for PSE Power .......................................................................... 7-2
Figure 8-1. Two Electrical Terms: Voltage and Current .................................................... 8-12
Figure 8-2. Electrical and Magnetic Fields Produced by Voltage and Currents ................. 8-13
Figure 8-3. Frequency and Wavelength .............................................................................. 8-13
Figure 8-4. Magnetic Field Strength Decreases with Distance ........................................... 8-15
Figure 8-5. Sample of Magnetic Field Diminishing at Distance from Transmission
Lines ................................................................................................................ 8-16
Figure 10-1. Future Land Use Designation by Type .......................................................... 10-4
Figure 10-2. Future Land Uses Map ................................................................................... 10-5
Figure 10-3. Shorelines of the State .................................................................................... 10-8
Figure 10-4. Existing Land Use by Type .......................................................................... 10-12
Figure 10-5. Existing Land Uses Map .............................................................................. 10-13
Figure 10-6. Local Area Population (2015) ...................................................................... 10-14
Figure 10-7. Housing Types In the Study Area Communities .......................................... 10-16
Figure 11-1. Views, Viewpoints, and Visual Resources ..................................................... 11-2
Figure 11-2. Wooded Neighborhood in Bellevue ............................................................... 11-9
Figure 11-3. Major Visual Resources ............................................................................... 11-12
Figure 11-4. Mount Rainier View from a neighborhood in Northwest Bellevue ............. 11-13
Figure 11-5. View of the Bellevue skyline ....................................................................... 11-13
Figure 11-6. View of Mount Rainier from Renton ........................................................... 11-13
Figure 11-7. View of Lake Washington, Seattle skyline, and the Olympic Mountain
Range from a neighborhood in Renton ........................................................ 11-13
TABLE OF CONTENTS January 2016 xvi PHASE 1 DRAFT EIS
Figure 11-8. View of Lake Sammamish and the Cascades from Neighborhood in
Northeast Bellevue .......................................................................................11-13
Figure 11-9. Lake Sammamish ..........................................................................................11-13
Figure 11-10. Public Views ...............................................................................................11-16
Figure 11-11. Percentage of View Types in the Combined Study Area ...........................11-17
Figure 11-12. Percent of Private Viewpoints Identified by King County Assessor in
Study Area Communities ..........................................................................11-18
Figure 11-13. Property View Scores ................................................................................11-19
Figure 11-14. 115 kV transmission line at the intersection of NE 8th and 136th Ave
NE in Bellevue ..........................................................................................11-20
Figure 11-15. 230 kV transmission line crossing SE May Creek Park Road in
Newcastle ..................................................................................................11-20
Figure 11-16. Lakeside Substation ....................................................................................11-20
Figure 11-17. PSE’s Eastside Electrical Transmission Infrastructure ...............................11-22
Figure 11-18. 115 kV Existing Overhead lines in a residential area of Bellevue .............11-35
Figure 11-19. 115 kV Existing Overhead lines in Bellevue affecting views of Lake
Washington and the Seattle Skyline, from a distance of 500 feet. ............11-36
Figure 11-20. PSE Transition Station at Enatai. ................................................................11-39
Figure 12-1. Recreation Sites in the Study Areas ................................................................12-5
Figure 13-1. Locations of Aboveground Historic Register Listed Properties .....................13-9
Figure 13-2. Statewide Predictive Model for Archaeological Risk ...................................13-12
Figure 14-1. Major Roadways .............................................................................................14-5
Figure 14-2. Transit Facilities .............................................................................................14-7
Figure 14-3. Major Trails ....................................................................................................14-9
Figure 16-1. Existing Electric Transmission and Natural Gas/Petroleum Pipelines ...........16-4
Figure 16-2. Existing Regional Wastewater and Water Lines ............................................16-5
Figure 16-3. Existing Electric Transmission and Natural Gas Pipelines (Combined
Study Area – South) .......................................................................................16-9
Figure 16-4. Illustration of Induction ................................................................................16-15
January 2016 TABLE OF CONTENTS PHASE 1 DRAFT EIS xvii
ACRONYMS AND GLOSSARY
Term/Acronym Description
Acetylene A colorless gas that is widely used as a fuel.
AC Alternating Current
ACGIH American Council of Governmental Industrial Hygienists
Adzes Hand tools used for woodworking.
ALS Advanced Life Support
AM Amplitude Modulation
Ambient Noise Level The existing noise environment to which one has adapted.
Amplitude Pressure level or energy content
Anaerobic Digesters A collection of processes by which microorganisms break
down biodegradable material in the absence of oxygen. The
process is used for industrial or domestic purposes to
manage waste and/or to produce fuels.
Ancillary Providing necessary support to the primary activities or
operation of an organization, institution, industry, or system.
Appurtenances An accessory or other item associated with a particular
activity.
ARCH A Regional Coalition for Housing
Arcing A luminous discharge of current that is formed when a strong
current jumps a gap in a circuit or between two electrodes.
Arterial A high-capacity urban road. The primary function of an
arterial road is to deliver traffic from collector roads to
freeways or expressways, and between urban centers at the
highest level of service possible.
ASCE American Society of Civil Engineers
Auger A tool with a large helical bit for boring holes in the ground.
Auxiliary Rubber Tire Vehicle A vehicle with spare rubber tires.
Backfill To refill an excavated hole with the material dug out of it.
Backhoe A mechanical excavator that draws toward itself a bucket
attached to a hinged boom.
Best Management Practices
(BMPs)
Measures developed on a project-specific basis to minimize
potential construction-related impacts. BMPs vary
depending on the activities involved.
January 2016 ACRONYMS AND GLOSSARY PHASE 1 DRAFT EIS AG-1
Term/Acronym Description
BiOp Biological Opinion
BIP Bellevue-Issaquah Pipeline
BKR Bellevue-Kirkland-Redmond Pipeline
Block Load The expected increase in energy demand from a specific
customer or group of customers.
BMP Best Management Practice
BPA Bonneville Power Administration
Btus British Thermal Units
Bucket Truck A truck equipped with an extendable, hydraulic boom
carrying a large bucket for raising workers to elevated,
inaccessible areas.
Bulk Power System A system for bulk transfer of electrical energy, from
generating power plants to electrical substations located
near demand centers. This is distinct from the local wiring
between high-voltage substations and customers, which is
typically referred to as electric power distribution.
CAA Clean Air Act
CAP Corrective Action Plan
Capacity Savings Program A program to reduce demand temporarily in response to a
price signal or other type of incentive, particularly during the
system’s peak periods. End-user customers receive
compensation (either through utility incentives or rate design)
to reduce non-essential electricity use or to shift electric load
to a different time, without necessarily reducing net usage.
Carbon Sink A natural environment that absorbs more carbon dioxide
than it releases.
Carcinogen A substance or agent that causes cancer.
Cathodic Protection System A technique used to control the corrosion of a metal surface
such as a pipe using an electrical current. The pipe is
connected to a more easily corroded "sacrificial metal."
CEQ Council on Environmental Quality
Certificate of Appropriateness
(COA)
The entitlement required to alter an individual landmark and
any property within a landmark district.
CFAI Commission on Fire Accreditation International
CFR Code of Federal Regulations
CH4 Methane
CHP Combined Heat and Power
ACRONYMS AND GLOSSARY January 2016 AG-2 PHASE 1 DRAFT EIS
Term/Acronym Description
CIP Critical Infrastructure Protection
Clear Zone Area where vegetation has been removed to construct a new
facility, create an access road, or meet design criteria for
operation of transmission lines.
Climate Change The changing of the earth’s climate caused by natural
fluctuations and human activities that alter the composition
of the global atmosphere.
CO Carbon monoxide
CO2 Carbon dioxide
CO2e CO2 equivalents
COA Certificate of Appropriateness
Cofferdam A watertight enclosure pumped dry to permit construction
work below the waterline, as when building bridges or
repairing a ship.
Collector A low-to-moderate-capacity road that serves to move traffic
from local streets to arterial roads.
Collisions When birds fly directly into conductors, resulting in injury or
mortality from impact.
Combined Heat and Power
(CHP) Plant
A plant designed to produce both heat and electricity from a
single heat source.
Combustion Turbine Facilities There are two types of combustion turbine technologies:
single-cycle combustion turbines and combined-cycle
combustion turbines. Electric utilities primarily use single-
cycle combustion turbines as peaking or backup units.
Concrete Pump Truck A machine used for transferring liquid concrete via a
pumping motion.
Conductor Reel Trailer Construction equipment used for overhead and underground
cabling construction.
Conductor An object or type of material that allows the flow of electrical
current in one or more directions. A transmission line is an
electrical conductor. Conductivity, in general, is the capacity
to transmit electricity.
Conservation Voltage
Reduction
Refers to controlling PSE’s distribution voltage at slightly
reduced levels to conserve energy.
Corrective Action Plan (CAP) List of corrective actions that are to be made manually by
local electrical system dispatchers to control local electrical
problems.
January 2016 ACRONYMS AND GLOSSARY PHASE 1 DRAFT EIS AG-3
Term/Acronym Description
Corona The electrical ionization of the air that occurs near the
surface of the energized conductor and suspension
hardware because of very high electric field strength.
Corona Discharge Occurs when the voltage of the line exceeds the insulating
capability of air. May result in audible noise such as random
crackling or hissing being produced by the transmission
lines.
Corona Ionization The electrical breakdown of air in very strong electric fields.
Critical Areas Areas identified by counties and local municipalities as
needing to be protected. Critical areas include: geologic
hazard areas, frequently flooded areas, wetlands, streams,
fish and wildlife habitat conservation areas (FWHCAs), and
critical aquifer recharge areas.
Crustal Faults Faults formed by deformation of the earth’s crust.
Cultural Resource Collective evidence of the past activities and
accomplishments of people. Buildings, objects, features,
locations, and structures with scientific, historic, and cultural
value are all examples of cultural resources.
CWA Cascade Water Alliance
DAHP Washington State Department of Archaeology and Historic
Preservation
dB Decibels
dBA A-weighted decibels
DC Direct Current
DDT Dichlorodiphenyltrichloroethane, a colorless, crystalline,
tasteless and almost odorless organochloride known for its
insecticidal properties.
Demand Response Program An incentive-based program that encourages electric power
customers to temporarily reduce their demand for power at
certain times in exchange for a reduction in their electricity
bills. Some demand response programs allow electric power
system operators to directly reduce load, while in others,
customers retain control. Customer-controlled reductions in
demand may involve actions such as curtailing load,
operating on-site generation, or shifting electricity use to
another time period.
Dielectric Having the property of transmitting electric force without
conduction; insulating.
Directional Boring A steerable trenchless method of installing underground
pipes, conduits, and cables in a shallow arc along a
prescribed bore path by using a surface-launched drilling rig,
with minimal impact on the surrounding area.
ACRONYMS AND GLOSSARY January 2016 AG-4 PHASE 1 DRAFT EIS
Term/Acronym Description
Dispatch Generation Short-term determination of the optimal output of a number
of electricity generation facilities to meet the system load,
given the transmission and operational constraints.
Distributed Generation Power generation at the point of consumption.
Distribution Efficiency When goods and services are consumed by those who need
them most.
Distribution System The final stage in the delivery of electric power; it carries
electricity from the transmission system to individual
consumers.
DNR Washington State Department of Natural Resources
DOE U.S. Department of Energy
Dredging To clean out the bed of a harbor, river, or other water body
by scooping out mud, weeds, and rubbish with a dredge.
Duct Bank An assembly of conduits installed underground between
buildings, structures, or devices to allow installation of power
and communication cables. They may either be directly
buried in earth, or encased in concrete (sometimes with
reinforcing rebar).
Eastside An area of King County, Washington, roughly defined as
extending from Renton in the south to Redmond in the north,
and between Lake Washington and Lake Sammamish.
EBCC East Bellevue Community Council
Ecology Washington State Department of Ecology
EIS Environmental Impact Statement
Electrocutions When birds directly contact energized and grounded
conductors or equipment.
Electromagnetic Of or relating to the interrelation of electric currents or fields
and magnetic fields.
Electromagnetic Interference Disturbance generated by an external source that affects an
electrical circuit by electromagnetic induction, electrostatic
coupling, or conduction.
Electric and Magnetic Fields
(EMF)
Invisible areas of energy often referred to as radiation that
are associated with the use of electrical power and various
forms of natural and man-made lighting. Also referred to as
electromagnetic fields.
Electric Field The electric force per unit charge.
ELF Extremely Low Frequency
Emergency Limit A specific level of electrical loading that a system, facility, or
element can support or withstand for a finite period.
January 2016 ACRONYMS AND GLOSSARY PHASE 1 DRAFT EIS AG-5
Term/Acronym Description
EMI Electromagnetic Interference
EMS Emergency Medical Services
ENA Energy Networks Association
ESA Endangered Species Act
Endangered Species A species of animal or plant that is seriously at risk of
extinction. These species are listed by state or federal
agencies to implement protection measures.
Environmentally Acceptable A solution that, through the environmental review process,
would be found to minimize, to the extent practicable, the
environmental impacts on the affected communities.
EPA U.S. Environmental Protection Agency
Epidemiology The study of patterns and possible causes of diseases in
human populations.
EPF Essential Public Facility
EPRI Electric Power Research Institute
Erosion Hazard An area where soils may experience severe to very severe
erosion from construction activities or through changes in
surficial conditions that expose soils to new erosive forces.
Erosive forces can come from precipitation, changes in
drainage patterns, removal of vegetation, wind, or wave
action. Certain types of soil, such as silts, are generally more
prone to erosion hazards. The potential for erosion also
increases as the slope steepness increases.
ERP Emergency Response Plan
Essential Public Facility (EPF) A concept established by state law (RCW 36.70A.200 and
WAC 365-196-550), intended to ensure that necessary
facilities that are typically difficult to site can in fact be
placed appropriately.
Excavator Large machine for removing soil from the ground, especially
on a building site.
FAA Federal Aviation Administration
Facility Response Plan (FRP) A plan prepared by certain facilities that store and use oil to
demonstrate the facility's preparedness to respond to a
worst-case oil discharge.
FCC Federal Communications Commission
FEMA Federal Emergency Management Agency
FERC Federal Energy Regulatory Commission
FHWA Federal Highway Administration
ACRONYMS AND GLOSSARY January 2016 AG-6 PHASE 1 DRAFT EIS
Term/Acronym Description
Firm Load Electricity supplies that are intended to be available at all
times during a period covered by an agreement.
FM Frequency Modulated
Foreground The part of a view that is nearest to the observer.
Fossil Fuels Buried combustible geologic deposits of organic materials,
formed from decayed plants and animals that have been
converted to crude oil, coal, natural gas, or heavy oils by
exposure to heat and pressure in the earth's crust over
hundreds of millions of years.
Frequency The number of cycles that occur in 1 second, measured in
hertz (Hz).
FRP Facility Response Plan
Ft Feet
Fuel Cell A cell producing an electric current directly from a chemical
reaction.
FWHCA Fish and Wildlife Habitat Conservation Area
G Gauss
Gas Turbine A facility typically consisting of an air compressor and one or
more combustion chambers where liquid or gaseous fuel is
burned and the hot gases are passed to the turbine. The hot
gases expand to drive the generator and are then used to
run the compressor.
GHG Greenhouse Gas
GHG Emissions Any of the atmospheric gases that contribute to the
greenhouse effect by absorbing infrared radiation produced
by solar warming of the Earth's surface. They include carbon
dioxide (CO2), methane (CH4), nitrous oxide (NO2), and water
vapor.
Generating Unit Any combination of physically connected generators,
reactors, boilers, combustion turbines, and other equipment
operated together to produce electric power.
Generator Machine for converting mechanical energy into electricity.
Geologic Hazard Areas Areas susceptible to erosion, sliding, earthquake, or other
geologic events.
GIS Geographic Information Systems
GPS Global Positioning System
January 2016 ACRONYMS AND GLOSSARY PHASE 1 DRAFT EIS AG-7
Term/Acronym Description
Grounding Conductor A wire on a transmission pole, used for protection from
lightning strikes that connects the static wire to the ground
rod. Visually recognizable as the wire running the entire
length of the pole, top to bottom.
Grounding Rules Grounding is a means to provide safety to electrical workers
and any people who may come in contact with structures
such as streetlights, mast arms, metal poles, and guy wires.
The NESC provides rules on grounding components as a
means to safeguard any person from injury that could be
caused by electrical potential.
Groundwater Recharge A hydrologic process where water moves downward from
surface water to groundwater. Recharge is the primary
method by which water enters an aquifer.
gWh Gigawatt Hours
GWP Global Warming Potential
Haul Route A crude, temporary road built to facilitate the movement of
people, equipment, and materials during construction.
Hazardous Material Any substance or material that could adversely affect the
safety of the public, handlers, or carriers during
transportation.
Hazardous Waste Waste that is dangerous or potentially harmful to human
health or the environment. Hazardous wastes can be liquids,
solids, gases, or sludges. They can be discarded commercial
products, like cleaning fluids or pesticides, or the byproducts
of manufacturing processes.
HCA High Consequence Area
HDD Horizontal Directional Drilling
HFCs Hydrofluorocarbons
High Consequence Land Use A use that, if located in the vicinity of a hazardous liquid
pipeline, would present an unusually high risk in the event of
pipeline failure due to its function, including utilities providing
regional service.
High Pressure Natural Gas
Mains
The portion of the natural gas distribution system that
operates at pressures greater than 60 pounds per square
inch gage (psig).
Historic Resource A prehistoric or historic archaeological site, as well as
historic sites, buildings, structures, objects, districts, and
landscapes.
Hoe Ram A ram powered by an auxiliary hydraulic system on an
excavator. Demolition crews employ the hoe ram for jobs too
large for jackhammering or areas where blasting is not
possible due to safety or environmental issues.
ACRONYMS AND GLOSSARY January 2016 AG-8 PHASE 1 DRAFT EIS
Term/Acronym Description
HOV High Occupancy Vehicle
HPA Hydraulic Project Approval
HPFF High-Pressure Fluid Filled
HUD U.S. Department of Housing and Urban Development
HVAC Heating, Ventilating, and Air Conditioning
Hz Hertz
IARC International Agency for Research on Cancer
ICES International Committee on Electromagnetic Safety
ICNIRP International Commission on Non-Ionizing Radiation
Protection
IEEE Institute of Electrical and Electronics Engineers
Impressed Current Anode One type of anode used in a cathodic protection system to
reduce pipe corrosion.
Insulator (electrical) A material whose internal electric charges do not flow freely,
and therefore make it nearly impossible to conduct an
electric current under the influence of an electric field.
Insulators are used in electrical equipment to support and
separate electrical conductors without allowing current
through themselves. They are often used to attach electric
power distribution or transmission lines to utility poles and
transmission towers. They support the weight of the
suspended wires without allowing the current to flow through
the tower to ground.
Integrated Resource Plan
(IRP)
A plan prepared by PSE and updated every 2 years,
describing how forecasted annual peak and energy demand
will be met into the future. The IRP process considers a full
range of power sector investments to meet new demand for
electricity, not only in new generation sources, but also in
transmission, distribution, and demand-side measures such
as energy efficiency on an equal basis.
Interstate 405 (I-405) A freeway that serves as the primary north-south facility on
the east side of Lake Washington, connecting to I-5 in
Lynnwood to the north and Tukwila to the south.
Interstate 90 (I-90) An east-west freeway that traverses the entire continental
United States, connecting to Seattle in the west and Boston,
Massachusetts, in the east.
IRP Integrated Resource Plan
January 2016 ACRONYMS AND GLOSSARY PHASE 1 DRAFT EIS AG-9
Term/Acronym Description
Issaquah Alps The unofficial name for the highlands near the city of
Issaquah, and includes Cougar Mountain, Squak Mountain,
Tiger Mountain, Taylor Mountain, Rattlesnake Ridge,
Rattlesnake Mountain, and Grand Ridge.
Jack-and-Bore Drilling A method of installation that simultaneously ‘jacks’ casing
while rotating helical augers within the casing to remove
spoil. Hydraulic jacks located on the bore machine in the
sending shaft provide the thrust that pushes the casing
through the ground. The rotating augers carry the spoil to the
back of the casing pipe for removal by muck bucket,
excavator or conveyor.
K4C King County – Cities Climate Collaboration
Ksat A measurement of saturated hydraulic conductivity
(permeability) that refers to the ability of soil to transmit
water.
kV Kilovolts
kV/M Kilovolts per Meter
Kyoto Protocol An international treaty among industrialized nations that sets
mandatory limits on greenhouse gas emissions.
Labrets Personal adornment items made of stone or bone, worn in
the lower lip.
Lanceolate projectile points A particular style of chipped stone artifacts used to tip
arrows, dart points or spears.
Landslide Hazard Areas Areas mapped by local jurisdictions where there is evidence
of past landslides, where the slope is 15 percent to 40
percent and the soils are underlain by silt or clay that can
perch groundwater, or where the slope is steeper than 40
percent, regardless of soil type.
Ldn (DNL) Day-Night Average Sound Level
Lead Agency The agency responsible for all procedural aspects of SEPA
compliance. Typically it is the agency proposing the project,
but lead agency status may be transferred to another agency
through an agency agreement.
LED Light-Emitting Diode
Leq Equivalent Sound Level
LID Low-Impact Development
Line Truck (electrical) A truck used to transport personnel, tools, and material for
electric supply line work.
ACRONYMS AND GLOSSARY January 2016 AG-10 PHASE 1 DRAFT EIS
Term/Acronym Description
Lifecycle Emissions Emissions associated with the creation and existence of a
project, including emissions from the manufacture,
transportation of the component materials, and from the
manufacture of the machines required to produce the
component materials.
Liquefaction A loss of soil strength and stiffness caused by earthquake
shaking or other rapid loading.
Lmax Instantaneous Maximum Noise Level
LNG Liquefied Natural Gas
Load Shedding Cutting off the electric current on certain lines when the
demand for electricity exceeds the power supply capability
of the network. A last-resort measure used by an electric
utility company to avoid a total blackout of the power
system.
µT Microtesla
M Meters
Magnetic Field Magnetic effect of electric currents and magnetic materials.
Max Load Maximum amount of something a system is designed to
handle or the maximum amount of something that the
system can produce.
Mauls Hand tools used for woodworking
Metro King County Metro Transit
mG Milligauss
Microturbines Miniature rotating machines that convert fluid energy into
mechanical energy.
Middens Archaeological deposits consisting of refuse from human
activities, usually composed of a mixture of soil, charcoal,
and various food remains such as bone, shell, and
carbonized plant remains; may also contain human remains.
MMT Million Metric Tons
MUTCD Manual on Uniform Traffic Control Devices
MVA Megavolt Amperes
MW Megawatts
N-0 When the electrical system is operating normally.
N-1 Outage condition that can occur at any time when a single
element trips offline.
January 2016 ACRONYMS AND GLOSSARY PHASE 1 DRAFT EIS AG-11
Term/Acronym Description
N-1-1 An N-1 outage followed by a period of time to manually
adjust the system to a secure state, followed by a second N-
1 outage.
N-2 Outage condition that occurs when a single event trips
multiple facilities.
N2O Nitrous Oxide
NAAQS National Ambient Air Quality Standards
NACE National Association of Corrosion Engineers
Nameplate Capacity The number registered with authorities for classifying the
power output of a power station usually expressed in
megawatts (MW).
National Electric Safety Code The safety guidelines that PSE follows during the installation,
operation, and maintenance of transmission lines and
associated equipment. The NESC contains the basic
provisions considered necessary for worker and public
safety under specific conditions, including electrical
grounding and protection from lightning strikes.
National Pollutant Discharge
Elimination System (NPDES)
A program authorized by the Clean Water Act to control
water pollution by regulating point sources that discharge
pollutants into waters of the United States.
Natural Gas Pipeline Safety
Act
An act passed in 1968 (now called the Pipeline Safety Law,
49 USC Section 60101 et seq.). Gives the federal
government authority over pipeline safety for transporting
hazardous liquids, natural gas, and other gases. The intent is
for states to assume responsibility for intrastate pipeline
safety, while the federal government (U.S. Department of
Transportation, Research and Special Programs
Administration, Office of Pipeline Safety) retains
responsibility for interstate pipeline safety.
Nearshore Environment An indefinite zone extending waterward from the shoreline,
typically to a water depth of about 10 feet, and providing
unique habitat for aquatic species.
NEPA National Environmental Policy Act
NERC North American Electric Reliability Corporation
NESC National Electric Safety Code
NHPA National Historic Preservation Act
NIEHS National Institute of Environmental Health Science
NMFS National Marine Fisheries Service
NO2 Nitrogen Dioxide
ACRONYMS AND GLOSSARY January 2016 AG-12 PHASE 1 DRAFT EIS
Term/Acronym Description
Noise Contour A line on a map that represents equal levels of noise
exposure.
Noise Receptor A location where noise can interrupt ongoing activities.
Sensitive receptors for noise are generally considered to
include hospitals, nursing homes, senior citizen centers,
schools, churches, libraries, and residences.
Normal Operating Limit A specific level of electrical loading that a system, facility, or
element can support or withstand through the daily demand
cycles without loss of equipment life.
NPDES National Pollutant Discharge Elimination System
NRCA Natural Resource Conservation Area
NRCS Natural Resources Conservation Service
NRHP National Register of Historic Places
Olympic Pipeline Two steel pipeline systems, 16 inches and 20 inches in
diameter, that transport gasoline, diesel, and jet fuel
(petroleum products) from Blaine, Washington to Portland,
Oregon. The pipelines are buried approximately 3 to 4 feet
below the ground surface.
Open-Cut Trenching Excavating a trench for the manual installation of an
underground pipe or cable.
OPLC Olympic Pipe Line Company
OPS Office of Pipeline Safety
OSHA Occupational Safety and Health Administration
PCBs Polychlorinated Biphenyls
Peak Generation Plant A supplemental power plant that operates only when
demand for power is high. These plants often run on natural
gas.
Peak Power Demand (event) The maximum load during a specified period of time.
Perched A term to describe a water table (or aquifer) located above an
impermeable layer of rock or sediment, above the main
water table/aquifer but below the surface of the land.
PFCs Perfluorocarbons
PHMSA Pipeline Hazardous Materials Safety Administration
PHS Priority Habitat and Species
Pile Driver A machine for driving piles into the ground.
PIPA Pipelines and Informed Planning Alliance
January 2016 ACRONYMS AND GLOSSARY PHASE 1 DRAFT EIS AG-13
Term/Acronym Description
Pipeline Corrosion Deterioration and destruction of pipe material due to
electrochemical processes and other reactions of pipeline
materials with their environment.
PM Particulate Matter
Postcontact Dating to after the point of contact between European-
American peoples (including explorers, fur traders, and
military personnel) with Native American peoples. In Seattle,
the Postcontact or historic period is generally considered to
have started with the arrival of the Denny Party in 1851.
Post Insulator An insulator suitable for higher voltage applications. The
conductor (transmission line) is fixed on top of the insulator
via a connector clamp. The fixing clamps are located on the
top and bottom of the insulator.
Power Grid A system of synchronized power providers and consumers
connected by transmission and distribution lines and
operated by one or more control centers.
Precontact Dating prior to the point of contact between European-
American peoples (including explorers, fur traders, and
military personnel) with Native American peoples. In Seattle,
the Precontact period is considered to have ended with the
arrival of the Denny Party in 1851.
Problem Nests When nest material on utility towers touches energized
equipment, potentially conducting electricity when wet and
igniting, resulting in outages and hazards to the nesting
birds.
Programmatic EIS An environmental impact statement (EIS) that addresses in
general terms the environmental effects of long-term, multi-
step programs.
Projectile Points Chipped stone artifacts used to tip arrows, dart points, or
spears.
Proven Technology Technology that has successfully operated with acceptable
performance and reliability within a set of predefined criteria.
It has a documented track record for a defined environment,
meaning there are multiple examples of installations with a
history of reliable operations. Such documentation shall
provide confidence in the technology from practical
operations, with respect to the ability of the technology to
meet the specified requirements.
PSAP Public Safety Answering Point
PSCAA Puget Sound Clean Air Agency
PSE Puget Sound Energy
ACRONYMS AND GLOSSARY January 2016 AG-14 PHASE 1 DRAFT EIS
Term/Acronym Description
PSE’s Green Power program A program where Puget Sound Energy buys electricity from
independent clean-energy producers that generate electricity
from wind, sun, biogas and other renewable sources. It adds
electricity to the grid, which offsets some of the conventional
power used.
PSRC Puget Sound Regional Council
PSRP Pipeline Spill Response Plan
Puget Sound Basin An elongated, north-south trending depression in western
Washington between the Olympic Mountain Range to the
west and the Cascade Mountain Range to the east.
Puget Sound Regional
Council (PSRC)
An association of cities, towns, counties, ports, and state
agencies that serves as a forum for developing policies and
making decisions about regional growth management,
environmental, economic, and transportation issues in the
four-county central Puget Sound region of Washington state.
Puller A device for separating two components that are secured by
press fitting them.
RAS Remedial Action Scheme
RCRA Resource Conservation and Recovery Act
RCW Revised Code of Washington
Reciprocating Engine Typically a heat engine that uses one or more reciprocating
pistons to convert pressure into a rotating motion.
Remedial Action Scheme
(RAS)
A scheme designed to detect predetermined electrical
system conditions and automatically take corrective actions
that may include, but are not limited to, adjusting or tripping
(shutting down) generation, shedding load, or reconfiguring a
system.
RD&D Research, Development, and Demonstration
Rill A small stream
Right-of-Way (electric) A corridor of land on which electric lines may be located. The
transmission owner may own the land in fee, own an
easement, or have certain franchise, prescription, or license
rights to construct and maintain lines.
Sacrificial Anode Highly active metals that are used to prevent a less active
material surface from corroding. Sacrificial anodes are
created from a metal alloy with a more negative
electrochemical potential than the other metal it will be used
to protect.
Saturated Hydraulic
Conductivity
A property that describes the ease with which a fluid (usually
water) can move through saturated media such as soil.
January 2016 ACRONYMS AND GLOSSARY PHASE 1 DRAFT EIS AG-15
Term/Acronym Description
SBCC State Building Code Council
SCAP Strategic Climate Action Plan
SCENIHR Scientific Committee on Emerging and Newly Identified
Health Risks
SCFF Self-Contained Fluid Filled
SCL Seattle City Light
Scoping An initial step in the SEPA and NEPA environmental review
process, where agencies, tribes, and the public learn about
the proposed project and provide comments on the content
that should be covered in the Environmental Impact
Statement (EIS). Often, comments on the scope describe
potential environmental impacts or suggest alternatives that
should be evaluated.
Seiche Waves A series of standing waves of an enclosed body or partially
enclosed body of water caused by earthquake shaking.
Seismic Hazards The primary effects of earthquakes, such as ground
displacement from fault rupture and ground shaking, as well
as secondary effects including liquefaction, settlement,
tsunamis, and seiche waves.
SEPA State Environmental Policy Act
Settlement Increase in vertical strain on the soil causes the soil to
compact.
Sequestration Long-term storage of carbon dioxide or other forms of
carbon.
Service Levels Measures of system reliability, such as the number and
hours of power interruption considered acceptable within a
specified time period.
Sharrow A street marking placed in the travel lane to indicate where
people should preferably cycle.
Shed Load Measure of last resort to prevent the collapse of the power
system region-wide. When there is insufficient power station
capacity to supply the demand (load) from all the customers,
the electricity system becomes unbalanced, which can
cause it to trip out regionally (a blackout), and which could
take days to restore. PSE increases supply or reduces
demand to bring the system back into balance by switching
off parts of the network in a planned and controlled manner.
Sheet Erosion The uniform removal of soil in thin layers by the forces of
overland stormwater flow.
ACRONYMS AND GLOSSARY January 2016 AG-16 PHASE 1 DRAFT EIS
Term/Acronym Description
Sheet Piles A group of piles made of timber, steel, or prestressed
concrete set close together to resist lateral pressure, as from
earth or water. Combined sheet pile walls are mostly used in
marine applications where they provide increased stiffness
combined to regular sheet pile walls.
Sheet Piling A construction technique used to retain soil during
excavation that involves installing interlocking steel sheets
along the planned excavation perimeter or shoreline.
Shoreline Areas Areas of regulated shorelines that are identified by local
governments via their shoreline master programs. Shoreline
areas are classified into specific environment designations
based on the existing use pattern, the biological and physical
character of the shoreline, and the goals and aspirations of
the community. Depending on the shoreline environment
assigned, local governments assign different use allowances.
Common shoreline environments include: high-intensity,
shoreline residential, urban conservancy, rural conservancy,
natural, and aquatic.
Soldier Pile Driving An earth retention technique that retains soil, using vertical
steel piles that are drilled or driven at regular intervals along
the planned excavation perimeter, with horizontal lagging
between piles.
SF6 Sulfur Hexafluoride
SF-E Single Family – Suburban Estates
SF-S Single Family – Suburban
Simple-Cycle Gas-Fired
Generator
Gas turbine that is connected to an electrical generator. In
the gas turbine, air is compressed in the gas compressor.
Energy is added to the compressed air by burning liquid or
gaseous fuel in the combustor. The hot, compressed air is
expanded through a gas turbine, which drives both the
compressor and an electric power generator. It can be
started up quickly, bringing electricity on-line whenever it is
needed. Simple-cycle power plants are often used to provide
peak load or standby service.
SMA Shoreline Management Act
Small Hydro The development of hydroelectric power on a scale serving a
small community or industrial plant.
Smart Growth An urban planning and transportation concept that
concentrates growth in compact walkable urban centers to
avoid sprawl. It also advocates compact, transit-oriented,
walkable, bicycle-friendly land use, including neighborhood
schools, complete streets, and mixed-use development with
a range of housing choices.
SMP Shoreline Master Program
January 2016 ACRONYMS AND GLOSSARY PHASE 1 DRAFT EIS AG-17
Term/Acronym Description
SO2 Sulfur Dioxide
SPU Seattle Public Utilities
Stepped Down To reduce or decrease voltage.
Photovoltaic System A power system designed to supply usable solar power by
means of photovoltaics. Also known as “solar farms.”
Significant Tree Trees that are specifically defined and protected for their
unique ecological and aesthetic value.
Soldier Pile Barriers Retaining walls using steel piles or reinforced concrete piles
spaced at regular intervals.
Spill Prevention and Control
Plan
A plan to prevent the discharge of oil or other substances
into water bodies.
SR State Route
State Route 520 An east-west freeway that connects I-5 to the west in
Seattle, and SR 203 to the east in unincorporated King
County.
Static Wire The top wire on a transmission pole that bleeds lightning
surges off the transmission lines during a storm. Without a
static wire, lightning-induced voltage would otherwise build
up on the lines, causing damage. The static wire is
connected to the grounding conductor.
Statistically Significant An interpretation of statistical data that indicates that an
occurrence was probably the result of a causative factor and
not simply a chance result. Statistical significance at the 1%
level indicates a 1 in 100 probability that a result can be
ascribed to chance.
Stormwater Pollution
Prevention Plan (SWPPP)
A plan describing best management practices (BMPs) to
control and treat stormwater.
Study Area Communities Beaux Arts Village, Bellevue, Clyde Hill, Hunts Point,
Issaquah, Kirkland, Medina, Newcastle, Redmond, Renton,
Sammamish, and Yarrow Point.
Subduction Zone The place where two plates of the Earth’s crust come
together with one riding over the other, often resulting in the
formation of volcanoes inland.
Substation Facility with equipment that switches, changes, or regulates
electric voltage.
SWPPP Stormwater Pollution Prevention Plan
T Tesla
Take Pursuing, shooting, poisoning, wounding, killing, capturing,
trapping, collecting, molesting, or disturbing eagles.
ACRONYMS AND GLOSSARY January 2016 AG-18 PHASE 1 DRAFT EIS
Term/Acronym Description
TCDD Dioxin
Telecommunication Line A pipe, cable, or an arrangement of lines of wire or other
conductors, by which telephone or other kinds of
communications are transmitted and received.
Tensioner A device that applies a force to create or maintain tension.
The force may be applied parallel to, or perpendicular to, the
tension it creates.
Thermal Runaway A positive feedback loop where an increase in cell
temperature and pressure leads to an uncontrolled heat
reaction.
Threatened Species Any species (including animals, plants, fungi, etc.) that are
vulnerable to endangerment in the near future.
Trackhoe A hydraulic excavator that is used in construction to dig
holes or trenches for infrastructure.
Transformer A device used to change the voltage of an alternating current
in one circuit to a different voltage in a second circuit, or to
partially isolate two circuits from each other. Transformers
consist of two or more coils of conducting material, such as
wire, wrapped around a core (often made of iron). The
magnetic field produced by an alternating current in one coil
induces a similar current in the other coils. If there are fewer
turns on the coil that carries the source of the power than
there are on a second coil, the second coil will provide the
same power but at a higher voltage. This is called a step-up
transformer. If there are fewer turns on the second coil than
on the source coil, the outgoing power will have a lower
voltage. This is called a step-down transformer.
Transformed The byproduct of a process through which energy is
changed from one form to another. Oftentimes, this refers to
the change in voltage of an electrical current.
Transmission The bulk transfer of electrical energy from generating power
plants to electrical substations located near demand centers.
Transmission Line A system of structures, wires, insulators, and associated
hardware that carry electric energy from one point to another
in an electric power system. Lines are operated at relatively
high voltages varying from 69 kV up to 765 kV, and are
capable of transmitting large quantities of electricity over
long distances.
Transmission Line Splicing The act of cutting into an existing transmission line to add a
new connection to that line or extend the line.
Trench To dig a long cut or trench into the ground.
Trenchless Construction A type of subsurface construction work that requires few
trenches or no continuous trenches.
January 2016 ACRONYMS AND GLOSSARY PHASE 1 DRAFT EIS AG-19
Term/Acronym Description
TSP Tubular Steel Pole
Turbidity A measure of water clarity indicating how much materials
suspended in the water reduce the passage of light through
the water. Suspended materials could include soil particles,
algae, plankton, microbes, or other substances.
Turbine A machine that generates rotary mechanical power from the
energy produced by a stream of fluid (such as water, steam,
or hot gas).
UGA Urban Growth Area
Urban Growth Areas/ Urban
Growth Boundaries
The areas immediately adjacent to city limits where
development can occur at urban densities.
USACE U.S. Army Corps of Engineers
U.S. Conference of Mayors
Climate Protection Agreement
An agreement where participating cities commit to: (1) strive
to meet or beat the Kyoto Protocol targets in their own
communities; (2) urge their state governments, and the
federal government, to enact policies and programs that
meet or beat the greenhouse gas emission reduction target
suggested for the United States in the Kyoto Protocol (7%
from 1990 levels by 2012) and urge the U.S. Congress to
pass the bipartisan greenhouse gas reduction legislation.
USDA U.S. Department of Agriculture
USFWS U.S. Fish and Wildlife Service
USGS U.S. Geological Survey
UTC Washington State Utilities and Transportation Commission
Underbuild To place transmission and distribution lines on the same
poles.
Utility Locates The process of identifying and labeling underground utility
lines. Excavating without knowing the location of
underground utilities can result in damage, which can lead to
service disruptions.
Variable-Load Resources A renewable energy source that cannot be dispatched due to
its fluctuating nature, like wind power and solar power, as
opposed to a controllable renewable energy source such as
hydroelectricity, or biomass, or a relatively constant source
such as geothermal power.
ACRONYMS AND GLOSSARY January 2016 AG-20 PHASE 1 DRAFT EIS
Term/Acronym Description
Vault An underground room providing access to subterranean
public utility equipment, such as switchgear for electrical
equipment. Utility vaults are commonly constructed of
reinforced concrete boxes, poured concrete, or brick. They
are placed at regular intervals along an underground
transmission or distribution line to allow access to the line for
installation and maintenance of the line.
Viewpoints Locations from which visual resources can be viewed.
Typically associated with residential properties or publicly
accessible recreation areas, such as parks, trails, and open
spaces.
Views The observation of a visual resource from a particular
location, such as a private residence or a public park.
Visual Resources Natural and constructed features of a landscape that are
viewed by the public and contribute to the overall visual
quality and character of an area. Such features often include
distinctive landforms, water bodies, vegetation, or
components of the built environment that provide a sense of
place, such as city skylines.
V/M Volts per Meter
WAC Washington Administrative Code
Wall Loss The loss of material on the inside or outside of a casing or
tubing due to corrosion.
Washington State Growth
Management Act (GMA)
Requires state and local governments to manage
Washington’s growth by identifying and protecting critical
areas and natural resource lands, designating urban growth
areas, preparing comprehensive plans, and implementing
those plans through capital investments and development
regulations.
Watt (W) The unit of electrical power equal to one ampere under a
pressure of one volt. A watt is equal to 1/746 horse power.
Wavelength The distance between a peak on the wave and the next peak
of the same polarity.
WDFW Washington State Department of Fish and Wildlife
WECC Western Electricity Coordinating Council
Wedges Hand tools used for woodworking.
Wellhead Protection Area A surface and subsurface land area regulated to prevent
contamination of a well or well-field supplying a public water
system. This program, established under the Safe Drinking
Water Act (42 U.S.C. 330f-300j), is implemented through
state governments.
WHBR Washington Heritage Barn Register
January 2016 ACRONYMS AND GLOSSARY PHASE 1 DRAFT EIS AG-21
Term/Acronym Description
WHO World Health Organization
WHR Washington Heritage Register
Wind Turbine A turbine that generates electricity via a large vaned wheel
that is rotated by the wind.
WNHP Washington Natural Heritage Program
WRIA Water Resources Inventory Area
WSDOT Washington State Department of Transportation
XLPE (Cross-Linked
Polyethylene)
The most common polymeric insulation material, widely used
as electrical insulation in power cables of all voltage ranges.
It is especially well suited to medium-voltage applications.
ACRONYMS AND GLOSSARY January 2016 AG-22 PHASE 1 DRAFT EIS
CHAPTER 1. INTRODUCTION AND
SUMMARY
The City of Bellevue and its partner Eastside Cities (partner Cities) are jointly conducting a
phased environmental review process under the State Environmental Policy Act (SEPA) for
the “Energize Eastside” Project proposed by Puget Sound Energy (PSE). Energize Eastside is
a proposal to build new electrical infrastructure to serve PSE’s customers in the area between
Lake Washington and Lake Sammamish, in King County, Washington. This first phase
assesses the comprehensive range of impacts and implications associated with broad options
for addressing PSE’s objectives, in a non-project or programmatic Environmental Impact
Statement (EIS). The second phase of this EIS process will assess project-level alternatives,
as described in Section 1.5. This chapter provides an overview of the project and a summary
of the findings of the Phase 1 Draft EIS. The project includes numerous terms that may not
be familiar to all readers. Words shown in italics when they first appear in the document are
included in the glossary, which follows the Table of Contents and precedes this chapter.
1.1 WHAT IS THE PROJECT THAT
IS BEING EVALUATED IN THIS
DRAFT EIS?
PSE is proposing to construct and operate a new 230
kilovolt (kV) to 115 kV electrical transformer served by
approximately 18 miles of new high-capacity electric
transmission lines (230 kV) extending from Renton to
Redmond. The proposed transformer would be placed at a
substation site near the center of the Eastside. The
Eastside is an area of King County, Washington, roughly
defined as extending from Renton in the south to
Redmond in the north, and between Lake Washington and
Lake Sammamish. Electrical power would be transmitted
to this substation and the voltage lowered, or “stepped
down” (transformed), from 230 kV to 115 kV for
distribution to local customers.
This set of facilities is proposed in order to address a
deficiency in electrical transmission capacity during peak
periods that has been identified by PSE through its system
planning process. This deficiency is expected to arise as a
result of anticipated population and employment growth
on the Eastside, and it is expected to negatively affect
service reliability for Eastside customers within the next
few years. The project would improve reliability for
Eastside communities and would supply the needed
What is an electrical
transformer? An electrical
transformer is a stationary
piece of equipment that
converts electricity from one
voltage to another. For
Energize Eastside, the
transformer would convert 230
kV power to 115 kV power to
supply the local electrical
distribution system.
What is a transmission line? A
transmission line is a system of
support structures and wires
that typically carry electricity
from a power source to a
substation or between
substations. In western North
America’s electrical grid
system, transmission lines are
operated at voltages of 115 kV,
230 kV, 500 kV, and greater.
What is a substation? A
substation is a facility with
equipment that switches,
changes, or regulates electric
voltage. Substations typically
include transformers and other
equipment and obtain power
from transmission lines.
January 2016 CHAPTER 1 INTRODUCTION AND SUMMARY 1-1
PHASE 1 DRAFT EIS
electrical capacity for anticipated growth and development on the Eastside.
Based on federally mandated planning standards, PSE’s analysis found that the existing
transmission system could place Eastside customers and/or the regional power grid at risk of
power outages or system damage during peak power events due to cold or hot weather. PSE’s
analysis concluded that the most effective solution was to add a 230-to-115 kV transformer
within the center of the Eastside to relieve stress on the existing 230-to115 kV transformers
that currently supply the area. This would need to be fed by new 230 kV transmission lines
from the north and south. Figure 1-1 shows the Eastside and the locations of existing
substations and transmission lines, and the area where a new substation and new 230 kV lines
are proposed. The 230 kV system is proposed because that is the next highest voltage line
(greater than the existing115 kV lines) that PSE could feasibly install and operate consistent
with the regional grid system. As illustrated in Figure 1-1, there is no 230 kV transmission
line that reaches the center of the Eastside area.
This Phase 1 Draft EIS evaluates the proposed 230 kV improvements as well as alternatives
to PSE’s proposal as described in more detail in Chapter 2.
CHAPTER 1 January 2016 1 -2 INTRODUCTION AND SUMMARY
PHASE 1 DRAFT EIS
Figure 1-1. PSE Bulk Transmission System in the Eastside Area
Source: Nexant
January 2016 CHAPTER 1 INTRODUCTION AND SUMMARY 1-3
PHASE 1 DRAFT EIS
1.2 WHY IS THIS EIS BEING PREPARED?
Discussions between partner Cities and PSE determined that the proposal is likely to have
significant adverse environmental impacts. Pursuant to SEPA, a Threshold Determination of
Significance was issued as required in the Washington Administrative Code (WAC) 197-11-
360 on April 30, 2015.
To address the potential for significant environmental impacts, PSE submitted an application
for processing of an EIS with the City of Bellevue. As the largest and potentially most
affected city, the City of Bellevue agreed with the other partner Cities to take the role of lead
agency, consistent with WAC 197-11-944. The City of Bellevue is directing overall
preparation of the EIS. Partner Cities including the Cities of Kirkland, Newcastle, Redmond,
and Renton have reviewed preliminary versions of this Draft EIS and provided input on its
preparation.
This Phase 1 Draft EIS is the first phase of a two-phase Draft EIS process to evaluate the
potential for significant environmental impacts (see Section 1.5.1 for an explanation about
the Phase 1 Draft EIS and the Phase 2 Draft EIS). The Phase 1 Draft EIS broadly evaluates
the general impacts and implications associated with feasible and reasonable options
available to address PSE’s identified objectives for the project. The evaluations conducted
during Phase 1 will be used to narrow the range of alternatives for consideration in the Phase
2 Draft EIS. The Phase 2 Draft EIS will be a project-level evaluation, describing impacts at a
site-specific and project-specific level. This approach is consistent with the requirements for
Phased Review outlined in WAC 197-11-060 (5)(c).
1.3 WHAT IS THE PURPOSE AND NEED FOR THE
ENERGIZE EASTSIDE PROJECT?
PSE has determined that there is a need to construct a new
230 kV bulk electrical transmission line and an associated
electrical substation east of Lake Washington to supply
future electrical capacity and improve the reliability of the
Eastside’s electrical grid. PSE provided two documents
that describe the need: the Eastside Needs Assessment
Report and the Supplemental Eastside Needs Assessment
Report (Gentile et al., 2014, 2015). These are referred to
collectively as PSE’s Eastside Needs Assessment.
To better understand PSE’s project proposal, the EIS Consultant Team obtained clearance
and reviewed internal utility planning and operations information used by PSE in developing
the Energize Eastside Project proposal. Because of security concerns, this information is
released only to individuals with approved security clearance and who can meet other
evaluation factors established by the Federal Energy Regulatory Commission (FERC)
allowing restricted disclosure of Critical Energy Infrastructure Information (FERC, 2007).
What is bulk electrical
transmission? Bulk electrical
transmission is a system for
transfer of electrical energy,
from power generation
plants to electrical
substations near or within
demand centers.
CHAPTER 1 January 2016 1 -4 INTRODUCTION AND SUMMARY
PHASE 1 DRAFT EIS
The EIS Consultant Team, represented by Stantec (an electrical system planning and
engineering subconsultant working in support of the Energize Eastside EIS effort), has
reviewed this background information and studied the process used by PSE to establish a
need for the proposed Energize Eastside Project. Stantec prepared a memorandum evaluating
the stated need for the project, and confirmed that PSE’s Eastside Needs Assessment was
conducted in accordance with industry standards for utility planning (Stantec, 2015). See
Appendix A for more information.
As outlined in WAC 197-11-060 (3)(a), it is the responsibility of the lead agency to make
certain that a proposal that is the subject of environmental review is properly defined. The
process of defining the proposal includes an objective understanding of the need for the
project, to enable a thorough understanding of the project’s objectives (see Chapter 2) and
technical requirements, and in order to accurately identify feasible and reasonable project
alternatives for consideration in the EIS. As noted in WAC 197-11-060(3)(a)(iii), proposals
should be described in ways that encourage considering and comparing alternatives, and
agencies are encouraged to describe proposals in terms of objectives rather than preferred
solutions. An understanding of the need for the project helps in clarifying the objectives that
have been used to develop the broad alternatives.
This EIS will not be used to reject or validate the need for the proposal. Rather, the EIS is
intended to identify alternatives that could attain or approximate PSE’s objectives at a lower
environmental cost and disclose potential significant adverse environmental impacts
associated with all alternatives identified.
The deficiency in transmission capacity on the Eastside that PSE has identified is based on a
number of factors. It arises from growing population and employment, changing
consumption patterns associated with larger buildings, more air-conditioned space, and a
changing regulatory structure that requires a higher level of reliability than was required in
the past. The regulatory changes that underlie the heightened concerns about reliability trace
back to an August 2003 blackout in the midwestern and northeastern portions of North
America that affected 55 million customers.1 PSE has concluded that the most effective and
cost-efficient solution to meet its objectives is to site a new 230 kV transformer in the center
of the Eastside, which would be fed by new 230 kV transmission lines from the north and
south (Stantec, 2015).
The population of the Eastside is expected to grow at a rate of approximately 1.2 percent
annually over the next decade, and employment is expected to grow at an annual rate of
approximately 2.1 percent, a projection based on internal forecasting conducted by PSE. For
this forecast PSE used demographic data based on U.S. Census information and the Puget
Sound Regional Council. PSE also relies on Moody’s Analytics U.S. Macroeconomic
Forecast, a long-term forecast for the U.S. economy, with adjustments for PSE’s service
territory using equations that relate national to regional conditions. Local economic data are
provided by the Washington State Employment Security Department, U.S. Bureau of Labor
1 See U.S. - Canada Power System Outage Task Force Final Report on the August 14, 2003 Blackout in the
United States and Canada: Causes and Recommendations, April 2004.
January 2016 CHAPTER 1 INTRODUCTION AND SUMMARY 1-5
PHASE 1 DRAFT EIS
Statistics and Bureau of Economic Analysis, and local
organizations such as the Washington Builders Association
(Gentile et al., 2015).
This forecast is based on the assumption that economic
activity has a significant effect on energy demand. Given
the nature of expected development, PSE has projected that
electrical demand will grow at an annual rate of 2.4
percent. As described in PSE’s Eastside Needs Assessment,
this growth rate takes into account population and
employment growth as well as expected “block load”
growth that PSE is aware will be coming in the next 10
years (Gentile et al., 2014, 2015).
Without adding at least 74 megawatts (MW) of transmission capacity for local peak periods
in the Eastside, a deficiency could develop as early as winter of 2017 - 2018 or summer of
2018, putting customers at risk of load shedding (forced power outages) (Stantec, 2015).
According to PSE projections, the 74 MW would marginally meet the demand through 2018
(Gentile et al., 2015). Figure 1-2 shows PSE’s projected growth in load for the eastside from
2014 to 2024 and the capacity of its transmission system.
Figure 1-2. Eastside Customer Demand Forecast
Source: Gentile et al., 2015.
Based on these projections, load demand could increase to a point where, if adverse weather
conditions occur and one or more components of the system are not operating for any reason,
load shedding could be required in order to protect the Eastside and the rest of the regional
grid. This is because, once the threshold is crossed, the physical limitations of the system are
such that even the slightest overload will produce overheating that can damage equipment,
and larger overloads will produce overheating more quickly. Once equipment is in an
overload condition, the options are to let it fail or take it out of service. Both conditions leave
the Eastside in a vulnerable state where the system is incapable of reliably serving customer
What is a block load? A block
load is the expected increase
in energy demand from a
specific customer or group of
customers. PSE regularly asks
its largest customers if they
anticipate substantial increases
in their electrical demand, to
help estimate energy
consumption growth expected
to occur independent of
employment or population
growth rates.
CHAPTER 1 January 2016 1 -6 INTRODUCTION AND SUMMARY
PHASE 1 DRAFT EIS
load. At that point, further actions such as load shedding may be needed in order to keep the
system intact within the Eastside service area and beyond. By the end of the 10-year forecast
period, a large number of customers would be at risk, and the load shedding requirement
could be as high as 133 MW (Stantec, 2015). Specifically, PSE’s estimate is that in the
summer 2024 scenario, over 211,000 customers experience rotating outages on up to 9 days
over a period of 16 days. In the winter 2023-2024 scenario, around 175,000 customers
experience rotating outages on up to 13 days over a period of 29 days (Nexant, 2015).
The load area in question is situated between two existing
sources of bulk electrical power: the Sammamish
substation on the north end (Redmond/Kirkland area) and
the Talbot Hill substation on the south end (Renton area)
(Figure 1-1). These two sites are the closest substations
that bring 230 kV power supply to the Eastside, and
therefore supply power to support most of this geographic
area. Increases or decreases in load that are not directly
supplied by these two substations, or power flow to other
parts of the system outside the service area, have minimal effect on the ability of these
substations to supply load. Because of the configuration and limited capacity of the
transmission system within the Eastside, a direct change in electrical demand for power
flowing through these two substations, or a change in power being supplied to these two
substations, will affect the Eastside area. Once the higher voltage (230 kV) is transformed
down to a lower voltage (115 kV) at these two substations, the system is limited by the
physical capacity of the conductors and transformers that connect those two substations to the
load and feed the area (Stantec, 2015).
1.4 HOW DOES PUGET SOUND ENERGY’S ELECTRICAL
SYSTEM WORK?
PSE is a regulated utility that serves approximately 1.1 million customers with electricity in a
4,500-square-mile service area (PSE, 2013a). Figure 1-3 shows PSE’s service area for both
electricity and gas service. This service area includes the study area for the Energize Eastside
project. Study areas were developed for each of the three action alternatives evaluated in this
Phase 1 Draft EIS (depicted on Figures 2-4, 2-5, and 2-6 in Chapter 2), because each
alternative would affect slightly different geographic area. The combined study area is shown
in Figure 1-4.
What is a conductor? An
object or type of material that
allows the flow of electrical
current in one or more
directions. The wires on a
transmission line are
conductors.
January 2016 CHAPTER 1 INTRODUCTION AND SUMMARY 1-7
PHASE 1 DRAFT EIS
Figure 1-3. PSE Service Area
Source: PSE, 2016
CHAPTER 1 January 2016 1 -8 INTRODUCTION AND SUMMARY
PHASE 1 DRAFT EIS
Energize Eastside EIS 140548
Figure 1-4
Combined Study Area
SOURCE: King County 2015; ESA 2015;
Puget Sound Energy 2015; WA Ecology 2014.
Lake Washington
Lake
Sammamish
Bellevue Sammamish
Issaquah
Renton
Newcastle
RedmondKirkland
Beaux Arts
Medina
Clyde
Hill
Hunts
Point
Yarrow
Point
Mercer
Island
Kent
Maple
ValleyCovington
Tukwila
SeaTac
Seattle
Ardmore
Berrydale
Hazelwood
Pickering
Clyde Hill
Lakeside
Sammamish
Talbot Hill
Novelty Hill
Lake Tradition
Existing Substation
Roadway
Unincorporated
King County
Alternative 1
(waterside)
Alternative 3
Water bodies
City Limit
U:\GIS\GIS\Projects\14xxxx\D140548_EastsidePSETransmisisonCoor\MXD\Com binedAlts.m xd
0 2.5
Miles
Note: This map is for reference only. It is not guaranteed that the information is accurate or complete.
The Eastside represents approximately 14 percent of PSE’s total electrical load. PSE is part
of a western regional system, through which electricity is produced elsewhere and
transported to the Eastside along high-voltage transmission lines. As electricity nears end
users, the voltage is reduced (using transformers) and redistributed through transmission
substations and distribution substations. Figure 1-5 provides an overview of how electrical
transmission and distribution systems work.
Power is carried on high-voltage transmission lines (230 kV and greater) from generating
facilities to the Eastside via the Sammamish substation in Redmond and Talbot Hill
substation in Renton. From these substations, voltage is reduced to 115 kV and distributed to
numerous Eastside distribution substations (PSE, 2013b). See Figure 1-1 above and Figure
16-1 in Chapter 16 for a map that shows PSE’s existing electrical system on the Eastside and
vicinity.
Figure 1-5. How Electricity is Delivered from Generation to Customers
The Energize Eastside Project is intended to address an identified deficiency in the capacity
of PSE’s transmission system. It does not address the sources of generation, which at present
are primarily located outside of the Eastside area. PSE conducts a separate planning process
called an Integrated Resource Plan regarding its sources of energy (PSE, 2013a).
PSE’s electric delivery system is regulated and coordinated by several state and federal
agencies, including FERC, North American Electric Reliability Corporation (NERC),
Western Electricity Coordinating Council (WECC), and Washington Utilities and
CHAPTER 1 January 2016 1 -10 INTRODUCTION AND SUMMARY
PHASE 1 DRAFT EIS
Transportation Commission (UTC). PSE cooperates and supports ColumbiaGrid in its
regional planning processes. Figure 1-6 shows the agencies involved in regulation of PSE’s
transmission system. The general roles of each agency are described briefly in parentheses in
Figure 1-6 and in further detail in Table 1-1.
Figure 1-6. Regulatory and Planning Framework for PSE
FERC: Federal Energy Regulatory Commission; FRCC: Florida Reliability Coordinating Council; MRO:
Midwest Reliability Organization; NERC: National Electric Reliability Corporation; NPCC: Northeast Power
Coordinating Council; RF: Reliability First; SERC: Southeastern Electric Reliability Council; SPP RE:
Southwest Power Pool Regional Entity; TRE: Texas Reliability Entity; UTC: Washington State Utilities and
Transportation Commission; WECC: Western Electricity Coordinating Council. Source: WECC 2015
Canadian Provincial
Authorities
FERC
(Open Access to
Transmission)
NERC
(Nationwide Reliability)
WECC
(Western Region Reliability)
ColumbiaGrid
(NW Regional
Reliability and
Planning)
UTC
(Statewide Reliability,
Safety, Rates, and
Energy Planning)
January 2016 CHAPTER 1 INTRODUCTION AND SUMMARY 1-11
PHASE 1 DRAFT EIS
Table 1-1. Regulatory and Coordinating Agencies Governing PSE
Federal Energy
Regulatory
Commission (FERC)
FERC is a U.S. federal agency that regulates interstate transmission of
electricity, natural gas, and oil, as well as Liquefied Natural Gas (LNG)
terminals, interstate natural gas pipelines, and hydropower projects.
FERC requires any public utility (including PSE) that owns, controls, or
operates facilities used for transmission of electric energy in interstate
commerce to provide open access transmission service comparable to
that provided by transmission owners (such as PSE) to themselves (18
CFR 35.28).
North American
Electric Reliability
Corporation (NERC)
NERC is a not-for-profit international regulatory authority whose
mission is to ensure the reliability of the bulk power system in North
America, as certified by FERC. NERC develops and enforces Reliability
Standards and annually assesses seasonal and long‐term reliability.
PSE is required to meet the Reliability Standards and is subject to fines
if noncompliant.
Western Electricity
Coordinating
Council (WECC)
WECC is a Utah nonprofit corporation with the mission to foster and
promote reliability and efficient coordination in the Western
Interconnection, which includes much of western North America. The
PSE service area is in the WECC region. WECC develops and
implements Regional Reliability Standards and WECC Regional Criteria
for the Western Interconnection. PSE is part of the Western
Interconnection and is obligated to meet the Regional Reliability
Standards.
ColumbiaGrid ColumbiaGrid is a nonprofit membership corporation formed to:
improve reliability of the transmission grid and efficiency in its use;
provide cost-effective transmission planning and expansion; develop
and facilitate the implementation of solutions relating to improved use
and expansion of the interconnected Northwest transmission system;
and support effective market monitoring within the Northwest and
within the Western Interconnection while considering environmental
concerns, regional interests, and cost-effectiveness. The corporation
itself does not own transmission, but its members and the parties to its
agreements own and operate an extensive network of transmission
facilities. As a signatory to ColumbiaGrid, PSE is obligated to meet the
objectives of operating a reliable electric grid.
Utilities and
Transportation
Commission (UTC)
The UTC is a Washington state regulatory agency. The UTC requires
that PSE make its electric service available to all residents and
businesses within its service area, and that the service must be
delivered in a safe and reliable manner. This is known as the
“obligation to serve” and is codified in Washington state law. This
means that PSE shall operate a system that is safe and delivers
reliable power, thus minimizing interruptions and outages. The UTC
has the authority to levy fines against the company for failure to
comply with regulatory requirements.
The UTC requires providers of electricity to provide service on demand in support of growth
that occurs in their service areas. PSE conducts an ongoing capacity planning process to
ensure its power supply and infrastructure are adequate to meet anticipated future needs
(PSE, 2013a). The 2013 Integrated Resource Plan is the strategic plan for securing reliable
and cost-effective energy resources (PSE, 2013a). PSE develops both short-range and long-
CHAPTER 1 January 2016 1 -12 INTRODUCTION AND SUMMARY
PHASE 1 DRAFT EIS
range infrastructure plans based upon economic, population, and load growth projections, as
well as information from large customers and government stakeholders. The plan is reviewed
annually with periodic updates to the plan. PSE’s revised plan was submitted to the UTC
November 30, 2015, but was not included in this Draft EIS because it was completed too late
in this EIS process. It will be considered in Phase 2. The 2015 Integrated Resource Plan
(PSE, 2015) is available for review on PSE’s website at
https://www.pse.com/aboutpse/EnergySupply/Pages/Resource-Planning.aspx.
1.5 HOW IS THE SEPA REVIEW BEING CONDUCTED
FOR THIS PROJECT?
1.5.1 Phase 1 and Phase 2 EIS
The Eastside Cities (Bellevue, Kirkland, Newcastle, Redmond, and Renton) determined that
a Phased EIS (WAC 197-11-060(5)), supported by the EIS Consultant Team and in
collaboration with the applicant, PSE, would be the best approach to adequately evaluate the
proposal. The first phase, for which this Draft EIS has been prepared, programmatically
evaluates the potential environmental impacts of various alternatives to be considered for
addressing the identified project need. This Phase 1 Draft EIS broadly describes the types of
impacts that the alternatives could cause and mitigation that would be available to minimize
or avoid such impacts. It also describes any significant impacts that would be unavoidable for
each alternative. This broad evaluation is intended to provide decision-makers and
community members with a better understanding of what constructing and operating the
alternative methods would mean to the community, and how to best evaluate the
environmental impacts of project-level alternatives in Phase 2.
Following release of the Phase 1 Draft EIS, comments will be reviewed and responded to, in
a Phase 1 Draft EIS comment summary. These comments will be used to inform the
alternatives carried forward into the Phase 2 Draft EIS, which will include additional detail
on the proposed project alternatives.
The Phase 1 Draft EIS generally does not analyze impacts associated with specific
development at specified geographic locations. The Phase 2 Draft EIS will include project-
level alternatives based on more defined geographic locations and a more detailed analysis of
potential environmental impacts. Figure 1-7 illustrates the overall process for preparing the
two phases of the Draft EIS. A Final EIS will be prepared to respond to comments on both
Draft EIS documents.
The Phase 1 Draft EIS and Phase 2 Draft EIS together are intended to provide a
comprehensive analysis of the project and alternatives. The Phase 2 Draft EIS will be a
supplement to the Phase 1 Draft EIS as described in WAC 197-11-600 and WAC 197-11-620,
and as part of a Phased EIS process per WAC 197-11-060(5). Commenting is invited for each
of the Draft EIS stages and at each of the scoping stages. The Final EIS will include
responses to comments on both Draft EIS documents and will be used by the partner Cities to
support any permit decisions required.
January 2016 CHAPTER 1 INTRODUCTION AND SUMMARY 1-13
PHASE 1 DRAFT EIS
Figure 1-7. Environmental Impact Statement Process
CHAPTER 1 January 2016 1-14 INTRODUCTION AND SUMMARY
PHASE 1 DRAFT EIS
1.6 HOW WAS THIS EIS DEVELOPED?
The EIS was developed under the direction of the City of Bellevue, working closely with its
partner Cities and its consultants. As previously noted, the project is proposed by PSE, a
regulated utility. Therefore, PSE developed the project objectives and helped to define
alternatives that would attain or approximate the proposal’s objectives, as required by SEPA.
The City of Bellevue and its team refined the Phase 1 alternatives to meet SEPA
requirements, including development of a No Action Alternative.
The following major steps were taken to develop the Phase 1 Draft EIS:
1. Programmatic alternatives were defined through an iterative process with input by the
EIS Consultant Team, PSE, City of Bellevue, and the other partner Cities. After
examining the materials provided by PSE regarding its planning process for the
project, alternatives were selected that would broadly define different ways of
approaching the deficiency in transmission capacity identified by PSE. One approach
would use 230 kV transmission lines as PSE proposes; one would use alternative
methods that would minimize the need for new transmission lines; and one would use
115 kV transmission lines (which are more common on the Eastside and smaller in
scale than 230 kV) along with substation upgrades. These three alternatives plus a No
Action Alternative were carried forward in Phase 1 EIS scoping, which commenced
in April 2015.
2. Phase 1 EIS public scoping outreach was conducted to assist in identifying
technically viable alternatives that address PSE’s reported deficiency in electrical
transmission capacity. Scoping comments were requested to focus on identification of
viable alternatives and associated impacts. Five public meetings were held at venues
in Bellevue, Kirkland, Newcastle, and Renton, along with opportunities to provide
comments online. More than 400 comments in the form of website forms, emails,
oral testimony, and letters were received during scoping, as summarized in the Phase
1 Draft EIS Scoping Summary and Final Alternatives (City of Bellevue, 2015).
3. As a result of scoping, the alternatives were expanded and refined. The EIS
Consultant Team reviewed all alternatives proposed during scoping, made a technical
review of the efficacy of the proposed alternatives, and screened the alternatives
against PSE’s criteria for an effective solution as listed in PSE’s 2015 Supplemental
Solutions Report (Gentile et al., 2015). Staff representing each of the partner Cities
discussed the findings, and a final set of alternatives was established by agreement
among the Cities and PSE. These are also summarized in the Phase 1 Draft EIS
Scoping Summary and Final Alternatives (City of Bellevue, 2015). The alternatives
reflect the 19 project criteria developed by PSE (described in detail in Chapter 2).
The Phase 1 Draft EIS includes three action alternatives and the No Action
Alternative. All alternatives would attain or approximate PSE’s objectives.
Alternatives 2 and 3 would not fully meet all objectives, but would address the
objectives sufficiently enough to be reasonable for consideration at this phase of
analysis.
January 2016 CHAPTER 1 INTRODUCTION AND SUMMARY 1-15
PHASE 1 DRAFT EIS
4. Input received during scoping was also used to define the environmental analysis
needed, including methods used, area of study, and other topics. The topics to be
studied were also summarized in the Phase 1 Draft EIS Scoping Summary and Final
Alternatives (City of Bellevue, 2015).
5. Each chapter of this Phase 1 Draft EIS describes the methods used by the EIS
Consultant Team to analyze potential environmental impacts. This process included
consultation with PSE and numerous agencies throughout the Eastside, including the
partner Cities as well as other study area communities.
6. The City of Bellevue and the other partner Cities reviewed drafts prepared by the EIS
Consultant Team and provided comments for EIS Consultant Team response.
Following this review, PSE reviewed a preliminary version of a portion of this Phase
1 Draft EIS for technical accuracy. PSE was provided and reviewed sections of
Chapter 1 and Chapter 2 that did not contain analysis or conclusions of the analysis.
The City of Bellevue, as SEPA lead agency, performed final review of the Phase 1
Draft EIS prior to publication.
1.7 HOW HAS PUBLIC INPUT BEEN INCORPORATED
INTO THE EIS PROCESS?
As described above, the scope of this EIS has incorporated public comment received through
website forms, emails, oral testimony, and letters. Comments regarding the need for the
project helped focus attention on clarifying the project objectives. Comments regarding the
alternatives resulted in changes to the alternatives proposed in the initial Scoping Notice
published in April 2015. Comments regarding potential impacts were catalogued and
evaluated by the lead agency to determine which impacts could potentially be significant. For
some topics, even though significant impacts are not anticipated, there is sufficient
controversy about potential impacts that the topics are included in the EIS. The results of the
scoping process were summarized in the Phase 1 Draft EIS Scoping Summary and Final
Alternatives (City of Bellevue, 2015).
1.8 WHAT ARE THE APPLICANT’S OBJECTIVES FOR
THE ENERGIZE EASTSIDE PROJECT AND HOW
WERE THEY USED FOR THIS DRAFT EIS?
The purpose and need for the project, summarized in Section 1.3, helped to define PSE’s
broad objectives for the project, which are as follows:
• Address PSE’s identified deficiency in transmission capacity;
• Find a solution that can be feasibly implemented before system reliability is
impaired;
• Be of reasonable project cost;
• Meet federal, state, and local regulatory requirements; and
CHAPTER 1 January 2016 1 -16 INTRODUCTION AND SUMMARY
PHASE 1 DRAFT EIS
• Address PSE’s electrical and non-electrical criteria for the project (described in
further detail in Chapter 2).
1.9 WHAT ALTERNATIVES ARE EVALUATED IN THE
PHASE 1 DRAFT EIS?
Chapter 2 describes in detail the alternatives included in the Phase 1 Draft EIS. The EIS
evaluates a No Action Alternative and three action alternatives, summarized below.
1.9.1 No Action Alternative
As required by SEPA, the No Action Alternative must be evaluated in an EIS, as a baseline
against which the action alternatives can be gauged. The No Action Alternative includes the
following:
• Ongoing maintenance that PSE can do without requiring state or local approvals;
• No new 230 kV transmission lines, substations, energy generation, or storage
facilities; and
• No change to conservation efforts as described in the 2013 Integrated Resource Plan
(PSE, 2013a).
1.9.2 Alternative 1: New Substation and 230 kV Transmission Lines
This alternative includes installing a new transformer that would transform 230 kV bulk
power to 115 kV. This new transformer would require either expansion of an existing
substation on the Eastside or construction of a new substation. It would also need to be fed by
new 230 kV transmission lines. The Phase 1 Draft EIS considers a range of 230 kV
transmission options to serve the Eastside. These would range in length from approximately
18 miles up to 26 miles in length. The key elements of this alternative include the following:
• New substation at Vernell or Westminster, or adding a 230 kV substation near the
existing 115 kV Lakeside substation. A new substation adjacent to the Lakeside
substation would be known as Richards Creek substation; however, for simplicity,
this site will be referred to as Lakeside.
• New 230 kV transmission line or an upgrade of an existing 230 kV transmission line
from Redmond to Renton, located between Lake Washington and Lake Sammamish,
using the following possible options:
A. Use of overhead lines in new or existing PSE or public rights-of-way and/or
utility corridors;
B. Use of Seattle City Light’s 230 kV transmission line corridor along with
construction of new 230 kV lines looping the system into both the
Sammamish and Lakeside substations;
C. Use of underground lines; and
D. Use of submerged lines.
January 2016 CHAPTER 1 INTRODUCTION AND SUMMARY 1-17
PHASE 1 DRAFT EIS
• No change to conservation efforts as described in PSE’s 2013 Integrated Resource
Plan (PSE, 2013a).
A new 230 kV transmission line would run a minimum of approximately 18 miles. The
submerged line option would require the greatest length of all options considered under this
alternative.
1.9.3 Alternative 2: Integrated Resource Approach
Alternative 2 combines the following methods to meet the projected need and PSE’s stated
electrical criteria:
• Energy efficiency (e.g., promoting use of LED lightbulbs rather than incandescent,
more efficient appliances, and updated windows and insulation);
• Demand response (e.g., installing specialized devices to control customer electrical
usage and help manage peak uses);
• Distributed generation (e.g., promoting use of various small-scale energy generation
equipment tied to the PSE distribution system and controllable by PSE);
• Energy storage using large-scale battery systems; and
• Simple-cycle generation facilities of approximately 20 MW size, located at some PSE
substations within the Eastside and operated as needed during peak demand periods,
or other times as needed.
1.9.4 Alternative 3: New 115 kV Lines and Transformers
This alternative includes the following changes to the PSE transmission system:
• A new 230 to 115 kV transformer at Lake Tradition substation;
• A new transmission line between the Bonneville Power Administration (BPA) Maple
Valley-Sammamish 230 kV line and the Lake Tradition substation;
• A third 230 to 115 kV transformer at Sammamish substation;
• A third 230 to 115 kV transformer at Talbot Hill substation;
• Three new 115 kV lines at Lake Tradition substation;
• Two new 115 kV lines at Sammamish substation; and
• Two new 115 kV lines at Talbot Hill substation.
The seven additional 115 kV lines would total approximately 60 miles in length. There would
be no change to conservation efforts as described in the 2013 Integrated Resource Plan (PSE,
2013a).
1.10 WHAT ARE THE KEY FINDINGS OF THIS DRAFT EIS?
The following pages provide a summary of the findings of each chapter of this Phase 1 Draft
EIS regarding the impacts of the alternatives. For each element of the environment evaluated
CHAPTER 1 January 2016 1 -18 INTRODUCTION AND SUMMARY
PHASE 1 DRAFT EIS
in the EIS, these two-page summaries provide a brief description of key findings about the
affected environment, potential impacts, mitigation available, and any unavoidable
significant impacts. The number at the top of each page identifies the chapter from this Phase
1 Draft EIS that is summarized below. Summaries are not intended as a replacement for more
thorough review undertaken in each chapter.
Impacts are generally categorized as minor, moderate, or significant. Each chapter defines
these categories for the specific element of the environment and provides detailed
descriptions of impacts. Impacts that are described in this EIS as “negligible” refer to small
impacts that would be inconsequential.
January 2016 CHAPTER 1 INTRODUCTION AND SUMMARY 1-19
PHASE 1 DRAFT EIS
January 2016 CHAPTER 1
INTRODUCTION AND SUMMARY
PHASE 1 DRAFT EIS
1-21
Affected Environment
Earth3
Geology of the combined study area is characterized by recent, surficial soils over thick
glacially consolidated soils underlain by bedrock.
The Puget Sound basin is located within a seismically active area dominated by the
Cascadia subduction zone.
Earthquakes in the region result from the Cascadia subduction zone, the deep
subduction zone below the Puget Sound, or shallow crustal faults.
Liquefaction hazard areas include lowland lakeside areas of the northern and southern
tips of Lake Sammamish, as well as the floodplains of Cedar River and Evans Creek.
Other geological hazards (steep slopes, erosion, landslides, and other hazards such as
soft soils and old coal mines) are located in the combined study area.
January 2016CHAPTER 1
INTRODUCTION AND SUMMARY
PHASE 1 DRAFT EIS
1-22
Summary of Impacts Common to All Alternatives
■Erosion during construction could occur.
■All of the alternatives would rely on a system that crosses seismic and other geologic hazard areas
that range in severity.
■Incorporation of National Electric Safety Code (NESC) 2012 and NERC/ FERC standards and
requirements into project design would minimize hazards.
■All impacts would be minor with implementation of best management practices, geotechnical
recommendations, regulatory requirements, and industry standards.
Summary of Impacts by Alternative
NO ACTION
■With no new improvements, there would be
no impacts related to geologic and seismic
hazards that do not already exist today.
ALTERNATIVE 1
■Impacts from all options would be similar.
■Implementation of facility design measures in
accordance with regulatory requirements would
result in minor impacts for each of the four
options under Alternative 1.
ALTERNATIVE 2
■Demand-side strategies would require less new
construction, reducing the potential for new
hazards. Impacts of battery storage and peak
generation plants would be similar to Alternative
1 (minor).
ALTERNATIVE 3
■Involves the most new construction over the
widest area and would likely encounter a range
of geotechnical and seismic hazards. Although
the area of impact is the largest, the impacts
themselves would be minor.
Mitigation Measures
■Avoid construction on steep slopes, known
and potential landslide zones, and areas with
organic or liquefiable soils, where feasible.
■Implement construction best management
practices.
■Adhere to applicable code requirements and
monitor all improvements for changes.
Significant Unavoidable Adverse
Impacts
■Under all alternatives, including the No Action
Alternative, there is an unavoidable seismic
risk. None of the alternatives would increase
that risk, but all action alternatives increase the
number of facilities. New facilities built to current
standards reduce risks, and no significant
impacts are likely.
Earth
Affected Environment
January 2016 CHAPTER 1
INTRODUCTION AND SUMMARY
PHASE 1 DRAFT EIS
1-23
Greenhouse Gas Emissions4
King County’s Strategic Climate Action Plan has committed to a countywide Green
House Gas (GHG) emission reduction of 25 percent by 2020.
Eight of the 12 study area cities have committed to reduce GHG emissions by 7
percent from 1990 levels through climate action plans.
Ecology estimated that in 2010, Washington produced about 106 million U.S. tons of
CO2e. Sources of GHG emissions in the state are transportation, electric generation;
residential commercial, and industrial energy; agriculture, water management, and
industrial processes.
January 2016CHAPTER 1
INTRODUCTION AND SUMMARY
PHASE 1 DRAFT EIS
1-24
Summary of Impacts Common to All Alternatives
■All alternatives would release GHG during construction.
Summary of Impacts by Alternative
NO ACTION
■The No Action Alternative would not result in
construction or operational GHG impacts.
■As part of ongoing maintenance, vegetation and tree removal would continue.
ALTERNATIVE 1
■Option A could result in CO2 sequestration
losses from tree removal that exceed the
state’s GHG reporting threshold and could be a
potentially significant adverse impact.
■Option B could require less tree removal than
Option A and sequestration loss impacts could
be a minor impact.
■Option C could result in the least sequestration
loss from tree removal of the Alternative 1
options and would be considered a minor
impact.
■Option D would result in a minor impact from
construction emissions. Sequestration loss
would occur on overland segments, similar to
other options.
ALTERNATIVE 2
■Peak generation plants could produce GHG
emissions during operation and result in a
moderate GHG impact.
ALTERNATIVE 3
■Alternative 3 could result in CO2 sequestration losses from tree removal that would be a significant adverse impact.
Mitigation Measures
■Gas turbines or reciprocating engines may
require air quality permits to restrict the use of
fuel and associated GHG emissions.
■Vegetation replacement could reduce
sequestration losses under Alternative 1,
Option A, and Alternative 3 to a moderate level.
■Carbon offsets could be purchased.
Significant Unavoidable Adverse
Impacts
■ If mitigation measures are employed, there
would be no significant and unavoidable
adverse impacts related to GHG emissions
associated with any of the project alternatives.
Greenhouse Gas Emissions
Affected Environment
January 2016 CHAPTER 1
INTRODUCTION AND SUMMARY
PHASE 1 DRAFT EIS
1-25
Water Resources5
The combined study area is within Cedar-Sammamish River watershed (WRIA 8) and
Duwamish-Green River watershed (WRIA 9).
The two largest waterbodies are Lake Washington and Lake Sammamish.
There are about 2,000 mapped streams and rivers in the combined study area with
associated floodplains. These include the Sammamish River, Cedar River, Bear Creek,
Evans Creek, Kelsey Creek, Richards Creek, May Creek, Coal Creek, and Issaquah
Creek.
There are over 1,000 mapped wetlands.
Most mapped groundwater aquifers in the combined study area are within King
County’s jurisdiction.
January 2016CHAPTER 1
INTRODUCTION AND SUMMARY
PHASE 1 DRAFT EIS
1-26
Summary of Impacts Common to All Alternatives
Summary of Impacts by Alternative
■There is a potential for minor water quality impacts from construction site runoff, dewatering discharge,
or accidental spills.
■There is a potential for minor impacts to water quality from operation, if impervious areas and
associated surface water runoff are increased, or stored hazardous materials or chemicals are
inadvertently released into surface waters.
NO ACTION
■Existing water resource conditions would not
change and no impacts are expected.
ALTERNATIVE 1
■There is a potential with all options for significant
impacts to water resources from construction
of overhead or underground lines in streams,
lakes, wetlands, or their buffers, however,
limitations imposed by regulatory agencies
would reduce impacts to minor or moderate.
■Under Option D, minor to moderate temporary
impacts to Lake Washington could result from
construction of underwater transmission lines
including impaired water quality, local turbidity,
disturbance of contaminated sediment,
underwater noise, and impacts to the shoreline.
■Although unlikely, significant impacts on water
resources could occur if the Olympic Pipeline
were ruptured during construction.
ALTERNATIVE 2
■Minor impacts on water resources from
construction and operation could occur for
components that involve ground disturbance.
ALTERNATIVE 3
■Similar impacts as for overhead transmission
lines as under Alternative 1, Option A, could
occur.
Mitigation Measures
■Avoid locating facilities and infrastructure near
or in streams, lakes, wetlands, floodplains, and
groundwater.
■Employ best management practices required
by water quality regulations during construction.
■Comply with local critical areas and stormwater
management regulations for water retention
and treatment at substations and other facilities
during operation.
Significant Unavoidable Adverse
Impacts
■No significant unavoidable adverse impacts
to water resources are likely to occur given
the breadth of regulations that would govern
construction and operation.
Water Resources
Affected Environment
January 2016 CHAPTER 1
INTRODUCTION AND SUMMARY
PHASE 1 DRAFT EIS
1-27
Plants & Animals6
Vegetation cover types include forest, herbaceous, scrub-shrub,agriculture, and woody
and herbaceous wetlands.
Habitat for fish and wildlife occurs in freshwater wetlands, forest, lakes and ponds,
biodiversity areas and corridors, and natural areas within the combined study area.
Fish species listed under the Endangered Species Act are found in lakes and streams
in the combined study area.
State priority species with potential habitat in the combined study area include
waterfowl, pileated woodpecker, great blue heron, purple martin, and several raptors,
turtles, and bats.
January 2016CHAPTER 1
INTRODUCTION AND SUMMARY
PHASE 1 DRAFT EIS
1-28
Summary of Impacts Common to All Alternatives
Summary of Impacts by Alternative
■All alternatives could cause impacts to plants and animals due to habitat disturbance from infrastructure constructed and operated within existing developed areas.
NO ACTION
■Existing habitat conditions would not change and no impacts are expected.
ALTERNATIVE 1
■Construction of any of the Alternative 1 options
could cause minor to significant impacts from:
habitat alteration; interference with critical
survival activities; or direct injury, death, or
harassment of some species. Impacts would
depend on the scale of habitat alteration and
species disturbance, and species affected.
■Option D could cause minor to significant
impacts on fish from construction and operation
of underwater transmission lines.
■Although the probability is low, once
constructed, overhead transmission lines
under Option A and B could result in significant
impacts to threatened or endangered species
or species of concern from collisions or
electrocution.
ALTERNATIVE 2
■Impacts to plants and animals may be significant
resulting from the construction of a battery
storage facility or peak generation plant,
depending on the species affected and scale of
habitat alteration and species disturbance.
■Impacts could be moderate to significant on
wildlife due to noise disturbance from peak
generation plants.
ALTERNATIVE 3
■Similar impacts as for overhead transmission
lines using existing corridors under Alternative 1,
Option A.
Mitigation Measures
■Avoid and minimize vegetation, tree, and habitat
removal to extent possible in development of
facilities and infrastructure.
■Require measures to reduce noise and human
activity near priority habitat areas in accordance
with applicable permit requirements.
■Implement PSE Avian Protection Program
to reduce avian collisions with overhead
transmission lines, once constructed.
Significant Unavoidable Adverse
Impacts
■Alternative 1 could result in significant
unavoidable impacts due to habitat loss, and if
threatened or endangered species or species
of concern are affected. Alternative 3 would
use existing corridors, but system requirements
could force additional clearing in valuable
habitat areas, similar to Alternative 1.
Plants & Animals
Affected Environment
January 2016 CHAPTER 1
INTRODUCTION AND SUMMARY
PHASE 1 DRAFT EIS
1-29
Energy & Natural Resources7
The mix of resources used regionally for energy production includes hydropower, coal, natural gas, wind, nuclear, biomass, landfill gas, petroleum, and waste. Relative use of each changes over time.
No federal policies or regulations govern types of energy resources PSE consumes; state policy guides types of resources and conservation levels.
The Energy Independence Act of Washington State requires that PSE must obtain 15
percent of its electricity from new renewable resources by 2020, as well as undertaking cost-effective energy conservation.
No local jurisdiction controls how PSE provides power; some have policies addressing sustainable development, climate change, or energy conservation.
January 2016CHAPTER 1
INTRODUCTION AND SUMMARY
PHASE 1 DRAFT EIS
1-30
Summary of Impacts Common to All Alternatives
Summary of Impacts by Alternative
■No adverse impacts are likely to energy and natural resources from construction or operation.
■All alternatives are generally consistent with local jurisdictions’ energy policies.
■None of the alternatives change the amount of energy generated regionally. All consume small
amounts of energy during operation.
NO ACTION
■Involves no construction activities, and therefore
no change to energy or natural resource usage.
■Operations do not increase energy used to
provide power.
■No expanded transmission capacity could
mean limits to peak energy availability, possibly
with lower consumption of electricity than
projected.
ALTERNATIVE 1
■Described under impacts common to all.
ALTERNATIVE 3
■Described under impacts common to all.
ALTERNATIVE 2
■Would employ energy resources locally, but
would not substantially change the overall mix
or amount of regional energy resources used
for Eastside power delivery.
Mitigation Measures
■No mitigation is needed.
Significant Unavoidable Adverse
Impacts
■These are no significant unavoidable adverse
impacts.
Energy & Natural Resources
Affected Environment
January 2016 CHAPTER 1
INTRODUCTION AND SUMMARY
PHASE 1 DRAFT EIS
1-31
Environmental Health8
Contaminated soil or groundwater is likely in places, from historical land uses (logging,
agriculture, industry).
Hazardous materials are likely in electrical infrastructure (e.g., oil-containing
transformers, High Pressure Fluid-Filled [HPFF] power lines used in some underground
lines).
Pressurized flammable petroleum products transported in the Olympic Pipeline, which shares a corridor with a PSE transmission line, and is located in other portions of the combined study area.
Some risk of fire or explosion at substations or transmission lines exists due to damage
from earthquakes or lightning strikes.
Power lines, electrical wiring, and appliances produce EMF and corona ionization is
likely occurring around existing transmission lines; associated health risks for both have
not been definitively identified through ongoing research.
Hazardous materials and public safety risks are regulated by federal, state, and local
codes/standards.
January 2016CHAPTER 1
INTRODUCTION AND SUMMARY
PHASE 1 DRAFT EIS
1-32
Summary of Impacts Common to All Alternatives
Summary of Impacts by Alternative
■Hazardous materials spilled during construction or operations would be subject containment and
cleanup requirements that would prevent more than a minor impact from occurring.
■Each action alternative could be constructed in/near previously contaminated sites; proper
management of those materials is expected impacts could be minor depending on location.
■Risk to the public is not likely from constructing or operating the project near pipelines due to
extensive safety policies and regulations.
■EMF and corona ionization impacts are not expected.
NO ACTION
■Earthquakes or lightning strikes could damage
transformers or drop power poles or lines, but
potential public safety risks are not likely and
negligible to minor impacts could be expected.
ALTERNATIVE 1
■Similar to No Action, potential for minor to
moderate impacts depending on option
chosen.
■Risk of accidental rupture and explosion
of Olympic Pipeline would increase during
construction but be minimize by employing best
management practices.
■With new equipment being installed, greater
potential for spills of hazardous materials during
construction and operation than No Action.
■HPFF cable, if used for new underground
transmission, could be damaged and leak.
■Risks associated with encountering
contamination or conflicts with petroleum
pipelines are higher for Option C because of
increased ground disturbance and the impacts
are expected to be minor to moderate.
ALTERNATIVE 2
■Distributed generation, energy storage, and
peak generation plant components have a
potential risk of minor impacts from fire or
explosion at energy storage or generation
facilities, similar to Alternatives 1 and 3.
ALTERNATIVE 3
■Same as Alternative 1, Option A, potential for
minor to moderate impacts, but increased
potential to encounter contamination during
construction because of longer corridors.
Mitigation Measures
■Use vegetable-based oil for transformers rather
than petroleum based oil or SF6.
■Minimize use of HPFF lines.
■Prior to starting work, conduct targeted
characterization of soils at identified high- and
moderate impact site locations.
■Design to avoid intercepting known
contamination and use specialized material
management plans to control contamination
encountered during construction.
■Use best management practices for spill
containment and cleanups.
■Install native plantings not needing pesticides at
new sites.
■Investigate feasibility of alternative design
options for transformers for greater seismic
protection and avoidance of safety risks.
■Local governments and PSE would further
evaluate the PIPA recommendations to
determine if any additional safety practices
could be implemented for Energize Eastside
Project.
■Comply with all applicable requirements for
avoiding utility conflicts during siting and design.
Coordinate with potentially affected utilities.
Significant Unavoidable Adverse
Impacts
■Significant impacts would be avoided through
compliance with all applicable regulations and
industry safety standards.
Environmental Health
Affected Environment
January 2016 CHAPTER 1
INTRODUCTION AND SUMMARY
PHASE 1 DRAFT EIS
1-33
Noise9
Transportation is the primary source of noise in the study areas.
Both state and local codes establish limits on permissible noise levels but exempt
substations and daytime construction activity.
Corona discharge from existing transmission lines may be audible, but it is a relatively
low noise level.
Existing transformers and ancillary equipment may be audible at adjacent sensitive land
uses.
Existing electrical substations produce audible noise, but are exempt from maximum
permissible nose levels in the WAC.
January 2016CHAPTER 1
INTRODUCTION AND SUMMARY
PHASE 1 DRAFT EIS
1-34
■Construction impacts would be minor if restricted to daytime hours, but nighttime work, if required,
would be a moderate but temporary impact.
NO ACTION
■No construction-related or operational noise
impacts.
ALTERNATIVE 1
■Electrical substations could result in minor
operational noise impacts.
■Operational noise from corona discharge would
be negligible.
ALTERNATIVE 2
■Peak generation plants or distributed generation
could result in a minor to moderate operational
noise impact.
ALTERNATIVE 3
■Transformer noise could result in a minor
operational noise impact.
■Operational noise from corona discharge would
be negligible.
Mitigation Measures
■Siting of transformers, substations, distributed
generation sources (gas turbines, anaerobic
digesters, etc.) should include attenuation
measures to maintain noise levels at the nearest
receptors within 5 dBA of existing levels.
Significant Unavoidable Adverse
Impacts
■There would be no significant unavoidable
noise impacts.
Noise
Summary of Impacts Common to All Alternatives
Summary of Impacts by Alternative
Affected Environment
January 2016 CHAPTER 1
INTRODUCTION AND SUMMARY
PHASE 1 DRAFT EIS
1-35
Land Use & Housing10
Population is projected to increase.
Land use is, and will remain, predominantly residential.
Housing was mostly single family units in 2014. The percentage of multifamily units will
increase over time through most of the area. Mixed use development (housing and
commercial combined) will become more common.
All jurisdictions have land and shoreline use policies and zoning regulations addressing
project consistency and design.
The percentage of industrial land uses will remain about the same.
January 2016CHAPTER 1
INTRODUCTION AND SUMMARY
PHASE 1 DRAFT EIS
1-36
Summary of Impacts Common to All Alternatives
Summary of Impacts by Alternative
■Construction of action alternatives would be of relatively short duration at any one location with
negligible land use impacts.
■Land use goals and policies of the combined study area communities provide some guidance as to
where new transmission lines, transformers, or the features of Alternative 2 should be located, and
some have goals or policies supporting undergrounding of electrical lines. All acknowledge a need for
adequate infrastructure to support development.
■Five jurisdictions promote combining utilities within the same corridors in some cases; some may
prohibit combining regional utility lines with high flammable liquid pipelines for safety.
■Most jurisdictions would require new utilities that are not dependent on a shoreline location to be
located outside the shoreline jurisdiction unless there is no feasible alternative.
Land Use & Housing
NO ACTION
■Would not directly change any property uses,
but could delay growth or shift growth to other
areas of the region.
■Inconsistency with planning goals for adequate
power supply could be a significant adverse
impacts.
ALTERNATIVE 1
■Moderate to significant land use impacts and
housing impacts could occur because up
to 327 acres of land could change to utility
use, and some housing could be removed to
accommodate new transmission lines.
■Although generally consistent with most
planning policies, it may not be permissible to
co-locate with Olympic Pipeline through three
jurisdictions due to regulations for pipeline
safety.
■Option C could use less new land because
underground lines require less clear zone than
overhead.
■Option D would have less over-land area and
less potential for impacts than other options, but
shoreline regulations prohibit new utilities in Lake
Washington.
ALTERNATIVE 2
■Negligible to moderate land use and housing
impacts because limited conversion of land
use would be required, mainly for the energy
storage and peak plant components.
■Some development regulations would prohibit
components in certain locations.
ALTERNATIVE 3
■Same types of impacts as Alternative 1, Option
A, but would only install new overhead lines
along existing road or utility right-of-way.
■Total area of new corridor/clear zone could be
less than building a new corridor but greater
than using an existing corridor, as described
under Alternative 1.
Mitigation Measures
■Use existing utility corridors or properties
already owned by PSE to minimize conversion
of other land uses.
■Underground all or part of the line, or place
through Lake Washington, to minimize
conversion of land to utility use.
■Provide relocation assistance.
Significant Unavoidable Adverse
Impacts
■No significant unavoidable adverse impacts to
land use or housing are expected. Alternative
1, Option A, could have significant impacts if
a new corridor were required. The No Action
Alternative could lead to unavoidable significant
impacts. If unreliable power supply were to
result in growth that is inconsistent with regional
growth plans.
Affected Environment
January 2016 CHAPTER 1
INTRODUCTION AND SUMMARY
PHASE 1 DRAFT EIS
1-37
Views & Visual Resources11
The area is mostly urbanized, bounded by large lakes to the east and west, and
comprised primarily of low, rolling hills.
Views can affect property values positively or negatively. Although views of transmission
lines can negatively affect property values, studies are inconclusive on the duration of
negative effects.
Most views are observed from private residences or publicly accessible parks, trails,
and open spaces.
Visual resources include nearby mountains (e.g. the Cascades, Olympics, and
Issaquah Alps), water bodies (e.g. Lake Washington, Lake Sammamish, and the Cedar
River), and the Seattle skyline. Territorial views are the most common types of views.
Existing large substations are typically in industrial, or commercial areas. Smaller
substations are found adjacent to most land uses, including residential areas.
Existing 115 kV lines are generally along road rights-of-way or in dedicated utility
easements, and are suspended on 50 to 90-foot tall wood poles. Existing 230 kV
lines operated by Seattle City Light are predominantly in residential areas, and are
suspended on 100 to 135-foot steel poles, and lattice structures.
Most of the development, including residential areas, were developed after the
transmission lines were constructed.
January 2016CHAPTER 1
INTRODUCTION AND SUMMARY
PHASE 1 DRAFT EIS
1-38
Summary of Impacts Common to All Alternatives
Summary of Impacts by Alternative
■Visual character of neighborhoods could change due to introduction of new or taller electrical infrastructure
(e.g., transmission poles and substations) and creation of clear zone.
■View obstruction or changes to viewpoints or visual resources could result from placement of new
infrastructure.
■Extent of impact would depend on the degree of contrast, number of viewers, duration of impact, and the
sensitivity of the viewers.
■Construction impacts would be temporary and minor to moderate depending on location.
NO ACTION
■No visual impacts are expected.
ALTERNATIVE 1
■All options would include a new or expanded
substation. Westminster and Lakeside sites could
have moderate impacts on adjacent park and
residential uses.
■Option A could have greatest impacts due to taller
poles, widest clear zones.
■Option B would use only the existing clear zone of
SCL line.
■Option C would have the least visual impacts
because lines would be underground.
■Option D would not be visible for the segment
underwater, but requires overland segments to
connect to substations, that could require a new
corridor similar to Option A.
ALTERNATIVE 2
■Primary visual impacts would be from 6-acre battery
storage facility and from several 1-acre peak power
generation facilities, all near substations.
■Total clearing and development would be less than
all other alternatives.
ALTERNATIVE 3
■Impacts could be minor where new transmission
lines replace existing poles with taller poles and
limited additional clearing is required.
■Impacts could be significant where 40 feet of
additional corridor is required, especially where there
are no lines at present.
Mitigation Measures
■Co-locate transmission lines with current routes to
reduce clearing.
■Place and design structures to minimize impacts.
■Use aesthetically pleasing system components
(such as poles and davit arms) and landscaping to
shield equipment.
Significant Unavoidable Adverse
Impacts
■Significant impacts from Alternative 1 would be
unavoidable if a new corridor were developed.
■Significant impacts from Alternative 3 may be
unavoidable due to the extensive area that must be
served with new or taller poles.
Views & Visual Resources
Affected Environment
January 2016 CHAPTER 1
INTRODUCTION AND SUMMARY
PHASE 1 DRAFT EIS
1-39
Recreation12
There are approximately 265 recreation sites covering about 16,400 acres in the study
area.
Informal recreation also occurs outside of formal recreation sites throughout the study
area, including within some transmission easements that are used as trails.
Recreation sites include small pocket parks to large natural areas under the jurisdiction
of 11 communities, King County, and Washington State.
Recreation opportunities include:
Hiking/walking/running • Bicycling • Beach/water access • Horseback riding • Nature
viewing • Playgrounds • Sports fields • Community centers
Transmission lines and substations are found adjacent to several parks.
January 2016CHAPTER 1
INTRODUCTION AND SUMMARY
PHASE 1 DRAFT EIS
1-40
Summary of Impacts Common to All Alternatives
Summary of Impacts by Alternative
■There could be minor to moderate impacts to recreation if construction activities occur within or adjacent
to a recreation site. Level of impact would vary depending on time of year of construction, recreation
facilities affected, and how many facilities are affected concurrently.
■For any of the action alternatives, there could be significant impacts if use of recreation facility
is permanently lost and cannot be replaced. Recreation facilities will be avoided to the extent
practicable.
■Recreation facilities are often subject to restrictions limiting their conversion to another use.
NO ACTION
■There would be no impacts to recreation.
ALTERNATIVE 1
■If infrastructure is placed within a recreation site
and substantially alters, limits, or precludes the
use of that site, impacts could be significant.
■Where existing transmission lines are already
located within a recreation facility (Alternative 1,
Option A) it is more likely that impacts cannot
be avoided.
ALTERNATIVE 2
■Permanent impacts from operation of Alternative
2 are not expected, with the possible exception
of Lake Tradition NRCA if the substation in this
location is chosen for a peak generation plant;
impacts could be significant.
ALTERNATIVE 3
■Impacts could be similar to Alternative 1, Option
A, but there is greater potential to cross or be
near recreation sites.
Mitigation Measures
■Place any permanent infrastructure outside of
recreation sites, where feasible.
■Employ best management practices to minimize
construction traffic, dust, and noise.
■Restore recreation sites after construction
where feasible; if they cannot be restored,
replace lost recreation facilities and screen new
infrastructure with vegetation.
Significant Unavoidable Adverse
Impacts
■Some significant impacts may be unavoidable if
design or siting factors limit the ability to locate
lines or facilities away from recreation sites.
Recreation
Affected Environment
January 2016 CHAPTER 1
INTRODUCTION AND SUMMARY
PHASE 1 DRAFT EIS
1-41
Summary of Impacts Common to All Alternatives
Historic
& Cultural Resources13
Less than 25% of the combined study area has been tested for cultural resources.
There are 69 historic properties and 94 known archaeological resources in the study
areas.
All action alternatives have areas classified as high to very high risk for containing
Precontact cultural resources.
January 2016CHAPTER 1
INTRODUCTION AND SUMMARY
PHASE 1 DRAFT EIS
1-42
Summary of Impacts Common to All Alternatives
Summary of Impacts by Alternative
■Ground disturbance could impact cultural resources, if present, and could be significant depending on
the resource affected.
■Impacts to above ground historic properties could include vibration and increased dust.
■Energy efficiency methods that modify building facades, such as weatherization, may result in minor to
moderate impacts to historic properties, if present.
NO ACTION
■Same as impacts common to all alternatives.
ALTERNATIVE 1
■Ground disturbance would be greatest
near new or expanded substation and for
underground corridor (Option C).
■Possible underwater disturbance under Option
D could affect sumerged historic resources.
ALTERNATIVE 2
■This would cause the least amount of ground
disturbance of all alternatives.
■Battery storage and peak power generation
have greatest potential for impacts among
components of Alternative 2.
ALTERNATIVE 3
■Similar impacts as for Alternative 1, Option A
and B except that more miles of transmission
lines would be built, and several substations
would be expanded, resulting in ground
disturbance.
Mitigation Measures
■Prior to construction, conduct a survey for any
archaeological resources in areas of proposed
ground disturbance, and prepare plans to
address affected resources.
■If there are potential impacts to eligible or listed
historic register properties, develop property-
specific mitigation measures with stakeholders,
including the Washington State Department of
Archaeology and Historic Preservation.
Significant Unavoidable Adverse
Impacts
■There are no known significant unavoidable
adverse impacts to historic and cultural
resources. However, the exact location of the
project is not known, and will be evaluated in
phase 2.
Historic & Cultural Resources
Affected Environment
January 2016 CHAPTER 1
INTRODUCTION AND SUMMARY
PHASE 1 DRAFT EIS
1-43
Transportation14
The street system consists of a mix of freeways, arterials, collectors, and local access
streets that represent varying levels of emphasis on pedestrian orientation, mobility,
and access. Most neighborhoods have on-street public parking and off-street private
parking.
The combined study area is served by bus service that is most concentrated in the
vicinity of transit centers, park-and-ride lots and freeway stations.
Pedestrian and bicycle facilities include sidewalks, shoulders, multi-use trails, and
painted on-street bicycle and shared-use lanes.
January 2016CHAPTER 1
INTRODUCTION AND SUMMARY
PHASE 1 DRAFT EIS
1-44
Summary of Impacts Common to All Alternatives
Summary of Impacts by Alternative
■Project elements would be physically separated from transportation infrastructure and services.
Transportation infrastructure disrupted during construction would be restored, and streets,
sidewalks, and trails disturbed during construction would be repaved.
NO ACTION
■No construction impacts.
■Power outages during operations could impact
traffic operations and safety.
ALTERNATIVE 1
■Construction impacts include restrictions on
roadway use, sidewalk use, property access,
transit, and parking, as well as construction-
generated truck and commute trips, and
potential pavement degradation.
■If the Olympic Pipeline were accidentally
damaged during construction, products
normally transported by pipeline would need to
be shipped by other means, primarily by trucks.
■Construction impacts would be minor to
moderate and operation impacts would be
negligible.
ALTERNATIVE 2
■Negligible to moderate construction
impacts and negligible to minor operational
transportation impacts, depending on
components used.
ALTERNATIVE 3
■Construction impacts similar to Alternative
1, with lower magnitude and duration of
construction at any one location, but more
geographically spread out.
■Negligible operational impacts.
Mitigation Measures
■Mitigation could include “maintenance of traffic”
plans that identify traffic control and detours to
maintain mobility and safety for vehicular and
nonmotorized travelers, and maintain access to
properties.
■A public involvement program could provide
information about the types and locations of
construction impacts and the measures to
minimize those impacts.
Significant Unavoidable Adverse
Impacts
■With the appropriate mitigation measures in
place, no unavoidable significant adverse
impacts to transportation are anticipated.
Transportation
Affected Environment
January 2016 CHAPTER 1
INTRODUCTION AND SUMMARY
PHASE 1 DRAFT EIS
1-45
Public Services15
The public services that were considered for this programmatic analysis are fire,
emergency medical, and police services.
Individual communities may have their own police and fire departments or may contract
with other jurisdictions, such as adjacent cities or King County, to provide the services.
Many local fire and police agencies in the combined study area have mutual response
agreements, which allow public safety responsibilities to be shared across jurisdictional
boundaries.
Throughout the combined study area, individual fire departments set levels of service
and target response times. Fire departments throughout the combined study area
reported meeting level of service and response time targets for various types of
emergencies, including emergency medical and other incidents.
Except for a few incidents of theft of ground wires in a utility corridor, police departments
reported few unique crime-related problems associated with existing electricity
substations or transmission corridors.
Patch.com
January 2016CHAPTER 1
INTRODUCTION AND SUMMARY
PHASE 1 DRAFT EIS
1-46
Summary of Impacts Common to All Alternatives
Summary of Impacts by Alternative
■Minor to moderate impacts related to increased demand for emergency response services.
■Negligible impacts related to additional law enforcement demands.
■No adverse impacts on emergency communication or devices.
NO ACTION
■There could be minor impacts associated
with a sudden, unplanned loss of electricity.
Emergency response facilities are the highest
priority for maintaining power during an outage,
and they are equipped with backup power
supplies.
■Although a significant adverse impact
could result if a pipeline explosion near the
transmission line occurred, the risk is minimized
by conformance with regulatory requirements
and procedures that address pipeline safety.
ALTERNATIVE 1
■There could be minor to moderate impacts to
emergency services as a result of construction
or operation.
■Conformance with regulatory requirements and
procedures would ensure that potential hazards
are identified, and design plans developed, that
minimize adverse effects from pipeline hazards.
ALTERNATIVE 2
■Given the potential complexity of emergency
response to certain facilities (i.e., battery
storage and peak generation plant), moderate
impacts could occur.
ALTERNATIVE 3
■There could be minor to moderate impacts to
emergency services as a result of construction
and operation.
Mitigation Measures
■Follow all siting, design, construction, and
operational requirements, standards, and
plans to reduce risk of pipeline damage and to
reduce risk of a substation fire:
■Implement maintenance of traffic plans to
minimize effects on emergency response.
■Notify emergency service providers and
neighborhood residents of construction
schedules, street closures, and utility
interruptions as far in advance as possible.
■Coordinate with law enforcement agencies to
implement crime prevention plans for construction
sites and staging areas.
Significant Unavoidable Adverse
Impacts
■There would be no significant unavoidable adverse
impacts.
Public Services
Affected Environment
January 2016 CHAPTER 1
INTRODUCTION AND SUMMARY
PHASE 1 DRAFT EIS
1-47
Utilities16
Comprehensive plans for study area communities contain goals and policies relating to
the provision and management of utilities to meet community needs.
The combined study area includes both regional and local utilities. This programmatic
analysis focuses on regional utilities in the combined study area, which includes:
overhead 115 kV, 230 kV, and 500 kV transmission lines; electric substations; high-
pressure natural gas mains; petroleum pipelines; water mains; major sewer conveyance
lines; main feeder telephone and fiber optic lines.
Utilities are provided by a combination of City-managed providers and providers
managed by other entities. Depending on their services, utilities not managed by the
Cities are state regulated, federally licensed, and/or municipally franchised providers.
PSE natural gas mains and the Olympic Pipeline, an underground, flammable liquids
pipeline, are located in existing PSE and Seattle City Light transmission lines easements
and through other areas of the combined study area.
January 2016CHAPTER 1
INTRODUCTION AND SUMMARY
PHASE 1 DRAFT EIS
1-48
Summary of Impacts Common to All Alternatives
Summary of Impacts by Alternative
■Construction disturbance could affect existing utilities if present. Potential for encountering utilities is
higher when constructing within a road right-of-way or within existing utility easements. Impacts would
be minor to moderate for all alternatives except Alternative 1, Option B (moderate to significant).
■Temporary service outages could occur during utility relocations; disruptions would likely be minimal.
■Inadvertent damage to underground utilities could occur if utility locations are uncertain or
misidentified. Although such incidents do not occur frequently, if numerous relocations are required
during project construction, the potential for accidents is more likely.
■ Appropriate cathodic-protection measures would be determined by the utility owner on a case-by-
case basis in accordance with applicable federal requirements; impacts on buried pipelines would be
minor.
NO ACTION
■High electrical loads and lack of bulk
transmission in the vicinity of the load could
result in moderate to significant adverse
impacts to electrical service reliability.
■A potential significant adverse impact if Olympic
Pipeline were damaged and explodes near
existing PSE lines. Potential hazards minimized
to minor levels with conformance to standards
and requirements.
ALTERNATIVE 1
■If located in PSE easement, extensive
coordination with Olympic Pipe Line Company
would be required during project design and
construction. Conformance with standards
and requirements would ensure that potential
hazards are identified and design plans
developed to minimize adverse effects.
ALTERNATIVE 2
■There could be moderate to significant adverse
impacts on electric service reliability given the
level of uncertainty in implementing this solution.
The risk would be lower than the No Action, but
higher than other action alternatives.
■Increased demand for natural gas and water to
supply simple-cycle generators could require
upgrades to major gas and water supply lines
which are also difficult to site.
ALTERNATIVE 3
■Higher likelihood of utility conflicts than all
options under Alternative 1 due to more line
installation along road rights-of-way and more
substation expansion work.
■New overhead lines and substation expansion
could be constructed near gas mains and the
Olympic Pipeline resulting in the same potential
impacts as Alternative 1, Option A.
Mitigation Measures
■Coordinate with utility providers during project
design to avoid and minimize conflicts.
■Schedule any utility relocations in advance
to minimize the impact of potential service
outages.
■Design, construct, and operate new facilities
according to industry standards and applicable
requirements.
Significant Unavoidable Adverse
Impacts
■No Action Alternative – less reliable service
could result in power disturbances and could
increase likelihood of power outages.
■Alternative 2 – uncertainties about feasibility and
performance, participation, and conservation
levels would result in risk to reliability.
Utilities
1.11 HOW DO THE IMPACTS OF THE ALTERNATIVES
COMPARE?
The following tables compare of the degree of impacts that can be expected from each of the
alternatives on each of the elements in the environment that was evaluated in the Phase 1
Draft EIS. Table 1-2 compares construction impacts. Table 1-3 compares operational
impacts.
January 2016 CHAPTER 1 INTRODUCTION AND SUMMARY 1-49
PHASE 1 DRAFT EIS
Table 1-2. Construction Impacts Comparison
CHAPTER 1 January 2016 1 -50 INTRODUCTION ND SUMMARY
PHASE 1 DRAFT EIS
Table 1-2. Construction Impacts Comparison (Continued)
January 2016 CHAPTER 1 INTRODUCTION AND SUMMARY 1-51
PHASE 1 DRAFT EIS
Table 1-2. Construction Impacts Comparison (Continued)
CHAPTER 1 January 2016 1 -52 INTRODUCTION ND SUMMARY
PHASE 1 DRAFT EIS
Table 1-3. Operation Impacts Comparison
January 2016 CHAPTER 1 INTRODUCTION AND SUMMARY 1-53
PHASE 1 DRAFT EIS
Table 1-3. Operation Impacts Comparison (Continued)
CHAPTER 1 January 2016 1 -54 INTRODUCTION ND SUMMARY
PHASE 1 DRAFT EIS
Table 1-3. Operation Impacts Comparison (Continued)
January 2016 CHAPTER 1 INTRODUCTION AND SUMMARY 1-55
PHASE 1 DRAFT EIS
1.12 WHAT ARE THE AREAS OF SIGNIFICANT
CONTROVERSY?
1.12.1 Need for the Project
Controversy about the need for the project is high. Some members of the community reject
the idea that the project is needed based on their understanding of how much energy actually
needs to be transmitted through and into the Eastside area. Other members of the community
accept PSE’s assertion that the need is real and want only the most efficient and cost-
effective approach to addressing it.
The purpose of this EIS is not to determine whether the project is needed, but to confirm that
the methods used to define the need are consistent with industry standards and generally
accepted methods. After determining that PSE’s evaluation process has been conducted
according to industry standards, the lead agency and the partner Cities have worked to
understand the nature of the need that PSE has identified, and to look broadly at the possible
alternatives that could address that need. This Phase 1 Draft EIS reflects the Cities’ concern
that the alternatives should include more options than alternative routes for 230 kV
transmission lines.
1.12.2 What Alternatives Should be Examined
Prior to the development of the scope for this Phase 1 Draft EIS, PSE had considered a wide
range of possible options in addition to a 230 kV transmission line solution, identifying that
as its preferred approach. Because of the desire of the Cities to examine a wider range of
options than only the 230 kV transmission line solution, PSE has cooperated in developing
the alternatives solutions that have been evaluated in this EIS. PSE has conducted additional
modeling to guide the scale of a 115 kV solution, and commissioned analysis on different
routes and methods of developing a 230 kV solution.
In developing Alternative 2, the Cities have outlined a combination of options suggested by
community members and evaluated by PSE in its own planning process. These options would
require far greater efforts by PSE and its customers in adopting energy efficiency, demand-
side reduction, distributed generation, energy storage, and peak power supplies than anything
PSE has proposed or studied in its prior evaluations.
The intent in examining these alternatives in this Phase 1 Draft EIS is that the consequences
of selecting specific project-level alternatives will be better understood.
Several options suggested by community members would modify assumptions PSE made in
its planning analysis regarding the need for the project, specifically around the use of
additional power plants outside of the Eastside during peak demand periods, and prohibiting
the flow of electricity to Canada during peak demand periods. Options like these were
examined but were found to be technically incapable of addressing the capacity deficiency
PSE has identified on the Eastside. Options considered but not carried forward for analysis in
this EIS are discussed in Chapter 2.
CHAPTER 1 January 20161-56 INTRODUCTION ND SUMMARY
PHASE 1 DRAFT EIS
1.12.3 Impacts from the Project
Controversy also remains about how the impacts from any solution for the Energize Eastside
Project will be borne by the communities the project will serve. Growth in electrical demand
in the coming decades is expected to be driven by new multifamily and commercial
development. The deficiency in transmission capacity could result in power outages
throughout the Eastside, which is predominantly developed with single-family residences.
Because there are no significant sources of electricity within the Eastside, virtually all
electricity for the Eastside must come via transmission lines that extend through rural, single-
family, and industrial areas as well as multifamily and commercial areas. Furthermore,
residents in both single-family and multifamily areas on the Eastside work in the commercial
areas where growth in electrical demand is expected to be concentrated. The controversy
centers around what parts of the community would benefit from the lines, and what parts
would bear the impacts.
Although significant impacts could occur with any alternative, the most controversial impacts
relate to concerns about the visual impacts and potential for conflicts between electrical and
flammable-liquid pipelines. Fear of these and other impacts led to concerns in the community
about reduced property values, degradation of neighborhood character, and public safety. The
Phase 1 Draft EIS acknowledges these concerns and provides the results of relevant studies
prepared by local and national experts on the topics.
This Phase 1 Draft EIS does not define specific locations of impacts, and therefore it
describes the impacts and associated tradeoffs in general terms. The project-level analysis in
the Phase 2 Draft EIS will provide more detailed information about the areas that would be
affected by various alternatives.
1.13 WHAT HAPPENS NEXT IN THE ENERGIZE EASTSIDE
EIS PROCESS?
The Fact Sheet at the beginning of this Phase 1 Draft EIS includes the timeframe for public
comment on the Draft EIS, including times and locations for public meetings to take
comment, and the addresses where comments can be submitted. Once public comments have
been received, the partner Cities will issue a Scoping Notice for the Phase 2 Draft EIS. The
findings from this Phase 1 Draft EIS and comments received on it will be used to help outline
proposed alternatives for inclusion in the Phase 2 (project-level) Draft EIS. Comments
received on the Phase 1 Draft EIS will also be summarized and made available to the public.
Scoping meetings will be held and comments accepted on the project-level analysis that will
be prepared in the Phase 2 Draft EIS. Comments received on the scope of the Phase 2 Draft
EIS will be summarized and made available to the public. Then the Phase 2 Draft EIS will be
prepared.
After publication of the Phase 2 Draft EIS, public meetings will be held to take comments on
that document. The Final EIS will include responses to comments on the Phase 1 and
Phase 2 Draft EIS documents, as well as any additional analysis that may be required to
provide a thorough project-level environmental review for the Energize Eastside Project. The
Final EIS, expected to be completed in spring 2017, will be used by each of the study area
communities in making permit decisions regarding the project.
January 2016 CHAPTER 1 INTRODUCTION AND SUMMARY 1-57
PHASE 1 DRAFT EIS
CHAPTER 2. PROJECT ALTERNATIVES
2.1 WHAT DOES THIS CHAPTER COVER?
This chapter provides a description of project alternatives evaluated in the Draft
Environmental Impact Statement (EIS). The alternatives described in this chapter were
developed based on discussions between the partner Cities, the EIS Consultant Team, and
Puget Sound Energy (PSE). This chapter also identifies alternatives considered but not
evaluated in the Draft EIS because they did not meet PSE’s project objectives. As required by
the State Environmental Policy Act (SEPA), benefits and disadvantages of delaying PSE’s
project are described at the end of this chapter. The project includes numerous terms that may
not be familiar to all readers. Words shown in italics when they first appear in the document
are included in the Glossary following the Table of Contents.
2.2 WHAT ARE PUGET SOUND ENERGY’S PROJECT
OBJECTIVES FOR ENERGIZE EASTSIDE?
Under SEPA, alternatives evaluated in an EIS must feasibly meet or approximate the project
objectives. PSE, a regulated utility and the proponent for the Energize Eastside Project,
developed the objectives of the proposal. Under SEPA, the objectives must be defined in a
manner that does not preclude feasible alternatives that would have lower environmental
costs (WAC 197-11-440(5)(b)).
As described in Chapter 1, the objectives for the project are to address a deficiency in
transmission capacity on the Eastside that PSE expects will arise in the near future; find a
cost-effective solution that can be implemented before system reliability is impaired; meet
federal, state, and local regulatory requirements; and address PSE’s electrical and non-
electrical criteria for the project as outlined below. The transmission capacity deficiency PSE
has identified is a product of the complex system that PSE uses to supply power to the
Eastside, and the regulations PSE must follow as a utility provider making use of the regional
electrical grid. As such, the criteria for what constitutes a viable solution are correspondingly
complex.
The following is a list of project criteria from PSE’s Supplemental Eastside Solutions Study
Report (May, 2015) (Gentile et al., 2015). PSE’s criteria are based on regulations for utilities
and prudent, safe industry practices. They include 15 electrical criteria and 4 non-electrical
criteria. The criteria are listed below, followed by a detailed explanation of each criterion in
Sections 2.2.1 and 2.2.2. Background information regarding system contingencies and
normal winter and summer load forecasts is provided in Sections 2.2.3 and 2.2.4.
January 2016 CHAPTER 2 PROJECT ALTERNATIVES 2-1
PHASE 1 DRAFT EIS
Electrical Criteria Summary
The project would meet the following criteria:
1. Applicable transmission planning standards and guidelines, including mandatory
North American Electric Reliability Corporation (NERC) and Western Electricity
Coordinating Council (WECC) standards (e.g., NERC TPL-001-4 and WECC TPL-
001-WECC-CRT-2);
2. Within study period (2015– 2024);
3. Less than or equal to 95 percent of emergency limits for lines;
4. Less than or equal to 90 percent emergency limit for transformers;
5. Normal winter load forecast with [both] 100 percent and 75 percent conservation;
6. Normal summer load forecast with 100 percent conservation;
7. Adjust regional flows and generation to stress cases similar to annual transmission
planning assessment;
8. Take into account future transmission system improvement projects that are expected
to be in service within the study period;
9. Minimal or no re-dispatching of generation;
10. No load shedding;
11. No new Remedial Action Schemes;
12. No Corrective Action Plans;
13. Must address all relevant PSE equipment violations;
14. Must not cause any adverse impacts to the reliability or operating characteristics of
PSE’s or surrounding systems; and
15. Must meet performance criteria listed above for 10 or more years after construction
with up to 100 percent of the emergency limit for lines or transformers.
Non-electrical Criteria Summary
The project would meet or approximate the following criteria:
1. Environmentally acceptable to PSE and communities;
2. Constructible by winter of 2017 - 2018;
3. Utilize proven technology which can be controlled and operated at a system level;
and
4. Reasonable project cost, as defined in Section 2.2.2.4.
Collectively, these criteria were considered the fullest expression of PSE’s objectives in
developing solutions for the Energize Eastside Project. The electrical criteria listed are
generally in line with criteria used in the electrical industry. Therefore, these criteria were
CHAPTER 2 January 2016 2 -2 PROJECT ALTERNATIVES
PHASE 1 DRAFT EIS
used to identify reasonable alternatives for consideration in this EIS. The non-electrical
criteria listed are typical of considerations made by utilities in project planning. While these
are important in considering the solution, for this Phase 1 Draft EIS these criteria were
generally not used to screen out alternatives.
Consideration of environmental impacts is part of the process for selecting alternatives under
SEPA, in that alternatives considered in an EIS must approximate the proponent’s objectives
at a lower environmental cost. While the desired implementation schedule is important and
reasonable, there are uncertainties associated with any of the alternatives including PSE’s
proposal that could delay implementation beyond these dates. With regard to what is
considered proven technology, there is no clear-cut definition of what makes a technology
proven. Therefore, a wide range of technologies that are in use at various scales have been
evaluated, including some technologies that PSE does not currently utilize. For PSE, what
constitutes reasonable cost is driven by PSE’s responsibilities to deliver power at the lowest
feasible cost to ratepayers. However, under SEPA, alternatives may be considered that are
not the lowest feasible cost. For the Phase 1 Draft EIS alternatives, cost was not used to
screen out any alternatives, in order to provide a more complete understanding of the
environmental effects of alternatives before project-level alternatives are selected.
To clarify PSE’s criteria for the community and decision-makers, PSE, the Eastside Cities,
and the EIS Consultant Team developed brief explanatory descriptions for each criterion,
provided in Sections 2.2.1 and 2.2.2. These descriptions were developed based on PSE
documents and the EIS Consultant Team’s familiarity with the power delivery system in
western North America. The descriptions have been reviewed for accuracy and completeness
by PSE and City staff with the five partner Eastside Cities that are leading this EIS process,
and consulting electrical engineers on the EIS Consultant Team (Stantec).
2.2.1 Electrical Criteria
The electrical criteria used by PSE are briefly defined below.
2.2.1.1 Applicable transmission planning standards and guidelines,
including mandatory NERC and WECC standards
These federal requirements mandate that PSE “shall demonstrate through a valid assessment
that its portion of the interconnected transmission system is planned such that the Network
can be operated to supply projected customer demands and projected Firm (non-recallable
reserved) Transmission Services, at all demand levels over the range of forecast system
demands” under NERC performance categories. Essentially, PSE must plan the system to
function in scenarios where customer demand may be at its highest and/or elements of the
system may be out of service. Below are examples of the standards and guidelines used
during the PSE planning process.
2.2.1.1.1 N-0 Thermal and Voltage Performance – NERC and
WECC standards
This refers to system performance with all system components operating normally. The
system must perform without violations (exceedances) of thermal and voltage limits with all
systems operating and no contingencies occurring. A contingency refers to a system
January 2016 CHAPTER 2 PROJECT ALTERNATIVES 2-3
PHASE 1 DRAFT EIS
condition in which an equipment component is not operating normally and may be turned off
or in limited operation, either as a result of an emergency or as part of scheduled maintenance
or system improvements. Additional discussion of N-0 is providwed in Section 2.2.3.
2.2.1.1.2 N-1 Thermal and Voltage Performance – NERC and
WECC standards
This refers to system performance with one contingency in the system. The system must
perform without violations (exceedances) of thermal and voltage limits with one contingency
occurring. Additional discussion of N-1 is provided in Section 2.2.3.
2.2.1.1.3 N-1-1 & N-2 Thermal and Voltage Performance – NERC
and WECC standards
This refers to system performance with two contingencies in the system. This could be due to
an emergency, as part of scheduled maintenance or system improvements, or a combination
of circumstances. The system must perform without violations of thermal and voltage limits
with two contingencies occurring. Additional discussion of N-1-1 and N-2 is provided in
Section 2.2.3.
2.2.1.1.4 Use of Corrective Action Plans (CAPs) and Remedial
Action Schemes (RAS) – NERC and WECC standards
See Sections 2.2.1.11 and 2.2.1.12 below.
2.2.1.1.5 Substation Planning and Security Guidelines
PSE’s Transmission Planning Guidelines state: “Transmission substations should be laid out
for ultimate double 230 - 115 kV transformer bank configuration.” On November 20, 2014,
the Federal Energy Regulatory Commission (FERC) issued Order 802 Critical Infrastructure
Protection (CIP). That order states, “Physical attacks to the Bulk-Power System can
adversely impact the reliable operation of the Bulk-Power System, resulting in instability,
uncontrolled separation, or cascading failures.” On July 15, 2015, FERC issued a follow-up
order to CIP-014. Paraphrasing from that order, certain registered entities are required to take
steps (or demonstrate that they have already taken steps) to address physical security risks
and vulnerabilities related to the reliable operation of the bulk power system. Owners or
operators of the bulk power system must identify facilities that are critical to reliable
operation. The owners or operators of those identified critical facilities shall develop,
validate, and implement plans to protect against physical attacks that may compromise the
operability or recovery of such facilities. Following the FERC direction, as well as prudent
planning and operating standards, PSE limits the number of transformers at substations to
two 230 – 115 kV transformer banks. In other words, based on security threats to the physical
electric infrastructure, it is not reasonable or prudent to “put all your eggs in one basket.”
2.2.1.2 Within study period (2015 – 2024)
This refers to the 10-year study period during which potential solutions must meet the
solution criteria. The study period is defined as the 10-year period between 2015 (the study
year of the Supplemental Eastside Solutions Study Report) and 2024 (the final year of the
WECC base cases used for the study).
CHAPTER 2 January 2016 2 -4 PROJECT ALTERNATIVES
PHASE 1 DRAFT EIS
2.2.1.3 Less than or equal to 95 percent of emergency limits for lines
PSE has two thermal operating limits: normal and emergency. The normal operating limit is
a specific level of electrical loading that a system, facility, or element can support or
withstand through the daily demand cycles without loss of equipment life. The emergency
limit is a specific level of electrical loading that a system, facility, or element can support or
withstand for a finite period. The emergency rating is based upon the acceptable loss of
equipment life or other physical or safety limitations for the equipment involved. If there is a
violation of the emergency limit, a transmission line may not meet applicable clearance
criteria and risk loss of mechanical strength due to overheating.
PSE’s operating practice is to shift or shed load, or increase or decrease electrical generation,
to avoid reaching an emergency limit. PSE utilizes 95 percent of the emergency limit as an
indication of when PSE needs to start the process to study and upgrade the system to prevent
violations of mandatory performance requirements and equipment degradation. The system
operator receives an alarm when the transmission line reaches 95 percent of its emergency
limit. If an alarm is triggered, the system operator takes steps to shift or shed load to prevent
damage to the transmission line.
All PSE transmission lines of any voltage must remain equal to or below 95 percent of the
emergency line-loading limit over the study period in order for a viable alternative to be
considered a potential solution. This includes all periods of the year, whether the system is
operating under normal or abnormal system configurations, or during light load or peak load
conditions.
2.2.1.4 Less than or equal to 90 percent emergency limit for
transformers
As discussed above, PSE has two thermal operating limits: normal and emergency. If there is
a violation of the emergency limit in a transformer, it may overheat, causing a breakdown in
internal insulation and leading to a transformer failure or reducing its operational life.
Substation transformers are filled with oil to facilitate cooling and insulation. However, if the
transformer overheats, the oil may catch fire or explode, which is a serious safety concern.
PSE’s operating practice is to shift or shed load or dispatch generation to avoid reaching an
emergency limit. PSE uses a measure of 90 percent of the emergency limit for transformers
as an indication of when PSE needs to start the process to study and upgrade the system to
prevent violations of mandatory performance requirements and equipment loss of life. The
system operator receives an alarm when a 230 to 115 kV transformer reaches 90 percent of
its emergency limit. If an alarm is triggered, the system operator takes steps to shift or shed
load, or dispatch generation to prevent damage to the transformer.
All 230 kV to 115 kV PSE transformers must remain equal to or below 90 percent of the
emergency loading limit over the study period in order for a viable alternative to be
considered a potential solution. This includes all periods of the year, whether the system is
operating under normal or abnormal system configurations, or during light load or peak load
conditions.
January 2016 CHAPTER 2 PROJECT ALTERNATIVES 2-5
PHASE 1 DRAFT EIS
2.2.1.5 Normal winter load forecast with both 100 percent and 75
percent conservation
A normal winter load forecast represents a snapshot in time reflecting the highest expected
load in winter for the given year of the forecast. The load is calculated for the coldest winter
weather event with a 1 in 2 (50 percent) chance of occurring in a given year (also referred to as
the two-year winter weather event). This would not be considered an average load, but a peak
load. The peak load is used to ensure that the system can withstand the highest estimated
loading under all system configurations and still reliably serve customers.
A 100 percent conservation level is the amount of reduction in load that PSE estimates could
reasonably be attained through energy efficiency, demand response, and distributed
generation. The 75 percent conservation level is the estimated amount of reduction in load
multiplied by 0.75 to account for the possibility of achieving only 75 percent of the projected
conservation. This factor addresses the potential that the level of conservation that is actually
achieved may be inconsistent with the study model assumptions in some locations. Perfect
precision cannot be attained without completely accurate data, and the 75 percent
conservation level serves as a gauge to help planners understand the ramifications if the
model does not precisely mimic a real-world scenario.
The “normal winter forecast with 100 percent conservation” is the peak load forecast for
winter, taking into account the 100 percent conservation level for winter. The “normal winter
forecast with 75 percent conservation” is the peak load forecast for winter, taking into
account the 75 percent conservation level for winter. PSE needs both forecast scenarios to be
met for a viable solution.
Load forecasts and conservation levels (reduction in load) are evaluated in detail in PSE’s
most recent Needs Assessment report and are based on several parameters, such as historical
metering data and population statistics. Refer to the Supplemental Eastside Needs Assessment
Report (PSE and Quanta Technology, 2015) for detailed information. Additional information
on what is considered a normal winter load is provided in Section 2.2.4.
2.2.1.6 Normal summer load forecast with 100 percent conservation
A normal summer load forecast represents a snapshot in time reflecting the highest expected
load in summer for the given year of the forecast. The load is calculated for the warmest
summer weather event with a 1 in 2 (50 percent) chance of occurring in a given year (two-year
summer weather event). One major difference between summer and winter peak loads is the
different demand levels and use patterns associated with winter heating versus summer
cooling. The 100 percent conservation level used in summer is different from the amount of
reduction used for a 100 percent winter conservation level. The “normal summer forecast
with 100 percent conservation” is the peak load forecast for summer, taking into account the
100 percent conservation level for summer. It is the peak expected load to be used in the
study for summer conditions.
Additional information on what is considered a normal summer load is provided in
Section 2.2.4.
CHAPTER 2 January 2016 2 -6 PROJECT ALTERNATIVES
PHASE 1 DRAFT EIS
2.2.1.7 Adjust regional flows and generation to stress cases similar to
annual transmission planning assessment
In the course of conducting a load flow study to determine system constraints, many
scenarios must be evaluated to simulate real-world possibilities. This is a requirement of the
regional agencies (NERC and WECC) that govern the power grid in order to make sure it
functions reliably for all utility customers. To that end, the transmission planning assessment
is just one measure of system reliability. The load flow model itself is merely a mathematical
simulation of all the components of the interconnected electric system. The model can only
represent a snapshot of the system at a particular moment in time. To gain a full picture of
system performance, many scenarios—sometimes called stress cases, sensitivity cases, or
snapshots—must be reviewed. Each stress case adjusts both generation and regional flows. The
combination gives a sense of real-world reaction to system operating conditions. The regional
flows and generation levels used are based on a range of possible real-world conditions and
are not a theoretical device to overwhelm the system. PSE studied both a minimal generation
level stress case and a stress case that included an additional 1,000 megawatts (MW) of
generation.
In addition, thousands of contingencies are evaluated. Contingencies are similar snapshots of
the system that evaluate what happens when a transmission line or a transformer is out of
service. The study also evaluates the possibility of two components being out of service at the
same time. Light load periods as well as peak load periods present their own peculiar
problems, and these too must be evaluated in snapshots. Finally, all of these snapshots begin
to paint a picture for the planner of where the strengths and weaknesses of the system reside.
This criterion requires that this type of stress case assessment must be performed for all
solutions and a viable solution must work under all stress cases.
2.2.1.8 Take into account future transmission system improvement
projects that are expected to be in service within the study
period
The transmission system is constantly evaluated by each utility and the regional entities that
unite them to ensure its performance and ability to provide electric power to customers. Each
utility and regional agency proposes improvements as needed, such as the 230 kV
transformer and transmission line PSE has proposed. When an improvement project has been
identified by a utility, it is the utility’s or regional authority’s responsibility to accurately
report the change to WECC so that it can be reflected in the future load flow models that
WECC prepares. It is important to know not only the extent of the project, but also when it
will be placed in service. One of WECC’s responsibilities is to gather this information and
prepare the models of specific configurations of generation and transmission in operation
(also referred to as cases) based on specific year, load, and other conditions, and make these
available to utility planners. However, it is PSE’s or the other utility planners’ responsibility
to make sure that the models they use are correct. Part of that responsibility includes
adjusting for any facility plans that may have changed after the WECC model is built, and
adjusting for any facilities that may not yet be in service for the years that the utility planner
is assessing.
January 2016 CHAPTER 2 PROJECT ALTERNATIVES 2-7
PHASE 1 DRAFT EIS
2.2.1.9 Minimal or no re-dispatching of generation
Minimal or no re-dispatching of generation means that, in the normal course of study, PSE
does not adjust the amount of generation coming from various generation sources to solve
long-term problems. In a real-time scenario, generation is normally dispatched, which means
a particular generation output level is set based on the needs of the local economy at a
particular time period. Therefore, planners do not want a solution that involves ramping
generation up or down to solve a long-term problem. In this case, dispatching generation has
little or no impact on solving the transformer overloads on the Eastside, since there is no
existing generation within the Eastside area, and ramping generation up or down outside of
the Eastside area has little impact on Eastside transformer loading.
2.2.1.10 No load shedding
Load shedding is an intentionally engineered electrical power shutdown when electricity
delivery is stopped for a period of time, usually during peak load. A rolling blackout, also
referred to as rotational load shedding or feeder rotation, is an intentionally engineered
electrical power shutdown when electricity delivery is stopped for periods of time over
different parts of the distribution region. Load shedding or rolling blackouts are a last-resort
measure used by an electric utility company to avoid a larger or more catastrophic outage of
the power system. Load shedding is a type of demand response for a situation when the
demand for electricity exceeds the power supply capability of the network. Load shedding, or
rolling blackouts, generally result from one of two causes: insufficient generation capacity, or
inadequate transmission infrastructure to deliver sufficient power to the area where it is
needed.
As is typical of electric service providers, PSE does not
use load shedding as a long-term solution to meet
mandatory performance requirements. While NERC and
WECC allow dropping load for certain contingencies,
intentionally dropping firm load for an N-1-1 or N-2
contingency to meet federal planning requirements is not a
practice that PSE endorses, because of the costs and inconvenience that outages impose on its
customers.
2.2.1.11 No new Remedial Action Schemes
A Remedial Action Scheme (RAS) is designed to detect predetermined system conditions
and automatically take corrective actions that may include, but are not limited to, adjusting or
tripping (shutting down) generation, shedding load, or reconfiguring a system. An RAS may
accomplish objectives such as the following:
• Meet requirements identified in the NERC Reliability Standards;
• Maintain acceptable voltages;
• Maintain acceptable power flows; or
• Limit the impact of cascading outages, system instability, or extreme events.
What is firm load? Firm load is
energy that a supplier is required
by contract to provide without
interruption (except during
extreme emergencies).
CHAPTER 2 January 2016 2 -8 PROJECT ALTERNATIVES
PHASE 1 DRAFT EIS
An RAS is normally administered automatically to control regional issues in the power
system. PSE, like other utilities, develops and employs RASs to address short-term
conditions that may arise as a result of problems on their system or on the regional grid.
This criterion requires that for a solution to be viable, no additional RASs would be needed.
This is because use of RASs complicates the operation of the existing system, which adds
risk and reduces predictability. An RAS is not considered a long-term solution to solve a
local transmission deficiency.
2.2.1.12 No Corrective Action Plans
A Corrective Action Plan (CAP) is similar to an RAS. However, CAPs are usually corrective
actions made manually by local system dispatchers and are intended to control local
problems. In contrast, an RAS is typically administered automatically to control regional
issues in the power system.
According to NERC, CAPs are temporary until a permanent solution is put in place. For a
solution to be viable, no additional CAPs can be needed because they only complicate the
operation of the existing system and do not provide a long-term solution.
2.2.1.13 Must address all relevant PSE equipment violations
PSE will only accept solutions that will solve any existing or future anticipated loading issues
of PSE equipment. PSE’s normal and emergency thermal operating limits, and potential
consequences of violating those limits, are discussed earlier in this section.
2.2.1.14 Must not cause any adverse impacts to the reliability or
operating characteristic of PSE’s or surrounding systems
Under NERC and WECC guidelines, PSE cannot propose a project that will adversely affect
the region, and it would be counterproductive for PSE to introduce a solution that raises other
issues within its own system.
2.2.1.15 Must meet performance criteria listed above for 10 or more
years after construction with up to 100 percent of the
emergency limit for lines or transformers
If the proposed solution is needed by the winter of 2017 - 2018 and the solution is only viable
until the end of the study period (2024), then PSE would need to start its next system
improvement within a couple of years after the solution is put into service. PSE does not see
this as realistic or prudent. A long-term solution must last through 2028, which is considered
to be 10 years past the estimated 2018 in-service date. Additionally, the solution must not
exceed 100 percent of the emergency limit for lines and transformers. Exceeding the 100
percent emergency limit will incur mandatory performance violations and equipment loss of
life.
This criterion is established as a minimum period of time for a solution to be considered a
long-term solution. Because of the standardized steps in voltage and equipment sizes (e.g.,
115 kV and 230 kV), an alternative may exceed the 10-year minimum. Ideally, the best
January 2016 CHAPTER 2 PROJECT ALTERNATIVES 2-9
PHASE 1 DRAFT EIS
solution would exceed these minimum longevity requirements by providing options for
future needed electric system reinforcements, such as an additional transformer, which could
accommodate future growth beyond the 2028 timeframe.
2.2.2 Non-electrical Criteria
The criteria listed below reflect PSE’s preferences regarding environmental concerns, project
timing, degree of control and reliability of any solutions, and project cost. While these
objectives are acknowledged as important, under SEPA and other permitting authority, the
partner Cities generally did not weigh these equally with electrical criteria in selecting
alternatives. This is because electrical criteria are generally non-discretionary, except in
certain cases, such as system security. In contrast, non-electrical criteria are more
discretionary. The partner Cities applied their own discretion in determining if an alternative
was environmentally acceptable to carry forward in this Phase 1 Draft EIS, and did not
eliminate any alternatives because of timing, unproven technology, controllability by PSE, or
cost. These criteria, which are explained in greater detail below, may be considered in the
project-level Draft EIS in Phase 2 of this EIS process.
2.2.2.1 Environmentally acceptable to PSE and communities
For PSE, environmentally acceptable means a solution that, through the environmental
review process, would be found to minimize, to the extent practicable, the environmental
impacts on the affected communities. This Phase 1 Draft EIS provides an evaluation of
impacts for the range of alternatives so that citizens and decision-makers can understand the
environmental tradeoffs.
2.2.2.2 Constructible by winter of 2017 - 2018
PSE studies show that Eastside customer demand will reach a point when the Eastside’s
electric transmission system capacity could experience a deficiency as early as winter 2017 -
2018. To be a viable solution, a project must be completed and in service by the identified
target need date. For example, PSE’s current schedule for the proposed 230 kV transformer
and transmission line installation targets construction to begin in 2017, with project
completion in 2018. Any delay in the schedule would push the in-service date beyond the
2018 winter timeframe, which would increase PSE’s reliance on the use of CAPs and load
shedding. PSE must prepare for project construction several years in advance because some
specialized equipment can take up to 3 years to procure. Alternatives must be reviewed to
ensure they are reasonably constructible by the in-service target date of 2018.
2.2.2.3 Utilize proven technology which can be controlled and
operated at a system level
To PSE, proven technology means technology that has been successfully operated with
acceptable performance and reliability within a set of predefined criteria. Proven technology
must have a documented track record for a defined environment, meaning there are multiple
examples of installations with a history of reliable operations. Such documentation must
provide confidence in the technology from practical operations, with respect to the ability of
the technology to meet the specified requirements.
CHAPTER 2 January 2016 2 -10 PROJECT ALTERNATIVES
PHASE 1 DRAFT EIS
“Controlled and operated at a system level” means a dispatcher at a local control center can
turn resources on/off or reroute resources either manually or automatically from the dispatch
center, or a dispatcher can instruct field personnel to do the same. This criterion rules out
independent “behind-the-meter” resources that PSE could not call on as needed. Further, it
means that PSE would need to conduct maintenance on, or inspections of, the resources to
ensure that they are:
• Operational;
• Providing the capacity they are designed and intended to provide (referred to as
nameplate capacity); and
• Available to be used when needed.
2.2.2.4 Reasonable project cost
PSE has a legal obligation to deliver safe, dependable
power, and an obligation to do so at a reasonable cost. PSE
continually balances these obligations in determining the
best solutions to solve problems facing the electric system.
The Washington Utilities and Transportation Commission
(UTC) also has an obligation to review all PSE projects to
determine if the solution is reasonable and prudent. After a
project is complete and before the costs are allowed to be
placed into the rate base, PSE must prove to the UTC that
the cost to build a project is prudent and reasonable to
ratepayers. This means PSE must research and compare
costs and benefits of multiple alternatives that can accomplish the desired objectives. This is
not a simple lowest project cost test; it is a holistic review and analysis of factors such as
projected duration of solution, risk to the electric system associated with the type of solution
(e.g., is the solution an untested technology), and impacts to the community, as well as the
dollar cost of the project. PSE has completed some of this evaluation already, and will
continue to evaluate costs through the design and permitting phase of the project.
2.2.3 Understanding System Contingencies and their Frequencies
To understand the nature of the issue that PSE is proposing to address with the Energize
Eastside Project, it is helpful to know about the frequency of conditions that produce the
deficiency in transmission capacity that PSE has identified. This includes an understanding of
how often there are equipment outages that affect the transmission system.
The PSE bulk electric transmission system includes approximately 2,100 components1 that
are included in its system model. Not all of these components affect the systems on the
Eastside, but many components that are outside of the Eastside do affect how and where
power flows into the Eastside. When everything is operating normally, the system is said to
1 Transmission system elements include transmission lines 115 kV and above, transformers whose low side
is 115 kV or above, generators connected to transmission, generator stepup transformers, reactive devices
connected to transmission, substation bus sections at 115 kV and above, and circuit breakers at 115 kV
and above.
What is a rate base? A rate
base is a set of costs that PSE
is allowed to recover over time
through rates and fees
charged to its customers. See
the UTC website for more
information:
http://www.utc.wa.gov/regulat
edIndustries/utilities/energy/Pa
ges/financialDataForElectricCo
mpanies.aspx
January 2016 CHAPTER 2 PROJECT ALTERNATIVES 2-11
PHASE 1 DRAFT EIS
be in an N-0 state. An N-1 outage condition can occur at any time when a single component
trips or is taken offline. This occurs when a problem is detected or because some damage has
occurred. It can also be a result of routine maintenance when a system component must be
taken out of service (if possible, routine maintenance would not be scheduled during peak
load periods or during bad weather). In a typical year, the PSE system operates in an N-1
condition about 350 - 360 days per year (almost every day). These conditions persist for
approximately 60 percent of the time each year 2.
An N-1-1 outage condition is an N-1 outage followed by a period of time to manually adjust
the system to a secure state, followed by a second N-1 outage. This occurs when a problem is
detected or some damage occurs followed by an additional problem or damage event.
However, it can also be a result of routine maintenance when a system component must be
taken out of service, and the second N-1 outage occurs unexpectedly. Most days PSE
operates in a mode where multiple elements are taken out of service across PSE’s service
territory. Most of these combinations do not cause customer outages the way the “N-1-1”
outages do. In a typical year, the PSE system operates in an N-1-1 condition that causes
customer outages about 15 to 30 times per year, each of which persists for approximately 4 to
12 hours 3, or less than 2 percent of the year2.
An N-2 outage is when a single event trips multiple facilities, such as certain instances when
all the breakers in a substation trip offline, leaving several circuits without power, or a
problem occurs that affects both circuits of a double circuit transmission line (two
transmission circuits located on one structure). This occurs when a problem is detected, or
some sort of damage has occurred. It can also be a result of routine maintenance when
multiple system components must be taken out of service. However, if at all possible, routine
maintenance avoids multiple elements, and if necessary, would most likely not be scheduled
during peak load periods or poor weather. In a typical year, the PSE system operates in an
N-2 condition about 10 to 20 days per year, and persists for approximately 4 to 12 hours, or
less than 1 percent of the year2.
2.2.4 Understanding Normal Winter and Summer Load Forecasting
The normal peak weather events that PSE uses in its model to test its system are typical
extended periods of either cold winter temperatures or hot summer temperatures,
temperatures that have a 50 percent likelihood of occurring in a given year. For winter, this
means a temperature of 23 degrees Fahrenheit or lower at the time of the system peak. For
summer, this means a temperature of 86 degrees Fahrenheit or higher at the time of the
system peak.
2.3 PROJECT ALTERNATIVES
This Phase 1 Draft EIS evaluates PSE’s proposed Energize Eastside Project (a 230 kV
overhead line), a No Action Alternative (as required by SEPA), and two other “action
alternatives.” These alternatives were developed by the partner Cities in cooperation with
PSE, with the intent of providing options that could attain or approximate PSE objectives for
2 These are estimates; PSE does not track outages in this format.
3 This duration is an average and storm events can run much longer than 12 hours or shorter than 4 hours.
CHAPTER 2 January 2016 2 -12 PROJECT ALTERNATIVES
PHASE 1 DRAFT EIS
the project at a lower environmental cost. The No Action Alternative provides a benchmark
against which the proposed project and other action alternatives can be compared.
Alternative 1 includes the 230 kV overhead lines but also includes options for locations,
including underground and underwater options. Alternative 2 includes a variety of solutions
that would require very limited new transmission lines next to existing substations and would
need to be implemented in combination in order to meet the project objectives. Alternative 3
would involve installing enough 115 kV lines and transformers to address the project
objectives without building 230 kV lines. Each alternative is described in more detail below.
2.3.1 No Action Alternative
The No Action Alternative is defined as those actions
PSE would undertake to serve the project objectives
without requiring issuance of state or local permits
(something PSE could build or undertake immediately if
the proposed project is not approved). The No Action
Alternative represents the most likely outcome if the
proposed project is not implemented, and it is considered
the baseline condition.
The study area for the No Action Alternative is shown on
Figure 1-4, which is the combined study area for all
alternatives. The combined study area was used to
describe the affected environment for this Phase 1 Draft
EIS. The alternatives are located collectively within the
following public land survey system townships and
ranges: T25N / R6E, T25N / R5E, T24N / R6E, T24N /
R5E, and T23N / R5E.
Based on U.S. Census and Puget Sound Regional
Council population forecast data, PSE’s analysis
concluded that the population in PSE’s service area on
the Eastside is projected to grow by approximately 1.2
percent per year over the next 10 years and employment
is expected to grow by 2.1 percent per year, resulting in
additional electrical demand (Gentile et al., 2015).
If electrical load growth occurs as PSE has projected,
PSE’s system would likely experience loads on the
Eastside that would place the local and regional system at risk of damage if no system
modifications are made. To address this risk in the near term, PSE would use CAPs
(described in Section 2.2.1.12), which are a series of operational steps used to prevent system
overloads or large-scale loss of customers’ power. CAPs generally involve shutting off or
reducing load on overloaded equipment and rerouting the load to other equipment. The CAPs
are seen as temporary measures used to keep the entire system operating, but they can place
large numbers of customers at risk of a power outage if anything else on the system begins to
fail.
How does PSE’s
conservation compare to
other utilities? PSE’s level of
conservation is higher than
other nearby utilities. For
example, PSE expects to
conserve about 500 MW
cumulatively from 2013 to
2023, which represents
approximately 15 percent of
their projected average
demand (load) of about 3,300
MW for that year (PSE, 2013).
Seattle City Light (SCL)
expects slower load growth
than PSE, and total cumulative
conservation from 2014
through 2023 to represent
approximately 9 percent of
average load (SCL, 2014).
Snohomish Public Utility
District (PUD), which expects
load growth of approximately 2
percent per year, projects its
total cumulative conservation
since 2014 to represent
approximately 9 percent of
average load in 2024
(Snohomish PUD, 2013).
January 2016 CHAPTER 2 PROJECT ALTERNATIVES 2-13
PHASE 1 DRAFT EIS
Under the No Action Alternative, PSE would continue to manage its system as at present.
This includes maintenance programs to reduce the likelihood of equipment failure, and
stockpiling additional equipment so that in the event of a failure, repairs could be made as
quickly as possible.
Under the No Action Alternative, this EIS assumes that PSE would continue to achieve 100
percent of the company’s conservation goals as outlined in its 2013 Integrated Resource Plan
(PSE, 2013), systemwide and for the Eastside. Conservation goals are achieved through a
variety of energy efficiency improvements implemented by PSE and its customers.
Conservation refers to electrical energy savings above and beyond state or local energy code
requirements.
Table 2-1 shows PSE’s projected conservation for its entire system and for the Eastside. For
the Eastside in 2024, PSE projected that proposed conservation measures would address
approximately 110 MW of peak usage, leaving a remaining Eastside load of 764 MW
needing to be served during projected peak periods. The conservation measures would
address approximately 13 percent of the peak load. PSE currently conserves approximately
21 MW, or 3 percent of the Eastside baseline peak load. For comparison, systemwide, PSE is
estimated to have achieved system peak conservation of approximately 91 MW or
approximately 1.9 percent of the system peak of 4,803 MW (peak load without conservation)
in 2014 through 2015.
Table 2-1. Peak Load Addressed Through Conservation Measures by PSE Service
Area and Year
PSE Service
Area and Year
Peak Load
Addressed Through
Conservation
Measures
Remaining
Peak Load
Percent of Peak Load
Addressed Through
Conservation Measures
Eastside
2015 21 MW 679 MW 3%
2024 110 MW 764 MW 13%
Systemwide
2014-2015 91 MW 4,712 MW 1.9%
To achieve its electrical conservation goals, PSE expects to incentivize the following types of
measures:
• Energy Efficiency: weatherization, efficient lighting, etc.;
• Fuel Conversion: converting from electric to natural gas;
• Distribution Efficiency: implemented on PSE distribution systems;
• Distributed Generation: customer combined heat and power (CHP), solar, wind, etc.;
and
CHAPTER 2 January 2016 2 -14 PROJECT ALTERNATIVES
PHASE 1 DRAFT EIS
• Demand Response: capacity savings programs.
Energy efficiency is the largest contributor to total energy savings in PSE’s conservation
program, accounting for approximately 90 percent of total energy savings systemwide by
2024. Fuel conversion (from electric to natural gas) and distributed generation (smaller
sources of power such as solar, wind, and other generation types) represent a small but
growing component of PSE’s conservation program, jointly comprising less than 10 percent
of existing energy savings but projected to increase to approximately 14 percent of energy
savings by 2024. Figure A-1 in Appendix A provides additional detail.
Distribution efficiency can include conductor replacement and conservation voltage
reduction. Conductor replacement on existing lines could occur under the No Action
Alternative as part of normal maintenance. However, these improvements would not
substantially increase overall system capacity because capacity issues driving this project are
typically associated with transformer overloads rather than conductor overloads. PSE would
continue the current practice of using advanced systems, such as conservation voltage
reduction, to improve system efficiency and reduce overall loading. Conservation voltage
reduction refers to controlling PSE’s distribution voltage at slightly reduced levels to
conserve energy.
The other components of PSE’s conservation program comprise relatively small percentages
of their conservation target at present. Distributed generation and demand response are two of
the components that are included in Alternative 2 and are discussed in further detail in
Section 2.3.3.
There are no currently known new technologies that PSE would employ that could
substantially affect the transmission capacity deficiency on the Eastside. Under the No
Action Alternative, PSE would not be precluded from seeking out new technologies,
however.
2.3.1.1 Construction
Under the No Action Alternative, construction activities would likely be limited to occasional
conductor replacement, implementation of new technologies not requiring discretionary
permits, and installation of distributed generation facilities under PSE’s conservation
program (e.g., solar panels, wind turbines, or rooftop generators). While conductor
replacement could occur under the No Action Alternative, installation methods would likely
involve the use of a single-man lift.
2.3.2 Alternative 1: New Substation and 230 kV Transmission Lines
(Puget Sound Energy Proposal)
Under this alternative, PSE would install a new transformer somewhere near the center of the
Eastside to convert 230 kV bulk power to 115 kV to feed the Eastside distribution system.
The new transformer would be installed at or near one of three properties that are either
adjacent to existing substations or have been purchased by PSE for future substations.
January 2016 CHAPTER 2 PROJECT ALTERNATIVES 2-15
PHASE 1 DRAFT EIS
The study areas for each action alternative correspond to the areas where the project
components would be constructed and operated. The Alternative 1 study area includes
portions of Bellevue, Kirkland, Newcastle, Redmond, and Renton, and unincorporated King
County (Figure 2-1). Alternative 1, Option D assumes in-water work within a portion of Lake
Washington, including waterside areas along the shorelines of Beaux Arts Village, Bellevue,
Clyde Hill, Hunts Point, Kirkland, Medina, Mercer Island, Renton, and Yarrow Point (Figure
2-1).
To supply the new transformer, two new 230 kV transmission lines would be constructed to
bring power from existing 230 kV sources. PSE’s Talbot Hill substation in Renton and
Sammamish substation in Redmond are the closest existing 230 kV sources to the center of
the Eastside, and are considered the southern and northern ends of this alternative. The Phase
1 Draft EIS considers that transmission lines could be placed in existing or new corridors,
including adjacent to roads or highways. Because of the density of development on the
Eastside, any new overland corridor would be likely to entail acquisition and removal of
buildings.
For the Phase 1 Draft EIS, three basic types of 230 kV transmission lines are considered
capable of meeting the project objectives: overhead (new as well as existing transmission
lines), underground, and underwater (also referred to as submerged or submarine). The new
230 kV line could also be a combination of these types.
Solutions considered part of this alternative include “single
circuit” lines as well as solutions that would allow for
addition of a second 230 kV circuit on the same poles, in the
same corridor, or in the same underground or underwater
facility.
Operation of Alternative 1 would involve limited but regular
maintenance along the transmission lines. Substation
operation would involve regular site inspection and
maintenance. All proposed equipment is subject to wearing out and would need to be
replaced when this occurs, typically after several years of use. Replacement of conductors
would be similar to the final steps of installation. Replacement of substation equipment
would be similar to the final stages of construction, involving heavy trucks delivering
equipment and cranes to remove and replace equipment.
The types of lines being considered for Alternative 1 have been categorized into four options
as follows: Option A—new overhead transmission lines; Option B –use existing Seattle City
Light (SCL) overhead transmission lines; Option C–underground transmission lines; and
Option D–underwater transmission lines. These options are described in Sections 2.3.2.2
through 2.3.2.5.
For the Phase 1 Draft EIS, a study area was selected that assumes the 230 kV lines could be
installed anywhere from Lake Sammamish to Lake Washington, plus a portion of Lake
Washington for Option D (Figure 2-1).
A single circuit transmission
line includes three conductors
(wires). A double circuit
includes six conductors (See
Figure 2-2 for a depiction of
typical poles for single and
double circuit transmission
lines).
CHAPTER 2 January 2016 2 -16 PROJECT ALTERNATIVES
PHASE 1 DRAFT EIS
Energize Eastside EIS 140548
Figure 2-1
Alternative 1 Study Area
SOURCE: King County 2015; ESA 2015;
Puget Sound Energy 2015; WA Ecology 2014.
Lake Washington
Lake
Sammamish
Bellevue Sammamish
Issaquah
Renton
Newcastle
RedmondKirkland
Beaux Arts
Medina
Clyde
Hill
Hunts
Point
Yarrow
Point
Mercer
Island
Lakeside
Sammamish
Talbot Hill
Novelty Hill
Lake Tradition
Alternative 1
(waterside)
Alternative 1
(landside)
Existing Substation
Roadway
Water bodies
City Limit
Unincorporated
King County
U:\GIS\GIS\Projects\14xxxx\D140548_EastsidePSETransmisisonCoor\MXD\Alternatives.m xd
0 2
Miles
Note: This map is for reference only. It is not guaranteed that the information is accurate or complete.
Figure 2-2. Typical Pole Dimensions for 230 kV Overhead Transmission Lines
2.3.2.1 Features Common to All Options
2.3.2.1.1 New Transformer
PSE currently owns three properties that
have been designated as possible
locations for future substations in the
central portion of the Eastside. These
substations could potentially serve the
project objectives with a new 230 kV to
115 kV transformer (Figure 2-3).
Potential locations could be adjacent to
the existing Lakeside substation (Figure
2-4), or at one of two possible new
substation sites referred to as
Westminster and Vernell, all within
Bellevue city limits (Figure 2-5). These
sites are near multiple 115 kV lines,
which would allow them the most
efficient location to inject additional
power to the Eastside. The property
Figure 2-3. Transformer
CHAPTER 2 January 2016 2 -18 PROJECT ALTERNATIVES
PHASE 1 DRAFT EIS
adjacent to the existing Lakeside 115 kV
substation presents the most effective
location from a systemwide perspective
because of its immediate proximity to the
existing 115 kV substation and multiple
existing 115 kV lines. Both the
Westminster and Vernell sites would
require the addition of one or more new
115 kV lines.
At any of these sites, development of a
new 230 kV substation yard would be
required. The substation yard would need
to be large enough to accommodate the
new transformer and associated electrical
equipment such as circuit breakers, bus,
and connections to the new transmission lines. The gravel yard would include the necessary
foundations, access ways, stormwater drainage, and security fencing (typically 8-foot-tall
chainlink, but other types of fencing may be used). In order to accommodate a new
transformer and associated equipment, acquisition of property adjacent to the Lakeside
substation site could be required. Both the Westminster and Vernell sites are owned by PSE,
vacant and large enough for a new substation.
Figure 2-4. Lakeside Substation
January 2016 CHAPTER 2 PROJECT ALTERNATIVES 2-19
PHASE 1 DRAFT EIS
Energize Eastside EIS 140548
Figure 2-5
Alternative 1 - New Substation
and 230 kV Transmission Line
SOURCE: King County 2015; ESA 2015; WA Ecology 2014;
Puget Sound Energy 2015.
Lake Washington
Lake
Sammamish
Bellevue Sammamish
Issaquah
Renton
Newcastle
RedmondKirkland
Beaux Arts
Medina
Clyde
Hill
Hunts
Point
Yarrow
Point
Mercer
Island
Vernell Westminster
Lakeside
Sammamish
Talbot Hill
Novelty Hill
Lake Tradition
Proposed Substation
Existing Substation
Proposed 230 kV
Transformers
Options A+C -
Overhead or
Underground 230kV
Transmission Line
Corridor
Option B - Existing
230kV Seattle City
Light Corridor
Option D - Underwater
230kV Transmission
Line Corridor
Roadway
Water bodies
City Limits
Unincorporated King
County
U:\GIS\GIS\Projects\14xxxx\D140548_EastsidePSETransmisisonCoor\MXD\Alternative1_230kV_location.mxd
0 2
Miles
Note: This map is for reference only. It is not guaranteed that the information is accurate or complete.
2.3.2.1.2 Construction
Construction of a new substation would require clearing and grading to prepare the area for
foundations to support the new transformer that converts the bulk power into the distribution
system. The new transformer would also require supporting equipment that would be placed
on a concrete pad in accordance with regulatory requirements and industry standards. The
expansion of the substations would require construction of underground foundations to
support the new transformer.
Construction for transformers would require delivery of the transformers to the site; grading
of the site and creation of a foundation; and placement of the transformer on the foundation.
Construction equipment required would include:
• Specialized oversize trucks and trailers;
• Backhoes or excavators;
• Concrete trucks; and
• Cranes or other specialty equipment to place transformers.
Use of oversize trucks would be restricted to certain hours to avoid or minimize traffic
impacts. Additional information on construction equipment is included in Appendix B.
Construction of transformers would take up to 18 months. The duration of transformer
construction would depend on location. Installation in a new facility with construction of a
new substation yard would require the longest duration. Transformers and transmission lines
could be constructed concurrently. Depending on site access and configuration, construction
activities could require temporary street closures and detours.
Construction would also be required for new 230 kV transmission lines. Construction
activities would vary by option and are described below. Temporary construction easements
may be needed to build any of the options, and PSE would execute an agreement with the
property owner for site access and site restoration during any such use.
2.3.2.2 Option A: New Overhead Transmission Lines
New overhead transmission lines may be located entirely within existing utility easements, or
partially in new locations currently not dedicated to utility operations (such as along
roadways or rail corridors, over or through private or other public property). This option
would include a minimum of 18 miles of new overhead transmission lines (connecting in the
most direct manner using PSE right-of-way from the Lakeside substation to the Talbot Hill
and Sammamish substations). Additional transmission lines could be needed depending on
the substation chosen and other route possibilities.
In the near term, one of the existing 115 kV lines between the Lakeside substation and the
Talbot Hill substation may need to be rebuilt with a 115 kV line that provides a higher
capacity. There would be little difference in conductor type (including size and appearance)
between a high-capacity 115 kV line and a 230 kV line; therefore, the same line could
potentially be used for a future 230 kV line. While there is not an immediate need for a
second 230 kV circuit through the Eastside, there are cost efficiencies with installing a
January 2016 CHAPTER 2 PROJECT ALTERNATIVES 2-21
PHASE 1 DRAFT EIS
second circuit transmission facility in the same corridor as the proposed 230 kV line. PSE
will consider this as part of efforts to identify the least costly infrastructure to serve its
customers.
For overhead lines, an additional wire would be installed on top of the new poles for
lightning protection. Any existing fiber-optic cable would need to be transferred to the new
poles.
2.3.2.2.1 Overhead Transmission Line Locations
Figure 2-5 shows the area where installing a new 230 kV transformer and transmission line
under Alternative 1, Option A would meet PSE’s project objectives. Within this area,
overhead lines could be constructed anywhere. PSE policy is to use its existing easements or
rights-of-way wherever possible, but road and other utility right-of-way corridors (such as
city streets, state and interstate highways, and some sections of the SCL corridor) are also
possible locations. PSE may need to obtain new right-of-way to extend the transmission lines
to a desired substation, or to avoid an area of potential impact elsewhere. Additionally,
relocation of existing distribution or 115 kV lines may be needed in order to accommodate
the new 230 kV line.
Specific pole locations would be determined based on site engineering. Pole locations would
generally be based on tensioning needs for the wire (including where turns are needed along
the route), underground obstacles at pole foundation locations, and allowable structural
heights, all while attempting to use as few poles as possible. Consideration is also made to
avoid placing poles in environmentally critical areas like wetlands and unstable slopes.
2.3.2.2.2 Pole Types and Heights for Overhead Lines
Poles would likely be steel or laminated wood monopoles; however, other designs such as H-
frames using wood or steel poles could be used in some locations. Concrete poles are not
commonly used in this region because they are more expensive than wood or steel. The
diameter of the poles depends on height and would be greatest at the base. Typical in-line
(tangent) poles would be 2 to 4 feet in diameter at the base, while typical corner and
termination poles may need to be 4 to 6 feet in diameter at the base depending on the angle
and the terrain. Termination poles and poles where the transmission line changes direction
need to be larger than tangent poles to handle the asymmetrical weight and tension from the
lines they are holding.
In order to meet National Electric Safety Code (NESC) and FERC/NERC requirements to
prevent contact with the lines, adequate clearances must be maintained between each
conductor, the ground, adjacent buildings, and trees. Pole height therefore would vary
depending on the number of circuits, the arrangement of the circuits on the poles,
topography, and surrounding land cover. Figure 2-2 shows the typical range of pole
dimensions for 230 kV transmission lines. Generally, for a double circuit system, pole
heights would range from 85 to 100 feet. In some configurations that could occur under
Alternative 1, Option A, a double circuit would incorporate an existing 115 kV line with a
new 230 kV line on poles similar to those shown in Figure 2-2. In special cases, such as
crossing a ravine or highway, pole heights could be shorter or taller.
CHAPTER 2 January 2016 2 -22 PROJECT ALTERNATIVES
PHASE 1 DRAFT EIS
2.3.2.2.3 Construction
Under Alternative 1, Option A, new 230 kV transmission lines would be constructed along a
minimum of 18 miles of corridor. Construction could occur within existing transmission or
other utility easements, or in new locations currently not dedicated to transmission such as
areas along road rights-of-way, rail corridors, or over or through private or other public
property.
Clear zones. To ensure safe and reliable operation of overhead or underground transmission
lines, the NESC specifies minimum horizontal and vertical clearance requirements for
overhead lines, where trees and overhanging branches must be removed, and structures are
generally prohibited (the clear zone). Existing 115 kV corridors on the Eastside vary in
width, as do standards for 230 kV corridors. Because of this variability, generic assumptions
were made based on standard practice in the industry (AEPOhio, 2014). These clear zone
requirements typically determine transmission right-of-way (or easement) widths. Specific
easement agreements may require more clearance.
For this Phase 1 Draft EIS, if a range of corridor widths is possible, the impact analysis
assumes the worst case. In practice, PSE may be able to reduce the required clear zone, in
which case impacts would be less than those assumed for this phase of the EIS.
The clear zone for an overhead 230 kV line could be approximately 120 to 150 feet wide.
The transmission line could be located along existing 115 kV easements, which are typically
70 to 100 feet wide. Therefore, this analysis assumes that use of a 115 kV corridor could
require the corridor to be widened by up to 50 feet. Section 2.3.5 summarizes the clear zone
widths and other assumptions used for all alternatives in this EIS.
Coordination with Olympic Pipeline. If located along the existing 115 kV easement,
construction of a 230 kV line has the potential to disrupt the Olympic Pipeline. Extensive
coordination with the Olympic Pipe Line Company would be required during project design
and construction to avoid disruption to the two lines, or to establish relocation procedures.
Pole installation. During construction, existing wooden poles and conductors would be
removed, if present. The methods used to install new steel poles will depend on the type of
pole used and both its physical and functional location. Poles can be directly embedded in the
ground or utilize an anchor bolt cage, which is a drilled pier foundation that involves setting
the anchor bolt cage in a poured column of concrete. Foundations for new 230 kV poles are
typically augered (drilled) 4 to 8 feet in diameter with steel reinforcements that could extend
25 to 50 feet deep depending on the structure type. Steel poles are set and anchored to the
foundations. In some cases, a caisson foundation is used for greater stability. (No foundations
are used for wooden poles.) Approximately 100 pole foundations would need to be installed
with a typical spacing between poles of 1,000 feet to extend the 18-mile distance between the
Sammamish and Talbot Hill substations.
Transmission line installation. Once the pole is set in place, the transmission line (wire)
would be installed (Figures 2-6, 2-7, 2-8, and 2-9). The wire-stringing operation requires
equipment at each end of the section being strung. Wire would be pulled between these
temporary pulling sites through pulleys at each structure. These pulling sites would be set up
January 2016 CHAPTER 2 PROJECT ALTERNATIVES 2-23
PHASE 1 DRAFT EIS
at various intervals along the right-of-way, typically 1 to 3 miles apart. Specific pulling sites
would be determined close to the time the stringing activity takes place. Once the wire is
strung, the stringing blocks (i.e., guide rollers) would be removed and the wire clipped into
its final hardware attachment. Once poles are installed, surfaces around the new poles and in
work areas would be restored.
Figure 2-6. Workers prepare to
energize a transmission line (Gulf
Power, 2015) Figure 2-7. Workers Rebuilding a
Transmission Line (Fischbach, 2014)
Figure 2-8. Installation of
Transmission Line (Transelect, 2015)
Figure 2-9. Workers Rebuilding a
Transmission Line (Fischbach, 2014)
CHAPTER 2 January 20162-24 PROJECT ALTERNATIVES
PHASE 1 DRAFT EIS
Ground disturbance. Disturbance of site soils would be necessary for clearing and grading
to prepare foundation pads as well as potentially a staging area and equipment access
depending on the location of the transmission line. Construction would require temporary
construction access roads. Installation of transmission lines under existing roadways could
require excavation, construction, backfill, and pavement restoration within roadway rights-of-
way.
Equipment. Construction equipment required for overhead transmission lines would include
the following:
•Bulldozers;
•Backhoes;
•Trackhoes;
•Bucket trucks;
•Auxiliary rubber tire vehicles;
•Auger or vacuum trucks;
•Dump trucks;
•Concrete trucks or concrete pump trucks;
•Cranes;
•Line trucks;
•Conductor reel trailer for hauling conductor reels;
•Tensioner for applying tension to conductor coming off reels during pull; and
•Puller for pulling rope/hard line with attached conductor.
Length of Construction Period. Construction of overhead transmission lines would take
approximately 12 to 18 months and could be constructed concurrently with the substation. If
a new corridor were to be developed, the duration would likely be longer due to the need for
more extensive clearing. Construction of a new corridor is also more likely to require
demolition or removal of buildings, which would extend the duration of construction and
could also result in temporary stockpiles of demolition debris.
Typically, the foundation for a steel transmission line pole involves work at a site for 1 to 3
days; setting the pole occurs in a day; and stringing the wires across the pole occurs within a
day. These three stages of work can be separated by up to a month. Therefore, in any given
location, construction activity would take place over 3 to 5 days within a period of up to 2
months. For wood poles, no foundation is set. Typically, the hole is prepared and the pole is
set in a single day, with the wires installed up to a month later.
Other activities. Installation of new overhead transmission lines would require other
construction activities that may include boring holes for geotechnical investigations, or
relocating existing distribution and telecommunications facilities.
January 2016 CHAPTER 2
PROJECT ALTERNATIVES 2-25
PHASE 1 DRAFT EIS
2.3.2.3 Option B: Use Seattle City Light 230 kV Overhead
Transmission Lines
Alternative 1, Option B makes use of an overhead 230 kV transmission line belonging to
SCL (see Figure 2-5). PSE has explored the idea of using the SCL line as an option; however,
the SCL facility is not under PSE ownership, and SCL stated that it needs this line to serve its
customers (Gentile et al., 2014). This option is included in this Phase 1 Draft EIS so that, if
conditions change, this option will remain open.
System operational studies by PSE have shown that Option B would require significant
modifications of the SCL line, including replacing most of the existing structures and all
conductors, to provide the necessary capacity to meet PSE’s identified need for the Energize
Eastside Project. The present emergency ratings of the SCL lines are 426 megavolt amperes
(MVA) in the summer and 526 MVA in the winter. In order for PSE to utilize these lines as
the source for an additional 230 kV transformer on the Eastside, the present ratings are
insufficient. If lines were upgraded by replacing only the conductor, then the assumed ratings
for the reconductored lines are 692 MVA in the summer and 771 MVA in the winter. This
would not be adequate to meet both SCL’s needs and PSE’s project objectives (Strauch,
personal communication, 2015c). Therefore, if SCL were to grant use of this line, PSE would
need to both tie into it and upgrade it. The next incremental increase in capacity would be to
rebuild the SCL lines (replace structures and conductors), which could provide a line capacity
of approximately 1,139 MVA in the summer and 1,366 MVA in the winter.
Option B would involve both of the SCL SnoKing-Maple Valley 230 kV transmission lines.
It would also require connecting one double circuit 230 kV line to the Lakeside substation
and connecting another double circuit 230 kV line to the Sammamish substation. The exact
length of that alignment is not known, but the proximity of the Lakeside and Sammamish
substations to the line suggests that each connection would be approximately 1 mile or less
(Figure 2-5). This option would also require modifications to and expansion of several
substations.
The rebuild of the SCL line was estimated by PSE to provide sufficient capacity for a period
of less than 10 years, failing to meet electrical criteria #2 and #15 (Section 2.2.1), but it could
otherwise attain or approximate PSE’s objectives (Strauch, personal communication, 2015c).
2.3.2.3.1 Construction
Alternative 1, Option B would require replacing most of the existing structures of the SCL
230 kV lines. The SCL lines may need to remain in service; therefore, the replacement line
may need to be constructed adjacent to the existing line and placed into service prior to
removing the existing structures and conductor.
Construction activities needed would be similar to Alternative 1, Option A, except that it is
assumed that the only new corridor needed would be the connection to the Lakeside
substation. It is assumed that no additional clear zone would be required for the existing SCL
230 KV corridor. Activities would be concentrated along an approximately 15-mile-long
corridor.
CHAPTER 2 January 2016 2 -26 PROJECT ALTERNATIVES
PHASE 1 DRAFT EIS
Due to the added complexity of rebuilding the SCL system while in operation, construction
of transmission lines would last up to 24 months (Strauch, personal communication, 2015c).
Construction equipment required for Option B would be the same as described for Option A.
2.3.2.4 Option C: Underground Transmission Lines
Under Alternative 1, Option C, any portion of the alignments of new transmission lines
considered for Option A could be placed underground.
The route alignment for new 230 kV underground transmission lines under Option C requires
additional study because construction and operation of underground lines has different
considerations than aboveground lines. It is possible that underground lines could be placed
within PSE’s existing 115 kV overhead line rights-of-way, public road right-of-way, or other
right-of-way that PSE owns, purchases, or obtains rights to, when topography and operational
considerations would allow it. PSE would maintain permanent access to the underground
lines in order to make necessary inspections and repairs.
An underground transmission line would likely be a cross-linked polyethylene cable system
consisting of stranded copper or aluminum conductor surrounded by insulation and a series
of protective barriers. The outermost barriers are typically concrete or steel. Access vaults are
needed periodically along an underground route to facilitate cable installation, maintenance,
and repairs. Underground, reinforced concrete vaults (typically approximately 8 feet wide by
26 feet long) are usually spaced approximately every 1,500 to 2,500 feet along the route.
2.3.2.4.1 Construction
Underground transmission lines could be constructed through existing PSE 115 kV overhead
transmission line rights-of-way, other utility rights-of-way (such as roadway or rail
corridors), or new rights-of-way.
Installation techniques. Most underground installations are open-cut trench construction.
The trench width for trench excavation would vary from 2 to 6 feet, plus temporary clearing
for access roads and staging. The total work area would be approximately 30 feet wide.
Trench depth is determined by future use of the area, location of other utilities, obstructions,
and other factors. Additional excavation is done to construct access and splice vaults.
Installation techniques for open-cut placement of transmission lines would likely include
clearing and grading, excavation, and operation of large equipment. Trenchless methods
could also be used.
Construction techniques for underground transmission lines largely depend upon the type of
terrain and surface conditions:
• Flat terrain – Typically a temporary road is constructed along the full length of the
trenching operation to provide the necessary construction access.
• Rolling hills – Where slopes are less than 10 percent, open trench construction is
typically used. Slopes greater than 10 percent can limit access for construction
equipment. In some cases access roads are cut into the hill or switchbacks are used to
January 2016 CHAPTER 2 PROJECT ALTERNATIVES 2-27
PHASE 1 DRAFT EIS
climb steeper slopes. Horizontal directional drilling (HDD) or trenchless construction
can sometimes be utilized to cross a series of hills.
• Rock - If bedrock is encountered, only trenchless methods such as directional boring
would be used. PSE has indicated that explosives would not be used in urban areas or
adjacent to the Olympic Pipeline. Because the project area is all considered urban, no
blasting would occur.
• Wetlands – Open cutting can sometimes be used to cross wetlands; however,
significant environmental controls are applied. In some cases, HDD can be used to
span a wetland area.
• Other obstructions – There are other situations where open trenching is not
practical. This includes crossing of streams, rivers, waterways, highways, railroad
tracks, and other situations where open cutting is not allowed or practical. Various
trenchless techniques or routing changes may be needed in these cases.
Equipment. Construction equipment required for excavation of trenches and cable pulling
for underground transmission lines would include the following:
• Excavators or backhoes;
• Dump trucks;
• Bulldozers;
• Concrete mixers;
• Cranes;
• Conductor reel trailer for hauling conductor reels;
• Tensioner for applying tension to conductor coming off reels during pull; and
• Puller for pulling rope/hard line with attached conductor.
Construction of underground transmission lines would last 28 to 36 months. Construction of
underground transmission lines would move in a linear fashion so that, in any given location,
the duration of construction would be approximately 2 months.
2.3.2.5 Option D: Underwater Transmission Lines
Alternative 1, Option D involves constructing an underwater transmission line in Lake
Washington. For the Phase 1 Draft EIS, a study area was selected that assumes cables could
be installed within 1,000 feet of the eastern shoreline of Lake Washington from Kirkland to
Renton, including the entire channel along Mercer Island (Figure 2-5). Underwater cable
could be installed in Lake Washington provided that the appropriate equipment and materials
could be transported to the lake.
Overland connections would be required to connect a submerged line to the Sammamish and
Talbot Hill substations, and to a new transformer near the center of the Eastside. The
underwater line would need to cross existing submarine cables in Lake Washington,
CHAPTER 2 January 2016 2 -28 PROJECT ALTERNATIVES
PHASE 1 DRAFT EIS
requiring adequate spacing. Appropriate design steps would need to be taken to protect both
existing and new cable systems.
2.3.2.5.1 Construction
Alternative 1, Option D would include installation of underwater transmission lines and
overhead or underground transmission lines on land that would connect to the underwater
portion of the line. In the south end of the underwater line, an overland connection could be
accomplished in an existing transmission corridor. However, connecting the underwater line
to the Sammamish substation or a new substation in the middle of the Eastside would require
new corridors. For construction of overhead lines, refer to Option A, and for underground
lines refer to Option C.
Underwater cables. PSE commissioned Power Engineers to prepare a report on an
underwater option in one segment of Lake Washington. The report provides details and
recommendations about what this option would entail (Power Engineers, 2015). The
underwater cable system would likely be composed of three to six conductors spaced at least
16.5 feet apart from one another. Because of system demands, it was assumed that six cables
would be needed. These cables could be buried 3 to 5 feet below the lake bottom, although in
some areas that are deep enough to avoid potential conflicts with deep-draft vessels, cables
may be laid directly on the lake bottom. Depending on the underlying conditions present, the
installation of underwater transmission lines could be completed using trenchless methods
such as horizontal directional drilling or trenching methods using special vessels to dredge
the trenches.
In order to avoid potential impacts to the lake from inadvertent leaks, the cable would not be
of the type that uses high pressure fluid-filled pipe. Additional information about laying
submarine cable in Lake Washington can be found in the Eastside 230 kV Project Lake
Washington Submarine Cable Alternative Feasibility Report prepared for PSE (Power
Engineers, 2015).
Overland lines. For Alternative 1, Option D, east-west overland transmission lines would be
required at up to three locations:
• At the south end, extending from Talbot Hill to Lake Washington;
• From Lake Washington to a substation near the center of the Eastside; and
• At the north end, from the Sammamish substation to Lake Washington.
Overland connections could be via overhead lines as described for Alternative 1, Option A or
underground as described for Option C.
Transition between underwater and overland lines. Shore landings where the underwater
cables transition onto land would be constructed using open-cut trenching, sheet piling, and
dredging. (Trenchless installation is possible but requires larger cable sizes and higher costs.)
On the shoreline, splicing vaults are needed to connect the submerged cable to the overland
portion of the transmission system. Figure 2-10 shows how a submarine cable would
typically be attached to a land-based transmission line in a splicing vault.
January 2016 CHAPTER 2 PROJECT ALTERNATIVES 2-29
PHASE 1 DRAFT EIS
Figure 2-10. Submarine Cable Landing via Open Trench (Power Engineers, 2015)
The number of splicing vaults is dependent on the design and the maximum length of cable
that can be transported to and installed in Lake Washington. For a submerged transmission
line that runs from Renton to Redmond, a minimum of three landing points for vaults would
be needed, and it could be necessary to have one or more additional splice points on land,
each of which would be similar in size to those described for underground cable in
Alternative 1, Option C. At each landing point, up to six vaults would be needed to connect
the underwater cables to the land cables (Power Engineers, 2015). Each of the cable runs
would be physically separated with individual vaults and termination structures so that any
two cables in a circuit could continue to operate if the third were taken down (de-energized)
for maintenance activities. PSE would have to acquire property, remove vegetation and
structures, install the vaults, and maintain access to the vault via a road that could
accommodate commercial trucks. Since it is unknown exactly where or how submarine
cables would be installed, worst-case assumptions have been used for installing the cables
and shore landings.
Installation of upland cable transition points could require sheet or soldier pile driving and
cofferdams in shoreline or nearshore areas, if trenchless techniques are not feasible or
practicable to accomplish the offshore-to-upland transitions. It is expected that vibratory pile
driving techniques would be adequate to install piles, which would substantially reduce the
potential effects compared to impact pile driving methods.
Equipment. Construction equipment required for installation of underwater cables would
include the following:
•Excavator or backhoe for open-cut and vault area trenching and loading dump truck;
•Dump truck for hauling spoils;
CHAPTER 2 January 20162-30 PROJECT ALTERNATIVES
PHASE 1 DRAFT EIS
•Pile driver for sheet piles;
•Dredge for in-water conduit near shoreline;
•Concrete truck for poured-in-place vaults;
•Crane for lifting miscellaneous materials;
•Mixer truck and compaction grout pump to inject thermal backfill;
•Vacuum truck for site and street cleanup;
•Heavy-duty trucks for site deliveries of equipment and materials;
•Conductor reel trailer for hauling conductor reels;
•Tensioner for applying tension to conductor coming off reels during pull;
•Puller for pulling rope/hard line with attached conductor;
•Submarine cable laying barge designed to lay the cable in one continuous piece.
Additional information on construction equipment is included in Appendix B.
Installation of underwater transmission lines would require special vessels to dredge trenches
in the lake bottom and lay cable (Figure 2-11) (Power Engineers, 2015). Because of the
limitations on the size of vessels capable of passing under the I-90 floating bridge, multiple
passes with a smaller vessel may be required for the complete installation of the cable
system. Use of special vessels to dredge trenches in the lake bottom and lay cables in the
trenches could restrict boat access in the work areas.
Materials would likely be transported via ship or barge from marine waters (via the Hiram M.
Chittenden Locks) due to the size of transmission cables that would be needed. Truck
delivery is considered infeasible because the longest cable segment that could be transported
by truck is approximately 1,100 feet, due to highway weight limits.
Length of Construction Period. Construction of underwater transmission lines would take
approximately 8 months. Additional time would be required to construct overhead or
underground lines to connect to substations.
Figure 2-11. Typical Barge for 230 kV Cable Installation (Power Engineers, 2015)
January 2016 CHAPTER 2
PROJECT ALTERNATIVES 2-31
PHASE 1 DRAFT EIS
2.3.2.6 Conservation
Under Alternative 1, PSE would continue the conservation efforts called out in its 2013
Integrated Resource Plan (PSE, 2013), as described in the No Action Alternative. Alternative
1 is expected to result in the same levels of conservation as the No Action Alternative.
2.3.3 Alternative 2: Integrated Resource Approach
The focus of Alternative 2 is on energy conservation and use of technologies other than
transmission lines to address the project objectives. Alternative 2 would address the projected
deficiency in transmission capacity on the Eastside by reducing the growth in peak period
demand through energy efficiency, storing and releasing energy when needed to address peak
demand, and providing reliable additional peak period energy sources in the area where the
transmission capacity is deficient.
The study area for Alternative 2 is shown on Figure 2-12. The Alternative 2 study area
excludes in-water work, but includes potential project activity anywhere from the east side of
Lake Washington to west side of Lake Sammamish. As described below, some components
would need to be close to the center of this area to be effective.
CHAPTER 2 January 2016 2 -32 PROJECT ALTERNATIVES
PHASE 1 DRAFT EIS
Energize Eastside EIS 140548
Figure 2-
Alternative 2 Study Area
SOURCE: King County 2015; ESA 2015;
Puget Sound Energy 2015; WA Ecology 2014.
Lake Washington
Lake
Sammamish
Bellevue Sammamish
Issaquah
Renton
Newcastle
RedmondKirkland
Beaux Arts
Medina
Clyde
Hill
Hunts
Point
Yarrow
Point
Mercer
Island
Lakeside
Sammamish
Talbot Hill
Novelty Hill
Lake Tradition
Alternative 2
Existing Substation
Roadway
Water bodies
City Limit
Unincorporated
King County
U:\GIS\GIS\Projects\14xxxx\D140548_EastsidePSETransmisisonCoor\MXD\Alternatives.mxd
0 2
Miles
Note: This map is for reference only. It is not guaranteed that the information is accurate or complete.
Determining the amount of non-
transmission resources that would be
needed to address the capacity
deficiency that PSE has identified is
complex because every solution has a
different degree of effectiveness and
reliability. For these reasons, it is not
sufficient to look at the transmission
capacity deficiency and replace that with
an equal amount of non-transmission
resources, such as energy efficiency or
new generation. According to PSE
projections, it would take 74 MW of
additional transmission capacity to
marginally meet the demand through
2018 (Gentile et al., 2015). However, to
address the capacity deficiency in 2018
with non-transmission resources would
take approximately 163 MW of
additional conservation, storage, and
new generation within the Eastside
beyond the 50 MW of conservation
planned in 2013 Integrated Resource
Plan (Nedrud, personal communication, 2015; PSE, 2013) (Figure 2-13). To address the
capacity deficiency in winter 2024 with non-transmission resources would take
approximately 205 MW of additional conservation, storage, and new generation within the
Eastside beyond the currently planned 119 MW of conservation (Figure 2-13). If growth
continues as predicted, additional conservation or a system upgrade would be necessary to
reliably serve the area beyond 2024.
For comparison, PSE’s current plan for the entire PSE service area (Figure 1-3) is to
implement 852 MW of conservation by 2024. The Eastside represents approximately 14
percent of the total load for the PSE system, and therefore 14 percent of the total projected
conservation (119 MW of conservation).
Alternative 2 would require close monitoring and management because it is based on the
assumption that just enough conservation and new energy supply would be accomplished
within the Eastside each year throughout the study period (2015 - 2024; electrical criterion
#2) to avoid needing additional transmission capacity. This alternative could address the
project need but results in uncertainty about how much infrastructure would be installed and
how much additional supply would be needed each year. This alternative assumes that at the
end of the 10-year study period, additional measures or facilities would be required to
address future growth. The approach could be continued conservation efforts, but because of
strict building codes already in place and the acceleration of retrofitting assumed under this
alternative, the availability of additional capacity for conservation is uncertain. If
conservation cannot address identified capacity needs, additional transmission or generation
infrastructure could be required.
Figure 2-13. Additional Non-Transmission
Resources Needed to Meet Project
Objectives in 2018 and 2024
CHAPTER 2 January 2016 2 -34 PROJECT ALTERNATIVES
PHASE 1 DRAFT EIS
Alternative 2 assumes a mix of measures to accomplish conservation savings. In order to
fully address the identified capacity need, Alternative 2 would include a combination of
energy storage units, demand response devices, distributed generation, peak generation
production, and energy efficiency improvements. These measures are described below.
Figure 2-14 summarizes a theoretical mix of measures and anticipated energy conservation
for each component. This figure is provided to illustrate the approximate magnitude of the
effort required to meet the project need. The actual mix would depend on the success of each
component adopted. Some, like energy storage, could be built by PSE, while others require
voluntary participation by customers. The technical feasibility of each option within this
approach would require further study to determine how much of each component is feasible,
economical, and sufficiently reliable. For example, it could be more economical for PSE to
install more peak generator plants than to incentivize customers to install as much distributed
generation as is shown.
Figure 2-14. Example Mix of Energy Conservation, Storage, and Generation for
Components of Alternative 2
2.3.3.1 Energy Efficiency Component
The energy efficiency measures under Alternative 2 would be the same as those described for
the No Action Alternative, such as replacing older, inefficient appliances and lighting, and
adding insulation and weatherproofing. Energy efficiency would reduce the total demand,
thus lowering the peak load requirements. However, to meet the project objectives for
Energize Eastside, these efforts would need to be substantially accelerated and expanded on
the Eastside. The potential for additional energy efficiency on the Eastside is not currently
known and would require additional evaluation. Stricter building energy code standards could
accomplish part of the project objective but are not within the control of PSE. Therefore,
building codes are not part of this alternative, but they could be considered by study area
communities as a means to help ensure the success of this alternative.
January 2016 CHAPTER 2
PROJECT ALTERNATIVES 2-35
PHASE 1 DRAFT EIS
Additional promotion and incentives would be
necessary to encourage this higher level of
conservation. For the Phase 1 Draft EIS
analysis, it was assumed that the current energy
efficiency incentive program could be
accelerated and expanded for the Eastside
(Figure 2-15). This analysis assumes PSE would
need to accomplish approximately 42 MW of
additional energy efficiency within the Eastside
by 2024, over and above the approximately 45
MW of energy efficiency gains in the Eastside
that PSE expects for that time period. It is
recognized that this is an aggressive goal. PSE’s
Integrated Resource Plan (2013a) estimated PSE could achieve approximately 100 MW of
additional energy efficiency during the period from 2024 to 2033 systemwide, which would
equate to approximately 14 MW of energy efficiency gains on the Eastside during that time
period. The additional energy efficiency assumed for Alternative 2 would be triple the
amount that PSE estimated is achievable after 2024, and that additional energy efficiency
would have to be accomplished before 2024.
2.3.3.2 Demand Response Component
Demand response involves end-use electric
customers reducing their electricity usage
typically during peak load times, and
sometimes involves shifting that usage to
another time period. Typically this is done in
response to a price consideration, a financial
incentive, an environmental condition, or a
reliability issue. Demand response requires
special meters and control equipment that
can be used to adjust electricity usage,
usually adjusting automatically according to
pre-agreed parameters (Figure 2-16). Some
of the features of a demand response system
could include the following:
• Meters that provide customers and PSE information about when and how much
energy each customer is using, including on-line real-time information;
• Installation of in-home monitoring and control equipment that would allow PSE to
control heating and cooling systems;
• Programmatic options to reduce peak demand during system emergencies, improve
system reliability, and balance variable-load resources;
• Incentives for customers to curtail loads during specified events or pricing structures
to induce customers to shift load away from peak periods; and
• Capability of sending a continuous wireless signal to the utility.
Figure 2-15. Adding Insulation in an
Existing Home (U.S. DOE, 2015a)
Figure 2-16. Example Energy Monitoring
System (Clauser, 2016)
CHAPTER 2 January 2016 2 -36 PROJECT ALTERNATIVES
PHASE 1 DRAFT EIS
The Integrated Resource Plan (PSE, 2013) estimated that demand response systems would
result in 116 MW systemwide reduction in capacity needed by 2024. Because the Eastside
represents approximately 14 percent of the systemwide load, and assuming that adoption of
demand response would be proportional on the Eastside to the rest of PSE service areas, it is
assumed that approximately 14 percent of the systemwide reduction (16 MW of conservation
by 2024) would occur on the Eastside under the No Action Alternative. In order to address
the capacity deficiency projected for the Eastside, the program would need to be substantially
accelerated and expanded within the Eastside in the next 10 years, at a rate that exceeds the
rest of the system. For the Phase 1 Draft EIS, it is assumed that an additional 32 MW of
demand reduction would need to be accomplished in the Eastside by 2024 (Figure 2-14). This
would triple the expected rate of adoption of demand response in PSE’s Integrated Resource
Plan (2013a) to a total of 48 MW.
2.3.3.3 Distributed Generation Component
Distributed generation involves generating power on a customer’s site. By producing power
within the Eastside, distributed generation reduces the need for transmission of power
through substations serving the Eastside. Distributed generation reduces costs and
interdependencies associated with transmission and distribution and can shift control to the
consumer.
2.3.3.3.1 Types of Facilities Included in EIS Analysis
In order to address the Eastside transmission deficiency with distributed generation alone,
approximately 300 to 400 MW of capacity would be needed by 2024 depending on the
geographic location of the generation (PSE, 2013; Strauch, personal communication, 2015a).
While all distributed sources reduce the total amount of electricity that needs to be supplied
through the transmission system, only a limited set of these resources, those that can be relied
upon to produce power during periods of peak demand, would help to address the Eastside
transmission capacity deficiency. For this analysis, distributed generation facilities were
assumed to consist primarily of gas turbines, anaerobic digesters, reciprocating engines,
microturbines, and fuel cells, with each system generating less than 10 MW. These types of
facilities are discussed below, and are shown in Figures 2-17, 2-18, 2-19, 2-20, and 2-21).
New distributed generation resources would need to be capable of producing power when
needed at peak times, such as during a winter cold snap or a summer warm spell, or they
would need to be associated with an energy storage system that would allow use of the
energy during peak periods. For an energy generating resource to be effective, it also has to
be reliable, which means it must be well maintained and capable of producing a specified
amount of energy when needed. To ensure adequate capacity even when some equipment is
not working, a substantial degree of redundancy is needed in distributed generation resources.
In addition, the distributed generation needs to be located at or near the load in order to be
effective. This also contributes to the need for an overall higher capacity requirement. As
with energy code requirements, cities could require these types of installations, but PSE must
rely on voluntary installation.
Although these conditions suggest there could be difficulty implementing a robust distributed
generation system sufficient to meet a substantial portion of the need, it is included in the
Phase 1 Draft EIS because it is technically feasible and could address a portion of the need.
January 2016 CHAPTER 2 PROJECT ALTERNATIVES 2-37
PHASE 1 DRAFT EIS
Figure 2-19. Reciprocating Engine
(Madison Gas and Electric, 2015)
Figure 2-17. Gas Turbine
(Simens, 2015)
Figure 2-18. Anaerobic Digester
(Biomass Energy Centre, 2015)
Figure 2-20. Microturbine (Capstone
Turbine Corporation, 2015)
Figure 2-21. Fuel Cell (Soutter, 2012)
CHAPTER 2 January 2016 2 -38 PROJECT ALTERNATIVES
PHASE 1 DRAFT EIS
Gas Turbines. Gas turbines are machines that use hot gas to generate rotary mechanical
power. They include a compressor, a combustion system, and a turbine. The compressor pulls
air into the engine, pressurizes it, and moves it through to the combustion system. The
combustion system injects fuel into the air to produce a hot, high-pressure gas. The high-
pressure gas expands, moving through the turbine and causing the blades of the turbine to
spin. This spinning action causes the connected generator to produce energy (Department of
Energy, 2015).
Anaerobic Digesters. Anaerobic digesters use a collection of processes by which
microorganisms break down biodegradable material (such as sewage, animal manure, and
food waste) in the absence of oxygen, resulting in the production of biogas and digestate fuel.
Biogas is a mixture of approximately 60 percent methane and 40 percent carbon dioxide that
can be burned in a CHP unit to produce heat and electricity (Department for Environment,
Food & Rural Affairs and Department of Energy & Climate Change, 2015).
Reciprocating Engines. Reciprocating engines are composed of an internal combustion
engine and an electrical generator. The internal combustion engine burns fuel (diesel,
propane, natural gas, or gasoline) to power the generator, which converts the power of the
engine into electricity (Madison Gas and Electric, 2015).
Microturbines. Microturbines are small combustion turbines approximately the size of a
refrigerator, with outputs of 25 kW to 500 kW. They are often composed of a compressor,
combustor, turbine, alternator, recuperator (a device that captures waste heat to improve the
efficiency of the compressor stage), and generator. They work much like a gas turbine, only
on a smaller scale (Capehart, 2014).
Fuel Cells. Fuel cells are electrochemical devices that combine hydrogen and oxygen to
produce electricity.
2.3.3.3.2 Generation Facilities Not Included in EIS Analysis
On-site energy generation can also include solar photovoltaic systems, wind turbines, and
small hydroelectric facilities. These technologies were not included in Alternative 2 because
they would contribute minimally to addressing the identified capacity deficiency.
Solar and wind power are typically less effective at addressing peak power needs because
wind and sun may not be at their full potential during periods of peak demand.
A typical 6 kW rooftop solar photovoltaic system installed on a single-family residence
generates 6,000 kWh per year. Currently, wind turbines on the Eastside are limited to two
small-scale (approximately 1 MW) turbines, due to a lack of consistent wind.
Typically, winter peak system loading occurs in the morning and evening, when solar is less
effective because of shorter daylight hours. Solar could help reduce summer peak loads but
because additional capacity would continue to be needed for winter, the use of solar
generation to address the transmission capacity deficiency would need to be matched by
winter generation capacity and therefore would be redundant.
January 2016 CHAPTER 2 PROJECT ALTERNATIVES 2-39
PHASE 1 DRAFT EIS
Because there are no identified locations on the Eastside where small hydroelectric facilities
would be feasible, it was assumed that small-scale hydroelectric would not contribute to
addressing capacity.
2.3.3.4 Energy Storage Component
The energy storage component considers the
use of batteries installed within the Eastside
that would charge during off-peak periods and
discharge to the power supply system during
peak demand times (Figure 2-22). Like
distributed generation, energy storage would
reduce the amount of electricity that must be
delivered to the Eastside through the
transmission system. While it is possible that
home battery storage could occur in homes
using technology that is currently being
developed, this analysis considers a PSE-
controlled facility capable of storing 121 MW,
which would be adequate to eliminate
emergency overloads (Strategen, 2015). This
would require a site of approximately 6 acres and would need to be close to the center of the
Eastside, ideally adjacent to an existing substation. Battery storage could be developed at one
or more substations, but for this analysis, a total of 6 acres is assumed.
The feasibility of using energy storage combined with other previously identified alternatives
was studied in March 2015 by Strategen Consulting, LLC. Results of this study can be found
in the Eastside System Energy Storage Alternatives Screening Study (Strategen, 2015).
Conclusions from that study stated the following:
• An energy storage system with power and energy storage ratings large enough to
reduce normal overloads has not yet been installed anywhere in the world. For
comparison, the largest operational transmission scale battery facility in the U.S. can
provide 32 MW of power for about 40 minutes (Strategen, 2015). However, larger
facilities are being developed in California and elsewhere.
• The Eastside system has significant constraints during off-peak periods that could
prevent an energy storage system from maintaining sufficient charge to eliminate or
sufficiently reduce normal overloads over multiple days.
• A system large enough to address the entire transmission capacity deficiency would
need to deliver approximately 328 MW of electricity and store 2,338 (MWh) of
power. A storage system of this size is not technically feasible because the existing
Eastside transmission system does not have sufficient capacity to fully charge the
system.
• Summer requirements were not evaluated because the limitations identified during
the winter study indicated that energy storage would not be a feasible stand-alone
alternative.
Figure 2-22. Battery Storage (Wood,
2014)
CHAPTER 2 January 2016 2 -40 PROJECT ALTERNATIVES
PHASE 1 DRAFT EIS
For these reasons, energy storage was considered a partial solution that would be
implemented together with other demand-side reduction strategies.
2.3.3.1 Peak Generation Plant Component
Peak generation located within the Eastside
would provide a source of electricity
controlled by PSE that could be used to
provide power at peak demand times to
reduce the demands on the transmission
system. This component would involve
installing three 20 MW generators at existing
substations within the Eastside. These could
be any type of generator but the most likely
type would be a simple-cycle gas-fired
generator (Figure 2-23). These systems
typically burn natural gas to turn a turbine
that powers a generator, and are sometimes
designed to also work with an alternate fuel
that can be stored on-site. They can also be
combined with heat recovery units to improve
overall efficiency. These generators are
referred to as peak generation plants.
PSE evaluated using these types of generators alone to meet the project objective. PSE
determined that 20 such generators (totaling 400 MW) would be needed because the farther
the generator is located from the center of the Eastside, the less effective it becomes at
addressing the identified capacity deficiency. Most of the substations on the Eastside are in
residential areas, and these types of generators produce a high noise level that would be
incompatible with those surroundings. For this reason PSE had eliminated this option from
consideration. However, these are proven technologies that could possibly be sited in some
locations and be compatible with adjacent uses, addressing a portion of the identified need.
Therefore, Alternative 2 includes three 20 MW generators to be implemented in combination
with the other components described for Alternative 2.
2.3.3.2 Construction
Construction of energy efficiency measures (such as weatherization and efficient lighting)
would be limited and primarily focused on existing building upgrades.
Demand response is an end-user strategy that pertains more to customer usage patterns and
requires little construction of new infrastructure. Construction would be limited to installation
of meters and in-home monitoring systems and control equipment.
Distributed generation facilities (gas turbines, anaerobic digesters, reciprocating engines,
microturbines, and fuel cells) would require minor construction activities primarily on
residential and commercial sites. Some would be constructed at the same time as new
buildings are being built, while others would be constructed independently. Facilities would
Figure 2-23. Simple-Cycle Peak
Generation Plant with 3 Gas-Fired
Generators (Energy Capital Partners,
2015)
January 2016 CHAPTER 2 PROJECT ALTERNATIVES 2-41
PHASE 1 DRAFT EIS
range in size from small rooftop installations to larger facilities requiring up to 1 acre of
space. Construction activities for larger facilities could require clearing and grading.
Construction duration would vary depending on scale and technology.
The component of Alternative 2 that would require the most construction activity would be
the energy storage component. Construction of battery storage facilities would last
approximately 6 months and would require standard construction equipment similar to what
is required for construction of a substation under Alternative 1. Construction for a battery
storage facility would require clearing and grading adjacent to one or more existing
substations. The battery storage facility or facilities would occupy approximately 6 acres in
total.
Construction of three gas-fired simple-cycle generators for the peak generation plant
component would require construction similar to a substation, including trenching to access
upgraded natural gas, water, and wastewater utility lines. Construction would occur within or
adjacent to existing PSE substations. The construction duration would be approximately 12
months.
2.3.4 Alternative 3: New 115 kV Lines and Transformers
Under Alternative 3, new 115 kV transmission lines would be constructed in existing or new
rights-of-way around a broad portion of the Eastside. Figure 2-24 shows the study area for
Alternative 3. The Alternative 3 study area includes the same western boundary as
Alternative 2 but extends eastward beyond Lake Sammamish and into the foothills of the
Cascade Mountains. Portions of the cities of Sammamish and Issaquah are within the
Alternative 3 study area.
The transmission lines would be similar to those described for Alternative 1, Option A,
except that Alternative 3 would involve shorter poles, smaller foundations, and narrower
rights-of-way. The corridor for the 115 kV transmission lines would be in existing corridors
such as along roadways, requiring a clear zone 30 to 40 feet wide (refer to Table 2-3, in
Section 2.3.5). Alternative 3 would involve construction of approximately 60 miles of new
transmission line. Most of the corridor for Alternative 3 would be co-located or constructed
adjacent to existing PSE transmission lines or other utility rights-of-way (roadways, rail
corridors). New 115 kV transmission lines could be built along existing road rights-of-way
that currently do not have overhead transmission lines. Figure 2-25 shows a conceptual
routing of lines that PSE developed to estimate the extent of additional 115 kV transmission
lines that would be need to meet the project objectives. In instances where there is not an
adequate existing transmission corridor, construction would include vegetation clearing to
ensure adequate clearance for the new overhead lines.
Operation of Alternative 3 would be similar to Alternative 1 and would involve limited but
regular maintenance along the transmission lines. Substation operation would involve regular
site inspection and maintenance. All proposed equipment is subject to wearing out and would
need to be replaced when this occurs, typically after several years of use. Replacement of
conductors would be similar to the final steps of installation. Replacement of substation
equipment would be similar to the final stages of construction, involving heavy trucks
delivering equipment and cranes to remove and replace equipment.
CHAPTER 2 January 2016 2 -42 PROJECT ALTERNATIVES
PHASE 1 DRAFT EIS
Energize Eastside EIS 140548
Figure 2-24
Alternative 3 Study Area
SOURCE: King County 2015; ESA 2015;
Puget Sound Energy 2015; WA Ecology 2014.
Lake Washington
Lake
Sammamish
Bellevue Sammamish
Issaquah
Renton
Newcastle
RedmondKirkland
Beaux Arts
Medina
Clyde
Hill
Hunts
Point
Yarrow
Point
Mercer
Island
Kent
Maple
ValleyCovington
Tukwila
SeaTac
Seattle
Ardmore
Berrydale
Hazelwood
Pickering
Clyde Hill
Lakeside
Sammamish
Talbot Hill
Novelty Hill
Lake Tradition
Existing Substation
Roadway
Unincorporated
King County
Alternative 3
Water bodies
City Limit
U:\GIS\GIS\Projects\14xxxx\D140548_EastsidePSETransmisisonCoor\MXD\Alternative3.mxd
0 2.5
Miles
Note: This map is for reference only. It is not guaranteed that the information is accurate or complete.
Energize Eastside EIS 140548
Figure 2-25
Alternative 3 - New 115 kV
Lines and Transformers
SOURCE: King County 2015; ESA 2015; WA Ecology 2014;
Puget Sound Energy 2015.
Lake Washington Lake
Sammamish
Bellevue Sammamish
Issaquah
Renton
Newcastle
RedmondKirkland
Beaux Arts
Medina
Clyde
Hill
Hunts
Point
Yarrow
Point
Mercer
Island
Kent
Maple
ValleyCovington
Tukwila
SeaTac
Seattle
New 115kV line to Berrydale
su bstation in cludes a 120ft
wide stud y area corridor
Ardmore
Berrydale
Hazelwood
Pickering
Clyde Hill
Lakeside
Sammamish
Talbot Hill
Novelty Hill
Lake Tradition
Existing Substation
New 230 kV/115
kV Transformers
New 115 kV
Transmission Lines
Roadway
Unincorporated
King County
Alternative 3
Water bodies
City Limit
U:\GIS\GIS\Projects\14xxxx\D140548_EastsidePSETransmisisonCoor\MXD\Alt3Substation_New115kV_location.m xd
0 2.5
Miles
Note: This map is for reference only. It is not guaranteed that the information is accurate or complete.
Under Alternative 3, three new 230 kV to 115 kV transformers would be installed, one at
each of the existing Lake Tradition, Talbot Hill, and Sammamish substations. In order to
accommodate the additional transformers it is assumed, at a minimum, that the Talbot Hill
substation would need to be expanded, and that additional security measures would be
required at all three substations. At Sammamish and Talbot Hill, this would result in three
230 kV to 115 kV transformers being located in the same substation. PSE considers more
than two transformers at a substation to be a high risk because damage to one substation with
more than two transformers could take out a substantial portion of the capacity, so this
alternative would not strictly meet PSE’s current standards for substation design (electrical
criterion #1). However, other utilities have developed and safely operated substations with
three transformers, so this alternative has been included for the Phase 1 Draft EIS.
2.3.4.1 Construction
Substation. The construction methods for substation expansions and improvements would be
the same as described in Alternative 1 (Section 2.3.2). Delivery of equipment would require
special trucks and space for special equipment such as a crane. Table 2-2 provides a summary
of the substation modifications that would be required to accommodate the new 115 kV lines.
Some substations could accommodate the new lines, while five substations would require
complete rebuilds and expansion for this alternative.
Table 2-2. Substation Modifications Required for Alternative 3
Substation
New
230/115 kV
Transformer
Required
New
115 kV Line
Connections
Required to:
Fits in
Existing
Substation
Footprint
Notes
Sammamish Install 3rd
230/115kV
Transformer
Ardmore and
Clyde Hill
No Would need to expand the
substation footprint by
approximately 10 to 20%.
Lakeside
115 kV
Pickering and
Talbot Hill
No Requires substation yard
expansion to fit additional
buswork. Would not likely need
to buy property, but would
need to extend approximately
10 to 20% of the existing fence
footprint.
Lake
Tradition
Install 1st
230/115kV
Transformer
Novelty Hill
and
Berrydale
Yes Requires existing Bonneville
Power Administration (BPA)
230 kV line to be extended to
bring 230 kV to Lake Tradition
substation.
Talbot Hill Install 3rd
230/115kV
Transformer
Lakeside and
Hazelwood
No Only enough space for one 115
kV line bay and three would be
needed. Would need to expand
the yard by approximately 5 to
10%.
January 2016 CHAPTER 2 PROJECT ALTERNATIVES 2-45
PHASE 1 DRAFT EIS
Substation
New
230/115 kV
Transformer
Required
New
115 kV Line
Connections
Required to:
Fits in
Existing
Substation
Footprint
Notes
Ardmore Sammamish Yes Requires fourth line; should fit
within the existing substation
footprint.
Clyde Hill Sammamish No Requires reconfiguring the
substation. Preliminary rebuild
designs have the substation
increasing about 50 to 60%
larger than existing yard.
Pickering Lakeside 115
kV
Yes
Berrydale Lake
Tradition
Yes
Novelty Hill Lake
Tradition
Yes
Hazelwood Talbot Hill No Requires rebuilding the
substation. A preliminary layout
has the substation increasing
about 200% larger than the
existing yard. Additional
property potentially needed.
Source: Strauch, personal communication, 2015a and 2015c
Transmission poles and lines. The exact number and locations of lines have not been
determined. Figure 2-25 provides a conceptual layout of where new 115 kV lines would be
required. A complete routing study would be done to evaluate the feasibility of any potential
route. It is assumed that these lines would follow existing utility or road rights-of-way, and
would either replace or be co-located with existing transmission and distribution lines
wherever possible. This represents approximately 60 miles of new 115 kV lines. It is
assumed these lines would be overhead lines. Additionally, an existing Bonneville Power
Administration (BPA) 230 kV line would have to be extended to bring 230 kV to the Lake
Tradition substation.
For a typical single circuit 115 kV system, without any distribution lines on the same poles,
pole heights would generally vary from 60 feet to 75 feet depending on span length, structure
configuration, and topography. However, in some instances taller poles may be required to
span obstacles, meet right-of-way constraints, and address topographic variations. If co-
location is required with existing 115 kV lines (a likely scenario, creating a double circuit),
then pole heights would likely need to be up to 40 feet taller (approximately 100 feet total) in
order to meet NESC requirements and right-of-way constraints.
Standard single circuit 115 kV lines are constructed on wood poles that are embedded
directly in the ground and supported by guy wires as necessary. A hole is augured or created
CHAPTER 2 January 2016 2 -46 PROJECT ALTERNATIVES
PHASE 1 DRAFT EIS
using a vacuum truck. The pole is placed, and the hole is backfilled with crushed rock. For
locations that lack space or right-of-way for adequate guying, self-supporting poles may be
utilized that are typically steel or laminated wood. Insulators are usually installed directly on
the poles, followed by the conductor using the same general methodology as described earlier
for the 230 kV system (Alternative 1).
Selection of appropriate pole material for 115 kV or 230 kV lines depends on height
requirements, available space for guying, and location along the corridor. NESC
requirements dictate the minimum separation between conductors. Turning and termination
structures are typically under heavier structural loading and may require the use of down
guys or self-supporting structures (i.e., glue-laminate or steel). The conductors for 115 kV
would typically be smaller in diameter, but they would not be noticeably different in
appearance from those used for 230 kV.
Length of Construction Period. Construction sequencing for overhead transmission lines
would be similar to construction of Alternative 1, Option A, although some poles may be
wood, which require less construction time than steel poles. Construction of transmission
lines would last for 24 to 28 months. Along the transmission line, any given location would
only see 3 to 5 days of construction activity spread over a period of 2 months. Three to four
crews would each install an average of three poles per day.
Equipment. Construction equipment required for Alternative 3 would be similar to
Alternative 1, Option A (see Appendix B).
2.3.4.2 Conservation
Under Alternative 3, PSE would continue the conservation efforts called out in its Integrated
Resource Plan (PSE, 2013), as described in the No Action Alternative. Alternative 3 is
expected to result in the same levels of conservation as the No Action Alternative.
2.3.5 Construction Summary Table
Table 2-3 shows a summary of construction details for each alternative, option, and
component. See Appendix B for a list of construction equipment associated with all project
alternatives.
January 2016 CHAPTER 2 PROJECT ALTERNATIVES 2-47
PHASE 1 DRAFT EIS
Table 2-3. Construction Summary Table
Alternative/
Component
Construction
Features
Construction
Footprint Construction Duration
No Action
Alternative
Occasional
conductor
replacement,
implementation of
new technologies
not requiring
discretionary
permits, and
installation of
distributed
generation facilities
under PSE’s
conservation
program
N/A N/A
Alternative 1 –
New Substation
(all options)
New substation yard
with a new
transformer and
associated electrical
equipment
• 3 to 4 acres Up to 18 months
Alternative 1 –
Option A: New
Overhead
Transmission
Lines
New 230 kV
transmission lines
• 18-mile corridor
• 120- to 150-foot-
wide clear zone
• If located along
existing easement,
clear zone could be
widened by 50 feet
• In any given
location, 3 to 5 days
within a period of up
to 2 months
• 12 to 18 months
total
Alternative 1 –
Option B:
Existing SCL 230
kV Transmission
Corridor
Complete rebuild of
existing 230 kV
transmission lines
• 15-mile corridor
• Up to 2 miles for
connector
transmission
corridors
• No new clear zone
along existing SCL
corridor
Up to 24 months total
Alternative 1 –
Option C:
Underground
Transmission
Lines
Underground 230
kV transmission
lines
• 30-foot-wide work
area and
permanent clear
zone
• Approximately 2
months in any given
location
• 28 to 36 months
total
CHAPTER 2 January 2016 2 -48 PROJECT ALTERNATIVES
PHASE 1 DRAFT EIS
Alternative/
Component
Construction
Features
Construction
Footprint Construction Duration
Alternative 1 –
Option D:
Underwater
Transmission
Lines
Underwater 230 kV
transmission lines
• Cable lines buried
3 to 5 feet below
the lake bottom or
directly on the lake
bottom
• Minimum of three
landing points for
vaults connecting
to overland lines
• Overland 230 kV
transmission lines
for approx. 8 miles
to connect to
substations
8 months
Alternative 2 –
Energy Efficiency
Component
Existing building
upgrades
N/A Limited
Alternative 2 –
Demand
Response
Component
Installation of
meters and in-home
monitoring systems
and control
equipment
N/A Limited
Alternative 2 –
Distributed
Generation
Component
Minor construction
activities primarily
on residential and
commercial sites
Facilities ranging from
rooftop installations to
up to 1 acre
Varying depending on
scale and technology
Alternative 2 –
Energy Storage
Component
Installation of
battery storage
facilities
6 acres 6 months
Alternative 2 –
Peak Generation
Plant Component
Three gas-fired
simple-cycle power
generation facilities
• Construction would
occur within or
adjacent to existing
PSE substations
• Up to 1 acre each
12 months
Alternative 3 –
New 115 kV
Lines and
Transformers
115 kV transmission
lines
• 60 miles of corridor
• 30- to 40-foot-
wide clear zone
• In any given
location, 3 to 5 days
within a period of up
to 2 months
• 24 to 28 months
total
January 2016 CHAPTER 2 PROJECT ALTERNATIVES 2-49
PHASE 1 DRAFT EIS
2.4 ALTERNATIVES CONSIDERED BUT NOT INCLUDED
The following alternatives were identified through scoping but are not included for analysis
in the Phase 1 Draft EIS for reasons explained below.
2.4.1 Use Existing BPA High-Power Transmission Line
Using the existing BPA line east of Lake Sammamish instead of installing a new 230 kV line
in the Eastside is not being included in the Phase 1 Draft EIS because this source is outside
the area that PSE has identified as being in need of more electrical power. To connect this
source to the deficiency area would require new 115 kV line construction to marginally
support the area. PSE considered several scenarios examining this potential solution. These
included the following:
• Tapping the BPA Maple Valley – Sammamish 230 kV line and the SCL SnoKing –
Maple Valley 230 kV line, and looping a new 230–115 kV Lakeside substation
between the tapped lines.
• Using the 230 kV BPA Maple Valley – Sammamish Line to loop into Lake Tradition
and installing a new 230–115 kV transformer at Lake Tradition to serve 115 kV load.
The solution also included re-conductoring the SCL Maple Valley – SnoKing 230 kV
with high-temperature conductors.
• Adding a 230–115 kV transformer at Lake Tradition and looping in BPA Maple
Valley –Sammamish 230 kV line. Adding a third 230–115 kV transformer at
Sammamish substation and assuming no new 115 kV lines are added to either
substation.
• Adding a 230–115 kV transformer at Lake Tradition, looping in BPA Maple Valley –
Sammamish 230 kV line, and adding a third 230–115 kV transformer at Talbot Hill
substation. It was assumed that no new 115 kV lines were added to either substation.
• Adding a 230–115 kV transformer at Lake Tradition, looping in BPA Maple Valley –
Sammamish 230 kV line, and adding a third 230–115 kV transformer at Sammamish
substation. This assumed new 115 kV lines would be constructed to both substations.
• Adding a 230–115 kV transformer at Lake Tradition and looping in BPA Maple
Valley –Sammamish 230 kV line, and adding a third 230–115 kV transformer at
Talbot Hill substation. This assumed new 115 kV lines would be constructed to both
substations.
All of these solutions were found to overload either transmission lines or transformers and
therefore would not address all relevant PSE equipment violations (electrical criterion #13).
See Eastside Transmission Solutions Report, October 2013 (updated February 2014), Tables
4.1 and 4.2, and Sections 4.6.3, 4.6.6, 4.6.8, 5.1.1, and 5.1.2 for more information (Gentile et
al., 2014).
2.4.2 Upgrade/Adjust Existing Electrical System
Several changes and adjustments to the electrical transmission system were proposed as
potential solutions. Several related to discontinuing the flow of electricity through the
CHAPTER 2 January 2016 2 -50 PROJECT ALTERNATIVES
PHASE 1 DRAFT EIS
Eastside to Canada during some peak demand periods. These were described in comments
received during scoping regarding renegotiation of the Columbia River Treaty (which relates
to river flows and electrical supply across the U.S. - Canada border), diverting power flowing
from the south toward Canada to other transmission lines, or simply cutting off power flow to
Canada altogether. Disconnecting the system from the region or not providing power to the
rest of the region during peak periods is not included as an alternative because it was not
considered viable for the following reasons:
• PSE has statutory and regulatory obligations that require being interconnected to the
electric grid and that cannot be violated without penalties. Those obligations are with
the FERC, NERC, WECC, ColumbiaGrid, and UTC (electrical criterion #1).
• This solution would also compromise PSE’s ability to supply power and maintain
reliability in an efficient and cost-effective manner; the generation that is owned and
contracted for by PSE is generally outside PSE’s service area and requires
transmission lines to transport that power to PSE’s service area. The diversity of the
generation mixture provides security in the event that one kind of generation becomes
limited (e.g., hydroelectricity in a year with low snowmelt or rainfall). Being part of
the regional grid allows the dispatch of the least costly generating units within the
interconnected area, providing an overall cost savings to PSE customers. Planned
outages of generating and transmission facilities for maintenance can be better
coordinated so that overall cost and reliability for the interconnected network is more
efficient. Being interconnected also allows economies of scale for both transmission
and generation facilities. Finally, this solution could reduce the supply of power to
the Eastside, necessitating additional conservation, generation, or storage beyond that
considered in the other alternatives in the EIS (electrical criteria #1 and 7).
• Disconnecting the north and south sections of the route at a central Bellevue
substation to prevent non-Eastside load from being carried on this line during peak
periods of demand on the Eastside would deprive the Eastside of power supply
needed during these periods. Separating the system in central Bellevue from the
regional grid would also not meet FERC mandatory reliability standards. This could
be a CAP, which is temporary in nature and not a long-term solution, and does not
bring a new source or new generation into the deficiency area (electrical criteria #1
and 7).
• Relying on BPA projects would not deliver the appropriate amount of power to the
Eastside area because the BPA sources are outside the deficiency area and would
address only wider regional problems, leaving a deficiency on the Eastside (electrical
criterion # 7).
• Renegotiating the Columbia River Treaty is outside the purview of PSE and the
Eastside Cities and would not help solve the problem as described previously
(electrical criterion #1).
Other suggested solutions made during scoping include converting an existing alternating
current (AC) line to a direct current (DC) power line, using “self-healing” lines, and changing
conductor types and sizes.
January 2016 CHAPTER 2 PROJECT ALTERNATIVES 2-51
PHASE 1 DRAFT EIS
Although switching to DC could potentially address the problem by marginally increasing the
capacity of the lines, it would add complexity to the system that would reduce operational
flexibility, which could have adverse impacts to the reliability and the operating
characteristics of PSE’s system. For example, if there was a problem within the DC portion
of the system, it would not be possible to switch among other sources, as it is when the entire
system is on AC. This alternative has not been included because avoiding such adverse
impacts to reliability is one of PSE’s stated electrical criteria (electrical criterion #1).
Suggested upgrades to the system (such as self-healing lines, up-conductoring, and installing
transformers and inductors) would not improve reliability but would shift electrical load onto
other components of the system, causing new deficiencies without addressing the
transmission problem. Self-healing lines are automated switching systems that are triggered
by adverse events in the system. They do not add capacity to the system, just speed in
recovery from an adverse event. Inductors perform similarly, shifting load but not adding
capacity. PSE examined up-conductoring in its solutions report and found that increasing
capacity of 115 kV conductors led to transformers being overloaded (Gentile et al., 2014).
Conversely, adding transformer capacity led to overloading lines. These solutions either do
not meet the project objectives, or they offer a short-term solution that would not meet PSE’s
performance criteria for serving 10 years or more after construction (electrical criterion #1).
2.4.3 Larger Generation Facilities
Adding a large generation facility is not included as an alternative. To be effective, PSE
found that the facilities would have to be located near the center of the Eastside area, such as
near the Lakeside substation. This alternative is not included because the Cities determined
that it does not meet SEPA requirements to provide a reasonable alternative that could
feasibly attain or approximate a proposal’s objectives at a lower environmental cost or
decreased level of environmental degradation (WAC 197-11-440(5)(b)). Such a facility
would likely have to be gas-fired to be capable of producing power reliably whenever it is
needed.
PSE determined that at least 300 MW of power generating capacity would be needed and the
most cost-effective way to generate that amount of power would be in a single plant. The
2013 Solutions Report (Gentile et al., 2014) found that small distributed generation and
energy storage would have little impact on the problem unless a large number were
developed, as described in Alternative 2, Integrated Resource Approach. Generation facilities
at the 300 MW size would require gas and/or water infrastructure that is presently
unavailable. These types of facilities also generate “atmospheric emissions and noise [that]
would be extremely challenging” to permit in a feasible location that would not also require a
significant new transmission line (Gentile et al., 2014).
Even if it were economically feasible to create multiple generation facilities of less than 300
MW, such as a series of plants generating 10 MW or more, they would need to be clustered
close to the center of the Eastside to be effective, and would likely impose noise, air, and
utilities impacts similar to or even greater than a single plant. Therefore multiple generation
facilities of greater than 10 MW were not included for the same reason a single large
generation plant was not included.
CHAPTER 2 January 2016 2 -52 PROJECT ALTERNATIVES
PHASE 1 DRAFT EIS
Smaller backup generators within the Eastside could potentially solve the peak demand;
however, PSE did not find that there are currently enough generator owners willing to
connect to the network to meet the project objectives (Gentile et al., 2014). PSE cannot
compel owners of generators to connect to a network. In addition, increased usage of diesel
generators would not meet present clean air regulations, and such facilities often have
considerable noise impacts. This is not included as a stand-alone alternative because it does
not meet PSE’s performance criteria of serving 10 years or more after construction (electrical
criteria #5, 6, and 15 and non-electrical criterion #3). However, providing a portion of the
projected load by this method is examined as part of the distributed generation component of
Alternative 2.
Generating more power outside of the Eastside area during peak periods, such as at PSE’s
existing peak generator plants, would not address the project objectives, because that would
still require transmission to deliver power to the load area without risking damage to
transmission equipment. This alternative is not included because it would not address the
deficiency in the Eastside (electrical criteria #5, 6 and 14). Peak generator plants providing a
portion of the projected load within the Eastside are considered under Alternative 2.
2.4.4 Submerged 230 kV Transmission Line in Lake Sammamish
The option of using a submerged line in Lake Washington is included in the Phase 1 Draft
EIS. Scoping comments also suggested using Lake Sammamish for a submerged line.
However, there are a number of technical issues that constrain the feasibility of a Lake
Sammamish submerged line. These include the following:
• Submerged cables are typically delivered to a site by ship or barge. Large barges
cannot access Lake Sammamish due to the weir at the outlet.
• Weight limits on highways would limit the length of cable reels to 1,100 feet, which
would mean approximately 34 splices to reach the length of the lake.
• Highway transport may also be limited due to the 14-foot reel diameter.
• Underwater splices increase the risk of cable failure, while splices on land require
construction of a vault at each splice. (Strauch, personal communication, 2015b)
Given these constraints, placing a cable in Lake Sammamish was deemed to not be a viable
option.
2.4.5 Other Approaches
An alternative addressing a phased approach is not included because it would not address the
quickly approaching transmission capacity deficiency during peak periods identified in the
Eastside (electrical criterion #10).
Combining alternatives that provide partial solutions was suggested during scoping.
Combinations of various solutions were considered. Alternative 2 includes suggested
components that would directly address the transmission capacity deficiency in the Eastside
that has been identified by PSE. Combinations with other components that would either
increase the problem or have little or no effect, such as those listed above, were not carried
forward.
January 2016 CHAPTER 2 PROJECT ALTERNATIVES 2-53
PHASE 1 DRAFT EIS
Solving the Eastside deficiency requires a reliable alternative composed of one or more of the
following:
• A new high-voltage energy source from the outside brought into the deficiency area;
• A new generation source or energy storage of sufficient size and duration installed
within the deficiency area; and/or
• Reduction in electrical load during peak demand periods.
Alternatives that would violate PSE’s Planning Standards and Guidelines (such as changing a
transmission line from AC to DC) or that could harm other utilities in the region (such as
disconnecting the Eastside from the regional grid during peak periods) would not become
compliant by combining them with other alternatives (electrical criterion #1). Alternatives
that would reduce the availability of power to the Eastside (such as limiting the flow of
power from sources outside of the Eastside) would require even greater measures to
compensate for the reduced power supply to the Eastside (such as new generation or storage,
more conservation, or new transmission capacity) and as such would likely have greater
impacts than the alternatives that are evaluated in the EIS (electrical criteria #1, 5, 6, and 14).
Among the alternatives suggested, this leaves only the alternatives that will be studied and a
few alternatives that provide temporary solutions, such as increasing the capacity of wires
and transformers, or temporary rerouting of power during peak periods. Combining
temporary solutions with the alternatives included in the EIS does not materially change the
range of alternatives for the EIS, although such measures could reduce the severity or risk of
impacts under the No Action Alternative.
Reducing the scope to include only Bellevue would require a generation facility within the
Bellevue city limits, which is not included for the same reasons as indicated earlier under
Larger Generation Facilities, or a solution similar to the Integrated Resource Approach
(Alternative 2). Therefore, narrowing the scope to include only Bellevue will not be
considered as a separate alternative.
2.5 BENEFITS AND DISADVANTAGES OF DELAYING
THE PROPOSAL
Delaying the project would have the benefit of avoiding the impacts in the near future for the
action alternatives described in the EIS. It is possible that by delaying the project, some of the
expanded conservation measures described in Alternative 2 would be incorporated into
development, reducing energy demand further than PSE has projected. Additional
conservation could have the benefit of reducing greenhouse gas generation from electrical
consumption on the Eastside. Delaying the project could allow technological advancements
to occur in areas such as battery storage or generation, providing additional feasible
alternatives to increased transmission capacity in the near term.
The disadvantages of delaying the project are that the risks of power outages (described in
Chapter 1) that would be associated with the No Action Alternative could develop over time.
It is also possible that the awareness of such risks would discourage development within the
Eastside.
CHAPTER 2 January 2016 2 -54 PROJECT ALTERNATIVES
PHASE 1 DRAFT EIS
CHAPTER 3. EARTH
3.1 HOW WERE EARTH RESOURCES IN THE STUDY
AREAS EVALUATED?
This chapter describes earth resources in the combined
study area (Alternatives 1, 2, and 3 as depicted on
Figure 1-4 in Chapter 1) at a programmatic level.
Geology and soils information was obtained from U.S.
Geological Survey (USGS) data (including
GEOMapNW)1, and critical areas mapping was
obtained from study area communities. No site visits
were conducted at this stage, largely due to the vast
geographical extent of the study area and the
programmatic approach to the analysis. In addition to
the USGS data, the following sources were reviewed to
obtain the data presented in this chapter:
• Natural Resources Conservation Service’s soil
surveys for King County (NRCS, 2015);
• King County geographic information systems (GIS) web portal (King County, 2015);
and
• Information from the Cascadia Region Earthquake Workgroup (City of Seattle,
2015).
3.2 WHAT ARE THE RELEVANT PLANS, POLICIES, AND
REGULATIONS?
This section provides the relevant regulatory framework including plans, policies, and
regulations related to geology and soil resources that would apply to the alternatives
proposed in Chapter 2. The National Electric Safety Code (NESC) establishes basic
provisions for safeguarding of persons from hazards arising from the installation, operation,
or maintenance of (1) conductors and equipment in electric substations, and (2) overhead and
underground electric supply and communication lines. The NESC is adopted by the state
public utility commission (in Washington it is the Utilities and Transportation Commission or
UTC), and utility providers must adhere to it. The NESC also includes work rules for the
construction, maintenance, and operation of electric supply and communication lines and
equipment. The standards are applicable to the systems and equipment operated by utilities,
or similar systems and equipment, of an industrial establishment or complex under the
1 Geologic mapping in the Pacific Northwest urban corridor is a cooperative effort among the USGS,
Washington Division of Geology and Earth Resources, Oregon Department of Geology and Mineral
Industries, University of Washington (GeoMapNW), Oregon State University, and Portland State University.
Earth Key Findings
Seismic and geotechnical
hazards including ground
shaking, liquefaction,
landsliding, coal mines and
other hazards are present
throughout the area. Impacts
under all alternatives would be
minor with implementation of
BMPs, geotechnical
recommendations, regulatory
requirements, and industry
standards.
January 2016 CHAPTER 3 EARTH 3-1
PHASE 1 DRAFT EIS
control of qualified persons. This standard consists of the
introduction, definitions, grounding rules, list of
referenced and bibliographic documents, and Parts 1, 2, 3,
and 4 of the 2012 Edition of the National Electrical Safety
Code (IEEE, 2012).
Washington State’s Growth Management Act (GMA)
requires all cities and counties to identify critical areas
within their jurisdictions and to formulate development
regulations to protect these areas (Chapter 36.70A RCW).
Among the critical areas designated by the GMA are
geologic hazard areas, which are areas susceptible to
erosion, sliding, earthquake, or other geologic events.
These hazards could affect the design, construction, and operation of the project and, if not
considered appropriately, could pose a risk to public safety.
As required by the GMA, each city and most of the towns in the combined study area have
codes regulating development in or near geologic hazard areas (including building codes).
These codes and local policies require measures to address hazards such as slope instability,
largely through avoidance by adhering to setbacks (unless a geotechnical slope stability
investigation can demonstrate feasibility). Projects are not allowed to increase the potential
for slope failure, and they must adhere to performance standards for construction in
geologically hazardous areas. Other hazards, such as liquefaction and ground shaking, are
addressed through implementation of building code standards that include seismic design
measures. Feasibility is typically demonstrated through a site-specific geotechnical
investigation that identifies underlying soil and bedrock properties, geotechnical hazards, and
whether identified hazards can be overcome through application of geotechnical engineering
recommendations.
The Washington State Building Code Council (SBCC) was created to advise the Legislature
on building code issues and to develop the building codes used in Washington State. These
codes help to ensure buildings and facilities constructed in the state are safe and healthy for
building occupants, workers, and the public and provide regulations to address various
geologic and soils conditions. The state building code is modeled on the 2012 International
Building Code and is combined with Washington State amendments. The building code
includes requirements for site preparation and foundations for aboveground improvements
that represent new loadings (i.e., placement of new structures that require bearing more
weight than previously).
Petroleum pipelines are regulated by the U.S. Department of Transportation under the
Pipeline and Hazardous Materials Safety Administration (PHMSA). PHMSA’s mission is to
protect people and the environment from the risks of hazardous materials transportation by
setting national policy, enforcing standards, and conducting research to prevent incidents.
Pipeline safety regulations are contained in Code of Federal Regulations (CFR), Title 49
Parts 190 to 199. In the state of Washington, the UTC is responsible for developing and
enforcing safety standards for natural gas and hazardous liquid pipelines located within the
state.
Grounding is a means to
provide safety to electrical
workers and any people who
may come in contact with
structures such as streetlights,
mast arms, metal poles, and
guy wires. The NESC provides
rules on grounding
components as a means to
safeguard any person from
injury that could be caused by
electrical potential.
CHAPTER 3 January 2016 3 -2 EARTH
PHASE 1 DRAFT EIS
Erosion hazards are typically addressed through drainage control requirements both during
and after construction. Typically, local jurisdictions have clearing and grading requirements
within the grading permit process to ensure that earth-disturbing construction activities are
conducted in a manner that protects topsoil and minimizes the potential for erosion.
Following the construction period, local drainage control requirements include design
measures to ensure that stormwater runoff is managed in a way that also minimizes the
potential for erosion.
3.3 WHAT EARTH RESOURCES AND GEOLOGIC
HAZARDS ARE PRESENT IN THE COMBINED STUDY
AREA?
3.3.1 Regional Geology and Topography
The combined study area is located in the central portion of the Puget Sound basin, an
elongated, north-south trending depression in western Washington between the Olympic
Mountain Range to the west and the Cascade Mountain Range to the east. The regional
topography is characterized by a series of north-south trending ridges separated by deep
troughs that are now known as Puget Sound, Elliott Bay, Lake Washington, and Lake
Sammamish. Land elevations range from about zero up to approximately 3,000 feet above
mean sea level at Tiger Mountain (National Geodetic Vertical Datum 29).
The regional topography was formed by the movement of glaciers over thousands of years.
The glaciers were up to several thousand feet thick, and soils that were present beneath them
are generally very hard and compacted as a result of the weight of the glaciers. More
recently, erosional processes and landform changes resulting from human development have
modified the regional topography. Geology in the region generally includes recent, surficial
soils over a thick sequence of glacially consolidated soils and then bedrock. Subsurface
conditions may vary greatly and unpredictably over short distances, and project planners
frequently must contend with multiple geological concerns (e.g., expansive soils, artificial
fills, corrosive soils, and liquefiable soils) for linear projects such as transmission lines.
3.3.2 Soils
The EIS Consultant Team reviewed soils data available from the Natural Resources
Conservation Service (NRCS) Soil Survey Data (NRCS, 2015). The NRCS categorizes soils
of similar composition into what are called soil series. Table 3-1 provides the soil series
identified and their approximate portion of the combined study area.2
2 Table 3-1 only provides soil series that were quantified above 0.2 percent because of the number of
series that were identified in smaller percentages. The table also does not include the amount of surface
water in the study area, which was calculated at approximately 5.5 percent.
January 2016 CHAPTER 3 EARTH 3-3
PHASE 1 DRAFT EIS
Table 3-1. Soils in Combined Study Area
Soil Series Percent of Study Areas
Alderwood 44.7
Everett 10.7
Arents 8.0
Beausite 6.3
Ovall 3.4
Kitsap 2.7
Urban Land 2.6
Seattle Muck 2.2
Indianola 2.2
Bellingham 1.3
Neilton 1.0
Sammamish 0.9
Puyallup 0.9
Briscot 0.8
Ragnar 0.8
Norma 0.6
Pits 0.5
Puget 0.5
Earlmont 0.5
Mixed Alluvial Land 0.4
Pilchuck 0.4
Tukwila Muck 0.3
Riverwash 0.2
Shalcar Muck 0.2
Snohomish 0.2
Sultan 0.2
Source: NRCS, 2015.
As shown in Table 3-1, the Alderwood series makes up the soil in almost half of the
combined study area. It consists of Alderwood gravelly sandy loam on zero to 8 percent
CHAPTER 3 January 2016 3 -4 EARTH
PHASE 1 DRAFT EIS
slopes (1.4 percent), Alderwood gravelly sandy loam on 8 to 15 percent slopes (32.2 percent),
Alderwood gravelly sandy loam on 15 to 30 percent slopes (5.8 percent), and Alderwood
combined with Kitsap soils on very steep slopes (5.3 percent). The Alderwood series is
derived from glacial drift or outwash and is moderately well drained. Erosion hazard (also
discussed below) for the Alderwood series is slight on slopes of zero to 6 percent, slight to
moderate on slopes of 6 to 15 percent, and severe to very severe on slopes greater than 15
percent. Slippage potential along the geologic contact between the till deposits and the
underlying native deposits is moderate to severe on slopes greater than 15 percent (NRCS,
2015).
The Everett soils series is the next most prominent group of soils mapped in the combined
study area. It consists of gravelly sandy loam on zero to 5 percent slopes (3.1 percent),
gravelly sandy loam on 5 to 15 percent slopes (5.5 percent), gravelly sandy loam on 15 to 30
percent slopes (1.2 percent), and gravelly sandy loams mixed with Alderwood series soils
(0.9 percent). Erosion hazard for Everett soils is slight on slopes of zero to 6 percent, slight to
moderate on slopes of 6 to 15 percent, and severe to very severe on slopes greater than 15
percent (NRCS, 2015).
The Arents series is also fairly prominent and consists of till plains derived from basal till.
Runoff on Arents soils is generally slow, and the erosion hazard is slight (NRCS, 2015).
3.3.3 Geologic Hazards
An important consideration for the construction and operation of the alternatives would be
the potential to encounter geologic hazards, including steep slopes, erosion, landslides,
seismic hazards, and other hazards such as soft soils.
Steep Slope Hazards 3.3.3.1
Steep slope hazards are generally characterized as areas where slopes are steeper than 15
percent or have shown evidence of past slope failure. The state legislature (WAC 365-190-
120) defines landslide hazard areas as areas of historic failures, inclines of 15 percent or more
containing a geologic contact or groundwater seepage, and bedrock slopes of greater than 40
percent. However, steep slope hazards can occur wherever the force of gravity becomes
greater than either friction forces or the internal strength of the rock, soil, or sediment. Slope
hazard areas are considered hazards because they are prone to landslides, either during
periods of wet weather which reduces friction, as a result of human activities such as grading,
or during seismic events. Landslide hazard areas are identified in Figure 3-1.
Erosion Hazards 3.3.3.2
Erosion hazards occur where soils may experience severe to very severe erosion from
construction activities or through changes in surficial conditions that expose soils to new
erosive forces. Erosive forces can come from precipitation, changes in drainage patterns,
removal of vegetation, wind, or wave action. Certain types of soil, such as silts, are generally
more prone to erosion hazards. The potential for erosion also increases as the slope steepness
increases. Surficial soils and topographic maps can be used to identify areas that are
particularly susceptible to erosion.
January 2016 CHAPTER 3 EARTH 3-5
PHASE 1 DRAFT EIS
The NRCS rates soils based on an erosion factor “K,”
which indicates the susceptibility of a soil to sheet and rill
erosion by water (NRCS, 2015). Factor K is one of six
factors used to predict the average annual rate of soil loss
by sheet and rill erosion in tons per acre per year. The
estimates are based primarily on percentage of silt, sand,
and organic m atter and on soil structure and saturated
hydraulic conductivity (Ksat). Values of K range from
0.02 to 0.69. Other factors being equal, the higher the
value, the more susceptible the soil is to sheet and rill
erosion by water. The Factor K values for the soils within
the study areas range from 0.05 (Everett series on zero to
5 percent slopes) up to 0.43 (Earlmont series and Ellwell
series on 30 to 60 percent slopes). Figure 3-1 illustrates
areas of high erosion hazard mapped by local jurisdictions
in accordance with the GMA.
Landslide Hazards 3.3.3.3
Landslide hazard areas are mapped by local jurisdictions
in accordance with the GMA. They include areas where
there is evidence of past landslides, where the slope is 15
percent to 40 percent and the soils are underlain by silt or clay that can perch groundwater, or
where the slope is steeper than 40 percent, regardless of soil type. This type of hazard is
closely associated with the steep slope hazard. Landslide hazard areas identified within the
combined study area are shown in Figure 3-1.
Sheet erosion is the uniform
removal of soil in thin layers by
the forces of overland
stormwater flow.
Rill erosion is the removal of
soil by concentrated water
running through little
streamlets, or headcuts.
Saturated hydraulic
conductivity is a property that
describes the ease with which
a fluid (usually water) can move
through saturated media such
as soil.
A perched water table occurs
above the regional water table,
in the vadose zone, when there
is an impermeable layer of rock
or sediment that can suspend
the water there.
CHAPTER 3 January 2016 3 -6 EARTH
PHASE 1 DRAFT EIS
Energize Eastside EIS 140548
Figure 3-1
Landslide and Erosion Hazard Areas
SOURCE: King County 2015; Sammamish 2015; Issaquah 2015; Bellevue 2015;
Kirkland 2015; Redmond 2015; ESA 2015; WA Ecology 2014.
For more info visit www.energizeeastsideeis.org/map-landslide-erosion
Lake Washington
Lake
Sammamish
Bellevue Sammamish
Issaquah
Renton
Newcastle
RedmondKirkland
Beaux Arts
Medina
Clyde
Hill
Hunts
Point
Yarrow
Point
Mercer
Island
Lakeside
Sammamish
Talbot Hill
Novelty Hill
Lake Tradition
Erosion Hazard
Area
Landslide Hazard
Area
100ft Contour
Existing
Substations
Roadway
Combined Study
Area Boundary
Water bodies
City Limits
Unincorporated
King County
U:\GIS\GIS\Projects\14xxxx\D140548_EastsidePSETransmisisonCoor\MXD\LandslideAndErosionHazardAreas.m xd
0 2
Miles
Note: This map is for reference only. It is not guaranteed that the information is accurate or complete.
Seismic Hazards 3.3.3.4
The Puget Sound basin is located within a seismically
active area dominated by the Cascadia subduction zone,
which forms the boundary between two tectonic plates: the
North American plate and the Juan de Fuca plate. The
project vicinity has been subject to earthquakes in the
historic past and will undoubtedly undergo shaking again
in the future.
Earthquakes in the Puget Sound region result from one of
three sources: the Cascadia subduction zone off the coast
of Washington, the deep intraslab subduction zone located
approximately 20 to 40 miles below the Puget Sound area,
or shallow crustal faults.
1. The Cascadia subduction zone shapes the geography of northern California, Oregon,
Washington, and southern British Columbia, where the North American plate collides
with a number of smaller plates. The largest of these is the Juan de Fuca plate,
flanked by the Explorer plate to the north and the Gorda plate to the south. These
smaller plates “subduct” (descend) beneath the North American plate as they
converge along a 700-mile-long boundary. A large portion of the boundary between
the subducting and overriding plates resists the convergent motion, until this part of
the boundary releases the stored energy in an earthquake.
2. The closest active crustal source is the Seattle Fault Zone which runs roughly east-
west in south Bellevue and roughly parallel to Interstate 90 (see Figure 3-2). A fault
is considered active when it has shown evidence of displacement within the last
11,000 years. An earthquake on the Seattle Fault poses the greatest risk to the Seattle
urban region (City of Seattle, 2015).
3. Deep quakes are the most common large earthquakes that have occurred in the Puget
Sound region. Quakes larger than magnitude 6.0 occurred in 1909, 1939, 1946, 1949,
1965, and 2001 (City of Seattle, 2015). However, shallow quakes are the type
expected on the Seattle Fault Zone, which can create more damage than deep quakes
because of the proximity to the epicenter. Damage from earthquakes depends on
many factors including distance to epicenter, soil and bedrock properties, and
duration of shaking.
Seismic hazards include the primary effects of earthquakes, such as ground displacement
from fault rupture and ground shaking, as well as secondary effects including liquefaction,
settlement, tsunamis, and seiche waves. These scenarios are defined below.
3.3.3.4.1 Earthquake-induced ground rupture
Defined as the physical displacement of surface deposits in response to an earthquake’s
seismic waves. The magnitude, characteristics, and nature of fault rupture can vary for
different faults or even along different strands of the same fault. Strong ground shaking from
a major earthquake can produce a range of intensities experienced at any one location.
Subduction is the process
when one tectonic plate moves
under another and sinks into
the mantle as the plates
converge.
Crustal faults refer to the
deformation caused by
tectonic forces that are
accumulated in the earth’s
crust (generally the upper 20 to
30 miles of the earth’s surface).
CHAPTER 3 January 2016 3 -8 EARTH
PHASE 1 DRAFT EIS
Ground shaking may affect areas hundreds of miles distant from the earthquake’s epicenter.
The ground shaking can result in slope failure, settlement, soil liquefaction, tsunamis, or
seiches, all of which pose a risk to the public. Areas considered to be of high seismic risk are
depicted in Figure 3-2.
3.3.3.4.2 Liquefaction
Of particular concern because it has often been the cause of damage to structures during past
earthquakes. Liquefaction occurs where soils are primarily loose and granular in consistency
and located below the water table. Saturated loose soils that are found within 50 feet of the
ground surface are considered at most risk of liquefaction. The consequences of liquefaction
include loss in the strength and settlement of the soil. The loss of strength can result in lateral
spreading, bearing failures, or flotation of buried utility vaults and pipes. Seismic hazard
areas identified in Figure 3-2 are those areas where the foundation soils are considered to be
subject to liquefaction or lateral spreading during an earthquake (but could also be
susceptible to seismically induced settlement). Typically, these soils are found in low-lying
areas near bodies of water, such as along the larger streams and around lakes where is a high
probability of loose saturated alluvial soils. In the combined study area, areas such as lowland
lakeside areas of the northern and southern tips of Lake Sammamish, as well as the
floodplains of the Cedar River and Evans Creek, contain areas considered susceptible to
liquefaction.
3.3.3.4.3 Tsunamis or seiches
Possible secondary effects from seismic events. Tsunamis, often incorrectly described as tidal
waves, are sea waves usually caused by displacement of the ocean floor. Typically generated
by seismic or volcanic activity or by underwater landslides, a tsunami consists of a series of
high-energy waves that radiate outward like pond ripples from the area in which the
generating event occurred. For the Puget Sound region, either a large subduction zone quake
off the coast or along the Seattle Fault could produce a tsunami. However, while a tsunami
generated by a distant or Cascadia subduction earthquake could result in much damage to the
coast, the impact in King County would not be as great. In the case of a subduction zone
quake, a tsunami would travel from the coast through the Strait of Juan de Fuca into Puget
Sound, and then south to Seattle. As a result, primary concerns lie with a tsunami or seiche
generated by a land movement originating on the Seattle Fault (King County, 2009). A
tsunami from the Seattle Fault could create tsunamic waves affecting areas of the shoreline
along Elliott Bay which is outside of the study area.
3.3.3.4.4 Seiche waves
Consist of a series of standing waves in an enclosed or partially enclosed body of water
caused by earthquake shaking, similar to what could be described as sloshing action. Seiche
waves can affect harbors, bays, lakes, rivers, and canals. Both Puget Sound and Lake
Washington could experience a seiche as they did in 1891, 1949, and 1964 as well as on Lake
Sammamish. A seiche could affect a larger area than a tsunami because of King County’s
extensive shoreline (King County, 2009). The “sloshing” effect of a seiche could cause
damage to facilities close to the water.
January 2016 CHAPTER 3 EARTH 3-9
PHASE 1 DRAFT EIS
Energize Eastside EIS 140548
Figure 3-2
Seismic Hazard Areas
SOURCE: King County 2015; Kirkland 2015; Redmond 2015;
Bellevue 2015(fault line); ESA 2015; WA Ecology 2014.
Lake Washington
Lake
Sammamish
Bellevue Sammamish
Issaquah
Renton
Newcastle
RedmondKirkland
Beaux Arts
Medina
Clyde
Hill
Hunts
Point
Yarrow
Point
Mercer
Island
Lakeside
Sammamish
Talbot Hill
Novelty Hill
Lake Tradition
Seattle Fault
Combined Study
Area Boundary
Seismic Hazard
Area
Existing
Substations
Roadway
Water bodies
100ft Contour
City Limits
Unincorporated
King County
U:\GIS\GIS\Projects\14xxxx\D140548_EastsidePSETransmisisonCoor\MXD\Seism icHazardAreas.m xd
0 2
Miles
Note: This map is for reference only. It is not guaranteed that the information is accurate or complete.
Other Hazards 3.3.3.1
Soft soil conditions or soils that cannot support new improvements can also be a form of
geologic hazard, causing subsidence or settlement over the short or long term. Soft soils can
consist of undocumented fill materials or natural soils that have not been subject to
overburden forces and thus have low strengths and are compressible. Other hazards could
include coal mining areas and tunnels such as those present in southern Bellevue and
Newcastle. Without appropriate design consideration, soft soils can lead to embankment
failures during construction or long-term settlement after construction if left unaddressed.
The presence of soft soils or soils that are not suitable to support new loadings (i.e.,
placement of buildings or towers) can only be determined on a site-specific basis through
observation and laboratory testing of subsurface materials.
3.4 WHAT GEOLOGIC RISKS ARE PRESENT FOR
EXISTING ELECTRICAL INFRASTRUCTURE?
PSE is not aware of any past major geological incidents affecting power facilities on the
Eastside. Following the Nisqually Earthquake in 2001, PSE reported 200,000 customers
without power due to tripped circuit breakers immediately after the earthquake, which was
restored to all but 8,000 customers by the end of the day (Nisqually Earthquake
Clearinghouse Group, 2001). Systemwide, there have been no structure failures of steel
transmission poles due to geologic hazards, and failures of wood poles have been rare,
involving extenuating circumstances like placement in a bog or being impacted by a landslide
in a remote mountain setting (Strauch, personal communication, 2016).
Although it is possible that the Cascadia subduction zone could move in a way that causes a
series of large earthquakes (each measuring magnitude 8.0 to 8.5) over a period of years, the
earthquake that many scientists and emergency planners anticipate is modeled on the zone’s
last major quake in 1700 that caused ruptures from end to end, causing one great earthquake
measuring magnitude 9.0 (CREW, 2013). The shaking that results from this type of abrupt
shifting of the earth’s crust would be felt throughout the Pacific Northwest, causing shaking
for 4 to 6 minutes. In general, the intensity and destructiveness of the shaking will be greater
at locations closer to the plate interface, with coastal areas experiencing the highest
intensities and the level of shaking diminishing farther inland. Distance, however, is not the
only factor: local geologic conditions, including soil type, can increase or decrease the
intensity of the shaking and produce a range of secondary effects, including landslides and
liquefaction (the latter occurs when certain types of soil lose cohesion and behave like a
liquid). Widespread power outages are expected throughout the Pacific Northwest, including
the combined study area, from downed power lines or damage to substations as a result of an
earthquake. Slope failure, soil erosion, etc. could also impact electrical infrastructure by
causing downed power lines or other damage to infrastructure that would interrupt service.
January 2016 CHAPTER 3 EARTH 3-11
PHASE 1 DRAFT EIS
3.5 HOW WERE POTENTIAL EARTH IMPACTS
ASSESSED?
Geology and soil considerations important to the Energize Eastside Project include general
topography, underlying geological characteristics and properties, and soil characteristics, as
well as seismic and other related geologic hazards. These considerations affect the type of
construction methods used for the project and, if not adequately considered during project
design, could affect the long-term safety of the proposed improvements. Regional geology
and seismicity would not change as a result of the project, but they would have an important
influence on how the project is designed and constructed.
Potential impacts were determined by identifying the range of geologic hazard areas and soil
types present within the study area associated with each alternative.
Minor - If implementation of regulatory requirements and project design would address
potential adverse impacts such that there would be little likelihood of adverse or even
noticeable effects. While some damage might be anticipated during a seismic event, provided
that there is protection of human health and limited disruption to power supply capabilities,
impacts would be considered minor.
Moderate - If implementation of regulatory requirements and project design would address
most potential adverse impacts, but some reasonable potential for adverse or substantive
effects would remain such that risks to human health or structural improvements would
remain above acceptable levels3.
Significant – Even with implementation of regulatory requirements and design measures, if
substantive damage, injury, death, or widespread or long-term interruption of power supply
would likely occur, then impacts would be considered significant. With regard to seismic
hazards, these impacts would be considered significant even if the probability is remote.
3.6 WHAT ARE THE LIKELY CONSTRUCTION IMPACTS
RELATED TO EARTH?
Construction activities involve varying degrees of earthwork, including grading, excavation,
and stockpiling of soils. Soils formerly protected by vegetation or covered by asphalt or
concrete can become exposed to winds and water flows that can result in soil erosion or loss
of topsoil. As detailed in Chapter 5, projects that disturb more than 1 acre would be required
to obtain a General Construction Permit through the National Pollutant Discharge
Elimination System (NPDES) program. Such projects must include construction best
management practices (BMPs), as detailed in a Stormwater Pollution Prevention Plan
3 The use of “acceptable levels of risk” is used here to acknowledge that eliminating all risk from
geotechnical hazards such as seismic groundshaking and landslides is technically not feasible, and due to
the inherit uncertainties regarding the timing and severity of natural disasters, some risk will inevitably
remain. However, the basis for regulatory requirements including those set by the National Electric Safety
Code (NESC), Federal Energy Regulatory Commission (FERC), and the North American Electric Reliability
Corporation (NERC) requirements take into account a variety of risk factors that are protective of human
health.
CHAPTER 3 January 2016 3 -12 EARTH
PHASE 1 DRAFT EIS
(SWPPP). These BMPs are developed on a project-specific basis and may vary depending on
the activities involved. Typical examples of construction BMPs could include installation of
silt fences, use of straw bales, or application of soil stabilization measures that are designed
to minimize the potential for erosion to occur on exposed areas. In general, these water
quality BMPs are effective in minimizing erosion and loss of topsoil such that additional
protection measures are not necessary, and with implementation the BMPs would result in a
minor impact for all construction activities.
3.6.1 Construction Impacts Considered
Construction activities common to all action alternatives have the potential to cause a number
of short-term impacts on the environment related to geology and soils, including the
following:
Erosion Hazards 3.6.1.1
Clearing of protective vegetation, fill placement, and spoils removal or stockpiling during
construction allows rainfall and runoff to erode soil particles. The severity of potential
erosion depends on the quantity of vegetation removed, site topography, rainfall, types of
soils, and the volume and configuration of soils stockpiled. BMPs that could help minimize
erosion hazards include, but are not limited to, the following:
• Maintaining vegetation cover and providing adequate surface water runoff systems;
• Constructing silt fences downslope of all exposed soil and using plastic covers over
exposed earth; and
• Using temporary erosion control blankets and mulching to minimize erosion prior to
vegetation establishment.
Slope Instability and Landslide Hazards 3.6.1.2
Construction of the proposed infrastructure could involve grade changes, cuts and fills, and
installation of bridge and retaining wall structures in areas susceptible to landsliding or
slumping of hillsides. Geotechnical evaluations and slope stability analysis, where necessary,
would be completed to limit the risk of impacts resulting from constructing in landslide
hazard areas. Construction in landslide hazard areas is more likely to occur under
Alternatives 1 and 3 than Alternative 2.
All grading and cut-and-fill activities would be done in accordance with a grading plan that
would be developed following a final geotechnical evaluation for the proposed
improvements. Construction specifications would include quality assurance programs that
prohibit construction in oversteepened slopes in accordance with local and state building
code requirements.
Seismic Hazards 3.6.1.3
An earthquake could occur during construction, resulting in embankment slope failures,
liquefaction, ground settlement, or equipment destabilization. The risk of seismic hazards to
construction is considered low because of the relatively low probability that an earthquake
January 2016 CHAPTER 3 EARTH 3-13
PHASE 1 DRAFT EIS
would coincide with the actual limited construction period. If a large earthquake were to
occur, the major risk would be to the ongoing construction activities although injury to
workers is also possible. Work schedules would likely be delayed as efforts are made to
repair damaged components of the work. Damage to exposed cuts or fills could disrupt
utilities or nearby structures.
Construction-Induced Vibrations 3.6.1.4
The use of heavy equipment during construction causes ground vibrations. The level of
vibrations depends on the type of heavy equipment, distance from the source, and ability of
the soil to transmit vibrations. The main concern for construction vibration is potential
damage to structures. Most construction processes do not generate high enough vibration
levels to approach damage criteria because ground vibrations tend to dissipate quickly with
distance. The major sources of construction vibration include impact pile driving, augered
piling, vibratory rollers, and horizontal directional drilling.
Olympic Pipeline 3.6.1.5
In addition to the aforementioned hazards, portions of the existing 115 kV overhead easement
corridor are shared with the Olympic Pipe Line Company (OPLC) which operates two steel
pipelines that transport petroleum products. The pipelines are 16 inches and 20 inches in
diameter and buried approximately 3 to 4 feet below the ground surface. Construction of new
transmission lines in the vicinity of the petroleum pipelines or other earthwork activities in or
near these pipelines could represent potential hazards from inadvertent contact, causing
excessive ground vibrations, or result in damage from erosion. Although a significant adverse
impact could occur during construction near petroleum pipelines, these potential hazards do
not constitute a probable impact due to existing regulations and practices in place for pipeline
safety. OPLC has stringent construction requirements in the area of its pipelines and would
continue close coordination with PSE for all construction activities located adjacent to these
pipelines. Therefore, no potentially significant adverse impacts related to work near pipelines
are expected under any of the alternatives. See also Chapter 8 for a discussion of potential
rupture hazards.
3.6.2 No Action Alternative
Under the No Action Alternative, PSE’s existing maintenance activities and programs would
continue. No utility lines or facilities would be built; therefore, no construction impacts
related to geologic and seismic hazards are anticipated.
3.6.3 Alternative 1: New Substation and 230 kV Transmission Lines
Impacts are described according to the major components associated with Alternative 1. The
substation impacts are described first, followed by transmission line options.
The expansion of the substations or construction of a new substation would require clearing
and grading to prepare the area for foundations to support the new transformer. The new
transformer would also require supporting equipment that would be placed on a concrete pad
in accordance with regulatory requirements and industry standards. All construction activities
CHAPTER 3 January 2016 3 -14 EARTH
PHASE 1 DRAFT EIS
for the expansion of the substations would be done in accordance with identified BMPs to
minimize erosion, resulting in minor effects.
The transmission lines considered under this alternative fall under four different options, and
they all involve some disturbance of surface soils or submerged soils. Disturbance of site
soils would be necessary for clearing and grading to prepare foundation pads, as well as
potentially a staging area and equipment access depending on the location of the transmission
line.
Option A: New Overhead Transmission Lines 3.6.3.1
Under this option, a minimum of 18 miles of new overhead transmission lines would be
constructed. Most construction would occur within existing easements but could also occur in
new locations that might need more extensive grading and clearing activities. As noted
above, construction activities would be conducted in accordance with BMPs outlined in the
SWPPP prepared for the NPDES construction permitting. These erosion control BMPs would
cover all construction activities and provide protection of any disturbed soils. Implementation
of these BMPs would ensure that the potential for erosion during construction is minimized
such that impacts would be minor.
In addition, prior to construction, geotechnical evaluations would be completed to identify
and limit potential impacts resulting from constructing in landslide hazard areas.
Construction specifications would include quality assurance programs that prohibit
construction in oversteepened slopes in accordance with local and state building code
requirements.
Option B: Existing Seattle City Light 230 kV Transmission 3.6.3.2
Corridor
This option includes rebuilding both of the Seattle City Light SnoKing-Maple Valley 230 kV
transmission lines and constructing a new transmission substation. This option would result
in less disturbed area and a reduced potential for erosion and other hazards compared to
Alternative 1, Option A. Implementation of required BMPs in accordance with NPDES
Construction General Permit requirements would be effective in ensuring that the erosion
potential is minor.
Option C: Underground Transmission Lines 3.6.3.3
Placement of the new transmission lines underground would require the most disturbance of
surface soils and have the greatest potential for erosion compared to the other options. This is
because of the amount of earthwork required to create trenches and potentially the need for
imported fill in cases where the natural soils are not suitable for reuse. Adherence to the
NPDES Construction General Permit would be effective in reducing the erosion potential to
the point it would be considered minor.
Option D: Underwater Transmission Lines 3.6.3.4
Depending on the underlying conditions present, the installation of underwater transmission
lines could be completed using trenchless methods, such as horizontal directional drilling, or
January 2016 CHAPTER 3 EARTH 3-15
PHASE 1 DRAFT EIS
trenching methods using special vessels to dredge the trenches. Trenchless methods would
disturb soils at the entry and exit points (where the splicing vaults would be located landside)
to enable the horizontal drilling equipment to reach desired depths. Ultimately, trenchless
methods would result in less disturbance than conventional methods, and BMPs would also
be required at the entry and exit points to ensure that erosion potential is minimized.
Underwater dredging using conventional methods would result in localized disruption of
sediments during construction, however, they would likely be reused to bury the line (water
quality impacts associated with turbidity are discussed in the Chapter 5). Nonetheless, both
trenchless and conventional methods would require implementation of BMPs for all landside
disturbances, ensuring that erosion potential is minimized and impacts reduced to minor
levels consistent with applicable in-water permit requirements.
3.6.4 Alternative 2: Integrated Resource Approach
Potential construction impacts under Alternative 2 would be much more limited than
Alternative 1 because less construction of new infrastructure would be necessary. Clearing
and grading would be necessary for the battery storage site and peak generator plants.
Depending on location, this could include replacing major gas mains to increase natural gas
supply capacity. Construction BMPs would be implemented to address potential erosion
impacts. Earthwork activities would be done in accordance with design plans supervised by a
state-licensed geotechnical engineer, and thus potential impacts would be minor.
3.6.5 Alternative 3: New 115 kV Lines and Transformers
Alternative 3 would replace or co-locate over 60 miles of new 115 kV transmission and
distribution lines. The lines would be constructed overhead and would generally have similar
potential construction impacts to Alternative 1 although the amount of construction would be
greater. By covering a greater area there would likely be more probability of encountering
critical areas such as steep slopes or unstable soils. As noted above for Alternative 1,
geotechnical evaluations would identify and limit potential impacts resulting from
constructing in landslide hazard areas. Construction specifications would prohibit
construction in oversteepened slopes in accordance with local and state building code
requirements.
During construction, erosion control BMPs would be implemented during all earthwork
activities to address potential erosion impacts. Earthwork activities would be done in
accordance with design plans supervised by a state-licensed geotechnical engineer.
Therefore, with implementation of required erosion control BMPs and other applicable
permit requirements, construction impacts would be minor.
3.7 HOW COULD OPERATION OF THE PROJECT
AFFECT EARTH RESOURCES?
3.7.1 Operation Impacts Considered
All of the alternatives would rely on an electrical system that crosses seismic and other
geologic hazard areas. In general, Alternative 2 would have a more limited geographic
CHAPTER 3 January 2016 3 -16 EARTH
PHASE 1 DRAFT EIS
coverage than Alternatives 1 and 3, but facility footprints for energy storage and peak
generation plant components could be large (similar in size to a substation). The study areas
cover relatively large geographical areas that contain a range of geologic conditions and
potential hazard areas, from flat lowland areas of the floodplains to upland areas with steep
topography. In general, potential impacts would likely include the following:
Erosion Hazards 3.7.1.1
Clearing of protective vegetation or asphalt/concrete, fill placement, and spoils removal or
stockpiling during construction allows exposed soils to be susceptible to the erosive effects of
wind and water. However, once the project is constructed, revegetation or replacement with
asphalt or concrete would reduce the potential for erosion. As noted above, the project would
be required to adhere to the NPDES Construction General Permit. This permit includes
postconstruction BMP requirements to ensure that drainage is managed during project
operation to protect soils from erosion.
Slope Instability and Landslide Hazards 3.7.1.2
Proposed improvements would consist primarily of new or expanded substations or
development of storage or generation facilities, as well as construction of new transmission
lines that would have a relatively limited footprint. These facilities would be in developed
areas and would be subject to building codes that require geotechnical investigations and an
evaluation of slope stability where necessary.
In addition, transmission poles and towers constructed under Alternatives 1 and 3 would
adhere to construction standards as outlined in National Electric Safety Code (NESC),
Federal Energy Regulatory Commission (FERC), and North American Electric Reliability
Corporation (NERC) requirements including foundation designs to ensure long-term stability.
Also, the American Society of Civil Engineers (ASCE) produces Manual No. 74 that
provides Guidelines for Electrical Transmission Line Structural Loading, including standards
for reliability-based design to prevent cascading types of failures.
Seismic Hazards 3.7.1.3
Seismic activity is likely to occur during the life of the proposed improvements 4 and could be
substantial, resulting in significant damage, power outages, injury, and death, if the facilities
are not designed appropriately. Catastrophic failures of circuit breakers, transformer
bushings, and disconnect switches at substations or downed power lines can result in
widespread power outages. For the substation expansions under Alternatives 1 and 3, prior to
the issuance of grading permits, PSE would be required to retain a Washington-licensed
geotechnical engineer to design the project facilities to withstand probable seismically
induced ground shaking at each location. All grading and construction would adhere to the
specifications, procedures, and site conditions contained in the final design plans, which
would be fully compliant with the seismic recommendations of the Washington State
Building Code and any local building code amendments. The required measures would
encompass site preparation and foundation specifications.
4 In general, the design life of improvements is considered to be very roughly 50 years.
January 2016 CHAPTER 3 EARTH 3-17
PHASE 1 DRAFT EIS
The final structural design would comply with NESC 2012 as adopted by the UTC, which
also includes seismic standards. For the transmission lines, NESC 2012 states that the
structural requirements necessary for wind/ice loadings are more stringent than seismic
requirements and sufficient to resist anticipated earthquake ground motions. In addition,
according to ASCE Manual No. 74, “transmission structures need not be designed for
ground-induced vibrations caused by earthquake motion because historically, transmission
structures have performed well under earthquake events, and transmission structure loadings
caused by wind/ice combinations and broken wire forces exceed earthquake loads.”
Nonetheless, load comparisons would be performed between a seismic event and extreme
weather conditions to ensure that the appropriate structural design would be able to withstand
either of these conditions.
Liquefaction 3.7.1.4
Liquefaction of soils during an earthquake could result in vertical and lateral displacements
of structures, embankments, and paved areas, potentially resulting in substantial damage or
injury and system outages. The liquefaction potential of each project site would be confirmed
during the design stage as required by law. Design of structures to resist seismic forces and
secondary effects such as liquefaction would be required.
Unstable or Unsuitable Soils 3.7.1.5
Existing soils that cannot support proposed improvements, cannot be reused as structural fill
or landscape material, or could cause corrosion of subsurface improvements could be a
source of damage to new facilities. Geotechnical investigations would identify underlying
materials and their engineering properties including the presence of unique geotechnical
conditions such as areas with shallow soils over bedrock or the presence of former coal
mining tunnels. Soils unsuitable for use as structural fill, such as expansive soils or
compressible soils, would be replaced such that foundation soils would be able to meet
building code specifications.
See also Chapter 8 for discussion of other potential health effects such as seismic safety
related to the proposed improvements.
3.7.2 No Action Alternative
Under the No Action Alternative, PSE’s existing maintenance activities and programs would
continue. No utility line or facility construction is likely and there would be no additional loss
of vegetation or disturbance to animals from new permanent structures. However, there will
be continued loss or disturbance of vegetation as a result of PSE’s Transmission Vegetation
Management Program; trees would be trimmed, managed with herbicides or removed under
existing transmission lines to limit vegetation to low-growing height species.
The types of conservation measures PSE expects to implement to achieve its goals would
occur on customers’ properties. No permanent impacts are likely from operation since new
infrastructure would be minimal and not require substantial clearing or result in other habitat
impacts.
CHAPTER 3 January 2016 3 -18 EARTH
PHASE 1 DRAFT EIS
Under the No Action Alternative, PSE would use Corrective Action Plans instead of building
new infrastructure to address risk in the near term. With no new improvements, there would
be no operational impacts related to geologic and seismic hazards. However, it is possible
that PSE would implement new technologies and there would be continued maintenance
activities. These would likely represent very minor physical improvements that would have
negligible potential geologic and seismic hazard impacts.
3.7.3 Alternative 1: New Substation and 230 kV Transmission Lines
Following construction, the new facilities could be subject to or contribute to impacts from
erosion, slope instability, seismic hazards, liquefaction, unstable soils, and ground vibrations.
However, with proper facility design measures in accordance with regulatory requirements
discussed earlier and appropriate maintenance, the potential for these impacts would be
minor for the substation and as described for each transmission line option below.
Option A: New Overhead Transmission Lines 3.7.3.1
Under this option, a minimum of 18 miles of new overhead transmission lines would be
constructed. As noted above, the transmission lines would be constructed in accordance with
the standards outlined by NESC, FERC, NERC, and ASCE Manual No. 74. In areas of
common utility corridors, coordination with other utility providers would be conducted as
appropriate. Site-specific geotechnical investigations would be required to define the
underlying engineering properties and identify any geotechnical hazards that may be present.
Geotechnical engineering methods, such as use of engineered fill or foundation design, would
be used to ensure that the effects of any identified hazards are minimized and impacts during
operation would be minor.
Option B: Existing Seattle City Light 230 kV Transmission 3.7.3.2
Corridor
This option includes rebuilding the Seattle City Light SnoKing-Maple Valley 230 kV
transmission line and constructing a new transmission substation. The three potential sites for
the new substation, referred to as Vernell, Westminister, and Lakeside, are all located within
areas that are not identified as landslide or seismic hazard areas but are within areas
considered an erosion hazard (Figure 3-1). Of note, the Lakeside substation is located
relatively close to the Seattle Fault trace and therefore could potentially be subject to higher
ground shaking hazards. However, site-specific geotechnical investigations would identify
any geologic or seismic hazards such as unstable soils, liquefaction, landslides, or others and
provide geotechnical engineering recommendations to minimize any adverse effects. Impacts
would be minor with implementation of geotechnical recommendations in accordance with
regulatory requirements.
Option C: Underground Transmission Lines 3.7.3.3
Placement of the new transmission lines underground removes many of the geotechnical
considerations for safe design such as structural loading and seismic ground shaking. In
general, buried improvements perform well during a seismic event, although they can be
subject to damage from liquefiable soils, if present. Sand boils or lateral spreading, both
related to liquefaction, can cause substantial damage in underground improvements if not
January 2016 CHAPTER 3 EARTH 3-19
PHASE 1 DRAFT EIS
designed appropriately. However, as mentioned above, all improvements including
underground transmission lines would require geotechnical investigations to determine the
geotechnical engineering properties of site-specific materials prior to construction.
Engineering approaches such as treatment of liquefiable soils or replacement with engineered
fills can reduce these potential impacts such that they would be considered minor.
Option D: Underwater Transmission Lines 3.7.3.4
Once completed, underwater transmission lines would generally be expected to perform very
well in an earthquake event, although they could be susceptible to liquefaction hazards if not
designed appropriately. However, with incorporation of geotechnical recommendations in
accordance with regulatory requirements, potential impacts would be reduced to minor
levels.
3.7.4 Alternative 2: Integrated Resource Approach
Alternative 2 includes energy efficiency methods, end-user strategies, and small-scale
distributed generation improvements (gas turbines, anaerobic digesters, and others) that
would require less new construction than Alternatives 1 or 3. There would still be some
relatively large-scale facilities such as the battery storage and peak generation plants and any
future improvements after the end of the 10-year target period when additional solutions are
required to address future growth. These facilities would have seismic considerations similar
to substation expansion under Alternative 1. As a result, operational impacts would generally
be the same as Alternative 1. Conformance with industry standards and regulatory
requirements, including building code requirements enforced by local jurisdictions and the
UTC, would ensure that geotechnical and seismic hazards are identified and design plans
developed to minimize adverse effects from these hazards to minor levels.
Energy Efficiency Component 3.7.4.1
Energy efficiency strategies would not involve much new construction. Impacts related to
earth resources would be negligible.
Demand Response Component 3.7.4.2
Demand response is an end-use strategy that pertains more to customer usage patterns and
requires little construction of new infrastructure. Impacts related to earth resources would be
negligible.
Distributed Generation Component 3.7.4.3
On-site energy generation could involve the construction of gas turbines, anaerobic digesters,
reciprocating engines (e.g., diesel generators), microturbines, and fuel cells. In general, these
on-site facilities would entail relatively small footprints. Similar to Alternative 1, new
facilities would require compliance with existing regulatory requirements. As a result, there
would be little likelihood for these improvements to result in adverse effects related to earth
resources, and the potential impacts would be considered minor.
CHAPTER 3 January 2016 3 -20 EARTH
PHASE 1 DRAFT EIS
Energy Storage Component 3.7.4.4
Energy storage units would consist of relatively large battery sites constructed on sites
approximately 6 acres in size (Strategen, 2015). The battery sites would receive geotechnical
evaluations to identify any site-specific hazards and geotechnical recommendations to ensure
that the new improvements can withstand the anticipated new loadings (i.e., weight of the
batteries and appurtenances). Incorporation of geotechnical recommendations including site
preparation methods and foundation design would ensure that any identified geologic hazards
are minimized, resulting in minor impacts.
Peak Generation Plant Component 3.7.4.5
Simple-cycle gas-fired generators would be installed at existing substations within the
Eastside and would require substation expansion at each location. Similar to energy storage
sites, but at a much smaller scale (footprint is 2,000 square feet); generator sites would
receive geotechnical evaluations to identify any site-specific hazards and recommendations to
ensure that the new improvements can withstand the anticipated new loadings (i.e., weight of
the batteries and appurtenances). Incorporation of geotechnical recommendations including
site preparation methods and foundation design would ensure that any identified geologic
hazards are minimized, resulting in minor impacts.
3.7.5 Alternative 3: New 115 kV Lines and Transformers
Alternative 3 involves the most new construction and covers the widest area of the
alternatives considered. These new improvements would likely encounter a range of
geotechnical and seismic hazards that would be identified in site-specific geotechnical
investigations. Similarly, the proposed transmission line from Lake Tradition to Berrydale
would also encounter a range of geotechnical and seismic hazards such as the seismic hazard
areas (liquefaction) associated with the Cedar River floodplain.
As noted in Chapter 2, five substations would require complete rebuilds and expansion for
this alternative including Sammamish, Lakeside, Talbot Hill, Clyde Hill, and Hazelwood.
The Sammamish and Hazelwood substations are adjacent to a mapped landslide hazard area.
The Lakeside and Hazelwood substations are adjacent to mapped erosion hazards. In
addition, the Lakeside substation is relatively close to the Seattle Fault. The remaining two
substations, Talbot Hill and Clyde Hill, are not within or near any identified hazard areas.
The location of these substations relative to hazard areas does not necessarily preclude the
feasibility of developing the improvements in a way that minimizes any hazards that may be
present. With incorporation of regulatory requirements such as NESC 2012 and NERC/FERC
standards and requirements, the proposed improvements would be designed and constructed
to minimize hazards such as seismic ground shaking, liquefaction, and unstable soils. As a
result, the potential impacts would be minor.
January 2016 CHAPTER 3 EARTH 3-21
PHASE 1 DRAFT EIS
3.8 WHAT MITIGATION MEASURES ARE AVAILABLE
FOR POTENTIAL IMPACTS TO EARTH RESOURCES?
3.8.1 Construction Measures
Use of the following measures during construction would reduce or minimize the potential
for erosion, slope failure, unsuitable soils, or settling impacts for all alternatives that involve
earthwork:
• Avoid construction on steep slopes, known and potential landslide zones, and areas
with organic or liquefiable soils, where feasible.
• Use appropriate shoring during construction.
• Use erosion and runoff control measures, including retention of vegetation,
replanting, ground cover, etc.
• Comply with relevant state and local critical areas codes and other applicable
requirements.
• Dispose of soils at approved disposal sites.
• Coordinate with other utility providers, as appropriate, to determine how best to
avoid or minimize any impacts. PSE would work with other utility service providers
during design of the project to coordinate the placement of new facilities and ensure
protection of other utilities.
• Conduct settlement and vibration monitoring, as applicable, during construction to
identify potential adverse conditions to critical structures and local facilities.
If site-specific earth impacts are identified during future review of individual projects,
additional measures to reduce or minimize those impacts may be identified.
3.8.2 Operation Measures
Use of the following measures during operation would reduce or minimize the potential for
erosion, slope failure, unsuitable soils, or settling impacts for all alternatives that involve
earthwork:
• Monitor all improvements for changes in conditions such as cracking foundations,
slumping slopes, or loss of vegetative cover.
• Implement inspection and maintenance programs for all improvements to ensure
consistent performance and stability.
• Comply with relevant state and local critical areas codes.
If changes are identified during future inspection and monitoring of conditions, additional
measures to reduce or minimize those impacts may be identified.
CHAPTER 3 January 2016 3 -22 EARTH
PHASE 1 DRAFT EIS
3.9 ARE THERE ANY CUMULATIVE IMPACTS TO EARTH
RESOURCES AND CAN THEY BE MITIGATED?
Although the entire region is a seismically active area, geologic and soil conditions vary
widely within a relatively short distance. Other projects in the area would also be required to
adhere to the same Washington state and local building codes as the Energize Eastside
Project, which would reduce the risk to people and property in the region. While future
seismic events cannot be predicted, adherence to federal, state, and local programs,
requirements, and policies pertaining to building safety and construction would limit the
potential for injury or damage. Therefore, the Energize Eastside Project, combined with past,
present, and other foreseeable development in the area, would not result in a cumulatively
significant impact by exposing people or structures to risks related to geologic hazards, soils,
or seismic conditions.
3.10 ARE THERE ANY SIGNIFICANT UNAVOIDABLE
ADVERSE IMPACTS TO EARTH RESOURCES?
While damage and potential injury or death from a significant seismic event is never
completely avoidable, the probability is substantially reduced when new improvements are
constructed in accordance with current seismic standards and building code requirements that
incorporate the most recent scientifically based design standards. As a result, there would be
no probable significant adverse impacts related to earth resources under any of the
alternatives analyzed.
January 2016 CHAPTER 3 EARTH 3-23
PHASE 1 DRAFT EIS
CHAPTER 4. GREENHOUSE GAS
EMISSIONS
4.1 HOW WERE GREENHOUSE GAS EMISSIONS IN THE
COMBINED STUDY AREA EVALUATED?
This chapter evaluates greenhouse gas (GHG) emissions, a
component of air quality, at a programmatic level. GHG
emissions are inventoried as part of GHG reduction efforts
to minimize climate change. Unlike air pollutant
emissions, which have local or regional effects, GHG
emissions contribute to cumulative carbon dioxide (CO2)
concentrations on a global scale.
Because the Phase 1 Draft EIS is programmatic and is not
a project-level analysis, it is not possible to quantify
differences among alternatives with regard to GHG given
the lack of detail about materials and sources that would be
used. However, this chapter provides a qualitative
comparison to indicate the likely range of impacts among
the alternatives. This analysis is conducted in light of the
fact that Washington State regulations (Revised Code of
Washington Chapter 80.80) address GHG emissions from
baseload electrical generation and direct utilities to
consider both achievement of GHG emission limits and
economic impacts to ratepayers.
The EIS Consultant Team used available data for carbon
sequestration to estimate GHG contributions associated
with vegetation removal during construction, and to
compare how the loss of CO2 absorption would relate to
state and federal reporting thresholds for GHGs. Likewise,
available data for lifecycle GHG emissions were used to
estimate GHG contributions associated with traditional and
non-wire technologies (such as demand response
components included in Alternative 2) for electricity transmission.
Continuous emissions from operation of stationary sources such as peak generation plants are
qualitatively considered. It is not possible to quantify these emissions without specific data
on the operational characteristics of such sources.
This chapter describes GHG emissions, carbon sequestration, and lifecycle emissions.
Greenhouse Gas Emissions
Key Findings
The primary differences among
alternatives with regard to
GHGs are the degree to which
trees would need to be
removed (resulting in a loss of
carbon storage or
sequestration) and the lifecycle
GHG cost of materials from
which the projects would be
constructed.
Construction of new overhead
lines that require new corridors
and a larger amount of clearing
(Alternative 1, Option A, and
Alternative 3) could result in
significant impacts. However,
impacts could be mitigated to
a less-than-significant level
through engineering controls,
purchase offsets, vegetation
replacement, or offset
acquisition.
Peak generation plants
(Alternative 2, Option D) have
the potential to generate
operational GHG emissions,
resulting in a moderate impact.
January 2016 CHAPTER 4 GREENHOUSE GAS EMISSIONS 4-1
PHASE 1 DRAFT EIS
4.1.1 Greenhouse Gases Defined
Gases that trap heat in the atmosphere are referred to as greenhouse gases (GHGs) because,
like a greenhouse, they capture heat radiated from the earth. The accumulation of GHGs has
been identified as a driving force in global climate change. Definitions of climate change
vary among regulatory authorities and the scientific community. In general, however, climate
change can be described as the changing of the earth’s climate caused by natural fluctuations
and human activities that alter the composition of the global atmosphere.
The principal GHGs of concern include the following:
• Carbon dioxide (CO2);
• Methane (CH4);
• Nitrous oxide (N2O);
• Sulfur hexafluoride (SF6);
• Perfluorocarbons (PFCs); and
• Hydrofluorocarbons (HFCs).
Electric utilities, including PSE, often use SF6 in electric equipment at substations, because of
its effectiveness as an insulating gas.
Each of the principal GHGs has a long atmospheric lifetime, existing in the atmosphere for
one year to several thousand years. In addition, the potential heat-trapping ability of each of
these gases varies significantly. For example, CH4 is 28 times as potent as CO2 at trapping
heat, while SF6 is 23,500 times more potent than CO2 (IPCC, 2013). The ability of these
gases to trap heat is called global warming potential (GWP).
In emissions inventories, GHG emissions are typically reported in terms of metric tons of
CO2 equivalents (CO2e). CO2e are calculated as the product of the mass emitted of a given
GHG and its specific GWP. While CH4 and N2O have much higher GWPs than CO2, CO2 is
emitted in such vastly higher quantities that it accounts for the majority of GHG emissions in
CO2e, both from residential developments and human activity in general.
The primary human activities that release GHGs include combustion of fossil fuels for
transportation, heating, and electricity; agricultural practices that release CH4, such as
livestock production and decomposition of crop residue; and industrial processes that release
smaller amounts of gases with high global warming potential such as SF6, PFCs, and HFCs.
Deforestation and land cover conversion have also been identified as contributing to global
warming by reducing the earth’s capacity to remove CO2 from the air and altering the earth’s
albedo (surface reflectance), thus allowing more solar radiation to be absorbed.
4.1.2 Carbon Sequestration
Terrestrial carbon sequestration is the process in which atmospheric CO2 is taken up into
plants or soil and subsequently “trapped.” Terrestrial sequestration can occur through
planting trees, restoring wetlands, land management, and forest fire management. This
Conventionally, GHGs have
been reported as CO2
equivalents (CO2e). CO2e takes
into account the relative
potency of GHGs other than
CO2 and converts their
quantities to an equivalent
amount of CO2.
CHAPTER 4 January 2016 4 -2 GREENHOUSE GAS EMISSIONS
PHASE 1 DRAFT EIS
analysis focuses on the terrestrial sequestration associated specifically with trees and shrubs,
as related to the proposed project.
Trees and shrubs act as both carbon sinks and carbon
sources. Vegetation can act as a carbon sink by absorbing
CO2 from the atmosphere, releasing oxygen through
photosynthesis, and retaining the carbon within the
vegetation. Trees also act as a carbon source when they are
dying and decomposing; the carbon that was stored in the trees is released and reacts with
oxygen in the air to form CO2. Younger trees that are growing rapidly can store more carbon
in their leaves than older trees. However, the total amount of carbon sequestered annually by
healthy, large trees is greater than younger trees because the greater number of leaves
compensates for the lower productivity of larger trees (USDA, 2011; N.L. Stephenson et al.,
2014).
Trees suffering from disease will slow and eventually arrest the process of photosynthesis,
thus limiting the ability of the affected tree to act as a carbon sink. Therefore, maintaining
healthy trees keeps carbon stored in trees; however, some landscape maintenance activities
result in GHG emissions (USDA, 2011). For example, water use, fertilizer use, exhaust from
gas- and diesel-powered landscape equipment, and vehicle trips for maintenance crews result
in CO2 emissions.
4.1.3 Lifecycle Emissions
Although there is no regulatory definition for lifecycle emissions, the term is generally used
to refer to all emissions associated with the creation and existence of a project, including
emissions from the manufacture and transportation of component materials, and even from
the manufacture of the machines required to produce those materials. However, since it is
impossible to accurately estimate the entire chain of emissions associated with any given
project, lifecycle analyses have limited effectiveness in assessing emissions for this SEPA
analysis.
The federal Council on Environmental Quality (CEQ) has updated its Draft Guidance for
Greenhouse Gas Emissions and Climate Change Impacts, which makes no reference to
lifecycle emissions (CEQ, 2014). CEQ recommends that agencies rely on basic National
Environmental Policy Act (NEPA) principles and consider all reasonably foreseeable effects
that may result from proposed actions, using reasonable temporal and spatial parameters,
rather than engaging in analyses that focus on speculative emissions (CEQ, 2014).
However, the CEQ recognizes that proposed land and resource management actions
evaluated under NEPA can result in both carbon emissions and carbon sequestration.
Agencies should compare net GHG emissions and changes in sequestered carbon that are
relevant in light of the proposed actions and timeframes under consideration. Agencies have
substantial experience estimating GHG emissions and sequestration, and numerous tools and
methods are available. CEQ encourages agencies to use quantitative tools when it would be
useful for informing decision-makers and the public. When a quantitative analysis would not
be useful, a qualitative analysis should be completed, and an agency should explain its basis
for doing so.
A carbon sink is a natural
environment that absorbs more
CO2 than it releases.
January 2016 CHAPTER 4 GREENHOUSE GAS EMISSIONS 4-3
PHASE 1 DRAFT EIS
4.2 WHAT ARE THE RELEVANT PLANS, POLICIES, AND
REGULATIONS?
Air quality in the Puget Sound region is regulated and enforced by federal and state
agencies—the U.S. Environmental Protection Agency (EPA) and Washington State
Department of Ecology (Ecology). Several local study area communities have plans or
policies addressing GHG emissions. King County provides overarching guidance policy for
the region on GHGs and climate change through implementation of its Strategic Climate
Action Plan, discussed below.
4.2.1 U.S. Environmental Protection Agency
The EPA is the federal agency responsible for implementing the Clean Air Act (CAA). The
U.S. Supreme Court ruled on April 2, 2007, that CO2 is an air pollutant as defined under the
CAA, and that the EPA has the authority to regulate emissions of GHGs.
On December 9, 2009, the EPA Administrator signed two distinct findings regarding GHGs
under Section 202(a) of the CAA, which states that the EPA Administrator should regulate
and develop standards for “emission[s] of air pollution from any class or classes of new
motor vehicles or new motor vehicle engines, which in [its] judgment cause, or contribute to,
air pollution which may reasonably be anticipated to endanger public health or welfare.” The
final rule was effective January 14, 2010. The rule addresses two distinct findings:
Endangerment Finding and Cause or Contribute Finding.
Under the Endangerment Finding, the Administrator found that the current and projected
concentrations of the six key GHGs (CO2, CH4, N2O, HFCs, PFCs, and SF6) in the
atmosphere threaten the public health and welfare of current and future generations. Under
the Cause or Contribute Finding, the Administrator found that the combined emissions of
these GHGs from new motor vehicles and new motor vehicle engines contribute to GHG
pollution, which threatens public health and welfare.
4.2.2 Washington State Department of Ecology
At the state level, in December 2010, Ecology adopted Chapter 173-441 Washington
Administrative Code – Reporting of Emissions of Greenhouse Gases. This rule institutes
mandatory GHG reporting for the following:
• Facilities that emit at least 10,000 metric tons of GHGs per year in Washington; or
• Suppliers of liquid motor vehicle fuel, special fuel, or aircraft fuel that supply
products equivalent to at least 10,000 metric tons of CO2 per year in Washington.
In 2007, voters in Washington passed Initiative 937, the Energy Independence Act. The
Energy Independence Act requires electric utilities in Washington, serving at least 25,000
retail customers, to use renewable energy and energy conservation in serving those
customers. There are 17 utilities which qualify under the Act, including Puget Sound Energy,
which provide 81 percent of the electricity sold to retail customers in Washington State.
CHAPTER 4 January 2016 4 -4 GREENHOUSE GAS EMISSIONS
PHASE 1 DRAFT EIS
4.2.3 King County
Regionally, King County recently released its 2015 Strategic Climate Action Plan (SCAP),
which is a comprehensive update to the 2012 SCAP (King County, 2015). The SCAP is King
County’s blueprint for climate action. It provides a resource for county decision-makers,
employees, and the general public to learn about the County’s climate change commitments.
King County has committed to reduce countywide sources of GHG emissions, compared to a
2007 baseline, by 25 percent by 2020, 50 percent by 2030, and 80 percent by 2050 (King
County, 2015).
4.2.4 City Governments
Of the 12 cities in the combined study area, 8 have signed
the U.S. Conference of Mayors Climate Protection
Agreement1, which promotes participation of U.S. cities in
the goals of the Kyoto Protocol (U.S. Conference of
Mayors, 2007). Most of these cities have integrated GHG
reduction goals into their comprehensive plans, and/or a
specific climate plan, which identify and develop targets,
strategies, policies, and regulations to limit the
community’s impact on climate change.
Signatories of the U.S. Conference of Mayors Climate
Protection Agreement seek to reduce GHG emissions by 7
percent from 1990 levels. This has resulted in the creation
of climate action plans at the municipal level that
inventory baseline GHG emissions and suggest improvements in government operations and
throughout the community that can assist the cities with meeting their reduction goals.
More recently, King County implemented the King County-Cities Climate Collaboration
(K4C). King County and 11 cities (Bellevue, Burien, Issaquah, Kirkland, Mercer Island,
Redmond, Renton, Seattle, Shoreline, Snoqualmie, and Tukwila), representing 75 percent of
the county’s population base, have partnered to coordinate and enhance the effectiveness of
local government climate and sustainability actions. There are three shared K4C
commitments that parallel the Conference of Mayors.
1. Collaborating through the Growth Management Planning Council, Sound Cities
Association, and other partners to adopt countywide GHG emissions reduction
targets, including mid-term milestones needed to support long-term reduction goals;
2. Building on King County’s commitment to measure and report on countywide GHG
emissions by sharing this data between cities and partners, establishing a public
dashboard for tracking progress, and using the information to inform regional climate
action; and
1 Cities include Bellevue, Clyde Hill, Issaquah, Kirkland, Redmond, Renton, Sammamish, and Yarrow Point.
The Kyoto Protocol is an
international agreement linked
to the United Nations
Framework Convention on
Climate Change, which
commits its Parties by setting
internationally binding emission
reduction targets. The Protocol
places a heavier burden on
developed nations and was
adopted in Kyoto, Japan, on
December 11, 1997, and
entered into force on February
16, 2005. The United States
never ratified the protocol.
January 2016 CHAPTER 4 GREENHOUSE GAS EMISSIONS 4-5
PHASE 1 DRAFT EIS
3. Developing and adopting near-term and long-term government operational GHG
reduction targets that support countywide goals, and implementing actions to reduce
each local government’s GHG footprint.
4.2.4.1 City of Bellevue
The City of Bellevue formally joined K4C in August 2014 and has taken action on all of the
three shared K4 commitments to date. The City’s climate actions to date include the
following:
1. In 2007 Bellevue joined over 1,000 cities nationwide in signing the Mayors’ Climate
Protection Agreement, establishing a target to reduce communitywide and municipal
emissions to 7 percent below 1990 emissions by 2012. Bellevue did not reach this
goal.
2. Bellevue formally completed an emissions inventory for the interim years 2006 and
2011, and established a baseline for 2001.
3. Bellevue Department Directors agreed to a renewal of the Environmental
Stewardship Initiative Strategic Plan (2013 - 2018).
4. Since 2012, Bellevue has measured GHG emissions on a public dashboard (called
Scope 5) that uses transparent emission factors and could be used to report to the
Climate Disclosure Project if desired with some additional resources.
5. In July 2014 Bellevue and other cities adopted GHG emission reduction targets of 25
percent by 2020, 50 percent by 2030, and 80 percent by 2050, compared to a 2007
baseline.
6. In November 2014 Bellevue entered into a community energy reduction campaign,
the Georgetown University Energy Prize (GUEP), which awards a $5 million prize to
the small or medium sized U.S. city that can save the most residential and municipal
energy over a two year period. The Community Energy Efficiency Plan is guiding
Bellevue’s energy reduction efforts.
Additionally, the City of Bellevue addresses climate change and GHG emissions reductions
by promoting resources available to residents through PSE (City of Bellevue, 2015). In
addition, the City implemented “Solarize Bellevue,” a campaign to reduce the cost of solar
electricity for Bellevue residents and businesses. The City has also pursued the following six
natural resource conservation projects:
• Electric vehicle charging stations;
• Replacement of 90 gas vehicles in the City fleet with hybrids;
• Traffic demand management services for Bellevue businesses and residents;
• Retrofit of lighting fixtures at recreation facilities;
CHAPTER 4 January 2016 4 -6 GREENHOUSE GAS EMISSIONS
PHASE 1 DRAFT EIS
• Home energy reports for residents, in partnership with PSE and the C-7 New Energy
Partnership;2 and
• Sustainability web portal, an information and education tool.
4.2.4.2 City of Kirkland
The City of Kirkland addresses climate change and GHG emissions primarily by reducing
emissions associated with government operations. Similar to Bellevue, the City of Kirkland
also purchases green power from PSE for “a substantial percentage of its operations” and
encourages its residents to do the same in partnership with PSE and the C-7 New Energy
Partnership. The City also has a similar “Solarize Kirkland” program. The City recycles food
waste, uses paper products with recycled content, and created a commute trip reduction
program to meet GHG reduction goals.
4.2.4.3 City of Redmond
The City of Redmond ratified a climate action implementation plan in September 2014. The
plan addresses climate change by reducing GHG emissions associated with transportation,
heating or cooling buildings, reducing waste production, restoring natural resources, and
educating the public about climate change and encouraging actions that reduce impacts on
the environment. The plan suggests that comprehensive inventories and assessments of GHG
emissions associated with government operations as well as emissions associated with the
community are to be conducted (City of Redmond, 2013). GHG inventories were collected
from 2008 through 2011 for different City operations and sectors of the community as a
whole.
4.2.4.4 City of Renton
The City of Renton completed a GHG inventory in 2011. The City proposes the following
actions to achieve the Mayors Climate Protection Agreement target (City of Renton, 2011)
• Conducting energy audits on all City buildings;
• Implementing energy efficiency management and performance monitoring systems;
• Targeting efficiency upgrades on energy-intensive buildings;
• Installing motion sensor-controlled lighting in all municipal building spaces;
• Decreasing the amount of water that needs to be treated (such as through low impact
development techniques);
• Minimizing water demand through conservation measures;
• Increasing the efficiency of equipment to treat, store, and transport water;
• Purchasing the most fuel-efficient City vehicles; and
2 In 2010, seven cities in King County, Washington — known as the C-7 New Energy Partnership — joined
with PSE and energy management software company OPOWER to help nearly 100,000 residents reduce
their home energy consumption. The C-7 New Energy Partnership includes the Cities of Bellevue,
Issaquah, Kirkland, Mercer Island, Redmond, Renton and Sammamish.
January 2016 CHAPTER 4 GREENHOUSE GAS EMISSIONS 4-7
PHASE 1 DRAFT EIS
• Creating policies for employees to limit idling and use the most fuel-efficient
vehicles whenever possible.
Since 2011, the City has not updated its GHG inventory.
4.2.4.5 City of Sammamish
In 2011, the City of Sammamish published a sustainability strategy that suggested that
reductions in GHG emissions could be achieved through the following:
• Reducing City energy use to 3 percent below 2007 consumption rates by 2012, in
alignment with the U.S. Conference of Mayors Climate Protection Agreement;3
• Investigating municipal purchase of green power from PSE’s Green Power program
by applying savings from energy conservation to purchasing green power;
• Increasing use of transportation alternatives to single-occupancy and/or fossil-fueled
vehicles for City staff commutes and work-related travel, and promoting use of
transportation alternatives by the public;
• Reducing energy used by non-City building operations, including residential
dwellings, businesses and industry; and
Since 2011, the City has not updated its GHG inventory.
4.2.5 Puget Sound Energy
In its Greenhouse Gas Policy Statement (2015), PSE identifies the following specific, near-
term strategies that it continues to pursue:
1. Ongoing development and investment in PSE’s customer energy efficiency program;
2. Pursuit of a diverse energy portfolio mix of resources including renewable generation
that will lower PSE’s GHG emissions consistent with least-cost planning principles;
3. Customer or community-based generation of renewable energy;
4. Opportunities to reduce GHG emissions with partners in the utility industry, local
communities, and state and national governments;
5. Ongoing development and investment in PSE’s green fleet and low emission vehicle
programs;
6. Customer choice through the Green Power and Carbon Balance programs to reduce
their carbon footprint while supporting local projects;
7. Transparency with PSE’s GHG emissions footprint reporting; and
8. Coordination with customers to help them minimize their GHG emissions footprint.
3 The City of Sammamish is a signatory of the U.S. Conference of Mayors Climate Protection Agreement,
which calls for reducing emissions by 7 percent less than 1990 levels by 2012. Because the City was not
incorporated until 2000, this objective calls for reducing emissions by 3 percent of 2005 emissions levels
(City of Sammamish, 2013).
CHAPTER 4 January 2016 4 -8 GREENHOUSE GAS EMISSIONS
PHASE 1 DRAFT EIS
The most recent (2014) inventory of PSE emissions indicates that emissions from all sources
totaled approximately 14.4 million metric tons of CO2; 2,980 metric tons of CH4; 161 metric
tons of N2O; and 0.58 metric tons of SF6. Most of the CO2 emissions were from generated
and purchased electricity (71.1 percent), while the remaining emissions were from natural gas
supply to end users (28.9 percent). For CH4, the majority of emissions were fugitive from
natural gas operations (79.2 percent). Generated and purchased electricity also accounted for
all N2O emissions and all SF6 emissions.
4.3 WHAT IS THE STATUS OF GREENHOUSE GAS
EMISSIONS IN THE COMBINED STUDY AREA?
Ecology estimated that in 2010, Washington produced about 96 million gross metric tons
(about 106 million U.S. tons) of CO2e (Adelsman, 2014). Sources of GHG emissions in the
state are shown in Figure 4-1.
Figure 4-1. Sources of GHG Emissions in Washington State
King County last inventoried countywide GHG emissions for the year 2012. Community
consumption-based emissions (which include some lifecycle emissions associated with food
consumption within the county but grown elsewhere) totaled 55 million metric tons of CO2e
(King County, 2015).
The City of Bellevue updates its GHG inventory yearly. Emissions remained virtually equal
to 2007 levels across the whole community in 2012. As of 2013, municipal emissions from
City operations were reduced 21 percent compared to 2007. The City has not reached its
Mayors Climate Protection Agreement target (Resolution 7517) to reduce emissions to 7
percent below 1990 levels by 2012 (City of Bellevue, 2015).
In 2009, the Renton community generated an estimated 1,216,300 metric tons of CO2e.
Transportation contributed the largest share of these GHG emissions (49 percent), followed
by commercial (21 percent) and residential (20 percent). Solid waste accounted for a small
portion (0.3 percent) of total community GHG emissions. It is unknown whether the City
achieved the goals in the Mayors Climate Protection Agreement.
The City of Kirkland updates its GHG inventory for government operations annually and
those associated with the city as a whole every 3 years. A community inventory is not
January 2016 CHAPTER 4 GREENHOUSE GAS EMISSIONS 4-9
PHASE 1 DRAFT EIS
available at this time (City of Kirkland, 2013). As of 2012, municipal emissions from City
operations were reduced 10 percent compared to 2005; however, the City has not reached its
Mayors Climate Protection Agreement target (Resolution 7517) to reduce emissions to 7
percent below 1990 levels by 2012.
None of the other cities in the combined study area have
publicly available GHG inventory estimates.
4.4 HOW WERE POTENTIAL
IMPACTS TO GREENHOUSE
GAS EMISSIONS ASSESSED?
The potential loss of carbon sequestration from tree
removal is based on sequestration rates of the Climate
Registry. This analysis compares the associated change in
GHG emissions for each alternative to the State of
Washington GHG reporting thresholds. A qualitative
discussion of lifecycle emissions associated with each
project alternative is also included. Lifecycle GHG
emissions are roughly estimated based on publically
available research data. Emissions from the operation of
construction equipment are also qualitatively discussed
relative to each of the other project alternatives.
4.5 WHAT ARE THE LIKELY CONSTRUCTION IMPACTS
RELATED TO GREENHOUSE GAS EMISSIONS?
4.5.1 Construction Impacts Considered
The alternatives could generate GHG emissions from the operation of vehicles and
equipment (off-road equipment, vendor and hauling truck trips, and construction worker
trips), lifecycle emissions from construction materials (e.g., GHGs generated at the batch
plant during production of concrete used in foundations or street work), and from release of
sequestered GHGs as a result of tree removal. While vegetation could be replanted in cleared
transmission alignment corridors, replanting was not included in the assessment of
sequestration impacts in order to provide a worst-case estimate. Additionally, construction
materials would have lifecycle emissions associated with their procurement. Project-related
GHG emissions from construction would be temporary and would not represent a continuing
burden on the statewide inventory. Both GHG emissions from construction equipment and
lifecycle emissions are somewhat speculative at the programmatic level so a general
qualitative comparison among the alternatives and options is provided.
The Climate Registry is a
nonprofit collaboration
between North American
states, provinces, territories,
and Native Sovereign Nations
to record and track the
greenhouse gas emissions of
businesses, municipalities and
other organizations. The
Climate Registry's Board of
Directors is made up of 31
states of the USA, 13
provinces/territories of
Canada, six states of Mexico,
and three Native Sovereign
Nations.[1] The data is to be
independently verified to
ensure accuracy, however
participation by organizations
is voluntary.
CHAPTER 4 January 2016 4 -10 GREENHOUSE GAS EMISSIONS
PHASE 1 DRAFT EIS
This chapter conservatively quantifies and assesses impacts from losses of carbon
sequestration according to the following criteria:
Minor – Project would result in construction-related GHG emissions below the State of
Washington reporting threshold 4 of 10,000 metric tons.
Moderate – If the project would result in construction-related GHG emissions at or above
the State of Washington reporting threshold of 10,000 metric tons in a given year but would
implement best management practices 5 to reduce GHG emissions.
Significant – If the project would result in construction-related GHG emissions at or above
the State of Washington reporting threshold of 10,000 metric tons in a given year and would
not implement best management practices to reduce GHG emissions, or would result in
construction-related GHG emissions at or above 25,000 metric tons in a given year even if
BMPs are implemented.
4.5.2 No Action Alternative
The No Action Alternative would not result in construction activities or changes to
maintenance activities. While conductor replacement could occur under the No Action
Alternative, GHG emissions associated with truck operations and fabrication of new
conductors would be negligible. Similarly, there would be no change in energy efficiency
improvements implemented to achieve PSE’s conservation goals, which involves a negligible
amount of construction.
4.5.3 Alternative 1: New Substation and 230 kV Transmission Lines
Construction impacts are discussed below for each transmission line option. Construction of
the substation would be the same under each option and occur simultaneously. Therefore,
substation construction is considered as part of each option.
4.5.3.1 Option A: New Overhead Transmission Lines
GHG Emissions from Construction Vehicles and 4.5.3.1.1
Equipment
Construction truck trips, off-road equipment, and worker trips would generate GHG
emissions. The equipment likely to be used for construction under Alternative 1, Option A is
presented in Appendix B. Most of this equipment would operate on diesel fuel which has an
emission factor of 10.15 kilograms of CO2 per gallon.
Of all the options under Alternative 1, Option A would potentially have the shortest
construction period (approximately 12 to 18 months). Installing transformers under Option A
would be performed concurrently with the transmission line and poles. Consequently,
although Option A would involve a relatively large amount of construction equipment as
4 In practice, the reporting threshold applies to emissions from a facility and not to temporary construction
activities. However it is being applied in this EIS to assessment of construction impacts as a tool for
determining relative significance.
5 Best management practices to minimize GHG emissions could take the form of a number of measures,
depending on whether it is a construction-related emission or an operational emission source.
January 2016 CHAPTER 4 GREENHOUSE GAS EMISSIONS 4-11
PHASE 1 DRAFT EIS
indicated in Appendix B, its relatively short duration would result in lower direct
construction GHG emissions than those associated with Option C, and emissions would
likely be similar to Options B and D.
Lifecycle GHGs 4.5.3.1.2
The primary material resources required for Alternative 1, Option A are concrete for pier and
transformer foundations, steel or laminated wood poles for towers, and conductors. Of these
materials, concrete is likely the most GHG-intensive to produce. Production of 1 cubic meter
of concrete generates approximately 101 kilograms (222 pounds) of CO2 (Kjellsen et al.,
2005) which accounts for cement production, aggregate production, water, and transport.
With an alignment of approximately 18 miles and a typical spacing between poles of 1,000
feet, approximately 100 pole foundations would need to be installed. Assuming caisson
foundations 35 feet deep and 6 feet in diameter, each foundation would require
approximately 6 cubic meters of concrete, yielding a minimum GHG estimate for all towers
of 60.6 metric tons of CO2. This value is a rough estimate for comparative purposes only and
is not intended for use as a component of a GHG emission inventory.
Loss of Sequestered CO2 (Tree Removal) 4.5.3.1.3
Removal of existing vegetation would result in the loss of sequestered (stored) CO2 as well as
the loss of continued sequestration in the future by this vegetation. If a new corridor is used,
there would be more intensive vegetation removal than other options. The amount of
sequestered CO2 per unit area (expressed as metric tons of CO2 per acre) depends on the
specific vegetation type. Table 4-1 presents CO2 sequestration values from the California
Climate Action Registry (now known as the Climate Action Registry).6 As shown in the
table, trees can sequester the largest amount of CO2 per acre compared to other types of
vegetation.
Table 4-1. CO2 Sequestration by Vegetation Type
Land Use Sub-Category CO2 Sequestration
(metric tons CO2/ acre)
Forest Land Scrub 14.3
Trees 111
Cropland -- 6.20
Grassland -- 4.31
Source: CAPCOA, 2013
Using an existing 115 kV corridor for Alternative 1, Option A could require up to an
additional 50 feet of lateral clearing along the length of the alignment. This would result in
removal of up to 44 acres of forested land under a worst-case scenario which could result in
up to 4,900 metric tons of CO2 sequestration losses (loss of active CO2 intake by trees acting
6 Data from the CAR Forest Protocol and Urban Forest Research Tree Carbon Calculator are not used
since their main focus is annual emissions for carbon offset considerations. As such they are designed to
work with very specific details of the vegetation that are not available at a SEPA level of analysis.
CHAPTER 4 January 2016 4 -12 GREENHOUSE GAS EMISSIONS
PHASE 1 DRAFT EIS
as a carbon sink). This would not exceed the state’s GHG reporting threshold and would be a
minor impact with respect to GHG emissions.
Assuming a new right-of-way alignment of approximately 18 miles and a maximum 150-
foot-wide clear zone under a worst-case scenario, up to 327 acres could be cleared under
Option A if the corridor had 100% tree coverage. Because most likely corridors include
existing rights of way or other utility corridors, an average tree coverage of 40 percent
throughout the project alignment was considered a conservative assumption (see Chapter 6).
With this assumption a worst-case estimate of up to approximately 131 acres of forested land
could be removed under Option A, which could result in up to 14,500 metric tons of CO2
sequestration losses (loss of active CO2 intake by trees acting as a carbon sink). This estimate
exceeds that of Alternative 1, Option C (Underground Transmission Lines), below, due to the
substantially wider corridor needed for overhead lines. This impact would exceed the state’s
GHG reporting threshold and, without best management practices or mitigation, it would be a
significant adverse impact with respect to GHG emissions. Installation of the new
transformer at a new or expanded substation would be unlikely to meaningfully contribute to
further loss of CO2 sequestration. It should be noted that, unlike Option C, trees could be
replanted along the corridor under Option A after construction of the utility lines.
4.5.3.2 Option B: Existing Seattle City Light 230 kV Transmission
Corridor
GHG Emissions from Construction Vehicles and 4.5.3.2.1
Equipment and Lifecycle GHGs
Alternative 1, Option B would require a complete rebuild of the Seattle City Light lines,
including replacing most of the existing structures. However, some of the existing structures
may be adequate and not require replacement, thus reducing the amount of construction
equipment and materials needed. Construction duration would be somewhat longer than
Option A: up to 24 months for overhead lines with concurrent substation construction.
Construction-related GHG impacts would likely be somewhat higher than those described
above for Option A.
Loss of Sequestered CO2 (Tree Removal) 4.5.3.2.2
While Alternative 1, Option B could require a complete rebuild of the Seattle City Light
lines, including replacing most of the existing structure, the land for these structures within
the SCL right-of-way would already have largely been cleared. Therefore, the impacts from
loss of sequestration described for Option A would not occur, or would be substantially less.
However, this option would require a segment of new transmission to connect the SCL line to
the Lakeside substation. The exact length of that alignment is not known, but the proximity
of the Lakeside substation to the line suggests it would be approximately 1 mile or less,
meaning the impact would be approximately 800 metric tons of CO2 sequestration losses.
This would be a minor impact with respect to GHG emissions.
January 2016 CHAPTER 4 GREENHOUSE GAS EMISSIONS 4-13
PHASE 1 DRAFT EIS
4.5.3.3 Option C: Underground Transmission Lines
GHG Emissions from Construction Vehicles and 4.5.3.3.1
Equipment
The equipment involved for construction under Alternative 1, Option C is presented in
Appendix B. Most of this equipment would operate on diesel fuel which has an emission
factor of 10.15 kilograms of CO2 per gallon.
Of all the options under Alterative 1, underground transmission line construction would have
the longest construction period (approximately 28 to 36 months). Construction for the
transformer installations under Option C would be performed concurrently with the
transmission line. Additionally, excavation and removal of soils throughout the construction
route would require many more truck trips than the other options. Consequently, direct
construction-related GHG emissions of Option C would be the greatest of all the options.
Lifecycle GHGs 4.5.3.3.2
The primary material required for Alternative 1, Option C would be concrete to construct an
outermost barrier in the excavated trench and for access vaults. With an alignment corridor
length of 18 miles and assuming a trench width of 5 feet, and a concrete layer of 3 feet
encasing the lines, approximately 40,400 cubic meters of concrete would be required,
yielding approximately 4,080 metric tons of CO2. This value is a rough estimate to be used
for comparative purposes only, not as a component of a GHG emission inventory.
Loss of Sequestered CO2 (Tree Removal) 4.5.3.3.3
With an alignment corridor length of 18 miles and a cleared work area of 30 feet for a new
corridor under a worst-case scenario, Alternative 1, Option C could require a clearance area
up to 66 acres in total, assuming tree coverage of 40 percent throughout the project
alignment. The reduced width of the cleared work area compared with Option A results in a
relatively lower loss of sequestered CO2. Conservatively assuming that lost sequestration
would entirely be in the form of forestland (trees), Option C could result in over 7,300 metric
tons of lost CO2 sequestration. This projected loss would not exceed the State’s GHG
reporting threshold and would be considered a minor impact with respect to GHG emissions.
However, unlike Option A, replacement trees could not be planted in the corridor after
construction due to the buried utilities. If an existing utility or roadway corridor were used,
there may be no clearing necessary and thus no CO2 sequestration losses, although there
could be some losses of street trees. It is also possible that only a portion of the line would be
placed underground, and the rest would be as described for Option A or B. On a per mile
basis, Option B would have less CO2 sequestration losses than Option A, while use of the
SCL corridor under Option B would have lower CO2 sequestration losses than Option C.
4.5.3.4 Option D: Underwater Transmission Lines
GHG Emissions from Construction Vehicles and 4.5.3.4.1
Equipment
The types of construction equipment likely to be needed under Alternative 1, Option D are
presented in Appendix B. Most of this equipment would operate on diesel fuel which has an
emission factor of 10.15 kilograms of CO2 per gallon. Installing underwater transmission
lines would have the shortest construction period of approximately 8 months. Consequently,
CHAPTER 4 January 2016 4 -14 GREENHOUSE GAS EMISSIONS
PHASE 1 DRAFT EIS
although Option D would involve a relatively large amount of construction equipment as
indicated in Appendix B, its relatively short duration would result in direct construction GHG
emissions less than those associated with Option A, Option B or Option C.
Lifecycle GHGs 4.5.3.4.2
The primary material required for Alternative 1, Option D would be concrete for cable
landings and for foundations of any poles needed for transition to on-land transmission.
There would be two cable landing points requiring a modest amount of concrete for the
landing vaults. An estimate of concrete volume is speculative at this programmatic review,
but Option D is likely to have the lowest lifecycle emissions of the four Alternative 1 options
or any of the other alternatives.
Loss of Sequestered CO2 (Tree Removal) 4.5.3.4.3
East-west connections to Talbot Hill or Lakeside substation and to Sammamish substation
necessary under Alternative 1, Option D would require vegetation removal and associated
loss of sequestration impacts. Assuming new right-of-way would be necessary for all three
connections, with a combined alignment of approximately 7.8 miles and a maximum 150-
foot-wide clear zone (worst-case), up to 143 acres could be cleared under Option D.
Conservatively assuming an average tree coverage of 40 percent throughout the project
alignment (see Chapter 6), a worst-case estimate of up to 57 acres of forested land could be
removed under Option D.
Option D could result in a loss of up to 6,330 metric tons of CO2 sequestration. This would
not exceed the state’s GHG reporting threshold. Installation of the new transformer at a new
or expanded substation would be unlikely to meaningfully contribute to further loss of CO2
sequestration.
Installation of cable landing points may require clearing of wetlands on the lake shore, but
this would be unlikely to contribute meaningfully to loss of sequestration and would be
considered a minor impact with respect to GHG emissions.
4.5.4 Alternative 2: Integrated Resource Approach
4.5.4.1 Energy Efficiency Component
Energy efficiency improvements would entail implementing accelerated measures and
incentives to reduce demand. This component would not involve infrastructure
improvements, changes to maintenance activities, or construction of new or relocated
maintenance yards. Consequently, energy efficiency improvements would have no impact
with regard to direct GHG emissions, lifecycle GHG emissions, or sequestration loss.
4.5.4.2 Demand Response Component
Demand response measures would entail implementing measures to reduce and/or shift
electrical demand and would not involve infrastructure improvements, changes to
maintenance activities, or construction of new or relocated maintenance yards. Consequently,
implementation of demand response systems would have no impact with regard to direct
GHG emissions, lifecycle GHG emissions, or sequestration loss.
January 2016 CHAPTER 4 GREENHOUSE GAS EMISSIONS 4-15
PHASE 1 DRAFT EIS
4.5.4.3 Distributed Generation Component
GHG Emissions from Construction Vehicles and 4.5.4.3.1
Equipment
Construction of distributed generation facilities could result in direct GHG emissions, such as
from gas turbines or diesel reciprocating engines. The amount of GHG released would vary
with the type and number of facilities constructed, making it speculative to quantify direct
construction emissions at this programmatic level of analysis. In addition, the number of
hours that such facilities would need to operate in direct response to the need identified by
PSE for the Energize Eastside Project would be relatively small (see Chapter 7 for additional
discussion of energy consumption). Therefore, the quantities of GHG generated to address
the project need would be negligible.
Lifecycle GHGs 4.5.4.3.2
The lifecycle emissions for distributed generation facilities would be speculative to quantify
without a precise estimate of the number and size of facilities to be constructed. However,
lifecycle emissions could be greater than those associated with either Option A, Option B, or
Option D of Alternative 1 primarily due to the potential for ongoing combustion of natural
gas associated with peak generation plants or other combustion turbines or engines.
Loss of Sequestered CO2 (Tree Removal) 4.5.4.3.3
Loss of sequestration would depend on the condition of sites selected for distributed
generation facilities (i.e., whether the sites are currently vegetated and the type of vegetation
present). Since most of this equipment is anticipated to be on or adjacent to buildings, the
amount of vegetation removed would be negligible.
4.5.4.4 Energy Storage Component
GHG Emissions from Construction Vehicles and 4.5.4.4.1
Equipment
Like the distributed generation component, construction of the energy storage component
would generate GHG emissions that are not possible to quantify at this programmatic level of
analysis. However, given that a battery storage facility would resemble an open yard of
containers, a surface parking lot represents a reasonable approximation of such a land use.
Construction of a 10-acre surface parking lot could generate an estimated 302 metric tons of
CO2. This assumes a 6-month construction period, no demolition, and cut and fill balanced
on-site 7. This would be considered a minor impact with respect to GHG emissions.
Lifecycle GHGs 4.5.4.4.2
Lifecycle GHG emissions associated with battery storage technologies can be high because
some of the materials used in their manufacture are scarce. For example, the energy demand
for the manufacture of new lithium-ion batteries for plug-in hybrid motor vehicles has been
estimated to be 1,700 megajoules of primary energy to produce 1 kilowatt-hour of lithium-
ion battery capacity (Samaras et al., 2008). This energy demand would also have lifecycle
emissions that would be in addition to the materials used for construction of any required
structures. However, battery lifecycle emissions can be reduced by as much as 70 percent
7 Calculated using the California Emissions Estimator Model Version 2013.2.2.
CHAPTER 4 January 2016 4 -16 GREENHOUSE GAS EMISSIONS
PHASE 1 DRAFT EIS
with recycling techniques that would be reflected in operational emissions as batteries are
replaced.
4.5.4.1 Peak Power Generation Component
This component would involve installing three 20 MW generators at existing substations
within the Eastside. These could be any type of generator but the most likely type would be a
simple-cycle gas-fired generator. Construction of three gas-fired simple-cycle generators
would be similar to a substation, including trenching to access upgraded natural gas, water,
and wastewater utility lines. Construction would occur within or adjacent to existing PSE
substations over 12 months. Construction emissions would be similar to those identified
above for the battery storage component, approximately 750 metric tons of CO2.
4.5.5 Alternative 3: New 115 kV Lines and Transformers
4.5.5.1 GHG Emissions from Construction Vehicles and Equipment
and Lifecycle GHGs
Alternative 3 would develop 115 kV transmission lines that would require a more narrow
clearing area than a 230 kV alignment, from 40 feet up to 100 feet wide under a worst-case
scenario, compared with 150 feet for the 230 kV corridor. However, the 115 kV alternative
would require up to 60 miles of transmission alignment, resulting in more vegetation
removal. Alternative 3 construction would have the second longest construction period
(approximately 24 to 28 months). Substation improvements would occur simultaneously with
construction along the alignment. GHG emissions from construction equipment and
potentially loss of sequestration would incrementally increase, but these contributions would
be negligible compared to work for the alignment. Consequently, the longer construction
duration for Alternative 3 would result in higher direct construction GHG emissions than
those associated with Alternative 1. Additionally the increased number of support towers
would require more concrete, and lifecycle emissions would also be greater than
Alternative 1.
4.5.5.2 Loss of Sequestered CO2 (Tree Removal)
Assuming a new right-of-way alignment of approximately 60 miles and a 40-foot-wide clear
zone under a worst-case scenario, Alternative 3 could require clearing up to 291 acres.
Conservatively assuming an average tree coverage of 40 percent throughout the project
alignment (see Chapter 6), a worst-case estimate of up to 116 acres of forested land could be
removed under Alternative 3, resulting in up to 12,900 metric tons of CO2 sequestration
losses (loss of active CO2 intake by trees acting as a carbon sink). This is a worst-case
estimate because it conservatively assumes that additional clearance would be required over
the entirety of the existing alignment. This impact would exceed the state’s GHG reporting
threshold and, without best management practices or mitigation, would be a significant
adverse impact with respect to GHG emissions.
January 2016 CHAPTER 4 GREENHOUSE GAS EMISSIONS 4-17
PHASE 1 DRAFT EIS
4.6 HOW COULD OPERATION OF THE PROJECT
AFFECT GREENHOUSE GAS EMISSIONS?
4.6.1 Operation Impacts Considered
Operational GHG impacts would result primarily from employee vehicle trips to maintain the
new facilities. However, some distributed energy components and peak generation plants
would have operational emissions associated with fuel combustion.
4.6.2 No Action Alternative
Demand response programs, the primary component of the No Action Alternative, would
implement operational measures to reduce and/or shift electrical demand. No infrastructure
improvements, changes to maintenance activities, or new or relocated maintenance yards
would be required. No new employee vehicle trips are envisioned under the No Action
Alternative. Consequently there would be no operational GHG impacts associated with the
No Action Alternative.
4.6.3 Alternative 1: New Substation and 230 kV Transmission Lines
Potential operational GHG impacts associated with all of the Alternative 1 options would
result from vehicle travel associated with occasional maintenance of the electrical facilities.
Such trips would be infrequent and would not result in appreciable GHG emissions.
Therefore, Alterative 1 would have a minor impact with regard to operational GHG
emissions.
4.6.4 Alternative 2: Integrated Resource Approach
4.6.4.1 Energy Efficiency and Demand Response Components
Energy efficiency and demand response components would not involve infrastructure
improvements, changes to maintenance activities, or new or relocated transformers,
substations, or maintenance yards. These components would have no impact with regard to
operational GHG emissions. There may be an indirect beneficial impact because conservation
measures would reduce energy demand and associated GHG emissions associated with the
mix of energy generation.
4.6.4.2 Distributed Generation Component
Distributed generation facilities could result in operational GHG impacts that would vary
with the type and magnitude of facility. Because of the limitations of distributed generation
systems described in Chapter 2, the Phase 1 evaluation assumed that these sources would
contribute minimally to addressing the identified deficiency in capacity by 2024.
Certain types of distributed generation facilities, specifically gas turbines and reciprocating
engines, have the potential to generate operational GHG emissions associated with fuel
combustion, which would vary depending on the frequency of operation, size of engine, and
type of fuel used. For this analysis, it is assumed that distributed generation facilities could
result in negligible to moderate adverse impacts.
CHAPTER 4 January 2016 4 -18 GREENHOUSE GAS EMISSIONS
PHASE 1 DRAFT EIS
4.6.4.3 Energy Storage Component
Operation of a battery storage facility would be similar to that of a small office building, with
worker vehicle trips and vendor trips to perform periodic replacement of degraded cells. Such
trips would be infrequent and not result in appreciable GHG emissions. Lifecycle GHG
Emissions associated with battery storage technologies can be high because some of the
materials used in their manufacture are scarce. For example, the energy demand for the
manufacture of new lithium-ion batteries for plug-in hybrid motor vehicles has been
estimated to be 1,700 megajoules of primary energy to produce 1 kilowatt-hour of lithium-
ion battery capacity (Samaras et al., 2008). This energy demand would have lifecycle
emissions. However, battery lifecycle emissions can be reduced by as much as 70 percent
with recycling techniques that would be reflected in operational emissions as batteries are
replaced. Therefore, the energy storage component would have a minor impact with regard to
operational GHG emissions.
4.6.4.4 Peak Power Generation Component
This component would involve operation of three 20 MW generators at existing substations
within the Eastside, likely simple-cycle gas-fired generators called peak generation plants. In
2013, the overall mix of fuels used by PSE to provide all electricity to all of its customers
was led by hydropower (32 percent), followed closely by coal, natural gas, and wind energy
(PSE, 2015). While hydropower is considered to be renewable and to have negligible GHG
emissions, coal is a relatively carbon-intensive energy source, producing between 205 and
230 pounds of CO2 per million British thermal units (Btus). Natural gas is relatively less
carbon intensive, producing 117 pounds of CO2 per million Btu. Because peak generation
plants would be powered by natural gas, their operational GHG emissions would be similar
to the average of overall carbon intensity of PSE’s current mix of resources.
Peak generation plants would be operated to provide power at peak demand times to reduce
the demands on the transmission system. These plants would also need to be operated for
maintenance purposes at least monthly (typically permitted for weekly operation of an hour,
or 50 hours per year). Because operational GHG emissions would be a function of
operational frequency (including peak power demand situations), quantitative estimates of
operational GHG emissions would be speculative, but they are likely to be the highest of any
distributed generation source. Such power plants can be required to report GHG emissions
pursuant to Chapter 173-441 Washington Administrative Code – Reporting of Emissions of
Greenhouse Gases. This could be considered a moderate GHG impact, warranting mitigation.
4.6.5 Alternative 3: New 115 kV Lines and Transformers
Potential operational impacts of 115 kV overhead power lines would be the same as those
identified above for maintenance-related vehicle trips for 230 kV power lines. Such trips
would be infrequent and not result in appreciable GHG emissions. Therefore, Alterative 3
would have a minor impact with regard to operational GHG emissions.
January 2016 CHAPTER 4 GREENHOUSE GAS EMISSIONS 4-19
PHASE 1 DRAFT EIS
4.7 WHAT MITIGATION MEASURES ARE AVAILABLE
FOR POTENTIAL IMPACTS TO GREENHOUSE GAS
EMISSIONS?
If gas turbines or reciprocating engines are selected as distributed energy components, air
quality permits may require installation of a fuel flow meter to restrict the use of fuel and
associated GHG emissions over a given time period. A vegetation replacement program
could be implemented to reduce sequestration losses under Alternative 1, Option A, and
Alternative 3 to a moderate level. Alternative 1, Options B and C would also involve
vegetation clearing for alignments, although to a lesser extent. Additionally, carbon credits
may be purchased to offset operational emissions generated by permitted sources.
4.8 ARE THERE ANY CUMULATIVE IMPACTS TO
GREENHOUSE GAS EMISSIONS AND CAN THEY BE
MITIGATED?
By definition, GHG impacts are cumulative impacts. The sum of all emission sources
throughout the globe drives planet-wide GHG concentrations that result in climate change.
Emission sources exceeding 10,000 metric tons per year of CO2e are required to report their
emissions to the state; they could be considered cumulatively considerable contributions and
may require mitigation. There are two project elements that could potentially result in GHG
emissions of this magnitude. The first is operational emissions from gas turbines or
reciprocating engines, if they are selected as distributed energy components.
The second potentially significant adverse GHG impact would involve the substantial loss of
sequestration associated with clearing for transmission alignments that could accompany
Alternative 1, Option A, and Alternative 3. Given the substantial size of areas to be cleared
and the relatively high tree canopy cover in the area, loss of sequestration could exceed
10,000 metric tons annually. A vegetation replacement program could be implemented to
reduce sequestration losses to a moderate level.
4.9 ARE THERE ANY SIGNIFICANT UNAVOIDABLE
ADVERSE IMPACTS TO GREENHOUSE GAS
EMISSIONS?
There would be no significant and unavoidable adverse impacts related to GHG emissions
associated with any of the project alternatives, with implementation of mitigation measures.
Potential significant impacts from operational GHG emissions of gas turbines or
reciprocating engines, if they are selected as distributed energy components, could be
mitigated by a combination of engineering controls and the purchase of offsets. Significant
impacts related to sequestration losses associated with clearing activities for transmission
alignments that could accompany Alternative 1, Option A, and Alternative 3 could be
mitigated to a less-than-significant level through vegetation replacement or offset acquisition.
CHAPTER 4 January 2016 4 -20 GREENHOUSE GAS EMISSIONS
PHASE 1 DRAFT EIS
CHAPTER 5. WATER RESOURCES
5.1 HOW WERE WATER RESOURCES IN THE
COMBINED STUDY AREA EVALUATED?
Several sources of information were used to characterize
the known and likely water resources in the combined
study area (Alternatives 1, 2, and 3 as depicted on Figure
1-4 in Chapter 1), including the following federal, state,
and local sources:
• Washington Department of Ecology (Ecology)
Water Quality Assessment and 303(d) List
(Ecology, 2014);
• U.S. Fish and Wildlife Service (USFWS) National
Wetlands Inventory (USFWS, 2015);
• U.S. Department of Agriculture (USDA) Natural
Resources Conservation Science (NRCS) Web Soil
Survey (NRCS, 2015);
• Critical areas GIS datasets for the study area
communities;
• Technical reports; and
• Aerial imagery.
These information sources indicate the resources that may
be present in the combined study area. No field surveys
were performed for this programmatic analysis, because
the specific location of project elements has not been
determined. The description of resources includes streams,
rivers, lakes, ponds, wetlands, and groundwater, as well as
stormwater and floodplains.
The resource protection policies and requirements of the study area communities that could
apply to the project were identified, primarily from comprehensive plans and critical area
regulations and codes. These requirements are described, along with federal and state
regulations for protection and management of water resources. The applicability of
regulations would be determined based on project design and location.
Water Resources Key
Findings
Alternatives 1 and 3 could
cause potentially significant
impacts if overhead or
underground lines are placed
in streams, lakes, wetlands or
their buffers; however,
limitations imposed by
regulatory agencies and
avoidance of these resources
would reduce this potential to
minor or moderate.
Construction of an underwater
transmission line (Alternative 1,
Option D) could result in
temporary and localized
impacts to Lake Washington,
including local turbidity,
potential disturbance of
contaminated sediment,
underwater noise, and impacts
to the shoreline.
All of the alternatives have the
potential to cause minor water
quality impacts due to
construction site runoff,
dewatering discharge, or
accidental spills.
January 2016 CHAPTER 5 WATER RESOURCES 5-1
PHASE 1 DRAFT EIS
5.2 WHAT ARE THE RELEVANT PLANS, POLICIES, AND
REGULATIONS?
Policies and regulations to manage and protect surface and groundwater resources are
administered by federal, state, and local governments. The primary agencies and their
regulations that might apply to this project are summarized in Tables 5-1 and 5-2. The
applicability of these regulations would be determined based on project design and location.
Table 5-1. Surface Water Resource Protection Framework
Regulatory
Program or Policies
Regulatory
Agency Regulated Activities/Program
Federal
Dredge and Fill
Requirements and
Section 10 Permit for
Work in Navigable
Waters - Clean Water
Act (33 CFR1 Part 320)
Section 404
U.S. Army Corps of
Engineers (Corps)
Any project that proposes discharging
dredged or fill material into Waters of the
United States must obtain a Section 404
permit. Case law and rule amendments
have specifically defined Waters of the
United States (40 CFR 230.3). Case-by-
case analysis is required to confirm
applicability of this law to surface waters
such as rivers, streams, ditches, lakes,
ponds, territorial seas, and wetlands.
Any work in, over, or under navigable
Waters of the United States requires a
Section 10 permit. The purpose of Section
10 permitting is to prohibit the obstruction
or alteration of these navigable waters.
Federal Emergency
Management Agency
(FEMA)
Executive Order
12127 merged many
previous separate
disaster-related
responsibilities into
FEMA.
Public Law 100-707
amended the
Disaster Relief Act of
1974 (Public Law 93-
288) - creating the
system by which a
presidential disaster
declaration of an
emergency triggers
financial and physical
assistance through
FEMA.
Federal law requires that all local
governments review and appropriately
manage land uses in floodways and
floodplains to prevent increased flooding.
CHAPTER 5 January 2016 5 -2 WATER RESOURCES
PHASE 1 DRAFT EIS
Regulatory
Program or Policies
Regulatory
Agency Regulated Activities/Program
State
Water Quality
Certification - Clean
Water Act Section 401
(33 United States Code
1251 et seq.) and
Washington State
Water Pollution Control
Act (Chapter 90.48
RCW1)
Ecology
Ecology issues a Section 401 water quality
certification to applicants receiving a
Section 404 permit from the Corps,
indicating that Ecology anticipates that the
applicant’s project will comply with state
water quality standards and other aquatic
resource protection requirements under
Ecology’s authority. This process is the
mechanism by which Ecology helps ensure
the state’s policy of “no net loss” of
wetlands is implemented. Depending on
the type of Section 404 permit, some 401
permits are preauthorized.
All projects affecting surface waters in the
state, including those that are not subject
to the federal Clean Water Act Sections
404/401, must still comply with the
provisions of the state’s Water Pollution
Control Act.
National Pollutant
Discharge Elimination
System (NPDES) –
Clean Water Act 33
USC Sections 1251 et
seq. and WAC2 197-
11-200 through 240
Ecology and local
governments through
NPDES Municipal
Stormwater Permits
The Environmental Protection Agency has
delegated authority to Ecology. Local
governments are municipal stormwater
permittees (King County, Bellevue, Clyde
Hill, Issaquah, Kirkland, Medina, Mercer
Island, Newcastle, Redmond, Renton, and
Sammamish). The NPDES permit program
controls water pollution by regulating
sources that discharge pollutants into
Waters of the U.S. Different types of
permits are issued for different types of
projects and sites under this program.
All construction projects disturbing more
than 1 acre of land and discharging to
surface water or a conveyance system that
drains to surface waters must obtain
NPDES coverage.
Municipal NPDES permits require local
governments to develop and implement a
stormwater management program to
reduce the contamination of stormwater
runoff and prohibit illicit discharges. Local
governments must ensure development
projects and certain public and private
facility operations comply with the
program.
January 2016 CHAPTER 5 WATER RESOURCES 5-3
PHASE 1 DRAFT EIS
Regulatory
Program or Policies
Regulatory
Agency Regulated Activities/Program
Hydraulic Project
Approval (HPA) – WAC
220-660
Washington State
Department of Fish
and Wildlife (WDFW)
Although primarily intended to address
aquatic species and habitat protection, it
indirectly protects surface water quality by
limiting and regulating activities that can
occur in or discharge to Waters of the
State. The HPA program applies to work
that uses, diverts, obstructs, or changes
the natural flow or bed of any of the salt or
fresh waters of the state. This includes bed
reconfiguration, all construction or other
work waterward, under and over the
ordinary high water line, including dry
channels, and may include projects
landward of the ordinary high water line
(e.g., activities outside the ordinary high
water line that will directly impact fish life
and habitat, such as felling trees into
streams or lakes, bridge maintenance, dike
construction, etc.).
Local
Local Comprehensive
Plans – required under
the State of
Washington Growth
Management Act
(Chapter 36.70A RCW)
King County and all
study area cities
Local government planning policies call for
the protection, preservation, and
enhancement of water resources.
Shoreline Management
Act- Chapter 90.58
RCW
King County and all
study area cities
through authority
delegated by
Ecology
As discussed in Chapter 10, cities and
counties adopt shoreline master programs
that establish allowed uses, buffers,
setback requirements, and mitigation
requirements for regulated waterways. All
cities and counties in Washington are
required by the Shoreline Management Act
to enact shoreline management programs.
Local Critical Area
Ordinances/
Regulations – required
under the State of
Washington Growth
Management Act
(Chapter 36.70A RCW)
King County and all
study area cities
Local governments establish policies and
development guidelines to protect the
functions and values of critical areas (rivers,
streams, lakes, wetlands, floodplains,
aquifer recharge areas, and other). All cities
and counties in Washington are required by
the Growth Management Act to adopt
critical area regulations (RCW 36.70A.060).
Buffers are designated by the local
governments around critical areas to help
protect their functions. The size of the
buffer depends on the classification of the
area, and activities within those buffers are
regulated to further protect the critical area.
CHAPTER 5 January 2016 5 -4 WATER RESOURCES
PHASE 1 DRAFT EIS
Regulatory
Program or Policies
Regulatory
Agency Regulated Activities/Program
Local codes for
floodplain management
(required for
participation in the
Federal Emergency
Management Act Flood
Insurance Rate
Program) including:
King County Code
Chapter 21A.24
Bellevue City Code
Chapter 20.25H
Section IX
Renton Municipal Code
4.3.050
Kirkland Municipal
Code Chapter 21.56
Newcastle Municipal
Code Chapter 18.24
Redmond City Code
Chapter 15.04
King County and all
study area cities
Many of the streams and rivers in the
combined study area have designated 100-
year floodplains, which must be considered
when nearby development is proposed
(Figure 5-1). Study area communities
regulate development in the floodplain to
reduce the impact of flooding on
structures.
1Code of Federal Regulations 2Revised Code of Washington 3Washington Administrative Code
Table 5-2. Groundwater Resource Protection Framework
Regulatory Program or
Policies
Regulatory
Agency Regulated Activities/ Program
State
EPA water pollution control
regulations (Section 431.02
of the Clean Water Act and
corresponding State of
Washington regulations)
Ecology Establishes the mechanism for regulating
discharges of pollutants to groundwater.
Water Quality Standards for
Groundwaters of the State
of Washington (Chapter
173-200 WAC)
Ecology Establishes maximum contaminant
concentrations for the protection of a
variety of beneficial uses of Washington's
groundwater.
Washington Groundwater
Management Areas
(Chapter 173-100 WAC)
Ecology Establishes procedures to designate
groundwater management areas and
procedures for developing groundwater
management programs to protect
groundwater quality.
January 2016 CHAPTER 5 WATER RESOURCES 5-5
PHASE 1 DRAFT EIS
Regulatory Program or
Policies
Regulatory
Agency Regulated Activities/ Program
Washington Well Head
Protection (Chapter 246-290
WAC)
Ecology Establishes the boundaries for each well,
well field, or spring and processes to
manage potable water.
Washington Underground
Injection Control Program
(Chapter 173-218 WAC)
Ecology Protects groundwater quality by regulating
the disposal of fluids into the subsurface.
Washington water rights
regulations (various)
Ecology Establishes a permitting process to allow
applicants to apply water to a specific
beneficial use.
Local
Local Critical Aquifer
Recharge Area ordinances –
GMA RCW 36.70A
Study area
communities
Provides local governments with a
mechanism to classify, designate, and
regulate areas deemed necessary to
provide adequate recharge and protection
for aquifers used as sources of potable
(drinking) water. Most jurisdictions in the
combined study area (except Clyde Hill,
Hunts Point, Yarrow Point, Medina, and
Beaux Arts Village) have identified aquifer
protection zones and/or enacted
groundwater or aquifer protection policies.
These policies are considered when
development is proposed in the vicinity.
5.3 WHAT WATER RESOURCES ARE FOUND IN THE
COMBINED STUDY AREA?
Surface waters in the combined study area consist of wetlands, lakes and ponds, rivers and
streams, and their associated floodplains. The combined study area is located within Water
Resources Inventory Area (WRIA) 8 (the Cedar-Sammamish River watershed) and WRIA 9
(the Duwamish-Green River watershed). The combined study area contains two rivers and
numerous streams, described below under Section 5.3.1. In addition to Lake Washington and
Lake Sammamish, there are several smaller lakes, described under Section 5.3.2. Additional
wetlands and small streams are likely present that have not been mapped, as well as drainage
ditches and other stormwater features that have been added, modified, or diverted over time.
5.3.1 Streams and Rivers
There are about 2,000 mapped streams and rivers in the combined study area (King County,
2015). The major streams and rivers in the combined study area include the Sammamish
River, Cedar River, Bear Creek, Evans Creek, Kelsey Creek, Richards Creek, May Creek,
Coal Creek, and Issaquah Creek (Figure 5-1).
CHAPTER 5 January 2016 5 -6 WATER RESOURCES
PHASE 1 DRAFT EIS
The Sammamish River begins at the northern outlet of Lake Sammamish and empties into the
northern end of Lake Washington. Major tributaries of the Sammamish River in the
combined study area include Bear Creek and Evans Creek. A number of streams flow into
Lake Sammamish, including Issaquah, Tibbetts, Pine Lake, and Laughing Jacobs creeks. The
Cedar River is part of the Cedar River – Lake Washington drainage and empties into Lake
Washington at its southern end. In addition to the Sammamish and Cedar rivers, a number of
smaller streams flow into Lake Washington, including Kelsey Creek, May Creek, and Coal
Creek.
5.3.2 Lakes and Ponds
The two largest lakes in the combined study area are Lake Washington and Lake
Sammamish. Smaller lakes in the area include Lakes Bellevue, Kathleen, and McDonald; and
Larsen, Phantom, Pine, Beaver, and Tradition lakes (Figure 5-1).
Lake Washington is bordered on the east by unincorporated King County, Kirkland,
Bellevue, Medina, Newcastle, and Renton, and the Towns of Beaux Arts Village, Hunts
Point, and Yarrow Point (Figure 5-1). The Alternative 1 and 3 study areas are in the direct
vicinity of Lake Washington or Lake Sammamish. The smaller lakes in Issaquah,
Sammamish, and King County are only within the Alternative 3 study area.
Most of Lake Washington’s shoreline is developed with residences and urban development.
The lake has been highly altered and its water level regulated through the Lake Washington
Ship Canal, operated by the U.S. Army Corps of Engineers (USACE, 2012a, 2012b). As
mentioned previously, the Cedar River and the Sammamish River drain into Lake
Washington, which eventually drains out through the Ship Canal. Portions of Lake
Washington are on Ecology’s 303(d) list as impaired (Category 5) for bacteria,
polychlorinated biphenyls (PCB), 2,3,7,8 TCDD (dioxin), total chlordane, as well as
derivatives of DDT (Ecology, 2015). Site-specific evaluations of potential locations of
contaminated sites will be conducted in Phase 2; however, it has been assumed that
contaminated sediments associated with historical uses and stormwater discharges are also
present in Lake Washington.
Similar to Lake Washington, the shorelines of Lake Sammamish are highly developed for
residential uses, but with large parks (Marymoor Park to the north and Lake Sammamish
State Park to the south (Figure 5-1). Lake Sammamish is bordered on the west by the cities of
Bellevue and Redmond, to the east by Sammamish, and to the south by Issaquah. Portions of
the north and south ends of the lake are also bordered by unincorporated King County.
Portions of Lake Sammamish are also on Ecology’s 303(d) list as impaired (Category 5) for
bacteria and dissolved oxygen (Ecology, 2015). Low -density development typically
surrounds the smaller lakes in the combined study area, although several are surrounded by
recreational areas, and one (Larsen Lake) has both agricultural and recreational uses along its
perimeter.
5.3.3 Wetlands
Wetlands are commonly defined as areas with wetland hydrology (inundated or saturated
most of the year), hydric soils (soils with characteristics affected by the presence of water),
January 2016 CHAPTER 5 WATER RESOURCES 5-7
PHASE 1 DRAFT EIS
and hydrophytic (water-loving) vegetation. Wetlands can be associated with lake edges,
streams, and riparian corridors as well as scattered, low-lying places. They provide a suite of
ecosystem functions and services, such as fish and wildlife habitat, floodwater control,
groundwater recharge, pollutant removal, and others. They also provide economic services
because of their connection to hunting, fishing, agriculture, and recreation. Over 1,000
wetlands have been mapped in the combined study area (King County, 2015). Some of the
larger wetland complexes are found in or adjacent to Phantom and Larsen Lakes; Mercer
Slough; the north and south portions of Lake Sammamish; and adjacent to many of the major
streams and rivers in the combined study area (Figure 5-1).
5.3.4 Floodplains
Floodplains are relatively flat lands adjacent to rivers, streams, and lakes that are subject to
occasional or periodic flooding. Included within the floodplain are the floodway (an area that
carries flood flows) and the flood fringe (areas covered by the flood that do not experience a
strong current). In the event of a flood, floodplains can help to detain debris, sediment, and
water, and reduce damage to surrounding areas. Construction and development activity
within the floodplain reduces the floodway capacity and is regulated, as described in Section
5.2. Floodplains are delineated by the Federal Emergency Management Agency (FEMA),
which also determines the flood risks in areas susceptible to flooding. The 100-year flood is
used as the base flood by FEMA, and it has a 1 percent chance of occurring in each year.
5.3.5 Stormwater
Stormwater runoff comes from any surface that rain or snow can reach (rooftops, paved
areas, bare soil, lawns, etc.). Even natural systems (forests and fields) may release
stormwater. As raindrops reach the ground or as snow melts, water that does not immediately
infiltrate (soak into the soil) moves downhill and accumulates with other rain or meltwater,
eventually reaching surface waters. Stormwater moving over impervious surfaces (rooftops,
paved surfaces, etc.) will continue flowing toward surface waters until it is controlled.
Stormwater may pick up and transport pollutants such as fertilizers, oil, and gasoline and
carry them to surface waters or groundwater. Stormwater also often gathers in increasingly
large amounts as it moves downhill toward surface waters, and if stormwater volumes are not
managed, they can contribute to or cause flooding. Flooding is a public safety issue and can
cause property damage and habitat destruction. Therefore, stormwater is regulated to protect
water quality and to prevent flooding.
CHAPTER 5 January 2016 5 -8 WATER RESOURCES
PHASE 1 DRAFT EIS
Energize Eastside EIS 140548
Figure 5-1
Major Water Resources
SOURCE: King County 2015; ESA 2015; WA Ecology 2014; FEMA 2010;
Kirkland 2015; Redmond 2015; Sammamish 2015; Issaquah 2015;
Newcastle 2015; Renton 2015; Bellevue 2015.
For more info visit www.energizeeastsideeis.org/map-surfacewater
Lake Washington
Lake
Sammamish
Bellevue Sammamish
Issaquah
Renton
Newcastle
RedmondKirkland
Beaux Arts
Medina
Clyde
Hill
Hunts
Point
Yarrow
Point
Mercer
Island
Lake
Bellevue
Larsen
Lake
Phantom
Lake
Pine
Lake
Beaver
Lake
Lake
Kathleen
Lake
McDonald
S
a
m
m
a
mish River
Tradition
Lake
Mercer
Slough
Lakeside
Novelty
Hill
Lake
Tradition
Sammamish
Talbot
Hill
B e a r C r e e k
Kel
seyCreekEvansCreekCoalCreek
Cedar Ri
verMayCreek
Existing
Substations
Roadway
Combined Study
Area Boundary
Lakes and Ponds
Streams and
Rivers
Wetland
FEMA Floodplain
City Limits
Unincorporated
King County
U:\GIS\GIS\Projects\14xxxx\D140548_EastsidePSETransmisisonCoor\MXD\SurfaceWater.mxd
0 2
Miles
Note: This map is for reference only. It is not guaranteed that the information is accurate or complete.
5.3.6 Groundwater
Chapter 3 describes the geologic setting in which groundwater has developed. Groundwater
is water found underground in cracks and spaces in soil, sand and rock. It is stored in and
moves slowly through these geologic formations, which are called aquifers, and can also be
isolated in lenses or pockets below ground. Groundwater is a source of recharge for lakes,
rivers, and wetlands. It supplies drinking water and is also frequently used for irrigation and
in many industrial processes.
Since groundwater is an important source of potable water
in the Pacific Northwest, Washington’s Growth
Management Act requires local governments to protect
aquifers. Most of the aquifer protection areas in the
combined study area are within King County jurisdiction,
with some smaller areas within the city limits of Renton and
Issaquah (King County, 2015). In addition, wellhead
protection areas are found within the cities of Sammamish,
Issaquah, Renton, Newcastle, Bellevue, and Redmond, and
the Towns of Beaux Arts Village and Yarrow Point (King
County, 2015).
Groundwater is also considered from an engineering perspective for development projects.
Project plans must account for the depth and likely volumes of groundwater to ensure
structural stability and avoid flooding related to groundwater. As described in Chapter 3, 25
soil types have been mapped in the combined study area (NRCS, 2015). The soils and their
likely groundwater characteristics are presented in Appendix D.
It is anticipated that recent development (after the NRCS soil mapping occurred) has further
disturbed native soils or groundwater. Depending on the location, type of project, and likely
depth to groundwater and likelihood to encounter it, engineers will conduct site-specific
geotechnical borings confirming actual groundwater conditions and elevations to supplement
existing mapping.
5.4 HOW WERE POTENTIAL WATER RESOURCE
IMPACTS ASSESSED?
The analysis of water resources used project construction methods and criteria for facility
locations described in Chapter 2 to assess whether construction or operation of the action
alternatives could affect surface water and groundwater. The general applicability of water
resource regulations to the project was assessed for each alternative. The analysis considered
the scale of each alternative in determining potential impacts to surface and groundwater
quality, and whether clearing of vegetation, construction grading activities, or other project
actions could alter groundwater or surface waters.
For this analysis, the magnitude of project-related impacts are classified as being minor,
moderate, or significant as follows:
A wellhead protection area is
the surface and subsurface
area surrounding a water well
or well field supplying a public
water system. Within this area,
uses and activities are
regulated to prevent
contamination of the water
supplied by the well or wells.
CHAPTER 5 January 2016 5 -10 WATER RESOURCES
PHASE 1 DRAFT EIS
Turbidity is a measure of
water clarity. It indicates how
much materials suspended in
the water reduce the passage
of light through the water.
Suspended materials could
include soil particles, algae,
plankton, microbes, or other
substances.
(EPA, 2012)
Minor – If project activities would cause temporary alterations or disturbance of water
resources; impacts can be fully mitigated, according to permit requirements; or impacts are
largely avoided by the implementation of best management practices.
Moderate – If project activities would cause permanent alterations to water resources but can
be fully mitigated, according to permit requirements.
Significant – If project activities would cause permanent or net loss of acreage or impairment
of functions that cannot be fully mitigated; noncompliance with applicable water quality
standards; or groundwater contamination that cannot be avoided by construction best
management practices.
5.5 WHAT ARE THE LIKELY CONSTRUCTION IMPACTS
RELATED TO WATER RESOURCES?
5.5.1 Construction Impacts Considered
Although construction details for each alternative have yet to be developed, general
construction activities are understood for these types of projects. A site-specific analysis of
impacts from construction will be completed during Phase 2 of the EIS process. Most of the
alternatives for the proposed project would include vegetation clearing for infrastructure, and
operation of heavy equipment. The scale and proximity of construction activities to water
resources would determine the intensity of potential impacts.
Federal, state, and local regulations that address protection of water resources during
construction are discussed in Section 5.2. Best management practices would be implemented
to control stormwater around the construction sites to avoid erosion and associated
sedimentation in water bodies.
5.5.1.1 Construction Site Runoff
Construction areas would be susceptible to erosion
during rain events as construction, excavation, or grading
activities expose bare soils. Increased sedimentation and
turbidity of project site runoff could occur in surface
waters if erosion is untreated or uncontrolled. Besides
sediment, runoff could also contain other contaminants
such as fuels, oils, hydraulic fluids, and organic
compounds. Significant surface water impacts could be
avoided if construction complies with applicable local
and state permits and best management practices.
Additionally, a Stormwater Pollution Prevention Plan
(SWPPP) and a Construction Stormwater and Erosion Control Plan would be prepared and
implemented, to ensure that measures are in place to protect water quality, prevent erosion
and sedimentation, and manage activities and potential pollutant sources.
January 2016 CHAPTER 5 WATER RESOURCES 5-11
PHASE 1 DRAFT EIS
5.5.1.2 Discharge from Dewatering
Dewatering may be required to remove water that seeps or drains into excavation areas
during construction. Sedimentation tanks would be used to settle soil particles and potentially
filter or treat water pumped from excavation areas. Depending upon the quality and quantity
of the pumped water, it could be discharged onsite, to an upland area for infiltration and/or
filtration or directly to nearby surface waters or to sewer systems. Resulting impacts would
likely be minor as long as projects comply with applicable local and state permits and best
management practices.
5.5.1.3 Accidental Spills or Leaks
Oil, fuel, and other chemicals could inadvertently spill or leak from construction equipment,
leading to contamination of surface waters. Large, uncontrolled spills could potentially flow
to nearby storm drainage systems or seep into groundwater or surface waters. Uncontrolled
spills are expected to be unlikely because Spill Prevention and Control Plans and local and
state permit requirements would be implemented and followed.
5.5.1.4 Impacts to Wetlands, Streams, and Lakes
Wetlands, streams, lakes, and their buffers could be
temporarily altered during construction, potentially leading
to loss of acreage or function. Any such alteration would be
required to comply with applicable regulations and
accompanying mitigation requirements. Temporary periods
of turbidity or disturbance of contaminated sediments could
occur during in-water work, potentially impacting the water
quality of streams or lakes, including offshore and
nearshore environments of Lake Washington. The
implementation of best management practices, and
compliance with local and state permit requirements would
be required to reduce potential water quality impacts.
5.5.1.5 Impacts to Groundwater
Construction activities have the potential to contaminate shallow groundwater resources, as
described above for accidental spill and leaks. In addition, the installation of power poles and
the construction of substations could change or interfere with the flow of shallow
groundwater in adjacent areas, and the compaction of soils along the transmission corridor
could reduce the rate surface water infiltration and groundwater recharge. The
implementation of best management practices would be required as part of complying with
local and state permits. These measures would help to minimize potential water quality
impacts.
5.5.1.6 Potential Pipeline Damage
While unlikely due to measures employed to prevent such accidents, it is possible that the
Olympic Pipeline could be damaged during construction. A pipeline rupture could have
significant adverse effects on surface water and groundwater quality, depending on the
location, size, and length of time of the rupture.
The nearshore environment is
a zone extending waterward
from the shoreline, typically to
a water depth of about 10 feet,
and providing unique habitat
for aquatic species. See
Chapter 6 for a more detailed
description of aquatic habitat.
CHAPTER 5 January 2016 5 -12 WATER RESOURCES
PHASE 1 DRAFT EIS
5.5.2 No Action Alternative
Under the No Action Alternative, PSE’s existing maintenance activities and programs would
continue. No utility lines or facilities would be built; therefore, there would be little or no
additional impacts to water resources.
5.5.3 Alternative 1: New Substation and 230 kV Transmission Lines
Impacts are described according to the major components associated with Alternative 1.
Substation impacts are described first, followed by impacts associated with the transmission
line options. All four options under Alternative 1 would require expansion of an existing
substation (Lakeside) or construction of a new transformer and substation (Vernell or
Westminster) on property already owned by PSE. This would involve the use of heavy
equipment and other ground disturbing activities. If wetlands, streams, or their buffers are
located on or near the substation construction sites, they could be impacted. Depending on
the location of the water resource, impacts could be temporary or permanent. Impacts to
wetlands, streams, or their buffers would require mitigation under applicable regulations. If
facilities are constructed adjacent to water resources but can avoid long term impacts and
comply with all permit requirement, impacts would be minor. Some wetlands or streams
and/or their buffers may be permanently affected, depending on the facility siting process. If
long term impacts cannot be avoided, impacts could be moderate. Impacts would not be
significant due to limitations imposed by regulatory agencies.
Groundwater could be encountered during excavation at substations, depending on location
and depth of the excavation. If groundwater were encountered in construction areas, it would
be managed with isolation or dewatering measures, in accordance with the project
Construction Stormwater and Erosion Control Plan, and other applicable best management
practices. Temporary pumping of excavations could occur if groundwater were present in
large quantities. Pumped water would need to be discharged in compliance with appropriate
regulations to avoid potential turbidity from sediment or hazardous material impacts to
surface waters. Impacts are expected to be minor, given that they would be limited to the
construction period and would be compliant with permit conditions.
As described above, ground disturbance from construction could result in pollutants and
sediments entering stormwater runoff, and an increased short-term risk of impacts to water
resources. Best management practices would be implemented to reduce the potential for these
effects, in accordance with local requirements. Spill prevention plans would also be prepared
to ensure that measures are in place to protect water quality. Therefore, impacts to
groundwater and surface water quality are not anticipated.
5.5.3.1 Option A (New Overhead Transmission Lines) and Option B
(Existing Seattle City Light 230 kV Transmission Corridor)
Construction Site Runoff 5.5.3.1.1.
As discussed in Section 5.5.1.1, no significant surface water impacts are expected from
construction site runoff because construction will be required to comply with applicable local
and state permits, and best management practices would be implemented.
January 2016 CHAPTER 5 WATER RESOURCES 5-13
PHASE 1 DRAFT EIS
Discharge from Dewatering 5.5.3.1.2.
If groundwater is encountered during excavation or drilling for power poles, the area would
be isolated and dewatered as necessary. Pumped water would be discharged in compliance
with appropriate regulations to avoid potential turbidity from sediment or hazardous material
impacts to surface waters.
Accidental Spills or Leaks 5.5.3.1.3.
Equipment used for access, staging, and installing power poles (listed in Appendix B) could
accidently discharge or deposit pollutants, such as hydraulic fluids, fuels or oils into surface
waters unless proper site controls are in place. However, impacts from uncontrolled spills are
expected to be minimal because Spill Prevention and Control Plans and local and state permit
requirements would be implemented.
Impacts to Wetlands, Streams, and Lakes 5.5.3.1.4.
Wetlands and streams and their buffers are located within or adjacent to existing rights-of-
way and are likely to occur in any new corridors for potential new lines. The existing SCL
rights-of-way cross several major streams, including Kelsey, Coal, May, and Richards
Creeks, and the Cedar River, along with the wetlands associated with them. Ground
disturbance from heavy machinery and excavation for the installation of poles for new or
rebuilt overhead transmission lines has the potential to impact these resources. Equipment
could be operated in a manner to avoid wetlands, streams, and their buffers, and new poles
would also be located to avoid these areas, to the extent feasible. However, impacts to some
wetlands, streams, and their buffers are likely to be unavoidable. Mitigation would be
required to comply with applicable regulations. Impacts to water resources would be minor to
moderate; however, impacts would not be significant due to limitations imposed by
regulatory agencies.
Construction could also potentially occur within floodplains around streams, rivers, or lakes
in the combined study area. Facility siting would attempt to avoid construction in these areas,
but they may be difficult to avoid. Compliance with local codes would reduce potential
floodplain impacts, helping to reduce potential impacts. . For example, local codes apply
measures such as not allowing equipment or material to be stored in the floodplain, and
putting strict limits on excavation in floodplain areas (King County Code Chapter 21A.24,
Bellevue City Code Part 20.25H Section IX Part 20.25 E., Renton Municipal Code 4.3.050,
Kirkland Municipal Code Chapter 21.56, Newcastle Municipal Code Chapter 18.24,
Redmond City Code Chapter 15.04). If construction in a floodplain is found to be necessary,
additional mitigation would be required. Because of strict requirements associated with work
in streams, rivers, lakes, and floodplains, construction impacts are expected to be minor.
Impacts to Groundwater 5.5.3.1.5.
As described above, construction activities are expected to have minor impacts on
groundwater, due to the limited areas of excavation required. The size, number, and likely
locations of the power poles would be unlikely to result in an adverse effect on shallow
groundwater flow. Any minor effects would be localized and would need to be evaluated
during design to ensure that groundwater is not redirected in a way that affects structures or
surface waters.
CHAPTER 5 January 2016 5 -14 WATER RESOURCES
PHASE 1 DRAFT EIS
Potential Pipeline Damage 5.5.3.1.6.
The Olympic Pipeline, which parallels one of PSE’s 115 kV transmission lines, could be
damaged during construction under Alternative 1, Option A. Although this is considered
unlikely due to measures that PSE and the pipeline operator employ whenever construction
occurs near the pipeline, a rupture could have significant adverse effects on groundwater
quality and other surrounding water resources depending on the location, size and length of
time of the rupture.
5.5.3.2 Option C: Underground Transmission Lines
Construction Site Runoff 5.5.3.2.1.
As discussed in Section 5.5.1.1, no significant surface water impacts are expected from
construction site runoff because construction will comply with applicable local and state
permits, and best management practices would be implemented.
Discharge from Dewatering 5.5.3.2.2.
This option results in the greatest amount of excavation, and therefore the greatest potential
to encounter groundwater. If groundwater is encountered during excavations to install
underground transmission lines, the area would be isolated and dewatered as necessary.
Pumped water would be discharged in compliance with appropriate regulations to avoid
potential impacts to surface or groundwater resources.
Accidental Spills or Leaks 5.5.3.2.3.
Equipment used for access, staging, and installing the underground transmission lines (listed
in Appendix B) could accidently discharge or deposit pollutants, such as hydraulic fluids,
fuels or oils into surface waters or contaminate groundwater resources unless proper site
controls are in place. However, uncontrolled spills are expected to be minimal since Spill
Prevention and Control Plans and local and state permit requirements would be implemented.
Should spills or leaks occur, groundwater in the vicinity of excavations could be
contaminated.
Impacts to Wetlands, Streams, and Lakes 5.5.3.2.4.
Construction of new underground transmission lines would require trenching and conduit
installation. The installation is expected to use conventional open-cut methods (trenching),
but horizontal directional drilling or other trenchless construction methods could be used to
avoid wetlands, streams, or their buffers. In the event that trenching is proposed through
wetlands, streams, or their buffer areas, the same impacts and regulations described for
Alternative 1, Options A and B would apply. If impacts to wetlands, streams, or their buffers
were limited to the construction period, and were able to be mitigated in accordance with
applicable permit requirements, impacts would be minor. Permanent impacts would be minor
to moderate. Impacts to wetlands, streams, or their buffers that would be mitigated through
compliance with applicable regulations would not be considered significant. Trenching
methods in floodplains or areas of shallow groundwater would have a greater potential of
impacting these resources compared to Options A or B.
January 2016 CHAPTER 5 WATER RESOURCES 5-15
PHASE 1 DRAFT EIS
Impacts to Groundwater 5.5.3.2.5.
Underground transmission lines and associated vaults could adversely affect shallow
groundwater flow, either by penetrating a perched water table, or by laterally blocking flow.
Such effects would be localized and would need to be evaluated during design to ensure that
groundwater is not redirected in a way that affects structures or surface waters. Underground
transmission lines would be designed so no significant impact would result.
Potential Pipeline Damage 5.5.3.2.6.
If the corridor selected for the transmission line is adjacent to the Olympic Pipeline, the risk
of damage to the pipeline from construction of the underground transmission line would be
greater than the other alternatives, due to the much greater extent of excavation necessary for
underground installation. As described for Alternative 1, Option A, a rupture of the pipeline
could significantly affect groundwater quality and other surrounding water resources.
Although the risk would be greater under Option C, the likelihood of a rupture is still
considered low due to measures employed to prevent such accidents.
5.5.3.3 Option D: Underwater Transmission Lines
Construction Site Runoff 5.5.3.3.1.
Stormwater management would be required for any actions on land, as described for the
options above. With its largely underwater components, Alternative 1, Option D would have
fewer upland areas where stormwater would need to be managed during construction.
Site runoff impacts resulting from Option D would most likely occur where the underwater
line would come ashore to connect to overland facilities. Ground disturbed near the lake
shore could lead to erosion of soil, which could be transported into the lake during rain
events. This could lead to localized turbidity in the lake; however, best management practices
required by state and local permits would likely avoid or abate this type of impact.
Potential impacts would also be substantially greater for conventional trenching operations,
than if directional boring methods were used. Trenching would result in greater ground
disturbances, thereby increasing the potential for erosion and turbidity discharges to the lake
and nearshore environment. Best management practices would be implemented to minimize
or eliminate such discharges; however, some localized water quality impacts could occur.
Trenchless equipment such as horizontal directional drilling could be employed to further
minimize potential impacts, if feasible. With either method however, some type of barrier
(sheet or soldier pile barriers and cofferdams) between in-water work areas and the rest of the
lake would likely be installed.
Discharge from Dewatering 5.5.3.3.2.
As described above for the other Alternative 1 options, if groundwater is encountered during
excavations to install power poles or underground transmission lines in the upland portions of
Option D, the area would be isolated and dewatered as necessary. Pumped water would be
discharged in compliance with appropriate regulations to avoid potential impacts to surface
or groundwater resources. However, excavation of nearshore areas for the upland-to-
underwater transition segment, is expected to encounter substantially greater amounts of
groundwater, which is not likely to be manageable with pumping. Therefore, it is expected
CHAPTER 5 January 2016 5 -16 WATER RESOURCES
PHASE 1 DRAFT EIS
that the area would be isolated with a sheet pile cofferdam or soldier pile walls to prevent the
release of sediments or turbid water into Lake Washington. With best management practices
impacts would be minor.
Accidental Spills or Leaks 5.5.3.3.3.
As described for the other Alternative 1 options, equipment used for access, staging, and
installing the above ground or underground portions of transmission lines for Alternative 1,
Option D could accidently discharge or deposit pollutants, such as hydraulic fluids, fuels or
oils into surface waters or contaminate groundwater resources unless proper site controls are
in place. However, uncontrolled spills are expected to be minimal since Spill Prevention and
Control Plans and local and state permit requirements would be implemented.
In addition, equipment needed to install the nearshore and underwater portions of the
transmission line under Option D would have similar or greater potential to impact the
surface water of Lake Washington. During placement of the underwater cable, although
unlikely, it is possible that barges could have leaks or accidents that could spill diesel fuel
into the lake, with potential negative impacts on water quality. However, appropriate best
management practices are expected to minimize or eliminate the potential for spills or leaks.
Any construction on or near the lake would be subject to in-water permit requirements that
strictly control work activities.
Impacts to Wetlands, Streams, and Lakes 5.5.3.3.4.
Alternative 1, Option D would have lower potential to impact wetlands, streams, or buffers
than Options A and B, since a large portion of the line would be underwater. Impacts to
wetlands, streams, and their buffers associated with the shoreline of Lake Washington could
be avoided if the upland-to-underwater transition segment were installed using trenchless
construction methods. If trenchless methods are not practicable, and these areas associated
with the lake could not be avoided, then impacts to wetlands and streams or their buffers
would be mitigated in accordance with permit requirements. If impacts are limited to the
construction period in accordance with all permit requirements, impacts would be considered
minor. Long term impacts that affect the shoreline water resources could be moderate.
Impacts would not be significant due to limitations imposed by regulatory agencies. The
potential for floodplain impacts would be the same as described for Options A and B.
As described in Chapter 2, underwater cables would likely be installed using a barge
designed to dredge and bury the cable 3 to 5 feet below the lake bottom, or laid directly on
the lake bottom in deeper areas. This type of in-water construction would result in localized
turbidity in the vicinity of the construction area. Contaminated sediments, such as petroleum,
metals, and semivolatile and volatile organic compounds, could be located along the cable
alignment, although the siting and design process would include studies to determine this
potential and avoid known or suspected areas of contamination. If contaminated sediments
are disturbed during construction, they could be resuspended into the water column, resulting
in potential impacts to water quality and aquatic habitat.
Best management practices would be used to minimize potential water quality impacts during
in-water work, such as using a temporary sheet pile containment wall or turbidity curtain.
The type and extent of contaminants, if present, would determine if additional or different
January 2016 CHAPTER 5 WATER RESOURCES 5-17
PHASE 1 DRAFT EIS
construction methods should be used. PSE would be required to meet all applicable water
quality standards and in-water work permit conditions. As discussed in Chapter 6,
construction would occur within approved in-water construction windows as determined by
the Washington Department of Fish and Wildlife (WDFW) as part of the permitting process.
In addition, all in-water work would be subject to the requirements of the Corps and Ecology.
If PSE meets regulatory criteria, then impacts to water quality from construction of the
underwater transmission line would be minor.
Impacts to Groundwater 5.5.3.3.5.
As described above, construction activities are expected to have minor impacts on
groundwater, due to the limited areas of excavation required in upland areas. Alternative 1,
Option D would have lower potential to impact groundwater resources because a large
portion of the line would be underwater. The size, number, and likely locations of the upland
power poles would be unlikely to result in an adverse effect on shallow groundwater flow.
Trenching for the underwater line has the potential to alter patterns of upwelling groundwater
in nearshore areas adjacent to hillside seeps or groundwater discharge zones. Groundwater
discharge in these areas supplies cool water to lakeshore spawning salmonids, and supports
longshore transport of sediment. Additional site-specific evaluations would be needed to
determine the potential magnitude of this impact.
Potential Pipeline Damage 5.5.3.3.6.
If the corridor selected for the upland transmission line segments is adjacent to the Olympic
Pipeline, the risk of damage to the pipeline from construction would be similar to those
described above for the other options. However, the potential for such damage would likely
be substantially lower for Alternative 1, Option D, because the upland segments would be
substantially shorter, due to the underwater segment.
5.5.4 Alternative 2: Integrated Resource Approach
The types of impacts described for Alternative 1 would be similar for some of the
components of Alternative 2. The energy storage and peak generation plant components of
Alternative 2 could be similar to transformer/substation work since they would be located at
or adjacent to existing substations. Overall, Alternative 2 has a lower potential for impact to
water resources than Alternative 1 because construction would be smaller in scale (small
projects on individual homes and businesses). Groundwater, floodplains, and stormwater
issues would be handled in the same way as described above for Alternative 1. As a result,
impacts on water resources are anticipated to be minor.
5.5.5 Alternative 3: New 115 kV Lines and Transformers
The type of impacts for this alternative would be the same as those anticipated for Alternative
1, Option A. However, the extension of shared rights-of-way needed for Alternative 3 would
likely be narrower, up to 40 feet, and involve less construction activity than for a 230 kV
transmission line, as components are smaller. However, the transmission corridor for
Alternative 3 would be much longer (60 miles) than Alternative 1, Option A (18 miles), and
thus would have the greatest likelihood of crossing wetlands, streams or their buffers of the
alternatives considered, with resulting potential impacts. If water resources can be largely
CHAPTER 5 January 2016 5 -18 WATER RESOURCES
PHASE 1 DRAFT EIS
avoided during construction, impacts would be minor. If these resources cannot be avoided
impacts would be minor to moderate. Impacts would not be significant due to compliance
with limitations imposed by regulatory agencies.
5.6 HOW COULD OPERATION OF THE PROJECT
AFFECT WATER RESOURCES?
5.6.1 Operation Impacts Considered
Water quality could be affected during the long-term operation of the project if impervious
surface areas and associated surface water runoff are increased, or stored hazardous materials
or chemicals are inadvertently released to surface or ground waters. However, regulations
enacted to protect water resources in the State of Washington, and mitigation measures that
would be required for impacts, make these types of direct losses unlikely to occur.
5.6.2 No Action Alternative
Under the No Action Alternative, PSE’s existing maintenance or repairs of substations and
any underground or overhead distribution lines would continue. No utility line or facility
construction beyond conductor replacement is likely to occur.
As described in Chapter 8, hazardous materials used for ongoing facility operations and
maintenance could reach area surface waters or groundwater if not properly contained or
managed. The oil in distribution transformers on power poles could reach streams, rivers,
lakes, or ponds unimpeded, since poles would be the most likely type of existing
infrastructure to exist in wetlands or buffers, or directly adjacent to these water resources. Oil
spills from maintenance or repair equipment could potentially degrade water quality. The
potential impacts of spilled oil would depend on many factors, including the type and
existing condition of the water resource potentially contaminated; the time of year (wet or dry
season) of the spill; the volume of oil spilled; and the chronic effects of the oil spilled. In
general, because of ongoing maintenance of PSE facilities, the potential for impact to surface
water resources is low, and the potential impact is minor.
5.6.3 Alternative 1: New Substation and 230 kV Transmission Lines
At the new or expanded substation, operation of all four of the options under Alternative 1
would generally have the same types of potential impacts as described above. All four
options would require stormwater management as part of design, depending on the substation
size and location. Impacts to wetlands and streams from operation of the project are expected
to be minor.
Impacts associated with the transmission line options are described below.
5.6.3.1 Option A (New Overhead Transmission Lines) and Option B
(Existing Seattle City Light 230 kV Transmission Corridor)
Once construction is complete, operational impacts would be minimal, associated with minor
vegetation removal and regular upkeep such as painting or cleaning. Access roads for poles
January 2016 CHAPTER 5 WATER RESOURCES 5-19
PHASE 1 DRAFT EIS
and transmission lines would also be maintained; however, impacts to water resources would
likely be minor.
5.6.3.2 Option C: Underground Transmission Lines
Once installed, regular access to the underground transmission line for Alternative 1, Option
C would be limited to regularly scheduled maintenance. However, if an accident should
occur and repairs to the transmission line are needed, there could be impacts to wetlands,
streams, or buffers if the transmission line is adjacent to these water resources. Access to the
line would likely occur through vaults left in place along the alignment, although some
trenching could be required depending on the location and nature of the problem. If impacts
cannot be avoided, as with the initial installation during construction, mitigation for impacts
to wetlands, streams, or their buffers would be required by existing regulations. Impacts to
wetlands, streams, or their buffers would be minor because it is expected that they could be
avoided and any impact fully mitigated.
5.6.3.3 Option D: Underwater Transmission Lines
No permanent impacts on water resources are anticipated for underwater transmission lines in
Lake Washington because access to the underwater transmission line would not be required
once operational. If the cable were damaged by other activities in the lake, it would need to
be repaired or replaced, which would likely involve removal and reinstallation. Impacts
associated with substantial repairs or replacement could be similar to that associated with
initial construction, including localized turbidity during the replacement period.
Underwater transmission lines would require aboveground or underground lines on land to
connect to a substation. Access roads and aboveground vaults would also be needed in
nearshore areas as well as upland areas. Permanent impacts on water resources for
aboveground and underground lines under Alternative 1, Option D would be similar to those
described for Options A and C.
5.6.4 Alternative 2: Integrated Resource Approach
No permanent impacts on water resources would be likely from operation of some
Alternative 2 components since infrastructure would be minimal and likely located on private
properties with a small footprint. As for Alternative 1, stormwater management would be
needed for the energy storage and peak generation plant components of Alternative 2. Some
equipment or facilities could contain hazardous materials (for example, batteries used in
energy storage facilities and transformers with wind turbines for distributed generation
facilities). If these components were to be damaged or leak, that material could reach water
resources, with the same types of impacts described under the No Action Alternative and the
potential impact is minor.
5.6.5 Alternative 3: New 115 kV Lines and Transformers
Operational impacts for Alternative 3 would be similar to those anticipated for Alternative 1,
Option A. Because the corridor proposed for Alternative 3 is longer (60 miles) than
Alternative 1, there is more potential for impacts from maintenance or repair. As previously
noted, these impacts are expected to be minor because all maintenance will be consistent with
applicable permit and regulatory requirements.
CHAPTER 5 January 2016 5 -20 WATER RESOURCES
PHASE 1 DRAFT EIS
5.7 WHAT MITIGATION MEASURES ARE AVAILABLE
FOR POTENTIAL IMPACTS TO WATER
RESOURCES?
A substantial set of federal, state, and local regulations are in place to protect water resources
including surface waters and their buffers, floodplains, and groundwater, and to control
stormwater. Site-specific mitigation measures will be determined by appropriate agencies.
Overall, these regulations require the following:
• Comply with applicable requirements from local, state, and federal regulatory
agencies for all construction affecting water resources directly or indirectly.
• Avoid and minimize impacts to Waters of the U.S. (lakes, wetlands, streams, and
buffers), or provide compensatory mitigation for losses that are approved.
• Control construction within floodplains so that flood risk is not increased and
floodway capacity is not reduced.
• Avoid placing splice vaults in nearshore environments or where wetlands or stream
mouths are present.
• Require trenchless construction for underground and underwater power line
segments.
• Manage stormwater to ensure it is properly detained and treated prior to release.
• Bore underneath water resources to avoid temporary and permanent impacts to those
areas when feasible.
• Design, install, and maintain underwater pipelines consistent with applicable
regulatory requirements and standards set by the Washington Utilities and
Transportation Commission and the U.S. Department of Transportation’s Pipeline
and Hazardous Materials Safety Administration.
5.8 ARE THERE ANY CUMULATIVE IMPACTS TO WATER
RESOURCES AND CAN THEY BE MITIGATED?
If wetlands, surface waters, or groundwaters were impacted by the project (either directly
through fill or indirectly via water quality or other impacts) the project would contribute to
regional losses of these resources. As the region urbanizes, these resources are incrementally
reduced through development projects, and any further losses would contribute to that trend.
Compliance with permit requirements would help to minimize losses to resource function and
value, but some permanent loss could be unavoidable.
5.9 ARE THERE ANY SIGNIFICANT UNAVOIDABLE
ADVERSE IMPACTS TO WATER RESOURCES?
Alternatives 1 and 3 could result in potentially minor to moderate impacts to water resources,
if facilities are sited to cause temporary or permanent impacts to wetlands, streams, Lake
January 2016 CHAPTER 5 WATER RESOURCES 5-21
PHASE 1 DRAFT EIS
Washington, or buffers for these areas. The siting and design process will undertake to avoid
these resources to the extent possible, if it is not possible to avoid them, PSE will comply
with all applicable mitigation requirements. Impacts would not be significant due to
limitations imposed by regulatory agencies. Nearshore excavation associated with
Alternative 1, Option D could result in the resuspension of contaminated sediments and
increased turbidity in surrounding area. However, these water quality impacts would be
temporary and localized.
CHAPTER 5 January 2016 5 -22 WATER RESOURCES
PHASE 1 DRAFT EIS
CHAPTER 6. PLANTS AND ANIMALS
6.1 HOW WERE PLANTS AND ANIMALS IN THE
COMBINED STUDY AREA EVALUATED?
Several sources of information were used to characterize
the known vegetation and wildlife habitat in the combined
study area (Alternatives 1, 2, and 3 as depicted on Figure 1-
4 in Chapter 1), including the following federal, state, and
local sources:
• Washington Department of Fish and Wildlife
(WDFW), Priority Habitat and Species (PHS)
database (WDFW, 2015);
• Washington Department of Natural Resources
(DNR), National Heritage Program GIS dataset
(WNHP, 2015);
• U.S. Fish and Wildlife Service (USFWS), species
database (USFWS, 2015);
• U.S. Geological Survey (USGS), National Land
Cover database (Homer et al., 2015);
• WDFW SalmonScape database (WDFW, 2007);
• City of Bellevue, Urban Wildlife Habitat Literature
Review (The Watershed Company, 2009);
• Critical areas GIS datasets for the study area
communities;
• Tree inventory reports and other technical reports;
and
• Aerial imagery.
These information sources can only indicate the resources
that may be present in the combined study area. This
analysis is programmatic and no site surveys have been
performed. A site-specific analysis and fieldwork would be
required to verify the occurrence of sensitive or protected
wildlife, fish, plants, or habitat.
Plants and Animals
Key Findings
Alternatives 1 and 3 could
cause minor to significant
impacts from habitat
alteration; interference with
critical survival activities; or
direct injury, death or
harassment of some species.
Impacts would depend on the
scale of habitat alteration or
species disturbance, and the
species affected.
Alternative 1 (Option A) and
Alternative 3 have the most
potential to cause significant
impacts on plants and animals
– severity of impacts will
depend on location of project
and adjacent habitat and
species that use it.
Construction and operation of
a submerged line (Alternative
1, Option D) could result in
moderate to significant
impacts on aquatic species,
depending on the type and
amount of in-water work.
The energy storage and peak
generator plant components
of Alternative 2 could have the
lowest impacts on plants and
animals.
January 2016 CHAPTER 6 PLANTS AND ANIMALS 6-1
PHASE 1 DRAFT EIS
6.2 WHAT ARE THE RELEVANT PLANS, POLICIES, AND
REGULATIONS?
Several federal, state, and local government policies, regulations, and ordinances relating to
the protection of plants and animals apply to this project. Such regulations and policies
influence planning, land use, and management activities that can impact fish and wildlife
species and their habitats within the combined study area.
6.2.1 Federal and Washington State
Table 6-1 summarizes federal and state regulations and programs for fish, wildlife, plants,
and habitats.
Table 6-1. Federal and State Regulations and Programs
Statute Lead Agency Regulated Activities / Program
Federal
Endangered
Species Act (50
CFR1 Part 17)
National Marine
Fisheries
Service (NMFS)
and USFWS
Protects species identified as endangered or
threatened along with designated critical habitat
required for the conservation of those species. NMFS
has authority over most anadromous fishes, marine
mammals, marine reptiles, and other marine fish
species, while the USFWS has authority over
terrestrial wildlife and resident fish species that
inhabit inland waters. Requires that federal actions
(such as issuing a permit for wetland fill) do not
jeopardize the continued existence of any threatened,
endangered, or proposed species or result in the
destruction or adverse modification of critical habitat.
Magnuson-Stevens
Fishery
Conservation Act,
as amended by the
Sustainable
Fisheries Act of
1996 (Public Law
104-267)
NMFS Requires federal agencies to consult with NMFS on
federal actions that may adversely affect designated
Essential Fish Habitat for federally managed fish
species.
Bald and Golden
Eagle Protection
Act (50 CFR Part
22)
USFWS Protects bald and golden eagles and makes it
unlawful to take, import, export, sell, purchase, or
barter any bald or golden eagles, their parts,
products, nests, or eggs. Take means pursuing,
shooting, poisoning, wounding, killing, capturing,
trapping, collecting, molesting, or disturbing eagles.
To avoid potential disturbance to bald eagles, the
National Bald Eagle Management Guidelines
(USFWS, 2007) provide recommendations that will
likely avoid take for a list of activities.
CHAPTER 6 January 2016 6 -2 PLANTS AND ANIMALS
PHASE 1 DRAFT EIS
Statute Lead Agency Regulated Activities / Program
Migratory Bird
Treaty Act (50 CFR
Part 21)
USFWS Protects many common native birds as well as birds
that are listed as threatened or endangered. USFWS
regulates most aspects of the taking, possession,
transportation, sale, purchase, barter, exportation,
and importation of migratory birds. Of particular
concern are activities that affect birds nesting on
bridges, buildings, signs, illumination poles, and other
structures in areas planned for construction.
State
Growth
Management Act
(Chapter 36.70A
RCW2)
Department of
Commerce
Requires county and local municipalities to manage
Washington’s growth through the identification and
protection of critical areas and natural resource lands;
the designation of urban growth areas; and the
preparation and implementation of comprehensive
plans. Critical areas include: geologic hazard areas,
frequently flooded areas, wetlands, streams, fish and
wildlife habitat conservation areas (FWHCAs), and
critical aquifer recharge areas. FWHCAs are wildlife
habitats that are mapped or designated by WDFW,
corridors connecting priority habitats, or areas that
support species of local importance.
Shoreline
Management Act
(Chapter 90.58
RCW)
Department of
Ecology
(Ecology)
Regulates water bodies above a threshold size as
well as lands within 200 feet of the ordinary high
water mark of those water bodies. Includes policies
and regulations to protect shoreline habitat, preserve
public access, and allow for water-dependent uses.
Regulations include restrictions on development in
the shoreline zone, requirements for maintaining
native vegetation, and development standards.
Implemented by local jurisdictions through shoreline
master programs.
State Hydraulic
Code (Chapter
220-110 WAC3)
WDFW Protects fish and their habitat through regulation of
activities in streams and lakes. WDFW administers
state rules through its Hydraulic Project Approval
(HPA) program. An HPA must be obtained from
WDFW before work can be conducted that uses,
obstructs, diverts, or changes the natural flow or bed
of state waters. The conditions of an HPA can be
designed to protect fish, shellfish, and their habitat.
Priority Habitats
and Species
Program
WDFW Nonregulatory program that provides information on
documented locations of fish and aquatic resources,
terrestrial plants and animals, and habitats listed or
defined as priority. Priority species include state
endangered, threatened, sensitive, or candidate
species; animal aggregations considered vulnerable;
and species of recreational, commercial, or tribal
importance that are vulnerable (WDFW, 2015). Priority
habitats are habitat types or elements of habitat with
January 2016 CHAPTER 6 PLANTS AND ANIMALS 6-3
PHASE 1 DRAFT EIS
Statute Lead Agency Regulated Activities / Program
unique or significant value to a diverse assemblage of
species. A priority habitat may consist of a unique
vegetation type (e.g., shrub-steppe) or dominant plant
species, a described successional stage (e.g., old-
growth forest), or a specific habitat feature (e.g.,
cliffs).
Natural Heritage
Program
DNR Nonregulatory program that provides information for
listed plant species or those defined as rare. Also
maintains information on rare ecological communities
and priority species.
Definitions:
1Code of Federal Regulations
2Revised Code of Washington
3Washington Administrative Code
6.2.2 Local Regulations
Table 6-2 describes the regulatory programs implemented by the study area communities.
Table 6-2. Local Regulations and Programs
Regulatory Program Jurisdiction Regulated Activities/Program
Critical Areas
Ordinances/Regulations – required
under the Growth Management Act
(Chapter 36.70A RCW)
King County
and all cities
except Clyde
Hill1
Protect and regulate activities on or
adjacent to designated critical areas.
Establish allowed uses, buffers,
setback requirements, and mitigation
requirements for regulated critical
areas.
Shoreline Master Programs/Plans –
required under the Shoreline
Management Act (Chapter 90.58
RCW)
King County
and all cities
except Clyde
Hill
Establish allowed uses, buffers,
setback requirements, and mitigation
requirements for shorelines of
regulated waterways.
Local codes for tree protection or
preservation including:
King County Code Chapter 21A.16
Bellevue City Code 20.20.900
Beaux Arts Municipal Code 16.25
Issaquah Municipal Code 18.12
Kirkland Municipal Code 95.30,
95.34
Redmond Municipal Code
20D.80.20
Renton Municipal Code 4-4-130
Sammamish Municipal Code
21A.35
Yarrow Point Municipal Code 12.26
King County
and all study
area cities
Regulate the protection of trees in
addition to the critical areas code.
Significant trees are specifically
protected and defined for their unique
ecological and aesthetic value. A
review and site plan may be required
for any proposed alterations to
significant trees.
1When Clyde Hill was incorporated as a city there was no evidence of critical areas as defined under GMA.
Therefore it was determined that Clyde Hill is not required to develop a Critical Areas Ordinance (City of
Clyde Hill, 2014).
CHAPTER 6 January 2016 6 -4 PLANTS AND ANIMALS
PHASE 1 DRAFT EIS
Comprehensive plans for the study area communities have policies associated with plants and
animals, including: restoration of natural features, tree retention, targets for tree canopy
cover, and/or protection of ecological processes and functions of natural features (e.g.,
wetlands, streams).
6.3 WHAT TYPES OF VEGETATION ARE FOUND IN THE
COMBINED STUDY AREA?
6.3.1 Vegetation Cover Types
Although substantial portions of the combined study area are already developed to varying
degrees, a variety of vegetation cover types occur including herbaceous, scrub-shrub, forest,
agriculture, and woody and herbaceous wetland vegetation types (Figures 6-1 and 6-2). Most
of the combined study area is developed (59 percent total), but has varying amounts of
vegetation cover (Figure 6-1). Forest (30 percent), open space (15 percent), and other
vegetation cover types make up the remaining vegetation cover found in the combined study
area (Figure 6-1). The largest patches of forested vegetation cover are found in state parks,
open space areas, and undeveloped areas. Section 6.4 describes these vegetation cover types
in more detail, including common plant species and associated wildlife.
Figure 6-1. Vegetation Cover by Type
Source: Homer et al., 2015
6.3.2 Rare Plants and High-Quality Vegetation Communities
The Washington Natural Heritage Program (WNHP) database, managed by WDNR,
identifies one rare plant occurrence in the combined study area: Vancouver ground-cone
(Boschniakia hookeri) in Bridle Trails State Park. The WHNP database also identifies two
high-quality vegetation types between Squak Mountain and Tiger Mountain: Douglas fir-
madrone/salal forest, and a forested sphagnum bog. Because these are sensitive resources
subject to collection and vandalism, their precise locations are not disclosed to the public.
January 2016 CHAPTER 6 PLANTS AND ANIMALS 6-5
PHASE 1 DRAFT EIS
Energize Eastside EIS 140548
Figure 6-2
Vegetation Cover
SOURCE: King County 2015; ESA 2015; WA Ecology 2014; NOAA 2011.
For more info visit www.energizeeastsideeis.org/map-vegetationcover
Lake Washington
Lake
Sammamish
Bellevue Sammamish
Issaquah
Renton
Newcastle
RedmondKirkland
Beaux Arts
Medina
Clyde
Hill
Hunts
Point
Yarrow
Point
Mercer
Island
Lakeside
Sammamish
Talbot Hill
Novelty Hill
Lake Tradition
U:\GIS\GIS\Projects\14xxxx\D140548_EastsidePSETransmisisonCoor\MXD\VegetationCover.mxd
0 2
Miles
Existing Substations
Roadway
Combined Study Area
Boundary
Water bodies
City Limits
Land Cover
Open Space with 80%+
Vegetation Cover
Developed with 50-80%
Vegetation Cover
Developed with 20-50%
Vegetation Cover
Developed with 0-20%
Vegetation Cover
Forest
Scrub-Shrub
Herbaceous
Agriculture
Woody and Herbaceous
Wetland
Note: This map is for reference only. It is not guaranteed that the information is accurate or complete.
6.3.3 Trees
Trees provide numerous functions and benefits. For instance, tree canopy cover helps to
reduce stormwater runoff by intercepting and taking up water; this can improve water quality
and reduce stream erosion. Canopy cover also provides shade to help maintain stream
temperatures to benefit aquatic species, as well as provide important carbon sequestration
functions. Snags and den trees provide habitat for cavity-nesting animals such as birds and
raccoons. Forested areas also provide wildlife corridors to enhance population connectivity to
various habitat types that support such activities as breeding, rearing and foraging.
Typical tree species in the combined study area include both deciduous and coniferous
species such as Douglas fir, big-leaf maple, red alder, black cottonwood, Pacific madrone,
pines, western red cedar, and western hemlock. Existing tree canopy cover in the combined
study area is shown in Table 6-3 based on information from study area communities that
have completed tree inventory reports.
Table 6-3. Tree Canopy Cover in Study Area Communities with Tree Inventory
Reports1
Jurisdiction Tree Canopy Cover
Bellevue 36%
Issaquah 47%
Kirkland 36%
Redmond 39%
Renton 29%
Sammamish 46%
1 Newcastle, Medina, Clyde Hill, Yarrow Point, Hunts Point, and Beaux Arts do not currently have tree
inventories available.
6.4 WHAT ANIMAL SPECIES AND HABITATS CAN BE
FOUND IN THE COMBINED STUDY AREA?
This section provides a general description of the wildlife habitats and species likely
occurring in the combined study area and describes threatened and endangered species and
species of concern that may occur in this area.
6.4.1 Habitat Types and Associated Species
As indicated above, about 59 percent of the combined study area is developed as urban,
suburban and exurban areas. As a result a substantial portion of the combined study area
consists of substantially modified wildlife habitat, including extensive landscaped or
maintained areas. Animal species typically found in landscape areas have a high tolerance for
human disturbance, and include crows, squirrels, raccoons, sparrows, and rats. Landscape
areas can include backyards, golf courses, and recreational parks that provide cover and
January 2016 CHAPTER 6 PLANTS AND ANIMALS 6-7
PHASE 1 DRAFT EIS
foraging for animal species, such as the Bellevue Municipal Golf Course, Glendale Country
Club, and Tam O’Shanter Park in Bellevue.
Although typically small and disconnected, urban habitat is identified by the City of Bellevue
as important for wildlife (The Watershed Company, 2009). Urban habitat includes areas
where commercial, industrial, or dense residential land use dominates; habitat is limited to
small city parks and residential and commercial landscaping. Common habitat features used
by animal species found in these habitats include man-made structures such as bridges,
chimneys, abandoned buildings, ledges, and telephone poles and wires (The Watershed
Company, 2009). Suburban habitat is dominated by single-family homes on residential lots
and includes parks, riparian corridors, residential landscapes, and critical areas and their
buffers. Exurban habitat is found in areas of low-density residential development located in
rural areas and includes many of the same habitat features as suburban habitat, but also
includes forest communities.
Despite the extensive development in the combined study area, important aquatic and
terrestrial habitat is also present, including WDFW designated priority habitats. Table 6-4
provides an overview of the general distribution of these habitat types within the different
jurisdictions in the combined study area, based on a coarse interpretation of the data
presented in Figure 6-1. Therefore, the table primarily represents concentrations of similar
habitat, while small or disperse patches are not represented. These habitat types also tend to
overlap in many areas. For example, freshwater wetlands and forest habitat can also be found
in biodiversity areas and corridors. A short description of each habitat and species that
typically use the habitat follows the table.
Table 6-4. Aquatic and Terrestrial Habitats within the Combined Study Area
Jurisdiction Bellevue Clyde Hill Hunts Point King County1 Kirkland Medina Newcastle Redmond Renton Sammamish Yarrow Point Habitats
Lakes and Ponds2 • • • • • • • • • •
Biodiversity Areas and
Corridors2 • • • • •
Freshwater Wetlands2 • • • • • • • •
Forest • •
Natural Areas • • • • •
1Unincorporated areas of King County
2WDFW designated priority habitats
Source: WDFW, 2015 and The Watershed Company, 2009
CHAPTER 6 January 2016 6 -8 PLANTS AND ANIMALS
PHASE 1 DRAFT EIS
6.4.1.1 Lakes and Ponds
Lake Washington, Lake Sammamish, and other
aquatic systems provide important resources for
fish and other aquatic species. Priority aquatic
species designated by WDFW and species of
local importance likely to occur in lakes or ponds
in the combined study area include Chinook,
coho, and sockeye salmon; steelhead; rainbow,
cutthroat, and potentially bull trout; reptiles
(Pacific pond turtle); and numerous bird species
that forage in these areas (gulls, terns,
cormorants, and waterfowl) (Figure 6-3). The
WDFW priority terrestrial species or species of
concern expected to occur in these areas include
bald eagles, peregrine falcon, and great blue
heron. All of the communities in the combined
study area have lake and pond habitat; (see
Chapter 5 and Figure 5-1 for further discussion
of lake and pond habitat).
6.4.1.2 Biodiversity Areas and
Corridors
Biodiversity areas are terrestrial areas that are
either identified by a scientifically based
assessment on a landscape scale, or contain
valuable habitat for fish and wildlife within a city
or urban growth area (UGA) where the
vegetation is vertically diverse (e.g., snags,
downed woody debris) and horizontally diverse
(e.g., mosaic of habitat types). Corridors are
areas of moderately undisturbed and unbroken
tracts of vegetation that connect habitats to
support wildlife movement and migration
(WDFW, 2008).
Corridors also include riparian areas, which are
vegetated areas adjacent to streams, commonly
found throughout low-lying areas east and
southeast of Lake Washington and into the
foothills (WDFW, 2008). Riparian corridors in
the combined study area include Mercer Slough,
and Coal, Issaquah, Kelsey, Lewis, and May
creeks. These corridors and the associated stream
habitat are discussed in more detail in Chapter 5.
Figure 6-3. Great Blue Heron in Lake
and Pond Habitat
Figure 6-4. Path through Marymoor
Park
Photo credit: Eastside Audubon
January 2016 CHAPTER 6 PLANTS AND ANIMALS 6-9
PHASE 1 DRAFT EIS
Native plant species commonly found in habitat corridors include big-leaf maple, red alder,
conifers, Indian plum, and oceanspray. Typical aquatic plants include sedges, rushes,
duckweed, and common cattail. Corridors support a range of both terrestrial and aquatic
animal species such as small mammals, songbirds, and raptors. Corridors in the combined
study area range in size and vegetative cover.
Major corridors in the combined study area, designated by WDFW as biodiversity and
corridor areas include Marymoor Park, Bridle Trails Park, and the Cedar River Open Space
areas. Marymoor Park, a 640-acre recreational and nature park, is located at the north end of
Lake Sammamish (Figure 6-4), and contains extensive scrub-shrub and emergent wetland
habitat for a range of species including fish, waterfowl, and other bird species. Bridle Trails
State Park is an approximately 500-acre primarily forested park in Kirkland. The Cedar River
Valley Open Space Area in Renton consists of steep forested slopes and riparian areas that
provide habitat for many birds, other terrestrial species, and fish.
The other major habitat corridor is found in the southeast corner of the combined study area,
connecting Cougar Mountain Regional Wildlands Park, Squak Mountain State Park, and
Tiger Mountain Natural Resource Conservation Area (WDFW, 2015). This area consists of
mixed forest (predominantly older second-growth trees), streams, and wetlands. It provides
habitat for resident and migratory wildlife such as black bear, bobcat, cougar, deer, eagle,
waterfowl, reptiles, fish, and amphibians as well as small animals and birds.
Other habitat connectivity corridors occurring in the combined study area follow
transmission lines, such as the Seattle City Light (SCL) transmission line that bisects the
Bridle Trails State Park biodiversity area and corridor. Many small and large mammal
species likely use such utility corridors for breeding, rearing, foraging and migration
purposes.
6.4.1.3 Freshwater Wetlands
Over 1,000 wetlands are mapped in the combined study area (see Figure 5-1 for locations of
major wetlands) (King County, 2015). Figure 6-5 shows a typical freshwater wetland in this
region. The plant species commonly associated with wetlands in the combined study area
include soft rush, common
cattail, willow, dogwood, and
reed canarygrass (a nonnative
grass), among others.
Freshwater wetlands support
habitat for songbirds,
amphibians, and other
terrestrial and aquatic species.
Most of the study area
communities have this type of
WDFW designated priority
habitat (see Table 6-4). One
major freshwater wetland
complex is Mercer Slough
Nature Park in Bellevue, a
Figure 6-5. Freshwater Wetland Habitat
CHAPTER 6 January 2016 6 -10 PLANTS AND ANIMALS
PHASE 1 DRAFT EIS
large (about 450-acre) mixed wetland system
associated with Lake Washington. A complex
of open water, emergent, and forested wetland
vegetation provides habitat for migrating
salmon, great blue heron, waterfowl, and other
priority species (WDFW, 2015). Other major
wetland complexes include the Larsen and
Phantom Lake complex, and wetlands adjacent
to the north and south ends of Lake Sammamish
(see Figure 6-1).
6.4.1.4 Forests
Patches of forest habitat are scattered
throughout the combined study area, although
the largest patches are found in unincorporated
King County (Squak Mountain, Cougar
Mountain Wildlands Park, Tiger Mountain
Forest) (Figure 6-1). Common plant species in
forest communities include western red cedar,
Douglas fir, western hemlock, big-leaf maple,
sword fern, and vine maple. Forests provide
habitat for small and large mammals, songbirds, raptors, and many other bird species. Figure
6-6 shows typical forest habitat with a large wildlife snag.
Bridle Trails State Park provides about 500 acres of primarily forested habitat for a variety of
species, including coyotes, raccoons, other small mammals, and many birds. It is designated
by WDFW as a biodiversity area and corridor.
6.4.1.5 Natural Areas
Natural areas include unmaintained parks and other public lands that support native plants
and animals. These areas can consist of a variety of habitat types, including wetlands, forest
communities, riparian corridors, and shrub and herbaceous areas. Natural areas can provide
important habitat for animal species and are found throughout the combined study area. The
Kelsey Creek Open Space Area is a forested open space in the Kelsey Creek basin in
Bellevue. Kelsey Creek Park, named after Kelsey Creek which runs through the park to
Mercer Slough, provides 150 acres of forested riparian and wetland habitat.
Coal Creek Park Natural Area provides about a 3-mile-long forested riparian corridor,
adjacent to Coal Creek, extending from Lake Washington to Cougar Mountain Wildlands
Park. This park provides diverse fish and wildlife habitat, and enhances habitat connectivity
through the area. May Creek Park provides similar functions, although this corridor consists
of smaller and lower density forested areas.
6.4.2 Federal, State, and Local Listed Species
The combined study area provides potential habitat for several bird, mammal, reptile,
amphibian, and fish species that are listed or designated as Species of Concern under the
Figure 6-6. Forest Habitat
January 2016 CHAPTER 6 PLANTS AND ANIMALS 6-11
PHASE 1 DRAFT EIS
federal Endangered Species Act, or that have a Washington state designation (for example,
state threatened). A list of these species and their federal/state designation is provided in
Appendix C. The only federal or state listed endangered or threatened species expected to
typically occur in the combined study area are aquatic species. The critical areas ordinances
of King County and some of the other communities list species of local concern in addition to
those under federal and state designation. The following paragraphs summarize additional
species of local concern:
• Chapter 21A.24.382 of the King County Zoning Code requires the County to protect
the following species: bald eagle, great blue heron, osprey, peregrine falcon, northern
spotted owl, marbled murrelet, Townsend’s big-eared bat, Vaux’s swift, red-tailed hawk,
and goshawk.
• The City of Bellevue’s Land Use Code 20.25H.150 designates the following species
of local importance: great blue heron, red-tailed hawk, bald eagle, peregrine falcon,
osprey, pileated woodpecker, purple martin, common loon, western grebe, merlin,
great egret, green heron, Vaux’s swift, Townsend’s big-eared bat, and western toad.
• The City of Redmond’s Critical Areas Ordinance (Ordinance #2259) designates great
blue heron as a locally important species.
6.5 HOW WERE POTENTIAL IMPACTS TO PLANTS AND
ANIMALS ASSESSED?
Because specific locations of proposed facilities have not yet been determined, potential
impacts to plants and animals were evaluated conceptually for this programmatic phase of the
EIS. A range of potential impacts identified during the scoping process were evaluated in this
assessment, including noise disturbance, habitat loss (including plant and tree loss), and the
introduction of invasive plant species (City of Bellevue, 2015). A site-specific analysis of
impacts will be completed during Phase 2 of the EIS process.
6.6 WHAT ARE THE LIKELY CONSTRUCTION IMPACTS
RELATED TO PLANTS AND ANIMALS?
6.6.1 Construction Impacts Considered
Although construction details for each alternative have yet to be developed, general
construction activities are understood for these types of projects. To evaluate impacts at a
programmatic level, the overall size of the construction footprint (amount of surface area
disturbance) associated with each alternative was used to compare the potential for impacts
associated with the proposed project. Most of the alternatives would require site clearing for
infrastructure and operation of heavy equipment. The scale and proximity of construction
activities would determine the intensity of potential impacts on plants and animals. Site-
specific studies to document plant and animal species in the area and potential impacts on
those species would be conducted prior to facility placement and construction.
Minor - Impacts would be minor where construction occurs over a short duration in
developed areas with minimal or poor quality habitat; there is temporary habitat alterations or
CHAPTER 6 January 2016 6 -12 PLANTS AND ANIMALS
PHASE 1 DRAFT EIS
construction activities (such as noise) with the potential to disrupt or disturb wildlife
movement or critical survival activities of native species; or when impacts are mitigated
through compliance with tree protection or critical areas ordinances.
Moderate - Impacts are moderate where construction activities would cause injury, death, or
harassment of native resident or migratory fish, bird, amphibian, or mammal species; or there
is moderate interference with the breeding, feeding, or movement of native resident or
migratory fish, bird, amphibian, or mammal species.
Significant - Impacts are considered significant where construction activities would cause
the following: injury, death, or harassment of federal and state listed endangered or
threatened species, or bald eagle and peregrine falcon (state sensitive and federal species of
concern); a reduction of habitat quality or quantity that can substantially affect the critical
survival activities (breeding, rearing, and foraging) of listed species; substantial interference
with the breeding, feeding, or movement of native resident or migratory fish, bird,
amphibian, or mammal species; or noncompliance with tree protection ordinances or critical
areas ordinances.
6.6.1.1 Direct Loss of Habitat
Construction would require grading or permanent removal of vegetation or trees that
currently provides habitat for animals. Impacts resulting from direct losses of terrestrial
habitat would vary depending upon the location of construction. Impacts would be minor,
moderate, or significant as defined above. The significance of an impact would be further
defined by the extent of the impact (how much area is affected) and if listed species, species
of concern, or priority habitats are affected.
6.6.1.2 Disturbance from Construction Noise and Human Activity
Increased noise and human activity associated with construction could impact plants and
animals. Some animal species living in urban areas are generally tolerant of high noise levels
and likely would not be disturbed. Other species could be displaced and relocate to
surrounding habitats. Because available habitat is likely to be already inhabited by wildlife,
some individual animals may not be able to successfully relocate, resulting in increased
mortality of some species. This would be a significant adverse impact if listed species are
lost. Construction activities that disturb the vegetation and soil can leave areas susceptible to
invasive plant species, which would decrease the value of the habitat for wildlife.
6.6.1.3 Sedimentation of Aquatic Habitats
As described in Chapter 5, sedimentation of aquatic habitats due to runoff from disturbed
areas or turbidity from in-water work may occur during construction. Aquatic species,
including threatened and endangered fish, could be impacted if sedimentation resulted from
uncontrolled runoff in aquatic habitats. In order to comply with state and local stormwater
permit requirements, best management practices to control surface water runoff would be
implemented, minimizing the potential for uncontrolled runoff. Similarly, best management
practices during in-water work would be used to control turbidity.
January 2016 CHAPTER 6 PLANTS AND ANIMALS 6-13
PHASE 1 DRAFT EIS
6.6.1.4 Contamination of Aquatic Habitats
As described in Chapter 5, there is a risk for accidental spills of oils, solvents, and other
chemicals from construction equipment. If not controlled, such spills could flow into nearby
surface waters and contaminate aquatic habitats and species. The potential for spills would be
minimized by fulfilling permit requirements and implementing Spill Prevention and Control
Plans. Contaminated sediments could also be disturbed during dredging or other in-water
work, and released into the aquatic habitat. Contamination of lake-bottom sediments is
known to exist in some locations in Lake Washington as discussed in Chapter 5. PSE would
need to determine the likelihood of encountering hazardous materials prior to construction,
and implement best management practices to minimize potential effects on aquatic species.
6.6.2 No Action Alternative
Under the No Action Alternative, PSE’s existing maintenance activities and programs would
continue. Utility line or facility construction would be limited to that described in Chapter 2.
As a result, there would be negligible loss of vegetation or disturbance to animals from
permanent structures.
The types of conservation measures PSE expects to implement as part of achieving its
conservation goals would occur mostly on a smaller scale. Since minimal construction would
be required to achieve these goals, short-term impacts on plants and animals are anticipated
to be minor.
PSE’s Vegetation Management Program would continue under the No Action Alternative
(Figure 6-6). This program includes removal of mature trees greater than 15 feet tall that are
located within the transmission right-of-way, (typically including the area directly under the
wires (the wire zone), and 10 feet from the outer transmission wires (border zones).
Therefore, the overall size of the right-of-way typically varies, by the wire zone width. Trees
within the transmission right-of-way would be trimmed or removed, as needed. In addition,
trees at risk of falling and likely to come in contact with nearby wires are proactively
removed outside of the border zones (the danger tree zone), which also varies by the height
of the trees in this zone. PSE selectively uses herbicides, in combination with tree removal
and pruning, for vegetation management in accordance with best management practices.
PSE’s policy is to restore vegetation other than trees within transmission corridors to “as like
or better” condition. Outside of the required zones, tree replacement is agreed upon with the
property owner (in some cases the owner may prefer tree removal). Tree replacement would
also comply with local code requirements.
PSE would continue to achieve 100 percent of the company’s conservation goals as outlined
in its Integrated Resource Plan (PSE, 2013a). The types of conservation PSE expects to
implement would occur mostly on a smaller scale (small projects on individual homes and
businesses), including energy efficiency (weatherization, efficient lighting, etc.), fuel
conversion (electric to gas), distributed generation (solar, wind, etc.), distribution efficiency,
and demand response (capacity savings programs). Since minimal construction would be
required to achieve these goals, short-term impacts on plants and animals are anticipated to
be minor.
CHAPTER 6 January 2016 6 -14 PLANTS AND ANIMALS
PHASE 1 DRAFT EIS
Figure 6-6. PSE Vegetation Management Program Zones
Source: PSE, 2015
6.6.3 Alternative 1: New Substation and 230 kV Transmission Lines
Impacts are described according to the major components associated with Alternative 1. The
substation impacts are described first, followed by transmission line options.
In general, construction would occur largely in developed areas on or adjacent to existing
PSE utility easements and rights-of-way or roadways and other utility corridors. It is less
likely that construction would occur through undeveloped areas, where wetlands and other
priority habitats are more likely to occur. Transmission lines, new transformers, and
substations would be located in developed areas to the extent feasible. Potential transmission
line locations could be constructed across or adjacent to any of the habitats described above.
All four options under Alternative 1 would require expansion of an existing substation
(Lakeside) or construction of a new transformer and substation (Vernell or Westminster). The
Lakeside substation and the proposed Westminster substation are located within existing
transmission rights-of-way. Vernell and Westminster are located in urban areas with limited
habitat value on the properties themselves; Lakeside is adjacent to a larger greenspace
(including critical areas) but listed species are not anticipated to be present because of the
urbanized nature of these areas. Species of concern or native resident or migratory species
may use the adjacent greenspace. Construction could take up to 18 months, resulting in short-
term temporary construction impacts on plants and animals in the vicinity. Animals would
likely avoid these substation and transformer locations during construction because of noise
and human activities. Habitat loss and disturbance from construction would be moderate to
significant if listed species, species of concern, or native resident or migratory species are
harmed or displaced. The potential for these species to be present is low, as noted above.
Similarly, impacts to critical survival activities of threatened or endangered species or species
of concern, or interference with the breeding, feeding, or movement of native resident or
migratory species could also result in moderate to significant impacts caused by habitat loss
and disturbance, but these species are not likely to be present in these areas. Site specific
evaluations during the Phase 2 EIS process will determine the potential for these species to
be present in the potentially affected areas.
January 2016 CHAPTER 6 PLANTS AND ANIMALS 6-15
PHASE 1 DRAFT EIS
6.6.3.1 Option A: New Overhead Transmission Lines
6.6.3.1.1 Direct Loss of Habitat
Construction of a new overhead transmission line under this option could result in permanent
impacts on plants and animals and their habitats. Although most of the corridor would be
constructed through existing PSE easements or other utility rights-of-way (roadways, rail
corridors), transmission lines could also be constructed through new utility corridors that are
currently vegetated, where wetlands and other priority habitats are more likely to occur. If the
corridor is located along the existing PSE easement it would be widened by up to 50 feet. The
new corridor for a 230 kV line would be approximately 120 to 150 feet wide, wider than a
115 kV line (30 to 40 feet) (see Figure 6-6). Trees would be removed for the construction of
overhead transmission lines according to PSE’s Vegetation Management Program. Trees
posing a threat to transmission lines outside of the corridor would also be removed. As
discussed under No Action, PSE has a policy regarding revegetation and replacement of
trees, which includes compliance with local tree replacement and critical areas regulations.
If a new transmission line corridor were located entirely in currently vegetated areas, up to
327 acres of vegetation could be removed, assuming an 18-mile corridor up to 150 feet in
width, with 100% vegetation coverage. Because the corridor includes areas of existing rights-
of-way, it is not likely to be 100% vegetated. Assuming an average tree canopy coverage of
40 percent within the corridor (see Section 6.3.3), up to 131 acres of canopy cover could be
removed under Alternative 1, Option A, in a worst-case scenario. Those species using
forested areas for nesting, foraging, movement or shelter could be displaced by species
preferring less forest cover and open spaces. Habitat connectivity would be reduced or
disrupted in some areas. For these reasons, Option A could result in moderate to significant
adverse impacts to habitat and listed species, species of concern, or native resident or
migratory species. However, a new transmission line corridor is likely to be located in
existing PSE easements and other utility rights-of-way, where the habitat is already disturbed.
In this scenario, up to about 109 acres of vegetation (including about 43 acres of forested
habitat) could be removed, assuming an 18-mile corridor widened 50 feet with 40 percent
tree canopy cover. The actual impact of a new transmission line corridor would likely be
somewhere between these two scenarios (entirely new corridor or entirely within existing
rights-of-way), as some combination of these areas would likely be used, and would be
determined more specifically in Phase 2. Federal, state, and local regulations (critical areas
and tree protection ordinances) would require protection and mitigation for impacts to
species, habitat, or vegetation removal during construction.
6.6.3.1.2 Disturbance from Construction Noise and Human
Activity
New access roads could also be installed for construction of overhead transmission lines.
Animals in the vicinity of construction activities could experience increased noise and human
activity for up to 18 months, if the new overhead transmission line and transformer and
substation facilities are constructed concurrently. Individual locations along the transmission
line corridor would have construction-related activity for up to a week over a period of up to
2 months. Many animal species would likely avoid the area during construction periods,
although species living in urban areas are generally tolerant of high noise levels and likely
would not be substantially disturbed. Species in the combined study area that are more
CHAPTER 6 January 2016 6 -16 PLANTS AND ANIMALS
PHASE 1 DRAFT EIS
sensitive to human activity, such as bald eagle or peregrine falcon, could be temporarily
displaced and relocate to surrounding habitats if disturbed. Impacts could be significant
depending on the timing and species present if the project disturbs or substantially disrupts
critical survival activities (nesting, foraging, and migration) of threatened or endangered
listed species or species of concern. However, impacts would likely be short-term and minor,
and mitigation would follow local, state, and federal environmental review and permit
requirements.
6.6.3.1.3 Sedimentation of Aquatic Habitats
As indicated in Section 6.6.1.3, sedimentation of aquatic habitats is expected to be
minimized, and thus minor, with the implementation of best management practices. Potential
impacts would also be reduced if construction activities are limited to existing rights-of-way,
utility corridors, or other previously disturbed or developed areas. Refer to Chapter 5 for
more information.
6.6.3.1.4 Contamination of Aquatic Habitats
As discussed in Section 6.6.1.4, potential contamination or aquatic habitats is expected to be
avoided or minimized with the implementation of best management practices. Impacts would
be negligible or minor.
6.6.3.2 Option B: Existing Seattle City Light 230 kV Transmission
Corridor
6.6.3.2.1 Direct Loss of Habitat and Disturbance from
Construction Noise and Human Activity
Some construction activities for this option would disturb wildlife or remove vegetation. The
SCL 230 kV transmission line currently crosses WDFW designated biodiversity corridors or
natural habitat areas such as Bridle Trails State Park, Coal Creek Natural Area, and May
Creek Park. If construction activities in Bridle Trails State Park occur in or near where the
rare Vancouver ground-cone plant species occurs, there could be significant impacts to the
species. In general, construction activities would be less intense than with new overhead lines
and would potentially involve substantially less vegetation clearing, because existing
corridors would primarily be used (and not widened), and a shorter (1-mile-long) new
transmission corridor would be required to connect the SCL corridor line to the Lakeside
substation. Activities would be concentrated along an approximately 15-mile corridor similar
to transmission lines for Alternative 1, Option A. Animals in the vicinity of construction
areas could experience noise and human activity and would likely avoid the area during
construction periods.
Rebuilding transmission lines is expected to take longer than installing new lines (up to 24
months) and would have the greatest potential to disrupt wildlife in the vicinity. Impacts from
construction activities would be similar to Option A. Alternative 1, Option B would be
primarily constructed along corridors already being used for transmission, where wildlife
may be more adapted to human activity, and potentially less affected by construction
activities. Impacts from Option B could range from minor to significant.
January 2016 CHAPTER 6 PLANTS AND ANIMALS 6-17
PHASE 1 DRAFT EIS
6.6.3.2.2 Sedimentation of Aquatic Habitats
As discussed above for Alternative 1, Option A, sedimentation of aquatic habitats is expected
to be minimized, and thus minor, with the implementation of best management practices.
Potential impacts would also be reduced if construction activities are largely limited to
existing rights-of-way, utility corridors, or other previously disturbed or developed areas.
Refer to Chapter 5 for more information.
6.6.3.2.3 Contamination of Aquatic Habitats
As discussed above for Alternative 1, Option A, potential contamination or aquatic habitats is
expected to be avoided or eliminated with the implementation of best management practices.
Impacts would be negligible or minor. Refer to Chapter 5 for more information.
6.6.3.3 Option C: Underground Transmission Lines
6.6.3.3.1 Direct Loss of Habitat
Construction of new underground transmission lines would result in temporary impacts, and
could result in some permanent impacts, on plants and animals. Most new underground
transmission lines would likely be constructed through existing PSE 115 kV overhead
transmission line rights-of-way, other utility rights-of-way (roadways, rail corridors), or new
rights-of-way. Installation techniques for open-cut placement of transmission lines would
likely include clearing and grading, excavation, and operation of large equipment. The trench
width for trench excavation would vary from 2 to 6 feet, plus temporary clearing for access
roads and staging (approximately 30 feet wide). These impacts would be temporary but
establishment of a maintenance zone, where only certain types of vegetation would be
allowed to grow, would be a permanent impact. Street trees and other roadside vegetation
would be removed. This option results in a narrower clear zone, compared with up to 150
feet of clear zone needed for a 230 kV overhead transmission line (under Alternative 1,
Option A), but may have more permanent vegetation removal.
It is less likely that the new underground line would be constructed through undeveloped
areas, where wetlands and other priority habitats are more likely to occur. However, if a new
underground line were located in currently forested areas, a worst case estimate of up to 66
acres of tree canopy cover could be lost, assuming at least an 18-mile-long corridor with a
30-foot-wide work area and 100% vegetation cover. Impacts from construction would be
significant if habitat loss resulted in harm to threatened or endangered species, species of
concern, or their critical survival activities. In the absence of these species or their suitable
habitat, impacts would be considered moderate to significant if the project harmed or
interfered with the breeding, feeding, or movement of native resident or migratory species.
Alternative 1, Option C would be subject to the same regulations as those described for
Option A.
6.6.3.3.2 Disturbance from Construction Noise and Human
Activity
Noise and construction activity could disturb animals in the vicinity. If the affected wildlife
includes threatened or endangered species, species of concern, or native resident or migratory
species these impacts could be significant; however other construction activities are expected
to result in minor to moderate impacts, depending on the ambient background noise levels, or
CHAPTER 6 January 2016 6 -18 PLANTS AND ANIMALS
PHASE 1 DRAFT EIS
the tolerance of the species to such activities. The duration of construction for underground
transmission lines, if the entire line was placed underground, would be the longest of the
options under Alternative 1. Construction would take approximately 28 to 36 months.
Construction of new transmission lines would move in a linear fashion so that in any given
location, the duration of construction would be approximately 2 months.
6.6.3.3.3 Sedimentation of Aquatic Habitats
As discussed above for Alternative 1, Option A, sedimentation of aquatic habitats is expected
to be minimized, and thus minor, with the implementation of best management practices.
Potential impacts would also be reduced if construction activities are largely limited to
existing rights-of-way, utility corridors, or other previously disturbed or developed areas.
Refer to Chapter 5 for more information.
6.6.3.3.4 Contamination of Aquatic Habitats
As discussed above for Alternative 1, Option A, potential contamination or aquatic habitats is
expected to be avoided or minimized with the implementation of best management practices.
Impacts would be negligible or minor. Refer to Chapter 5 for more information.
6.6.3.4 Option D: Underwater Transmission Lines
6.6.3.4.1 Direct Loss of Habitat
A new underwater transmission line would require east-west overhead and/or underground
transmission lines to connect it to a substation on land. Permanent and temporary impacts on
plants and animals as well as associated habitats under this option would be similar to those
described for Alternative 1, Options A and C, depending upon the chosen upland connection
alignment. Impacts would be minor to significant.
6.6.3.4.2 Disturbance from Construction Noise and Human
Activity, Sedimentation, and Contamination of Aquatic
Habitats
Under Alternative 1, Option D, construction of a new underwater transmission line in Lake
Washington would introduce noise and human activity and require in-water work. The
primary impacts to plants and animals would be the potential for affecting water quality and
underwater noise conditions in the lake. These potential impacts would be substantially
greater for conventional trenching operations in the nearshore environment, compared to
trenchless techniques. Conventional trenching would require the installation of sheet pile
isolation structures, which would shore up the sides of the in-water and/or nearshore trench.
Localized turbidity could occur, potentially altering the behavior of aquatic species, such as
the ability to avoid predation or to capture prey, or causing physical harm if aquatic species
are present close to the disturbance. Best management practices would limit the effects from
turbidity, and the project would meet applicable water quality standards and in-water work
permit conditions.
Construction in Lake Washington would occur in habitat for Chinook salmon, Puget Sound
steelhead trout, and Coastal-Puget Sound bull trout, which are all federally listed threatened
species. If sheet or soldier pile driving is required for construction, either in the nearshore or
January 2016 CHAPTER 6 PLANTS AND ANIMALS 6-19
PHASE 1 DRAFT EIS
in-water locations, the resulting underwater noise could negatively affect these species, as
well as other aquatic species. Noise could alter their behavior and, at close proximity, noise
could cause physical harm or death, potentially resulting in significant impacts to federally
listed fish species and moderate impacts to native resident or migratory species. However, it
is expected that vibratory pile driving techniques would be adequate to install such piles,
which would reduce the potential effects, compared to impact pile driving methods.
Vibratory methods do not produce concussive sound waves, like impact pile driving, that
have been shown to injure or kill fish and other aquatic species. Potential impacts to fish can
be reduced by employing noise attenuation measures such as using a bubble curtain around
the pile driving locations. Specific measures and pile driving restrictions will be provided in
the project-specific permits from WDFW, Corps of Engineers, U.S. Fish and Wildlife
Service, and National Marine Fisheries Service. In-water work and ground disturbing
activities would be conducted in accordance with timing windows intended to avoid breeding
or spawning seasons for sensitive aquatic species, along with other mitigation measures to
reduce short-term impacts.
6.6.4 Alternative 2: Integrated Resource Approach
Substantially less construction would be required for some components of Alternative 2 than
Alternative 1 because activities would occur on a smaller scale (small projects at individual
homes and businesses). Other components, such as energy storage and peak generator plants,
would have similar construction impacts as transformer/substation work in Alternative 1. As
a result, impacts on plants and animals with Alternative 2 could be minor for the smaller
components to potentially significant for a large component such as a large battery storage
system. Larger components such as a 6-acre battery storage yard and three peak generation
plants, if constructed in vegetated areas, could result in potentially significant impacts as
described in Section 6.6.1.
6.6.4.1 Energy Efficiency and Demand Response Component
Energy efficiency and demand response improvements would not involve infrastructure
improvements. As a result, these components would have no impacts on plants and animals.
6.6.4.2 Distributed Generation Component
Construction of distributed generation facilities could result in short-term minor impacts on
plants and animals within the vicinity of each facility. Impacts would vary in intensity and
duration with the type and extent of facility.
Distributed generation facilities would be constructed throughout the combined study area,
requiring construction activities such as clearing, grading, and new infrastructure. However,
construction activities for distributed generation facilities would remain lower than for
construction of any options under Alternative 1. Distributed generation facilities would likely
be located on rooftops or inside buildings, with minor impacts to plants and animals.
Construction of distributed generation facilities would vary in duration depending on scale
and technology. Some would occur at the same time new buildings are being built, while
others would be constructed independently. Construction activities and noise would result in
a minor impact.
CHAPTER 6 January 2016 6 -20 PLANTS AND ANIMALS
PHASE 1 DRAFT EIS
6.6.4.3 Energy Storage Component
Construction of a battery energy storage system would likely occur on currently developed
sites and would be approximately 6 acres in size (Strategen, 2015). However, if a battery
energy storage system is constructed in an undeveloped area, in or adjacent to habitat used by
threatened or endangered species, species of concern or that supports critical survival
activities of these species, then impacts could be significant. Impacts would be moderate to
significant if the project interfered with the breeding, feeding, or movement of native resident
or migratory species. Human activity and noise from construction would have similar
impacts as those described under Option A of Alternative 1, although the construction period
would be much shorter (6 months).
6.6.4.4 Peak Generation Plant Component
Construction of three peak generation plants would occur within or adjacent to existing PSE
substations, possibly including the Lakeside substation. Impacts to plants and animals from
construction would be similar to those described in Section 6.6.4.3.
6.6.5 Alternative 3: New 115 kV Lines and Transformers
6.6.5.1.1 Direct Loss of Habitat
Most of the corridor for Alternative 3 would be co-located or constructed adjacent to existing
PSE corridors or other utility rights-of-way (roadways, rail corridors), but extensions for new
transmission lines could also be constructed through new areas that are currently vegetated.
The types of construction impacts for Alternative 3 would be the same as those described for
Option A of Alternative 1. The extension of shared rights-of-way needed for Alternative 3
would likely be narrower, approximately 40 feet, and involve less construction activity than
for a 230 kV transmission line. However, the transmission corridor for Alternative 3 would
be much longer (60 miles) compared to Alternative 1, Option A (18 miles).
If a new transmission line corridor extension were located entirely in currently vegetated
areas, up to 728 acres of vegetation could be removed, assuming a 60-mile corridor and a
clear zone up to 100 feet in width. This is not likely to occur, because the corridor would
include some portions in existing developed rights-of-way and would not be 100% vegetated.
Assuming an average tree canopy coverage of 40 percent throughout the corridor (see
Section 6.3.3), up to 291 acres of tree canopy could be removed under Alternative 3, in a
worst-case scenario. The impacts would be the same (loss of habitat connectivity,
displacement of species, etc.) as those described for Alternative 1, Option A, but greater in
scale since more acres of vegetation and tree cover could be lost. For these reasons,
Alternative 3 would have the greatest potential to disturb animal species and eliminate habitat
(forest, wetlands, migratory corridors, etc.) of all the options and alternatives. Alternative 3
could result in significant adverse impacts to threatened or endangered species or species of
concern, if their critical survival activities are negatively affected. Impacts would be
moderate to significant if Alternative 3 harmed or interfered with the breeding, feeding, or
movement of native resident or migratory species. However, a new transmission line corridor
would be likely co-located or constructed adjacent to existing PSE easements or other utility
rights-of-way, rather than an entirely new corridor. In this scenario, up to 291 acres of
vegetation could be removed, of which 116 acres could be tree canopy cover, assuming a 60-
January 2016 CHAPTER 6 PLANTS AND ANIMALS 6-21
PHASE 1 DRAFT EIS
mile corridor with a clear zone up to 40 feet in width, with 40 percent tree cover. The actual
impact of a new transmission line corridor would be somewhere between 291 and 116 acres
of trees removed, and would be determined more specifically in Phase 2.
Tree removal for the construction of overhead transmission lines would follow parameters set
by PSE’s Vegetation Management Program, described under the No Action Alternative. This
would be offset by tree planting conducted by PSE within its service area and if new
transmission lines are located along roadways, street trees would be replaced with smaller
trees that remain below the overhead lines. Resulting impacts to habitat or removal of trees
would be subject to the same applicable regulations related to critical areas and tree
protection as described for Alternative 1.
6.6.5.1.2 Disturbance from Construction Noise and Human
Activity
Animals in the vicinity of construction areas could experience noise and human activity for
24 to 28 months, if the new 115 kV transmission line, transformer, and substations are
constructed concurrently. Many animal species would likely avoid the area during
construction periods. Because Alternative 3 would be located in existing corridors, species in
the vicinity are expected to have a tolerance for noise and human activity. Similar to
Alternative 1, Option A, in any given location there would likely be up to a week of
construction activity spread over a period of 2 months. Therefore, in most areas, short-term
impacts are expected to be minor. However, like Alternative 1, impacts could be significant
depending on the timing and species present if the project disturbs or substantially disrupts
critical survival activities (nesting, foraging, and migration) of threatened or endangered
listed species or species of concern.
6.6.5.1.3 Sedimentation of Aquatic Habitats
As discussed above for Alternative 1, Option A, sedimentation of aquatic habitats is expected
to be minimized, and thus minor, with the implementation of best management practices.
Potential impacts would also be reduced if construction activities are largely limited to
existing rights-of-way, utility corridors, or other previously disturbed or developed areas.
Refer to Chapter 5 for more information.
6.6.5.1.4 Contamination of Aquatic Habitats
As discussed above for Alternative 1, Option A, potential contamination or aquatic habitats is
expected to be minimized or eliminated with the implementation of best management
practices. Impacts would be negligible to minor. Refer to Chapter 5 for more information.
6.7 HOW COULD OPERATION OF THE PROJECT AFFECT
PLANTS AND ANIMALS?
6.7.1 Operation Impacts Considered
This section describes how long-term project operation and maintenance could affect plants
and animals within the combined study area. Operational impacts could result from routine
vegetation management around overhead transmission lines; bird electrocution or collisions
with overhead transmission lines or towers; and disturbance of wildlife during maintenance
CHAPTER 6 January 2016 6 -22 PLANTS AND ANIMALS
PHASE 1 DRAFT EIS
activities. Operational impacts would be considered significant, moderate, or minor based on
the same criteria described for construction impacts in Section 6.6.1.
6.7.2 No Action Alternative
Under the No Action Alternative, PSE’s existing maintenance activities and programs would
continue. No utility line or facility construction is likely and there would be no additional loss
of vegetation or disturbance to animals from new permanent structures. However, there will
be continued loss or disturbance of vegetation as a result of PSE’s Transmission Vegetation
Management Program; trees would be trimmed or removed under existing transmission lines
to limit vegetation to low-growing height species. Herbicides would also continue to be
selectively used as part of the program and in accordance with best management practices,
with expected minor impacts on plants and animals.
The types of conservation measures PSE expects to implement to achieve its goals would
occur on customers’ properties. No permanent impacts are likely from operation since new
infrastructure would be minimal and not require substantial clearing or result in other habitat
impacts.
6.7.3 Alternative 1: New Substation and 230 kV Transmission Lines
In general, all four of the options under Alternative 1 would have similar types of operational
impacts. Indirect impacts would occur along new transmission lines, substations, and access
roads as a result of human activity and noise associated with operations and maintenance
(such as vegetation management). Impacts could include displacement of local birds and
other species using the right-of-way or the surrounding area. However, noise impacts are
expected to be minor because species in the combined study area are generally tolerant of
some level of human activity and the duration of noise associated with maintenance is
anticipated to be minimal.
Differences in operational impacts for each transmission line option are discussed below.
Impacts for the substation would be the same for all options.
6.7.3.1 Option A: New Overhead Transmission Line
In addition to the impacts common to all the options described above, transmission towers
and power lines under Alternative 1, Option A could have moderate to significant impacts on
threatened or endangered species, species of concern, or native resident or migratory species.
Depending on the terrain and positioning, transmission towers would range from 85 to 100
feet tall. The presence of transmission towers and power lines could potentially result in an
increase in bird collisions, electrocution, and mortality (PSE, 2013). While there are no
federally listed threatened or endangered bird species with critical habitat in the combined
study area, species such as marbled murrelet and northern spotted owl could occasionally
occur or pass through the corridor. Therefore there would be a potential, although a low
probability, for significant impacts to some threatened or endangered species, through
collisions or electrocution with transmission lines and towers. In addition, there could also be
significant impacts to some species of concern (bald eagles and peregrine falcons), as well as
a potential for similar impacts to other avian species due to injury or mortality caused by
electrocution or collisions with transmission lines and towers. PSE implements an Avian
January 2016 CHAPTER 6 PLANTS AND ANIMALS 6-23
PHASE 1 DRAFT EIS
Protection Program to address avian issues and concerns
with electrical systems, including methods and equipment
to reduce avian collisions, electrocution, and problem nests
(PSE, 2013).
6.7.3.2 Option B: Existing Seattle City Light
230 kV Transmission Corridor
Impacts resulting from maintenance of existing
transmission lines would be similar to those for
maintenance of new lines (Alternative 1, Option A).
Because this option would primarily occupy a corridor that
already has 230 kV overhead lines, there would fewer new
impacts. In the areas where this option would require new
transmission corridor, impacts would be similar to those
described for Option A.
6.7.3.3 Option C: Underground Transmission Lines
Repairs to the transmission line associated with maintenance, system malfunction, or
accident could result in minor impacts to plants and animals in the vicinity of the line, if
additional access points are required. Vaults along the transmission route would likely
provide access to the line, but trenching could be necessary depending upon the location and
nature of the issue. The severity of impacts from these repair activities would depend upon
the extent of repair needed and the alignment of the underground transmission line, but is
expected to be minor. Maintenance activities are expected to be less extensive and less
frequent, compared to the alternatives with above ground transmission lines.
6.7.3.4 Option D: Underwater Transmission Lines
Impacts on plants and animals from operation of underwater transmission lines in Lake
Washington are expected to be minor since the lines would be buried or laid on the lake
bottom below where threatened or endangered aquatic species occur. If the underwater line
were damaged by activities in the lake, it would need to be repaired or replaced, resulting in
temporary impacts similar to those described for construction impacts.
Aboveground and/or underground transmission lines would be required for this option to
connect the underwater transmission line to a substation, as would access roads and
aboveground vaults. The potential operational impacts on plants and animals for
aboveground and underground transmission lines under Alternative 1, Option D would be
similar to those for Options A and C. However, Option D could have fewer operational
impacts on plants and animals since long corridors of upland habitats would be avoided
altogether by the underwater transmission line.
6.7.4 Alternative 2: Integrated Resource Approach
No permanent impacts on plants and animals are likely from operation of energy efficiency,
demand response, or distributed generation components since the infrastructure would be
small and likely located on private properties. Components requiring a larger footprint
Electrocutions happen when
birds directly contact
energized and grounded
conductors or equipment.
Collisions happen when birds
fly directly into conductors,
resulting in injury or mortality
from impact.
Problem nests occur when
nest material on utility towers
touches energized equipment,
potentially conducting
electricity when wet and
igniting, resulting in outages
and hazards to the nesting
birds. (PSE, 2013)
CHAPTER 6 January 2016 6 -24 PLANTS AND ANIMALS
PHASE 1 DRAFT EIS
(energy storage and simple-cycle peak generators) would have the same operational impacts
as those described for substations under Alternative 1. In addition to requiring a larger
footprint, peak generators would also produce increased noise levels. Noise disturbance from
peak generators located in or adjacent to wildlife habitats could be moderate to significant if
mitigation is not effective and if threatened or endangered species, species of concern, or
their critical survival activities were substantially affected, or if the component interferes
with the breeding, feeding, or movement of native resident or migratory species.
6.7.5 Alternative 3: New 115 kV Lines and Transformers
Impacts on plants and animals from Alternative 3 would be similar to those anticipated for
Alternative 1, Option A (moderate to significant). Operational impacts would result from
continued maintenance of vegetation through PSE’s Vegetation Management Program;
potential bird collisions with overhead lines or towers; and human disturbance during
maintenance activities. However, because the length of the corridor proposed for Alternative
3 is substantially longer, the potential for the corridor to cross or be in the vicinity of
functional wildlife habitat, listed species, or species of concern is greater. Therefore, there
would be a greater likelihood of operational impacts to plants and animals.
6.8 WHAT MITIGATION MEASURES ARE AVAILABLE FOR
POTENTIAL IMPACTS TO PLANTS AND ANIMALS?
Short-term impacts on vegetation and habitat caused by development of facilities and
infrastructure would be mitigated through site and facility design to minimize the need for
vegetation and tree removal to the extent feasible. Facilities, access roads, and staging areas
should be located in areas of disturbed vegetation cover if possible. Removal of mature trees
should be avoided where possible in all construction areas. If intact vegetation or habitat is
present, the footprint of the facility should be minimized and situated to result in the least
amount of disturbance. Where possible, vegetation that is removed for construction would be
replaced with appropriate native plant species. PSE has vegetation management permits for
their right-of-way in Bellevue that minimize tree removal in transmission line clear zones
that are located in critical areas in favor of tree pruning where feasible. Revegetated areas
would be monitored to ensure success and invasive species would be controlled.
No specific mitigation is proposed for the temporary displacement of animals because this is
expected to be a minor impact. Wildlife is expected to return following construction except in
areas replaced by facilities. Measures to reduce noise and human activity should be
implemented for construction activities located near undisturbed or functional wildlife habitat
areas such as forests and wetlands, riparian zones, and Lake Washington. During
construction, best management practices would be used to minimize potential impacts from
noise, dust, and turbidity, and established water quality standards and in-water work permit
conditions would be met.
The impacts on animals, including listed species, caused by the development of facilities and
infrastructure would be mitigated through site and facility design to minimize the need for
habitat removal and construction activity. Habitat that is determined to be of significant
importance (e.g., presence of listed species, priority habitats) will be avoided to the greatest
January 2016 CHAPTER 6 PLANTS AND ANIMALS 6-25
PHASE 1 DRAFT EIS
extent possible. Timing of construction work would occur outside of critical time periods for
listed species such as nesting and spawning seasons. Specific measures and pile driving
restrictions will be provided in the project-specific permits from WDFW, Corps of Engineers,
U.S. Fish and Wildlife Service, and National Marine Fisheries Service. The PSE Avian
Protection Program would also be implemented to address avian issues and concerns with
electrical systems, including methods and equipment to reduce avian collisions,
electrocution, and problem nests.
Additional specific mitigation measures would likely be developed as part of the Phase 2
environmental analysis, depending on the exact location, design, and timing of project
elements.
6.9 ARE THERE ANY CUMULATIVE IMPACTS TO PLANTS
AND ANIMALS AND CAN THEY BE MITIGATED?
Urbanization is resulting in overall habitat loss in the combined study area. The proposed
project would contribute to that trend directly by removing trees and habitat for some
alternatives, and indirectly by continuing to supply energy to a growing, developing region.
Of the alternatives for the proposed project that contribute most to this trend are Options A
and C under Alternative 1 and Alternative 3. Mitigation would help to reduce cumulative
impacts, but it would not be able to replace all habitat lost. Other large projects, such as
Sound Transit’s East Link project, overlap with the proposed Energize Eastside Project. The
East Link project will impact plants and animals by continuing to contribute to the trend of
reducing habitat (forested areas) in Bellevue, Redmond, and King County (Sound Transit,
2011).
6.10 ARE THERE ANY SIGNIFICANT UNAVOIDABLE
ADVERSE IMPACTS TO PLANTS AND ANIMALS?
Depending on the alignment selected, Alternative 1 could result in significant unavoidable
adverse impacts to plants and animals, especially if a new corridor is created (Option A).
A new corridor under Alternative 1, Options A and C, located in or adjacent to habitats used
by listed species, could result in permanent habitat alteration and disturbance to these species,
along with species of concern, or native resident or migratory species. Depending on the
scale of habitat alteration and level of disturbance, impacts could be significant. The
overhead or underground lines would be located in existing developed corridors to the extent
possible, but there is a chance that it could be located in undeveloped habitat areas, resulting
in a greater potential for significant impacts. Reconstruction activities under Option B in or
near the location of the rare Vancouver ground cone in Bridle Trails State Park could also
result in significant impacts to the species. Avoidance of habitat used by listed or threatened
species, or species of concern would reduce this impact to a minor or moderate impact.
Underwater noise levels produced during construction of the submerged line under
Alternative 1, Option D could potentially result in injury or death of listed aquatic species,
with potentially significant impacts. Applicable work windows and noise attenuation
CHAPTER 6 January 2016 6 -26 PLANTS AND ANIMALS
PHASE 1 DRAFT EIS
measures will be implemented to mitigate for these potential impacts, and vibratory pile
driving methods will also be used to the extent feasible to further minimize potential
underwater noise effects to a level of non-significance.
The construction impacts from the battery energy storage system component and peak
generators under Alternative 2 could result in similar unavoidable impacts as Alternative 1,
Options A and C if located in or adjacent to habitats used by listed species, species of
concern, or native resident or migratory species. The operation of the peak generators
produces elevated noise levels which could disturb or disrupt listed species, species of
concern, or native resident or migratory species, and could result in significant impacts.
However, these components would be located in currently developed areas to the extent
feasible, and avoidance of habitats used by listed or threatened species, or species of concern
would reduce the magnitude of the impact to non-significant levels.
Alternative 3 could have similar unavoidable impacts as Options A and C under Alternative 1
if a new corridor is located in or adjacent to habitats used by listed species, species of
concern, or native resident or migratory species. However, the corridor would be primarily
co-located or constructed adjacent to an existing, developed corridor, minimizing the
potential for significant impacts.
January 2016 CHAPTER 6 PLANTS AND ANIMALS 6-27
PHASE 1 DRAFT EIS
CHAPTER 7. ENERGY AND NATURAL
RESOURCES
7.1. HOW WERE ENERGY AND NATURAL RESOURCES
IN THE COMBINED STUDY AREA EVALUATED?
This chapter describes at a programmatic level the types of
energy resources used by PSE to generate or provide
electrical power to its customers. This chapter describes
the regulatory context in which PSE operates, including
federal, state, and local government policies and
regulations. See Chapter 1 for a discussion of the overall
process by which electrical energy is generated,
transferred, and delivered.
7.2. WHAT ARE THE ENERGY
DELIVERY POLICIES AND
REQUIREMENTS THAT APPLY
TO PSE?
There are no federal policies or regulations that govern what types of energy resources PSE
should consume. The Energy Independence Act of Washington State affects both the types of
resources to be used and the level of conservation to be implemented. PSE operates under the
regulatory framework described in Chapter 1 to deliver power to the Eastside.
None of the study area communities (Figure 1-4 in Chapter 1) have control over how PSE
uses energy to provide power. However, all of the study area communities have
comprehensive plan energy goals or policies that lead them to encourage, facilitate, promote,
or participate in actions addressing climate change, sustainability, or energy conservation and
efficiency, or reduction of greenhouse gases (which would indirectly lead to changes in types
of energy resources used). Examples are as follows:
• Bellevue Policy UT-70: Facilitate the conversion to cost-effective and
environmentally sensitive alternative technologies and energy sources.
• Newcastle Policy UT-P6: The City shall promote conservation measures to reduce
the need for additional utility distribution facilities in the future.
• King County Policy F-311: King County should encourage its energy utilities to
provide energy efficiency services and renewable energy options to all their
customers. Additionally, the County should encourage the state and energy utilities to
mitigate the environmental and greenhouse gas emissions impacts of energy and, as
conservation and alternative energy sources demonstrate capacity to address energy
Energy and Natural
Resources Key Findings
None of the alternatives would
likely have adverse impacts to
energy or natural resources.
Alternative 2 would not
substantially change the overall
mix of resources used by PSE
to deliver power to its
customers, but would lead to
more local (Eastside) use of
resources for power
generation, some of which
would not be renewable.
January 2016 CHAPTER 7 ENERGY AND NATURAL RESOURCES 7-1
PHASE 1 DRAFT EIS
needs, phase out existing fossil fuel based power plants, especially coal based
sources.
• Issaquah LU Policy F2: Encourage all development and infrastructure in the public
and private sectors which: a. Use less energy and have a lower climate impact, and
incorporate into developments, where possible.
• Redmond Policy FW-10: Additionally, promote efficient energy performance and
use of energy sources that move beyond fossil fuels.
Appendix F lists the currently identified local energy policies.
7.3. WHAT NATURAL RESOURCES ARE USED TO
GENERATE THE ELECTRICAL ENERGY PROVIDED
BY PSE?
As discussed in Chapter 1, PSE expects peak winter electrical power demand on the Eastside
to grow from 619 MW in 2014 to 783 MW in 2024. The power supply to serve this growth in
demand derives from a variety of sources.
In 2013, the overall mix of fuels used by PSE to provide all electricity to all of its customers
was led by hydropower, followed closely by coal, natural gas, and wind energy. Nuclear and
other sources (biomass, landfill gas, petroleum, and waste) each contributed 1 percent or less
(Figure 7-1) (PSE, 2015a). Hydropower and wind are considered to be renewable types of
resources, as opposed to the finite or nonrenewable resources of coal, nuclear, and natural
gas.
Figure 7-1. Energy Sources for PSE Power
Source: PSE, 2015a
CHAPTER 7 January 2016 7 -2 ENERGY AND NATURAL RESOURCES
PHASE 1 DRAFT EIS
The resources used for energy production change over
time and PSE updates its projected mix of energy sources
in its Integrated Resource Plan (IRP) (PSE, 2013) every
two years.
The Energy Independence Act of Washington State
requires that PSE must obtain 15 percent of its electricity
from new renewable resources by 2020, as well as
undertaking cost-effective energy conservation. The Act
also requires PSE to report on its progress toward
achieving renewable energy goals. PSE stated that it was
meeting and exceeding its incremental target for
renewable resource use by the end of 2015, using PSE’s
wind power facilities plus power purchased from
independent producers (PSE, 2015b). Although water is
considered to be a renewable resource, its uses in meeting
the targets of the Act are somewhat restricted. In fact,
most new water-driven electric generation may not be
used to meet the targets.
7.4. HOW WERE POTENTIAL IMPACTS TO ENERGY AND
NATURAL RESOURCES ASSESSED?
The energy analysis considered how construction of the alternatives would likely use energy
(in the form of fuel), as well as the natural resources needed for energy production once the
project became operational. The analysis also assessed how operation of each alternative
would use or conserve energy. Because the Phase 1 Draft EIS is programmatic, and not a
project-level analysis, it is not possible to quantify differences among alternatives with regard
to energy usage. However, this chapter provides a qualitative comparison to indicate the
likely range of impacts among the alternatives. Chapter 4, Greenhouse Gas, evaluates
potential greenhouse gas emissions associated with the alternatives, and the range of potential
impacts associated with loss of carbon sequestration associated with vegetation removal.
In evaluating construction impacts, the relative amounts of energy likely to be used for each
alternative (in the form of fuel used by equipment) was considered, based on information
about likely equipment types and construction durations provided by PSE 1. Information on
equipment usage is contained in Appendix B, and information on duration is found in
Chapter 2. Combining these pieces of information provided a sense of the relative extent of
energy usage that would be likely for construction of each alternative and option.
On the operational side, the analysis considered the types of energy the alternatives would
use to operate and how efficient the alternatives would be in providing energy to customers.
The specific energy conservation features included with each alternative are described in
Chapter 2.
1 These durations are high-level estimates that would need to be refined for project-specific analysis.
PSE’s Integrated Resource
Plan, which is updated every 2
years, is a plan for meeting
forecasted annual peak and
energy demand, plus some
established reserve margin,
through a combination of
supply-side and demand-side
resources, into the future. The
IRP process considers a full
range of power sector
investments to meet new
demand for electricity, not only
in new generation sources, but
also in transmission,
distribution, and demand-side
measures such as energy
efficiency on an equal basis.
January 2016 CHAPTER 7 ENERGY AND NATURAL RESOURCES 7-3
PHASE 1 DRAFT EIS
The alternatives were evaluated to determine whether they would be consistent with energy
policies of local jurisdictions regarding energy and natural resource conservation.
The magnitude of potential energy impacts during construction is classified as minor,
moderate, or significant, which have been defined for this analysis as follows:
Minor – Construction of the project would not likely strain natural resource supplies, but
energy used for operation would contribute to a cumulative shortage of supplies of non-
renewable natural resources providing energy; however, that shortage would not affect the
project over its lifetime or contribute to shortages for other sectors in the foreseeable future.
Moderate –Adequate natural resources would be available to serve the project need, but
building and operating the project would use a critical supply of any given resource, possibly
leading to energy shortages for other sectors or needs.
Significant –Natural resources and energy would not be available to build, or to operate the
project once constructed.
7.5. HOW WOULD CONSTRUCTION OF THE PROJECT
AFFECT ENERGY AND NATURAL RESOURCES?
7.5.1 Construction Impacts Considered
Constructing any of the action alternatives would entail use of fuel. Most of the alternatives
and options would involve use of fossil fuels to power construction equipment, along with
some electrical power. Fuel would likely be used by vehicles in transporting materials or
workers to project sites for any of the alternatives.
7.5.2 No Action Alternative
There would be no construction activities; thus, no related energy or natural resource usage
associated with construction would occur.
7.5.3 Alternative 1: New Substation and 230 kV Transmission Lines
In general, the construction process may use some electrical power for lighting or other
miscellaneous activities, but it would rely primarily on diesel and gasoline fuel, both of
which are expected to remain in good supply in the near future. Therefore, negligible impacts
to energy and associated natural resources are expected from construction of any of the
alternatives.
7.5.3.1. Option A: New Overhead Transmission Lines
Construction of this option would likely use equipment such as auger trucks, dump trucks,
cranes, concrete trucks, backhoes, and bulldozers, as described in Appendix B. Most of this
equipment would operate on diesel fuel. Construction of this option would take
approximately 12 to 18 months. Although Alternative 1, Option A would involve a more
varied type of construction equipment as indicated in Appendix B, its relatively short
duration would likely result in lower fuel usage than Options B or C. Overall, the likely
CHAPTER 7 January 2016 7 -4 ENERGY AND NATURAL RESOURCES
PHASE 1 DRAFT EIS
adverse energy impacts for construction of this option would be negligible considering the
current and likely continuing availability of fuel resources.
7.5.3.2. Option B: Existing Seattle City Light 230 kV Transmission
Corridor
Alternative 1, Option B would require a complete rebuild of the SCL 230 kV lines, including
replacing most of the existing structures (although some structures may be adequate and not
require replacement, reducing the amount of construction equipment and materials needed).
Construction duration would be slightly longer than Option A, approximately 24 months for
overhead lines, with concurrent substation construction, although it could be somewhat less if
major structural rebuild is not required. In any event, adverse energy impacts in the form of
fuel used for construction would be negligible.
7.5.3.3. Option C: Underground Transmission Lines
As with Alternative 1, Options A and B, the equipment involved for construction under
Option C would operate on diesel fuel. Of all the options under Alterative 1, underground
transmission line construction would have the longest construction period (approximately 28
months). Construction for the transformer installations under Option C would likely be
performed concurrently with the transmission line. Additionally, excavation and removal of
soils throughout the construction route would require many more truck trips than the other
options. Therefore, energy usage for construction of Option C would likely be the greatest of
the Alternative 1 options, but would still result in a negligible to minor adverse impact.
7.5.3.4. Option D: Underwater Transmission Lines
As with the other options, the types of construction equipment likely to be needed for this
option would mostly operate on diesel fuel. Eight months would be needed for construction,
with underwater work likely occurring simultaneously with work on land. Negligible adverse
energy impacts are anticipated.
7.5.4 Alternative 2: Integrated Resource Approach
7.5.4.1. Energy Efficiency Component
Negligible energy would be used for this component, which would not involve substantial
infrastructure improvements, changes to maintenance activities, or construction of new or
relocated maintenance yards. Vehicles (gasoline or diesel) would be used to reach job sites
for home improvements, with hand tools (electric or battery powered) used to change out
windows or install appliances, new weatherproofing, etc.
7.5.4.2. Demand Response Component
Energy usage would be the same (or less) as for the energy efficiency component for the
same reason: limited physical site improvements. Vehicles would be used to reach job sites
and hand tools used to install meters.
7.5.4.3. Distributed Generation Component
Some of the same types of equipment would likely be used to construct this component as
would be used for Alternative 1, Option A (backhoes and dump trucks for site grading,
January 2016 CHAPTER 7 ENERGY AND NATURAL RESOURCES 7-5
PHASE 1 DRAFT EIS
delivery trucks, cranes to lift equipment into place). Sites for some of the components could
be similar in size to the substations of Option A. Overall, less energy would likely be needed
for this component than for Option A due to smaller scale of the work. It is not known
exactly how many locations would be involved or the specific sizes of sites. However even
assuming a similar construction duration and size of work areas as for Alternative 1, Option
A, negligible adverse energy impacts would be expected.
7.5.4.4. Energy Storage Component
The site needed to accommodate this component would be essentially a 6-acre paved lot.
Some of the same types of equipment would likely be used to construct this component as
would be used for Alternative 1, Option A (backhoes and dump trucks for site grading,
delivery trucks, cranes to lift equipment into place). The component would take
approximately 6 months to construct. The fuel needed for construction (and potential energy
impacts) would likely be less than for Alternative 1, Option A and would constitute a
negligible adverse impact.
7.5.4.5. Peak Generation Plant Component
This component would involve installing three 20 MW gas-fired simple-cycle generators,
called peak generation plants, at existing substations within the Eastside. Construction of
these peak generation plants would be similar to a substation, including trenching to access
upgraded natural gas, water, and wastewater utility lines. Construction would occur within or
adjacent to existing PSE substations over 12 months with a negligible adverse energy impact,
the same as Alternative 1.
7.5.5 Alternative 3: New 115 kV Transmission Lines and
Transformers
In building 60 miles of new transmission line, along with substation improvements,
Alternative 3 would be the most fuel-intensive of the alternatives. The alternative would be
most similar in duration to Alternative 1, Option C, likely taking between 24 and 28 months
to construct. The same types of equipment would be used to build this alternative as for
Alternative 1 and as with that alternative, the adverse energy impacts would likely be
negligible due to easy availability of fuel resources.
7.6. WHAT ARE THE LIKELY IMPACTS TO ENERGY AND
NATURAL RESOURCES FROM OPERATION OF THE
PROJECT?
7.6.1 Operation Impacts Considered
An increase in the amount of energy needed to operate the project could be considered an
adverse impact, if availability of natural resources needed to generate that energy were to
become more limited. All alternatives require energy (provided by natural resources) to
operate. Depending on the alternative, this could include hydropower, coal, natural gas,
CHAPTER 7 January 2016 7 -6 ENERGY AND NATURAL RESOURCES
PHASE 1 DRAFT EIS
wind 2, nuclear, gasoline or diesel fuel, and waste. None of these resources are anticipated to
be in short supply in the foreseeable future.
All alternatives would involve consumption of small amounts of energy for operational
controls and maintenance. For example, some PSE facilities are lighted (using electrical
energy), and PSE vehicles operating on diesel, gas, electricity, or compressed natural gas
would visit sites for maintenance or repairs as needed. Heating and cooling equipment is also
needed for some facilities. None of these facilities use significant amounts of energy for these
purposes.
Relatively greater inefficiencies in operating an alternative might make it less favorable than
others, but would not necessarily lead to an adverse energy impact given availability of the
resources as discussed above. None of the alternatives include any inherent inefficiencies in
providing power, other than minor losses of electricity that occur over distance along high-
voltage power lines. Some electricity transported over transmission lines is lost due to
resistive heating of the conducting materials and in the transformers. These losses vary based
on the amount of electricity transmitted over the line at any given time relative to the size of
the line. This loss is likely minimal and would not affect the overall efficiency of energy
transmission or the amount of energy that needs to be generated to meet the demand.
An inconsistency with applicable energy policies would likely constitute an adverse impact.
All alternatives would likely be consistent (or at least not inconsistent) with the energy
conservation policies of study area communities described in Section 7.2. This would be true
for Alternatives 1 and 3 due to their inclusion of PSE’s ongoing conservation measures, and
for Alternative 2 due to its increased reliance on such measures.
7.6.2 No Action Alternative
Negligible adverse energy impacts would occur with this alternative. Under this alternative,
with no new infrastructure added, PSE would continue to manage its energy portfolio as
described in its 2013 Integrated Resource Plan (PSE, 2013). Natural resources used to
provide energy for the region could shift as described in Section 7.3, but would be expected
to continue in good supply for the foreseeable future. Because this alternative would not
expand transmission capacity (as PSE indicates is needed), the amount of energy that could
be used on the Eastside during peak periods would be somewhat limited. Therefore, the
alternative could result in slightly lower overall consumption of electricity than the demand
PSE has projected; however, on a broad scale, power generation and use of resources to
generate energy would not likely change. Power generated by existing facilities would likely
be sold to other utilities if available. This alternative would not change PSE’s current
conservation program.
The energy used for operation and maintenance of facilities and equipment under this
alternative would be primarily fuel for vehicles, lighting, and heating and cooling equipment,
the same as currently occurs. Typical vehicles include light- and medium-duty trucks running
2According to the American Wind Energy Association, PSE is the second-largest utility producer of wind
power in the United States (PSE, 2015a).
January 2016 CHAPTER 7 ENERGY AND NATURAL RESOURCES 7-7
PHASE 1 DRAFT EIS
on either diesel fuel or gasoline. PSE’s vehicle fleet also includes some hybrid vehicles, as
well as some vehicles using compressed natural gas (PSE, 2015c).
7.6.3 Alternative 1: New Substation and 230 kV Transmission Lines
Operation of this alternative would not be expected to lead to additional need for power
generation or additional use of resources in power generation. The resources used to generate
power would be the same as those discussed in Section 7.3. As noted in that discussion, types
and percentage of energy resources used can change over time. Conservation and use of
alternative energy would likely be at the same levels as under the No Action Alternative as
described in Chapter 2. Alternative 1 would not change PSE’s current conservation program
and is expected to be consistent with PSE’s legally mandated energy delivery requirements.
7.6.3.1. Option A: New Overhead Transmission Lines
This option would involve the same types of energy usage as the No Action Alternative,
primarily in the form of fuel for vehicles, lighting, and heating and cooling equipment.
Adverse energy impacts from this option would be negligible.
7.6.3.2. Option B: Existing Seattle City Light 230 kV Transmission
Corridor
This option would have the same operational characteristics as the No Action Alternative and
Alternative 1, Option A. Negligible adverse energy impacts would occur.
7.6.3.3. Option C: Underground Transmission Lines
This option would have the same operational characteristics as the No Action Alternative and
Alternative 1, Options A and B, with negligible adverse energy impacts.
7.6.3.4. Option D: Underwater Transmission Lines
This option would have the same operational characteristics as the No Action Alternative and
the other options, with negligible adverse energy impacts.
7.6.4 Alternative 2: Integrated Resource Approach
With its energy efficiency and demand response components, Alternative 2 would increase
use of conservation on the Eastside. The alternative would also lead to slightly less use of
regional energy than the No Action Alternative, or Alternatives 1 or 3. As described in
Chapter 2, Alternative 2 could result in a reduction in demand of power provided via PSE’s
proposed energy sources of approximately 74 MW, assuming the conservation targets
described in Chapter 2 were met.
Although Alternative 2 could lead to less demand for regional power on the Eastside during
peak periods due to increased conservation measures and local power production, that change
in demand is negligible in the overall context of power generation and distribution since the
power needed on the Eastside is a small part of the overall system of power that PSE
provides. In implementing distributed generation and peak power generation locally, the
alternative would lead to a slightly different energy mix than is used for regional power
supply.
CHAPTER 7 January 2016 7 -8 ENERGY AND NATURAL RESOURCES
PHASE 1 DRAFT EIS
7.6.4.1. Energy Efficiency Component
Operation of the energy efficiency component would not use energy over and above No
Action Alternative levels and should lead to less energy usage overall, with more efficient
appliances, better weather proofing, etc. Little fuel would be regularly used by service
vehicles to maintain new features (such as new windows or appliances). The measures
installed with this component would likely incrementally reduce the usage of regionally
produced energy by individual customers, and would have a negligible adverse energy
impact.
7.6.4.2. Demand Response Component
This component would have the same operational characteristics with regard to energy usage
as the energy efficiency component, contributing to some reduction in regional energy usage
by the Eastside, with negligible adverse energy impacts.
7.6.4.3. Distributed Generation Component
As defined for this EIS, the small-scale energy generation facilities that would be constructed
around the Eastside could use waste (a renewable energy resources) in anaerobic digesters or
would rely on non-renewable resources (fossil fuels in the form of diesel or natural gas), to
generate electrical power. Because natural gas and diesel-fueled generators are more readily
controlled3, these were considered the most likely types of new generation facilities for this
analysis, possibly increasing overall use of petroleum products in the region incrementally.
Natural gas that could be needed for this alternative is expected to remain in good supply for
at least the next 100 years, with a strong supply available in the United States (AGA, 2015)
and diesel fuel would also be expected to remain available. Ability to use waste products to
operate generation facilities would depend in part on location of source material and logistics
of transport, but could be considered a practically inexhaustible resource.
The IRP notes that expanded use of natural gas across the region could strain its gas
infrastructure, and that ensuring sufficient gas supply regionally could require expansion of
the Northwest’s gas transmission pipeline system and more underground gas storage
capacity. The IRP also notes that another option for natural gas distribution could involve
PSE development of a liquefied natural gas facility to help meet customer peak demands and
serve marine and road transportation powered with natural gas.
Although the component would not substantially affect large-scale use of energy resources
for power production, this local generation activity would incrementally reduce the usage of
regionally produced energy by individual customers. This component of Alternative 2 could
also lead to an incrementally greater use of non-renewable energy sources, with fossil fuels
as an energy source relied upon for some of the facilities; however, since those energy
sources are in good supply, the component would have a negligible adverse energy impact.
7.6.4.4. Energy Storage Component
Operation of a battery storage facility would be similar to that of a small office building, with
worker vehicle trips and vendor trips to perform periodic replacement of degraded cells. Such
3 See Chapter 2 for a discussion of the reliability of the Alternative 2 components for energy production.
January 2016 CHAPTER 7 ENERGY AND NATURAL RESOURCES 7-9
PHASE 1 DRAFT EIS
trips would be infrequent and not use appreciable amounts of fuel. Operation of this
component would have negligible adverse impacts.
7.6.4.5. Peak Generation Plant Component
This component would involve operation of three peak generation plants at existing
substations within the Eastside, likely simple-cycle gas-fired generators fueled by natural gas.
The plants would be operated to provide power at peak demand times to reduce the demands
on the transmission system, but could be used more regularly to provide power once
installed. These plants would also need to be operated for maintenance purposes at least
monthly (typically permitted for weekly operation of an hour, or 50 hours per year).
As described for the distributed generation component, natural gas is expected to remain in
good supply for the foreseeable future, although distribution infrastructure may need to be
upgraded to deliver fuel supplies. Some worker vehicle trips (using gasoline or diesel fuel)
would also be needed to perform periodic maintenance.
The component could incrementally reduce the usage of regionally produced energy.
Operating this type of facility would lead to incrementally greater use of non-renewable
energy sources, with fossil fuels as the energy source. Even so, the component would be
anticipated to have a negligible adverse energy impact since fossil fuel supplies (natural gas
in this case) are expected to be adequate.
7.6.5 Alternative 3: New 115 kV Transmission Lines and
Transformers
Potential operational impacts of this alternative would be the same as those identified for
Alternative 1, with some maintenance-related vehicle trips needed to service the 115 kV
powerlines and substations over time. Such trips would be infrequent and not result in
appreciable energy usage. Operation of the substation components would also have similar
characteristics as Alternative 1 and would not be expected to lead to additional need for
power generation or additional use of resources in power generation, and the resources used
to generate power would be the same as those discussed in Section 7.3. Conservation and use
of alternative energy would be at the same levels as under the No Action Alternative and
Alternative 1 and this alternative would not change PSE’s current conservation program.
Negligible adverse energy impacts would result from operating Alternative 3.
7.7. WHAT MITIGATION MEASURES ARE AVAILABLE
FOR POTENTIAL IMPACTS TO ENERGY AND
NATURAL RESOURCES?
With no negative impacts to energy and natural resources expected with any alternative, no
mitigation measures would be warranted.
CHAPTER 7 January 2016 7 -10 ENERGY AND NATURAL RESOURCES
PHASE 1 DRAFT EIS
7.8. ARE THERE ANY CUMULATIVE IMPACTS TO
ENERGY AND NATURAL RESOURCES AND CAN
THEY BE MITIGATED?
No cumulative adverse impacts to energy and natural resources are anticipated from any of
the alternatives, including the No Action Alternative. None of the alternatives are expected to
substantially change the regional use or mix of natural resources that would be used to
generate electrical power or affect availability of energy resources for usage by others. PSE is
required to comply with state mandates regarding use of renewable resources and
conservation. Implementing this project would not postpone any of those conservation
measures. Alternative 2 would accelerate and expand energy efficiency and demand response
measures, which would reduce peak demand and also potentially reduce demand throughout
the year. However, it is unclear whether Alternative 2 would establish a long-term trend
toward more localized and independent power generation that might have implications for
reliable power supply to the community in the future.
7.9. ARE THERE ANY SIGNIFICANT UNAVOIDABLE
ADVERSE IMPACTS TO ENERGY AND NATURAL
RESOURCES?
No significant adverse impacts to energy or natural resources are expected from any of the
alternatives.
January 2016 CHAPTER 7 ENERGY AND NATURAL RESOURCES 7-11
PHASE 1 DRAFT EIS
CHAPTER 8. ENVIRONMENTAL
HEALTH
8.1 HOW WAS ENVIRONMENTAL HEALTH EVALUATED
FOR THE COMBINED STUDY AREA?
This chapter provides a high-level discussion of four
types of environmental health concerns raised
during the scoping period:
1. Hazardous materials and the potential to
encounter, handle, or generate them;
2. Public safety risks associated with activities
near pipelines (including those carrying
flammable petroleum products) during
construction or operation;
3. Public safety risks posed by the project
related to natural phenomena such as
earthquakes or lightning; and
4. Health effects from electric and magnetic
fields (EMF) and corona ionization.
Regulations and policies addressing these topics
were investigated to confirm how these issues and
materials are managed.
This chapter provides basic descriptive information
about EMF and corona ionization, including what
they are, how they are generated, and where they
can be found in the environment. This topic is
included to respond to public concern on the topic.
This chapter includes information on the state of the science regarding potential health
effects.
8.2 WHAT ARE THE RELEVANT PLANS, POLICIES, AND
REGULATIONS?
8.2.1 Hazardous Materials
Hazardous materials and wastes, including contaminated soils and groundwater, are
addressed through laws and regulations that address handling, transport, storage, and disposal
of hazardous materials and wastes, as well as management and cleanup of contaminated sites.
Other types of state and local regulations, such as those for stormwater management
described in Chapter 5, also indirectly control hazardous materials. The following list of the
Environmental Health Key
Findings
Hazardous Materials:
Compliance with federal, state,
and local regulations would
likely prevent construction or
operational impacts related to
potential releases of hazardous
materials from occurring,
resulting in a minor potential
for impacts.
Public Safety: Compliance
with safety policies, regulatory
requirements, and industry
standards would likely prevent
construction or operational
impacts related to pipeline
proximity or natural
phenomena, resulting in a
minor potential for impacts.
Further, impacts related to
natural phenomena have a low
probability of occurrence.
EMF or Corona Ionization: No
impacts are anticipated.
January 2016 CHAPTER 8 ENVIRONMENTAL HEALTH 8-1
PHASE 1 DRAFT EIS
primary state and federal regulations that apply to hazardous materials demonstrates the
breadth of the overall regulatory framework.
8.2.1.1 Code of Federal Regulations (CFR)
• 40 CFR, Sections 761.60 – 761.79 (Toxic Substances Act Regulations)
• 40 CFR Sections 260 and 280 (Resource Conservation and Recovery Act
Regulations)
• 40 CFR Part 300 (CERCLA)
• 40 CFR Part 112 (All Appropriate Inquiries)
• 40 CFR, Part 112 (Oil Pollution Prevention)
• 29 CFR 1910.1200 (Occupational Safety and Health Administration [OSHA] hazard
communication standard and requirement for Material Safety Data Sheets for
hazardous chemicals)
8.2.1.2 Washington Administrative Code (WAC)
• Chapter 173-303 WAC (Dangerous Waste Regulations)
• Chapter 173-340 WAC (Model Toxics Control Act)
• Chapter 173-204 WAC (Sediment Management Standards)
• Chapter 173-360 WAC (Underground Storage Tank Regulations)
• Chapter 173-200 WAC (Water Quality Standards for Groundwaters of the State of
Washington)
• Chapter 173-201A WAC (Water Quality Standards for Surface Waters of the State of
Washington)
• Chapter 296-62 WAC (General Occupational Health Standards)
8.2.1.3 Local Codes
Local regulations exist in all of the study area communities that would indirectly address
hazardous material management by regulating water pollution or runoff from construction
sites and spill containment for operating sites. These types of regulations are discussed in
Chapter 5.
8.2.2 Public Safety Risks
8.2.2.1 Activities Near Pipelines
Appendix M provides a list of identified regulations that apply to pipelines, along with
response plans implemented by the Olympic Pipeline Company (OPLC) in particular, since
OPLC’s facilities were identified as a source of concern during EIS scoping. Some of the
regulations are described here.
Congress passed the Natural Gas Pipeline Safety Act in 1968 (now called the Pipeline Safety
Law, 49 USC Section 60101 et seq.). The law gave the federal government authority over
CHAPTER 8 January 2016 8 -2 ENVIRONMENTAL HEALTH
PHASE 1 DRAFT EIS
pipeline safety for transporting hazardous liquids, natural
gas, and other gases. The law left responsibility for
intrastate pipeline safety in the hands of the states, with
the U.S. Department of Transportation, Research and
Special Programs Administration, Office of Pipeline
Safety (OPS) (a federal agency) retaining responsibility
for interstate pipeline safety. The OPS developed
minimum pipeline safety regulations for natural gas
transportation (Title 49 CFR, Part 192). Implementing
regulations are in Chapter 480-93 WAC.
An explosion related to an OPLC pipeline in Bellingham
in 1999 led local governments in Washington to look more
closely at pipeline safety issues and led to changes in
federal and state regulations (Bellingham Herald, 2009).
In 2000, the Pipeline Safety Act of 2000 was enacted in
Washington, enabling the Utilities and Transportation
Commission (UTC) as the interstate agent for pipelines. The act made the UTC able to
enforce federal laws on pipelines in Washington State. The UTC has authority for inspections
of interstate pipelines (UTC, 2015) and oversees the Pipeline Safety Program. This program
provides standards for natural gas pipeline operations and inspects natural gas and hazardous
liquid pipelines (such as the OPLC pipelines) operating in Washington.
The UTC participates with OPS in the certification program for intrastate gas companies and
regulates interstate pipelines under 49 CFR, Part 195. These regulations address safety in
design, construction, testing, operation, maintenance, and emergency response for pipeline
facilities.
The UTC has adopted the American Standard Association Code for Pressure Pipeline
(B31.8), requiring gas companies to have operating and maintenance plan provisions for
periodic leak surveys (UTC, 2015).
In 2002 the federal Pipeline Safety Improvement Act (49 USC 60101) was passed. It applies
to pipelines transporting both natural gas and hazardous liquids in interstate commerce. Some
of the most important aspects of the act are as follows:
• Federal inspection and safety requirements: To help prevent leaks and ruptures,
mandatory inspections of all U.S. oil and natural gas pipelines within 10 years, with
more problematic pipelines to be inspected within the next 5 years and all pipelines
re-inspected every 7 years following the 10-year interval.
• Safety orders: Secretary of the Department of Transportation is allowed to require
corrective action of pipeline facilities.
• Risk analysis: Operators of natural gas pipelines required to conduct analysis of their
pipeline facilities’ risks where located in high-density areas and adopt and implement
integrity management programs for such facilities within 2 years.
Where is the Olympic
Pipeline addressed in this
EIS?
A number of chapters in this
EIS address potential impacts
associated with the Olympic
Pipe Line Company’s
petroleum pipelines through
the combined study area. See
Chapter 3 (Earth - seismic
conditions), Chapter 10 (Land
Use – compatibility and policy
consistency), Chapter 15
(Public Services - emergency
response), and Chapter 16
(Utilities - potential impacts to
pipelines and transmission
lines).
January 2016 CHAPTER 8 ENVIRONMENTAL HEALTH 8-3
PHASE 1 DRAFT EIS
• Increase in penalties: Civil penalty to pipeline operators established for safety
violations in an amount between $25,000 and $100,000 for each violation, and
between $500,000 and $1,000,000 for a related series of violations.
• One-call notification program: Department of Transportation to encourage
operators to adopt and implement certain best practices for notification of leaks and
ruptures.
• Public education programs: Pipeline facilities to establish public education
programs within one year to advise municipalities, schools, and other entities on the
use of the one-call notification system, possible hazards from unintended releases
from a pipeline facility, and what to do in the event of a release.
• Environmental reviews: Structure established for development of a coordinated
environmental review and permitting process to enable pipeline operators to conduct
any necessary pipeline repairs.
• Research and development: National Institute of Standards and Technology and
Departments of Transportation and Energy directed to work with an advisory
committee to develop a plan addressing critical research and development needs to
ensure pipeline safety.
• Whistle-blower protection: Prohibits pipeline operators from firing or taking
adverse action against an employee for providing information regarding pipeline
safety to the employer or to the federal government.
Pipeline safety improvements that have been instituted in
the past 10 years include the following (Pipeline Safety
Trust, 2016):
• Integrity management and inspections;
• Greater transparency in pipeline safety
information;
• Increased fines;
• Public pipeline maps;
• Whistle blower protections;
• 811 – Call Before You Dig;
• Community technical assistance grants;
• Excess-flow valves on distribution pipelines;
• Control room management;
• State Pipeline Safety Advisory Committees; and
• Initiatives on local land use and pipelines.
The State of Washington’s Underground Utilities Damage Prevention Law (RCW 19.122)
requires pipeline companies, underground facility owners, and excavators to participate in
To comply with federal
regulations, the Olympic Pipe
Line Company has an integrity
management program,
including requirements to
regularly inspect and monitor
both natural gas and
petroleum pipelines.
Inspections are performed
using a combination of tools to
determine the suitability of the
pipeline based on any
anomalies detected, including
corrosion, dents, or actual wall
loss (loss of material on the
inside or outside of the
pipeline due to corrosion)
(West, personal
communication, 2015).
CHAPTER 8 January 2016 8 -4 ENVIRONMENTAL HEALTH
PHASE 1 DRAFT EIS
protecting the public health and safety when excavating, with civil penalties for violation.
The law also provides that any excavator who willfully or maliciously damages a field-
marked underground facility may be liable for triple the cost incurred in repairing or
relocating the facility.
In 2006, the federal government enacted the Pipeline Inspection, Protection, Enforcement and
Safety (PIPES) Act, which addresses the following:
• Enhanced communication between operators and excavators;
• Support for and partnership of all stakeholders;
• Operator’s use of performance measures for locators;
• Partnership in employee training;
• Partnership in public education;
• Enforcement agencies’ role to help resolve issues;
• Fair and consistent enforcement of the law;
• Use of technology to improve the locating process; and
• Data analysis to continually improve program effectiveness.
A federally supported effort brought together a large stakeholder group to make
recommendations for procedures and regulations related to land uses and land development
near pipelines. That group, known as the Pipelines and Informed Planning Alliance (PIPA),
produced a report in 2010 that is available for local governments to consider and use in
comprehensive planning and development of land use regulations. The report includes
recommended practices for local governments, property developers and owners, transmission
pipeline operators, and real estate boards to be aware of and to implement as appropriate.
The combined study area communities (Alternatives 1, 2, and 3 as depicted on Figure 1-4 in
Chapter 1) do not directly regulate pipeline safety, but they have the authority to regulate
land uses near pipelines within their jurisdictions to protect public health and safety. Some
communities encourage co-location of pipelines with other utilities where safe, while others
specifically discourage co-location of critical utilities with hazardous fluid pipelines like the
Olympic Pipeline.
Appendix F includes some of the planning policies of King County and the Eastside cities
that directly address co-location of gas pipelines and other developments. The study area
communities would interpret and apply their policies to the project when PSE applies for
permits. Some examples of policies that could address co-location are as follows:
• To reduce the likelihood of pipeline-related safety hazards, King County’s
comprehensive plan restricts land uses within hazardous liquid and gas transmission
pipeline rights-of-way (King County, 2013).
January 2016 CHAPTER 8 ENVIRONMENTAL HEALTH 8-5
PHASE 1 DRAFT EIS
• The City of Bellevue’s comprehensive plan requires that the City administer
regulations and franchise agreement authority over both the Seattle City Light and
Olympic Pipeline infrastructure in their jurisdiction (City of Bellevue, 2015).
• The City of Kirkland’s comprehensive plan includes policies that: establish standards
to minimize pipeline damage, prohibit new high consequence land uses1 from
locating near a hazardous liquid pipeline corridor, support coordination with the
pipeline operator when developments are proposed near the pipeline corridor, and
require maintenance of the hazardous liquid pipeline corridor through their franchise
agreement and other mechanisms (City of Kirkland, 2015).
• The City of Redmond’s comprehensive plan has policies related specifically to
pipeline safety, addressing required setbacks for adjacent land uses and structures,
mitigation for certain types of adjacent land uses, and prohibition of new high
consequence land uses near pipelines (City of Redmond, 2015).
• The City of Renton’s plan includes a goal promoting safe transport and delivery of
fuels and one policy encouraging co-location of utilities with rights-of-way and utility
corridors. The City also has a code (RMC 4-3-070) requiring notice on title regarding
proximity to hazardous pipelines (City of Renton, 2015).
• The City of Newcastle encourages combining utilities into single corridors where safe
(City of Newcastle, 2015).
8.2.2.2 Natural Phenomena
Local governments have regulations in place to address structural design and stability,
including earthquakes as discussed in Chapter 3. Each study area community also
implements codes conforming to International Building, Mechanical, and Fire Codes, which
have been enacted to safeguard public health, safety, and general welfare. These codes
address issues such as structural strength, stability, and protection of life and property from
fire and other hazards. Projects in known seismic hazard areas require special geotechnical
review.
The National Electrical Safety Code (NESC, 2012) provides the safety guidelines that PSE
follows during the installation, operation, and maintenance of transmission lines and
1 High Consequence Land Use: A land use that if located in the vicinity of a hazardous liquid pipeline
represents an unusually high risk in the event of a pipeline failure due to characteristics of the inhabitants or
functions of the use. High consequence land uses include:
1. Land uses that involve a high-density on-site population that are more difficult to evacuate. These
uses include:
• Schools (through grade 12).
• Hospitals, clinics, and other facilities primarily for use by the elderly or handicapped, other than
those within single-family residences.
• Stadiums or arenas.
• Day care centers, and does not extend to family day care or adult family homes.
2. Land uses that serve critical “lifeline” or emergency functions, such as fire and police facilities, utilities
providing regional service, or water supplies if exposed to a significant risk that will curtail its lifeline
function for a critical period of time.
3. Uses with similar characteristics as determined by the Planning Official.
CHAPTER 8 January 2016 8 -6 ENVIRONMENTAL HEALTH
PHASE 1 DRAFT EIS
associated equipment. The NESC contains the basic provisions considered necessary for
worker and public safety under specific conditions, including electrical grounding and
protection from lightning strikes.
8.2.3 Electric and Magnetic Fields
The City of Bellevue has adopted comprehensive plan policies that encourage City and utility
involvement with regional or statewide agencies when and if they are developing policies
regarding exposure to EMF. The policies also address intent to stay abreast of new accepted
scientific research of potential health impacts, revise policies if the situation warrants, and
require a reasonable balance between potential health effects and costs of mitigating for such
impacts in the planning, siting, and construction of electrical infrastructure.
Only two states (Florida and New York) have enacted their own standards related to EMF
that are applicable to parties other than electrical workers. These two states have standards
for magnetic fields from overhead transmission lines. The foundation of these standards was
to make the field levels from new overhead transmission lines similar to those from existing
overhead lines. Table 8-1 presents a summary of the state standards for magnetic fields
permitted (National Institute of Environmental Health Science [NIEHS], 2002).
Table 8-1. State Transmission Line Magnetic Field Standards and Guidelines
State Magnetic Field at ROW Edge
Florida 150 mG (max load)1
200 mG (max load)2
250 mG (max load)3
New York 200 mG (max load)
Notes:
1For lines of 69-230 kV.
2For >230 and ≤500 kV lines.
3For >230 and 500 kV lines on certain existing ROW.
ROW = right-of-way (or in Florida standard, certain additional areas adjoining the right-of-way).
mG = milligauss
max load = maximum load-carrying conditions
Source: NIEHS, 2002
Guidelines and standards have been developed by three organizations for limiting magnetic
field exposure for the general public and/or workers (Tables 8-2, 8-3, and 8-4). Guidelines
and standards developed for limiting EMF exposure are based on known biological effects
from very high fields, such as occur in some occupations.
The guidelines are published by the International Commission on Non-Ionizing Radiation
Protection (ICNIRP); the guidelines of the American Council of Governmental Industrial
Hygienists (ACGIH), which apply to workers in the United States; and the International
Committee on Electromagnetic Safety (ICES), operating under the oversight and rules of the
Institute of Electrical and Electronics Engineers (IEEE) Standards Association (IEEE
guidelines).
January 2016 CHAPTER 8 ENVIRONMENTAL HEALTH 8-7
PHASE 1 DRAFT EIS
Table 8-2. Summary of ICNIRP Exposure Guidelines
Exposure (60 Hz) Magnetic Field
Occupational 10 G (10,000 mG)
General public 2.00 G (2,000 mG)
G = gauss; Hz = hertz; ICNIRP = International Commission on Non-Ionizing Radiation Protection;
mG = milligauss
Source: ICNIRP, 2010
Table 8-3. Summary of ACGIH Exposure Guidelines
Exposure (60 Hz) Magnetic Field
Occupational exposure should not exceed: 10 G (10,000 mG)
Prudence dictates the use of protective clothing above: ___
Exposure of workers with cardiac pacemakers should not
exceed: 1 G (1,000 mG)
ACGIH = American Council of Governmental Industrial Hygienists; G = gauss; Hz = hertz; mG = milligauss
Source: ACGIH, 2009
Table 8-4. IEEE Exposure Levels for 60 Hz Magnetic Fields
Exposure (60 Hz) Magnetic Field
General public should not exceed: 9,040 mG (9.04 G)
Controlled environments should not exceed: 27,100 mG (27.1 G)
G = gauss; Hz = hertz; IEEE = Institute of Electrical and Electronics Engineers; mG = milligauss
Source: IEEE, 2002
8.2.4 Corona Ions
There are no known policies, regulations, or standards addressing corona ionization.
8.3 WHAT HAZARDS ARE PRESENT IN THE COMBINED
STUDY AREA OR COULD BE ASSOCATED WITH THE
PROJECT?
8.3.1 Hazardous Materials
Hazardous materials are generally defined as any substance or material that could adversely
affect the safety of the public, handlers, or carriers during transportation. Hazardous materials
would only be considered to generate environmental impacts if they were spilled or released
in an uncontrolled fashion. A range of hazardous materials could be used in the construction
and operation of any of the alternatives. Gasoline and oil would be used in construction
equipment discussed in Chapter 2, and other chemicals such as solvents or paint may be
brought onto and used on the project sites during construction.
CHAPTER 8 January 2016 8 -8 ENVIRONMENTAL HEALTH
PHASE 1 DRAFT EIS
Operating and maintaining any of the newly constructed PSE-owned facilities would also
involve use of some hazardous materials. Gasoline, paint, or pesticides could be used for site
maintenance. The operation of Alternative 1 or 3 would involve transformers with insulating
oil or sulfur hexafluoride (SF6) and possibly high-pressure fluid-filled (oil-containing)
(HPFF) conductors. (Alternative 1, Option D would likely use only cross-linked polyethylene
(XLPE) type cable rather than HPFF type.) The transformers would be installed without their
insulating oils or SF6, which would be brought onto the site and added to the equipment once
it is in place. Energy storage (batteries) installed with Alternative 2 would likely contain
some type of acid. Operation of any the distributed generation components would involve
gasoline, diesel, or other types of fuel.
It is possible that contaminated soils or groundwater could already exist where the
alternatives would be constructed. Historical land uses (logging, agriculture, industry, or
others) may have discharged materials now known to be hazardous in nature. These types of
materials can accumulate in soils or groundwater. Existing land uses in the combined study
area also handle or store hazardous materials, including gas stations or automotive service
stations, and residential properties where paints or pesticides may be used.
Electrical infrastructure already existing on the Eastside includes transformers and other
electrical equipment and transmission lines. PSE does not operate any HPFF or self-
contained fluid filled (SCFF) lines on land through the combined study area. These types of
lines contain pressurized gas or fluid (usually nitrogen or synthetic oil) and may contain
polychlorinated biphenyls (PCBs). PSE does operate two SCFF marine cables that cross Lake
Washington to Mercer Island (Strauch, personal communication, 2015).
Small “distribution” transformers are found on
transmission line poles around the Eastside. These devices
step down the voltage being sent along distribution lines
to the level that can be used by customers. All of these
distribution transformers contain some amount of
insulating oil (usually highly refined petroleum/mineral
oil), and older ones may contain PCBs. The larger
transformers at substations also usually contain insulating
oil, and there may be some older ones in operation
throughout the Eastside with insulating oil containing
PCBs. Newer transformers may also contain an insulating
gas, sulfur hexafluoride (SF6), rather than oil.
As described in Chapter 16, high-pressure natural gas
mains and distribution pipelines are found throughout the
area. The Olympic Pipe Line Company (OPLC) operates
two underground fuel pipelines carrying petroleum
products under pressure. These two petroleum lines
traverse the Eastside from north to south and are located
primarily in the same corridor as existing 115 kV
transmission lines operated by PSE. These types of
pipelines are described in Chapter 16 and shown on
PCBs were historically widely
used as dielectric (poor
conductor of electricity) and
coolant fluids in electrical
equipment and by industries
such as machining operations.
According to the U.S.
Environmental Protection
Agency, PCBs cause cancer in
animals and are probable
human carcinogens. The
production of PCBs has been
banned in the U.S. and
elsewhere.
SF6 is used in the electrical
industry as a gaseous
dielectric medium for high-
voltage circuit breakers,
switchgear, and other electrical
equipment, often replacing oil
filled circuit breakers (OCBs)
that can contain harmful PCBs.
SF6 is a highly toxic gas.
January 2016 CHAPTER 8 ENVIRONMENTAL HEALTH 8-9
PHASE 1 DRAFT EIS
Figure 16-1. Damage to these pipelines could release materials they carry to the environment.
These materials (natural gas, gasoline, diesel, and aviation fuel) have the properties listed in
Table 8-5 (the specific properties can vary somewhat depending on formulation and
additives).
Table 8-5. Properties of Materials Carried by Fuel Pipelines
Material Typical Properties and Their Effect on Human and Aquatic Health
Diesel Combustible liquid. Contact with this product may cause skin and eye
irritation. Prolonged or repeated contact may cause skin irritation, defatting,
drying, and dermatitis. Inhalation of this product may cause respiratory tract
irritation and central nervous system depression, symptoms of which may
include weakness, dizziness, slurred speech, drowsiness, unconsciousness
and, in cases of severe overexposure, coma and death. Ingestion of this
product may cause gastrointestinal irritation. Aspiration of this product may
result in severe irritation or burns to the respiratory tract.
Gasoline Extremely flammable liquid and vapor. Vapor can cause flash fire. Cancer
hazard. Causes skin and eye irritation. Can enter lungs and cause damage.
Aviation Fuel Flammable liquid and vapor. Can be ignited by heat, sparks, flames, or other
sources of ignition (e.g., static electricity, pilot lights, mechanical/electrical
equipment, and electronic devices such as cell phones, computers,
calculators, and pagers that have not been certified as intrinsically safe).
Vapors may travel considerable distances to a source of ignition where they
can ignite, flash back, or explode. May create vapor/air explosion hazard
indoors, in confined spaces, outdoors, or in sewers. This product will float
and can be reignited on surface water. Vapors are heavier than air and can
accumulate in low areas. If container is not properly cooled, it can rupture in
the heat of a fire. Causes skin irritation. May be fatal if swallowed and enters
airways. May cause drowsiness or dizziness. Toxic to aquatic life with long-
lasting effects.
Natural Gas Extremely flammable gas. Can be ignited by hot surfaces, sparks, vehicles,
lights, electronic devices, or other sources of ignition. Overexposure to this
gas can result in shortness of breath, drowsiness, headaches, confusion,
decreased coordination, visual disturbances and vomiting; these symptoms
are reversible if exposure is ended. Continued exposure can lead to
inadequate oxygen (hypoxia), rapid breathing, discoloration of the skin
(cyanosis), numbness of extremities, unconsciousness, and death. If natural
gas leaks underground, it can permeate through the soil and accumulate in
confined spaces such as basements or sewers.
Note: Specific properties can vary somewhat depending on formulation and additives.
Source: Material Safety Data Sheets (MSDSOnline, 2015)
Operation of the project over time could generate hazardous or dangerous2 wastes needing
special management. Site lighting with any of the alternatives could contain mercury ballasts
2 In Washington, the term “dangerous waste” is used, while the federal rules use the term “hazardous
waste.” The state rules are more protective than the federal rules, so dangerous waste includes more
wastes than the federal definition. The Washington Dangerous Waste Regulations (Chapter 303 WAC) are
based on the federal Resource Conservation and Recovery Act, but Washington requires businesses to
follow additional rules.
CHAPTER 8 January 2016 8 -10 ENVIRONMENTAL HEALTH
PHASE 1 DRAFT EIS
that would be regularly changed out and need proper disposal. Mineral oil or SF6 of the
transformers in Alternatives 1 or 3 could need to be recharged over time. Operation of
anaerobic digesters for the distributed generation component of Alternative 2 leaves a
byproduct known as digestate (the solid remnants of the original input material to the
digesters) that must be properly characterized for disposal. Operating the engines and
turbines of Alternative 2 may generate sludge materials that would be cleaned out. All of
these waste materials would need to be characterized and disposed of properly.
8.3.2 Public Safety Risks – Activities Near Pipelines
If ruptured or damaged, fuel pipelines mentioned in Section 8.1.1 could pose a risk to public
safety and the environment due to high operating pressure and/or the highly flammable,
explosive, and toxic properties of the transported products. If damage prevention measures
were not employed and any of these pipelines were damaged, and standard pipeline safety
protocols and mechanisms were then to fail, there would be a risk of explosion and fire.
Other pipelines (natural gas in particular as described in Chapter 16) are found throughout the
area and could have some of the same risks as the OPLC pipelines.
8.3.3 Public Safety Risks – Natural Phenomena
As described in Chapter 3, the Eastside is located in a seismically active region. Existing
infrastructure (substations, transmission and distribution lines) is at risk of damage in the
event of an earthquake. New infrastructure constructed for the Energize Eastside Project
would be at the same risk. Damage to infrastructure from an earthquake poses a risk of fires,
electrocution, and explosion that could potentially endanger nearby populations. Similarly,
electrical infrastructure could experience fires after damage by lightning strikes, leading to
potential public safety risks. Both earthquakes and lightning strikes could also lead to damage
to fuel pipelines described above.
8.3.4 Electric and Magnetic Fields and Corona Ionization
There has been substantial research into the possibility of health effects from EMF, as well as
potential effects from corona ionization. There is substantial agreement among experts that
there are no confirmed adverse health impacts from 60 hertz (Hz) 3 EMF exposure. Scientific
evidence remains inconclusive on risk of childhood leukemia in homes with stronger
magnetic fields, and research on this topic continues. However, while it does not appear that
EMF and corona ionization are in fact a hazard, they are discussed in this document due to
public concerns raised during EIS scoping.
Transmission lines, electrical wiring, and appliances all produce EMF. Corona ionization is
associated with transmission lines. It is the electrical breakdown of air in very strong electric
fields. Corona ionization can be a source of audible noise, electromagnetic radiation, and
sometimes visible light from transmission lines. Sections 8.3.5 and 8.3.6 provide background
information about these topics.
3 Electricity is transmitted in North America at 60 cycles per second, or 60 Hz.
January 2016 CHAPTER 8 ENVIRONMENTAL HEALTH 8-11
PHASE 1 DRAFT EIS
8.3.5 Electric and Magnetic Fields
Electric and magnetic fields each have different origins and
different properties. Electric fields are produced by the voltage
in use, and magnetic fields are produced by current. Figure 8-
1 demonstrates voltage and current and how they relate.
Most electrical equipment has to be turned on (current must be
flowing) for a magnetic field to be produced. Electric fields
are often present even when the equipment is switched off, as
long as it remains connected to the source of electric power.
Brief bursts (sometimes called transients) can also occur when
electrical devices are turned on or off.
Electric fields are shielded or weakened by materials that
conduct electricity, even materials that conduct poorly,
including trees and buildings. Magnetic fields, however, pass
through most materials without change.
The amount of current, and therefore magnetic field strength,
varies with the amount of electrical power being used at any
moment (see Figure 8-2). Magnetic fields are commonly
measured in milligauss (mG) or gauss (G), and microtesla
(µT) or tesla (T). The terms in this chapter include milligauss,
gauss, and microtesla. For non-magnetic materials such as air,
one tesla is equivalent to 10,000 gauss.
Figure 8-1. Two Electrical Terms: Voltage and Current
Source: NIEHS, 2002
Information on EMF
fundamentals provided in this
chapter is based primarily on
documents prepared by the
NIEHS (2002) and the Electric
Power Research Institute (EPRI)
(2012). Some information about
magnetic field levels for specific
types of proposed project
facilities was also provided by
Enertech Consulting as noted in
the section.
The NIEHS is one of 27 research
institutes and centers that
compose the National Institutes
of Health (http://www.nih.gov/),
U.S. Department of Health and
Human Services. The mission of
the NIEHS is to discover how the
environment affects people in
order to promote healthier lives.
The EPRI is a nonprofit
institution that conducts
research, development, and
demonstration relating to the
generation, delivery, and use of
electricity.
CHAPTER 8 January 2016 8 -12 ENVIRONMENTAL HEALTH
PHASE 1 DRAFT EIS
Figure 8-2. Electrical and Magnetic Fields Produced by Voltage and Currents
Source: NIEHS, 2002
Electric fields and magnetic fields are characterized by their wavelength, frequency, and
amplitude (strength). Figure 8-3 shows the waveform of an alternating electric or magnetic
field 4. The direction of the field switches from one polarity to the opposite and back to the
first polarity in a period of time called one cycle. Wavelength is the distance between a peak
on the wave and the next peak of the same polarity. The frequency of the field describes the
number of cycles that occur in 1 second and is measured in hertz (Hz).
Figure 8-3. Frequency and Wavelength
Source: NIEHS, 2002
4 The term electromagnetic is generically used in Figure 8-3. However, this EIS refers to electric fields and
magnetic fields separately because they are not coupled or interrelated the same way at extreme low
frequencies (60 Hz) as they are at higher frequencies.
January 2016 CHAPTER 8 ENVIRONMENTAL HEALTH 8-13
PHASE 1 DRAFT EIS
A range of frequencies of EMF can occur. The terms EMF and ELF are both used in this
discussion. Electricity generation, transmission and use in North America is almost entirely at
60 Hz, a frequency that falls in the extremely low frequency (ELF) range of 3 to 3,000 Hz, at
the low end of the overall frequency spectrum. ELFs include the power-frequency fields of
50 or 60 Hz associated with generation, transmission, and use of electric power. The overall
term of EMF includes ELFs and higher frequency fields. At the other end of the frequency
spectrum from ELF is ionizing radiation, such as x-rays and gamma rays, with frequencies in
the range of a billion-billion cycles per second. In the middle of the spectrum (millions to
billions of cycles per second) are the radio-frequency fields used for TV, radio, cell phones,
and microwaves. The higher frequency or radiofrequency magnetic fields are generated by
many different technologies, including broadcast TV and radio, cell phones, and other radio
communications.
Even though electrical equipment, appliances, and transmission lines produce both electric
and magnetic fields, most recent research has focused on potential health effects of magnetic
field exposure. This is because some epidemiological studies have reported an increased
cancer risk associated with estimates of magnetic field exposure. No similar associations
have been reported for electric fields; many of the studies examining biological effects of
electric fields were essentially negative. Since there have been no observed health effects
related to electric fields, the discussion of EMF from this point forward focuses on the
magnetic field component only.
As noted above, electric fields are easily shielded or weakened by conducting objects such as
buildings; as they pass through these objects, their energy is quickly dispersed. Magnetic
fields generated by electrical equipment and appliances are not shielded or weakened by such
objects. Magnetic fields found very close to electrical appliances and power tools are often
much stronger than those near other sources, such as magnetic fields directly under
transmission lines. However, the fields surrounding appliances and electric motors decrease
in strength with distance more quickly than transmission line fields because of the confined
wiring configuration in appliances and motors. Figure 8-4 provides a sample of how a
magnetic field related to a common type of household equipment changes over distance (also
see Table 8-6).
CHAPTER 8 January 2016 8 -14 ENVIRONMENTAL HEALTH
PHASE 1 DRAFT EIS
Figure 8-4. Magnetic Field Strength Decreases with Distance
Source: NIEHS, 2002
Magnetic field strength from a transmission line (or other electrical infrastructure) also
reduces in strength (attenuates) rapidly with distance. The rate of magnetic field attenuation
is different for an overhead line configuration versus an underground (or underwater) line
configuration. Figure 8-5 presents a generalized diagram of calculated magnetic field strength
as a function of distance away from a transmission line, for both overhead and underground
line configurations.
For underground lines, the conductors are encased with insulating material. Conductors can
therefore be placed very close to one another (often bundled together within a common pipe
or duct). Whenever energized conductors are close together, the magnetic field cancellation
between these conductors is increased significantly. For underground lines, the magnetic
field typically decreases in strength as a function of 1/d3 (where d = distance) in distance
from the transmission line (Enertech, 2016).
For overhead lines, the air is used as an insulator between each of the phase conductors,
resulting in a larger distance separation between the conductors than with underground lines.
Whenever energized conductors are spread farther apart, the magnetic field cancellation
between the conductors is diminished. For overhead lines, the magnetic field typically
decreases in strength with the square of distance (1/d2) from the transmission line (Enertech,
2016).
January 2016 CHAPTER 8 ENVIRONMENTAL HEALTH 8-15
PHASE 1 DRAFT EIS
Figure 8-5. Sample of Magnetic Field Diminishing at Distance from Transmission
Lines
Source: Enertech Consulting
Note: This graphic does not include data for underwater lines. Water, like earth, does not reduce magnetic
fields; therefore underwater cables can be considered the same as underground lines for purposes of this
EIS.
For overhead lines, the conductor (at midspan) is farther away from the ground surface than
the underground cables are below ground. Underground cables are potentially closer to
people than overhead lines. Therefore, the magnetic field is generally higher directly above
an underground cable than it is below an overhead line. However, because the underground
cables are close to one another, the magnetic field strength decreases very rapidly with
distance away from the cables due to their magnetic field cancellation. This is different from
overhead lines, where the magnetic field strength persists farther away from the line since the
conductors are spread farther apart than with underground lines, and the magnetic strength
decreases more slowly over the distance (Enertech, 2016). People walking directly over the
center of underground transmission lines would experience higher magnetic fields than if
they were walking directly underneath overhead lines, but if walking several feet away from
the center of the line, magnetic fields from underground lines would drop off more quickly.
Underwater transmission line cables have magnetic field attenuation characteristics similar to
underground cables. The magnetic field typically decreases in strength as a function of 1/d3 in
distance from the underwater cable. However, the public is unlikely to be near underwater
cables in deep water (at the bottom of Lake Washington). In shallow water, magnetic field
levels would be comparable to underground cables.
CHAPTER 8 January 2016 8 -16 ENVIRONMENTAL HEALTH
PHASE 1 DRAFT EIS
8.3.5.1 Status of Scientific Research on Electric and Magnetic Fields
8.3.5.1.1 Magnetic Field Exposure
Most people in the United States are exposed to
magnetic fields that average less than 2 milligauss
(mG) in strength, although exposures for each
individual vary. Average magnetic field levels within
rooms have been found to be approximately 1 mG
based on several large surveys, while in the
immediate area of appliances, the measured values
ranged from 9 to 20 mG (Severson et al., 1988; Silva
et al., 1998). Another study of 992 homes reported
the average residential magnetic field value at 0.9
mG (Zaffanella, 1993). The closest local participants
in this study were the City of Seattle and Seattle City
Light.
Table 8-6 lists the median magnetic field levels in mG generated by electrical appliances
typically found in households. The strength of the magnetic field does not depend on the
complexity, size, or power of the appliance. Large appliances often have weaker magnetic
fields than small devices.
Table 8-6. Median Magnetic Fields Generated by Household Appliances in
Milligauss (mG)
Appliance Distance from Source
6 inches 4 feet
Bathroom
Hair dryers 300 -
Electric shavers 100 -
Family Room
Ceiling fans 3 -
Window air conditioners 3 -
Televisions1 7 -
Bedroom
Digital clock2 1 -
Baby monitor 6 -
Laundry/Utility
Dryer 3 -
This section describes the scope
and findings of studies published
through mid-November 2015 by
organizations that continue to
examine the possible health effects
from power-frequency EMF, such
as the World Health Organization
(WHO), NIEHS, Advisory Group on
Non-Ionizing Radiation of the
Health Protection Agency of
England, and International Agency
for Research on Cancer (IARC)
(Sheppard, 2015).
January 2016 CHAPTER 8 ENVIRONMENTAL HEALTH 8-17
PHASE 1 DRAFT EIS
Appliance Distance from Source
Washing machine 20 -
Iron 8 -
Portable heaters 100 -
Vacuum cleaner 300 1
Kitchen
Blender 70 -
Can opener 600 2
Coffee maker 7 -
Dishwasher 20 -
Food processer 30 -
Garbage disposal 80 -
Microwave oven3 200 2
Mixer 100 -
Electric oven 9 -
Electric range 30 -
Refrigerator 2 -
Toaster 10 -
Workshop
Battery charger 30 -
Drill 150 -
Power saw 200 -
Source: EMF in Your Environment, U.S. Environmental Protection Agency, 1992, as cited in NIEHS, 2002.
Notes:
Dash (-) means that the magnetic field at this distance from the operating appliance could not be
distinguished from background measurements taken before the appliance had been turned on.
1 Some appliances produce both 60 Hz and higher frequency fields. For example, televisions produce fields
at 10,000 to 30,000 Hz (10 to 30 kHz) as well as 60 Hz fields.
2 Most digital clocks have low magnetic fields. In the example in this table, the clocks are electrically
powered using alternating current, as are all the appliances described in this table.
3 Microwave ovens produce 60 Hz fields of several hundred milligauss, but they also create microwave
energy inside the appliance that is at a much higher frequency (about 2.45 billion Hz). Users are shielded
from the higher frequency fields but not from the 60 Hz fields.
CHAPTER 8 January 2016 8 -18 ENVIRONMENTAL HEALTH
PHASE 1 DRAFT EIS
8.3.5.1.2 Research Background
Over the last 40 years, hundreds of scientific studies have been carried out around the world
to determine whether exposure to EMF can have harmful health effects. In order to draw
valid scientific conclusions, the same or similar results must be seen by different
investigators, who may employ different scientific approaches addressing the same question.
Studies of potential adverse health effects from EMF associated with electric power systems
began in the early 1960s as electric power systems moved to higher transmission line
voltages of 345 kV and above. Research initially was focused on effects of strong electric
fields to which workers could be exposed, though by the 1980s public and scientific interest
shifted to weak magnetic fields, the area in which EMF research continues to date. While
research on both electric and magnetic fields has answered many questions and brought
consensus on certain topics, uncertainty remains as a result of contradictory and inconclusive
research results.
8.3.5.1.3 Research Methods
A number of scientific methods and topics in biology, human disease, biophysics, and
engineering feed into answering questions bearing on public health. Research falls into these
general categories:
• Epidemiology;
• Laboratory studies of humans, animals, tissues, and cells; and
• Theoretical analyses.
Epidemiology is the study of patterns and possible causes of diseases in human populations.
Epidemiologists study short-term health conditions, such as outbreaks of food poisoning, as
well as long-term diseases such as cancer and heart disease. Results of these studies are
reported in terms of statistical associations between various factors and disease.
Epidemiological studies often drive public health discussion and risk assessment because the
research directly concerns humans.
Epidemiology has the significant challenge of determining whether statistical findings reflect
a true causal association or whether other factors (notably, confounders) are involved. To a
non-expert the language of epidemiology can appear more precise and definitive than it is. A
statistically significant finding indicates a probability that the finding occurred above a
certain level of chance, and regardless of statistical probability, a positive association does
not itself provide proof of a cause-and-effect relationship. Typically, supplemental data are
needed from multiple epidemiologic approaches and other study methods before a causal
relationship can be established. The other study methods that bear on whether an agent such
as EMF causes disease include clinical studies of humans, and laboratory studies with
animals, biological tissue, and cells.
A recurrent feature of EMF science is that effects tend to be small and difficult to reproduce
even after undertaking considerable effort to match experimental conditions. This is an
important limitation that prevents drawing firm conclusions. It is noteworthy that there has
been difficulty in replicating animal studies that have reported adverse effects. Taken
January 2016 CHAPTER 8 ENVIRONMENTAL HEALTH 8-19
PHASE 1 DRAFT EIS
together with the inconclusive nature of the epidemiological research, there is consequently a
high level of skepticism among many scientists that the positive associations of some
epidemiological analyses are scientifically valid. There is therefore skepticism about the role,
if any, that ELF magnetic fields play in human health. Skepticism also is promoted by studies
indicating that environmental ELF fields are too weak to produce effects in cells, tissues,
organs, animals, or humans.
8.3.5.1.4 Ongoing Research and Unresolved Issues
Work is still underway to find answers to questions about EMF and possible health effects.
Some examples include the following:
• Research on childhood leukemia – Large studies continue, with one being
conducted in California sponsored by the Electric Power Research Institute.
• Research on co-carcinogenesis – Questioning whether one or more agents, such as
EMF plus a biochemical, environmental, chemical, or physical agent, act together to
exacerbate the growth and expansion of tumor cells, while alone one such agent may
not have an effect.
• Research on neurodegenerative diseases – There are suggestive findings of a
connection between neurodegenerative diseases, particularly amyotrophic lateral
sclerosis (ALS), and magnetic fields, though there is no known mechanism for such
an effect. Worker studies are in process to examine the possibility that frequent
electric shock may increase the risk of ALS, rather than EMF.
• Research on EMF interference with implanted medical devices – Longstanding
research has concerned possible interference with the functioning of implanted
devices such as cardiac pacemakers, which is of most concern within occupational
environments. However, certain devices in use close to very high-voltage electric
fields remain a potential concern for the general public. Exposure guidelines have
been developed for workers, and manufacturer data sheets provide limitations on
device performance during EMF exposure. Work is continuing to develop laboratory
bench testing and a more precise understanding of EMF tolerances of these devices.
8.3.5.1.5 Summary of Research Findings on EMF
Conclusions on public impacts of EMF exposure cannot be obtained from a single study or a
small number of studies. Such conclusions require a considerable body of evidence placed in
the context of biological knowledge, obtained from laboratory experiments and physical
principles. To meet the challenge of fairly assessing the information, public health analysts
assemble evidence from the entire body of science using established measures and
techniques. The methods of the “Weight of the Evidence for Carcinogenicity” developed by
the U.S. Environmental Protection Agency (EPA) (2005), and a method developed for the
International Agency for Research on Cancer (IARC) Monographs Program (IARC, 2006),
are prominent mainstream approaches for risk assessment. IARC is an agency of the World
Health Organization and draws upon top research scientists throughout the world. Both EPA
and IARC methodologies have been used by other agencies worldwide and have been
adapted for assessing diseases other than cancer.
CHAPTER 8 January 2016 8 -20 ENVIRONMENTAL HEALTH
PHASE 1 DRAFT EIS
After more than 40 years of research, unresolved questions about ELF magnetic field
exposure and childhood leukemia that surfaced in 1979 (Wertheimer and Leeper, 1979)
continue to drive risk assessment. This is indicated by publications, comments, and
conclusions from various scientific bodies including the following:
• IARC (2002) conducted an extensive review of the literature in epidemiology,
animal, and cell laboratory studies and a review of biophysical principles. Their
conclusion was that power-frequency magnetic fields fell into the category of
“possible carcinogens” based on “limited evidence in humans for the carcinogenicity
of extremely low-frequency magnetic fields in relation to childhood leukemia.” For
leukemia and all other cancers among adult populations (both residential and
occupational), evidence was not considered sufficient to support classification of
EMF as a possible causal factor. More information is available at:
http://monographs.iarc.fr/ENG/Monographs/vol80/index.php.
• IARC’s conclusions and classifications closely resemble those of an earlier National
Institute of Environmental Health Sciences (NIEHS) evaluation that found that ELF
magnetic fields were possible carcinogens. NIEHS drew this conclusion based on the
“limited evidence” from childhood epidemiology and evidence concerning one type
of adult leukemia among workers exposed occupationally. More information is
available at: http://www.niehs.nih.gov/health/assets/docs_a_e/emf1.pdf (NIEHS,
1998).
• In response to inquiries on The Health Council of the Netherlands (2008)
interpretation of the research, this organization offered the following perspective:
“Epidemiological studies showed an increased risk of leukemia among children
living in locations where the field strength was higher than 0.3 – 0.4 microtesla (µT).
However no indications of a causal mechanism have been found in experimental
research. The possibility cannot be excluded that a factor other than exposure to a
low-frequency magnetic field could explain the association found in epidemiological
research.” More information is available at:
http://www.gezondheidsraad.nl/en/publications/high-voltage-power-lines-0.
• The Health Protection Agency of the United Kingdom has published opinions on
EMF human health effects in recent years. The last full Health Protection Agency
report on power-frequency EMF was in 2001. In 2013, the Agency stated: “At
present there is insufficient new information that would justify the development of an
update to the 2001 report, although it will be needed at some point in the future”
(HPA, 2013).
• The most recent update to the European Union position prepared by the Scientific
Committee on Emerging and Newly Identified Health Risks (SCENIHR, 2009)
presented conclusions similar to those above.
January 2016 CHAPTER 8 ENVIRONMENTAL HEALTH 8-21
PHASE 1 DRAFT EIS
The source of information on
corona ionization in this
section (8.3.6) is information
produced by the Energy
Networks Association (ENA)
(2009).
ENA represents the “wires and
pipes” transmission and
distribution network operators
for gas and electricity in the UK
and Ireland. Members are
utilities that control and
maintain the national energy
infrastructure.
8.3.6 Corona Ions
Corona effects are the result of the ionization of the air by
the strong electric fields present at the surface of sharp
metallic points, such as small-diameter wires, when they
are raised to a high voltage. Generation of corona ions is
dependent on the strength of the electric field on the
transmission line’s fittings and conductors—called the
surface voltage gradient. Water droplets can cause
increases in the conductor’s surface voltage gradient,
increasing the likelihood of corona discharges occurring.
This may occur during very moist atmospheric conditions,
such as fog or rain, but the effect is temporary. The corona
appears as a faint (filamentary) discharge radiating
outward from its source, and is the cause of the faint
crackling noise sometimes heard in the vicinity of
transmission lines. The corona ions produced by the line
are carried by the wind and disappear with distance from
the line as the charged particles recombine or are deposited.
The health concern with corona ions is related to how they may combine with airborne
pollutants to create health impacts. As airborne pollutants enter the body by inhalation, they
may be deposited in the respiratory system. The extent to which inhaled particles deposit in
the various regions of the respiratory system depends upon physical factors such as their size,
shape, and density, as well as charge. The extent of effects of corona ions on health will
depend upon the increase in individuals’ exposure to pollutants and the extent to which these
pollutants are causes of disease.
Professor Denis Henshaw of Bristol University in the United Kingdom has developed a
corona ion hypothesis, based on work proposing a theoretical mechanism involving the effect
of electric fields producing corona ions, against an extensive background of research into the
effects of magnetic fields on health. However, Professor Henshaw’s theoretical mechanisms
involving corona ions and pollutant particles have not been proven by health studies on
populations near transmission lines.
8.4 HOW WERE POTENTIAL ENVIRONMENTAL HEALTH
IMPACTS ASSESSED?
The analysis considered the general potential to encounter preexisting site contamination
during construction, and how that type of material would be addressed if encountered. The
potential to use hazardous materials or generate hazardous waste during project construction
and operation was considered, along with how these materials would be managed. The
analysis includes the potential for public safety risks related to earthquake, lightning strike, or
explosions related to natural gas or petroleum pipelines. Finally, the scientific findings
regarding EMF and corona ionization were evaluated to consider what they would mean
relative to operation of this project.
CHAPTER 8 January 2016 8 -22 ENVIRONMENTAL HEALTH
PHASE 1 DRAFT EIS
8.5 WHAT ARE THE LIKELY CONSTRUCTION IMPACTS
RELATED TO ENVIRONMENTAL HEALTH?
8.5.1 Construction Impacts Considered
As previously described, there are four types of potential environmental health impacts
considered in this chapter. Because of the different types of impacts considered, each
potential impact category includes a specific set of impact classification criteria.
8.5.1.1 Hazardous Materials
Constructing any of the action alternatives would be likely to involve use of the hazardous
materials described in Section 8.3.1 (e.g., gasoline, oil, solvents, paint). Improper
management of those materials or accidental spills that are not properly cleaned up could
release hazardous materials to air or water, which could create an environmental impact.
Construction activities are not expected to generate any hazardous/dangerous wastes.
Each alternative and option or component has the potential to be constructed in or near sites
already contaminated with hazardous materials. The types of hazardous materials that could
be encountered would depend on previous site uses. When contained in place these materials
may pose little active risk to the environment. However, these types of materials may become
mobile if they are disturbed during construction, at which point they would be more likely to
have a negative impact on human health and the environment. Disturbance of these materials
during construction could create an environmental impact by releasing hazardous materials to
the air or water, or exposing construction workers to hazardous substances, if proper handling
methods were not used. Existing site contamination could occur in water as well as on land.
The magnitude of potential hazardous material related impacts during construction is
classified as minor, moderate, or significant and has been defined for this EIS as follows:
Minor- If small quantities of hazardous materials could be released but could be cleaned up
in accordance with regulations such that sites could be restored to full function with no
adverse health impacts to the public, impacts would be considered minor.
Moderate–If substantial quantities of hazardous materials could be released to the
environment but could be cleaned up and restored to full function in accordance with
applicable regulations with no adverse health impacts to the public, impacts would be
considered moderate.
Significant–If hazardous materials would be likely to be encountered with the potential for
uncontrollable chemical releases, or large quantities of hazardous materials could be released
in a sensitive environment (such as a water resource, wetland, residential area or near a
school) with limited or no ability for cleanup and possible adverse public health impacts,
impacts would be considered significant.
January 2016 CHAPTER 8 ENVIRONMENTAL HEALTH 8-23
PHASE 1 DRAFT EIS
8.5.1.2 Public Safety Risks – Activities Near Pipelines
Construction of the project could theoretically damage the hazardous liquid pipelines
operated by OPLC and other gas lines mentioned in Section 8.3.2, creating an explosion risk
if safety policies and regulations were not implemented as required.
The UTC identifies five major reasons why gas pipelines leak or fail, potentially creating a
public safety hazard: (1) third-party excavation damage; (2) corrosion; (3) construction
defects; (4) material defects; and (5) outside forces resulting from earth movement, including
earthquakes, washouts, landslides, frost, lightning, ice, snow, and damage done by authorized
on-site personnel. The UTC also notes that other causes of failure can include cast-iron bell
joint leaks and human error (UTC, 2015). Holes in pipelines can also be created by electrical
arcing from downed transmission lines, leading to gas leaks and potential explosions (UTC,
2012). Construction equipment can create pipe gouges, dents, scrapes, and cracks in the
pipeline. This type of damage can grow and lead to a catastrophic failure (UTC, 2015).
The magnitude of potential project construction impacts related to activities near pipelines is
classified as follows for this EIS:
Minor - If damage to pipelines could lead to leaks of materials that could be cleaned up and
sites fully restored in accordance with applicable regulatory requirements, impacts would be
considered minor.
Moderate - If implementation of regulatory requirements and project design would address
most potential adverse impacts, but there is a reasonable potential for some damage to
pipelines that could result in impacts to property or human health, impacts would be
considered moderate.
Significant–Even with implementation of regulatory requirements and design measures, if
substantial damage, injury, or death would likely occur associated with pipeline damage,
leaks, or explosions, impacts would be considered significant.
8.5.1.3 Public Safety Risks – Natural Phenomena
Lightning strikes would not be a particular concern or lead to adverse impacts to the public
during construction. Members of the public would not be allowed to be in the vicinity of the
construction site, and therefore, would not be exposed to any additional environmental health
risk.
As discussed in Chapter 3, an earthquake could occur during construction, resulting in
embankment slope failures, liquefaction, ground settlement, and possibly associated
equipment destabilization. The risk of seismic hazards during construction is considered low
because of the relatively low probability that an earthquake would coincide with the actual
limited construction period. If a large earthquake were to occur, the major risk would be to
the ongoing construction activities or injury to workers.
The magnitude of potential construction impacts related to public safety risks from natural
phenomena is classified as follows for this EIS:
CHAPTER 8 January 2016 8 -24 ENVIRONMENTAL HEALTH
PHASE 1 DRAFT EIS
Minor –If earthquakes or seismic activity occurred during construction that could cause
disruption of equipment and construction activities, but would not cause risks to human
health or property, impacts would be considered minor.
Moderate - If an earthquake during construction would have a reasonable potential to disrupt
construction activities, and risk human health and property, impacts would be considered
moderate.
Significant -If an earthquake during construction would result in substantive damage to
property, injury, death, or substantive property loss, impacts would be considered significant.
8.5.1.4 EMF and Corona Ionization
Although small motors in construction equipment generate some level of magnetic fields,
these fields are very small and would be indistinguishable from background levels for the
public outside of the construction site. Workers within the construction site would experience
magnetic fields from this equipment as they would from working on any similar construction
site (these fields would be at lower levels than those investigated as potentially causing health
impacts). As described above, there is not a consensus in the scientific community on the
environmental health risks from EMF, particularly at the frequencies that would be expected
to result from the proposed transmission line. EMF is a concern that has been identified by
the public, but based on the available scientific information there does not appear to be a
potential environmental health impact associated with the proposed transmission line. PSE
will continue to comply with all applicable regulations, including requirements that may
emerge in the future.
Corona ionization would not be generated by construction. As with EMF, there is no
scientific consensus that it is an environmental health risk, and while this issue has been
identified as a concern by the public, it is not considered to be an impact to environmental
health.
8.5.2 No Action Alternative
Under the No Action Alternative, maintenance activities at existing facilities would occur
and could intensify, but they would not involve work on new sites or involve use of large
quantities of hazardous materials. Occasional conductor replacement, implementation of new
technologies not requiring discretionary permits, and installation of distributed generation
facilities under PSE’s conservation program would require minor construction activities.
Construction impacts related to hazardous materials, public safety risks, or EMF and corona
ionization would be negligible.
8.5.3 Alternative 1: New Substation and 230 kV Transmission Lines
Impacts are discussed associated with transmission line construction, followed by substation
construction where differences in impacts could be encountered.
January 2016 CHAPTER 8 ENVIRONMENTAL HEALTH 8-25
PHASE 1 DRAFT EIS
8.5.3.1 Option A: New Overhead Transmission Lines
8.5.3.1.1 Hazardous Materials
Construction of Alternative 1, Option A would likely require the types of equipment
described in Chapter 2, including those for earth movement (dump trucks, bulldozers, or
backhoes), cranes, concrete trucks, and delivery and worker vehicles. Overall construction
duration could be up to 18 months (not at all locations). All of these vehicles and types of
equipment would use some type of fuel, which if not handled and managed properly could
spill or leak.
The transmission lines installed for this alternative could use either the HPFF-type cable or
XLPE cable, which does not contain oil. If HPFF cable were chosen and were damaged
during installation, oil from the lines could leak. Spills of transformer insulating oil or gas
(SF6) could occur during installation of this equipment at one of the three substation sites.
Without containment and immediate cleanup, these materials could potentially generate an
adverse environmental impact. However, regulations (including those for water quality
protection during construction described in Chapter 5) require spill prevention, site
containment, and cleanup measures. Compliance with these regulations would reduce
impacts to a minor level.
In keeping with applicable regulations, PSE has an Emergency Spill Response Program to
ensure that accidentally released substances are contained. This program incorporates a 24-
hour contact number for reporting spills. The number is widely distributed to PSE and its
contractor’s employees through training, facility signs, Spill Prevention, Control, and
Countermeasure (SPCC) plans, office bulletin board posters, internal mailings and company
vehicle dashboard stickers (Strauch, personal communication, 2016). Upon receiving
notification of a release, PSE initiates a spill response process, which includes providing
notification of the releases to state or federal agencies. Smaller incidental releases can often
be addressed by internal PSE staff. Releases that are larger or more complex or involve
regulatory oversight from state or federal agencies are directed by an environmental
consultant that is contracted to provide 24-hour emergency spill response services. PSE
contracts with a number of emergency response contractors that have the necessary
equipment and personnel to remediate the sites per the appropriate state or federal regulations
(Strauch, personal communication, 2016). It is acknowledged that unforeseen circumstances
can occur during construction. However, compliance with all applicable local, state and
federal regulations and adherence with PSE’s existing processes would reduce the probability
for leaks or spills to occur, and if spills did occur, potential impacts would be reduced to a
minor level.
Federal regulations would require PSE to determine the location and types of preexisting soil
or groundwater contamination on-site when purchasing property (40 CFR Part 112). If
contaminated sites were purchased for either substation improvements (transformer) or
transmission lines, they would need to be cleaned up to appropriate standards, with the
appropriate cleanup level determined based on likely future use of the site. Once a particular
project site or alignment is chosen, an assessment can be conducted of the potential to
encounter existing contamination.
CHAPTER 8 January 2016 8 -26 ENVIRONMENTAL HEALTH
PHASE 1 DRAFT EIS
Hazardous materials on property already owned by PSE would also need to be addressed if it
were likely the hazardous materials would be disturbed. Releases (or threatened releases) of
such materials would need to be reported to the Washington State Department of Ecology
under the Model Toxics Control Act (MTCA). These notification requirements also apply to
historical releases once a property owner is aware they have occurred. Cleanup actions could
be initiated under MTCA; the Comprehensive Environmental Response, Compensation and
Liability Act (CERCLA); or the Resource Conservation and Recovery Act (RCRA).
If hazardous materials in soils or groundwater were not known to exist prior to the start of
construction, but were encountered during the work, federal and state regulations (primarily
WAC 173-340) would require PSE to ensure appropriate site management to avoid
displacement of the materials and to conduct appropriate cleanup and disposal. The standard
practice when a contractor finds previously unknown hazardous materials is to stop work in
the immediate area until the materials can be categorized and the extent/nature of the release
determined. PSE would also need to report the release of any hazardous substances that may
be a threat to human health or the environment to Ecology per WAC 173-340-300. Given the
extensive regulatory framework in place for contaminated site management, negligible to
minor impacts related to preexisting contamination are expected.
8.5.3.1.2 Public Safety Risks – Activities Near Pipelines
Construction could occur in the vicinity of regional natural gas pipelines or those that supply
natural gas to homes and businesses. In addition to distribution gas lines throughout the area,
the transmission lines could be constructed near the two OPLC regional pipelines.
Regulations such as those described in Section 8.2 (and Appendix M) require that pipelines
must be properly identified and located prior to construction (through review of utility maps,
coordination with utilities, or fieldwork to precisely locate them).
In addition to federal and state regulations, local governments in the combined study area
have also adopted land use policies or regulations regarding co-location of other development
with hazardous material pipelines such as the OPLC pipelines (Section 8.2.2.1). The OPLC
pipelines extend through six of the study area communities (Kirkland, Redmond, King
County, Bellevue, Newcastle, and Renton) all of which have planning policies addressing
such facilities, including safety considerations in siting and co-locating utilities. These
communities also have other codes addressing related public safety which would guide
facility siting and design.
Careful coordination with potentially affected utilities during the design process, along with
compliance with applicable regulatory requirements, will help to avoid potential construction
conflicts with existing underground pipelines. Compliance with current safety requirements
and regulations would minimize the probability that an existing pipeline could be damaged
during construction and spill or leak petroleum products. Should a spill occur, the risk would
depend in part on the location of the accident and the amount of product released. Materials
could enter area storm drains or watercourses, pool on-site, soak into the ground and
potentially reach groundwater, or drain across land onto private property or public rights-of-
way. Depending on other activities occurring in the area, in a worst case scenario these
materials could possibly ignite, leading to explosion and potential loss of life and property.
January 2016 CHAPTER 8 ENVIRONMENTAL HEALTH 8-27
PHASE 1 DRAFT EIS
Compliance with applicable regulations would be expected to reduce the potential impact to a
minor level.
In addition to injuries or loss of life that might result from an explosion of any type of
pipeline, human health effects could occur after inhaling smoke from fires or coming in
contact with the spilled petroleum materials. If petroleum products were to reach a drinking
water aquifer, significant adverse impacts to human health could occur if these materials
were ingested.
Although a significant adverse impact to public safety
could occur if a leak or an explosion of any of these types
of gas lines resulted from the project, this type of event
would not be likely to occur because PSE would comply
with all applicable regulations and requirements in place
for pipeline safety, including local land use requirements
for siting facilities of this type. Site-specific investigations
would be conducted during design to avoid existing gas
lines by maintaining appropriate separation between
existing and proposed facilities. Close coordination with
potentially affected utilities would also be done, and the
design and construction would be conducted consistent
with all applicable requirements. Given these safeguards,
the probability of a pipeline disruption resulting in an
explosion is low, but the potential magnitude of the impact
is potentially significant if this unlikely event were to
occur. Because compliance with all applicable requirements would help to reduce the
probability of an occurrence to a very low likelihood, potential adverse impacts associated
with construction of the project are characterized as minor.
8.5.3.1.3 Public Safety Risks – Natural Phenomena
No public safety impacts related to lightning strikes would be anticipated during
construction; however, construction workers could be exposed during tower construction.
Transmission pole design includes features to reduce the potential for lightning strikes,
described in more detail in Section 8.6.2.3 below. Earthquakes during construction would not
be expected to create adverse impacts in terms of public safety risks specific to the project
construction. As described in Chapter 3, the risk of seismic hazards during construction is
considered low because of the relatively low probability that an earthquake would coincide
with the limited construction period. If a large earthquake were to occur, the major risk
would be to the ongoing construction activities, and construction workers. Risks to workers
on the Energize Eastside project would not be greater than the risks to workers on other
construction projects in the region, and would be considered minor.
8.5.3.1.4 EMF and Corona Ionization
As noted in Section 8.5.1.4, corona ionization would not be generated by construction
activities, and EMF would not be an issue during construction for Alternative 1, Option A or
any of the other options or alternatives.
Pipeline Safety
The UTC has investigated a
few gas pipeline incidents that
were caused by the failure of
underground facility owners to
mark, or excavators’ failure to
call or precisely locate gas
pipeline facilities. The UTC has
referred violations to the State
Attorney General Office for
enforcement. The UTC’s
recommendations for
enforcement have included
technical assistance,
education, training, and
penalties (UTC, 2015).
CHAPTER 8 January 2016 8 -28 ENVIRONMENTAL HEALTH
PHASE 1 DRAFT EIS
8.5.3.2 Option B: Existing Seattle City Light 230 kV Transmission
Corridor
8.5.3.2.1 Hazardous Materials
Alternative 1, Option B would likely use the same types of hazardous materials in
construction and mostly similar equipment to Option A (see Appendix B). The construction
period for Option B would likely be longer than Option A (24 months), extending the period
during which accidental spills of materials could potentially occur. Option B also includes the
potential for use of HPFF lines, which could be damaged and spill oil. In addition, for
purposes of this evaluation, the potential for preexisting contamination within the Seattle City
Light corridor was considered equally likely to that of any other location. Option B is likely
to have negligible to minor construction impacts related to hazardous materials, the same as
Option A, because PSE would comply with all applicable permit requirements prior to and
during construction.
8.5.3.2.2 Public Safety Risks - Activities Near Pipelines
As with Alternative 1, Option A, construction could occur in the vicinity of regional natural
gas pipelines or smaller pipelines that supply natural gas to homes and businesses. Although
the PSE lines would in large part be located in or near the existing Seattle City Light corridor,
that corridor crosses a PSE gas main and the two regional petroleum product pipelines
operated by OPLC several times (as described in Chapter 16). Other gas utilities may also be
present. As with Option A, in the unlikely event that construction activities result in a
rupture, leak, or explosion of a nearby pipeline, impacts could be significant. However,
conformance with existing regulations and industry standards would help to ensure that
impacts are not likely. Given the low probability of occurrence, the potential impact is
considered minor.
8.5.3.2.3 Public Safety Risks – Natural Phenomena
Alternative 1, Option B would have the same potential for minor adverse impacts as
described for Option A with regard to lightning strikes and earthquakes during construction.
8.5.3.3 Option C: Underground Transmission Lines
8.5.3.3.1 Hazardous Materials
The potential for spills of hazardous materials at substations would be the same as described
for Alternative 1, Options A and B although slightly different types of construction
equipment would be used (see Appendix B). Duration of construction would also be longer
than Option A, at approximately 36 months. The same type of HPFF lines described for
Option A could be used, which could leak during construction. The underground
transmission lines of Option C could have a higher potential to encounter contaminated
materials than the overhead transmission of Option A due to the larger extent of ground
disturbance. PSE would perform site-specific evaluations during facility design, including
geotechnical evaluations to determine the potential for contaminated materials to be present.
Where possible, the facilities would avoid areas of contamination. The potential magnitude of
impacts is expected to be minor, because it is anticipated that PSE would attempt to avoid
areas of contamination and where that is not possible would comply with all applicable
permit requirements, cleaning up any disturbed contaminated sites to meet regulations.
January 2016 CHAPTER 8 ENVIRONMENTAL HEALTH 8-29
PHASE 1 DRAFT EIS
8.5.3.3.2 Public Safety Risks - Activities Near Pipelines
As with Alternative 1, Options A and B, construction could occur in the vicinity of regional
natural gas pipelines, or those that supply natural gas to homes and businesses, or near the
linear alignment of the two regional petroleum product pipelines operated by OPLC. The
potential to encounter these facilities would be higher than described for Options A and B,
because more excavation would be required. As noted for Option A, PSE would comply with
all applicable requirements during facility design and construction to avoid potential conflicts
with these facilities. Due to the increased area of ground disturbance, the probability of
impacts would be somewhat higher than described for Options A and B, but still considered
low, and anticipated impacts are expected to be minor to moderate.
8.5.3.3.3 Public Safety Risks – Natural Phenomena
This option would have the same or lower potential for minor adverse impacts as described
for Alternative 1, Options A and B with regard to lightning strikes and the same potential
impacts from earthquakes during construction.
8.5.3.4 Option D: Underwater Transmission Lines
8.5.3.4.1 Hazardous Materials
Construction of Alternative 1, Option D would require equipment similar to that described
for Option A, plus a submarine cable laying vessel (a specialized type of barge). Spills from
the equipment are not considered likely to occur, although if they did occur, they would
likely have a minor adverse impact if in water 5. As described in Chapter 2, approximately 8
months would be needed for the underwater portion plus additional time for the land-based
portions of the line and the new transformer.
As with Alternative 1, Option C, the submerged transmission lines of Option D (and possible
underground segments on land) have greater potential to encounter contaminated material
than the overhead transmission of Option A due to the larger extent of ground disturbance.
This option could also encounter contaminated sediments within Lake Washington 6 along the
alignment. These sediments could be disturbed through burying the cable at relatively
shallow depth underneath the lake bed or by laying cable on the lake bed. Ground disturbance
could also occur if the lines were placed underground at the point where they come ashore.
As with Options A, B, and C, compliance with permit and regulatory requirements would
help to ensure that adverse impacts related to site contamination would likely not occur.
Impacts, if they occurred, would be temporary and would be expected to be mitigated in
accordance with applicable regulatory requirements.
Potential hazardous material impacts would be the same as described for Alternative 1,
Option A (negligible to minor).
5 This analysis assumed that neither fluid-filled cable would likely be used in Lake Washington PSE’s Lake
Washington Submarine Cable Alternative Feasibility Study (Power Engineers, 2015) indicates that use of
SCFF cable in Lake Washington is not recommended, and HPFF cable was not considered as an option in
their feasibility analysis.
6 Contamination of lake-bottom sediments is known to exist in some locations in Lake Washington
(Ecology, 2014).
CHAPTER 8 January 2016 8 -30 ENVIRONMENTAL HEALTH
PHASE 1 DRAFT EIS
8.5.3.4.2 Public Safety Risks – Activities Near Pipelines
This option would have lower potential for minor adverse impacts related to construction
activities near gas pipelines, compared to Alternative 1, Options A, B and C.
8.5.3.4.3 Public Safety Risks - Natural Phenomena
This option would have the same potential for minor adverse impacts as described for
Alternative 1, Options A, B, and C with regard to lightning strikes and earthquakes during
construction.
8.5.4 Alternative 2: Integrated Resource Approach
8.5.4.1 Energy Efficiency and Demand Response Components
8.5.4.1.1 Hazardous Materials
Hazardous materials are not likely to be used in any quantity, or otherwise encountered or
generated, in constructing energy efficiency measures. No adverse impacts related to
hazardous materials are likely.
8.5.4.1.2 Public Safety Risks – Activities Near Pipelines and
Natural Phenomena
Public safety risks related to proximity to gas lines, earthquakes, or potential for lightning
strikes during construction are not likely from this component of Alternative 2. Energy
efficiency measures do not involve major infrastructure or substantial construction, and
would not likely be located near pipelines or gas lines.
8.5.4.1.3 EMF and Corona Ionization
Construction of all components of Alternative 2 would not likely have any adverse impacts,
the same as Alternative 1.
8.5.4.2 Distributed Generation Component
8.5.4.2.1 Hazardous Materials
Some of the same types of equipment and vehicles used to construct portions of Alternative 1
could be used for installation of distributed generation measures. The construction period,
during which materials could potentially spill, would likely be shorter than the larger, more
complex facilities and sites of the energy storage and peak generation plant components.
Adverse impacts related to accidental spills or encounters with previous site contamination
are expected to be negligible to minor.
8.5.4.2.2 Public Safety Risks – Activities Near Pipelines
As with Alternative 1, construction of distributed generation facilities could occur in the
vicinity of regional natural gas pipelines or those that supply natural gas to homes and
businesses. The likelihood of an explosion would be similar to or lower than Alternative 1
(extremely low potential for occurrence). The risks during construction of distributed
generation facilities would be lower than with Alternative 1 because there would be greater
flexibility in locating the facilities away from pipelines.
January 2016 CHAPTER 8 ENVIRONMENTAL HEALTH 8-31
PHASE 1 DRAFT EIS
8.5.4.2.3 Public Safety Risks – Natural Phenomena
This component would have the same or lower potential for minor adverse impacts as
Alternative 1 with regard to lightning strikes and earthquakes during construction.
8.5.4.3 Energy Storage Component
8.5.4.3.1 Hazardous Materials
In addition to construction equipment and vehicles, which would contain or use hazardous
materials, it is assumed that the battery units would contain some type of acid. Any of these
types of materials could spill in the event of an accident during construction, which would
potentially take approximately six months to complete. Battery systems would be expected to
be shipped in spill-proof containers. Construction of new facilities like this would be
expected to comply with local codes for stormwater management and spill prevention and
cleanup to avoid impacts to surface waters or groundwater that might occur with accidental
spills during construction. Overall, construction impacts related to hazardous materials are
expected to be negligible to minor.
8.5.4.3.2 Public Safety Risks – Activities Near Pipelines
As with the distributed generation component, construction could occur in the vicinity of
regional natural gas pipelines or those that supply natural gas to homes and businesses, with
accompanying potential risks of accidental disruption. The likelihood of this occurrence is
low, and potential impacts are considered to be minor.
8.5.4.3.3 Public Safety Risks – Natural Phenomena
This component would have the same potential for minor adverse impacts as Alternative 1
with regard to lightning strikes and earthquakes during construction.
8.5.4.4 Peak Generation Plant Component
8.5.4.4.1 Hazardous Materials
In addition to construction equipment and vehicles, which would contain or use hazardous
materials for approximately 12 months to build this component, the plant would run on fuel,
possibly natural gas, which would be delivered to the site prior to initial startup. Any of these
types of materials could spill in the event of an accident during construction. However, as
with the energy storage component, construction of this type of facility would be required to
comply with local codes for hazardous material transport and storage, as well as construction
site stormwater management and spill prevention and cleanup. Compliance with regulations
would avoid impacts to surface waters or groundwater that might occur with accidental spills
during construction. Therefore, impacts would be negligible to minor.
8.5.4.4.2 Public Safety Risks - Activities Near Pipelines
As with the distributed generation component, construction could occur in the vicinity of
regional natural gas pipelines or those that supply natural gas to homes and businesses. As
previously described, PSE would coordinate with potentially affected utilities to avoid
potential conflicts or disruptions, and would comply with all applicable requirements during
facility design and construction. Adverse impacts are not expected to occur.
CHAPTER 8 January 2016 8 -32 ENVIRONMENTAL HEALTH
PHASE 1 DRAFT EIS
8.5.4.4.3 Public Safety Risks – Natural Phenomena
This component would have the same or lower potential for minor adverse impacts as
Alternative 1 with regard to lightning strikes and earthquakes during construction.
8.5.5 Alternative 3: New 115 kV Transmission Lines and
Transformers
8.5.5.1.1 Hazardous Materials
Alternative 3 would likely use the same types of hazardous materials during construction as
Alternative 1 but because the transmission line would be much longer, the construction area
would cover a larger area than Alternative 1 or 2. Alternative 3 would require more
transmission line poles to be installed to support a longer line than Alternative 1, potentially
increasing the potential to encounter contaminated materials.
New transformers at three substations (many of which would require expansion or other work
outside the existing facility footprint as described in Chapter 2) could also increase the
potential to encounter contaminated soils. PSE would conduct site-specific investigations
during facility siting and design to determine if contaminated soils are present, and would
avoid contaminated areas to the extent possible. Should contaminated soils be encountered,
PSE would comply with all applicable regulatory requirements regarding containment and
cleanup, and impacts would be expected to be minor.
8.5.5.1.2 Public Safety Risks - Activities Near Pipelines
As with Alternative 1, construction could occur in the vicinity of regional natural gas
pipelines or those that supply natural gas to homes and businesses. Construction could also
occur near the linear alignment of the two regional petroleum product pipelines operated by
OPLC. The increased length of Alternative 3 could result in an increased potential for
conflicts with existing natural gas providers than described for Alternative 1, depending upon
the alignment chosen. If existing pipelines were not properly identified and located prior to
construction (through review of utility maps, coordination with utilities, or fieldwork to
precisely locate them), or if proper safety precautions required by regulations were not taken
during construction, the pipelines could be damaged during construction and leak. If leaked
material encountered an ignition source, an explosion could occur. As with Alternative 1, this
type of event could be a significant adverse impact (depending on specific size and location
of the pipeline and the leak) if it occurred. However, PSE would comply with all applicable
requirements during design and construction to avoid potential utility conflicts, and would
coordinate closely with all potentially affected utilities, to clearly identify and avoid existing
pipelines. Given conformance with existing regulations and industry standards and the low
probability of occurrence, the potential impact is considered minor.
8.5.5.1.3 Public Safety Risks - Natural Phenomena
Alternative 3 would have the same potential for minor adverse impacts as described for
Alternative 1, Option A with regard to lightning strikes and earthquakes during construction.
8.5.5.1.4 EMF and Corona Ionization
As described for Alternative 1, no impacts related to these issues are likely to occur with
construction.
January 2016 CHAPTER 8 ENVIRONMENTAL HEALTH 8-33
PHASE 1 DRAFT EIS
8.6 HOW COULD OPERATION OF THE PROJECT
AFFECT ENVIRONMENTAL HEALTH?
8.6.1 Operation Impacts Considered
8.6.1.1 Hazardous Materials
Operating any of the action alternatives would likely involve use of the hazardous materials
described in Section 8.3.1. Operation of some of the alternatives could generate
hazardous/dangerous wastes over time. Improper management of any of these types of
materials or wastes, or accidental spills that are not properly cleaned up, could potentially
release hazardous materials or waste to air or water, creating an adverse environmental
impact 7.
The magnitude of potential operational hazardous material related impacts is classified as
minor, moderate, or significant and has been defined for this EIS as follows:
Minor – If small quantities of hazardous materials or waste could be released during
operation but could be cleaned up in accordance with applicable regulatory requirements,
with sites restored to full function and no adverse health impacts to the public, impacts would
be considered minor.
Moderate – If substantial quantities of hazardous materials or waste would likely be released
to the environment during operation, but sites could be cleaned up in accordance with
applicable regulatory requirements, with no adverse health impacts to the public, impacts
would be considered moderate.
Significant – If operations would be likely to lead to uncontrollable releases of hazardous
materials or wastes, or likely releases of materials or wastes in a sensitive environment
(wetlands, residential areas or schools) with no ability to clean up or restore sites if spills
occurred and/or possible adverse public health impacts, impacts would be considered
significant.
8.6.1.2 Public Safety Risks - Activities Near Pipelines
Ongoing maintenance activities during operation could theoretically damage or break the
OPLC pipelines or other pipelines in the area, leading to a chemical release or explosion if
safety policies and regulations were not implemented.
If transmission lines were improperly designed or located relative to pipelines, or if pipelines
themselves were not properly designed with cathodic protection, pipelines could be damaged
by stray electric current, leading to risk of chemical release or explosion.
7 Possible leaks of fuel from pipeline damage are described as a public safety risk.
CHAPTER 8 January 2016 8 -34 ENVIRONMENTAL HEALTH
PHASE 1 DRAFT EIS
The magnitude of potential operational impacts related to
activities near pipelines is classified as minor, moderate,
or significant and has been defined for this EIS as follows:
Minor – If damage to pipelines could occur leading to
leaks of materials that could be cleaned up fully in
accordance with applicable requirements, with minimal
adverse risks to property or human health, impacts would
be minor.
Moderate –If potentially substantial damage to pipelines
could occur, but with no adverse impacts to human health
or property damage, impacts would be considered
moderate.
Significant – If operation of the project resulted in the
potential to damage pipelines, leading to explosion or
potential releases resulting in adverse impacts to human
health or property damage, impacts would be considered
significant.
8.6.1.3 Public Safety Risks - Natural Phenomena
Lightning strikes directly to electrical infrastructure could
occur. Facilities are designed to direct electricity from
lightning to the ground according to NESC guidelines. A
mechanical means is installed to convey lightning to the
ground and avoid equipment damage or fires (such as a
system of lightning rods at substations, and static wires
and grounding conductors at poles). Although unlikely, it
is possible that, even with these protective measures in
place, lightning strikes directly to electrical infrastructure
could occur. Direct strikes to poles or lines could damage
the pole, causing it to topple or drop transmission lines to
the ground. Downed transmission lines could pose a
safety risk to the public from electrocution or shock due to
direct contact, or if electricity from the line were
transferred to other metal utilities or structures. Lightning
strikes to equipment at substations could create an
electrical fault (abnormal electric current) within
substation equipment, with subsequent fire or risk of
electrocution of workers.
Transmission lines located near gas pipelines (such as in
the existing corridor where PSE’s 115 kV transmission line coexists with OPLC’s petroleum
lines) could pose a particular safety concern. Energized transmission lines on the ground after
an earthquake, lightning strike (or accidents) could send electric current to anything else
metal in the vicinity, such as utilities (including pipelines). In addition to electrocution or
Pipeline Design to Avoid
Stray Current
In accordance with 49 CFR
Part 195, OPLC has cathodic
protection on all of its pipelines
to protect against corrosion
and inspects these systems
annually. Criteria to determine
the adequacy of cathodic
protection are included in 49
CFR Part 195.571, which
incorporates by reference
industry standards and
practices developed by the
National Association of
Corrosion Engineers (NACE)
(2007).
Static Wires and Grounding
Conductors
The static wire is the pole's
top wire which bleeds lightning
surges off the transmission
lines during a storm. Without a
static wire, lightning induced
voltage would otherwise build
up on transmission line
conductors during a lightning
strike and cause damage. The
static wire is connected to the
grounding conductor.
The grounding conductor is a
wire that connects the static
wire to the ground rod. Visually
recognizable as the wire
running the entire length of the
pole, top to bottom.
January 2016 CHAPTER 8 ENVIRONMENTAL HEALTH 8-35
PHASE 1 DRAFT EIS
shock potential, this type of electrical contact could create holes in pipelines, leading to a risk
of explosion if regulations were not followed by the pipeline (or other utility) owner or if
facilities had not been designed properly.
As described in Chapter 3, seismic activity is likely to occur during the life of the project and
could be substantial, resulting in significant damage, power outages, injury, and death, if
facilities are not designed appropriately. Catastrophic failures of circuit breakers, transformer
bushings, and disconnect switches at substations, or downed transmission lines, could result
in widespread power outages.
The magnitude of potential operational public safety impacts related to natural phenomena is
classified as minor, moderate, or significant and has been defined for this EIS as follows:
Minor – If lightning or earthquakes could result in minor damage to infrastructure, but there
would be no adverse impacts to property of public safety, impacts would be considered to be
minor.
Moderate – If lightning or earthquakes resulted in damage to infrastructure, leading to
potential releases or safety risks that could be contained to the facility, impacts would be
considered moderate.
Significant – If lightning or earthquakes caused damage to infrastructure, leading to
explosion or electrocution risk on uncontained sites with substantial risk to public safety or
property, impacts would be significant.
8.6.1.4 EMF and Corona Ionization
Potential 8 magnetic field strength was assessed for each of the action alternatives. The
scientific findings regarding EMF and corona ionization described in Sections 8.3.4, 8.3.5,
and 8.3.6 do not lead to a conclusion of a probable significant adverse health impact related
to operation of this project. The potential health effects from EMF have been an area of
controversy and scientific inquiry for several decades, but at this time, review of available
research findings indicates that there are no confirmed adverse health impacts from the types
of EMF exposure that electrical infrastructure such as this project generates. Scientific
evidence remains inconclusive on risk of childhood leukemia in homes with stronger
magnetic fields and, as described in Section 8.3.5.1, research on this topic continues.
Therefore, impacts from EMF are not further characterized.
There is also no scientific evidence that corona ionization poses a health risk. The results of
the available studies mentioned in Section 8.3.6 were inconclusive and do not lead to a
finding of a probable significant adverse impact related to corona ionization with operation of
this project (Sheppard, 2015) and as such, are not further characterized in this EIS.
8 Potential magnetic fields were modeled by Enertech Consultants based on a set of design and
operational assumptions provided by PSE. Full design of the facilities could lead to different fields; actual
field levels will be dependent upon the line geometry and loading.
CHAPTER 8 January 2016 8 -36 ENVIRONMENTAL HEALTH
PHASE 1 DRAFT EIS
8.6.2 No Action Alternative
8.6.2.1 Hazardous Materials
Ongoing use of existing substation facilities would likely involve use of paints, solvents, and
other hazardous materials described in Section 8.3.1 during equipment maintenance.
Transformer oil or SF6 is used in equipment and may need to be recharged or changed out
over time. Accidental spills of any of these materials could occur and, depending on facility
age and design9, could enter the environment, including groundwater or surface waters.
Transformer oil (some of which may contain PCBs) and light ballasts are types of hazardous
wastes that could possibly be generated during equipment maintenance at existing sites or
could spill in case of accident. Existing equipment at PSE’s substations is operating on
concrete foundations within gravel yards. Where PSE has determined it is required, spill
containment structures or other measures are installed to contain potential equipment leaks so
that they are not discharged directly to surface water or storm sewers. The same spill
response procedures that are described for construction of Alternative 1 above would be used
for operation of facilities.
The potential risk of transformer overheating associated with system overload during peak
periods would be expected to increase under the No Action alternative, if system capacity is
not increased. More frequent system overloading could increase the potential for transformers
to catch fire or explode, with accompanying releases of materials and associated potential
safety hazards. Under the No Action alternative, these hazards would be addressed through
load shedding to avoid damaging the equipment, but the frequency of overloading would be
expected to increase as the Eastside area grows.
Given PSE’s operational controls, it is anticipated that spilled or leaked hazardous materials
would be properly handled under existing regulations, and they would be cleaned up and
abated in accordance with applicable regulations.
Transmission corridors would be maintained by PSE (and/or any other entity sharing the
corridor with PSE). Maintenance of these areas would primarily involve control of vegetation
that may interfere with transmission lines. PSE uses Integrated Vegetation Management
(IVM) techniques to control vegetation on transmission line corridors. Selective application
of herbicides is included in the IVM. PSE does not broadcast spray herbicides on
transmission corridors, and when used, herbicides are applied directly to the vegetation by a
Washington State licensed applicator. In general, PSE does not apply herbicides in
maintained landscape settings, particularly in urbanized settings. However, in some instances,
for example, a tree is removed and stump sprouting occurs, then direct application of
herbicides may be used (Strauch, personal communication, 2016). Public health impacts
associated with the IVM are not expected to occur, as all herbicides used are approved for
use by appropriate regulatory agencies as safe for application.
9 Newer facilities would be expected to have oil containment or other design features to prevent surface
water runoff from rainfall carrying hazardous materials offsite.
January 2016 CHAPTER 8 ENVIRONMENTAL HEALTH 8-37
PHASE 1 DRAFT EIS
If proper management and disposal measures are followed for facility operations as required
by federal and state regulations, impacts related to hazardous materials in the event of an
accidental release would be expected to be negligible to minor.
8.6.2.2 Public Safety Risks - Activities Near Pipelines
It is possible, but unlikely, that maintenance activities associated with ongoing operation of
PSE’s existing transmission line in the OPLC corridor could damage or break the pipeline. If
this did occur, it could create the same types of significant adverse impacts to public safety
described in Section 8.5.3.1.2. An explosion could also affect electrical transmission, and
substantial or long-term power outages could occur. These outages could potentially create
significant public safety impacts if transportation systems were affected or if large numbers
of homes were without power during cold periods (public facilities such as hospitals
generally have backup power generators). However, as described in Section 8.5.3.1.2, such
impacts are not likely to occur considering the regulatory framework for siting and design,
and for post-construction pipeline monitoring, as well as stringent requirements during
fieldwork to avoid contact with pipelines. The UTC, for instance, conducts inspections of
hazardous liquid and natural gas pipeline companies; works to improve safety laws and
regulations; provides technical assistance to pipeline operators, local governments, and
communities; and enforces laws and regulations, among other activities (UTC, 2016). Given
compliance with all applicable safety requirements during maintenance activities and
operation of the facilities, impacts would be considered negligible.
8.6.2.3 Public Safety Risks – Natural Phenomena
With the No Action Alternative, although unlikely, existing transmission lines could fall
during a natural disaster such as an earthquake (or accident), or if struck by lightning,
creating a safety risk to the public. Downed lines pose a risk of electrocution if still energized
and may also arc (send current to other metal structures such as pipelines), possibly
damaging those facilities. Power poles include grounding equipment intended to guide
electricity into the ground in the event of a strike, to prevent damage to poles or lines. It is
possible that where electricity is conducted to ground, it could reach utilities such as
pipelines. However, pipelines are designed with cathodic protection to minimize this
possibility. Impacts to underground pipelines related to downed lines resulting from lightning
strikes to poles are not likely and would be considered minor.
Some research indicates that, where overhead transmission lines share corridors with
pipelines, the lightning risk to the pipeline would likely stay the same or be reduced under
normal circumstances by the presence of the power lines and poles (Stantec, 2016). The lines
would likely absorb any lightning strikes that might occur in an area, rather than lightning
striking the pipeline directly. The Pacific Northwest has up to 10 days a year on average
when thunderstorms are likely and when they occur, lighting is sparse (Mass, 2016). Since
1999, PSE recorded 23 power outages due to lightning strikes on transmission lines. The
proposed 230 kV line would have a shield wire that would reduce the probability of potential
outages arising from a lightning strike (Strauch, personal communication, 2016).
CHAPTER 8 January 2016 8 -38 ENVIRONMENTAL HEALTH
PHASE 1 DRAFT EIS
Lightning protection is provided at substations via a static mast10 with shield wires or air
terminals. Ground grids are installed for personnel protection, which also act as a grounding
mat for lightning strikes. Some potential for fire at substations exists in the unlikely event of
direct lightning strikes, or in case of earthquake damage, and the public safety impacts could
be significant depending on specific location and size of a fire. At four substations
(Hazelwood, Lakeside, Westminster, and Clyde Hill), residences or schools are located
within approximately 100 feet of the facility. Chapter 15 discusses emergency response
measures that would be employed in the event of fire at substations, whatever the cause.
While the poles used for overhead transmission structures would not likely have been
specifically designed for ground-induced vibrations caused by earthquakes, they would have
been designed to withstand structure loadings caused by wind/ice combinations and broken
wire forces. These types of forces exceed earthquake loads (Chapter 3 provides more
information on this topic).
Public safety impacts relating to lightning strikes and earthquakes are a low probability and
negligible to minor impacts are expected to occur.
8.6.2.4 Electric and Magnetic Fields and Corona Ionization
With no health effects known from power-frequency EMF or corona ionization, no adverse
impacts related to either of these issues would be expected related to existing infrastructure.
8.6.3 Alternative 1: New Substation and 230 kV Lines
Impacts are described associated with the major components.
8.6.3.1 Option A: New Overhead Transmission Lines
8.6.3.1.1 Hazardous Materials
Alternative 1 would add approximately 18 miles of new transmission lines, with some
reconstruction of distribution power lines (and associated new pole-mounted transformers
along the routes). The option would add more equipment containing hazardous materials to
one of the three possible substations (Lakeside, Westminster, or Vernell). The transmission
lines could be co-located with other utilities including gas pipelines. Chemical means would
likely be used by one or more parties for vegetation management in the corridor. New pole-
mounted transformers that might be installed would not include PCB-containing oil as
required by law. Operation and maintenance of Alternative 1, Option A would carry the same
or lower risk than the No Action Alternative. Minor impacts could occur in the event of
releases or spills of hazardous materials, which would be expected to be contained in
accordance with applicable regulations.
8.6.3.1.2 Public Safety Risks - Activities Near Pipelines
Alternative 1, Option A could be in operation near the OPLC regional pipelines or could
share portions of the OPLC corridor or other utilities such as gas lines. Considering the
federal and state regulatory framework and safety mechanisms in place (described in Section
10 Static mast is a single, free-standing pole that creates a shield to protect all of the equipment inside a
substation from lightning.
January 2016 CHAPTER 8 ENVIRONMENTAL HEALTH 8-39
PHASE 1 DRAFT EIS
8.2.2.1), negligible adverse impacts related to improper design or pipeline safety are expected
with operation of the project.
As described in Section 8.5.3.1.2, local governments have adopted land use policies
regarding co-location of utilities and development adjacent to hazardous materials pipelines,
which would ensure that the proposed transmission lines would be constructed in areas safe
to maintain and operate.
8.6.3.1.3 Public Safety Risks – Natural Phenomena
The impacts of this alternative would be similar to the No Action Alternative. At substations,
new equipment would be designed to meet current codes. As described in Chapter 3, for the
substation expansions, design of structures to resist seismic forces and secondary effects such
as liquefaction would be required by law. Following construction, risks would be very low.
The required measures would encompass site preparation and foundation specifications. In
addition, the state public utility commission has adopted seismic standards that utilities must
follow, with structural requirements for poles that would be sufficient to resist anticipated
earthquake ground motions.
Lightning strikes to new poles or substation equipment, leading to downed lines or fires, are
not likely to occur. Poles would include the same type of grounding equipment described for
the No Action Alternative, with the same issues relative to underground infrastructure such as
pipelines. Impacts are not likely.
Either an earthquake or lightning strike could theoretically lead to fires at substations. The
impacts would vary depending on specific location and size of the fire. The closest residence
to any of the three substations where new equipment could be located with this option occurs
at the Westminster substation where the nearest residential structure is approximately 30 feet
away from the substation fence line. The distance to residences at the Vernell substation is
approximately 1,200 feet and at Lakeside is approximately 90 feet.
Overall, negligible to minor impacts related to natural phenomena from operation of
Alternative 1, Option A are anticipated.
8.6.3.1.4 EMF and Corona Ionization
With no health effects known from power-frequency EMF or corona ionization, no adverse
impacts related to either of these issues would be expected from any of the options under
Alternative 1.
8.6.3.1 Option B: Existing Seattle City Light 230 kV Transmission
Corridor
8.6.3.1.1 Hazardous Materials
Operating and maintaining the PSE-owned facilities of this option would carry the same risk
and have the same possibly minor impacts as Alternative 1, Option A (and No Action
Alternative).
8.6.3.1.2 Public Safety Risks - Activities Near Pipelines
Alternative 1, Option B would be located near the OPLC petroleum pipelines in places and
could be in operation near, or share corridors with, other utility infrastructure such as gas
CHAPTER 8 January 2016 8 -40 ENVIRONMENTAL HEALTH
PHASE 1 DRAFT EIS
lines. The Seattle City Light corridor parallels the OPLC corridor through much of Newcastle
and into Renton, and crosses the corridor in two locations in the Renton/Newcastle area
(Figure 16-1). As with Option A, impacts to the OPLC pipelines or other gas lines in the area
from operation of the project are not expected.
8.6.3.1.3 Public Safety Risks – Natural Phenomena
The potential safety issues relative to lightning, earthquakes, and accidental damage would be
the same as Alternative 1, Option A and the No Action Alternative.
8.6.3.2 Option C: Underground Transmission Lines
8.6.3.2.1 Hazardous Materials
Operating and maintaining the PSE-owned facilities of Alternative 1, Option C would have
the same types of issues as Options A and B with regard to hazardous materials and
hazardous/dangerous wastes. No more than minor impacts would likely occur in the event of
spills or other releases of hazardous materials for Option C.
8.6.3.2.2 Public Safety Risks - Activities Near Pipelines
Alternative 1, Option C could also be located near the OPLC petroleum pipelines in places
and could be in operation near, or share corridors with, other utility infrastructure such as gas
lines. As with Options A and B, impacts to the OPLC pipelines or other gas lines in the area
from operation of the project are not expected.
8.6.3.2.3 Public Safety Risks – Natural Phenomena
The potential for lightning, earthquakes, and accidents to lead to fires or other risks would be
less than with Alternative 1, Options A and B and the No Action Alternative since the line
would be underground with Option C. No impacts are likely to occur.
8.6.3.3 Option D: Underwater Transmission Lines
8.6.3.3.1 Hazardous Materials
As with Alternative 1, Options A, B, and C, operating and maintaining Option D could have
minor impacts if spills or releases occurred. The PSE transmission lines could be co-located
with other utilities in the areas, where chemicals would likely be used for vegetation
management. Oil-filled lines would not likely be used in Lake Washington, so no potential
impacts related to that type of line are associated with Option D.
8.6.3.3.2 Public Safety Risks - Activities Near Pipelines
With Alternative 1, Option D, the risk of fire or explosion at substations, although unlikely to
occur, would be the same as for Option A. The transmission line segments on land would
have the same potential risks and impacts as Options A and B. The underwater transmission
line would not likely be located near pipelines, so no related impacts could occur.
8.6.3.3.3 Public Safety Risks – Natural Phenomena
The submarine lines of Alternative 1, Option D would not be vulnerable to fires or lightning
strikes. The risks and potential impacts on land would be the same as described for Option A
(negligible to minor).
January 2016 CHAPTER 8 ENVIRONMENTAL HEALTH 8-41
PHASE 1 DRAFT EIS
8.6.4 Alternative 2: Integrated Resource Approach
8.6.4.1 Energy Efficiency and Demand Response Components
8.6.4.1.1 Hazardous Materials
Small quantities of hazardous materials might have been used to install some energy
efficiency or demand response measures. However, use or release of hazardous materials
would be unlikely over time for measures such as windows, appliances, weatherproofing, or
insulation once they are in place. There would be no likely operational impact related to
hazardous materials.
8.6.4.1.2 Public Safety Risks - Activities Near Pipelines
The activities (changes in energy usage patterns), structural upgrades (windows, insulation,
etc.), and meters for these components would not pose a threat to pipeline safety.
8.6.4.1.1 Public Safety Risks – Natural Phenomena
There would not likely be any particular fire or explosion risk or impacts related to lightning
strikes or earthquakes with implementation of energy efficiency or demand response
components.
8.6.4.1.2 EMF and Corona Ionization
With no health effects known from power-frequency EMF or corona ionization, no adverse
impacts related to either of these issues would be expected under any of the components of
Alternative 2.
8.6.4.2 Distributed Generation Component
8.6.4.2.1 Hazardous Materials
As with Alternative 1, accidental damage or leaks during maintenance of distributed
generation equipment could lead to hazardous materials (primarily fuels or lubricants)
leaving the site. However, if these facilities contained enough fuel to present a hazard, the
facilities would likely be designed and installed with fuel containment to meet local codes.
Adverse impacts would likely be minor if spills or leaks did occur.
8.6.4.2.2 Public Safety Risks – Activities Near Pipelines
The small-scale infrastructure installed on discrete sites would not pose a threat to pipeline
safety.
8.6.4.2.3 Public Safety Risks – Natural Phenomena
Demand response facilities would not be uniquely susceptible to fire or explosion related to
lightning strikes or earthquakes. Facilities would be installed in accordance with current
codes, including electrical, spill containment as needed, and seismic and structural stability.
New small-scale equipment would not be the tallest features on sites and not prone to
lightning strikes. The presence of combustibles, such as fuel, increases the risk of fire and/or
explosion, but the risk of a direct lightning strike on combustibles would be minimal due to
shielding. No adverse public safety impacts are anticipated for this component.
CHAPTER 8 January 2016 8 -42 ENVIRONMENTAL HEALTH
PHASE 1 DRAFT EIS
8.6.4.3 Energy Storage Component
8.6.4.3.1 Hazardous Materials
The specific technology likely to be used for energy storage facilities is unknown. There may
be types of systems that do not contain hazardous materials. This discussion assumes that a
battery system containing some type of acid would be employed.
As with almost any chemical reaction, the energy stored and released by battery cells has the
potential to cause overheating and, if undetected and unmitigated, eventually cause the
battery to experience thermal runaway (a positive feedback loop where an increase in cell
temperature and pressure leads to an uncontrolled heat reaction). Runaway could result in the
destruction of the cell through melting or fire, which has the potential to spread to other cells
(Strauch, personal communication, 2016). A primary concern with battery fires includes the
release of toxic fumes from hazardous materials (varying by battery chemistry and enclosure
materials), in addition to challenges and uncertainty with extinguishing battery fires by first
responders as described in Chapter 15. In addition, accidental damage of the equipment could
possibly lead to leaks or spills, with a potentially significant adverse impact if the materials
were to reach area water bodies or locations where the public could come in contact with the
acid. However, these types of systems would be constructed with the same type of
containment as distributed generation facilities. Minor adverse impacts could occur.
8.6.4.3.2 Public Safety Risks - Activities Near Pipelines
The proximity of energy storage facilities to pipelines would not pose a particular type of
threat to pipeline safety.
8.6.4.3.3 Public Safety Risks – Natural Phenomena
As with the distributed generation component, facilities would be installed in accordance
with current codes for electrical, spill containment, and seismic and structural stability. There
would not likely be any particular fire or explosion risk related to lightning strikes or
earthquakes, or concern about proximity to pipelines, with operation of this component. No
adverse public safety impacts are expected to occur.
8.6.4.4 Peak Generation Plant Component
8.6.4.4.1 Hazardous Materials
The potential for impacts associated with this component would likely be similar to that of
the distributed generation component. Although fuel used to power these facilities could leak
or spill, and there would be more fuel in one location with this type of larger-scale generation
system than with distributed generation, these generation plants operating within existing
substations would be required to have containment design. Adverse impacts related to
potential releases of hazardous materials would be expected to be negligible to minor.
8.6.4.4.2 Public Safety Risks – Activities Near Pipelines
As with the distributed generation and energy storage components, no impacts would be
expected to occur during operation.
January 2016 CHAPTER 8 ENVIRONMENTAL HEALTH 8-43
PHASE 1 DRAFT EIS
8.6.4.4.1 Public Safety Risks – Natural Phenomena
The potential risks and level of likely impacts would be negligible, as described for the
distributed generation and energy storage components.
8.6.5 Alternative 3: New 115 kV Transmission Lines and
Transformers
8.6.5.1 Hazardous Materials
Operation of Alternative 3 is expected to have negligible to minor adverse hazardous material
impacts. The 60 miles of new transmission lines (and possible reconstruction of area
distribution power lines) would mean more pole-mounted transformers containing small
quantities of oil installed in the area than with No Action or Alternative 1, with more
potential for accidental spills. However, regulations are in place for facility design and for
reporting and cleaning up spills when they occur, and there are relatively small quantities of
hazardous materials involved with the lines. The new transformers at substations would be
designed to current codes with spill protection measures in place to avoid accidental releases
of materials, the same as Alternative 1.
8.6.5.2 Public Safety Risks - Activities Near Pipelines
The potential public safety risks would be the same as described for Alternative 1, including
potential proximity to the OPLC pipeline. As with Alternative 1, adverse public safety
impacts would not be likely.
8.6.5.3 Public Safety Risks – Natural Phenomena
The potential risks and impacts would be the same as described for Alternative 1.
8.6.5.4 EMF and Corona Ionization
With no health effects known from power-frequency EMF or corona ionization, no adverse
impacts related to either of these issues would be expected.
8.7 WHAT MITIGATION MEASURES ARE AVAILABLE
FOR POTENTIAL IMPACTS TO ENVIRONMENTAL
HEALTH?
8.7.1 Hazardous Materials
For all alternatives, it is anticipated that PSE would comply with regulations intended to
control potential hazardous materials-related impacts, applying industry best management
practices such as the following:
• Conduct due diligence to identify any preexisting contamination on properties PSE
may choose to purchase for the project.
• Conduct any site cleanups that may be required by law.
CHAPTER 8 January 2016 8 -44 ENVIRONMENTAL HEALTH
PHASE 1 DRAFT EIS
• Provide contamination-related information in construction contracts and to PSE
workers, identifying locations and types of known contamination.
• Require training for agency and contractor staff to identify contamination when
encountered unexpectedly during construction work; prepare and implement a health
and safety plan that addresses construction work with contaminated soil and water.
• During construction, prepare and implement a Temporary Erosion and Sediment
Control Plan to prevent wind and stormwater dispersal of any contaminated soil that
may be encountered.
• Prepare and implement Spill Prevention, Control, and Countermeasures Plans to
prevent releases of hazardous materials that may be used during project construction,
and contain them and clean them up if a spill should occur.
• Design facilities with adequate spill containment where needed.
• Use industry best practices and safety protocols during operation. This would include
equipment maintenance procedures to contain spills, and safety procedures and
cleanup plans in place in the event of accidental spills.
While regulations are likely adequate to minimize impacts, PSE could also do the following:
• Conduct targeted characterization of soils prior to construction at identified high- and
moderate- impact site locations.
• Prior to start of work, develop a remediation plan for sites known to be contaminated
and that will be impacted by construction, and determine disposal requirements
(including whether significant groundwater dewatering may be necessary).
• Prepare and implement a contaminated-media management plan to address
unanticipated contaminated soil, groundwater, and surface water that might be found
during construction.
• Design the project where feasible to avoid intercepting known soil and/or
groundwater contamination.
• For the alternatives with transformers, if technically feasible, install vegetable-based
oil in transformers rather than mineral oil or SF6.
• Choose XLPE type cable, rather than SCFF or HPFF, to avoid bringing one type of
hazardous material into the area where feasible, especially into Lake Washington.
• Select and use landscape and plants that minimize the need for pesticides (generally
containing hazardous materials).
• In shared utility corridors, PSE could coordinate use of hazardous materials for
corridor (vegetation) maintenance with the operations and uses of hazardous
materials by the other utility if this is not already part of operation and maintenance
plans or easement agreements.
January 2016 CHAPTER 8 ENVIRONMENTAL HEALTH 8-45
PHASE 1 DRAFT EIS
8.7.2 Public Safety Risks
8.7.2.1 Activities Near Pipelines
For public safety during construction, PSE would follow regulatory requirements to correctly
locate and plan for other utility locations such as gas lines or the OPLC pipelines prior to
start of construction, including showing pipeline locations on plans and requiring contractors
to field locate utilities.
PSE would comply with all applicable local requirements for siting of transmission lines and
other electrical facilities.
PSE would site new transmission lines according to industry best practices, which includes
proper positioning and design (separation and grounding) relative to other utilities.
PSE would ensure that staff or contractors working near pipelines fully understand the
location of those features, have plans in place to avoid and protect those facilities, and have
emergency response protocols in place in the event of a disruption of gas or petroleum lines.
Local governments and PSE would further evaluate the PIPA recommendations (discussed in
Section 8.2.2.1) to determine if any additional safety practices could be implemented for the
Energize Eastside Project.
8.7.2.2 Natural Phenomena
Standard substation facility design according to the NESC incorporates features that abate the
risk of fire related to lightning strikes or earthquakes. If needed to meet applicable permit
requirements, PSE could investigate the feasibility of alternative design options for
transformer foundations, to provide increased seismic stability and further abate risk of fire at
substations.
8.7.3 EMF and Corona Ionization
No adverse impacts relative to these issues are expected; therefore no mitigation is proposed.
8.8 ARE THERE ANY CUMULATIVE IMPACTS TO
ENVIRONMENTAL HEALTH AND CAN THEY BE
MITIGATED?
No cumulative adverse impacts to environmental health are anticipated. The project would
not contribute to a cumulative impact with regard to public safety risks since regulations are
expected to ensure that facilities are designed to avoid such risks and that appropriate safety
measures are conducted in case of such events. Further, local planning policies and
development regulations are expected to ensure that new infrastructure is located
appropriately to protect public health and safety. As the combined study area increases in
developmental density, increased risks to public safety would be expected to occur, however,
implementation of the Energize Eastside project would not significantly contribute to those
risks.
CHAPTER 8 January 2016 8 -46 ENVIRONMENTAL HEALTH
PHASE 1 DRAFT EIS
8.9 ARE THERE ANY SIGNIFICANT UNAVOIDABLE
ADVERSE IMPACTS TO ENVIRONMENTAL HEALTH?
There would not likely be any significant unavoidable adverse impacts related to
environmental health from any of the alternatives if construction and operations adhere to
regulations, safety protocols and industry practices. There is a risk of damage and subsequent
explosion whenever construction or operations and maintenance occur near buried natural
gas lines or the Olympic Pipeline. However, that risk is not considered an unavoidable
significant impact because the probability of damage occurring is minimized by conformance
with industry standards, regulatory requirements, and construction and operational
procedures that address pipeline safety.
January 2016 CHAPTER 8 ENVIRONMENTAL HEALTH 8-47
PHASE 1 DRAFT EIS
CHAPTER 9. NOISE
9.1 WHAT IS NOISE AND HOW IS IT EVALUATED?
Noise is defined as unwanted sound. Sound is created
when a source (such as a machine) creates mechanical
energy that travels as pressure waves through the air.
Several parameters are used to measure noise, including
the rate of oscillation of sound waves (frequency), the
speed of wave propagation, and the pressure level or
energy content (amplitude).
The sound pressure level has become the most common
descriptor used to characterize the loudness of a sound.
Sound pressure level is measured in decibels (dB), which
is a logarithmic loudness scale. On this scale, 0 dB
corresponds roughly to the threshold of human hearing,
and 120 to 140 dB corresponds to the threshold of pain
(HUD, 1985).
The typical human ear is not equally sensitive to all
frequencies of sound. When assessing potential noise
impacts, sound is measured using an electronic filter that
deemphasizes the frequencies below 1,000 hertz (Hz) and above 5,000 Hz. This mimics the
human ear’s decreased sensitivity to low and extremely high frequencies. This method of
adjusting the sound scale to reflect human hearing is referred to as A-weighting and is
expressed in units of A-weighted decibels (dBA).
Community noise levels must be measured over an extended period of time because they are
constantly changing. This time-varying characteristic of environmental noise is described
using statistical noise descriptors. The most frequently used noise descriptors are as follows
(Caltrans, 2013):
Leq: The Leq or equivalent sound level is used to describe noise over a specified
period of time, typically 1 hour, in terms of a single numerical value. The Leq is
the constant sound level that would contain the same acoustic energy as the
varying sound level, during the same time period. It reflects the average noise
exposure level for the given time period.
Lmax: The Lmax is the instantaneous maximum noise level measured during the
measurement period of interest.
Ldn: The Ldn or day-night average sound level (also written as DNL) is the energy
average of the A-weighted sound levels occurring during a 24-hour period. It
accounts for the greater sensitivity of most people to nighttime noise by
Noise Key Findings
Alternatives 1 and 3, and the
distributed generation, energy
storage, and peak generation
plant components of
Alternative 2, would result in
minor construction noise
impacts during daytime hours
and moderate impacts if
nighttime work were to occur.
Operation of Alternative 1,
Option A, or Alternative 3 could
cause minor noise impacts.
Operation of the distributed
generation component
(Alternative 2) or the new peak
generation plants (Alternative
2) could result in minor to
moderate noise impacts.
January 2016 CHAPTER 9 NOISE 9-1
PHASE 1 DRAFT EIS
weighting (penalizing) nighttime noise levels: 10 dBA is added to noise occurring
between 10:00 PM and 7:00 AM.
Steady-state sound remains constant (on average) over time; examples include the sound of
an air conditioner, fan, or pump. Steady-state sounds are typically described using the Leq
descriptor.
Impulse sound is generated over a relatively short period (e.g., a car horn or backup alarm).
Impulsive sound is typically characterized using the Lmax.
The effects of noise on people can be placed into three categories: (1) subjective effects of
annoyance, nuisance, and dissatisfaction; (2) interference with activities such as speech,
sleep, and learning; and (3) physiological effects such as hearing loss or sudden startling.
Because there is such wide variation in how people respond to noise, an important way of
predicting human reaction to noise is the way that noise levels compare to the existing
environment to which one has adapted, or the ambient noise level. In general, the more a new
noise exceeds the previously existing ambient noise level, the less acceptable the new noise
will be to the individual. With regard to increases in A-weighted noise levels, the following
relationships occur (Caltrans, 2013):
• Except in carefully controlled laboratory experiments, a change of 1 dBA cannot be
perceived by the human ear.
• Outside of the laboratory, a 3 dBA change is considered a just-perceivable difference.
• A change of at least 5 dBA is required before any noticeable change in human
response is expected.
• People perceive a 10 dBA change as approximately a doubling in loudness and it can
cause an adverse response.
9.2 WHAT ARE THE RELEVANT PLANS, POLICIES, AND
REGULATIONS?
9.2.1 Washington State
The Washington Administrative Code (WAC) has established limits on maximum
permissible noise levels for residential, commercial, and industrial zones (Chapter 173-60
WAC). The exterior sound level limits for specified land use zones or “districts” vary
depending on the district generating the sound and the district affected by the sound (Table
9-1). Noise from electrical substations and construction activity occurring between 7 AM and
10 PM are exempt from these limits. However, these levels would apply to new transmission
lines that operate continuously.
CHAPTER 9 January 2016 9 -2 NOISE
PHASE 1 DRAFT EIS
Table 9-1. Exterior Sound Level Limits (Washington Administrative Code 173-60-040)
Sound Generating
District
Sound Receiving District
Residential
(dBA Leq)
Commercial
(dBA Leq)
Industrial
(dBA Leq)
Class A (Residential) 55 57 60
Class B (Commercial) 57 60 65
Class C (Industrial) 60 65 70
9.2.2 King County
The King County Comprehensive Plan (2013 Update) addresses noise only from airports and
mining operations, and it contains no specific policies regarding construction noise or
stationary source noise. Section 12.86 of the King County Code establishes maximum
exterior sound level limits for specified land use districts, which vary depending on the
district generating the sound and the district affected by the sound (Table 9-2). Temporary
noise from construction is allowed to exceed these limits depending on the time of day and
type of equipment in use (King County, 2015).
Table 9-2. Exterior Sound Level Limits (King County Code 12.88.020)
Sound
Generating
District
Sound Receiving District
Rural
(dBA, Leq)
Residential
(dBA Leq)
Commercial
(dBA Leq)
Industrial
(dBA Leq)
Rural 49 52 55 57
Residential 52 55 57 60
Commercial 55 57 60 65
Industrial 57 60 65 70
9.2.3 City Codes and Policies
Bellevue, Redmond, Kirkland, and Beaux Arts Village have policies in their comprehensive
plans regarding excessive noise. These generally address noise that could impair permitted
land use activities in all zones, with special emphasis on nighttime noise in residential zones.
All study area communities have noise regulations similar to those described for King
County. Table 9-3 summarizes noise-related codes and policies of cities in the combined
study area (Alternatives 1, 2, and 3 as depicted on Figure 1-4 in Chapter 1). While some
cities have adopted the noise standards contained in the Washington Administrative Code,
some cities, as indicated in Table 9-3, have different or more stringent standards and these
would apply to construction and stationary noise sources in these communities.
January 2016 CHAPTER 9 NOISE 9-3
PHASE 1 DRAFT EIS
Table 9-3. Noise Codes and Policies of Cities in the Combined Study Area
Comprehensive Plan Policies Code Requirements
Beaux Arts Village
The 2014 Draft Comprehensive Plan
states that noise should be considered
during review of public facilities
proposed by King County and other
agencies.
No applicable code requirements.
Bellevue
Ensure that excessive noise does not
impair the permitted land use activities
in residential, commercial, and
industrial land use districts.
Protect residential neighborhoods from
noise levels that interfere with sleep
and repose through development
standards and code enforcement.
Bellevue City Code Chapter 9.18 provides
maximum permissible sound levels for stationary
sources generally consistent with Table 9-2 for King
County. Bellevue exempts construction noise from
these limits between 7:00 AM and 6:00 PM on
weekdays, and 9:00 AM and 6:00 PM on Saturdays
(not including legal holidays). More stringent noise
restrictions apply to Robinsglen Community Park
and Lake Hills Greenbelt Access Areas (designated
quiet zones).
Clyde Hill
No applicable comprehensive plan
policies.
Municipal Code 8.10.030 prohibits sounds
originating from construction sites, except between
the hours of 7:00 AM and 6:00 PM on weekdays
and 10:00 AM and 4:00 PM on weekends and
holidays,
Hunts Point
No applicable comprehensive plan
policies.
Municipal Code 15.50.010 permits site
development and building construction activities
that transmit noise to surrounding properties (over
55 dB) only during the hours of 7:30 AM to 4:30 PM
(Monday through Friday) and from 9:00 AM to 2:00
PM on Saturday (not including legal holidays).
Municipal Code 8.40.010 and 8.40.020 adopts by
reference the noise standards of the King County
Code, Chapters 12.86 through 12.100, which
govern excessive noise and noise control by
reference. Chapter 12.91, Watercraft Sound Levels,
is excluded.
Issaquah
No applicable comprehensive plan
policies.
Issaquah Municipal Code 18.07.36 adopts by
reference the noise standards of Chapter 173-60
WAC (Table 9-1). Issaquah Municipal Code Chapter
19.22 prohibits noisy activity in general but does
not identify quantitative standards.
CHAPTER 9 January 2016 9 -4 NOISE
PHASE 1 DRAFT EIS
Comprehensive Plan Policies Code Requirements
Kirkland
Policy CC.4-11: Minimize Impacts on
Residential Neighborhoods states that
the City should have development
regulations and urban design principles
to reduce and, in some cases, prohibit
impacts such as noise, lighting, glare
and odor. Site design, building
orientation, underground parking,
landscape buffers, solid screen fencing,
acoustical sound walls, directional
lighting, and limitation on business
hours of operation are some of the
techniques that may be used.
Kirkland Municipal Code Chapter 115.95 adopts by
reference the noise standards of Chapter 173-60
WAC (Table 9-1). Kirkland Municipal Code
11.84A.070 prohibits noisy activity in general but
does not identify quantitative standards.
Medina
No applicable comprehensive plan
policies.
Municipal Code 8.06.010 adopts by reference the
noise standards of the King County Code, Chapters
12.86 through 12.100. It adds that a technical
variance may be granted by the hearing examiner
on the grounds that there is no practical means
known or available for the adequate prevention,
abatement, or control of the noise involved.
Municipal Code 12.06.330 requires the permittee to
take appropriate measures to reduce noise during
excavation work. No noise sufficient to disturb
neighboring properties is allowed between the
hours of 10:00 PM and 7:00 AM.
Municipal Code 20.32.040 states that fences
surrounding electrical power and utility substations
must be located in a manner that minimizes noise
impacts to adjoining properties and streets.
Municipal Code 20.71.030 states that a use must
not have materially detrimental effects on
neighboring properties due to excessive noise if it is
to be approved for an administrative special use
permit.
Newcastle
No applicable comprehensive plan
policies.
Newcastle Municipal Code 9.05.510 prohibits noisy
activity in general but does not identify quantitative
standards. It prohibits sounds originating from
construction sites, including but not limited to
sounds from construction equipment, power tools
and hammering, between the hours of 7:00 PM and
7:00 AM on weekdays and 6:00 PM and 9:00 AM
on weekends and holidays, unless authorized by
the City Manager.
January 2016 CHAPTER 9 NOISE 9-5
PHASE 1 DRAFT EIS
Comprehensive Plan Policies Code Requirements
Redmond
Maintain noise regulations to limit noise
to levels that protect the public health
and that allow residential, commercial
and manufacturing areas to be used for
their intended purposes. Provide
flexibility in the regulations to allow
construction at night when necessary
to protect worker safety while
maintaining the tranquility of the city.
Require buffering or other noise
reduction and mitigation measures to
reduce noise impacts from commercial
and industrial zones on residential
areas.
Redmond Municipal Code Chapter 9.18 establishes
maximum permissible sound levels for stationary
sources generally consistent with Table 9-2 for King
County. The City exempts construction noise from
these limits between 7:00 AM and 10:00 PM if not
impacting a residential zone. In residential zones,
construction noise is exempt from these limits
between the hours of 7:00 AM and 7:00 PM on
weekdays, and 9:00 AM and 6:00 PM on Saturdays
that are not legal holidays.
Renton
Policy SH-3: All shoreline policies,
regulations, and development shall
recognize and protect private rights
consistent with the public interest and,
to the extent feasible, shall be designed
and constructed to protect the rights
and privacy of adjacent property
owners. Shoreline uses and activities
should be discouraged if they would
cause significant noise or odor or
unsafe conditions that would impede
the achievement of shoreline use
preferences on the site or on adjacent
or abutting sites.
Renton Municipal Code Chapter 8.7 adopts by
reference the noise standards of Chapter 173-60
WAC (Table 9-1).
Sammamish
No applicable comprehensive plan
policies.
Sammamish Municipal Code 8.15.020 prohibits
public nuisances in general but does not identify
quantitative standards.
Yarrow Point
No applicable comprehensive plan
policies.
Yarrow Point Municipal Code 12.31.030 restricts
noisy construction activity audible within 50 feet to
between the hours of 7:00 AM and 6:00 PM,
Monday through Friday, and 9:00 AM and 5:00 PM
on Saturdays. Section 8.04 prohibits public
nuisances in general but does not identify
quantitative standards.
CHAPTER 9 January 2016 9 -6 NOISE
PHASE 1 DRAFT EIS
9.3 WHAT IS THE EXISTING NOISE ENVIRONMENT IN
THE COMBINED STUDY AREA?
The EIS Consultant Team reviewed multiple recent noise studies performed in Bellevue and
surrounding areas. This review revealed that transportation is the primary source of noise in
most of the study area communities. Locations within 100 feet of Interstate 90 or I-405 can
experience noise levels of 70 dBA Ldn or greater, while more secluded areas, such as lower
density residential areas in Bellevue, may not have noise levels above 53 dBA Ldn (Sound
Transit, 2011).
Hourly noise fluctuates consistent with daily activity levels. Noise levels during the day (7
AM to 10 PM) typically average between 50 and 60 dBA in suburban residential areas of
King County, falling to between 40 and 50 dBA during nighttime hours (King County
Department of Natural Resources and Parks, 2012).
9.3.1 Corona Discharge
The potential for noise from corona discharge was identified as a concern during scoping.
Corona is the electrical ionization of the air that occurs near the surface of the energized
conductor and suspension hardware because of very high electric field strength. Corona
discharge occurs when the voltage of the line exceeds the insulating capability of air and may
result in audible noise such as random crackling or hissing being produced by the
transmission lines.
The amount of corona produced by an overhead transmission line is a function of the voltage
of the line, the diameter of the conductors, the locations of the conductors in relation to each
other, the elevation of the line above sea level, the condition of the conductors and hardware,
and the local weather conditions.
Corona discharge is greater on misty days because the air has a lower insulating ability when
wet. Also, particles such as dust or water droplets that might come in contact with a
conductor tend to increase corona discharge. Therefore, the potential for noise from corona
discharge is greatest during wet weather. However, the noise generated by falling heavy rain
hitting the ground will typically be greater than the noise generated by corona, masking the
audible noise from the transmission line. Corona generated noise is of concern primarily for
transmission lines operating at voltages of 345 kV and above (U.S. DOE, 2006).
Recent analyses in the Pacific Northwest indicate that maximum corona noise produced from
230 kV lines at ground level during wet weather conditions is 29 dBA (Oregon DOE, 2013).
This is a relatively low noise level that would not be noticeable in most suburban
environments. As a point of reference, the U.S. Department of Housing and Urban
Development identifies a noise level of 45 dBA (Ldn) as an interior noise goal for federal
housing (HUD, 1985), which is equivalent to a steady state noise level over a 24-hour period
of 39 dBA.
January 2016 CHAPTER 9 NOISE 9-7
PHASE 1 DRAFT EIS
9.3.2 Other Equipment Noise
Transformers and their cooling fans generate noise as could any ancillary equipment such as
air handling equipment or backup generator testing. PSE has established noise standards for
autotransformers (upon initial installation) of 70 and 65 dBA at 1 meter with and without
cooling, respectively. Monitoring at a relatively small substation in a quiet suburban area in
Seattle found that typical daytime noise at the fence line during operation of a bank of three
transformers with cooling fans running was 64 dBA Leq 1. This level of noise could be
audible at adjacent sensitive land uses, depending on their distance and the existing ambient
noise level.
Electrical substations are exempt from the maximum permissible noise levels established in
Chapter 173-60 of the Washington Administrative Code.
9.4 HOW WERE POTENTIAL NOISE IMPACTS
ASSESSED?
For this programmatic EIS, a programmatic-level analysis was conducted to provide a
general evaluation of potential noise impacts from construction and operation of the proposed
project alternatives. The EIS Consultant Team reviewed available data on estimated noise
levels generated by construction activities, electrical transmission lines, and substation
equipment. Anticipated project noise levels were compared to the existing noise environment
for the types of land uses in the study areas.
9.5 WHAT ARE THE LIKELY CONSTRUCTION IMPACTS
RELATED TO NOISE?
9.5.1 Construction Impacts Considered
Construction of the proposed project would result in temporary increases in ambient noise
levels associated with the operation of heavy-duty construction equipment. Construction
noise levels would fluctuate depending on the particular type, number, and duration of use of
various pieces of construction equipment. The effect of construction noise would depend
upon the type of construction activity on a given day and equipment used, the distance
between construction activities and the nearest sensitive land uses, and the existing noise
levels around the site. Construction noise would be considered to impact surrounding land
uses if noise became noticeable to the extent that conversation or other outdoor activities are
disrupted, indoor activities are affected, or sleep is disturbed. An exceedance of noise
ordinance requirements, or the need for a variance, would be considered an impact.
Table 9-4 shows the type of equipment that would likely be used for construction of the
action alternatives.
1 Environmental Science Associates monitored noise levels at the Delridge substation in May 2013 as part
of a data gathering effort for the preparation of the Environmental Impact Statement for the proposed
Denny Substation in Seattle.
CHAPTER 9 January 2016 9 -8 NOISE
PHASE 1 DRAFT EIS
Construction noise impacts are assessed according to the following criteria:
Minor –Temporary construction-related noise consistent with local ordinances and occurring
during daytime hours.
Moderate –Temporary construction-related noise consistent with local ordinances but
potentially occur during nighttime hours in proximity to sensitive land uses
Significant –Temporary construction-related noise that would conflict with local ordinances
or occur during nighttime hours in proximity to sensitive land uses for a substantial (greater
than 2-week) period.
Table 9-4. Typical Noise Levels from Construction Equipment
Construction Equipment Noise Level (dBA, Leq at 50 feet)
Grader 85
Auger Drill 841
Scraper 84
Bulldozer 82
Pump Truck 82
Crane, mobile 81
Excavator 81
Generator 81
Roller 80
Concrete Mixer 79
Loader 79
Backhoe 78
Paver 77
Man Lift 75
Vibratory Sheet Pile Driver (Alternative 1, Option C
and Option D) 101
Source: Federal Highway Administration (FHWA), 2006.
1 Noise level from auger drill is reported for engine noise only. Augering can also generate noise from
shaking the bit to remove sticky soils.
9.5.2 No Action Alternative
The No Action Alternative would not result in construction activities. Corrective Action
Plans, the primary component of the No Action Alternative, would implement operational
measures to reduce and/or shift electrical demand and would not involve infrastructure
improvements. The No Action Alternative would not result in changes to maintenance
activities or require construction of new or relocated maintenance yards. While conductor
January 2016 CHAPTER 9 NOISE 9-9
PHASE 1 DRAFT EIS
replacement could occur under the No Action Alternative, installation methods would likely
involve the use of a single-man lift and would cause negligible construction noise.
9.5.3 Alternative 1: New Substation and 230 kV Transmission Lines
Impacts are described according to the major components associated with Alternative 1. The
transmission line options are described, with associated major facilities.
Option A: New Overhead Transmission Lines 9.5.3.1
Installation of new overhead transmission lines would require specific construction activities
that may include boring holes for geotechnical investigations, removing existing wood poles
and replacing them with tubular steel poles (TSPs) and foundations, installing conductors,
relocating existing distribution and telecommunications facilities, and associated site
preparation activities (e.g., road grading and work pad construction). These activities would
require use of much of the equipment presented in Table 9-4. Additionally, construction of
the new transformer would require similar equipment, depending on whether the transformer
would be added to an existing substation or installed in a new substation.
Table 9-5 provides an estimate of noise contour distances
from each of the activities associated with transmission
line installation. Tower locations would be spaced
approximately 1,000 feet apart, and noise receptors within
the distances indicated in Table 9-5 could be exposed to
the noise levels indicated over a period of approximately 1
week while the work is conducted. Additionally, stringing
of power lines would likely be completed using cranes,
which would generate additional noise.
If the selected alignment under Alternative 1, Option A
has supporting structures or transformers closer than 180
feet to sensitive receptors, those receptors could be
exposed to noise levels in excess of 75 dBA. While likely to be above background noise
levels, this would likely be within the restrictions for construction noise in Section 12.88 of
the King County Code (and most local codes), which exempt construction noise from
quantitative noise exposure limits but restrict construction noise to daytime hours. If
nighttime construction work were required, a moderate noise impact could occur. Nighttime
construction activity would require a variance or exemption from regional or local codes and
would potentially be disruptive to adjacent sensitive land uses during typical sleeping hours.
A Noise Contour is a line on a
map that represents equal
levels of noise exposure.
A Noise Receptor is a location
where noise can interrupt
ongoing activities. Sensitive
receptors for noise are
generally considered to include
hospitals, nursing homes,
senior citizen centers, schools,
churches, libraries, and
residences.
CHAPTER 9 January 2016 9 -10 NOISE
PHASE 1 DRAFT EIS
Table 9-5. Construction Activity Noise Contour Distances
Construction Activity dBA Leq Contour Distance (feet)
75 70 65 60 55
Conductor Removal 183 327 572 975 1,610
Wood Pole Removal 171 307 537 916 1,517
TSP Foundation Installation 173 309 539 924 1,534
TSP Erection 132 239 420 726 1,219
Conductor Installation at Stringing Site 204 364 630 1,067 1,757
Source: Based on SCE, 2013 and 2014.
Option B: Existing Seattle City Light 230 kV Transmission 9.5.3.2
Corridor
Rebuilding and reconductoring the existing Seattle City Light transmission lines would
require replacing most of the existing structures and all conductors. Consequently the
construction-related noise impacts for Alternative 1, Option B would be similar to those
described for Option A. Noise impacts would depend on the relative distances of the
alignment from sensitive receptors.
Option C: Underground Transmission Lines 9.5.3.3
Construction techniques for Alternative 1, Option C would be different and require
substantially more earthwork that either Option A or Option B. Rather than construction
occurring at discrete tower locations, Option C would require open-cut trenching techniques
over a continuous alignment. Construction activity would likely progress along the alignment
at about 100 feet per day, typically affecting nearby receptors for a duration of approximately
1 week.
Trenching typically involves the use of excavators or backhoes, dump trucks, bulldozers,
concrete mixers, and cranes. At some locations such as busy intersections, or to cross hills or
streams, trenchless techniques such as jack-and-bore or horizontal directional drilling may be
required. Trenchless techniques can require the brief use of relatively noisy impact
equipment such as vibratory sheet pile drivers to install sheet piles around the bore pit.
Jackhammers or hoe rams are other relatively noisy impact equipment that may be used to
remove concrete structures.
The construction noise impacts of Option C would be more substantial than either those of
Alternative 1, Option A or Option B because of the increased intensity and duration of
construction and the potential use of impact equipment or other noisy construction
techniques. However, the overall impact would still be consistent with local codes regarding
construction noise and considered a minor impact if the work is restricted to daytime hours. If
nighttime construction work were required, a moderate noise impact could occur. Nighttime
construction activity would require a variance from regional or local codes and could
potentially be disruptive to adjacent sensitive land uses during typical sleeping hours.
January 2016 CHAPTER 9 NOISE 9-11
PHASE 1 DRAFT EIS
Option D: Underwater Transmission Lines 9.5.3.4
Construction techniques for Alternative 1, Option D would require a combination of standard
construction equipment, such as backhoes and vacuum trucks, as well as equipment for
potential trenchless methods such as horizontal directional drilling. Cable would be installed
using a ship designed to lay the cable in one continuous piece. Installation of cable landing
points may require sheet or soldier pile driving, and cofferdams may be required for bore pits
that also would require sheet pile driving. Construction would be centralized at the cable
landing points and therefore would impact the fewest sensitive receptors with construction
noise.
Although sheet pile driving is relatively noisy and likely under this option, the overall impact
would still be consistent with local codes regarding construction noise and considered a
minor impact if restricted to daytime hours. If nighttime construction work were required, a
moderate noise impact could occur depending on the proximity of sensitive receptors.
Nighttime work would require a variance from regional or local codes and could potentially
be disruptive to adjacent sensitive land uses during typical sleeping hours.
9.5.4 Alternative 2: Integrated Resource Approach
Energy Efficiency and Demand Response Component 9.5.4.1
Energy efficiency and demand response components would not involve infrastructure
improvements, changes to maintenance activities, or construction of new or relocated
maintenance yards. Consequently, these components would have no impact with regard to
construction noise.
Distributed Generation Component 9.5.4.2
Construction of distributed generation facilities could result in noise impacts within the
vicinity of each facility. Impacts would vary in intensity and duration depending on the type
and magnitude of facility.
The most likely forms of distributed generation would be gas turbines, anaerobic digesters,
microturbines, and fuel cells. These facilities would be relatively small units (ranging from a
small rooftop installation up to 1 acre) distributed throughout the study area rather than one
large generation facility. Construction of these facilities would vary in duration and require
standard construction equipment presented in Table 9-4.
Depending on the distance to the construction area, receptors in the vicinity of each facility
could be exposed to noise levels in excess of 75 dBA. While likely to be above background
noise levels, this construction noise would likely be within the restrictions for construction
noise in Section 12.88 of the King County Code (and most local codes), which exempt
construction noise from quantitative noise exposure limits but restrict construction noise to
daytime hours. If nighttime construction work were required, a moderate noise impact could
occur depending on the proximity of sensitive receptors. Nighttime work would require a
variance from regional or local codes and could potentially be disruptive to adjacent sensitive
land uses during typical sleeping hours.
CHAPTER 9 January 2016 9 -12 NOISE
PHASE 1 DRAFT EIS
Energy Storage Component 9.5.4.3
Construction of an energy storage facility could result in noise impacts within the vicinity of
each facility. Impacts would vary in intensity and duration depending on the proximity to
receptors. Construction of these facilities would typically take up to 6 months and require
many of the standard types of construction equipment presented in Table 9-4.
Depending on the distance to the construction area, receptors in the vicinity of each facility
could be exposed to noise levels in excess of 75 dBA. While likely to be above background
noise levels, this construction noise would likely be within the restrictions for construction
noise in Section 12.88 of the King County Code (and most local codes), which exempt
construction noise from quantitative noise exposure limits but restrict construction noise to
daytime hours. If nighttime construction work were required, a moderate noise impact could
occur depending on the proximity of sensitive receptors. Nighttime work would require a
variance from regional or local codes and could potentially be disruptive to adjacent sensitive
land uses during typical sleeping hours.
Peak Generation Plant Component 9.5.4.4
Peak generation plants would have construction noise impacts similar to those described
above for distributed generation. Construction of these facilities would typically take up to 12
months and require standard construction equipment presented in Table 9-4.
9.5.5 Alternative 3: New 115 kV Lines and Transformers
The construction noise impacts of Alternative 3 would largely be the same as Alternative 1,
except that a new transformer would need to be installed at each of three existing substations,
thus potentially impacting more receptors. The Sammamish substation is approximately 700
feet from the nearest receptor; the Lake Tradition substation is approximately 3,200 feet from
the nearest receptor; and the Talbot Hill substation is approximately 200 feet from the nearest
receptor, although this substation is expansive and, depending the location of the transformer,
the nearest receptor could be much farther away.
As with Alternative 1, Option A, if the selected alignment would have supporting structures
or transformers closer than 180 feet, receptors could be exposed to noise levels in excess of
75 dBA. While likely to be above background noise levels, this would likely be within the
restrictions for construction noise in Section 12.88 of the King County Code (and most local
codes), which exempt construction noise from quantitative noise exposure limits but restrict
construction noise to daytime hours. If nighttime construction work were required, a
moderate noise impact could occur depending on the proximity of sensitive receptors.
Nighttime work would require a variance from regional or local codes and could potentially
be disruptive to adjacent sensitive land uses during typical sleeping hours.
January 2016 CHAPTER 9 NOISE 9-13
PHASE 1 DRAFT EIS
9.6 HOW COULD OPERATION OF THE PROJECT
AFFECT THE NOISE ENVIRONMENT?
9.6.1 Operation Impacts Considered
Impacts Common to All Alternatives 9.6.1.1
There are no impacts that would be common to all alternatives because of the diversity of
alternatives considered in this Draft EIS. Alternatives involving overhead power lines would
have common impacts regarding operational noise from corona discharge. Alternatives
involving construction of new facilities (Alternative A), some components of Alternative B
(distributed generation), and Alternative C would all have operational noise impacts of
varying degrees and durations which are discussed individually below.
Operational noise impacts are assessed according to the following criteria:
Minor – Project would generate operational noise consistent with local ordinances and would
increase ambient noise levels by less than 3 dBA (see Section 9.2).
Moderate – Project would generate operational noise consistent with local ordinances and
would increase ambient noise levels by less than 5 dBA (see Section 9.2).
Significant – Project would generate operational noise that would conflict with local
ordinances or would increase ambient noise levels by 5 dBA or greater at a sensitive land
use.
9.6.2 No Action Alternative
The No Action Alternative would rely on Corrective Action Plans to reduce and/or shift
electrical demand. This alternative would not involve infrastructure improvements, changes
to maintenance activities, or operation of new or relocated maintenance yards. Consequently
there would be no operational noise impacts associated with the No Action Alternative.
9.6.3 Alternative 1: New Substation and 230 kV Transmission Lines
Operational impacts for Alternative 1 are described for the major components, with
transmission lines discussed first, followed by equipment noise from substations.
Option A: New Overhead Transmission Lines 9.6.3.1
Corona Discharge 9.6.3.1.1
Potential operational impacts from overhead transmission lines associated with any of the
transmission line alternatives would occur from corona discharge. The maximum corona
noise produced from 230 kV lines at ground level during wet weather conditions a relatively
low noise level that would not be noticeable in most suburban environments, see Sections 9.3
and 9.4. Background ambient noise levels in suburban residential areas of King County fall
between 40 and 50 dBA during nighttime hours. Even in rural areas, corona noise from 230
kV transmission lines would be unlikely to impact sensitive uses. Consequently, audible
corona noise would be a negligible operational noise impact of Alternative 1, Option A.
CHAPTER 9 January 2016 9 -14 NOISE
PHASE 1 DRAFT EIS
Other Equipment Noise 9.6.3.1.2
The new substation would be an operational noise source of Alternative 1, Option A.
Transformers and their cooling fans generate noise as could any ancillary equipment such as
air handling equipment or backup generator testing. PSE has established noise standards for
autotransformers (upon initial installation) of 70 and 65 dBA at 1 meter with and without
cooling, respectively. This level of noise could be audible at adjacent sensitive land uses,
depending on their distance and the existing ambient noise level.
Electrical substations are exempt from the maximum permissible noise levels established in
Chapter 173-60 of the Washington Administrative Code. Consequently, substation operations
would likely be consistent with local municipal codes governing noise sources. However, the
substation could result in a noticeable increase in local ambient noise levels and result in a
minor noise impact. Mitigation measures are identified to address this potential (Section 9.8).
Option B: Existing Seattle City Light 230 kV Transmission 9.6.3.2
Corridor
Alternative 1, Option B would replace existing Seattle City Light lines with new lines rated
for increased electrical capacity. The existing and proposed lines are 230 kV. Option B would
reduce the potential for exposing new receptors to corona noise because the improvements
would be confined to existing electrical facilities. Also, as discussed under Option A, corona
noise would be a negligible noise impact. As with Option A, additional substations would be
required under Option B. Therefore, Option B would have a similar noise impacts to Option
A (negligible to minor).
Option C: Underground Transmission Lines 9.6.3.3
Alternative 1, Option C would locate transmission lines underground through the entirety of
the transmission alignment as well as from the alignment to local substations. There would be
no audible noise resulting from operation of Option C for those portions of the line placed
underground. If some portions of the transmission line are aboveground, impacts in those
segments would be consistent with those described for Option A. Option D: Underwater
Transmission Lines. As with Option A, additional substations would be required. Therefore,
Option C would have a similar noise impacts to Option A (negligible to minor).
Option D: Underwater Transmission Lines 9.6.3.4
While Alternative 1, Option D would locate transmission lines underwater through most of
the transmission alignment, some overhead transmission lines would be required connecting
the proposed underground lines to the three substation locations. There would be a small
potential for exposing sensitive land uses to corona noise, but this would be a negligible
adverse impact as described for Option A. As with Option A, additional substations would be
required. Therefore, Option D would have a similar noise impacts to Option A (negligible to
minor).
January 2016 CHAPTER 9 NOISE 9-15
PHASE 1 DRAFT EIS
9.6.4 Alternative 2: Integrated Resource Approach
Energy Efficiency Component 9.6.4.1
Energy efficiency improvements would not involve infrastructure improvements, changes to
maintenance activities, or new or relocated transformers, substations, or maintenance yards.
These components would have no impact with regard to operational noise.
Demand Response Component 9.6.4.2
Demand response measures would entail implementing measures to reduce and/or shift
electrical demand and would not involve infrastructure improvements, changes to
maintenance activities, or new or relocated transformers, substations, or maintenance yards.
Consequently, implementation of demand response systems would have no impact with
regard to operational noise.
Distributed Generation Component 9.6.4.3
Distributed generation facilities could result in operational noise impacts within the vicinity
of each facility. The impacts would vary in intensity and duration with the type and
magnitude of facility. Gas turbines, reciprocating engines, and similar mechanical generators
could generate operational noise on an intermittent basis. This noise could be a concern to
neighbors or require mitigation to ensure operations are consistent with noise standards in
county or municipal codes. This represents a minor to moderate noise impact.
Energy Storage Component 9.6.4.4
Operation of a battery storage facility would be similar to that of a small office building, with
worker vehicle trips and vendor trips to perform periodic replacement of degraded cells
representing the only meaningful noise source. Energy storage would have a negligible
impact with regard to operational noise.
Peak Generation Plant Component 9.6.4.1
The peak generation plants are assumed to be 20 MW simple-cycle gas-fired generators or
similar equipment. The primary noise sources of this type of generation plant include the gas
turbine generators, gas turbine air inlets, selective catalytic reduction units and their exhaust
stacks, electrical transformers, fuel gas compressors and metering equipment, and various
pumps and fans. Cumulatively this equipment can result in operational noise levels of
approximately 65 dB at 300 feet (Siemens AG, 2005), which is high enough that in some
residential areas it would not meet noise regulations. Depending on the location of receptors
relative to a generation plant, local noise levels could be elevated, especially during nighttime
hours, and represent a moderate noise impact. Mitigation measures are identified to address
operational noise from combustion turbine facilities (Section 9.8).
CHAPTER 9 January 2016 9 -16 NOISE
PHASE 1 DRAFT EIS
9.6.5 Alternative 3: New 115 kV Lines and Transformers
Corona Discharge 9.6.5.1
Potential operational impacts of 115 kV overhead power lines resulting from corona
discharge would be the same as those identified above for 230 kV power lines. Corona
discharge from 115 KV lines would be a negligible operational noise impact.
Other Equipment Noise 9.6.5.2
New transformers would be an operational noise source under Alternative 3. As discussed
above with respect to Alternative 1, Option A, operational transformer noise could be audible
at adjacent sensitive land uses, depending on their distance and the existing ambient noise
level. While electrical substations are exempt from the maximum permissible noise levels
established in Chapter 173-60 of the Washington Administrative Code, the transformers
could result in a noticeable increase in local ambient noise levels and a minor noise impact.
Mitigation measures are identified to address this potential (Section 9.8).
9.7 WHAT MITIGATION MEASURES ARE AVAILABLE
FOR POTENTIAL NOISE IMPACTS?
9.7.1 Nighttime Construction Noise
For project elements that would require prolonged nighttime construction activities, portable
acoustical barriers may be used to reduce noise. Moveable sound barrier curtains can provide
15 dBA of sound attenuation (INC, 2014). Static sound barrier curtains can provide sound
transmission loss of 16 to 40 dBA, depending on the frequency of the noise source (ENC,
2014).
9.7.2 Substation/Transformer Operational Noise
Although electrical substations are exempt from the maximum permissible noise levels
established in Chapter 173-60 of the Washington Administrative Code, the transformers
could result in a noticeable increase in local ambient noise levels and therefore elicit an
adverse community reaction. If new transformers are proposed for installation in a new
substation facility, siting of that facility should consider the proximity of sensitive land uses.
Site plans should include noise attenuation measures as necessary to maintain noise levels at
the nearest receptors within 5 dBA of existing ambient noise levels. Static sound barrier
curtains can provide sound transmission loss of 16 to 40 dBA, depending on the frequency of
the noise source (ENC, 2014).
9.7.3 Distributed Energy Operational Noise
The following distributed generation sources have the potential to result in minor to moderate
operational noise impacts: wind turbines, gas turbines, anaerobic digesters, reciprocating
engines, and microturbines. Siting of facilities that would operate these types of equipment
should consider the proximity of sensitive land uses. Site plans should include noise
attenuation measures as necessary to maintain noise levels at the nearest receptors within 5
dBA of existing ambient noise levels. Static sound barrier curtains can provide sound
January 2016 CHAPTER 9 NOISE 9-17
PHASE 1 DRAFT EIS
transmission loss of 16 to 40 dBA, depending on the frequency of the noise source (ENC,
2014). The efficacy of such barriers would depend on the surrounding elevations of the plant
and receptors, and air flow requirements of the plant that might prohibit ceiling barriers.
Exhaust stack silencers are also widely available for electrical generator engine applications.
9.8 ARE THERE ANY CUMULATIVE IMPACTS FROM
NOISE AND CAN THEY BE MITIGATED?
Because local conditions play an important role in assessing potential noise impacts, it would
be speculative, at the programmatic level, to identify potential cumulative noise impacts.
First, the specific locations of facilities are not yet identified and, therefore, existing ambient
noise conditions and sources are also unavailable. Secondly, the contribution from other
foreseeable projects that may cumulatively contribute to noise impacts would also depend on
the proximity to proposed noise sources and existing or proposed receptors. However, it can
be acknowledged that the Eastside is continuing to urbanize, with accompanying increased
noise levels from roadway traffic, construction, and aircraft overflights. Additional noise
from energy facilities will contribute to that overall trend, but specific quantitative increases
cannot reliably be estimated.
9.9 ARE THERE ANY SIGNIFICANT UNAVOIDABLE
ADVERSE NOISE IMPACTS?
With prudent siting of new substations and distributed generation facilities, there would be no
significant and unavoidable construction-related or operational adverse noise impacts
associated with any of the project alternatives. However, peak generation plants, which
would need to be located next to substations that are generally within or adjacent to
residential areas, could have significant noise impacts that can only be avoided by ensuring
that there are no residential uses in close proximity to the plants.
CHAPTER 9 January 2016 9 -18 NOISE
PHASE 1 DRAFT EIS
CHAPTER 10. LAND USE AND
HOUSING
10.1 HOW WERE EXISTING LAND
USES AND HOUSING IN THE
COMBINED STUDY AREAS
EVALUATED?
This chapter describes the types of existing land uses, and
planning designations within the combined study area
shown in Figure 1-4, as well as applicable land use and
housing policies. Land use information was obtained from
data maintained by the King County Assessor for property
valuation and tax purposes. Existing population and
housing supply in the study area are also described, based
on U.S. Census data and local comprehensive plans. Since
there is no data source specific to the study area itself, for
this programmatic evaluation, population and housing data
at the city level are used as a proxy to provide context for
the study area.
Planning designations were obtained from comprehensive
plans and zoning maps from study area communities.
Shoreline planning designations were identified using
shoreline master programs and Washington State
Department of Ecology (Ecology) data.
To provide context for discussion of land use impacts, it is
also important to understand the regulatory framework by
which land uses are established and regulated. Therefore,
this chapter describes the applicable state, regional, and
local legislation, policies, and regulations for land use and
shoreline planning. The land use and shoreline policies of
each study area community that would likely apply to the
project (including those related to essential public
facilities) were identified based on local comprehensive
plans and shoreline master programs.
Land Use and Housing Key
Findings
Construction would not be
expected to lead to land use
impacts.
The No Action Alternative
would likely lead to declining
reliability of the electrical
power supply on the Eastside,
which could be inconsistent
with local planning policies and
constitute a significant adverse
impact.
Of the action alternatives,
Alternative 1, Option A has the
greatest potential to create
significant adverse land use
and housing impacts. The
magnitude of probable impacts
ranges from minor to
significant, depending on final
project location and adjacent
uses.
Alternative 3 could result in
land use changes similar to
Alternative 1, Option A, but
would require less property
acquisition. The severity of
probable impacts ranges from
minor to moderate, depending
on specific project siting and
adjacent uses.
Alternative 2 would have the
fewest overall land use
impacts, ranging from
negligible to minor.
January 2016 CHAPTER 10 LAND USE AND HOUSING 10-1
PHASE 1 DRAFT EIS
10.2 WHAT ARE THE RELEVANT PLANS, POLICIES, AND
REGULATIONS?
10.2.1 Comprehensive Planning Framework
In 1990, the State of Washington adopted the Growth
Management Act (GMA) in response to rapid population
growth and concerns with suburban sprawl, environmental
protection, and quality of life. The GMA requires the
fastest growing counties and the cities within them to
identify and protect critical areas and natural resource
lands, designate urban growth areas, prepare
comprehensive plans, and implement those plans through
capital investments and development regulations. The
GMA also establishes a goal related to adequate utilities
and services for development – Growth Management Act
Goal 12.
Each study area community has adopted a comprehensive
plan in compliance with the GMA. The local comprehensive plans lay out the goals and
policies by which housing and employment growth over a 20-year period will be managed by
each city and county. At a minimum, plans must provide for land uses and densities, capital
facilities, and transportation infrastructure sufficient to
meet future needs.
In conjunction with the GMA, regional planning strategies
are articulated by the Puget Sound Regional Council
(PSRC). The PSRC has published a planning document
titled VISION 2040, which serves as the long-range
growth management, environmental, economic, and
transportation strategy for the central Puget Sound region.
VISION 2040 also contains a Regional Growth Strategy
that provides substantive guidance for planning for the
roughly 1.7 million additional people and 1.2 million
additional jobs expected in the region between 2000 and
2040 (PSRC, 2015b).
In complying with GMA, coordinating with regional
planning, and setting local planning parameters, local
governments establish comprehensive plan land use
designations to guide future growth and development. Comprehensive plan land use
designations are unique to each study area community but typically reflect the following
broad categories:
• Residential - Depending on the community, designates land for a range of
different densities of housing types (characterized as low, moderate, and high). In
Puget Sound Regional
Council is an association of
cities, towns, counties, ports,
and state agencies that serves
as a forum for developing
policies and making decisions
about regional growth
management, environmental,
economic, and transportation
issues in the four-county
central Puget Sound region of
Washington state (King,
Pierce, Snohomish and Kitsap
Counties).
0
Growth Management Act
Goal 12: Public facilities and
services. Ensure that those
public facilities and services
necessary to support
development shall be adequate
to serve the development at
the time the development is
available for occupancy and
use without decreasing current
service levels below locally
established minimum
standards.
CHAPTER 10 January 2016 10-2 LAND USE AND HOUSING
PHASE 1 DRAFT EIS
some cases allowed or desired housing types may be designated (such as single-
family detached, townhouse, etc.).
• Mixed-Use – Incorporates both residential and commercial uses in close
proximity in the interest of creating high-density communities where housing,
services, and employment are within easy walking distance. Some communities
designate more specialized areas such as Transit-Oriented Development or Urban
Center.
• Parks/Open Space - Designates land for parks, recreation facilities, open space,
greenbelts, conservation easements, and urban/rural separators.
• Commercial - Designates land for commercial uses such as office and retail, and
may be divided into specialty classifications such as Business Park or Medical.
• Industrial - Designates land for warehouses and manufacturing, and may be
divided into categories such as Light Industrial, Heavy Industrial, or
Manufacturing.
• Institutional - Designates land for public schools, government buildings, civic
centers, and other public facilities.
• Resource Lands - Designates land for forestry, mining, and agriculture in
unincorporated areas of King County.
The comprehensive plans adopted by study area communities that were evaluated for this EIS
are listed in Appendix E. For this programmatic Draft EIS, subarea plans were not reviewed,
but subarea plans could be applicable at the project level analysis. The comprehensive plan
land use designations of these plans vary among the communities and were grouped into
generalized categories, reflecting the seven categories above, for the purposes of
summarizing planned future land uses consistently across the combined study area. The
proportional distribution of designations across categories are shown in Figure 10-1 and
mapped in Figure 10-2. Future land uses are mostly single-family residential with a mix of
multifamily, mixed-use, and commercial in urban areas.
January 2016 CHAPTER 10 LAND USE AND HOUSING 10-3
PHASE 1 DRAFT EIS
Figure 10-1. Future Land Use Designation by Type 1
Sources: City of Bellevue, 2015a; City of Issaquah, 2015; City of Kirkland, 2015b; City of Newcastle, 2015; City of
Redmond, 2015; City of Renton, 2015; City of Sammamish, 2015
Comprehensive plans also include goals and policies that establish a 20-year vision and
roadmap for each study area community’s anticipated future. Appendix F lists the
comprehensive plan land use goals and policies that could address or guide the Energize
Eastside Project’s location or type of electrical infrastructure. Goals and policies that relate to
electrical infrastructure can be grouped into the following broad topics2:
1. Encouragement of energy efficiency and conservation - Goals and policies
generally promote investment in, and proliferation of, renewable energy resources
and reduce the demand for fossil fuels.
2. Hazardous pipeline safety - Goals and policies generally require coordination
between the pipeline operator, development project proponents, and local
jurisdictions to examine the potential for construction and operational conflicts, and
to avoid, minimize, or mitigate for such conflicts.
3. Utility corridor development/management - Goals and policies generally promote
co-location and shared use of utility corridors in order to minimize impacts, except
when major adverse safety or land use consequences could result. Timely
improvements to infrastructure are encouraged in order to meet anticipated energy
demands.
1 Figures 10-1 and 10-2 do not include the communities of Medina, Clyde Hill, Yarrow Point, Hunts Point,
and Beaux Arts Village since GIS data used for this land use analysis were not available from the
jurisdictions. The land use within those communities is primarily single-family residential and
comprehensive plans indicate no proposed changes from existing land uses (see Figure 10-5).
2 The “broad topics” provided in this chapter are intended to facilitate comprehension of applicable land
use goals and policies and therefore do not exactly match the “topics” in Appendix F, which are applicable
to multiple EIS chapters.
CHAPTER 10 January 2016 10-4 LAND USE AND HOUSING
PHASE 1 DRAFT EIS
Energize Eastside EIS 140548
Figure 10-2
Future Land Uses
SOURCE: King County 2015; ESA 2015; WAECY 2014; Renton 2015;
Newcastle 205; Bellevue 2015; Sammamish 2015; Kirkland 2015; Redmond 2015.
For more info visit www.energizeeastsideeis.org/map-futurelanduse
Lake
Washington
Lake
Sammamish
Bellevue Sammamish
Issaquah
Renton
Newcastle
RedmondKirkland
Beaux Arts
Medina
Clyde
Hill
Hunts
Point
Yarrow
Point
Mercer
Island
Text
Lakeside
Sammamish
Talbot Hill
Novelty Hill
Lake Tradition
Generalized Comprehensive
Plan Land Use Designations
Single-family Residential
Multi-family Residential
Mixed-use (residential and
commercial)
Commercial (retail and
office)
Industrial
Institutional
Resource Lands
Parks/Open Space
Recreation
Existing Substations
Combined Study Area
Boundary
Roadway
Water bodies
City Limits
No Data Available
U:\GIS\GIS\Projects\14xxxx\D140548_EastsidePSETransmisisonCoor\MXD\Com pPlan.mxd
0 2
Miles
Note: This map is for reference only. It is not guaranteed that the information is accurate or complete.
4. Protection of community or neighborhood character and safety - Goals and
policies generally support siting and designing utilities to minimize conflicts with
community character and maintain safety.
5. General utility coordination regarding location and service provision - Goals and
policies generally support coordination between the utility purveyors and government
to ensure safe, efficient, and reliable service provision consistent with land use
regulations.
6. Ensuring compatibility of land uses - Goals and policies generally encourage
locating, designing, and screening infrastructure to ensure compatibility with the
surrounding land use pattern and, where feasible, siting within the area requiring
additional service.
7. Undergrounding of utility lines - Goals and policies support undergrounding
existing and new or expanding lines where safe, practical, and in accordance with
rules, regulations, and other utility- and site-specific factors.
8. Shoreline management – Goals and policies generally discourage locating non-
water-related utilities in the shoreline jurisdiction, particularly in-water. Uses that
negatively impact ecological functions are generally prohibited.
9. Adequate infrastructure for development – Goals and policies generally
acknowledge that electrical service and infrastructure should be available to serve
development.
Each comprehensive plan is required to establish a
process for identifying and siting essential public
facilities (EPFs). State, regional, county, and local
agencies are also required to coordinate in determining
the location of these facilities. EPFs are facilities that are
typically difficult to site, such as airports, state education
facilities, and state or regional transportation facilities
(RCW 36.70A.200). A determination of whether the
Energize Eastside Project qualifies as an EPF would be
made by the permitting agency at the time of permit
preparation or submittal.
10.2.2 Shoreline Planning Framework
In 1971, the State of Washington adopted the Shoreline Management Act (SMA) to foster
reasonable and appropriate land uses along Shorelines of the State (simply referred to as
“shorelines” in this document). A goal of the SMA is to protect shorelines and adjacent
shorelands from incompatible development as well as “to prevent the inherent harm in an
uncoordinated and piecemeal development of the state’s shorelines” (Chapter 90.58 RCW,
1971). Ecology oversees management of the shoreline resources in the State of Washington.
The SMA applies to all 39 counties and more than 200 towns and cities that have shorelines
(RCW 90.58.030(2)) within their boundaries.
0
Essential Public Facilities
(EPF) are defined by state law
(RCW 36.70A.200 and WAC
365-196-550) as necessary
facilities that are typically
difficult to site. The GMA
requires planning so that such
facilities can be placed
appropriately.
CHAPTER 10 January 2016 10-6 LAND USE AND HOUSING
PHASE 1 DRAFT EIS
Local jurisdictions with shorelines have adopted shoreline
master programs (SMPs) to comply with the SMA. These
local SMPs include shoreline management goals and
policies, identify shoreline environment designations and
allowed uses, and outline regulations and permit
requirements for activities within shoreline jurisdiction.
An SMP is considered to be both a policy document,
identifying the community’s 20-year vision of its
shorelines, and a regulatory document. SMPs must be
consistent with the state implementing regulations for the
SMA (WAC 173-26).
The communities of Clyde Hill and Newcastle do not
have their own specific SMPs. Newcastle has adopted
(and implements) King County’s program and Clyde Hill
does not have any jurisdictional shoreline areas. The City
of Bellevue is updating its SMP consistent with state law.
Not all shoreline areas have been established on adopted
maps. Figure 10-3 shows the location of the available
mapped shorelines of the state within the combined study
area (Ecology, 2015a-c 3), including Lake Washington,
Lake Sammamish, Sammamish River, Bear Creek, and
Issaquah Creek. These shorelines would be regulated in addition to other areas where
shoreline jurisdiction would be applied based on criteria described above (e.g., location
relative to known waters of the state, rate of stream flow).
3 The Department of Ecology does not purport to maintain up-to-date shoreline mapping for local
jurisdictions.
Shorelines of the State
include:
• All marine waters;
• Streams and rivers with
greater than 20 cubic feet
per second mean annual
flow;
• Lakes 20 acres or larger;
• Upland areas called
shorelands that extend 200
feet landward from the edge
of these waters; and
• The following areas when
they are associated with one
of the above:
• Biological wetlands and river
deltas; and
• Some or all of the 100-year
floodplain including all
wetlands within the 100-year
floodplain.
January 2016 CHAPTER 10 LAND USE AND HOUSING 10-7
PHASE 1 DRAFT EIS
Energize Eastside EIS 140548
Figure 10-3
Shorelines of the State
SOURCE: King County 2015; WA Ecology 2015; Bellevue 2015;
Redmond 2015; Sammamish 2015; Issaquah 2015.Note: This map is for reference only. It is not guaranteed that the information is accurate or complete. Lake Washington
Lake
Sammamish
Bellevue Sammamish
Issaquah
Renton
Newcastle
RedmondKirkland
Beaux
Arts
Medina
Clyde
Hill
Hunts
Point
Yarrow
Point
Mercer
Island
K e l s ey Creek
Lakeside
Sammamish
Talbot Hill
Novelty Hill
Lake Tradition
Ames Lake
Beaver Lakes
Lake Kathleen
Phantom Lake
Pine Lake
CedarRiver
I
ssaquahC
reek
B e a rCreek
S
a
m
m
amish
River
Bl
ackRi
verSno q u almieRiver
M
a
yCreek
Ev ans
Cr
eekShoreline of the
State - Streams
Shoreline of the
State - Water
bodies
Existing
Substations
Roadway
Combined Study
Area Boundary
Water bodies
City Limits
0 2
MilesU:\GIS\GIS\Projects\14xxxx\D140548_EastsidePSETransmisisonCoor\MXD\ShorelineMasterPlans.mxdNote: The Department of Ecology does not purport to maintain up-to-date shoreline mapping for local jurisdictions.
Shoreline Master Programs map and classify known
shorelines, and establish policies on how to determine
where other regulated shorelines may exist. Shoreline
areas are classified into specific shoreline environment
designations, based on the existing land use pattern,
biological and physical characteristics of the shoreline,
and the goals of the community as expressed through
comprehensive plans and in conformance with state’s
recommended classification system (WAC 173-26-211
(4) and (5)). The state code recommends the following six
basic shoreline environment designations:
1. High-Intensity to provide for high-intensity
water-oriented commercial, transportation, and
industrial uses while protecting existing ecological
functions and restoring ecological functions in
areas that have been previously degraded;
2. Shoreline Residential to accommodate residential development and appurtenant
structures along with appropriate public access and recreational uses;
3. Urban Conservancy to protect and restore ecological functions of open space,
floodplains, and other sensitive lands where they exist in urban and developed
settings, while allowing a variety of compatible uses;
4. Rural Conservancy to protect ecological functions and conserve existing natural
resources and valuable historic/cultural areas to provide for sustained resource use,
achieve natural floodplain processes, and provide recreational opportunities;
5. Natural to protect shoreline areas that are relatively free of human influence or that
include intact or minimally degraded functions intolerant of human use; and
6. Aquatic to protect, restore, and manage the unique characteristics and resources of
the areas waterward of the ordinary high water mark.
Local governments map their designated shoreline environments where known. Each
community’s SMP describes the criteria for determining shoreline environment
classifications around area water bodies. Local governments can develop shoreline
environment designations that are different from the general categories listed above.
Appendix F provides a sample of SMP goals and policies from study area communities that
could guide the Energize Eastside Project’s location or type of electrical infrastructure. The
goals and policies for activity within the shoreline jurisdiction can be generally grouped into
the following broad topics:
1. Protection of ecological functions and aesthetics- Goals and policies generally
promote the protection and preservation of vegetation, fish and wildlife species and
their habitats, and viewsheds for the enjoyment of current and future generations.
The SMA states that “the
interests of all the people shall
be paramount in the
management of shorelines of
statewide significance.” In
western Washington,
Shorelines of Statewide
Significance in the combined
study area include:
• Lakes or reservoirs with a
surface area of 1,000 acres
or more (includes Lake
Washington and Lake
Sammamish); and
• Wetlands associated with all
of the above.
January 2016 CHAPTER 10 LAND USE AND HOUSING 10-9
PHASE 1 DRAFT EIS
2. Use priorities - Goals and policies generally reflect a preference for water-oriented
uses and place limitations or prohibitions on non-water-oriented uses.
3. Avoidance, minimization, mitigation - Goals and policies generally promote
avoidance, minimization, and mitigation of interruptions to natural shoreline
functions.
4. Limitation on infrastructure – Goals and policies generally state that infrastructure
should be limited to the minimum necessary to achieve its purpose. Location outside
of the shoreline jurisdiction is preferred unless other locations are infeasible or a
water-dependent component exists.
5. Coordinated management and development - Goals and policies generally
promote coordination between local, state, and federal agencies to prevent harm to
shorelines.
6. Maintenance of natural areas and dynamics - Goals and policies generally
promote maintaining shorelines to perform natural dynamic processes that support
fish and wildlife and associated habitat.
Many of the adopted SMPs do not contain specific goals and policies for locating EPFs.
Where EPFs are not specifically defined in the SMP, the applicable jurisdiction would
preliminarily evaluate the proposed activities, classify the project as a use identified within
the adopted SMP (for example, as a “utility” use), and then proceed with project review to
ensure consistency with adopted policies and regulations.
10.2.3 Development and Zoning Framework
The comprehensive plans adopted by study area communities are implemented through each
City’s zoning map and local land use code, which set the stage for land development
intensities and patterns. Based on the comprehensive plan land use designations that define a
broad range of allowed land uses, local communities establish zoning districts, and develop
detailed maps, specific land use type classifications, and development criteria for each of the
identified zones.
Examples of land use designations are: the City of Bellevue’s Single-Family Comprehensive
Plan land use designation, implemented through the ‘R-1’ zone (Single Family – Residential
Estate, one dwelling unit per acre), or Kirkland’s Commercial Comprehensive Plan land use
designation implemented through the BN zone (Neighborhood Business). A development
review process is implemented by each study area community to assess a project’s
compliance with zoning and code requirements.
Shoreline environment designations, determined under the SMPs described above, also
establish land use type classifications and development criteria over and above what zoning
allows. The SMP includes shoreline regulations that help to implement the shoreline goals
and policies. Some communities include shoreline environment designations as a type of
overlay on their zoning maps. Review of SMP compliance and potential impacts to shorelines
are assessed as part of development review.
CHAPTER 10 January 2016 10-10 LAND USE AND HOUSING
PHASE 1 DRAFT EIS
Development of any of the project alternatives would ultimately be subject to the zoning and
other development regulations of each community, including shoreline management.
Development permits would be required for land disturbing activities and to install most of
the components of the project alternatives (concrete pads for transformers and other
equipment, security fencing, power poles, transmission and distribution lines, battery storage
facilities, etc.). When a project location is determined, PSE would submit permit applications
to the applicable study area communities.
In addition to the overall zoning and other code compliance for each City, Bellevue and
Kirkland have community municipal corporations enacted by statute in certain areas as a
result of past annexations. These corporations have statutory authority to approve or
disapprove ordinances of the city council with respect to certain actions, including
conditional use permits, special exceptions, or variances. Disapproval cannot affect the
application of any ordinance affecting areas outside the community municipal corporation.
In addition to the powers and duties related to the approval of zoning regulations, the
community municipal corporation, acting through its community council, may make
recommendations and provide a forum for proposals that affect property or land within the
service area (of the corporation) and may advise, consult and cooperate with the city council
on local matters that may directly or indirectly affect the service area (RCW 35.14.050). The
East Bellevue Community Council (EBCC) was established in 1969 and has jurisdiction
within a designated planning boundary in East Bellevue (City of Bellevue, 2015b). The
Houghton Community Council was established in 1968 and has jurisdiction within the area
formerly designated as the Town of Houghton (City of Kirkland, 2015a).
10.3 WHAT ARE THE EXISTING LAND USES,
POPULATION, AND HOUSING IN THE COMBINED
STUDY AREA?
10.3.1 Existing Land Uses
The combined study area comprises approximately 90,000 acres of land area. According to
the King County Assessor’s 2015 geographic information systems (GIS) data, the most
prevalent land use in this combined area is single-family residential properties (40 percent),
followed by vacant land (17 percent), transportation and parking (13 percent), and parks and
open space combined with other recreational uses (10 percent).
Existing land uses are shown in Figures 10-4 and 10-5 4. Single-family residential properties
are located throughout all of the study area communities, while multifamily properties (4
percent of the project area) are congregated around larger urban areas. Although vacant and
recreational land is present throughout the combined study areas, the greatest concentration
4 Differences may exist between the land uses shown in figures and actual current land uses due to
anomalies between Assessor’s and Planning Departments’ land use categorization, changes in actual land
use from the time Assessor’s information was obtained, and broad categorization of multiple jurisdictions’
discrete land use designations. Because of the large study area coupled with the programmatic nature of
this analysis, these discrepancies are relatively minor and therefore not anticipated to have an influence on
overall analysis or conclusions; therefore, parcel-by-parcel data reconciliation was not conducted.
January 2016 CHAPTER 10 LAND USE AND HOUSING 10-11
PHASE 1 DRAFT EIS
of these land uses is in the southeastern portion of the
study area surrounding the southern and eastern
boundaries of Newcastle, Bellevue, and Issaquah. This
includes the large forested areas comprising the Issaquah
Alps and undeveloped portions of unincorporated King
County. Institutional land uses such as schools, churches,
hospitals, and libraries are scattered throughout the
combined study area. Commercial land uses are primarily
clustered around the city centers and major highways,
with the highest concentrations in Bellevue, Redmond,
and Issaquah. Industrial uses are relatively scarce in the combined study area, clustered in
Bellevue, Redmond, Renton, and Newcastle with small areas in Kirkland, King County, and
Sammamish as well.
Figure 10-4. Existing Land Use by Type
Source: King County, 2015
0
The Issaquah Alps is the
unofficial name for the
highlands near the city of
Issaquah, and includes Cougar
Mountain, Squak Mountain,
Tiger Mountain, Taylor
Mountain, Rattlesnake Ridge,
Rattlesnake Mountain, and
Grand Ridge.
CHAPTER 10 January 2016 10-12 LAND USE AND HOUSING
PHASE 1 DRAFT EIS
Energize Eastside EIS 140548
Figure 10-5
Existing Land Uses
SOURCE: King County 2015; ESA 2015; WA Ecology 2014.
For more info visit www.energizeeastsideeis.org/map-existinglanduse
Lake
Washington
Lake
Sammamish
Bellevue Sammamish
Issaquah
Renton
Newcastle
RedmondKirkland
Beaux Arts
Medina
Clyde
Hill
Hunts
Point
Yarrow
Point
Mercer
Island
Text
Lakeside
Sammamish
Talbot Hill
Novelty Hill
Lake Tradition
Existing Land Use
Single-family
Residential
Multi-family
Residential
Commercial (retail
and office)
Industrial
Institutional
Parks/Open Space
Recreation
Resource Lands
Transportation and
Parking
Utility
Vacant
Other
Existing Substations
Roadway
Combined Study Area
Boundary
Water bodies
City Limits
U:\GIS\GIS\Projects\14xxxx\D140548_EastsidePSETransmisisonCoor\MXD\ExistingLandUse.mxd
0 2
Miles
Note: This map is for reference only. It is not guaranteed that the information is accurate or complete.
10.3.2 Population
The total population in the study area communities was 477,875 as of April 2015 (Figure
10-6). However, the population of the combined study area is smaller because the study area
boundaries do not align with city boundaries (or census tract boundaries, which were the
basis of the population information for the cities) and portions of some cities are outside of
the combined study area. City population data is presented in Figure 10-6.
Figure 10-6. Local Area Population (2015)
Source: Municipal Research and Services Center (MRSC), 2015
The population of the unincorporated King County portion of the combined study area (in
2014) is estimated at 54,800 based on interpolation of Census Block Group data (2010)
obtained from the Municipal Research and Services Center (MRSC, 2015). Although these
city and county numbers are not exact, they provide a general sense of the population in the
combined study area.
10.3.3 Housing Characteristics
The majority of the housing stock in the combined study area is single-family, detached
housing (Figure 10-7). Communities such as Hunts Point (with no employment centers and
developed primarily as a residential community) are composed almost entirely of single-
family homes, while approximately half of the housing stock in more urbanized areas like
Redmond is multifamily. The larger cities in the project area (Kirkland, Renton, Bellevue,
Issaquah, Redmond, and Newcastle) typically have apartment complexes with over 10 units
per building, composing approximately a quarter of their housing stock (U.S. Census, 2013).
CHAPTER 10 January 2016 10-14 LAND USE AND HOUSING
PHASE 1 DRAFT EIS
This is indicative of the land use planning strategy seen throughout the Eastside communities,
which is to preserve existing single-family residential neighborhoods while fostering
population growth in high-density housing in the urban areas.
The communities with the oldest housing stock in the combined study area are Beaux Arts
Village, Clyde Hill, and Yarrow Point, where approximately 70 percent of the housing was
constructed prior to 1980. The rest of the combined study area communities (Bellevue,
Renton, Kirkland, Redmond, Sammamish, Issaquah, Newcastle, Medina, and Hunts Point)
experienced residential property development between 1960 and 2010, but generally have a
greater proportion of newer housing than the communities previously described. The newest
housing is likely to be found in Issaquah or Newcastle where 2.9 percent and 2.2 percent of
the housing was constructed after 2009, respectively (U.S. Census, 2013).
January 2016 CHAPTER 10 LAND USE AND HOUSING 10-15
PHASE 1 DRAFT EIS
Figure 10-7. Housing Types In the Study Area Communities
CHAPTER 10 January 2016 10-16 LAND USE AND HOUSING
PHASE 1 DRAFT EIS
10.4 HOW WILL LAND USE, POPULATION, AND HOUSING
CHANGE IN THE FUTURE?
Population in most of the study area communities is
projected to increase through 2040. The PSRC expects
population in the Puget Sound region to grow by about 24
percent to approximately 4.9 million by 2040. Along with
that increase in population, the number of households in
the region is expected to increase by about 37 percent to
approximately 2.1 million (PSRC, 2015a). Consistent with
that trend, from 2010 to 2014 the population of King
County grew at an average annual rate of 1.1 percent,
slightly above the regional average. Between 2013 and
2014, the King County population grew by 35,350 (1.8
percent) and King County is expected to continue to lead
the region in growth.
The Regional Growth Strategy established by VISION
2040 (described in Section 10.2.1) calls for broad shifts in
locations where growth should be located within the
region. The Strategy establishes six clusters of
jurisdictions called “regional geographies” including four
types of cities (by size ) and two unincorporated types
(urban and rural). The study area communities within each
cluster are in bold font as follows:
1. Metropolitan Cities: Seattle, Bellevue
2. Core Suburban Cities: Auburn, Bothell, Burien,
Federal Way, Kent, Kirkland, Redmond,
Renton, SeaTac, Tukwila
3. Larger Suburban Cities: Des Moines, Issaquah, Kenmore, Maple Valley, Mercer
Island, Sammamish, Shoreline, Woodinville
4. Small Cities: Algona, Beaux Arts, Black Diamond, Carnation, Clyde Hill,
Covington, Duvall, Enumclaw, Hunts Point, Lake Forest Park, Medina, Milton,
Newcastle, Normandy Park, North Bend, Pacific, Skykomish, Snoqualmie, Yarrow
Point
5. Urban Unincorporated King County: all unincorporated areas within urban growth
areas
6. Rural Unincorporated King County: rural- and resource-designated areas outside
urban growth areas
The Strategy calls for: (1) increasing the amount of growth targeted to metropolitan cities and
core suburban cities; (2) increasing the amount of growth targeted to larger suburban cities;
(3) decreasing the amount of growth targeted to urban unincorporated areas, rural designated
PSRC Growth Centers
Centers are locations
characterized by compact,
pedestrian-oriented
development, with a mix of
different office, commercial,
civic, entertainment, and
residential uses. While relatively
small geographically, centers are
strategic places identified to
receive a significant proportion
of future population and
employment growth when
compared to the rest of the
urban area. Centers of different
sizes and scales - from the
largest centers to the smallest -
are envisioned for all of the
region’s cities.
Concentrating growth in centers
allows cities and other urban
service providers to maximize
the use of existing infrastructure,
make more efficient and less
costly investments in new
infrastructure, and minimize the
environmental impact of urban
growth.
January 2016 CHAPTER 10 LAND USE AND HOUSING 10-17
PHASE 1 DRAFT EIS
unincorporated areas, and small cities; and (4) achieving a greater jobs-housing balance
within the region.
As land redevelopment continues within the comprehensive planning framework, land use
patterns will change. Figure 10-2 in Section 10.2 shows what land uses are planned to look
like in the future. The majority of the combined study area (76 percent) is anticipated to
remain suburban in character, with single-family housing, while the current trend of focusing
new development within the established city limits and urban growth areas is expected to
continue. The majority of new residential and commercial growth is expected to occur as
mixed-use and multifamily developments within designated downtown and neighborhood
commercial centers. Multifamily residential uses are anticipated to be 5 percent of the total
land acreage, commercial uses 3 percent, and mixed-use areas 7 percent. Single-family
development will also continue, but likely on smaller lots, resulting in higher densities in
some single-family areas.
10.5 HOW WERE POTENTIAL IMPACTS TO LAND USE
AND HOUSING ASSESSED?
This chapter evaluates the alternatives’ consistency within the general regulatory framework,
including applicable land use and shoreline goals and policies. Zoning and shoreline
designations in the combined study area were reviewed to confirm whether the alternatives
would be allowed in all types of zones and shoreline environments.
Because study area communities would determine whether to designate the project as an EPF
as part of the project-specific permit application process, this programmatic evaluation does
not include a complete analysis for consistency with EPF policies and regulations. This
chapter generally discusses the EPF designation and what it would mean for location and
development of the project.
The EIS Consultant Team conducted research to identify potential changes in land use related
to transmission lines and other utility components. Information was obtained from land use
studies and an interview with a local Assessor’s Office (FCS, 2016).
The potential for the project to convert existing non-utility land uses to a utility use was also
considered. The evaluation includes the potential for the project to physically separate
existing neighborhoods.
10.6 WHAT ARE THE LIKELY CONSTRUCTION IMPACTS
TO LAND USE AND HOUSING?
10.6.1 Construction Impacts Considered
The project could be considered to have an adverse land use impact if construction would
cause a substantial disruption of normal access, services, or activities.
CHAPTER 10 January 2016 10-18 LAND USE AND HOUSING
PHASE 1 DRAFT EIS
The magnitude of potential land use impacts during construction is classified as minor,
moderate, or significant, which have been defined for this analysis as follows:
Minor - Construction could temporarily disrupt normal access at any one location, but
adequate alternate access could be provided to approximate or maintain existing uses.
Moderate – Construction continues for a substantial amount of time at any one location or at
numerous locations in close proximity, compromising access sufficiently to adversely affect
service provision and site uses for brief periods.
Significant – Long-term construction at any one location or numerous locations in close
proximity disrupts normal access to area homes, services, or businesses, where alternate
access cannot be provided and uses/services are disrupted.
10.6.2 No Action Alternative
Under the No Action Alternative, the project would not be constructed and no impacts would
occur. While some existing equipment could be replaced, no major construction would occur.
10.6.3 Action Alternatives
The study area communities would ensure that appropriate access to properties (homes,
businesses, or services) from public rights-of-way would be maintained for all alternatives,
options, or components considered.
All alternatives involving construction of new infrastructure (except the Energy Efficiency
and Demand Response Components of Alternative 2) would need permits prior to
construction. During the permit process, development review would determine how access
would be maintained. Negligible land use and housing impacts would be expected from
project construction under any of the action alternatives.
10.7 HOW COULD OPERATION OF THE PROJECT
AFFECT LAND USES AND HOUSING?
10.7.1 Operation Impacts Considered
10.7.1.1 Consistency with Goals, Policies, and Regulations
The project could have an adverse land use impact if it were inconsistent with planning goals
and policies, or if the zoning and shoreline environment designation restrictions of any study
area community would prohibit any aspect of the project.
Land use goals and policies of the study area communities (Appendix F) provide some
guidance as to where new transmission lines, transformers, or the features of Alternative 2
should be located, and some have goals or policies supporting undergrounding of electrical
lines. All of the area comprehensive plans acknowledge a need for adequate infrastructure to
support development.
January 2016 CHAPTER 10 LAND USE AND HOUSING 10-19
PHASE 1 DRAFT EIS
The infrastructure components of all of the alternatives would likely be allowed by most
zoning designations of the study area communities. The exceptions are described in the
sections below for each alternative. Development regulations related to height/scale and
setbacks would be applied depending on specific location and the project component.
Specific designs for the project would need to be reviewed by each community to determine
compliance with applicable zoning codes and regulations. Most local area SMPs would
require new utilities that are not dependent on a shoreline location to be built outside of the
shoreline jurisdiction unless there were no feasible alternative. Some study area communities
specifically prohibit particular types of utility activities in some shoreline areas, as described
for the alternatives below.
Most local area comprehensive plans establish policies for developing EPFs. These generally
relate to coordination, applying sustainability principles in siting decisions and intent to
ensure impacts are adequately mitigated (see applicable policies in Appendix F). For the
project or any component of the project to be considered as an EPF by one or more of the
study area communities, the jurisdiction would need to determine that the project is critical
infrastructure, important regionally as well as locally and difficult to site. This determination
would be made based on a specific project proposal.
10.7.1.2 Conversion of Land or Housing to Utility Use
Properties could be converted to utility uses. If land were converted to utilities it could take
away land otherwise available to cities to accommodate the required King County Growth
Targets for housing and jobs, including land already developed with housing or commercial
uses. Although the planning process that established those targets also identified the need for
utilities, none of the study area communities specifically identify how much land is expected
to be needed for utility use. Use of land for utilities that would have been used to meet
mandated growth targets would not necessarily create an adverse impact. The amount of land
converted to utilities would need to be considered in the context of remaining available land
to confirm whether an impact would likely occur and whether it would be significant.
Housing impacts would occur in the event that residences needed to be purchased and
removed in order to build the project. PSE confirms that due to safety regulations,
transmission lines would never be placed directly over homes (Strauch, personal
communication, 2015).
10.7.1.3 Classifying Impacts
The magnitude of potential land use impacts from operation of the project is classified as
minor, moderate, or significant, which have been defined for this analysis as follows:
Minor – Project could be developed consistent with policies and regulations, and would
convert some land to utility uses, but not require the removal of existing homes or businesses.
Moderate – Project could be developed consistent with policies and regulations and would
convert a relatively small percentage of land targeted to meet housing or employment goals
to utility use.
CHAPTER 10 January 2016 10-20 LAND USE AND HOUSING
PHASE 1 DRAFT EIS
Significant – Project could not be developed consistent with policies or regulations, and
would convert substantial numbers of homes or businesses to utility uses, or otherwise
substantially affect the ability of study area communities to meet their housing or
employment targets, or other adopted development goals.
10.7.1.4 Property Values
During EIS scoping, a number of public comments were received on the topic of whether the
proposed new transmission line would affect property values. Although the effect of
transmission lines on property values is an economic rather than an environmental issue as
defined by SEPA, the issue is discussed in this land use analysis to the extent that a change in
property values could result in a change in land use (for example, a single-family residential
use becoming vacant or substantially changed resulting
from loss in property value).
To respond to these comments, the EIS Consultant Team
reviewed existing studies addressing whether location of
transmission lines could affect property values to the
extent that devaluation would result in a change of use. A
search of online literature databases found over 25 articles
and reports related to power line effects on property
values. Of that number, one study prepared for The
Electric Power research Institute (EPRI) titled
Transmission Lines and Property Values: State of Science
(Mullins et al., 2003) was chosen for use as the source of information for this EIS because it
synthesizes and summarizes the findings of over 50 surveys and studies.
The EPRI report finds that the results of previous studies are mixed. In some cases the report
found that small decreases in property values had been associated with proximity to a
transmission line. In other cases no changes in property values were found. In some cases
there were increases in property values. The specific conclusions of the report are provided
verbatim below, starting with the statement that findings are not conclusive (Mullins et al.,
2003):
“Quoting from William N. Kinnard Jr. (1990), no quantitative generalizations about
findings from the studies can be made with any degree of reliability. Still today,
differences in location and time of data collection, as well as research design, make
direct comparisons of results from all of the studies reviewed very difficult. That said, the
research projects covered in this report do suggest a number of conclusions that are not
substantially different from what we already knew, as listed below.
• There is evidence that transmission lines have the potential to decrease nearby
property values, but this decrease is usually small (6.3% or lower);
• Lots adjacent to the ROW [right-of-way] often benefit; lots next to adjacent lots
often have value reduction;
• Higher-end properties are more likely to experience a reduction in selling price
than lower end properties;
EPRI is a nonprofit
organization that conducts
“research, development and
demonstration relating to the
generation, delivery and use of
electricity for the benefit of the
public.” See:
http://www.epri.com/About-
Us/Pages/Our-Business.aspx
January 2016 CHAPTER 10 LAND USE AND HOUSING 10-21
PHASE 1 DRAFT EIS
• The degree of opposition to an upgrade project may affect the size and duration
of the sales price effects;
• Setback distance, ROW landscaping, shielding of visual and aural effects, and
integration of the ROW into the neighborhood can significantly reduce or
eliminate the impact of transmission structures on sales prices;
• Although appreciation of property does not appear to be affected, proximity to a
transmission line can sometimes result in increased selling times for adjacent
properties;
• Sales-price effects are more complex than they have been portrayed in many
studies. Even grouping adjacent properties may obscure results;
• Effects of a transmission line on sales prices of properties diminish over time and
all but disappear in five years;
• Opinion surveys of property values and transmission lines may not necessarily
overstate negative attitudes but they certainly understate (or ignore) positive
attitudes; and
• The release of findings from the Swedish study on EMF 5 and health effects had no
measurable influence on sales prices.”
Overall, the EPRI study does not support a conclusion that
property value shifts would occur that would lead to
negative impacts on land uses. The King County Assessor
does consider views of powerlines in assessing property
values, as discussed in Chapter 11 Views and Visual
Resources. Therefore, the land use analysis in this Phase 1
Draft EIS considered effects on property values but found
them to be inconclusive with regard to causing changes in
land use.
More recent studies have confirmed the results of the 2003
EPRI report. A 2012 study concluded that effects, if they
occurred, ranged from 3 to 6% of value, and other factors
such as property use, size, and uniqueness affected
property values more significantly (Chalmers, 2012). A
2014 literature review found that the presence of
transmission lines does not automatically adversely impact
property values of adjacent properties, and what effects are
seen dissipate with distance, usually disappearing at 200 –
300 feet (Roddewig and Brigden, 2014). No studies were
found indicating a different conclusion than those
summarized in the EPRI study.
5 The EPRI document cited includes reference to the following study: Des F. Rosiers. 2002. Power lines,
visual encumbrance and house values: a microspatial approach to impact measurement. Journal of Real
Estate Research 23(3):275–301.
Examples of Goals and
Policies for Reliable Energy
Provision
Redmond Policy UT-59: Work
with energy service providers
to promote an affordable,
reliable, and secure energy
supply that increases
development and use of
renewable and less carbon-
intensive sources, and that
minimizes demand and
consumption.
Kirkland Policy U-7.3: Work
with and encourage PSE to
provide clean and renewable
energy that meets the needs of
existing and future
development, and provides
sustainable, highly reliable, and
energy-efficient service for
Kirkland customers.
CHAPTER 10 January 2016 10-22 LAND USE AND HOUSING
PHASE 1 DRAFT EIS
10.7.2 No Action Alternative
Under this alternative, no properties would be purchased, no neighborhoods would be
traversed by a new transmission line, and no new transformers would be installed, with no
expansions of existing substations. There would be no conversions of other land uses to
utility uses and no resulting land use impacts.
However, the No Action Alternative would likely lead to declining reliability of the electrical
power supply on the Eastside, which could be inconsistent with Growth Management Act
Goal 12, described in Section 10.2.1. It would also be inconsistent with local planning
policies for Redmond, Kirkland, Renton, Bellevue, and others regarding provision of reliable
energy.
Planning goals in the region recognize the importance of
economic development for community stability, creation
and retention of jobs, adequate housing, and efficiencies
in service provision such as transportation (sometimes
referred to collectively as smart growth). Without a
confident forecast of reliable power by PSE, developers
and businesses may choose not to invest in the Eastside
area, which could delay growth or shift growth (including
housing) to other areas of the region. Since electrical
reliability is only one of many factors that developers and
businesses consider, in the short term some businesses
could ensure against power outages with their own
backup generators. In the long term; however, if a trend
of unreliable power supply were to continue, it could have a negative impact on the role the
Eastside is expected to play in accommodating growth in the region.
Therefore, due to policy inconsistencies and potential changes to land use patterns from those
planned under the GMA, the No Action Alternative would likely have a moderate to
significant land use and housing impact, depending upon the degree to which uncertain
power availability affects land development.
10.7.3 Alternative 1: New Substation and 230 kV Transmission Lines
Impacts are described according to the major components associated with Alternative 1. The
substation impacts are described first, followed by transmission line options.
This alternative includes placing a new 230 kV to 115 kV transformer near the center of the
Eastside at one of three locations described in Chapter 2 (Vernell, Westminster, or Lakeside).
PSE has proposed this alternative as their solution to best ensure reliability of the electrical
supply system, consistent with local and regional planning goals. In addition, new
transmission lines would be constructed connecting the new transformer to the Sammamish
and Talbot Hill substations.
The Vernell and Westminster sites shown in Table 10-1 below (owned by PSE) would likely
be adequate to accommodate the proposed new substation and impacts to land use and
Smart growth is an urban
planning and transportation
concept that concentrates
growth in compact walkable
urban centers to avoid sprawl.
It also advocates compact,
transit-oriented, walkable,
bicycle-friendly land use,
including neighborhood
schools, complete streets, and
mixed-use development with a
range of housing choices.
January 2016 CHAPTER 10 LAND USE AND HOUSING 10-23
PHASE 1 DRAFT EIS
housing would be negligible. If the Lakeside site were chosen, PSE would need to purchase
and develop land adjacent to the existing substation. Table 10-1 summarizes the existing land
uses around the three potential substation sites for the new transformer, in order of their
prevalence.
Table 10-1. Alternative 1 - Existing Land Uses around Substations Needing
Expansion
Substation Land Use
Lakeside Industrial, institutional, vacant land (and single-family residential across the
street).
Westminster Parks/open space, recreation, commercial, and single-family residential
(across the street).
Vernell Industrial, transportation, and commercial.
Source: King County Assessor
The conversion of land to utility use at the Lakeside site is considered a minor impact on land
use, considering the small amount of land that would be needed along with other appropriate
measures that would be employed to address compatibility with adjacent uses, such as
screening for visual impacts and addressing potential noise. Impacts from the substation
should be considered together with the transmission line impacts of each option, which are
described in Sections 10.7.3.1 through 10.7.3.4.
10.7.3.1 Option A: New Overhead Transmission Lines
Overall, the potential impacts to land use and housing with the transmission lines of
Alternative 1, Option A could range from minor to significant depending on specific location
and whether a new or existing corridor were used for the facility.
10.7.3.1.1. New Corridor
Impacts to specific properties would occur if land were purchased and used for the project.
With this option, overhead transmission lines could be placed in entirely new corridors, with
conversion of existing uses to utility uses. Conversion could occur with purchase of complete
parcels (including homes or businesses), portions of parcels, or easements across land. If the
overhead line were placed in a new corridor, it is assumed the corridor would be
approximately 150 feet wide under the worst-case scenario described in Chapter 2. Given that
a new corridor would need to be at least 18 miles long, this width would mean a change to
utility land use for approximately 327 acres out of the approximately 90,000 acres in the
combined study area.
PSE would attempt to avoid placing a new transmission corridor directly where single-family
or multifamily housing structures now exist and lines would not be allowed directly over
residential structures (Strauch, personal communication, 2015). However, a new transmission
corridor would likely not be able to completely avoid housing impacts due to the
predominance of residential uses in the combined study area. If a route crossing existing
CHAPTER 10 January 2016 10-24 LAND USE AND HOUSING
PHASE 1 DRAFT EIS
housing were needed, those homes would need to be purchased and removed. In this
scenario, direct land use and housing impacts would range from moderate to significant,
depending on the specific corridor location and proximity of housing to the corridor.
10.7.3.1.2. Existing Corridor
Placing the line through existing PSE corridors or other dedicated utility easements, or along
roadways, would be more consistent with land use and utility policies supporting utility co-
location, although it could still result in some conversions of adjacent properties or purchases
of housing. These conversions could occur in the event that the corridors needed to be
widened to accommodate the new utility and allow an adequate clear zone between the lines
themselves and between lines and other structures. Up to 50 feet of additional clear zone
could be needed throughout the corridor. This could require removal of some structures,
including housing, and would reduce the availability of vacant land for additional housing or
other development. The use of an existing shared corridor would have a lower potential for
impacts from property conversion than a new corridor. Impacts would range from minor to
moderate, depending on location and actual design.
Alternative 1, Option A would be generally consistent with
local planning policies listed in Appendix F except in the
event that PSE intended to co-locate the transmission line
with the Olympic Pipeline Company (OPLC) high pressure
pipeline described in further detail in Chapter 16. While
some local planning policies encourage co-location with
utilities where safe (see Chapter 8), three study area
communities (King County, Redmond, and Kirkland) have
policies or regulations that could specifically prohibit
combining new or expanded transmission lines (which are
considered high consequence land uses) with hazardous material pipelines. Development
regulations would need to be consulted for all study area communities. The City of Bellevue,
for instance, has one code section (LU 20.20.255) which would disfavor site selection in
residential areas.
Some of the study area communities have zoning requirements (including shoreline overlay
requirements) that would specifically prohibit placement of this alternative in certain
locations. Table 10-2 shows the zoning districts and shoreline environment designations in
which Beaux Arts Village, Hunts Point, Issaquah, Newcastle, Redmond, Renton, and Yarrow
Point appear to prohibit all or portions of Alternative 1 6. This table will also apply to the
other options of Alternative 1.
6 The City of Bellevue is updating its SMP. The existing, adopted SMP was used for this analysis.
High Consequence Land Use
is a use which, if located in the
vicinity of a hazardous liquid
pipeline, would present an
unusually high risk in the event
of pipeline failure due to its
function, including utilities
providing regional service.
January 2016 CHAPTER 10 LAND USE AND HOUSING 10-25
PHASE 1 DRAFT EIS
Table 10-2. Potential Land Use Restrictions for Alternative 1
Study Area
Community Use Restriction
Beaux Arts
Village
New utilities prohibited in following shoreline environment designations:
Urban Conservancy, Residential, and Aquatic
Hunts Point • Primary electrical utilities prohibited in: Stormwater Utility
• Primary electrical utilities prohibited in these shoreline environment
designations: Natural, Residential, and Aquatic
Issaquah Utilities not allowed in: Mineral zoning district
Newcastle Utility yards not allowed in: Mixed Use, Urban Residential, Neighborhood
Business zoning districts
Redmond • Regional utilities not allowed in these neighborhoods: Anderson Park,
Carter, East Hill, Old Town, River Bend, River Trail, Sammamish Trail,
Trestle, Town Square, Town Center, or Valley View
• Substations (and utility storage) not allowed in these shoreline
environment designations: Aquatic, Natural, Urban Conservancy
• No additional utilities allowed in: utility corridor along the west side of the
edge of Lake Sammamish containing the City’s sewer line 7
Renton All utilities prohibited in: Shoreline Natural shoreline environment designation
Yarrow Point Primary utilities prohibited in the following shoreline environment
designations: Urban Conservancy, Residential, Natural, Aquatic
Note: This list of restrictions is not intended to be comprehensive. Study area communities may identify
other regulations not included here during review of a project level proposal in Phase 2 of this EIS.
Other study area communities not listed in the table would appear to either allow the
alternative outright or as a conditional use in all zones; some would prohibit the project in
some or all shoreline areas unless there was no other alternative. In some cases, the zoning
code does not specifically articulate whether the project would be allowed or prohibited. In
those circumstances, the local government would need to perform a code interpretation to
determine if the project were allowed, conditionally allowed, or prohibited. The same would
be true in the event that project development were proposed inconsistent with zoning and
shoreline regulations.
10.7.3.2 Option B: Existing Seattle City Light 230 kV Transmission
Corridor
The Seattle City Light (SCL) transmission line is an existing corridor with a 230 kV line.
Sharing the transmission line with SCL would likely require rebuilding the existing system of
transmission lines as described in Chapter 2. Because the other utility’s functioning lines
could not be taken out of service during construction, new lines would be built adjacent to the
existing lines. For this analysis, it was assumed that that width of the existing corridor would
7 Determination of whether additional/new components added to an existing utility would be considered a
new use or expansion of an existing use would be made by the jurisdiction(s) with approval authority at the
time of permit submittal.
CHAPTER 10 January 2016 10-26 LAND USE AND HOUSING
PHASE 1 DRAFT EIS
not need to be expanded. However, if it was expanded, additional adjacent property may need
to be purchased in order to maintain adequate, safe clearance between construction activities
and the operating line and thus similar conversions of properties or houses could occur as
with existing corridors under Alternative 1, Option A. This would likely be a minor impact,
because this likelihood is considered to be low.
In addition, some west-east transmission lines would be needed outside of the existing north-
south corridor to connect to the existing substations, leading to some land or easement
purchases and changes in land use. Additional land would also be needed for a new Lakeside
substation as described in Chapter 2.
This option would have some of the same zoning consistency issues as Option A (Table
10-2) including potential for co-location with a high consequence land use, since it also
crosses the OPLC pipeline in places and is parallel to it in other locations. Option B would
not affect Lake Washington shorelines to the extent that Option D would, but could intersect
shorelines associated with other waterbodies such as Kelsey Creek.
10.7.3.3 Option C: Underground Transmission Lines
An underground line placed within a new corridor would be narrower than Alternative 1,
Option A’s overhead line, because the underground facilities require a more narrow clear
zone. A new corridor for underground transmission might require less land, easement area, or
homes to be purchased than for Option A. As with Option A, PSE would attempt to avoid the
removal of residential structures in establishing a route for the line. Potential impacts for a
new corridor would likely be minor in nature due to the relatively narrow corridor and more
limited likelihood for land conversion to utility uses than with Option A.
With this option, the underground transmission line could be entirely or partially constructed
through existing PSE 115 kV overhead transmission line rights-of-way, other utility rights-
of-way (such as roadway or rail corridors), or new rights-of-way. As with Option A, new
property could be needed for new corridors or additional property could be needed to widen
existing corridors depending on space available. However, existing underground utilities
present constraints in siting new underground corridors in the highly developed study area.
This option has a lower potential for land use impacts than Option A, because of the reduced
corridor width. Overall, impacts would be expected to be minor.
Alternative 1, Option C would have the same general zoning and shoreline constraints as
Option A (Table 10-2). An underground transmission line would have the same potential
constraints as Option A’s overhead line regarding co-location with OPL’s pipeline. Co-
location may not be allowed if the uses are determined to be incompatible or unsafe. If co-
location were not permissible, either the pipeline would need to be relocated (likely given the
prior easement rights owned by PSE in the corridor as described in Chapter 16) or the
proposed transmission line would need to be sited elsewhere, with consideration given to
current easement holders of the utility corridor.
January 2016 CHAPTER 10 LAND USE AND HOUSING 10-27
PHASE 1 DRAFT EIS
10.7.3.4 Option D: Underwater Transmission Line
This option would be subject to the same types of zoning and shoreline restrictions as
Alternative 1, Option A (see Table 10-2). The in-water component would not generate
changes to land use; the potential for land use impacts would begin at the shoreline where the
line would transition from in-water to on-land and where vaults would be needed. PSE would
acquire land for vaults either outright purchase or through easements.
Once away from the shoreline area, the potential changes to land use from the transmission
line would be the same as for Option A (minor to significant), with two lines routed generally
west to east (either overhead or underground) to connection points, as described in Chapter 2.
There are some existing east west corridors that could be used, except in the Kirkland area. In
that location, a new corridor would be required to provide the connection to substations.
In Beaux Arts Village and Yarrow Point, a transmission line would be prohibited in the
Shoreline Aquatic environment, which includes Lake Washington. Therefore, if proposed in
those communities, the underwater component could have a significant impact due to
inconsistency with shoreline regulations.
10.7.4 Alternative 2: Integrated Resource Approach
A number of the communities in the Alternative 2 study area have energy policies that would
appear to specifically support some of the types of actions and features of this alternative.
There are no local planning policies that would oppose or discourage the components of
Alternative 2, although some development regulations would prohibit some components in
certain locations as described below.
10.7.4.1 Energy Efficiency and Demand Response Components
These components would have negligible land use impacts, with no new structures and no
purchases of land required. They would not likely lead to changes in use of properties or
housing impacts, and would therefore have negligible impacts to land use and housing. No
development regulations have been identified that would prohibit these components.
10.7.4.2 Distributed Generation Component
This component would likely have negligible land use impacts because it would involve
adding small-scale infrastructure (generation sources such as anaerobic digesters, gas
turbines, reciprocating engines, microturbines, or fuel cells). The component would not lead
to changes in existing land use or housing impacts. If these types of facilities were installed
in conformance with all applicable development regulations, consistency with adjacent land
uses would be ensured, and these types of facilities would not create trends for changes in
land use.
Local development regulations would address specific site compatibility issues for such
structures, ensuring proper setbacks from property lines, appropriate access, and site
landscaping; any specific height, bulk, and scale limitations established by local zoning codes
would be applied as the site was being designed. Generally, these facilities would not be
considered utility uses, but would be regulated along with the primary land use on the site.
CHAPTER 10 January 2016 10-28 LAND USE AND HOUSING
PHASE 1 DRAFT EIS
Table 10-3 shows four cities in the Alternative 2 study area that have zoning designations
(including shorelines) where these types of facilities may not be allowed or where they could
be restricted in size.
Table 10-3. Land Use Restrictions for Alternative 2
Study Area
Community Use Restriction
Beaux Arts Village New utilities prohibited in following shoreline environment designation:
Urban Conservancy, Residential, and Aquatic
Kirkland Utility production and processing facilities1 prohibited in these
shoreline environment designations: Natural and Aquatic
Redmond No additional utilities allowed in: the utility corridor along the west side
of the edge of Lake Sammamish containing the City’s sewer line
Renton • Electrical power generation and co-generation is permitted as an
accessory use when located more than 100 ft. from any property
zoned for residential use and production of less than 10 MW of
electricity. In the CO zone the use must be accessory to a medical
institution.
• All utilities prohibited in: Shoreline Natural shoreline environment
designation
1”Facilities for the making or treatment of a utility such as power plants and sewage treatment plants or
parts of those facilities” (Kirkland Municipal Code 83.80.130).
10.7.4.3 Energy Storage Component
This component would likely have minor to moderate land use impacts. PSE would locate the
site for this component near the load to be served. It would ideally be adjacent to one or more
existing substations, and would occupy approximately 6 acres, Similar to the substation
component of Alternative 1, Option A, an existing substation footprint could be expanded to
accommodate the site, or PSE could place the facility on land not adjacent to one of its
substations, which PSE may not currently own. Existing housing could be purchased and
converted to this new utility use. There would be a potentially negligible to minor land
use/housing impact considering that 6 acres is a relatively small land area compared to the
land area of the Eastside. A 6-acre site could require removal of more than one home or
business depending on location.
10.7.4.4 Peak Generation Plant Component
Three peak generation plants could be placed on sites of approximately 1 acre, and each
would be adjacent to or within existing PSE substations on the Eastside. Land use impacts
would be similar to but smaller than for the substation component of Alternative 1, Option A.
As with the energy storage component, peak generation plants would likely encompass entire
sites near the load to be served. These sites would need to be purchased and maintained by
PSE, converting some land uses, possibly including housing, to a utility land use (or the use
classification determined by the governing authority). Impacts would be minor to moderate
but similar to energy storage as there would be relatively compact, types of development
(compared to transmission corridors).
January 2016 CHAPTER 10 LAND USE AND HOUSING 10-29
PHASE 1 DRAFT EIS
The local code restrictions described above (see Table 10-3) would likely apply to peak
generation plants, and the same type of local site review (setbacks, height, and other
parameters) would occur.
10.7.5 Alternative 3: New 115 kV Lines and Transformers
10.7.5.1 Substations
As discussed in Chapter 2 and shown in Table 2-3, provision of the new 115 kV transmission
lines would necessitate expansion of five existing substations for this alternative, as opposed
to the one substation needing alteration with Alternative 1. Table 10-4 below describes the
existing land uses around the substation sites that would be expanded with Alternative 3. One
of the facilities, the Lakeside substation, would likely expand onto property already owned
by PSE. Work at the other substations listed would require purchase of property.
Table 10-4. Alternative 3 - Existing Land Uses around Substations Needing
Expansion
Substation Percent
Expansion Abutting Land Uses
Hazelwood
(Newcastle)
200% Single-family residential, vacant, and other uses, with
recreation (Hazelwood Park) and institutional
(Hazelwood Elementary) uses in the immediate vicinity
Clyde Hill
(Bellevue)
50-60% Single-family residential
Sammamish
(Redmond)
10-20% Utility, commercial, industrial, recreation, and vacant
uses
Lakeside
(Bellevue)
10-20% Industrial, institutional, vacant (and single-family
residential uses across the street)
Talbot Hill
(Renton)
5-10% Transportation, utility, parks and open space, multifamily
residential, vacant and recreation uses
10.7.5.2 Transmission Lines
The same types of property conversions expected for the transmission line of Alternative 1,
Option A, would also occur for Alternative 3, with potential purchase and demolition of
homes or other uses; however, Alternative 3 would only install the new lines overhead along
existing road or utility rights-of-way, and not in a new corridor. The utility easement for a
new 60-mile long, 40-foot wide corridor could involve a conversion of up to 291 acres from
other land uses to utilities. The potential impacts of this alternative could range from minor to
moderate, depending on location and specific adjacent uses. As with Alternative 1, this
alternative would likely be consistent with local planning policies stating a need to plan for
adequate power supply.
The same types of development regulations that would apply to Alternative 1would be
applied by study area communities to Alternative 3. This alternative would be subject to the
same zoning and shoreline restrictions as Alternative 1, Option A (see Table 10-1).
CHAPTER 10 January 2016 10-30 LAND USE AND HOUSING
PHASE 1 DRAFT EIS
10.8 WHAT MITIGATION MEASURES ARE AVAILABLE
FOR POTENTIAL IMPACTS TO LAND USE OR
HOUSING?
Planning, locating, and designing the project consistent with local policies and regulations
would generally ensure compatibility of land uses.
To limit impacts associated with conversion of properties to utility uses, PSE could apply the
following measures:
• Use existing utility corridors or properties already in PSE-ownership to the extent
feasible.
• Underground all or part of the line, or place the line through Lake Washington.
• Provide relocation assistance for any residents displaced or businesses purchased.
10.9 ARE THERE ANY CUMULATIVE IMPACTS TO LAND
AND SHORELINE USE OR HOUSING AND CAN THEY
BE MITIGATED?
The project would add utility infrastructure to a highly developed area where it is already
commonly found, expected to exist, and needed to support existing and future land uses. No
cumulative adverse impacts are expected.
10.10 ARE THERE ANY SIGNIFICANT UNAVOIDABLE
ADVERSE IMPACTS TO LAND AND SHORELINE USE
OR HOUSING?
No significant unavoidable adverse impacts to land use or housing are expected with any of
the action alternatives. Alternative 1, Option A, would likely have significant impacts if a
new transmission corridor was developed, but mitigation is available as discussed above.
The No Action Alternative could lead to unavoidable significant adverse impacts in the long
term if unreliable power supply were to outweigh the regional factors amenable to growth
and development, leading to development inconsistent with regional growth plans and
targets.
January 2016 CHAPTER 10 LAND USE AND HOUSING 10-31
PHASE 1 DRAFT EIS
CHAPTER 11. VIEWS AND VISUAL
RESOURCES
11.1 HOW WERE VIEWPOINTS AND
VISUAL RESOURCES IN THE
COMBINED STUDY AREA
EVALUATED?
This chapter describes the visual resources, views, and
viewpoints within the combined study area (Figure 1-4 in
Chapter 1).
The importance of visual resources is subjective, based on
the viewer’s perspective, but study area communities have
identified and characterized visual resources in their
planning documents and regulations. For this EIS,
viewpoints and visual resources were characterized by
reviewing comprehensive plans, shoreline master plans
(SMPs), and regulatory codes of study area communities
(see Appendix G). For this programmatic EIS, subarea
plans were not reviewed. A list of key viewpoints and
visual resources can be found in Section 11.3.
The EIS Consultant Team also considered comments
received during the scoping process for the EIS. Comments
received during scoping expressed concern that a 230 kV
transmission line would negatively impact views from
individual houses, including territorial and neighborhood
views. For this reason, in addition to public places with
views, the analysis focused on potential effects on views
from residential areas with single-family homes. Scoping
comments also noted that new transmission lines could
negatively affect the look of Eastside neighborhoods and
cities (City of Bellevue, 2015c). For this programmatic
EIS, regional-scale visual resources were evaluated;
individual or specific neighborhoods and backyards were
not evaluated due to their site-specific nature. Specific
potentially affected neighborhoods will be evaluated as part
of the Phase 2 EIS.
Views and Visual Resources
Key Findings
Alternatives 1 and 3 could
cause significant impacts to
views and visual resources due
to vegetation removal and
obstruction of scenic views.
Overhead transmission lines
have the greatest potential to
affect residential views. Of all
overhead options, 230 kV lines
in a new corridor would have
the greatest visual impact
(Alternative 1, Option A), while
using the existing Seattle City
Light 230 kV corridor would
have a lower impact
(Alternative 1, Option B).
Undergrounding the
transmission line or placing it
underwater (Alternative 1,
Options C and D) would
reduce impacts. If new
overland corridors are
required, significant impacts
may result due to loss of
vegetation.
Using existing corridors for the
230 kV lines (Alternative 1)
could affect fewer residential
properties than using 115 kV
lines (Alternative 3). However,
the taller poles used in
Alternative 1 would have a
greater contrast with the
existing visual setting.
Energy storage facilities
(Alternative 2) could result in
significant impacts. Other
components, such as peak
generation plants or distributed
generation facilities, could
have moderate impacts
depending on size and
location.
January 2016 CHAPTER 11 VIEWS AND VISUAL RESOURCES 11-1
PHASE 1 DRAFT EIS
11.1.1 Visual Resources, Views, and Viewpoints Defined
Visual resources are generally
defined as natural and
constructed features of a
landscape that are viewed by the
public and contribute to the
overall visual quality and
character of an area. Such
features often include distinctive
landforms, water bodies,
vegetation, or components of the
built environment that provide a
sense of place, such as city
skylines.
Views are defined as the observation of a visual resource from a particular location, such as a
private residence or a public park.
Viewpoints are places from which views can be seen. They are typically associated with
residential properties or publicly accessible recreation areas, such as parks, trails, and open
spaces or along scenic roadways or in civic centers (Figure 11-1).
11.1.2 Property Values, Views and Visual Resources
During the scoping process, commenters voiced concern over the potential for property
values to decrease due to visual impacts associated with the project. The EIS Consultant
Team mapped properties that the King County Assessor has identified as having a view that,
in the Assessor’s judgment, affects the value of those properties to varying degrees. While
this dataset does not provide an exhaustive assessment of properties with views, or a precise
method of scoring views, it is useful to describe general patterns of view properties in the
combined study area. Assessor’s information also identifies properties with a view of a power
line that, in the judgment of the Assessor, lowers the property valuations. These data were
also mapped and reviewed. Differences in actual assessed values were not useful for this
evaluation because the data were inconclusive as to whether the reason parcels were valued
differently was because of use restrictions within a power line easement, because of visual
impacts, or for some other reason.
11.2 WHAT ARE THE RELEVANT PLANS, POLICIES, AND
REGULATIONS?
Many of the study area communities highlight the importance of visual resources, and their
planning documents include policies that emphasize the benefits of visual resources. There is,
however, little specific guidance in adopted comprehensive plans regarding the placement of
new utilities and reduction of impacts to views and visual resources. Most of the plans
emphasize the visual benefits provided by large parks and natural areas, wooded
neighborhoods, water bodies, mountain views, and city skylines. In general, local plans
Figure 11-1. Views, Viewpoints, and Visual
Resources
CHAPTER 11 January 2016 11-2 VIEWS AND VISUAL RESOURCES
PHASE 1 DRAFT EIS
support the preservation of existing public viewpoints and views that are enjoyed by a
“significant number” of residential properties. In many of the smaller suburban communities
(such as Clyde Hill), diverse views are considered to provide a positive impact on property
values (City of Clyde Hill, 2015a).
Most of the study area communities have adopted plans that prioritize protection of views of
shorelines, as well as views from the shoreline, and consider the impact of utility location in
shoreline areas. These policies are outlined in adopted SMPs. In most of the applicable
SMPs, utility development on shoreline areas is discouraged but allowed if no other
alternative is available. In such instances, it is usually suggested that the utility lines should
be buried underground or placed within existing utility corridors to reduce visual impacts. A
detailed summary of the applicable plan goals and policies from study area communities is
provided in Appendix G.
The municipal codes of King County, the City of Newcastle, the City of Sammamish, and the
Town of Beaux Arts Village do not include regulations that specifically guide development
of new utilities in order to reduce impacts to views or visual resources. The Cities of
Issaquah, Redmond, and Renton have regulations that place a general emphasis on screening
utility infrastructure by using aesthetically pleasing fences, materials, or landscaping. The
City of Bellevue provides specific guidance on how new electrical infrastructure should be
screened. A more detailed summary of the applicable codes is provided in Appendix G.
A general overview of each community’s plans, policies, and regulations that are applicable
to the visual environment is provided below. All of the communities have recently updated or
are in the process of updating their comprehensive plans. The EIS Consultant Team reviewed
both draft comprehensive plan chapters and current, adopted versions for each community. A
summary of the primary visual resources and viewpoints identified through that review is
provided in Section 11.3.
11.2.1 King County
The 2013 King County Comprehensive Plan (King County, 2013), and the incorporated SMP
policies, emphasize the value of visual resources, particularly those related to shorelines,
open space, and rural areas. These plans do not include specific guidance regarding the
placement of new utilities and reduction of impacts to views and visual resources. The King
County Code (Title 21A, updated April 15, 2015) does not include regulations that guide
development of new utilities to reduce impacts to views or visual resources (King County,
2015c).
11.2.2 Beaux Arts Village
Neither the Beaux Arts Comprehensive Plan nor the Beaux Arts Village Municipal Code (last
updated April 9, 2013) explicitly discusses visual resources in regard to utility infrastructure
(Town of Beaux Arts Village, 2013, 2014a). The Beaux Arts Village SMP does prohibit new
utilities in the Urban Conservancy, Shoreline Residential, and Aquatic Shoreline areas. The
SMP states that all development on navigable water should consider impacts to public views
(Town of Beaux Arts Village, 2014b).
January 2016 CHAPTER 11 VIEWS AND VISUAL RESOURCES 11-3
PHASE 1 DRAFT EIS
11.2.3 Bellevue
In its comprehensive plan, Bellevue characterizes itself as being a “City in a Park” as a result
of its “breathtaking vistas, viewpoints, and recreation areas” (City of Bellevue, 2015a).
Inherent to its character are “tree-lined streets, public art, vast parks, natural areas, wooded
neighborhoods, two large lakes, and mountain views.” The Bellevue Comprehensive Plan
states that views from public places of water, mountains, skylines, or other unique landmarks
should be identified and preserved as valuable civic assets (City of Bellevue, 2015a).
The City of Bellevue seeks to provide utility service in a manner that balances adequate,
reliable utility service and the aesthetic impacts of the infrastructure associated with such
service (City of Bellevue, 2015a). The Bellevue Comprehensive Plan states that utilities
should be developed and maintained to the appropriate levels of service to accommodate
future growth. It also states that utility service should be provided in a way that considers the
aesthetic compatibility with surrounding uses (City of Bellevue, 2015a).
The Bellevue City Code (current through August 3, 2015)
regulates how electrical utility facilities are developed,
setting design standards to reduce visual impacts. It also
requires that visual and aesthetic impacts associated with an
essential public facility (EPF) are “mitigated to the greatest
extent technically feasible” (City of Bellevue, 2015b).
The City of Bellevue is updating its SMP; the draft SMP
under consideration was not reviewed for this Phase 1 Draft
EIS.
11.2.4 Clyde Hill
The comprehensive plan for Clyde Hill notes the City’s views of Lake Washington, the
Seattle skyline, Meydenbauer Bay, Kirkland, and downtown Bellevue (City of Clyde Hill,
2015a). The Clyde Hill Municipal Code (current through June 9, 2015) states that views
contribute to the economic vitality of the City, particularly because the community is mostly
residential and relies upon property taxes. The primary focus of the City’s regulations
regarding views is to resolve neighborhood disputes concerning landscaping (trees) and their
effects on surrounding properties’ exposure to views and sunlight (City of Clyde Hill,
2015b). Clyde Hill does not have an SMP.
11.2.5 Hunts Point
The 2014 Draft Comprehensive Plan Update for the Town of Hunts Point does not identify
specific views or visual resources of importance. However, it does state that its tree code
regulates the removal and replacement of significant trees to “soften the visual impacts of
development” and protect the town’s wooded character (Town of Hunts Point, 2014).
The Hunts Point Municipal Code (current through April 13, 2015) does not include any
policies or regulations that guide development of new electrical utilities to reduce impacts to
views or visual resources. However, development in general is restricted to avoid or
minimize impacts to view corridors of wetlands (Town of Hunts Point, 2015). The Hunts
An Essential Public Facility
(EPF) is a concept established
by state law (RCW 36.70A.200
and WAC 365-196-550),
intended to ensure that
necessary facilities that are
typically difficult to site can, in
fact, be placed appropriately.
CHAPTER 11 January 2016 11-4 VIEWS AND VISUAL RESOURCES
PHASE 1 DRAFT EIS
Point SMP does not provide explicit guidance with regard to transmission lines and their
impacts on views and visual resources (Town of Hunts Point, 2012).
11.2.6 Issaquah
The 2014 City of Issaquah Comprehensive Plan states that, as long as the safety of the
facility and emergency access are not compromised, utilities should be reasonably screened
or designed so that new aboveground facilities are architecturally compatible with the
surrounding area. In addition, the plan states that proposals for major utility installations,
such as transmission lines and substations, must be reviewed to ensure impacts to aesthetic
values and land use conflicts are minimized and mitigated (City of Issaquah, 2015a).
The Issaquah Municipal Code (current through April 20, 2015) guides how utility
infrastructure should be implemented, providing height requirements and material
suggestions for fences and walls depending on the location of the facility (City of Issaquah,
2015b).
The City’s SMP does not provide explicit guidance with regard to transmission lines and
their impacts on views and visual resources (City of Issaquah, 2013).
11.2.7 Kirkland
The City of Kirkland 2015 Comprehensive Plan Update (Kirkland 2035) includes design
principles and development regulations that are used, in part, to protect public views (City of
Kirkland, 2015a). The plan states that public views of the city, surrounding hillsides, Lake
Washington, Seattle, the Cascades, and the Olympics should be protected. Public streets and
spaces and view corridors along the Lake Washington shoreline are identified as viewpoints
that should be preserved as development occurs.
Under Kirkland 2035, private views are protected only where such views are specifically
mentioned in the neighborhood plan chapters of the comprehensive plan and in the City’s
development regulations. However, the plan establishes a policy that states the siting analysis
for new and expanded electrical transmission and substation facilities should address land use
and sensitive areas, as well as provide mitigation to minimize visual and environmental
impacts. It also states that new or expanded aerial transmission lines should be sited and
designed to minimize impacts to critical areas, preserve trees, and reduce visual impacts,
especially where views of Lake Washington, the Olympic Mountains, and view corridors are
affected (City of Kirkland, 2015a).
The City of Kirkland Municipal Code (updated June 16, 2015), which includes the City’s
SMP regulations, states that whenever feasible, utility facilities must be located outside the
shoreline jurisdiction. Should there be no alternative location; the code requires utilities to be
placed so that they do not obstruct scenic views (City of Kirkland, 2015b).
11.2.8 Medina
The Draft 2015 City of Medina Comprehensive Plan describes Medina as a community set in
a semi-wooded and heavily landscaped environment. Many residences are located in open
settings with territorial views and views of Lake Washington.
January 2016 CHAPTER 11 VIEWS AND VISUAL RESOURCES 11-5
PHASE 1 DRAFT EIS
The Medina Comprehensive Plan states that utilities should be placed outside of the
shoreline. If this is not possible, the plan includes policies supporting the location of utilities
in a manner that protects scenic views (City of Medina, 2015a).
According to the Medina Municipal Code (current through July 13, 2015), all electrical
utilities should be enclosed in buildings or structures (City of Medina, 2015b). Specifications
regarding the types of materials that can be used, heights of walls and fences, and setbacks
are discussed in further detail in Appendix G.
Medina Municipal Code states that regional utility facilities involved in production,
processing, and transmission must be located outside of the shoreline jurisdiction “unless no
other feasible option exists.” If no other reasonable location is found, utilities must be placed
so that they do not obstruct views of a “significant number” of nearby residential properties.
The code supports combining utility corridors and placing utility infrastructure underground
whenever feasible.
The City’s SMP states that substations, and similar primary utility facilities, are not permitted
within the shoreline environment (City of Medina, 2014).
11.2.9 Newcastle
The Draft 2015 City of Newcastle Comprehensive Plan states that the city is “a small town
situated in a lush green setting” (City of Newcastle, 2015a). The draft plan also states that
utilities, including electricity, should be provided to serve the projected population growth
within the planning area in a manner that is aesthetically acceptable to the community (City
of Newcastle, 2015a). Specifically, the plan states that utility lines should be placed in shared
utility corridors, and that utility providers should minimize visual impacts of overhead
transmission lines on adjacent land uses (City of Newcastle, 2015a). The City of Newcastle
Municipal Code (current through May 5, 2015) does not include any regulations that guide
development of new utilities to reduce impacts to views or visual resources (City of
Newcastle, 2015b). Newcastle does not have an SMP.
11.2.10 Redmond
The City of Redmond has views of Mount Rainier, Mount Baker, the Cascade Mountains,
Lake Sammamish, the Sammamish River, Bear and Evans Creeks, and the open and pastoral
vistas in the northern Sammamish River valley (City of Redmond, 2015a). City policies
recognize the aesthetic benefits derived from views of natural landscapes, wildlife, water
bodies, and shorelines, and also note that unique public views can set apart one community
from another and define the unique character of a place. As such, the Redmond
Comprehensive Plan identifies specific view corridors that should be preserved, some of
which are located in the combined study area (see Appendix G). In general, the plan
highlights ways to reduce visual impacts to shorelines, open space, and residential views.
The City’s SMP is embodied in the City’s comprehensive plan (City of Redmond, 2015a). It
states that transmission lines and cables should be placed underground in shoreline zones. If
private utility owners place utility corridors on public property within the shoreline, they
must integrate them with trails and other open space connections to the shoreline, whenever it
CHAPTER 11 January 2016 11-6 VIEWS AND VISUAL RESOURCES
PHASE 1 DRAFT EIS
is possible. However, utilities cannot encroach on shoreline views unless “no feasible
alternative exists.” The SMP requires utilities to incorporate screening and landscaping to
maintain the aesthetic quality of the shoreline (City of Redmond, 2015b).
The Redmond Zoning Code promotes placement of utilities underground to improve the
appearance and aesthetics of public ways, but this does not apply to electrical lines over 50
kV unless it is economically feasible (City of Redmond, 2015b).
11.2.11 Renton
The City of Renton’s 2015 Comprehensive Plan seeks to preserve the natural setting as an
important component of residents’ quality of life, including trees and clear mountain views
(City of Renton, 2015a). The comprehensive plan states that public scenic views and public
view corridors should be protected, including Renton’s “physical, visual, and perceptual
linkages to Lake Washington and Cedar River.” The plan also states that natural forms,
vegetation, distinctive stands of trees, natural slopes, and scenic areas that “contribute to the
City’s identity, preserve property values, and visually define the community neighborhoods”
should be preserved (City of Renton, 2015a).
The City of Renton’s SMP also promotes preservation of scenic and aesthetic qualities
derived from natural features of the shoreline, such as vegetative cover and shore forms. This
includes reducing the visual prominence of structures, including associated light and glare. In
addition to these requirements, the SMP also prohibits utilities in the Shoreline Natural
shoreline environment designation (City of Renton, 2011).
The Renton Municipal Code (current through May 18, 2015) states that local utility services
that are permitted within the shoreline are “subject to standards for ecological protection and
visual compatibility.” It also states that a structure or other facility enclosing an electrical
substation, or other aboveground public utility built in the shoreline, should be housed in a
building that conforms with the architecture of surrounding buildings (current or planned), as
well as the applicable design standards of the zoning district in which it is located (City of
Renton, 2015b). Details regarding the height and materials of the surrounding walls/fence
and screening methods are provided in Appendix G. The municipal code states that new
electrical distribution lines should be placed underground if they are located within the
shoreline. However, in the event underground placement is not feasible, visual impacts must
be “minimized to the extent feasible” (City of Renton, 2015b).
11.2.12 Sammamish
The City of Sammamish has adopted policies to protect views, particularly those of
shorelines and water bodies. The Draft 2015 City of Sammamish Comprehensive Plan states
that “residents identify streams, lakes, forested areas and other natural features as defining
features of the City, and they believe the preservation of these natural features should be an
important priority” (City of Sammamish, 2015a). City policies also recognize the positive
aesthetic benefits associated with Sammamish parks and recreation facilities, and suggest that
they should be maintained to “ensure the longevity of their benefits” (City of Sammamish,
2015a).
January 2016 CHAPTER 11 VIEWS AND VISUAL RESOURCES 11-7
PHASE 1 DRAFT EIS
The Draft Comprehensive Plan also supports identifying and protecting, where appropriate,
scenic areas such as designated view corridors, with an emphasis on providing visual public
access to public shorelines, such as Lake Sammamish, Pine Lake, Beaver Lake, and all
tributary waters and wetlands in the city. The plan includes policies that utilities should be
placed underground if it is “physically and financially feasible” (City of Sammamish, 2015a).
If undergrounding utilities is not possible, aboveground utility facilities should be
aesthetically compatible with the surrounding area. The plan includes policies that visual
impacts associated with towers should be minimized in the community.
The City of Sammamish Municipal Code (current through March 17, 2015) does not include
regulations that guide development of new utilities to reduce impacts to views or visual
resources. There are, as of yet, no designated view corridors in Sammamish (City of
Sammamish, 2015b). However, the Sammamish SMP protects visual access to the shorelines
(City of Sammamish, 2011).
11.2.13 Yarrow Point
The 2014 Town of Yarrow Point Comprehensive Plan states that the Town’s long-term
vision for electrical utility infrastructure is to have it placed underground (Town of Yarrow
Point, 2015). This is reflected in the Yarrow Point Municipal Code (current through June 10,
2014), which states that existing overhead electrical facilities should be converted to
underground facilities prior to any system modification, and any new electrical facilities
should be installed underground (Town of Yarrow Point, 2014). This preference for
undergrounding utilities is also discussed in the SMP, which states that new utilities should
be located outside of the shoreline jurisdiction whenever feasible. Utilities that must be
located in the shoreline must be placed in existing rights-of-way (Town of Yarrow Point,
2012).
11.3 WHAT ARE THE VISUAL RESOURCES, VIEWPOINTS,
AND VIEWS IN THE COMBINED STUDY AREA?
11.3.1 Visual Character on the Eastside
The Eastside is a landscape bounded on the east and west by large lakes, centered in the
Puget Sound region where the horizons are defined by the Cascade Mountains to the east and
Olympic Mountains to the west. Except for the southeast portion of the Eastside, the
topography consists of low, rolling hills rising from approximately 20 feet above sea level
near Lake Washington, to hilltops 400 to 500 feet above sea level. The highest points in the
Eastside are in the southeast portion, where topography rises to approximately 1,200 feet in
Newcastle and 1,400 feet in Bellevue. Cougar Mountain, a natural area in unincorporated
King County, rises to 1,614 feet.
The higher elevation areas and areas directly adjacent to the lake shorelines generally afford
the widest views. Oftentimes, the clearing associated with residential development can result
in the creation of new view corridors. However, due to the extensive tree cover and rolling
topography common throughout the Eastside, views are often limited despite the presence of
CHAPTER 11 January 2016 11-8 VIEWS AND VISUAL RESOURCES
PHASE 1 DRAFT EIS
residential development (Figure 11-2).
Developed shoreline and hilltop areas are the
exception; these areas tend to have less tree
cover and more extensive views.
From the more open shorelines and hilltops,
portions of Lake Washington, Lake
Sammamish, the Cascades, and the Olympics
are generally visible. The skylines of downtown
Seattle and downtown Bellevue are also visible
from many of these same areas. There are also
areas throughout the Eastside where closer
territorial views are available. Because of the
tree cover generally found throughout the
Eastside, these territorial views are often views
of wooded hillsides with a few houses or other
structures visible among the trees. A few areas
are dominated by more urban views, including freeways and commercial development.
Several existing overhead electrical transmission corridors cross the Eastside. These are
typically areas cleared of trees that abut single-family and multifamily residential
development over much of their length, but they also cross commercial and industrial areas.
While several neighborhoods on the Eastside have underground electrical distribution lines,
most neighborhoods have overhead distribution lines. Distribution lines are typically on
shorter poles than transmission lines, and they do not require as large a clear zone around the
lines as transmission lines. There are also numerous other structures that are tall enough to
protrude into views, including buildings and cell phone towers.
In residential areas, single-family homes and low-scale multifamily buildings mostly range
from 15 to 35 feet in height. In commercial areas, building heights are mostly less than 60
feet, but in some areas mid-rise and high-rise development extends much higher.
11.3.2 Visual Resources
Many visual resources are documented in local plans and regulations as being important to
Eastside communities (Appendix G). Comprehensive plans note the visual benefits provided
by natural features, such as parks and open spaces, as well as built features that provide
character and identity to the area, such as the Seattle skyline. For this programmatic EIS,
visual resources are defined as areas that are viewed from a particular location (a viewpoint).
Therefore, although plans and scoping comments discuss the visual benefits of parks (such as
Bridle Trails State Park), for this analysis these are listed as viewpoints rather than visual
resources because viewers generally would be located within the park to enjoy the views of
the park (see Section 11.3.3).
Figure 11-2. Wooded Neighborhood
in Bellevue
January 2016 CHAPTER 11 VIEWS AND VISUAL RESOURCES 11-9
PHASE 1 DRAFT EIS
The following features are considered to be major visual resources because they are regional
in nature, and they are identified as visual resources by the study area communities:
• Cascade Mountain Range;
• Mount Rainier;
• Olympic Mountain Range;
• Lake Washington;
• Seattle skyline;
• Issaquah Alps (Cougar Mountain, Tiger Mountain, and Squak Mountain);
• Lake Sammamish;
• Sammamish valley;
• Beaver Lake;
• Pine Lake; and
• Cedar River.
These visual resources are discussed below and mapped on Figure 11-3. Several of these are
also identified as important for property value assessment by the King County Assessor
(King County, 2012).
The Cascade Mountain Range extends from British Columbia to southern Oregon. Most of
the peaks are around 6,000 feet tall, although some such as Mount Rainier are much higher.
Because the mountains are located 8 to 10 miles east of the easternmost study area boundary,
they are visible from various private and public locations throughout the combined study
area.
Mount Rainier, the tallest peak in the Cascade Mountain Range, provides a visual landmark
for the greater Seattle area (Figures 11-4, 11-6). At 14,410 feet tall, Mount Rainier “visually
dominates the skyline” from numerous locations throughout the combined study area, and up
to 100 miles away (The National Geographic Society, 2015).
The Olympic Mountain Range is on the Olympic Peninsula, west of Puget Sound. The
highest peak, Mount Olympus, is 7,980 feet tall. The Olympic Mountain Range can generally
be seen in the background anywhere there are views of the Seattle skyline (Figure 11-7).
Lake Washington, at 34 square miles, is the largest lake in King County. It separates the city
of Seattle from the Eastside, with Kirkland, Bellevue, Beaux Arts, Hunts Point, Yarrow
Point, and Renton sharing its shoreline in the combined study area (WDFW, 2015). In
addition to views from residences abutting the lake shoreline, Lake Washington is visible
from many properties on the hillsides above the shoreline, from taller hills within the
combined study area, and from several public parks. Most views of Lake Washington from
the Eastside also include Seattle and the Olympic Mountain Range in the background
(Figure 11-7).
CHAPTER 11 January 2016 11-10 VIEWS AND VISUAL RESOURCES
PHASE 1 DRAFT EIS
The Seattle skyline includes Seattle’s tallest buildings, such as the Space Needle, the
Columbia Center, and Two Union Square. Located west of Lake Washington, the skyline is
visible from most locations in the combined study area that have views of the lake. Residents
on the highest hills on the Eastside, such as in Newcastle and on Cougar Mountain, also have
a view of the Seattle skyline (Figure 11-7).
Cougar, Tiger, and Squak Mountains are part of the Issaquah Alps and are prominent
features in the southern portion of the combined study area. These large natural areas include
King County’s Cougar Mountain Regional Wildland Park, Tiger Mountain State Forest, and
Squak Mountain State Park. Ranging from approximately 1,600 to 3,000 feet in elevation,
these peaks are visible from many residential locations in the southwest portion of the
combined study area.
Lake Sammamish is visible from shoreline residences, many other properties on the
hillsides above the shoreline, and from several public parks (Figures 11-8, 11-9).
The Sammamish valley is in Redmond, north of Lake Sammamish beginning at Marymoor
Park. The northern portion of the valley is composed of recreational and agricultural lands.
Beaver Lake is a 79-acre lake in Sammamish, east of Lake Sammamish. It is surrounded by
residential development and Beaver Lake Park (King County, 2015a).
Pine Lake is an 88-acre lake in Sammamish, surrounded by residential development and
Pine Lake Park (King County, 2015b).
The Cedar River is a 45-mile-long river that originates in the Cascade Mountain Range and
flows through Renton, emptying into the southern portion of Lake Washington. Its primary
viewpoint is from the Cedar River Trail and Park.
Other, smaller features that are considered to be visual resources include small water bodies,
parks, and natural areas. Natural areas and parks are described in Chapters 5 and 12, and
listed in Appendix G.
January 2016 CHAPTER 11 VIEWS AND VISUAL RESOURCES 11-11
PHASE 1 DRAFT EIS
Energize Eastside EIS 140548
Figure 11-3
Major Visual Resources
SOURCE: King County 2015; ESA 2015; WA Ecology 2014.
Olympic
Range C a s c a d e R a n g e
Mt. Rainier Combined Study
Area Boundary
City Limits
MountainTops
U:\GIS\GIS\Projects\14xxxx\D140548_EastsidePSETransmisisonCoor\MXD\MajorVisualResources.mxd
0 10
Miles
Tiger Mtn.
Squak Mtn.Cougar Mtn.Ce
d
a
r
R
i
v
e
r
Lake
Washington
Lake
Sammamish
Pine LakeSeattle
P u g e t
S o u n d
Sammamish Valley
Mercer Slough
Beaver Lake
Note: This map is for reference only. It is not guaranteed that the information is accurate or complete.
Figure 11-8. View of Lake Sammamish
and the Cascades from Neighborhood in
Northeast Bellevue
Figure 11-9. Lake Sammamish
Figure 11-5. View of the Bellevue Skyline Figure 11-4. Mount Rainier View from a
Neighborhood in Northwest Bellevue
Figure 11-6. View of Mount Rainier from
Renton Figure 11-7. View of Lake Washington,
Seattle Skyline, and the Olympic Mountain
Range from a Neighborhood in Renton
January 2016 CHAPTER 11 VIEWS AND VISUAL RESOURCES 11-13
PHASE 1 DRAFT EIS
11.3.3 Public Viewpoints
According to the comprehensive plans described in Section 11.2, most public viewpoints in
the combined study area are provided at parks, trails, and public open spaces. However, they
may also be located in less obvious areas, such as along roadway corridors or municipal
buildings. Viewpoints and important visual or aesthetic resources that have been identified as
such by local communities through their comprehensive plans or other policies are described
in greater detail in Appendix G. The EIS Consultant Team used City websites and GIS data
to identify parks, trails, and open spaces that provide views, both of visual resources or of the
parks themselves. These identified public viewpoints are summarized in Table 11-1. Figure
11-10 shows the larger parks, trails, and public open spaces. Smaller parks are not shown on
the figure, but will be considered in the project-level analysis if potentially affected by any of
the Alternatives evaluated in Phase 2 of this EIS.
Table 11-1. Public Viewpoints
Jurisdiction Major Parks, Trails, and Open Spaces
Washington
State Parks
Bridle Trails State Park, Issaquah to High Point Trail Site, Lake Sammamish
State Park, Squak Mountain State Park, West Tiger Mountain Natural
Resources Conservation Area
King County Bridle Crest Trail Site, Cavanaugh Pond Natural Area, Cedar Grove Natural
Area, Cedar River to Lake Sammamish Trail Site, Cougar Mountain Regional
Wildland Park, Cougar/Squak/Tiger Corridor, East Lake Sammamish Trail Site,
Eastside Rail Corridor, Evans Creek Preserve, Evans Creek Natural Area,
Grand Ridge Park, Issaquah Creek Natural Area, Marymoor Park, May Valley
164th Natural Area, Sammamish River Trail Site, Soaring Eagle Regional Park,
Soos Creek Trail
Beaux Arts Western Academy of Beaux Arts (WABA) Lake Washington waterfront beach
Bellevue Bellevue Downtown Park, Burrows Landing, Chesterfield Beach Park, Coal
Creek Natural Area, Goddard Mini Park, Kelsey Creek Park, Lake Hills
Greenbelt Park, Lake Washington Trail, Lewis Creek Park, McCormick Park,
Mercer Slough Nature Park, Phantom Lake/ Larson Lake Wetland Complex,
Pikes Peak Greenbelt, Robinsglen Nature Park, Weowna Beach Park, YMCA
Trail
Clyde Hill Clyde Hill City Park, Clyde Hill Viewpoint Park
Hunts Point Wetherill Nature Preserve
Issaquah The City’s Central Park, Emily Darst Park, Tibbetts Valley Park, Squak Valley
Park, Talus Open Space, Timberlake Park, The Tradition Plateau Natural
Resource Conservation Area
Kirkland David E. Brink Park, Heritage Park, Houghton Beach Park, Houghton
Neighborhood Park, Lake Washington Trail, Marina Park, Marsh Park, Rose Hill
Meadows, Street End Park, Watershed Park, Waverly Beach
Medina Lake Washington Trail, Medina Beach Park, Viewpoint Park
CHAPTER 11 January 2016 11-14 VIEWS AND VISUAL RESOURCES
PHASE 1 DRAFT EIS
Jurisdiction Major Parks, Trails, and Open Spaces
Newcastle Clubhouse Trail, East Cross Town Trail, Golf Course Trail, Hazelwood Park,
Highland Trail, Lake Boren Esplanade, Lake Boren Park, Lake Washington
Trail, May Creek Park, May Creek Trail, May Creek Open Space, Meadowview
Trail, Mid Cross Town Trail, Olympus Trail, Terrace Trail, West Cross Town
Trail, Windtree Park
Redmond Bridle Crest Trail Site, Dudley Carter Park, Idylwood Beach Park, Luke
McRedmond Landing, Redmond Central Connector, Reservoir Park
Renton Cedar River Trail and Park, Gene Coulon Memorial Beach Park, Honey Creek
Open Space, Jones Park, Kennydale Beach Park, Lake Washington Trail,
Maplewood Golf Course, Phillip Arnold Park, Riverview Park, Ron Regis Park
Sammamish Beaver Lake Park, Ebright Creek Park, Evans Creek Preserve, Pine Lake Park,
Sammamish Landing
Yarrow Point Yarrow Bay Wetlands Trail
January 2016 CHAPTER 11 VIEWS AND VISUAL RESOURCES 11-15
PHASE 1 DRAFT EIS
Energize Eastside EIS 140548
Figure 11-
Public Views
SOURCE: King County 2015; ESA 2015; WA Ecology 2014;
Issaquah 2015; Newcastle 2015; Bellevue 2015; Sammamish 2015;
Renton 2015; Kirland 2015; Redmond 2015.
Lake Washington
Lake
Sammamish
Bellevue
Sammamish
Issaquah
Renton
Newcastle
RedmondKirkland
Beaux Arts
Medina
Clyde
Hill
Hunts
Point
Yarrow
Point
Mercer
Island
Grass Lawn
Com. Park
Bridle Trails
State Park
Marymoor
Park
PSE TrailCross Kirkland
Corridor
Yarrow Bay
Wetlands
Wetherill Nature
Reserve
Medina Park
SR520
Trail
SR520
Trail
Evans Cr.
Preserve
Beaver Lk.
Park
Lk. Sammamish
State Park
Cougar Mountain
Regional Park
Squak Mountain
State Park
West Tiger
Moutain NRCA
Talus
Open Space
May Cr.
Park
Cedar River
Natural Zone
Gene Coulon
Memorial Beach Park
Cedar River
Trail
Coal Cr.
Natural
Area
Lk. Wasghinton
Trail
Mountains
to Sound
Trail Mercer Slough
Nature Area
Kelsey Cr.
Park
Bellevue
Botanical
Gardnes
Tradition Plateau
NRCA
Sammamish
River Trail
Lakeside
Sammamish
Talbot Hill
Novelty Hill
Lake Tradition
Existing
Substations
100ft Contour
Trails
Roadway
Combined Study
Area Boundary
Water bodies
Parks With Views
Parks and Natural
Areas
City Limits
U:\GIS\GIS\Projects\14xxxx\D140548_EastsidePSETransmisisonCoor\MXD\RecreationViews.mxd
0 2
Miles
Note: This map is for reference only. It is not guaranteed that the information is accurate or complete.
11.3.4 Private Viewpoints
King County Assessor data were used to identify views associated with study area properties
and examine correlations between views and property values. Many of the visual resources
identified earlier in the chapter are used by the King County Assessor to evaluate property
values. These include views of Puget Sound, Lake Washington, Lake Sammamish, the
Olympic Mountains, the Cascade Mountains, Mount Rainier, territorial views, and views of
small lakes, rivers, or creeks.
Highly valued views are available from many properties in the combined study area. King
County Assessor tax assessment data were used to estimate how many properties have views
that are valued sufficiently to affect property values. The Assessor’s office identifies
properties with views, and rates those views with a view score. Because the Assessor
typically makes these observations without entering the structures on the properties, this
analysis likely does not identify all properties with views, but it provides a broad sense of the
most likely locations where views are available (King County, 2012).
Of the 114,000 parcels within the combined study area, the King County Assessor identified
16,000 parcels (15 percent) as having a view. Figure 11-11 shows the views most commonly
noted in the King County Assessor data. Many properties have more than one view (visual
resource) listed, such as a territorial view and a view of mountains or an urban skyline in the
background. The most common views noted within the combined study area were territorial
views.
Figure 11-11. Percentage of View Types in the Combined Study Area
Source: King County, 2012
The King County Assessor’s office assigns each property a view score, with higher values
being assigned to better quality views as judged by the assigned property Assessor. Each
Assessor takes into account the extent of view, obstructions, and other factors based on their
external site observations. Recognizing that the data collected by the Assessors were intended
for property tax assessment purposes and do not constitute an exhaustive inventory of
properties with views, these observations provide a broad overview of where view properties
are clustered within the combined study area. Properties with the highest view scores are
January 2016 CHAPTER 11 VIEWS AND VISUAL RESOURCES 11-17
PHASE 1 DRAFT EIS
along the Lake Washington shoreline, particularly in Bellevue, Medina, and Hunts Point; in
Clyde Hill at 300 to 400 feet above sea level; along the flanks and top of Cougar Mountain,
and to a lesser degree on the flanks of Squak Mountain and Tiger Mountain; and along the
shoreline of Lake Sammamish in Bellevue, Issaquah, Redmond, and Sammamish (Figure
11-13).
As stated above, territorial views are the most commonly noted views. Many properties have
more than one visual resource noted by the Assessor; therefore, the number of views is
greater than the total number of parcels. Overall, Bellevue has the highest number of view
properties (6,299) in the combined study area, followed by Sammamish which has 2,205
view properties. Smaller cities, such as Beaux Arts Village, have the fewest view properties.
This skew toward the larger cities is partially because larger cities have more properties
overall. Figure 11-12 summarizes the percentage of common views noted in the Assessor’s
data in each study area community.
Figure 11-12. Percent of Private Viewpoints Identified by King County Assessor in
Study Area Communities
Source: King County, 2012
CHAPTER 11 January 2016 11-18 VIEWS AND VISUAL RESOURCES
PHASE 1 DRAFT EIS
Energize Eastside EIS 140548
Figure 11-13
Property View Scores
SOURCE: King County 2015; ESA 2015; WA Ecology 2014.
For more info visit www.energizeeastsideeis.org/map-propertyviews
Lake Washington
Lake
Sammamish
Bellevue Sammamish
Issaquah
Renton
Newcastle
RedmondKirkland
Beaux Arts
Medina
Clyde Hill
Hunts
Point
Yarrow
Point
Mercer
Island
Cougar Mt.
Squak Mt.
Tiger Mt.
Vernell
Lakeside
Sammamish
Westminster
Talbot Hill
Novelty Hill
Lake Tradition
Mountain Tops
100ft Contour
View Score - Quality
of Views
1 - 3 (low)
4 - 6
7 - 10 (medium)
11 - 15
16 - 24 (high)
Existing
Substations
Roadway
Combined Study
Area Boundary
Water bodies
City Limits
Unincorporated
King County
U:\GIS\GIS\Projects\14xxxx\D140548_EastsidePSETransmisisonCoor\MXD\View Score.mxd
0 2
Miles
Note: This map is for reference only. It is not guaranteed that the information is accurate or complete.
11.3.5 Existing Light and Glare
The combined study area is mostly urbanized with
residential, commercial, and industrial land uses.
Daytime glare is mostly associated with reflected
sunlight from building doors and windows and
vehicles. Current sources of nighttime light and
glare include pole-mounted streetlights, lighting
from vehicle headlights and traffic, illuminated
buildings and residences, and exterior lighting
associated with buildings and residences (parking
lots, building signs, entryways for single-family
homes, etc.). Ambient nighttime light and glare
levels typically depend on surrounding land uses.
Commercial areas and roadways usually have the
most light and glare, while agricultural lands and
open space often have the lowest levels. Ambient
nighttime light levels are expected to be lowest in
the rural areas at the foothills of the Issaquah Alps,
varied from low to moderate in single-family
residential areas, and highest in commercial areas
such as downtown Bellevue (Figure 10-5).
11.3.6 Existing Electrical Facilities
Within the combined study area, electrical
infrastructure is already present including 12.5 kV
lines, 115 kV lines, 230 kV lines, and transmission
and distribution substations (Figures 11-14, 11-15,
and 11-16).
The 12.5 kV lines distribute electricity directly to
consumers. These lines are commonly constructed
of wood poles up to approximately 60 feet tall; the
shorter poles make the lines less visible from a
distance (Antunes et al., 2006). As stated in the
comprehensive plans noted in Section 11.2 most
study area communities are working to
underground these smaller distribution lines as
new development occurs.
Typically, 115 kV lines are suspended on single
wood poles and are generally 70 to 90 feet above
ground (Corbin, 2007), but within the Eastside
some are as short as 49 feet (Strauch, personal
communication, 2015). Depending on the terrain,
the poles are typically spaced 300 to 400 feet apart
(Corbin, 2007).
Figure 11-15. 230 kV Transmission
Line Crossing SE May Creek Park
Road in Newcastle
Figure 11-14. 115 kV Transmission
Line at the Intersection of NE 8th
and 136th Ave NE in Bellevue
Figure 11-16. Lakeside Substation
CHAPTER 11 January 2016 11-20 VIEWS AND VISUAL RESOURCES
PHASE 1 DRAFT EIS
The 230 kV lines are typically suspended on steel poles that are 100 to 135 feet tall and 200
to 1,000 feet apart (Corbin, 2007).
Substations are fenced areas that contain a building and a yard with electrical equipment. On
the Eastside, overhead wires typically feed the substation and the surrounding electrical
distribution system.
Figures 11-14, 11-15 and 11-16 show an example of existing electrical infrastructure,
including substations, 115 kV lines, and 230 kV lines located within the combined study
area.
The main 115 kV PSE line enters the combined study area from the north through Redmond
and heads south through the Westminster substation and the Lakeside substation, terminating
at the Talbot Hill substation in Renton, with minor offshoot lines diverging from the mainline
along the way (Figure 11-17).
The existing large substations (e.g., Sammamish, Lakeside, Talbot Hill, and Lake Tradition)
are typically located in industrial, commercial, or vacant areas where topography and
vegetation can shield the substation. Smaller substations, which are lower in height and easier
to conceal, can be found adjacent to most land uses, including residential properties, but
vegetation and fences are often used so that they are less noticeable. The 115 kV lines, which
are more prominent, are most common along commercial rights-of-way, while 230 kV lines,
with their large easements, are located in residential areas but are often buffered by
vegetation.
January 2016 CHAPTER 11 VIEWS AND VISUAL RESOURCES 11-21
PHASE 1 DRAFT EIS
Energize Eastside EIS 140548
Figure 11-17
PSEs Eastside Electrical
Transmission Infrastructure
SOURCE: King County 2015; ESA 2015; WA Ecology 2014;
Puget Sound Energy 2015.
Lake Washington
Lake
Sammamish
Bellevue Sammamish
Issaquah
Renton
Newcastle
RedmondKirkland
Beaux Arts
Medina
Clyde
Hill
Hunts
Point
Yarrow
Point
Mercer
Island
Lakeside
Sammamish
Talbot Hill
Novelty Hill
Lake Tradition
Existing 115kV (PSE)
Existing 230kV (SCL)
Existing 230kV (PSE)
Existing Substations
Roadway
Combined Study Area
Boundary
Water bodies
City Limits
Unincorporated King
County
U:\GIS\GIS\Projects\14xxxx\D140548_EastsidePSETransmisisonCoor\MXD\ElecticInfrastructure.mxd
0 2
Miles
Note: This map is for reference only. It is not guaranteed that the information is accurate or complete.
11.4 HOW WERE POTENTIAL VISUAL IMPACTS
ASSESSED?
Due to the programmatic nature of this EIS, a general
overview of potential impacts is provided. In order to
conduct a detailed visual impact assessment, the exact
location, size, and configuration of the proposed project
would need to be known. A more site-specific analysis
will be provided in Phase 2 of this EIS process, when a
specific project is proposed.
Because the value of visual resources is subjective based
on the viewer, it is difficult to quantify or estimate visual
impacts, particularly at a programmatic level. Available
methods focus on project-level evaluations. For this
programmatic evaluation, potential visual impacts were
evaluated using an adaptation of the Federal Highway
Administration Guidelines for Visual Impact Assessment
(FHWA, 2015). This method, although developed for
project-level review, takes into account visual
compatibility (e.g., scale, form, materials); viewer
sensitivity (e.g., proximity, extent, awareness, focus,
protected views); and degree of impact (adverse, neutral,
or beneficial). The general methods and impact assessment
criteria are applicable to this evaluation. This EIS analysis
used the four impact assessment criteria from the FHWA
guidelines shown in Table 11-2.
Table 11-2. Impact Assessment Criteria
Criterion Description
Degree of contrast The extent to which a viewer can distinguish
between an object and its background.
Duration of impact How long the visual impact would last.
Number of viewers How many viewers would notice the change
in the visual environment.
Sensitivity of the viewer The proximity of viewers and their level of
awareness.
In most cases, viewers who are closer to new electrical infrastructure would be subject to
greater visual impacts than those located farther away from the project. However, factors
such as topography and vegetation are considered because they could substantially affect
project visibility and perceived visual contrast levels.
Who are the potential
viewers?
A viewer is anyone who
observes project-related
changes to the visual
environment. For instance,
viewers of new transmission
lines in a transportation
corridor would include drivers
and pedestrians. Viewers of
expanded substations in
single-family residential areas
would likely be residents.
Knowing the type of viewer
helps determine the viewer’s
sensitivity to the impact
because it determines the
context and how long they
experience the view. To learn
more about the types of
viewers present in the
combined study area, see
Figure 10-4 which shows
existing land uses.
January 2016 CHAPTER 11 VIEWS AND VISUAL RESOURCES 11-23
PHASE 1 DRAFT EIS
For this analysis, the magnitude of project-related impacts is classified as being minor,
moderate, or significant as follows.
Minor - If they would be noticeable but infrequent or limited in extent. The duration of the
impact would be temporary, the degree of contrast would be minimal, few viewers would be
impacted, or the viewers who would be impacted have a
low sensitivity to the change to the visual environment.
Moderate - If they would be long term or permanent, but
limited in scope or effect. The degree of contrast could be
high with few, less sensitive viewers, or the degree of
contrast could be low but with more viewers with higher
sensitivity to the change in the visual environment.
Significant - If the duration of impact would be
permanent, the degree of contrast would be high, and there would be a medium to high
number of viewers with medium to high sensitivity to the change in the visual environment.
A summary of how the four assessment criteria are used to assign impact classifications is
provided in Table 11-3.
Table 11-3. Applying Assessment Criteria to Assign Impact Classification
Impact Degree of
Contrast
Number of
Viewers
Duration of
Impact
Sensitivity of
the Viewer
Minor Low to Medium Low to Medium Short-Term to
Long-Term
Low to Medium
Moderate Medium to High Medium to High Short-Term to
Long-Term
Medium to High
Significant High Medium to High Permanent Medium to High
11.5 WHAT ARE THE LIKELY CONSTRUCTION IMPACTS
TO VIEWS AND VISUAL RESOURCES?
11.5.1 Construction Impacts Considered
This section describes the types of project-related construction impacts that could affect the
visual environment of the study areas. Common construction-related impacts to views and
visual resources include clearing and grading or general construction activities (presence of
construction workers, vehicles, or equipment).
Clearing and grading can result in a visual impact because areas that were once vegetated
would be cleared, and natural undulations in the topography would be graded. Clearing and
grading has the potential to permanently change the character of the area, particularly if a
substantial amount of taller vegetation (such as trees) is removed or if grading noticeably
alters any existing landforms. Therefore, clearing and grading is less likely to be noticeable in
Who are Sensitive Viewers?
Viewers are considered
sensitive if they have traveled
to a viewpoint to enjoy the
view, and/or they are residents
who enjoy a view over the long
term.
CHAPTER 11 January 2016 11-24 VIEWS AND VISUAL RESOURCES
PHASE 1 DRAFT EIS
areas that are already mostly flat and have limited vegetation. However, clearing in heavily
forested areas, or areas with varied terrain such as hills or mountain ranges, would potentially
impact foreground views, especially where extremely linear forms contrast against curved
landscapes. The effects of permanent clear zones for transmission lines are discussed under
operational impacts.
Construction activities often require introduction of large equipment into the visual
environment. Construction vehicles and equipment often produce visible dust while clearing
the right-of-way and traveling on unpaved access roadways. Increases in local traffic during
construction could also result in temporary visual impacts, particularly if a given location
requires numerous workers and on-site parking.
Construction-related impacts to views and visual resources from the project would be
temporary and vary depending upon the component, ranging from approximately 2 to 36
months (see Table 2-3 in Section 2.3.5 for anticipated construction durations for each
alternative). Impacts resulting from the project would vary throughout the combined study
area, depending on the duration of the construction activities and the visibility and proximity
of the construction to viewers. In general, construction impacts to visual resources and views
are not considered significant because they would be temporary.
All of the alternatives would likely require some degree of construction, and therefore would
produce temporary construction impacts. Impacts would likely result from creation of access
roads, clearing for transmission line rights-of-way, or increased presence of construction
vehicles, equipment, materials, and personnel, as well as the potential for increased light and
glare associated with construction site lighting. Alternatives 1 and 3 present the greatest
potential for visual impacts during construction, while Alternative 2 presents the least
potential for visual impacts, due to the decentralized and small-scale nature of most of the
components.
Vegetation clearing during construction can be either temporary or permanent. Temporary
vegetation removal that can be restored after construction is discussed in Section 11.5.
Adopted plans and policies for visual impacts and view protection focus on the permanent
structures that remain following construction. Long-term impacts associated with permanent
facilities are discussed in Section 11.6.
11.5.2 No Action Alternative
Under the No Action Alternative, PSE would not engage in any construction activities
beyond the occasional conductor or pole replacement that is necessary for regular
maintenance. Individual property owners may choose to construct solar panels, wind
turbines, or rooftop generators as a means of reducing energy consumption, but the level of
such activity is not expected to change. Impacts to visual resources or views are expected to
be negligible.
11.5.3 Alternative 1: New Substation and 230 kV Transmission Lines
Impacts are described according to the major components associated with Alternative 1. The
substation impacts are described first, followed by transmission line options.
January 2016 CHAPTER 11 VIEWS AND VISUAL RESOURCES 11-25
PHASE 1 DRAFT EIS
Construction or expansion of a substation would be required for any of the options under
Alternative 1. Substation construction would require equipment and activities that would
contrast with the visual character of residential areas since it would be larger scale
construction than is common in such areas. The duration of construction would also be longer
than in any other location in the transmission corridor. The visual impacts from substation
construction activities at the Westminster and Lakeside substation sites would be minor to
moderate, depending on design and location. The Westminster substation site is surrounded
by residential uses, and therefore has higher viewer sensitivity, while the Lakeside substation
is surrounded by commercial, industrial, and institutional land uses and has lower viewer
sensitivity. Impacts at the Vernell site (which is just south of SR 520 and surrounded by
industrial and commercial uses) would be minor, due to lower contrast with the character of
the areas and lower viewer sensitivity.
Under the options proposed for Alternative 1, clearing would be required for construction of
the transmission line, access roads, substation expansion, and placement of accessory
infrastructure (vaults, etc.) Depending on where the alignment is placed, construction could
affect many viewers (such as along a major highway) or few viewers (for example, in a
heavily wooded area where there is less development). The sensitivity of viewers could also
vary depending on whether the alignment is placed in a highly developed area (such as along
a freeway where viewers are accustomed to views of large construction projects) or within a
lower density residential neighborhood (where viewers may be accustomed to other
residential development but not large-scale construction equipment). The duration of impact
for construction would vary depending on the amount of vegetation that needs to be cleared
and other construction requirements, but could range up to 8 weeks in any given location.
11.5.3.1 Option A: New Overhead Transmission Lines
Clearing, grading, and construction activities described above would be required for
construction of Alternative 1, Option A. Most construction vehicles and equipment would be
visible only in the immediate vicinity. Cranes would be visible from a distance. In any given
location, construction activity would be visible for a few weeks. Due to the short construction
period in any location, construction activities for Option A are generally expected to have
minor impacts on visual resources and viewers if the work is conducted within an existing
corridor or right-of-way. If a new corridor were selected, the duration would likely be longer
due to the need for more extensive clearing. The longer duration and likelihood of stockpiled
construction debris in or near residential areas and parks, where more sensitive viewers
reside, could have a moderate impact on viewers.
11.5.3.2 Option B: Existing Seattle City Light 230 kV Transmission
Corridor
Alternative 1, Option B would have the same clearing, grading, and construction activities as
described for Option A because the existing transmission line would need to be replaced, and
the new transmission line and substation equipment would be the same or similar to Option
A. Option B would require modifications to and expansion of several substations in order to
make the interconnections with the existing transmission line. Minor impacts are anticipated.
CHAPTER 11 January 2016 11-26 VIEWS AND VISUAL RESOURCES
PHASE 1 DRAFT EIS
11.5.3.3 Option C: Underground Transmission Lines
Clearing, grading, and construction activities described above would be required for
construction of Alternative 1, Option C. Undergrounding transmission lines generally
requires more extensive construction effort to cut trenches and place concrete duct banks,
conduits, and vaults that carry the conductors, resulting in a longer construction period. This
longer construction period could result in greater short-term impacts than for Option A or B,
but they would still be considered minor because of the temporary nature of construction.
11.5.3.4 Option D: Underwater Transmission Lines
Alternative1, Option D would require clearing, grading, and construction activities described
above. This option would require underground transmission line installation near the
shoreline and underwater construction in Lake Washington. The lake is considered to be a
visual resource by most nearby communities. Although submerged lines are not visible after
they are constructed, barges and other construction vessels would be present on the lake for a
period of time. The presence of unusual vessels would not necessarily be considered an
adverse visual impact for a short duration. Due to the short construction period, Option D
could have minor impacts on visual resources.
11.5.4 Alternative 2: Integrated Resource Approach
In general, Alternative 2 would result in fewer construction-related impacts than Alternative
1 because the components are smaller in scale and distributed over a larger area, resulting in
less noticeable contrast. Viewer sensitivity is also expected to be less because construction
would be small-scale and similar in nature to other construction projects in the area.
Potential construction-related activities associated with the different components (energy
efficiency, demand response, distributed generation, energy storage, and peak generation
plant) would result in minor impacts to visual resources. The construction impacts associated
with the energy storage component would be of longer duration but would still be considered
minor.
11.5.5 Alternative 3: New 115 kV Lines and Transformers
Under Alternative 3, clearing and grading would likely be required for widening of
easements for 115 kV lines and expansion of the Talbot Hill, Sammamish, Lakeside, Clyde
Hill, and Hazelwood substations. Construction equipment and personnel would be necessary
at the substation sites and the 115 kV alignments.
The new 115 kV alignments would primarily be along roads, crossing through all types of
neighborhoods and potentially near visual resources such as parks. Viewer sensitivity would
range from low for viewers in cars (for whom power pole installation activities are relatively
common) to high near natural areas and in new corridors that may need to be developed,
especially near residential areas.
The visual contrast present during construction is anticipated to be less than Alternative 1,
Option A or B (which involve overhead lines) because the scale of poles would be smaller,
and smaller construction equipment would be needed. However, compared to Alternative 1,
January 2016 CHAPTER 11 VIEWS AND VISUAL RESOURCES 11-27
PHASE 1 DRAFT EIS
the longer corridor of Alternative 3 would result in more dispersed construction impacts that
are more likely to be seen by a higher number of viewers.
In general, construction activities for Alternative 3 would have a short duration and result in
minor to moderate impacts on the visual environment, depending on viewer sensitivity.
11.6 WHAT ARE THE LIKELY OPERATIONAL IMPACTS TO
VIEWS AND VISUAL RESOURCES?
11.6.1 Operation Impacts Considered
All operation impacts are considered to be permanent. Common operation-related impacts
include the following:
• Changes to visual character;
• Changes to views, viewpoints, and visual resources; and
• Light, glare, and exhaust.
These impacts were assessed using the impact criteria listed in Section 11.4, to assign impact
classifications (minor, moderate, significant). Impacts resulting from views of existing power
lines on assessed property values were also examined. While it is common for properties
abutting or within a transmission line corridor to have lower assessed property values than
similar properties that are not abutting or within the corridor, a direct correlation between
views of high-voltage transmission lines and changes to assessed property values could not
be made, because much of the effect is likely due to restrictions on property use in the
easement, rather than the view of the property line. For this reason, impacts on property
values were not classified as minor, moderate or significant.
11.6.1.1 Changes to Visual Character
The visual character of the Eastside is described in Section 11.3.1. Changes to visual
character can occur through introduction of new infrastructure that creates contrast against
the natural or built environment due to its height or geometric form. Changes to visual
character can also occur as a result of introducing a clearing or opening in an area that was
previously forested.
11.6.1.2 Changes to Views, Viewpoints, and Visual Resources
Changes to views could occur through obstruction of the view. For example, taller
infrastructure can obscure or block views. Changes to visual resources would most likely
occur if infrastructure were placed on a visual resource or viewpoint.
11.6.1.3 Light, Glare, and Exhaust
Light, glare, and exhaust could occur if new lighting fixtures were required, previously
unlighted areas were lit, new infrastructure was composed of reflective materials, or new
infrastructure produces visible exhaust. The degree of the impact would depend on the
contrast created by the new lighting source and the proximity to viewers. The amount of
CHAPTER 11 January 2016 11-28 VIEWS AND VISUAL RESOURCES
PHASE 1 DRAFT EIS
impact produced through glare would depend on the amount of reflective materials used and
how much is already present in the surrounding environment. Impacts associated with
exhaust, such as from a peak generation plant, would depend on how visible it is from a
distance, and whether it changes the character of the visual environment into which it is
placed. Visibility from a distance depends on the density of visible emissions and climatic
conditions (such as clear cold air or fog) and frequency of operation.
11.6.1.4 Impacts to Property Values
As described in Chapter 10, there have been a wide range of findings regarding the
relationship between property values and views of power lines. As previously discussed, for
this evaluation, potential impacts to property values are discussed in terms of assessed
valuations, in order to use recent published data with a broad base that can be used for
comparison.
Property owners have expressed concern about market value. Because market value is based
on a variety of factors in addition to visual resources (for example, amenities of the house,
proximity to schools, transit, local services, etc.) it is difficult to obtain data for comparison.
Therefore, this analysis describes property values in terms of assessed value, not market
value.
Several studies have found that areas adjacent to major transmission lines have lower
property values than comparable properties where there is no view of a transmission line. The
studies indicate a range of 1 to 20 percent reduction in property value, with most of the
reductions in value around 6 percent (Cowger et al., 1996; Rosiers, 2002; Chalmers, 2012).
However, in a review of studies investigating the relationship between transmission lines and
property values, the Electric Power Research Institute (EPRI) determined that neither the
proximity of transmission lines nor the voltage and size of transmission lines and easements
were determining factors regarding changes in property values (EPRI, 2003).
Despite the varying conclusions on whether or not views of transmission lines translate into
reduced property values, the King County Assessor’s Office noted that factors such as
construction of a view-obstructing transmission line could result in a negative influence on
property values (FCS Group, 2016). The Assessor’s Office noted that when a property value
appears to be affected by the presence of a power line, the Assessor of the property adjusts
the assessed value downward (Prins, personal communication, 2015).
Numerous transmission lines are located in the combined study area. It is beyond the scope of
this analysis to prepare a complete cost comparison of all properties having views of
transmission lines with comparable properties that do not have views. To conduct a
programmatic-level evaluation, the EIS Consultant Team examined Assessor’s data to
identify a potential correlation between a view of a power line and lower property valuations.
The EIS Consultant Team found that the data were inconclusive about the reasons for
different valuations set by the Assessor. For example, adjustments are sometimes made to
reflect views of power lines, but they may also reflect other factors such as restrictions on use
of property in a power line easement. The EIS Consultant Team could not determine the
degree to which these various factors negatively impacted the property assessment.
January 2016 CHAPTER 11 VIEWS AND VISUAL RESOURCES 11-29
PHASE 1 DRAFT EIS
In conclusion, because of the number of factors and interrelationships affecting property
values, it is not possible to determine from Assessor’s data how much of the effect on
property values is due specifically to views. It is reasonable to assume that some existing
properties would have lower property values following construction of an overhead
transmission line. Refer to Chapter 10 for additional discussion of the effect of overhead
transmission lines and property values.
11.6.1.5 Consistency with Plans and Policies
At a programmatic level, it is assumed that PSE would follow policies associated with design
of the project relating to visual aspects of projects, such as use of fencing around substations.
If design policies are followed, Alternative 2 would likely be consistent with the plans and
policies of study area communities.
Alternative 1, Option C would also likely be consistent with plans and policies because it
would place the transmission line underground and would avoid the shoreline and major
visual resources.
Additional evaluation of Alternative 1, Option D would be required to determine if the use of
the shoreline to connect underwater portions of the line with overhead lines would be
consistent with comprehensive plan and SMP guidance (see Appendix G).
The study area policies provided in Appendix G and described in Section 11.2 will be
considered in greater detail in the Phase 2 EIS.
11.6.2 No Action Alternative
Under the No Action Alternative, no substantial new infrastructure would be introduced into
the visual environment, and therefore no substantial changes to the visual character of the
Eastside would occur. The primary changes to the visual environment under the No Action
Alternative would be those associated with PSE’s conservation efforts. These include
dispersed and minor changes to buildings, such as weatherproofing and addition of solar
collectors. Because conservation improvements would be integrated into an urban
framework, no visual resources would be impacted. Public places such as parks, trails, or
open spaces and associated viewpoints would also not be impacted.
Due to the dispersed nature of the No Action Alternative, there would be numerous viewers,
but viewer sensitivity would be low because improvements would not differ substantially
from current conservation efforts in the area. Window replacements and similar
weatherproofing would have negligible visual impacts. However, the dispersed presence of
solar collectors and similar small infrastructure could result in minor impacts for some
viewers because they would create slightly more contrast.
The most visible elements that are expected under the No Action Alternative would be wind
turbines and solar panels that may be installed by PSE or its customers as a means of
reducing energy consumption. Solar panels can introduce a strong, regular geometry into the
landscape and can produce glare from their highly reflective surfaces. However, impacts are
reduced when the panels are placed in urban settings, as would occur under this alternative. If
CHAPTER 11 January 2016 11-30 VIEWS AND VISUAL RESOURCES
PHASE 1 DRAFT EIS
wind turbines are used, they would likely be small-scale turbines serving individual houses or
small buildings. Such turbines are typically 6 to 24 meters in height and have rotors with a
diameter of 2 to 7 meters (Fortis Wind Energy, 2015). A flickering effect could be produced
as sunlight passes through the moving blades of a wind turbine; however, visual impacts are
typically minimal. Reflections from the blades of house-scale turbines are unlikely due to the
new coatings that are used (Fortis Wind Energy, 2015). As noted in Chapter 2, in the past
there have been few solar energy systems installed and even fewer wind turbines on the
Eastside. As long as these types of infrastructure continue to be scarce and dispersed
throughout urbanized areas of the Eastside, impacts from solar and wind installation
produced under the No Action Alternative would be minor.
11.6.3 Alternative 1: New Substation and 230 kV Transmission Lines
Under all options proposed for Alternative 1, permanent clear zones would be required for
transmission lines, access roads, substation expansion, and accessory infrastructure (vaults,
etc.). All options would include visual changes at substations. Overhead options would also
produce impacts associated with new power poles and wires, and there is the potential for
minor light and glare impacts. These types of impacts are discussed generally below and then
in greater detail under the heading for each option.
11.6.3.1 Permanent Clear Zones
To ensure safe and reliable operation of overhead or underground transmission lines, the
National Electric Safety Code (NESC) specifies minimum horizontal and vertical clearance
requirements for overhead lines, where trees and overhanging branches are removed. These
clear zone requirements typically determine transmission right-of-way (or easement) widths.
The amount of right-of-way necessary depends on many factors, including whether or not it
is adjacent to an existing transmission corridor or along a roadway. Typical right-of-way
widths for 115 kV and 230 kV lines are between 70 and 150 feet depending on voltage and
location (AEP-Ohio, 2014). Chapter 2 describes clearing requirements for each alternative.
Specific easement agreements may require more clearance.
For this Phase 1 Draft EIS, where a range of widths is possible the analysis assumes the worst
case for impact assessment. In practice, PSE may be able to reduce the required clear zone, in
which case impacts would be less than assumed for this phase of the EIS. Also, in some
cases, such as along street rights-of-way, small trees can remain below the wires. Clearing in
a right-of-way is not restricted to vegetation. Easements allow PSE to remove anything
located within the right-of-way (such as lawn furniture and other landscaping).
In areas where trees would be removed, the transmission lines and poles would be visible to
nearby viewers. Clear zones can result in impacts by changing the visual character of the area
(removal of trees, landscaping, and structures) and by opening up views of transmission lines
and/or other features of the landscape that were previously obscured by vegetation, such as a
highway or an industrial site.
The degree of contrast produced by clear zones would vary depending on where the
alignment is placed and which option is implemented. For instance, the clear zone for an
overhead transmission line in a new corridor in a wooded area would produce a higher degree
January 2016 CHAPTER 11 VIEWS AND VISUAL RESOURCES 11-31
PHASE 1 DRAFT EIS
of contrast than one placed along a major highway. The clear zone for an overhead
transmission line would have a higher degree of contrast with the surrounding environment
than an underground line. Cleared areas would be less noticeable in areas that are currently
flat and devoid of vegetation. However, foreground views where the transmission line
traverses heavily forested areas, or areas with varied terrain such as hills or mountain ranges,
would potentially be impacted due to the contrast between the straight linear form of the
transmission line rights-of-way and the curved landscape. Therefore, maintaining the clear
zone could result in permanent impacts to residents located along the transmission easement
in that the visual character of their backyards could be significantly altered.
The extent of the required clear zone would be less if the transmission line is placed along a
typical roadway or within an existing right-of-way. However, utilities paralleling existing
corridors can cumulatively create wide, long areas of visual disturbance. In general, the study
area communities, through their comprehensive plans, have identified roadways themselves
as not being aesthetically pleasing and have policies to include landscaping to soften the
visual impact. Locating utility lines along roadways concentrates the visual impact and
allows the opportunity for landscaping to soften the impact.
The sensitivity of viewers would generally be higher in residential areas than in commercial
and industrial areas or along a major arterial or highway, because the contrast created by a
new transmission line would be greater in a residential area. However, the number of viewers
who would see the alignment would be substantially greater along a major arterial or
highway. Because the Eastside is predominantly single-family residential, there is a high
likelihood that any overhead transmission corridor would affect sensitive viewers.
11.6.3.2 Visual Changes at Substations
All of the options associated with Alternative 1 require installation of a new transformer at,
or adjacent to, either the Lakeside substation or the possible substation sites referred to as
Westminster and Vernell.
Substations can have footprints that range from less than an acre (e.g., Eastgate substation) to
8 acres (e.g., Talbot Hill substation). Equipment in substations typically ranges between 20
and 45 feet tall depending on the type of equipment present. Smaller distribution substations
can be screened from view using berms, fencing, or landscaping. Conversely, larger
substations often have an institutional or industrial appearance that is harder to conceal.
For this project, existing substation footprints may need to be expanded by up to 4 acres.
Substations that already have a 115 kV setup, such as the Lakeside substation, would need
less acreage, while additions to Westminster and Vernell substations would need up to the
full 4 acres to install the necessary equipment.
The Westminster and Lakeside substation sites are adjacent to parks and open space and
residential uses, respectively (Figure 10-5); therefore, changes to these locations would be
viewed by more sensitive viewers than the Vernell site, which is adjacent only to commercial
development and a highway. The impact on the visual character of the area would depend on
the design of the expansion and where it is located relative to sensitive viewers. Because the
CHAPTER 11 January 2016 11-32 VIEWS AND VISUAL RESOURCES
PHASE 1 DRAFT EIS
Lakeside site already has a substation and associated overhead lines, the substation expansion
for the new transformer would not substantially contrast with the existing environment.
The Westminster site has no existing substation but has overhead lines. A substation at this
location would alter the character of that area, which includes Viewpoint Park. (Viewpoint
Park, despite its name, does not provide significant views and is not listed in Table 11-1 as a
public viewpoint.) Therefore, visual impacts associated with development of a substation at
either the Westminster or Lakeside substation sites would likely be moderate. At the Vernell
site, there are no sensitive viewers nearby and the visual character is dominated by
commercial development and a major highway, so impacts from a substation would be
minor.
11.6.3.3 Increase in Overhead Poles and Lines
Poles and wires for overhead lines have the potential to impact views by introducing
structures that may be of a different scale than existing structures in the area. They may also
impact the enjoyment of visual resources by partially obstructing views.
11.6.3.4 Light and Glare
The Federal Aviation Administration (FAA) has standards and guidelines that determine
when structures need to be marked and lighted for aircraft safety. It is not anticipated that
aviation warning lights would be required for this project because the proposed electrical
infrastructure, including transmission poles, would be less than 200 feet in height and would
not exceed the obstruction standards contained in 14 CFR Part 77 (FAA, 2007).
Substations include security lighting that operates all night to discourage vandalism and
trespassing. When work at the substation is required at night (e.g., to fix a power outage),
lighting intensity is increased for the duration of the work. In residential areas, substation
lighting is generally required to be kept at the lowest possible levels and shielded to reduce
light spillage impacts. In some areas, landscape screening is also required.
11.6.3.5 Option A: New Overhead Transmission Lines
Long-term visual impacts associated with Alternative 1, Option A include changes to visual
character through introduction of new electrical infrastructure, partially obstructing views of
visual resources, and maintenance of clear zones. Some viewers would likely perceive a
significant impact.
11.6.3.5.1 Permanent Clear Zones
Permanent clear zones would be required under Alternative 1, Option A. The combined study
area is highly varied in visual character, and many areas of the Eastside are already cleared
and developed or have limited tree cover; in such areas clear zones would not contrast
strongly. However, if located adjacent to forested parks or natural areas such as Cougar
Mountain Natural Area, clear zones would produce a pronounced contrast.
It is anticipated that Option A would require a clear zone between 120 and 150 feet wide,
requiring clearance of up to 327 acres of vegetation. Existing transmission corridors in the
combined study area vary in width. If an overhead transmission line were placed in an
January 2016 CHAPTER 11 VIEWS AND VISUAL RESOURCES 11-33
PHASE 1 DRAFT EIS
existing transmission right-of-way, the existing right-of-way would need to be extended to
meet clear zone requirements. In the combined study area, many existing 115 kV
transmission lines have clear zones that are close to the required width for a 230 kV line.
Replacing the existing line with a 230 kV line would involve a more limited amount of
clearing than a new corridor, but could still require removal of up to 109 acres of vegetation.
If a 230 kV transmission line was placed along a typical roadway, a cleared corridor outside
of the road right-of-way could be required in order to provide the required horizontal
clearance.
Because the clear zone would create views of the transmission line, placing a new
transmission line in a residential area where one does not currently exist would have a
significant impact on the visual character of the area adjacent to it, and could have moderate
to significant effects on territorial views or views of visual resources from surrounding
properties within approximately 750 feet (depending on topography and vegetation). Visual
impacts from replacing an existing transmission line could range from minor (in commercial
or industrial areas) to significant (in residential areas or public viewpoints with unique
views).
11.6.3.5.2 Visual Changes at Substations
Visual changes at substations would be as described in Section 11.6.3.2 for all options under
Alternative 1.
11.6.3.5.3 Increase in Overhead Poles and Lines
The presence of transmission lines often results in a sharp contrast with the surrounding
landscapes. The size of transmission line poles and the material they are made of can
influence the amount of impact they create. It is anticipated that 85- to 100-foot-tall steel or
wood poles would be used for the 230 kV lines. Depending on topography the pole height
may vary, with the tallest height being approximately 135 feet if a highway is crossed
(Corbin, 2007).
Placement of poles can also determine the degree of impact. When placed in relatively
unobstructed skylines, transmission lines can become the dominant structure on the horizon,
create contrast against the sky, and result in a more noticeable visual impact. Conversely,
transmission lines placed in areas where they would be surrounded by other tall structures or
trees can result in a less noticeable visual impact. Topography can also play a role in the
visibility of the poles, with poles that are atop hills, ridges, or slopes being more visible than
those that are located below the tree line.
Depending on where the poles are placed, views of visual resources could also be impacted.
Although it is not anticipated that the new transmission corridor would be routed through
known viewpoints, the presence of the line, depending on where it is being viewed, could
obscure views. For instance, if the transmission line were placed along a roadway, it is likely
that the impacts to visual character would be less than significant because the line would not
be a prominent aspect of the viewshed. However, if the transmission line were placed along a
scenic roadway, the lines could obscure views because the roadway itself would be
considered a viewpoint (see Section 11.3).
CHAPTER 11 January 2016 11-34 VIEWS AND VISUAL RESOURCES
PHASE 1 DRAFT EIS
Because of their height and geometric form, transmission lines are often visible above the
horizon, contrasting against the sky and skyline (Figure 11-18). An overhead transmission
line would cross or abut approximately 100 lots per mile in a typical single-family
subdivision with 4 lots per acre. In total, overhead transmission lines would need to extend at
least 18 miles to reach from Talbot Hill substation to Sammamish substation, with greater
length required depending on how many turns the line makes between these two substations.
In industrial, commercial, and lower density residential areas, fewer properties would be
affected. In multifamily areas, and in some commercial areas, the number of viewers could
be greater than in typical single-family subdivisions, even though the number of parcels
might be less.
Views are likely to be impacted where the transmission line is located in the foreground
distance zone (up to approximately 0.5 miles away from the project). However, impacts on
views could also be substantial at greater distances depending on the angle at which the
project is viewed and whether or not it is within the viewer’s direct line of sight. In addition
to affecting the visual character of the area adjacent to it, overhead transmission lines can
impact views of visual resources from surrounding properties. Researchers from the Argonne
National Laboratory analyzed the visibility of transmission lines in their 2013 paper,
Electrical Transmission Visibility and Visual Contrast Threshold Distances in Western
Landscapes. This analysis showed that high-voltage H-frame towers were noticeable to
casual observers at distances of up to 3.5 miles and were thought to “strongly attract visual
attention at distances of up to 1.5 miles” (Sullivan, 2013). However, topography and other
conditions of the setting and viewers can limit the level of visual contrast created by
transmission facilities. Smaller structures like those proposed for this project are not as
noticeable, and other characteristics of the Eastside landscape affect the distance at which
these structures would significantly affect views.
On the Eastside, topography and vegetation limit
visibility in many locations. Figure 11-18 shows an
example of an existing transmission line in Bellevue
that is estimated to be less than 65 feet above the
ground, seen from an uphill location approximately 500
feet horizontally from the line, where the view of Lake
Washington and the Seattle skyline is affected by the
overhead line. The proposed overhead lines would be
smaller than the H-frame facilities in the Argonne
National Laboratory study, but they would be at least
20 feet taller than those shown in Figure 11-19. For
Alternative 1, Option A, viewers within approximately
750 feet (depending on topography and vegetation)
would likely notice a high degree of contrast created by
the transmission line poles and conductors. Given the
approximately 18-mile length of the corridor and the
predominance of residential land uses, a high number
of viewers with high sensitivity would likely be
impacted.
Figure 11-18. 115 kV Existing
Overhead Lines in a
Residential Area of Bellevue
January 2016 CHAPTER 11 VIEWS AND VISUAL RESOURCES 11-35
PHASE 1 DRAFT EIS
Figure 11-19. 115 kV Existing Overhead Lines in Bellevue Affecting Views of Lake
Washington and the Seattle Skyline, from a Distance of 500 feet.
Several factors would affect the visibility of the transmission line and therefore would be
studied in detail in phase 2 of this EIS process. For viewpoints where the viewer’s eye
elevation is higher than the poles, the poles would appear below the horizon line and would
not contrast as much as in places where the poles penetrate the horizon line. For transmission
lines viewed from a distance greater than 1,000 feet, the lines and poles would likely be a
small part of the view and the contrast they produce would be minimal to moderate. In
addition, views from the east looking west toward downtown Bellevue would be less likely to
be impacted because the infrastructure would share the horizon with the tall buildings located
behind it. Except for locations immediately adjacent to the power line easement, new
overhead transmission lines are also less likely to be visible from a distance in heavily
vegetated areas, such as some forested areas of Newcastle and Bellevue. In these areas the
poles would share the horizon with trees, which would also obstruct views from neighboring
properties.
Replacing an existing 115 kV transmission line with a taller set of poles could affect a similar
number of parcels as a new corridor, but the change in contrast between the transmission
lines and the surrounding environment would be less noticeable than from a new line because
the existing lines already affect some views. Typically, properties within approximately 500
feet of and either uphill from or at the same elevation as existing transmission lines have
CHAPTER 11 January 2016 11-36 VIEWS AND VISUAL RESOURCES
PHASE 1 DRAFT EIS
views that are already affected. Replacement with new taller transmission lines could
increase the effect on those properties as well expand the area impact by approximately 250
feet because of the increased height. However, the greater the distance, the greater the
likelihood of intervening features such as vegetation, other structures, and changes in
topography that would obstruct views of the power lines. For immediately adjacent properties
with small structures such as single-family homes, duplexes, and triplexes, taller poles would
appear out of scale. For some adjacent properties where poles are not in sight but the wires
are, the higher placement of wires could mean that the transmission line is less noticeable
than at present, but generally, taller poles would make the lines more visually prominent.
11.6.3.5.4 Light and Glare
Steel poles, when coupled with the reflectivity of their conductors, are more likely to create a
stronger visual contrast than wood poles. They are also more likely to result in glare impacts.
If steel poles are used, a non-reflective coating would be used.
11.6.3.6 Option B: Existing Seattle City Light 230 kV Transmission
Corridor
Long-term visual impacts associated with Alternative 1, Option B include changes to visual
character through introduction of new electrical infrastructure and maintenance of clear
zones, transecting a viewpoint (Bridle Trails State Park), and having the potential to partially
obstruct views of visual resources.
11.6.3.6.1 Permanent Clear Zones and Increase in Overhead Poles
and Lines
Alternative 1, Option B would use an existing corridor for most of the north-south distance
but would require several miles of new corridor to connect to the existing PSE system.
Option B would utilize the portion of the Seattle City Light (SCL) corridor that transects the
Bridle Trails State Park. The SCL corridor already contains a 230 kV transmission line, so
the clear zone would generally not need to expand, except in limited areas where the new line
cannot be constructed in the center of the right-of-way due to the existing line that must
remain in service while the new one is constructed. Although new poles and conductors
would be required, the scale would be similar to that of existing structures and visual impacts
would be minor within the existing corridor. However, the need for a new corridor to
interconnect with the SCL line under Option B would likely involve moderate to significant
impacts on residential neighborhoods as a result of establishing and maintaining a clear zone
and installing new poles and wires to reach the selected substation site.
11.6.3.6.2 Visual Changes at Substations
Visual changes at substations would be described in Section 11.6.3.2 for all options under
Alternative 1.
11.6.3.6.3 Light and Glare
Light and glare impacts would be the same as described under Alternative 1, Option A.
January 2016 CHAPTER 11 VIEWS AND VISUAL RESOURCES 11-37
PHASE 1 DRAFT EIS
11.6.3.7 Option C: Underground Transmission Lines
11.6.3.7.1 Permanent Clear Zones
Long-term visual impacts associated with Alternative 1, Option C include changes to visual
character through maintenance of clear zones. Underground lines could be placed in
roadways or in off-street corridors. Off-street corridors would require clear zones (creating
more contrast), while in street settings, the street serves as a portion of the clear zone
(creating less contrast). Since many streets have limited underground areas where a
transmission line could be installed, it is likely that underground lines would need to be
constructed off-street. Off-street corridors would likely result in a greater contrast than
Alternative 1, Options A and B associated with removal of street trees and existing
landscaping, because no vegetation would be allowed to grow within the clear zone due to
maintenance access needs. Up to 66 acres of vegetation could be impacted PSE often allows
the presence of shorter, pruned vegetation within the clear zones of overhead lines, which
could help to reduce the visual contrast following construction.
11.6.3.7.2 Visual Changes at Substations
Visual changes at substations would be as described in Section 11.6.3.2 for all options under
Alternative 1.
11.6.3.7.3 Increase in Aboveground Structures
Although underground lines themselves would not be visible, vaults would still be required at
the surface or above ground. Vaults are large underground concrete boxes (8 feet by 26 feet)
that are buried at regular intervals, typically every 1,500 to 2,500 feet depending on
topography and the type of cable used. Vaults are equipped with hatches at the surface to
allow worker access for installing conductors and for maintenance and repair activities.
Vaults are generally not conspicuous except that they would be noticeable in a vegetated
landscape to a viewer walking close to them. It is anticipated that few viewers would be
impacted by Alternative 1, Option C, and impacts would be minor.
11.6.3.7.4 Light and Glare
No light, glare, or exhaust impacts are expected because the lines would be underground and
would not require any surface lighting.
11.6.3.8 Option D: Underwater Transmission Lines
Long-term visual impacts associated with Alternative 1, Option D include changes to visual
character where overhead lines are required, and potential impacts to views of Lake
Washington and viewpoints located along the shoreline.
11.6.3.8.1 Permanent Clear Zones and Increase in Overhead Poles
and Lines
Impacts associated with the overland portions would be similar to those described for
Alternative 1, Options A and C. However, Option D could require overhead lines close to the
shoreline, where they could impact views from surrounding areas. Option D would require an
overhead 230 kV transmission between the shoreline and the Sammamish substation. This
east-west line could cross portions of Kirkland, Clyde Hill, Medina, Yarrow Point, or Hunt’s
CHAPTER 11 January 2016 11-38 VIEWS AND VISUAL RESOURCES
PHASE 1 DRAFT EIS
Point. There are no existing east-west power line corridors in any of these locations that
could be used, so a new corridor would be necessary, resulting in visual impacts due to the
contrast created and the sensitivity of the viewers impacted. This section of the alternative is
also expected to impact the most viewers because the overhead line would traverse urbanized
areas, resulting in potentially significant visual impacts.
Once installed, the submerged portion of the line would not be visible. It is unknown at this
time whether or not buoys or other in-water markers would be needed for operation of the
submerged lines.
Installation of submerged transmission cables would require permanent right-of-way clearing
at the shoreline for access roads and vaults. For a submerged transmission line that runs from
Renton to Kirkland, splice vaults would be needed at a minimum of three shoreline locations
and it could be necessary to have one or more additional splice vaults on land. At each vault
location, a clear zone would be maintained from the vault to the water. Shoreline regulations
may require vegetative or other screening of utilities depending on the jurisdiction. Any such
screening would have to occur outside of the clear zone. Visual impacts associated with
vaults and access roads would likely be restricted to the immediate vicinity of the vaults, and
therefore would only impact a few viewers.
Visual impacts associated with a submerged
line, other than those associated with any
overhead lines connecting to the submerged
line, would be minor because once
constructed they would not be visible. Land-
based facilities including the transition
stations and power lines connecting the
submerged lines to substations in the Eastside
would be visible. Figure 11-20 shows an
existing PSE transition station on Lake
Washington at Enatai Beach Park in Bellevue.
Depending on siting, and other factors as
described for Option A, overhead lines, if
used, could have minor impacts if placed in
existing utility corridors. Significant impacts
could occur if overhead lines are placed near
the shoreline of Lake Washington or where
utility corridors do not presently exist.
11.6.3.8.2 Visual Changes at Substations
Visual changes at substations would be as described in Section 11.6.3.2 for all options under
Alternative 1.
11.6.3.8.3 Light and Glare
No light, glare, or exhaust impacts are expected because most of the lines would be
underwater. Overhead portions would have impacts as described in Alternative 1, Option A.
Figure 11-20. PSE Transition for
Underwater Cable Station at Enatai
(Ecology, 2014).
January 2016 CHAPTER 11 VIEWS AND VISUAL RESOURCES 11-39
PHASE 1 DRAFT EIS
11.6.4 Alternative 2: Integrated Resource Approach
In general, Alternative 2 is anticipated to result in few visual impacts because the
infrastructure would be small and distributed over a large expanse, resulting in a low degree
of contrast. Despite the wide geographic reach of the alternative, few viewers are expected
given the small scale of individual projects and the placement of projects in already
developed locations.
11.6.4.1 Energy Efficiency Component
Energy efficiency includes measures such as weatherization, efficient lighting and
appliances, and similar measures. These improvements are not anticipated to result in
permanent impacts to the visual environment. Most changes would be to features inside
buildings where they would not be visible to the general public. Changes to windows and
exterior lighting would occur, but they would not substantially change the appearance of
buildings or sites in a manner that would cause light or glare impacts or would adversely
affect viewers through contrast or hindrance of views. If placed in a historic neighborhood,
the equipment may not match the character of the area and would result in a more noticeable
contrast. These impacts are evaluated in Chapter 13. Overall, negligible impacts are
anticipated.
11.6.4.2 Demand Response Component
The demand response system hinges primarily on changes in consumer energy consumption.
Demand response meters are the only exterior fixtures required. They are small and not
substantially different in appearance from other electric meters, and would not result in light,
glare, or exhaust impacts. Therefore, negligible impacts to the visual environment are
anticipated from this component of Alternative 2.
11.6.4.3 Distributed Generation Component
The types of generators likely to be installed include small reciprocating engines, gas
turbines, microturbines, anaerobic digesters, and fuel cells. Typically, these would be placed
atop commercial or larger multifamily buildings and would not be visible to more than a few,
less sensitive, viewers. In this context, small generation equipment would be similar in
appearance to heating, ventilation, and air conditioning (HVAC) systems and other similar
equipment on the top of such buildings. These types of generation equipment would have
exhaust systems, and viewers may observe steam plumes and other gas emissions, in addition
to emissions that are common from other rooftop equipment
If numerous generators were placed on buildings in close proximity, it could create a more
cluttered appearance. None of these changes would contrast with the general appearance of
similar sized buildings, and for buildings over a few stories in height, few viewers would
notice their presence. The number of generation facilities needed is not known and would
depend on the scale of the facilities that are developed. In order to make a contribution
toward meeting the transmission capacity deficiency, it would likely require hundreds of
small facilities to be installed and interconnected with the grid. Given the total number of
buildings in the Eastside area, this would represent a small impact and would not likely
change the overall visual character of the Eastside. Distributed generation would have minor
CHAPTER 11 January 2016 11-40 VIEWS AND VISUAL RESOURCES
PHASE 1 DRAFT EIS
to moderate visual impacts, depending on whether components are concentrated, the scale of
individual facilities, and the design and location of the facilities.
11.6.4.4 Energy Storage Component
An energy storage component would be a new permanent feature in the Eastside environment
occupying approximately 6 acres. The setting for a battery facility would be similar to the
setting for substations discussed in Alternative 1, with most suitable sites being commercial
or industrial, impacting less sensitive viewers, but in some cases adjacent to more sensitive
residential areas. The battery containers can be stacked, but for technical reasons, it is
anticipated that they would not be stacked more than two high, so they would not be
prominent visual features. Security lighting would be installed. A 6-acre energy storage
facility in a residential area could create a significant visual impact, but a smaller facility in
an industrial area would be a minor impact.
11.6.4.5 Peak Generation Plant Component
The peak generation plants would be permanently located within or adjacent to existing
substations, and therefore would impact fewer and less sensitive viewers. It is anticipated that
inclusion of the additional generator would require less than 1 acre of expansion at each
substation.
The design of the generators would likely blend with the current infrastructure located at the
existing substations. However, depending on the contrast between the existing substations
and their surrounding uses, the new generator would provide additional contrast and could
increase the visual impact of the substation beyond existing conditions. Expansion of the
substations could also require additional security lighting, but this is not expected to result in
impacts due to light shielding practices. In addition, the generators would introduce a new
source of emissions (primarily a mix of carbon dioxide and water vapor) that may be visible
to viewers periodically (i.e., when the peak generation plants are running).
This component would likely result in minor to moderate impacts on the visual environment
depending on the scale and design of the generators and where they are located. The exact
location of these generators would be determined at the project level.
11.6.5 Alternative 3: New 115 kV Lines and Transformers
Long-term visual impacts associated with Alternative 3 include changes to visual character
through introduction of new electrical infrastructure, partially obstructing views of visual
resources, reducing the aesthetic quality of a viewpoint, and maintenance of clear zones. At
this stage, it is not anticipated that visual resources themselves would be impacted; however,
it is likely that this option would create contrast that would impact a large number of viewers
who, depending on the placement of the line, may be sensitive to the visual change.
11.6.5.1 Permanent Clear Zones
Under Alternative 3, permanent clear zones would be required that could result in removal of
street trees and roadside landscaping (up to 291 acres), and limitations on the height of trees
January 2016 CHAPTER 11 VIEWS AND VISUAL RESOURCES 11-41
PHASE 1 DRAFT EIS
placed under the transmission lines. It is anticipated that Alternative 3 would require a clear
zone that is 30 to 40 feet wide. This could slightly change the visual character of the area.
11.6.5.2 Visual Changes at Substations
Under Alternative 3, three new transformers would be installed, one at each of the following
substations: Sammamish, Lake Tradition, and Talbot Hill. In addition, the Clyde Hill and
Hazelwood substations would need to be expanded to accommodate connections for each of
the new lines. At the Sammamish, Talbot, and Lake Tradition substations, the expansions
would be relatively minor and therefore would have minor to moderate visual impacts,
similar to those described for a substation under Alternative 1.
Expansion of the Clyde Hill substation could impact views because it is surrounded by
residential properties with views of Lake Washington, the Seattle skyline, and the Olympic
Mountain Range (Figure 11-9). However, the properties immediately adjacent to the
substation are not identified by the Assessor as having views (King County, 2012). Whether
or not the expansion of the substation would obscure views would depend on the height of
the structures added, but tall structures other than the transmission lines are not anticipated.
The expansion would take place in a largely residential setting where viewer sensitivity is
likely to be high, and the expansions would be of a scale that moderate visual impacts could
be expected. Overall, minor to significant impacts are anticipated.
11.6.5.3 Increase in Overhead Poles and Lines
Installation of the new transmission lines could have impacts ranging from minor in areas
with existing lines, to significant visual impacts in residential areas where no transmission
line is present. Under Alternative 3, approximately 60 miles of 115 kV single circuit lines
would be constructed. These lines would consist of single, wood poles generally 60 to 75 feet
in height. New 115 kV lines would follow existing utility or road rights-of-way and would
either replace or be co-located with existing transmission and distribution lines, reducing the
likelihood of impacting sensitive viewers.
If new 115 kV lines are co-located with existing lines, poles must be taller than existing lines
with only one circuit on the transmission line. Where lines have to cross areas with existing
or planned multistory buildings, tall poles may be necessary, depending on building setbacks
from the transmission lines. This could result in views being obscured. The transmission lines
would generally be designed with a narrower profile than the 230 kV overhead lines
proposed under Alternative 1.
The number and sensitivity of viewers would vary depending on the location of the new
lines. Viewer sensitivity would likely be higher in residential areas than in most commercial
locations. Residential areas are predominant throughout the Eastside, and even more so in the
areas where Alternative 3 would need to be implemented. In residential areas 60- to 75-foot
transmission lines would be taller and therefore contrast more with the surrounding
structures. Viewer sensitivity would also be high near parks and natural areas. Parks and
homes within 500 feet of the project alignment would be the most likely to have their views
affected by the addition of a 115 kV transmission line. More detailed analysis should be
conducted for the Phase 2 EIS to confirm the distance where impacts are most likely. In most
CHAPTER 11 January 2016 11-42 VIEWS AND VISUAL RESOURCES
PHASE 1 DRAFT EIS
areas of the Eastside, power lines of this type and size are common along major roads.
However, along the approximately 60 miles of new lines that would be constructed under this
alternative, substantial clearing would be required in some areas where there are few tall
overhead lines present. In such areas, the contrast imposed by the new lines and the potential
for the lines to obstruct views would generate the greatest visual impacts from this
alternative.
In highly urbanized portions of the combined study area, the view is dominated by buildings
and other structures. In such areas, there would be a greater number of viewers, but the
contrast between new transmission lines and surrounding areas would be less than in lower
density residential areas. In addition, if the new transmission lines are placed along roadways,
street trees would be replaced with smaller trees that remain below the lines. Although this
would still change the visual character of the roadway, it would not result in the same level of
contrast that a clear zone would create.
11.6.5.4 Light and Glare
As the substations are expanded, additional security lighting would be required, which might
result in minor light impacts.
11.7 WHAT MITIGATION MEASURES ARE AVAILABLE
FOR POTENTIAL IMPACTS TO VIEWS AND VISUAL
RESOURCES?
In areas where new electrical infrastructure is introduced, the following mitigation options
should be considered:
• Choosing routes that are already developed with power lines and where minimal
vegetation clearing is necessary;
• Consulting with Cities and affected residents when locating structures, rights-of-way,
and other disturbed areas to minimize visual impacts;
• Complying with applicable plans and policies within potentially affected
jurisdictions;
• Placing and designing structures to minimize impacts on specific visual resources and
popular public viewpoints;
• Using aesthetically pleasing materials and landscaping to shield electrical equipment
from public view;
• For steel poles, using paint colors that reduce the contrast of the poles with the
surrounding environment;
• Placing portions of the transmission line underground (as in Alternative 1, Option C)
or underwater (as in Alternative 1, Option D) in areas where significant impacts
would occur from overhead lines; and
January 2016 CHAPTER 11 VIEWS AND VISUAL RESOURCES 11-43
PHASE 1 DRAFT EIS
• For 115 kV lines proposed in corridors with existing distribution lines, placing both
transmission and distribution lines on the same poles (referred to as “underbuild”) to
limit additional visual clutter.
11.8 ARE THERE ANY CUMULATIVE IMPACTS TO VIEWS
AND VISUAL RESOURCES AND CAN THEY BE
MITIGATED?
The Eastside is developing rapidly, with widespread construction-related visual impacts
associated with residential, commercial, and industrial projects, as well as regional roadway
and other infrastructure projects. Construction of the Energize Eastside Project would add to
the overall short-term visual impacts associated with construction equipment and activity, but
is not expected to represent a significant cumulative impact because of the overall high level
of construction in the area.
Once construction is complete, the finished project could contribute to cumulative visual
impacts. The region is urbanizing, with accompanying changes to its visual character. New
electrical infrastructure and associated clearing would result in long-term changes to views
and visual resources that would contribute to the trend of changing visual character.
Development of other transmission or distribution lines could contribute to a trend of
increased view obstruction in some neighborhoods. Road development and utility expansion
in the Eastside could result in clearing of vegetation that could contribute to the trend of
reduced vegetation and a more urbanized visual character.
11.9 ARE THERE ANY SIGNIFICANT UNAVOIDABLE
ADVERSE IMPACTS TO VIEWS AND VISUAL
RESOURCES?
Under Alternative 1, potentially significant impacts to visual resources are likely with any
overhead line alignment because of the high number of sensitive viewers and the high degree
of contrast that would be created. Significant impacts would be unavoidable with
development of a new overhead transmission line corridor. If existing corridors are used,
significant impacts may occur, but could be reduced through careful siting or installation of
underground lines.
It may be possible to implement Alternative 2 without significant visual impacts. However,
the energy storage facility could result in significant visual impacts, depending on the scale
and location of the facility, which are not known at this time. Other components, such as
peak generation plants or distributed generation facilities would be small enough in scale that
impacts would be minor to moderate, or they can be screened with vegetation or other means
to avoid significant impacts.
Under Alternative 3, significant impacts to visual resources may be unavoidable. In order to
provide transmission capacity where it is needed, transmission lines could be required in
areas where few overhead lines are present, creating new clear zones and introducing new
electrical infrastructure into the visual environment for a high number of sensitive viewers.
CHAPTER 11 January 2016 11-44 VIEWS AND VISUAL RESOURCES
PHASE 1 DRAFT EIS
Such construction would permanently change the visual environment for surrounding
viewers. However, at this time no specific alignment has been established. If this alternative
is carried forward into the project-level EIS for Energize Eastside, additional analysis will be
provided.
January 2016 CHAPTER 11 VIEWS AND VISUAL RESOURCES 11-45
PHASE 1 DRAFT EIS
CHAPTER 12. RECREATION
12.1 HOW WERE RECREATIONAL RESOURCES IN THE
COMBINED STUDY AREA EVALUATED?
This chapter provides a programmatic analysis of potential
impacts to recreation sites including parks, natural areas,
trails, and amenities as well as informal recreation in the
combined study area (Alternatives 1, 2, and 3 as depicted
on Figure 1-4 in Chapter 1). For the purpose of this study,
informal recreation includes activities that take place
outside of designated recreation sites (e.g., bicycling on a
street). Recreation sites include designated recreation
areas such as parks, natural areas, open spaces, trails, and
playfields. Amenities such as community centers,
playground equipment, and boat launches are included in
this evaluation as they are located within designated
recreation sites.
The EIS Consultant Team collected maps and other
information available from the cities, King County, and
Washington State to describe existing recreational
resources. Plans and policies for each study area
community were reviewed to evaluate goals and priorities
for recreation in the combined study area. Potential impacts to specific recreation sites were
not assessed because this evaluation was conducted at a conceptual level. However, where
specific location information was known, potential impacts to recreation sites were
considered.
12.2 WHAT ARE THE RELEVANT PLANS, POLICIES, AND
REGULATIONS?
The combined study area encompasses several state parks, which are governed by the
policies and regulations set by the Washington State Parks and Recreation Commission. The
combined study area also includes some lands managed by the Washington State Department
of Natural Resources (DNR) for multiple uses including recreation. All other public
recreation sites are governed by King County or one of the cities or towns within the
combined study area. King County and all cities in the combined study area are required to
consider parks and recreation as part of their comprehensive plans (RCW 36.70A.070). Cities
and counties often have a specific plan for parks and recreation (Table 12-1) as well as plans
for individual recreation sites. Jurisdictions develop capital improvement plans in order to
allocate funding to planned projects, such as new parks and renovations. Some communities
have also developed separate pedestrian or bicycle plans.
Recreation Key Findings
For any of the action
alternatives, there could be
significant impacts if use of
recreation facility is
permanently lost and cannot
be replaced. Recreation
facilities will be avoided to the
extent practicable. Where
existing transmission lines are
already located within a
recreation facility (Alternative 1,
Option A) it is more likely that
impacts cannot be avoided.
Recreation facilities are often
established using funds which
restrict their conversion to
another use. These restrictions
would further limit impacts to
recreation facilities.
January 2016 CHAPTER 12 RECREATION 12-1
PHASE 1 DRAFT EIS
Table 12-1. Parks and Recreation Plans for Study Area Communities
Jurisdiction Parks and Recreation Plans
Washington State Strategic Plan 2014-2019: Moving Towards a Healthy and Sustainable
Washington State Parks System (Washington State Parks and
Recreation Commission, 2013)
King County King County Open Space Plan: Parks, Trails, and Natural Areas (2010)
(currently updating)
Beaux Arts Village Draft Town of Beaux Arts Village Comprehensive Plan, Chapter 4 Capital
Facilities (2014)
Bellevue Parks and Open Space System Plan (2010)
Pedestrian and Bicycle Transportation Plan (2009)
Clyde Hill City of Clyde Hill Comprehensive Plan, Parks and Open Space Chapter
(2015)
Hunts Point Draft Town of Hunts Point Comprehensive Plan, Parks and Open Space
Chapter (2014)
Issaquah Parks, Recreation, Trails and Open Space Plan (2009);
Walk and Roll Issaquah (2014)
Kirkland City of Kirkland Parks Recreation and Open Spaces Plan (final review
and adoption scheduled to occur later in 2015)
Medina Medina Parks Long Range Vision and Strategic Planning Document
(2015a) City of Medina Draft Comprehensive Plan, Parks and Open
Spaces Element (2015b)
Newcastle City of Newcastle Comprehensive Plan, Parks, Trails, and Recreation
Element (2013); Non-motorized Transportation Plan (2008)
Redmond Parks, Arts, Recreation, Culture and Conservation Plan (2010) (currently
updating)
Renton Parks, Recreation, and Natural Areas Plan (2011);
Renton Trails and Bicycle Master Plan (2009)
Sammamish City of Sammamish Parks, Recreation and Open Spaces Plan (2012);
Trail, Bikeway and Paths Master Plan (2015)
Yarrow Point Town of Yarrow Point Comprehensive Plan, Parks/Open Space Chapter
(2014)
The City of Bellevue’s comprehensive plan has a policy to avoid placing overhead lines in
greenbelts or open spaces, which are often recreation sites. The Cities of Bellevue, Issaquah,
Newcastle, and Redmond all have similar policies to encourage use of utility corridors for
nonmotorized recreation. The other communities’ plans do not have specific policies
regarding the placement of electric utilities in or near recreation sites, but they generally
discourage the use of recreation sites for non-recreational uses. The enjoyment of recreation
sites can be linked to visual quality and natural resources. For additional discussion of
CHAPTER 12 January 2016 12-2 RECREATION
PHASE 1 DRAFT EIS
Recreational Opportunities
in Study Areas:
Beach with water access
Boat launch with water access
Bicycling
Boating
Gardening
Golf
Hiking/walking/running
Horseback riding
Nature viewing
Off-leash dog areas
Picnicking
Playgrounds
Skateboarding (skate-park)
Sports fields/sports leagues
Swimming
Tennis
policies related to visual quality, see Chapter 11. For discussion of policies related to general
protection of plants and wildlife, see Chapter 6.
Many recreation sites in the combined study area were acquired with federal, state, and local
grants, bonds, or other funding sources. The funding comes with provisions that protect the
land for recreation in perpetuity. The conversion of recreation land purchased with restricted
funds for non-recreation purposes would need to meet site-specific agency requirements. The
City of Bellevue’s comprehensive plan also requires a public review process for the
conversion to non-recreational use of park lands and facilities. Other study area communities
do not include specific language regarding conversion of recreation land.
12.3 WHAT RECREATIONAL RESOURCES ARE IN THE
COMBINED STUDY AREA?
The combined study area contains approximately 265
recreation sites under the jurisdiction of 11 different
communities as well as King County and Washington
State, shown on Figure 12-1. This encompasses
approximately 16,400 acres in recreation sites. The
recreation sites provide a wide range of facilities and
opportunities and range from small neighborhood or
“pocket” parks to natural areas spanning thousands of
acres.
Table 12-2 lists some of the recreation sites in each study
area community. Some of the larger recreation sites are as
follows:
• The Cougar Mountain Regional Wildlands
Park, Squak Mountain State Park, and Tiger
Mountain Natural Resource Conservation Area
cover more than 9,000 acres (some of this area is
outside of the combined study area). The forested
wildlife preserve is owned primarily by King County and Washington State with
smaller adjoining parks owned by other communities. Hiking, biking, and horseback
riding are the primary recreational opportunities (King County, 2015; Washington
State Parks, 2015a; DNR, 2015).
• Marymoor Regional Park is a 640-acre King County Park located where Lake
Sammamish flows into the Sammamish River. It has trails, multiple sports fields, an
off-leash dog area, rock-climbing wall, community gardens, the historic Willowmoor
Farms, and unique features such as a radio-controlled airplane field and velodrome
(bicycle track). It is the location of festivals and events, including a summer concert
series and outdoor movies (King County, 2015).
• Lake Sammamish State Park is a 512-acre park at the south end of Lake
Sammamish. It is primarily a day-use park with a large waterfront and beach area,
January 2016 CHAPTER 12 RECREATION 12-3
PHASE 1 DRAFT EIS
boat access, ball fields, trails, a forested area and a wetland area. There is also a group
camping area for up to 200 people (Washington State Parks, 2015b).
• Bridle Trails State Park is a 482-acre park in the Kirkland area. It is a forested park,
with 28 miles of equestrian/pedestrian trails as well as horse show grounds and arenas
(Washington State Parks, 2015c).
• Mercer Slough Nature Park in Bellevue is a 320-acre preserve that includes a large
wetland, blueberry farm, an environmental education center, walking trails, a canoe
launch, and the historic Winters House (City of Bellevue, 2015).
• Kelsey Creek Park in Bellevue is a 150-acre park with wetlands and forested areas.
It is also the site of a historic farm which has animals and provides farm-themed
tours, classes, and camps (City of Bellevue, 2015).
Along the Cedar River a series of Renton and King County parks together form a major open
space. A key feature is the Cedar River Trail (King County, 2015; City of Renton, 2015).
Along May Creek a series of parks owned by Renton, Newcastle, and King County form
another major open space featuring forested areas and the May Creek Trail (King County,
2015; City of Renton, 2015; City of Newcastle, 2015). Regional trails located at least
partially within the combined study area include the Sammamish River Trail, SR 520 Trail,
Eastside Rail Corridor, Mountains to Sound Trail (I-90), and Lake Washington Trail (Figure
12-1). Designated on-street bicycle lanes and trail corridors cross throughout the combined
study area.
There are 18 city-operated community centers within the combined study area providing
indoor and outdoor recreational activities and programs. Public and private facilities such as
tennis courts, swimming pools, and golf courses add to the activities available. Many public
schools have sports fields or playground equipment available to the public during non-school
hours.
Recreation is not limited to designated areas. Informal recreational activities occur
throughout the combined study area, taking advantage of the natural environment. There are
both formal and informal recreation trails within and across several segments of the existing
PSE and Seattle City Light (SCL) transmission line corridors within the combined study area.
Lake Washington and Lake Sammamish are also important recreational features for
neighboring communities and the region. Bellevue, Hunts Point, Kirkland, Medina, Renton,
and Yarrow Point all have public parks along Lake Washington, most offering water or beach
access for swimming, boating, and fishing. Lake access is a key feature of Lake Sammamish
State Park, whereas at Marymoor Regional Park the shoreline features a nature preserve with
limited public access. In addition, there are multiple private docks with opportunities for lake
access. Only portions of Lake Sammamish and Lake Washington are within the combined
study area.
CHAPTER 12 January 2016 12-4 RECREATION
PHASE 1 DRAFT EIS
Energize Eastside EIS 140548
Figure 12-1
Recreation Sites
SOURCE: King County 2015; ESA 2015; WA Ecology 2014; Bellevue 2015;
Newcastle 2015; Renton 2015; Issaquah 2015; Kirkland 2015; Redmond 2015.
For more info visit www.energizeeastsideeis.org/map-recreation
Lake Washington
Lake
Sammamish
Bellevue
Sammamish
Issaquah
Renton
Newcastle
RedmondKirkland
Beaux Arts
Medina
Clyde
Hill
Hunts
Point
Yarrow
Point
Mercer
Island
Grass Lawn
Com. Park
Bridle Trails
State Park
Marymoor
Park
PSE TrailCross Kirkland
Corridor
Yarrow Bay
Wetlands
Wetherill Nature
Reserve
Medina Park
SR520
Trail
SR520
Trail
Evans Cr.
Preserve
Beaver Lk.
Park
Lk. Sammamish
State Park
Cougar Mountain
Regional Park
Squak Mountain
State Park
West Tiger
Moutain NRCA
Talus
Open Space
May Cr.
Park
Cedar River
Natural Zone
Gene Coulon
Memorial Beach Park
Cedar River
Trail
Coal Cr.
Natural
Area
Lk. Wasghinton
Trail
Mountains
to Sound
Trail Mercer Slough
Nature Area
Kelsey Cr.
Park
Bellevue
Botanical
Gardnes
Tradition Plateau
NRCA
Sammamish
River Trail
Viewpoint
Park
Sunset
Park
Eastside Rail
Corridor
Lakeside
Sammamish
Talbot Hill
Novelty Hill
Lake Tradition
Parks and Natural
Areas
Trails
Existing
Substations
Roadway
Combined Study
Area Boundary
Water bodies
City Limits
U:\GIS\GIS\Projects\14xxxx\D140548_EastsidePSETransmisisonCoor\MXD\Recreation.m xd
0 2
Miles
Note: This map is for reference only. It is not guaranteed that the information is accurate or complete.
Table 12-2. Major Recreation Sites in the Combined Study Area
Jurisdiction Park, Natural Area, or Amenity
Washington State Bridle Trails State Park, Squak Mountain State Park, Lake
Sammamish State Park
King County Cedar River Natural Area, Cougar/Squak/Tiger Mountains parks and
natural areas, May Creek Park and Open Space, Marymoor Regional
Park
Beaux Arts Village Beaux Arts Beach and Boat Docks1
Bellevue Bellevue Botanical Gardens, Coal Creek Natural Area, Kelsey Creek
Park, Lake Hills Greenbelt Park, Lakemont Park and Open Space,
Mercer Slough Nature Park, Wilburton Hill Park
Clyde Hill Clyde Hill City Park
Hunts Point Hunts Point Playfield, DK McDonald Park
Issaquah Talus Open Space, Pickering Barn, Tradition Plateau Natural
Resources Conservation Area
Kirkland Heritage Park, Watershed Park, Kirkland Waterfront (and associated
parks), Yarrow Bay Wetlands
Newcastle Lake Boren and Park, May Creek Park and Open Space
Medina Fairweather Nature Preserve, Medina Park, Overlake Golf and
Country Club
Redmond Grass Lawn Community Park, Idylwood Beach Park
Renton Cedar River Natural Area and adjoining parks, Gene Coulon Memorial
Beach Park, May Creek Park
Sammamish Evans Creek Preserve, Beaver Lake Park
Yarrow Point Wetherill Nature Preserve
1Privately owned by Western Academy of Beaux Arts
Sources: King County, 2015; Bellevue 2015; Newcastle 2015; Renton 2015; Issaquah, 2009; Kirkland 2015;
Redmond, 2010; Washington State Parks, 2015a-c.
12.4 HOW WERE POTENTIAL IMPACTS TO RECREATION
ASSESSED?
Because this first phase is programmatic in nature and the specific locations of energy
facilities have not yet been determined, potential impacts were evaluated conceptually. The
EIS Consultant Team evaluated potential impacts within and adjacent to recreation sites, as
well as impacts to informal recreation that may occur near proposed facilities. The
assessment considers potential indirect effects to recreational facilities from impacts to other
elements of the environment, such as vegetation and aesthetics.
CHAPTER 12 January 2016 12-6 RECREATION
PHASE 1 DRAFT EIS
12.5 WHAT ARE THE LIKELY CONSTRUCTION IMPACTS
RELATED TO RECREATION?
12.5.1 Construction Impacts Considered
Details of how the alternatives would be constructed have not yet been developed; however,
general construction activities with these types of projects are generally understood. Site-
specific impacts will be evaluated in the Phase 2 EIS. However, PSE will avoid recreation
facilities to the extent practicable. Construction of all alternatives would involve clearing for
infrastructure and use of heavy equipment. Alternatives 1 and 3 would also result in
construction of temporary access roads. These impacts would be limited to the construction
period. Permanent impacts that may begin during construction are discussed below under
Operational Impacts. The intensity of potential impacts to formal and informal recreation
would vary based on proximity to recreation sites, scale of construction activities, the time of
year of construction (e.g., during peak summer use), number of users affected, and number of
recreation facilities affected. Significance would also depend on how many recreation
facilities are affected from the construction of the transmission lines.
Minor – If a recreation facility is not usable for a short duration or if construction activities
are noticeable (e.g. noise and decreased visual enjoyment) and cause irritation to users but do
not preclude recreation use, then impacts are considered minor. However, if these types of
minor impacts were to occur at multiple recreation facilities concurrently impacts would be
moderate.
Moderate – If a recreation facility was unusable or access completely blocked outside of
peak use or in a recreation facility or area of a recreation facility that is not frequently used,
then impacts are considered moderate.
Significant – If a major recreation facility is unusable or access is completely blocked during
peak use (e.g. a park is inaccessible during the summer months and many users are affected),
then impacts are considered significant.
If construction impacts at recreation facilities are from noise or to aesthetic impacts, impacts
are as defined in Chapter 9 and Chapter 11.
Construction Within a Recreation Site 12.5.1.1
Impacts to recreation would occur if construction takes place within a recreation site.
Construction activities would reduce the enjoyment of the recreation site, during the
construction period, which would vary depending on the alternative. Portions of a recreation
site could be closed and access limited during construction. Construction trucks around a
recreation site may also disrupt traffic or make parking difficult (see Chapter 14). Noise and
disturbance from construction equipment and trucks could also reduce the enjoyment for park
users (see Chapter 9). Construction activities and noise may disturb or temporarily displace
wildlife, which could decrease user enjoyment. Removal of vegetation would result in a
temporary loss of habitat and subsequently reduce the aesthetic quality of the recreation site
(see Chapter 6 and Chapter 11). Furthermore, construction activities may pose safety risks to
the public, due to the proximity of construction vehicles or activities in areas that are for
January 2016 CHAPTER 12 RECREATION 12-7
PHASE 1 DRAFT EIS
pedestrians or bicycles only. Safety risks would increase if people cross construction barriers
during nonworking hours.
Construction Adjacent to a Recreation Site 12.5.1.2
If construction occurs adjacent to a recreation site, users may be disturbed by noise, truck
traffic, restricted access, dust, and other construction activities. Wildlife may also be deterred
by construction activities and avoid portions of the recreation site close to construction,
which could diminish user enjoyment.
Construction in Rights-of-Way 12.5.1.3
Construction in rights-of-way, sidewalks, bicycle trails, or other corridors used for informal
recreation, could decrease the enjoyment of informal recreation users such as pedestrians and
cyclists. Access may be restricted due to road or sidewalk closures, traffic diversions, and
additional vehicles for construction. This potential impact would be larger where there are
sidewalks or bicycle facilities (e.g., on-street bicycle lanes), especially those that are
connected with the network of trails or paths throughout the Eastside.
12.5.2 No Action Alternative
There would be no impacts to recreation from the No Action Alternative because
construction activities would be limited to maintenance of existing facilities. Maintenance of
facilities located in recreation areas would be limited and short in duration.
12.5.3 Alternative 1: New Substation and 230 kV Transmission Lines
Impacts are described according to the major components associated with Alternative 1. The
substation impacts are described first, followed by transmission line options.
All four options for Alternative 1 would require expansion of an existing substation
(Lakeside) or construction of a new substation (Vernell or Westminster) to accommodate a
new transformer and associated equipment. The Westminster substation would be located
within an existing transmission right-of-way that crosses Viewpoint Park. The Lakeside
substation is located adjacent to Sunset Park. Construction would take up to 18 months.
Construction activities and noise would cause minor and temporary noise and visual
disturbance to park users and informal recreation and potentially decrease enjoyment. Noise
would be above background levels but would likely be within the restrictions for construction
noise (see Chapter 9). Construction activities may decrease the visual enjoyment of the park
by park users, but impacts would be minor (see Chapter 11).
Option A: New Overhead Transmission Lines 12.5.3.1
If new overhead transmission lines were built in new utility corridors or along existing
corridors, they would likely cross recreation sites, be located near recreation sites, and cross
areas used for informal recreation. The corridor would be relatively wide (120 to 150 feet)
and thus may require more clearing than for a 115 kV line (70 to 100 feet). If the corridor is
located along the existing PSE easement it would be widened by up to 50 feet. Construction
activities would be concentrated along a minimum of 18 miles of corridor, and would require
temporary construction access roads. Construction of infrastructure may temporarily reduce
CHAPTER 12 January 2016 12-8 RECREATION
PHASE 1 DRAFT EIS
enjoyment of recreation sites or visitors may avoid these sites during the construction period.
Construction of new overhead transmission lines may take up to 18 months and would be
constructed concurrent with the substation. The location of impacts would change as
construction progressed along the corridor. Construction in any one location would occur in 3
stages, each 1 to 3 days long, over a period of 2 months. Clearing for if new corridors are
used would take longer. In segments where existing transmission line corridors with formal
and informal trails would be used, the trails may be closed for extended periods due to safety
and security concerns. As construction in any one location would not be a long duration,
potential impacts from construction of overhead transmission lines would be considered
minor to moderate depending on the time of year of construction, if a major recreation
facility is affected, and how many recreation facilities are affected concurrently. Types of
impacts could include those described in Section 12.5.1.1.
Option B: Existing Seattle City Light 230 kV Transmission 12.5.3.2
Corridor
The use of existing SCL overhead transmission lines would involve reconstruction of the
existing infrastructure and likely construction of access roads. Some of the existing overhead
transmission lines are located within and adjacent to recreation sites, and thus would impact
visitors to those sites during construction. The existing SCL 230 kV transmission line crosses
North Rose Hill Park, Bridle Trails State Park, Wilburton Hill Park, Coal Creek Natural
Area, May Creek Park, and Cedar River Natural Zone, and is adjacent to others. Construction
activities would be less intense than new overhead lines in new corridors and would involve
substantially less land clearing. Activities would be concentrated along a similar length of
corridor as for the new transmission lines for Alternative 1, Option A. Recreation users may
avoid a recreation site or construction activities may decrease the user experience during
active construction. Recreation areas as well as formal and informal trails along the existing
transmission line would also likely be closed, or partially closed, during construction for
safety and security reasons. These impacts would likely be longer in duration for Option B
(up to 24 months) than Option A because existing SCL lines would need to be completely
rebuilt. The location of impacts would change as construction progresses along the corridor.
Similar to construction of new overhead transmission lines, Option B would cause minor to
moderate construction-related impacts on recreational resources depending on the time of
year of construction, if a major recreation facility is affected, and if construction occurs in
recreation facilities concurrently. Types of impacts could include those described in Section
12.5.1.1. Construction in recreation facilities will be avoided where practicable.
Option C: Underground Transmission Lines 12.5.3.3
Underground transmission lines could be placed in existing PSE 115 kV overhead line rights-
of-way, in public road rights-of-way, or in new rights-of-way. Placing transmission lines
underground usually involves open-cut installation depending on geography and the features
the line may need to cross. Construction could include large equipment, construction
materials, land disturbance, road closures, and noise. If construction were to occur in or
adjacent to recreation sites or areas used for informal recreation, it would negatively affect
recreation user experience, and visitors may avoid recreation sites. The duration of
construction of underground transmission lines would likely be the longest of the three
alternatives, taking up to 28 months. The duration of impacts to individual recreational sites
January 2016 CHAPTER 12 RECREATION 12-9
PHASE 1 DRAFT EIS
would be less (approximately 2 months), because the affected area would change as
construction progressed. Alternative 1, Option C could cause moderate construction-related
impacts to recreation depending on the time of year of construction, if a major recreation
facility is affected, and how many recreation facilities are affected. The types of impacts
could include those described in Section 12.5.1.1. Construction in recreation facilities will be
avoided where practicable.
Option D: Underwater Transmission Lines 12.5.3.4
Construction of the underwater portion of the transmission line could take approximately 8
months. During this time, construction activities would be disruptive to water-based
recreation if access to portions of Lake Washington is restricted during construction. Access
restrictions may include closure of docks or lake access points, or areas of the lake near
construction boats or barges. Public shoreline access along Lake Washington is already
limited and used by a large number of people. A temporary loss of access to docks or other
lake access points could affect water-based recreation experiences and would be considered
minor (if it occurred during the winter months and/or in an area that is seldom used) to
significant (if occurring in a high use area during a peak use period). Impacts are anticipated
to be minor as PSE would likely be able to avoid affecting public recreation access.
Construction activities on the water may also decrease enjoyment for individuals by
negatively affecting scenic water views. See Chapter 11 for more details regarding visual
impacts. The types of impacts could include those described in Section 12.5.1.1.
12.5.4 Alternative 2: Integrated Resource Approach
Construction activities for Alternative 2 would be less than would occur for Alternative 1
because infrastructure would be smaller in scale. However, small-scale construction would be
distributed over a larger portion of the combined study area.
Energy Efficiency Component 12.5.4.1
Energy efficiency includes methods that reduce demand for energy such as weatherization
and efficient lighting, most of which would not affect recreation. Within recreation sites,
impacts would be limited to minor potential improvements to recreation buildings and
exterior lighting. These activities would be limited to small crews and construction vehicles
for a short duration and recreation impacts would be negligible.
Demand Response Component 12.5.4.2
Construction related to demand response would involve installation of meters and/or in-home
monitoring systems and control equipment. Construction disturbance would be minimal and
not result in impacts to recreation.
Distributed Generation Component 12.5.4.3
Distributed generation facilities would be located throughout the combined study area and
their construction would require more activity than for energy efficiency and demand
response components but less than for construction of Alternative 1. Distributed generation
facilities would likely be located on rooftops or inside buildings. It is possible that buildings
within recreation sites could be used to house distributed generation facilities. Impacts from
CHAPTER 12 January 2016 12-10 RECREATION
PHASE 1 DRAFT EIS
construction are anticipated to be short in duration and would not affect extensive areas of
any recreation site. Distributed generation would therefore have minor impacts on recreation
sites.
Energy Storage Component 12.5.4.4
An energy storage system site would be approximately 6 acres and would need to be close to
the center of the Eastside, ideally adjacent to an existing substation (Strategen, 2015). An
energy storage system would not be located within a recreational site but may be located
adjacent to a recreation site or in areas used for informal recreation. If located near a
recreation site or areas used informal recreation, construction activity could reduce the
enjoyment for recreationists. Construction of a battery storage facility would take
approximately 6 months. Impacts would be minor to moderate, depending on how close it is
to a recreation site, time of year of construction, and if access is restricted. Types of impacts
could include those described in Section 12.5.1.2.
Peak Generation Plant Component 12.5.4.5
Three peak generation plants would be located within or adjacent to existing PSE substations.
If located near a recreation site or in areas used for informal recreation, construction activities
may reduce the enjoyment of recreationists. Impacts from construction would be minor to
moderate, depending on the size of the facility and distance from a recreation site. The
substations that would be used have not been determined. However, if either Lakeside or
Lake Tradition is used, recreation sites may be impacted. The Lakeside substation is located
near Sunset Park and the Lake Tradition substation is in the Lake Tradition Natural Resource
Conservation Area (NRCA). Impacts to Sunset Park from construction would be minor as the
park is far enough away from the substation. The Lake Tradition substation is located within
the Lake Tradition NRCA, impacts would be minor to moderate depending on time of year of
construction and how access to the construction site affects access within NRCA. PSE will
avoid restricting access to recreation opportunities to the extent practicable, and thus impacts
to recreation would likely be minor.
12.5.5 Alternative 3: New 115 kV Lines and Transformers
For Alternative 3, new 115 kV transmission lines would need to be constructed in existing or
new rights-of-way. The types of impacts would be similar to those described for Alternative
1, Option A of Alternative 1, except that construction activities would be less intense because
of the use of existing corridors such as roads and narrower cleared areas required (30 to 40
feet). However, the corridor would be much longer (60 miles) and thus distributed over a
larger area. Construction of new 115 kV transmission lines would take 24 to 28 months,
assuming three to four crews installing an average of 3 poles per day. New 115 kV lines
could be located within or adjacent to recreation sites or in areas used for informal recreation.
Because the length of the corridor would be longer with 115 kV transmission lines compared
to 230 kV lines proposed in Alternative 1, there is a high likelihood that more recreation sites
would be affected. Impacts would be minor to moderate depending on how many recreation
facilities are affected from the overall project.
January 2016 CHAPTER 12 RECREATION 12-11
PHASE 1 DRAFT EIS
Five substations would require complete rebuilds or expansion under this option
(Sammamish, Lakeside, Talbot Hill, Clyde Hill, and Hazelwood) and three transformers
would be installed at existing substations (Sammamish, Talbot Hill, Lake Tradition). Some of
these substations are near recreation sites and construction activity may disrupt access for
visitors. The types of impacts could include those described in Section 12.5.1.1. Impacts to
Sunset Park from construction would be minor as the park is far enough away from the
substation. The Lake Tradition substation is located within the Lake Tradition NRCA,
impacts would be minor to moderate depending on time of year of construction and how
access to the construction site affects access within NRCA. PSE will avoid restricting access
to recreation opportunities to the extent practicable, and thus impacts are expected to be
minor.
12.6 HOW COULD OPERATION OF THE PROJECT
AFFECT RECREATION?
12.6.1 Operation Impacts Considered
If new infrastructure is located within recreation sites or in rights-of-way used for informal
recreation, operation of the facilities could reduce user enjoyment of a recreation site through
noise or visual impacts or changes to the resource, such as habitat loss or changes in light and
shade; access to a recreation site (such as for safety or security reasons); or disruption of
informal recreation activities. Infrastructure operating adjacent to a recreation site may affect
enjoyment of the recreation site through noise or visual impacts, or changes to the resource,
such as habitat loss or changes in light and shade. Siting of electrical facilities would consider
potential impacts to recreation sites and avoid these areas if possible. Land purchased with
grant funds for the purpose of recreation often has restrictions that preclude its conversion
into another use. During Phase 2 of the EIS, site-specific restrictions on recreation facilities
will be evaluated. PSE will avoid recreation facilities to the extent practicable.
Minor – If there is a change to a recreation facility but recreation opportunities are still
available, then impacts would be considered minor.
Moderate – If there are permanent changes in a recreation facility that decrease the
enjoyment of recreationist such as noise or visual impacts but the current use of the facility is
not lost, then impacts would be considered moderate. These types of impacts are defined in
Chapters 9 and 11 respectively. Operational impacts to recreation would also be moderate if
the current use of recreation site is permanently lost but could be replaced.
Significant – If the current use of recreation site is permanently lost and could not be
replaced, or if there is conversion of vegetation type (e.g., from forested to low-growing
vegetation) that would substantively change or negatively impact the scenic nature of a
recreation facility, then impacts would be considered significant.
12.6.2 No Action Alternative
There would be no changes to recreation sites from the No Action Alternative because no
new infrastructure would be constructed.
CHAPTER 12 January 2016 12-12 RECREATION
PHASE 1 DRAFT EIS
12.6.3 Alternative 1: New Substation and 230 kV Transmission Lines
Impacts are described according to the major components associated with Alternative 1. The
substation impacts are described first, followed by transmission line options.
All four options for Alternative 1 would require expansion of an existing substation
(Lakeside) or a new substation (Vernell or Westminster) to accommodate a new transformer
and associated equipment. There are no parks near the proposed Vernell substation.
Westminster substation would be located adjacent to an existing transmission line right-of-
way that crosses Viewpoint Park. If the new transformer with substation is sited at
Westminster, there could be some loss of vegetation and changes to the scenic nature of the
area that may negatively impact users of this recreation site. The Lakeside substation is
located adjacent to Sunset Park and 115 kV lines already cross the site, so expansion here
would not substantially change the scenic nature of the area. However, at Westminster,
although 115 kV lines already cross the site, the scenic nature would change and noise from a
new transformer would be an increase over existing conditions; thus impacts from the new
substations would be considered moderate (see Chapters 9 and 11).
Option A: New Overhead Transmission Lines 12.6.3.1
Permanent Infrastructure within a Recreation Site 12.6.3.1.1
If transmission lines are located in recreation sites they could impact recreation users. There
would be permanent loss of vegetation, including trees, because a 230 kV transmission line
would require a cleared corridor of 120 to 150 feet wide (or up to 50 feet of clearing where
the existing PSE easement is used). The corridor would be maintained with low-growing
vegetation and all trees would be removed. Trees outside of the corridor that pose a threat to
the transmission lines would also be removed. Impacts from vegetation loss would be
considered significant if there is a permanent conversion of vegetation type (e.g., from
forested to low-growing vegetation) that would substantively change or negatively impact the
scenic nature of a recreation site. In recreation sites where there is a permanent conversion of
vegetation type, a loss of habitat for animals that may use these areas would result, which
could reduce user enjoyment. In addition, benches, playground equipment, gazebos, or other
structures may be removed underneath the transmission lines. Visitors may avoid a recreation
site if it no longer offers the amenities they previously used at that site. Refer to Chapter 6
and Chapter 11 for further description of potential impacts to plants, animals, and visual
quality.
Infrastructure would also reduce the available space for recreation activities, potentially
reducing visitor enjoyment; however, this impact would only be considered significant if
recreation opportunities could not be replaced. Noise from transmission lines may be audible
in recreation sites, depending on weather conditions, but would be low relative to background
noise, even in a rural setting. Transmission line noise could have a minor impact on
recreation. Refer to Chapter 9 for a discussion of noise impacts.
Permanent Infrastructure Adjacent to a Recreation Site 12.6.3.1.2
Because of the wide corridor needed for 230 kV transmission lines, lines adjacent to a
recreation site could result in loss of vegetation. Poles and wires may be visible from within
January 2016 CHAPTER 12 RECREATION 12-13
PHASE 1 DRAFT EIS
or approaching the recreation site. Changes in vegetation and the visual appearance of
transmission structures could negatively affect the enjoyment of a recreation site by visitors
and result in a moderate impact (see Chapter 11). Noise from transmission lines may be
audible near the recreation site, but would be a minor impact (see Chapter 9).
Permanent Infrastructure in Right-of-Way 12.6.3.1.3
If the transmission lines are located along rights-of-way, sidewalks, bicycle trails, or other
corridors used for informal recreation, these activities may be impacted. Sidewalks or paths
might be narrowed to accommodate towers, making it more difficult to navigate safely;
however, all facilities would comply with applicable permit requirements. Pedestrians or
bicycles may be required to share the road with vehicles where they currently have a
protected path. These changes may decrease the enjoyment of informal recreational activities
or change where these activities take place, and could result in minor to moderate impacts.
Loss or relocation of informal trails on existing transmission line rights-of-way would
generally be a minor impact, because these recreation activities are ancillary to the primary
use of the property.
Option B: Existing Seattle City Light 230 kV Transmission 12.6.3.2
Corridor
For Alternative 1, Option B, impacts to recreation from using the existing SCL transmission
lines would be minor because most of the corridor is already cleared and infrastructure in
place. Towers would be larger than existing, but changes in views and enjoyment of the area
are unlikely to change. There would be minimal changes in recreation sites or to informal
recreation opportunities. For the new transmission line connections that would be needed to
tie the SCL line to PSEs substations, the impacts would be similar to those described for
Option A. A significant impact would occur if new lines were to be located within a
recreation site and the use of the recreation site was lost and recreation opportunities could
not be replaced.
Option C: Underground Transmission Lines 12.6.3.3
Underground transmission lines would not be visible after installation; however, there would
be permanent access roads for maintenance, and hatch access to underground vaults.
Furthermore, trees are not permitted to grow over underground transmission lines and in
some areas there could be a conversion from trees to small shrubs or grass where
underground lines are not placed along roads or in already cleared areas. If constructed in
recreation sites, the roads, vaults, and vegetation removed would result in a change to the
appearance of the recreation site, potentially reducing visitor enjoyment. A significant impact
could occur if these changes were to occur within a recreation site, use of the recreation site
was permanently lost, and recreation opportunities could not be replaced. Impacts would be
negligible if recreation sites and access are avoided. Similar types of impacts would occur if
underground lines are located in areas used for informal recreation.
Option D: Underwater Transmission Lines 12.6.3.4
Underwater transmission lines would not result in permanent visual impacts that would affect
recreation. Underwater transmission lines would require aboveground or underground lines
CHAPTER 12 January 2016 12-14 RECREATION
PHASE 1 DRAFT EIS
on land to connect to a substation. Vaults and permanent access roads would be located on
the shoreline every 1,500 to 2,500 feet to provide access for maintenance and repair of the
underwater cables. There would be a potential impact to recreation if transmission lines,
vaults, or access roads are located in or near recreation sites, or areas that are used for
informal recreation. If these changes were to result in the permanent loss of use of a
recreation facility that cannot be mitigated, there would be a significant impact. However,
recreation sites and recreation access points would be avoided to the extent practicable and
thus impacts would be minor to moderate.
12.6.4 Alternative 2: Integrated Resource Approach
Permanent impacts from operation of Alternative 2 are not expected because infrastructure
would be minimal and likely located on rooftops or inside buildings. It is possible that
buildings in recreation sites could be used for distributed generation facilities, but these
would be located on roofs or inside buildings and no impact on visitor enjoyment of
recreation sites is likely. The exceptions are some fuel cells, an energy storage facility, and
peak generator plants. These large facilities would not be located in a recreation site but may
be near a recreation site or near areas used for informal recreation, so they may have visual
impacts and negatively impact user enjoyment. The substations that would be used for peak
generator plants have not been determined. Permanent impacts from these large facilities
would be minor to moderate and would depend on their proximity to recreation sites. There
would be no permanent loss of recreation facilities from Alternative 2 with the exception of
Lake Tradition NRCA if this substation is chosen for a peak generator plants. A permanent
loss of use of this recreation site that cannot be replaced or mitigated would be significant.
12.6.5 Alternative 3: New 115 kV Lines and Transformers
The types of impacts to recreation from Alternative 3 would be similar to impacts from
Alterative 1. The corridor for a 115 kV transmission line would use existing corridors such as
roads and be narrower than for a 230 kV line, but the new corridor would be longer (60 miles
of new lines). Thus, the potential to cross or be located near recreation sites is greater. If new
115 kV transmission lines are sited in a recreation site and there is a permanent change or
reduction in the use of that site that cannot be replaced or mitigated, the impacts may be
significant.
Five substations would require complete rebuilds or expansion under this option
(Sammamish, Lakeside, Talbot Hill, Clyde Hill, and Hazelwood) and three transformers
would be installed at existing substations (Sammamish, Talbot Hill, Lake Tradition). Once
established, these substations are unlikely to impact recreation. Visitors to recreation sites
may observe a permanent loss of vegetation where the substation is located near a recreation
site, but this impact is not considered to be significant. The Lakeside substation is adjacent to
Sunset Park but expansion of the substation is not anticipated to affect the park. The Lake
Tradition substation is located within Lake Tradition NRCA, but would not be expanded
beyond its existing footprint. Operational impacts to these recreation facilities would be
negligible.
January 2016 CHAPTER 12 RECREATION 12-15
PHASE 1 DRAFT EIS
12.7 WHAT MITIGATION MEASURES ARE AVAILABLE
FOR POTENTIAL IMPACTS TO RECREATION?
12.7.1 Construction Measures
Best management practices would be used to minimize noise, dust, and other disturbances to
visitors to recreation sites during construction, as well as in areas used for informal
recreation. Recreation facilities and access to recreation activities (e.g. water access points)
would be avoided to the extent practicable. Alternative access points to recreation sites and
trail detours would be provided and months in which recreation sites are busier would be
avoided as much as reasonably possible. Recreation sites would be restored after
construction.
12.7.2 Operation Measures
To minimize potential operational impacts to recreation sites, placement of infrastructure
within or adjacent to recreation sites would be avoided to the extent possible. All impacts to
recreational sites would comply with applicable requirements, such as restrictions that protect
recreation land from conversion to other uses (for example, state or federal grant funded
sites). If it is not possible to avoid a recreation site, vegetation screening could be used
outside of any required clear zone. If recreation sites are affected and cannot be restored, they
would be relocated and replaced as required; for example property could be purchased and a
new recreation facility created.
12.8 ARE THERE ANY CUMULATIVE IMPACTS TO
RECREATION AND CAN THEY BE MITIGATED?
As the population of the Eastside grows, there is increased demand for recreation facilities,
while available lands for new facilities within the urbanized areas are being considered for
other uses. This trend will likely continue, resulting in more pressure on recreational
facilities. The Energize Eastside project, when combined with other major construction
projects in the region, could contribute to this trend.
The most likely future action that could alter or affect recreation sites within the Energize
Eastside project area is Sound Transit’s East Link project, which could be constructed during
the same general time frame. The East Link project will impact some parks in Bellevue,
Redmond, and King County (Sound Transit, 2011). In combination with the East Link project
and other projects planned in the project area, the Energize Eastside project could potentially
cause cumulative impacts on recreation if the same recreation sites are affected or if
construction periods overlap. Energize Eastside may avoid direct impacts on recreation sites
by siting facilities outside of designated park or recreation areas. Construction of the East
Link project is anticipated to occur between 2015 and 2021. Construction for the Energize
Eastside Project may occur during this same period; however, construction could be planned
to avoid working in the same areas concurrently. Construction activity throughout the region
could result in potential impacts to parks and other recreation sites. Coordination with
potentially affected cities will help to reduce potential impacts through facility siting, and
would comply with all applicable permitting requirements to mitigate impacts. With
CHAPTER 12 January 2016 12-16 RECREATION
PHASE 1 DRAFT EIS
appropriate mitigation, the cumulative construction and operation effects of the project and
other planned projects are not expected to change long term trends related to the use of
recreation facilities in the project area under any of the alternatives.
12.9 ARE THERE ANY SIGNIFICANT UNAVOIDABLE
ADVERSE IMPACTS TO RECREATION?
Significant impacts could occur under Alternatives 1 and 3 if transmission lines are placed
within a highly used or unique recreation site that substantially alters, limits, or precludes the
use of that site. Depending on the specific corridor selected, some significant impacts may be
unavoidable if design or siting factors limit the ability to locate a transmission lines away
from recreation sites. There could also potentially be significant adverse impacts to recreation
under Alternative 2 if the Lake Tradition substation site is selected for a peak generation
plant and design or siting factors limit the ability to locate the facility away from the Lake
Tradition NRCA.
January 2016 CHAPTER 12 RECREATION 12-17
PHASE 1 DRAFT EIS
CHAPTER 13. HISTORIC AND
CULTURAL RESOURCES
13.1 HOW WERE HISTORIC AND CULTURAL
RESOURCES IN THE COMBINED STUDY AREA
EVALUATED?
This chapter addresses two main types of historic and
cultural resources: (1) aboveground historic properties; and
(2) recorded and potential archaeological resources. The
EIS Consultant Team conducted research to identify
recorded historic and cultural resources located within the
combined study areas (Alternatives 1, 2, and 3 as depicted
on Figure 1-4 in Chapter 1).
For the purposes of this programmatic EIS, specific
geographic locations of proposed construction have not been identified. Research within the
study areas focused on collecting and summarizing data on previously recorded resources,
and it did not include fieldwork or evaluation of recorded resources. For the Phase 2 Draft
EIS, additional detail will be developed on the presence of and potential impacts to historic
resources.
13.1.1 Historic Properties
The analysis of aboveground historic properties focused on buildings or structures currently
listed on a historic register. In some cases, an aboveground historic property also includes a
belowground archaeological component, as with a historic cemetery; these have been
categorized with aboveground resources within this chapter. To be considered historic, a
property (building, structure, or site) generally must meet minimum age requirements.
However, historic properties are not defined solely by their age but also by criteria related to
their historic or cultural importance; this is known as “significance”. Significant historic
properties represent important themes, cultures, or patterns in our past. The significance of a
property may be on the national, state, or local level.
Recorded historic properties that are listed on federal, state, or local historic registers were
identified through a review of records at the Washington State Department of Archaeology
and Historic Preservation (DAHP) and the King County Historic Preservation Program. The
Cities of Issaquah, Kirkland, Newcastle, and Redmond participate in DAHP’s Certified Local
Government program; their historic registers are maintained through an interlocal agreement
with the King County Historic Preservation Program. No municipal historic registers exist for
the Cities of Bellevue, Clyde Hill, Hunts Point, Medina, Mercer Island, Renton, Sammamish,
or Yarrow Point.
Historic and Cultural
Resources Key Findings
There are no known significant
impacts to historic and cultural
resources that cannot be
avoided through appropriate
mitigation measures.
January 2016 CHAPTER 13 HISTORIC AND CULTURAL RESOURCES 13-1
PHASE 1 DRAFT EIS
Other information reviewed included local histories, historic property inventories, King
County and City Landmarks List, the National Register of Historic Places (NRHP),
Washington Heritage Register (WHR) properties, and historic maps. Examined documents
were acquired from DAHP, online, and within Environmental Science Associates’ research
library.
13.1.2 Archaeological Resources
Locations of recorded archaeological sites were obtained from DAHP during a records search
conducted in July 2015. The team also reviewed DAHP’s statewide archaeological predictive
model to analyze the potential for additional, unrecorded buried resources to be located
within the combined study area (DAHP, 2010).
Other information reviewed included archaeological survey reports and site forms and
ethnographic studies. Documents were examined at DAHP, the University of Washington
Libraries, online, and Environmental Science Associates’ research library.
13.2 WHAT ARE THE RELEVANT PLANS, POLICIES, AND
REGULATIONS?
There are several Washington State laws protecting archaeological resources that apply to
this project: Archaeological Sites and Resources (Chapter 27.53 RCW), Indian Graves and
Records (Chapter 24.44 RCW), Abandoned and Historic Cemeteries and Historic Graves
(Chapter 68.60 RCW), and Human Remains (Chapter 68.50 RCW).
Because this review is being conducted under SEPA, consideration of impacts to cultural
resources by the project is required. Cultural resources are defined in SEPA as buildings,
structures, or sites that are on or near the project area, over 45 years old, and listed or eligible
for listing in national, state, or local historic preservation registers (WAC 197-11-960).
Applicable national, state, and local historic preservation registers reviewed for this project
include the following (for more information, see Appendix J):
• National Register of Historic Places (NRHP), as established through the National
Historic Preservation Act (NHPA);
• Washington Heritage Register (WHR) and Washington Heritage Barn Register
(WHBR); and
• King County Landmarks (including Cities of Issaquah, Kirkland, Newcastle, and
Redmond).
The historical significance required for listing on each register varies based on criteria
including association with significant events, significant people, distinctive architectural or
artistic value, or ability to inform our past. Properties can possess significance on multiple
levels and thus be listed on more than one register. For example, there are 16 barns
throughout the state that are listed on the NRHP, WHR, and WHBR.
CHAPTER 13 January 2016 13-2 HISTORIC AND CULTURAL RESOURCES
PHASE 1 DRAFT EIS
The age at which a property can be considered “historic” varies by register (Table 13-1). For
the NRHP, WHR, and WHBR, the standard threshold is 50 years, while for King County
Landmarks the standard threshold is 40 years. A property that has achieved exceptional
significance within a shorter timespan can also be considered eligible for the NRHP and King
County Landmarks, although this is rare. Changes to designated King County Landmarks are
managed through the Certificate of Appropriateness (COA) process (King County, 2015b).
The COA process typically involves multiple meetings and includes an appeals process.
Table 13-1. Historic Registers Applicable to this Project
State / Local Preservation
Register
Standard Age
Threshold Managing Agency
WHR 50 years DAHP
WHBR 50 years DAHP
King County Landmarks 40 years King County
WHR = Washington Heritage Register; WHBR = Washington Heritage Barn Register; DAHP= Department of
Archaeology and Historic Preservation
This project is not subject to compliance with federal cultural resources regulations because
there is no federal funding, federal permits, or federal lands involved. However, the state and
local preservation regulations under SEPA refer to NRHP eligibility; therefore, familiarity
with the eligibility criteria is helpful. In brief, a resource can be eligible for listing on the
NRHP if it has integrity of location, design, setting, materials, workmanship, and feeling and
is associated with significant events, significant people, embodies distinctive architectural
characteristics, or has the potential to yield important information about history or prehistory.
13.3 WHAT HISTORIC AND CULTURAL RESOURCES ARE
PRESENT IN THE COMBINED STUDY AREA?
13.3.1 Precontact Period
The Precontact cultural chronology of the Pacific
Northwest and Puget Sound extending from the Late
Pleistocene era to the Postcontact Period has been studied
and interpreted in several publications (e.g., Ames and
Maschner, 1999; Blukis Onat et al., 2001; Kidd, 1964;
Matson and Coupland, 1995; Nelson, 1990). The various
chronologies generally agree on broad patterns in culture
but may differ regarding the timing and significance of
changes in specific aspects of culture, such as subsistence,
technology, and social organization. The following
overview of Precontact sequences draws broadly on the
various chronologies, but follows Ames and Maschner
(1999) by recognizing five time periods: Paleoindian
What does “Precontact”
Mean?
Precontact archaeological
sites date prior to the point of
contact between European-
American peoples (including
explorers, fur traders, and
military personnel) with Native
American peoples. In King
County, the Precontact
period is considered to have
ended with the arrival of the
Denny Party in 1851.
January 2016 CHAPTER 13 HISTORIC AND CULTURAL RESOURCES 13-3
PHASE 1 DRAFT EIS
What does “Postcontact” or
“Historic” Mean?
Postcontact or historic
archaeological sites date to
after the point of contact
between European-American
peoples (including explorers,
fur traders, and military
personnel) with Native
American peoples. In King
County, the Postcontact or
historic period is generally
considered to have started
with the arrival of the Denny
Party in 1851.
(before 12,500 years ago); Archaic (12,500 to 6,400 years ago); Early Pacific (6,400 to 3,800
years ago); Middle Pacific (3,800 to 1,800/1,500 years ago); and Late Pacific (1,800/1,500
years ago to AD 1851). Information about the time periods is summarized in Table 13-2.
Table 13-2. Precontact Time Periods
Time
Period
Approximate
Date Range Characteristics
Associated Recorded
Archaeological
Resources in Study
Areas
Paleoindian Before 12,500
years ago
Often referred to as Clovis culture
and located in the uplands;
represented by projectile points
(Ames and Maschner, 1999:65)
Yes (45-KI-839*)
Archaic 12,500 to
6,400 years
ago
Often referred to as Olcott culture
and located in riverine and lake
settings; represented by cobble
tools and lanceolate projectile
points
Yes (45-KI-1227)
Early
Pacific
6,400 to 3,800
years ago
Located in marine and estuary
settings; represented by large
shell middens and decorative
artifacts such as labrets and
bracelets
None known
Middle
Pacific
3,800 to
1,800/1,500
years ago
Represented by large plank
houses, increase in decorative
items, woodworking tools (adzes,
mauls, wedges)
None known, but likely
present
Late
Pacific
1,800/1,500
years ago to
AD 1851
Represented by seasonal camps
associated with resource
procurement and increased
variability in burial methods
None known, but likely
present
*Smithsonian Archaeological Site number format
13.3.2 Postcontact or Historic Period
Early nonnative explorations in Puget Sound took place in
1792 and 1841, though the first nonnative settlers did not
arrive in Elliott Bay until 1851. After passage of the 1850
Donation Land Act of Oregon, settlers began to claim
homestead lands throughout the Puget Sound region,
including lands within the combined study area. Early
settlements were located in easily accessible areas, such as
boat landings on lakeshores, along trails, wagon roads, and
railroads, or at river mouths (U.S. Coast and Geodetic
Survey, 1902a, 1902b, 1902c; USGS, 1895, 1897a, 1897b,
1898, 1900; U.S. Surveyor General, 1864a, 1864b, 1864c,
1870, 1872, 1874).
CHAPTER 13 January 2016 13-4 HISTORIC AND CULTURAL RESOURCES
PHASE 1 DRAFT EIS
The combined study area is located within the traditional territory of the Duwamish and
Snoqualmie people (Suttles and Lane, 1990). During the Postcontact period, these groups had
villages along the shores of Lake Washington and Lake Sammamish and on the banks of the
former Black, Cedar, and Sammamish Rivers (Haeberlin and Gunther, 1930; Smith, 1940;
Spier, 1936; Swanton, 1979). During the winter, groups lived in permanent villages of cedar
plank houses and practiced local hunting and fishing while sharing supplies of preserved food
such as smoked fish and shellfish and dried berries. During the rest of the year, groups moved
seasonally to known gathering locations for berries, roots, bulbs, sprouts, nuts, marine and
freshwater fish, shellfish, land game, and waterfowl. These resources were used for winter
supplies and trade, as well as immediate consumption. Salmon was a dietary staple. Other
important resources included plants for medicinal or other uses; western red cedar for rope,
baskets, and numerous household items; and reeds such as tules and cattails for mat making.
The range in landforms would have provided a variety of gathering opportunities for these
types of items and subsistence needs. Traditional burial practices at the time of European-
American contact included tree burials, whereby the deceased was placed in a canoe and then
raised into a tree or on a frame.
There are over 40 known (recorded) Native American names for places within the combined
study area (Hilbert et al., 2001; Miller, 2014; Waterman, 1922). The majority of these are
concentrated along the shores of Lake Sammamish, Lake Washington, Sammamish River,
Issaquah Creek, Bear Creek, Evans Creek, Cedar River, and the former Black River. Of these
40 places, 25 were recorded on the eastern shoreline of Lake Washington between today’s
Kirkland and Renton, including one on the southern tip of Mercer Island. Other
concentrations are located along the shores of Lake Sammamish, the lower reach of the
Sammamish River, and within the Issaquah valley. Further, numerous place names were
recorded in the vicinity of today’s Renton, which was once the confluence of the Black and
Cedar Rivers. The place names range between villages, resource procurement sites,
geographical features, and locations with oral tradition and spiritual associations.
The U.S. Government entered into treaties with many of the local Native American groups
during the 1850s. Although a signatory of the Treaty of Point Elliott in 1855, the Duwamish
were not given their own reservation lands. The Duwamish continue to reside in and around
Seattle and are petitioning the U.S. Government for federal recognition. The Snoqualmie
were awarded federal recognition by the U.S. Government in 1999.
Industrial Development 13.3.2.1
Industries within the combined study area during the 19th century were primarily logging and
coal mining. By 1897 most of the study area between Lake Washington and Lake
Sammamish was logged (USGS, 1897a, 1897b). Major industries during the 20th century
included agriculture and dairying with smaller operations such as the American Pacific
Whaling’s headquarters on Lake Washington during the 1920s and 1930s and the Lake
Washington Shipyards during the 1940s. A population boom after World War II contributed
to the rise in single-family residences throughout the combined study area (Bryant, 2000;
Eastside Heritage Center, 2006; Fish, 1981; Gellatly, 1977; Hardy, 2006; McDonald, 2000;
Way, 1989).
January 2016 CHAPTER 13 HISTORIC AND CULTURAL RESOURCES 13-5
PHASE 1 DRAFT EIS
Several major construction events during the 20th century disturbed the ground and modified
shorelines, likely reducing the potential for intact archaeological resources within some
portions of the combined study area. First, the construction of the Hiram M. Chittenden
Locks and Lake Washington Ship Canal between 1911 and 1916 resulted in an approximate
9-foot drop in Lake Washington shorelines, exposing former lakebed and eliminating the
flow of the Black River (Bryant, 2000). The resulting drop means that any archaeological
sites along the original shorelines have likely been subject to development. Secondly,
construction of a network of highways required major ground disturbance. Interstate 90,
which includes the Lacey V. Murrow Memorial Bridge, first opened in 1940, and Interstate
405 opened in 1957. State Route 520, including the Evergreen Point Floating Bridge, opened
in 1963.
13.3.3 Previous Archaeological Work
More than 200 archaeological reports have been previously prepared within the combined
study area, but these surveys cover less than 25 percent of the area (DAHP, 2015). The
reports were prepared by a range of project proponents for a variety of project types,
including construction of highways and roads, mass transit, conversion of former railroads to
pedestrian trails, and installation of various utilities. The reports vary from simple literature
reviews to summaries of differing levels of fieldwork, including surveys to identify historic
properties and archaeological resources up to archaeological site investigations at identified
sites. Reports have been conducted at a variety of jurisdictional levels.
As of July 2015, previous archaeological reports have identified a combined total of 94
archaeological sites in the combined study area. The locations of these sites are protected
from public disclosure under state law (RCW 42.56.300) and therefore are not mapped for
this study (see Appendix H for a list). Of the recorded sites, 43 are located within all three
study areas. The 94 recorded archaeological sites include 42 from the Precontact period and
52 from the historic period. The 42 recorded Precontact sites include permanent and
temporary camps, cemeteries, culturally modified trees, and fishing, hunting, and resource
gathering sites. There are 14 isolated artifacts (10 Precontact and 4 historic); isolated artifacts
are typically not eligible for inclusion on historic registers. There are 15 recorded cemeteries;
14 are historic and thus treated here as aboveground historic properties, while 1 cemetery
(45-KI-51) dates to the Precontact era and thus is treated here as an archaeological site. There
are 6 submerged historic period resources, all of which are located within the Alternative 1
study area; these include sunken vessels, aircraft, railroad cars, and docks. For a summary
comparison of recorded resources within each study area, see Table 13-3.
Table 13-3. Comparison of Recorded Archaeological Resources by Alternative
Alternative Study
Area
Total Number of
Recorded Sites Precontact Historic
Alternative 1 52 21 31
Alternative 2 43 21 22
Alternative 3 88 42 46
Source: DAHP, 2015
CHAPTER 13 January 2016 13-6 HISTORIC AND CULTURAL RESOURCES
PHASE 1 DRAFT EIS
Precontact Archaeological Sites 13.3.3.1
Archaeological evidence indicates that Native Americans have lived within the region and
along the shorelines of Lake Sammamish for more than 12,000 years (45-KI-839, the Bear
Creek Site). DAHP’s statewide predictive model classifies the combined study area as
ranging from low to very high risk for containing Precontact archaeological sites (Figure
13-1). The statewide predictive model is a tool used by archaeologists and planners to
evaluate potential archaeological risks on a broad scale. The model was developed to
statistically evaluate multiple environmental factors (i.e., elevation, slope percent, aspect,
distance to water, soils, and landforms) in order to predict where archaeological resources
might be found (Kauhi, 2013). It is not a substitute for conducting site-specific subsurface
investigations, which may be required for project-level review.
Historic Period Archaeological Sites 13.3.3.2
As of July 2015, there were 41 recorded historic archaeological sites located within all three
of the study areas (DAHP, 2015). Generally, these sites date to the late 1800s and mid-1900s.
Historic sites typically include infrastructure such as railroads, roads, bridges, docks, and
piers; ruins of commercial factories, water conveyance and reservoirs, lumber mills, and
mines; submerged vessels, aircraft, and railroad cars; and residential farmsteads, houses, and
scatters of historic debris. Of these historic archaeological sites, none are listed on the NRHP;
30 sites are classified as potentially eligible and 11 sites have been determined not eligible
for listing on the NRHP. One is listed on the Washington Heritage Register: the Renton Coal
Mine (45-KI-211).
13.3.4 Aboveground Historic Register Listed Properties
As of July 2015, there were a total of 69 structures or buildings listed on historic registers
within the combined study area: 55 are aboveground historic structures of buildings and 14
are recorded historic period cemeteries (Appendix I) (DAHP, 2015; King County Historic
Preservation Program, 2015b). Aboveground historic properties are shown on Figure 13-1.
For a comparison of historic properties by alternative, see Table 13-4. The listed properties
date from 1880 to c. 1938 and are either listed on the NRHP, WHR, WHBR, or are
designated King County Landmarks. Some properties are listed on multiple registers. All
properties listed on the NRHP are automatically also listed on the WHR.
Table 13-4. Comparison of Historic Register Listed Properties by Alternative
Source: DAHP, 2015; King County Historic Preservation Program, 2015b
Location Historic Register
Listed Properties
Recorded Historic
Period Cemeteries Total
Alternative 1 37 8 45
Alternative 2 39 8 47
Alternative 3 55 14 69
January 2016 CHAPTER 13 HISTORIC AND CULTURAL RESOURCES 13-7
PHASE 1 DRAFT EIS
Two designated King County Landmarks have also been determined eligible for listing on
the NRHP: the Justice William White House (45-KI-190) and the Jacob and Emma Reard
House (45-KI-659). There are 19 properties listed on both the NRHP and WHR; 7 properties
are only listed on the WHR, while 1 property is listed on the WHR and is also a designated
King County Landmark (Newcastle Cemetery, 45-KI-141). There are 30 designated King
County Landmarks, 9 of which are also listed on the NRHP and WHR. Finally, there are 6
WHBR properties.
Historic period cemeteries are recorded in all three alternative study areas. Cemeteries are
protected under state law (Abandoned and Historic Cemeteries and Historic Graves, Chapter
68.60 RCW).
CHAPTER 13 January 2016 13-8 HISTORIC AND CULTURAL RESOURCES
PHASE 1 DRAFT EIS
Energize Eastside EIS 140548
Figure 13-1
Historic Registered Properties
(Refer to Appendix G)
SOURCE: King County 2015; ESA 2015; WA Ecology 2014.
Lake Washington
Lake
Sammamish
Bellevue Sammamish
Issaquah
Renton
Newcastle
Redmond
Kirkland
Beaux Arts
Medina
Clyde
Hill
Hunts
Point
Yarrow
Point
3,4,5,6,7,9,10,11,12
15,16,17,18,19,21,22
Mercer
Island 41
4547
23
1
8
24
14 13
54
20
26
52
43
46
42
35
34
2728
33
29
51
53
37
25
48
39
2
40
49
38
50
31
32
36
30
44
Lakeside
Novelty
Hill
Lake
Tradition
Sammamish
Talbot
Hill
Historic Registered
Properties
Existing
Substations
Roadway
Combined Study
Area Boundary
Water bodies
City Limits
Unincorporated
King County
U:\GIS\GIS\Projects\14xxxx\D140548_EastsidePSETransmisisonCoor\MXD\HistoricRegistredProperties.mxd
0 2
Miles
Note: This map is for reference only. It is not guaranteed that the information is accurate or complete.
13.4 HOW WERE POTENTIAL IMPACTS TO HISTORIC
AND CULTURAL RESOURCES ASSESSED?
It is not possible to identify likely construction impacts to specific historic properties and
archaeological resources because the locations of proposed construction areas in relation to
documented and probable historic properties and archaeological resources are not yet known.
Any ground disturbance has the potential to impact belowground archaeological resources, if
present, including recorded and unrecorded archaeological resources. Any construction
impacts to intact belowground archaeological resources would be irreversible and permanent,
and considered a significant adverse impact. No impacts to belowground archaeological
resources would be minor or moderate, as any disturbance to the depositional integrity (i.e.,
context) of buried archaeological resources is irreversible.
For aboveground historic resources, potential impacts may range from minor to significant,
and have been assessed here depending on their potential permanence.
Minor – Temporary impacts and potential minor impacts from increased vibration, increased
dust, and alterations to a historic resource that do not impact its ability to convey its historical
significance.
Moderate – Those impacts which are reversible or can be mitigated through design choices.
Potential moderate impacts include alterations to a resource’s architectural elements (i.e.,
window replacement, insulation or cladding modifications, and rooftop additions). Moderate
impacts have the potential to diminish the ability of the property to convey its historical
significance, if not done in a style that is architecturally sympathetic to the property’s
significant historical characteristics.
Significant – Permanent impacts to the resource. Construction vibration may cause moderate
to significant impacts, depending on the proximity to and structural stability of potential
nearby historic resources. Vibration from pile driving, for example, has the potential for
cumulative significant impacts to the structural integrity of historic buildings, particularly
those constructed of brick. Impacts to a building’s structural integrity may limit its ability to
convey its historical significance, and would be considered a significant impact.
13.5 WHAT ARE THE LIKELY CONSTRUCTION IMPACTS
RELATED TO HISTORIC AND CULTURAL
RESOURCES?
13.5.1 Construction Impacts Considered
All of the action alternatives propose some measure of ground disturbance. Any ground
disturbance has the potential to impact archaeological resources. Impacts could occur from
trenching, dredging, clearing and grading, excavation, pile driving, and compression from
driving construction equipment over a resource, or staging construction material or
equipment over a belowground resource. While over 200 archaeological reports have been
CHAPTER 13 January 2016 13-10 HISTORIC AND CULTURAL RESOURCES
PHASE 1 DRAFT EIS
written for projects in the combined study area, these studies cover limited areas around their
associated projects. Much of the combined study area for the Energize Eastside Project has
not undergone systematic testing for archaeological resources. Based on the high number of
recorded archaeological resources throughout the combined study area, as well as review of
the DAHP Statewide Predictive Model, Precontact use, and Postcontact history, all study
areas contain high-probability locations for encountering archaeological resources.
To continue to meet PSE’s conservation goals under any alternative, customers would
voluntarily continue to implement energy efficient improvements. Expected types of
conservation include energy efficiency (weatherization, efficient lighting, etc.), fuel
conversion (from electric to gas), distributed generation (customer generated heat and power,
solar, wind, etc.), distribution efficiency, and demand response. All of these have the
potential to change the appearance of historic resources, such as through window
replacements, adding rooftop equipment, and other building modifications.
13.5.2 No Action Alternative
Under the No Action Alternative, no new construction would occur. This alternative would
consist primarily of maintenance of existing facilities and infrastructure.
The No Action Alternative includes implementation of energy efficiency conservation
measures (weatherization, efficient lighting) and distributed generation (solar panels, wind
turbines, or rooftop generators) that may result in minor to moderate impacts to aboveground
historic properties and archaeological resources. No ground disturbance is expected under the
No Action Alternative, and therefore no impacts to archaeological resources are anticipated.
13.5.3 Alternative 1: New Substation and 230 kV Transmission Lines
Impacts are described according to the major components associated with Alternative 1. The
proposed new substation and installation of a new transformer is discussed first, followed by
descriptions of the transmission line options.
Alternative 1 proposes construction of a new substation and installation of a new transformer
at either the existing Lakeside substation, or at either of the possible new substations sites at
Vernell and Westminster. This would require ground disturbance for foundations for the
transformer and associated switchgear, drainage, and other underground components.
Construction of a new substation at Vernell or Westminster would require ground disturbance
for foundations.
The land surrounding the proposed Westminster substation site is classified in the statewide
predictive model as having a low to moderately low risk for Precontact archaeological
resources, while the land surrounding the proposed Vernell substation site is classified as
having moderately low to moderate risk (see Figure 13-2). The existing Lakeside substation
is classified as high and very high risk for Precontact archaeological resources (see
Figure 13-2).
January 2016 CHAPTER 13 HISTORIC AND CULTURAL RESOURCES 13-11
PHASE 1 DRAFT EIS
Energize Eastside EIS 140548
Figure 13-2
Statewide Predictive Model
for Archaeological Risk
SOURCE: King County 2015; ESA 2015; WA Ecology 2014;
DAHP 2015.
Lake Washington
Lake
Sammamish
Bellevue
Sammamish
Issaquah
Renton
Newcastle
Redmond
Kirkland
Beaux Arts
Medina
Clyde
Hill
Hunts
Point
Yarrow
Point
Mercer
Island
Lakeside
Sammamish
Talbot Hill
Novelty Hill
Lake Tradition
Existing Substation
Roadway
Combined Study
Area Boundary
Water bodies
City Limits
U:\GIS\GIS\Projects\14xxxx\D140548_EastsidePSETransmisisonCoor\MXD\CulturalPredictiveModel.mxd
0 2
Miles
Archaeological Risk
Very High Risk
High Risk
Moderate Risk
Moderately Low Risk
Low Risk
Note: This map is for reference only. It is not guaranteed that the information is accurate or complete.
A review of Assessor data indicates that the Vernell location is surrounded by several
structures built in the 1950s and 1960s, while the Westminster location is bordered by
structures built in the 1970s and 1980s. Adjacent to the Lakeside location are buildings
constructed in the 1960s and later. Buildings or structures 40 years or older at the time of
potential impacts would qualify for consideration as a potential King County Landmark
based solely on the age criterion. In addition, any building or structure 50 years or older at
the time of potential impacts would qualify for consideration regarding its potential eligibility
for the National Register of Historic Places, the Washington Heritage Register, and the
Washington Heritage Barn Register. Therefore, the structures adjacent to the Vernell location
would qualify for consideration as potential historic properties, based solely on their age. For
the structures adjacent to the Westminster and Lakeside locations, the date of potential
impacts will determine if these structures meet the minimum age requirement for
consideration to a historic register (for example, if construction were to start in 2020, then
those built in and before 1980 would need to be evaluated, as they would be 40 years or older
in age at the time of potential impact).
Alternative 1 also includes new 230 kV transmission lines between the new substation and
existing Sammamish substation and Talbot Hill substation, which could be overhead,
underground, or submerged in Lake Washington. Overhead lines would have the least area of
ground disturbance per mile of transmission line, requiring excavations only for pole
footings. Underground lines would require excavation for the entire length of the alignment
or portion of the alignment that is placed underground. The area of disturbance would be
proportional to the length of transmission line installed underground.
The Alternative 1 study area contains the fewest recorded historic properties (37) and 52
recorded archaeological resources, which is the second highest of the three study areas.
Existing surveys provide coverage of about 15 percent of the study area for Alternative 1,
which is the middle amount of all the alternatives.
Option A: New Overhead Transmission Lines 13.5.3.1
A minimum of 18 miles of new overhead transmission lines may be constructed wholly or
partially within existing utility easements and partially within new locations currently not
dedicated to utility operations. Depending on the location of the new transmission lines, there
may be significant impacts to archaeological resources, if present, during installation of the
transmission line poles. This is because any disturbance to the depositional integrity of
archaeological resources is irreversible.
The transmission lines may pass near historic properties that meet the minimum age
qualifications for consideration to be listed on federal, state, and local historic registers.
Construction of new lines may involve impacts from noise and vibration; however, these
impacts are considered minor. Therefore, no adverse effects from noise or vibration are
expected on historic structures, where present.
January 2016 CHAPTER 13 HISTORIC AND CULTURAL RESOURCES 13-13
PHASE 1 DRAFT EIS
Option B: Existing Seattle City Light 230 kV Transmission 13.5.3.2
Corridor
Use of existing Seattle City Light lines would necessitate replacing most of the existing
structures and conductors. This may involve building a replacement line adjacent to the
existing line and placing the new line in service prior to removing the existing structures.
This would result in ground disturbance and the potential for minor to significant impacts to
archaeological resources, if present. Noise and vibration resulting from construction may
impact historic structures, if present, but these impacts are considered minor.
Option C: Underground Transmission Lines 13.5.3.3
The installation of underground transmission lines wholly or partially within existing utility
easements and partially within new locations currently not dedicated to utility operations
would cause ground disturbance and the potential for minor to significant impacts to
archaeological resources, if present. Noise and vibration resulting from construction may
impact historic structures, if present, and these impacts range from minor to moderate,
depending on the historic structure.
Option D: Underwater Transmission Lines 13.5.3.4
Alternative 1 is the only alternative to propose in-water work along the eastern shoreline of
Lake Washington. There are six known submerged archaeological resources within these
portions of Lake Washington: two sunken vessels, one aircraft, a grouping of derailed coal
cars, and two former dock complexes.
Underwater transmission line could be installed within 1,000 feet of the eastern shoreline of
Lake Washington from Kirkland to Renton, including within the entire channel along Mercer
Island. Underwater transmission line would be either buried 3 to 5 feet below the lake bottom
or laid directly on the lake bottom. Installation methods would involve dredging, open-cut
trenching, and sheet piling. At least three shoreline landing points would be needed, and up to
six vaults would be constructed at each landing point. Constructing the vaults and burying
underwater transmission line would require ground disturbing excavation. Shorelines are
generally higher probability areas for encountering buried archaeological resources.
Construction methods proposed by Alternative 1, Option D would result in ground
disturbance and therefore have the potential for significant impacts to archaeological
resources, if present. Noise and vibration resulting from construction may impact historic
structures, if present, but these impacts are considered minor.
For the underwater portion of the line, the lack of information for Lake Washington increases
the likelihood that a cultural resources survey would need to be completed. Although several
underwater archaeological resources have been identified in Lake Washington, little of Lake
Washington has undergone underwater survey. Based on the results of the survey, additional
study to determine impacts to archaeological resources may be required. If a submerged
archaeological resource is identified during construction, redesign may be possible to avoid
or minimize disturbance to the resource. If there is no redesign option, the submerged
archaeological resource may need to be recorded and removed. Removal would cause a
significant impact.
CHAPTER 13 January 2016 13-14 HISTORIC AND CULTURAL RESOURCES
PHASE 1 DRAFT EIS
There are 8 recorded historic period cemeteries within the Alternative 1 study area. It is
assumed that no construction would occur within cemetery boundaries, but there may be
noise and dust impacts to those cemeteries. These impacts are considered minor and
temporary.
13.5.4 Alternative 2: Integrated Resource Approach
The components being considered under Alternative 2 have the potential for minor to
significant impacts to archaeological resources, if present, depending on the proposed
locations. If the historic properties are King County Landmarks, a Certificate of
Appropriateness (COA) may be necessary depending on the terms of the designating
ordinance.
The Alternative 2 study area contains 39 historic register properties (the second highest
amount of the three study areas) and 43 recorded archaeological resources (the least of the
three study areas). Existing surveys provide coverage of about 25 percent of the study area,
which is the highest amount of all the alternatives. The Alternative 2 study area includes the
eastern shoreline of Lake Sammamish. There are many recorded archaeological resources
along these shorelines. Alternative 2 contains the same 8 recorded historic period cemeteries
as Alternative 1 and impacts would be the same.
Energy Efficiency Component 13.5.4.1
The types of potential impacts from energy efficiency efforts may include modifications to
existing buildings (weatherization, efficient lighting). Weatherization could include
replacement of original windows which has the potential to diminish a building or structure’s
integrity of design, materials, workmanship, and feeling, if the replacement windows are not
in-kind with their original architectural character, thus impacting the property’s potential for
conveying its historical significance (Myers, 1981). Any modifications that are permanent
have the potential to impact a property’s ability to convey its historical significance, which
would be significant impact, as described in Section 13.4. No impacts are anticipated to
potential archaeological resources under this component. Continued implementation of
existing energy efficient improvements may result in minor to significant impacts to historic
properties and archaeological resources.
Demand Response Component 13.5.4.2
Few impacts to historic properties and archaeological resources are anticipated from this
component. No impacts are expected to occur to archaeological resources, if present. Meter
installation may contribute minor visual impacts to historic properties, if present.
Distributed Generation Component 13.5.4.3
Ground disturbance could result from the installation of gas turbines, anaerobic digesters,
reciprocating engines, microturbines, and fuel cells. Construction of these facilities would
range from rooftop installations to larger facilities requiring up to 1 acre; larger facilities
would require ground disturbing clearing and grading. Depending on the location of these
larger facilities, there may be significant impacts to archaeological resources, if present.
January 2016 CHAPTER 13 HISTORIC AND CULTURAL RESOURCES 13-15
PHASE 1 DRAFT EIS
Noise and vibration resulting from the construction of larger facilities may impact historic
structures, if present, but these impacts are considered minor.
Energy Storage Component 13.5.4.4
Ground disturbance is anticipated to occur with installation of energy storage systems. This
may cause significant impacts to archaeological resources, if present. Noise and vibration
resulting from construction may impact historic resources, if present, but these impacts are
considered minor.
Peak Generation Plant Component 13.5.4.5
Under this component, ground-disturbing trenching to access upgraded natural gas, water,
and wastewater utility lines would be required to install three peak generation plants at or
adjacent to existing PSE substations within the Eastside. This may cause significant impacts
to archaeological resources, if present. Noise and vibration resulting from construction may
impact historic resources, if present, but these impacts are considered minor. Noise from the
operation of peak generation plants is considered significant and may cause minor to
significant impacts to historic properties at these locations, if present.
This component may also necessitate an upgrade to major natural gas or water supply lines in
order to supply the generators. Installation of these underground utilities could also encounter
archaeological resources.
13.5.5 Alternative 3: New 115 kV Lines and Transformers
Alternative 3 proposes construction of three new transformers at existing substations:
Sammamish, Talbot Hill, and Lake Tradition. This alternative also includes rebuilding or
expanding five existing substations: Sammamish, Lakeside, Talbot Hill, Clyde Hill, and
Hazelwood. Approximately 60 miles of new 115 kV transmission lines would be constructed
within existing or new rights-of-way.
Construction of transmission lines would involve ground disturbance and thus have the
potential for significant impacts on archaeological resources, if present, depending on the
proposed corridors. Installation of new transformers at the Sammamish, Talbot Hill, and
Lake Tradition substations would require ground disturbance and has the potential for
significant impacts to archaeological resources, if present.
No cultural resources surveys of the three substation properties have been performed. The
conservation efforts component of Alternative 3 is anticipated to have the same potential
impacts as the No Action Alternative (minor to moderate impacts to historic properties, if
present, and no impacts to archaeological resources due to no proposed ground disturbance).
The Alternative 3 study area is geographically the largest of the three and contains the
greatest amount of historic properties (55) and recorded archaeological resources (88).
Existing surveys provide coverage of less than 10 percent of the study area, which is the
lowest amount of all the alternatives. Alternative 3 is the only alternative to propose work at
the Lake Tradition substation. There are two recorded Precontact period archaeological
resources on the east side of Lake Tradition within 1,200 feet of the substation (45-KI-481
CHAPTER 13 January 2016 13-16 HISTORIC AND CULTURAL RESOURCES
PHASE 1 DRAFT EIS
and 45-KI-430). Ground disturbance may cause significant impacts to archaeological
resources, if present.
The Alternative 3 study area contains all 15 recorded historic period cemeteries. It is assumed
that no construction would occur within cemetery boundaries, but there may be minor
impacts to those cemeteries from noise and dust. Noise and vibration resulting from
construction may impact historic structures, if present, but these impacts are considered
minor.
13.6 HOW COULD OPERATION OF THE PROJECT
AFFECT HISTORIC AND CULTURAL RESOURCES?
13.6.1 Operation Impacts Considered
For belowground resources, any potential impacts to historic properties and archaeological
resources would occur during construction.
For aboveground resources, potential operational impacts may result from visual changes to
register properties resulting from construction of new electrical facilities. There may also be
noise impacts affecting the setting of nearby cemeteries. Depending on the nature of the
energy efficiency measures proposed by Alternatives 1, 2, and 3, these may incentivize a loss
to the architectural integrity of historic properties through the replacement of original
windows with modern energy-efficient types, if not in-kind with the original architectural
character. However, for historic properties that are designated King County Landmarks,
replacement of windows would likely require a COA.
13.6.2 No Action Alternative
Under the No Action Alternative, no construction would occur. No impacts to archaeological
resources are anticipated. Conservation efforts could impact aboveground historic properties
as described in Section 13.5.2.
13.6.3 Alternative 1: New Substation and 230 kV Transmission Lines
No impacts are expected from operation of the substation. Potential operational impacts from
the transmission line options are discussed below.
Option A: New Overhead Transmission Lines 13.6.3.1
Noise, vibration, and visual impacts resulting from maintenance of overhead transmission
lines, such as pole replacement, may impact aboveground historic properties, if present.
Depending on the resource and proximity of the overhead line to the resource, these impacts
would range from minor to significant. Noise and visual impacts from maintenance work
would be considered temporary and thus minor, however pole replacement has the potential
for causing significant impacts to the structural integrity of historic properties built of brick,
if present and depending on proximity to areas being maintained.
January 2016 CHAPTER 13 HISTORIC AND CULTURAL RESOURCES 13-17
PHASE 1 DRAFT EIS
Option B: Existing Seattle City Light 230 kV Transmission 13.6.3.2
Corridor
Noise and visual impacts resulting from operation of overhead transmission lines may impact
historic structures, if present. However, since these lines would replace existing lines, the
impacts are considered minor, depending on proximity.
Option C: Underground Transmission Lines 13.6.3.3
No operational impacts are anticipated to occur to aboveground historic properties, if present.
Option D: Underwater Transmission Lines 13.6.3.4
No operational impacts are anticipated to occur to aboveground historic properties, if present.
13.6.4 Alternative 2: Integrated Resource Approach
Energy Efficiency Component 13.6.4.1
An increase in energy efficiency implementation (for example, replacement of windows with
styles that are not in-kind with the original architectural style) may reduce the integrity of the
design, materials, and workmanship of historic resources, if present. This may result in minor
to moderate impacts to historic and cultural resources, as described in Section 13.5.1.
Demand Response Component 13.6.4.2
Visual impacts resulting from the presence of new meters may impact historic and cultural
resources, if present. These may reduce the integrity of setting for historic resources, if
present, but are not anticipated to permanently impact a property’s ability to convey its
historical significance. These impacts would be minor.
Distributed Generation, Energy Storage, and Peak Generation 13.6.4.3
Plant Components
Increased noise and visual impacts resulting from distribution generation, energy storage, or
peak generators measures may reduce the integrity of setting for historic resources, if present,
but they are not anticipated to permanently impact a property’s ability to convey its historical
significance. These impacts would be minor.
13.6.5 Alternative 3: New 115 kV Lines and Transformers
Increased noise and visual impacts resulting from operation of overhead transmission lines
and transformers may reduce the integrity of setting for historic resources, if present, but are
not anticipated to permanently impact a property’s ability to convey its historical
significance. These impacts would be minor to moderate, depending on the proximity to
potential resources.
CHAPTER 13 January 2016 13-18 HISTORIC AND CULTURAL RESOURCES
PHASE 1 DRAFT EIS
13.7 WHAT MITIGATION MEASURES ARE AVAILABLE
FOR POTENTIAL IMPACTS TO HISTORIC AND
CULTURAL RESOURCES?
Impacts to specific cultural resources cannot be determined at this time because locations of
project elements have not yet been identified. The following mitigation measures are
typically used.
13.7.1 Construction Measures
If the selected alternative presents potential impacts to eligible or listed historic properties,
mitigation measures would depend upon the nature of the property and the characteristics
contributing to its significance. If impacts to a designated King County Landmark are
proposed, the project will be subject to the Certificate of Appropriateness (COA) process
with the King County Landmarks Commission.
An archaeological survey of proposed areas of ground disturbance is typically conducted
prior to construction. Should impacts to belowground archaeological resources be
anticipated, avoidance and mitigation measures would be specific to the nature of the
identified resources.
Under state law (RCW 27.53), prehistoric archaeological sites are protected in all cases.
Historic archaeological sites must be determined eligible for listing in the Washington
Heritage Register (WHR) (RCW 27.34.220) or National Register of Historic Places (NRHP)
before they are considered protected. DAHP will make a final determination whether the
resource is eligible or not eligible for register listing. If a resource that is considered protected
cannot be avoided, the project proponent must apply for an archaeological excavation permit
from DAHP (WAC 25-48-060) to conduct any activity that disturbs the site. DAHP will then
provide the archaeological excavation permit application for review to the appropriate
stakeholders and Tribes.
At a minimum, an Inadvertent Discovery Plan would be prepared for use during construction.
The Inadvertent Discovery Plan would outline the procedures to be followed in the event that
archaeological resources are identified during construction activities. Under state law (RCW
27.44), archaeological resources identified during construction would need to be evaluated. If
the resources are considered significant, any impacts on archaeological resources would
require mitigation, which would likely entail archaeological investigation such as scientific
excavation and analysis. For archaeological resources found during construction, an
emergency archaeological excavation permit may be issued by DAHP and is typically
received within three business days. It is possible that archaeological monitoring would be
recommended for portions of the project; this work would be conducted under an
Archaeological Resources Monitoring Plan.
Best management practices would be implemented during construction to minimize impacts
from dust, noise, and vibration. Vibration monitoring may be conducted at historic buildings
to document that vibration does not exceed acceptable levels.
January 2016 CHAPTER 13 HISTORIC AND CULTURAL RESOURCES 13-19
PHASE 1 DRAFT EIS
13.7.2 Operation Measures
If the selected alternative presents potential operational impacts to eligible or listed historic
properties, mitigation measures would depend upon the nature of the property and the
characteristics contributing to its significance. If impacts to a designated King County
Landmark are proposed, the project will be subject to the COA process with the King County
Landmarks.
Operational impacts to aboveground resources may include noise, vibration, and views. The
impacts to each identified historic resource will need to be assessed individually to determine
mitigation measures, which may include redesign options or measures to minimize noise and
vibration impacts. No operational impacts are anticipated for belowground archaeological
resources.
13.8 ARE THERE ANY CUMULATIVE IMPACTS TO
HISTORIC AND CULTURAL RESOURCES AND CAN
THEY BE MITIGATED?
It is assumed that any impact to a belowground archaeological resource would occur during
construction and would be mitigated during the construction phase. Thus cumulative impacts
related to belowground archaeological resources are considered unlikely.
For aboveground eligible or listed historic properties, impacts may occur under all
alternatives through the promotion of energy efficiency, which is assumed to include
replacement of original windows, as described in Section 13.5.1. Any loss of historical
integrity, together with ongoing projects in the region, would continue the past and current
trends of historic buildings being modified and destroyed. However, no impacts are
anticipated from the Energize Eastside project that cannot be mitigated. For King County
Landmarks, any loss of historical integrity would be mitigated through the COA process.
Therefore, no cumulative impacts on aboveground historic properties are anticipated.
13.9 ARE THERE ANY SIGNIFICANT UNAVOIDABLE
ADVERSE IMPACTS TO HISTORIC AND CULTURAL
RESOURCES?
Based on the programmatic evaluation, no known significant impacts to historic and cultural
resources have been identified that cannot be avoided through appropriate mitigation
measures. However, the exact location of the project is not known. For the Phase 2 Draft EIS,
site-specific analysis will be conducted to more definitively determine potential impacts.
CHAPTER 13 January 2016 13-20 HISTORIC AND CULTURAL RESOURCES
PHASE 1 DRAFT EIS
CHAPTER 14. TRANSPORTATION
14.1 HOW WERE TRANSPORTATION FACILITIES IN THE
COMBINED STUDY AREA EVALUATED?
The transportation study includes vehicular and non-
motorized transportation facilities that could potentially be
disturbed by construction of the proposed Energize
Eastside Project. The study areas for the three alternatives
are shown on Figure1-4 in Chapter 1. Transportation
elements include the roadway system, transit, non-
motorized travel (walking, bicycling), and parking. The
transportation system was identified based on geographic
information systems (GIS) data, and each transportation
element was evaluated at a high level for this
programmatic EIS.
14.2 WHAT ARE THE RELEVANT
PLANS, POLICIES, AND
REGULATIONS?
Existing transportation plans, policies, and regulations
primarily govern construction activities and road
operations. Table 14-1 describes transportation standards
and regulations related to construction within public road
rights-of-way.
Table 14-1. Regulations, Guidelines, and Permits for Construction of Projects that
Affect the Transportation System
Statute or
Guideline
Lead
Agency Regulated Activities
Federal
Manual on
Uniform
Traffic Control
Devices
(MUTCD)
Federal
Highway
Administration
(FHWA)
Defines standards used by road managers nationwide to
install and maintain traffic control devices on all public
streets, highways, bikeways, and private roads open to
public traffic. The MUTCD is a compilation of national
standards for all traffic control devices, including road
markings, highway signs, and traffic signals. It is updated
periodically to accommodate the nation's changing
transportation needs and address new safety technologies,
traffic control tools, and traffic management techniques.
The MUTCD includes standards for signs, flagging, and
barricades in temporary construction work zones. (FHWA,
2009).
Transportation Key Findings
Construction of Alternatives 1
and 3 could result in minor to
moderate impacts relating to
restrictions on roadway use,
sidewalk use, property access,
transit, and parking, as well as
construction-generated truck
and commute trips, and
potential pavement
degradation. Construction of
Alternative 2 could result in
negligible to moderate
impacts, depending on the
component and facility.
Negligible operational
transportation impacts are
anticipated for all of the
alternatives except for the
energy storage and peak
generation plant components
of Alternative 2, which would
result in minor impacts.
January 2016 CHAPTER 14 TRANSPORTATION 14-1
PHASE 1 DRAFT EIS
Statute or
Guideline
Lead
Agency Regulated Activities
State
Work Zone
Traffic Control
Guidelines
Washington
State
Department of
Transportation
(WSDOT)
WSDOT has jurisdiction over state highways and ramp
intersections. Work conducted within the right-of-way of
state highways must be coordinated with WSDOT. The
Work Zone Traffic Control Guidelines for Maintenance
Operations (WSDOT, 2014) are based on the standards set
forth in the MUTCD.
Local
Street Use
Permits and
Franchises
Cities and
King County
Construction activities that affect the transportation system
within a city or county are subject to the street use permit
requirements of that jurisdiction, as reflected in its locally
adopted county or city municipal code. Street use permits
would be required from multiple study area communities,
depending on the location of project. Cities and counties
typically adopt construction guidelines based on the
MUTCD. Construction activities may also be guided by the
terms of franchise agreements with local jurisdictions.
Source: FHWA, 2009; WSDOT 2014
In addition to the standards and regulations described in Table 14-1, there are rules
established by railroad owners that apply to work near rail facilities. However, the only
existing rail line that passes through the combined study area, the Eastside Rail Corridor, is
no longer operational. Ownership of this line is divided among the Port of Seattle, King
County, Sound Transit, and the Cities of Kirkland and Redmond (King County, 2015a).
14.3 WHAT ARE THE EXISTING TRANSPORTATION
FACILITIES IN THE COMBINED STUDY AREA?
The existing transportation system includes roadways, parking facilities, transit, and non-
motorized facilities, as described in the following sections.
14.3.1 Roadways
All roadways in the combined study area have designated functional classifications, which
depend on the types of vehicular trips the roadways serve and the relative levels of traffic
volumes they carry. There may be different classifications at the municipal and national
levels. Since the combined study area includes several municipalities, each with minor
differences in classification definitions, the following analysis uses the national designations
defined by the Federal Highway Administration (FHWA). Each roadway in the combined
study area has been designated with one of the following FHWA classifications (FHWA,
2013):
• Interstate Freeways provide the highest capacity and least impeded traffic flow for
longer vehicle trips, with limited access.
CHAPTER 14 January 2016 14-2 TRANSPORTATION
PHASE 1 DRAFT EIS
• Freeways and Expressways are very similar physically to interstates with limited
access, but they are not officially designated as interstates.
• Principal Arterials serve as primary routes for moving traffic through each city,
connecting urban centers to one another or to the regional transportation network.
• Minor Arterials distribute traffic from principal arterials to collectors and local
roads.
• Major and Minor Collectors collect and distribute traffic from principal and minor
arterials to local access streets or provide direct access to destinations. Major and
minor collectors are differentiated by length, connecting driveway density, speed
limits, and street widths.
• Local Access Streets provide access to residential neighborhoods, commercial
facilities, or other streets. They are not intended for long-distance travel.
These functional classifications represent varying levels of emphasis on mobility and access.
For example, freeways and expressways serve mobility needs for high volumes of traffic,
with access fully controlled. Arterials provide a high degree of mobility and have more
limited access to adjacent land uses, accommodating larger traffic volumes at higher speeds.
Collectors generally provide a more balanced emphasis on traffic mobility and access to
adjacent land uses. All streets not designated as freeways, arterials, or collectors are
considered local access streets, which include most streets in the roadway system. Local
access streets provide a high degree of access to adjacent land and are not intended to serve
through traffic, carrying smaller traffic volumes at lower speeds.
Regional access to the Eastside is provided via the following freeways.
Interstate 90 (I-90) is an east-west freeway that traverses the entire continental United
States, connecting to Seattle in the west and Boston, Massachusetts, to the east. In the
combined study area, I-90 is 8 to 16 lanes wide, including one High Occupancy Vehicle
(HOV) lane in each direction along much of its length, and center express lanes that change
direction according to the peak direction of traffic flow. It typically carries about 110,000 to
150,000 vehicles per day (WSDOT, 2015a).
I-405 is a freeway that serves as the primary north-south facility on the east side of Lake
Washington, connecting to I-5 in Lynnwood to the north and Tukwila to the south. In the
combined study area, I-405 is 6 to 10 lanes wide, including an HOV lane in each direction
along much of its length. It typically carries between 100,000 and 200,000 vehicles per day
(WSDOT, 2015a).
State Route (SR) 520 is an east-west freeway that connects to I-5 to the west in Seattle, and
SR 203 to the east in unincorporated King County. It is generally six lanes wide, including
HOV lanes along portions of its length. It typically carries 40,000 to 80,000 vehicles per day
(WSDOT, 2015a). The SR 520 Bridge Replacement and HOV Program is currently
underway. Major construction is complete for the Eastside Transit and HOV Project phase,
which provided transit, HOV, and non-motorized improvements between Evergreen Point in
January 2016 CHAPTER 14 TRANSPORTATION 14-3
PHASE 1 DRAFT EIS
Medina and 108th Avenue NE in Bellevue. Replacement of the floating bridge across Lake
Washington is currently scheduled for completion by the end of 2016 (WSDOT, 2015b).
In general, WSDOT has jurisdiction over these freeways, although ramp intersections are
also under the jurisdiction of the city or county in which they are located. In addition to these
regional freeways, the combined study area includes a mix of arterial, collector, and local
roadways, shown on Figure 14-1. Traffic volumes on different roadways vary widely; they
can be greater than 25,000 vehicles per day on a principal arterial, or less than 2,000 vehicles
on a minor collector. Local access streets carry low traffic volumes, typically less than 700
vehicles per day, and often lower than 100 vehicles per day (WSDOT, 2013).
Many municipalities also designate streets as truck routes. Designated truck route streets are
typically required to meet design standards to accommodate larger and heavier vehicles, and
they are intended to channel truck traffic away from local access streets. Appropriate truck
haul routes for construction projects are typically identified as part of the construction
permitting process. In general, construction trucks are directed toward designated truck route
streets, other arterials, and freeways to the greatest possible extent.
CHAPTER 14 January 2016 14-4 TRANSPORTATION
PHASE 1 DRAFT EIS
Energize Eastside EIS 140548
Figure 14-1
Major Roadways
SOURCE: King County 2015; ESA 2015; WA Ecology 2014;
WSDOT 2015.
Lake Washington
Lake
Sammamish
Bellevue Sammamish
Issaquah
Renton
Newcastle
RedmondKirkland
Beaux Arts
Medina
Clyde
Hill
Hunts
Point
Yarrow
Point
Mercer
Island
NE 85th St/ Central Way
Lake Washington BlvdW Lake Sammamish PkwyBellevue Way112th Ave SE148th St NENE 8th St
Ri
char
d's RdCoal Creek Pkwy SE228th Ave SEHighlands Dr NERenton-Issaquah Rd SEE
L
a
k
e
S
a
mma
mi
s
h
P
k
wy
Factoria Blvd SENE Sunset Blvd
N E P a rk D rMaple Valley Hwy 17th Ave NWI-5 Lake St SLakeside
Novelty
Hill
Lake
Tradition
Sammamish
Talbot
Hill
Interstate Freeway
Freeway and
Expressway
Principal Arterial
Minor Arterial
Major Collector
Minor Collector
Combined Study Area
Boundary
Existing Substations
Water bodies
City Limits
Unincorporated King
County
U:\GIS\GIS\Projects\14xxxx\D140548_EastsidePSETransmisisonCoor\MXD\MajorRoadways.mxd
0 2
Miles
Note: This map is for reference only. It is not guaranteed that the information is accurate or complete.
14.3.2 Parking Facilities
Most neighborhoods in the combined study area have unrestricted on-street parking in lower
density residential and commercial neighborhoods. Many homes and businesses in the
combined study area also have parking on-site in garages or surface parking strips or lots.
In the denser downtown areas of Bellevue, Kirkland, Redmond, Newcastle, and Renton, on-
street parking is time-restricted. There are both public and private fee-based parking lots and
garages in these areas. Some streets near schools, athletic facilities, and public parks may
also have time restrictions.
14.3.3 Transit
Public transit in the combined study area consists of bus service provided by King County
Metro (Metro) and Sound Transit; a limited amount of additional service is provided by
Snohomish County’s Community Transit. Bus service consists of: (1) commuter routes,
which operate only during weekday peak periods, with service to employment centers in the
morning and away from them in the evening, and (2) local routes, which generally provide
two-way, all-day service.
The combined study area is served by 59 Metro routes, 11 Sound Transit routes, and 1
Community Transit route. The Alternative 3 study area is served by an additional five Metro
routes. Transit routes and facilities within the study areas are shown on Figure 14-2. Bus
volumes and frequencies are typically more concentrated in the vicinity of transit centers,
park-and-ride lots, and freeway stations. Bus service becomes more dispersed away from
these centers, primarily operating on arterials and freeways (King County Metro, 2015;
Sound Transit, 2015a; Community Transit, 2015). Transit routes are regularly adjusted by
transit agencies in response to shifts in demand as well as available funding, so the numbers
and locations of transit routes and facilities could change slightly over the duration of
environmental analysis, design, and construction of the Energize Eastside Project.
Sound Transit is planning to open the East Link Extension light-rail line, which will extend
light-rail service from downtown Seattle, across the I-90 bridge, to Mercer Island, Bellevue,
and Redmond. The light rail is planned to operate at grade or on elevated platforms along
most of its length, with a tunnel section planned in downtown Bellevue. Eight stations are
planned in the combined study area, including three with adjacent park-and-ride lots and five
without. This project is currently in the design stage, with construction planned for
completion in 2023 (Sound Transit, 2015b).
CHAPTER 14 January 2016 14-6 TRANSPORTATION
PHASE 1 DRAFT EIS
Energize Eastside EIS 140548
Figure 14-2
Transit Facilities
SOURCE: King County 2015; ESA 2015; WA Ecology 2014;
WSDOT 2015.
Lake Washington
Lake
Sammamish
Bellevue Sammamish
Issaquah
Renton
Newcastle
RedmondKirkland
Beaux Arts
Medina
Clyde
Hill
Hunts
Point
Yarrow
Point
Mercer
Island
NE 85th Street
Lake Washington BlvdNE 85t h St r eet
W Lake Sammamish PkwyBellevue Way112th Ave SE148th Ave NENE 8th Street
Ri
char
d's RdCoal Creek Pkwy SE228th Ave SEHighlands Dr NERenton - Issaquah RdE
L
a
k
e
S
a
mma
mi
s
h
P
k
wy
Lakeside
Novelty
Hill
Lake
Tradition
Sammamish
Talbot
Hill
Park-and-Ride,
Transit Center, or
Freeway Station
Roadway
Existing
Substations
Combined Study
Area Boundary
Water bodies
City Limits
Unincorporated
King County
U:\GIS\GIS\Projects\14xxxx\D140548_EastsidePSETransmisisonCoor\MXD\TransitFacilities.mxd
0 2
Miles
Note: This map is for reference only. It is not guaranteed that the information is accurate or complete.
14.3.4 Non-motorized Facilities
The combined study area includes a mix of facilities to support walking and bicycling. Most
downtown areas have complete sidewalk networks. Many residential neighborhoods have
sidewalks on one or both sides of the street. However, sidewalks are absent in some
neighborhoods. Areas farther away from city centers, particularly those in unincorporated
King County, are less likely to have sidewalk systems.
Some roadways have shoulders that can accommodate pedestrians. For roadways without
sidewalks or shoulders, pedestrians typically walk along the edge of the roadway pavement.
Signalized intersections typically include marked crosswalks with pedestrian signals. Marked
crosswalks are provided at some stop-controlled intersections and mid-block locations. All
intersections that do not have marked crosswalks are still considered to be legal pedestrian
crossings.
Bicycle facilities in the combined study area include painted on-street bicycle lanes, and
roadway lanes that are marked with sharrows indicating that motorists should share the lane
with bicyclists. On streets without bike lanes or sharrows, bicyclists may travel in the
general-purpose lanes or on adjacent sidewalks.
Denser downtown neighborhoods that include a mixture of commercial and residential
development typically generate higher levels of pedestrian and bicycle travel. Neighborhoods
that include parks, libraries, recreational facilities, colleges, schools, and commercial
development are also more likely to generate pedestrian and bicycle traffic. Neighborhoods
that consist primarily of low-density residential or commercial development typically have
lower levels of non-motorized activity.
The combined study area includes a number of multi-use trails separated from roadways that
are shared by pedestrians and bicyclists. Some trails utilize portions of the Eastside Rail
Corridor, a 42-mile former rail line located between Renton and Snohomish, previously
owned by BNSF Railway. In the mid-2000s, BNSF stopped using the rail line and in
subsequent years, the Port of Seattle, King County, Sound Transit, and the Cities of Kirkland
and Redmond each purchased portions of the corridor. Kirkland and Redmond are currently
replacing the rails with multi-use trails. (King County, 2015a)
Major trails located in the combined study area are shown on Figure 14-3.
CHAPTER 14 January 2016 14-8 TRANSPORTATION
PHASE 1 DRAFT EIS
Energize Eastside EIS 140548
Figure 14-3
Major Trail Facilities
SOURCE: King County 2015; ESA 2015; WA Ecology 2014;
Renton 2015; Newcastle 2015; Issaquah 2015; Sammamish 2015;
Bellevue 2015; Kirland 2015; Redmond 2015; WSDOT 2015.
Lake Washington
Lake
Sammamish
Bellevue
Sammamish
Issaquah
Renton
Newcastle
RedmondKirkland
Beaux Arts
Medina
Clyde
Hill
Hunts
Point
Yarrow
Point
Mercer
Island
Lake to
Lake Trail
I-90 Trail
Lake Washington TrailCedar River Trail East Lake Sammamish TrailEast Plateau Trail
Issaquah-Preston Trail
I-90 Trail
Marymoor
Connector Trail
Rai
ni
er Trai
l
Coulon
Park Trail
C
edar River Trail SR 520 TrailS R 520 T railLakeside
Novelty
Hill
Lake
Tradition
Sammamish
Talbot
Hill Major Multi-Use Trails
Roadway
Bus Route
Combined Study Area
Boundary
Existing Substations
Water bodies
City Limits
Unincorporated King
County
U:\GIS\GIS\Projects\14xxxx\D140548_EastsidePSETransmisisonCoor\MXD\MajorNonMotorizedFacilities.mxd
0 2
Miles
Note: This map is for reference only. It is not guaranteed that the information is accurate or complete.
14.4 HOW WERE POTENTIAL IMPACTS TO
TRANSPORTATION ASSESSED?
Because this Phase 1 Draft EIS is programmatic, the types of transportation impacts that
could be expected from implementation of the alternatives are generally discussed, but
potential impacts at specific sites are not evaluated. Impacts were assessed at a general level,
based on the amount of disruption to transportation facilities that could potentially result
during and after construction, and the types of transportation facilities potentially affected.
Site-specific transportation analysis will be conducted during Phase 2 project-level review.
14.5 WHAT ARE THE LIKELY CONSTRUCTION IMPACTS
RELATED TO TRANSPORTATION?
14.5.1 Construction Impacts Considered
Transportation impacts resulting from project construction could include restrictions on
roadway use, sidewalk use, access to intersecting alleys and driveways, transit, and parking.
Impacts could also include truck trips and employee commute trips generated by construction
work, and pavement degradation from heavy trucks.
For this analysis, the magnitude of project-related impacts is classified as being minor,
moderate, or significant as follows:
Minor – Access to residences and businesses could be maintained, and vehicular and non-
motorized travel could still occur with minimal additional traveler delay.
Moderate – Access to residences and businesses could be maintained and vehicular and non-
motorized travel could still occur, but with expected increases in traveler delay.
Significant – If the construction activities would prohibit access to residences or businesses,
or prohibit travel through a major corridor.
14.5.2 No Action Alternative
The No Action Alternative would not include construction of new facilities; therefore, no
construction impacts to transportation would occur.
14.5.3 Alternative 1: New Substation and 230 kV Transmission Lines
Impacts are described according to the major components associated with Alternative 1. The
substation impacts are described first, followed by transmission line options.
Substation Construction under Options A through D 14.5.3.1
The following transportation impacts related to construction of a new substation could occur
under Alternative 1, Options A through D. Without mitigation, these impacts to
transportation could be significant. However, with implementation of measures described in
Section 14.7, impacts would be expected to be minor to moderate, depending on factors such
CHAPTER 14 January 2016 14-10 TRANSPORTATION
PHASE 1 DRAFT EIS
as the adjacent transportation facility types, vehicular and non-motorized traffic volumes, day
of week, time of day, and size of transportation right-of-way disturbed.
14.5.3.1.1 Roadway Capacity Restrictions
Substation construction would likely result in temporarily narrowing or closing lanes on the
roadways adjacent to the substation construction site, both to construct the substation and to
connect transmission lines to the substation. Access to properties located adjacent to the
construction site would need to be maintained. The level of impact would depend on the type
of roadway, ranging from minor to moderate. Arterials and collectors tend to be wider but
more vehicles would be potentially affected by capacity restrictions; local access streets tend
to be narrower, but fewer vehicles would be potentially affected.
14.5.3.1.2 Sidewalk Impacts
Construction at the substation could result in temporary closures of sidewalks or walkways
adjacent to the substation site while construction is underway. The level of impact would
vary from minor to moderate associated with the level of pedestrian activity, depending on
proximity to high-use pedestrian areas, the time of day, and day of the week.
14.5.3.1.3 Transit Impacts
Substation construction could require temporarily moving or closing adjacent bus stops. Bus
stop closure impacts are expected to be minor to moderate, depending on the walking
distance to the nearest alternative bus stop, which would typically be one to three blocks.
14.5.3.1.4 Parking Impacts
Construction at the substation could result in temporary closures of parking lanes on
roadways adjacent to construction. However, the impacts are likely to be minor because there
is little to no on-street parking near the potential construction sites. Private parking lots are
located near Lakeside, Vernell, and Westminster substations, and access to these lots would
need to be maintained. Additional parking demand could also be generated by construction
employees who work at the site.
14.5.3.1.5 Mobilization of Large Equipment to Substation Sites
Construction at the substation site could require delivery of very large equipment, such as
transformers, requiring overweight and/or oversized loads to be carried on surface streets
from regional freeways. Carriers of all such loads would be required to obtain a permit from
the cities in which they need to travel, and those traveling on state highways would also be
required to obtain a permit from WSDOT. Oversized loads can only be routed over roadways
that have sufficient clearance. WSDOT and the Cities may also dictate the time of day when
such loads can travel. Because of restrictions that accompany the permits necessary to
transport oversized loads, transporting these loads is not expected to have a significant impact
on traffic along the haul route, and could range from minor to moderate.
14.5.3.1.6 Construction-generated Vehicle Trips
Trips would be generated by trucks traveling to and from the substation site to support
construction activities, and also by construction workers commuting to and from the site.
Impacts would be minor.
January 2016 CHAPTER 14 TRANSPORTATION 14-11
PHASE 1 DRAFT EIS
14.5.3.1.7 Pavement Impacts
In areas where construction-generated trucks are concentrated, high truck volumes can
potentially result in degradation to the street pavement. As part of construction permitting
processes, communities typically require that pavement must be restored upon completion of
construction, so this impact is expected to be minor.
Option A: New Overhead Transmission Lines 14.5.3.2
Construction of the overhead lines would require installation of utility poles along a project
length of at least 18 miles, some of which would likely be adjacent to roadways.
Transmission lines installed overhead would not require construction within the roadway, but
could require narrowing or closing vehicle lanes or sidewalks near the pole construction sites,
to separate vehicular and non-motorized traffic from construction activities. After utility
poles are installed, transmission wire would be strung between the poles. During the period in
which wire is pulled, no vehicular traffic could be allowed on roadways or sidewalks located
beneath the areas of pulling activity.
Overhead transmission line poles would need to be evaluated for compliance with height
restrictions around local airports or seaplane bases. No impact is expected to airplane
operations assuming compliance with airport area height regulations.
The following transportation impacts related to overhead transmission line construction
would be expected to occur. Without mitigation, some construction impacts to transportation
could be significant. However, with implementation of measures described in Section 14.7,
impacts would be expected to be minor to moderate, depending on factors such as the
transportation facility location and type, vehicular and non-motorized traffic volumes, day of
week, time of day, and size of the transportation right-of-way disturbed.
14.5.3.2.1 Roadway Capacity Restrictions
Installation of utility poles could require closure of the roadway lanes in the vicinity of the
poles for the duration of construction. Full or partial roadway closures could require traffic to
be detoured. The level of impact would depend on the type of roadway but would be
expected to range from minor to moderate. Arterials and collectors tend to be wider but more
vehicles would be potentially affected by capacity restrictions; local access streets tend to be
narrower, but fewer vehicles would be potentially affected.
14.5.3.2.2 Disruption at Alleys and Driveways
Construction across a driveway or alley would disrupt property access at that location.
Driveways located along the transmission line route must be passable during construction
unless there is an alternative driveway serving a property that can accommodate vehicles if
one driveway is closed. Impacts would range from minor to moderate.
14.5.3.2.3 Sidewalk Impacts
Construction of overhead transmission lines would likely result in temporary closures of
sidewalks or walkways adjacent to construction activities. The level of impact could be minor
to moderate, varying with the level of pedestrian activity and depending on proximity to
high-use pedestrian areas and the time of day.
CHAPTER 14 January 2016 14-12 TRANSPORTATION
PHASE 1 DRAFT EIS
14.5.3.2.4 Bicycle Impacts
Where roadway lanes with marked bicycle facilities (bicycle lanes or sharrows) would be
narrowed or closed during construction, bicyclists would be detoured to a roadway lane or
sidewalk where they could travel safely. Where marked bicycle facilities do not exist,
maintenance of traffic plans to accommodate closed or narrowed roadway lanes would also
need to be designed to safely accommodate bicyclists. Impacts would likely be minor to
moderate, depending upon the distance and duration of the detour.
14.5.3.2.5 Transit Impacts
Construction along roadway segments with bus routes could require temporarily moving or
closing bus stops adjacent to pole construction or beneath wire pulling areas. Bus stop
closure impacts are expected to be minor to moderate, depending on the walking distance to
the nearest alternative bus stop, which would typically be one to three blocks.
14.5.3.2.6 Parking Impacts
Construction along roadway segments with on-street parking could result in temporary
closures of parking lanes adjacent to pole construction or beneath wire pulling activities.
Additional parking demand could also be generated by construction employees who work at
the site. Impacts would be expected to be minor.
14.5.3.2.7 Construction-generated Vehicle Trips
Trips would be generated by trucks traveling to and from the site to support construction
activities, and also by construction workers commuting to and from the site. However, the
majority of construction-generated trips typically occur outside of peak commute periods and
are dispersed throughout the day, so their impact on roadway operations would be expected
to be minor.
14.5.3.2.8 Pavement Impacts
In areas where construction-generated trucks are concentrated, high truck volumes can
potentially result in degradation to the street pavement. As part of construction permitting
processes, jurisdictions typically require that pavement must be restored upon completion of
construction, so this impact is expected to be minor.
14.5.3.2.9 Olympic Pipeline
The possibility that the Olympic Pipeline would be damaged during construction is
considered low, because of regulatory requirements and safety practices that govern
construction near the pipeline. However, if significant damage to the pipeline were to occur,
or if there is a planned temporary disruption during project construction, petroleum products
normally transported in the pipeline would be transported by other means, primarily by trucks
using interstate highways. This would be expected to generate up to a few hundred truck trips
per day, resulting in a minor impact when distributed throughout the day and across the
interstate highway system. No disruption in petroleum product supply to airports or other
customers of the Olympic Pipeline would be anticipated for any planned temporary shutdown
or relocation. If there were an accidental shutdown, short-term disruption could occur until
trucking could be arranged.
January 2016 CHAPTER 14 TRANSPORTATION 14-13
PHASE 1 DRAFT EIS
Option B: Existing Seattle City Light 230 kV Transmission 14.5.3.3
Corridor
Since this option would include rebuilding or replacing existing poles and other structures,
and pulling new transmission wire, the types of construction impacts to transportation would
be similar to those described for installing new transmission lines in Alternative 1, Option A.
However, fewer roadways would be affected because activities would be concentrated in
existing utility corridors. The upgraded transmission line would also need to be connected to
existing PSE substations, resulting in additional construction transportation impacts between
the existing corridors and the substation locations.
Option C: Underground Transmission Lines 14.5.3.4
Installation of transmission lines under existing roadways could require excavation,
construction, backfill, and pavement restoration within roadway rights-of-way. Impacts to
roadway capacity, sidewalks, bicycle facilities, transit and parking, as well as construction-
generated vehicle trips and potential pavement degradation, would be similar to those
described for overhead construction. However, impacts would be less localized, extending
along the entire lengths of roadway segments rather than only at pole locations, and longer in
duration. Because installation of underground transmission line segments would likely occur
in continuous lengths of one block or longer, the following sections identify additional
transportation impacts that would be expected during construction. Without mitigation, these
impacts to transportation described below could be significant. However, with
implementation of measures described in Section 14.7, impacts would be expected to be
minor to moderate, depending on factors such as the affected transportation facility location
and type, vehicular and non-motorized traffic volumes, day of week, time of day, and size of
area disturbed.
14.5.3.4.1 Disruption at Roadway Intersections
Construction through an intersection would disrupt intersection operations and require
manual traffic control (flaggers). In addition, some signalized intersections have in-pavement
induction loops that control traffic light operations. Excavation of the pavement at these
locations would destroy the existing induction loops and require replacement. Impacts would
be temporary and would be expected to be minor.
14.5.3.4.2 Disruption at Alleys and Driveways
Construction across a driveway or alley would disrupt property access at that location.
Driveways located along the transmission line route must be passable during construction
unless there is an alternative driveway serving a property that can accommodate vehicles if
one driveway is closed.
For areas where trenchless techniques would be required, similar types of transportation
impacts would be expected in the areas where construction activities are concentrated.
Option D: Underwater Transmission Lines 14.5.3.5
Use of special vessels to dredge trenches in the lake bottom and lay cables in the trenches
could restrict boat access in the work areas, but would not be expected to have surface
CHAPTER 14 January 2016 14-14 TRANSPORTATION
PHASE 1 DRAFT EIS
transportation impacts. Surface transportation impacts would primarily occur at the locations
where the cables connect to the shore. At the land connections, construction vehicle trips,
roadway capacity restrictions, transit restrictions, and sidewalk impacts similar to those
described for Alternative 1, Option A could occur, depending on the location, but would be
expected to affect smaller localized areas. Land connections to a submerged line would be
underground, resulting in potential construction impacts similar to those described for
Alternative 1, Option C.
Marine vessels needed to support project construction would be required to follow the rules
of navigation established by the U.S. Coast Guard and U.S. Army Corps of Engineers, and
therefore are not expected to result in marine transportation impacts.
Minor impacts to boat traffic in the vicinity of construction could occur, resulting in boats
being relocated to avoid the construction area. Depending on the location of the line,
recreational boat traffic could be rerouted. Additional site-specific evaluations would be
conducted during project design to minimize potential impacts to boat traffic.
14.5.4 Alternative 2: Integrated Resource Approach
Energy Efficiency Component 14.5.4.1
Strategies to promote energy efficiency would consist primarily of communications to
customers and are not expected to require construction. Therefore, this component would not
result in construction impacts to transportation.
Demand Response Component 14.5.4.2
Installation of specialized devices to manage customer usage would require minor
construction activities, primarily on single residential and commercial sites. Construction
activities would generate a small number of trips that would be widely dispersed
geographically and over time, and would not involve disruptions to roadways or non-
motorized facilities. Therefore, construction impacts to transportation would be negligible.
Distributed Generation Component 14.5.4.3
Installation of devices to generate on-site power would require minor construction activities
primarily on commercial sites. Therefore, construction impacts to transportation would be
similar to those described for demand response.
Energy Storage Component 14.5.4.4
Construction of the large battery storage facilities required to store energy would require
construction similar to a substation, with potential minor transportation impacts similar to
those described for Alternative 1 substation construction.
Peak Generation Plant Component 14.5.4.5
Construction peak generation plants would require construction at existing substations.
Potential transportation impacts would be similar in type (minor) to those described for
January 2016 CHAPTER 14 TRANSPORTATION 14-15
PHASE 1 DRAFT EIS
Alternative 1 substation construction, but likely less intense because activities would consist
of modifying existing sites rather than constructing new facilities.
14.5.5 Alternative 3: New 115 kV Lines and Transformers
Improvements to Existing Substations 14.5.5.1
Potential transportation impacts associated with adding transformers at existing substations
would be similar in type to the impacts associated with building a new substation, as
described for Alternative 1, and would be expected to be minor to moderate, depending on
factors such as the affected transportation facility location and type, vehicular and non-
motorized traffic volumes, day of week, time of day, and size of area disturbed. Construction
could require closing or narrowing roadways and sidewalks adjacent to construction
activities, with associated impacts to vehicular travel, non-motorized travel, transit, and
parking. Trips would be generated by trucks traveling to and from the sites to support
construction activities, and also by construction workers commuting to and from the sites.
Because construction would consist of improvements to existing facilities, the magnitude and
duration of construction impacts to transportation would be lower at any one site than those
expected for construction of a new substation in Alternative 1, but impacts would occur at 10
substation locations instead of one substation and therefore would be more geographically
widespread.
New Transmission Lines 14.5.5.2
Potential transportation impacts associated with construction and installation of
approximately 60 miles of new transmission lines would be similar in type to the impacts
described for new transmission lines in Alternative 1. These could include narrowing or
closing roadways and sidewalks adjacent to construction activities, and the associated
impacts to vehicular travel, non-motorized travel, transit, and parking. Trips would be
generated by trucks traveling to and from the sites to support construction activities, and also
by construction workers commuting to and from the sites. However, compared to Alternative
1, more transmission lines would be installed over a larger area under Alternative 3;
therefore, the construction impacts to transportation are expected to be more widespread, and
would be expected to be minor to moderate, depending on factors such as the affected
transportation facility location and type, vehicular and non-motorized traffic volumes, day of
week, time of day, and size of area disturbed.
14.6 HOW COULD OPERATION OF THE PROJECT
AFFECT TRANSPORTATION?
14.6.1 Operation Impacts Considered
When constructed, the project elements would be located mostly overhead or underground,
on commercial properties, or adjacent to substation sites, and they would be physically
separated from transportation infrastructure and services. Transportation infrastructure
disrupted during construction would be restored, and streets, sidewalks, and trails disturbed
during construction would be repaved. Transportation impacts resulting from project
operation could include commute trips of employees at new facilities, truck trips generated
CHAPTER 14 January 2016 14-16 TRANSPORTATION
PHASE 1 DRAFT EIS
by facility maintenance, and permanent removal of or changes to transportation facilities and
public parking. Impacts described below are expected to be minor. Overall, impacts could be
negligible to moderate.
14.6.2 No Action Alternative
The No Action Alternative would continue conservation and maintenance activities at the
current frequency. Maintenance of existing facilities would continue largely as it does under
current conditions, and no traffic impacts are expected. Power outages that could occur with
the No Action Alternative would affect traffic lights and street lights in the areas where
outages occur. This could adversely impact traffic operations by increasing delay at
signalized intersections. During nighttime conditions, loss of street lighting during a power
outage would reduce visibility along streets and sidewalks.
14.6.3 Alternative 1: New Substation and 230 kV Transmission Lines
Impacts are described according to the major components associated with Alternative 1. The
substation impacts are described first, followed by transmission line options.
New Substation under Options A - D 14.6.3.1
14.6.3.1.1 Operational Trips
Maintenance and operation of the new substation would generate a small number of
employee trips. The substation could have ancillary uses such as storage for a small number
of trucks or staff facilities. Operational transportation impacts would be minor.
14.6.3.1.2 Equipment Delivery
A new substation would require infrequent (less than once a year) replacement of very large
equipment such as transformers, resulting in oversized loads being carried on surface streets
from regional freeways to the substation site. The same route and time of day restrictions
could be imposed by a City and/or WSDOT for such loads, as described previously in
construction impacts. Operational transportation impacts would be minor.
Option A: New Overhead Transmission Lines 14.6.3.2
When constructed, the transmission lines would be located overhead and physically separated
from transportation infrastructure and services. Transportation infrastructure disrupted during
construction would be restored prior to project operation, and would not typically generate
vehicle trips. However, the new transmission lines would need to be inspected occasionally,
generating a small number of trips. Should a transmission line require repairs, truck trips to
support those activities would be generated for a short period of time in a localized area.
Operational impacts to transportation are expected to be negligible.
Option B: Existing Seattle City Light 230 kV Transmission 14.6.3.3
Corridor
When constructed, the upgraded transmission lines would be located overhead and physically
separated from transportation infrastructure and services. The operational transportation
impacts would be similar to those described for Alternative 1, Option A.
January 2016 CHAPTER 14 TRANSPORTATION 14-17
PHASE 1 DRAFT EIS
Option C: Underground Transmission Lines 14.6.3.4
When constructed, the transmission lines would be located underground and physically
separated from transportation infrastructure and services. The operational transportation
impacts would be similar to those described in Alternative 1, Option A.
Option D: Underwater Transmission Lines 14.6.3.5
When constructed, the transmission lines would be located underwater and physically
separated from transportation infrastructure and services. The lines would be located at a
depth that would avoid potential impacts to boat traffic, anchors, etc., so no impacts are
anticipated. The operational surface transportation impacts would be similar to those
described in Alternative 1, Option A.
14.6.4 Alternative 2: Integrated Resource Approach
Energy Efficiency Component 14.6.4.1
No operational trips, and therefore no operational impacts to transportation, are anticipated as
a result of energy efficiency strategies.
Demand Response Component 14.6.4.2
Once installed, specialized devices to control customer usage do not typically generate
operational trips. Infrequent trips to support maintenance and repair of these devices would
be expected, but they would be widely dispersed over a large geographic area and over time,
and consistent with other site-specific routine maintenance activities. Operational impacts to
transportation are expected to be negligible.
Distributed Generation Component 14.6.4.3
Once installed, specialized devices to generate on-site electricity do not typically generate
operational trips. Operational impacts to transportation would be negligible, similar to those
described for demand response.
Energy Storage and Peak Generation Plant Components 14.6.4.4
Battery storage and peak generation plant facilities would have minor operational
transportation impacts similar to those described for the Alternative 1 substation.
14.6.5 Alternative 3: New 115 kV Lines and Transformers
Operational Trips Generated by Substations 14.6.5.1
Additional equipment installed at existing substation sites could slightly increase the
employees needed to operate those sites, and would also increase the substations’
maintenance needs. However, few additional operational trips are expected.
Operational Trips Generated by Transmission Lines 14.6.5.2
A small number of trips would occasionally be generated to support maintenance and repair
needs for additional transmission lines, similar to those described for Alternative 1, Option A.
CHAPTER 14 January 2016 14-18 TRANSPORTATION
PHASE 1 DRAFT EIS
14.7 WHAT MITIGATION MEASURES ARE AVAILABLE
FOR POTENTIAL IMPACTS TO TRANSPORTATION?
Since no significant operational impacts are identified for the project alternatives, no
mitigation measures would be needed. This section presents general mitigation measures
identified to avoid or reduce the potential transportation impacts expected to occur during
construction of Alternatives 1 or 3, and battery storage and peak generation plant facilities for
Alternative 2. No construction mitigation would be needed for the No Action Alternative.
Maintenance of Traffic Plans: The contractor would be required to prepare “maintenance of
traffic” plans for any work within the public right-of-way that affects vehicular, transit,
bicycle, or pedestrian traffic. These plans must show the location of traffic cones, traffic
control personnel, and signs; note if bus stops are to be closed or relocated; and indicate
special treatments for pedestrian and bicycle access.
Haul Routes: The contractor would need to coordinate with municipalities to determine
appropriate times of travel and haul routes for construction-generated truck traffic. Haul
routes generally would be on arterial streets through commercial areas and use the most
direct path to and from the state highway system.
Construction through an Intersection: Manual traffic control would be needed when
construction occurs through an intersection. Work in a signalized intersection may require
police officer control; work in an unsignalized intersection can typically be performed with
certified flaggers.
Construction across Driveways: Access to residential and commercial properties would
need to be maintained at all times. When trenching across a driveway, the work can usually
be done in two parts: trench across one-half of the driveway and then plate it for driving
before trenching the other half of the driveway. At major driveways, flagger control may be
needed to facilitate alternating enter and exit traffic. Special treatment would be needed for
developments that have split driveways (with one driveway serving entering traffic and one
serving exiting traffic) if traffic cannot easily be shifted to the other driveway for two-way
operation. The contractor would be required to coordinate with property owners when
driveways or alleys are affected by construction.
Signal Detection Disruption: Some intersections have in-pavement induction loops that
control traffic signal operations. Prior to trenching through these intersections, alternative
detection equipment (e.g., camera detectors) might need to be installed to maintain proper
signal function. Loops or permanent cameras would need to be installed as part of restoration.
Bus Stop Closure or Relocation: For bus stops that would need to be closed or relocated
during construction, the contractor would be required to coordinate with King County Metro
Transit, Sound Transit, or Community Transit.
Coordination with Other Projects: PSE must coordinate all construction needs and impacts
of this project with the other infrastructure and development projects in the combined study
January 2016 CHAPTER 14 TRANSPORTATION 14-19
PHASE 1 DRAFT EIS
area. This would typically be done as part of the permitting process with each community
affected by potential construction.
Pavement Restoration: Any pavement degradation that results from increased construction
truck traffic or excavation would need to be fully restored upon completion of construction
activities. This includes restoration of streets, curbs, gutters, sidewalks, parking lots,
driveways, and traffic signal induction loops where appropriate.
Education and Outreach: A public involvement program should be implemented prior to
project construction. It would provide information about the purpose and importance of the
project, and detailed information about the types and locations of expected construction
impacts and the measures that would be implemented to minimize those impacts. A
Construction Outreach Team may be desired, which would work closely with affected
residents and business owners to minimize construction-related impacts throughout the
duration of project construction. A contact person should be identified whom community
members can contact to address specific concerns both prior to and during project
construction.
14.8 ARE THERE ANY CUMULATIVE IMPACTS TO
TRANSPORTATION AND CAN THEY BE MITIGATED?
Cumulative transportation impacts could result from concurrent construction of other major
projects in the combined study area, including the SR 520 Bridge Improvement and Sound
Transit East Link Extension projects. PSE would be required to coordinate with all
jurisdictions in which construction activities would occur. As part of the construction
permitting process, agencies may require construction phasing or other coordination
strategies to minimize the potential cumulative transportation impacts of concurrent
construction projects.
14.9 ARE THERE ANY SIGNIFICANT UNAVOIDABLE
ADVERSE IMPACTS TO TRANSPORTATION?
With the appropriate mitigation measures in place, no unavoidable significant adverse
impacts to transportation are anticipated from either construction or operation of the Energize
Eastside Project alternatives.
CHAPTER 14 January 2016 14-20 TRANSPORTATION
PHASE 1 DRAFT EIS
CHAPTER 15. PUBLIC SERVICES
15.1 HOW WERE PUBLIC SERVICES IN THE COMBINED
STUDY AREA EVALUATED?
This chapter describes existing public services including
police, fire, and emergency response services located
within the combined study area (Alternatives 1, 2, and 3 as
depicted on Figure 1-4 in Chapter 1). The combined study
area spans large geographic regions that were reviewed
programmatically because specific project locations have
yet to be identified. The EIS Consultant Team identified
existing emergency response and police services by
reviewing local comprehensive plans for the study area
communities. Information on emergency response and
polices services was obtained from emergency service
provider’s website information, publicly available plans
and reports, and through interviews with representatives of
service providers.
The topic of environmental and public health, including
public safety and hazardous materials, is discussed in
Chapter 8.
15.2 WHAT ARE THE RELEVANT
PLANS, POLICIES, AND
REGULATIONS?
Public services within the study area communities are primarily managed and regulated by
state and local government agencies. The Washington State Growth Management Act
requires cities and counties to develop and adopt comprehensive plans that include long-
range planning for future public service needs. Among the required elements is a capital
facility plan element. The capital facility plan element must include an inventory of existing
facilities showing locations and capacities, forecasts of future needs, proposed locations and
capacities of new or expanded facilities, and a financing strategy (Revised Code of
Washington [RCW] 36.70A.070(3)).
Comprehensive plans for study area communities range from those containing basic
information primarily focused on meeting requirements under the Growth Management Act
(e.g., The Town of Beaux Arts Village, 2004) to inclusive documents containing a variety of
goals and policies related to the provision of police, fire, and emergency services with
references to master plans for associated equipment and facilities (e.g., City of Bellevue,
2015). All plans describe general provisions for fire and police protection services and
facilities, and some describe existing and ongoing regional coordination efforts to ensure
Public Services Key Findings
Existing local and regional
emergency services are
expected to be adequate to
address increased demand for
fire and emergency response
services; minor to moderate
impacts could occur. Impacts
on response times from
construction would also be
minor to moderate depending
on the alternative.
Although a significant impact
on public services could occur
if a pipeline leak or an
explosion resulted from the
project, the risk is minimized
by conformance with industry
standards, regulatory
requirements, and construction
and operational procedures
that address pipeline safety.
January 2016 CHAPTER 15 PUBLIC SERVICES 15-1
PHASE 1 DRAFT EIS
high levels of service through cost-effective means. Common goals expressed throughout the
study area plans are to ensure citizens’ feelings of safety and provide effective, efficient, and
equitable police, fire, and emergency services and facilities.
15.3 WHAT PUBLIC SERVICES ARE AVAILABLE IN THE
COMBINED STUDY AREA?
Emergency services include fire, emergency medical response, and police services, which are
provided by cities, counties, and emergency medical providers throughout the combined
study area. Individual communities may have their own police and fire departments or may
contract with other jurisdictions, such as adjacent cities or the county, to provide the services.
15.3.1 Fire and Emergency Response Services
Providers, Levels of Service, and Response Times 15.3.1.1
Table 15-1 summarizes fire and emergency services providers in the combined study area.
The Cities of Bellevue, Kirkland, Redmond, and Renton have their own fire departments that
provide fire and emergency medical services. The Bellevue Fire Department also provides
fire and emergency medical services for Newcastle, Hunts Point, Yarrow Point, Clyde Hill,
Medina, and Beaux Arts Village. Eastside Fire and Rescue provides fire and emergency
services to Issaquah and Sammamish and unincorporated areas of King County within the
combined study area. Multiple fire stations are located throughout the service areas to ensure
timely response to emergency calls. For large incidents, fire departments from outside of the
combined study area could be dispatched as backup (Anderson, personal communication,
2015).
Table 15-1. Fire and Emergency Medical Services (EMS) Provider for Each
Community
Fire and EMS Service Provider Community Served
Bellevue Fire Department Bellevue, Newcastle, Hunts Point, Yarrow Point,
Clyde Hill, Medina, Beaux Arts Village, and much of
east King County (for Medic One ALS)
Eastside Fire and Rescue Issaquah, Sammamish, King County
Kirkland Fire Department Kirkland
Redmond Fire Department Redmond, and northeast King County (for Medic
One ALS)
Renton Fire and Emergency Services
Department
Renton
King County Public Health – Seattle &
King County
Renton and south King County (for Medic One ALS)
Sources: Bellevue Fire Department 2015; Eastside Fire and Rescue 2015; Redmond Fire Department 2015;
Renton Fire and Emergency Services Department 2015; King County Medic One 2015.
CHAPTER 15 January 2016 15-2 PUBLIC SERVICES
PHASE 1 DRAFT EIS
Hospitals and emergency medical facilities are located throughout the combined study area.
One such facility is Overlake Hospital Medical Center in Bellevue, a level III trauma center.
The Bellevue Fire Department, Redmond Fire Department, and King County Public Health –
Seattle & King County provide advanced life support (ALS) and transport services for the
Medic One/Emergency Medical Services (EMS) program, which runs out of Overlake
Hospital. Bellevue Fire Department operates four paramedic ALS units that serve Bellevue
and much of east King County; Redmond Fire Department operates three ALS units that
serve northeast King County and King County operates eight ALS units that serve Renton
and south King County.
In addition to fire suppression and emergency medical response, fire departments in the
combined study area also have training and equipment to provide hazardous materials spill
response and rescue services. Regional emergency response capacity includes rope, confined
space, near surface and swift water, hazardous material, trench, advanced vehicle, and
structural collapse rescue. Responders can be trained at the operations level and the
technician level. First responders at the operations level protect nearby persons, property, or
the environment from the effects of the emergency. Technician responders receive additional
training and assume a more central role in that they perform physical rescues or attempt to
abate or arrest the cause for emergency. Responders within the departments pursue
technician- and operations-level training on a regular basis. In the event of a major incident,
rescuers and specialized response units from throughout the region arrive to ensure full
capacity (Moulton, personal communication, 2015a; Turner, personal communication, 2015).
Throughout the combined study area, individual fire departments set levels of service and
target response times. Levels of service standards generally refer to a number of units per
member of the public (units can be measured in numbers of firefighters, fire engines, fully
equipped response components, or another measure). Levels of service standards can also be
used to determine the number of fire facilities needed per geographic service area. The
response time is the time interval from receipt of the alarm at the primary public safety
answering point (PSAP) to when the first emergency response unit is initiating action or
intervening to control the incident. Targets vary depending on the nature of the incident (fire,
life support, or other) and level of risk to public safety (low versus high). Within the
combined study area, response targets vary but are generally 10 minutes or under, according
to information available in comprehensive plans, master plans, and reports (Eastside Fire and
Rescue, 2013; City of Renton, 2015; City of Redmond, 2011; City of Bellevue, 2014).
The EIS Consultant Team interviewed representatives of fire departments within the
combined study area to determine the departments’ ability to quickly and effectively respond
to fires and medical emergencies that could potentially be associated with the type of
facilities considered for the project proposal (Bunting, personal communication, 2015).
Interview questions included whether the department is currently meeting response targets;
whether the department has the ability to respond to incidents involving electrical facilities,
including downed 115 kV and 230 kV transmission lines, and substation fires and explosions;
whether there are different levels of complexity in responding to each scenario; and how the
department coordinates with PSE (see Appendix K for interview questions). Departments
were also interviewed to determine their ability to respond to a fire or explosion along the
Olympic Pipeline, including training and response protocols. Responses were used to
January 2016 CHAPTER 15 PUBLIC SERVICES 15-3
PHASE 1 DRAFT EIS
determine whether departments have adequate capacity to effectively respond to the range of
emergencies that could occur under the alternatives.
Fire departments throughout the combined study area reported meeting level of service and
response time targets for various types of emergencies, including emergency medical and
other incidents (Moulton, personal communication, 2015a; Walgren, personal
communication, 2015; Bunting, personal communication, 2015; and Turner, personal
communication, 2015), with the exception of Eastside Fire and Rescue who fell just short of
a structural fire response target by “literally seconds” in 2014 (Tryon, personal
communication, 2015). When an emergency is reported and fire and emergency services are
needed, the request for services is routed through one of three dispatch systems in King
County. If available resources are limited due to a high volume of incident reporting (such as
during heavy storms), response times may take “a little longer” (Bunting, personal
communication, 2015). The Bellevue Fire Department is unique in that it is accredited by the
Commission on Fire Accreditation International (CFAI); an element considered in the
accreditation process is meeting response time targets (Moulton, personal communication,
2015a).
Electrical Incidents 15.3.1.2
Fire departments reported using standard operating procedures to respond to live electrical
fires, including downed 115 kV and 230 kV overhead transmission lines on houses and
across rights-of-way (Moulton, personal communication, 2015a). Emergency response is
coordinated with the utility purveyor through a dispatch system. The fire department and
utility purveyor are dispatched simultaneously: Fire department first responders secure the
scene and prevent access to the hazard area; and the utility purveyor disconnects or otherwise
addresses utility service to the affected equipment. To resolve the emergency, the fire
department proceeds to manage fire and emergency medical response, and the utility
purveyor manages technical aspects of the emergency, including returning service to
customers (Moulton, personal communication, 2015a; Walgren, personal communication,
2015; Bunting, personal communication, 2015; Turner, personal communication, 2015; and
Tryon, personal communication, 2015).
Fire departments generally responded that no significant difference exists in their approach to
a 230 kV versus a 115 kV incident. A perimeter is secured and the utility purveyor is
dispatched to address the utility-specific issue (Moulton, personal communication, 2015a;
Walgren, personal communication, 2015; Bunting, personal communication, 2015; Turner,
personal communication, 2015; and Tryon, personal communication, 2015). One fire
department responded that a greater capacity for harm and damage exists when more power
is overhead, and the response would involve securing a larger perimeter than would be
secured for lower-power incidents (Moulton, personal communication, 2015a). Generally, the
capacity for harm and damage can be minimized if operating under large overhead wires can
be avoided (Moulton, personal communication, 2015a). Response actions also include
ensuring that adequate resources are deployed to address the incident, such as dispatching
additional fire units to the scene and ensuring that law enforcement is present to help isolate
the area and direct traffic (Anderson, personal communication, 2015). The fire departments
interviewed reported adequate training and capability to respond to live electrical fires, with
CHAPTER 15 January 2016 15-4 PUBLIC SERVICES
PHASE 1 DRAFT EIS
the provision that PSE also responds with specialized knowledge that enables them to safely
address the incident (Moulton, personal communication, 2015a; Walgren, personal
communication, 2015; Bunting, personal communication, 2015; Turner, personal
communication, 2015; and Tryon, personal communication, 2015).
If there is a fire at a substation, either electrical or oil, PSE sends the appropriately qualified
personnel to meet fire department crews on site. If the responding fire department requires
additional resources, such as a foam truck from the Port of Seattle, they contact those
resources for assistance in responding to the fire (Strauch, personal communication, 2016).
Pipeline Fire or Explosion 15.3.1.3
The Olympic Pipe Line Company (OPLC) Facility Response Plan (FRP) provides guidelines
to respond to a spill from the Olympic Pipeline, and supplements responders’ training and
experience during an actual response. Study area communities located along the pipeline
corridor have adopted emergency response plans outlining procedures for responding to
pipeline incidents (Anderson, personal communication, 2015). In the event of a pipeline
rupture or explosion that requires services such as rescue, evacuation, traffic control,
hazardous materials cleanup, etc., the first responders will immediately attempt to establish a
safe perimeter and will conduct emergency response activities described above. However,
response steps that occur following securing the perimeter could be more extensive than for
other emergencies, depending on the magnitude of the incident.
For a large incident involving the Olympic Pipeline, the fire department and OPLC technical
staff would be contacted simultaneously (Anderson, personal communication, 2015). Fire
departments within other jurisdictions could be dispatched as backup, as could OPLC, Port of
Seattle Fire Department, and Boeing for backup equipment and fire suppression supplies
(Anderson, personal communication, 2015; Strauch, personal communication, 2016). The
Incident Commander of the Fire Department and OPLC would collaborate, along with other
affected jurisdictions, to form a multijurisdictional unified command (Anderson, personal
communication, 2015). Adopted tactics, unified management of the incident, along with
management of the perimeter and public safety, would be employed (Anderson, personal
communication, 2015).
Both the Bellevue Fire Department and Redmond Fire Department reported having
petroleum-absorbent boom systems that could be employed should petroleum products be
spilled in a waterway (Anderson, 2015, personal communication; Moulton, personal
communication, 2015b). The booms could be used to stop the flow and expansion of the spill,
as well as siphon up the product. They also have the means to monitor and contain flow of
petroleum products in the sewer system. The response to a fuel leak in the water system is the
same as in other situations: locate the leak, contain the incident, and work collaboratively to
address the incident. Bellevue Fire Department engines, ladder companies, and hazardous
materials response vehicle all have the necessary monitoring instrumentation to permit
ongoing evaluation of flammable materials (Moulton, personal communication, 2015b).
Interview respondents indicated that within the last 16 years following the Olympic Pipeline
explosion in Whatcom County, many precautionary measures have been taken to increase
safety and avoid a pipeline fire or explosion (Anderson, personal communication, 2015;
January 2016 CHAPTER 15 PUBLIC SERVICES 15-5
PHASE 1 DRAFT EIS
Moulton, personal communication, 2015b). Stronger laws are in place that require monitoring
for digging that occurs near the pipeline (Anderson, personal communication, 2015). Also,
pressure changes and flow levels within the pipeline are continuously measured to identify
possible leaks, allowing OPLC to address the issue before an incident occurs (Anderson,
personal communication, 2015). To monitor for leaks and ensure unauthorized digging is not
occurring, OPLC flies the pipeline corridor once per week to check for discoloration of the
grass or other anomalies and to ensure unauthorized digging is not occurring within the
easement (Anderson, personal communication, 2015). Additionally, product shut-off valves,
located at a distance of up to 5 miles, previously were turned by hand only, but are now
automated so product flow can be shut off remotely and immediately (Anderson, 2015;
Moulton, personal communication, 2015b).
In the event of other utility-related incidents, such as a natural gas line rupture or explosion,
the fire department would contact PSE and follow a protocol similar to other incidents:
secure the perimeter, isolate the incident, and deny entry to the hazardous area. When the
incident is capable of causing a widespread safety concern, additional units from surrounding
jurisdictions are employed to contain and manage the incident. The affected utility and fire
department are informed of the incident simultaneously. The utility company disconnects
service to the area and is dispatched to the scene to coordinate with the Incident Commander,
Chief Commander, or another designated fire department official. The affected utility and fire
department establish an action plan and engage in emergency management activities (Tryon,
personal communication, 2015; Moulton, personal communication, 2015a).
15.3.2 Police Services
Table 15-2 summarizes police service providers in the combined study area. Study area
communities primarily rely on municipal police departments for police services. County
sheriff departments serve the unincorporated King County area, while local municipal police
departments typically serve incorporated cities and towns; some cities contract with the
County or another city to provide police service. The Medina Police Department provides
law enforcement services for both Medina and Hunts Point. Newcastle, Beaux Arts Village,
and Sammamish contract with the King County Sheriff’s Office, which also provides police
services for unincorporated King County within the study areas.
Many local fire and police agencies now have mutual response agreements, which allow
public safety responsibilities to be shared across jurisdictional boundaries. This is especially
helpful in emergency situations when sheriff departments are unable to respond in a timely
manner, particularly in unincorporated “islands” where city departments may have staff close
by who are available to respond.
CHAPTER 15 January 2016 15-6 PUBLIC SERVICES
PHASE 1 DRAFT EIS
Table 15-2. Law Enforcement Provider for Each Community
Law Enforcement Provider Community Served
Bellevue Police Department Bellevue
Clyde Hill Police Department Clyde Hill, Yarrow Point
Issaquah Police Department Issaquah
Kirkland Police Department Kirkland
King County Sheriff’s Department Newcastle, King County, Beaux Arts Village,
Sammamish
Medina Police Department Medina, Hunts Point
Redmond Police Department Redmond
Renton Police Department Renton
Sources: Bellevue Police Department 2015; Clyde Hill Police Department 2015; Issaquah Police
Department 2015; Kirkland Police Department 2015; King County Sheriff’s Department 2015; Medina
Police Department 2015; Redmond Police Department 2015; Renton Police Department 2015
Electric transmission corridors and substations are located throughout the combined study
area. The EIS Consultant Team interviewed representatives from major police departments
within the combined study area to determine whether they have observed an increased rate of
reported crime within the transmission corridors and substations in their service areas
(Appendix L). Except for a few incidents of theft of ground wires in a utility corridor no
other incidents of unique crime-related problems associated with existing electricity
substations or transmission corridors (Farman, personal communication, 2015; Irvine,
personal communication, 2015; Parks, personal communication, 2015; and Trader, personal
communication, 2015). According to the interview respondents, no problems with graffiti,
illegal drug sales and use, or other disorderly or illegal behavior were reported in these areas
by police patrols. None of the interview respondents expected that the level of crime would
change depending on whether a transmission line corridor was located in an urban or rural
location.
Similarly, none of the respondents suggested that there are existing problems with electric
substations as places that attract crime, such as graffiti or other property crimes. Respondents
stated that no notable difference in crime is likely whether a substation is located within a
densely populated area versus a low-density area. Online crime data and mapping reflect that
littering, graffiti, theft, and other crime are not disproportionately reported in utility corridors
or substations (PublicStuff, 2015).
The response from study area police departments is consistent with available research, which
indicates that crime associated with electrical facilities is generally directed at power theft
rather than property crime or violent crime (Depuru et al., 2011). However, petty metal theft
at electrical utility sites also occurs (Kooi, 2010). Overall, published research focusing on
crime occurring in transmission line corridors and at substations is not as well documented.
January 2016 CHAPTER 15 PUBLIC SERVICES 15-7
PHASE 1 DRAFT EIS
15.4 HOW WERE POTENTIAL IMPACTS TO PUBLIC SERVICES ASSESSED?
Potential effects on public services were determined by reviewing comprehensive plans and
policies of each jurisdiction, conducting phone interviews with the major police and fire
departments, and reviewing published literature on the topic of corona interference. Factors
considered for the analysis of construction effects included increased demands on emergency
services, and the project’s potential to alter or hinder the timely provision of emergency
services or other public services during construction. Factors considered for the analysis of
operational effects include an increased demand for emergency services, and the ability of
emergency services to respond to potential fires and accidents at proposed electric facilities.
This analysis address both fire and accident risks confined to electrical facilities, and risks
that electrical facilities could have for other nearby or co-located utilities. The potential for
facilities included under the alternatives to attract crime and result in increased demand for
police services was also addressed.
Based on the potential change to property values described in Chapter 11, this chapter also
identifies the potential range of impacts to tax revenue and how that could affect the cities’
ability to continue to provide the same level of public services (FCS Group, 2016).
For this analysis, the magnitude of project-related impacts are classified as being minor,
moderate, or significant as follows:
Minor – Conformance with industry standards and regulatory requirements, and
implementation of project design, would address potential adverse impacts such that there
would be little likelihood of adverse effects. While there could be some temporary or short-
term increase in demands on public services requiring local response from public service
providers, or localized temporary or short-term changes in response times, there would be no
long term changes.
Moderate – Conformance with industry standards and regulatory requirements, and
implementation of project design, would address most potential adverse effects, but some
reasonable potential for adverse effects would remain. Temporary or short-term increase in
demands on public services could require regional response providers to assist local response.
Temporary or short term changes in response times would be noticeable and may require
providers to make service adjustments, but there would be no long term changes.
Significant –Even with conformance with industry standards and regulatory requirements,
and implementation of project design, adverse impacts are likely. Impacts are also considered
significant if there would be permanent increase in demand, or changes in response times,
that could tax the ability to provide adequate fire protection services, emergency response
services, and law enforcement services.
CHAPTER 15 January 2016 15-8 PUBLIC SERVICES
PHASE 1 DRAFT EIS
15.5 WHAT ARE THE LIKELY CONSTRUCTION IMPACTS
RELATED TO PUBLIC SERVICES?
15.5.1 Construction Impacts Considered
Increased Demand for Emergency Services 15.5.1.1
Construction of the new transmission lines, expanded substations, distributed generation,
generators, and energy storage facilities could temporarily increase demand for emergency
services. The discussion of construction impacts considers the demand created for fire,
police, or medical response services if any of the following emergency incidents occurred:
• Injury or fire due to a construction accident;
• Spill of hazardous materials;
• Damage to an existing natural gas pipeline or the Olympic Pipeline; or
• Theft of materials or equipment.
See also Chapter 8 for discussion of potential pipeline rupture risks.
Changes in Response Times 15.5.1.2
To varying degrees, construction could result in increased congestion along adjacent
roadways as a result of temporary reductions in available lane width for travel, changes from
signalized to manual intersection control, roadway closures, detours, and general construction
activities associated with the project. This could temporarily affect access and response times
for public service providers.
15.5.2 No Action Alternative
Under the No Action Alternative, maintenance activities would occur and could intensify, but
they would not involve a significant increase in demand for emergency services. Occasional
conductor replacement, implementation of new technologies not requiring discretionary
permits, and installation of distributed generation facilities under PSE’s conservation
program would require minor construction activities. Construction impacts on public services
would be negligible.
15.5.3 Alternative 1: New Substation and 230 kV Transmission Lines
Impacts are generally described according to the major components associated with
Alternative 1 (substation impacts first, followed by transmission line impacts).
Option A: New Overhead Transmission Lines 15.5.3.1
Increased Demand for Emergency Services 15.5.3.1.1
Fire department service calls could increase related to inspection of specific construction
projects and to respond to potential construction-related accidents, injuries, and spills. Site
preparation and construction of new electric infrastructure could also increase the risk of an
accidental fire requiring a response by the fire department. If construction-related accidents,
January 2016 CHAPTER 15 PUBLIC SERVICES 15-9
PHASE 1 DRAFT EIS
injuries, spills, or fires were to occur, PSE personnel and the local fire departments are
trained to respond.
Fire department response would also be required if construction equipment or activity
damaged nearby natural gas or petroleum pipelines. The Olympic Pipeline crosses near the
Lakeside substation and follows the same corridor as PSE’s 115 kV easement, within the
service areas for Bellevue Fire Department and Redmond Fire Department. In addition,
several high-pressure gas mains cross PSE’s easement, and gas mains are also located in
other portions of the study area. If those lines were not properly identified and located prior
to construction (through review of utility maps, coordination with utilities, or fieldwork to
precisely locate them), they could be damaged during construction and leak, potentially
leading to an explosion if leaked material encountered an ignition source, as described in
Chapter 8.
A potential significant adverse impact on public services could occur if a rupture and
explosion of a pipeline occurred requiring response from both local and regional emergency
service providers. Depending on the magnitude of the incident, the response could be large
and involve multiple regional agencies and responders. However, as described in Chapters 8
and 16, conformance with industry standards and regulatory requirements would ensure that
potential hazards are identified and design plans developed to minimize adverse effects from
these hazards to minor levels. Because existing local service providers are expected to be
adequate to address increased demand for fire and emergency response services for
construction–related incidents that could occur under Alternative 1, Option A, impacts on
emergency services would be minor.
Service calls to police departments could increase during construction due to construction site
theft and vandalism. The increase is expected to be minor, and existing police department
staff and equipment are anticipated to be sufficient.
Changes in Response Times 15.5.3.1.2
If the 230 kV transmission lines were constructed in road rights-of-way, emergency response
would potentially be able to access the construction sites more quickly than in an off-road
corridor.
Construction of a new 230 kV substation yard to accommodate a new transformer could
include temporary street closures and detours. Construction of the overhead lines would
require installation of utility poles along a project length of at least 18 miles, some of which
would likely be adjacent to roadways. For these areas, transmission lines installed overhead
could require vehicle closures near the pole construction sites. During the period in which
wire is pulled, no vehicular traffic would be allowed on roadways located beneath the areas
of pulling activity. These delays and closures could delay response by requiring emergency
service and other public service providers to use a less direct route, or by increasing traffic
congestion such that vehicles are forced to reduce their speeds. Implementation of measures
described in Chapter 14, Section 14.7, would be effective in ensuring that impacts on
response times would be minor.
CHAPTER 15 January 2016 15-10 PUBLIC SERVICES
PHASE 1 DRAFT EIS
Option B: Existing Seattle City Light 230 kV Transmission 15.5.3.2
Corridor
Increased Demand for Emergency Services 15.5.3.2.1
As with Alternative 1, Option A, construction could occur in the vicinity of regional natural
gas pipelines or smaller pipelines that supply natural gas to homes and businesses. Although
the transmission lines would, in large part, be located in or near the existing SCL corridor,
that corridor does cross a PSE high-pressure gas main and the Olympic Pipeline several times
as described in Chapter 16, and other gas utilities may also be present in the area. As
described for Option A, a rupture and explosion, if it were to occur, could constitute a
significant adverse impact due to the increased demand for emergency services. However,
conformance with industry standards and regulatory requirements would ensure that potential
hazards are identified and design plans developed to minimize adverse effects from these
hazards to minor levels. Because existing local service providers are expected to be adequate
to address increased demand for emergency response services for construction–related
incidents that could occur, impacts on emergency services would be the same as Option A
(minor).
Changes in Response Times 15.5.3.2.2
Since Alternative 1, Option B would include rebuilding or replacing existing poles and other
structures, and pulling new transmission wire, the types of construction impacts on response
times would be similar to those described for installing new overhead transmission lines in
Option A. If constructed along road rights-of-way, the new transmission segment connecting
the transmission lines to the Lakeside substation could result in localized impacts on
responders. With implementation of measures described in Chapter 14, Section 14.7, impacts
on response times would be the same as Option A (minor).
Option C: Underground Transmission Lines 15.5.3.3
Increased Demand for Emergency Services 15.5.3.3.1
The types of emergency services potentially needed for construction of an underground line
would be the same as for construction of an overhead line. If the underground line was
constructed in the existing PSE 115 kV easement under Alternative 1, Option A or SCL
easement under Option B, this option would potentially require the same emergency service
response as described for Options A and B, should an accidental rupture and explosion of a
high-pressure gas main or the Olympic Pipeline occur during construction. Given the greater
amount of ground disturbance associated with constructing an underground line, the potential
risk would be higher relative to an overhead line. Nonetheless, conformance with industry
standards and regulatory requirements would ensure that potential hazards are identified and
design plans developed to minimize adverse effects from these hazards. Due to the increased
area of ground disturbance, the probability of impacts would be somewhat higher than
described for Alternative 1, Options A and B, but still considered low, and anticipated
impacts are expected to be minor to moderate.
Changes in Response Times 15.5.3.3.2
As with Alternative 1, Option A, if an underground line is constructed in road rights-of-way,
emergency response would potentially be able to access the construction sites more quickly
January 2016 CHAPTER 15 PUBLIC SERVICES 15-11
PHASE 1 DRAFT EIS
than in an off-road corridor. Impacts on response times from construction activity affecting
roadways would be similar to those described for overhead construction. However, with
Option C the impacts would be less localized, likely extending along continuous lengths of
one block or longer rather than only at pole locations, potentially causing more traffic
disruption. With implementation of measures described in Chapter 14, impacts on response
times would be expected to be minor to moderate.
Option D: Underwater Transmission Lines 15.5.3.4
Increased Demand for Emergency Services 15.5.3.4.1
In addition to the types of emergency services described for an overhead or underground line,
construction of an underwater line could potentially require special emergency services to
respond to an in-water accident, such as a spill. Although unlikely to occur, local fire
departments have capabilities to respond to in-water spills and other accidents. With
implementation of measures described in Chapter 8 and Chapter 16, impacts on emergency
services are expected to be minor.
Changes in Response Times 15.5.3.4.2
At the land connections, response time impacts would be the same as those described for
Alternative 1, Option A, if overhead and Option C, if underground, (minor), but would be
expected to affect smaller localized areas.
15.5.4 Alternative 2: Integrated Resource Approach
Potential construction impacts under Alternative 2 would be much more limited than
Alternative 1 because less construction of new infrastructure would be necessary.
Energy Efficiency and Demand Response Components 15.5.4.1
Strategies to promote energy efficiency and installation of demand response devices would
not increase the demand for construction-related emergency services.
Demand Response Component 15.5.4.1
Demand response is an end-user strategy that pertains more to customer usage patterns and
requires little construction of new infrastructure and would not increase the demand for
construction-related emergency services.
Distributed Generation Component 15.5.4.2
Installation of devices to generate on-site power would require minor construction activities
primarily on single residential and commercial sites. Construction impacts on public services
would be negligible.
Energy Storage Component 15.5.4.3
Construction of large battery storage facilities would require activities similar to a substation,
with potential impacts on public services the same as those described for Alternative 1
substation construction (minor).
CHAPTER 15 January 2016 15-12 PUBLIC SERVICES
PHASE 1 DRAFT EIS
Peak Generation Plant Component 15.5.4.4
Construction of peak generation plants would require construction similar to a substation, but
would likely also require replacing or extending major gas mains for natural gas supply.
Nonetheless, existing local service providers are expected to be adequate to address increased
demand for fire and emergency response services for construction–related incidents that
could occur. As a result, impacts would be the same as those described for Alternative 1
substation construction (minor).
15.5.5 Alternative 3: New 115 kV Lines and Transformers
Increased Demand for Emergency Services 15.5.5.1
Increased demand for emergency response associated with adding transformers at three
existing substations and rebuilding or expanding five existing substations would be similar in
type to the impacts associated with building a new substation, as described for Alternative 1.
However, Alternative 3 would involve more sites than Alternative 1 and would potentially
involve greater distances from some substations to fire departments and hospitals.
Alternative 3 would require a longer transmission line alignment (60 miles as opposed to 18
miles) and could slightly increase the demand for emergency services over a longer duration
compared to overhead lines under Alternative 1, Option A and Option B. Also, construction
for Alternative 3 would potentially occur in less urbanized areas than Alternative 1. The need
for emergency response during construction in less urban areas would potentially have
greater impacts on existing overall emergency response services because of potentially less
well equipped local fire departments and the longer distances to public service facilities and
mutual aid fire departments that may need to be dispatched to construction areas.
Nonetheless, any increased demand for emergency services would be temporary and short-
term, and local and regional emergency response providers in the study area would be
capable of responding to construction-related incidents. Therefore, impacts on emergency
services would be minor to moderate.
As with Alternative 1, construction could occur in the vicinity of the Olympic Pipeline, and
regional natural gas pipelines or those that supply natural gas to homes and businesses, and
would potentially require the same emergency service response as described for Alternative
1, Options A, B, and C in the unlikely event an accidental rupture and explosion of a pipeline
occur during construction. Conformance with industry standards and regulatory requirements
would ensure that potential hazards are identified and design plans developed to minimize
adverse effects from these hazards to minor levels.
Changes in Response Times 15.5.5.2
Potential response impacts associated with adding transformers at three existing substations
and rebuilding or expanding five existing substations would be similar in type to the impacts
associated with building a new substation, as described for Alternative 1. However,
Alternative 3 would involve more sites than Alternative 1 and would potentially have greater
response impacts due to temporary road closures.
January 2016 CHAPTER 15 PUBLIC SERVICES 15-13
PHASE 1 DRAFT EIS
Potential response time impacts associated with construction and installation of new 115 kV
transmission lines would be similar in type to the impacts described for new 230 kV
transmission lines in Alternative 1, Option A. Lane closures, other traffic revisions, and
construction staging areas could affect travel times for public service providers. Compared to
Alternative 1, more transmission lines would be installed over a larger area under
Alternative 3; therefore, the response time impacts are expected to be more widespread. With
implementation of measures described in Chapter 14, Section 14.7, impacts on response
times would be expected to be minor to moderate.
15.6 HOW COULD OPERATION OF THE PROJECT
AFFECT PUBLIC SERVICES?
15.6.1 Operation Impacts Considered
Operation of new transmission lines, expanded substations, distributed generation,
generators, and energy storage facilities associated with the alternatives could increase
demand for emergency services in the study areas. The discussion of operation impacts
considers the demand created for fire, police, or medical response services if any of the
following emergency incidents occurred:
• Fire due to equipment malfunction;
• Spill of hazardous materials;
• Damage to an existing pipeline (from natural phenomena, or maintenance and
operations activities); and
• Vandalism of equipment, structures, or property.
The potential for corona-ions from transmission lines to interfere with police and emergency
communication or devices was often cited as a concern during the scoping process and is also
addressed in this section.
See also Chapter 8 for discussion of potential health effects related to the proposed
improvements.
15.6.2 What is corona-ion interference and is it a concern?
Corona can occur at the surface of an overhead high-voltage transmission line conductor,
when the electric field intensity at the surface of the conductor exceeds a threshold (the
breakdown strength of air). When this situation occurs, a very small electrical discharge is
generated that can create audible noise and radio frequency noise, such as those used by fire
and emergency responders. Corona effects on high-voltage transmission lines have been
studied for over 60 years and engineers take steps in the design of overhead transmission
lines to limit corona activity to acceptable levels (EPRI, 1982). Interference from corona-
generated noise is generally associated with lines operating at voltages of 345 kV or higher
(Enertech, 2015).
CHAPTER 15 January 2016 15-14 PUBLIC SERVICES
PHASE 1 DRAFT EIS
Corona is affected by the local electric field at the surface of the conductor (called the surface
gradient). The conductor surface gradient is affected by many factors, including the
conductor size, voltage of the line, smoothness or irregularities (such as nicks on the
transmission line conductor, water droplets, insects, or debris) on the surface of the
conductor, phase configuration, location of other energized conductors, distance to ground,
etc. For new projects, such as the Energize Eastside Project, electrical engineers will usually
design overhead transmission lines to comply with recommended maximum conductor
surface gradient values set forth in the Institute of Electrical and Electronics Engineers
(IEEE) Radio Noise Design Guide for High-Voltage Transmission Lines (IEEE, 1971). The
design guide is applicable to overhead AC transmission lines in the voltage range of 115 kV
to 800 kV. This design guide is a valuable tool in the design of overhead high-voltage
transmission lines because it gives guidelines for acceptable electrical parameters (conductor
surface gradients) that engineers can use to evaluate design options. The IEEE guide is based
on many years of research and practical experience. Engineers can control the conductor
gradients by selection of conductor size (larger conductors have lower gradients), phase
spacing and arrangement, and sometimes by bundling (use of multiple conductors per phase
lowers the surface gradient).
Gap discharges (where electricity crosses tiny gaps between mechanically connected parts)
can also generate noise. Generally, higher voltage transmission lines (such as the 115 kV and
230 kV transmission lines associated with the Energize Eastside Project) do not produce
noise due to gap discharges, since these lines would be constructed with modern hardware
that eliminates such problems and therefore minimizes gap noise. Gap discharges are
typ ically more common on lower-voltage distribution lines, caused by loose hardware and
wires (Enertech, 2015).
Communication interference is dependent upon the frequency of the system in use, the
relative locations of the transmitters and receivers with respect to one another, and other
parameters (Enertech, 2015). Overhead transmission lines do not, as a general rule, interfere
with radio or TV reception. Corona-generated radio frequency noise decreases with distance
from a transmission line and also decreases with higher frequencies. Whenever corona is a
problem, it is usually for amplitude modulation (AM) radio and not the higher frequencies
associated with frequency modulation (FM) radio or TV/satellite signals. Generally most
modern fire and emergency responder communication systems (such as mobile-radio
communications) utilize either FM or digital signals that are not affected by transmission line
corona. In addition, interference is unlikely with other communications devices such as cell
phones and GPS units that operate with digital signals at much higher microwave
frequencies.
In the U.S., electromagnetic interference from transmission systems is governed by the
Federal Communications Commission (FCC), which requires the operator of any device that
causes “harmful interference” to take prompt steps to eliminate it (FCC, 1988). Transmission
line owners are also required to resolve interference complaints from licensed operators in
accordance with FCC Rules and Regulations (47 CFR Part 15). Electric power companies
have been able to work well under the present FCC rule because harmful interference can
generally be eliminated. It has been estimated that more than 95 percent of power line
sources that cause interference are due to gap-type discharges. These can be found and
January 2016 CHAPTER 15 PUBLIC SERVICES 15-15
PHASE 1 DRAFT EIS
completely eliminated when required to prevent interference (USDOE, 1980). Complaints
related to corona-generated interference occur infrequently.
15.6.3 No Action Alternative
If a fire, explosion, or spill were to occur along the existing transmission line or at a
substation as a result of an earthquake, storm, or accident (as described in Chapter 8), there
would be a need for emergency response. The need for emergency services would the same
as described for construction under Alternative 1. The potential risk of transformer
overheating associated with system overload during peak periods would be expected to
increase under the No Action alternative, if system capacity is not increased. More frequent
system overloading could increase the potential for transformers to catch fire or explode, with
accompanying potential safety hazards. These hazards would be managed by load shedding
and increased outages under the No Action Alternative.
The proximity of natural gas mains and the two Olympic Pipeline regional lines to the
existing 115 kV transmission line through PSE’s easement presents a potential operational
hazard during PSE maintenance activities, such as conductor replacement near these utility
lines. If an accidental rupture and explosion of a pipeline occurred during conductor
replacement or other maintenance activities near these utility lines, an explosion would
constitute a significant adverse impact due to the increased demand for local and regional
emergency services. However, as described in Chapters 8 and 16, conformance with industry
standards and regulatory requirements ensure that potential hazards are identified and
operations and maintenance procedures in place to minimize adverse effects from these
hazards to minor levels. Because existing local service providers are expected to be adequate
to address the demand for fire and emergency response services for most operations and
maintenance-related incidents that could occur under the No Action Alternative, impacts on
emergency services would be minor.
Public service providers and facilities require continuous and reliable supplies of electricity.
Under the No Action Alternative, maintenance of existing electrical facilities would likely
increase, possibly causing brief interruptions or outages of electrical service. However, these
would be planned events with advance notification, and if necessary, public service providers
could employ backup generators during outages.
As described in Chapter 2, the risk of interruptions or outages of electrical service would
grow under the No Action Alternative. In a sudden, unplanned loss of electricity, emergency
response facilities are the highest priority for maintaining power during an outage, and they
are equipped with backup power supplies. During load shedding, PSE’s approach is to have
rolling blackouts, where one area is subject to outages for a few hours, then another area is
affected. As a result, only minor impacts on emergency response capabilities are anticipated.
Full restoration from a large-scale power outage would likely take several hours. During this
time, there could be an increased demand for emergency services to respond to accidents,
fires, or other incidents that could occur if traffic controls or alarm systems that do not have
backup generators stop functioning.
CHAPTER 15 January 2016 15-16 PUBLIC SERVICES
PHASE 1 DRAFT EIS
15.6.4 Alternative 1: New Substation and 230 kV Transmission Lines
Impacts are generally described according to the major components associated with
Alternative 1 (substation impacts first, followed by transmission line impacts).
Option A: New Overhead Transmission Lines 15.6.4.1
Increased Demand for Fire Services 15.6.4.1.1
The demand for fire department services associated with equipment at the new substation that
presents a fire risk could increase relative to the No Action Alternative. The following
paragraphs describe potential scenarios that could result in a fire at a new or expanded
substation. While an increase in fire demand response is possible, it is not expected to be
significant relative to the ability of the fire departments to respond to such emergencies. With
implementation of measures described in Chapters 8 and 16, impacts on fire services are
expected to be minor. Operational environmental health and hazardous materials impacts of
the substation alternatives are discussed in Chapter 8.
Oil-insulated equipment, such as capacitors, transformers, and inductors, has been known to
cause fires at substations. Oil is used to insulate electrical equipment because it is more
effective than air as an insulator, and it allows equipment to be more compact and placed
closer together or underground. Oil insulation comes with the risk that when an element (for
example, a capacitor) becomes overheated, the oil can convert to a gaseous state and, if it
leaks and is exposed to sparks or high heat, can ignite and cause a fire or even an explosion.
Other activities or events that pose risks of igniting a fire include the following:
• Electrical fault;
• Cable overheating;
• Arcing, such as at switches;
• Lightning strike;
• Hot work, such as welding; and
• Equipment failure.
When these events occur at substations, they typically do not cause fires because of the safety
systems that have been installed. A fire is not considered a probable outcome of operating the
substation. However, if a fire were to occur, it would most likely be similar to the types of
fires described in the following paragraphs, and the fail-safe systems described below would
be in place to contain the damage (Orth, personal communication, 2014).
Electrical faults can occur in any type of electrical equipment. A typical substation will
experience three to five electrical faults per year. Substation equipment has relays and circuit
breakers to cut power to a piece of equipment when a fault occurs. Faults typically occur
during an unexpected event, such as a lightning strike, a break in a cable, or equipment
malfunction. When relays and circuit breakers function properly, they are designed to
disconnect power within a fraction of a second to protect equipment and prevent fires that
could damage substation equipment and transmission and distribution lines. However, there
January 2016 CHAPTER 15 PUBLIC SERVICES 15-17
PHASE 1 DRAFT EIS
is a very small risk that a fault would go undetected and the equipment could overheat, cause
sparks, catch fire, or even explode before being detected.
Oil used in insulating electrical equipment is monitored for the presence of acetylene and
other dissolved gasses that are byproducts of arcing. If these dissolved gases are detected, the
equipment may be subject to a combination of the following: being monitored more
frequently, inspected, repaired, and/or replaced.
Although lightning occurs relatively infrequently in the combined study area, it still poses a
risk of damaging substation equipment if the equipment is struck or if there is a lightning
strike nearby. The risk is primarily to aboveground equipment; underground equipment is not
expected to be at risk of lightning strikes. Substations would be equipped with mechanical
means (such as a system of lightning rods) to convey lightning to the ground to avoid
equipment damage and harm to workers on the site. These systems are expected to largely
eliminate risks from lightning, but a small risk would remain. The other fail-safe systems
described in this section are designed to operate if a lightning strike caused a fault or cable
overload or other system malfunction.
Hot work such as welding can pose risks but is sometimes necessary to repair or modify
equipment in a substation. While precautions, such as removing the piece of equipment that
needs to be welded and welding it inside and away from electrical equipment, would reduce
the potential for starting a fire, a small risk would remain. Crews conducting hot work are
also trained to shut down equipment being worked on, shield equipment from exposure to
intensive heat and sparks, let equipment cool adequately before re-energizing, and monitor
any repairs to limit risk of fire.
In addition to the relays and circuit breakers described above, a number of other features are
included as fail-safe systems to provide protection in case another system does fail. PSE
personnel remotely monitor for conditions of overloading in the system, malfunctions, and
other factors that could lead to a fire.
If a fire were to start in a substation, PSE personnel and the local fire departments are trained
to deal with substation fires, including how to protect surrounding properties, minimize risk
to substation personnel and firefighters, and avoid exacerbating the fire. The protocol is to
contain the fire and prevent it from spreading beyond the substation site rather than entering
the facility and risking injury to firefighters. Because existing local service providers are
expected to be adequate to address increased demand for fire and emergency response
services, impacts on public services would be minor.
The same types of hazards and potential need for emergency services related to operation of
new 230 kV transmission lines in proximity to the Olympic Pipeline are already present with
the existing 115 kV lines and would remain similar with a 230 kV line, even if it were to be
located in a new right-of-way corridor. See the No Action Alternative for discussion of
impacts. As described in Chapters 8 and 16, conformance with industry standards and
regulatory requirements ensure that potential hazards are identified and operations and
maintenance procedures in place that minimize adverse effects from these hazards to minor
levels.
CHAPTER 15 January 2016 15-18 PUBLIC SERVICES
PHASE 1 DRAFT EIS
Increased Demand for Police Services 15.6.4.1.2
The demand for police services could increase if the project increases the opportunity for
illegal activity to occur at the new substation site or on or near the transmission corridor. As
described in Section 15.3.2, none of the interviewed police departments cited any incidents of
theft and vandalism at PSE’s existing substations. Security design features would minimize
potential impacts on police response services during operations. Substations have security
fences or walls and employ a variety of measures, including motion detectors and closed-
circuit television surveillance, as needed to monitor each site. These measures would reduce
the need for police services. Therefore, additional law enforcement demands are expected to
be minimal, resulting in a minor impact on such services.
The potential for incidences of illegal activity and vandalism along the transmission corridor
is anticipated to be low based on interview responses received from law enforcement
agencies when asked about crime along existing transmission corridors. Unique crime-related
problems associated with transmission corridors were generally not cited as an existing
problem or future concern. To limit public accessibility into these areas, private property
owners can install gates on service roads required for maintenance in locations where PSE
has an easement but does not own the property. Therefore, only a minor impact on law
enforcements services is expected.
Corona Interference 15.6.4.1.3
In general, corona interference is not considered a problem for transmission lines rated at 230
kV and below. Corona levels for the 230 kV transmission line (Alternative 1, Option A)
would be low, and no corona-generated interference with police and emergency personnel
communication/emergency devices would be anticipated. Furthermore, if interference should
occur, and to comply with FCC regulations, PSE would work with owners and operators of
communications facilities along the transmission line to identify and implement mitigation
measures. As a result, impacts related to corona interference with emergency communication
devices would be negligible. See Section 15.6.2 for additional information.
Option B: Existing Seattle City Light 230 kV Transmission 15.6.4.2
Corridor
The demands for public services would be the same as those described for the No Action
Alternative (minor), except that fewer portions of the transmission line would be located in
proximity to the Olympic Pipeline. As described for Alternative 1, Option A, conformance
with industry standards and regulatory requirements ensure that potential hazards are
identified and operations and maintenance procedures developed that minimize adverse
effects from these hazards. Same as Alternative 1, Option A, impacts related to corona
interference with emergency communication devices would be negligible.
Option C: Underground Transmission Lines 15.6.4.3
Because the transmission line would be underground, there would be no risk of fire from
lightning strike on the transmission line. Alternative 1, Option C would be located near the
Olympic Pipeline in places and could be in operation near, or share corridors with, other
utility infrastructure such as gas lines. Same as Alternative 1, Options A and B, with
January 2016 CHAPTER 15 PUBLIC SERVICES 15-19
PHASE 1 DRAFT EIS
conformance to industry standards and regulatory requirements, impacts related to the OPLC
pipelines or other gas lines in the area from operation of the project are expected to be minor.
Corona and radio noise are not factors for underground lines since they are not in corona (i.e.,
they are insulated by a solid dielectric material instead of air and therefore do not generate
corona). As a result, there would be no impacts from corona interference with emergency
communication devices.
Option D: Underwater Transmission Lines 15.6.4.4
Accidents along the submerged cable that might require emergency response would be
unlikely considering the depth of water where they would be placed and the dimensions and
strength of the cable itself, which would make it difficult to break. With implementation of
measures described in Chapters 8 and 16, impacts on emergency service providers would be
the same as Alternative 1, Options A, B, and C (minor).
An underwater transmission line will produce no electric fields in the surrounding
environment due to the shielding of the conductors. As a result, there would be no impacts
from corona interference with emergency communication devices.
Property Tax Revenues 15.6.4.5
During the public scoping process for the proposed project, the public expressed interest and
concern regarding the potential impacts of 230 kV transmission lines on property values, with
resulting loss in property tax revenues and the ability to adequately fund public services in
the study area communities. The EIS Consultant Team conducted a literature review on
proximity impacts for property values. Claims of diminished property value through
decreased marketability are based on the reported concern about hazards to human health and
safety and increased visual impacts associated with living in proximity to high-voltage
transmission lines. This issue is discussed in Chapter 11.
As described in Chapter 11, it is reasonable to assume that properties with views of existing
transmission lines may have somewhat lower property values than those nearby that do not
have views of the power lines. However, because of the number of factors and
interrelationships affecting property values, it is not possible to determine from Assessor’s
data how much of the effect on property values is due specifically to views.
For the purpose of identifying potential impacts of the Energize Eastside Project, the EIS
Consultant Team developed a rough estimate of the effect of reduced property values on
property tax revenues. A fiscal analysis prepared for the Project (FCS Group, 2016) utilized
an estimate of a theoretical $10 million decrease in assessed value to demonstrate the relative
effect of such a decrease on property tax revenues in one of the study area communities (City
of Bellevue). The results indicated that for each $10 million decrease in assessed value,
property tax revenues collected by the City of Bellevue would decrease by $9,800 per year.
Although the specific change in property values is not known, out of approximately $35
million that Bellevue collects each year, this change (-0.03%) is small and would not affect
the Cities’ ability to adequately fund public services.
CHAPTER 15 January 2016 15-20 PUBLIC SERVICES
PHASE 1 DRAFT EIS
15.6.5 Alternative 2: Integrated Resource Approach
Energy Efficiency, Demand Response, and Distributed 15.6.5.1
Generation Components
During operation of site-level and small-scale strategies implemented to address energy
efficiency, demand response, and distributed generation components, an increased need for
emergency services and law enforcement is unlikely. The existing emergency services are
expected to be adequate to meet the demands.
Energy Storage Component 15.6.5.2
Accidental damage or equipment replacement with this component of Alternative 2 could
possibly lead to leaks or spills of hazardous materials, requiring emergency response
services. Although the specific technology likely to be used for these devices is unknown, for
purposes of this discussion it was assumed that a battery system would likely contain
hazardous materials.
As described in Chapter 8, the energy stored and released by battery cells has the potential to
cause overheating and, if undetected and unmitigated, eventually cause the battery to
experience thermal runaway (i.e., a positive feedback loop where an increase in cell
temperature and pressure leads to an uncontrolled heat reaction). Primary concerns with
battery fires include the release of toxic fumes from hazardous materials, challenges and
uncertainty with extinguishing battery fires by first responders (as recommended response
techniques vary by chemistry type), and re-ignition and overhaul procedure after
extinguishment. Given the potential complexity of a response to a battery storage incident,
moderate impacts on emergency service providers could occur.
The incidence of vandalism at battery storage facilities is expected to be negligible, the same
as a substation as described for Alternative 1.
Peak Generation Plant Component 15.6.5.1
Generators would be located within substation yards and would have the same security
measures as the rest of the substation. Therefore, the incidence of vandalism at these facilities
is expected to be negligible.
As with Alternatives 1 and 3, accidental damage or equipment replacement under Alternative
2 could lead to leaks or spills of hazardous materials, which would potentially require
emergency response from fire departments. The energy storage batteries, generators, and
turbines of this alternative have the greatest potential for this type of situation, since they
incorporate equipment containing materials such as acid, natural gas, insulating oil, or diesel
fuel. Given the potential complexity of the response, moderate impacts on emergency service
providers could occur.
15.6.6 Alternative 3: New 115 kV Lines and Transformers
The demand for emergency services and law enforcement with Alternative 3 would be the
same as described for Alternative 1. As a result, minor impacts on emergency response
services could occur.
January 2016 CHAPTER 15 PUBLIC SERVICES 15-21
PHASE 1 DRAFT EIS
In general, corona interference is not a problem for transmission lines rated at 230 kV and
below. Because of the lower voltage, the 115 kV transmission line associated with
Alternative 3 would generally have less corona than the 230 kV line associated with
Alternative 1. Corona levels for these proposed lines would be low, and no corona-generated
interference with police and emergency personnel communication/emergency devices is
anticipated. Furthermore, if interference should occur, and to comply with FCC regulations,
PSE would work with owners and operators of communications facilities along the
transmission line to identify and implement mitigation measures.
15.7 WHAT MITIGATION MEASURES ARE AVAILABLE
FOR POTENTIAL IMPACTS TO PUBLIC SERVICES?
A variety of project design features and best management practices to reduce the effects on
public services would be implemented as part of the Energize Eastside Project.
15.7.1 Emergency Response Services
Measures PSE could take to minimize potential demand for emergency response services
during construction and operation are described in Chapter 8.
To further reduce emergencies related to the proposed project, PSE is required by law to
contact the appropriate Underground Service Alert organization to identify the location of
underground utilities and pipelines prior to any excavation work. An OPLC representative
would be present to observe excavation activities around buried pipelines during
construction. Further discussion of measures to reduce risks associated with construction or
operation in proximity to the Olympic Pipeline is provided in Chapter 8 and Chapter 16.
15.7.2 Response Times
The contractor would be required to prepare “maintenance of traffic” plans for any work with
the public right-of-way as described in Chapter 14. These plans would minimize effects on
emergency response and other public services.
Other potential mitigation measures include the following:
• Notify service providers and neighborhood residents of construction schedules, street
closures, and utility interruptions as far in advance as possible.
• Notify and coordinate with fire departments for water line relocations that could
affect water supply for fire suppression, and establish alternative supply lines prior to
any service interruptions.
• Where feasible, schedule construction outside of hours of peak traffic congestion and
times when service providers such as school buses and waste collectors are in the
area.
• Coordinate with law enforcement agencies to implement crime prevention plans for
construction sites and staging areas.
CHAPTER 15 January 2016 15-22 PUBLIC SERVICES
PHASE 1 DRAFT EIS
15.7.3 Substation Fire Risk
In order to reduce the risk of substation fire, PSE would routinely do the following:
• Use sulfur hexafluoride (SF6) gas for closely spaced equipment. SF6 is a
nonflammable gas and an excellent insulator.
• Install relays and circuit breakers to shut down equipment experiencing a fault or
malfunction.
• Install systems to conduct lightning to the ground rather than through lines or
equipment.
• Monitor oil insulation for evidence of arcing and gassing. Monitor substations for
evidence of overloading, overheating, or malfunctions.
15.8 ARE THERE ANY CUMULATIVE IMPACTS TO
PUBLIC SERVICES AND CAN THEY BE MITIGATED?
As the regional population has increased, so has the demand for public services. Demands for
these services will continue to increase as the area continues to grow. The Energize Eastside
Project will incrementally contribute to those increased demands. Design and operation in
accordance with applicable standards and requirements will reduce the incremental increase
associated with the Energize Eastside Project.
15.9 ARE THERE ANY SIGNIFICANT UNAVOIDABLE
ADVERSE IMPACTS TO PUBLIC SERVICES?
With the appropriate mitigation measures in place, no unavoidable significant adverse
impacts to public services are anticipated from either construction or operation of the
Energize Eastside Project alternatives.
There is a risk of damage and subsequent explosion requiring local, and potentially regional,
emergency service response whenever construction or operations and maintenance occur near
buried natural gas lines or the Olympic Pipeline. However, that risk is not considered an
unavoidable significant impact because the probability of damage occurring is minimized by
conformance with industry standards, regulatory requirements, and construction and
operational procedures that address pipeline safety.
January 2016 CHAPTER 15 PUBLIC SERVICES 15-23
PHASE 1 DRAFT EIS
CHAPTER 16. UTILITIES
HOW WERE UTILITIES IN THE COMBINED STUDY 16.1
AREA EVALUATED?
This chapter discusses electrical, natural gas, petroleum,
telecommunications, water, wastewater, and drainage
utilities in the combined study area (Alternatives 1, 2, and
3 as depicted on Figure 1-4 in Chapter 1) at a
programmatic level.
The EIS Consultant Team used geographic information
system (GIS) data to identify the types of utilities in the
combined study area and the general location of major
known utility infrastructure (including water, wastewater,
stormwater, and electrical facilities). Service providers for
each utility were identified, along with the area served by
each of the utilities, and any plans that service providers
have for major utility maintenance or expansion in the
area. Baseline information about utilities systems was
obtained through a review of relevant plans. Additional
information on utilities systems was obtained from local
government, utility district, and private provider website
information, publicly available plans and reports, and
through interviews with representatives of service
providers.
Because this project proposes to construct new electric
facilities, this assessment also includes a brief discussion
of the current service provided by PSE and how the
proposed project could affect fees charged to customers.
For further discussion of the project’s purpose and need,
refer to Chapter 1.
WHAT ARE THE RELEVANT 16.2
PLANS, POLICIES, AND
REGULATIONS?
This section describes plans, policies, and regulations
applicable to general utility provision and management in
the combined study area. Applicable federal, state and local regulations that pertain to
specific utilities are discussed in Section 16.3.
Utilities Key Findings
Impacts related to constructing
and operating a transmission
line near natural gas and
petroleum pipelines would
range from minor (No Action
Alternative, Alternative 1,
Options A and B and
Alternative 3) to moderate
(Alternative 1, Option C).
Although a significant adverse
impact on utilities could occur
if an explosion of any of these
types of lines resulted from the
project, the risk is minimized
by conformance with industry
standards, regulatory
requirements, and construction
and operational procedures
that address pipeline safety.
Under the No Action
Alternative, high electrical
loads could result in forced
outages that are considered
moderate to significant
adverse impacts to electrical
service reliability. Alternatives 1
and 3 would eliminate this risk,
while under Alternative 2, some
risk to reliability would remain.
Other construction-related
impacts would be minor to
moderate (Alternative 1,
Options A, C, D; Alternatives 2
and 3) and moderate to
significant (Alternative 1,
Option B).
January 2016 CHAPTER 16 UTILITIES 16-1
PHASE 1 DRAFT EIS
The comprehensive plans for the study area communities contain a variety of goals and
policies related to utilities (City of Bellevue, 2015; City of Clyde Hill, 2014; City of
Issaquah, 2015; City of Kirkland, 2013; City of Medina, 2015; City of Newcastle, 2015; City
of Redmond, 2015; City of Renton, 2015; City of Sammamish, 2015; King County, 2013;
Town of Beaux Arts Village, 2014; Town of Hunts Point, 2014; and Town of Yarrow Point,
2014).
The comprehensive plans establish goals and policies addressing the provision and
management of utilities, and the visual and safety aspects of the location of utilities, in
particular siting of utility lines. This chapter focuses on policies relating to the provision and
management of utilities. Policies relating to safety, land use (siting), and visual aspects of
utilities are described in Chapter 8, Chapter 10, and Chapter 11, respectively.
Appendix F lists the comprehensive plan utilities goals and policies that could address or
guide the Energize Eastside Project, including those goals and policies related to the
provision and management of electrical infrastructure. These goals and policies are generally
focused on the following:
• Ensuring that adequate public utilities and facilities are planned for, located,
extended, and sized consistent with planned growth;
• Ensuring utility systems are constructed in a manner that minimizes negative impacts
to existing development and utilities;
• Encouraging utility coordination regarding location and service provision; and
• Minimizing and preventing unnecessary risk due to hazardous liquid pipelines.
In addition, some study area communities include policies encouraging the use of new or
innovative technologies to increase the quality and efficiency of utility service. See Chapter 7
for more information.
Utilities in the combined study area are provided by a combination of City-managed
providers (typically water, wastewater, drainage) and providers managed by other entities
(typically electricity, natural gas, petroleum, telecommunications). Depending on their
services, utilities not managed by Cities are state regulated, federally licensed, and/or
municipally franchised providers.
Utilities operating within the combined study area that are not managed by the Cities conduct
their own planning processes and maintain their own systems with limited involvement from
the study area communities. However, all development and expansion proposals by utility
providers are subject to the relevant policies and regulations of the communities where the
proposals are located. Utility providers in the combined study area and their utility planning
processes and plans are described below in Sections 16.3, 16.4, and 16.5.
CHAPTER 16 January 2016 16-2 UTILITIES
PHASE 1 DRAFT EIS
WHAT UTILITIES ARE PRESENT IN THE COMBINED 16.3
STUDY AREA?
The combined study area includes both regional and local
utilities. Regional utilities in the combined study area
include power transmission systems (overhead 115 kV,
230 kV, and 500 kV), electric substations, gas transmission
pipelines, petroleum pipelines, and large water and
wastewater pipelines and associated pump stations. Local
utilities include distribution and collection systems (power
distribution, water mains, wastewater mains, stormwater
systems) that are generally connected to regional utilities.
Given the large study area and programmatic nature of this
evaluation, local utilities (and telecommunication utilities)
were not inventoried. For the Phase 2 Draft EIS, additional
detail will be developed on the location of utilities.
Figures 16-1 and 16-2 present GIS data for regional
electric transmission and natural gas and petroleum
pipelines in the combined study area. Existing regional water and wastewater lines are
presented in Figure 16-3. While not inventoried or shown on Figures 16-1, 16-2, and 16-3,
the combined study area also contains main feeder telephone and fiber optic lines.
This section provides
information on natural gas and
petroleum pipeline utilities in
the study area, related to the
proximity of these pipelines to
transmission lines under the
alternatives and potential risks
associated with co-locating
these types of utilities. This
information includes brief
discussion on how natural gas
and petroleum pipeline utilities
are regulated, inspection and
monitoring requirements, and
special issues related to co-
location (corrosion).
January 2016 CHAPTER 16 UTILITIES 16-3
PHASE 1 DRAFT EIS
Energize Eastside EIS 140548
Figure 16-1
Existing Electric Transmission and
Natural Gas/Petroleum Pipelines
SOURCE: King County 2015; ESA 2015; WA Ecology 2014;
Puget Sound Energy 2015; Seattle City Light 2015.
For more info visit www.energizeeastsideeis.org/map-electric-gas
Lake Washington
Lake
Sammamish
Bellevue Sammamish
Issaquah
Renton
Newcastle
RedmondKirkland
Beaux Arts
Medina
Clyde
Hill
Hunts
Point
Yarrow
Point
Mercer
Island
Lakeside
Sammamish
Talbot Hill
Novelty Hill
Lake Tradition
115kV (PSE)
Existing 230kV (PSE)
Seattle City Light
Corridor (230kV)
Existing Substations
Olympic Pipeline
Company
Northwest Pipeline
(Natural Gas)
PSE Gas Main
Roadway
Combined Study Area
Boundary
Water bodies
City Limits
Unincorporated King
County
U:\GIS\GIS\Projects\14xxxx\D140548_EastsidePSETransmisisonCoor\MXD\UtilitiesElectric.mxd
0 2
Miles
Note: This map is for reference only. It is not guaranteed that the information is accurate or complete.
Energize Eastside EIS 140548
Figure 16-2
Existing Regional
Wastewater and Water Lines
SOURCE: King County 2015; ESA 2015; WA Ecology 2014;
Puget Sound Energy 2015; Seattle Public Utilities 2016.
For more info visit www.energizeeastsideeis.org/map-water-utilities
Lake Washington
Lake
Sammamish
Bellevue Sammamish
Issaquah
Renton
Newcastle
RedmondKirkland
Beaux Arts
Medina
Clyde
Hill
Hunts
Point
Yarrow
Point
Mercer
Island
Lakeside
Sammamish
Talbot Hill
Novelty Hill
Lake Tradition
Existing
Substations
Water Mainline
(SPU)
Wastewater Line
(King County)
Pump Station
Roadway
Combined Study
Area Boundary
Water bodies
City Limits
Unincorporated
King County
U:\GIS\GIS\Projects\14xxxx\D140548_EastsidePSETransmisisonCoor\MXD\UtilitiesWater.m xd
0 2
Miles
Note: This map is for reference only. It is not guaranteed that the information is accurate or complete.
Table 16-1 lists both regional and municipal utility providers (except telecommunications)
that provide service or have facilities located in the combined study area. Utility providers
are described in greater detail following the table.
Table 16-1. Utility Providers Serving or Located in the Combined Study Area
Primary Provider Utility Community Served or
Physically Located
Regional Provider
PSE Electric and Natural Gas Kirkland, Redmond, Hunts
Point, Yarrow Point, Clyde
Hill, Medina, Bellevue,
Beaux Arts Village,
Sammamish, Issaquah,
Newcastle, Renton, King
County
Northwest Pipeline Natural Gas King County, Sammamish,
Issaquah
Seattle City Light Electric Seattle
Bonneville Power
Administration
Electric King County
Snohomish Public Utility
District
Electric King County
Tanner Electric Cooperative Electric King County
King County Wastewater Kirkland, Redmond, Hunts
Point, Yarrow Point, Clyde
Hill, Medina, Bellevue,
Beaux Arts Village,
Sammamish, Issaquah,
Newcastle, Renton, King
County
Seattle Public Utilities Water Cascade Water Alliance1
(Bellevue, Kirkland,
Redmond, Issaquah,
Sammamish), Hunts Point,
Yarrow Point, Clyde Hill,
Medina, Beaux Arts Village,
Newcastle, King County
CHAPTER 16 January 2016 16-6 UTILITIES
PHASE 1 DRAFT EIS
Primary Provider Utility Community Served or
Physically Located
Municipal Providers
Beaux Arts Village Water, Stormwater Beaux Arts Village
Bellevue Wastewater Bellevue, Clyde Hill, Beaux
Arts Village, Medina, Hunts
Point, Yarrow Point
Bellevue Stormwater Bellevue
Bellevue Water Bellevue, Clyde Hill, Medina,
Hunts Point, Yarrow Point
Clyde Hill Stormwater Clyde Hill
Hunts Point Stormwater Hunts Point
Kirkland Water, Wastewater,
Stormwater
Kirkland
Medina Stormwater Medina
Newcastle Stormwater Newcastle
Coal Creek Utility District Water, Wastewater Newcastle
Redmond Water, Wastewater,
Stormwater
Redmond
Renton Water, Wastewater,
Stormwater
Renton
Sammamish Stormwater Sammamish
Northeast Sammamish
Water and Sewer District
Water, Wastewater Sammamish
Sammamish Plateau Water
and Sewer District
Water, Wastewater Sammamish
Yarrow Point Stormwater Yarrow Point
1 Cascade Water Alliance is a wholesale water provider to its members and has a purchase contract with
Seattle Public Utilities (CWA, 2015)
Sources: PSE, 2015b; SCL, 2015; King County, 2013; SPU, 2015; CWA, 2015; Town of Beaux Arts Village,
2014; City of Bellevue, 2015; City of Clyde Hill, 2015; Town of Hunts Point, 2014; City of Kirkland, 2013;
City of Medina, 2015; City of Newcastle, 2015; City of Redmond, 2015; City of Renton, 2015; City of
Sammamish, 2015; Town of Yarrow Point, 2014.
January 2016 CHAPTER 16 UTILITIES 16-7
PHASE 1 DRAFT EIS
16.3.1 Electrical
Puget Sound Energy 16.3.1.1
PSE serves approximately 1.1 million customers with electricity in a 4,500-square-mile
service area (PSE, 2013a). This service area includes the combined study area for
Alternatives 1, 2, and 3 (as depicted on Figure 1-4 in Chapter 1) and portions of King County
north and south of the study areas. The Eastside represents approximately 14 percent of
PSE’s total electrical load. PSE is part of a western regional system, through which electricity
is produced elsewhere and transported to the Eastside along high-voltage transmission lines.
As electricity nears the end users, the voltage is reduced (using transformers) and
redistributed through transmission substations and distribution substations.
Power is carried on high-voltage transmission lines (230 kV and greater) from generating
facilities to the Eastside via the Sammamish substation in Redmond and Talbot Hill
substation in Renton. From these substations, voltage is reduced to 115 kV and distributed to
numerous Eastside distribution substations (PSE, 2013b). PSE has existing transmission
easements or rights-of-way for 115 kV lines located within the combined study area.
Figure 16-1 shows PSE’s existing electrical system in the Eastside and vicinity.
Customers in the Eastside service area consume electricity at a rate of approximately 3,000
gigawatt hours (gWh) per year (gWh/yr). Residential uses represent the largest portion (about
90 percent) of PSE’s customers; however, business and industry consume about 62 percent of
the electricity provided (Strauch, personal communication, 2016).
PSE’s electric delivery system is regulated and coordinated by several state and federal
agencies described in Chapter 1. These include the Federal Energy Regulatory Commission
(FERC), North American Electric Reliability Corporation (NERC), Western Electricity
Coordinating Council (WECC), and Washington Utilities and Transportation Commission
(UTC). PSE cooperates and supports ColumbiaGrid in its regional planning processes.
For additional description of PSE’s service in the Eastside area and the general roles of each
agency involved in regulatory oversight, see Chapter 1.
Seattle City Light 16.3.1.2
Seattle City Light (SCL), an electric utility owned by the City of Seattle, owns and maintains
approximately 650 miles of transmission lines. These lines carry power from the electrical
generating facilities to 14 major substations (City of Seattle, 2014). None of these substations
are located directly within the combined study area. Two SCL 230 kV transmission lines (on
steel towers) run through Kirkland, Bellevue, Newcastle, and Renton, but they do not serve
the study area communities (see Figure 16-1). Both of these lines are leased to, and operated
by, the Bonneville Power Administration as part of the regional transmission grid (SCL,
2008).
SCL’s electric delivery system is regulated and coordinated by the same state and federal
agencies as described above for PSE.
CHAPTER 16 January 2016 16-8 UTILITIES
PHASE 1 DRAFT EIS
Bonneville Power Administration 16.3.1.3
The Bonneville Power Administration (BPA) is a federal nonprofit agency based in the
Pacific Northwest. BPA markets wholesale electrical power from 31 federal hydro projects in
the Columbia River Basin, one nonfederal nuclear plant and several other small nonfederal
power plants. About one-third of the electric power used in the Northwest comes from BPA.
BPA also operates and maintains high-voltage transmission in its service territory. While
BPA transmission lines (230 kV and 500 kV) cross the southern portion of the combined
study area (Figure 16-3), BPA does not provide service within the combined study area.
Figure 16-3. Existing Electric Transmission and Natural Gas Pipelines (Combined
Study Area – South)
January 2016 CHAPTER 16 UTILITIES 16-9
PHASE 1 DRAFT EIS
16.3.2 Natural Gas
Puget Sound Energy 16.3.2.1
PSE serves over 760,000 customers with natural gas in a 2,800-square-mile service area
(PSE, 2013a). PSE receives natural gas from various regions of the U.S. and Canada. Natural
gas lines are located throughout the streets, public properties, and private properties located
within the combined study area. PSE’s system includes a network of high-pressure natural
gas mains, district regulators that reduce natural gas pressures, mains, service lines, valves,
and meters, all of which are located underground, except for the meters. Several high-
pressure gas mains cross through PSE and SCL transmission corridors located within the
combined study area.
A number of federal and state agencies are responsible for and involved in the regulation and
oversight of pipelines in the United States. The Washington Utilities and Transportation
Commission (UTC) is the primary agency responsible for the regulatory oversight of the
natural gas pipelines in Washington State. The UTC Pipeline Safety Program provides
standards for natural gas pipeline operations and inspects natural gas pipelines operating in
Washington in accordance with federal standards. PSE is subject to full compliance with the
applicable provisions of Title 49, Code of Federal Regulations (CFR) Part 192, which
address federal safety standards related to transportation of natural gas, including
requirements for pipeline corrosion control. Additional information on pipeline corrosion is
presented in Section 16.3.7.
High-pressure gas mains through PSE’s and SCL’s existing corridors are made of steel. PSE
provides corrosion protection for its steel gas pipelines as required by Title 49 CFR. This
includes dielectric coatings, cathodic protection, and maintenance. The cathodic protection
meets the criteria specified in federal law and recommended by the National Association of
Corrosion Engineers (NACE). PSE surveys steel pipelines for leaks every 6 months, and
electronic gas-detection equipment is used to inspect every neighborhood’s system (PSE,
2015a). As described in Chapter 8, the UTC identifies five major reasons why pipelines leak
or fail: (1) third-party excavation damage; (2) corrosion; (3) construction defects; (4) material
defects; and (5) outside forces resulting from earth movement, including earthquakes.
Information currently available from UTC indicates that the leading cause of gas distribution
pipeline failures in 1998 was excavation damage, causing 58 percent of leaks that occurred in
Washington State. Construction equipment can create pipe gouges, dents, scrapes, and cracks
in pipelines. This type of damage can grow and lead to a catastrophic failure (UTC, 2015).
Northwest Pipeline 16.3.2.2
The Northwest Pipeline is an interstate natural gas pipeline system for the mainline
transmission of natural gas. It is owned and operated by the Williams Companies. High-
pressure gas mains traverse portions of the combined study area in King County,
Sammamish, and Issaquah (see Figure 16-1).
Northwest Pipeline is regulated and coordinated by the same state and federal agencies as
described above for PSE. In addition, the pipeline is also subject to FERC, which regulates
interstate natural gas pipelines.
CHAPTER 16 January 2016 16-10 UTILITIES
PHASE 1 DRAFT EIS
16.3.3 Petroleum Pipelines
The Olympic Pipe Line Company (OPLC) operates a
petroleum pipeline system that runs along a 299-mile
corridor from Blaine, Washington, to Portland, Oregon.
The pipes carry gasoline, diesel, and aviation fuel. This
fuel originates at four Puget Sound refineries, two in
Whatcom County and two in Skagit County, and is
delivered to Seattle’s Harbor Island, Seattle-Tacoma
International Airport, Renton, Tacoma, Vancouver
(Washington), and Portland, Oregon (B.P. Pipelines North
America, 2014).
Two parallel steel lines (16-inch and 20-inch) run north-
south through western Redmond, Bellevue, Newcastle, and
Renton, generally along the PSE easement (EFSEC, 1998)
(see Figure 16-1). The pipelines through the combined
study area are buried 3 feet to 10 feet below the surface; however, the depth of cover over the
pipelines may change over time due to erosion or other reasons (West, 2015). The two lines
weave back and forth within PSE’s easement, and in some instances leave the corridor onto
other easements or public rights-of-way and then reenter PSE’s easement corridor farther
along the route (West, 2015).
OPLC operates its lines pursuant to its own easements and, where they overlap, subject to
agreement with PSE and PSE’s prior rights. In entering this agreement with PSE, OPLC
agreed to: (1) install its pipeline at a depth and in a manner that would not interfere with
PSE’s facilities; (2) install and maintain permanent markers to give notice of the location of
the pipeline; and (3) adjust and/or relocate the pipeline in the event of a conflict with PSE
facilities.
The pipelines are considered hazardous liquid pipelines, as designated by RCW 81.88.040
and WAC 480-93-005. Hazardous liquid pipelines, if ruptured or damaged, can cause large
explosions and/or fires due to high operating pressure and the highly flammable and
explosive properties of the transported products.
Hazardous liquid pipelines are regulated by federal and state rules (see Appendix M, Pipeline
Safety Requirements and Plans Relating to Petroleum Pipelines). The standards and
enforcement actions are the responsibility of the federal Office of Pipeline Safety (OPS), as
described in Chapter 8. Through passage of the Washington Pipeline Safety Act of 2000
(E2SHB 2420), the UTC was directed and obtained the authority from the OPS to inspect
interstate hazardous liquid pipelines in Washington State in accordance with federal
standards (UTC, 2015). OPLC is subject to full compliance with the applicable provisions of
Title 49, CFR Part 195 for hazardous liquid pipelines, and as reinforced by the company’s
franchise agreements with the study area cities. These regulations address safety in design,
construction, testing, operation, maintenance, and emergency response for pipeline facilities.
In accordance with 49 CFR Part 195, regular inspections and monitoring of the pipelines are
performed using a combination of tools to determine the suitability of the pipeline based on
Where is the Olympic
Pipeline Addressed?
A number of chapters in this
EIS address potential impacts
associated with the Olympic
Pipe Line Company’s
petroleum pipelines through
the combined study area. See
Chapter 3 (Earth - seismic
conditions), Chapter 8
(Environmental Health – public
safety risks), and Chapter 10
(Land Use – compatibility and
policy consistency).
January 2016 CHAPTER 16 UTILITIES 16-11
PHASE 1 DRAFT EIS
any anomalies detected, including wall loss, corrosion, or dents. The pipelines through the
combined study area are currently on a 5-year general inspection schedule. If anomalies were
to be detected, this timeframe would be shortened in accordance with federal requirements
(West, 2015).
In accordance with 49 CFR Part 195, OPLC has cathodic protection on all of its pipelines to
protect against corrosion and inspects these systems annually. Criteria to determine the
adequacy of cathodic protection are included in 49 CFR Part 195.571, which incorporates by
reference industry standards and practices developed by the National Association of
Corrosion Engineers (NACE) (NACE, 2007).
OPLC has franchise agreements with the Cities of Bellevue (2005), Kirkland (2011),
Newcastle (2008), Renton (2006), and Redmond (2006) that establish the conditions related
to the company’s use of the pipeline corridor and the ways the parties will work
cooperatively in the public’s best interest. The Cities use reasonable efforts to require all
excavators working within the pipeline corridor in proximity to the pipeline to notify OPLC
at least 48 hours prior to start of any work and to ensure compliance with the requirements of
the State of Washington’s “one-call” locator service law (Chapter 19.122 RCW). As further
stipulated by the franchise agreements, if OPLC becomes aware that a third party conducts
any excavation or other significant work that may affect the pipeline, the company is required
to conduct such inspections and testing as is necessary to determine that no direct or indirect
damage was done to the pipeline and that the work did not abnormally load the pipeline or
impair the effectiveness of the cathodic protection system (City of Bellevue, 2005; City of
Kirkland, 2011; City of Newcastle, 2008; City of Renton, 2006).
16.3.4 Water, Wastewater, and Stormwater
Seattle Public Utilities (SPU) operates a regional water supply system that provides potable
water to most of King County, including most of the Eastside. Water is provided through
wholesale contracts to municipalities and special-purpose districts within the combined study
area. Water is also sold to Cascade Water Alliance, an association of Eastside water districts
and cities that serves as a wholesale water provider (CWA, 2015). Other cities in the
combined study area obtain their water supply from a combination of groundwater wells,
local watersheds, and contracts with other utility providers.
SPU’s system includes large-diameter transmission pipelines, storage facilities, pump
stations, and other facilities that are used in conveying water from SPU supply sources to its
wholesale customers and the SPU retail service area (SPU, 2013).
Regional water transmission pipelines in the combined study area generally range in diameter
from 16 inches to 96 inches (SPU, 2013). The large regional pipelines that are owned and
operated by SPU within the combined study area include the Tolt Eastside Supply Line,
Cedar Eastside Supply Line, and Mercer Island Pipeline.
City water departments, special-purpose districts, and wholesale water suppliers also
maintain water mains throughout the combined study areas, many 16 inches or larger. This
includes Cascade Water Alliance’s Bellevue-Issaquah Pipeline (BIP), which transports water
CHAPTER 16 January 2016 16-12 UTILITIES
PHASE 1 DRAFT EIS
purchased from SPU’s Tolt Eastside Supply Line and Eastside Reservoir to Issaquah and the
Sammamish Plateau (CWA, 2012).
The bulk of SPU’s transmission pipelines are made of steel and concrete, with a small portion
consisting of ductile or cast iron. SPU has used cathodic protection on numerous sections of
steel pipelines where significant leaks have been experienced in the past or may be expected
in the future due to corrosive soils. SPU is developing a comprehensive strategy to identify
where it would be cost-effective to install cathodic protection on other pipes in its system
(SPU, 2013).
King County Wastewater Treatment Division owns and operates regional wastewater
pipelines, pump stations, and related facilities within the combined study area. Study area
cities and special-purpose districts maintain smaller wastewater collection lines and facilities,
with most maintaining agreements with King County for wastewater conveyance, treatment,
and disposal. Wastewater flows through pipes owned and maintained by Cities or special
districts into King County’s regional trunk lines where it is then conveyed to the Renton or
Brightwater Wastewater Treatment Plant for treatment. In addition, the City of Bellevue
owns submerged wastewater pipelines in Lake Sammamish and Lake Washington (see
Section 16.4.6). Major King County trunk lines in the combined study area generally range in
diameter from 24 inches to 96 inches.
Each of the Cities on the Eastside maintains its own stormwater drainage system. The
stormwater systems in the study area communities include a combination of ditches, pipes,
catch basins, detention basins, infiltration facilities, and flood control sites. Stormwater and
drainage regulations within these communities are discussed in more detail in Chapter 5.
16.3.5 Telecommunications
Telecommunications companies operating in the combined study area include Comcast and
CenturyLink. A number of other companies (e.g., AT&T, Verizon, Frontier
Communications, Broadstripe) maintain fiber optic cables throughout the area.
Cable television, landline telephone service, broadband internet, and wireless
communications in the combined study area are provided by various private utility
companies. Major telecommunications companies operating in the combined study area
include Comcast and CenturyLink. A number of other companies (e.g., AT&T, Verizon,
Frontier Communications, Broadstripe) also provide service. Telecommunication lines in the
combined study area include both coaxial and fiber optic cables. In most cases,
telecommunication services use existing utility corridors, public rights-of-way, and other
City-owned properties. Some companies have franchise agreements with the study area
communities for placement of their cable transmission lines within the public rights-of-way.
16.3.6 Submerged Utilities and “Lake Lines”
Several existing pipes and cables are located along the bottom of Lake Washington and Lake
Sammamish. Many of them provide electricity, gas, communications, wastewater, and water
service to Mercer Island from the Eastside (Power Engineers, 2015). King County’s Mercer
Island/ Enatai Wastewater Interceptor crosses the bottom of Lake Washington from Mercer
January 2016 CHAPTER 16 UTILITIES 16-13
PHASE 1 DRAFT EIS
Island to Bellevue, and along the lakefront (underwater). King County also has a submerged
wastewater interceptor from Issaquah to Bellevue in Lake Sammamish. The City of Bellevue
owns 15 miles of submerged wastewater pipelines in Lake Washington and 4 miles of
submerged wastewater pipelines in Lake Sammamish. These “lake lines” were constructed in
the late 1950s and 1960s and may be nearing the end of their useful life. The City is
evaluating their condition to determine when rehabilitation or replacement will be necessary
(City of Bellevue, 2015).
16.3.7 What is pipeline corrosion and why is it a concern?
As described in Chapter 8, high-voltage transmission lines produce electric and magnetic
fields. Electric fields are produced by the voltage in use and magnetic fields are produced by
current. The strength of the electromagnetic field (both electric and magnetic fields, also
known as EMF) decreases rapidly with distance from the source.
A consequence of high-voltage power lines and buried petroleum pipelines sharing a corridor
is that electromagnetic interference can be introduced on the pipelines, which can cause
corrosion on the pipeline over time. Corrosion accounts for about 23 percent of the
significant failures in both hazardous liquid and gas pipelines (Baker, 2008).
Electromagnetic interference, or induction, on pipelines occurs when there is extended and
close parallel routing with three-phase overhead transmission lines (Figure 16-4). The voltage
is due to any phase imbalance in the lines. Electromagnetic fields from high-voltage power
lines are especially a concern where the pipeline route is in parallel with, or crosses, high-
voltage power lines. The corrosion concern depends on the currents flowing in the pipeline,
which result in a voltage difference between the pipeline and the surrounding soil. The
corrosion potential is influenced by various parameters such as soil properties, pipeline to
transmission line distance and configuration, and the overhead line’s operating current
(Baker, 2008).
CHAPTER 16 January 2016 16-14 UTILITIES
PHASE 1 DRAFT EIS
Figure 16-4. Illustration of Induction
Different distances between the pipeline and each phase transmission line, along with phase imbalance,
lead to induced interference on the pipeline.
Source: Smart et al., 1999
To protect buried pipelines against corrosion, a noncorrosive coating is used along with
cathodic protection. Cathodic protection is a method used to minimize the rate of
electrochemical corrosion of metallic materials, such as pipes, by shifting the corrosion
process away from the metal to be protected and onto other more easily corroded “sacrificial”
pieces of metal. Cathodic protection systems are commonly referred to as either a sacrificial
anode or impressed current anode. The utility provider is responsible for its own pipeline,
but electric utilities may compensate or provide other mitigation if they install new or higher
voltage lines where pipelines are already present.
As described by Baker (2008), from a scientific point of view, corrosion is well understood,
both in terms of cause and method of control. However, despite the level of industry
knowledge, pipelines continue to experience failures due to corrosions. Factors cited include
the following:
• The chemical properties of the environment surrounding a buried pipeline are not
adequately understood.
• Variations in the oxygen content, moisture content, and chemical composition of the
soil along the pipe length and from top to bottom of the pipe can act as concentration
cells that promote corrosion.
January 2016 CHAPTER 16 UTILITIES 16-15
PHASE 1 DRAFT EIS
• Moisture content and oxygen content of the soil vary with time.
• Coating quality varies along the length of a pipeline.
• Coatings sometimes become disbonded from the pipe surface, allowing groundwater
to contact the steel but shielding the steel from cathodic-protection currents.
• Disbonded coating will prevent aboveground survey detection of underlying
corrosive conditions.
• Physical variations in soil characteristics and placement (gaps, etc.) affect the
distribution of cathodic-protection current.
• Visual inspection of the outside of the pipe and the coating require excavation.
• Stray currents from nearby buried structures can interfere with a pipeline’s cathodic-
protection system (Baker, 2008).
WHAT ARE THE UTILITIES’ PLANS FOR FUTURE 16.4
EXPANSION IN THE COMBINED STUDY AREA?
Several study area utilities are anticipating that demand will require investment to build new
utility facilities. Major utility upgrades or expansions planned in the combined study area are
described below.
16.4.1 Electrical
The UTC requires providers of electricity to provide service on demand in support of growth
in their service areas. As described in Chapter 1, PSE conducts an ongoing capacity planning
process to ensure its power supply and infrastructure are adequate to meet anticipated future
needs (PSE, 2013a). PSE develops both short-range and long-range infrastructure plans based
upon economic, population, and load-growth projections, as well as information from large
customers and government stakeholders. The plan is reviewed by PSE annually and is
periodically updated.
Systemwide, in the next decade, PSE anticipates building over 200 miles of new transmission
lines (100 kV and above) and upgrading over 200 miles of existing transmission lines to
carry greater loads. Energize Eastside is the only project in the combined study area that
proposes new 230 kV transmission lines. In addition, PSE anticipates needing to add up to
six 230 to 115 kV bulk power transformers across its service area, including a new
transformer for Energize Eastside (Strauch, personal communication, 2016).
PSE is monitoring preliminary “point load” needs where two new substations may be needed
in the combined study area to help serve new load, where adjacent existing substations are
inadequate, or to serve specific facilities. The timing of the construction of these substations
would be aligned with customer plans to add point loads and available capacity from existing
substations to serve this load (PSE, 2013b). Additionally, PSE replaces many major
substation components, including those in the combined study area, on a continuous basis as
a result of ongoing inspection and diagnostics (PSE, 2013b).
CHAPTER 16 January 2016 16-16 UTILITIES
PHASE 1 DRAFT EIS
Seattle City Light plans transmission capacity and reliability projects to deliver power to the
regional power grid. Projects potentially located in the Eastside area and included in the 2015
Capital Improvement Program include installation and reconductoring of transmission lines
to address increased load growth in the Puget Sound area. The capacity of the Bothell-
SnoKing double circuit 230 kV line would be increased to meet area reliability requirements
(City of Seattle, 2015).
16.4.2 Natural Gas
As with the electric system, PSE addresses aging gas infrastructure within the system in
accordance with regulatory requirements and operating practices. Systemwide, in the next
decade, PSE plans to replace or install the following (PSE, 2013b):
• New high-pressure pipe (27.5 miles);
• New intermediate-pressure pipe (28 miles); and
• Gas main replacement (200 to 300 miles).
16.4.3 Water and Wastewater
In portions of the combined study area, water and wastewater lines are aging or reaching
capacity, and may require rehabilitation or replacement over the next 20 years. SPU has
identified the following major implementation and action plan items for its water
transmission system (SPU, 2013; City of Seattle, 2015):
• Cathodic Protection Program;
• Transmission Pipeline Rehabilitation;
• Purveyor Meter Replacements;
• Replace Air Valve Chambers; and
• Water System Dewatering.
The Cascade Water Alliance has identified the future need for additional conveyance
capacity between Bellevue and Redmond (CWA, 2012).
King County plans to complete a number of wastewater conveyance projects in the combined
study area over the next 15 years, including the following (King County WTD, 2014):
• Factoria Pump Station and Trunk Diversion;
• Eastgate Parallel Pipe Storage;
• Coal Creek Siphon and Trunk;
• Bryn Mawr Storage;
• Issaquah Storage;
• Issaquah Interceptor Section 2 Parallel;
• Issaquah Creek Highlands Storage; and
• Sammamish Plateau Diversion.
January 2016 CHAPTER 16 UTILITIES 16-17
PHASE 1 DRAFT EIS
HOW WERE POTENTIAL IMPACTS TO UTILITIES 16.5
ASSESSED?
This section discusses potential impacts to utilities, including electrical, natural gas,
petroleum, water, wastewater, stormwater, and telecommunications lines resulting from the
construction and operation of the proposed project. The analysis is based on a consistency
review of local comprehensive plans, utility plans, and applicable laws, regulations, and
guidelines, as well as the following technical reports prepared for the proposed project:
• Eastside 230 kV Project – Lake Washington Submarine Cable Alternative Feasibility
Study (Power Engineers, 2015);
• Eastside 230 kV Project – Underground Feasibility Study (Power Engineers, 2014);
and
• Eastside Transmission Solutions Report – King County Area (Quanta Technology,
2014).
Due to the programmatic nature of this EIS, a general overview of potential impacts to
utilities is provided. In order to conduct a detailed assessment of impacts to utilities, the
precise location, size, and configuration of the proposed project in relation to existing utilities
would need to be known. For example, construction impacts on utilities are primarily related
to the utilities’ depth below grade and material composition, construction excavation limits,
and the location of the electric facilities and any associated foundations relative to the
location of other utilities. These details will be determined and verified with utility providers
during project-level evaluations and design.
For this analysis, the magnitude of project-related impacts is classified as being minor,
moderate, or significant as follows:
Minor – Impacts to existing utilities could occur but could be addressed through temporary
connections or other means, and would result in only minimal effect on services.
Moderate – Impacts to existing utilities could occur, resulting in localized interruptions of
service, or constraints on operation.
Significant – Impacts to existing utilities would occur resulting in widespread or substantial
interruptions of service or other constraints, and restoration would be difficult.
WHAT ARE THE LIKELY CONSTRUCTION IMPACTS 16.6
RELATED TO UTILITIES?
16.6.1 Construction Impacts Considered
Construction impacts to utilities were assessed by considering the potential for facilities to be
constructed in proximity to other utilities, and how that might result in different potential
impacts among the alternatives and options. The discussion includes the potential for utility
conflicts and service disruption, the potential for accidental disruption due to inadvertent
CHAPTER 16 January 2016 16-18 UTILITIES
PHASE 1 DRAFT EIS
damage, and the extent of coordination that would be needed with utility service providers in
order to construct each alternative.
Utility Conflicts and Service Disruption 16.6.1.1
Construction disturbance from earthmoving (excavation), foundation work, and other
activities could affect existing utilities if present. PSE would coordinate with all utility
providers that operate facilities within or adjacent to the proposed project to ensure that
design does not conflict with other utilities. Exact location and depth of utilities would be
verified with utility providers during project design and prior to construction to ensure new
excavations are far enough away from existing facilities to avoid damage. This may include
potholing (minor excavations to precisely locate utility lines) to identify and minimize
potential conflicts.
In order to avoid conflicts with construction and to prevent access disruptions during future
maintenance of utilities, some existing utilities would likely need to be temporarily rerouted
or relocated. Relocation approaches would be evaluated by PSE on a case-by-case basis and
in accordance with applicable franchise agreements.
Temporary service outages could occur during utility relocations. These outages would likely
be short-term and intermittent. Disruptions to utility service during utility relocations would
likely be minimal because, in most cases, temporary connections to customers would
typically be established before relocating utility conveyances. In these situations, impacts
would be negligible. If relocating utility conveyances would require service disruptions,
impacts would be considered minor, moderate, or significant depending on the extent and
duration of the interruption. All service disruptions would be coordinated between PSE’s
public outreach efforts (Section 16.8), the service provider, and customers. The potential for
utility relocations and service disruption is higher when constructing within the road right-of-
way or within existing utility corridors or easements.
Accidental Disruption 16.6.1.2
Inadvertent damage to underground utilities could occur during construction if utility
locations are uncertain or misidentified. Although such incidents do not occur frequently, if
numerous relocations are required during project construction, the potential for accidents is
more likely. Such accidents could affect service to customers, and would be considered a
minor, moderate, or significant impact depending on the extent and duration of the
interruption. Although a pipeline-related explosion as a result of project construction appears
unlikely given the regulatory framework now in place (see Chapter 8), such an event would
equate to a moderate to significant impact depending on the size of such an event, the number
of customers affected, and the time needed to restore service.
Efforts to minimize impacts would include potholing and preconstruction surveys to identify
utility locations, and outreach to customers about potential service disruptions. PSE would
also coordinate with utility providers to establish replacement procedures and standards of
facilities as applicable.
January 2016 CHAPTER 16 UTILITIES 16-19
PHASE 1 DRAFT EIS
16.6.2 No Action Alternative
Under the No Action Alternative, construction activities would likely be limited to occasional
conductor replacement, implementation of new technologies not requiring discretionary
permits, and installation of distributed generation facilities under PSE’s conservation
program (e.g., solar panels, wind turbines, or rooftop generators). None of these activities
would likely involve heavy equipment and construction activity near major utility lines. No
construction impacts on utilities are likely, and therefore impacts would be considered
negligible.
16.6.3 Alternative 1: New Substation and 230 kV Transmission Lines
Under the options proposed for Alternative 1, construction activity would be required for
substation expansion, construction of the transmission lines, and placement of accessory
infrastructure (vaults, etc.). Construction would involve the use of heavy equipment and
excavation activity. If this work occurs within existing utility corridors, it would have the
potential to cause utility conflicts and service disruption.
Impacts are described below according to the major components associated with
Alternative 1. The substation impacts are described first, followed by transmission line
impacts.
Option A: New Overhead Transmission Lines 16.6.3.1
Utility Conflicts and Service Disruption 16.6.3.1.1
The expansion of the Lakeside substation or the Westminster or Vernell substation sites
would require construction of underground foundations to support the new transformer.
Depending on the site, and the depth and placement of the transformer foundation, substantial
utility relocations could be required. Given their proximity to the Olympic Pipeline (see
Figure 16-1), the potential for utility conflicts and need for coordination would be greater for
the Lakeside and Vernell substation sites, depending on the area used for expansion. All
relocations would be coordinated with the utility service provider during final design.
Construction would also require coordination with utility providers to extend utilities to the
new transformer.
During installation of new 230 kV to 115 kV transformers, there would be potential for
service interruptions or utility damage in the event of an accident during construction.
However, the substations are owned and operated by PSE and thus crews are familiar with
the facility. In the event that any accidental damage was to occur, impacts would be minor
because PSE employees are trained to respond and to minimize or avoid potential service
interruptions by transferring load.
Under Alternative 1, Option A, most construction of transmission lines would occur within
existing transmission or other utility easements. However, construction could also occur in
new locations currently not dedicated to transmission, such as areas along road rights-of-way,
rail corridors, or over or through private or other public property. If new overhead
transmission lines were built in existing utility easements or along road rights-of-way or rail
corridors, coordination with other utility providers would be required to avoid disrupting
existing buried utility lines or overhead lines that may be co-located along the corridor.
CHAPTER 16 January 2016 16-20 UTILITIES
PHASE 1 DRAFT EIS
If located along the existing PSE 115 kV easement, construction of a 230 kV line has the
potential to disrupt existing natural gas lines or the Olympic Pipeline. Extensive coordination
with OPLC would be required during project design to avoid disruption to the two lines, or to
establish relocation procedures. For large projects, such as Energize Eastside, OPLC would
establish a team to review design, identify any vulnerabilities, and identify measures to avoid
potential impacts, in coordination with the project proponent (West, 2015). Construction risks
associated with the Olympic Pipeline include potential for compression damage from heavy
vehicles or machinery driving or placed above the buried lines, potential for pipe disturbance
during excavations for new poles, and potential for pipe disturbance from removal of current
poles. Certain machinery, such as auger equipment, can be a particular concern because of
how heavy the equipment is. If there is a concern, measures can be used to avoid crossing the
pipeline by taking a different route, or reducing or eliminating the concern by placing matting
or other material to distribute the load to acceptable levels or relocating the pipeline.
As much as possible, poles for new overhead transmission lines would be located to avoid
conflicts with underground utilities. Foundations for new 230 kV poles are typically 4- to 8-
feet in diameter and extend approximately 25 to 50 feet deep depending on the structure type.
Any existing utilities located within or immediately adjacent to the auger hole would need to
be relocated. Because there is typically flexibility in designing and locating pole foundations,
it is likely that utility relocations could be avoided.
Foundation locations for poles would be coordinated with OPLC during project design to
ensure a safe distance from the pipeline for construction and operation considerations. The
risk of pipeline disturbance during construction would be further minimized by stabilizing
foundation walls, such as using metal sleeves or slurry walls, to avoid movement of adjacent
soils that could potentially disturb the pipeline.
A potential significant adverse impact on utilities could occur if a rupture and explosion of a
pipeline occurred during construction resulting in widespread service disruption and
difficulties in reestablishing service. Service disruption for OPLC customers would likely be
minimal because delivery of the product would switch to surface transport by tanker truck, if
the outage exceeds customers’ on-hand reserve supply. If a pipeline rupture and explosion
also damaged the 230 kV transmission lines, there could be substantial and long-term power
outages to PSE customers. Extensive coordination with OPLC, gas utility providers, and
study area communities would be required during project design to avoid disruption to
nearby pipelines. In addition, as described in Sections 16.3.3 and 16.8 (and in Chapter 8),
conformance with industry standards and regulatory requirements would ensure that potential
hazards are identified and design plans developed to minimize adverse effects from these
hazards to minor levels.
Given the level of coordination and number of utility relocations potentially required under
Alternative 1, Option A, minor to moderate impacts to utilities could occur from constructing
new transmission lines in existing easements or road rights-of-way. If the new lines were
built within new corridors, there would be less potential for construction to encounter
existing utilities, and impacts would likely be negligible.
January 2016 CHAPTER 16 UTILITIES 16-21
PHASE 1 DRAFT EIS
Accidental Disruption 16.6.3.1.2
Construction of the new transformer has the potential to damage natural gas mains or the
Olympic Pipeline (if the Lakeside or Vernell substations are expanded) if utility locates are
incorrect, or if excavation work were to go off course. Construction along the existing 115
kV easement also has the potential to damage natural gas mains or the Olympic Pipeline if
utility locates are incorrect, or if auger or pole installation were to go off course.
These types of potential risks for the pipeline are managed under the regulatory framework
described in Section 16.3.3. The state has an excavation damage prevention law that requires
pipeline companies, underground facility owners, and excavators to participate in protecting
the public health and safety when excavating, with civil penalties for violation. The law also
provides that any excavator who willfully or maliciously damages a field-marked
underground facility may be liable for triple the cost incurred in repairing or relocating the
facility. The UTC has investigated a few gas pipeline incidents that were caused by the
failure of underground facility owners to mark utilities, or excavators’ failure to call or
precisely locate gas pipeline facilities (UTC, 2015). As a standard practice, OPLC provides
Damage Prevention Teams, established by district or area, to monitor excavations located
near the pipeline (West, 2015).
If a natural gas main or the Olympic Pipeline were to rupture
due to an accident during construction, there could be
significant impacts related to service disruption to PSE or
OPLC customers while damage is addressed, repairs are
conducted, or alternative delivery methods are implemented.
However, as described in Sections 16.3.3 and 16.8 (and in
Chapter 8), conformance with industry standards and
regulatory requirements would ensure that potential hazards are
identified and safeguards established during construction to
minimize adverse effects from these hazards to minor levels.
Option B: Existing Seattle City Light 230 kV Transmission 16.6.3.2
Corridor
Utility Conflicts and Service Disruption 16.6.3.2.1
Similar types of utility relocations, as described for Alternative 1, Option A, may be required
to construct a new substation under Option B. Electric service interruptions during
construction of the new substation would not be anticipated.
The use of SCL’s existing 230 kV overhead transmission lines would likely require
rebuilding both of the SnoKing-Maple Valley 230 kV transmission lines as described in
Chapter 2. To avoid service disruption to SCL customers, work would involve constructing
the replacement line adjacent to the functioning lines and placing them into service prior to
removing the existing structures and conductor. Extensive coordination with SCL would be
required. If constructed along road rights-of-way, the new transmission segment connecting
the SCL line to the Lakeside substation could involve a potential for more utility conflicts
than Alternative 1, Option A (if only existing easements are used for Option A).
Utility location is the
process of identifying and
labeling underground
utility lines. Excavating
without knowing the
location of underground
utilities can result in
damage, which can lead
to service disruptions.
CHAPTER 16 January 2016 16-22 UTILITIES
PHASE 1 DRAFT EIS
Although the transmission lines would in large part be located in or near the existing SCL
corridor, that corridor does cross PSE gas mains and the Olympic Pipeline several times, and
other gas utilities may also be present in the area. As described for Option A, extensive
coordination with OPLC, gas utility providers, and study area communities would be
required during project design to avoid disruption to the Olympic Pipeline. Same as Option
A, conformance with industry standards and regulatory requirements would ensure that
potential hazards are identified and design plans developed to minimize adverse effects from
these hazards to minor levels.
Given the level of coordination required with SCL and other utility providers and the number
of utility relocations potentially required, moderate to significant impacts to utilities could
occur under Alternative 1, Option B.
Accidental Disruption 16.6.3.2.2
The potential for accidental disruption to existing buried utilities, if present within the
construction area, would be similar to that described for Alternative 1, Option A. As with
Option A, construction could occur in the vicinity of the Olympic Pipeline and regional
natural gas pipelines or smaller pipelines that supply natural gas to homes and businesses.
Although the transmission lines would in large part be located outside the Olympic Pipeline
corridor, the Olympic Pipeline crosses the SCL easement at several locations as shown on
Figure 16-1.
As described for Option A, PSE would coordinate closely with OPLC, other utility providers,
and study area communities during project design and construction to avoid accidental
rupture and thus avoid impacts to OPLC and PSE operations. Same as Option A,
conformance with industry standards and regulatory requirements would ensure that potential
hazards are identified and safeguards established during construction to minimize adverse
effects from these hazards to minor levels.
Option C: Underground Transmission Lines 16.6.3.3
Utility Conflicts and Service Disruption 16.6.3.3.1
Similar types of utility relocations as described for Option A may be required to construct the
new substation under Option C. All relocations would be coordinated with the utility service
provider during project design.
Underground transmission lines could be placed in any of the transmission line alignments
considered under Alternative 1, Option A, including the existing 115 kV overhead line
easement or along public road rights-of-way or new rights-of-way. Construction of an
underground line would require trenching for the line and excavation for vault construction.
Construction would result in greater potential for conflicts with existing utilities if
accomplished within road rights-of-way that already contain a substantial amount of utility
infrastructure. In this situation it would be necessary to protect, relocate, or reconstruct
existing utilities. Subsequent project-level evaluations of an underground line would identify
the exact location of existing utilities and potential conflicts with the proposed new
transmission lines.
January 2016 CHAPTER 16 UTILITIES 16-23
PHASE 1 DRAFT EIS
Construction of underground transmission lines would cause a substantially greater amount
of ground disturbance compared to overhead lines, and has the potential for substantial
conflicts with buried utilities that cross or run parallel to the alignment. Relocation of
existing utilities, including the Olympic Pipeline, may be required. Given the greater amount
of ground disturbance associated with constructing an underground line, the potential risk
would be higher relative to an overhead line. Nonetheless, conformance with industry
standards and regulatory requirements would ensure that potential hazards are identified and
design plans developed to minimize adverse effects from these hazards. Due to the increased
area of ground disturbance, the probability of impacts would be somewhat higher than
described for Alternative 1, Options A and B, but still considered low, and anticipated
impacts are expected to be minor to moderate. As described for Option A, PSE would
coordinate closely with OPLC, other utility providers, and study area communities during
project design and construction.
Where an underground transmission line would cross or run parallel to other underground
utilities (natural gas lines, telecommunications lines, water mains, storm drains, wastewater
lines), a minimal radial clearance would be required to minimize the potential for impacts to
existing utilities. To provide the required radial distance around the underground 230 kV line,
underground utilities located within public road rights-of-way, parallel to and near or under
the proposed line, would be moved to a different location within the right-of-way. Trenchless
methods to complete underground lines may reduce the potential for utility conflicts along
the trenchless portion of the alignment, but would involve substantial disturbance and
potential for conflicts at entry and exit points.
Removal of pavement from roadways can cause vibration impacts on older water mains,
wastewater, and drainage lines if present in the immediate vicinity. Special provisions would
be needed to prevent damage to existing utility lines in these areas during transmission line
installation, or proactive pipeline replacement would be needed. With appropriate measures,
which would be determined in the field on a case-by-case basis, impacts would be minor and
any necessary repairs would be made.
Compared to Options A and B, the potential for service disruptions would be higher for an
underground line because of greater number of potential utility relocations needed and
potential for conflicts, if located within existing road rights-of-way or utility corridors. Any
impacts to existing utilities due to utility relocations would be anticipated to be limited to
localized interruptions of service only. As a result, impacts are considered moderate.
Accidental Disruption 16.6.3.3.2
If constructed within PSE’s existing 115 kV line easement, the potential impacts associated
with construction activity in proximity to natural gas mains and the Olympic Pipeline would
be the same as described for Alternative 1, Options A and B. Given the greater amount of
ground disturbance associated with constructing an underground line, the potential risk would
be higher relative to an overhead line. Nonetheless, conformance with industry standards and
regulatory requirements would ensure that potential hazards are identified and safeguards
established during construction to minimize adverse effects from these hazards. Due to the
increased area of ground disturbance, the probability of impacts would be somewhat higher
than described for Options A and B, but still considered low, and anticipated impacts are
CHAPTER 16 January 2016 16-24 UTILITIES
PHASE 1 DRAFT EIS
expected to be minor to moderate. As described for Options A and B, PSE would coordinate
closely with OPLC, other utility providers, and study area communities during project design
and construction to avoid accidental rupture and thus avoid impacts to OPLC and PSE
operations.
Option D: Underwater Transmission Lines 16.6.3.4
Utility Conflicts and Service Disruption 16.6.3.4.1
Similar types of utility relocations as described for Option A may be required to expand a
substation for construction of a new transformer under Option D. As described for Option A,
interruptions of electric service during construction would not be anticipated.
Alternative 1, Option D would include the construction of overhead or underground
transmission lines on land that would connect to the underwater portion of the line. This
would result in ground disturbance and the potential for utility conflicts, if utilities cross or
run parallel to the alignment. The underwater portion of the line would need to cross existing
submarine lines and cables in Lake Washington, requiring adequate spacing. The overland
lines would potentially cross natural gas lines and the Olympic Pipeline. Impacts would be
similar to those described for Alternative 1, Options A, B and C; however, less construction
would likely occur in the vicinity of the Olympic Pipeline. With appropriate design measures
to protect both existing and new lines, the potential for utility conflicts is considered low and
impacts would be considered minor.
Accidental Disruption 16.6.3.4.2
Construction of the underwater segment of the transmission lines would have a low potential
for accidental disruption of existing utilities for the same reasons as described above. For the
overland segment constructed underground or overhead, the potential for accidental
disruption would be the same as described for Alternative 1, Options A and B (if overhead),
and Option C (if underground) for alignments located in road rights-of-way or new corridors.
Anticipated impacts are expected to be minor.
16.6.4 Alternative 2: Integrated Resource Approach
Energy Efficiency Component 16.6.4.1
Energy efficiency includes methods that reduce demand for energy such as weatherization
and efficiency lighting. Construction activity would be limited and primarily focused on
existing building upgrades. These activities are unlikely to cause utility conflicts or service
disruption. As a result, no construction-related impacts to utilities are anticipated.
Demand Response Component 16.6.4.2
Demand response is an end-user strategy that pertains more to customer usage patterns and
requires little construction of new infrastructure. Construction disturbance would be minimal
and would not result in utility conflicts, service disruption, or accidental disruption. As a
result, no construction-related impacts to utilities are anticipated.
January 2016 CHAPTER 16 UTILITIES 16-25
PHASE 1 DRAFT EIS
Distributed Generation Component 16.6.4.3
Heavy equipment operation and excavation activity would be required for installation of gas
turbines, anaerobic digesters, reciprocating engines, microturbines, and fuel cells. Depending
on the location of these systems, there may be minor impacts to existing buried or overhead
utilities, if present. These utility conflicts would primarily involve small distribution lines
located on private or public properties (not including road rights-of-way). No impacts to
major transmission lines are anticipated.
Energy Storage Component 16.6.4.4
Energy storage would consist of relatively large battery facilities constructed on a site of
approximately 6 acres near a substation. Heavy equipment operation and excavation would
be required for installation of energy storage systems. With larger sites, there is a greater
potential for utility conflicts, service disruption, and accidental disruption if there are existing
utility easements located on the parcels. This may cause minor impacts to utilities, similar to
the distributed generation component.
Peak Generation Plant Component 16.6.4.5
Installation of new peak generation plants would occur adjacent to existing substations.
Heavy equipment operation and excavation would be required for installation of generators
and related equipment. The potential for utility conflicts and disruption would generally be
the same as for the distributed generation and energy storage components. Utilities would
need to be extended at the site, and upgrades or extensions of natural gas or water distribution
lines may be required to supply a generator at a particular location, resulting in minor to
moderate impacts to utilities including temporary interruptions of service to customers.
16.6.5 Alternative 3: New 115 kV Lines and Transformers
Utility Conflicts and Service Disruption 16.6.5.1
Construction associated with complete rebuilds or expansion of the Sammamish, Lakeside,
Talbot Hill, Clyde Hill, and Hazelwood substations, and installation of transformers at the
Sammamish, Talbot Hill, and Lake Tradition substations, would involve substantial
construction disturbance and thus have the potential for utility conflicts. Similar to
Alternative 1, construction adjacent to the Lakeside substation would likely require a greater
amount of utility coordination due to its proximity to the Olympic Pipeline. Construction
would also require coordination with utility providers to extend utilities to the new
transformers. Electric service interruptions during construction of substation modifications
would not be anticipated. In the event that any accidental damage to the existing substation
equipment was to occur, PSE employees are trained to respond and to minimize or avoid
potential service interruptions by transferring load.
Under Alternative 3, new 115 kV transmission lines would likely be constructed along
existing utility or road rights-of-way. Impacts would be similar to those described for
Alternative 1, Option A, except that the shorter towers (smaller foundations) and narrower
rights-of-way could involve less construction disturbance. However, Alternative 3 would
involve construction of more miles of new transmission line than Alternative 1 and would
CHAPTER 16 January 2016 16-26 UTILITIES
PHASE 1 DRAFT EIS
potentially include more line installation along public road rights-of-way. As a result,
Alternative 3 would have a higher likelihood of utility conflicts.
New overhead lines under Alternative 3 could be constructed near natural gas mains and the
Olympic Pipeline, depending on utility or road rights-of-way used, resulting in the same
potential impacts as described for Alternative 1. Same as Alternative 1, conformance with
industry standards and regulatory requirements would ensure that potential hazards are
identified and design plans developed to minimize adverse effects from these hazards to
minor levels.
While Alternative 3 would potentially have a higher likelihood of utility conflicts than
Alternative 1, Option A, any impacts to existing utilities due to utility relocations would
likely be limited to localized interruptions of service only. As a result, impacts are considered
moderate.
Accidental Disruption 16.6.5.2
The potential for accidental disruption to existing buried utilities, if present within the
construction area, would be the same as described for Alternative 1. As with Alternative 1,
Option A, Option B, and Option C, construction could occur in the vicinity of regional
natural gas pipelines or smaller pipelines that supply natural gas to homes and businesses.
Although the new 115 kV transmission line would be located outside the Olympic Pipeline
corridor, expansion of the Lakeside substation could occur in proximity to the Olympic
Pipeline, depending on the area used for expansion. As described for Alternative 1, PSE
would coordinate closely with OPLC, other utility providers, and study area communities
during project design and construction to avoid accidental rupture and thus avoid impacts to
OPLC and PSE operations. Same as Option A, conformance with industry standards and
regulatory requirements would ensure that potential hazards are identified and safeguards
established during construction to minimize adverse effects from these hazards to minor
levels.
HOW COULD OPERATION OF THE PROJECT 16.7
AFFECT UTILITIES?
16.7.1 Operation Impacts Considered
Operational impacts to utilities include the potential for utility conflicts and service
disruption, the types of coordination that would be needed with utility service providers in
order to operate each alternative, and the potential for alternatives to conflict with applicable
plans and policies. In addressing the potential for utility damage and service disruption,
consideration was given to issues of corrosion from proximity to high-voltage lines, and the
potential for accidental damage to nearby utilities from maintenance activities or as a result
of catastrophic damage from natural hazards. The potential for an alternative to result in
changes to PSE customer rates is also addressed.
Operation of utility systems in the combined study area is not expected to change as a result
of any of the alternatives. None of the alternatives are anticipated to increase demand for
other utility services (e.g., gas, water, wastewater) beyond the current capacity of service
January 2016 CHAPTER 16 UTILITIES 16-27
PHASE 1 DRAFT EIS
providers. In addition to electricity (see Chapter 7 for information on electricity usage), the
new transformers would require connections to water, wastewater, and stormwater systems.
Some of the facilities under Alternative 2 would require more utility extensions and increased
demand than other alternatives. However, it is anticipated that the new demand would not
exceed the capacity of utilities, and no upgrades related to supply or transmission capacity
would be anticipated. As a result, none of the alternatives would have adverse operational
impacts on the services provided by those utilities.
Consistency with Applicable Plans and Policies 16.7.1.1
The utilities goals and policies of the study area communities are focused on encouraging the
provision of adequate public utilities and facilities, consistent with planned growth, and
ensuring utility systems are constructed in a manner that minimizes negative impacts to
existing utilities. Goals and policies related to energy, safety, land use (siting), and visual
aspects of utilities are described in Chapter 7, Chapter 8, Chapter 10, and Chapter 11,
respectively. None of the goals and policies of the study area communities specifically
prohibit utility placement within new corridors. However, the use of existing or shared
trenches or utility corridors is encouraged by many study area communities (Redmond,
Kirkland, Bellevue, Newcastle, and King County), when such joint use can be accomplished
in accordance with applicable safety considerations. Three study area communities - King
County, Redmond, and Kirkland - have policies or regulations that would specifically
prohibit combining transmission lines (‘high consequence land uses’) with hazardous
material pipelines.
Utility Conflicts and Service Disruption 16.7.1.2
For any alternative, if new lines or other facilities are co-located with other utilities, PSE
would need to coordinate with other nearby utility providers during project design to avoid
utility damage, service disruption, or issues with ongoing and future operations and
maintenance activities. Depending on the location, new lines or facilities have the potential to
conflict with future utility installation.
Earthquakes or other natural hazards (storms) could cause structural damage to electrical
infrastructure under any alternative. As described in Chapter 3, the Eastside is located in a
seismically active region, and existing infrastructure is at risk of damage in the event of an
earthquake. Due to the close proximity of other utilities to existing electrical infrastructure
(substations, transmission and distribution lines), damage to electrical infrastructure from an
earthquake poses risks that could potentially damage nearby utilities. Similarly, electrical
infrastructure could be damaged by lightning strikes that could generate fires. Both
earthquakes and lightning strikes could also cause damage to nearby buried utilities.
Although not likely, high winds from storms could potentially cause transmission poles,
conductors, or other electric infrastructure to break and fall, damaging nearby utilities and
leading to service disruptions. The new transformers and power lines of Alternatives 1 and 3
and the energy storage facilities of Alternative 2 would be installed according to current
industry standards established in the National Electric Safety Code by the Institute of
Electrical and Electronics Engineers (IEEE), and safety standards of each jurisdiction that are
designed to withstand high winds.
CHAPTER 16 January 2016 16-28 UTILITIES
PHASE 1 DRAFT EIS
16.7.2 No Action Alternative
The proximity of natural gas mains and the two Olympic Pipeline regional lines to the
existing 115 kV transmission line through PSE’s easement presents potential operational
risks to PSE. If a natural gas main or the Olympic Pipeline were to rupture or explode due to
defects, corrosion, or an earthquake, there could be substantial and long-term power outages
to PSE customers, resulting in a significant adverse impact. However, as described in
Sections 16.3.3 and 16.8 (and in Chapter 8), conformance with industry standards and
regulatory requirements ensure that potential hazards are identified and operations and
maintenance procedures in place to minimize adverse effects from these hazards to minor
levels.
Under the No Action Alternative, PSE would take steps to provide consistent power to
existing and future customers through existing facilities, but the proposed electrical
transmission capacity improvements would not occur. If electrical load growth occurs as PSE
has projected, PSE’s system would likely experience loads on the Eastside that would place
the local and regional system at risk of damage. For example, the potential risk of
transformer overheating associated with system overload during peak periods would be
expected to increase under the No Action alternative, if system capacity is not increased.
More frequent system overloading could increase the potential for transformers to catch fire
or explode, with accompanying potential safety hazards. These hazards would be managed
by load shedding and increased outages under the No Action Alternative. While not likely to
occur, impacts from transformer overheating could range from minor to moderate, depending
upon the location of the transformer overload.
Because electrical demand on the Eastside is expected to grow, PSE would face challenges in
providing reliable service while continuing to meet this need without damaging the regional
electrical grid. To address this risk in the near term, PSE would use Corrective Action Plans
(CAPs), which are a series of operational steps used to prevent system overloads or large-
scale loss of customers’ power. CAPs generally involve shutting off or reducing load on
overloaded equipment and rerouting the load to other equipment. Some CAPs can keep the
entire system operating, but place large numbers of customers at risk if anything else on the
system begins to fail. For example, PSE is already using CAPs to prevent winter overloads
on the Talbot Hill transformer banks. When these CAPs are employed for Talbot Hill, up to
approximately 68,800 customers are at risk of outages if another piece of equipment fails.
Under more extreme conditions CAPs can also include temporarily shutting off power to
some customers (referred to as load shedding). In the event of load shedding under CAPs,
PSE prioritizes delivery of power to emergency and critical public services.
Under the No Action Alternative, less reliable service could result in power disturbances and,
without additional capacity in the near future, increase the likelihood of power outages during
extreme temperature periods in both summer and winter. As a result, the No Action
Alternative could result in significantly reduced reliability of electrical service to some areas
due to increasing load on the existing system, resulting in potentially moderate to significant
negative impacts to electrical service reliability. Consequently, the No Action Alternative
would be inconsistent with some local planning policies related to providing adequate power
supply for anticipated growth.
January 2016 CHAPTER 16 UTILITIES 16-29
PHASE 1 DRAFT EIS
16.7.3 Alternative 1: New Substation and 230 kV Transmission Lines
Impacts are described according to the major components associated with Alternative 1. The
substation impacts are described first, followed by transmission line impacts.
Option A: New Overhead Transmission Lines 16.7.3.1
Consistency with Applicable Plans and Policies 16.7.3.1.1
Alternative 1 would be consistent with local planning policies stating a need for adequate
power supply. Under Option A, it is anticipated that new overhead lines would be installed
within existing transmission or other utility easements, or in new locations currently not
dedicated to transmission. New locations could include areas along road rights-of-way, rail
corridors, or over or through private or other public property. While not prohibited, locating
utilities in new corridors is not encouraged by goals and policies of many study area
communities. However, a new 230 kV line within PSE’s existing 115 kV line easement may
not be consistent with goals and policies of some study area communities that specifically
discourage co-location of critical utilities with hazardous fluid pipelines like the Olympic
Pipeline.
Utility Conflicts and Service Disruption 16.7.3.1.2
Substation expansion and the new 230 kV transmission lines would be designed and placed
to minimize future conflicts with existing or proposed utility lines. If transmission lines are
located along road rights-of-way, the poles could limit the possible location of future
stormwater control measures, such as biofiltration swales. Major service disruptions to utility
customers during repair and maintenance are unlikely. Electric facilities would be located so
that access to utilities for repair and maintenance could be maintained.
New overhead lines under Option A could be in operation near natural gas mains and the two
Olympic Pipeline regional lines described earlier. There would be some risk to PSE and its
customers from continuing to operate a transmission line within the same corridor as existing
natural gas mains and the Olympic Pipeline. The same potential impacts that might occur
during construction could also occur during ongoing operations. For example, maintenance
activities on the transmission line could require heavy equipment to cross the buried Olympic
Pipeline, or excavation at existing pole foundations could require excavation in proximity to
the Olympic Pipeline. These same risks are already present with the existing 115 kV lines
and would remain with a 230 kV line. As described under the No Action Alternative,
conformance with industry standards and regulatory requirements ensure that potential
hazards are identified and operations and maintenance procedures in place that minimize
adverse effects from these hazards to minor levels.
Corrosion 16.7.3.1.3
No impacts to utilities around the substation and new transformer relative to electric current
are anticipated. If necessary, PSE would provide nonconductive pipe on underground utilities
leaving the substation site to avoid damage to utility line coatings in the rare event of a
possible fault condition at the substation site (Strauch, personal communication, 2016).
Compared to a 115 kV line, EMF is stronger with the higher voltage of a 230 kV line, but
higher voltage requires more ground clearance which can mitigate this stronger field to some
CHAPTER 16 January 2016 16-30 UTILITIES
PHASE 1 DRAFT EIS
extent. The closer to the ground the lines are, the stronger the electric field at the surface
(Marrinan, personal communication, 2015).
Given the higher voltage of the 230 kV line, there is potential for the new line to increase
cathodic-induced corrosion of steel or other metallic pipelines, if present, which could lead to
long-term accidental system disruption of such pipelines. If existing utility lines were
damaged by corrosion and taken out of service for repairs, it would temporarily impact the
utility provider’s ability to provide service to its customers. As described in Section 16.4,
operators of natural gas and hazardous liquid pipelines must establish procedures to
implement and maintain a corrosion control program for their piping systems under 49 CFR
Part 192 (gas) and 49 CFR Part 195 (hazardous liquid pipelines). These procedures include
design, installation, operation, and maintenance activities on a cathodic protection system.
If PSE’s existing 115 kV easement is used for the new 230 kV line, there may be a need for
changes to the cathodic protection on natural gas mains and the Olympic Pipeline to address
the change in EMF. Criteria that pipeline owners use to determine the adequacy of cathodic
protection on hazardous liquid pipelines are included in CFR Part 195.571, which
incorporates by reference industry standards and practices developed by NACE (2007). As
described in Section 16.4.3, cathodic inspection is conducted annually according to 49 CFR
Part 195.573.
With appropriate cathodic-protection measures, which would be determined by the utility
owner on a case-by-case basis in accordance with applicable federal requirements, any
impacts would be minor.
Option B: Existing Seattle City Light 230 kV Transmission 16.7.3.2
Corridor
Consistency with Applicable Plans and Policies 16.7.3.2.1
Alternative 1, Option B would utilize existing 230 kV overhead transmission lines in SCL’s
existing easement. This option is consistent with the goals and policies of the study area
communities that explicitly encourage the use of existing utility corridors.
As described in Chapter 2, SCL has not agreed to this option. Any use of the existing corridor
would be subject to SCL agreement and review. SCL has policies related to the incidental use
of real property and real property rights by others. These policies generally allow that
incidental uses may be permitted provided they do not interfere with the primary use of the
property for SCL purposes, do not create hazardous conditions or obstruct the operation and
maintenance of the utility system, or limit SCL’s ability to serve its customers (City of
Seattle, 1996).
Utility Damage and Service Disruption 16.7.3.2.2
As with Alternative 1, Option A, the new 230 kV transmission line would be designed and
placed to minimize future conflicts with existing and proposed utility lines. PSE would work
with other utility service providers during design of the project to coordinate the placement of
the poles and transmission lines as well as any utility lines that would need to be replaced and
relocated as part of the project.
January 2016 CHAPTER 16 UTILITIES 16-31
PHASE 1 DRAFT EIS
New overhead lines under Alternative 1, Option B would be in operation over natural gas
mains and the Olympic Pipeline, which cross the SCL easement in several locations. There
would be some risk to PSE and its customers from continuing to operate a transmission line
in proximity to natural gas mains and the Olympic Pipeline. The same potential impacts that
might occur during construction could also occur during ongoing operations. For example,
maintenance activities on the transmission line could require heavy equipment to cross the
buried Olympic Pipeline, or excavation at existing pole foundations could require excavation
in proximity to the Olympic Pipeline. In the event that a PSE maintenance activity were to
damage or breach a natural gas main or the Olympic Pipeline, there could be significant
impacts related to service disruption to PSE customers, SCL customers, and/or OPLC’s
customers while repairs are made or alternative delivery is implemented. As described for
Option A, conformance with industry standards and regulatory requirements ensure that
potential hazards are identified and operations and maintenance procedures developed that
minimize adverse effects from these hazards to minor levels.
Corrosion 16.7.3.2.3
Locating an additional 230 kV transmission line along SCL’s easement would increase the
potential for corrosion of any buried metallic pipelines present within the easement. With
appropriate cathodic-protection measures, which would be determined by the utility owner on
a case-by-case basis in accordance with applicable federal standards, impacts would be
minor.
Option C: Underground Transmission Lines 16.7.3.3
Consistency with Applicable Plans and Policies 16.7.3.3.1
Alternative 1, Option C could utilize any of the transmission line alignments considered
under Option A, including the existing 115 kV overhead line easement, or public road rights-
of-way or new rights-of-way. Alignments along existing utility corridors would generally be
consistent with the goals and policies of the study area communities that explicitly encourage
the use of existing utility corridors. Alignments within new utility corridors may not be
prohibited but are generally not encouraged by the goals and policies of the study area
communities. In addition, a new underground 230 kV line within PSE’s existing 115 kV line
easement may not be consistent with goals and policies of some study area communities that
specifically discourage co-location of critical utilities with hazardous fluid pipelines like the
Olympic Pipeline.
Utility Conflicts and Service Disruption 16.7.3.3.2
Major service disruptions to utility customers during repair and maintenance along the buried
line are unlikely. However, if existing utility lines were damaged and taken out of service for
repairs, it would temporarily impact service to customers. As described for construction, the
new transmission line would be designed and placed to minimize future conflicts with
proposed utility lines. Repair and maintenance along the line is generally accomplished
through vaults, avoiding the need to disrupt nearby utilities to gain access.
Given the finite space within road rights-of-way for placement of utilities, the presence of
underground lines and vaults (if located within road right-of-way) can present a barrier for
other utility work in the future. For example, if located along road rights-of-way, the lines
could limit the possible location of stormwater control measures, such as biofiltration swales.
CHAPTER 16 January 2016 16-32 UTILITIES
PHASE 1 DRAFT EIS
PSE would work with other utility service providers during design and construction of the
project to coordinate the placement of the transmission line and vaults as well as other utility
lines being replaced and relocated as part of the project. With proper coordination, impacts
are assumed to be minor.
If located within PSE’s existing 115 kV line easement, the potential impacts associated with
operation and maintenance activity in proximity to natural gas mains and the Olympic
Pipeline would be the same as those described for Alternative 1, Option A. In the event that a
PSE maintenance activity were to damage or rupture a gas main or the Olympic Pipeline,
there could be service disruptions to PSE natural gas and OPLC’s customers until repairs or
alternative delivery methods are implemented. In addition, there would be some risk to PSE
and its customers from operating a transmission line within the same corridor as existing
natural gas and petroleum pipelines. An explosion, regardless of cause, would potentially
damage an underground transmission line, leading to substantial power outages. In the event
that a PSE maintenance activity were to damage or breach a natural gas main or the Olympic
Pipeline, there could be service disruption to PSE natural gas or OPLC’s customers while
repairs are made or alternative delivery is implemented. As described for Option A, PSE
would coordinate closely with OPLC, other utility providers, and study area communities
during project design and construction to avoid accidental rupture and thus avoid impacts to
OPLC and PSE operations. Same as Option A, conformance with industry standards and
regulatory requirements would ensure that potential hazards are identified and safeguards
established during operations and maintenance activities to minimize adverse effects from
these hazards to minor levels.
No special co-location issues related to natural hazards or accidents have been identified for
Alternative 1, Option C. In general, buried facilities perform well during a seismic event,
although they can be subject to damage from liquefiable soils, if present. See Chapter 3 for
additional discussion of seismicity in the region.
Corrosion 16.7.3.3.3
Underground lines are typically constructed in a trefoil configuration and the EMF fields tend
to cancel more completely. Underground lines are also shielded, which further cancels the
EMF field. As a result, underground lines have a weaker field strength compared to overhead
lines (Marrinan, personal communication, 2015). In the event that transmission lines were
installed parallel to other utility lines over long distances and in very close proximity, it is
theoretically possible, but unlikely, that the sustained electric or magnetic field from the line
could negatively affect or corrode the other utility lines over time. However, it is likely such
long parallel distances could be avoided, and bare copper conductors along the line would
help prevent this type of corrosion from occurring. Therefore, impacts would be minor. No
operational impacts to other utilities are expected.
Option D: Underwater Transmission Lines 16.7.3.4
Consistency with Applicable Plans and Policies 16.7.3.4.1
Under Alternative 1, Option D, most construction would occur within new corridors currently
not occupied by utilities. New locations would include submerged corridors under Lake
Washington, and could include private or other public property where the line transitions
from the lake bed to land and the substation. While not prohibited, locations in new corridors
January 2016 CHAPTER 16 UTILITIES 16-33
PHASE 1 DRAFT EIS
where utilities are not already present is not encouraged by goals and policies of many study
area communities.
Utility Conflicts and Service Disruption 16.7.3.4.2
For the overland portion of the transmission lines under Alternative 1, Option D, the potential
for major maintenance activities to damage nearby utilities or cause service disruptions
would be the same as described for Options A or B (if overhead) and for Option C (if
underground). Impacts would be minor.
No special co-location issues related to natural hazards or accidents have been identified for
Alternative 1, Option D. Once completed, underwater transmission lines would generally be
expected to perform very well in an earthquake event. See Chapter 3 for additional discussion
of seismicity.
Corrosion 16.7.3.4.3
Underwater transmission cables would be designed to require limited maintenance once
installed. Cables used would be solid-state, with protective layers designed to provide
superior corrosion protection, thereby reducing the need for repairs. In-water cables would be
inspected regularly to confirm system integrity.
For the on-land portion of the transmission lines under Alternative 1, Option D, the potential
for corrosion of nearby buried metallic pipelines would be the same as described for Options
A or B (if overhead) and for Option C (if underground). Measures would be implemented to
help prevent corrosion from occurring. With appropriate cathodic-protection measures, which
would be determined by the utility owner on a case-by-case basis in accordance with
applicable federal standards, any impacts would be minor.
16.7.4 Alternative 2: Integrated Resource Approach
A number of the Alternative 2 study area communities have energy policies that would
support the types of actions and features of this alternative (see Chapter 7 for more
information on energy policies).
In order to ensure consistent electrical service to existing and future PSE customers, this
alternative would require additional measures to address uncertainties inherent in relying on
voluntary participation and non-transmission resources. This would include strengthening of
voluntary requirements and additional incentives to encourage participation. It would also
require increased monitoring of electric power use, demand, and trends to support ‘just-in-
time’ electrical management. If measures do not bring about the needed conservation, there
could be reliability issues that could place the local and regional system at risk, similar to the
No Action Alternative.
The discussion of individual components below acknowledges that there could be significant
impacts to relying on a single strategy or component to meet PSE’s objectives for Energize
Eastside. A combination of the components would be needed, but uncertainties about the
feasibility and performance of certain technologies, customer participation levels, and
achievable conservation result in a risk to reliability. Given the uncertainty in implementing
CHAPTER 16 January 2016 16-34 UTILITIES
PHASE 1 DRAFT EIS
this solution within the timeframe when capacity is anticipated to be needed, this alternative
could have moderate to significant impacts on electric service reliability.
Energy Efficiency Component 16.7.4.1
To meet the project objectives for Energize Eastside, existing energy efficiency and
conservation efforts would need to be substantially accelerated and expanded on the Eastside.
Additional studies would be required to determine efficiency potential on the Eastside and
the costs to substantially accelerate and expand programs. Given uncertainties about the
ability to increase participation, energy efficiency and conservation efforts would need to be
implemented together with other demand-side reduction strategies.
Implementation of the energy efficient component is not anticipated to cause impacts to other
(non-electric) utilities. The potential for damage, service disruption, or increased demand for
other utility services is considered low.
Demand Response Component 16.7.4.2
In order to address the electric deficiency projected for the Eastside, adoption of this program
within the Eastside would have to be substantially accelerated and expanded in the near
future. Given uncertainties about participation, demand response would need to be
implemented together with other demand-side reduction strategies and would not be
considered a stand-alone option.
The potential for damage, service disruption, or increased demand for other (non-electric)
utility services is considered low.
Distributed Generation Component 16.7.4.3
Distributed generation would involve building new small-scale energy generation facilities at
various sites across the Eastside. These facilities would use renewable energy sources such as
wind, solar, or waste, or petroleum products such as diesel or natural gas to provide electrical
power.
New distributed generation resources would need to be capable of producing power when
needed at peak times, such as during a winter cold snap or a summer warm spell, or be
associated with an energy storage system that would allow use of the energy during peak
periods. For an energy generating resource to be effective, it also has to be reliable, which
means it must be well-maintained and capable of producing a specified amount of energy
when needed. If adequate system redundancy is not provided, electrical power production
would likely not meet the demand during certain times. Also, if distributed generation is not
located at or near the load, effectiveness would be reduced.
The potential for damage or service disruption to other (non-electric) utilities as a result of
operations and maintenance is considered low. Depending on the type of facility, there could
be additional demand for utilities (e.g., natural gas, water, wastewater) to serve the facility,
but the additional demand is not expected to exceed the ability of utilities to provide service.
January 2016 CHAPTER 16 UTILITIES 16-35
PHASE 1 DRAFT EIS
Energy Storage Component 16.7.4.4
The Eastside system has constraints during off-peak periods that could prevent an energy
storage system from maintaining sufficient charge to eliminate or sufficiently reduce normal
overloads over multiple days. Also, the existing Eastside transmission system does not have
sufficient capacity to fully charge a baseline storage configuration as described in Chapter 2.
These and other technical challenges suggest that energy storage could be considered only as
a partial solution that would need to be implemented together with other demand-side
reduction strategies.
There is a low potential for damage or service disruption to other (non-electric) utilities as a
result of operations and maintenance. Depending on the utility extensions and connections
needed for a battery storage facility, there could be additional demand for utilities to serve the
storage sites, but the additional demand is not expected to exceed the ability of utilities to
provide service.
Peak Power Generation Component 16.7.4.5
Increased demand for natural gas and water to supply peak generation plants during peak
times could require upgrades to major gas and water supply lines. While upgrades or
extensions of gas and water distribution lines could be needed, this new demand is not
expected to adversely affect the natural gas supply over the long term.
16.7.5 Alternative 3: New 115 kV Lines and Transformers
Consistency with Applicable Plans and Policies 16.7.5.1
Where constructed in existing corridors where other utilities are present, Alternative 3 would
be generally consistent with the goals and policies of the study area communities that
explicitly encourage the use of existing utility corridors.
Utility Conflicts and Service Disruption 16.7.5.2
Same as Alternative 1, the new 115 kV transmission lines under Alternative 3 would be
designed and placed to minimize future maintenance conflicts with existing and proposed
utility lines. Alternative 3 would involve construction of more miles of new transmission line
than Alternative 1 and would likely include more line installation along public road rights-of-
way. However, potential for utility damage or service disruption during operations and
maintenance activities would remain low with appropriate design and placement.
New overhead lines under Alternative 3 could be in operation near natural gas mains and the
Olympic Pipeline, depending on utility or road rights-of-way used. The same potential
impacts that might occur during construction could also occur during ongoing operations. For
example, maintenance activities on the transmission line could require heavy equipment to
cross the buried Olympic Pipeline, or excavation at existing pole foundations could require
excavation in proximity to the Olympic Pipeline. Given conformance with existing
regulations and practices now in place for pipeline safety, adverse effects from these hazards
would be minimized to minor levels.
CHAPTER 16 January 2016 16-36 UTILITIES
PHASE 1 DRAFT EIS
Corrosion 16.7.5.3
The potential risk of new 115 kV lines to induce corrosion on buried metallic pipelines would
be slightly reduced compared to 230 kV lines because of the reduced voltage. However, there
would still be an increased corrosion potential for any buried metallic pipelines, if present
along the transmission line alignment. With appropriate cathodic-protection measures, which
would be determined by the utility owner on a case-by-case basis, impacts would be minor.
WHAT MITIGATION MEASURES ARE AVAILABLE 16.8
FOR POTENTIAL IMPACTS TO UTILITIES?
A substantial set of federal, state, and local regulations and practices are in place to minimize
the potential for utility conflicts and disruptions during both construction and operation,
including regulations specific to work near petroleum pipelines (see Section 16.3.3). PSE
would be required to design, construct, and operate new facilities according to industry
standards and applicable requirements.
This section presents general mitigation measures identified to avoid or reduce the potential
utility impacts expected to occur during construction or operation. As part of project final
design, specific mitigation measures for effects on utilities would be developed during the
ongoing coordination process between PSE, SCL, OPLC, and other local and regional utility
providers. Some of the potential mitigation measures for effects on utilities are the following:
Coordination with Other Utility Providers: PSE would site new transmission lines
according to industry best practices, which includes proper positioning and design (separation
and grounding) relative to other utilities. For all alternatives, coordination with the individual
utility providers would be required to determine whether or not existing and future utilities
could be affected and how best to avoid or minimize those impacts. PSE would work with
other utility service providers during design and construction of the project to coordinate the
placement of new facilities and ensure protection of other utilities. In some instances,
vibration and settlement monitoring may be required where construction would occur near
existing utilities.
Coordination with Other Projects: PSE would coordinate all construction needs and
impacts of this project with the other infrastructure and development projects in the
combined study area. This would typically be done as part of the permitting process with
each community affected by potential construction.
Utility Location: PSE would follow regulatory requirements to correctly locate and plan for
other utility locations such as gas lines or the OPLC pipelines prior to start of construction,
including showing pipeline locations on plans and requiring contractors to field locate
utilities. Prior to the start of construction, existing utilities would be located and field-verified
where feasible to avoid conflicts with the proposed facilities.
Utility Relocations: PSE and its contractors would be required to develop construction
sequence plans and coordinate schedules for utility work to minimize service disruptions and
provide ample advance notice when service disruptions are unavoidable, consistent with
January 2016 CHAPTER 16 UTILITIES 16-37
PHASE 1 DRAFT EIS
utility owner policies. Relocation plans and service disruptions would be reviewed and
approved by the affected utility providers before construction begins. PSE would develop a
plan for public outreach to inform customers of potential service outages and construction
schedules. The public outreach effort would be coordinated with other utility service
providers.
ARE THERE ANY CUMULATIVE IMPACTS TO 16.9
UTILITIES AND CAN THEY BE MITIGATED?
Construction of the Energize Eastside Project, in combination with other concurrent
construction activities, may result in temporary adverse cumulative effects by increasing the
potential for service outages or damage to existing infrastructure. Utility outages could affect
businesses and residential customers. Specific construction-related cumulative effects will be
identified for the project-level EIS, when reasonably foreseeable projects can be identified.
Once construction is completed, the Energize Eastside Project would result in cumulative
long-term benefits through upgrades of utility infrastructure in accordance with anticipated
future development, thereby reducing the risk of future service disruptions.
ARE THERE ANY SIGNIFICANT UNAVOIDABLE 16.10
ADVERSE IMPACTS TO UTILITIES?
Under the No Action Alternative, Alternative 1, and Alternative 3, there is a risk of damage
and subsequent disruptions to utility customers whenever construction or operations and
maintenance occur near buried natural gas or petroleum pipelines. However, that risk is not
considered an unavoidable significant impact because the probability of damage occurring is
minimized by conformance with industry standards, regulatory requirements, and
construction and operational procedures that address pipeline safety.
Both the No Action Alternative and Alternative 2 have potential unavoidable significant
impacts to utilities. Under the No Action Alternative, PSE would be required to implement
CAPs (load shedding) if electrical load growth occurs as PSE has projected, resulting in
potentially significant risks to service reliability. Under the No Action Alternative, less
reliable service could result in power disturbances and, without additional capacity in the
near future, increase the likelihood of power outages during extreme temperature periods in
both summer and winter.
Under Alternative 2, uncertainties about the feasibility and performance of certain
technologies, customer participation levels, and achievable conservation would result in a
risk to reliability. Given the uncertainty in implementing an integrated resource solution
within the timeframe when capacity is expected to be needed, this alternative could have
moderate to significant impacts on electric service reliability.
CHAPTER 16 January 2016 16-38 UTILITIES
PHASE 1 DRAFT EIS
REFERENCES CHAPTER 17.
CHAPTER 1 INTRODUCTION
City of Bellevue. 2015. Phase 1 Draft EIS Scoping Report. June 30, 2015.
FERC (Federal Energy Regulatory Commission). 2007. Order No. 890 CEII Request
Procedure. Available July 11, 2007. Available at
http://www.oatioasis.com/PSEI/PSEIdocs/CEII_Procedures_(07-11-07).pdf. Accessed
December 28, 2015.
Gentile, T.J., D.J. Morrow, Z.A. Gill Sanford, C.O. Jaeger, and J.V. Nedrud. 2014. Puget
Sound Energy and Quanta Technology. Eastside Transmission Solutions Report, King
County Area. October 2013. Updated February 2014.
Gentile, T.J., D.J. Morrow, E.M. Ewry, and C.O. Jaeger. 2015. Puget Sound Energy and
Quanta Technology. Supplemental Eastside Needs Assessment Report, Transmission
System, King County. April 2015.
Nexant. 2015. Puget Sound Energy Energize Eastside Outage Cost Study. Prepared for Puget
Sound Energy. October 30, 2015.
PSE (Puget Sound Energy). 2013a. Puget Sound Energy 2013 Integrated Resource Plan.
Available at http://pse.com/aboutpse/EnergySupply/Pages/Resource-Planning.aspx.
Accessed August 11, 2015.
PSE (Puget Sound Energy). 2013b. Puget Sound Energy 2013 Integrated Resource Plan,
Appendix E: Regional Transmission Resources. Prepared by Puget Sound Energy,
Bellevue, Washington. May 30, 2013. Available at
http://pse.com/aboutpse/EnergySupply/Pages/Resource-Planning.aspx. Accessed
August 11, 2015.
PSE (Puget Sound Energy). 2015. 2015 Integrated Resource Plan (PSE, 2015). Available at
https://www.pse.com/aboutpse/EnergySupply/Pages/Resource-Planning.aspx. Accessed
January 12, 2016.
PSE (Puget Sound Energy). 2016. Puget Sound Energy service area. Available at
https://pse.com/aboutpse/PseNewsroom/MediaKit/1213_ServiceAreaMap_web.pdf.
Accessed January 12, 2016.
Stantec. 2015. Energize Eastside Project Memorandum from Keith DeClerck to Mark
Johnson, dated July 31, 2015. Available at
http://www.energizeeastsideeis.org/library.html.
U.S.-Canada Power System Outage Task Force. 2004. Final Report on the August 14, 2003
Blackout in the United States and Canada: Causes and Recommendations. April 2004.
January 2016 CHAPTER 17 REFERENCES 17-1
PHASE 1 DRAFT EIS
CHAPTER 2 PROJECT ALTERNATIVES
AEPOhio. 2014. Encroachments on Transmission Rights of Way. Published by AEPOhio, a
division of American Electric Power. Undated. Available at:
https://www.aepohio.com/global/utilities/lib/docs/info/facts/aepohio-encroachment-
ontransrow.pdf. Accessed August 2015.
Biomass Energy Centre. 2015. Anaerobic digestion. Available at
http://www.biomassenergycentre.org.uk/portal/page?_pageid=75,17509&_dad=portal&
_schema=portal. Accessed December 17, 2015.
Capehart, B.L. 2014. Microturbines. Whole Building Design Guide. Last updated: November
11, 2014. Available at https://www.wbdg.org/resources/microturbines.php.
Capstone Turbine Corporation. 2015. Products: C200. Available at
http://www.capstoneturbine.com/products/c200. Accessed December 17, 2015.
Clauser, G. 2016. 4 Smart Energy Monitoring Systems to Help You Control Your Electricity
Bill. EH Network Home Energy Management. Published January 6, 2016. Available at
http://www.electronichouse.com/daily/home-energy-management/4-smart-energy-
management-systems-help-control-electricity-bill/. Accessed December 17, 2015.
Department for Environment, Food & Rural Affairs and Department of Energy and Climate
Change. 2013. How to comply with regulations for energy recovery and advanced
conversion technologies. Gov. UK. Published on January 22, 2013. Available at
https://www.gov.uk/guidance/generating-energy-from-waste-including-anaerobic-
digestion.
Energy Capital Partners. 2015. Broad River Power LLC. Available at
http://www.ecpartners.com/investhm.aspx?invID=19. Accessed January 13, 2016.
Fischbach, A. 2014. Linemen Rebuild for Future Energy Needs. Transmission and
Distribution World (T&D Word) Magazine. Published September 2, 2014. Available at
http://tdworld.com/features/linemen-rebuild-future-energy-needs. Accessed December
17, 2015.
Gentile, T.J., D.J. Morrow, Z.A. Gill Sanford, C.O. Jaeger, and J.V. Nedrud. 2014. Puget
Sound Energy and Quanta Technology. Eastside Transmission Solutions Report, King
County Area. October 2013. Updated February 2014.
Gentile, T.J., D.J. Morrow, E.M. Ewry, and C.O. Jaeger. 2015. Puget Sound Energy and
Quanta Technology. Supplemental Eastside Needs Assessment Report, Transmission
System, King County. April 2015.
Gulf Power. 2015. Work Completed on Gulf Power’s Largest Grid Construction Project.
Gulf Power News Center. Published July 23, 2015. Available at
CHAPTER 17 January 2016 17-2 REFERENCES
PHASE 1 DRAFT EIS
http://www.gulfpowernews.com/work-completed-on-gulf-powers-largest-grid-
construction-project/. Accessed December 17, 2015.
Nedrud, 2015 Personal communication. Email from Jens Nedrud, Senior Project Manager,
(Puget Sound Energy) to Keith DeClerck (Stantec) and Mark Johnson (ESA) June 24,
2015 at 4:56 PM.
Madison Gas and Electric. 2015. Reciprocating Engine Generators. Available at
https://www.mge.com/saving-energy/business/bea/article_detail.htm?nid=1741.
Accessed December 17, 2015.
PSE (Puget Sound Energy). 2013. Puget Sound Energy 2013 Integrated Resource Plan.
Power Engineers. 2015. Eastside 230 kV Project, Lake Washington Submarine Cable
Alternative Feasibility Study – Final. June 8, 2015.
SCL (Seattle City Light). 2014. 2014 Integrated Resource Plan Update and Progress Report.
Simens. 2015. Industrial Gas Turbines for Immediate Sale. Available at
http://www.energy.siemens.com/hq/en/fossil-power-generation/gas-
turbines/immediate-sale.htm. Accessed December 17, 2015.
Snohomish Public Utility District. 2013 Integrated Resource Plan. Public Utility District #1
of Snohomish County. Adopted November 19, 2013.
Soutter, Will. 2012. Nanotechnology in Fuel Cells. AZO Nano. Published on June 25, 2012.
Available at http://www.azonano.com/article.aspx?ArticleID=3032. Accessed
December 17, 2015.
Strategen. 2015. Eastside System Energy Storage Alternatives Screening Study, March 2015.
Strauch, Bradley. 2015a. Personal communication. Email from Bradley Strauch, Senior Land
Planner/Environmental Scientist (Puget Sound Energy) to Mark S. Johnson (ESA).
October 27, 2015 at 10:54 AM.
Strauch, Bradley. 2015b. Personal communication. Email from Bradley Strauch, Senior Land
Planner/Environmental Scientist (Puget Sound Energy) to Mark S. Johnson (ESA).
October 29, 2015 at 8:25 AM.
Strauch, Bradley. 2015c. Personal communication. Email from Bradley Strauch, Senior Land
Planner/Environmental Scientist (Puget Sound Energy) to Mark S. Johnson (ESA).
October 30, 2015 at 12:57 PM with attachment.
Transelect. 2015. Our Services Level 1 Construction – Distribution/Transmission. Available
at http://www.transelect.com.au/level1-distribution.htm. Accessed December 17, 2015.
January 2016 CHAPTER 17 REFERENCES 17-3
PHASE 1 DRAFT EIS
U.S. DOE (U.S. Department of Energy). 2015. Adding Insulation to an Existing Home.
Available at http://energy.gov/energysaver/adding-insulation-existing-home. Accessed
December 17, 2015.
Wood, E. 2014. Transmission and Energy Storage 2014 Outlook: The Macro and Micro
Transformation of Electric Grids. Renewable Energy World. Com. Published January
23, 2014.
CHAPTER 3 EARTH
City of Seattle. 2015. Emergency Management, Earthquake Risks. Available at
http://www.seattle.gov/emergency-management/what-if/hazards/earthquake. Accessed
August 24, 2015.
CREW (Cascadia Region Earthquake Workgroup). 2013. Cascadia Subduction Zone
Earthquakes: A Magnitude 9.0 Earthquake Scenario, update 2013.
IEEE Standards Association, 2012 National Electric Safety Code. Available at
https://standards.ieee.org/findstds/standard/C2-2012.html. Accessed December 18,
2015.
King County. 2009. Hazard Mitigation Plan, Tsunamis and Seiches. Prepared by Regional
Partners and King County Office of Emergency Management. November 2009.
King County. 2015. GIS database. Available at http://www5.kingcounty.gov/gisdataportal/.
Accessed August 12, 2015.
Nisqually Earthquake Clearinghouse Group. 2001. The Nisqually Earthquake of 28 February
2001. Preliminary Reconnaissance Report. University of Washington, March 2001.
NRCS (Natural Resources Conservation Service). 2015. Web Soil Survey, King County.
Available at http://websoilsurvey.nrcs.usda.gov/app/. Accessed August 24, 2015.
Strategen. 2015. Eastside System Energy Storage Alternatives Screening Study, March 2015.
Strauch, Bradley. 2016. Personal communication. Phone conversation between Bradley
Strauch, Senior Land Planner/Environmental Scientist (Puget Sound Energy) and Mark
S. Johnson (ESA). January 14, 2016.
CHAPTER 4 GREENHOUSE GAS EMISSIONS
Adelsman, H. 2014. Washington State Greenhouse Gas Emissions Inventory 2010 – 2011.
Washington State Department of Ecology. Published December 2014. Publication No.
14-02-024.
CHAPTER 17 January 2016 17-4 REFERENCES
PHASE 1 DRAFT EIS
CAPCOA (California Air Pollution Control Officers Association). 2013. California
Emissions Estimator Model, Appendix A Calculation Details for CalEEMod, Revised
July 2013.
CEQ (Council on Environmental Quality). 2014. Revised Draft Guidance for Greenhouse
Gas Emissions and Climate Change Impacts, December 2014.
City of Bellevue. 2015. Excerpts from City website, Climate and Energy - What the City is
Doing. Available http://www.ci.bellevue.wa.us/greenhouse-gas-bellevue.htm. Accessed
August 25, 2015.
City of Kirkland. 2013. City of Kirkland Climate Protection Action Plan Update. November
2013.
City of Redmond. 2013. Redmond’s Draft Climate Action Implementation Plan. February 12,
2013.
City of Renton. 2011. Appendix D: Greenhouse Gas Inventory. Energy and Climate Plan
2011. Available
https://rentonwa.gov/uploadedFiles/Living/CED/CleanEconomy/Appendix_D_Greenho
use_Gas_Inventory.pdf?n=1920.
City of Sammamish. 2013. City of Sammamish Sustainability Strategy. March 2011.
IPCC (International Panel on Climate Change). 2013. Climate Change 2013, The Physical
Science Basis, Working Group 1 Contribution to the 5th Assessment Report.
King County. 2015. Strategic Climate Action Plan, June 2015.
Kjellsen, K.O. et al. 2005. CO2 Uptake During the Concrete Lifecycle: The CO2 Balance of
Concrete in a Lifecycle Perspective.
PSE (Puget Sound Energy). 2014. Puget Sound Energy 2014 Greenhouse Gas Inventory,
prepared by Environmental Resources Management, July, 2015. Available at
https://pse.com/aboutpse/Environment/Documents/GHG_Inventory2014.pdf. Accessed
August 26, 2015.
PSE (Puget Sound Energy). 2015. Puget Sound Energy’s Greenhouse Gas Policy Statement.
Available at https://pse.com/aboutpse/Environment/Pages/Greenhouse-Gas-
Policy.aspx. Accessed August 26, 2015.
Samaras, C. and K. Meisterling. 2008. Lifecycle Assessment of Greenhouse Gas Emissions
from Plug-in Hybrid Vehicles: Implications for Policy. Environmental Science
Technology Journal of the American Chemical Society, April 2008.
Stephenson, N.L. et al. 2014. Rate of Tree Carbon Accumulation Increases Continuously
with Tree Size. Nature 507: 90-93. March 6, 2014.
January 2016 CHAPTER 17 REFERENCES 17-5
PHASE 1 DRAFT EIS
U.S. Conference of Mayors. 2007. List of Participating Mayors. Available at
http://www.usmayors.org/climateprotection/list.asp. Accessed August 28, 2015.
USDA (U.S. Department of Agriculture). 2011. Assessing Urban Forest Effects and Values,
Los Angeles’ Urban Forest. March 2011.
Washington State Department of Ecology. 2012. Washington State Greenhouse Gas
Emission Inventory 1990–2010. December 2012.Federal Register. 2014. Federal
Register Volume 79 No. 247, Wednesday December 24, 2014, Notices.
CHAPTER 5 WATER RESOURCES
City of Newcastle. 2015. Draft Update to the City of Newcastle Comprehensive Plan. Sent to
City Council January 20, 2015.
Ecology (Washington Department of Ecology). 2014. Washington State’s Water Quality
Assessment and 303(d) List Website. Available at
http://www.ecy.wa.gov/programs/Wq/303d/currentassessmt.html. Accessed August
2015.
Ecology (Washington Department of Ecology). 2015. Water Quality Assessment of
Washington. Available at
https://fortress.wa.gov/ecy/wqamapviewer/default.aspx?res=1920x1200. Accessed
December 29, 2015.
EPA (Environmental Protection Agency). 2012. Water: Monitoring & Assessment. Available
at http://water.epa.gov/type/rsl/monitoring/vms55.cfm. Accessed October 1, 2015.
King County. 2015. GIS database. Available at http://gismaps.kingcounty.gov/iMap.
Accessed August 12, 2015.
NRCS (Natural Resources Conservation Service). 2015. Web Soil Survey. Available at
http://websoilsurvey.nrcs.usda.gov/. Accessed August 11, 2015.
USACE (U.S. Army Corps of Engineers). 2012a. Lake Washington Ship Canal and Hiram
M. Chittenden Locks. Available at
http://www.nws.usace.army.mil/PublicMenu/Menu.cfm?sitename=lwsc&pagename=m
ainpage. Accessed July 15, 2015.
USACE (U.S. Army Corps of Engineers). 2012b. Lake Washington Basin, Lake Washington
Summary Hydrograph. Available at http://www.nwd-
wc.usace.army.mil/nws/hh/basins/lwscsh.html. Accessed July 15, 2015.
USFWS (U.S. Fish and Wildlife Service). 2015. National Wetlands Inventory spatial view
GIS data layer. Accessed July 15, 2015.
CHAPTER 17 January 2016 17-6 REFERENCES
PHASE 1 DRAFT EIS
CHAPTER 6 PLANTS AND ANIMALS
City of Bellevue. 2010. Fish Use of Stream Drainage Basins in the City of Bellevue. March
2010.
City of Bellevue. 2015a. Bellevue Comprehensive Plan 2015.
City of Bellevue. 2015b. Phase 1 Draft EIS Scoping Report. June 30, 2015.
City of Clyde Hill. 2014. City of Clyde Hill 2015-2035 Comprehensive Plan.
City of Issaquah. 2014. Sustainability City Report 2014 Update: Community Sustainability
Indicators.
City of Kirkland. 2013. Urban Forestry Strategic Management Plan.
City of Medina. 2015. City of Medina Comprehensive Plan 2015 Amendment (Draft).
City of Newcastle. 2015. Draft Update to the City of Newcastle Comprehensive Plan. Sent to
City Council January 20, 2015.
City of Sammamish. 2014. i-Tree Canopy Planning Commission Presentation.
Homer, C.G., J.A. Dewitz, L. Yang, S. Jin, P. Danielson, G. Xian, J. Coulston, N.D. Herold,
J.D. Wickham, and K. Megown. 2015. Completion of the 2011 National Land Cover
Database for the Conterminous United States, Representing a Decade of Land Cover
Change Information. Photogrammetric Engineering and Remote Sensing 81(5): 345-
354.
King County. 2013. King County Comprehensive Plan 2013 Update.
King County. 2015. GIS database. Available at http://gismaps.kingcounty.gov/iMap.
Accessed August 12, 2015.
PSE (Puget Sound Energy). 2013. Puget Sound Energy Avian Protection Plan Brochure.
Available at
http://pse.com/aboutpse/psenewsroom/MediaKit/4483_Avian_program_brochure.pdf.
Accessed September 18, 2015.
PSE (Puget Sound Energy). 2015. Vegetation Management Boards. Available at
http://www.energizeeastside.com/Media/Default/Library/JanuaryOpenHouses/Vegetati
onMgmt_boards.pdf. Accessed September 2015.
Sound Transit. 2011. East Link Project Final EIS July 2011. Available at
http://www.soundtransit.org/Projects-and-Plans/East-Link-Extension/East-Link-
Extension-document-archive/East-Link-Documents/East-Link-document-
collections/East-Link-Final-EIS-document-collection. Accessed September 24, 2015.
January 2016 CHAPTER 17 REFERENCES 17-7
PHASE 1 DRAFT EIS
Strategen. 2015. Eastside System Energy Storage Alternatives Screening Study, March 2015.
The Watershed Company. 2009. Bellevue Urban Wildlife Habitat Literature Review.
Available at
http://www.ci.bellevue.wa.us/pdf/Development%20Services/ca_urban_habitat_lit.pdf.
Prepared for the City of Bellevue. Kirkland, WA.
USFWS (U.S. Fish and Wildlife Service). 2007. National Bald Eagle Management
Guidelines. May 2007.
USFWS (U.S. Fish and Wildlife Service). 2015. Data set for federal threatened and/or
endangered species.
WDFW (Washington Department of Fish and Wildlife). 2007. SalmonScape interactive
mapping tool. Available at http://apps.wdfw.wa.gov/salmonscape/.
WDFW (Washington Department of Fish and Wildlife). 2008. Priority Habitats and Species
List. August 2008.
WDFW (Washington Department of Fish and Wildlife). 2013. Threatened and Endangered
Wildlife, State of Washington Annual Report 2012.
WDFW (Washington Department of Fish and Wildlife). 2015. Priority Habitats and Species
(PHS) on the Web.
WNHP (Washington Natural Heritage Program). 2015. Geographic information data set for
rare plant species and ecosystems.
CHAPTER 7 ENERGY AND NATURAL RESOURCES
AGA (American Gas Association). 2015. Supply. Available at https://www.aga.org/supply.
Accessed October 31, 2015.
PSE (Puget Sound Energy). 2013. Puget Sound Energy 2013 Integrated Resource Plan.
Available at http://pse.com/aboutpse/EnergySupply/Pages/Resource-Planning.aspx.
Accessed August 11, 2015.
PSE (Puget Sound Energy). 2015a. Electric Supply. Available at
https://pse.com/aboutpse/EnergySupply/Pages/Electric-Supply.aspx. Accessed August
18, 2015.
PSE (Puget Sound Energy). 2015b. Puget Sound Energy’s 2012-2013 Biennial Electric
Conservation Achievement. Available at
http://pse.com/savingsandenergycenter/About/Pages/default.aspx. Accessed September
16, 2015.
PSE (Puget Sound Energy). 2015c. Savings and Energy Center Alternative Fuels Vehicles.
Available at
CHAPTER 17 January 2016 17-8 REFERENCES
PHASE 1 DRAFT EIS
https://pse.com/savingsandenergycenter/AlternativeFuelVehicles/Pages/Fleet-
vehicles.aspx. Accessed September 23, 2015.
CHAPTER 8 ENVIRONMENTAL HEALTH
American Council of Governmental Industrial Hygienists (ACGIH). 2009. Threshold Limit
Values for Chemical Substances and Physical Agents, Biological Exposure Indices.
Cincinnati, ACGIH.
Bellingham Herald. 2009. Bellingham Explosion Led to Stronger Pipeline Regulation.
Available at http://www.bellinghamherald.com/news/local/article22200438.html.
Accessed January 8, 2016.
City of Bellevue. 2015. City of Bellevue Comprehensive Plan. Updated August 2015.
City of Kirkland. 2015. City of Kirkland 2015 Comprehensive Plan Update & Totem Lake
Planned Action – Draft Environmental Impact Statement.
City of Newcastle. 2015. Draft Update to the City of Newcastle Comprehensive Plan. Sent to
City Council January 20, 2015.
City of Redmond. 2015. 2030 City of Redmond Comprehensive Plan. Amended May 30,
2015.
City of Renton. 2015. City of Renton Comprehensive Plan.
Ecology (Washington Department of Ecology). 2014. Washington State’s Water Quality
Assessment and 303(d) List Website. Available at
http://www.ecy.wa.gov/programs/Wq/303d/currentassessmt.html. Accessed August
2015.
Enertech Consulting. 2016. Technical Memo on Power-Frequency Electric and Magnetic
Fields Related to the Puget Sound Energy Energize Eastside Project.
ENA (Energy Networks Association). 2009. Comments on the Corona–Ion Hypothesis.
Revised November 2009. Available at
http://www.emfs.info/sources/underground/EMS.info. Accessed August 17, 2015.
EPA (U.S. Environmental Protection Agency). 2005. Guidelines for Carcinogen Risk
Assessment. EPA/630/P-03/001F, 166. Available at
http://www.epa.gov/cancerguidelines,
http://oaspub.epa.gov/eims/eimscomm.getfile?p_download_id=439797.
EPRI (Electric Power Research Institute). 2012. EMF and Your Health. January 2012.
Health Council of the Netherlands. 2008. High-voltage power lines. The Hague: Health
Council of the Netherlands. 2008/04E, pages 1-7. Available at
http://www.gezondheidsraad.nl/en/publications/high-voltage-power-lines-0.
January 2016 CHAPTER 17 REFERENCES 17-9
PHASE 1 DRAFT EIS
HPA (Health Protection Agency). 2013. Advisory Group on Non-ionising Radiation
(AGNIR): Power Frequency Electromagnetic Fields. Public Health England. Available
at
http://www.hpa.org.uk/Topics/Radiation/RadiationAdvisoryGroups/AdvisoryGroupOn
NonIonisingRadiation/. Accessed January 14, 2014.
IARC (International Agency for Research on Cancer). 2006. IARC Monographs on the
Evaluation of Carcinogenic Risks to Humans: Preamble (amended January 2006).
Lyon, France: World Health Organization, International Agency for Research on
Cancer. Available at http://monographs.iarc.fr/ENG/Preamble/CurrentPreamble.pdf.
ICNIRP (International Commission on Non-ionizing Radiation Protection). 2010. Guidelines
for Limiting Exposure to Time-varying Electric and Magnetic Fields (1 Hz to 100
kHz). Health Phys 99(6):818-836. Available at
http://www.icnirp.de/documents/LFgdl.pdf.
King County. 2013. King County Comprehensive Plan 2012 (2013 Update).
Mass, C. 2016. Cliff Mass WeatherBlog. Available at
http://cliffmass.blogspot.com/2013/07/why-few-big-thunderstorms-in-northwest.html.
Accessed January 12, 2016.
MSDSonline Search. Available at https://msdsmanagement.msdsonline.com/. Accessed
September 27, 2015.
NESC (National Electric Safety Code). 2012. Published by Institute of Electrical and
Electronics Engineers. Available at http://standards.ieee.org/findstds/standard/C2-
2012.html.
NIEHS (National Institute of Environmental Health Sciences). 1998. Assessment of Health
Effects from Exposure to Power-line Frequency Electric and Magnetic Fields. Portier,
C. J. and Wolfe, M. S. (eds.). Research Triangle Park, NC.
NIEHS (National Institute of Environmental Health Sciences) and NIH (National Institutes of
Health). 2002. Electric and Magnetic Fields Associated with the Use of Electric Power,
Questions and Answers. Sponsored by the NIEHS/Department of Energy Electric and
Magnetic Fields (EMF) Research and Public Information Dissemination (RAPID)
Program. Available at
http://www.niehs.nih.gov/health/assets/docs_p_z/results_of_emf_research_emf_questio
ns_answers_booklet.pdf. Accessed July 11, 2013.
Pipeline Safety Trust. 2016. Available at http://whatcomcreek.pstrust.org/federalsafety.htm.
Accessed January 8, 2016.
Power Engineers. 2015. Eastside 230 kV Project, Lake Washington Submarine Cable
Alternative Feasibility Study – Final, Power Engineers. June 8, 2015.
CHAPTER 17 January 2016 17-10 REFERENCES
PHASE 1 DRAFT EIS
SCENIHR (Scientific Committee on Emerging and Newly Identified Health Risks). 2009.
Health Effects of Exposure to EMF. Available at
http://ec.europa.eu/health/ph_risk/committees/04_scenihr/docs/scenihr_o_022.pdf.
Severson R.K., R.G. Stevens, W.T. Kaune, D.B. Thomas, L. Heuser, S. Davis, and L.E.
Sever. 1988. Acute Nonlymphocytic Leukemia and Residential Exposure to Power
Frequency Magnetic Fields. American Journal of Epidemiology 128(1):10-20.
Sheppard, A.R. 2015. Memorandum to ESA from Dr. Asher Sheppard, PhD concerning
updating prior reports on powerline health effects issues. November 25, 2015..
Silva, J.M., N. Hummon, D. Rutter, and C. Hooper. 1998. Power Frequency Magnetic Fields
in the Home. Piscataway, NJ: Institute of Electrical and Electronics Engineers.
Strauch, Bradley. 2015. Personal communication. Email from Bradley Strauch, Senior Land
Planner/Environmental Scientist (Puget Sound Energy) to Mark S. Johnson (ESA).
October 29, 2015 at 8:25 AM.
Strauch, Bradley. 2016. Personal communication. Email from Bradley Strauch, Senior Land
Planner/Environmental Scientist (Puget Sound Energy) to Reema Shakra (ESA).
January 6, 2016 at 11:19 PM with attachment.
UTC (Washington Utilities and Transportation Commission). 2012. State Investigators Find
Downed Power Line Caused North Seattle Home Explosion in 2011. December 26,
2012. Available at
http://www.utc.wa.gov/aboutUs/Lists/News/DispForm.aspx?ID=174. Accessed
October 30, 2015.
UTC (Washington Utilities and Transportation Commission). 2015. Pipeline Safety Section
Natural Gas Leak History. UTC website. Available at
http://www.wutc.wa.gov/webimage.nsf/0/2124646a14c305b7882567c10062b0bd?Ope
nDocument. Accessed August 17, 2015.
UTC (Washington Utilities and Transportation Commission). 2016. About Pipeline Safety.
Available at
http://www.utc.wa.gov/publicSafety/pipelineSafety/Pages/aboutPipelineSafety.aspx.
Accessed January 12, 2016.
Wertheimer, N., and E. Leeper. 1979. Electrical Wiring Configurations and Childhood
Cancer. American Journal of Epidemiology 109:273-284.
West, Kim. 2015. Personal communication. Project Engineer / Operating Agent for Olympic
Pipeline Co., OPLC. Interview regarding information on Olympic Pipeline segment
through study area and OPLC operations and maintenance procedures, July 27, 2015.
Zaffanella, L. 1993. Survey of Residential Magnetic Field Sources. Volume 1: Goals, Results
and Conclusions, Final Report. TR-102759-V1. Palo Alto, CA: EPRI.
January 2016 CHAPTER 17 REFERENCES 17-11
PHASE 1 DRAFT EIS
CHAPTER 9 NOISE
Caltrans. 2013. Technical Noise Supplement to the Traffic Noise Analysis Protocol,
September 2013.
ENC (Environmental Noise Control). 2014. Product Specification Sheet, ENC STC-32
Sound Control Panel System, 2014.
FHWA (Federal Highway Administration). 2006. Roadway Construction Noise Model User
Guide.
HUD (U.S. Department of Housing and Urban Development). 1985. The Noise Guidebook.
Available at
http://portal.hud.gov/hudportal/HUD?src=/program_offices/comm_planning/environme
nt/training/guidebooks/noise; divided into chapters with Chapter 1 at
http://portal.hud.gov/hudportal/documents/huddoc?id=DOC_16414.pdf. Accessed
October 1, 2015.
INC (Industrial Noise Control). 2014. Product Specification Sheet, INC Portable Noise
Screen, 2014.
King County. 2015. King County Code, Section 12.86.520. Available online at:
http://www.kingcounty.gov/council/legislation/kc_code/15_Title_12.aspx. Accessed
December 28, 2015.
King County. 2013. King County Comprehensive Plan 2012 (2013 Update).
King County Department of Natural Resources and Parks. 2012. Noise Technical
Memorandum, Factoria Recycling and Transfer Station Replacement Project. Prepared
by HDR Engineering, Seattle, WA.
Oregon DOE (Department of Energy). 2013. Site Certificate Application for Troutdale
Energy Center, Exhibit AA, March, 2013.
Siemens AG. 2005. Specification Brochure for SGT-500 Industrial Gas Turbine.
Sound Transit. 2011. East Link Project Draft Environmental Impact Statement.
U.S. DOE (Department of Energy). 2006. Bonneville Power Administration, Transmission
Business Line Policy T2006-1, Audible Noise Policy, 2006.
CHAPTER 10 LAND AND USE AND HOUSING
Chalmers, J. 2012. High-Voltage Transmission Lines and Rural, Western Real Estate Values.
The Appraisal Journal, Winter 2012.
CHAPTER 17 January 2016 17-12 REFERENCES
PHASE 1 DRAFT EIS
City of Bellevue. 2015a. Bellevue Comprehensive Plan Land Use GIS Data. Acquired on
July 20, 2015.
City of Bellevue. 2015b. City of Bellevue website. East Bellevue Community Council
Available at http://www.ci.bellevue.wa.us/EBCC_Homepage.htm. Accessed August
25, 2015.
City of Issaquah. 2015. Issaquah Comprehensive Plan Land Use GIS Data. Acquired August
5, 2015.
City of Kirkland. 2015a. Kirkland Boards and Commissions – Houghton Community
Council. Available at
http://www.kirklandwa.gov/depart/Boards_and_Commissions.htm. Accessed
December 31, 2015.
City of Kirkland. 2015b. Kirkland Comprehensive Plan Land Use GIS Data. Acquired July
17, 2015.
City of Newcastle. 2015. Newcastle Comprehensive Plan Land Use GIS Data. Acquired
August 3, 2015.
City of Redmond. 2015. Redmond Comprehensive Plan Land Use GIS Data. Acquired
September 25, 2015.
City of Renton. 2015. Renton Comprehensive Plan Land Use GIS Data. Acquired August 18,
2015.
City of Sammamish. 2015. Sammamish Comprehensive Plan Land Use GIS Data. Acquired
September 23, 2015.
Ecology (Washington Department of Ecology). 2015a. SMA_Jurisdiction_Lakes shapefile.
Updated September 2015.
Ecology (Washington Department of Ecology). 2015b. SMA_Jurisdiction_Marine shapefile.
Updated September 2015.
Ecology (Washington Department of Ecology). 2015c. SMA_Jurisdiction_Streams shapefile.
Updated September 2015.
FCS Group, 2016. Energize Eastside Phase 1 Draft EIS Economic Considerations Report.
Prepared by FCS Group. January 22, 2016.
King County. 2015. 2012 Assessor Real Property Data and 2015 Parcel Data, updated July
10, 2015.
Mullins, P., et al. 2003. Transmission Lines and Property Values: State of the Science.
Prepared for Electric Power Research Institute, Inc.(EPRI). Technical Report 1005546.
November 2003.
January 2016 CHAPTER 17 REFERENCES 17-13
PHASE 1 DRAFT EIS
MRSC (Municipal Research and Services Center). 2015. Available at
http://mrsc.org/Home/Research-Tools/Washington-City-and-Town-Profiles.aspx.
Accessed October 27, 2015.
PSRC (Puget Sound Regional Council). 2015a. Data/Forecasts. Available at
http://www.psrc.org/data/forecasts. Accessed September 22, 2015.
PSRC (Puget Sound Regional Council). 2015b. Vision 2040. Available at
http://www.psrc.org/growth/vision2040/pub/vision2040-document/. Accessed October
28, 2015.
Roddewig, Richard J. and Charles T. Brigden. 2014. Power Lines and Property Prices. Real
Estate Issues, Vol. 39, No.2.
Strauch, Bradley. 2015. Personal communication. Telephone conversation between Mark S.
Johnson of ESA and Bradley Strauch, Planner, Puget Sound Energy, October 29, 2015.
U.S. Census. 2013. American Community Survey 2009-2013. S2504 Physical Housing.
CHAPTER 11 VIEWS AND VISUAL RESOURCES
AEPOhio. 2014. Encroachments on Transmission Rights of Way. Published by AEPOhio, a
division of American Electric Power. Undated. Available at:
https://www.aepohio.com/global/utilities/lib/docs/info/facts/aepohio-encroachment-
ontransrow.pdf. Accessed August 2015.
Antunes, A., J.P. Soares, N. Mendes, and P. Gomes. 2006. Live Working in Medium Voltage
Overhead Lines – Better Performance Due to a Good Project.
Chalmers, J. 2012. High-Voltage Transmission Lines and Rural, Western Real Estate Values.
The Appraisal Journal, Winter 2012.
City of Bellevue. 2015a. Bellevue Municipal Code (BMC) Current through July 6, 2015
City of Bellevue. 2015b. City of Bellevue Comprehensive Plan. Updated August 2015.
City of Bellevue. 2015c. Phase 1 Draft EIS Scoping Report. July 30, 2015.
City of Clyde Hill. 2015a. City of Clyde Hill 2015-2035 Comprehensive Plan.
City of Clyde Hill. 2015b. Clyde Hill Municipal Code (CHMC) Current through June 9, 2015
City of Issaquah. 2015a. City of Issaquah Comprehensive Plan. Updated June 2015.
City of Issaquah. 2015b. Issaquah Municipal Code (IMC) Current through April 20, 2015
City of Issaquah. 2013. City of Issaquah Shoreline Master Program. February 2013.
CHAPTER 17 January 2016 17-14 REFERENCES
PHASE 1 DRAFT EIS
City of Kirkland. 2015a. City of Kirkland 2015 Comprehensive Plan Update (Kirkland
2035). Updated December 2015.
City of Kirkland. 2015b. Kirkland Municipal Code (KMC) Current through June 16, 2015
City of Medina. 2014. City of Medina Shoreline Master Program.
City of Medina. 2015a. City of Medina Comprehensive Plan 2015 Amendment. Updated
October 2015.
City of Medina. 2015b. Medina Municipal Code (MMC) Current through July 13, 2015
City of Newcastle. 2015a. Draft Update to the City of Newcastle Comprehensive Plan. Sent
to City Council January 20, 2015.
City of Newcastle. 2015b. Newcastle Municipal Code (NMC). Current through May 5, 2015
City of Redmond. 2015a. 2030 City of Redmond Comprehensive Plan. Amended October
2015.
City of Redmond. 2015b. Redmond Zoning Code (RZC). Current through June 16, 2015
City of Renton. 2011. City of Renton, Washington Ordinance No. 5633: Shoreline Master
Program Regulations.
City of Renton. 2015a. City of Renton Comprehensive Plan. Updated July 2015.
City of Renton. 2015b. Renton Municipal Code (RMC). Current through May 18, 2015
City of Sammamish. 2011. City of Sammamish Shoreline Master Program Update.
City of Sammamish. 2015a. City of Sammamish Comprehensive Plan (Draft).
City of Sammamish. 2015b. Sammamish Municipal Code (SMC) Current through March 17,
2015.
Corbin, D. 2007. Covington-Berrydale 230 kV and Berrydale-Krain Corner 115 kV
Transmission Project Update Newsletter. Puget Sound Energy.
Cowger, JR., Steven C. Bottemiller, MAI, and James M. Cahill. 1996. Transmission Line
Impact on Residential Property Values: A Study of Three Pacific Northwest
Metropolitan Areas. Published September/October 1996.
Ecology (Washington Department of Ecology). 2014. Washington State Coastal Atlas.
Shoreline Photos. Available at
http://fortress.wa.gov/ecy/coastalatlas/tools/shorephots.aspx . Accessed December 23,
2015.
January 2016 CHAPTER 17 REFERENCES 17-15
PHASE 1 DRAFT EIS
EPRI (Electric Power Research Institute, Inc.). 2003. Transmission Lines and Property
Values: State of Science. Technical Report 1005546. November 2003.
ETA (Eastern Technical Associates). 2013. Visible Emissions Observer Training Manual.
Published June 2013.FHWA-HEP-15-029. January 2015.
FAA (U.S. Department of Transportation Federal Aviation Administration). 2007.
Obstruction Marking and Lighting. Advisory Circular. Ac 70/7460-1K.Effective
2/1/2007.
FCS Group, 2016. Energize Eastside Phase 1 Draft EIS Economic Considerations Report.
Prepared by FCS Group. January 22, 2016.
FHWA (Federal Highway Administration). 2015. Guidelines for the Visual Impact
Assessment of Highway Projects.
Fortis Wind Energy. 2015. Small Wind Turbines FAQ. Available at
http://www.fortiswindenergy.com/faq. Accessed August 7, 2015.
King County. 2012. 2012 Assessor Real Property Value History Data and 2015 Parcel Data,
updated July 10, 2015.
King County. 2013. King County Comprehensive Plan 2012 (2013 Update).
King County.2015a. Beaver Lake. Available at
http://www.kingcounty.gov/environment/waterandland/lakes/lakes-of-king-
county/beaver.aspx. Accessed July 27, 2015.
King County. 2015b. Pine Lake. Available at
http://green2.kingcounty.gov/SmallLakes/lakepage.aspx?SiteID=31. Accessed July 27,
2015.
King County. 2015c. King County Municipal Code (KCMC) Current through April 15, 2015
Prins, D. 2015. Personal communication.Telephone conversation between Jessica Conquest
of ESA and Deborah Prins, Residential Division Manager, King County Department of
Assessments, August 5, 2015.
Rosiers, F.D. 2002. Power Lines, Visual Encumbrance and House Values: A Microspatial
Approach to Impact Measurement. JRER Vol. 23, No. 3.
Strauch, Bradley. 2015. Personal communication. Email from Bradley Strauch, Senior Land
Planner/Environmental Scientist (Puget Sound Energy) to Mark S. Johnson (ESA).
December 28, 2015 at 11:47 AM.
Sullivan, R. 2013. Impacts of Utility-Scale Solar Energy Development on Visual Resources.
Argonne National Laboratory. Environmental Science Division. Solar Workshop.
February 20-22, 2013.
CHAPTER 17 January 2016 17-16 REFERENCES
PHASE 1 DRAFT EIS
The National Geographic Society. 2015. Mount Rainer National Park. Available at
http://travel.nationalgeographic.com/travel/national-parks/mount-rainier-national-park/.
Accessed July 24, 2015.
Town of Beaux Arts Village. 2013. Beaux Arts Village Municipal Code (BAVC) Current
through April 9, 2013.
Town of Beaux Arts Village. 2014a. Town of Beaux Arts Village Draft 2014 Comprehensive
Plan.
Town of Beaux Arts Village. 2014b. Town of Beaux Arts Village Shoreline Master Program
2014. August 2014.
Town of Hunts Point. 2012. Town of Hunts Point Shoreline Master Program.
Town of Hunts Point. 2014. 2014 Draft Comprehensive Plan Update for the Town of Hunts
Point.
Town of Hunts Point. 2015. Hunts Point Municipal Code (HPMC) Current through April 13,
2015
Town of Yarrow Point. 2012. Town of Yarrow Point Shoreline Master Program.
Town of Yarrow Point. 2014. Yarrow Point Municipal Code (YPMC) Current through June
10, 2014.
Town of Yarrow Point. 2015. Town of Yarrow Point Comprehensive Plan. Updated
September 2015.
WDFW (Washington Department of Fish and Wildlife). 2015. Lake Washington. Available
at http://wdfw.wa.gov/fishing/washington/37/. Accessed July 24, 2015.
CHAPTER 12 RECREATION
City of Bellevue. 2009. Pedestrian and Bicycle Transportation Plan. Available at
http://www.ci.bellevue.wa.us/pedbike-plan-2009.htm. Accessed August 6, 2015.
City of Bellevue. 2010. Parks and Open Space System Plan 2010.
City of Bellevue. 2015. Find Bellevue Parks and Facilities. Available at
http://www.ci.bellevue.wa.us/parks_intro.htm. Accessed August 27, 2015.
City of Clyde Hill. 2015. City of Clyde Hill Comprehensive Plan.
City of Issaquah. 2009. Parks, Recreation, Trails and Open Space Plan. Available at
http://www.ci.issaquah.wa.us/DocumentCenter/View/561. Accessed August 6, 2015.
January 2016 CHAPTER 17 REFERENCES 17-17
PHASE 1 DRAFT EIS
City of Issaquah. 2014. Walk and Roll Issaquah. Available at
http://issaquahwa.gov/index.aspx?nid=1284. Accessed August 6, 2015.
City of Kirkland. 2015. City of Kirkland Parks Recreation and Open Spaces Plan.
City of Medina. 2015a. Medina Parks Long Range Vision and Strategic Planning Document
(no date). Available at
http://www.medina.govoffice.com/vertical/Sites/%7B82D584EB-93EE-48B4-B853-
6CBC215E08A2%7D/uploads/%7B515AC562-02F4-4786-98AC-
7FA6AE250D4D%7D.PDF. Accessed August 27, 2015.
City of Medina. 2015b. City of Medina Comprehensive Plan 2015 Amendment (Draft).
City of Newcastle. 2008. Draft Non-motorized Transportation Plan. Available at
http://www.ci.newcastle.wa.us/planning_division/planning_pdfs/documents/nonmotori
zed.pdf. March.
City of Newcastle. 2013. City of Newcastle Comprehensive Plan, Parks, Trails, and
Recreation Appendix. Available at
http://www.ci.newcastle.wa.us/documents_press_releases/documents/6PTRElement3.1
9.13.pdf.
City of Newcastle. 2015. Parks and Trails. Available at
http://www.ci.newcastle.wa.us/parks/parks_trails.htm. Accessed August 27, 2015.
City of Redmond. 2010. Parks, Arts, Recreation, Culture and Conservation Plan 2010-2016.
Available at http://www.redmond.gov/PlansProjects/Parks/PARCCPlan/Documents/.
Accessed August 6, 2015.
City of Renton. 2009. Renton Trails and Bicycle Master Plan. Available at
http://rentonwa.gov/living/default.aspx?id=26666. Accessed August 6, 2015.
City of Renton. 2011. Parks, Recreation, and Natural Areas Plan.
City of Renton. 2015. Master Park Directory. Available at
http://rentonwa.gov/living/default.aspx?id=2328. Accessed August 27, 2015.
City of Sammamish. 2012. City of Sammamish Parks, Recreation and Open Spaces Plan.
Available at http://www.sammamish.us/departments/parksandrec/OpenSpacePlan.aspx.
Accessed August 6, 2015.
City of Sammamish. 2015. Trail, Bikeway and Paths Master Plan. Available at
http://www.sammamish.us/projects/TrailsPlan.aspx. Accessed August 2015.
DNR (Washington State Department of Natural Resources). 2015. West Tiger Mountain
Natural Resources Conservation Area. Available at http://www.dnr.wa.gov/west-tiger-
mountain-natural-resources-conservation-area. Accessed August 27, 2015.
CHAPTER 17 January 2016 17-18 REFERENCES
PHASE 1 DRAFT EIS
King County. 2010. King County Open Space Plan: Parks, Trails, and Natural Areas.
King County. 2015. King County Parks List. Available:
http://www.kingcounty.gov/recreation/parks/inventory/parks-list.aspx. Last updated:
July 15, 2015. Accessed August 27, 2015.
Sound Transit. 2011. East Link Project Final EIS July 2011.
http://www.soundtransit.org/Projects-and-Plans/East-Link-Extension/East-Link-
Extension-document-archive/East-Link-Documents/East-Link-document-
collections/East-Link-Final-EIS-document-collection. Accessed September 24, 2015.
Strategen. 2015. Eastside System Energy Storage Alternatives Screening Study, March 2015.
Town of Beaux Arts Village. 2014. Town of Beaux Arts Village Draft 2014 Comprehensive
Plan.
Town of Hunts Point. 2014. 2014 Draft Comprehensive Plan Update for the Town of Hunts
Point.
Town of Yarrow Point. 2014. Comprehensive Plan 2014.
Washington State Parks and Recreation Commission. 2013. Strategic Plan 2014-2019:
Moving Towards a Health and Sustainable Washington State Parks System.
Washington State Parks. 2015a. Squak Mountain State Park. Available at
http://www.parks.wa.gov/588/Squak-Mountain. Accessed August 27, 2015.
Washington State Parks. 2015b. Lake Sammamish State Park. Available at
http://parks.state.wa.us/533/Lake-Sammamish. Accessed August 27, 2015.
Washington State Parks. 2015c. Bridle Trails State Park. Available at
http://www.parks.wa.gov/481/Bridle-Trails. Accessed August 27, 2015.
CHAPTER 13 HISTORIC AND CULTURAL RESOURCES
Ames, K.M. and H.D.G. Maschner. 1999. Peoples of the Northwest Coast: Their
Archaeology and Prehistory. London: Thames and Hudson Ltd.
Blukis Onat, A.R., M.E. Morgenstein, P.D. LeTourneau, R.P. Stone, J. Kosta, and P.
Johnson. 2001. Archaeological Investigations at Stuwe’yuq – Site 45KI464, Tolt River,
King County, Washington. On file, Washington State Department of Archaeology and
Historic Preservation (DAHP), Olympia, WA.
Bryant, A. (ed.). 2000. A Hidden Past: An Exploration of Eastside History. The Seattle
Times. Seattle, WA.
January 2016 CHAPTER 17 REFERENCES 17-19
PHASE 1 DRAFT EIS
DAHP (Department of Archaeology and Historic Preservation). 2015. Washington
Information System for Architectural and Archaeological Records Data (WISAARD).
Available at http://www.dahp.wa.gov/. Accessed July 2015.
DAHP (Department of Archaeology and Historic Preservation). 2010. Statewide Predictive
Model. Available at http://www.dahp.wa.gov/. Last updated: 2010. Accessed July 31,
2015.
Eastside Heritage Center. 2006. Lake Washington: The East Side. Images of America Series.
Charleston, SC: Arcadia Publishing.
Fish, E.R. (ed.). 1981. The Past at Present in Issaquah, Washington. 4th Edition. Port
Angeles, WA: Pen Print, Inc. Originally published 1961, Kingsport Press. Kingsport,
TN.
Gellatly, J. 1977. Mercer Island: The First 100 Years. Mercer Island, WA: Mercer Island
Bicentennial Committee.
Haeberlin, H. and E. Gunther. 1930. The Indians of Puget Sound. University of Washington
Publications in Anthropology Vol. 4, No. 1. Seattle, WA: University of Washington
Press.
Hardy, N. (ed.). 2006. Redmond Reflections, From Settlers to Software. Redmond, WA:
Redmond Historical Society.
Hilbert, V., J. Miller, and Z. Zahir. 2001. Puget Sound Geography: Original Manuscript from
T. T. Waterman. Federal Way, WA: Lushootseed Press.
Kauhi, T.C. 2013. Statewide Predictive Model. Prepared for the Department of Archaeology
and Historic Preservation (DAHP). Prepared by GeoEngineers, Tacoma, Washington.
On File at DAHP at: http://www.dahp.wa.gov/. Accessed November 25, 2014.
Kidd, R.S. 1964. A Synthesis of Western Washington Prehistory for the Perspective of Three
Occupation Sites. Unpublished Master’s Thesis, Department of Anthropology,
University of Washington. Seattle, WA.
King County Historic Preservation Program. 2015a. King County Landmark Designation
Criteria. Available at
http://www.kingcounty.gov/~/media/property/historic_preservation/documents/resourc
es/T05_LandmarkDesignationCriteria.ashx?la=en, Last updated: February 2014.
Accessed August 20, 2015.
King County Historic Preservation Program. 2015b. King County and City Landmarks List.
Available at
http://www.kingcounty.gov/~/media/property/historic_preservation/documents/resourc
es/T06_KCLandmarkList.ashx?la=en. Last updated: July 14, 2015. Accessed July 23,
2015.
CHAPTER 17 January 2016 17-20 REFERENCES
PHASE 1 DRAFT EIS
Matson, R.G. and G. Coupland. 1995. The Prehistory of the Northwest Coast. San Diego,
CA: Academic Press.
McDonald, L. 2000. Bellevue: Its First 100 Years. Bellevue, WA: Bellevue Historical
Society.
Miller, J. 2014. Elders Dialog: Ed Davis and Vi Hilbert Discuss Native Puget Sound
Language, Culture, and Heritage. Federal Way, WA: Lushootseed Press.
Myers, John H. 1981. The Repair of Historic Wooden Windows. National Park Service
Technical Preservation Brief No. 9. Available at http://www.nps.gov/tps/how-to-
preserve/briefs/9-wooden-windows.htm. Accessed August 7, 2015.
Nelson, C.M. 1990. Prehistory of the Puget Sound Region in Northwest Coast. Pages 481-
484 in Handbook of North American Indians, Vol. 7, Wayne Suttles (ed.). Washington,
D.C.: Smithsonian Institution Press.
Smith, M.W. 1940. The Puyallup-Nisqually. Columbia University Contributions to
Anthropology No. 32. New York: Columbia University Press.
Spier, L. 1936. Tribal Distribution in Washington. General Series in Anthropology No. 3.
Menasha, WI: George Banta Publishing Company.
Suttles, W. and B. Lane. 1990. Southern Coast Salish. Pages 458-502 in Handbook of North
American Indians, Vol. 7, Wayne Suttles (ed.). Washington, D.C.: Smithsonian
Institution Press.
Swanton, J.R. 1979. Indian Tribes of Washington, Oregon, and Idaho. Reprint of the 1952
edition published by the Government Printing Office, Washington, issued as Bulletin
145 of the Bureau of American Ethnology, Smithsonian Institution. Fairfield, WA: Ye
Galleon Press.
Thrush, C.P. 2007. Native Seattle: Histories from the Crossing-Over Place. Seattle, WA:
University of Washington Press.
U.S. Coast and Geodetic Survey. 1902a. East Shore of Lake Washington, Juanita Bay to
Meydenbauer Bay, Washington. Register No. 2607.
U.S. Coast and Geodetic Survey. 1902b. East Shore of Lake Washington, Meydenbauer Bay
to May Creek, Washington. Register No. 2608.
U.S. Coast and Geodetic Survey. 1902c. Lake Washington, Southern Sheet, Washington.
Register No. 2609.
USGS (U.S. Geological Survey). 1895. Snohomish, WA, 30’ Series Quadrangle. U.S.
Geological Survey. Reston, VA.
January 2016 CHAPTER 17 REFERENCES 17-21
PHASE 1 DRAFT EIS
USGS (U.S. Geological Survey). 1897a. Snohomish, WA, 30’ Series Quadrangle. U.S.
Geological Survey. Reston, VA.
USGS (U.S. Geological Survey). 1897b. Tacoma, WA, 30’ Series Quadrangle. U.S.
Geological Survey. Reston, VA.
USGS (U.S. Geological Survey). 1898. Tacoma, WA, 30’ Series Quadrangle. U.S.
Geological Survey. Reston, VA.
USGS (U.S. Geological Survey). 1900. Tacoma, WA, 30’ Series Quadrangle. U.S.
Geological Survey. Reston, VA.
U.S. Surveyor General. 1864a. Township 24 North, Range 5 East Survey Map. Available at
http://www.blm.gov/or/landrecords/survey/yPlatView1_2.php?path=PWA&name=t240
n050e_001.jpg. Accessed July 29, 2015.
U.S. Surveyor General. 1864b. Township 24 North, Range 6 East Survey Map. Available at
http://www.blm.gov/or/landrecords/survey/yPlatView1_2.php?path=PWA&name=t240
n060e_001.jpg. Accessed July 29, 2015.
U.S. Surveyor General. 1864c. Township 23 North, Range 5 East Survey Map. Available at
http://www.blm.gov/or/landrecords/survey/yPlatView1_2.php?path=PWA&name=t230
n050e_001.jpg. Accessed July 29, 2015.
U.S. Surveyor General. 1870. Township 25 North, Range 5 East Survey Map. Available at
http://www.blm.gov/or/landrecords/survey/yPlatView1_2.php?path=PWA&name=t250
n050e_001.jpg. Accessed July 29, 2015.
U.S. Surveyor General. 1872. Township 23 North, Range 6 East Survey Map. Available at
http://www.blm.gov/or/landrecords/survey/yPlatView1_2.php?path=PWA&name=t230
n060e_001.jpg. Accessed July 29, 2015.
U.S. Surveyor General. 1874. Township 25 North, Range 6 East Survey Map. Available at
http://www.blm.gov/or/landrecords/survey/yPlatView1_2.php?path=PWA&name=t250
n060e_001.jpg. Accessed July 29, 2015.
Waterman, T.T. 1922. The Geographical Names Used by the Indians of the Pacific Coast.
Geographical Review 12(2): 175-194.
Way, N. 1989. Our Town Redmond. Redmond, WA: Marymoor Museum.
CHAPTER 14 TRANSPORTATION
Community Transit. 2015. Schedules and Maps. Available at
http://www.communitytransit.org/. Updated June 7, 2015. Accessed August 2015.
FHWA (Federal Highway Administration). 2009. Manual on Uniform Traffic Control
Devices for Streets and Highways. 23 CFR Part 655m Subpart F. December.
CHAPTER 17 January 2016 17-22 REFERENCES
PHASE 1 DRAFT EIS
FHWA (Federal Highway Administration). 2013. Highway Functional Classification
Concepts, Criteria and Procedures. Available at
http://www.fhwa.dot.gov/planning/processes/statewide/related/highway_functional_cla
ssifications/section00.cfm. Updated October 7, 2013. Accessed August 2015.
King County. 2015. Eastside Rail Corridor Regional Advisory Committee. Available at
http://www.kingcounty.gov/operations/erc-advisory-council.aspx. Updated May 20,
2015. Accessed August 2015.
King County Metro. 2015. Schedules and Maps. Available at http://metro.kingcounty.gov/.
Updated June 6, 2015. Accessed August 2015.
Sound Transit. 2015a. Schedules and Maps. Available at http://www.soundtransit.org/
Updated June 7, 2015. Accessed August 2015.
Sound Transit. 2015b. East Link Extension. Available at
http://www.soundtransit.org/Projects-and-Plans/East-Link-Extension. Accessed August
2015.
WSDOT (Washington State Department of Transportation). 2013. Guidelines for Amending
Functional Classification in Washington State. October 2013.
WSDOT (Washington State Department of Transportation). 2014. Work Zone Traffic
Control Guidelines. Publication No. M 54-44. December 2014.
WSDOT (Washington State Department of Transportation). 2015a. 2014 Annual Traffic
Report.
WSDOT (Washington State Department of Transportation). 2015b. SR 520 Bridge
Replacement and HOV Program. Available at
http://www.wsdot.wa.gov/Projects/SR520Bridge/. Accessed August 2015.
CHAPTER 15 PUBLIC SERVICES
Anderson, Steve. 2015. Personal communication. Phone conversation between Steve
Anderson, Fire Department Hazardous Materials Technician (Redmond, WA) and
Jennifer Hagenow (ESA). October 28, 2015.
Bellevue Fire Department. 2015. Bellevue Fire Department website – Fire Department
General Information. Available at
http://www.bellevuewa.gov/fire_department_intro.htm. Accessed August 25, 2015.
Bellevue Police Department. 2015. Bellevue Police Department website – Available at
https://www.bellevuewa.gov/police-about.htm. Accessed August 31, 2015.
Bunting, Mark. 2015. Personal communication. Phone conversation between Mark Bunting,
Captain of Fire Department (Kirkland, WA) and Jennifer Hagenow (ESA). July 21,
2015.
January 2016 CHAPTER 17 REFERENCES 17-23
PHASE 1 DRAFT EIS
City of Bellevue. 2014. Bellevue Fire Department Facilities Master Plan. May.
City of Bellevue. 2015. City of Bellevue Comprehensive Plan. Planning Commission
Recommendation. March 2015.
City of Redmond. 2000. Redmond Fire Department Olympic Pipeline Response Plan. May.
Amended June 2000.
City of Redmond. 2011. Redmond 2030 - City of Redmond Comprehensive Plan. Amended
June 2014.
City of Renton. 2015. City of Renton Comprehensive Plan. Renton, WA. Adopted June 22,
2015.
City of Sammamish. 2015. Sammamish Comprehensive Plan 2035.
Clyde Hill Police Department. 2015. Clyde Hill Police Department website. Available at
http://www.clydehill.org/Departments/Police/. Accessed August 31, 2015.
Depuru, S., L. Wang, and V Devabhaktuni. 2011. Electricity Theft: Overview, Issues,
Prevention and a Smart Meter Based Approach to Control Theft. Energy Policy,
Elsevier.
Eastside Fire and Rescue. 2013. 2013 Eastside Fire and Rescue Response Coverage Report.
Available at https://www.sammamish.us/files/document/13137.pdf. Accessed
December 29, 2015.
Eastside Fire and Rescue. 2015. Eastside Fire and Rescue website. Available at
http://www.eastsidefire-rescue.org/. Accessed August 24, 2015.
Enertech. 2015. Technical Memo on Power-Frequency Electric and Magnetic Fields Related
to the Puget Sound Energy Energize Eastside Project. December 29, 2015.
EPRI (Electric Power Research Institute). 1982. Transmission Line Reference Book: 345 kV
and Above - Second Edition.
FCC (Federal Communications Commission). 1988. Rules and Regulations, Volume II, Part
15, 47 CFR, Chapter 1, October 10, 1988.
FCS Group, 2016. Energize Eastside Phase 1 Draft EIS Economic Considerations Report.
Prepared by FCS Group. January 22, 2016.
Farman, Brian. 2015. Personal communication. Phone conversation with Brian Farman,
Police Officer (Kirkland, WA) and Jennifer Hagenow (ESA). July 21, 2015.
IEEE (Institute of Electrical and Electronics Engineers). 1971. Radio Noise Design Guide for
High-Voltage Transmission Lines, IEEE Transactions on Power Apparatus and
Systems, Vol. PAS-90, No. 2, pp 833-842, March/April, 1971.
CHAPTER 17 January 2016 17-24 REFERENCES
PHASE 1 DRAFT EIS
Irvine, Melinda. 2015. Personal communication. Phone conversation with Melinda Irvine,
Chief of Police Services (Newcastle, WA) and Jennifer Hagenow. July 21, 2015.
Issaquah Police Department. 2015. Issaquah Police Department website – Available at
http://www.ci.issaquah.wa.us/index.aspx?NID=306. Accessed August 31, 2015.
King County. 2013. King County Comprehensive Plan 2012 (2013 Update).
King County Medic One. 2015. King County Medic One website. Available at
http://www.kingcounty.gov/healthservices/health/ems/MedicOne.aspx. Accessed
December 28, 2015.
King County Sheriff’s Office. 2015. King County Sheriff’s Office website. Available at
http://www.kingcounty.gov/safety/sheriff/Patrol%20Precincts.aspx. Accessed
December 28, 2015.
Kirkland Fire Department. 2015. Kirkland Fire Department website. Available at
http://www.kirklandwa.gov/depart/Fire_Services.htm. Accessed August 24, 2015.
Kirkland Police Department. 2015. Kirkland Police Department website. Available at
http://www.kirklandwa.gov/depart/PD/About.htm. Accessed August 31, 2015.
Kooi, B.R. 2010. Problem-Oriented Guides for Police, Problem Specific Guides Series No.
58 – Theft of Scrap Metal.
Medina Police Department. 2015. Medina Police Department website. Available at
http://www.medina-wa.gov/index.asp?SEC=4972CDC7-2456-4C31-946B-
599F7745BCDE&Type=B_BASIC. Accessed August 31, 2015.
Moulton, Mark. 2015a. Personal communication. Phone conversation between Mark
Moulton, Deputy Chief of Operations (Bellevue, WA) and Jennifer Hagenow (ESA).
July 22, 2015.
Moulton, Mark. 2015b. Personal communication. Phone conversation between Mark
Moulton, Deputy Chief of Operations (Bellevue, WA) and Jennifer Hagenow (ESA).
October 16, 2015.
Orth, Joseph, PE MSEE. 2014. Personal communication. Phone converstation between
Joseph Orth, Principal Electrical Engineer & Technical Lead for Seattle City Light
Denny Substation Project and Mark S. Johnson (ESA). November 14, 2014.
Parks, Cyndie. 2015. Personal communication. Email from Cyndie Parks, Crime Investigator
(Renton, WA) to Jennifer Hagenow (ESA). July 28, 2015.
Public Stuff. 2015. Crime mapping within study area. Available at
https://www.publicstuff.com. Last updated 2015. Accessed July 22, 2015.
January 2016 CHAPTER 17 REFERENCES 17-25
PHASE 1 DRAFT EIS
Redmond Fire Department. 2015. Redmond Fire Department website. Available at
https://www.redmond.gov/PublicSafety/FireMainPage. Accessed August 24, 2015.
Redmond Police Department. 2015. Redmond Police Department website. Available at
http://www.redmond.gov/cms/one.aspx?objectId=1183. Accessed August 31, 2015.
Renton Fire and Emergency Services Department. 2015. Renton Fire and Emergency
Services Department website. Available at http://rentonwa.gov/fire/. Accessed August
24, 2015.
Renton Police Department. 2015. Renton Police Department website. Available at
https://rentonwa.gov/government/default.aspx?id=1688. Accessed August 31, 2015.
Strauch, Bradley. 2016. Personal communication. Email from Bradley Strauch, Senior Land
Planner/Environmental Scientist (Puget Sound Energy) to Reema Shakra (ESA).
January 6, 2016 at 11:19 PM with attachment.
Town of Beaux Arts Village. 2004. Village of Beaux Arts Comprehensive Plan.
Trader, Holly. 2015. Personal communication. Email from Holly Trader, Community
Programs Coordinator (Renton, WA) to Jennifer Hagenow (ESA). July 28, 2015.
Tryon, Greg. 2015. Personal communication. Phone conversation between Greg Tyron,
Deputy Chief (Eastside Fire and Rescue, WA) and Jennifer Hagenow (ESA). August
21, 2015.
Turner, Scott. 2015. Personal communication. Phone conversation between Scott Turner,
Assistant Fire Marshall (Newcastle, WA) and Jennifer Hagenow (ESA). July 21, 2015.
U.S. DOE (U.S. Department of Energy), Bonneville Power Administration. May 1980. A
Practical Handbook for the Correction of Radio Interference from Overhead Powerlines
and Facilities. Portland, OR. 1980.
Walgren, Eric. 2015. Personal communication. Phone conversation between Eric Walgren,
Deputy Chief of Response (Renton, WA) and Jennifer Hagenow (ESA). July 22, 2015.
CHAPTER 16 UTILITIES
Baker. 2008. Pipeline Corrosion – Final Report. Prepared by Michael Baker, Jr., Inc. (Baker)
for Pipeline and Hazardous Materials Safety Administration. November 2008.
B.P. Pipelines North America. 2014. Olympic Pipeline information. Available at
http://www.olympicpipeline.com/. Last updated 2014. Accessed June-August 2015.
City of Bellevue. 2005. Ordinance 5603 (Franchise with Olympic Pipe Line Company). May
7, 2005.
CHAPTER 17 January 2016 17-26 REFERENCES
PHASE 1 DRAFT EIS
City of Bellevue. 2015. City of Bellevue Comprehensive Plan – Utilities Chapter; Planning
Commission Recommendation. March 2015.
City of Clyde Hill. 2014. City of Clyde Hill Comprehensive Plan, Utilities Chapter.
City of Clyde Hill. 2015. Stormwater Management website. Available at
http://www.clydehill.org/departments/public-works/stormwater-management/.
Accessed December 31, 2015.
City of Issaquah. 2015. City of Issaquah Comprehensive Plan, Utilities and Public Services
Chapter. Adopted 1995, Ordinance 2741 Approved June 2015.
City of Kirkland. 2011. Ordinance 4298 (Franchise with Olympic Pipe Line Company). June
1, 2011.
City of Kirkland. 2013. City of Kirkland Comprehensive Plan, Utilities Chapter. Adopted
1993, Ordinance 4428 Approved, December 2013.
City of Medina. 2015. City of Medina Comprehensive Plan, Utilities Chapter. City of Medina
Planning Commission, Medina, WA. Adopted May 1994, Amendment (Draft).
City of Newcastle. 2008. City of Newcastle, Washington. Order No. 2008-0388 (Franchise
with Olympic Pipe Line Company). July 2008.
City of Newcastle. 2015. Draft Update to the City of Newcastle Comprehensive Plan. Sent to
City Council January 20, 2015.
City of Redmond. 2015. Redmond 2030: City of Redmond Comprehensive Plan. Amended
May 30, 2015.
City of Redmond. 2006. Ordinance No. 2289 (Franchise with Olympic Pipe Line Company).
City of Renton. 2006. Ordinance No. 06-1002 (Franchise with Olympic Pipe Line Company).
City of Renton. 2015. City of Renton Comprehensive Plan. Adopted June 22, 2015.
City of Sammamish. 2015. City of Sammamish Comprehensive Plan (Draft).
City of Seattle. 1996. Seattle City Light Department Policy & Procedures, Real Property Use
Permits, Leases, Consents, and Easements. DPP 500p III-132. September 11, 1996.
City of Seattle. 2014. City of Seattle Adopted 2014-2019 Capital Improvement Program.
City of Seattle. 2015. 2015-2020 Capital Improvement Program. Available
at http://www.seattle.gov/financedepartment/1520proposedcip/. Accessed January 5,
2016.
January 2016 CHAPTER 17 REFERENCES 17-27
PHASE 1 DRAFT EIS
CWA (Cascade Water Alliance). 2012. Cascade Water Alliance Transmission and Supply
Plan. Prepared by HDR in association with CDM. July 2012. Available at
http://cascadewater.org/supply_plans_2012.php. Accessed August 11, 2015.
CWA (Cascade Water Alliance). 2015. Cascade Water Alliance - Members. Available at
http://cascadewater.org/about_members.php. Accessed July 27, 2015.
EFSEC (Energy Facility Site Evaluation Council). 1998. Cross Cascade Pipeline. Application
96-1. Revised May 1, 1998.
King County. 2013. King County Comprehensive Plan 2012 (2013 Update).
King County WTD (King County Department of Natural Resources and Parks Wastewater
Treatment Division). 2014. 2014 Ratepayer Report. April 2014.
Marrinan, Timothy. 2015. Personal communication. Phone conversation between Timothy
Marrinan, Engineer / Project Manager (Stantec) and Karmen Martin (ESA). July 28,
2015.
NACE (National Association of Corrosion Engineers). 2007. Standard Practice. Control of
External Corrosion on Underground and Submerged Metallic Piping Systems. NACE
SP0169-2007 Item No. 21173. Reaffirmed March 15, 2007.
Power Engineers. 2014. Eastside 230 kV Project – Underground Feasibility Study. Prepared
for PSE. March 2014.
Power Engineers. 2015. Eastside 230 kV Project Lake Washington Submarine Cable
Alternative Feasibility Study – Final. Prepared for PSE. June 8, 2015.
PSE (Puget Sound Energy). 2013a. Puget Sound Energy 2013 Integrated Resource Plan.
Available at http://pse.com/aboutpse/EnergySupply/Pages/Resource-Planning.aspx.
Accessed August 11, 2015.
PSE (Puget Sound Energy). 2013b. Puget Sound Energy 2013 Integrated Resource Plan,
Appendix E Regional Transmission Resources. Available at
http://pse.com/aboutpse/EnergySupply/Pages/Resource-Planning.aspx. Accessed
August 11, 2015.
PSE (Puget Sound Energy). 2015a. Puget Sound Energy – Natural Gas Reliability. Available
at http://www.pse.com/aboutpse/SystemReliability/Pages/Gas-Reliability.aspx.
Accessed October 31, 2015.
PSE (Puget Sound Energy). 2015b. Puget Sound Energy Service Area Map. August 2015.
Quanta Technology. 2014. Eastside Transmission Solutions Report – King County Area.
Redacted Version. October 2013, updated February 2014.
CHAPTER 17 January 2016 17-28 REFERENCES
PHASE 1 DRAFT EIS
SCL (Seattle City Light). 2015. Seattle City Light Service Area Map website. Available at
http://www.seattle.gov/light/electricservice/map.asp. Accessed August 31, 2015.
SCL (Seattle City Light). 2008. Seattle City Light 2008 Integrated Resource Plan, Chapter 2
Existing Resources.
SPU (Seattle Public Utilities). 2013 Water System Plan. July 2012.
SPU (Seattle Public Utilities). 2015. Seattle Public Utilities ‘About the Water System’
website. Available at
http://www.seattle.gov/util/MyServices/Water/AbouttheWaterSystem/index.htm.
Accessed December 31, 2015.
Smart, III, John S., Dirk L. Van Oostendorp, and W. A. Wood. 1999. Induced AC Creates
Problems for Pipelines in Utility Corridors. Pipeline and Gas Industry, June 1999.
Strauch, Bradley. 2016. Personal communication. Email from Bradley Strauch, Senior Land
Planner/Environmental Scientist (Puget Sound Energy) to Reema Shakra (ESA).
January 6, 2016 at 11:19 PM with attachment.
Town of Beaux Arts Village. 2014. Town of Beaux Arts Village Draft 2014 Comprehensive
Plan.
Town of Hunts Point. 2014. 2014 Draft Comprehensive Plan Update for the Town of Hunts
Point.
Town of Yarrow Point. 2014. Town of Yarrow Point Comprehensive Plan 2014.
UTC (Washington Utilities and Transportation Commission). 2015. Pipeline Safety Section
Natural Gas Leak History. UTC website. Available at
http://www.wutc.wa.gov/webimage.nsf/0/2124646a14c305b7882567c10062b0bd?Ope
nDocument. Accessed August 17, 2015.
West, Kim. 2015. Personal communication. Phone conversation between Kim West, Project
Engineer / Operating Agent (Olympic Pipe Line Company) and Karmen Martin (ESA).
July 27, 2015.
January 2016 CHAPTER 17 REFERENCES 17-29
PHASE 1 DRAFT EIS
DISTRIBUTION LIST CHAPTER 18.
The following parties have received the Draft EIS by electronic link, compact disc, or printed
copy:
Federal Agencies
Army Corps of Engineers
Environmental Protection Agency
Federal Highway Administration
Postal Service
Tribal Governments
Duwamish Tribe
Muckleshoot Indian Tribe
Snoqualmie Nation
Suquamish Tribe
Tulalip Tribes
Regional
Puget Sound Clean Air Agency
Puget Sound Regional Council
Sound Transit
Washington State
Attorney General’s Office
Department of Agriculture
Department of Archaeology and Historic
Preservation
Department of Commerce
Department of Community Development
Department of Corrections
Department of Ecology SEPA Unit
Department of Fish and Wildlife
Department of Health
Regional Department of Housing and
Urban Development
Department of Natural Resources
Department of Social and Health Services
Department of Transportation
Parks & Recreation Commission
Recreation Conservation Office
Local
Beaux Arts Village
City of Bellevue Fire Department
City of Bothell
City of Clyde Hill
City of Covington
City of Issaquah
City of Kenmore
City of Kent
City of Kirkland
City of Medina
City of Mercer Island
City of Newcastle
City of Redmond
City of Renton
City of Renton Fire Department
City of Sammamish
City of Tukwila
City of Woodinville
January 2016 CHAPTER 18 DISTRIBUTION LIST 18-1
PHASE 1 DRAFT EIS
East Bellevue Community Council
Houghton Community Council
King County Boundary Review Board
King County Department of Permitting &
Environmental Review
King County Department of
Transportation
King County Executive Office
King County Historic Preservation
Program
King County Metro Transit
King County Department of Natural
Resources & Parks
King County Parks and Recreation
Division
King County Wastewater Division
King County Water and Land Resources
Division
King Eastside Community Services Office
Seattle and King County Public Health
Seattle City Light
Seattle Public Utilities
Town of Hunts Point
Town of Yarrow Point
Libraries
Bellevue Library
Fairwood Library
Lake Hills Library
Newcastle Library
Newport Way Library
Redmond Library
Renton Highlands Library
Renton Library
Seattle Public Library
University of Washington, College of
Architecture & Urban Planning Library
Other
Bellevue Chamber of Commerce
Bellevue Downtown Association
Bellevue School District #405
Cascade Water Alliance
Coal Creek Utility District
Comcast
Eastgate Public Health Center
Eastside Audubon Society
Eastlake Washington Audubon Society
Energy Facility Site Evaluation Council
Evergreen Health
Greater Seattle Chamber of Commerce
Issaquah School District
Lake Washington School District #414
Meydenbauer Bay Neighbors Association
Northshore Utility District
Olympic Pipeline Company
Puget Sound Energy
Puget Sound Partnership
Renton Chamber of Commerce
Qwest
West Bellevue Community Club
Woodinville Water District
CHAPTER 18 January 2016 18-2 DISTRIBUTION LIST
PHASE 1 DRAFT EIS
APPENDIX A. PSE CONSERVATION
PROGRAM
Conservation means a reduction in energy demand. Conservation is achieved mainly by
customers implementing voluntary energy efficiency improvements beyond those energy
efficiency measures that are required by regulations.
PSE uses conservation goals as an important factor in developing load forecasts. For the
Eastside, the current conservation goal is to conserve approximately 110 MW of power
beyond the baseline load growth expected through 2024.
Table A-1 below shows the total conservation that PSE expects to achieve systemwide and
for the Eastside. Values are for winter peak load. These loads are modeled on a typical winter
cold spell of 23 degrees Fahrenheit. Values are shown for the entire PSE system and for the
Eastside. “System Peak Net of 100% Conservation” means the peak load that would occur
during a cold weather event, assuming PSE has attained its annual target for conservation
measures. “System Peak 100% Conservation 2014” refers to the cumulative amount of
conservation targeted to be attained by a given year, with 2014 as the baseline. Similar values
are provided for the Eastside area.
Table A-1. Energy Conservation Systemwide and for the Eastside through 2024
2014 System
Peak Net of
100%
Conservation
System Peak
100%
Conservation
2014
2014 Eastside
Peak Net of
100%
Conservation
Eastside Peak
100%
Conservation
2014
Year MW
(23o F)
MW
(23o F)
MW
(23o F)
MW
(23o F)
2014-15 4,803 91 619 21
2015-16 4,820 177 641 31
2016-17 4,844 262 667 41
2017-18 4,891 341 688 51
2018-19 4,891 424 697 61
2019-20 4,904 490 708 74
2020-21 4,856 614 722 86
2021-22 4,850 694 730 96
2022-23 4,863 767 742 107
2023-24 4,888 832 764 110
2024-25 4,961 852 783 113
Source: PSE Solutions report
January 2016 APPENDIX A PSE CONSERVATION PROGRAM A-1
PHASE 1 DRAFT EIS
The types of conservation measures that PSE expects to implement to achieve its
conservation goals include the following:
• Energy Efficiency: Weatherization, efficient lighting, etc.
• Fuel Conversion: Converting from electric to gas
• Distributed Generation: Customer combined heat and power (CHP), solar, wind, etc.
• Distribution Efficiency: Measures implemented on PSE distribution systems
• Demand Response: Capacity savings programs
Figure A-1 shows PSE’s projected potential for achievable electric conservation by resource
type. Energy Efficiency is by far the largest contributor to total energy savings in PSE’s
conservation program, accounting for approximately 90 percent of total energy saving
systemwide by 2024. Distribution efficiency and demand response are included in the Energy
Efficiency category in this chart.
Figure A-1. Achievable Potential Electrical Conservation by Resource Type
Source- PSE IRP 2013- Appendix N (Figure 2)
Fuel conversion (from electric to gas) and distributed generation (smaller sources of power
such as solar, wind, and other generation types) represent a small but growing component of
PSE’s conservation program. PSE does not consider distributed generation to be cost
effective because it is expensive and therefore the projected energy savings from distributed
generation is very small.
In the past, PSE has conducted pilot programs with demand response. Those programs are
included in the forecast for future implementation as part of the energy efficiency component
shown in this graph.
APPENDIX A January 2016 A -2 PSE CONSERVATION PROGRAM
PHASE 1 DRAFT EIS
APPENDIX B. POTENTIAL CONSTRUCTION
EQUIPMENT
Table B-1. Alternative 1 (Options A and B) and Alternative 3
Alternative &
Option or
Component
Construction
Task Equipment
Alternative 1 (Options A and B) and Alternative 3
Overhead
Transmission Line
and Poles
Removal of
conductors from
existing poles
• Bucket truck
Removal of
existing wooden
poles
• Line truck or trackhoe to remove the old pole
• Backhoe to fill the hole
Installation of
foundations for
new steel poles
• Auger or vacuum truck to create holes
• Dump truck for hauling spoils
• Concrete truck for drilled pier foundations
• Backhoe to load the spoils into the dump truck
• Crane to install rebar cage if required
• Concrete pump truck if access to the site is
challenging
• Vacuum truck for site and street cleanup
• Heavy-duty flatbed trucks or semi-trucks for site
deliveries of equipment and construction
materials
Assembly and
erection of steel
poles
• Heavy duty trucks to deliver materials
• Crane for setting the poles (size dependent
upon weight of poles)
• Bucket truck or crane
• Basket for working on set structure (dependent
upon structure height)
• Auxiliary rubber tire vehicle to run the hydraulics
needed for jacking the poles together
• Vacuum truck for site and street cleanup
• Heavy-duty flatbed trucks or semi-trucks for site
deliveries of equipment and construction
materials
Installation of new
conductors
• Bucket truck or crane basket for working on set
structure (dependent upon structure height)
Stringing of power
lines
• Bucket truck or crane basket for working on set
structure (dependent upon structure height)
• Conductor reel trailer for hauling conductor reels
• Tensioner for applying tension to conductor
coming off reels during power line pull
• Puller for pulling rope/hard line with attached
conductor
January 2016 APPENDIX B POTENTIAL CONSTRUCTION EQUIPMENT B-1
PHASE 1 DRAFT EIS
Alternative &
Option or
Component
Construction
Task Equipment
Regrading
surfaces around
new poles and
work areas
• Bulldozer
• Trackhoe
• Backhoe
• Concrete mixers and/or pavers
New
Transformer(s) and
Substation or
Substation
Expansion
Construct new or
expanded
substation
• Small and heavy duty trucks for delivery of
materials and equipment
• Bulldozer
• Trackhoe
• Backhoe
• Concrete mixers
• Crane for unloading and placing transformer(s)
• Vacuum truck for site and street cleanup
• Heavy-duty flatbed trucks or semi-trucks for site
deliveries of equipment and construction
materials
Table B-2. Alternative 1, Option C
Alternative &
Option or
Component
Construction
Task Equipment
Alternative 1 (Option C)
Underground
Transmission Line
and Vaults
Excavation of
trench and cable
pulling
• Excavators or backhoes
• Dump trucks
• Bulldozers
• Concrete mixers
• Cranes
• Conductor reel trailer for hauling conductor
reels
• Tensioner for applying tension to conductor
coming off reels during power line pull
• Puller for pulling rope/hard line with attached
conductor
• Vacuum truck for site and street cleanup
• Heavy-duty flatbed trucks or semi-trucks for
site deliveries of small equipment and
construction materials
APPENDIX B January 2016 B -2 POTENTIAL CONSTRUCTION EQUIPMENT
PHASE 1 DRAFT EIS
Table B-3. Alternative 1, Option D
Alternative &
Option or
Component
Construction
Task Equipment
Alternative 1 (Option D)
Underwater Cable
Installation
Create cable
landing sites and
install vaults
• Excavator or backhoe for open-cut and vault
area trenching and loading dump truck
• Dump truck for hauling spoils
• Pile driver for sheet piles
• Dredge for in-water conduit near shoreline
• Concrete truck for poured in place vaults
• Crane for lifting miscellaneous materials
• Mixer truck and compaction grout pump to
inject thermal backfill
• Vacuum truck for site and street cleanup
• Heavy-duty flatbed trucks or semi-trucks for
site deliveries of small equipment and
construction materials
• Puller for pulling rope/hard line with attached
conductor
Install cable
underwater
• Submarine cable laying vessel (lay barge)
designed to lay the cable in one continuous
piece
January 2016 APPENDIX B POTENTIAL CONSTRUCTION EQUIPMENT B-3
PHASE 1 DRAFT EIS
Table B-4. Alternative 2
Alternative &
Option or
Component
Construction
Task Equipment
Alternative 2
Energy efficiency,
Demand response
Install minor
equipment and
modify buildings.
• Small trucks for delivery of materials
Distributed
generation
Install smaller
generation
equipment,
typically during
construction of a
new building
• Small and heavy duty trucks for delivery of
materials and equipment
• Grading equipment for ground level installations
• Crane for rooftop installations
Energy storage Construct battery
facility near
substation
• Small and heavy duty trucks for delivery of
materials and equipment
• Bulldozer
• Trackhoe
• Backhoe
• Concrete mixers
• Crane for unloading and placing batteries
Peak Power
Generation
Construct
generation facility
near substation
• Small and heavy duty trucks for delivery of
materials and equipment
• Bulldozer
• Trackhoe
• Backhoe
• Concrete mixers
• Crane for unloading and placing batteries
APPENDIX B January 2016 B -4 POTENTIAL CONSTRUCTION EQUIPMENT
PHASE 1 DRAFT EIS
APPENDIX C. ENDANGERED AND
THREATENED SPECIES
Table C-1. Federal and State Endangered and/or Threatened Species in the
Energize Eastside Study Areas
Species Federal/
State Status
Habitat Potentially
Present in Study
Areas?
Birds
Bald Eagle Federal Species of Concern and
State Sensitive Yes
Common loon State Sensitive Yes
Great blue heron State Monitored Yes
Green heron State Monitored Yes
Marbled murrelet Federal and State Threatened No
Northern Goshawk State Candidate Yes
Northern Spotted owl Federal Threatened and State
Endangered No
Osprey State Monitored Yes
Peregrine falcon Federal Species of Concern and
State Sensitive Yes
Pileated woodpecker State Candidate Yes
Purple martin State Candidate Yes
Trumpeter swan State Priority Yes
Vaux’s swift State Candidate Yes
Western grebe State Candidate Yes
Yellow-billed cuckoo Federal Threatened and State
Candidate No
Mammals
Townsend’s big-eared bat State Candidate Yes
Keen’s myotis State Candidate No
Long-legged myotis State Monitored Yes
Western long-eared bat State Monitored Yes
Reptiles and Amphibians
Western toad State Candidate Yes
January 2016 APPENDIX C ENDANGERED AND THREATENED SPECIES C-1
PHASE 1 DRAFT EIS
Species Federal/
State Status
Habitat Potentially
Present in Study
Areas?
Oregon spotted frog Federal Threatened Species and
State Endangered No
Western pond turtle State Endangered Yes
Fish
Coastal-Puget Sound bull
trout
Federal Threatened Species and
State Candidate Yes
Puget Sound Chinook
salmon
Federal Threatened Species and
State Candidate Yes
Puget Sound-Strait of
Georgia coho salmon Federal Species of Concern Yes
Puget Sound Steelhead
trout Federal Threatened Species Yes
River lamprey Federal Species of Concern,
State Candidate Yes
APPENDIX C January 2016 C-2 ENDANGERED AND THREATENED SPECIES
PHASE 1 DRAFT EIS
APPENDIX D. SOIL TYPES AND
GROUNDWATER IN STUDY AREAS
Table D-1. Soil Types and Groundwater in Study Areas
Soil Series Typical Depth to
Groundwater (inches)
Percent of Total Study
Area**
Alderwood 18-37 44.7
Everett 80+ 10.7
Arents 80+ 8
Beausite 80+ 6.3
Ovall 80+ 3.4
Kitsap 18-36 2.7
Urban Land N/A* 2.6
Indianola 80+ 2.2
Seattle Muck 0 2.2
Bellingham 0-12 1.3
Neilton 80+ 1
Puyallup 48-60 0.9
Sammamish 12-24 0.9
Briscot 12-24 0.8
Ragnar 80+ 0.8
Norma 0 0.6
Earlmont 24-36 0.5
Pits N/A* 0.5
Puget 0 0.5
Mixed Alluvial Land 12-36 0.4
Pilchuck 24-48 0.4
Tukwila Muck 0 0.3
Riverwash 0-24 0.2
Shalcar Muck 0 0.2
Snohomish 0-12 0.2
Sultan 24-36 0.2
*N/A = not applicable due to complete disturbance of mine pit or urban area.
**Soil series representing less than 0.1 percent of the total study area were not included as part of the
analysis.
Source: NRCS, 2015
January 2016 APPENDIX D SOIL TYPES AND GROUNDWATER IN STUDY AREAS D -1
PHASE 1 DRAFT EIS
APPENDIX E. PLANNING DOCUMENTS
REFERENCED FOR THIS ANALYSIS
Table E-1. Comprehensive Planning Documents Referenced for this Analysis
Comprehensive Plan Date of Adoption / Draft Date
City of Bellevue Comprehensive Plan Updated August 2015
City of Clyde Hill 2015-2035 Comprehensive Plan Updated Spring 2015
City of Issaquah Comprehensive Plan Updated June 2015
City of Kirkland 2015 Comprehensive Plan
(Kirkland 2035) Updated December 2015
City of Medina Comprehensive Plan 2015
Amendment Updated October 2015
City of Newcastle Comprehensive Plan 2015 Draft
City of Redmond Comprehensive Plan (Redmond
2030) Amended in 2015
City of Renton Comprehensive Plan Updated June 2015
City of Sammamish Comprehensive Plan 2015 Draft
King County Comprehensive Plan 2012 (2013
Update) Updated 2013
Town of Beaux Arts Village Comprehensive Plan 2014 Draft
Town of Hunts Point Comprehensive Plan Update 2014 Draft
Town of Yarrow Point Comprehensive Plan Updated September 2015
Note: In accordance with the GMA, four of the study area communities are in the process of updating their
comprehensive plans (Newcastle, Sammamish, Beaux Arts Village, and Hunts Point). For purposes of this
SEPA analysis, those draft documents were used since they appear to be nearing completion with some
degree of public process already integrated, and therefore they appear likely to form the basis for this
project’s land use approvals.
January 2016 APPENDIX E PLANNING DOCUMENTS REFERENCED FOR THIS ANALYSIS E -1
PHASE 1 DRAFT EIS
Table E-2. Shoreline Master Program Requirements/Documents Referenced for
this Analysis
Shoreline Master Program (SMP) Date of Adoption / Draft Date
City of Bellevue SMP Comprehensive Plan and Land Use
Code Amendments*
City of Clyde Hill SMP N/A
City of Issaquah SMP 2013
King County SMP 2013
City of Kirkland SMP 2010
City of Medina SMP 2014
City of Newcastle N/A
City of Redmond SMP 2009
City of Renton SMP 2011
City of Sammamish SMP 2011
Town of Beaux Arts Village SMP 2014
Town of Hunts Point SMP 2015
Town of Yarrow Point SMP 2012
* Amendments to the Bellevue Comprehensive Plan and the Land Use Code updating the city's shoreline
policies and the Shoreline Overlay District were used for this analysis as they represented an update to the
City’s Shoreline Master Program.
APPENDIX E January 2016 E -2 PLANNING DOCUMENTS REFERENCED FOR THIS ANALYSIS
PHASE 1 DRAFT EIS
APPENDIX F. POTENTIALLY APPLICABLE
COMPREHENSIVE PLAN AND SHORELINE
MASTER PROGRAM GOALS AND POLICIES
Table F-1. King County Planning Goals and Policies
King County
Planning Document Section* Topic* Goal or Policy and Text
King County
Comprehensive Plan
2012 (2013 Update)
Environment Greenhouse
Gas Emissions
Policy E-201: King County should participate in and support appropriate local,
regional, and national efforts and organizations focused on reducing
greenhouse gas emissions and preparing for climate change impacts.
Policy E-227: King County should support appropriate comprehensive
approaches to reduce greenhouse gas emissions, such as market-based
emissions reduction programs and products, renewable energy standards for
electricity production, and vehicle efficiency performance standards.
Economic
Development
Land Use
Policy ED-404: Through local subarea planning and partnerships with other
agencies and organizations, King County should use zoning, incentives, or
other measures to ensure that an appropriate proportion of the land adjacent
or near to major public infrastructure facilities is used to capitalize on the
economic benefit of that infrastructure. The surrounding land uses should be
compatible with the economic development uses or a buffer provided as
necessary.
Services,
Facilities, and
Utilities
Sustainability Policy F-203: When service providers are planning and designing facilities,
King County should encourage them to use sustainable development
practices.
Essential Public
Facilities
Policy F-226: Proposed new or expansions to existing essential public
facilities should be sited consistent with the King County Comprehensive Plan.
Listed existing essential public facilities should be preserved and maintained
until alternatives or replacements for such facilities can be provided.
Policy F-227: King County and neighboring counties, if advantageous to both,
should share essential public facilities to increase efficiency of operation.
Efficiency of operation should take into account the overall value of the
essential public facility to the region and the county and the extent to which, if
properly mitigated, expansion of an existing essential public facility located in
the county might be more economical and environmentally sound.
Policy F-228: King County should strive to site essential public facilities
equitably so that no racial, cultural, or socio-economic group is unduly
impacted by essential public facility siting or expansion decisions. No single
community should absorb an inequitable share of these facilities and their
January 2016 APPENDIX F
POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES F-3
PHASE 1 DRAFT EIS
King County
Planning Document Section* Topic* Goal or Policy and Text
impacts. Siting should consider equity, environmental justice and
environmental, economic, technical and service area factors. The net impact of
siting new essential public facilities should be weighted against the net impact
of expansion of existing essential public facilities, with appropriate buffering
and mitigation. Essential public facilities that directly serve the public beyond
their general vicinity shall be discouraged from locating in the Rural Area.
Policy F-229: A facility shall be determined to be an essential public facility if it
has one or more of the following characteristics:
a. The facility meets the Growth Management Act definition of an essential
public facility;
b. The facility is on a state, county or local community list of essential
public facilities;
c. The facility serves a significant portion of the county or metropolitan
region or is part of a countywide service system; or
d. The facility is the sole existing facility in the county for providing that
essential public service.
Policy F-230: Siting analysis for proposed new or expansions to existing
essential public facilities shall consist of the following:
a. An inventory of similar existing essential public facilities in King County
and neighboring counties, including their locations and capacities;
b. A forecast of the future needs for the essential public facility;
c. An analysis of the potential social and economic impacts and benefits
to jurisdictions receiving or surrounding the facilities;
d. An analysis of the proposal’s consistency with policies F-226 through F-
229;
e. An analysis of alternatives to the facility, including decentralization,
f. conservation, demand management and other strategies;
g. An analysis of economic and environmental impacts, including
mitigation, of any existing essential public facility, as well as of any new
site(s) under consideration as an alternative to expansion of an existing
facility;
h. Extensive public involvement; and
i. Consideration of any applicable prior review conducted by a public
agency, local government, or citizen’s group.
APPENDIX F January 2016 F-4 POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES
PHASE 1 DRAFT EIS
King County
Planning Document Section* Topic* Goal or Policy and Text
Service
Reliability
Policy F-301: Energy providers’ resource and facility plans should be
consistent with the King County Comprehensive Plan and should provide for a
reliable source of energy in the event of natural disaster or other potential
threats of disruption to service.
Alternative
Energy/New
Technology
Policy F-303: King County should encourage land uses and development that
will improve energy efficiency, and should support the expansion of renewable
energy resources through development regulations, prudent variances and
active incentive programs when the benefits of doing so outweigh the costs.
Policy F-307: King County should foster the development and increased use
of clean, renewable and alternative fuel and energy technologies
Policy F-311: King County should encourage its energy utilities to provide
energy efficiency services and renewable energy options to all their customers.
Additionally, the County should encourage the state and energy utilities to
mitigate the environmental and greenhouse gas emissions impacts of energy
and, as conservation and alternative energy sources demonstrate capacity to
address energy needs, phase out existing fossil fuel based power plants,
especially coal based sources.
Policy F-321: King County encourages:
a. the use of solar energy;
b. the siting of roads, lots, landscaping and buildings for improved solar
orientation;
c. the use of passive solar design and active solar technologies; and
d. the protection of solar access.
Utility Corridors/
Facilities
Policy F-324: To address the cumulative effects of multiple energy facilities,
King County should continue to participate in state and federal processes for
licensing, authorizing, or certifying, and any such renewals, of existing and
proposed power generation projects within King County. King County’s review
of individual projects in the state and federal processes should consider
consistency with designated land uses and environmental protection goals.
Specifically, power generation projects should:
a. Have climate change impacts considered and mitigated to the greatest
extent practical;
January 2016 APPENDIX F
POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES F-5
PHASE 1 DRAFT EIS
King County
Planning Document Section* Topic* Goal or Policy and Text
b. Be consistent with, and preferably directly incorporated in, utility
integrated resource plans;
c. Use renewable resources to the greatest extent practical;
d. Include public engagement;
e. Not significantly interfere with commercial forestry operations;
f. Be located and operated in a manner such that impacts to salmonid fish
and wildlife are minimized;
g. Avoid unstable and erosion-prone areas;
h. Include performance bonding to fund erosion control;
i. Provide full mitigation for construction and operation impacts;
j. Avoid, to the extent practicable, diminishing scenic values; and
k. Incorporate adequate public safety measures.
Policy F-325: King County and the utilities should identify and preserve
corridors to accommodate future electric power transmission and distribution
lines. Corridor designation should include:
a. Identification of appropriate shared uses and recognition of the values
provided by nonutility uses, such as recreation;
b. Recognition of county roads as utility corridors; and
c. Evaluation of proposed facility plans on a system-wide basis, rather
than project-by-project.
Policy F-326: When new, expanded or upgraded transmission is required, use
of existing corridors that have above-ground utilities should be evaluated first.
King County should facilitate appropriate corridor sharing among different
utility types and owners.
Policy F-327: New electrical distribution lines should be installed underground
where reasonably feasible and not a health or safety concern. The county
should encourage underground placement of existing distribution lines through
such tools as local improvement districts.
Health and
Safety
Policy F-328: King County will monitor scientific research on potential human
health effects of extremely low frequency electric and magnetic fields (EMF). If
federal or state agencies promulgate rules to reduce exposure to EMF —
through changes in the use of appliances, construction practices, the location
of electrical infrastructure or other activities — the county shall inform its
citizens and take appropriate actions.
APPENDIX F January 2016 F-6 POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES
PHASE 1 DRAFT EIS
King County
Planning Document Section* Topic* Goal or Policy and Text
Hazardous
Liquid and Gas
Transmission
Pipelines
Policy F-331: King County recognizes that federal and state regulatory
programs govern the design, construction, and operation of hazardous liquid
and gas transmission pipelines. To preserve the safety and reliability of the
hazardous liquid and gas transmission pipeline system, land use, zoning, and
regulations shall be consistent with state and federal requirements.
Policy F-334: When new, expanded, or upgraded hazardous liquid or gas
transmission pipelines are required, use of existing corridors should be
evaluated first. King County should facilitate appropriate corridor sharing
among different utility types and owners.
Policy F-338: Land uses shall be restricted within hazardous liquid and gas
transmission pipeline rights-of-way. Passive recreational uses, such as hiking
trails, may be allowed if the risk to life and property is assessed and
determined to be minimal.
Policy F-339: King County should promote the safety and reliability of the
hazardous liquid and natural gas transmission pipeline systems by requiring
developers, contractors, and excavators to notify the state, pipeline operators,
and utilities through the one-number locator service, before beginning
excavation or construction.
Parks, Open
Space and
Cultural
Resources
Parks and
Recreation
Policy P-109: King County shall provide local parks, trails and other open
spaces in the Rural Area. Local parks, trails and other open spaces that
complement the regional system should be provided in each community in
Rural Areas to enhance environmental and visual quality and meet local
recreation needs.
Rural Area and
Natural
Resource
Lands
Land Use
Policy R-655: Public services and utilities within and adjacent to APDs shall be
designed to minimize significant adverse impacts on agriculture and to
maintain total farmland acreage and the area’s historic agricultural character.
Shorelines Shoreline
Management
Policy S-203: King County, when determining allowable uses and resolving
use conflicts in the shoreline jurisdiction, shall apply the following preferences
and priorities in the order listed below:
Reserve shoreline areas for water-dependent and associated water related
uses. Harbor areas, established pursuant to Article XV of the State
Constitution, and other areas that have reasonable commercial navigational
January 2016 APPENDIX F
POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES F-7
PHASE 1 DRAFT EIS
King County
Planning Document Section* Topic* Goal or Policy and Text
accessibility and necessary support facilities, such as transportation and
utilities, should be reserved for water-dependent and water-related uses that
are associated with commercial navigation, unless adequate shoreline is
reserved for future water-dependent and water-related uses and unless
protection of the existing natural resource values of such areas preclude such
uses. Shoreline mixed-use developments may be allowed if they include and
support water dependent uses and address specific conditions that affect
water dependent uses.
Policy S-313: ensure that public and private development proposals protect
and restore the aesthetic quality of shorelines
Policy S-536: King County shall limit the size of new over-water structures in
the Aquatic Shoreline Environment to the minimum necessary to support the
structure's intended use.
Policy S-538: King County shall require all developments and uses on
navigable waters or their beds in the Aquatic Shoreline Environment to be
located and designed to minimize interference with surface navigation, to
consider impacts to public views, and to allow for the safe, unobstructed
passage of fish and wildlife and materials necessary to create or sustain their
habitat, particularly those species dependent on migration.
Policy S-539: King County shall not allow uses in the Aquatic Shoreline
Environment that adversely impact the ecological processes and functions of
critical saltwater and freshwater habitats, except when necessary to achieve
the objectives of RCW 90.58.020, and then only when the adverse impacts are
mitigated according to the sequence described in WAC 173-26-201(2)(e) as
necessary to assure no net loss of shoreline ecological processes and
functions.
Policy S-701: King County shall give preference to uses in the shoreline that
are consistent with the control of pollution and prevention of damage to the
natural environment or are unique to or dependent upon the shoreline.
APPENDIX F January 2016 F-8 POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES
PHASE 1 DRAFT EIS
King County
Planning Document Section* Topic* Goal or Policy and Text
Utility Corridors/
Facilities
Policy S-760: Utility facilities shall be designed and located to assure no net
loss of shoreline ecological processes and functions, preserve the natural
landscape, and minimize conflicts with present and planned land and shoreline
uses, while meeting the needs of future populations in areas planned to
accommodate growth.
Policy S-762: Transmission facilities for the conveyance of services, such as
power lines, cables, and pipelines, shall be located outside of the shoreline
jurisdiction where feasible. Transmission facilities located within the shoreline
jurisdiction shall assure no net loss of shoreline ecological processes and
functions.
Policy S-763: Utilities should be located in existing developed rights-of-way
and corridors to the maximum extent practical.
Policy S-764: Unless no other feasible alternative location exists, King County
should discourage:
a. Locating pipelines and cables in water, on tidelands or roughly parallel to
the shoreline; and
b. The development of facilities that may require periodic maintenance that
disrupts shoreline ecological processes and functions.
* The Section column indicates the element/chapter of the comprehensive plan where the goal or policy text was found. The Topic column indicates the subject
matter that is covered by the goal or policy text.
January 2016 APPENDIX F
POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES F-9
PHASE 1 DRAFT EIS
Table F-2. Beaux Arts Village Planning Goals and Policies
Beaux Arts Village
Planning Document Section* Topic* Goal or Policy and Text
Town of Beaux Arts
Village 2014
Comprehensive Plan
(Draft)
2014
Land Use Views and
Aesthetics
Plan Statement: Maintain desirability of residential character
Town of Beaux Arts
Village Shoreline
Master Program 2014
Utilities Policy 6.14.1:
A. Repair, maintenance, expansion and upgrades to existing primary utilities,
including the City of Bellevue’s sanitary sewer line and the Town’s municipal
water or stormwater management systems, should be allowed.
B. New primary utilities should be prohibited.
* The Section column indicates the element/chapter of the comprehensive plan where the goal or policy text was found. The Topic column indicates the subject
matter that is covered by the goal or policy text.
Table F-3. Bellevue Planning Goals and Policies
Bellevue Planning
Document Section* Topic* Goal or Policy and Text
City of Bellevue
Comprehensive Plan
2015
Citizen
Engagement
Land Use
Policy CE-4: Balance the interests of the commercial and residential
communities when considering modifications to zoning or development
regulations.
Capital
Facilities
Essential Public
Facilities
Policy CF-16: Define essential public facilities, consistent with the Growth
Management Act.
Policy CF-17: Require essential public facilities to be sited and designed
according to city standards and criteria in order to minimize potential impacts
to the community, while recognizing the public importance and difficult-to-site
nature of such facilities.
Policy CF-18: Participate in inter-jurisdictional efforts to site County-wide or
statewide essential public facilities. Pursue agreements among jurisdictions to
mitigate against the disproportionate burden that may fall on the jurisdiction
APPENDIX F January 2016 F-10 POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES
PHASE 1 DRAFT EIS
Bellevue Planning
Document Section* Topic* Goal or Policy and Text
which becomes the site of a facility.
Policy CF-19: Impose conditions of approval or other measures within the
scope of the city’s authority to mitigate environmental, compatibility, public
safety, or other impacts of the essential public facility.
Policy CF-20: Work to site or expand essential public facilities in ways that
equitably balance social, environmental, and economic impacts to achieve
citywide and regional planning objectives.
Policy CF-21: Locate Secure Community Transition Facilities, as defined by
RCW 71.09.020 now or as hereafter amended, outside of single family and
multifamily residential districts. Provide a separation between Secure
Community Transition Facilities and residentially developed property in other
land use districts.
Environment Alternative
Energy/New
Technology
Policy EN-4: Promote and invest in energy efficiency and renewable energy
resources as an alternative to nonrenewable resources.
Land Use
Land Use Goal: To develop and maintain a land use pattern that protects natural
systems and retains trees and open space; maintains and strengthens the
vitality, quality and character of Bellevue’s neighborhoods; and focuses
development activity in Downtown and other commercial and residential
centers.
Policy LU-2: Retain the city’s park-like character through the preservation and
enhancement of parks, open space, and tree canopy throughout the city.
Policy LU-29: Help communities to maintain their local, distinctive
neighborhood character, while recognizing that some neighborhoods may
evolve.
Policy LU-1: Promote a clear strategy for focusing the city’s growth and
development as follows:
1. Direct most of the city’s growth to the Downtown regional growth center
and to other areas designated for compact, mixed use development
served by a full range of transportation options.
2. Enhance the health and vitality of existing single family and multifamily
residential neighborhoods.
January 2016 APPENDIX F
POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES F-11
PHASE 1 DRAFT EIS
Bellevue Planning
Document Section* Topic* Goal or Policy and Text
3. Continue to provide for commercial uses and development that serve
community needs.
Views and
Aesthetics
Policy LU-13: Support neighborhood efforts to maintain and enhance their
character and appearance.
Policy LU-14: Protect residential areas from the impacts of nonresidential uses
of a scale not appropriate to the neighborhood.
Housing Neighborhoods Policy N-1: Maintain neighborhoods as safe and welcoming environments for
everyone to enjoy.
Parks and
Recreation
Views and
Aesthetics
Plan Statement: Define and enhance neighborhood character by using open
space as visual relief to separate and buffer between uses.
Natural Features Policy PA-5: Obtain, for preservation, natural areas that are sensitive to
urbanization or represent a valuable natural and aesthetic resource to the
community.
Utility Corridors/
Facilities
Policy PA-7: Maximize use of public lands by collaborating with other City
projects and programs to incorporate utility, storm drainage, underutilized
right-of-way and other public lands into the parks and open space system.
Vegetation Policy PA-29: Design, construct, operate, and maintain parklands and facilities
to preserve the ecology of natural systems on parklands.
Policy PA-30: Protect and retain, in a natural state, significant trees and
vegetation in publicly and privately-dedicated greenbelt areas.
Policy PA-31: Manage Bellevue’s forest resources, including street trees,
formal plantings, and self-sustaining natural stands, to ensure their long term
vitality.
Land Use Policy PA-37: Require a public review process for the conversion to non-
recreational use of park lands and facilities.
Urban Design Views and
Aesthetics
Policy UD-1: Enhance the appearance, image and design character to make
Bellevue an inspiring place to be.
Policy UD-2: Preserve trees as a component of the skyline to retain the image
of a “City in a Park.”
APPENDIX F January 2016 F-12 POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES
PHASE 1 DRAFT EIS
Bellevue Planning
Document Section* Topic* Goal or Policy and Text
Policy UD-3: Foster and value the preservation of open space as a dominant
element of the city’s character.
Policy UD-6: Encourage the green and wooded character of existing
neighborhoods.
Policy UD-7: Support neighborhood efforts to maintain and enhance their
character and appearance.
Policy UD-62: Views of water, mountains, skylines or other unique landmarks
from public places should be identified and preserved as valuable civic assets.
Utilities Alternative
Energy/New
Technology
Plan Statement: employment of new technology that improves utility services
and reliability while balancing aesthetic, health and safety, economic, and
environmental factors.
Utility Corridors/
Facilities
Plan Statement: Aesthetic impact of utilities can be reduced by using existing
facilities, where feasible. Examples of facilities that might be shared are
towers; electrical, telephone and light poles; substation sites; trenches; and
easements.
Utilities Goals:
• To develop and maintain all utilities at the appropriate levels of service
to accommodate the city’s projected growth.
• To ensure reliable utility service is provided in a way that balances
public concerns about infrastructure safety and health impacts,
consumer interest in paying a fair and reasonable price for service,
potential impacts on the natural environment, and aesthetic
compatibility with surrounding land uses.
• Utility facilities are permitted and approved by the city in a fair and
timely manner and in accord with development regulations, to
encourage predictability.
• New technology to improve utility services and reliability is used in
balance with health and safety, economic, aesthetics, and
environmental factors.
Policy UT-1: Manage utility systems effectively in order to provide reliable,
sustainable, quality service.
Policy UT-2: Build and manage city-owned utility infrastructure assets to
January 2016 APPENDIX F
POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES F-13
PHASE 1 DRAFT EIS
Bellevue Planning
Document Section* Topic* Goal or Policy and Text
reduce the likelihood of risks to public safety, property and environment, and
disruption due to asset failure.
Policy UT-3: Use design and construction standards that are environmentally
sensitive, safe, cost-effective, and appropriate.
Policy UT-6: Ensure that the location, type, and size of all public facilities is
determined and/or approved by the city.
Policy UT-7: Base the extension and sizing of system components on the land
use plan of the area. System capacity will not determine land use.
Policy UT-8: Design, construct, and maintain facilities to minimize their impact
on surrounding neighborhoods.
Policy UT-9: Encourage the joint use of public facilities such as the
development of a storm and surface water detention area as passive
recreation.
Policy UT-10: Emphasize cost effective management of city utility systems
over their lifetime, including planning for their renewal and replacement,
balancing risk, and maintaining desired service levels. Forecast future capital
and maintenance costs and manage rates so that customer rate revenue funds
the cost of ownership equitably across generations.
Policy UT-11: Educate and inform utility providers, consumers and the
community about the costs and benefits of emerging technologies.
Policy UT-12: Develop and periodically update functional utility system plans
that forecast system capacity and needs for at least a 20 year planning
horizon.
Policy UT-13: Consider Low Impact Development principles to minimize
impervious surfaces and native vegetation loss on all infrastructure
improvement projects.
Policy UT-45: Coordinate with non-city utility providers to ensure planning for
system growth consistent with the city’s Comprehensive Plan and growth
forecasts.
APPENDIX F January 2016 F-14 POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES
PHASE 1 DRAFT EIS
Bellevue Planning
Document Section* Topic* Goal or Policy and Text
Policy UT-46: Support new and emerging information and telecommunications
technologies that would benefit utility service delivery by being sustainable,
appropriate and viable.
Policy UT-47: Defer to the serving utility the implementation sequence of utility
plan components.
Policy UT-48: Coordinate with the appropriate jurisdictions and governmental
entities in the planning and implementation of multi-jurisdictional utility facility
additions and improvements.
Policy UT-49: Require effective and timely coordination of all public and
private utility activities including trenching and culvert replacements.
Policy UT-51: Maintain Bellevue’s competitive advantage and attraction as a
highly connected community.
Policy UT-57: Require notification to the city prior to a utility’s maintenance or
removal of vegetation in city right-of-way.
Policy UT-58: Require the undergrounding of all new electrical distribution
lines except that interim installation of new aerial facilities may be allowed if
accompanied by a program to underground through coordination with the city
and other utilities. Require the undergrounding of all existing electrical
distribution lines where a change in use or intensification of an existing use
occurs, unless delayed installation is approved as part of a specific program to
coordinate undergrounding of several utilities or in conjunction with an
undergrounding program for several sites or when related to street
improvements.
Policy UT-59: When implementing street projects, determine whether the
relocation of distribution facilities underground is required. If so, determine the
manner of payment: tariff schedule, capital improvement program, or the
formation of a local improvement district.
Policy UT-60: Work with Puget Sound Energy, telecom providers, state
regulatory agencies, and other responsible parties to develop funding tools
that enable full mitigation of the neighborhood impacts of deploying electrical
and telecommunications infrastructure.
January 2016 APPENDIX F
POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES F-15
PHASE 1 DRAFT EIS
Bellevue Planning
Document Section* Topic* Goal or Policy and Text
Policy UT-61: Allow new aerial telecommunication lines on existing systems
provided that they shall be designed to address visual impacts and are
required to be placed underground at the time of undergrounding electrical
distribution lines.
Policy UT-61: Support neighborhood efforts to underground existing electrical
transmission and distribution lines.
Policy UT-64: Require the reasonable screening and/or architecturally
compatible integration of all new utility and telecommunication facilities.
Policy UT-65: Protect Bellevue’s aesthetic quality and infrastructure
investment from unnecessary degradation caused by the construction of
telecommunication infrastructure.
Policy UT-66: Encourage directional pruning of trees and phased replacement
of improperly located vegetation in the right-of-way. Perform pruning and
trimming of trees in an environmentally sensitive and aesthetically acceptable
manner and according to professional arboricultural specifications and
standards.
Policy UT-68: Encourage the use of utility corridors as non-motorized trails.
The city and utility company should coordinate the acquisition, use, and
enhancement of utility corridors for pedestrian, bicycle and equestrian trails
and for wildlife corridors and habitat.
Policy UT-69: Avoid, when reasonably possible, locating overhead lines in
greenbelt and open spaces as identified in the Parks and Open Space System
Plan.
Policy UT-71: Facilitate and encourage conservation of resources. Discussion:
Items the city should consider in implementing this policy include conserving
the use of electric energy in its own facilities, and adopting practical and cost-
effective energy building codes.
Policy UT-72: Encourage cooperation with other jurisdictions in the planning
and implementation of multi-jurisdictional utility facility additions and
improvements. Decisions made regarding utility facilities shall be made in a
manner consistent with, and complementary to, regional demand and
resources, and shall reinforce an interconnected regional distribution network.
APPENDIX F January 2016 F-16 POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES
PHASE 1 DRAFT EIS
Bellevue Planning
Document Section* Topic* Goal or Policy and Text
Policy UT-74: Encourage system practices intended to minimize the number
and duration of interruptions to customer service.
Policy UT-77: Require all utility equipment support facilities to be aesthetically
compatible with the area in which they are placed by using landscape
screening and/or architecturally compatible details and integration.
Policy UT-91: Encourage the public to conserve electrical energy through
public education.
Policy UT-92: Encourage city and utility involvement with regional or statewide
agencies when and if they are developing policies regarding exposure to
electric and magnetic fields (EMF) or other utility issues.
Policy UT-93: Review new accepted scientific research of potential health
impacts associated with electrical and telecommunications facilities and make
changes to policies if the situation warrants.
Policy UT-94: Require in the planning, siting, and construction of all electrical
facilities, systems, lines, and substations that the electrical utility strike a
reasonable balance between potential health effects and the cost and impacts
of mitigating those effects by taking reasonable cost effective steps.
Policy UT-95: Work with Puget Sound Energy to implement the electrical
service system serving Bellevue in such a manner that new and expanded
transmission and substation facilities are compatible and consistent with the
local context and the land use pattern established in the Comprehensive Plan.
Discussion: Where feasible, electrical facilities should be sited within the area
requiring additional service. Electrical facilities primarily serving commercial
and mixed use areas should be located in commercial and mixed use areas,
and not in areas that are primarily residential. Further, the siting and design of
these facilities should incorporate measures to mitigate the visual impact on
nearby residential areas. These considerations must be balanced with the
community’s need to have an adequate and reliable power supply.
Policy UT-96: Require siting analysis through the development review process
for new facilities, and expanded facilities at sensitive sites, including a
consideration of alternative sites.
January 2016 APPENDIX F
POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES F-17
PHASE 1 DRAFT EIS
Bellevue Planning
Document Section* Topic* Goal or Policy and Text
Discussion: Sensitive facility sites are those new facilities and existing facilities
proposed to be expanded where located in or in close proximity to
residentially-zoned districts such that there is potential for visual impacts
absent appropriate siting and mitigation. The city will update Map UT-7 to the
extent needed to stay current with changes in Puget Sound Energy’s system
planning.
Policy UT-97: Avoid, minimize and mitigate the impacts of new or expanded
electrical facilities through the use of land use regulations and performance
standards that address siting considerations, architectural design, site
screening, landscaping, maintenance, available technologies, and other
appropriate measures.
Policy UT-99: Work with and encourage Puget Sound Energy to plan, site,
build and maintain an electrical system that meets the needs of existing and
future development, and provides highly reliable service for Bellevue
customers.
Discussion: Providing highly reliable service is a critical expectation for the
service provider, given the importance of reliable and uninterrupted electrical
service for public safety and health, as well as convenience. Highly reliable
service means there are few and infrequent outages, and when an unavoidable
outage occurs it is of short duration and customers are frequently updated as
to when power is likely to be restored. A highly reliable system will be
designed, operated and maintained to keep pace with the expectations and
needs of residents and businesses as well as evolving technologies and
operating standards as they advance over time.
Policy UT-100: Encourage the prioritization of restoring electrical service to
water and wastewater utility facilities following power outages.
Policy UT-101: Administer applicable regulations and franchise agreement
authority over the Seattle City Light and Olympic Pipeline infrastructure located
in Bellevue.
Energy Policy UT-70: Facilitate the conversion to cost-effective and environmentally
sensitive alternative technologies and energy sources.
* The Section column indicates the element/chapter of the comprehensive plan where the goal or policy text was found. The Topic column indicates the subject
matter that is covered by the goal or policy text.
APPENDIX F January 2016 F-18 POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES
PHASE 1 DRAFT EIS
Table F-4. Clyde Hill Planning Goals and Policies
Clyde Hill Planning
Document Section* Topic* Goal or Policy and Text
Clyde Hill
Comprehensive Plan
2015
Environment Energy ENV Policy 6.4: Support implementation of Washington State’s Renewable
Portfolio Standard and federal policy on reducing greenhouse gas emissions
from power production.
Land Use Utilities LU Policy 1.7: Provide policy guidelines that protect views and helps balance
the sometimes conflicting benefits of views and trees.
Utilities Utilities UTIL Policy 1.1: Continue to provide technical assistance to those
neighborhoods that wish to pursue the undergrounding of electrical,
telephone, and cable lines.
UTIL Policy 1.8: Work with electrical utility to address reliability in electrical
service.
* The Section column indicates the element/chapter of the comprehensive plan where the goal or policy text was found. The Topic column indicates the subject
matter that is covered by the goal or policy text.
Table F-5. Hunts Point Planning Goals and Policies
Hunts Point
Planning Document Section* Topic* Goal or Policy and Text
Draft Comprehensive
Plan Update for the
Town of Hunts Point
2014
Implementation Views and
Aesthetics
The Plan states that its tree code regulates the removal and replacement of
significant trees to “soften the visual impacts of development” and protect the
Town’s wooded and sylvan character
Shoreline Master
Program
2015
Shoreline Use
Policies
Utilities Policy 6.12
B. In areas where utilities must cross shoreline jurisdiction, they shall do so by
the most direct route feasible, unless such a route would negatively impact an
environmentally critical area, obstruct public access to the shoreline, or
interfere with the navigability of a waterbody regulated by this SMP.
C: Use of construction methods that avoid greater impact shall be used when
feasible, which may include directional boring, use of sleeves or other
construction methods which reduce or avoid temporary and long-term adverse
ecological impacts.
January 2016 APPENDIX F
POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES F-19
PHASE 1 DRAFT EIS
Hunts Point
Planning Document Section* Topic* Goal or Policy and Text
D. High voltage electric transmission lines are prohibited within shoreline
jurisdiction.
J. New accessory utility lines, including electricity and communications, shall
be located underground. Existing above ground lines shall be moved
underground when properties are redeveloped or in conjunction with major
system upgrades or replacements.
* The Section column indicates the element/chapter of the comprehensive plan where the goal or policy text was found. The Topic column indicates the subject
matter that is covered by the goal or policy text.
Table F-6. Issaquah Planning Goals and Policies
Issaquah Planning
Document Section* Topic* Goal or Policy and Text
City of Issaquah
Comprehensive Plan
2015
Introduction
and Vision
2040
Energy Care for the natural environment by…reducing greenhouse gas emission and
air pollutants.
Parks and
Recreation
The public realm is a community value and we strive to connect all aspects of
the public realm through trails, shared use routes and other connections.
Public Services The region will support development with adequate public facilities and
services in a coordinated, efficient and cost effective manner that supports
local and regional growth planning objectives.
Utilities and
Public Services
Ensure City utilities are maintained and improved while minimizing disruptions
to affected areas when utility improvements and new construction are
required.
Coordinate utilities and public facilities to ensure needed utility services will be
available when development occurs.
Encourage utility conservation efforts that minimize demand for natural
resources.
Provide efficient and cost-effective public services.
Provide high-quality public safety services and well-maintained and
dependable public facilities…The cost of providing and maintaining quality
services and facilities is shared equitably, balancing the needs of the
community with those of the individual.
APPENDIX F January 2016 F-20 POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES
PHASE 1 DRAFT EIS
Issaquah Planning
Document Section* Topic* Goal or Policy and Text
Vegetation As part of our fundamental value and identity of forested character, tree
cutting will be minimized outside Central Issaquah through stronger protection
of the forested hillsides. Protection of our remaining forested hillsides and tree
canopy enhancement on developed hillsides will ensure that Issaquah’s Alps
will provide the forested transition from our adjacent natural areas outside the
Urban Growth Boundary.
Economic
Vitality Element
Views and
Aesthetics
EV Policy A3: Plan for utility and other infrastructure assets to be available in
commercial areas, as addressed in the Utility element.
Land Use
Element
Vegetation LU Policy A5 Maintain the forested character of older developed hillsides such
as Squak Mountain, Cougar Mountain (not including Talus) Tiger Mountain and
the Plateau (such as Overdale Park) by requiring that new and infill
development should be made compatible through: limited clearing/grading
provisions; protection and preservation of existing tree canopy; limiting size of
development and number of buildings within clusters; limiting lot size and
height provisions; and providing links to sidewalks and bike paths since a
vehicular grid may be difficult in hillside development. For those hillside
neighborhoods that have recently undergone dense urban development, such
as Issaquah Highlands, Talus and Lakeside, protect and preserve the
remaining forested hillsides and restore the area over time so that it once again
attains the forested character so valued by the community. Restoration adds
to habitat, erosion protection and offsetting the urban heat island effects and
can include tree plantings in parks, critical area buffers, and other locations
where appropriate.
LU Goal B. Achieve and maintain an overall tree canopy of at least 50% for
reasons such as, but not limited to, offsetting the urban heat island effects,
sequestering carbon dioxide emissions, and creating an inviting pedestrian
environment.
LU Policy B1 Address the management of trees on two distinct levels.
a. Identify trees in our urban environments that create difficult conditions for
the maintenance of tree health, including limited root and canopy space, poor
soil quality inconsistent water, light and heat as well as pollution and
mechanical and chemical damage.
January 2016 APPENDIX F
POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES F-21
PHASE 1 DRAFT EIS
Issaquah Planning
Document Section* Topic* Goal or Policy and Text
b. Preserve the forest ecosystems found in Native Growth Protection and open
space areas through maintenance and restoration including planting of
appropriate trees, removal of invasive plants and adequate drainage and
watering.
LU Policy B2 Retain existing trees in critical areas and their buffers, along
designated pedestrian corridors and in other green spaces. Increase and
enhance the City’s Tree Canopy through a program of tree planting in public
areas, including street trees in planter strips, public parks, open spaces and
City facilities. Consider programs that create incentives for residents and
businesses to plant trees on their private property.
LU Policy B3 Maintain and strengthen, where possible, Tree City USA status.
Parks and
Recreation
LU Policy A11 Support the goals of the Mountains to Sound Greenway
Project.
Views and
Aesthetics
LU Policy A12 Integrate natural features such as wetlands, riparian corridors
and forested hillside views into the site design as amenities and protect them
as environmental resources. Require natural resources management practices
into site development and operation by:
a. incorporating natural drainage practices into park development to
provide community amenities and watershed benefits, where
appropriate and feasible;
b. integrating the Green Necklace into the riparian corridors to achieve
multiple benefits, including enhanced fish and wildlife habitat, trail
connections and environmental education; and
c. allowing flexibility in building design, orientation, spacing and
landscaping.
LU Policy E4 Enhance Riparian corridors and wetlands to integrate the views
and open space they provide into all developments, where applicable.
APPENDIX F January 2016 F-22 POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES
PHASE 1 DRAFT EIS
Issaquah Planning
Document Section* Topic* Goal or Policy and Text
LU Policy H9 Preserve, to the extent possible while achieving other City goals,
existing views of the Issaquah Alps, Mount Rainier and the Sammamish
Plateau from public spaces including circulation facilities, parks and open
space using methods such as increasing distances between high-rise
buildings, retaining or creating view corridors, and strategic placement of
building bulk or height.
LU Policy H10 Minimize the view impact of hillside development from the
valley floor and other hillsides by strategically integrating the architecture,
siting and landscaping into the natural environment. Techniques might include:
• using color hues which help buildings blend into the forested hillsides;
• using non-reflective surfaces to reduce glare;
• shifting buildings so they are not in a horizontal row; or
• strategically locating trees and other landscaping to reduce perceived
bulk and retain the forested hillside appearance.
Critical Areas LU Policy C3 Require new development and substantial redevelopment to
comply with adopted standards and buffers to protect critical areas.
Climate LU Goal F. Encourage innovative climate solutions which advance the City
towards a carbon neutral community.
LU Policy F1 Educate residents, businesses and developers regarding ways to
limit the community’s impact upon climate change such as through
development and redevelopment requirements, improved efficiency, carbon
sequestration and other climate solutions.
LU Policy F2 Encourage all development and infrastructure in the public and
private sectors which:
a. Use less energy and have a lower climate impact, and incorporate into
developments, where possible.
LU Policy F3 Reduce the city-wide greenhouse gas emissions, compared to a
2007 baseline, below 25% by 2020, below 50% by 2030 and below 80% by
2050.
January 2016 APPENDIX F
POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES F-23
PHASE 1 DRAFT EIS
Issaquah Planning
Document Section* Topic* Goal or Policy and Text
LU Policy F4 Reduce the impacts of climate through education, incentives,
policies and regulations that require reduction and mitigation of greenhouse
gas and carbon dioxide equivalent emissions in all land uses and by providing
incentives for innovative climate solutions which advance the City towards a
carbon neutral community.
LU Policy F6 Consider establishing a program to support energy efficiency
retrofits of existing buildings which will not be redeveloped in the short term.
Alternative
Energy
LU Policy F7: Work with Puget Sound Energy and other state and federal
programs to expand Issaquah participation in the Green Power Program, a
voluntary way for residents and businesses to buy renewable energy equal to
the amount of electricity they use.
General
LU Policy M5: Proactively coordinate with regional jurisdictions and agencies
to ensure that regional funding priorities do not overlook the needs of
Issaquah.
Utility Corridors/
Facilities
LU Policy N8: Control impacts of development on the following when
annexing.
• land use, including density, design, signage, landscaping and open
space provisions;
• surface and groundwater (wellhead protection and aquifer recharge
area and flooding);
• critical areas and natural resources;
• parks and recreation;
• utilities;
• transportation;
• housing;
• schools;
• economic vitality; and
• Issaquah’s Treasures.
Housing
Element
Energy H Policy A8 Encourage energy efficiency and other sustainability and
conservation measures into new and preserved housing, as well as the use of
environmentally sensitive housing development practices.
APPENDIX F January 2016 F-24 POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES
PHASE 1 DRAFT EIS
Issaquah Planning
Document Section* Topic* Goal or Policy and Text
Human
Services
Element
Energy HS Policy K1 Support utility assistance programs for low income households,
including financial assistance, weatherization and conservation programs in
order to help reduce individual household utility costs and provide for
increased housing stability.
Parks and
Recreation
Element
Views and
Aesthetics
P Policy B5.4 Scenic Visual Resources: Preserve the quality of surrounding
scenic and visual resources provided by the natural open space areas, such as
the forested hillsides of the “Issaquah Alps.” Encourage orienting park
development such that and facilities and activities preserve these picturesque
vistas for all to enjoy.
Utilities and
Public Services
Element
Land Use
Goal A. Facilitate the development of all utilities and public services at the
appropriate levels of service to accommodate Issaquah's planned growth and
ensure reliability of utilities and public services.
Essential Public
Facilities
U Policy I1: Essential public facilities shall be sited and designed to ensure
compatibility with the surrounding neighborhood.
Health and
Safety
U Policy A2: Ensure utility provision maximizes public safety, minimizes
adverse environmental impacts, and is compatible with surrounding land uses.
Balance public concerns over the potential safety and health impacts of utility
and public service infrastructure, consumers’ interest in paying a fair and
reasonable price for the utility and public service provider's product or service,
the natural environment and the potential impacts of utility or public service
infrastructures, and the community’s desire that utility and public service
projects be aesthetically compatible with surrounding land uses.
Utilities U Policy A4 Manage public facilities systems in order to provide reliable,
quality service and require that the location, type and size of all public facilities
be determined and/or approved by the City.
U Policy B4 Promote the efficiency of utility placement both in cost and timing
through methods such as:
a. collocate public and private utilities in shared trenches or utility corridors
where possible;
b. coordinate facility planning so utilities may locate in transportation
corridors and other dedicated rights-of-way;
January 2016 APPENDIX F
POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES F-25
PHASE 1 DRAFT EIS
Issaquah Planning
Document Section* Topic* Goal or Policy and Text
c. provide timely notice to utilities or coordinate with them when
construction/repair of existing and new roadway, bridges or sidewalks
is anticipated;
d. provide expeditious permitting, recognizing that avoiding utility project
delay can minimize service disruptions and associated costs for
residents and business;
e. design new public infrastructure to allow for projected future utilities that
may be placed within those facilities at a later time; and
f. encourage joint use of utility corridors for utilities, recreation and
appropriate nonmotorized connections.
U Policy F2: Require that all maintenance, repair and installation activities by
utilities are in compliance with the city codes and policies including critical
areas regulations.
U Policy F3: Require the undergrounding of all new electrical distribution lines
where it is reasonably feasible and in accordance with State rules, regulations
and tariffs.
U Policy F4: Encourage the consolidation of facilities such as towers, poles,
antenna, substation sites, trenches, and easements, and rights-of-way where
reasonably feasible and in accordance with prudent utility practice to minimize
adverse impacts on adjacent land uses.
U Policy F5: Decisions regarding utility facilities shall be made consistent with
the City's land use goals, regional demand and resources, and shall reinforce
an interconnecting regional distribution network.
City of Issaquah
Shoreline Master
Program
2013
Utilities -
Regulations
Shoreline
Management
Policy 5.18.1:
New public or private utilities, including utility production and processing
facilities and transmission facilities, should be located outside of the shoreline
area unless they are required for an authorized shoreline use
Utility Corridors/
Facilities
Policy 5.18.1:
Utilities should be located in existing rights-of-way and corridors wherever
possible; joint use of rights-of-way and corridors should be encouraged; new
utility facilities should be located and designed to preserve natural shoreline
features and to avoid public recreation and public access areas.
APPENDIX F January 2016 F-26 POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES
PHASE 1 DRAFT EIS
Issaquah Planning
Document Section* Topic* Goal or Policy and Text
Views and
Aesthetics
Policy 5.18.1:
Utility facilities and corridors should be located to protect scenic views, and
wherever possible, utility facilities should be placed underground or conversely
alongside or under bridges.
* The Section column indicates the element/chapter of the comprehensive plan where the goal or policy text was found. The Topic column indicates the subject
matter that is covered by the goal or policy text.
Table F-7. Kirkland Planning Goals and Policies
Kirkland Planning
Document Section* Topic* Goal or Policy and Text
City of Kirkland
Comprehensive Plan
2015
Community
Character
Element
Views and
Visual
Resources
Goal CC-3: Accommodate change within the Kirkland community and the
region in a way that maintains Kirkland’s livability and beauty.
Goal CC-4: Maintain and enhance Kirkland’s built and natural environment by
strengthening the visual identity of Kirkland and its neighborhoods.
Policy CC-4.5: Protect public scenic views and view corridors. Public
views of the City, surrounding hillsides, Lake Washington, Seattle, the
Cascades and the Olympics are valuable not only for their beauty but also for
the sense of orientation and identity that they provide. Almost every area in
Kirkland has streets and other public spaces that allow our citizens and visitors
to enjoy such views. View corridors along Lake Washington’s shoreline are
particularly important and should continue to be enhanced as new
development occurs. Public views can be easily lost or impaired and it is
almost impossible to create new ones. Preservation, therefore, is critical.
Private views are only protected where specifically mentioned in some of the
neighborhood plan chapters of the Comprehensive Plan and in the City’s
development regulations.
Policy CC-4.6: Preserve and enhance natural landforms, vegetation, and
scenic areas that contribute to the City’s identity and visually define the
community, its neighborhoods and districts.
Policy CC-4.10: Maintain and enhance the appearance of streets and other
public spaces.
January 2016 APPENDIX F
POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES F-27
PHASE 1 DRAFT EIS
Kirkland Planning
Document Section* Topic* Goal or Policy and Text
Policy CC-4.11: Minimize impacts on residential neighborhoods.
Economic
Development
Views and
Visual
Resources
Policy ED 4.1: Encourage construction and maintenance of infrastructure
systems for utilities, transportation, and telecommunication that optimize
service delivery to the business community.
Land Use
Element
Views and
Visual
Resources
Policy LU-1.3: Encourage attractive site and building design that is compatible
in scale and in character with existing or planned development.
Goal LU-6: Establish a coordinated and connected system of open space
throughout the City that:
• Preserves natural systems,
• Protects wildlife habitat and corridors,
• Provides land for recreation, and
• Preserves natural landforms and scenic areas.
Land Use Policy LU-1.4: Create effective transitions between different land uses.
Policy LU-1.5: Regulate land use and development in environmentally
sensitive areas to ensure improve and protect environmental quality and avoid
unnecessary public and private costs.
Policy LU-4.1: Maintain and enhance the character of Kirkland’s residential
areas.
Policy LU-4.4: Consider neighborhood character and integrity when
determining the extent and type of land use changes.
Parks and
Recreation
Policy LU-6.3: Consider the City’s streets and the Cross Kirkland Corridor as
integral parts of the overall open space network.
Alternative
Energy/New
Technology
Policy LU-7.2: Decrease energy use, promote renewable energy, and promote
public health through land use strategies that promote a mix of housing,
employment, and services at intensities sufficient to promote walking,
bicycling, and transit.
Essential Public
Facilities
Policy LU-8.1: Work cooperatively with King County, the State and/or other
cities to site essential public facilities.
APPENDIX F January 2016 F-28 POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES
PHASE 1 DRAFT EIS
Kirkland Planning
Document Section* Topic* Goal or Policy and Text
Policy LU-8.2: Consider the following in siting essential public facilities:
• Accessibility to the people served;
• Public involvement;
• Protection of neighborhoods;
• Preservation of natural resources;
• The cost-effectiveness of service delivery;
• Location near transit and mixed-use centers; and
• The goals and policies of the City’s Comprehensive Plan.
Policy LU-8.3: Design essential public facilities as well as government and
community facilities to reduce incompatibility with adjacent land uses.
Parks,
Recreation,
and Open
Space Element
Views and
Visual
Resources
The City should pursue opportunities to provide appropriate public access
(e.g. trails, viewpoints wildlife viewing areas, and boat landings) within natural
areas to support passive recreation and environmental education.
Parks and
Recreation
Goal PR-3: Protect, preserve, and restore publicly-owned natural resource
areas.
Policy 3.1: Maintain and enhance Kirkland’s waterfront parks to connect
residents with the water, provide unique recreational experiences, and support
tourism.
Policy 4.2: Develop, enhance and maintain signature greenways and trails that
stretch across the community and that connect residents to the City’s many
parks, natural areas, recreation facilities and other amenities.
Kirkland Waterfront: The City should strive to create a continuous pedestrian
and bicyclist greenway along the lakeshore through parks, neighborhood
greenway improvements, and trail easements.
Cross Kirkland Corridor: Develop or improve parks adjacent to the Cross
Kirkland Corridor to provide additional amenities and create pleasant
destinations or stopping points along the trail.
Shoreline Area
Element
Shoreline
Management
Policy SA-2.1: Designate properties as Natural in order to protect and restore
those shoreline areas that are relatively free of human influence or that include
intact or minimally degraded shoreline functions that are sensitive to potential
impacts from human use.
January 2016 APPENDIX F
POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES F-29
PHASE 1 DRAFT EIS
Kirkland Planning
Document Section* Topic* Goal or Policy and Text
Any use or development activity that would potentially degrade the ecological
functions or significantly alter the natural character of the shoreline area should
be severely limited or prohibited, as follows:
Roads, utility corridors, and parking areas that can be located outside of
Natural designated shorelines should be prohibited unless no other feasible
alternative exists. Roads, bridges and utilities that must cross a Natural
designated shoreline should be processed through a Shoreline Conditional
Use.
Policy SA-25.1: Locate new utilities and related appurtenances outside of the
shoreline area, unless this location is reasonably necessary for the efficient
operation of the utility.
To minimize potential impacts, these facilities should be located outside of the
shoreline area, and in particular, outside of the aquatic environment, where
feasible. If necessary within the shoreline, utility facilities should be located
and designed in a manner that preserves the natural landscape and shoreline
ecology, and minimizes conflicts with present and planned land uses.
Alternative energy use such as solar- and wind-based energy systems should
be encouraged within the shoreline environment, provided that any potential
adverse impacts are minimized.
Policy SA-25.2: Minimize impacts from the location, design, and maintenance
of utility facilities located within the shoreline.
Utility Corridors
/Facilities
Policy SA-25.3: Encourage consolidation of utilities within existing rights-of-
way or corridors.
Utilities
Element
Views and
Visual
Resources
Policy U-1. 78: Install new and, where feasible, existing utility distribution lines
underground. Undergrounding utilities can be especially effective along major
routes with good regional views; especially of Lake Washington and within
view corridors. The City should explore prioritizing the undergrounding of
existing utility lines in these areas.
Policy U-7.6: Screen above ground equipment cabinets and other structures
associated with electrical distribution without hindering access as required by
the provider.
APPENDIX F January 2016 F-30 POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES
PHASE 1 DRAFT EIS
Kirkland Planning
Document Section* Topic* Goal or Policy and Text
Policy U-7.7: Require siting analysis in the development review process for
new and expanded electrical transmission and substation facilities to address
land use and sensitive areas and provide mitigation to minimize visual and
environmental impacts.
New or expanded aerial transmission lines should be sited and designed to
minimize impacts to critical areas, preserve trees, and reduce visual impacts,
especially where views of Lake Washington, the Olympic Mountains and view
corridors are affected.
Utility Corridors/
Facilities
Policy U-1.8: Install new and, where feasible, existing utility distribution lines
underground.
Policy U-1.9: Encourage the joint use of utility corridors and facilities
consistent with prudent utility practice.
Policy U-7.5: Require new and, where feasible, existing electrical distribution
lines in the right of way to be underground.
Goal U-8: Facilitate the development and maintenance of non-City-managed
utilities at the appropriate levels of service.
Policy U-8.1: Work with non-City-managed utilities and review facility plans to
ensure that they reflect and support Kirkland’s land use plan. Likewise, the
City should work with providers to ensure that utilities are available to support
land uses and to maintain appropriate levels of service.
Policy U-8:3: Coordinate with the appropriate utility provider when considering
land use decisions in the vicinity of proposed facility locations to ensure land
use compatibility.
Health and
Safety
Goal U-3: Protect public health and environmental quality through appropriate
and efficient design, installation, and maintenance of sanitary sewer facilities
infrastructure.
Policy U-7.7: Require siting analysis in the development review process for
new and expanded electrical transmission and substation facilities to address
land use and sensitive areas and provide mitigation to minimize visual and
environmental impacts.
In addition, while the impacts of exposure to electric and magnetic fields (EMF)
on health remains a question, minimizing potential risk is appropriate.
January 2016 APPENDIX F
POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES F-31
PHASE 1 DRAFT EIS
Kirkland Planning
Document Section* Topic* Goal or Policy and Text
Accepted low-cost methods should be considered to reduce exposure without
unduly burdening the utility provider. The city should be involved with regional
or statewide agencies when and if they develop policies regarding exposure to
EMF. Periodic review of the state of scientific research on EMF may warrant
changes to policies.
Hazardous
Liquid and Gas
Transmission
Pipelines
During development review and construction of projects in the vicinity of the
pipeline, setting requirements for avoidance of damage and coordination
between Kirkland and the pipeline operator, Olympic Pipeline Company, or its
successor can help avoid problems.
Goal U-6: Reduce the risk to public safety and the environment in the event of
a hazardous liquid pipeline failure.
Policy U-6.1: Establish standards to minimize pipeline damage.
Require development activity near pipelines to provide the following
information in order to evaluate the proposal:
• Location of the liquid pipeline corridor in relation to proposed
structures,
utilities, or clearing and grading activities.
• Proposed techniques to minimize the potential disturbance to the
pipeline
prior to and during construction.
• Potential stormwater discharge impacts to the pipeline, and mitigation
measures to prevent erosion.
• Setbacks and other site design techniques to minimize the potential
hazard.
• Emergency plans as appropriate.
Policy U-6.2: Coordinate with the pipeline operator when developments are
proposed near the hazardous liquid pipeline corridor to reduce the potential for
problems.
The City and operator should communicate and coordinate their review.
Methods include the following:
• Notifying the pipeline operator of proposed development projects
located
near the pipeline corridor.
APPENDIX F January 2016 F-32 POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES
PHASE 1 DRAFT EIS
Kirkland Planning
Document Section* Topic* Goal or Policy and Text
• Receiving verification that the pipeline operator has received and
reviewed the proposal, and provided comments prior to City review of
development activity.
• Seeking the pipeline operator’s participation in preconstruction
meetings if warranted.
• Seeking monitoring by the pipeline operator of development that
involves land disturbance or other significant work within or near the
pipeline corridor.
Policy U-6.3: Prohibit new high consequence land uses from locating near a
hazardous liquid pipeline corridor. Design proposed expansions of high
consequence land uses to avoid increasing the level of risk in the event of a
pipeline failure, and where feasible, to reduce the risk.
Land uses with high-density on-site populations that cannot be readily
evacuated or protected in the event of a pipeline failure are considered “high
consequence land uses.” Examples are schools and multifamily housing
exclusively for the elderly or the handicapped.
Uses such as these carry a relatively higher risk and have higher potential
consequences in the event of a pipeline failure and therefore are not as
appropriate as other uses near pipelines. Facilities that serve critical “lifeline”
or emergency functions, such as fire and police facilities or utilities that provide
regional service, are also considered “high consequence land uses.”
Policy U-6.4: Require maintenance of the hazardous liquid pipeline corridor
through a franchise agreement or other mechanisms.
The pipeline operator can help reduce the likelihood of accidental damage by
adequately maintaining the pipeline corridor.
Dense vegetation such as blackberry bushes can impede visibility and access.
Instead, the pipeline corridor can be properly maintained with grass or other
low-growing vegetation that enables easy inspection while preventing erosion.
Ensuring that the pipeline locations are marked and that missing markers are
replaced is also important, as is periodic aerial inspection of the pipeline
corridor to detect potential problems. Kirkland can assist this effort when
permits are necessary for inspections or repair with prompt permit processing.
January 2016 APPENDIX F
POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES F-33
PHASE 1 DRAFT EIS
Kirkland Planning
Document Section* Topic* Goal or Policy and Text
The pipeline operator should maintain the pipeline corridor on a continual basis
by:
• Maintaining vegetation to enable visibility and access for inspection
while ensuring that such maintenance does not contribute to soil
erosion;
• Using plant species and plantings that prevent erosion;
• Ensuring that above and below grade pipeline markers containing
information, such as operator name and number and facility type, are in
place; and
• Conducting periodic visual inspections of the corridor.
Policy U-6.6: Continue to work with other jurisdictions, state and federal
governments, and the pipeline operator to seek improvements in safety
measures for hazardous liquid pipelines.
Working with other jurisdictions and agencies as part of a unified approach to
addressing pipeline safety issues is important. This unified approach can
address issues such as maintaining a model franchise agreement, periodic
review of the pipeline operator’s safety action plan to identify any deficiencies,
and advocacy of City concerns regarding pipeline safety regulations.
Alternative
Energy/New
Technology
Goal U-7 (related to Alternatives 2 and 3): Promote energy infrastructure that
is energy-efficient, addresses climate change, and protects the community
character.
Policy U-7.1: Encourage the public to conserve energy through public
education.
Policy U-7.2: Participate in regional efforts to increase renewable electricity
use 20% beyond 2012 levels countywide by 2030, phase out coal fire
electricity sources by 2025, limit construction of new natural gas based
electricity power plants, and support development of increasing amounts of
renewable energy sources.
Policy U-7.3: Work with and encourage PSE to provide clean and renewable
energy that meets the needs of existing and future development, and provides
sustainable, highly reliable, and energy efficient service for Kirkland customers.
Policy U-7.4: Promote the use of small to large scale renewable energy
production facilities.
APPENDIX F January 2016 F-34 POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES
PHASE 1 DRAFT EIS
Kirkland Planning
Document Section* Topic* Goal or Policy and Text
Health and
Safety
Policy U-8.6: Coordinate emergency response for utility disaster recovery.
During disasters, effective incident coordination between utility providers and
emergency management is imperative. Plans should include provisions for
mitigating impact of collapsed electrical poles and towers, pipeline failures of
all kinds (water, sewer, petroleum), for restoration of service as quickly as
possible, and for the citywide implementation of emergency management
plans.
* The Section column indicates the element/chapter of the comprehensive plan where the goal or policy text was found. The Topic column indicates the subject
matter that is covered by the goal or policy text.
Table F-8. Medina Planning Goals and Policies
Medina Planning
Document Section* Topic* Goal or Policy and Text
City of Medina
Comprehensive Plan
2015
Parks and
Open Space
Goals and
Policies
Views and
Aesthetics
Policy PO-P3: The City shall seek to acquire view rights to preserve the views
of view parks
Utilities Plan Utilities Policy UT-P1: The City shall coordinate with applicable service providers to
seek repairs and upgrades to existing utility facilities as necessary to maintain
and/or improve efficiency, reliability, and/or capacity.
Utilities Utilities UT-P2: The City shall provide leadership and seek to develop a plan to
underground remaining above-ground utility lines.
Shoreline Master
Program
2014
Shoreline
Management
Sub-Element
Views and
Aesthetics
Policy SM-P12.1: All development and uses on waters, or their beds, should
be located and designed with consideration to public views.
Policy SM-P12.4: Public’s visual access to all shoreline areas should be
preserved and enhanced through development regulations, such as setbacks
and high limits that ensure view corridors.
Shoreline
Management
Policy SM-P15.2: One of the policies stated in the SMP is that new utilities
should be located outside of the shoreline jurisdiction “unless no other feasible
location exists” (SM-P15.2; SMP). Should they be required in the shoreline,
utility facilities and corridors need to be located in manner that preserves that
January 2016 APPENDIX F
POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES F-35
PHASE 1 DRAFT EIS
Medina Planning
Document Section* Topic* Goal or Policy and Text
natural landscape, minimizes conflict with neighboring land uses, and
minimizes impacts on the aesthetic qualities of the shoreline.
Utility Corridors/
Facilities
Policy SM-P15.3: It is suggested that facilities be placed underground
whenever possible. Joint use of rights-of-way is also encouraged under the
SMP.
Policy SM-P15.5: Joint use of rights-of-way is also encouraged under the
SMP.
* The Section column indicates the element/chapter of the comprehensive plan where the goal or policy text was found. The Topic column indicates the subject
matter that is covered by the goal or policy text.
Table F-9. Newcastle Planning Goals and Policies
Newcastle Planning
Document Section* Topic* Goal or Policy and Text
Newcastle
2035 – 2015
Comprehensive Plan
Update
(Final Draft)
2015
Land Use
Element
Land Use Land Use Goals
LU-G3: preserve the existing character, scale, and neighborhood quality as
new development occurs
LU-G8: Strive to preserve and enhance natural features, such as stream
channels, that contribute to the City’s scenic beauty.
LU-G13: The City shall identify lands useful for public purposes such as utility
and transportation corridors, landfills, sewage treatment facilities, storm water
management facilities, recreation, schools, and other public uses.
Policy LU-P17: Non-residential uses may be allowed in new residential
developments when proposed uses are determined to be both viable and
beneficial to the surrounding neighborhood.
Views and
Aesthetics
Policy LU-P19: Specifically, the Plan encourages placement of utility lines in
shared utility corridors and recommends that aesthetics be considered during
design and maintenance. In general, the Plan states that design guidelines
should be used to “promote the aesthetic vision of the community”
APPENDIX F January 2016 F-36 POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES
PHASE 1 DRAFT EIS
Newcastle Planning
Document Section* Topic* Goal or Policy and Text
Water
Resources
Policy LU-P58: Stream crossings for streets, utilities, and other development
should be avoided where reasonable alternatives have lesser impacts on
habitats. Stream channels should not be placed in culverts unless absolutely
necessary for property access. Where no reasonable alternatives are possible,
impacts on habitats shall be minimized with compensatory mitigation provided
as appropriate.
Utilities
Element
Utilities The Utilities Element addresses utilities not owned or operated by the City of
Newcastle. The goal and supporting policies emphasize coordinated utility
planning, including co-location of utility lines in shared utility corridors. The
City of Newcastle recommends that the aesthetics and safety of utility
corridors be considered in their design and maintenance.
Utilities Goals:
UT-G1: To ensure that utilities including electricity, natural gas, and
telecommunications transmission are available or can be provided to serve the
projected population growth within the planning area in a manner which is
fiscally and environmentally responsible, justified by projected future demand,
aesthetically acceptable to the community and safe for nearby inhabitants.
Utility Corridors/
Facilities
Policy UT-P1: The City shall require that the undergrounding of new utility
distribution lines, with the exception of high voltage electrical transmission
lines.
Policy UT-P2: The City shall require the undergrounding of existing utility
distribution lines where physically feasible as streets are widened and/or areas
are redeveloped based on coordination with local utilities.
Policy UT-P3: The City shall promote co-location of major utility transmission
facilities such as high-voltage electrical transmission lines and water and
natural gas trunk pipelines within shared utility corridors, to minimize the
amount of land allocated for this purpose and the tendency of such corridors
to divide neighborhoods.
Policy UT-P4: The City of Newcastle shall promote co-location of utility
distribution facilities and share trenches in coordination of construction timing
to minimize construction related disruption to the public and to reduce the
cost of public utility delivery.
January 2016 APPENDIX F
POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES F-37
PHASE 1 DRAFT EIS
Newcastle Planning
Document Section* Topic* Goal or Policy and Text
Policy UT-P6: The City shall promote conservation measures to reduce the
need for additional utility distribution facilities in the future.
Policy UT-P7: Where found to be safe, the City shall promote recreational use
of utility corridors such as trails, sport courts, and similar facilities.
Policy UT-P8 The City shall encourage utility providers to limit disturbance to
vegetation within major utility transmission corridors to what is necessary for
the safety and maintenance of transmission facilities.
Policy UT-P10 The City should require utility providers to design and
construct overhead transmission lines in a manner that is environmentally
sensitive, safe, and aesthetically compatible with surrounding land uses.
Policy UT-P12: The City should encourage the replacement of outdated
equipment with technologically updated or advanced alternatives, providing
that the cost of the updated equipment is fiscally reasonable.
Policy UT-P14 The City should require utility providers to minimize visual and
other impacts of transmission towers and overhead transmission lines on
adjacent land uses through careful siting and design.
Policy UT-P15 The City should require new telecommunications and electric
utility distribution lines to be installed underground within the City where
practical in accordance with rules, regulations, and tariffs applicable to the
serving utility.
Policy UT-P16 The City should require new, modified, or replacement
transmission structures (such as lattice towers, monopoles, and the like) to be
designed to minimize aesthetic impacts appropriate to the immediate
surrounding area whenever practical.
Policy UT-P17 The City should require an analysis from utilities that states
either the direct benefits to the City of high capacity transmission lines or the
necessity of high capacity transmission lines through the City.
Policy UT-P19 The City shall require utility providers to mitigate the loss of
significant trees from the construction of new or expanded transmission
facilities.
APPENDIX F January 2016 F-38 POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES
PHASE 1 DRAFT EIS
Newcastle Planning
Document Section* Topic* Goal or Policy and Text
Policy UT-P20 The City shall, where appropriate, require reasonable
landscape screening of site-specific above-ground utility facilities in order to
diminish visual impacts.
Health and
Safety
Policy UT-P5: The City shall monitor current research efforts to determine
whether electrical or magnetic fields pose a potential health danger. The City
shall coordinate with other jurisdictions to pursue development of land use
regulations consistent with the findings.
Housing
Element
Land Use Policy HO-P2: The City shall protect the quality and character of existing
single family neighborhoods as described in the Land Use Element.
Health and
Safety
Policy HO-P8.A: The City should plan for neighborhoods that promote active
living and limit exposure to harmful environments.
* The Section column indicates the element/chapter of the comprehensive plan where the goal or policy text was found. The Topic column indicates the subject
matter that is covered by the goal or policy text.
Table F-10. Redmond Planning Goals and Policies
Redmond Planning
Document Section* Topic* Goal or Policy and Text
City of Redmond
Comprehensive Plan
2030
2015
Goals Vision
Framework
Policies
Goals Goals for Redmond
• To conserve agricultural lands and rural areas, to protect and enhance
the quality of the natural environment, and to sustain Redmond’s
natural resources as the City continues to accommodate growth and
development.
• To retain and enhance Redmond’s distinctive character and high quality
of life, including an abundance of parks, open space, good schools and
recreational facilities.
• To emphasize choices and equitable access in housing, transportation,
stores and services.
• To support vibrant concentrations of retail, office, service, residential
and recreational activity in Downtown and Overlake.
January 2016 APPENDIX F
POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES F-39
PHASE 1 DRAFT EIS
Redmond Planning
Document Section* Topic* Goal or Policy and Text
Utilities Infrastructure and services meet the needs of a growing population and
promote a safe and healthy community. The planning and placement of utilities
in Redmond has supported the community’s vision for the location and
amount of growth. Long-term planning for utilities has contributed to a high
quality of life for Redmond residents and businesses by ensuring efficient
utility delivery. Proper utility planning has also protected Redmond’s natural
environment and resources.
Shoreline
Management
Policy FW-7: Protect and restore the natural resources and ecological
functions of shorelines, maintain and enhance physical and visual public
access, and give preference to uses that are unique or dependent on shoreline
locations.
Views and
Aesthetics
Policy FW-9: Support Redmond as an urban community that values clean air
and water, views of stars at night, and quiet neighborhoods.
Policy FW-38: Maintain Redmond as a green city with an abundance of trees,
forested areas, open space, parks, wildlife habitats, riparian corridors, access
to shorelines and other elements of its beautiful natural setting.
Policy FW-40: Ensure that building and site design maintain and enhance
Redmond’s character, retain identities unique to neighborhoods and districts,
and create places that are high-quality, attractive and inviting to people.
Alternative
Energy/New
Technology
Policy FW-10: Additionally, promote efficient energy performance and use of
energy sources that move beyond fossil fuels.
Land Use
Policy FW-12: Ensure that the land use pattern accommodates carefully
planned levels of development, fits with existing uses, safeguards the
environment, reduces sprawl, promotes efficient use and best management
practices of land, provides opportunities to improve human health and
equitable provision of services and facilities, encourages an appropriate mix of
housing and jobs, and helps maintain Redmond’s sense of community and
character.
Policy FW-13: Ensure that the land use pattern in Redmond meets the
following objectives:
• Takes into account the land’s characteristics and directs development
APPENDIX F January 2016 F-40 POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES
PHASE 1 DRAFT EIS
Redmond Planning
Document Section* Topic* Goal or Policy and Text
away from environmentally critical areas and important natural
resources;
• Supports the preservation of land north and east of the city outside of
the Urban Growth Area, for long-term agricultural use, recreation and
uses consistent with rural character;
• Provides for attractive, affordable, high-quality and stable residential
neighborhoods that include a variety of housing choices;
Advances sustainable land development and best management practices,
multimodal travel and a high quality natural environment.
Policy FW-22: Make each neighborhood a better place to live or work by
preserving and fostering each neighborhood’s unique character and
preparation for a sustainable future, while providing for compatible growth in
residences and other land uses, such as businesses, services or parks.
Policy FW-26: Foster Old Town’s identity as a destination that has retained its
historic identity and traditional downtown character; ensure that it is linked
through attractive pedestrian connections to the rest of Downtown and
provides an inviting atmosphere in which to shop, stroll or sit during the day
and evening.
Parks and
Recreation
Policy FW-29: Maintain and promote a vibrant system of parks and trails that
are sustainably designed, preserve various types of habitat and protect the
natural beauty of Redmond.
Public Services
and Facilities
Policy FW-31: Plan, finance, build, rehabilitate and maintain capital facilities
and services consistent with the following principles:
• Ensure that capital facilities are sustainable, well designed, attractive
and safe;
• Provide facilities and services that protect public health and safety;
Ensure adequate provision of needed infrastructure and services;
Community
Character and
Historic
Preservation
Views and
Aesthetics
Policy CC-18: Use design standards and design review to accomplish the
following:
• Ensure the elements of design, proportion, rhythm and massing are
correct for proposed structures and the site;
January 2016 APPENDIX F
POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES F-41
PHASE 1 DRAFT EIS
Redmond Planning
Document Section* Topic* Goal or Policy and Text
• Retain and create places and structures in the city that have unique
features; • Ensure that building scale and orientation are appropriate to
the site;
• Encourage the use of high-quality and durable materials, as well as
innovative building techniques and designs;
• Promote environmentally friendly design and building techniques such
as LEED for the construction or rehabilitation of structures;
• Minimize negative impacts, such as glare or unsightly views of parking;
• Incorporate historic features whenever possible;
• Maintain integrity of zones such as Old Town with unique or historic
qualities; and
• Ensure that the design fits with the context of the site, reflecting the
historic and natural features and character.
Policy CC-23: Encourage landscaping that:
• Creates character and a sense of place,
• Retains and enhances existing green character,
• Preserves and utilizes native trees and plants, • Enhances water and air
quality,
• Minimizes water consumption,
• Provides aesthetic value,
• Creates spaces for recreation,
• Unifies site design,
• Softens or disguises less aesthetically pleasing features of a site, and
• Provides buffers for transitions between uses or helps protect natural
features.
Capital
Facilities
Health and
Safety
Future Vision for Redmond: Infrastructure and services meet the needs of a
growing population and promote a safe and healthy community.
Land Use Policy CF-18: Identify lands useful for public purposes in functional plans and
in the appropriate elements of the Comprehensive Plan. Identify alternative
sites or lands more generally where acquisition is not immediate. Identify lands
specifically when acquired and used for public purposes on the Land Use
Map, or in the appropriate elements of the Comprehensive Plan where not
otherwise identified by City or other governmental agency functional plans.
APPENDIX F January 2016 F-42 POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES
PHASE 1 DRAFT EIS
Redmond Planning
Document Section* Topic* Goal or Policy and Text
Land Use
Policies
Land Use Policy LU-14: Encourage the provision of needed facilities that serve the
general public, such as facilities for education, libraries, parks, culture and
recreation, police and fire, transportation and utilities. Ensure that these
facilities are located in a manner that is compatible with the City’s preferred
land use pattern.
Public Services
and Facilities
Policy LU-15: Support equitable delivery of and access to human services by
allowing these uses in suitable locations and encouraging their creation
through incentives or bonuses and other innovative measures.
Essential Public
Facilities
Policy LU-16: Allow essential public facilities in those zones in which they
would be compatible. Classify the type of land use review, such as whether the
use is permitted or conditionally allowed, based on the purpose of the zone
and the facility’s potential for adverse impacts on uses and the environment.
Consider allowing all essential public facilities in the Manufacturing Park zone
if such uses are not compatible elsewhere.
Parks and
Recreation
Policy LU-64:
Urban Recreation and Open Space Designation
Allowed Uses.
Implement this designation through the Urban Recreation zone. Permit uses
that fit a constrained area, such as public parks; trails; agricultural uses,
including the keeping of animals compatible with the size of the property;
riding stables and farm residences. Consider allowing uses, such as ball fields,
outdoor private recreation areas, such as golf courses used primarily for
nonmotorized recreation; limited accessory uses, such as a restaurant, and
regional utilities.
Urban Recreation, Semirural
Environmental hazards, such as flooding and seismic hazards, limit the
suitability of the Sammamish and Bear Creek Valleys for development. The
valleys are also subject to development limitations due to the need to provide
for groundwater recharge, the presence of important fish habitats and likely
wetlands, and the need to provide appropriate transitions to agricultural and
rural areas north and east of Redmond. Significant infrastructure constraints,
including transportation and utilities, also affect the type of uses suitable for
these places.
January 2016 APPENDIX F
POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES F-43
PHASE 1 DRAFT EIS
Redmond Planning
Document Section* Topic* Goal or Policy and Text
Neighborhoods
– Bear Creek
Views and
Aesthetics
Bear Creek is unique in Redmond: it is a residential area adjacent to
Downtown that contains large, ecologically important open spaces enjoyed not
only by those who live there, but also by those whose only link with the
neighborhood is a commute on Avondale Road.
Bear Creek continues to be a safe neighborhood where people feel connected
to one another. The neighborhood has a green character. It retains a
significant tree canopy, and those in the neighborhood take advantage of the
latest in energy efficient and low-impact development techniques. The
Bear/Evans Creek valley—the neighborhood’s front yard—continues to have a
rural-agricultural feel.
Policy N-BC-3: Preserve the public view corridor from Avondale Road through
the Keller Farm toward Mount Rainier.
Neighborhoods
– Education Hill
Views and
Aesthetics
Policy N-EH-2: Identify public view corridors unique to the Education Hill
Neighborhood, such as those of the Sammamish River and Sammamish
Valley, Bear Creek Valley and the Cascade Mountains, Lake Sammamish and
Mount Rainier. Design streets, trails and parks, as well as elements adjacent to
the public right-of-way, to preserve and enhance those view corridors, while
considering safety and privacy concerns of private property owners.
Neighborhood Vision: Education Hill is an attractive, green area. Critical
areas, such as streams and unstable slope areas, have been protected from
development. Most of the slopes overlooking the Sammamish and Bear Creek
Valleys are maintained in a native, undeveloped condition to protect the
environment and preserve the woodland views valued by neighborhood
residents.
Panoramic views from various locations on Education Hill further add to the
neighborhood’s character and identity and include vistas of Bear Creek Valley
and the Cascade Mountains to the east; Mount Rainier, Downtown Redmond,
Lake Sammamish and the Cascade foothills to the south; and the Sammamish
River and Sammamish Valley to the west.
Neighborhoods
- Idylwood
Utility Corridors/
Facilities
Policy N-ID-27: Promote undergrounding utility lines along West Lake
Sammamish Parkway, NE 24th Street and NE 36th Street. Coordinate
undergrounding of utility lines with significant street improvement projects as
feasible.
APPENDIX F January 2016 F-44 POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES
PHASE 1 DRAFT EIS
Redmond Planning
Document Section* Topic* Goal or Policy and Text
Utilities throughout the Idylwood Neighborhood offer possible opportunities for
upgrade over the next 20 years. The electrical and communication
infrastructure is the most visible and significant component for residents. The
elevated conduit experiences many issues during wet and windy weather, in
part due to the proximity of dense, mature vegetation. The neighborhood
supports priority undergrounding along corridors that provide the backbone of
the electrical infrastructure for the Idylwood Neighborhood.
Neighborhoods
– North
Redmond
Utilities The State Growth Management Act (GMA) and King County Countywide
Planning Policies direct cities to be the provider of local urban services to
urban areas. North Redmond property owners within the Urban Growth Area
(UGA) who decide to subdivide their land are required to install urban water
and sewer systems. Policies in the Utility Element of the Comprehensive Plan
seek to achieve the following: to protect the environment by minimizing
disruption of the natural and built environment when placing utilities, to
encourage provision of utilities in an economical fashion, and to minimize
disruption that results from the provision of utilities to the natural vistas and to
open spaces within the neighborhood. As development in North Redmond
continues, it is ever important to ensure that reliable and consistent utility
services are available to its residents.
Views and
Aesthetics
Policy N-NR-9: Promote the preservation of public view corridors through a
variety of techniques, such as innovative site design.
Policy N-NR-10: Preserve scenic, public view corridors toward the Cascades
and the Sammamish Valley. Public view corridors are defined along NE 116th
Street, 172nd Avenue NE, NE 122nd Street to 162nd Place NE, 154th Place
NE, Redmond-Woodinville Road, and along the easement of the
Redmond/Puget Sound Energy Trail.
Policy N-NR-28: Preserve and enhance, or reestablish, dense vegetation
within the Wedge subarea. Select and maintain species for required tree
preservation, common landscaping, visual screening, building setbacks, front
yards and other required landscape areas to provide vegetation that is
multistory at maturity, native, noninvasive and appropriate to the site.
January 2016 APPENDIX F
POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES F-45
PHASE 1 DRAFT EIS
Redmond Planning
Document Section* Topic* Goal or Policy and Text
Utility Corridors/
Facilities
Policy N-NR-78: Require the undergrounding of all new utilities in North
Redmond and as older utility lines are updated, with the exception of the
Puget Sound Energy high voltage transmission lines. Coordinate the
undergrounding of existing overhead utilities as street construction or
maintenance occurs in these service areas.
Policy N-NR-79: Minimize excavation, clearing and grading within the Wedge
subarea, as feasible, by combining all utility easements and by combining
other corridors and easements such as:
• Street right-of-way,
• Nonmotorized paths, and
• Other existing unvegetated corridors.
Neighborhoods
– Sammamish
Valley
Views and
Aesthetics
Policy N-SV-4: Development of the area adjacent to the Sammamish Valley,
west of Redmond Woodinville Road, and north of NE 116th Street shall be
required to protect significant tree stands, views from the valley and maintain
the rural quality of the site. Development of the area shall be required to
protect agricultural lands and to minimize the potential of trespass and
overspray. Measures to protect agricultural lands include setbacks on new
development, density limitations, and stormwater measures to prevent runoff
from flooding agricultural lands.
Neighborhoods
– Willows/Rose
Hill
Views and
Aesthetics
The following policy applies to the Willows Corridor north of the Puget Sound
Energy transmission line right-of-way. This policy is intended to maintain the
desired features of the Willows Corridor, allow for the continued use of the
area by high technology businesses, protect development from natural
hazards, and minimize the impacts of development on sensitive areas and the
Sammamish Valley. The design concepts set forth in the policy below shall be
implemented through regulations that use criteria to achieve the concepts.
Policy N-WR-G-1: Developments within the Willows Corridor north of the
Puget Sound Energy transmission line right-of-way shall be designed to ensure
the following:
• Important natural features of the hillside corridor are preserved.
• The area maintains a pastoral and parkway appearance.
APPENDIX F January 2016 F-46 POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES
PHASE 1 DRAFT EIS
Redmond Planning
Document Section* Topic* Goal or Policy and Text
• Buildings are visually compatible with the forested hills and open
pastures of the Willows Corridor. Buildings and parking do not
dominate views of the Willows Corridor.
• Developments are visually separated from each other and Willows Road
with areas of open space.
• High-quality site and building designs are maintained.
• Pedestrian and bicycle links to Willows Road are provided.
• Nearby residential uses to the west are visually buffered from the
development through screening by topography, trees or other
measures.
The purpose of the open space is to provide visual relief from the massing and
scale of the built environment
Development in the Willows Corridor must be managed to protect the valley
from negative impacts, such as increases in stormwater. Development must
also be set back from the valley to preserve view corridors and so it does not
interfere with agricultural practices north of NE 116th Street.
Parks, Arts,
Recreation,
Culture and
Conservation
Views and
Aesthetics
Policy PR-34: Encourage the acquisition of resource parkland to protect
environmental resources, represent significant natural and visual assets,
provide circulation linkages, wildlife corridors and habitat, and ensure
adequate separation and buffers between various land uses.
Policy PR-49: Encourage King County to develop and maintain the trail on the
west side of the Sammamish River to enhance access to and views of the
Sammamish River.
Policy PR-52: As a complement to the citywide pedestrian pathway system,
the City should develop a visual system for enhancing connections to the
shoreline and identifying shoreline areas, considering such elements as street
graphics, landscaping, street furniture or artwork. (SMP)
Shoreline
Master
Program
Views and
Aesthetics
Policy SF-3: Provide a comprehensive and focused system of physical, visual
and cultural access to Redmond’s shorelines.
Policy SF-5: Maintain shoreline views.
January 2016 APPENDIX F
POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES F-47
PHASE 1 DRAFT EIS
Redmond Planning
Document Section* Topic* Goal or Policy and Text
Policy SL-38: Maintain public view corridors as identified in RZC 21.42,
Identification of Citywide Public View Corridors, where required, within the
shoreline and from upland areas to the shoreline in shoreline developments,
through appropriately designed building setbacks, height and bulk, clustering
of structures, density bonuses where allowed, or similar design strategies.
Policy SL-39: Encourage shoreline development that provides views of the
water from the development, using appropriate building location and design,
thoughtful selection and location of landscaping, and other design strategies.
Policy SL-40: Maintain view corridors from Avondale Road and Union Hill
Road in the Bear Creek Design District land north of Bear and Evans Creeks
and east of Avondale Road, subject to the nexus and proportionality tests laid
out by the U.S. Supreme Court.
Policy SL-74: Locate utilities, where feasible, within existing utility corridors.
Locate above-ground utilities away from fish and wildlife habitat, public access
areas, and view corridors.
Policy SL-81: Prohibit outdoor lighting levels for security, building and parking
lot lighting, and intensive recreational uses in the shoreline that exceed the
minimum necessary for safe and effective use. Screen all lighting, except for
minimum pedestrian lighting, from the shoreline through landscaping, shields
or other design measures.
Shoreline
Management
Policy SL-50 Avoid location of nonwater-dependent and nonwater-related
uses, activities, and development, except for essential transportation and
utilities facilities, waterward of the ordinary high water mark. Transportation
and utilities facilities may be allowed where no feasible alternative exists and
negative impacts to salmon and steelhead habitat are mitigated.
Utility Corridors/
Facilities
Policy SL-73: Locate regional utilities outside of the shoreline. Locate such
facilities away from public access areas and view corridors and away from the
shoreline to the farthest location possible where a nonshoreline location is not
feasible.
Utilities
Utilities
Policy UT-2: Design and maintain public utility facilities to meet service
standards identified in the Capital Facilities Element and corresponding
functional plans.
APPENDIX F January 2016 F-48 POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES
PHASE 1 DRAFT EIS
Redmond Planning
Document Section* Topic* Goal or Policy and Text
Map UT-1: Shows the locations of major existing electrical facilities.
Map UT-2: Shows proposed major electrical facilities.
Alternative
Energy/New
Technology
Policy UT-3: Encourage the use of innovative technologies to:
• Provide and maintain utility services;
• Reduce the negative impacts of additional utility service demands;
• Improve the existing service; and
• Reduce, where appropriate, the overall demand on utility systems.
Policy UT-59: Work with energy service providers to promote an affordable,
reliable and secure energy supply that increases development and use of
renewable and less carbon-intensive sources, and that minimizes demand and
consumption.
Policy UT-71: Encourage and provide opportunities to convert existing homes
or businesses to natural gas from oil and less efficient electric space and water
heating equipment.
Policy UT-72: Facilitate efforts to develop a natural gas fuel infrastructure. This
may include:
• Updating regulations to address this technology,
• Training fire and police personnel so they are well versed with this
technology,
• Taking leadership or cooperating with other jurisdictions in building a
natural gas fueling facility for government vehicles, and
Identifying areas for the potential siting of a biomass production facility.
Policy UT-73: Promote, support, and increase the use of clean alternative
energy by:
• Advocating for the development of renewable energy sources;
• Facilitating development and use of innovative technologies, such as
alternative fuels and on-site renewable energy; and
• Providing incentives for development that incorporates renewable
energy.
Utility Corridors/
Facilities
The electrical transmission system is a utility system that fills an essential
public need. Therefore, zoning should allow the siting of major transmission
lines at or above 115 kilovolt capacity and substation facilities in areas where it
January 2016 APPENDIX F
POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES F-49
PHASE 1 DRAFT EIS
Redmond Planning
Document Section* Topic* Goal or Policy and Text
is reasonably necessary to provide efficient service. With coordination between
the utility and the City in advance of facility siting, problems of conflicting land
uses may be reduced or avoided.
Policy UT-9: Promote the efficiency of utility placement both in cost and
timing through methods such as the following:
• Collocate public and private utilities in shared trenches or utility
corridors, provided that such joint use is consistent with limitations as
may be prescribed by applicable legal and safety considerations;
• Coordinate facility planning so that utilities may locate in transportation
corridors and other dedicated rights-of way;
• Design new public infrastructure to allow for projected future utilities
that may be placed within those facilities at a later time; and
Encourage joint use of utility corridors for utilities, recreation and appropriate
nonmotorized connections.
Policy UT-12: Design, locate and construct facilities to minimize adverse
impacts to the environment and to protect environmentally sensitive areas.
Take into account both individual and cumulative impacts. Minimize impacts
through actions such as:
• Using construction methods and materials to prevent or minimize the
risk of overflows into watercourses and water bodies;
• Locating utility corridors in existing cleared areas;
• Locating utility facilities and corridors outside of wetlands;
• Minimizing crossings of fish-bearing watercourses;
• Using biostabilization, riprap or other engineering techniques to prevent
erosion where lines may need to follow steep slopes; and
• Minimizing corridor widths.
Policy UT-13: Require underground installation of all new utility distribution
lines, except where underground installation would cause greater
environmental harm than alternatives or where the Washington Utilities and
Transportation Commission tariff structure is not consistent with this policy.
Consider new technologies such as wireless transmission as they become
available.
APPENDIX F January 2016 F-50 POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES
PHASE 1 DRAFT EIS
Redmond Planning
Document Section* Topic* Goal or Policy and Text
Policy UT-62: Allow electrical utility facilities as a permitted use where
appropriate to ensure that land is available for the siting of electrical facilities.
Views and
Aesthetics
Policy UT-15: Require reasonable screening or architecturally compatible
design of above ground utility facilities, such as transformers and associated
vaults. Promote high-quality design of utility facilities through measures such
as:
• Use of varied and interesting materials,
• Use of color,
• Additions of artwork, and
• Superior landscape design.
Land Use Policy UT-58: Work with energy service providers to ensure energy facility
plans reflect and support Redmond’s Land Use Plan and that energy
resources are available to support the Land Use Plan.
Policy UT-61: Recognize the current Electrical Facilities Plan, authored by
Puget Sound Energy, as the facility plan for electrical utilities serving Redmond
and the vicinity. Use this plan, where it is consistent with Redmond’s land use
goals, as a guide in identifying and preserving utility corridors and locating
electrical facilities.
Policy UT-63: Coordinate with Puget Sound Energy or any successor when
considering land use designations or new development in the vicinity of
proposed facility locations that might affect the suitability of the designated
areas for location of facilities.
Energy Policy UT-59: Work with energy service providers to promote an affordable,
reliable, and secure energy supply that increases development and use of
renewable and less carbon-intensive sources, and that minimizes demand and
consumption.
Health and
Safety
Policy UT-67: Require designs that incorporate known and accepted low-cost
technological methods of reducing magnetic fields or the exposure to them
when siting high voltage electrical facilities until further research provides more
information on the health effects of electromagnetic fields. Methods may
include:
• Line configurations that reduce field strength,
January 2016 APPENDIX F
POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES F-51
PHASE 1 DRAFT EIS
Redmond Planning
Document Section* Topic* Goal or Policy and Text
• Sufficient right-of-way widths, and
• Sufficient height of lines from the ground for high-voltage transmission
facilities.
Policy UT-68: Periodically review the state of scientific research on ELF/EMF
and modify policies and regulations, if warranted, by changing knowledge or if
new state or federal regulation requires changes.
Hazardous
Liquid and Gas
Transmission
Pipelines
Policy UT-89: Require proposed developments, expansions of existing uses
and construction projects, both public and private, located near hazardous
liquid pipeline to:
• Show the location of the liquid pipeline corridors in relation to proposed
structures, utilities, or clearing and grading activities;
• Use techniques prior to and during construction to minimize the
potential for disturbing the pipeline;
• Identify and mitigate potential erosion over pipelines from storm water
discharge;
• Use setbacks and other site design techniques to minimize the potential
hazard; and
• Develop emergency plans as appropriate.
Policy UT-90: Coordinate with the pipeline operator when developments are
proposed near a hazardous liquid pipeline corridor to reduce the potential for
problems. Methods include but are not limited to:
• Notifying the pipeline operator of proposed development projects
located within one-quarter mile of a pipeline corridor;
• Seeking the pipeline operator’s participation in preconstruction
meetings for projects located within 150 feet of a pipeline corridor;
• Requesting the operator to determine if additional measures above the
normal locating process are necessary to physically verify the pipeline
locations before proceeding to develop; and
• Seeking monitoring by the pipeline operator of development that
involves land disturbance or other significant work within the pipeline
corridor, or within 30 feet of a pipeline, whichever is greater.
APPENDIX F January 2016 F-52 POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES
PHASE 1 DRAFT EIS
Redmond Planning
Document Section* Topic* Goal or Policy and Text
Policy UT-91: Prohibit new high consequence land uses from locating near a
hazardous liquid pipeline corridor. Design proposed expansions of existing
high consequence land uses to, at a minimum, avoid increasing the level of
risk in the event of a pipeline failure, and where feasible, to reduce the risk.
Policy UT-92: Require appropriate mitigation measures that help reduce
adverse impacts in the event of a pipeline failure to be used by commercial,
industrial, multifamily, or other development which, because of proximity to a
hazardous liquid pipeline corridor, poses safety concerns due to
characteristics of the occupants, development, or site.
Policy UT-115: New or expanded structures and other significant land
disturbance shall be setback from hazardous liquid pipelines to minimize the
likelihood of accidental damage to the pipelines. Required setbacks shall not
deny all reasonable economic use of property.
Policy UT-117: Locating new high consequence land uses near a hazardous
liquid pipeline corridor represents an unusually high risk and shall not be
allowed. Proposed expansions to high consequence land uses located near
pipeline corridors shall at a minimum be designed to avoid increasing the level
of risk in the event of a pipeline failure, and where feasible, reduce the risk.
Policy UT-118: Commercial, industrial, multi-family or other development
which, because of proximity to a hazardous liquid pipeline corridor, poses
safety concerns due to characteristics of the occupants, development or site,
shall use appropriate mitigation measures to help reduce adverse impacts in
the event of a pipeline failure.
* The Section column indicates the element/chapter of the comprehensive plan where the goal or policy text was found. The Topic column indicates the subject
matter that is covered by the goal or policy text.
January 2016 APPENDIX F
POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES F-53
PHASE 1 DRAFT EIS
Table F-11. Renton Planning Goals and Policies
Renton Planning
Document Section* Topic* Goal or Policy and Text
City of Renton
Comprehensive Plan
2015
Land Use Views and
Aesthetics
Goal L-BB: Maintain a high quality of life as Renton grows by ensuring that
new development is designed to be functional and attractive.
Goal L-FF: Strengthen the visual identity of Renton and its Community
Planning Areas and neighborhoods through quality design and development.
Policy L-48: Accommodate change within the Renton community in a way that
maintains Renton’s livability and natural beauty.
Policy L-55: Protect public scenic views and public view corridors, including
Renton’s physical, visual and perceptual linkages to Lake Washington and the
Cedar River.
Policy L-56: Preserve natural landforms, vegetation, distinctive stands of
trees, natural slopes, and scenic areas that contribute to the City’s identity,
preserve property values, and visually define the community and
neighborhoods.
Policy L-60: Thoughtfully balance the need for appropriate lighting levels for
safety and security to avoid light intrusion and glare impacts, and to preserve
the night sky.
Essential Public
Facilities
Policy L-6: Site and design essential public facilities to be efficient and
convenient while minimizing impacts on surrounding uses. Facilities should be
sited on an arterial street, where there is good access to transportation,
including transit service, location, and where parking requirements are
appropriate to the use. If the use is people intensive, it should be in a Center,
compatible with surrounding uses, and co-located with other uses when
possible.
Land Use Policy L-7: Coordinate with King County to ensure consistent land
development policies in the Potential Annexation Area.
GHG Emissions Policy L-44: Support and implement the Mayor’s Climate Protection
Agreement, climate pledges and commitments undertaken by the City, and
other multi-jurisdictional efforts to reduce greenhouse gases, address climate
change, sea-level rise, ocean acidification, and other impacts to global
conditions.
APPENDIX F January 2016 F-54 POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES
PHASE 1 DRAFT EIS
Renton Planning
Document Section* Topic* Goal or Policy and Text
Housing and
Human
Services
Element
Health and
Safety
Policy CF-7: Protect public health, enhance environmental quality and
promote conservation of man-made and natural resources through appropriate
design and installation of public facilities.
Goal HHS-A: Adopt best available housing practices and implement
innovative techniques to advance the provision of affordable, fair, healthy, and
safe housing for renters, homeowners, and the homeless. Adopt a strategic
housing plan tailored to achieve this goal.
Goal HHS-H: Actively work to increase the availability of healthy, equitable
and affordable housing for people in all demographic groups and at all income
levels and promote a balance of housing and the amenities needed by
residents at the neighborhood level, such as childcare, availability of fresh
food, recreational opportunities, and medical care.
Policy HHS-21: Support the development of housing and neighborhoods that
are sited, designed, constructed, and maintained to promote environmentally
healthy and safe living. “Environmental health,” in this context, includes factors
of the natural and built environment that affect human health, such as physical,
chemical, and biological factors external to a person.
Policy U-2: Promote the health and safety of Renton citizens from
environmental hazards associated with utility systems through the proper
design and siting of utility facilities.
Shoreline
Management
Program
Shoreline
Management
SHORELINE MANAGEMENT GOALS
The City adopts the goals and principles of the Shoreline Management Act as
provided in RCW 90.58.020 and as particularly relevant to Renton.
1. The shoreline jurisdiction is one of the most valuable and fragile of the
City’s natural resources. There is appropriate concern throughout the
watershed and the greater Puget Sound Region relating to the
utilization, protection, restoration, and preservation of the shoreline
jurisdiction.
2. Ever increasing pressures of additional use are being placed on the
shoreline jurisdiction, which in turn necessitates increased coordination
in its management and development.
3. Much of the shoreline jurisdiction and the uplands adjacent thereto are
in private ownership. Unrestricted construction on the privately owned
January 2016 APPENDIX F
POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES F-55
PHASE 1 DRAFT EIS
Renton Planning
Document Section* Topic* Goal or Policy and Text
or publicly owned shorelines is not in the best public interest; therefore,
coordinated planning is necessary in order to protect the public interest
associated with the shoreline jurisdiction while recognizing and
protecting private property rights consistent with the public interest.
4. There is a clear and urgent demand for a planned, rational, and
concerted effort, jointly performed by federal, state, and local
governments, to prevent the inherent harm in an uncoordinated and
piecemeal development of the City’s shoreline jurisdiction.
5. It is the intent of the City to provide for the management of the shoreline
jurisdiction by planning for and fostering all reasonable and appropriate
uses. The Shoreline Master Program is designed to ensure the
development in a manner that, while allowing for limited reduction of
rights of the public in the navigable waters, will promote and enhance
the public interest.
6. The City’s shoreline policies are intended to protect against adverse
effects to the public health, the land and its vegetation and wildlife, and
the waters of the state and their aquatic life, while protecting generally
public rights of navigation and corollary rights incidental thereto.
7. In the implementation of the Shoreline Master Program, the public's
opportunity to enjoy the physical and aesthetic qualities of natural
shorelines shall be preserved to the greatest extent feasible consistent
with the overall best interest of the state, the county, and the people
generally. To this end, uses shall be preferred which are consistent with
control of pollution and prevention of damage to the natural
environment or are unique to or dependent upon use of the state's
shoreline.
8. Alterations of the natural condition of the shoreline, in those limited
instances when authorized, shall be given priority for single family
residences and their appurtenant structures; ports; shoreline
recreational uses including but not limited to parks, marinas, piers, and
other improvements facilitating public access to shorelines; industrial
and commercial developments that are particularly dependent on their
location on or use of the shoreline jurisdiction; and other development
that will provide an opportunity for substantial numbers of the people to
enjoy the shorelines.
APPENDIX F January 2016 F-56 POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES
PHASE 1 DRAFT EIS
Renton Planning
Document Section* Topic* Goal or Policy and Text
9. Permitted uses in the shorelines zone shall be designed and conducted
in a manner to minimize, insofar as practical, any resultant damage to
the ecology and environment of the shoreline jurisdiction and any
interference with the public's use of the water.
Objective SH-A: Provide for use of the limited water resource consistent with
the goals of the Shoreline Management Act by providing a preference for
water-oriented uses.
Objective SH-B: Provide that the policies, regulations, and administration of
the Shoreline Master Program ensure that new uses, development, and
redevelopment within the shoreline jurisdiction do not cause a net loss of
shoreline ecological functions.
Objective SH-D: The resources and amenities of all shorelines and the
ecological processes and functions they provide, such as wetlands, upland
and aquatic vegetation, fish and wildlife species and habitats, as well as scenic
vistas and aesthetics should be protected and preserved for use and
enjoyment by present and future generations. Natural shorelines are dynamic
with interdependent geologic and biological relationships. Alteration of this
dynamic system has substantial adverse impacts on geologic and hydraulic
mechanisms important to the function of the water body and can disrupt
elements of the food chain.
Policy SH-1: Reasonable and appropriate shoreline uses and activities should
be planned for:
1. Short-term economic gain or convenience in development should be
evaluated in relationship to potential long-term effects on the shoreline.
2. Preference should be given to those uses or activities which enhance
the natural functions of shorelines, including reserving appropriate areas
for protecting and restoring ecological functions to control pollution and
prevent damage to the natural environment and public health.
3. Provide for the following priority in shoreline use and modification of the
shoreline:
a. Water-dependent and associated water related uses are the
highest priority for shorelines unless protection of the existing
natural resource values of such areas precludes such uses.
b. Water-related and water-enjoyment uses that are compatible with
January 2016 APPENDIX F
POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES F-57
PHASE 1 DRAFT EIS
Renton Planning
Document Section* Topic* Goal or Policy and Text
ecological protection and restoration objectives, provided that
adequate area is reserved for future water-dependent and water-
related uses.
c. Multiple use developments may be allowed if they include and
support water-oriented uses and contribute to the objectives of
the act including ecological protection and restoration and/or
public access.
d. Limit non-water-oriented uses to those locations where access to
the water is not provided or where the non-water-oriented uses
contribute to the objectives of the Act, including ecological
protection and restoration and/or public access.
e. Preserve navigational qualities, and the infrastructure that
supports navigation, to support water-oriented use.
4. Recognize existing single-family residential uses and neighborhood
character and ensure that existing uses, new uses, and alteration of
facilities:
a. Do not result in a net loss of shoreline ecological functions.
b. Avoid disturbance of unique and fragile areas.
c. Are provided with adequate public services including water,
sanitary sewer, and stormwater management.
5. Future shoreline subdivision, multi-family developments, and planned
urban developments of more than four units should provide public
benefits, including ecological protection and restoration, and/or public
or community access.
6. New residential developments should provide open space areas at or
near the shoreline through clustering of dwellings.
Policy SH-2: Aesthetic considerations should be integrated with new
development, redevelopment of existing facilities, or for general enhancement
of shoreline areas and should include:
1. Identification and preservation of areas with scenic vistas and areas
where the shoreline has high aesthetic value as seen from both upland
areas, areas across the water, and recreational and other uses on the
water.
2. Appropriate regulations and criteria should ensure that development
provides designs that contribute to the aesthetic enjoyment of the
APPENDIX F January 2016 F-58 POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES
PHASE 1 DRAFT EIS
Renton Planning
Document Section* Topic* Goal or Policy and Text
shoreline for a substantial number of people and provide the public with
the ability to reach, touch, and enjoy the water’s edge and view the
water and shoreline.
3. Regulations and criteria for building siting, maximum height, setbacks,
screening, architectural controls, sign regulations, designation of view
corridors, and other provisions should ensure that development
minimizes adverse impacts on views of the water from public property
or views enjoyed by a substantial number of residences.
Policy SH-3: All shoreline policies, regulations, and development shall
recognize and protect private rights consistent with the public interest and, to
the extent feasible, shall be designed and constructed to protect the rights and
privacy of adjacent property owners. Shoreline uses and activities should be
discouraged if they would cause significant noise or odor or unsafe conditions
that would impede the achievement of shoreline use preferences on the site or
on adjacent or abutting sites.
Policy SH-4: When necessary, Shoreline modifications should emulate and
allow natural shoreline functions to the extent feasible and where needed
utilize bioengineering or other methods with the least impact on ecological
functions.
Policy SH-5: Native shoreline vegetation should be conserved to maintain
shoreline ecological functions and mitigate the direct, indirect and/or
cumulative impacts of shoreline development, wherever feasible.
Policy SH-6: Existing natural resources should be conserved through
regulatory and non-regulatory means that may include regulation of
development within the shoreline jurisdiction, ecologically sound design, and
restoration programs, including:
1. Water quality and water flow should be maintained at a level to permit
recreational use, to provide a suitable habitat for desirable forms of
aquatic life, and to satisfy other required human needs.
2. Aquatic habitats and spawning grounds should be protected, improved
and, when feasible, increased to the fullest extent possible to ensure
the likelihood of salmon recovery for listed salmon stocks and to
increase the populations of non-listed salmon stocks.
January 2016 APPENDIX F
POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES F-59
PHASE 1 DRAFT EIS
Renton Planning
Document Section* Topic* Goal or Policy and Text
3. Wildlife habitats should be protected, improved and, if feasible,
increased.
4. Unique natural areas should be designated and maintained as open
space for passive forms of recreation and provide opportunities for
education and interpretation. Access and use should be restricted, if
necessary, for the conservation of these areas.
Policy SH-10: Shoreline areas having historical, cultural, educational, or
scientific value should be identified and protected.
Policy SH-14:
2. New over-water structures should be limited to water-dependent use
and the length, width, and height of over-water structures should be
limited to the smallest reasonable dimensions.
3. Shoreline developments should be designed to maintain or enhance
aesthetic values and scenic views.
Policy SH-16: Future economic uses and activities should utilize the shoreline
to achieve the use and other goals of the Act and The Shoreline Master
Program, including:
1. Economic uses and activities should locate the water-oriented portion
of their development along the shoreline.
2. New over-water structures should be limited to water-dependent use
and the length, width, and height of over-water structures should be
limited to the smallest reasonable dimensions.
3. Shoreline developments should be designed to maintain or enhance
aesthetic values and scenic views.
Utilities
Utility Corridors/
Facilities
GOAL U-O: Promote the availability of safe, adequate, and efficient electrical
service within the City and its planning area, consistent with the regulatory
obligation of the utility to serve customers.
Goal U-P: Promote the safe transport and delivery of natural gas and other
fuels with the planning area.
APPENDIX F January 2016 F-60 POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES
PHASE 1 DRAFT EIS
Renton Planning
Document Section* Topic* Goal or Policy and Text
Policy U-3: Promote the co-location of new utility infrastructure within rights-
of-way and utility corridors and coordinate construction and replacement of
utility systems with other public infrastructure projects to minimize
construction-related costs and disruptions.
Policy U-72: Coordinate with local and regional electricity providers to ensure
the siting and location of transmission and distribution facilities is
accomplished in a manner that minimizes adverse impacts on the environment
and adjacent land uses.
Policy U-73: Encourage electricity purveyors to make facility improvements
and additions within existing utility corridors wherever possible.
Policy U-74: Require underground electricity infrastructure installation to be
coordinated with the City of Renton Public Works Department to prevent
cross-boring through existing water, sewer, or natural gas lines.
Policy U-75: Coordinate with local and regional purveyors of natural gas for
the siting of transmission and distribution infrastructure within the Renton
Planning Area.
Policy U-77: Allow extension of natural gas distribution infrastructure within
the Renton Planning Area, provided such facilities are consistent with
development assumptions in the Land Use Element of the Comprehensive
Plan.
Health and
Safety
Policy U-78: Require underground natural gas infrastructure installation to be
coordinated with the City of Renton Public Works Department to prevent
cross-boring through existing utility lines.
* The Section column indicates the element/chapter of the comprehensive plan where the goal or policy text was found. The Topic column indicates the subject
matter that is covered by the goal or policy text.
January 2016 APPENDIX F
POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES F-61
PHASE 1 DRAFT EIS
Table F-12. Sammamish Planning Goals and Policies
Sammamish
Planning Document Section* Topic* Goal or Policy and Text
City of Sammamish
Comprehensive Plan
(Draft)
2015
Environmental
Element
Land Use Policy EC.1.4: Consider identifying and protecting where appropriate the
following special areas:
a. Natural areas including significant trees,
b. Scenic areas such as designated view corridors,
c. Natural drainage areas, including the Erosion Hazard Near Sensitive
Water Bodies and Wetland Management Areas designated locations
and the those areas draining to Erosion
d. Hazard Near Sensitive Water Bodies and Wetland Management Areas,
e. Urban landscaped areas such as public or private golf courses and
parks,
f. Land reserved as open space or buffers tracts as part of development,
including parcels subject to density averaging, where appropriate, and
g. Lands designated as open space under the Current Use taxation-open
space established according to King County for tax assessment
purposes.
Policy EC.1.21: Encourage the preservation of open space through incentives,
such as the King County Public Benefit Rating System (PBRS) or other
programs to encourage land donation.
Policy EC.1.23: Establish a system of publicly owned natural areas to:
a. Protect the integrity of wildlife habitat and conservation sites,
b. Protect corridors between natural areas, where feasible
c. Preserve outstanding examples of Sammamish’s diverse natural
heritage, and
d. Provide a broad range of opportunities for educational, interpretive and
recreational programs to meet community needs, and.
e. Facilitate completion of the vision of an Emerald Necklace, an
approximately 28-mile nonmotorized greenbelt encircling the Plateau.
Alternative
Energy/New
Technology
Policy EC.7.3:
Goal: Be a regional model in mitigating and adapting to climate change.
Policy: Consider a multi-pronged approach to climate change mitigation,
including support for energy efficiency, vehicle trip reduction, and
environmental protection.
APPENDIX F January 2016 F-62 POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES
PHASE 1 DRAFT EIS
Sammamish
Planning Document Section* Topic* Goal or Policy and Text
Housing
Element
Views and
Aesthetics
Goal H.1:
Neighborhood Vitality and Character
Promote safe, attractive, and vibrant residential and mixed-use
neighborhoods. Encourage housing design that is sensitive to quality, design,
and intensity within neighborhoods and with surrounding land uses. Land use
policies and regulations should emphasize compatibility with existing
neighborhood character. In areas where the existing character is in transition,
new development should be designed to incorporate the qualities of well-
designed neighborhoods.
Policy H.1.1: Ensure that new development and redevelopment are sensitive
to the context of existing and planned neighborhood character.
Land Use
Element
Land Use
Policy LU.2.2: Promote complementary and compatible development and
smooth transitions between differing land uses.
Residential Districts
The residential districts implement Comprehensive Plan policies for housing
quality, diversity (such as townhomes, cottage housing, apartments, duplex,
and single-family detached), and affordability, and efficient use of land, public
services, and energy. The R-1 district should be applied in areas with, or in
proximity to, lands with area-wide environmental constraints, wildlife corridors,
or in established neighborhoods of the same density. In the R-1 district, the
primary uses are single detached dwellings clustered as appropriate in relation
to environmental constraints. The R-4 through R-8 districts, provide for
predominantly single detached dwelling units at varying densities. The R-12
through R-18 districts allow for a mix of multifamily development at a variety of
densities. Minimum residential densities should be met in the R-8, R-12, R-18,
TC-A, and TC-B districts. In all residential districts, accessory uses and
complementary nonresidential uses may be allowed.
Neighborhood Business
The Neighborhood Business District provides small scale convenient daily
retail and personal services for a limited service area, minimizes the impacts of
commercial activities on nearby properties, and provides for limited residential
development not to exceed R-8 density.
January 2016 APPENDIX F
POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES F-63
PHASE 1 DRAFT EIS
Sammamish
Planning Document Section* Topic* Goal or Policy and Text
Community Business
The Community Business District provide convenience and comparison retail
and personal services for local service areas serving neighborhoods that
cannot be served conveniently by larger commercial centers. Compared to the
Neighborhood Business District, a wider range of uses are permitted, including
small-scale office and mixed-use developments.
Office
The Office District provides for pedestrian and transit-oriented, high-density
employment office uses together with the potential for complementary retail
and urban density residential development in certain locations.
Town Center
The Town Center designations create a focused mixed-use center for the City,
provide opportunity for a variety of housing types and retail and office uses;
provide for a comprehensive system of parks, open spaces and trails;
establish an efficient circulation system; provide community and civic facilities;
establish a distinctive design character; and promote sustainability, including
an integrated stormwater management system. The planned development
pattern encourages the most intensive development in core mixed use
development areas.
Designations within Town Center include the following:
• Town Center A—Commercial focus
• Town Center B—Residential focus
• Town Center C—Lower intensity residential
• Town Center D—Civic campus
• Town Center E—Reserve
The Town Center subarea plan and implementing development regulations
provide additional guidance for town center development.
Public Institution
This classification recognizes publicly owned facilities and sites that offer
governmental, utility, recreational, educational, and emergency response
services, respectively, to the community.
APPENDIX F January 2016 F-64 POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES
PHASE 1 DRAFT EIS
Sammamish
Planning Document Section* Topic* Goal or Policy and Text
Views and
Aesthetics
Policy LU.2.3: Recognize and preserve the natural environment as an
important element of the City’s identity.
Policy LU.2.4: Where appropriate, develop design guidelines and development
regulations to support the following:
a. Compatibility with natural site features
b. Retention of trees and native vegetation
c. Low impact development
d. Development at a scale and character appropriate to the site
e. Design that supports the human scale
f. Design that reflects community character
g. Landscaping to enhance building and site appearance and function
h. Integrated and connected access for bicycles, pedestrians and vehicles
i. Balanced consideration of automobile and pedestrian/bicycle mobility
and safety
j. Usable passive and active open space, including community gathering
places
k. Cohesive design character that minimizes visual clutter
l. Sense of personal safety
Goal LU.3: Preserve and enhance the natural features, quality, character and
function of the City’s residential neighborhoods.
Policy LU.3.4: Consider establishing a program to acquire property for public
purposes consistent with the policies of this comprehensive plan. This
evaluation should include consideration of the feasibility of both fee simple
acquisition and the acquisition of development rights, as well as identification
of potential funding sources, grants, and gifting strategies. Priorities for
acquisition may include: protection of environmentally sensitive areas,
preservation of view corridors, preservation of parcels that convey a unique
sense of the community’s character or historical tradition, parcels to provide
breaks in development patterns along designated arterials, passive and active
recreation opportunities.
Goal LU.5: Ensure that public facilities support and strengthen community
character.
January 2016 APPENDIX F
POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES F-65
PHASE 1 DRAFT EIS
Sammamish
Planning Document Section* Topic* Goal or Policy and Text
Goal LU.6: Promote development design that maintains a harmonious
relationship with the natural environment.
Vegetation Policy LU.6.2: Maximize tree retention and assure restoration where tree
retention is not feasible.
Alternative
Energy/New
Technology
Goal LU.9: Encourage sustainable development.
Policy LU.9.1: Identify and adopt zoning code amendments to allow
distributed energy generation (solar, wind, etc.) compatible with surrounding
uses and adopt incentives that promote distributed generation.
Utilities
Element
Introduction Goal UT.1: Promote and encourage development and maintenance of all
utilities at levels of service adequate to accommodate existing and projected
growth.
Utility Corridors/
Facilities
UT.1.1: Support the timely expansion, maintenance, operation, and
replacement of utility infrastructure in order to meet anticipated demand for
growth identified in the Land Use Element.
UT.1.2: Utilize franchise agreements with private utility providers and interlocal
agreements with public utility providers as a means to protect and advance
adopted City goals and policies.
Goal UT 2: Support coordination with service providers to minimize cost and
service disruption
UT 2.1: Coordinate the timing of construction activities with public and private
utilities to minimize disruption to the public and reduce costs of utility delivery
UT 2.2: Promote co-location of new public and private utility distribution
facilities in shared trenches.
UT.3.1: Promote the undergrounding of utilities where physically and
financially feasible and in coordination with local utilities.
Goal UT.4: Facilitate citywide utility services that are consistent, reliable,
equitable, competitive, and financially sustainable.
Utilities Policy UT.4.1: Coordinate with utility providers to ensure that services are
provided at competitive rates citywide.
APPENDIX F January 2016 F-66 POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES
PHASE 1 DRAFT EIS
Sammamish
Planning Document Section* Topic* Goal or Policy and Text
Views and
Aesthetics
Goal UT.3: Encourage placement, siting and design of utilities to support
community character and promote uninterrupted service.
Policy UT.3.2: Encourage aesthetically compatible design of above-ground
utility facilities
Policy UT.3.3: Minimize the visual impacts of telecommunications facilities
and towers in the community.
Parks and
Recreation
Policy UT.3.4: Promote recreational use of utility corridors, such as trails,
sports courts, or similar facilities.
Alternative
Energy/New
Technology
Policy UT.4.2: Seek to maximize effectiveness and efficiency of utility services
provided to Sammamish residents.
Goal UT.5: Encourage the use of innovative measures and new technologies
to reduce overall demand and enhance service to city residents.
Policy UT.5.1: Encourage opportunities for individual businesses or
homeowners to become more energy independent by reducing energy use
and/or generating a portion of their energy needs on site.
Policy UT.5.2: Remove barriers in the city codes to the use of alternative
energy sources for homes and businesses, including such technologies as
solar panels, wind-powered turbines, biomass/biogas, and fuel cells.
Policy UT.5.3: Support renewable energy production by encouraging
businesses and homeowners to consider purchase of green power through
programs such as Puget Sound Energy's Green Power Program.
Shoreline
Element
Utility Corridors/
Facilities
a. New public or private utilities should be located inland from the
land/water interface, preferably outside of shoreline jurisdiction, unless:
They have a water-dependent component such as a water intake or
outfall; or Water crossings are unavoidable; or Other locations are
infeasible; or They are required for authorized shoreline uses consistent
with this Program.
b. Utilities should be located and designed to avoid public recreation and
public access areas and significant natural, historic, archaeological or
cultural resources.
c. Development of pipelines and cables, particularly those running roughly
parallel to the shoreline, and development of facilities that may require
January 2016 APPENDIX F
POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES F-67
PHASE 1 DRAFT EIS
Sammamish
Planning Document Section* Topic* Goal or Policy and Text
periodic maintenance that would disrupt shoreline ecological functions,
should be discouraged except where no other reasonable alternative
exists.
d. When existing utilities located within shoreline jurisdiction require
maintenance or other improvements to address public health and
safety, the maintenance/improvement should be designed and
implemented to minimize additional impacts on the shoreline
environment and consideration should be given to correcting past
impacts caused by the utility.
e. Public utility development should use low impact development
stormwater management techniques and other methods that protect,
enhance, and restore shoreline ecological functions where reasonable.
f. When new utilities are to be located within shoreline jurisdiction, they
should be installed in such a manner to achieve no net loss of
ecological function. City of Sammamish Shoreline Master Program
City of Sammamish
Shoreline Master
Program Update
2011
25.03.020
Conservation
Goals
Views and
Aesthetics
The following goals address the preservation of natural resources, scenic
vistas, aesthetics, and vital shoreline areas for fisheries and wildlife and for the
benefit of present and future generations.
• Acquire (i.e., through purchase, easements, donation or other
agreement), and maintain as open space, shorelines with unique or
valuable natural attributes for public benefit.
• Preserve, enhance and/or protect shoreline resources (i.e., wetlands
and other fish /wildlife habitats) for their ecological functions and values,
and aesthetic and scenic qualities.
• Maintain natural dynamic processes of shoreline formation and
sustainability through effective stewardship, management, and use of
shorelines
• Where feasible, enhance or restore areas that are biologically and/or
aesthetically degraded while maintaining appropriate use of the
shoreline.
• Maintain or enhance shoreline vegetation to protect water quality, fish
and wildlife habitat, and other ecological functions and processes.
• Implement policies that can help reverse impacts caused by existing or
past development activities that adversely affect ecological or shoreline
functions such as untreated stormwater discharges.
APPENDIX F January 2016 F-68 POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES
PHASE 1 DRAFT EIS
Sammamish
Planning Document Section* Topic* Goal or Policy and Text
• Manage the City’s programs, services, and operational infrastructure in
a manner that achieves no net loss of ecological or shoreline functions.
• Achieve no net loss of ecological functions of Sammamish shorelines
25.03.030
Public Access
Goals
Utility Corridors/
Facilities
Ensure that public utility and transportation rights-of-way, including street
ends that abut the shoreline, are made available for public access and use
where appropriate (see RCW 35.79.035).
25.03.070
Transportation
and Public
Facility Goals
Utility Corridors/
Facilities
The following goals address the general location and extent of existing and
proposed thoroughfares, transportation/circulation routes, as well as other
public utilities and facilities.
1. Develop efficient circulation systems in harmony with the topography
and other natural characteristics of the shoreline and in a manner that
assures the safe movement of people and goods while minimizing
adverse effects on shoreline use and development or on shoreline
ecological functions and processes.
2. Provide and/or enhance physical and visual public access to shorelines
along public roads (i.e. turnouts and viewpoints) in accordance with the
public access goals.
3. Limit circulation systems in the shoreline jurisdiction to those that serve
permitted and/or preferred shoreline uses.
4. Limit transportation infrastructure in shoreline jurisdiction to the
minimum necessary to accomplish its purpose.
25.04.040
Recreational
Use Policies
Parks and
Recreation
(3) Public recreational development should be located where existing
infrastructure (utilities and roads) is adequate, or may be provided without
significant damage to shoreline features commensurate with the number and
concentration of anticipated users.
25.04.060
Utility Use
Policies
Utility Corridors/
Facilities
1. New public or private utilities should be located inland from the
land/water interface, preferably outside of shoreline jurisdiction, unless:
a. They have a water-dependent component such as a water intake
or outfall; or
b. Water crossings are unavoidable; or
c. Other locations are infeasible; or
d. They are required for authorized shoreline uses consistent with
this Program.
January 2016 APPENDIX F
POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES F-69
PHASE 1 DRAFT EIS
Sammamish
Planning Document Section* Topic* Goal or Policy and Text
2. Utilities should be located and designed to avoid public recreation and
public access areas and significant natural, historic, archaeological or
cultural resources.
3. Development of pipelines and cables, particularly those running roughly
parallel to the shoreline, and development of facilities that may require
periodic maintenance that would disrupt shoreline ecological functions,
should be discouraged except where no other reasonable alternative
exists.
4. When existing utilities located within shoreline jurisdiction require
maintenance or other improvements to address public health and
safety, the maintenance/improvement should be designed and
implemented to minimize additional impacts on the shoreline
environment and consideration should be given to correcting past
impacts caused by the utility.
5. Public utility development should use low impact development
stormwater management techniques and other methods that protect,
enhance, and restore shoreline ecological functions where reasonable.
When new utilities are to be located within shoreline jurisdiction, they
should be installed in such a manner to achieve no net loss of
ecological function.
25.07.010
Summary of
Uses, Approval
Criteria, and
Process
Land Use Utilities are permitted in the Lake Sammamish Shoreline Residential, Lake
Sammamish Urban Conservancy, Pine and Beaver Lakes Shoreline
Residential, Pine and Beaver Lakes Urban Conservancy.
Archaeological,
Historic and
Cultural
Resources
Policies
Shoreline
Management
Shoreline use and development should not significantly and negatively impact,
destroy, or damage any site having historic, cultural, scientific or educational
value.
Critical Areas
and
Environmental
Protection
Shoreline
Management
New shoreline uses and developments should occur in a manner that
maintains existing natural shorelines, assures no net loss of shoreline
ecological functions and processes and protects critical areas and associated
buffers within the shoreline jurisdiction as designated in SMC 21A.50.
APPENDIX F January 2016 F-70 POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES
PHASE 1 DRAFT EIS
Sammamish
Planning Document Section* Topic* Goal or Policy and Text
Policies New shoreline uses and developments should be designed and conducted in
accordance with the regulations of this Program to avoid, minimize and
mitigate damage to the ecology and environment. These regulations are
designed to protect shoreline ecological functions and processes. Shoreline
ecological functions that should be protected include, but are not limited to,
fish and wildlife habitat, conservation and recovery of threatened or
endangered species, food chain support and water temperature maintenance.
Shoreline processes that should be protected include, but are not limited to,
water flow; infiltration; groundwater recharge and discharge; sediment delivery,
transport, and storage; organic matter input; and nutrient and pathogen
removal.
Dredging
Policies
Shoreline
Management
New development should be sited and designed to avoid the need for
maintenance dredging.
When allowed, dredging should be planned and operated to minimize adverse
impacts to shoreline ecology, to existing shoreline uses, and to minimize
interference with navigation.
Flood Hazard
Reduction
Policies
Shoreline
Management
New development within the floodplains associated with the City’s shorelines
that would individually or cumulatively increase the risk of flood damage
should be discouraged.
Shoreline Use
Policies
Shoreline
Management
The following uses/developments should be given preference consistent with
the priority listed below for locating within the shoreline jurisdiction when they
are consistent with City zoning regulations and located, designed, and
maintained in a manner that is consistent with this Program:
i. Water-dependent and water-related use/development; and
ii. Public uses and developments that provide physical and/or visual
access to the shoreline for substantial numbers of people, and
iii. Single-family residences developed consistent with the policies of
25.04.030(1).
Non-water-oriented uses/developments should be limited to those shoreline
locations where water-oriented uses are inappropriate.
Non-water-oriented uses/developments should be allowed only when they
demonstrably contribute to the objectives of the Shoreline Management Act.
January 2016 APPENDIX F
POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES F-71
PHASE 1 DRAFT EIS
Sammamish
Planning Document Section* Topic* Goal or Policy and Text
Site Planning
Policies
Shoreline
Management
New shoreline uses and developments should be designed in a manner that
directs land alteration to the least sensitive portions of the site to maximize
vegetation conservation; minimize impervious surfaces and runoff; protect
riparian, nearshore and wetland habitats; protect fish and wildlife and their
habitats; protect archaeological, historic and cultural resources; and preserve
aesthetic values.
New shoreline uses and developments should not deprive other uses and
users of reasonable access to navigable waters and/or restrict access of treaty
tribes to their “usual and accustomed” areas.
Views and
Aesthetics
Policies
Views and
Aesthetics
New shoreline uses and developments should be encouraged to minimize
obstructions of the public’s visual access to the water and shoreline from
public lands, rights-of way and other public property.
New shoreline uses and developments should not significantly detract from
shoreline scenic and aesthetic qualities that are derived from natural or cultural
features, vegetative cover and historic sites/structures.
Water Quality,
Stormwater
and Nonpoint
Pollution
Policies
Shoreline
Management
New shoreline uses and developments are encouraged to minimize impervious
surface and incorporate low impact development stormwater management
techniques where reasonable to minimize surface water runoff and prevent
water quality degradation.
*The Section column indicates the element/chapter of the comprehensive plan where the goal or policy text was found. The Topic column indicates the subject
matter that is covered by the goal or policy text.
APPENDIX F January 2016 F-72 POTENTIALLY APPLICABLE COMPREHENSIVE PLAN AND SHORELINE MASTER PROGRAM GOALS AND POLICIES
PHASE 1 DRAFT EIS
APPENDIX G. APPLICABLE POLICIES AND
CODE REQUIREMENTS FOR VIEWS AND
VISUAL RESOURCES
Table G-1. Planning Policies
Plans Protected Views and Visual
Resources Guidance for Reducing Visual Impacts
King County
King County Comprehensive Plan
2013 Update (including the King
County SMP)
Shorelines (Plan Policy S-313) N/A
Parks, trails and other open spaces in
the Rural Area (Plan Policy P-109)
N/A
King County Municipal Code
(KCMC)
Current through April 15, 2015
The Code does not include any policies or regulations that guide development of new utilities to reduce
impacts to views or visual resources.
Beaux Arts Village
Town of Beaux Arts Village 2015-
2035 Comprehensive Plan (2015)
Residential Character N/A
Beaux Arts Village Municipal Code
(BAVC)
Current through April 9, 2013
The Code does not include any policies or regulations that guide development of new utilities to reduce
impacts to views or visual resources.
Beaux Arts Village SMP 2014 Shorelines Utilities prohibited in the urban conservancy, shoreline
residential, and aquatic shoreline areas.
All development on navigable water should consider impacts
to public views
Bellevue
Bellevue Comprehensive Plan
2015
Views of water, mountains, and skylines
from public places (Plan Policy UD-23)
N/A
N/A Requires utility equipment and support facilities be
aesthetically compatible with surrounding area (Plan Policy
UD-53).
January 2016 APPENDIX G
APPLICABLE PLANS AND POLICIES FOR VIEWS AND VISUAL RESOURCES G-1
PHASE 1 DRAFT EIS
Plans Protected Views and Visual
Resources Guidance for Reducing Visual Impacts
N/A Consolidate utility facilities and co-locate multiple utilities
(Plan Policy UT-43).
N/A States preference for use of new technology to reduce visual
impacts.
Green belts and open spaces per Parks
and Open Space System Plan
Avoid locating overhead lines in greenbelts or open spaces
(Plan Policy UT-45).
Factoria Boulevard (Plan Policy S-FA-32) N/A
Views of Richards Creek, Kelsey Creek,
and Mercer Slough (Plan Policy S-RV-
13)
N/A
Pathways and access points with views
of Sunset Creek, Richards Creek, Coal
Creek, and Mercer Slough (Plan Policy
S-FA-18)
N/A
Unique open spaces, landmarks, and
viewpoints (Plan Policy S-RV-24.)
N/A
Single-family neighborhood views in
Eastgate (Plan Policy S-EG-20.)
N/A
Bellevue Community College (Plan
Policy S-EG-30.)
N/A
Bellevue City Code
Current through August 3, 2015
N/A Visual and aesthetic impacts associated with the EPF must
be mitigated to the greatest extent technically feasible (BCC
20.20.350C.5.b).
N/A Electrical utility facilities shall be sight-screened through
landscaping and fencing (BCC 20.20.255).
Bellevue SMP (In Progress) Shoreline Master Program is currently in progress.
APPENDIX G January 2016 G-2 APPLICABLE PLANS AND POLICIES FOR VIEWS AND VISUAL RESOURCES
PHASE 1 DRAFT EIS
Plans Protected Views and Visual
Resources Guidance for Reducing Visual Impacts
Clyde Hill
City of Clyde Hill 2015-2035
Comprehensive Plan
Lake Washington, the Seattle Skyline,
Maydenbauer Bay, Kirkland, and
downtown Bellevue
N/A
Clyde Hill Municipal Code (CHMC)
Current through June 9, 2015
The natural visual character of the city ,
including its views of Lake Washington,
the mountain ranges, treed areas, and
the Seattle skyline (CHMC 17.50.010)
N/A
Views and visual resources that create a
special character for the community and
support property values (CHMC
17.77.020)
N/A
Clyde Hill SMP (N/A) Clyde Hill does not have an SMP
Hunts Point
2014 Draft Comprehensive Plan
Update for the Town of Hunts
Point
Hunt Point’s wooded and sylvan
character
Tree Code regulates removal and replacement of significant
trees to soften visual impacts.
Hunts Point Municipal Code
(HPMC)
Current through April 13, 2015
View corridors of wetlands (HPMC
16.15.010)
N/A
Town of Hunts Point SMP 2015 Shorelines High voltage electric transmission lines are prohibited within
shoreline jurisdiction (Policy 6.12)
Issaquah
City of Issaquah Comprehensive
Plan 2015
Tree Canopy N/A
Hillside Views Integrate hillside views into site design as amenities and
protect them as environmental resources (LU Policy A12).
January 2016 APPENDIX G
APPLICABLE PLANS AND POLICIES FOR VIEWS AND VISUAL RESOURCES G-3
PHASE 1 DRAFT EIS
Plans Protected Views and Visual
Resources Guidance for Reducing Visual Impacts
N/A Integrate views and open space provided by riparian
corridors and wetlands into all developments, where
applicable (LU Policy E4).
N/A Encourage new trails and viewing points along Issaquah
Creek (LU Policy H4).
Views of Issaquah Alps, Mount Rainier,
and the Sammamish Plateau from public
spaces (LU Policy H9)
N/A
Hillside Minimize the view impact of hillside development from the
valley floor and other hillsides by strategically integrating the
architecture, siting and landscaping into the natural
environment (LU Policy H10).
Surrounding Land Uses Ensure utility provision is compatible with surrounding land
uses. Balance public concerns over utility infrastructure (such
as safety, price, and natural environment) with the
community's desire that utility and public service projects be
aesthetically compatible with surrounding land uses (U Policy
A2).
Parks and Open Space Preserve and enhance the beauty of the City of Issaquah
through the parks and open spaces that make up the City’s
park system (P Policy B5).
Landscapes and Vistas from Parks Promote retention and replication of the area's natural beauty
and ecology (mountains, plantings, water etc.), sounds and
vistas in the park system (P Policy B5.2).
Natural Open Space Areas, such as the
Forested Hillsides of the Issaquah Alps
(P Policy B5.4)
N/A
Open Space and Views Preserve open space and views in accordance with view
policies found in the Land Use Element (EV Policy D8).
APPENDIX G January 2016 G-4 APPLICABLE PLANS AND POLICIES FOR VIEWS AND VISUAL RESOURCES
PHASE 1 DRAFT EIS
Plans Protected Views and Visual
Resources Guidance for Reducing Visual Impacts
Surround Land Uses Provide opportunities for artists’ and design professionals’
involvement and review in early design phases of community
facilities, amenities and infrastructure in order to enhance the
aesthetics of these projects (C Policy C2).
Issaquah Municipal Code (IMC)
Current through April 20, 2015
N/A Fence height should be 8 feet tall or less. Preferred materials
for fences are listed, as well as exemptions for use of hedging
(IMC 18.07.120).
Shorelines Preference for underground utilities (IMC 18.07.480).
City of Issaquah SMP 2013 Public’s views of the water Shoreline uses and development should be designed and
maintained to minimize obstructions of the public’s views of
the water.
N/A Development in shoreline areas should consider the scale,
arrangement and modulation of site buildings and elements to
achieve a balance of open space and development.
Kirkland
Kirkland 2035 (2015) Public views of the City, surrounding
hillsides, Lake Washington, Seattle, the
Cascades, the Olympics, and view
corridors along Lake Washington’s
shoreline (Plan Policy CC-4.5).
Require siting analysis in the development review process for
new and expanded electrical transmission and substation
facilities to address land use and sensitive areas and provide
mitigation to minimize visual and environmental impacts
(Policy U-7.7).
Natural landforms, vegetation, and
scenic areas that contribute to the City’s
identity and visually define the
community (Plan Policy CC-4.6).
N/A
Public Spaces (Plan Policy CC-4.10) N/A
N/A Screen above ground equipment associated with electrical
distribution without hindering access as required by the
provider (Policy U-7.6).
January 2016 APPENDIX G
APPLICABLE PLANS AND POLICIES FOR VIEWS AND VISUAL RESOURCES G-5
PHASE 1 DRAFT EIS
Plans Protected Views and Visual
Resources Guidance for Reducing Visual Impacts
Kirkland Zoning Code (KZC)
Current through June 16, 2015
Shorelines Locate utility facilities outside of the shoreline. If required in
shoreline, place where it will not obstruct scenic views (KZC
83.240).
Utilities shall provide screening of facilities from the lake and
adjacent properties in a manner that is compatible with the
surrounding environment (KZC 83.240).
No permit shall be issued for any new or expanded or
structure more than 35 feet above average grade level that
will obstruct the view to the lake of a substantial number of
residences on or adjoining the shoreline, except where this
Chapter does not prohibit a height of more than 35 feet and
only when overriding considerations of the public interest will
be served (KZC 83.240).
Development within the shoreline areas located west of Lake
Washington Boulevard and Lake Street South shall include
public view corridors that provide the public with an
unobstructed view of the water. The intent of the corridor is to
provide an unobstructed view from the adjacent public right-
of-way to the lake and to the shoreline on the opposite side of
the lake (KZC 83.240).
Kirkland SMP (2010) Lake Washington Maximize public access, use, and visual access to the lake
within Carillon Point and the surrounding commercial area
(Policy SA-7.3).
Enhance the physical and visual linkages to Lake Washington
in the Juanita Business District (Policy SA-7.4).
Shorelines
Provide a high quality shoreline environment where the public
enjoys access to and views of the lake (Goal SA-1)
Locate utility facilities and corridors to protect scenic views
and prevent impacts to the aesthetic qualities of the shoreline
(Policy SA-25.4).
APPENDIX G January 2016 G-6 APPLICABLE PLANS AND POLICIES FOR VIEWS AND VISUAL RESOURCES
PHASE 1 DRAFT EIS
Plans Protected Views and Visual
Resources Guidance for Reducing Visual Impacts
Require new development or redevelopment to include
establishment or preservation of appropriate shoreline
vegetation. Proper plant selection and design should be done
to ensure that views are not diminished (Policy SA-3.3).
Minimize tree clearing and thinning activities along the
shoreline and require mitigation for trees that are removed
(Policy SA-16.2).
Locate utility facilities and corridors to protect scenic views
and prevent impacts to the aesthetic qualities of the shoreline
(Policy SA-25.4).
Public View Corridors Preserve public view corridors along the City’s street
networks and public parks (Policy SA-26.1).
Locate and design new development to provide view
corridors of Lake Washington from Lake Washington
Boulevard and Lake Street South south of the Central
Business District (Policy SA-26.2).
Medina
City of Medina Comprehensive
Plan (2015)
Views from parks and open spaces (Plan
Policy PO-P3)
N/A
The Country Club and Golf Course N/A
Large tracts of public and private open
space that can be viewed from
residential lots and City streets
N/A
Views of Seattle, Mercer island, and
Mount Rainer from the Medina Beach
Property
N/A
Lake and territorial views from
residences
N/A
January 2016 APPENDIX G
APPLICABLE PLANS AND POLICIES FOR VIEWS AND VISUAL RESOURCES G-7
PHASE 1 DRAFT EIS
Plans Protected Views and Visual
Resources Guidance for Reducing Visual Impacts
Medina Municipal Code (MMC)
Current through July 13, 2015
Views from adjoining properties and
streets
All electrical utilities should be housed in buildings and
structures that minimize visual impacts (MMC 20.32.040).
Views of a “significant number” of
nearby residential properties
Combine utility corridors and placing utility infrastructure
underground whenever feasible (MMC 20.64.060).
Shoreline Regional utility facilities involved in production, processing
and transmission must be located outside of the shoreline
jurisdiction “unless no other feasible option exists” (MMC
20.64.060).
City of Medina, Washington SMP
(2014)
Views of Lake Washington from public
parks (Plan Policy SM-P12.1)
N/A
Scenic views of a significant number of
nearby residential properties (Plan Policy
SM-P12.1)
Locate regional utility facilities outside of the shoreline
jurisdiction or in a manner that doesn’t obstruct residential
views (Plan Policy SM-P12.1).
Public’s visual access to shoreline areas
(Plan Policy SM-P12.4)
N/A
N/A Locate new utilities outside of the shoreline “unless no other
feasible location exists” If unavoidable, locate utility facilities
and corridors in manner that preserves that natural
landscape, minimizes conflict with neighboring land uses, and
minimizes impacts on the aesthetic qualities of the shoreline
(Plan Policy SM-P15.2).
N/A Place facilities underground whenever possible (Plan Policy
SM-P15.3).
N/A Promotes joint use of rights-of-way (Plan Policy SM-P15.5).
Visual access to the shoreline (SM-P5.1) N/A
Newcastle
Draft 2015 Update to the City of
Newcastle Comprehensive Plan
Existing neighborhood scale and
character (Plan Policy LU-G3)
N/A
APPENDIX G January 2016 G-8 APPLICABLE PLANS AND POLICIES FOR VIEWS AND VISUAL RESOURCES
PHASE 1 DRAFT EIS
Plans Protected Views and Visual
Resources Guidance for Reducing Visual Impacts
Natural features, such as stream
channels that contribute to the City’s
scenic beauty (Plan Policy LU-G8)
N/A
N/A Placement of utility lines in shared utility corridors and
recommends that aesthetics be considered during design and
maintenance (Plan Policy LU-P19).
N/A Promote co-location of major utility transmission facilities
(Plan Policy UT-P3).
N/A Limit disturbance to vegetation within major utility
transmission corridors (Plan Policy UT-P8).
N/A Require utility providers to design and construct overhead
transmission lines in a manner that is aesthetically compatible
with surrounding land uses (Plan Policy UT-P10).
N/A Require utility providers to minimize visual impacts of
transmission towers and overhead transmission lines on
adjacent land uses through careful siting and design (Plan
Policy UT-P14).
N/A Require new, modified, or replacement transmission
structures (such as lattice towers, monopoles, and the like) to
be designed to minimize aesthetic impacts appropriate to the
immediate surrounding area whenever practical (Plan Policy
UT-P16).
N/A Require utility providers to mitigate the loss of significant
trees from the construction of new or expanded transmission
facilities (Plan Policy UT-P19).
N/A Require reasonable landscape screening of site-specific
above-ground utility facilities in order to diminish visual
impacts (Plan Policy UT-P20).
Newcastle Municipal Code (NMC)
Current through May 5, 2015
The Code does not include any policies or regulations that guide development of new utilities to reduce
impacts to views or visual resources.
January 2016 APPENDIX G
APPLICABLE PLANS AND POLICIES FOR VIEWS AND VISUAL RESOURCES G-9
PHASE 1 DRAFT EIS
Plans Protected Views and Visual
Resources Guidance for Reducing Visual Impacts
City of Newcastle SMP (N/A) The City of Newcastle does not have an SMP.
Redmond
Vision 2030 City of Redmond
Comprehensive Plan
Views of Mount Rainier, Mount Baker,
the Cascade Mountains, Lake
Sammamish, the Sammamish River,
Bear and Evans Creeks, and the open
and pastoral vistas in the northern
Sammamish River Valley
N/A
Unique public views that provide a
sense of place
N/A
View corridors should, such as:
• From Avondale Road and Union
Hill Road in the Bear Creek
Design District land north of
Bear and Evans Creeks and
east of Avondale Road (Plan
Policy SL-40).
• Scenic, public view corridors
toward the Cascades and the
Sammamish Valley (Plan Policy
NR-10).
• NE 116th Street (Plan Policy
NR-10)
• 172nd Avenue NE (Plan Policy
NR-10)
• NE 122nd Street to 162nd
Place NE (Plan Policy NR-10)
• 154th Place NE (Plan Policy
NR-10)
• Redmond-Woodinville Road
(Plan Policy NR-10)
N/A
APPENDIX G January 2016 G-10 APPLICABLE PLANS AND POLICIES FOR VIEWS AND VISUAL RESOURCES
PHASE 1 DRAFT EIS
Plans Protected Views and Visual
Resources Guidance for Reducing Visual Impacts
• Along the easement of the
Redmond/Puget Sound Energy
Trail (Plan Policy NR-10)
• Sammamish River (Plan Policy
N-EH-2)
• Sammamish Valley(Plan Policy
N-EH-2)
• Bear Creek Valley(Plan Policy
N-EH-2)
• Cascade Mountains(Plan Policy
N-EH-2)
• Lake Sammamish(Plan Policy
N-EH-2)
• Mount Rainier(Plan Policy N-
EH-2)
• Avondale Road through the
Keller Farm toward Mount
Rainier (Plan Policy N-BC-3)
Visual access to shorelines, including
existing parks and trails adjacent to the
shorelines and a in a few places from
view corridors or from major arterials or
bridges
Place utilities within existing utility corridors and have regional
transmission lines be located outside of the shoreline and
away from view corridors (Plan Policy SL-73 and SL-74).
The river; views of surrounding hillsides,
mountains, and tree line; large open
spaces, such as the Sammamish River,
Downtown Central Park, the Redmond
Central Connector, Anderson Park and
Bear Creek
Tree stands, views from the valley, and
rural area adjacent to the Sammamish
Valley, west of Redmond- Woodinville
N/A
January 2016 APPENDIX G
APPLICABLE PLANS AND POLICIES FOR VIEWS AND VISUAL RESOURCES G-11
PHASE 1 DRAFT EIS
Plans Protected Views and Visual
Resources Guidance for Reducing Visual Impacts
Road, and north of NE 116th Street
(Plan Policy N-SV-4)
The Willows Corridor, north of the Puget
Sound Energy transmission line right-of-
way (Plan Policy N-WR-G-1)
N/A
Natural vistas and open spaces within
neighborhoods.
Burry all new utilities and older utility lines that are being
updated in North Redmond, as well as those located in the
Idlywood neighborhood. An exception is made for PSE’s
high-voltage transmission lines (Policy N-NR-78 and N-ID-27).
N/A Burry utility lines along West Lake Sammamish Parkway, NE
24th Street, and NE 36th Street (Plan Policy N-ID-27).
Education Hill’s panoramic views of
Bear Creek Valley, the Cascade
Mountains, Mount Rainier, Downtown
Redmond, Lake Sammamish, the
Cascade foothills, the Sammamish
River, and the Sammamish Valley
N/A
Views of Lake Sammamish and
Marymoor Park from the Idylwood
neighborhood
N/A
Woodland views from neighborhood
residences
Keep the slopes overlooking the Sammamish and Bear Creek
Valleys undeveloped.
N/A Throughout the plan, landscaping is encouraged to provide
aesthetic value, unify site design, and soften or disguise “less
aesthetically pleasing features of a site” (Comp Plan; CC-23).
The Plan requires “reasonable screening or architecturally
compatible design of above ground utility facilities, such as
transformers and associated vaults” (Policy UT-15; Comp
plan). It suggests promoting well-designed utility facilities
through use of color, varied and interesting materials, art
work, and superior landscape design.
APPENDIX G January 2016 G-12 APPLICABLE PLANS AND POLICIES FOR VIEWS AND VISUAL RESOURCES
PHASE 1 DRAFT EIS
Plans Protected Views and Visual
Resources Guidance for Reducing Visual Impacts
Views associated with shoreline areas N/A
Redmond Zoning Code (RZC)
Current through June 16, 2015
Appearance of Public Ways Underground electrical facilities if economically-feasible (RZC
21.17).
Shoreline Views Underground electrical facilities or integrate them with trails
or other open space connections to the shoreline (RZC
21.68).
Redmond SMP (2009) Bear/Evans Creek Valley Public shoreline views along the Bear/Evans Creek Valley are
protected to some degree by Citywide Shoreline Public
Views.
Minimize negative visual impacts on adjacent or nearby
residential uses and recreational uses in the Agriculture and
Urban Recreation zones and shoreline areas. The use of
certain materials, shapes and colors and landscaping may be
required in order to minimize visual impacts (200.170.45-080).
Shorelines Where feasible, visual and physical access to the shoreline
should be required.
Lake Sammamish, open and pastoral
vistas in the northern Sammamish River
valley, and Mount Rainier along Bear
and Evans Creeks
N/A
Public view corridors as identified in
20D.42.50.
Site development should blend with natural landforms and be
designed to maximize scenic views identified as public view
corridors.
Locate regional utilities outside of the shoreline. Locate such
facilities away from public access areas and view corridors
and away from the shoreline to the farthest location possible
where a non-shoreline location is not feasible (SL-73).
Locate utilities, where feasible, within existing utility corridors.
Locate above-ground utilities away from view corridors
(SL-7 4).
January 2016 APPENDIX G
APPLICABLE PLANS AND POLICIES FOR VIEWS AND VISUAL RESOURCES G-13
PHASE 1 DRAFT EIS
Plans Protected Views and Visual
Resources Guidance for Reducing Visual Impacts
Renton
City of Renton Comprehensive
Plan (2015)
High volume of trees and clear mountain
views
N/A
Public scenic views and public view
corridors, such as “physical, visual, and
perceptual linkages to Lake Washington
and Cedar River” (Policy L-55).
N/A
Natural forms, vegetation, distinctive
stands of trees, natural slops, and
scenic areas that “contribute to the
City’s identity, preserve property values,
and visually define the community
neighborhoods” (Policy L-56).
N/A
Lakes and shorelines N/A
Views of the water from public property
or views enjoyed by a substantial
number of residences
N/A
N/A Design shoreline developments to maintain or enhance
aesthetic values and scenic views (Policy SH-16).
N/A Make facility improvements and additions within existing
corridors wherever possible (Policy U-73).
City of Renton Municipal Code
(RMC)
Current through November 16,
2015
Shoreline Design shoreline use and development to maintain shoreline
scenic and aesthetic qualities derived from natural features,
such as shore forms and vegetative cover (RMC 4-3-090.D.3)
Prohibits utilities in the Shoreline Natural shoreline
environment designation (RMC 4-3-090.E.1).
N/A Visual prominence of structures must be minimized, including
light, glare, and reflected light (RMC 4-3-090.D.3).
APPENDIX G January 2016 G-14 APPLICABLE PLANS AND POLICIES FOR VIEWS AND VISUAL RESOURCES
PHASE 1 DRAFT EIS
Plans Protected Views and Visual
Resources Guidance for Reducing Visual Impacts
N/A
Aboveground utilities must be screened with masonry,
decorative panels, and/or evergreen trees, shrubs, and
landscaping sufficient to form an effective sight barrier within
a period of five (5) years (RMC 4-6-090).
City of Renton SMP 2011 Scenic and aesthetic qualities derived
from natural features of the shoreline,
such as vegetative cover and shore
forms (Ordinance No. 5633).
N/A
Shoreline Reduce the visual prominence of structures, including an
associated light and glare (Ordinance No. 5633).
Prohibits utilities in the Shoreline Natural shoreline
environment designation (Ordinance No. 5633).
Sammamish
City of Sammamish
Comprehensive Plan (2015 Draft)
Streams, lakes, forested areas and other
natural features
N/A
Parks and recreation facilities N/A
View corridors and parcels that convey a
unique sense of the community’s
character
N/A
N/A Bury utilities if it is “physically and financially feasible.” If
unavoidable, have above-ground utility facilities be
aesthetically compatible with the surrounding area.
N/A Minimize visual impacts associated with towers in the
community.
Sammamish Municipal Code
(SMC)
Current through March 17, 2015
The Code does not include any policies or regulations that guide development of new utilities to reduce
impacts to views or visual resources.
January 2016 APPENDIX G
APPLICABLE PLANS AND POLICIES FOR VIEWS AND VISUAL RESOURCES G-15
PHASE 1 DRAFT EIS
Plans Protected Views and Visual
Resources Guidance for Reducing Visual Impacts
City of Sammamish SMP Update
August 2011
Lakes, rivers, and streams, and all
tributary waters and wetlands in the City
(Including Lake Sammamish, Pine Lake,
Beaver Lake)
N/A
Visual access to shorelines N/A
Yarrow Point
Town of Yarrow Point
Comprehensive Plan 2015-2035
N/A Long-term vision for electrical utility infrastructure is to have it
placed underground.
Yarrow Point Municipal Code
(YPMC)
Current through June 10, 2014
N/A Underground existing and new electrical facilities (YPMC
12.12.020).
Town of Yarrow Point SMP 2012 N/A Utilities that must be located within the shoreline should be
placed in existing rights-of-way or corridors.
Note: For this programmatic EIS, subarea plans were not reviewed unless their goals and polices were embodied in the community-wide comprehensive plan.
APPENDIX G January 2016 G-16 APPLICABLE PLANS AND POLICIES FOR VIEWS AND VISUAL RESOURCES
PHASE 1 DRAFT EIS
APPENDIX H. HISTORIC AND CULTURAL
SITES
Site # Site Name ALT 1 ALT 2 ALT 3 Isolated
Artifact
Precontact
Component
Human
Remains Submerged Residential
Historic
Refuse /
Scatter
Infrastructure Industrial Railroad NRHP
Status
45-KI-0008 - • • • •
Not
Evaluated
45-KI-0009 - • • • • Listed
45-KI-0010 - • • • •
Not
Evaluated
45-KI-0051 Earlington Woods • • • • •
Not
Evaluated
45-KI-0211 Renton Coal Mine • • • •
Potentially
Eligible
45-KI-0266 - • • • •
Not
Evaluated
45-KI-0285 Seattle and Walla Walla
RR • • • • Not
Evaluated
45-KI-0404 Submerged Vessel • - - •
Not
Evaluated
45-KI-0425 Submerged Vessel • - - •
Not
Evaluated
45-KI-0427 Submerged Aircraft • - - •
Determined
Not Eligible
45-KI-0430 Tradition Lake Peeled
Cedar - - • •
Not
Evaluated
45-KI-0433 Submerged RR coal cars • - - •
Potentially
Eligible
45-KI-0439 Renton Sears-Fred
Meyer Store Site • • • • •
Not
Evaluated
45-KI-0451 Seattle, Lake Shore &
Eastern RR • • • • Determined
Not Eligible
45-KI-0452
Gilman Water
Company/Old Issaquah
Water Works
- - • •
Determined
Not Eligible
45-KI-0453 Poured Concrete Block
Foundation - - • •
Determined
Not Eligible
45-KI-0457 - - - • •
Not
Evaluated
45-KI-0466 Bear/Evans Creek Site - - • • • •
Not
Evaluated
45-KI-0467 Union Hill Road Site - - • • •
Not
Evaluated
45-KI-0481 Tradition Lake Site - - • •
Not
Evaluated
January 2016 APPENDIX H HISTORIC AND CULTURAL SITES H-1
PHASE 1 DRAFT EIS
Site # Site Name ALT 1 ALT 2 ALT 3 Isolated
Artifact
Precontact
Component
Human
Remains Submerged Residential
Historic
Refuse /
Scatter
Infrastructure Industrial Railroad NRHP
Status
45-KI-0488 - - - • • •
Not
Evaluated
45-KI-0492 Marymoor Trench B • • • •
Not
Evaluated
45-KI-0493 Marymoor Trench F • • • •
Not
Evaluated
45-KI-0501 Renton High School
Indian Site • • • •
Not
Evaluated
45-KI-0537 Concrete foundations - - • •
Determined
Not Eligible
45-KI-0538 Columbia and Puget
Sound RR • • • • Potentially
Eligible
45-KI-0542 - • • • •
Not
Evaluated
45-KI-0543 Moore Farmstead • • • •
Not
Evaluated
45-KI-0587 Little Cedar River Fishing
Site • • • •
Not
Evaluated
45-KI-0686 Henry Moses Aquatic
Center Site • • • •
Not
Evaluated
45-KI-0698 Historic Road Grade - - • • • Potentially
Eligible
45-KI-0699 - - - • • Potentially
Eligible
45-KI-0701 - - - • •
Potentially
Eligible
45-KI-0704 Maxwell Corduroy Road - - • • Potentially
Eligible
45-KI-0718 Eastside Terrace Site • • • •
Not
Evaluated
45-KI-0739 - - - • •
Potentially
Eligible
45-KI-0748
Forbes Lake East
Mitigation Area Historic
Site
• • • • •
Potentially
Eligible
45-KI-0751 ELSP-ISO-01 - - • • •
Determined
Not Eligible
45-KI-0758 Coal Creek Mine • • • •
Potentially
Eligible
APPENDIX H January 2016 H-2 HISTORIC AND CULTURAL SITES
PHASE 1 DRAFT EIS
Site # Site Name ALT 1 ALT 2 ALT 3 Isolated
Artifact
Precontact
Component
Human
Remains Submerged Residential
Historic
Refuse /
Scatter
Infrastructure Industrial Railroad NRHP
Status
45-KI-0759 Bob Bridge Toyota Site • • • •
Potentially
Eligible
45-KI-0767 Talbot Road Dam and
Retaining Walls • • • •
Potentially
Eligible
45-KI-0771 1349-1 Milk Can - - • • •
Not
Evaluated
45-KI-0814 Floating Dry Docks YFD
48 and 51 • - - • •
Potentially
Eligible
45-KI-0821 - • • • •
Potentially
Eligible
45-KI-0823 Borrow Pit - - • •
Potentially
Eligible
45-KI-0824 Bullitt House - - • •
Potentially
Eligible
45-KI-0825 Gauthier Mill /
Milwaukee RR Tie Mill - - • •
Potentially
Eligible
45-KI-0829 Campbell Lumber
Company Mill - - • • •
Not
Evaluated
45-KI-0830 SLP-08-01 - - • • •
Not
Evaluated
45-KI-0834 - - - • •
Not
Evaluated
45-KI-0835 - - - • • •
Not
Evaluated
45-KI-0836 - - - • • •
Not
Evaluated
45-KI-0837 - - - • • •
Not
Evaluated
45-KI-0839 Bear Creek Site • • • •
Not
Evaluated
45-KI-0848
Renton Glass Company
Factory ruins and
retaining wall
• • • •
Determined
Not Eligible
45-KI-0941 Marymoor Pet Garden • • • •
Not
Evaluated
45-KI-0945 Historic Lake
Washington Boulevard • • • •
Not
Evaluated
45-KI-0956 MUT-10-01 • • • • •
Not
Evaluated
January 2016 APPENDIX H HISTORIC AND CULTURAL SITES H-3
PHASE 1 DRAFT EIS
Site # Site Name ALT 1 ALT 2 ALT 3 Isolated
Artifact
Precontact
Component
Human
Remains Submerged Residential
Historic
Refuse /
Scatter
Infrastructure Industrial Railroad NRHP
Status
45-KI-0969 Bridle Trails Listerine
Bottle • • • • •
Potentially
Eligible
45-KI-0985 - - - • • Potentially
Eligible
45-KI-0988 SP NHPP 07 - - • • •
Not
Evaluated
45-KI-1008 - • • • •
Potentially
Eligible
45-KI-1009 Moses Homestead • • • • •
Potentially
Eligible
45-KI-1010 Renton High School Ball
Field Site • • • •
Not
Evaluated
45-KI-1034 Zackuse Cemetery - - • •
Not
Evaluated
45-KI-1037 ELST01 • - • •
Determined
Not Eligible
45-KI-1038 ELST01 • - • •
Determined
Not Eligible
45-KI-1039 ELST03 • - • •
Determined
Not Eligible
45-KI-1095 15 Mile Isolate - - • • •
Not
Evaluated
45-KI-1100 Anderson Farmstead
Fire/Burn Pit - - • • •
Potentially
Eligible
45-KI-1101 - - - • •
Not
Evaluated
45-KI-1107 Reilly Tar & Chemical
Wharf and T-Dock • - - • •
Potentially
Eligible
45-KI-1116 - • • • • •
Not
Evaluated
45-KI-1117 - • • • •
Potentially
Eligible
45-KI-1118 - • • • •
Potentially
Eligible
45-KI-1156 Hemingray-10 - - • • •
Not
Evaluated
45-KI-1172 ELST Flaked Pebble - - • • •
Not
Evaluated
APPENDIX H January 2016 H-4 HISTORIC AND CULTURAL SITES
PHASE 1 DRAFT EIS
Site # Site Name ALT 1 ALT 2 ALT 3 Isolated
Artifact
Precontact
Component
Human
Remains Submerged Residential
Historic
Refuse /
Scatter
Infrastructure Industrial Railroad NRHP
Status
45-KI-1173
St. Andrew's Lutheran
Church Memorial
Garden
• • • •
Not
Evaluated
45-KI-1174
St. Luke's Lutheran
Church Memorial
Garden
• • • •
Not
Evaluated
45-KI-1175
Cross of Christ Lutheran
Church Garden of
Remembrance
• • • •
Not
Evaluated
45-KI-1176 Maclean Site - - • •
Not
Evaluated
45-KI-1177 Issaquah-Fall City Road
Segment - - • •
Potentially
Eligible
45-KI-1178 Peterson Farm • • • •
Potentially
Eligible
45-KI-1198 - - - • •
Potentially
Eligible
45-KI-1199 Superior Coal &
Improvement RR Grade - - • • Potentially
Eligible
45-KI-1206 - • • • •
Not
Evaluated
45-KI-1210 Black River Pilings • • • •
Potentially
Eligible
45-KI-1216 - - - • •
Not
Evaluated
45-KI-1217 EL105 • • • • •
Not
Evaluated
45-KI-1218 - • • • •
Determined
Not Eligible
45-KI-1227 ELST Wall 25 - - • •
Not
Evaluated
45-KI-1228 ELST Wall 4 - - • •
Not
Evaluated
45-KI-1229 ELST Wall 24 - - • •
Potentially
Eligible
45-KI-1238 - - - • • •
Potentially
Eligible
45-KI-1262 - - - • • • Not
Evaluated
January 2016 APPENDIX H HISTORIC AND CULTURAL SITES H-5
PHASE 1 DRAFT EIS
APPENDIX I. REGISTERED HISTORIC
PROPERTIES
Map # Site # Property Name Address Year Built ALT 1 ALT 2 ALT 3
Determ.
Eligible
NRHP
NRHP
Listed
WHR
Listed
Washington
Heritage Barn
Register Listed
Designated King
County
Landmark
- 45-KI-0786 Burial Not Mapped - • • • - - - - -
- 45-KI-0794 Charles and Judy Cramer
Farm Not Mapped 1911 - - • - - - • -
- 45-KI-0853 First Presbyterian Church of
Bellevue Memorial Garden Not Mapped - • • • - - - - -
- 45-KI-0854 Midlakes Pioneer Cemetery Not Mapped - • • • - - - - -
- 45-KI-0855 Sunset Hills Memorial Park Not Mapped - • • • - - - - -
- 45-KI-0860 House of Mercy All-Muslim
Cemetery Not Mapped - - - • - - - - -
- 45-KI-0868 Hillside Cemetery Not Mapped - - - • - - - - -
- 45-KI-0875 Tahoma National Cemetery Not Mapped - - - • - - - - -
- 45-KI-0876 Kirkland Cemetery Not Mapped - • • • - - - - -
- 45-KI-0885 Cedar Lawns Memorial Park Not Mapped - - - • - - - - -
- 45-KI-0886 Old Redmond Cemetery Not Mapped - - - • - - - - -
- 45-KI-0887 Greenwood Memorial Park Not Mapped - • • • - - - - -
- 45-KI-0888 Mt. Olivet Cemetery Not Mapped - • • • - - - - -
- 45-KI-0948 St. Margaret's Episcopal
Church Columbarium Not Mapped - • • • - - - - -
- 45-KI-1034 Zackuse Cemetery Not Mapped - - - • - - - - -
1 - Conrad Olson Farmstead 18834 NE 95th Street 1905 - - • - - - - •
2 45-KI-612 John George Kellet House 526 10th Avenue 1889 • • • - - • - -
3 45-KI-186
William A. Jones House /
Kirkland Land & Improvement
Company House / Loomis
House
304 8th Avenue W 1889 • • • - • • - •
4 45-KI-188 Joshua Sears Building 701 Market Street c.1891 • • • - • • - -
5 45-KI-189 Masonic Lodge Building 700 Market Street 1890 • • • - • • - -
6 45-KI-195 Peter Kirk House 620 Market Street c.1892 • • • - • • - •
7 45-KI-187 Dr. Trueblood House 127 7th Avenue 1889 • • • - • • - -
8 - Perrigo House (Community
Landmark) 17325 NE 85th Place 1909 - - • - - - - •
9 45-KI-572 Kirkland Woman’s Club 407 First Street 1925 • • • - • • - •
10 - First Church of Christ,
Scientist
NW corner of Market Street
and Lake Avenue W 1922 • • • - - - - •
11 - Kirkland Ferry Clock NW corner of Kirkland
Avenue and Lake Street 1935 • • • - - - - •
January 2016 APPENDIX I HISTORIC AND CULTURAL RESOURCES I-1
PHASE 1 DRAFT EIS
Map # Site # Property Name Address Year Built ALT 1 ALT 2 ALT 3
Determ.
Eligible
NRHP
NRHP
Listed
WHR
Listed
Washington
Heritage Barn
Register Listed
Designated King
County
Landmark
12 45-KI-631 Tourist II (Auto Ferry) 25 Lake Shore Plaza, Marina
Park 1924 • • • - • • - -
13 - Old Redmond School 16600 NE 80th Street 1922 • • • - - - - •
14 - Redmond Methodist Church
(Community Landmark) 16540 NE 80th Street 1908 • • • - - - - •
15 - Odd Fellows Hall 7979 Leary Way 1903 • • • - - - - •
16 - Lodge Hall (Community
Landmark) 7875 Leary Way 1903 • • • - - - - •
17 - Orson and Emma Wiley House 16244 Cleveland Street c.1916 • • • - - - - •
18 - Brown’s Garage 16389 Redmond Way 1920 • • • - - - - •
19 - Redmond State Bank 7841 Leary Way 1911 • • • - - - - •
20 45-DT-0219 Redmond City Park 7802 168th Ave. NE c.1938 • • • - • • - •
21 - Bill Brown Saloon 7824 Leary Way 1913 • • • - - - - •
22 45-KI-190 Justice William White House 7729 Leary Way 1889 • • • • - - - •
23 - Haida House Replica No. 4 7447 159th Place NE 1980 • • • - - - - •
24 - Redmond Cemetery 7000 – 180th Avenue NE c.1890 - - • - - - - •
25 45-KI-590 Louis S. Marsh House 6604 Lake Washington
Boulevard 1929 • • • - • • - •
26 45-KI-9 Marymoor Prehistoric Indian
Site Vicinity of Marymoor Park - • • • - • • - -
27 45-KI-191 James W. Clise House 6046 Lake Sammamish
Parkway NE 1904 • • • - • • - -
28 45-KI-192 Old Dutch Windmill 6046 Lake Sammamish
Parkway NE c.1905 • • • - - • - -
29 45-KI-196 The Yellowstone Road
196th Avenue NE Between
the Fall City Highway and
80th NE
1913 - - • - • • - •
30 45-KI-1143 Walter Cooper Dairy Farm 5703 208th Ave NE 1925 - - • - - - • -
31 45-KI-797 Bill Johnson Barn 20306 NE 50th Street 1933 - - • - - - • -
32 45-KI-802 Louis Hilger Barn 22627 NE Redmond-Fall
City Rd 1912 - - • - - - • -
33 45-KI-193 The Moorings 1401 92nd Avenue NE 1918 - • • - - • - -
34 45-KI-173 James G. Eddy House and
Grounds 1005 Evergreen Point Road 1927 - • • • •
35 45-KI-172 Old Ferry Dock Building –
Medina 501 Evergreen Point Road 1913 • • • •
36 45-KI-970 Twin Valley Dairy 410 130th Place SE 1933 • • • - - - • -
APPENDIX I January 2016 I-2 HISTORIC AND CULTURAL RESOURCES
PHASE 1 DRAFT EIS
Map # Site # Property Name Address Year Built ALT 1 ALT 2 ALT 3
Determ.
Eligible
NRHP
NRHP
Listed
WHR
Listed
Washington
Heritage Barn
Register Listed
Designated King
County
Landmark
37 45-KI-262 Wilburton Trestle Burlington Northern Railroad
crossing Mercer Slough 1904 • • • - - • - -
38 45-KI-659 Jacob and Emma Reard
House 1705 212th Ave SE 1895 - - • • - - - •
39 45-KI-606 Winters, Frederick W., House 2102 Bellevue Way SE 1929 • • • - • • - -
40 45-KI-618 Ray Brandes House 2202 212th Ave SE 1953 - - • - • • - -
41 - Issaquah-Fall City Road
Heritage Corridor
Sammamish Plateau and
Snoqualmie Valley 1883-1926 - - • - - - - •
42 45-KI-142 Pickering Farm 21809 SE 56th Street 1890 - - • - • • - -
43 45-KI-140 Pacific Coast Company House
No. 75 7210 138th Avenue SE c.1870 • • • - • • - •
44 45-KI-0793 Victor Taumala Barn 21003 SE 75th Street 1922 - - • - - - • -
45 - Hailstone Feed Store and
Gasoline Station 232 Front Street 1941 - - • - - - - •
46 45-KI-141 Newcastle Cemetery SW of 69th Way off 129th
Avenue SE c.1870 • • • - - • - •
47 - Thomas Rouse Road
(Community Landmark) 136th SE & 144th Place SE 1880 • • • - - - - •
48 45-KI-595 Issaquah Depot (Gilman
Station) 50 Rainier Boulevard North 1889 - - • - • • - •
49 45-KI-637 Issaquah Sportsmen’s Club 23600 SE Evans Street 1937 - - • - • • - •
50 45-KI-790 Colasurdo Barn 14339 S.E. May Valley Road 1949 • • • - - - • -
51 45-KI-209 Renton Fire Station Houser Way and Mill Avenue 1939 • • • - - • - -
52 45-KI-74
Renton Substation,
Snoqualmie Falls Power
Company
1017 South 3rd Street 1898 • • • - - • - -
53 45-KI-211 Renton Coal Mine Hoist
Foundation
Vicinity of Grady Way and
Benson Road 1890 • • • - - • - -
54 - Elliott Farm* 14207 Maple Valley
Highway 1911 • • • - - - - •
January 2016 APPENDIX I HISTORIC AND CULTURAL RESOURCES I-3
PHASE 1 DRAFT EIS
APPENDIX J. DESCRIPTION OF
APPLICABLE HISTORIC REGISTERS
WASHINGTON HERITAGE REGISTER
Established in 1971 (Senate Bill 363, RCW 27.34.200, and Chapter 25-12 WAC), the
Washington Heritage Register (WHR) is maintained by the Department of Archaeology and
Historic Preservation (DAHP). As of June 2015, a total of 441 properties were listed on the
WHR statewide. Properties listed on the National Register of Historic Places (NRHP) are
also automatically listed on the WHR, while some properties are only listed on the WHR.
Listing in the WHR is honorary and does not restrict private property owners from altering
these resources. However, SEPA review requires consideration of properties listed in or
eligible for the WHR. To qualify for listing on the WHR, the following criteria must be met:
• A building, site, structure, or object must be at least 50 years old. If newer, the
resource should have documented exceptional significance.
• The resource should have a high to medium level of integrity; it should retain
important character-defining features from its historic period of construction.
• The resource should have documented historical significance at the local, state, or
federal level.
• Advisory Council on Historic Preservation review and listing requires the consent of
the owner.
WASHINGTON HERITAGE BARN REGISTER
Created in 2007 under Substitute House Bill 2115, this register commemorates barns that are
historically significant to the agricultural, economic, and cultural development of the State of
Washington. As of June 2015, a total of 572 heritage barns were designated across
Washington. Listing on the register is honorary and does not protect the resource from
demolition nor require review of alterations. To qualify for listing on the Washington
Heritage Barn Register, the following criteria must be met:
• The barn must be over 50 years old.
• The barn must retain a significant degree of historic and architectural integrity.
KING COUNTY LANDMARKS
Historic properties in King County may be recognized at the local level for their historic
significance through a landmark nomination process administered by the King County
Landmarks Commission (Chapter 20.62 King County Code [KCC]). Most King County
Landmarks are in unincorporated King County; some are County-owned buildings within
city limits.
January 2016 APPENDIX J REGISTERED PROPERTIES J-1
PHASE 1 DRAFT EIS
Designation criteria for King County Landmarks are defined in Chapter 20.62 KCC as
follows:
A. A historic resource may be designated as a King County landmark if it is more than
40 years old, or in the case of a landmark district, contains resources that are more
than 40 years old, and possess integrity of location, design, setting, materials,
workmanship, feeling, and association; and meet at least one of the following
designation criteria:
A1. Is associated with events that have made a significant contribution to the
broad patterns of local, state or national history; or
A2. Is associated with the lives of persons significant in local, state or national
history; or
A3. Embodies the distinctive characteristics of a type, period, style or method of
design or construction, or that represents a significant and distinguishable
entity whose components may lack individual distinction; or
A4. Has yielded, or may be likely to yield, information important to prehistory or
history; or
A5. Is an outstanding work of a designer or builder who has made a substantial
contribution to the art.
B. A historic resource may be designated a community landmark because it is an easily
identifiable visual feature of a neighborhood or the county and contributes to the
distinctive quality or identity of such neighborhood or county because of its
association with significant historical events or historic themes, association with
important or prominent persons in the community or county, or recognition by local
citizens for substantial contribution to the neighborhood or community. An
improvement or site qualifying for designation solely by virtue of satisfying criteria
set out in this section shall be designated a community landmark and shall not be
subject to the provisions of KCC 20.62.080.
C. Cemeteries, birthplaces, or graves of historical figures, properties owned by religious
institutions or used for religious purposes, structures that have been moved from their
original locations, reconstructed historic buildings, properties primarily
commemorative in nature, and properties that have achieved significance within the
past 40 years shall not be considered eligible for designation. However, such a
property shall be eligible for designation if it is:
C1. An integral part of districts that meet the criteria set out in KCC 20.62.040A
or if it is:
C2. A religious property deriving primary significance from architectural or
artistic distinction or historical importance; or
C3. A building or structure removed from its original location but which is
significant primarily for its architectural value, or which is the surviving
structure most importantly associated with a historic person or event; or
APPENDIX J January 2016 J-2 REGISTERED PROPERTIES
PHASE 1 DRAFT EIS
C4. A birthplace, grave or residence of a historical figure of outstanding
importance if there is no other appropriate site or building directly associated
with his or her productive life; or
C5. A cemetery that derives its primary significance from graves of persons of
transcendent importance, from age, from distinctive design features, or from
association with historic events; or
C6. A reconstructed building when accurately executed in a suitable environment
and presented in a dignified manner or as part of a restoration master plan,
and when no other building or structure with the same association has
survived; or
C7. A property commemorative in intent if design, age, tradition, or symbolic
value has invested it with its own historical significance; or
C8. A property achieving significance with the past 40 years if it is of exceptional
importance (King County, 2015).
The Landmarks Commission manages changes to designated landmarks through the
Certificate of Appropriateness (COA) process (King County, 2015). Once a property has
been designated, owners considering making significant alterations to the features of the
resource that have been designated as significant, or seeking to move or demolish the
resource, must file a COA with the Commission’s Historic Preservation Officer for design
review. The COA process includes an initial consultation meeting with the applicant, Historic
Preservation Officer, and members of the Commission’s Design Review Committee. If all
parties agree to recommend approval of the COA, the COA is presented to the Commission
at the next regularly scheduled meeting. If the parties disagree, a public hearing is scheduled
before the Commission within 45 days. If, after the public hearing, the Commission declines
the COA, a written report clarifying the basis for the decision is prepared and distributed to
all interested parties. All Commission decisions may be appealed to the King County Council
within 30 days of the notice of the decision.
REFERENCES:
King County Historic Preservation Program. 2015. King County and City Landmarks List.
Available at
http://www.kingcounty.gov/~/media/property/historic_preservation/documents/resourc
es/T06_KCLandmarkList.ashx?la=en. Last updated: July 14, 2015. Accessed July 23,
2015.
January 2016 APPENDIX J REGISTERED PROPERTIES J-3
PHASE 1 DRAFT EIS
APPENDIX K. INTERVIEW QUESTIONS FOR
FIRE DEPARTMENTS
The following questions were asked of each study area fire department in July and
August, 2015.
1. Is your department meeting service (response) targets?
2. What kind of technical response teams do they have?
3. Do they have the ability (appropriate equipment and training) to respond to electrical
fires?
4. Do they have the ability to respond to a downed 230 kV transmission line on a house;
across a street ROW?
5. Have you had to respond to incidences involving 115 kV transmission lines?
6. Is responding to 230 kV transmission line incidences a different level of complexity
than responding to 115 kV incidences?
7. How does the department coordinate with PSE when there are downed lines?
8. Have you ever responded to a substation or transformer explosion and fire (Bellevue
Fire Department and Eastside Fire and Rescue only)?
9. Do you have the training and capability to respond to a substation fire?
January 2016 APPENDIX K INTERVIEW QUESTIONS FOR FIRE DEPARTMENTS K-1
PHASE 1 DRAFT EIS
APPENDIX L. INTERVIEW QUESTIONS FOR
POLICE DEPARTMENTS
The following questions were asked of study area police department in July, 2015.
1. Have you had any problems with existing transmission corridors in your service area
a. If yes, where and what was the nature of the problem (e.g., littering, drugs,
violent crime…)
b. Were these problems effectively dealt with or is it an ongoing issue?
2. Would you consider that a new transmission corridor is better sited (from the
perspective of minimizing potential for crime) if it’s located through a densely
populated area or through a more remote area?
3. Have you had any problems, or do you see electric substations as places that attract
crime (such as graffiti or other property crimes?). Would you say the level of problem
depends on whether it’s located in densely populated area vs. a more remote location?
January 2016 APPENDIX L INTERVIEW QUESTIONS FOR POLICE DEPARTMENTS L-1
PHASE 1 DRAFT EIS
APPENDIX M. PIPELINE SAFETY
REQUIREMENTS AND PLANS RELATING TO
PETROLEUM PIPELINES
Table M-1. Federal and State Laws and Regulations for Pipelines
Federal and State Laws
and Regulations Summary
Federal
Natural Gas Pipeline Safety
Act of 1968; now called the
Pipeline Safety Law, 49
USC Section 60101 et seq.
Gives the federal government authority over pipeline safety for
transporting hazardous liquids, natural gas, and other gases.
The intent is for states to assume responsibility for intrastate
pipeline safety, while the federal government retains
responsibility for interstate pipeline safety.
Title 49, Code of Federal
Regulations (CFR) Part 194
for hazardous liquid
pipelines
Contains requirements for oil spill response plans to reduce the
environmental impact of oil discharged from onshore oil
pipelines.
Title 49, CFR Part 195 for
hazardous liquid pipelines
Addresses safety in design, construction, testing, operation,
maintenance, and emergency response for pipeline
facilities. Require spill response/emergency response plans.
Title 49 CFR Part 195.571 Contains criteria to determine the adequacy of cathode
protection. Incorporates by reference industry standards and
practices developed by the National Association of Corrosion
Engineers (NACE).
Liquid Pipeline Integrity
Management in
High Consequence Areas
for Hazardous Liquid
Operators (49 CFR Parts
195.450 and 195.452); also
called The Liquid IM Rule
Specifies how pipeline operators must identify, prioritize,
assess, evaluate, repair, and validate the integrity of hazardous
liquid pipelines that could, in the event of a leak or failure, affect
High Consequence Areas. Includes requirements for regular
inspection and monitoring.
State
Washington Pipeline Safety
Act of 2000 (E2SHB 2420)
With this Act, the Washington Utilities and Trade Commission
(UTC) was directed and obtained the authority from the OPS to
inspect interstate pipelines in Washington State.
Underground Utilities –
Damage Prevention Law
RCW 19.122
Addresses public health and safety and prevention of disruption
of vital utility services through a comprehensive damage
prevention program.
WAC 173-182 – Oil Spill
Contingency Plan
Establishes covered vessel and facility oil spill contingency plan
requirements (Part II), drill and equipment verification
requirements (Part III), primary response contractor standards
(Part IV) and recordkeeping and compliance information (Part V).
January 2016 APPENDIX M PIPELINE SAFETY REQUIREMENTS AND PLANS M -1
PHASE 1 DRAFT EIS
Table M-2. Olympic Pipeline Response Plans
Plans Summary
Facility Response Plan BP
Pipelines (North America)
U.S. Pipelines and
Logistics: Northwest
Pipeline District
The Facility Response Plan (FRP) provides guidelines to respond
to a spill from the Olympic Pipeline (and the Cherry Point Crude
Line, Butane Pipeline and associated facilities).
The FRP is meant to supplement responders’ training and
experience during an actual response. Since each response is
different, the FRP may not always contain all the information
needed to manage a spill. This FRP is designed to satisfy the
requirements of the Oil Pollution Act of 1990 (OPA 90), and has
been prepared in accordance with the National Oil and
Hazardous Substances Pollution Contingency Plan (NCP) (40
CFR 300), and the Northwest Area Contingency Plan (NWACP).
Specifically, this Plan is intended to satisfy the requirements of:
• Pipeline and Hazardous Materials Safety Administration
(PHMSA), U.S. Department of Transportation (49 CFR 194)
• Washington Administrative Code (WAC) 173-182
• Oregon Administrative Rule (OAR) 340-141
Operations Maintenance
and Emergency Response
Manual BP Pipelines (North
America) U.S. Pipelines
and Logistics: Northwest
Pipeline District
Addresses how OPLC responds operationally to an emergency.
APPENDIX M January 2016 M -2 PIPELINE SAFETY REQUIREMENTS AND PLANS
PHASE 1 DRAFT EIS
January 2016 APPENDIX M PIPELINE SAFETY REQUIREMENTS AND PLANS M -3
PHASE 1 DRAFT EIS
APPENDIX M January 2016 M -4 PIPELINE SAFETY REQUIREMENTS AND PLANS
PHASE 1 DRAFT EIS
January 2016 APPENDIX M PIPELINE SAFETY REQUIREMENTS AND PLANS M -5
PHASE 1 DRAFT EIS
APPENDIX M January 2016 M -6 PIPELINE SAFETY REQUIREMENTS AND PLANS
PHASE 1 DRAFT EIS
January 2016 APPENDIX M PIPELINE SAFETY REQUIREMENTS AND PLANS M -7
PHASE 1 DRAFT EIS
APPENDIX M January 2016 M -8 PIPELINE SAFETY REQUIREMENTS AND PLANS
PHASE 1 DRAFT EIS
January 2016 APPENDIX M PIPELINE SAFETY REQUIREMENTS AND PLANS M -9
PHASE 1 DRAFT EIS
APPENDIX M January 2016 M -10 PIPELINE SAFETY REQUIREMENTS AND PLANS
PHASE 1 DRAFT EIS
January 2016 APPENDIX M PIPELINE SAFETY REQUIREMENTS AND PLANS M-11
PHASE 1 DRAFT EIS
APPENDIX M January 2016 M -12 PIPELINE SAFETY REQUIREMENTS AND PLANS
PHASE 1 DRAFT EIS
January 2016 APPENDIX M PIPELINE SAFETY REQUIREMENTS AND PLANS M-13
PHASE 1 DRAFT EIS
APPENDIX M January 2016 M -14 PIPELINE SAFETY REQUIREMENTS AND PLANS
PHASE 1 DRAFT EIS
January 2016 APPENDIX M PIPELINE SAFETY REQUIREMENTS AND PLANS M-15
PHASE 1 DRAFT EIS
APPENDIX M January 2016 M -16 PIPELINE SAFETY REQUIREMENTS AND PLANS
PHASE 1 DRAFT EIS
January 2016 APPENDIX M PIPELINE SAFETY REQUIREMENTS AND PLANS M-17
PHASE 1 DRAFT EIS
APPENDIX M January 2016 M -18 PIPELINE SAFETY REQUIREMENTS AND PLANS
PHASE 1 DRAFT EIS
January 2016 APPENDIX M PIPELINE SAFETY REQUIREMENTS AND PLANS M-19
PHASE 1 DRAFT EIS
APPENDIX M January 2016 M -20 PIPELINE SAFETY REQUIREMENTS AND PLANS
PHASE 1 DRAFT EIS
January 2016 APPENDIX M PIPELINE SAFETY REQUIREMENTS AND PLANS M-21
PHASE 1 DRAFT EIS
APPENDIX M January 2016 M -22 PIPELINE SAFETY REQUIREMENTS AND PLANS
PHASE 1 DRAFT EIS
January 2016 APPENDIX M PIPELINE SAFETY REQUIREMENTS AND PLANS M-23
PHASE 1 DRAFT EIS
Name Updated Size
05 - Additional Documents Jan 07, 2020 by Amanda Kleiss 198 Files
04 - Decisions and Staff Reports Jan 07, 2020 by Amanda Kleiss 3 Files
03 - Notice of Application Jan 07, 2020 by Amanda Kleiss
02 - Acceptance Letter Jan 07, 2020 by Amanda Kleiss
01 - Submittal Documents Jan 07, 2020 by Amanda Kleiss
Owner
Amanda Kleiss
Created
Jan 07, 2020 3:11 PM
Modified
Jan 08, 2020 11:12 AM
Size
809 MB
Folder Properties
Details
PSE - City of Renton Hearing - 1-8-2020 Renton Permit Documents Download
Log in Sign up
Page 1 of 1PSE -City of Renton Hearing -1-8-2020 | Powered by Box
3/20/2020https://vannessfeldmanllp.app.box.com/s/n7uf58u5m9ibvh1vykr5za7itm6shzbk/folder/992...