HomeMy WebLinkAboutC_Site_Plan_Response_Letter_200207_v1.pdf IHB Architects Architecture * Planning * Feasibility * Project Management Imad H. Bahbah, Principal July 15, 2019 Matthew Herrera, AICP - Senior Planner City of Renton Community & Economic Development 1055S. Grady Way, Renton , WA 98057-3232 425.430.6593 Re: Sunridge Townhomes 2 - Site Plan Review - Response Letter This letter and supporting materials serve as the response to the PRELIMINARY Renton Site Plan Review. Project Information and Submittal: Address ​122xx SE Petrovitsky Rd., Renton WA, 98058 Document List​: ●Letter of Response - New ●Project Narrative - Updated ●Land Use Master Plan Application - Updated ●Pre-App Meeting Notes ●Owner’s Policy of Title Insurance - New ●Site Plan - Updated ●Civil Construction Plans - New ●Sewer Availability ●Storm Drainage Report ●Water Availability ●Arborist Report ●Site Plan Analysis - New ●SEPA Checklist - New ●Neighborhood Detail Map - New ●Landscape Plan - New ●Floor Plans - New ●Elevations - New ●Colored Renderings - New ●Utilities Plan - New ●Geotech Report - New ●Tree Retention Plan - No Change ●Trash Enclosure Plan Comment Responses Responses to city’s comments shown in ​bold. Good Morning Rick, The following items will need to be corrected or provided before we can accept the application. The numbers reflect items listed in the attached site plan review submittal requirements checklist. 1.​ ​(Preapp Meeting Summary) ​ - ​Accepted 2.​ (​Waiver Form) - ​See attached 3.​ ​Make the following corrections: a.​ ​The proposed land use is residential; Done b.​ ​Comp plan designation – Residential High Density; Done c.​ ​Attach legal description per pg.2; 2 Updated - See attached file d.​ ​pg.2 Owner signature notarized or authorization to sign for owner. Refer to the revised Land Use Application 4.​ ​I’ll follow up with an invoice when provide corrected items. 2019 fees include the following: a.​ ​Administrative Site Plan Review $2,570; b.​ ​SEPA Checklist $1,540.00; c.​ ​Street Modification $250.00 d.​ ​Technology Fee: 5-percent of total. 5.​ ​Provide response to each bulleted item on Project Narrative or N/A Refer to Updated Project Narrative 6.​ ​No SEPA Checklist was submitted. Provide completed and signed environmental checklist. Use Washington State Department of Ecology version of checklist. Updated - see new SEPA Checklist 7.​ ​You will need a modification to keep the current curb line along Petrovitsky. See preapp comments for details. Noted 8.​ ​No Density Worksheet was submitted. Download from Digital Records Library on City Website, complete, and submit. Refer to included Density Worksheet 9.​ ​Provide copies of all easements identified in title report. Refer to the included Owner’s Policy of Title Insurance, Policy # 5011453-2853166 10.​ ​Waive 11.​ ​No construction mitigation description was submitted. See submittal requirements checklist for item description. ​Now attached. 12.​ ​No design overlay district report was submitted. Provide a written description of how the project meets the RMC 4-2-115 Residential Design and Open Space Standards for R10-R14. Refer to new design overlay district report. 3 13.​ ​No affidavit of public information sign was provided. Sign must be posted prior to accepting the application. Download from Digital Records Library on City Website, complete, and submit. Refer to new affidavit. 14.​ ​No neighborhood detail map was provided. Refer to new Neighborhood detail map. 15.​ ​Waive 16.​ ​Waive 17.​ ​Waive 18.​ ​Site Plan corrections: a.​ ​Driveways must be setback at least 5-feet from side property line; Updated. b.​ ​Provide recorded access easements from Sunridge Phase 1 and abutting east parcel. Refer to easement diagram on updated Site Plan c.​ ​Both arrow ends of the ROW dedication need to be visible. Updated. d.​ ​One area of the site plan shows 10-feet of ROW dedication and 9.5 feet in another area. The drainage plan shows a consistent 9.5 foot ROW dedication. Provide consistent ROW dedication on all sheets. Updated. e.​ ​Label the existing sidewalk that will be removed and replaced with 8-foot wide landscape planter. Updated. 19.​ ​No architectural elevations were provided. See item 19 for list of requirements to be noted on elevations. Refer to included elevations. 4 20.​ ​10-foot wide street frontage landscaping width to be located on the north side of sidewalk between buildings. ROW planter strip south of sidewalk is 8-feet wide. Refer to updated Site Plan. 21.​ ​No landscape analysis, lot coverage, and parking analysis was submitted. See item 21 description for list of requirements to be noted. Refer to the updated Site Plan analysis sheet. This will include all items required in item 22.​ ​No floor plans were submitted. See item 22 description for list of requirements. Refer to updated floor plans of both buildings. 23.​ ​Survey needs PLS stamp. Please see atatched. 24.​ ​Plan does not tell me what is staying or going. See item 24 description for list of requirements to be shown on plan. Plan needs to be prepared by certified arborist or landscape architect. Refer to new landscape plans. 25.​ ​No tree retention worksheet was submitted. Download from Digital Records Library on City Website, complete, and submit. Refer to new tree retention worksheet. 26.​ ​Arborist report needs to provide all bulleted items in #26 description list. Aborist report list is under #25. Below is the bulleted response. ●ID Scheme - See attached arborist report and Landscape plan ●Tree size and species - See attached arborist report ●Reasons for tree removal: as we are developing on a vacant lot, trees will need to be removed for our project to work. Nevertheless, tree condition, size and description in included in the arborist report. New plants with detail of protection, maintenance, location will be according to the landscape plan. ●Tree relocation will not happen. However, new trees, shrubs, and groundcover will be provided according to the Landscape plan 27.​ ​Waive 28.​ ​Waive 29.​ ​Waive 30.​ ​Waive 5 31.​ ​Waive 32.​ ​Geotech report is for neighboring site to the west. Provide updated report for project site. Refer to new Geotech Report. 33.​ ​Waive 34.​ ​No utilities plan was submitted. Refer to sheet C1, updated Civil plans a.​ ​Include a street cross section of SE Petrovitsky Road with the street frontage elements and labeling the widths of each element, existing ROW width, ROW dedication, and the future ROW width. Refer to sheet C4, updated Civil plans b.​ ​Undergrounding of all existing utilities in the frontage is required. No vaults to be located in the sidewalk. Understood. c.​ ​Include all hatch marks, all shadings, and all symbols in the legend. Understood & implemented. d.​ ​Label the driveway approach type. Understood & implemented. e.​ ​See item 34 description for list of requirements to be shown on plan. Understood & implemented. 35.​ ​Drainage Plan Refer to sheet C3, updated Civil Plans 36.​ ​Drainage Report Attached. a.​ ​TIR shall meet all the requirements of the 2017 Renton Surface Water Design Manual (RSWDM). b.​ ​Include all the figures, include the design and sizing calculations for the detention facility and the water quality facility. Include the WWHM model input and output information. 6 c.​ ​Provide the conveyance pipe sizing analysis per the section 1.2.4.1. of the 2017 RSWDM. Show the pipe sizing information. d.​ ​TIR shall mention that the Flow Control standard is Forested site conditions. e.​ ​Include the flow chart that determines the type of drainage review required. f.​ ​Include the downstream analysis that extends minimum one mile downstream of the project site (per RSWDM). Describe the Special Requirements 4, 5 to meet the requirements of the 2017 RSWDM. g.​ ​Mention all the on-site BMPS including Soil Amendment and Perforated pipe. h.​ ​Provide and show the water quality elements consistently in the TIR and in all the plan sheets. i.​ ​Show and label the detention facility and the water quality facility and the stormwater lines with flow direction arrows clearly in the plans. FOR ALL ITEMS 36 a-i, see Drainage Report / TIR attached. j.​ ​The TIR mentions that the permeable pavement should not be provided but the drainage plan notes say that permeable pavement must be used. Provide consistent information in all plans and documents. See updated Civil Plans. 37.​ ​No Grading Plan was submitted. See item 37 description for list of requirements to be shown on plan. See updated Civil Plans. 38.​ ​No screening detail for refuse/recycling was submitted. See item 38 description for list of requirements to be shown on plan. Refer to new Trash Enclosure Plan. 39.​ ​No traffic study or trip generation memo was submitted. Provide information of the net new peak hour trips (in AM Peak, PM peak) estimated from the proposed development (use the rates from the current ITE Trip Generation Book). If the net new trips in either peak time is 20 or more, then traffic impact analysis is required. A 10 unit townhouse development is not estimated to generate 20 or more number of new peak hour trips. Provide information of the estimated number of AM peak and PM peak hour trips due to the project. Low rise residential townhomes allow for 8.58 or 9 trips peak AM, PM (11units x 0.78 = 8.58) 7 40.​ ​Submit at least two (2) three-dimensional color renderings of the project. One street side and one from open space. Refer to file labeled “Color Renderings” accompanying the updated set. We hope this information is helpful Sincerely,    Imad Bahbah, Principal Architect IHB Architects 206-849-9158 Cc: Imad Bahbah, Principal Architect VY Properties, LLC, Owner contact 8