Utility Coordination Report
Sunset Relo
Site# WA6148
PRELIMINARY
Company: J5 Infrastructure Partners
Consultant: Devin Taylor
Phone Number: 503-803-2850
Email: dtaylor@j5ip.com
Power: PSE
Transport: TBD
Prelim: 1/3/2020
Final:
Revision: V1
Rev Date:
UCR: WA6148 Sunset Relo 2
Site Contacts
Site Address: 3410 NE 12th St.
Renton WA 98056
Lat/Long: 47.503639, -122.173819
Property Owner: City of Renton
Property Contact: Abdoul Gafour
Phone: 425-430-7210
E-mail Address: agafour@rentonwa.gov
Site Acq Vendor: J5 Infrastructure Partners
Site Acq Contact: Germaine Bazan
E-mail Address: gbazan@j5ip.com
☐Received Design Walk Package
☐Received PCD” s Revision Date:
☐Received 1A Survey Date:
UCR: WA6148 Sunset Relo 3
Power Company Contact Information
Provider: PSE App Sent:
Engineering Contact: TBD WO#
Phone Number(s): 188-225-5773 Fees:
WEB Address: https://www.pse.com/start-stop-move/start-service
Design Confirmation with Field Engineer:
☐Yes, Date:
☒No (explain): TBD
Power Run Information
Point of Origination: ☐Existing Pole ☐Pad-Mounted Transformer
☐Electrical Room ☐Sub-meter from Existing Power
☐Vault/Hand-hole ☒other- Abandoned Meter Base
Identification number on Point of Origination: Existing PSE Utility pole # 318643166904
Capacity at demarcation: 200A Service, 120/240V, 1 Phase, 3-Wire
Distance to site (via existing or proposed easement): 65’
Describe route to vendor equipment (be specific, including if and where a new transformer will be placed,
where new VENDOR meter will go, etc.):
Primary power will be brought to the site from existing abandon meter base.
AT&T GC will need to install (1) 3” Schedule 40 PVC conduit with pulltape, from the existing meter base to the
new H-Frame in AT&T lease area.
AT&T GC will need to install new H-Frame at proposed AT&T new site location for power and fiber handoff
equipment.
AT&T GC will need to size and install new A/C service panel on H-Frame.
AT&T GC will need to size and install power wire from meter base to A/C service panel.
UCR: WA6148 Sunset Relo 4
Notes:
• AT&T GC to request locates prior to any excavation.
• AT&A GC to maintain proper clearances from all existing pipin g, drainage and conduits on
property.
• Where power and telco are placed in a combined trench, a minimum 12” separation must be
maintained at all times.
• All sweeps to have a minimum 36” radius unless otherwise noted.
• AT&T GC to provide a minimum 3’-6” clearance in front of the meter base.
• PSE will require 24-hour access to their facilities.
• AT&T GC to have all required inspections complete prior to PSE installing their wiring and
energizing the service.
UCR: WA6148 Sunset Relo 5
_________________________________________________________________________________________
Power Easement (or equivalent) Information
Utility Co. Easement(s) Required (Utility Co. Document)? ☐Yes ☒No
Third-Party Easements(s) Needed? ☐Yes ☐No ☒Possible/Needs Verification
Who will Write Who Executes & Notarizes Who Records
☐Power Co.
☐SA Vendor
☐Other: See Below
☐Power Co.
☐SA Vendor
☐Other: See Below
☐Power Co.
☐SA Vendor
☐Other: See Below
Where the Utility places and maintains power and/or Telco assets on private property from the Right of Way to the site, the S ite Acq
agent is responsible for securing land rights for the path, environment (Aerial or Underground), and 24/7 access where the plant will
reside and as required by the utility. Also applicable to 3 rd party private property where required.
Where the Utility does not require an exclusive easement, the SA vendor shall determine the final means of securing the appropriate
land rights and approving with the utility and landlord/owner. Also applicable to 3 rd party private property where required.
UCR: WA6148 Sunset Relo 6
Transport Provider Contact Information
Available Transport: Providers in the vicinity of site location
1. Provider Name: CenturyLink fiber vault just outside fenced compound.
Path to follow proposed power route ☐Yes ☐No ☒Partially
2. Provider Name: ZAYO fiber vault just outside fenced compound.
Path to follow proposed power route ☐Yes ☐No ☒Partially
Is there an approved Transport Provider?
☐Yes ☒No
Approved Provider:
Engineering Contact:
Phone Number:
E-mail Address:
Met Engineer on-site? ☐Yes Date: ☒No (explain): Transport not selected at this time
Transport Provider Run Information
Will Ethernet over microwave be required?
☒No ☐Yes ☐Possible/Needs Verification
Point of Origination:
☐Pole ☐Pedestal ☐Terminal ☒Vault/Handhole ☐Other (Describe)
Number or address of point of origination: Existing fiber vault just outside fenced compound.
Distance from meet me point to site (via existing or proposed easement): 70’
Describe Route (be specific, including whether a new pedestal or terminal will be placed, where it would be
placed, etc.):
AT&T GC will need to provide and install a new 3048 handhole (or approved) by the existing fiber vault.
AT&T GC to install (1) 4” SCH 40 PVC conduit and (3) 1-1/4” innerducts, from the new 3048 handhole just outside the
fenced compound to the new AT&T lease area. AT&T GC will need to place the conduit in a 36” below grade trench.
AT&T GC will need to provide and install detectable warning tape in the trench above the fiber conduits.
UCR: WA6148 Sunset Relo 7
Transport Easement (or equivalent) Information
Utility Co. Easement(s) Required (Utility Co. Document)? ☐Yes ☒No ☐Possible
Third-Party Easement(s) Needed? ☐Yes ☐No ☒Possible/Needs Verification
Who will Write Who Executes & Notarizes Who Records
☐Telco Co.
☐SA Vendor
☐Other: See Below
☐Telco Co.
☐SA Vendor
☐Other: See Below
☐Telco Co.
☐SA Vendor
☐Other: See Below
Easement Requirements or Suggestions:
Once a fiber provider is selected, Site Acq will need to verify with the provider whether the existing
access/utility easement already in place by virtue of lease or non -exclusive easement will suffice in lieu of a
separate utility easement.
Where the Utility places and maintains power and/or telco assets on private property from the Right of Way
to the site, the Site Acq agent is responsible for securing land rights for the path, environment (Aerial or
Underground), and 24/7 access where the plant will reside and as required by the utility. Also applicable to 3rd
party private property where required.
Where the Utility does not require an exclusive easement, the SA vendor shall determine the final means of
securing the appropriate land rights and approving with the utility and landlord/owner. Also applicable to 3rd
party private property where required.
UCR: WA6148 Sunset Relo 8
Attachments
☒ Vicinity Map
☒ Aerial Site Map
☐ Drawing or sketch showing the following:
o Utility run(s) from demarcation(s) to site
o Identify whether utilities will be overhead or underground
☒ Labeled pictures showing utility run(s) from demarcation(s) to site
UCR: WA6148 Sunset Relo 9
Proposed New
AT&T Cell Site
Existing
abandon meter base
Existing
Fiber vault
UCR: WA6148 Sunset Relo 10
Existing
abandon meter base
AT&T GC to install 3” Schedule 40
PVC conduit from the existing meter
base to the new AT&T lease area
UCR: WA6148 Sunset Relo 11
AT&T GC to install 4”
SCH 40 PVC Conduit
w/ pull strings and
(3) 1-1/4”
innerducts for fiber.
AT&T GC to Install
new Fiber vault
Existing
abandon meter base
AT&T GC to install 3” Schedule 40
PVC conduit from the existing meter
base to the new AT&T lease area
UCR: WA6148 Sunset Relo 12
AT&T GC to install 4” SCH 40
PVC Conduit w/ pull strings and
(3) 1-1/4” innerducts for fiber.
Proposed New
AT&T Cell Site
AT&T GC to install 3” Schedule 40
PVC conduit from the existing
meter base to the new AT&T
lease area